- Burndown Charts and Information Radiators
Agile and Hybrid
Burndown Charts and Information Radiators
PMP · Agile and Hybrid · 2 lessons · about 28 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Agile projects do not explain progress through long status reports. They draw progress as a chart and post it where the team and stakeholders can see it. This chapter centers on two charts, the burndown chart and the burnup chart. Lesson 1 teaches you to read them: how the ideal line is drawn, how the actual line is compared with it, and why a burnup chart is used when scope changes. Lesson 2 uses the charts for forecasting and decisions: a trend line shows whether the iteration can be completed, remaining story points divided by velocity give the number of iterations the release still needs, and there is guidance on talking with the product owner when the team is behind. Finally it covers the medium these charts live on: the information radiator.
Questions on this chapter are of two kinds: identification questions (“which chart shows how much work remains?”) and scenario questions (“what to do when behind?”, “what to do when a stakeholder wants to see progress?”). The calculations cluster in two places: the ideal line's daily decrease, and trend forecasts and the number of release iterations.
Lessons in this chapter
- Lesson 1: Reading Burndown and Burnup Charts: Remaining Work, Completed Work and Scope. Ideal daily decrease = selected total ÷ number of iteration days; ideal remaining on day d = selected total − ideal daily decrease × d; variance = actual − ideal; remaining = total scope − cumulative completed; iteration-level and release-level charts; choose a burnup chart when scope can change.
- Lesson 2: Forecasting Progress with Charts, Making Decisions, and Information Radiators. Three reasons a line goes up; forecasting from the net trend and the daily completion rate; iterations in a release = remaining points ÷ velocity (velocity being the team's average points per iteration, rounded up); negotiating with the product owner when behind; information radiators are low tech and high touch, and when they meet the communication need they take priority over status reports.
How to study this chapter
Start by doing it yourself: take an iteration with 40 points selected over 10 days, draw the ideal line, fill in an actual remaining figure each day, work out the variance, and get a feel for what happens when the line moves upward. Then turn the same data into a burnup chart and check “remaining = total scope − cumulative completed”. For forecasting, remember only two formulas: within an iteration, look at the daily completion rate of the last few days; for a release, take remaining points divided by velocity and round up. For information radiators, remember the keywords: usually low tech and high touch, easy to update and updated frequently; when they meet the communication need they take priority over status reports, and formal reports can still accompany them where needed.
Chapter map
Visualizing progress
- Burndown chart (remaining, going down): ideal line + actual line + trend line; iteration and release levels
- Burnup chart (cumulative completed + total scope): clearer when scope can change
- Forecasting: within an iteration, the trend line; for a release, remaining points ÷ velocity
- Falling behind: keep the fixed timebox and iteration goal, have the developers and the product owner negotiate scope or plan, no overtime; if the iteration goal is obsolete, the product owner decides whether to cancel the iteration
- Information radiator: low tech, high touch, easy and frequent to update; when it meets the communication need it takes priority over status reports, with formal reports alongside where needed
Lesson 1
Reading Burndown and Burnup Charts: Remaining Work, Completed Work and Scope
Lesson overview
Agile teams do not explain progress with long status reports; they put progress on the wall as a chart. This lesson covers the two charts tested most often, the burndown chart and the burnup chart. First you learn how a chart is drawn, then how to read it, and finally which one to choose when scope can change. ECO: Process domain, Task 9 (Evaluate project status). The next lesson covers how to use the charts to forecast progress, what to do when behind, and the medium the charts live on, the information radiator.
The burndown chart: remaining work against time
PMBOK 8 defines a burndown chart as “a graphical representation of the work remaining versus the time left in a timebox.” The horizontal axis is time (days in an iteration, iterations in a release), and the vertical axis is the work remaining, measured in story points or in hours. As work is done there is less left, and the line “burns down” toward the lower right.
There are two lines on the chart. The ideal line is drawn from the work selected at iteration planning, falling in a straight line from the selected total to zero at the end of the timebox; the actual line is the work remaining recorded each day. The ideal line is drawn in three steps: after the planning meeting, enter the selected total as the starting point; mark the days on the horizontal axis; and draw a straight line from the starting point to zero. After that, plot the actual remaining work each day, and the actual line takes shape.
Worked example
An iteration selects 40 story points over 10 working days. The ideal line falls 40 ÷ 10 = 4 points a day, and the ideal remaining on day n is 40 − 4n. On day 7 the ideal remaining is 40 − 28 = 12 points. Check: on day 10, 40 − 40 = 0, so the line lands exactly on the end point.
The update rule affects how true the chart is. When measuring in story points, deduct a story from the remaining work only when it is done and meets the definition of done (DoD); a story that is half done is not deducted. When measuring in remaining hours, update the hours still needed each day. Otherwise the curve looks good but does not reflect real progress.
Reading a burndown chart: compare with the ideal line
Reading a chart comes down to one thing: subtract the ideal remaining from the actual remaining each day. Actual above ideal means behind; below ideal means ahead. Take the same iteration as above; from day 0 (end of planning) to day 7, the actual remaining recorded each day is 40, 36, 33, 33, 28, 24, 26 and 22.
| Day | Ideal remaining | Actual remaining | Variance (actual − ideal) | Judgment |
|---|---|---|---|---|
| 3 | 28 | 33 | +5 | Behind; no story was completed that day |
| 5 | 20 | 24 | +4 | Behind; the gap has narrowed by 1 from +5 on day 3 (work was completed on day 4, not shown in the table) |
| 6 | 16 | 26 | +10 | Behind; remaining work actually went up |
| 7 | 12 | 22 | +10 | Behind; the gap has not narrowed |
On day 6 the line goes up because the team completed 4 points and at the same time 6 points were added: 24 − 4 + 6 = 26. A burndown chart shows only the net result, so you cannot see how much was “done” and how much was “added” that day. This is exactly the problem the burnup chart in the next section solves.
An iteration burndown chart covers a single iteration and is updated daily by the team. A release contains several iterations; with iterations on the horizontal axis and the remaining story points for the whole release on the vertical axis, you have a release-level burndown chart. To see “can this iteration finish the selected work”, look at the iteration chart; to see “how far is the whole release from its goal”, look at the release-level chart.
The burnup chart: completed work plus a total scope line
PMBOK 8 defines a burnup chart as “a graphical representation of the work completed toward a milestone.” Burnup charts are used mostly within adaptive development approaches to show project progress over time. The chart tracks the work to be completed as a straight line across the top of the graph, and the work completed starts at zero and keeps increasing as more work is completed. So there are two lines on the chart: a “cumulative completed” line that goes up, and a “total scope” line at the top. When the completed line catches the scope line, the work is done.
Put the same data on a burnup chart: cumulative completed is 0, 4, 7, 7, 12, 16, 20 and 24; total scope is 40 for the first 5 days and 46 from day 6. The difference between the two lines is the remaining amount on the burndown chart, which gives a check: on day 7, 46 − 24 = 22, matching the burndown chart. On day 6 the scope line moves up 6 points while the completed line keeps rising 4 points; the two events are shown separately and can be told apart at a glance.
Compare
- Burndown chart: one actual remaining line (usually with an ideal burndown reference line) showing remaining work, going down; clear when scope is stable and suited to the iteration level.
- Burnup chart: two lines showing cumulative completed and total scope, with the completed line going up; clearer when scope can change and suited to the release level.
When scope does not change, the two charts convey about the same information. When scope can change, the burndown chart mixes “done” and “added” in one line, so when the line flattens or rises you cannot tell why; the burnup chart separates the two, and you can read both the progress and the scope change.
Worked examples
Example 1: What to use to see “how much work remains”
An agile team is developing an inventory management system for a supermarket chain. Development is in its middle to late stage, and the operations director wants to know how much development work remains and whether progress is going well. Which tool should the team use to explain this to the director?
Show answer and explanation
Correct answer: B
The project is in its middle to late stage, and the operations director is concerned with “how much work remains and whether progress is going well”. The question asks which tool to use to explain this to the business side.
“How much remains” and “is progress going well” are about remaining work and progress. A burndown chart plots remaining work as a curve over time and compares it with the ideal line: a line below the ideal line means ahead of plan, above it means behind. The director does not need to read a task list; a glance at the position and direction of the line shows whether work is falling as expected. It is also an information radiator, kept current and understood by everyone. The answer is B.
Why the other options are wrong
- A. An iteration plan mainly describes the work to be completed in the iteration and how it will be carried out. Even if the plan can be adjusted, it does not show the change in remaining work over time and the completion trend as intuitively as a burndown chart, and it does not show how much is done and how much remains.
- C. A product roadmap is long-term, high-level planning that answers what each version will roughly deliver. It does not reflect current development progress.
- D. A release plan schedules the releases and the iterations they contain. It is also a planning document and does not show the change in remaining work over time.
Key takeaway For “how much work remains and how is progress”, use a burndown chart; planning documents answer “what we intend to do”.
Variation If the director also wants to see when scope was added or removed, choose a burnup chart; if the question is how far the whole release is from its goal, use the release-level burndown or burnup chart, not a single iteration's chart.
Something wrong with this question?
Example 2: Iteration burndown chart versus the release level
An iteration planning meeting for an order-lookup feature has just ended and the story points have been totaled. The team draws an iteration burndown chart covering the next 4 weeks. A member makes four statements about the chart. Which one is NOT correct?
Show answer and explanation
Correct answer: C
An iteration planning meeting has just ended, and the team draws an iteration burndown chart covering four weeks. Note that the question asks which of the member's four statements is incorrect.
The scope of an iteration burndown chart is one iteration. Its starting point is the amount of work selected at iteration planning, which is also the starting point of the ideal line. After that, the work not yet completed in this iteration is recorded each day, and a trend line forecasts the situation at the end of the iteration. A release usually contains several iterations, and a chart covering one iteration cannot show how much of the whole release remains; for that you need the release-level burndown chart. “Records the amount of work remaining in the current release” is therefore the incorrect statement. The answer is C.
Why the other options are wrong
- A. Correct statement: an iteration burndown chart tracks the work not yet completed in this iteration's backlog.
- B. Correct statement: the starting point of the chart is the work selected at iteration planning, and the ideal line is drawn from it.
- D. Correct statement: the trend line on the chart extends from current progress and shows how much work is expected to remain in the iteration.
Key takeaway An iteration burndown chart covers only one iteration; for how much of the whole release remains, look at the release-level chart.
Variation If option C were changed to “records the work not yet completed in the current iteration”, it would be a correct description; if the question asked how far the whole project is from the release goal, the answer would be a release-level burndown or burnup chart.
Something wrong with this question?
Example 3: Which chart to choose when scope can change
An agile team is developing a voice assistant app. Stakeholders want the product owner to provide a tool that shows completed work clearly and also shows when scope is added or removed. What should the team use?
Show answer and explanation
Correct answer: D
The agile team is building a voice assistant app. Stakeholders want a tool that shows completed work intuitively and also shows when scope is added or removed.
The stem sets two requirements: show what is completed, and show changes in scope. A burnup chart has exactly two lines: a rising cumulative completed line and a total scope line at the top. When scope is added the scope line moves up, and when scope is removed it moves down; when the completed line catches the scope line, the work is done. A burndown chart has a single remaining-work line, so scope changes are mixed in with “work done” and you cannot tell whether the team slowed down or scope grew. When reading this kind of question, first circle the two requirements in the stem and then find the chart that meets both. The answer is D.
Why the other options are wrong
- A. An affinity diagram groups many ideas by similarity and is used to organize ideas. It does not show progress.
- B. A value stream map records and analyzes the flow of information or materials to find waste such as waiting. It does not show scope changes.
- C. A cause-and-effect diagram, also called a fishbone diagram, breaks a problem down layer by layer to find root causes. It has nothing to do with showing progress.
Key takeaway When scope can change and you need to see both completion and scope, use a burnup chart.
Variation If you only need to see how much remains and scope is stable, use a burndown chart; to find waiting time in a process, use a value stream map; to ask for the root cause of a problem, use a cause-and-effect diagram.
Something wrong with this question?
Common traps
Common trap
- A burndown chart shows “how much is left” and goes down; an earned value curve shows completed work in terms of the authorized budget and accumulates upward. When the stem asks about “remaining work”, the answer is the burndown chart.
- An iteration burndown chart covers one iteration only and cannot be used to answer how much of the whole release remains.
- A burndown line going up does not necessarily mean the team has slowed down; scope may have increased, so find the cause first.
- A half-done story is not deducted from the remaining work; only a story that meets the definition of done is.
- When you need to separate progress from scope change, prefer the burnup chart; a burndown chart shows only the net remaining amount.
Key takeaways
- Burndown chart: time on the horizontal axis and remaining work on the vertical axis; compare with the ideal line to read the variance; actual above the ideal line means behind.
- Ideal line = selected total ÷ number of days as the daily decrease, falling from the selected total to zero.
- Only stories that meet the definition of done are deducted from the remaining work.
- Burnup chart: a cumulative completed line plus a total scope line; remaining = total scope − cumulative completed.
- Choose a burnup chart when scope can change and a burndown chart for an iteration with stable scope; an iteration chart covers one iteration, and a release-level chart covers the whole release.
Lesson 2
Forecasting Progress with Charts, Making Decisions, and Information Radiators
Lesson overview
The previous lesson taught you to read the charts. This lesson uses them for two things: forecasting whether the work will be finished on time, and deciding what to do when the team is behind. Stepping back, all of these charts are posted on an “information radiator”, so the second half of the lesson covers what an information radiator is and why agile prefers it to status reports. Three questions come up often in the exam: why a line goes up, how a trend line shows whether the work can be completed, and what to do when a stakeholder wants to see progress. ECO: Process domain, Task 9 (Evaluate project status); People domain, Task 8 (Plan and manage communication).
Look at the trend, not a single day
One point on one day proves nothing. You have to look at which way the line is heading: staying flat, staying above the ideal line, or suddenly rising. The team looks at the chart at the daily coordination meeting and, if the trend is bad, discusses an adjustment on the spot. A line that goes up means the remaining work has increased, and there are three common reasons: new requirements were added midway through the iteration, the team found that stories are bigger than estimated, or defects increased. Find the cause first and then act, rather than blaming the team first.
Forecasting with the trend line and velocity
PMBOK 8 explains that on an iteration burndown chart a trend line is calculated from the remaining work and used to predict the likely variance at iteration completion. Velocity is a measure of a team's productivity rate at which deliverables are produced, validated and accepted within a predefined interval; the usual unit is “story points per iteration”, though a team may use another consistently applied measure of effort. Used together, they answer “will we make it?” A release-level burndown chart can also carry a trend line to show whether, at the current pace, it will reach zero before the target iteration (this is common exam practice; what PMBOK 8 states explicitly is the trend line of the iteration burndown chart).
Worked example 1: forecasting within an iteration. Continue with the iteration from the last lesson (40 points selected, 10 days). At the end of day 7, 22 points remain. Take the last 4 days (from 33 points on day 3 to 22 points on day 7) to look at the trend:
- Net drop 33 − 22 = 11 points, an average of 11 ÷ 4 = 2.75 points a day.
- On the net trend, clearing 22 points needs 22 ÷ 2.75 = 8 more days, which reaches day 15, far past day 10.
- During these 4 days the team also took in 6 points of new scope midway, so it actually completed 11 + 6 = 17 points (a net drop of 11 plus the 6 points offset by the new scope), an average of 17 ÷ 4 = 4.25 points a day. If no more scope is added, 22 ÷ 4.25 ≈ 5.2, so 6 working days, reaching day 13. Check: 6 × 4.25 = 25.5 ≥ 22, and 5 × 4.25 = 21.25 < 22.
- At the recent average pace, the remaining 3 days can complete about 3 × 4.25 = 12.75 points, so the expected gap is about 22 − 12.75 = 9.25 points; choose low-priority stories that can be moved out whole, and when story points are whole numbers move out at least 10 points in total (the final figure depends on story granularity).
The two ways of calculating reach the same conclusion: this iteration cannot be finished.
Worked example 2: forecasting at release level. A minimum viable product (MVP) has 72 points of scope and must be delivered by the end of the 4th iteration. The first two iterations completed 16 and 14 points, an average velocity of 15. Remaining is 72 − 30 = 42 points, and the 2 remaining iterations can do only 2 × 15 = 30 points, a gap of 12 points. 42 ÷ 15 = 2.8, rounded up to 3 iterations, so the work reaches the end of the 5th iteration. Check: 5 iterations give a cumulative 30 + 3 × 15 = 75 ≥ 72, and 4 iterations give a cumulative 60 < 72.
Key point
To forecast whether an iteration will be completed, look at the iteration burndown trend line, not predictive indices such as SPI or CPI. To forecast a release, you can look at the trend line of the release-level burndown chart or calculate how many iterations are still needed with “remaining story points ÷ velocity”, rounded up.
What to do when behind
The iteration timebox does not move, and the team does not catch up through overtime. The order is: talk early and in person with the product owner and stakeholders; the developers and the product owner negotiate an adjustment to the iteration backlog and, without endangering the iteration goal, move out some low-priority stories, after which the product owner reorders the work placed back in the product backlog; be transparent about the situation. If the whole release is behind, negotiate an adjustment to the release scope or date. Do not wait until delivery is near to tell people, and do not have the agile coach cut scope in the product owner's place.
Common trap
Deciding that the team's capability has degraded and arranging a performance review just because velocity falls is wrong. Velocity goes up and down. Find the cause first; it is used only for the team's own forecasting.
Information radiators
PMBOK 8 defines an information radiator as “a visible, physical display that provides information to the rest of the organization, enabling timely knowledge sharing.” Information radiators “may also be known as big visible charts”, are posted in a place where people can see the information easily, and “should be easy to update and should be updated frequently.” They are often “low tech and high touch” in that they are manually maintained rather than electronically generated. PMBOK 8 says only that an example can show work completed, work remaining and risks. In lean environments, information radiators are known as visual controls, and PMBOK 8 gives task boards and burn charts (burnup or burndown charts) as examples under visual controls; a cumulative flow diagram is in the PMBOK 8 glossary but is not among these visual control examples; it and parking-lot charts are common supplementary examples (common exam practice).
Agile prefers information radiators because they are open and transparent, give one consistent view of the numbers, and are updated more often than periodic reports. When a key stakeholder wants to know progress and an information radiator can meet the communication need, you can ask them to come and look at the wall; when the communication management plan, governance requirements or their preference calls for a formal status report, still provide one. When two executives get contradictory status, have them look at the same information radiator. When status is shown in color, write the meaning of the colors in a legend; otherwise people read them differently.
Compare
- Status report: sent at the frequency, in the format and to the audience set by the communication management plan, and can be directed at one or more stakeholders; the level of detail and presentation may differ by audience, but the underlying status data should remain consistent.
- Information radiator: frequently updated and posted where it is easy to see, providing information to members of the organization; stakeholders who can see the display can look for themselves, and those who cannot still need other means of communication.
Worked examples
Example 1: The burndown chart shows 5 days late; what to do
An e-commerce team is building a recommendation system and moves into the feature implementation phase after the framework is set up. The team reviews its burndown chart and finds that setting up the framework took longer than expected; at this rate, delivery of the features will be 5 days late. As an agile management professional, how should you help the team?
Show answer and explanation
Correct answer: B
On an agile project, the framework is set up and the team has moved into feature implementation. The burndown chart shows that the framework took longer than expected, and at this rate feature delivery will be 5 days late. The question asks how to help the team.
The burndown chart has already exposed the variance, and the next step follows the principles of transparency and adaptation: negotiate early and face to face with the product owner and stakeholders. They can choose to push out the delivery date or reduce the scope. The product owner listens to stakeholders and is responsible for the content and ordering of the product backlog, while business constraints such as the delivery date are negotiated with the relevant stakeholders. The team's responsibility is to lay out the facts and the options. A delivery commitment reached this way is reasonable and does not sacrifice the team's sustainable pace. The answer is B.
Why the other options are wrong
- A. Waiting until delivery is near gives stakeholders no time to adjust and only causes greater dissatisfaction. It goes against transparency.
- C. Cutting features is a decision for the product owner and stakeholders. The agile coach is a servant-leader role and has no authority to cut scope on his own initiative.
- D. Continuous overtime is not sustainable, harms quality, and does not change the team's real velocity, so the 5-day variance remains.
Key takeaway If the chart shows the team falling behind, negotiate early with the product owner and stakeholders to delay or reduce scope.
Variation If stakeholders insist the date cannot move, negotiate cutting low-priority scope, still without overtime. If only a single iteration is behind, the developers negotiate with the product owner and, without endangering the iteration goal, move low-priority stories out of the iteration and back into the product backlog, where the product owner reorders them.
Something wrong with this question?
Example 2: What to use to answer the concern “we will not make the MVP”
The product owner is anxious: the team may not make it to delivering the minimum viable product (MVP) in the fourth iteration. Which of the following should the project manager use to address this concern?
Show answer and explanation
Correct answer: A
The product owner is concerned that the team may not deliver the minimum viable product (MVP) in the fourth iteration. The project manager needs evidence that can address that concern.
The concern is whether the work will be finished on time, which calls for a tool that forecasts completion. A burndown chart plots the change in remaining work over time; compared with the ideal line and extended with a trend line, it shows whether at the current pace the MVP scope will reach zero before the end of the fourth iteration (this is at release level, and the remaining work is the remaining story points within the MVP scope). The product owner can then adjust scope or date in good time. PMBOK 8 attaches a trend line to the iteration burndown chart to predict the likely variance at iteration completion; applying the same idea to the release-level burndown chart is common exam practice. The answer is A.
Why the other options are wrong
- B. The schedule performance index measures schedule efficiency relative to planned value and is an earned value metric. This question is about forecasting whether the remaining MVP scope will be finished before the fourth iteration, and a burndown trend line is more direct, so B is not the best answer.
- C. The cost performance index measures cost efficiency, while the product owner is worried about on-time delivery, not how much has been spent.
- D. Qualitative risk analysis assesses the probability and impact of risks. It does not track delivery progress and cannot answer whether delivery will be on time.
Key takeaway To judge whether the target scope will be finished on time, look at the burndown trend line (the iteration burndown chart within an iteration, the release burndown chart at release level), not SPI or CPI.
Variation To forecast how many more iterations the whole release needs, use “remaining story points ÷ velocity” and round up; for example, with 42 points remaining and a velocity of 15, 42 ÷ 15 = 2.8, so 3 iterations are needed. CPI is relevant only when the question is whether cost is overrun.
Something wrong with this question?
Example 3: Information radiator: software or sticky notes
There is only a small space on the wall of an agile team's office for showing project status. The team is hesitating between using a software tool the company already holds a perpetual license for, to show progress, and putting sticky notes and index cards describing the current work on the wall. What should the team be advised to do?
Show answer and explanation
Correct answer: D
The wall space for showing project status is small, and the team is hesitating between a software tool the company already has a perpetual license for and sticky notes plus index cards.
The answer depends on the features of an information radiator. PMBOK 8 stresses that it leans toward “low tech and high touch”, is maintained by hand by the team, is posted where people can easily see it, and is easy to update and updated often. Index cards and sticky notes fit this: they move easily, are visible at a glance, and show real-time status, and they can be arranged flexibly even in a small space. A software tool has to be opened in a system before anyone can see it, so it is less timely and less visible than cards on a wall. The answer is D.
Why the other options are wrong
- A. That the license is already bought means there is no cost issue, but it is not a basis for the choice. A software tool must be opened before it can be seen, so it is less immediately visible than handwritten cards.
- B. What other teams do may not suit this team. It should choose the display that works best for itself.
- C. Printed reports updated weekly are not real-time status and lose the benefit of the team updating things as they work.
Key takeaway Information radiators favor low tech and high touch: updated by hand and visible at all times.
Variation If the team were spread across several cities with no shared wall, an electronic board could take its place, but it would still need to keep both features: always up to date and visible to everyone.
Something wrong with this question?
Common traps
Common trap
- When behind, do not work overtime and do not wait until delivery is near; negotiate early. Within an iteration, do not extend the iteration; without endangering the iteration goal, negotiate scope adjustment with the product owner. Negotiate an adjustment to release scope or date only when the release is behind.
- Ordering the product backlog is the product owner's responsibility (after hearing stakeholders). Scope adjustment within an iteration is negotiated by the developers and the product owner; the agile coach and the project manager do not cut it for them.
- To forecast whether an iteration will be completed, use the iteration burndown trend line; at release level use the release burndown trend line. Neither uses SPI or CPI.
- PMBOK 8 says an information radiator is usually a low-tech physical display maintained by hand rather than generated electronically, so there is no need to chase an electronic dashboard; what matters is that it is prominent and updated promptly, not technically advanced.
- When a stakeholder wants to see progress and an information radiator can meet their communication need, steer them to look at it first; when the communication management plan, governance requirements or their preference calls for a formal status report, still provide one.
Key takeaways
- Look at the trend, not a single day; when the line goes up, first find the cause: new requirements, underestimated stories or more defects.
- Forecasting within an iteration: use the daily completion rate of the last few days to work out the remaining days and compare it with the timebox.
- Release forecast: remaining story points ÷ velocity, rounded up.
- When behind, negotiate early: within an iteration do not extend the iteration and, without endangering the iteration goal, negotiate scope adjustment with the product owner; negotiate release scope or date only when the release is behind; no overtime.
- Information radiators are usually low tech and high touch and should be easy to update and updated frequently; displaying progress openly reduces dependence on lengthy status reports, with formal reports alongside where needed.
This chapter has 24 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.