What this chapter covers
Lean comes from manufacturing. Its core idea is to take the customer's point of view, find the activities that do not create value, and remove them. Many agile practices, including Kanban, visual controls and value stream mapping, carry the mark of lean. Lesson 1 shows how lean separates value from waste, gives the seven principles commonly used in software development and the seven wastes of manufacturing, and shows how to use a value stream map to find waiting and calculate process efficiency. Lesson 2 puts lean, Kanban, Scrum and Extreme Programming side by side so you can tell which is a philosophy, which is a method, which is a framework and which concerns engineering practices, and it uses a small worked example to show how pull exposes a bottleneck.
The exam points in this chapter are concentrated and each one is typical. Cancelling meetings that produce nothing is eliminating waste. A value stream map is the tool for finding wasted time. Kanban is lean-based visualization plus a WIP limit. "Make decisions as early as possible" is not a lean principle.
Lessons in this chapter
- Lesson 1: Lean thinking: the seven principles, the seven wastes and value stream mapping. The definition of waste; the seven principles (including "decide as late as possible"); the seven wastes matched to project situations; how to draw a value stream map; process efficiency = value-adding time ÷ total time.
- Lesson 2: How lean, Kanban and Scrum relate. Lean is a philosophy, Kanban is a method based on lean principles, and Scrum is a framework based on iterations; lean scheduling and pull; a small push-versus-pull example; how to choose.
How to study this chapter
First memorize one definition: waste is an activity that consumes resources and/or time without adding value. Then read the seven principles and the seven wastes twice each, paying attention to the counterintuitive item "decide as late as possible". You must be able to calculate from a value stream map: total processing time, total waiting time and process efficiency. Finally, put lean, Kanban, Scrum and Extreme Programming in one comparison table, and stop asking "lean or Kanban?", which compares things at different levels.
Chapter map
Lean (philosophy): value ↔ waste
- Seven principles: eliminate waste · amplify learning · decide as late as possible · deliver as fast as possible · empower the team · build quality in · see the whole
- Seven wastes: overproduction · waiting · transportation · over-processing · inventory · motion · defects
- Tools: value stream mapping (steps + time, to find waiting) · visual controls
- Method: Kanban (visualize · limit WIP · continuous delivery)
Scrum: an iteration-based framework; Extreme Programming: an agile method that emphasizes engineering practices
Lesson 1
Lean Thinking: the Seven Principles, the Seven Wastes and Value Stream Mapping
Lesson overview
Lean comes from manufacturing. Its core idea is to take the customer's point of view, find the activities that do not create value, and remove them. Kanban, visual controls and value stream mapping all carry the mark of lean. This lesson covers how lean separates value from waste, the seven principles commonly used in software development, the seven classic wastes of manufacturing, and how to use a value stream map to find waiting and calculate process efficiency. The next lesson covers how lean, Kanban and Scrum relate.
Value and waste
Lean sorts activities into two kinds: those that have value for the customer, and those that do not. The latter are waste. The PMBOK 8 glossary defines waste as activities that consume resources and/or time without adding value. The starting point is to do only what the customer is willing to pay for, and not to spend time on waiting, rework, documents no one reads and meetings that produce nothing. In its quality principle, PMBOK 8 also stresses that foundational to embedding target quality thresholds is continuous improvement and waste elimination. Continuous improvement allows teams to proactively identify and address areas for enhancement in both deliverables and workflows, while waste elimination streamlines processes, conserving resources and improving performance.
The seven lean principles
In software development, lean is often summarized as seven principles: eliminate waste, amplify learning, decide as late as possible, deliver as fast as possible, empower the team, build quality in, and see the whole. In plain language: remove what does not add value; learn through short cycles and feedback; do not lock in irreversible decisions too early when information is lacking; shorten the time from request to delivery; give the people doing the work the authority to decide how to do it; build quality into the process rather than inspecting for it afterward; and optimize the whole value stream rather than one local part.
Common trap
"Make decisions as early as possible" is not a lean principle. Lean stresses deciding once enough information is in hand and delaying irreversible decisions, but this is not procrastination or avoiding decisions. For a "which one is NOT correct" question, this is the one to catch.
The seven wastes
Lean manufacturing (the Toyota Production System) identified seven wastes: overproduction, waiting, transportation, over-processing, inventory, motion and defects. Carried over to software and projects, they can be matched like this:
| Waste | What it looks like in a project |
|---|---|
| Overproduction | Building features nobody wants |
| Waiting | Waiting for approvals, for a test environment, for others to deliver their results |
| Transportation | Requirements handed back and forth among several roles |
| Over-processing | Design beyond what is needed, documents no one reads |
| Inventory | Half-finished work that is written but not tested or released, a growing backlog |
| Motion | Frequent task switching, hunting for information |
| Defects | Rework, fixing errors |
The seven wastes are the common formulation in the lean field. On the exam you are more likely to be asked to recognize whether a situation is waste and which tool can reveal it.
Value stream mapping
PMBOK 8: value stream mapping is a display of the critical steps in a process and the time taken in each step to identify waste. It is a lean technique used to document, analyze, and improve the flow of information or materials required to produce a product or service for a customer. A value stream begins, ends, and hopefully continues with a customer. A value stream is the set of activities that takes place to add value for customers, from the initial request through realization of value by the customers.
How to draw one: start from the moment a request is raised and list each step it passes through, in actual order. Mark two times on each step: the processing time, when work is really being done, and the waiting time, the wait for the next step after this one is done.
Worked example. A request takes 15 days from being raised to going live: requirements clarification takes 1 day of processing and then 3 days waiting to be scheduled; development takes 3 days and then 4 days waiting for a test environment; testing takes 2 days and then 1 day waiting for approval; release takes 1 day.
- Total processing time is 1 + 3 + 2 + 1 = 7 days, total waiting time is 3 + 4 + 1 = 8 days, and the total is 15 days.
- Process efficiency = value-adding time ÷ total time. In this example we assume the processing time of every step adds value, so it is 7 ÷ 15 ≈ 46.7%. The waiting is longer than the processing.
- The improvement focus is not to have developers work overtime but to shorten "waiting to be scheduled" and "waiting for the test environment". Suppose each of those two drops to 1 day. Total waiting is then 1 + 1 + 1 = 3 days and the total is 7 + 3 = 10 days, so process efficiency is 7 ÷ 10 = 70%. Check: the saving is (3 − 1) + (4 − 1) = 5 days, and 15 − 5 = 10, which matches.
What stands out most on the map is often not the slowest step but the waiting between steps. If the team finds its actual velocity behind plan and wants to know which time could be saved by eliminating waste, it looks at the value stream map. If the map shows that a member spent 5 hours waiting for other members' deliverables, that wait produced nothing and is waste. The process should be improved, not the person judged as not trying hard enough. The PMBOK chapter on tailoring also recommends that when there is too much work in progress and/or waste, you use techniques like value stream mapping and kanban boards to visualize work, identify issues, and find solutions.
Worked examples
Example 1 Cancelling meetings that produce nothing: which principle
A team is using a lean approach to develop an online collaborative document tool. To improve efficiency, it cancels routine meetings that produce nothing, stops writing documents no one reads, and does only the work that is needed now. Which lean principle does this reflect?
Show answer and explanation
Correct answer: C
A team using a lean approach to develop an online collaborative document tool cancels routine meetings that produce nothing and unread documents, and does only the work needed now. The question asks which lean principle this reflects.
PMBOK 8 defines waste as activities that consume resources and/or time without adding value. Meetings that produce nothing and documents no one reads add no customer value, so they are waste. Removing them and doing only the necessary work is eliminating waste. There are two points of judgment here: the stem says nothing about being “faster” or about “quality”; it only says that activities that add no value are removed. The answer is C.
Why the other options are wrong
- A. Deliver as fast as possible stresses shortening the time from request to delivery. The stem does not mention delivery speed.
- B. See the whole stresses optimizing the whole value stream from a global rather than a local view. The stem is about removing activities that add no value.
- D. Build quality in stresses putting quality into the development process. It has nothing to do with cancelling meetings and documents.
Key takeaway Removing activities that add no value is lean's “eliminate waste”.
Variation If the stem said “work does not move to the next step if it fails review, so defects are stopped inside the process”, that corresponds to build quality in. If it said “shorten the cycle from request to going live”, that corresponds to deliver as fast as possible.
Something wrong with this question?
Example 2 Finding wasted time that can be saved in the process
The team compares actual velocity with planned velocity and finds the project is behind plan. The agile management professional wants to find out where in the process time could be saved by eliminating waste. What should be examined?
Show answer and explanation
Correct answer: B
The agile project's actual velocity is behind plan, and the agile management professional wants to find where in the process time could be saved by eliminating waste. The question asks what to look at.
A value stream map displays the critical steps in a process and the time taken in each step. Beyond processing time, it shows waiting, rework and other waste, and the steps it identifies are where to improve. To find where time can be saved, you need the time broken down by step, not the overall trend of progress. A progress chart only tells you that you are behind; the value stream map tells you which step the time is spent in. The answer is B.
Why the other options are wrong
- A. A product roadmap is a long-term plan for the product. It does not show where time goes in the process.
- C. A burnup chart shows work completed and scope. It can show that you are behind, but not which step the waste is in.
- D. A burndown chart shows remaining work over time. It too reflects only progress and does not analyze waste in the process.
Key takeaway To find waste time that can be eliminated in the process, use a value stream map.
Variation If the map shows 7 days of value-adding time against 15 days of total lead time, process efficiency is 7 ÷ 15 ≈ 46.7%; the other 8 days are non-value-adding time whose waiting and other waste should be investigated. If the stem asked only “how far behind are we”, a burndown or burnup chart containing a planned or ideal reference line would be enough.
Something wrong with this question?
Example 3 The value stream map shows a member waiting 5 hours
You have been appointed lead of an agile project at a software company. You analyze the team's performance with a value stream map, and the result shows that one team member spent 5 hours waiting for other members to deliver their results. What improvement advice should you give the team?
Show answer and explanation
Correct answer: D
The project lead analyzed team performance with a value stream map, and it shows that one member spent 5 hours waiting for other members to deliver their results. What improvement advice should the team get?
Time spent waiting creates no value. It is exactly the waste a value stream map is meant to find: it consumes time without adding value. The right attitude is to treat it as a process problem and act to reduce or eliminate it, so that the time goes into value-creating work. It is not to conclude that someone is not trying hard enough, and it is not to accept the wait as a matter of course. The answer is D.
Why the other options are wrong
- A. Limiting WIP is a way of controlling the amount of parallel work, and value stream analysis may also lead a team to adjust its WIP limits. But waiting itself is not a way of limiting WIP, and waste cannot be described as an effective practice.
- B. This statement only describes the situation and solves nothing. Waste can be reduced by improving the process.
- C. Delays cannot all be eliminated. The goal is to plan sensibly and reduce the steps that create waiting waste, not to allow none at all.
Key takeaway Waiting time on a value stream map is waste and should be reduced or eliminated.
Variation If instead the processing time of one step is itself too long, examine how that step is performed and its capability. If total waiting is 8 days and total processing is 7 days, focus on investigating and reducing waiting, prioritizing the longest avoidable waits shown on the map.
Something wrong with this question?
Common traps
Common trap
- A value stream map shows where the process has waste. A burndown chart and a burnup chart show progress, and earned value shows schedule and cost performance. Do not mix them up.
- A value stream map does not just add up working time; it is used to identify waiting, rework and other forms of waste.
- Waiting between activities cannot all be eliminated, but it should be reduced by improving the process.
- Lean advocates delaying irreversible decisions, not deciding early.
- Lean is a philosophy and a set of principles; the value stream map is one of its tools.
Key takeaways
- Waste: an activity that consumes resources and/or time without adding value. Lean means finding and eliminating it.
- The seven lean principles for software: eliminate waste, amplify learning, decide as late as possible, deliver as fast as possible, empower the team, build quality in, see the whole.
- The seven wastes: overproduction, waiting, transportation, over-processing, inventory, motion, defects.
- Value stream map: the process steps plus the time each takes, used to identify waiting and other waste.
- Process efficiency = value-adding time ÷ total time. In the worked example only, all processing time is assumed to be value-adding. Waiting time is the improvement focus.
Lesson 2
How Lean, Kanban and Scrum Relate
Lesson overview
Lean, Kanban, Scrum and Extreme Programming often appear together in a question stem, and candidates tend to treat them as things at the same level. This lesson separates them: which is a philosophy, which is a method, which is a framework, and which concerns engineering practices. It then uses a small worked example to show how "pull" makes a bottleneck visible instead of hiding it. ECO: Process domain, Task 3 (Help ensure value-based delivery). The previous lesson covered lean's principles and the value stream map; the next chapter covers Extreme Programming.
Philosophy, method and framework
Lean is a way of thinking and a set of principles: pursue value, eliminate waste, improve continuously. It does not prescribe which meetings to hold each day or how many columns to draw on a board; its tools include the value stream map and visual controls. Kanban is one specific method for putting lean principles into practice: visualize the workflow, limit work in progress, deliver continuously. The PMBOK 8 definition is clear: the Kanban method is a visual workflow management method to limit work in process (WIP) based on lean principles and focusing on continuous delivery without overburdening the team. Scrum is an iteration-based framework: fixed timeboxes, three accountabilities, three artifacts and five events. Extreme Programming particularly emphasizes engineering practices: test-driven development, pair programming, continuous integration and so on, though it also includes rhythm practices such as small releases and the planning game, and it is often combined with Scrum.
A common exam practice summarizes it from three viewpoints: seen from the product's point of view, agile is mostly lean thinking, pursuing return on investment and doing the highest-value work at the lowest cost; from the project's point of view, the typical representative is Scrum; from the technical point of view, the typical representative is Extreme Programming.
Compare
- Lean: a philosophy and principles, concerned with the value stream and waste; tools include the value stream map and visual controls.
- Kanban: a method based on lean principles; based on flow, limits WIP, delivers continuously, and does not require fixed iterations.
- Scrum: an iteration-based framework with fixed timeboxes, accountabilities such as the Product Owner, and events such as the Sprint Review.
- Extreme Programming: a collection of engineering practices, often used alongside the rhythm of Scrum.
Lean in PMBOK 8
PMBOK 8 uses lean in several places. Flow-based scheduling focuses on optimizing the flow of work through a system. One goal is to minimize time and resource waste and maximize the efficiency of processes and the throughput of deliverables, and it often draws on the Kanban method and the theory of constraints. Lean scheduling is based on the principles of lean project delivery and is designed to minimize waste and maximize value; it points to the importance of limiting queues by pulling work when there is capacity to place the work into the process. In lean environments, information radiators are known as visual controls. Figure 4-7 plots several agile approaches by breadth and depth of coverage. A method is a systematic way of doing something, typically involving a series of steps or procedures, and a tool kit is a collection of tools, techniques, and resources that can be used to support various methods or approaches.
How pull exposes a bottleneck
Worked example. Development completes 3 items per day and testing can test only 2 per day. Throughput is limited by testing, which is the bottleneck.
- Suppose development "pushes": it sends work on as soon as it is done, whether or not testing is busy. Development finishes 1 more item per day than testing (3 − 2). Over 5 days development completes 15 items and testing tests only 10, so at the end of day 5 there are 15 − 10 = 5 items piled up at testing (including the one being tested that day). That number grows by 1 every day and has no ceiling.
- Now suppose the test column is limited to 3 items and development "pulls". When the test column is full, development pauses starting new work and stops pushing items into the test column; the team turns to supporting testing (for this example, assume the support does not change testing's capacity of 2 items per day). WIP in the test column (including items being tested) is at most 3 and no longer grows.
- Comparison: looking only at WIP at the testing step, push gives 5 items and rising every day, while pull gives at most 3 and stays steady. Check: under both approaches the whole system can still deliver only 2 items per day, so throughput has not changed. The difference is that pushing piles half-finished work into inventory, lengthens waiting and finds defects later, while pull makes the bottleneck visible at a glance.
So when a column is full, the team does not put in new items for now. It concentrates its effort on finishing the work in testing, then pulls in the next item. Raising the limit, continuing to start new items, or removing the limit would only hide the bottleneck.
How to choose
When demand keeps arriving and you want continuous delivery without overloading the team, lean-based Kanban fits. When you want a usable increment produced on a fixed rhythm, with stakeholders regularly invited to inspect the results and give feedback so that later work can be adjusted, Scrum fits. In practice the two are often combined, for example by using a kanban board to manage tasks inside a Scrum Sprint. When a stem contains "visualize all the work, limit the work under way, deliver continuously, do not overload members" together, it points to Kanban based on lean principles.
Worked examples
Example 1 Which method best fits these lean features
A team maintains a logistics scheduling system. It wants to make all its work visible, limit the amount of work under way at the same time, deliver results continuously, and not overload its members. This approach is based on lean principles. Which of the following methods fits these features BEST?
Show answer and explanation
Correct answer: B
A team maintaining a logistics scheduling system wants to visualize all its work, limit the work under way at the same time, deliver continuously and not overload its members, and this approach is based on lean principles. Which method fits these features best?
PMBOK 8 defines the Kanban method as a visual workflow management method to limit work in process (WIP) based on lean principles and focusing on continuous delivery without overburdening the team. The four features in the stem (visualization, limited WIP, continuous delivery, no overloading of members) correspond to this definition one for one. The answer is B.
Why the other options are wrong
- A. Scrum sets its rhythm with fixed-length Sprints. Limiting work in progress is not its core.
- C. Extreme Programming is an agile method that particularly emphasizes engineering practices. Pair programming supports code quality, but it is not the WIP-limiting workflow method described in the stem.
- D. The waterfall method typically advances in phases; phase-gate reviews do not provide the stem's combination of lean-based workflow visualization, WIP limits, and continuous delivery.
Key takeaway Kanban is built on lean principles: visualize, limit WIP and deliver continuously. Scrum uses fixed-length Sprints.
Variation For “fixed two-week Sprints, with a Sprint Review and a Sprint Retrospective at the end of each Sprint”, the answer is Scrum. For “write the test first and then the code”, the answer is test-driven development in Extreme Programming.
Something wrong with this question?
Example 2 The test column is full: what next
A team manages its development process with a kanban board. The Test column has a WIP limit of 3 and already has 3 items in testing, and the Development column has just finished another item. The team wants to improve flow by addressing the bottleneck. What should it do NEXT?
Show answer and explanation
Correct answer: B
A team manages its development process with a kanban board. The Test column has a WIP limit of 3 and already has 3 items in testing, and Development has just finished another item. To improve flow by addressing the bottleneck, what is the right next step?
Kanban uses WIP limits to control the work under way so that bottlenecks become visible and the team concentrates on dealing with and easing them. A full Test column means the bottleneck is in testing, and nothing more can go in. The team should hold off on putting in new items, concentrate on finishing the work in testing, and pull in the next item once a space opens. The answer is B.
- The Test column limit is 3 and 3 items are in testing: 3 − 3 = 0 open slots.
- Development has just finished 1 item. It needs an open slot to enter testing, and there is none, so this item can only wait in the Development done area.
- Only when testing finishes 1 item does a slot open, and only then can the next item be pulled in. So the team should put its effort into finishing the work in testing.
- Check: if the item were forced in, the Test column would hold 4 items, over the limit of 3, which violates the WIP limit.
Why the other options are wrong
- A. Raising the limit only hides the bottleneck. More work in progress slows overall flow.
- C. If developers keep starting new items, work waiting for testing will keep piling up and the bottleneck gets worse.
- D. Removing the WIP limits throws away the means Kanban gives for exposing and eliminating bottlenecks.
Key takeaway When the WIP limit is reached, clear the bottleneck first. Do not keep putting work in.
Variation If the stem said the Test column had only 1 item, there would be 3 − 1 = 2 open slots, and the item Development finished should be pulled in. If the upstream pile-up continues, developers can go and help with testing (swarming).
Something wrong with this question?
Common traps
Common trap
- Lean is a philosophy, Kanban is a method and Scrum is a framework. They are not at the same level, so do not ask "lean or Kanban?".
- Kanban is based on lean principles but is not the same as lean. The value stream map and visual controls are lean tools.
- Scrum sets its rhythm with fixed-timebox Sprints; limiting work in progress is not its core.
- Extreme Programming particularly emphasizes engineering practices, though it also contains rhythm practices such as small releases and the planning game. Waterfall is not continuous delivery.
- When the bottleneck column is full, stop putting in new items. Do not raise or remove the limit.
Key takeaways
- Lean is a philosophy, Kanban is a method based on lean principles, Scrum is an iteration-based framework, and Extreme Programming particularly emphasizes engineering practices.
- Kanban: visualize, limit WIP, deliver continuously. Scrum: fixed timeboxes, three accountabilities and five events.
- Lean scheduling: bring work in only when there is capacity, and limit queues by pulling.
- When a column is full, do not put in new items for now. Clear the bottleneck first and do not raise the limit.
- The two can be combined: use a kanban board to manage tasks inside a Scrum Sprint.
This chapter has 7 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.