Agile and Hybrid
Release Planning and Prioritization
PMP · Agile and Hybrid · 4 lessons · about 48 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Predictive projects usually complete most of their planning up front and set baselines, then adjust continuously during execution through monitoring and change control. Agile projects also have plans, but the plans are layered and rolling: the nearer the work, the finer the detail, and the further away, the coarser. This chapter covers those layers in turn: the product vision and the product roadmap, the planning onion that links them, how a release plan uses velocity to work out “how many iterations are needed”, how backlog items are ordered by value, dependencies and risk (combined with cost), and how risk is worked into the ordering and the iteration plan.
This is a frequently tested chapter among the agile topics. In scenario questions the answer is often the same action: when the vision changes, first clarify the impact and confirm direction, then talk with the team face to face; when a customer asks about launch time, build a release plan; when velocity falls short, reorder by value, with no overtime and no squeezing of estimates; for a new risk, first analyze it and plan the response, and response work that has to be carried out or exploratory work goes into the backlog.
Lessons in this chapter
- From Vision to Iteration Plan: Planning Levels, the Product Roadmap and the Planning Onion. The vision answers why; the vision, roadmap and backlog are prepared at the start; the five layers of the onion; the difference between a roadmap and a release plan.
- Agile Release Planning: Forecasting a Release with Velocity. How a release differs from an iteration; features are commonly estimated in story points and tasks in hours (a common practice, not a fixed rule); iterations needed = remaining points ÷ velocity; how much can be done when the date is fixed; revising the release plan when velocity falls short; minimum marketable features.
- Prioritization: Value, Cost, Risk and Common Methods. MoSCoW, Kano analysis, the 100-point method and cost of delay; filling limited velocity by priority; how to handle new requirements and disagreements.
- Agile Risk Management: Risks in the Backlog. Risk response work goes into the backlog; the value-and-risk quadrants; the risk burndown chart (the vertical axis is Σ(probability × impact), that is, each risk is multiplied first and then summed); risk-based tasks in the iteration plan.
How to study this chapter
This chapter has many concepts and many test points, so study it in the order of the onion: first be clear about who each of the vision, the roadmap, the release plan and the iteration plan is for; then master velocity as the bridge, so that you can work out “how many iterations are needed” and “how much can be done by the deadline”; then learn the ordering methods and connect “velocity falls short” with “ordering by value”; finally bring risk in. When working a question, first find the keywords in the stem: wanting to know which day it goes live, a changed vision, low velocity, too many requirements, high risk. Each keyword corresponds to a fixed action.
Chapter map
Product vision (why)
- Product roadmap (high-level time view, for communicating with the team and stakeholders)
- Release plan (a few months; sets the iterations; story point estimates)
- Iterations = remaining points ÷ velocity (rounded up)
- Iteration plan → daily plan (tasks in hours)
- Release plan (a few months; sets the iterations; story point estimates)
Backlog ordering: value · cost · risk (a common exam practice; PMBOK 8 says value, dependencies, technical or operational risk, and cost can be combined)
- MoSCoW · Kano · 100-point method · cost of delay
- Risk response work goes into the backlog; order by value, risk and dependencies together (high-value, high-risk items usually go first for validation, depending on the situation)
Lesson 1
From Vision to Iteration Plan: Planning Levels, the Product Roadmap and the Planning Onion
Lesson overview
Agile projects also have plans, but the plans are layered and rolling: the nearer, the finer; the further, the coarser. This lesson covers the outermost layers of the plan: the product vision and the product roadmap (the charter of an adaptive project can be very light; it is only a starting document and not a layer of the planning onion), and the “onion” that connects the layers of the plan. The exam often asks two kinds of questions: what to do when the vision or goal changes, and what to give stakeholders who want something more concrete than the vision and coarser than the release plan. The next lesson covers the layer further in: the release plan.
Vision: stating why
PMBOK 8 says that the project vision “summarizes the project's purpose clearly and succinctly” and “describes a realistic, attractive view of the future project outcomes.” A vision developed collaboratively between project team members and key stakeholders should answer these questions: What is the project purpose? What defines successful project work? How will the future be better when the project outcomes are delivered? How will the project team know that it is drifting from the vision?
A vision workshop is the usual way to form a vision, with the product owner and all members (remote ones too) taking part, and then a very short statement such as an elevator pitch says it plainly: whom the product helps with what problem, and where the value lies. The charter of an adaptive project can be very light, ranging from a concise vision statement to a moderately detailed document, and it usually answers questions such as why the project is being undertaken, who will be engaged, what it is about, where it will occur, when it will start and end, how it will be carried out and who the customer is (PMBOK 8). Inside the team there is also a team charter that records working agreements. During initiation and early planning, three things are often built up gradually (which ones are used should be tailored to the project context): the vision says why, the product roadmap says roughly what each version delivers, and the product backlog organizes what is to be done.
Key point
When the vision or goal changes, first clarify and assess the impact with the product owner, the sponsor and key stakeholders, and confirm the direction within governance authority (a major change to project goals or vision may need a decision from the sponsor or the governance body). Then bring the team together and explain the new goal face to face so everyone understands it, and the product owner and the developers adjust the backlog and the plans according to their own responsibilities. When development content drifts from the vision, go back to the vision and adjust the order of the backlog.
The planning onion: nested layers of plans
Rolling wave planning plans near-term work in detail and far-off work only at a higher level. There are no fixed layers; applied to agile projects, a five-layer “planning onion” model is commonly used (tailor it to the project context). From the outside in, the layers are: product vision, product roadmap, release plan, iteration plan, daily plan. The outer layers are stable, updated slowly, and aimed at management; the inner layers are concrete, updated quickly, and aimed at the team. Before a roadmap can be created, the product vision must exist first.
The use of the onion is to decide “which layer to show to whom”. An operations director who wants something more concrete than the vision but not as detailed as the release plan corresponds to the second layer; what the development team does today corresponds to the innermost layer.
The product roadmap
The PMBOK glossary defines a roadmap as “a high-level timeline that depicts such things as milestones, significant events, reviews, and decision points.” A product roadmap is driven by the product vision. It often uses quarters as its time axis and says in broad strokes what problem each version solves, without going down to specific user stories.
Worked example
The roadmap of a neighborhood group-buying mini-app: in quarter 1, release 1.0, with the goal that residents can place orders and pick up at a store, and the key result that 3 neighborhoods go live; in quarter 2, release 2.0, adding group-leader commissions and order reminders; in quarter 3, release 3.0, opening the platform to merchants. The roadmap says only “what value each quarter delivers”; the specific features are developed in the next layer, the release plan.
A roadmap is mainly for management, investors and other departments, aligning their understanding of direction. To show senior leaders and shareholders the features to be delivered in the future, use the product roadmap, not the daily coordination meeting and not a single demonstration.
Compare
- Product roadmap: long term, often in quarters, broad, strategic, highly flexible; its audience is management and investors; its output is milestones and a value proposition.
- Release plan: short term, usually a few months, concrete, at the execution level; its audience is the development and testing team and the product owner; its output is the timeline for one release cycle, the number of iterations, and the features or release backlog each iteration is to deliver (PMBOK 8); acceptance criteria and risk arrangements can be linked and recorded as needed.
Worked examples
Example 1: The vision has changed; how do you tell the team
You are the agile team lead at a logistics software company. A new industry policy requires the product vision to be substantially adjusted, and the project goals change with it. How should you communicate these changes to the Developers on the team?
Show answer and explanation
Correct answer: C
During agile development, an external policy change forces a major adjustment to the product vision and project goals. The question asks how to communicate this significant change to the team members.
The agile principles stress that the most effective way of communicating is face to face. When the vision and goals change, the team has to understand what the change means for its work before the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities. Holding a team meeting to explain it in person lets you explain the background, check on the spot that everyone has understood, and answer questions. The answer is C.
Why the other options are wrong
- A. Forwarding the policy text by email is low-bandwidth communication and cannot ensure members understand what it means for the vision and goals.
- B. Having the leader change the plans and then tell the team to follow them is deciding for the team. In agile, the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities, after first understanding the change.
- D. Putting off the decision until the next release goes against the principle of timely adjustment, and the work being continued may no longer fit the new vision.
Key takeaway When the vision and goals change, first make sure the team understands face to face; then the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities.
Variation If members are spread across cities, still prefer a video meeting, which is close to face to face; if the change is only a minor scope adjustment within one iteration, communicating it at iteration planning is enough.
Something wrong with this question?
Example 2: More concrete than the vision, coarser than the release plan
An agile team is developing a warehouse management system for a logistics company. Early in the project, the logistics company's operations director wants something more concrete than the product vision but does not need the detail of a release plan or an iteration plan. What should the team provide to meet his need?
Show answer and explanation
Correct answer: D
Early in the project, the operations director wants something more concrete than the product vision but not as detailed as a release plan and an iteration plan. The question asks you to identify the right layer of the planning onion.
The planning onion (a common exam term; PMBOK 8 Figure 5-1 shows the first four layers) runs from the outside in: product vision, product roadmap, release plan, iteration plan, daily plan, with more detail toward the center. The director's two conditions pin the answer between layers: more concrete than the vision means going one layer in, and not as detailed as the release plan means not going as far as the third layer. That lands on the second layer, the product roadmap. The way to solve these questions is to line up the five layers from the outside in and then use “more concrete” and “not so detailed” to bracket the range between two layers. The answer is D.
Why the other options are wrong
- A. A status email reports current progress. It is not a plan for future versions and features, so it cannot show what he wants to see.
- B. The product vision is the highest-level goal, and the director explicitly wants something more concrete, so it is not enough.
- C. The daily plan is the innermost, most detailed layer, and the director explicitly does not need that much detail.
Key takeaway When the vision is too coarse and the release plan too detailed, show stakeholders the product roadmap.
Variation If the director wanted to show shareholders the themes of versions over the next few quarters, that is again the product roadmap; if he wanted to know which stories the next iteration will do, that would be the iteration plan.
Something wrong with this question?
Common traps
Common trap
- When the vision changes, do not blast out an email, and do not have the lead change the plan and then notify people. Make sure the team understands face to face, and then have the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities.
- A roadmap is not a release plan: the roadmap is coarse, long term and for management; the release plan is detailed, short term and for the team.
- Agile does not mean no plans; it means planning in layers on a rolling basis: the vision is the coarsest and the daily plan the finest.
- A vision is not the same document as a project charter: a vision is more inspiring, and a charter is more explicit and concrete; the two can also be combined.
- Before creating a roadmap, the product vision must exist first.
Key takeaways
- A vision answers why, how success is defined and how to tell when the team is drifting; it is developed by the team and key stakeholders together.
- During initiation and early planning, the vision, the product roadmap and the product backlog can be built up gradually; which artifacts are used is tailored to the project context.
- The onion from the outside in: product vision, product roadmap, release plan, iteration plan, daily plan.
- A roadmap is a high-level timeline, often in quarters, for management and investors.
- When the vision changes, after clarifying, assessing the impact and confirming within governance authority, bring the team together in a synchronous meeting so it understands, and the relevant roles adjust the backlog and the plans.
Lesson 2
Agile Release Planning: Forecasting a Release with Velocity
Lesson overview
Customers often ask roughly when the new version will be ready. A release plan answers with an expected release window. This lesson covers what a release plan is, how it differs from an iteration, which units are used to estimate features and tasks, and above all how to use velocity to work out “how many iterations are needed” and “how much can be done by the deadline”. In the exam, this area usually asks two things: how to build a release plan, and what to do when velocity falls short of expectations.
The release plan and the iteration
PMBOK 8 says that agile release planning “provides a high-level summary timeline of the release schedule (typically 3–6 months) based on the product roadmap and the product vision.” It determines the number of iterations in the release, and this planning “empowers the product owner and team to determine the development scope, timelines, and a releasable product, factoring in business goals, dependencies, impediments, and resource availability.” Since features represent expected value to the customer, the timeline “provides a more easily understood project schedule as it defines which features will be available at the end of each iteration.”
An iteration is the team's internal work cycle; in the Scrum way of working, every iteration produces a usable increment. A release hands functionality to users and is a product-level act. A release usually contains several iterations. Nor is faster always better for releases: each release affects existing users, so acceptance and support cost have to be considered.
Two levels of estimating: story points and hours
The release plan sets the iterations, and the iteration plan arranges the development of the features. A common practice is to estimate features (user stories) in story points and the tasks created to deliver the stories in hours; the units are agreed by the team and kept consistent. PMBOK points out that many agile teams use story points rather than hours because story points reflect relative effort or complexity, and in dynamic environments estimating hours can be more time-consuming and less reliable.
Forecasting a release with velocity
Velocity is a measure of a team's productivity rate at which deliverables are produced, validated and accepted within a predefined interval. It is commonly expressed as story points completed per iteration, and a team may also use another unit of work that it applies consistently. Only stories that meet the team's completion standard count; in Scrum, this means meeting the Definition of Done (DoD). The forecasting formula is just one: iterations needed = remaining story points ÷ velocity, rounded up when whole iterations are needed for delivery.
Worked example 1: how many iterations are needed. The backlog totals 156 points, and the team's velocities over the last three iterations are 22, 26 and 24; each iteration is 2 weeks.
- Average velocity (22 + 26 + 24) ÷ 3 = 24 points.
- 156 ÷ 24 = 6.5, rounded up to 7 iterations, about 14 weeks.
- Check: 6 iterations give a cumulative 6 × 24 = 144 < 156; 7 iterations give 168 ≥ 156.
- Take a range: at the lowest velocity of 22, 156 ÷ 22 ≈ 7.1, so 8 iterations; at the highest velocity of 26, 156 ÷ 26 = 6, so 6 iterations. So saying “6 to 8 iterations” to others is more honest than saying “7”.
Worked example 2: a fixed date; how much can be done. There are 5 iterations before the release date and the velocity is 24, so the team can deliver 5 × 24 = 120 points, 36 points fewer than 156. 36 ÷ 24 = 1.5, so either delay by 2 iterations or cut 36 points, starting with the lowest-priority stories. Look at the range too: pessimistic 5 × 22 = 110, optimistic 5 × 26 = 130. If later velocity still falls between 22 and 26, delivery of about 110 to 130 points can be predicted; the most important 110 points should be arranged first, and the forecast kept up to date with actual velocity (22 is not a statistically guaranteed lower bound).
Worked example 3: velocity falls short. After the start, the first two iterations complete only 20 and 18 points, 38 in total, an average of 19. Remaining is 156 − 38 = 118 points, and 118 ÷ 19 ≈ 6.2, rounded up to 7 iterations, so 2 + 7 = 9 iterations in total, 2 more than originally planned. Check: 7 × 19 = 133 ≥ 118, and 6 × 19 = 114 < 118.
Minimum marketable features and rolling adjustment
When requirements are many and changeable and management wants to see value early, first mark out the minimum marketable feature (MMF): the smallest set of features that brings value to users, ordered, and delivered as early as possible. MMF is a common exam term, and it should be distinguished from PMBOK 8's “minimum viable product”. During execution, track each iteration and adjust the release plan on a rolling basis. If velocity cannot keep up, revise the release plan according to actual velocity, instead of working overtime, running more stories in parallel or lowering the estimates.
Common trap
A release plan is not a contract and not an exhaustive specification; it is a rough, adjustable plan. When requirements change often, do not go down to a daily level. Commitments get coarser the further out they are: go broad first and become specific as uncertainty falls. Each team decides how many iterations to commit to according to its own velocity and confidence, so when two teams commit to different numbers of iterations, you cannot compare them one to one.
Worked examples
Example 1: Many changeable requirements; how to deliver value early
An agile team is creating a release plan for a company's internal approval system. The departments that use the system keep raising adjustments, there are many requirements to build and they change often, the backlog has already been ordered, and management wants to see value as early as possible. How should the team decide what the first release includes?
Show answer and explanation
Correct answer: D
The internal approval system is at the release planning stage. The backlog has been ordered, but there are many requirements and they change often, and management wants to see value as early as possible.
The backlog is already ordered; what is missing is “what goes into the first release”. To deliver value early, the key is to deliver a small, complete increment first. A minimum marketable feature (MMF) is the smallest scope of functionality that can be delivered independently and brings value to users (a common exam term). Organize the requirements into it and release the most valuable part first; the changing requirements can be adjusted in later releases. The answer is D.
Why the other options are wrong
- A. The stem says the backlog has already been ordered. Reordering again will not decide which content makes up the first release, and ordering is the product owner's responsibility anyway.
- B. Posting a Kanban board is an information radiator, which makes progress transparent but does not get value delivered sooner.
- C. Root cause analysis is for finding the cause of problems and has nothing to do with organizing requirements or delivering value early.
Key takeaway When requirements are many and changeable and you want value early, organize them into a minimum marketable feature and release it first.
Variation If the stem asked what to do so that stakeholders can see progress clearly, the answer would shift to the information radiator; if it asked which feature to build first, we are back to ordering by value.
Something wrong with this question?
Example 2: The customer keeps asking which day it will be usable
A major customer of a software vendor keeps asking: exactly which day will the new version be usable? The lack of a clear answer makes the customer more and more uneasy. What should the agile practitioner do to put the customer's mind at rest?
Show answer and explanation
Correct answer: D
A major customer of a software vendor keeps asking exactly which day the new version will be usable, and the absence of a clear answer unsettles the customer. The question asks how to ease the customer's concern.
What the customer wants is timing. A release plan provides a high-level summary timeline for the release, with the expected release window of each version and the iterations it contains, and among these documents it responds best to the customer's concern about time; it should be updated continuously as new information arrives and gives an expected window, not a commitment to an exact date. Building it together with stakeholders lets the customer take part in and accept the timeline, and the unease falls. The customer cares about “when can we use it”, and a document with no timeline or iteration arrangement cannot answer that, let alone ease the concern. The answer is D.
Why the other options are wrong
- A. Requiring all user stories to be written in advance and fixed to specific iterations creates unnecessary up-front work and false precision, and having every story written still would not give a reliable launch time. The customer cares about release timing, so first give an expected release window through a release plan that is updated continuously.
- B. A vision statement sums up goals and value and contains no schedule.
- C. A product strategy document explains direction and goals and likewise has no specific release timing.
Key takeaway When a customer wants to know when it will launch, build the release plan together with stakeholders.
Variation If the customer wanted to know roughly where the product is heading in two years, the answer would be the product roadmap; if they wanted to know what is being done next week, it would be the iteration plan.
Something wrong with this question?
Example 3: Velocity is below expectations; adjust the release plan
An agile team at an online education platform planned to release version 2.0 at the end of the year. For reasons within the team, velocity has been below expectations for several iterations in a row, and at this rate all deliverables will be completed after the planned release date. What should be done?
Show answer and explanation
Correct answer: C
A team at an online education platform is in the iterative delivery stage. For reasons within the team, velocity has been below expectations for several iterations, and at this rate all deliverables will be completed after the year-end release date. How should the team respond?
A release plan is derived from velocity and the size of the backlog. Actual data has shown that velocity is lower than expected, so the original projection no longer holds. The correct step is to revise the release plan, using the team's current actual velocity and in negotiation with stakeholders, so that it reflects the team's real delivery capability. The answer is C.
- Illustration (the stem gives no numbers; the numbers below only demonstrate the method): suppose the planned velocity was 24 points and the backlog 156 points, so 156 ÷ 24 = 6.5, rounded up to 7 iterations.
- After the start, the first two iterations actually complete 20 and 18 points, an average of (20 + 18) ÷ 2 = 19 points.
- Recalculate with actual velocity: remaining 156 − 38 = 118 points, 118 ÷ 19 ≈ 6.2, rounded up to 7 iterations, plus the 2 already done, 9 in total.
- Check: 7 × 19 = 133 ≥ 118 and 6 × 19 = 114 < 118. The release moves from 7 iterations to 9, two more, and the plan must be revised accordingly.
Why the other options are wrong
- A. Working on more stories at once increases work in progress and slows completion of individual stories; it does not reliably improve velocity. Update the forecast from actual data instead of trying to force it upward through more parallel work.
- B. The daily coordination meeting can check progress and adjust the execution plan within the iteration, but it cannot replace updating the release-level forecast; adjusting the release plan needs separate negotiation with stakeholders.
- D. Agile stresses a sustainable pace. Several weeks of overtime would put quality and sustainability at risk and is not an appropriate way to correct the release forecast.
Key takeaway When velocity falls short, adjust the release plan to fit actual velocity rather than pushing through with overtime or parallel work.
Variation If velocity is low because of an outside impediment (for example, an environment that stays unavailable), remove the impediment first and then recalculate at the restored velocity; if stakeholders insist the date cannot move, negotiate cutting scope.
Something wrong with this question?
Common traps
Common trap
- An iteration is not a release: a release contains several iterations, an iteration produces an increment, and a release is handing it to users.
- The common practice is story points for features (stories) and hours for tasks; estimates at the same level should use consistent units, and you should not mix units in a single calculation.
- Velocity is a team-specific forecasting metric; velocities of different teams cannot be compared directly, and velocity should not be used as a performance appraisal measure.
- When velocity is not enough, adjust the release plan to fit actual velocity; do not work overtime or run more stories at the same time.
- When whole iterations are needed for delivery, round the number of iterations up; convert to dates by the iteration rhythm, and give a forecast range when there is enough data.
Key takeaways
- A release plan is a timeline on the scale of a few months that sets the number of iterations in the release cycle and roughly predicts which features each iteration may deliver (which stories are actually selected is decided at iteration planning).
- The release plan sets the number and rhythm of iterations, and the iteration plan arranges the specific features; a common practice is to estimate features in story points and tasks in hours.
- Iterations needed = remaining story points ÷ velocity, rounded up; with a fixed date, deliverable amount = velocity × number of iterations.
- Give a range using the lowest and highest velocity, arrange the most important part first, and keep updating the forecast with actual velocity; the lower end of the range is not a guarantee.
- Deliver the minimum marketable feature first (a common exam term); when velocity falls short of expectations, revise the release plan by actual velocity.
Lesson 3
Prioritization: Value, Cost, Risk and Common Methods
Lesson overview
A backlog often contains more than one release can hold, so ordering is one of the product owner's most important jobs. This lesson covers what to look at when ordering and then four common methods: MoSCoW, Kano analysis, the 100-point method and cost of delay, with worked examples showing how ordering resolves the shortfall when velocity is not enough. ECO: Process domain, Task 3 (Help ensure value-based delivery). The previous lesson covered the release plan; this lesson decides what goes into the release.
What to look at when ordering
As a common exam practice, ordering looks at three things: value (how much business value it brings), cost (how much it takes to build) and risk (how uncertain it is). The ordering basis in the PMBOK 8 text is value, dependencies, and technical or operational risk; in practice cost or effort can also be weighed. The purpose of the product owner ordering user stories is to deliver first the value stakeholders care about most. The commonly used methods PMBOK lists under prioritization include MoSCoW (must have, should have, could have, and will not have), the 100-point method, cost of delay and Kano analysis.
MoSCoW and Kano analysis
MoSCoW sorts requirements into four classes: must have, which the current release cannot do without, and whose absence would make the release unworkable, unsafe, non-compliant or unable to reach its core goal, such as compliance requirements; should have, which is expected to be completed; could have, which is nice to have; and will not have, which is explicitly not done this time. Use it when you need to quickly separate what the delivery must include from what can be added later.
Kano analysis classifies along two dimensions, whether the feature is implemented and whether the user is satisfied. PMBOK 8 lists only the name of this method; the attribute classes are a common exam term. The core is three classes, must-be, performance (expected) and delighter, with two more, indifferent and reverse. Must-be attributes: very unhappy without them and not especially pleased with them. Performance attributes: the better implemented, the more satisfied, in a linear way. Delighter attributes: no one minds their absence, and having them is a pleasant surprise. Indifferent attributes: whether implemented or not, they do not noticeably change user satisfaction. Reverse attributes: having them actually makes users less satisfied. To tell apart the features customers take for granted, expect and are delighted by, use Kano analysis. Attributes shift over time: yesterday's delighter may be a must-be today.
The 100-point method and cost of delay
The 100-point method: each stakeholder has 100 points to distribute freely across the features; the more points, the more important. Three representatives allocate points to four features A, B, C and D:
| Representative | A | B | C | D | Total |
|---|---|---|---|---|---|
| Alex | 40 | 30 | 20 | 10 | 100 |
| Priya | 10 | 50 | 30 | 10 | 100 |
| Daniel | 30 | 20 | 40 | 10 | 100 |
| Total | 80 | 100 | 90 | 30 | 300 |
Check: each person's total is 100, the three people have 300 in all, and the column totals add up to 80 + 100 + 90 + 30 = 300, which matches. The order is B, C, A, D.
Cost of delay looks at “how much do we lose if this is done a week later?” Common exam practice is to divide the cost of delay by the duration needed and do the larger first. Feature X loses $6,000 a week and needs 2 weeks, giving 3 (thousand dollars per week squared, the same below; it is only a relative priority index); feature Y loses $9,000 a week and needs 6 weeks, giving 1.5; feature Z loses $2,000 a week and needs 1 week, giving 2. The order is X, Z, Y. Check the total cost of delay (assuming each feature keeps losing a fixed amount every week it is undelivered, total cost of delay = weekly loss × the week in which it is completed, summed): X, Z, Y are completed in weeks 2, 3 and 9, so 6×2 + 2×3 + 9×9 = $99,000; if Y, which loses the most, is done first, Y, X, Z are completed in weeks 6, 8 and 9, so 9×6 + 6×8 + 2×9 = $120,000, which is higher.
When velocity is not enough, trade off by ordering
Worked example: there are 2 iterations left before the release and the velocity is 12 points, so the team can do 2 × 12 = 24 points. The backlog scope is 30 points, a gap of 6 points. Classified by MoSCoW: must have 16 points, should have 8 points, could have 6 points, 16 + 8 + 6 = 30 in total. The 24 points fit exactly the must haves plus the should haves (16 + 8 = 24), and the 6 points of could haves are moved out of this release. This is the common exam practice for “the work cannot be finished at this velocity”: first agree with the product owner and stakeholders on the ordering by value, rather than adding people, delaying or squeezing estimates.
Look at value and risk together: items with higher business value, lower cost and risks that need earlier attention go first. High-value, high-risk items go first because they answer fastest whether it can be made to work; low-value, high-risk items should not be moved forward just because of their risk. But a high-risk item with lower direct value that threatens overall feasibility, compliance or later work (such as a key technology validation or a compliance matter) may also be moved forward, and the judgment should weigh value, risk exposure, dependencies and cost together.
Key point
When a new requirement arrives or stakeholders apply pressure, do not jump the queue or escalate immediately; first reorder by value with the product owner and the team. When requirements from several parties conflict, the product owner orders them uniformly by business value. After the iteration review, stakeholders give their input and the product owner reorders the backlog accordingly.
Worked examples
Example 1: What are the three things to look at when ordering
The product owner of a software team has to put the user stories in the backlog into order. Which factors should be the main ones considered when ordering?
Show answer and explanation
Correct answer: D
The product owner has to put the user stories in the backlog into order. The question asks which factors should be the main ones to consider when ordering.
The purpose of ordering is to deliver first the value that stakeholders care about most. As a common exam practice, ordering looks at three things: value (how much business value it brings), cost (how much it takes to build) and risk (how uncertain it is and whether it needs early attention). The ordering basis in the PMBOK 8 text is value, dependencies, and technical or operational risk, and in practice cost can also be weighed. The answer is D.
Why the other options are wrong
- A. Size can help measure effort and convenience may reflect customer value, but this group leaves out risk and dependencies and is not the main basis for ordering.
- B. Difficulty and duration can help with economic trade-offs, but this group lacks value, dependencies and risk, and team preference should not drive the order. Ordering is aimed at value, not at ease of work or preference.
- C. Schedule and staff availability affect how much can be selected into one iteration, not the main factors for ordering the user stories themselves.
Key takeaway Backlog ordering looks at three things: value, cost and risk.
Variation If the question asked for a method to quickly separate “must have” from “could have”, the answer would be MoSCoW; if it asked to tell basic expectations from delighters, it would be Kano analysis.
Something wrong with this question?
Example 2: Velocity cannot keep up with the backlog
An agile project has entered its second iteration. The product owner finds that after the first iteration about 30 story points within the scope of this release are still unfinished, while the team completed only 12 story points in the first iteration, and only 2 iterations remain before the release date, so at this velocity only about 24 more story points can be completed and the work cannot be finished before the release date. As an agile practitioner, how should you handle this?
Show answer and explanation
Correct answer: B
An agile project is in its second iteration. After the first iteration, about 30 story points within the scope of this release remain unfinished, but the team completed only 12 points in the first iteration, so at this velocity the work cannot be finished before the release date. How should this be handled?
With time limited and velocity known, not all of the scope can be completed, so trade-offs are necessary. The basis for the trade-off is value: together with the product owner, ask stakeholders to meet and agree on the ordering of the product backlog by value, so that the limited output goes to the most valuable items. This neither oversteps nor avoids the problem. The answer is B.
- Velocity is 12 points per iteration and the scope is about 30 points: 30 ÷ 12 = 2.5, so about 3 iterations are needed.
- Deliverable capacity = number of iterations remaining before release × historical velocity. 2 × 12 = 24 points, which is less than the 30-point scope, so trade-offs are required.
- Order by value, use the capacity on the highest-value items, and move the remaining items out of this release or negotiate them separately.
Why the other options are wrong
- A. The items that can be finished fastest are not necessarily the most valuable. Doing the easy ones first pushes high-value content later.
- C. Adding people does not raise velocity right away, and the ramp-up period can slow output in the short term. Changing resources also needs discussion with the sponsor and the team, and there is no need to ask for more people before trying to focus on value ordering.
- D. Asking for a delay straight away is the least suitable first reaction. First focus on value within the scope, rather than giving up the deadline first.
Key takeaway When velocity cannot keep up with the volume of the backlog, first agree with stakeholders on the value ordering, rather than adding people or delaying.
Variation Only if stakeholders agree that all 30 points are must-haves does it make sense to negotiate a delay or more iterations; if the stem said the team had spare capacity, no trade-off would be needed and items would go in by their order.
Something wrong with this question?
Example 3: Telling apart what is taken for granted, expected and delightful
A Scrum team is developing a consumer product. The product owner wants to analyze how features affect customer satisfaction differently, distinguish features the customer takes for granted, expects and is delighted by, and order the features accordingly. Which method can be used?
Show answer and explanation
Correct answer: C
A Scrum team develops a consumer product, and the product owner wants to separate features the customer takes for granted, features the customer expects and features that delight, and order the features accordingly. Which method can be used?
The three groups in the stem correspond to the basic, performance (expected) and delight attributes of Kano analysis. Kano analysis classifies features along two dimensions, whether the feature is implemented and whether the user is satisfied, and helps the product owner compare how each feature affects satisfaction and then order them. Attributes also shift over time: yesterday's delighter may be a basic expectation today, so reassess regularly when ordering. The answer is C.
Why the other options are wrong
- A. Planning poker is an estimating technique that produces story points. It is not used to analyze customer satisfaction.
- B. SMART is for setting goals that are specific and measurable. It cannot classify or order features.
- D. A cause-and-effect diagram traces the root cause of a problem and has nothing to do with ordering by customer preference.
Key takeaway To tell apart what customers take for granted, what they expect and what delights them, order with Kano analysis.
Variation If the stem asked about “must have, should have, could have and will not have”, the answer would be MoSCoW; if each stakeholder votes with 100 points, it is the 100-point method.
Something wrong with this question?
Common traps
Common trap
- The ordering basis in PMBOK 8 is value, dependencies, and technical or operational risk (in practice cost or effort can also be weighed); it is not how convenient something is to build or whose voice is loudest.
- When velocity is not enough, focus on ordering by value; do not add people, work overtime or squeeze estimates.
- Do not treat “do the easy ones first” as priority; items that can be finished quickly are not necessarily of high value.
- A feature with low value but high risk should not be put first just because of the risk (except foundational work that threatens feasibility or compliance).
- Planning poker is an estimating technique, SMART is goal setting, and cause-and-effect diagrams find root causes; none of them is an ordering method.
Key takeaways
- Ordering combines value, dependencies, and technical or operational risk, weighed together with cost or effort; the purpose is to deliver the most valuable part first.
- MoSCoW has four classes: must have, should have, could have and will not have; Kano analysis centers on must-be, performance and delighter attributes, with indifferent and reverse as two more (the attribute classes are a common exam term).
- The 100-point method orders by total points; cost of delay (common exam practice is cost of delay ÷ duration, larger first; PMBOK 8 lists only the method name).
- When velocity is limited: deliverable amount = velocity × remaining iterations; fill by priority and move the rest out.
- For priority disagreements or new requirements, go to the product owner and reorder with value data; do not jump the queue or decide unilaterally.
Lesson 4
Agile Risk Management: Risks in the Backlog
Lesson overview
An agile project can maintain a risk register lightly (the ECO requires maintaining a risk register, and whether it is a separate document is tailored to the project's needs) and builds risk into its everyday rhythm: write risk response work as backlog items, let it take part in ordering, deal with it within iterations, and keep showing it on a chart. This lesson covers how risk adjusts the backlog, the value-and-risk quadrants, and how a risk burndown chart is calculated. ECO: Business Environment domain, Task 5 (Plan and manage risk). For identification, analysis and response on predictive projects, see the chapters in the risk topic.
Write risk response work as backlog items and order it with the features
A newly found risk first has to be identified, analyzed and given a response plan. The work used to validate, mitigate or exploit a risk can be written as backlog items (exploratory tasks such as “validate the response time of the new map service under high concurrency”; only requirements that suit expression from the user's perspective are written as user stories) and placed in the product backlog, where they are ordered together with the feature stories by value and risk. The result is a risk-adjusted backlog. When the stories to be selected into an iteration carry high risk, add “risk-based iteration tasks” to the iteration plan, so the response work is planned in together with the features and not left for the retrospective. Whether an item is selected into the current iteration should be decided by weighing value, capacity, dependencies and risk together; where needed it can be reordered, split, explored first or deferred. For a sudden risk, first talk with the team, update the risk register promptly, analyze it and decide on a response together; then add any response or exploration work that must be performed to the Product Backlog as an appropriate type of item and order it with the rest.
Value-and-risk quadrants
With value and risk as the two dimensions, each item falls into a quadrant. A common exam practice (a simplified value-risk matrix, not a fixed total order): do high-value, high-risk first, because the return is large and uncertainty is exposed early; next high-value, low-risk; then low-value, low-risk; and stay away from low-value, high-risk where you can. In actual ordering you must also consider dependencies, compliance, urgency, the cost of delay and risk thresholds, and a low-value, high-risk item can also be foundational work that must be dealt with.
Worked example: four backlog items are scored 1 to 10 for value and risk, with 5 as the dividing line and anything above 5 counted as high:
| Item | Value | Risk | Quadrant | Order |
|---|---|---|---|---|
| A Integrate a new payment channel | 8 | 8 | High value, high risk | 1 |
| B Optimize the order list | 8 | 3 | High value, low risk | 2 |
| C Change the help page copy | 3 | 3 | Low value, low risk | 3 |
| D Build a custom map engine | 3 | 8 | Low value, high risk | 4, avoid if possible |
A comes first because it answers fastest “can the new channel be made to work?”: if it fails, the project can still adjust early, with little invested.
Common trap
“Do high risk first” has a precondition: the item also has fairly high value. A low-value, high-risk feature should not move to the front just because it is high risk.
The risk burndown chart
PMBOK 8 points out that a burndown chart can show the number of story points remaining or the amount of risk exposure that has been reduced. A risk burndown chart tracks the overall risk exposure over time; common exam practice (the one used in this lesson) is to add up each risk's score = probability × impact into a total, with time on the horizontal axis. All the risks in this lesson's example are threats, so the total is threat exposure and normally falls when responses work; if opportunities are included as well, show threats and opportunities separately, and do not conclude that overall risk has improved just because a combined total of threats and opportunities fell.
Worked example: before the iteration starts there are 5 risks (impact scored 1 to 10): Risk 1 probability 0.5, impact 8; Risk 2 probability 0.3, impact 10; Risk 3 probability 0.7, impact 5; Risk 4 probability 0.2, impact 6; Risk 5 probability 0.4, impact 9.
- The risk scores are 4.0, 3.0, 3.5, 1.2 and 3.6, with a total of 4.0 + 3.0 + 3.5 + 1.2 + 3.6 = 15.3.
- End of iteration 1: Risk 1's probability falls to 0.2 after the response, a score of 1.6; Risk 3 is closed and counts as 0; a new Risk 6 is found, probability 0.3 and impact 4, a score of 1.2. The total is 1.6 + 3.0 + 0 + 1.2 + 3.6 + 1.2 = 10.6.
- End of iteration 2: Risk 2's probability falls to 0.1 after the response, a score of 1.0; Risk 5 is closed. The total is 1.6 + 1.0 + 1.2 + 1.2 = 5.0.
- The total falls from 15.3 to 10.6 and then to 5.0, showing that in this example the threat exposure is going down. Check the first difference: 15.3 − 10.6 = 4.7, which equals closing Risk 3 (3.5) plus Risk 1's reduction (4.0 − 1.6 = 2.4), minus the new Risk 6 (1.2): 3.5 + 2.4 − 1.2 = 4.7.
A new risk raises the total, so the curve does not necessarily decline continuously; that is normal. To keep risk visible, show the risk burndown chart openly as an information radiator, together with the daily coordination meeting and the iteration planning meeting; for risks the team is worried about, bring in experts early to analyze them and include them in planning.
Worked examples
Example 1: How to handle a risk created by new technology
The agile team of a map app raises a question about a requirement during an iteration: the team left out the new technology needed to implement the requirement when it estimated, and this new challenge could take quite a lot of extra time. The requirement is very important. To keep the work moving smoothly, what should the product owner do?
Show answer and explanation
Correct answer: B
During an iteration, the map app team finds that its estimate left out the new technology needed to implement an important requirement, and this challenge could take considerable extra time. The question asks what the product owner should do.
The new technology was not estimated and may delay progress, which brings uncertainty. A technical exploration or validation item can be created for the challenge and put into the product backlog, where the product owner orders it by value and risk together with the other items, and the Developers adjust the implementation plan accordingly; if the work affects the current iteration goal, both sides should negotiate the scope of the current iteration. The uncertainty is then visible and ordered, and the iteration timebox is not broken. The answer is B.
Why the other options are wrong
- A. Agile does not make overtime a first choice, and it is not sustainable. Extra work should be handled through ordering and planning.
- C. The way to implement something is decided jointly by the self-organizing team. The stem says the requirement needs the new technology, so it cannot arbitrarily fall back on the old one.
- D. Once an iteration has started its timebox stays fixed and is not extended to finish one requirement. Handle it by negotiating scope and reordering; extending the timebox is not how a new risk is dealt with.
Key takeaway For uncertainty caused by new technology, create a technical exploration or validation item in the backlog and order it together with the features.
Variation If it were an impediment that has already occurred in the iteration rather than a potential risk, it would be raised at the daily coordination meeting and the Scrum Master would help remove it; if the uncertainty is high and the value is high, put the item near the top of the backlog.
Something wrong with this question?
Example 2: Considering value and risk together in ordering
On an agile project, an agile management professional is concerned about the high-risk parts of the project and wants to consider both risk and value when ordering solutions. What should be done?
Show answer and explanation
Correct answer: C
On an agile project, the agile management professional is concerned about parts with high risk and wants to consider both risk and value when ordering. What should be done?
To look at both dimensions, use a value-and-risk quadrant chart: each item falls into one quadrant. As a common exam practice for this simplified matrix, usually implement high-value, high-risk content first: the payoff is large and uncertainty is exposed early, so the team can adjust early if the approach does not work. The other quadrants are commonly considered in the order high-value and low-risk, low-value and low-risk, then low-value and high-risk. This is not a fixed total order, however: actual ordering also considers dependencies, compliance, urgency and risk thresholds, and foundational low-value, high-risk work may still need early attention. The value-and-risk quadrant chart is common exam practice. The answer is C.
Why the other options are wrong
- A. Content with low value should not be done first even when its risk is high; do high-value content first.
- B. An information radiator makes information visible and is not an ordering method. Looking only at risk also ignores value.
- D. A cause-and-effect diagram analyzes the causes of problems and cannot put value and risk together for ordering.
Key takeaway To order by value and risk together, use a quadrant chart and do high-value, high-risk items first.
Variation If an item has low value and high risk, avoid doing it where possible; if the question asked about tracking the overall risk exposure over time, the answer would be a risk burndown chart.
Something wrong with this question?
Example 3: How to place a high-risk story in the iteration plan
While planning the next iteration, the agile team on a logistics tracking project finds that several of the user stories it intends to select carry high risk. How should the iteration plan be arranged to manage these risks?
Show answer and explanation
Correct answer: D
While planning the next iteration, the team finds that several user stories it intends to select are high risk. The iteration plan has to include risk management.
Agile treats risk response as work in its own right. When high-risk stories are found, create risk-based iteration tasks and put the response work into the iteration plan together with the feature stories, for the team to complete during the iteration. The risk then enters the team's daily rhythm at the planning stage instead of waiting until something goes wrong. Risk response takes team capacity just like features do, so it must go into the iteration plan and not be left for “when there is time”. The answer is D.
Why the other options are wrong
- A. Dealing only with probability is not comprehensive, since risk management has to consider both probability and impact, and dealing with the rest after the event misses the time to respond.
- B. A story should not be moved out of the iteration and left for the risk to vanish simply because it is risky, since that only delays the problem surfacing. Assess the risk, adjust the order in light of value, dependencies and constraints, and put the needed response work into the plan.
- C. A retrospective reviews what has already happened. Discussing risks only then is far too late.
Key takeaway Pair high-risk stories with risk-based tasks in the iteration plan so they are dealt with early.
Variation If a new risk appears only midway through the iteration, first talk with the team and decide together, assess it promptly and choose a response; response work to be carried out later can be ordered together with other backlog items of an appropriate type.
Something wrong with this question?
Common traps
Common trap
- Risk response work can go into the backlog as items just like features; it does not need a separate document.
- High-risk items should be validated or dealt with early, not left for discussion at the retrospective; whether they go into the current iteration is decided by weighing value, capacity, dependencies and risk.
- High-value, high-risk goes first; low-value, high-risk does not go first.
- A risk burndown chart tracks risk exposure (common exam practice is the total of probability times impact), not how many response actions have been completed.
- A technology choice should be decided by the appropriate roles and the team together, weighing value, architectural constraints and risk; using proven technology, trying a new one or changing the approach can each be a reasonable risk response.
Key takeaways
- Risk response work can go into the product backlog as items, ordered with the features, forming a risk-adjusted backlog.
- In iteration planning, add risk-based iteration tasks for high-risk stories.
- The usual order of the quadrants (a common exam practice, not a fixed rule): high value, high risk; high value, low risk; low value, low risk; low value, high risk (avoid unless it is foundational work that must be dealt with).
- Risk score = probability × impact; the risk burndown chart tracks the sum over all items over time.
- Use the information radiator and the daily coordination meeting to keep risk visible.
This chapter has 42 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.