Agile and Hybrid
Kanban
PMP · Agile and Hybrid · 2 lessons · about 28 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
The Kanban method puts work on a board so the process is visible at a glance, then limits how much work is in progress so that work flows smoothly. It does not run on fixed iterations; it is based on flow. Lesson 1 shows how a kanban board is built, what "pull" means, and why limiting work in progress (WIP) exposes bottlenecks, and it teaches Little's Law: average time = average WIP ÷ average throughput (valid when the system is reasonably stable; count only work in progress and you get cycle time, count the backlog queue as well and you get lead time). Lesson 2 shows how to read a cumulative flow diagram, how cycle time differs from lead time, and the essential difference between Kanban and Scrum.
The chapter has two calculation points. The first is Little's Law (with everything else unchanged and the system stable, shorten average cycle time by reducing average WIP or raising average throughput; shorten average lead time by reducing the average total number of items in the system, including the queue, or raising average throughput). The second is reading WIP, cycle time and lead time off a cumulative flow diagram. Most questions are scenarios: what to do when a column is full, what it means when one band widens, and why service-type work suits Kanban.
Lessons in this chapter
- Lesson 1: Kanban boards, pull and WIP limits. The Kanban method and the kanban board; what a task board contains; a coach leads the team to draw its own process; pull instead of push; a full column plus a pile-up upstream means a bottleneck; swarming; Little's Law with worked numbers.
- Lesson 2: Cumulative flow diagrams, cycle time vs. lead time, and Kanban vs. Scrum. Read WIP vertically, time horizontally and throughput from the completion-line slope; two worked examples, one healthy and one with a bottleneck; the first response to a widening band; Kanban is based on flow, Scrum on iterations.
How to study this chapter
Start by looking at the kanban board figure. Trace it from left to right with your finger, then find which column is full and which column has finished items piled up. Next, work through two sets of calculations: Little's Law (WIP ÷ throughput), and reading WIP, cycle time and lead time from a cumulative flow diagram. Finally, separate Kanban from Scrum in one sentence: Kanban is based on flow, Scrum on iterations. When a question says a column is full, remember the direction of the answer: pause pulling new work, clear the bottleneck first, and swarm if needed. Do not raise the limit and do not remove it.
Chapter map
Kanban method (based on lean principles)
- Visualize: kanban board (column = status, left to right = flow)
- Pull: pull work from upstream only when downstream has capacity
- Limit WIP: full column + upstream pile-up = bottleneck → swarm, do not raise the limit
- Measure: average time = average WIP ÷ average throughput (stable system; count work in progress for cycle time, include the queue for lead time); read cycle time / lead time from a cumulative flow diagram
- Versus Scrum: no fixed iterations, continuous flow; suits service-type work with unpredictable demand
Lesson 1
Kanban Boards, Pull and WIP Limits
Lesson overview
The Kanban method puts work on a board so the process is visible at a glance, then limits how much work is in progress so that work flows smoothly. This lesson first covers how a kanban board is built and what "pull" means, then explains why limiting work in progress (WIP) exposes bottlenecks, and finally teaches one calculation tool: Little's Law. The next lesson covers the cumulative flow diagram and how Kanban differs from Scrum.
The Kanban method and the kanban board
"Kanban" is Japanese for "signal" or "card" and comes from manufacturing: each batch of work in progress on the shop floor carried a card showing the model, quantity and batch. Kanban is a management method; the board we usually picture is, more precisely, the kanban board, the tool that method uses. PMBOK 8 describes the Kanban method as a visual workflow management method to limit work in process (WIP) based on lean principles and focusing on continuous delivery without overburdening the team.
PMBOK defines a task board as a visual representation of the planned work that allows everyone to see the status of the tasks. A task board can show work that is ready to be started (to do), work in progress, and work that is completed. Different color sticky notes can represent different types of work, and dots can be used to show how many days a task has been in its current position. The columns stand for the states of the process, and left to right is the direction value flows; the column a card sits in is its status, and as work advances the card moves from left to right.
A common exam practice summarizes board setup in roughly five steps. First list the work the team does day to day. Then lay out the board. Next set WIP limits on the in-progress columns you want to control (columns such as To Do and Done usually need no limit). Then agree what "done" means (the definition of done). Finally agree whether to hold a short meeting and how often. A short meeting can be held daily, for example a daily coordination meeting where people move cards face to face, but Kanban itself does not require a daily meeting. When Kanban is introduced, the coach is a facilitator: the coach leads the team to draw its existing process with their own hands and then find improvements together. Participation builds buy-in, so a line manager must not draw the process and impose it. As a common exam practice, when the team is co-located, a physical board with a face-to-face short meeting is more effective than an online board.
Pull, not push
The core logic of Kanban is pull: only when downstream has spare capacity is a new piece of work pulled from upstream, and upstream may not push finished work downstream. The job of the "kanban" signal is to tell upstream to supply new work. Visualizing the workflow, pulling work through, and limiting WIP are the core features of the Kanban method.
Limiting work in progress
Work in progress is every work item in the process that has been started but not finished, including items waiting in queues. The more things are started at once, the slower each one gets done, switching between them costs effort, and problems get buried under everyone being busy. Put a numeric limit on each in-progress column that needs controlling (To Do and Done usually need none), and once a column is full no new work is pulled into it; the team is forced to focus on finishing what it has, and the bottleneck shows itself immediately. A bottleneck has two typical signs: the WIP in this column has reached its limit, and at the same time the column upstream has finished items piled up waiting to enter.
Worked example
A team's limits are Analysis 5, Development 6, Test 4 and Release 5. One day there are 2 items in Analysis. The Development column holds 6 items in all (2 in progress, and 4 finished and sitting in the done area waiting to enter Test, so Development is at its limit). Test is full with 4 items, and Release has 2. The bottleneck is Test. Do not raise the Test limit, and do not let Development keep starting new work. Instead, Development pauses starting new tasks and its people help Test finish what Test already holds. PMBOK calls this "swarming": if a column is approaching the work-in-progress limit, project team members can "swarm" around the current work to help those working on tasks that are slowing the flow.
Little's Law: average time = WIP ÷ throughput (count only work in progress for cycle time; add the backlog for lead time)
With stable flow: average time = average number of items in the system ÷ throughput. Throughput is the number of work items completed per unit of time. If WIP counts only the "in progress" columns, the result is cycle time (from when a task starts until it is completed). If you widen the system boundary to include the backlog queue and use the total number of items in the system (backlog + WIP), the estimate is lead time (from when a task is put on the board until it is delivered). This matches the definitions of cycle time and lead time in the PMBOK 8 kanban board figure (Figure 5-25).
Worked example: A customer service team has 24 tickets in the system at once (including those queued) and completes an average of 4 per day.
- Lead time = 24 ÷ 4 = 6 days.
- Suppose that after WIP is limited, the system runs stably with an average of 12 items in the system (including the queue) and throughput is still 4 per day. Average lead time = 12 ÷ 4 = 3 days. (A limit is only a ceiling; average WIP is determined by how the system actually runs.) Note: under stable flow, 12 ÷ 4 = 3 days is the long-run average lead time. If the team stopped accepting new work and still finished 4 per day, 3 days would be the expected time to clear the current 12 items. The two meanings are different, so do not use one to check the other.
- Now suppose the ticket-handling process is improved and throughput rises to 5 per day, with the number of items in the system still 12: 12 ÷ 5 = 2.4 days.
Under stable flow, shorten cycle time by reducing average WIP or raising throughput; shorten lead time by reducing the average total number of items in the system, including the queue, or raising throughput. Neither may come at the cost of quality. Limiting WIP is the first kind of lever.
Worked examples
Example 1 Introducing Kanban: what the team does first
PMLyceum sends an agile coach to guide a new team in learning to use Kanban. The coach gathers everyone in a meeting room and starts by talking about how to get going. In this discussion, what should the team do FIRST?
Show answer and explanation
Correct answer: B
An agile coach has taken on a new team that is to adopt Kanban. This is the initial discussion. What should the team do “first”?
The starting point of Kanban is to make the existing workflow visible. The coach is a facilitator and should lead the whole team in drawing the process together: while drawing, the team sees where it can improve, and it also genuinely buys into the process. Participation builds buy-in, and only once the current state is drawn do the later WIP limits and rules for done have anything to rest on. The answer is B.
Why the other options are wrong
- A. If the line manager alone draws the diagram and then imposes it on the team, the team has no sense of participation and will find it hard to buy into the process.
- C. The coach is already responsible for guiding the team in agile practices, so there is no need to bring in outsiders. Outside instruction also cannot replace the team working out its own process.
- D. Having the manager and the coach set the process and WIP limits and then require the team to follow them is a directive approach. It goes against the principle that the team builds its own process, and talking about limits before the process has even been drawn is premature.
Key takeaway When introducing Kanban, first have the team draw its existing process. Participation builds buy-in.
Variation If the process has already been drawn, the next step is to set WIP limits for each column and agree the definition of done. If the team is spread across several locations, an electronic kanban board can be used, but the team still builds the process itself.
Something wrong with this question?
Example 2 What it is called when you cap the work items in each stage
The team rules that no stage of the workflow may have more than a set number of work items in progress at the same time, so that inefficiencies show up earlier within a cycle. What is this practice called?
Show answer and explanation
Correct answer: B
There is a rule that no stage of the workflow may have more than a set number of work items in progress at once, so that inefficiencies show up earlier within a cycle. What is the name of this practice?
Work in progress (WIP) is the work items in the process that have been started but not finished. Putting a cap on the number of items in each stage is limiting WIP: once a stage is full, no new work is pulled in, the team is forced to focus on finishing what it has, and inefficiencies are easier to see. The two signals in the stem, “no more than a set number” and “inefficiencies show up earlier”, both point to it. The answer is B.
Why the other options are wrong
- A. Swarming is several team members concentrating on the same problem or work item. It is not a cap on quantity.
- C. Pair programming is two programmers writing code together. It has nothing to do with the number of items in progress.
- D. Continuous integration is merging work into the whole frequently and retesting it. It also has nothing to do with a limit on work in progress.
Key takeaway Capping the number of work items in each stage is limiting work in progress.
Variation If the stem said “a column is near its limit and members work together to help whoever is slowing the flow”, the answer would change to swarming. If it asked how to estimate the average time, use Little's Law: items in the system ÷ throughput (WIP only gives cycle time; include the queue for lead time).
Something wrong with this question?
Example 3 Some steps are full while others sit empty
During an iteration, you are the agile team lead and look at the kanban board. The team has not set WIP limits, work items are piled up in some process steps while other steps sit idle, and the team's velocity swings up and down. As an agile practitioner, what should you do?
Show answer and explanation
Correct answer: B
During an iteration, the kanban board shows work items piled up in some steps while other steps sit idle, and the team's velocity swings up and down. The question asks what the team lead should do.
The root of the problem is uneven distribution of work: some steps are jammed and others idle, so flow is blocked. The remedy is to set WIP limits on each process step on the kanban board, fixing the maximum number of work items each step may hold. When a column is full, upstream stops and puts its capacity into helping downstream, so overall flow evens out and velocity steadies. The limits are not there to get less done; they are there to stabilize flow first, and once it is stable the swings in velocity narrow as well. The answer is B.
Why the other options are wrong
- A. The problem is uneven distribution of work, not too many work items. Cutting items outright loses requirements and does not fix the unevenness.
- C. Little's Law can estimate average WIP, throughput or cycle time, but it is only a measurement relationship. It cannot directly remove the pile-up at a step or the imbalance in flow.
- D. Bringing in outside people is a temporary transfusion. It changes no process rules, so the pile-up will return and the pressure may move downstream. Idle team members with the appropriate skills may effectively swarm the bottleneck, but this option brings in people from outside the team without changing the process rules, so the flow imbalance remains.
Key takeaway When work piles up at a step on the kanban board, set a WIP limit for that step so flow evens out.
Variation If the stem said “you want to know how long each piece of work takes on average”, that is when Little's Law applies. For example, with 12 items in progress and throughput of 4 per day, the average is 12 ÷ 4 = 3 days.
Something wrong with this question?
Common traps
Common trap
- Equating Kanban with electronic task software is a mistake: the value lies in a visible process and limited parallel work; the tool is only a carrier.
- When a column is full, temporarily raising the limit or removing it gives up the point of having a limit. What needs solving is the bottleneck, not the number.
- Agile teams emphasize cross-functional collaboration and encourage members to broaden their skills, so developers with the right skills helping Test is normal agile practice.
- A WIP limit is not swarming: the first puts a cap on quantity, the second is everyone working together on the same work item.
- Little's Law gives an average. It cannot fix a pile-up at one step; pile-ups are handled by setting limits.
Key takeaways
- The core features of the Kanban method: visualize the workflow, pull work through, and limit WIP.
- The kanban board: columns are states, left to right is the direction of flow, and a card's position is its status.
- Five steps to set up a board: list the day-to-day work, lay out the board, set limits on the columns that need control, agree the definition of done, and agree whether to hold a short meeting and how often (a daily coordination meeting can be used to move cards face to face).
- Signs of a bottleneck: WIP in this column is at its limit and finished items are piled up in the column upstream. The response is swarming, not raising the limit.
- Average time = WIP ÷ throughput (count only work in progress for cycle time; add the backlog for lead time). To shorten it, either reduce WIP or raise throughput.
Lesson 2
Cumulative Flow Diagrams, Cycle Time vs. Lead Time, and Kanban vs. Scrum
Lesson overview
Once WIP is limited, how do you know whether flow has improved? Kanban teams use the cumulative flow diagram: arrival rate, WIP, cycle time and lead time can all be read from a single chart. This lesson first teaches how to read and calculate from the chart, then compares Kanban with Scrum. The exam often asks "which chart measures Kanban improvement", "what does it mean when one band widens", and "why does service-type work suit Kanban".
What a cumulative flow diagram is
The PMBOK glossary defines the cumulative flow diagram as a chart indicating features completed over time, features in other states of development, and those in the backlog. It is an area chart. The horizontal axis is time, the vertical axis is the cumulative number of work items, and each state gets its own band; the top edge of a band is the cumulative number of items that have entered that state.
How to read it: vertically, horizontally, and by slope
Read vertically. Draw a vertical line at a given day. The lengths cut off by the bands are the number of items in each state that day; the width of the "in progress" band is the WIP. Read horizontally. At the same cumulative count, the horizontal distance between the entry line and the exit line estimates the cycle time of that stage. To tie it to a specific piece of work, you must assume items flow in order (for example first in, first out). Read the slope. The slope of each line reflects the entry rate of the corresponding state. The steeper the completion line, the higher the throughput; a flat completion line means nothing is being completed.
The PMBOK kanban figure defines the two times. Cycle time is the time from when a task starts until it is completed. Lead time is the time from when a task is put on the board until it is delivered; because the order of the items in the ready column can be changed, lead time can be unpredictable.
Example 1 (healthy flow). The cumulative counts at the end of each day are as follows.
| Day | Cumulative arrived A | Cumulative started S | Cumulative done D | Backlog A−S | WIP S−D |
|---|---|---|---|---|---|
| 0 | 9 | 6 | 0 | 3 | 6 |
| 1 | 12 | 9 | 3 | 3 | 6 |
| 2 | 15 | 12 | 6 | 3 | 6 |
| 3 | 18 | 15 | 9 | 3 | 6 |
| 4 | 21 | 18 | 12 | 3 | 6 |
| 5 | 24 | 21 | 15 | 3 | 6 |
Throughput is the slope of line D: 3 items per day. Take the 15th item. Line A reaches 15 on day 2 (arrival), line S reaches 15 on day 3 (start), and line D reaches 15 on day 5 (completion). Cycle time = 5 − 3 = 2 days, and lead time = 5 − 2 = 3 days, with 1 day spent queuing in between. Check with Little's Law: cycle time = WIP ÷ throughput = 6 ÷ 3 = 2 days; lead time = (WIP + backlog) ÷ throughput = (6 + 3) ÷ 3 = 3 days. Both match.
A widening band: work is piling up
Example 2 (a bottleneck appears). Cumulative starts remain 3 per day (6, 9, 12, 15, 18, 21, 24, 27, 30). Cumulative completions are 3 per day for the first 2 days and only 2 per day from day 3 (0, 3, 6, 8, 10, 12, 14, 16, 18). WIP on day 2 is 12 − 6 = 6, on day 5 it is 21 − 12 = 9, and on day 8 it is 30 − 18 = 12, so the band keeps widening. Throughput has fallen from 3 to 2. Now look at cycle time. The 12th item starts on day 2 and finishes on day 5, taking 3 days; the 18th item starts on day 4 and finishes on day 8, taking 4 days. It keeps getting longer.
When a state reaches capacity, first stop new work from entering it. If no effective WIP limit exists, set and enforce one; if a limit already prevents new work from entering the full state, diagnose the bottleneck immediately and use swarming where helpful to finish blocked work. Do not start by adding people, lengthening the timebox or simply adding resources.
Key point
Cumulative flow diagram: read WIP vertically, cycle time and lead time horizontally, throughput from the completion-line slope, and the entry rate of each other state from its boundary-line slope. Apart from the "done" band, a state band that keeps widening means work is piling up in that state (a widening "done" band only means cumulative completions are increasing). Kanban teams use it to measure process improvement; one chart shows arrival rate, cycle time, lead time and WIP.
Agile measures how much value has been delivered and how long a piece of work takes to flow through (cycle time), not just variance against a plan. Agile pays more attention to value delivery and flow metrics, and it also uses burn charts and similar tools to check variance against the plan; performance should not be judged only by the number of documents or by how busy individuals are.
How Kanban differs from Scrum
The essential difference: Kanban is based on flow and does not require fixed iterations; new work is pulled into the system under a clear policy whenever the WIP limit allows. Scrum is based on iterations, with fixed-length timeboxes called Sprints, and each Sprint ends with a Sprint Review and a Sprint Retrospective. A doctor's clinic makes a useful comparison: Kanban is like a doctor who keeps seeing patients continuously, while Scrum is like a doctor who stops after every hour to take stock.
Compare
- Kanban: based on flow; no fixed iterations; continuous delivery; controlled by limiting WIP; does not prescribe Scrum-style accountabilities; suits work where demand keeps arriving and is hard to predict, such as operations and service support.
- Scrum: based on iterations (Sprints); fixed timeboxes, usually a few weeks; the Scrum Team collaboratively defines a Sprint Goal at Sprint Planning (the Developers select Product Backlog items through discussion with the Product Owner), and during the Sprint no changes are made that would endanger the Sprint Goal (scope may be clarified and renegotiated with the Product Owner as more is learned); each Sprint ends with a Sprint Review and a Sprint Retrospective; it defines three accountabilities: Developers, Product Owner, and Scrum Master; suits development work delivered in stages that the customer confirms.
Both often use visualization. Scrum prescribes the Daily Scrum, and Kanban teams may also adopt rhythms such as a daily kanban meeting, but Kanban itself does not require that meeting. The two can also be combined, for example by using a kanban board to manage tasks inside a Scrum Sprint.
Worked examples
Example 1 Which chart measures Kanban improvement
The team finds a process problem during an iteration and starts using a kanban board to improve it. You want to measure the results of the improvement and present the data clearly. What should you do?
Show answer and explanation
Correct answer: D
The team finds a process problem in an iteration and starts improving it with a kanban board. It wants to measure the results of the improvement and present the data clearly. What should it use?
The standard tool Kanban teams use to measure flow is the cumulative flow diagram: time on the horizontal axis, cumulative work items on the vertical axis, and one band per state. It shows the average arrival rate, cycle time and the amount of work in progress together, and changes in these three reflect the effect of process improvement directly, for example a narrowing in-progress band or a shorter cycle time. The answer is D.
Why the other options are wrong
- A. A burnup chart shows cumulative completions against total scope. It does not show work in progress along the way, so it is hard to use to measure process improvement.
- B. A burndown chart shows remaining work decreasing over time. It focuses on what remains, not on arrival rate, cycle time and work in progress in the process.
- C. A value stream map is good for depicting the end-to-end process, separating work from waiting and spotting waste, but it is not used, as a cumulative flow diagram is, to keep showing changes in arrival rate, cycle time and WIP for each state.
Key takeaway Kanban teams measure process improvement with a cumulative flow diagram: arrival rate, cycle time and WIP in one chart.
Variation If the stem asked what a continuously widening band means, the answer is a pile-up in that state. If no effective WIP limit exists, first set or enforce one and stop new intake; if the limit is already effective, keep intake stopped and diagnose why work is stuck. If it asked how to identify waiting waste in the process, use a value stream map.
Something wrong with this question?
Example 2 Which metrics agile values more
Unlike predictive projects, which focus on variance against the plan, which group of metrics do agile projects value MORE for measuring performance?
Show answer and explanation
Correct answer: B
The question contrasts the measurement orientation of predictive and agile projects: predictive focuses on variance against the plan, and the question asks which group of metrics agile values more for measuring performance.
Agile measures value delivery and flow: how much value has been delivered, and how long a piece of work takes from start to finish (cycle time). These two directly reflect whether the team can deliver value continuously and quickly, rather than how strictly the plan was executed. Checking variance against the plan is the predictive orientation. A simple way to remember it: predictive asks “did we stay on plan?”, while agile asks “how much value did we deliver and how fast does it flow?”. The answer is B.
Why the other options are wrong
- A. Variance between planned and actual duration is exactly the variance against plan that predictive projects focus on.
- C. The number of documents does not represent value. Agile values working software over comprehensive documentation.
- D. Individual hours utilization measures how busy people are, not what was delivered or how fast it flows.
Key takeaway Agile places more emphasis on value delivered and cycle time rather than treating plan deviation or individual busyness as the primary performance measures.
Variation Given a cumulative flow diagram, read cycle time as the horizontal distance from the start line to the completion line. For example, if item 15 starts on day 3 and finishes on day 5, the cycle time is 5 − 3 = 2 days.
Something wrong with this question?
Example 3 Why service-type work picks Kanban
An operations support team at a company receives service requests every day whose volume and urgency are hard to predict. The team is considering managing the work with Kanban rather than Scrum. What is the advantage of Kanban for this kind of service work?
Show answer and explanation
Correct answer: C
An operations support team receives service requests every day whose volume and urgency are hard to predict, and is considering Kanban instead of Scrum. The question asks for the advantage of Kanban for this kind of service work.
Kanban is based on flow. It has no fixed iterations, work keeps entering and being completed, and new requests can be added to the queue at any time, but they are pulled into active work only when capacity is available under the WIP limits. Service work with unpredictable demand needs exactly this “accept as they come, keep flowing” rhythm, rather than freezing a batch of requests and handling them together. The answer is C.
Why the other options are wrong
- A. Option A describes freezing every request before a fixed iteration, but Scrum does not freeze all incoming requests, and Kanban has no fixed iterations. Kanban lets new requests enter the queue at any time and pulls them into active work as capacity allows.
- B. Developers, Product Owner, and Scrum Master are Scrum's three defined accountabilities. Kanban does not prescribe those Scrum accountabilities, so this is not an advantage of Kanban.
- D. Visualizing the workflow is one of the core features of Kanban. Saying “no need to visualize” is the opposite of the facts.
Key takeaway Kanban has no fixed iterations and work flows continuously, which suits service work whose requests arrive at any time.
Variation If the stem said “a usable increment must be demonstrated to the customer every three weeks, with results confirmed in stages”, Scrum would be the better fit. The two can also be combined: use a kanban board to manage tasks inside a Scrum Sprint.
Something wrong with this question?
Common traps
Common trap
- A cumulative flow diagram shows the cumulative amount in each state. A burndown chart shows what remains, a burnup chart shows work completed against scope, and a value stream map shows the work and waiting time at each step.
- Cycle time counts from "started work"; lead time counts from "put on the board". Do not mix them up.
- A widening band is a signal of pile-up. Stop new work from entering the full state; set or enforce a WIP limit if needed, then diagnose the blockage. Do not start by adding people or lengthening the timebox.
- A Kanban team holding a daily meeting does not make Kanban Scrum. Kanban itself does not require iterations, the Sprint Review and Retrospective, or that fixed rhythm (a team may add a fixed rhythm itself, or combine Kanban with Scrum Sprints).
- Service-type work whose demand arrives at any time suits Kanban. In Scrum the Scrum Team collaboratively defines a Sprint Goal at Sprint Planning, with the Developers selecting Product Backlog items through discussion with the Product Owner, and no change that would endanger the Sprint Goal is made during the Sprint, although scope may still be clarified and renegotiated with the Product Owner as more is learned.
Key takeaways
- Cumulative flow diagram: time on the horizontal axis, cumulative count on the vertical axis, one band per state. Read WIP vertically, time horizontally, throughput from the completion-line slope, and other state-entry rates from their boundary-line slopes.
- Cycle time: from start to completion. Lead time: from put on the board to delivery. In a steady state, cycle time = WIP ÷ throughput.
- A widening in-progress band = completion slower than starts = a pile-up. Stop new intake immediately, setting or enforcing a WIP limit if needed; if the limit is already effective, diagnose why work is stuck.
- Kanban is based on flow, with no fixed iterations and continuous delivery. Scrum is based on iterations, with timeboxes and three defined accountabilities.
- For work with hard-to-predict demand, such as operations and service support, consider Kanban first.
This chapter has 15 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.