- Home
- PMP
- Study Guide
- Agile and Hybrid
- Scrum Roles
Agile and Hybrid
Scrum Roles
PMP · Agile and Hybrid · 5 lessons · about 1 h 2 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
A Scrum Team has three accountabilities (often called roles, a common exam term): the Product Owner, the Scrum Master and the Developers. (PMBOK 8 and many exam questions say “development team”. The current Scrum Guide says Developers, and there are no sub-teams or hierarchy within the team. This guide uses “Developers”.) The division of work can be remembered in one sentence: the Product Owner decides what to build, the Developers decide how to build it, and the Scrum Master helps the Scrum Team use Scrum effectively. This is a frequently tested chapter, and nearly every question tests the same thing: who should handle this problem, and what is the correct reaction for this role.
The chapter first covers the three roles one at a time: the Product Owner's ordering, acceptance, release and role as the front door to the outside; the Scrum Master's position and judgment as a servant leader; and the Developers' self-organization, cross-functional makeup and participative decision-making. It then covers two kinds of integrated scenarios: how to let the team try first when a problem appears, and how the Scrum Master removes impediments and shields the team from outside interference.
Lessons in this chapter
- Lesson 1: The Product Owner: decides what to build, what comes first, and whether to accept it. Accountable for product value and the Product Backlog; orders the backlog, confirms that business needs are met against the acceptance criteria (common exam practice; whether an Increment is done is judged by the Definition of Done), and leads the timing of releases. The Product Owner is the single person accountable for the Product Backlog and its order, and must be one person, although the Scrum Team can also work directly with stakeholders.
- Lesson 2: The Scrum Master: servant leader. Not a traditional command-and-control manager; serves the Product Owner, the Scrum Team and the organization; six kinds of everyday work; facilitates rather than rules.
- Lesson 3: The Developers: self-organizing, cross-functional and decision-making by participation. An ideal agile team size of 3 to 9 people (the current Scrum Guide says the whole Scrum Team is typically 10 or fewer), self-organizing (the Scrum Guide says self-managing), cross-functional, T-shaped people, and usually best kept stable and as dedicated as possible; estimating and decisions belong to the team.
- Lesson 4: Problem-solving in an agile environment: let the team try first. First work out whose problem it is, then collect data, analyze causes and act; the team first collaborates within its own accountabilities to solve the problem. When trade-offs on product value or scope are involved, adjust the Product Backlog with the Product Owner, and when organizational impediments are involved, the Scrum Master helps the right people remove them promptly.
- Lesson 5: Removing impediments and shielding the team from outside interference. Internal impediments versus external interference; typical scenarios such as a functional manager pulling members away or a supervisor chasing progress; when there are several impediments, handle first the ones that may stop the work or cause a serious violation (such as a compliance problem).
Chapter map
Scrum Team
- Product Owner: what to build · ordering · confirms whether business needs are met (common exam practice) · leads releases · main entry point for requirements and priorities (one person)
- Developers: how to build · estimating · how much to take in a Sprint (3–9 people · self-organizing · cross-functional · T-shaped)
- Scrum Master (servant leader): helps the team run Scrum smoothly
- Serves: Product Owner · Scrum Team · organization
- Day to day: clear impediments · coach · shield · foster collaboration · guard the process · drive change
- Judgment: offers opinions, does not rule; lets the team find its own way first
When a problem arises: whose problem is it? → data → cause → action; impediments: guide internal ones, negotiate external ones
Lesson 1
The Product Owner: Decides What to Build, What Comes First and Whether to Accept It
Lesson overview
A Scrum Team includes one Product Owner, one Scrum Master and a number of Developers. (The current Scrum Guide describes three accountabilities with no sub-teams or hierarchy inside the team. PMBOK 8 and the exam still often say “development team”. This guide uses “Developers”.) The division of work is clear: the Product Owner decides what to build, the Developers decide how to build it, and the Scrum Master helps the Scrum Team use Scrum effectively. Questions on Scrum roles almost all test the same thing: who should handle this problem. This lesson covers the Product Owner first. The next four lessons cover the Scrum Master, the Developers, problem handling, and removing impediments and shielding the team.
Who the Product Owner is
The Product Owner (PO) is the person accountable for the product. The PMBOK 8 glossary defines the product owner as “A person responsible for maximizing the value of the product and is accountable for the end product.” The Product Owner represents customers and the business and decides which features the product should have and which to build first. PMBOK 8 also notes that “the product owner should ensure that the development team is focused on delivering valuable features by maintaining and prioritizing the product backlog.” PMBOK 8 treats the sponsor, the customer and the product owner together, as those who communicate the organization's vision, objectives and expectations. In an adaptive team, this duty of “speaking for the business” is usually carried by the Product Owner (common exam practice).
The Product Owner is accountable for the content, the order and the transparency of the Product Backlog: what the vision and goals are, which items to build, who goes first, and whether everyone can see and understand the backlog. The Product Owner can write items personally or ask the Developers to help, but the final accountability is the Product Owner's. Turning the product direction and vision into a clearly ordered backlog is the core of the job.
The Product Owner's four core responsibilities
1. Ordering. The basis for ordering is value: the order aims to maximize value, taking cost, risk, dependencies and other constraints into account (in PMBOK 8: based on value, dependencies and technical or operational risk). Other things being equal, the more valuable and cheaper an item, the nearer the front it usually goes. The loudest voice does not count. Marketing, customer service and finance all say their needs are the most urgent: what then? The Product Owner orders them in one sequence and makes it public, and everyone works to that order.
2. Confirming that business needs are met. Under the Scrum Guide, work that meets the Definition of Done becomes an Increment. The Sprint Review is a working session where the Scrum Team and stakeholders inspect the outcome together. It is not a quality gate where the Product Owner approves the Increment. An item that does not meet the Definition of Done cannot be counted or shown as an Increment and goes back to the Product Backlog. Common exam practice: when the stem asks “who decides whether a result is accepted as meeting business needs”, choose the Product Owner (who confirms against the acceptance criteria). The QA engineer, the Scrum Master and the sponsor are not the answer.
3. Leading the timing and content of releases. Being technically finished does not mean the product must be released immediately. Within the authority granted, the Product Owner usually leads the timing and content of a release and can wait for a suitable market moment, coordinating with governance, operations or release management stakeholders. (Release authority also depends on the organization's arrangements, and the Scrum Guide also says an Increment can be delivered before the end of the Sprint, so the review is not a release gate.)
4. The single entry point for product decisions. Decisions about the product goal and about the items and order of the backlog are the Product Owner's to make. New ideas from stakeholders, concerns about releases and views on trade-offs usually enter the Product Backlog through the Product Owner. The Developers can work directly with stakeholders to get feedback, as agreed within the team (the whole Scrum Team is accountable for stakeholder collaboration), and keep the Product Owner informed. Forcing all communication through the Product Owner creates an information bottleneck. The Daily Scrum focuses on the Developers' Sprint plan and is not a routine stakeholder meeting. Common exam practice: when the team has agreed that the Product Owner is the single point of contact, a Developer who runs into a problem goes to the Product Owner first, and does not arrange a meeting with stakeholders, send an email, or bring outsiders into the Daily Scrum. When the customer and the Product Owner disagree about an acceptance conclusion, first clarify against the Definition of Done, the acceptance criteria and the established authority. The Product Owner manages and orders the Product Backlog.
It must be one person
The Product Owner is one person, not a committee. A committee's views can be reflected in the backlog, but to change an item's priority, you must first persuade this one person. Everyone else in the organization should respect the Product Owner's decisions and must not give the Developers a different set of requirements.
The Product Owner belongs to the Scrum Team and is not a liaison sent by the customer. A Product Owner who merely relays the customer's words is of limited value. An effective Product Owner thinks about the business actively and also explains the Developers' difficulties to the business side. When the Product Owner is not involved enough, first help the Product Owner and the team communicate directly, rather than confronting the Product Owner, sending a notice or rushing to replace the person. When you need someone who knows the business domain and can express requirements from the user's standpoint, a business analyst is a suitable helper, but the final ordering is still decided by the Product Owner.
Boundaries with other roles
| Matter | Who owns it |
|---|---|
| What to build, what comes first, the product vision | The Product Owner |
| How to build, how much to take in a Sprint, estimating | The Developers |
| Whether Scrum is understood and followed, impediments | The Scrum Master |
| An item is not understood and needs clarifying | Go to the Product Owner |
| Several parties compete over priority | The Product Owner orders in one sequence, and the Scrum Master helps convene |
The Scrum Master can insist that “there must be an order and it must be public”, and can help the Product Owner learn to manage the backlog, but cannot do the ordering for the Product Owner. A project manager may help with administrative matters (such as convening meetings), but the content and order of the backlog belong only to the Product Owner.
Where does the in-class quiz feature go?
The Product Owner of an online course platform hears from marketing that a competitor has launched an in-class quiz feature. The Product Owner does not ask the team to add it to the current Sprint that day. Instead, the Product Owner writes it up as an item and places it in the Product Backlog, evaluates its value and cost and ranks it third, to be selected at the next Sprint Planning. Later the marketing director asks about progress, and a Developer answers “Please ask the Product Owner”, who explains the ordering rationale to the director.
Worked examples
Example 1: A stakeholder response is needed: who should the Developers go to?
A logistics company's warehouse dispatch system is being developed with Scrum. During the Sprint, the Developers find an inventory rule that affects the warehouse supervisor, a key stakeholder, and they must get the supervisor's opinion soon or the Sprint will be affected. By team agreement, communication between the Developers and stakeholders goes through the Product Owner. The Product Owner normally meets this supervisor once a week, but this week's meeting has been postponed because of a schedule conflict. What should the Developers do?
Show answer and explanation
Correct answer: C
A warehouse dispatch system is being developed with Scrum and is in the middle of a Sprint. The Developers need a key stakeholder's (the warehouse supervisor's) opinion soon. By team agreement, communication goes through the Product Owner, and the Product Owner's regular meeting with the supervisor was postponed this week. What should the Developers do?
Division of roles is the core of this question. Scrum itself does not forbid the Developers from collaborating directly with stakeholders, but the Product Owner is responsible for understanding stakeholders' needs and conveying them to the team. The stem is explicit that there is an agreement that “communication goes through the Product Owner”, and the postponed regular meeting is only a distraction. It does not mean the agreement can be bypassed. The Developers should go to the Product Owner first, ask the Product Owner to arrange a separate consultation with the supervisor as soon as possible, and bring the result back to the team. The answer is C.
Why the other options are wrong
- A. Contacting the supervisor directly violates the communication channel the team agreed and leaves the Product Owner out. The supervisor's view may conflict with the order of the Product Backlog or with other stakeholders' needs, and without knowing it the Product Owner cannot coordinate.
- B. An email also bypasses the Product Owner, and the back-and-forth of emails is slower, which does not meet the need to get it “soon” and leaves a risk of confused communication channels.
- D. The Daily Scrum is a 15-minute meeting where the Developers inspect their own progress and coordinate the day's work. It is not an occasion for consulting stakeholders, and inviting an outsider would disrupt its rhythm.
Key takeaway When the team has agreed that the Product Owner is the single contact for stakeholders, Developers go to the Product Owner first.
Variation If the stem said a stakeholder called a Developer directly and demanded a feature, it would likewise be passed to the Product Owner. If it said the Sprint Review, stakeholders could give the team feedback directly at the review.
Something wrong with this question?
Example 2: After the review, who is ultimately accountable for the backlog revisions?
A team building smart door-access software has just finished its fourth Sprint Review. The Scrum Team and stakeholders inspected the Sprint's outcome together and discussed what to do next, and the feedback now needs to be reflected in revisions and reordering of the Product Backlog. Who is ultimately accountable for ensuring that this work is done?
Show answer and explanation
Correct answer: A
A Scrum project's Sprint Review has just ended. The Scrum Team and stakeholders inspected the outcome together and discussed what to do next. The Product Backlog now needs to be revised and reordered in light of the feedback; who is ultimately accountable for ensuring that this work is done?
The Sprint Review is a collaborative working session in which the Scrum Team and stakeholders inspect the outcome, discuss environmental changes, and determine future adaptations; the Product Backlog may be adjusted as a result. The Product Owner is ultimately accountable for effective Product Backlog management, including ensuring that its items are clear, transparent, and ordered, so the Product Owner must ensure that review feedback is reflected in appropriate revisions. Whether work becomes part of an Increment is judged by the Definition of Done, not by acceptance at the Sprint Review. The answer is A.
Why the other options are wrong
- B. The Scrum Master establishes Scrum, supports team effectiveness, and facilitates stakeholder collaboration, but is not ultimately accountable for effective Product Backlog management.
- C. The sponsor provides funding and senior support but does not hold Scrum accountability for revising and ordering the Product Backlog.
- D. A QA engineer may work with the other Developers to ensure the Increment meets the Definition of Done, but is not ultimately accountable for effective Product Backlog management.
Key takeaway Review feedback is developed collaboratively; the Product Owner is ultimately accountable for the resulting Product Backlog revisions and ordering.
Variation If the stem asked “whether the Increment is released”, release authority depends on the organization's arrangements, and the Product Owner usually leads the timing and content of a release within the authority granted. If it asked “how many items the team expects to select this Sprint”, the Developers forecast that from their capacity, and what they commit to is the Sprint Goal.
Something wrong with this question?
Common traps
Common trap
- The Product Owner does not direct the Developers on how to implement the work and does not manage task-level assignments.
- During development, the Product Owner still has a say on priorities. The role does not end once the requirements have been handed over.
- The project manager, the Scrum Master and the sponsor cannot order the Product Backlog in place of the Product Owner. As to whether a result meets business needs, common exam practice is to choose the Product Owner, confirming against the acceptance criteria, but formal acceptance still follows the governance arrangement and the authority relationships given in the stem.
- Only the Product Owner decides whether an item goes into the list and where it ranks. “Anyone can raise a requirement” does not mean “anyone can order it”.
- When stakeholders demand a trade-off or ask about the feature schedule, direct them to the Product Owner.
Key point
- The Product Owner decides what to build and what comes first, is one person, and is a member of the Scrum Team.
- The content, order and transparency of the backlog belong to the Product Owner, who is also mainly responsible for confirming business needs against the acceptance criteria and for leading the timing of releases.
- The Product Owner is the main entry point for requirements, priorities and business trade-offs: stakeholders' new requirements enter the backlog through the Product Owner. The team can still work directly with stakeholders at the Sprint Review and elsewhere, and the Scrum Master can help facilitate communication.
Key takeaways
- The Product Owner is the person responsible for maximizing the value of the product and accountable for the end product, and belongs to the Scrum Team.
- The Product Owner is accountable for the content, order and transparency of the Product Backlog; ordering is by value, with risk, cost and dependencies also considered.
- The Product Owner confirms whether results meet business needs against the acceptance criteria (common exam practice) and, within the authority granted, leads the timing and content of releases. Whether an Increment is done is judged by the Definition of Done.
- The Product Owner is the single person accountable for product decisions and the backlog. It must be one person, not a committee. The Developers can also work directly with stakeholders as agreed.
- When an item is unclear, go to the Product Owner. When several parties compete over priority, the Product Owner orders in one sequence and makes it public.
Lesson 2
The Scrum Master: Servant Leader
Lesson overview
The second role is the Scrum Master. Many candidates think of it as “the project manager of agile”. This is the most common misconception and the trap scenario questions love to set: options such as “assign tasks”, “require reports” and “decide the solution” are mostly wrong. This lesson covers the Scrum Master's position (servant leader), the three parties it serves, the six kinds of everyday work, and the judgment of “facilitate, do not rule”. The next lesson covers the Developers.
Not a manager, but a servant leader
The Scrum Master is accountable for making sure Scrum is understood and carried out. The Scrum Master is a servant leader, usually fulfilling the role through coaching and by facilitating team collaboration. (Agile coach and team facilitator are related roles, but neither is a formal synonym for Scrum Master.) PMBOK 8 defines servant leadership as “the practice of leading the team by focusing on understanding and addressing the needs and development of team members in order to enable the highest possible team performance.” In its discussion of leadership, PMBOK 8 also stresses that leaders “should be open to feedback and should work for the team, supporting their needs and removing barriers when possible”, and that these values form the basis for the concept of servant leadership.
So the Scrum Master does not assign tasks, collect status reports, make decisions for the team or carry out individual performance reviews. The focus is on the team's overall performance. When a team has no project manager and only an agile coach, do not think that “nobody is in charge”. It is precisely because the team is self-organizing that the coach moves from “managing” to “serving”.
The three parties the Scrum Master serves
The Scrum Master serves three parties at once:
- Serving the Product Owner: helping the Product Owner find effective ways to manage the Product Backlog, understand how to order it, and communicate the vision and goals clearly to the team.
- Serving the Scrum Team (including the Product Owner and the Developers): coaching team members in self-management and cross-functional collaboration, helping clear the impediments in the way, and giving guidance when the team is not familiar with Scrum.
- Serving the organization: helping the organization and its stakeholders understand and adopt Scrum, and driving changes that raise team productivity.
The third is often overlooked. When a company asks an experienced Scrum Master to guide another team that is still feeling its way, the Scrum Master is “serving the organization”. The right move is to assess the team's maturity together with that team's Scrum Master and Product Owner and then coach them, rather than pushing the matter to the project management office, first asking whether to be reassigned, or first analyzing the “reasons for failure” and reporting them.
Six kinds of everyday work
Put into daily practice, the responsibilities come down to about six kinds:
- Removing impediments: another department's cumbersome process, an unstable environment, permissions that are slow to be approved.
- Coaching: sparking the team's creativity and coaching self-organization.
- Shielding: keeping unwarranted interference away from the team.
- Facilitating collaboration inside and outside the team: arranging communication and making introductions.
- Guarding the Scrum process: for example, reminding the team and calling a halt when the Daily Scrum runs past 15 minutes.
- Driving change: pushing for adjustments when the existing process or culture gets in the way of agile.
The Scrum Master is familiar with estimating, splitting work and how the various meetings are run, but does not step in to do them for the team. The goal is for the team to run normally even when the Scrum Master is not there. When everyone lacks agile knowledge, the first thing a coach should do is get everyone trained, not train only the team or only the project manager.
Facilitate, do not rule
Where servant leadership takes the most judgment is when the Scrum Master “sees more clearly”.
Suppose the team has built a service architecture with a flaw that may keep it from scaling later. The coach has already raised the point with questions, but the team did not notice. What next? Do not keep circling with more questions, do not decide for the team to switch to another design, and above all do not say nothing and wait for the team to hit the wall later. The right move is to state your view plainly for the team to consider, while the team decides on the solution. In short: the coach can voice an opinion, but the decision stays with the team.
What if the team has come up with a solution and you think there is a quicker one? Do not feed the answer. Guide the team to find the better way itself, for example by asking “Have you tried…?” or “What does this approach cost?”. When conflict arises inside the team, first leave it to the team to resolve. The coach is a facilitator, not a judge.
The test-environment account was not set up
The team's test-environment accounts have still not been set up and half a day has been lost. The Scrum Master does not tell the team to go and plead with another department. Instead, the Scrum Master goes personally to the head of IT to sort it out, and the accounts are opened that same day, so the team goes back to focusing on development. This is “removing impediments”. In the same week, at the Sprint Retrospective, the team discusses how to shorten the wait for code review. The Scrum Master thinks there is a faster way but does not give the answer. Instead, the Scrum Master asks “How do other teams handle review queues?”, and the team comes up with pair review itself. This is “coaching”.
Worked examples
Example 1: After the reminders did not work, what should the coach do?
On an online food-ordering platform project, the agile coach finds that the service architecture the team built has a flaw and may not work when new features are added later. The coach had earlier raised this by asking questions, but the team did not realize the problem. What should the agile coach do next?
Show answer and explanation
Correct answer: B
On an online food-ordering platform project, the agile coach finds that the team's service architecture has a flaw and may fail when features are added later. The coach had raised this earlier by asking questions, but the team did not realize it. The question asks what the coach should do next.
First settle the role: an agile coach is a servant leader who neither makes technical decisions for the team nor watches a problem happen. If asking questions did not work, the coach should state their own view plainly for the team to consider, so the team has full information. What solution to adopt is still decided by the self-organizing team. The answer is B.
Why the other options are wrong
- A. The coach has already asked, and the team still did not see it. Continuing to question only delays matters and makes the team feel interrogated. Failing to speak up when you should is also a failure of duty.
- C. Deciding that the architecture is wrong and requiring the team to switch to another approach is command and control, and it infringes on the team's right to self-organize.
- D. Stopping the reminders and waiting for the team to meet problems later means keeping silent about a known risk and making the team pay a greater price. The coach has not fulfilled the coaching duty.
Key takeaway The coach can voice an opinion, but the decision stays with the team.
Variation If the stem said the team, having taken the coach's view into account, still wanted to try another architecture, the coach should respect the team's decision and check the results in a Sprint Retrospective.
Something wrong with this question?
Example 2: Invited to coach another team
The company is moving from waterfall management to agile, using Scrum. You are an experienced Scrum Master whose important project has a very high level of customer satisfaction. The company now asks you to coach another team that is struggling to implement Scrum. What should you do?
Show answer and explanation
Correct answer: D
The company is moving from waterfall to agile and has chosen Scrum. You are an experienced Scrum Master whose important project has high customer satisfaction, and you are asked to coach another team that is feeling its way with Scrum. What should you do?
The parties a Scrum Master serves include the organization, and one of the Scrum Master's duties is leading and coaching the organization in adopting Scrum. Since you have been asked to coach, the most appropriate move is to assess the team's current Scrum maturity together with that team's Scrum Master and Product Owner, and then give targeted guidance. The answer is D.
Why the other options are wrong
- A. You were asked to coach, and handing it to the project management office for training or assigning someone else is passing the buck, not giving help directly.
- B. Asking first whether you will be moved avoids the coaching task and does nothing for the other team's problem.
- C. The stem does not say that team has failed, so “analyzing the reasons for failure” has no basis, and reporting to the project management office is not coaching-style support either.
Key takeaway Serving the organization means assessing and coaching together with the other team's roles.
Variation If the stem said everyone on your team lacked agile knowledge, the first thing to do would be to get everyone trained, not only some of them.
Something wrong with this question?
Common traps
Common trap
- The Scrum Master is not a command-and-control manager (the Scrum Master is a servant leader, and the Scrum Guide calls the Scrum Master a true leader): the team does not report to the Scrum Master, and the Scrum Master does not carry out individual performance reviews.
- The Scrum Master does not have to be full time, and one experienced person can serve several teams.
- One person generally should not be both Scrum Master and Product Owner: one acts like a coach and the other like a decision-maker, and the roles easily conflict. (Common exam practice is to treat them as “cannot be combined”, although the Scrum Guide does not explicitly forbid it.)
- The coach can voice an opinion, but the decision stays with the team. Conflicts go first to the team to resolve, and the coach is a facilitator, not a judge.
- The Scrum Master does not write code or do estimating in place of the Developers. If the Scrum Master also takes on Developer duties (actively working on Sprint Backlog items), the Scrum Master may take part in development and in the team's estimating.
Key takeaways
- The Scrum Master is a servant leader (usually working by coaching and facilitating, although agile coach is not a formal synonym) and makes sure Scrum is understood and carried out.
- Three parties served: the Product Owner, the Scrum Team and the organization.
- Six kinds of everyday work: removing impediments, coaching, shielding, facilitating collaboration, guarding the Scrum process and driving change.
- Facilitate without ruling: voice an opinion and leave the decision to the team; team conflicts go to the team first.
- Does not assign tasks, collect status reports or conduct individual reviews. Combining the role with Product Owner is generally not recommended (common exam practice treats the roles as not combinable, but the Scrum Guide does not explicitly forbid it).
Lesson 3
The Developers: Self-Organizing, Cross-Functional and Decision-Making by Participation
Lesson overview
The Developers are a frequently tested topic among the Scrum roles. The questions look varied: what to do when the team is too large, what to do when there is a disagreement over a technical approach, what to do when a new member joins, whether people can be shared part time, and so on. Underneath there is only one logic: the Developers are a self-organizing, cross-functional whole, the decision on “how to build” is in the team's hands, and the role of managers and coaches is to facilitate, not to do it for the team. This lesson first covers the characteristics, then how decisions are made, and finally a few typical scenarios. The next lesson covers the order of handling when problems arise.
Who the Developers are
Every Sprint, the whole Scrum Team is accountable for creating a valuable, usable, “Done” Increment; one Sprint can form several Increments. PMBOK 8 gives this definition: “A timeboxed interval within a project during which a usable and potentially releasable increment of a product is created.” Within the Scrum Team, the Developers are accountable for creating the Increment and making sure it meets the Definition of Done. The Developers are the people who commit to creating the Increment each Sprint, and anyone in the Scrum Team who does that work is acting as a Developer. The organization forms and empowers this team to plan and manage its own work. The current Scrum Guide calls these people “Developers”, while PMBOK 8 and many exam questions say “development team”. This guide uses “Developers”. Both terms refer to the same kind of development accountability, and the team has no sub-teams within it.
Five basic characteristics
- A small team. The Agile Practice Guide suggests an ideal agile team size of 3 to 9 people. (The current Scrum Guide says the whole Scrum Team is typically 10 or fewer, and a team that is too large can be reorganized into several Scrum Teams that share the same Product Goal, Product Backlog and Product Owner.) With too many people, communication costs rise and the Daily Scrum does not deliver what it should. This size is often described as “two pizzas can feed the team”. When the headcount is clearly too high, say 14 after additions, consider reorganizing into several smaller teams rather than squeezing everyone into one meeting room.
- Self-organizing. Nobody tells the team how to turn backlog items into working functionality, not even the Scrum Master. The team makes its own task plan, and members may pick up work on their own initiative or have it allocated by negotiation as the team agrees. Self-organizing means the team manages its own work. It does not mean the team is formed by the members choosing one another.
- Cross-functional. The team as a whole has all the skills needed to create the Increment. There is no separate test or business-analysis sub-team, titles do not matter, and everyone is a developer. The value is end-to-end delivery, with less waiting on outside groups.
- T-shaped people. Breadth across the top of the T lets members help each other, and depth down the stem gives each person a specialty. When testing becomes a bottleneck, developers can test together. Having developers learn automated testing directly reduces bottlenecks and lowers dependence on individuals.
- As dedicated and stable as possible. The losses from task switching are large: working on two projects at once costs about 20% of efficiency, and three projects about 40%. Members should not be swapped in the middle of a Sprint, and adding people is done between Sprints. An agile team should keep its core members stable and dedicated as far as possible, to reduce the task switching that part-time sharing causes. When resources are constrained, scarce specialists or supporting roles can still be part time or shared across teams (PMBOK 8: the working arrangement can be full time or part time), but their available time should be made clear and the dependencies managed.
Co-location is encouraged but not mandatory. Distributed teams can also work in an agile way, and the key is to make good use of high-bandwidth communication such as video meetings. So “whether everyone is in the same building” is not the criterion for an agile team. Self-organization, cross-functional skills and T-shaped people are.
Estimating and decisions: who has the final say
Estimates are made by the people who do the work. The Product Owner can help the team weigh trade-offs, but the final number is decided by the Developers. The Developers plan the Sprint in collaboration with the Product Owner and forecast how many items they can select based on their capacity (what is committed to is the Sprint Goal, not a fixed number of items). PMBOK 8 notes that agile teams, through self-governance, make decisions on their own within well-defined boundaries.
Disagreements within the team are resolved through discussion and participative decision-making: each side puts its reasons on the table, the different views are discussed fully, and a decision is then reached by the decision method the team has agreed. (You can aim for consensus, but you do not have to require everyone to agree.) It is not settled by a manager's ruling, by simply adopting what management recommends or by copying another team. If the team charter sets a decision rule (for example, a proposal passes with more than 80% in favor) and a decision has been made according to that rule, leaders should respect it, may note the objections, and should not overturn it. A change in the team's way of working is decided by the team collectively and does not depend on the seniority of whoever proposed it. A suggestion from a tester who joined two months ago also gets a serious evaluation.
“Empowerment” means returning to the team the decisions on “how the tasks are divided and how the work is done”. What is delegated to a self-managing team is mainly the way of working and the delivery process (the priorities of the Product Backlog remain the Product Owner's accountability). Within clear boundaries and safeguards, the team decides its workflow, the order of tasks and work arrangements, and how to solve problems. Governance responsibilities and decision authority are defined by the organization's governance model and by agreed processes, norms and team agreements, and may be shared among the sponsor, the governance body, the project manager and the team. The purpose of empowerment is to let the team adapt to change faster and create more value.
Three typical scenarios
A new member joins mid-way. After the Scrum Master has shown the new member around the workplace and introduced the team, the team members brief the new member on the project and its progress, and the new member picks up tasks by choice. The Scrum Master does not assign them.
Whether to change the team's tool. An experienced member proposes switching to a requirements management tool used in a previous job. First have the team evaluate it together and gather everyone's feedback, and only then talk about training or approval. The project manager does not decide at once, and does not simply reject it.
A functional manager still assigns tasks to members. The project manager should help the functional manager understand how a self-organizing team works and return the authority to assign tasks to the team. How tasks are allocated is decided inside the team. Members can pick up work on their own initiative or have it allocated by negotiation as the team agrees, and outside managers do not assign tasks for them.
The interface is not done: who coordinates?
Halfway through the Sprint, Alex finds that a task depends on an interface Priya has not finished. Alex does not go to the Scrum Master for reassignment, and does not simply wait. Alex goes straight to Priya to talk it over: either adjust the order of work, or build the interface together. This is the normal state of a self-organizing team: members help each other, and how they divide the work and help each other is for the team to agree. The Scrum Master helps remove internal and external impediments and foster collaboration when needed, but does not assign tasks or make technical decisions for the team.
Worked examples
Example 1: The team is too large and a split has been proposed: what next?
After a Daily Scrum, a member complains that the team is too large and the meeting does not deliver what it should. Later, at the Sprint Retrospective, the team formally proposes splitting into several smaller teams. What should the agile management professional do?
Show answer and explanation
Correct answer: D
After a Daily Scrum, a member complains that the team is too large and the meeting is not effective. At the Sprint Retrospective, the team formally proposes splitting into several smaller teams. The question asks for the right response of the agile management professional.
An agile team is self-organizing, and nobody tells the team how to organize and manage its own work. The team has put forward a reorganization proposal through the Sprint Retrospective, which shows it has discussed and come up with a plan. The most appropriate step is to support and allow the team to decide for itself whether to reorganize and to carry it out itself. The answer is D.
Why the other options are wrong
- A. The problem is that the team is too large, not that members misunderstand the value of the meeting, so stressing the value does nothing about the size problem.
- B. A self-organizing team can handle this kind of problem itself, so there is no need to escalate it, let alone ask the sponsor to rule. Escalating weakens the team's decision-making authority.
- C. “Directly cutting headcount and having only some members attend” decides for the team, and with only some members attending, the whole team does not benefit. It is also not the “split” the team wanted.
Key takeaway When the team finds and raises a problem itself, let the team decide how to solve it.
Variation If the stem were changed to “the team has grown to 14 people and the Scrum Master finds the meeting room cannot hold them”, the answer would still be to have the team take part in reorganizing into several smaller, cohesive Scrum Teams, usually no more than 10 people each, focused on the same product and sharing the Product Backlog and Product Owner.
Something wrong with this question?
Example 2: A disagreement over the technical framework: how does the team choose?
An agile team is building a mobile payment page, and the members disagree sharply and cannot settle which front-end framework to use. What should the team do?
Show answer and explanation
Correct answer: C
An agile team building a mobile payment page is split on which front-end framework to use and cannot settle it. What should the team do?
A technical approach is a matter of “how to build”, and the development team decides it itself. When there is a disagreement, each side should put its reasons on the table and discuss them fully, and then the team should reach a decision using its previously agreed decision method. This preserves participative decision-making without treating unanimous agreement as the only valid method. The answer is C.
Why the other options are wrong
- A. Directly adopting the framework management recommends lets outside views stand in for the team's decision, without considering this project's characteristics or the members' ideas. Management can offer advice for reference, but the decision belongs to the development team.
- B. Matching other teams is only a convenience and may not suit this project, and it does not resolve the disagreement among members.
- D. Using “the most material” as the sole criterion lets a single factor conclude for the team, without listening to each member's considerations.
Key takeaway A technical disagreement is settled by discussion within the team, reaching a decision the team can accept, not by copying management or others. In discussion, each side presents facts and reasons, and in the end the team decides in the way it has agreed, with the leader not ruling for it.
Variation If the team charter set a decision rule and the vote passed under that rule, the leader should respect the result and may note objections but not overturn it.
Something wrong with this question?
Common traps
Common trap
- On an agile team, “the project manager assigns tasks to members” is basically wrong. How tasks are divided is decided by the team itself (members can pick up work or have it allocated by negotiation).
- Self-organizing is not “no rules”, and it is not “members choose one another”. It means the team manages its own work.
- A technical disagreement is not decided by who is more senior or who has more study material, nor by copying management or another team. It is decided after discussion by the method the team has agreed on (aim for consensus, but not everyone needs to agree).
- The Developers have no sub-teams and titles do not matter. Cross-functional does not mean everyone is expert at everything. It means T-shaped: one deep specialty plus many skills.
- Frequently adding and removing members damages team stability. Part-time sharing usually adds task switching and dependencies and should be kept to a minimum, but it can be used when resources are constrained, with available time made clear.
Key point
- The Developers are commonly described as 3 to 9 people (the ideal agile team size; the current Scrum Guide says the whole Scrum Team is typically 10 or fewer), self-organizing (the Scrum Guide says self-managing), cross-functional and T-shaped, with no sub-teams.
- Estimating, breaking down tasks, picking up tasks and deciding how much to take in a Sprint are all decided by the team.
- Internal disagreements: participative decision-making, not a manager's ruling.
Key takeaways
- The whole Scrum Team is accountable for each Sprint's Increment. Within it the Developers are the people who commit to creating the Increment, and anyone in the Scrum Team who does that work is acting as a Developer.
- Five characteristics: small team (3–9 people), self-organizing, cross-functional, T-shaped people, and core members kept as stable and dedicated as possible.
- Estimates are made by the people who do the work, and how much to take in a Sprint is decided by the team.
- Disagreements are resolved through discussion and participative decision-making, and a decision made under the team's agreed rule should be respected.
- Empowerment returns to the team the decisions on how tasks are divided and how the work is done. (The order of the Product Backlog remains the Product Owner's. The Sprint Goal is set collaboratively by the Scrum Team, and the Developers select the items for this Sprint and decide the delivery plan.) Managers and coaches facilitate and do not do it for the team.
Lesson 4
Problem-Solving in an Agile Environment: Let the Team Try First
Lesson overview
The first three lessons covered what each of the three roles owns. This lesson covers what to do when a problem arises. These questions are also common: the team's velocity drops, a member is absent, the team does not finish its planned Sprint work, the schedule slips, there are too few people, teams depend on each other, and so on. The scenarios differ, but the answer follows one steady main line: first decide whose problem it is, then let the team collect data, analyze causes and find solutions itself, with the leader and coach guiding and supporting, and escalate only what the team cannot solve. Once you see this main line, you can rank most options at a glance.
Step 1: Work out whose problem it is
When a problem arises, first judge which role's area it belongs to:
| Problem | Who handles it |
|---|---|
| The team's computers keep freezing, the environment is unstable | It is an impediment: the team handles what it can handle itself first, and the Scrum Master helps remove impediments the team finds hard to solve |
| A feature already built is no longer needed | The Product Owner: it concerns requirements and features |
| A technical problem is found | The Developers |
| At the end of the Sprint, whether the Increment is done | Judged by the Definition of Done (the Product Owner is accountable for maximizing product value and for managing and ordering the Product Backlog) |
| Product results, environment changes and stakeholder feedback | The Sprint Review inspects them and decides on later adjustments (the Product Backlog can be adjusted) |
| The way of working, process problems and lessons learned | The Sprint Retrospective, attended by the whole Scrum Team |
| A technical idea conflicts with the project goal | The Developers and the Product Owner work together directly to find a way that satisfies both |
Step 2: Collect data, analyze causes, take action
For problems such as a falling velocity, a member who cannot finish planned Sprint work, or a slipping schedule, the common exam approach is: collect data first, then analyze the cause, and only then take action. (This is common exam practice. When you need to contain something or remove an impediment immediately, do that first.) Until the cause is clear, do not rush to add people, add money, change scope or replace people. For example, if the team's velocity has dropped steadily over the last few Sprints, the cause may be a new framework the team does not know. First look for causes at the Sprint Retrospective and map the skill gaps, then decide between training and adjustment, rather than first adding budget or swapping members. Likewise, if velocity has fallen for several Sprints in a row and the data shows the cause is concentrated in one member, first talk with that person, find the root cause, and then discuss countermeasures.
When a member cannot finish planned Sprint work, first give the member peer support and work out the reason together and address the diagnosed cause; if the analysis identifies an estimating problem, improve estimating through the Sprint Retrospective rather than criticizing or piling on more. When a member's state declines and the member keeps missing meetings, the Scrum Master first checks in privately with the member, listens and offers support, rather than pressing or putting it off.
Step 3: The team finds its own way, and the coach guides without doing it for the team
For problems the team discovers itself, first let the team find its own way. A servant leader can guide, provide resources and support, but does not make the decision for the team. Some typical cases:
- One member falls behind. At the Daily Scrum, one member's item is revealed to be behind plan. The coach guides the team to talk it over together, and the team proposes the solution. The coach does not hand the item to someone else, does not call a meeting of stakeholders and certainly does not organize a team-building event.
- A member is absent for a while. First assess with the team the effect on the Sprint Goal and capacity, then let the team negotiate sharing the work, rather than immediately hiring externally, escalating or trying to keep the person; escalate or add people only if the team cannot absorb it.
- A member volunteers. A tester volunteers to learn a new technology that nobody on the team knows. Encourage and support it, without assigning or taking over.
- A story hits a hard problem. The Scrum Master guides the team to brainstorm and find a way together, rather than giving the answer in place of the team.
- The team is slow to decide. If the team is in an early stage of moving to agile, first assess the influence of culture, then use servant leadership to coach the team to adapt to the new way of deciding.
- A member raises a concern privately. First understand the nature of the concern. If it is something for the team to handle, bring it back into the team to be raised openly and resolved by the team, and the Scrum Master does not do it for them. If it involves personal privacy or sensitive matters, first learn what the person wants.
When the team lacks a sense of commitment, the same applies. As a servant leader, let the self-organizing team find the causes and solve the problem itself, rather than forcing every member to attend the Daily Scrum and report status, or simply applying pressure and making demands. Diagnose the cause first. You can facilitate the team's joint improvement through the Sprint Retrospective, and, depending on the situation, hold one-on-one listening and coaching sessions. (Common exam practice is to use coaching, mentoring and one-on-one communication to understand the core of a problem.) A command-style approach makes the team feel even less ownership.
Step 4: When to escalate or adjust the scope
Handle it according to the situation. For a cross-team dependency, coordinate first and remove the impediment. If it affects the current Sprint, the Developers negotiate scope with the Product Owner and protect the Sprint Goal. If it affects future work, the Product Owner adjusts the order of the Product Backlog. Escalate only when the matter goes beyond the team's authority. The following are practices commonly used in exam questions (common exam practice: when the team cannot solve it itself, the answer usually lands on “reorder priorities together with the Product Owner”, not on the Scrum Master deciding alone):
- A key member suddenly takes long leave, there are too few people, and the release date must be protected: assess the impact together with the Product Owner and the team, and the Product Owner reorders the priorities so the most critical deliverables are protected first.
- The team has failed to complete its planned work for several Sprints in a row and cannot even deliver the release: once the cause has been looked at together (for example, in the Sprint Retrospective), meet face to face with the Product Owner and the team to agree on adjusting the scope and the next steps.
- The Sprint is nearly over and a story needs more time: first meet with the team and agree on the response together.
- A change that affects delivery arises during the Sprint: if it affects the current Sprint, the Developers negotiate with the Product Owner to adjust the scope of the Sprint Backlog and make sure the Sprint Goal is not endangered. If it affects future work, the Product Owner reorders the Product Backlog, and communication follows.
- There are dependencies between teams and progress is affected: coordinate the dependencies with the teams concerned first. If this Sprint or later work is affected, reorder priorities with the Product Owner, and do not rely on overtime, extending the timebox or adding people.
Velocity falls for three Sprints in a row
The team of a finance shared-services platform has delivered steadily for a year, but its velocity has fallen in each of the last three Sprints. The Scrum Master does not add people to the team and does not go to the Product Owner to demand cutting scope. Instead, at the Sprint Retrospective the Scrum Master first puts the data on the table: the story points completed per Sprint fell from 32 to 26, 22 and 19. After discussion the team finds that nobody is familiar with a newly introduced reporting component and everyone is working “while reading the documentation”. So the team itself decides to arrange two internal knowledge-sharing sessions, without changing the estimating scale (a consistent estimating scale is what keeps velocity comparable over time). Three Sprints later velocity recovers, and the team also checks the completed volume and cycle time of similar stories to confirm that capability has recovered, not that estimates have grown. Throughout, the Scrum Master's actions are to supply data, ask questions and arrange training resources, and the decision stays with the team.
Worked examples
Example 1: A remote-work pilot team lacks commitment: what does a servant leader do?
A manufacturing company is moving from predictive methods to agile, and the project manager is sent to lead an inexperienced team on the first pilot. Because of a temporary arrangement, the whole team works remotely. By the second Sprint, the project manager notices that team members lack a sense of commitment, and the team has not yet discussed the reasons together. As a servant leader, what should the project manager do?
Show answer and explanation
Correct answer: A
A manufacturing company is moving from predictive to agile. The project manager leads an inexperienced team on the first pilot, and the team works remotely under a temporary arrangement. In the second Sprint the project manager finds members lack a sense of commitment, and the team has not yet discussed why. As a servant leader, what should the project manager do?
Two signals: “servant leader” and “lack of commitment”. When an agile team has a problem, first let the team self-organize to solve it: the team finds the causes and proposes the remedies itself, and the servant leader's role is to guide and support. The project manager can guide the team right now to discuss the causes together and propose solutions itself, providing support, coaching and removal of impediments as needed during the discussion but not deciding for the team. That keeps the initiative with the team and also builds commitment. The answer is A.
Why the other options are wrong
- B. Forcing every member to attend the Daily Scrum and report status is command and control, contrary to servant leadership. The Daily Scrum is also the team's own meeting to coordinate its work, not a place to report to a manager.
- C. The lack of commitment may not be caused by remote work, and remote work is already a settled arrangement, so asking for an exception is not necessarily realistic and does not first let the team find the causes.
- D. Interviewing members one by one, asking them to raise participation and having them report improvements is command and control. It treats a team problem as an individual problem, the cause has not been confirmed and the team has not analyzed it, which fits neither self-organization nor servant leadership.
Key takeaway When an agile team has a problem, first let the team find its own way, and the leader then provides support.
Variation If the stem said the team had tried for several Sprints and still could not solve it, and the impediment came from outside the team, the servant leader would step in to coordinate outside resources and help clear it.
Something wrong with this question?
Example 2: Someone is behind at the Daily Scrum: how does the coach help?
At the Daily Scrum, an agile coach learns that a developer's items are behind the Sprint plan. The coach wants to help the developer solve the problem. What should the coach do?
Show answer and explanation
Correct answer: A
In a team using Scrum, the Daily Scrum has revealed that one developer's items are behind the Sprint plan. The question asks what the agile coach should do to help.
An agile team is self-organizing. When a problem appears, first invite the team to offer suggestions and find its own way, with the coach only facilitating. That keeps the initiative with the team and lets everyone share ownership of the result. The one who is behind is supported as part of the team, not singled out or replaced. The answer is A.
Why the other options are wrong
- B. Having the coach decide who takes over the items amounts to assigning work for the team, which goes against self-organization and takes the decision away from the team.
- C. A progress problem within the team should first be solved by the team itself. There is no need to bring in stakeholders, which would escalate an internal matter and take away the team's chance to solve it itself.
- D. The stem does not say the delay comes from exhaustion, so a team-building event has nothing to do with the problem and misses the target.
Key takeaway When a problem appears, let the team find its own way first, with the coach guiding and not deciding for the team. The coach's role is to ask questions and guide so that the team finds the way and owns the result.
Variation If the stem said the cause of the delay was waiting for another department to grant access, that would be an external impediment, and the Scrum Master should step in personally to coordinate.
Something wrong with this question?
Common traps
Common trap
- “Report to a superior”, “reassign”, “bring in outsiders” and “add budget” are often the wrong options in agile scenario questions.
- When velocity drops, first find the cause through a retrospective. Do not first swap people, change scope or add budget.
- Do not rush into action before the cause is clear. The common exam line of thinking is data, cause, action.
- When a technical idea conflicts with the project goal, let the Developers and the Product Owner talk directly. The project manager does not arbitrate.
- “Doing it yourself” is not the same as “deciding for the team”: the Scrum Master can clear impediments, but problems inside the team must be solved by the team itself.
Key point
- When a problem arises, first judge whose it is: impediments are removed with the Scrum Master's help, requirements belong to the Product Owner, technical matters belong to the Developers.
- Common exam practice for the order: collect data, analyze causes, take action. The team tries first and the coach guides.
- When the team cannot solve it, adjust scope or reorder priorities together with the Product Owner (common exam practice; coordinate cross-team dependencies first, and escalate only when beyond authority).
Key takeaways
- First work out who owns the problem: impediments, requirements and technical matters each have their own role.
- Common exam practice for the order of handling: collect data, analyze causes, take action.
- For problems the team finds itself, let the team find its own way first. The servant leader guides and supports without doing it for the team.
- When velocity falls or planned Sprint work is not completed, first look for causes through a retrospective. Do not first add people, money or change scope.
- When the team cannot solve it, it often reorders priorities with the Product Owner to protect the most critical deliverables (depending on the situation, coordinate dependencies or escalate if necessary).
Lesson 5
Removing Impediments and Shielding the Team from Outside Interference
Lesson overview
One of the Scrum Master's most frequently tested responsibilities is helping impediments get removed. (The overall accountability is helping the team apply Scrum properly and raise its effectiveness.) Questions built around it are very common among the Scrum role questions. The stem almost always contains one concrete stumbling block: a functional manager suddenly assigns work to members, a senior executive keeps asking about progress, the open office is noisy, a laptop is broken, an external interface is still not in place. You only need to make two judgments: what type of impediment is this, and should the Scrum Master step in personally or guide the team to find its own way. This lesson is organized in three groups: “impediments within the team's own capability”, “cross-team or organizational impediments and outside interference”, and “several impediments at once”, and it ends with a summary of the judgment involved.
What counts as an impediment
PMBOK 8 defines an impediment as “an obstacle that prevents the team from achieving its objectives” (also known as a blocker). It is anything that stops the team from moving forward: another department's cumbersome process, an unstable environment, permissions that are slow to be approved, a laptop that will not boot, third-party interface documentation that does not match actual behavior, key data that cannot be accessed for the time being. It also includes interference from outside, such as other people coming straight to the team to ask for work, a functional manager calling frequent status meetings, or stakeholders phoning and emailing nonstop for progress.
A servant leader's first reaction to an impediment is to help resolve it actively, not just to offer advice and not to pass it up and leave it there. Impediments can be handled in several ways, but there is one dividing line: give priority to building the team's ability to resolve impediments itself. When an impediment is beyond the team's authority and needs cross-department coordination or management support, the Scrum Master should drive coordination, step in or escalate, making sure the problem keeps being dealt with. (Common exam practice: for what the team can solve internally, choose guiding the team to find its own way. For what involves people or resources outside the team, choose the Scrum Master stepping in to negotiate. This is a common judgment in exam questions.)
Type 1: Impediments the team can find a way around
When the team hits an internal sticking point and cannot identify its options, the coach organizes the team to brainstorm and find alternatives rather than giving orders, swapping the story or swapping people. If a key story depends on another supplier's output and has made no progress, contact the supplier first to understand the cause and agree on recovery actions, while also helping the team develop a contingency delivery plan. This directly addresses the external dependency while building the team's ability to devise responses.
Type 2: Outside interference and resource conflicts
Outside interference is the most frequently tested kind of “impediment”. The principle for handling it is: communicate and negotiate first, with no confrontation and no tattling. Take over the inquiries and stand in front of the team. Pass what belongs with the Product Owner to the Product Owner.
- A functional manager suddenly assigns work to a member, and the member cannot complete the team's tasks: talk with the functional manager and negotiate the member's available time. Sending the member back to the department would weaken the team and is not advisable. Reporting it to the sponsor is tattling. Citing the project charter and firmly “demanding compliance” is not appropriate either.
- A functional manager calls several status meetings a week, taking up members' time: take the initiative to negotiate an alternative with the manager, for example letting the manager look directly at the team's information radiator.
- A senior executive or sales director frequently asks about progress and launch dates: explain agile ways of working to the executive and ask that progress questions go to the Scrum Master, who takes them over and answers. General progress can also be seen first in the team's artifacts. Concerns about product scope, priorities and releases go to the Product Owner. Do not require team members to hand every inquiry over, do not tell the executive bluntly that the information radiator is “the only thing you can look at”, and certainly do not forbid the team from answering anyone's questions.
- Stakeholders frequently disturb the team: guide them to get information through suitable agile practices, such as attending the Sprint Review or looking at the information radiator.
- The team is interrupted by other teams or asked to help them: find the root cause first, then agree rules with the team to remove the interference.
Shielding the team does not mean keeping everyone out. It is more effective to explain the team's working rules to the source of interference. The Scrum Master stands in front of the team but does not order the backlog in place of the Product Owner. Environmental and permission impediments such as office noise, a broken laptop or access not yet granted are removed with the Scrum Master's help: the team handles what it can handle on its own, and what is beyond the team's authority the Scrum Master coordinates with the people concerned, escalates through the appropriate channel when necessary and follows through to resolution.
Type 3: Several impediments at once
When the team lists impediments and asks the Scrum Master to settle the order of handling, those that may cause work to stop or serious violations (such as compliance problems) are usually handled first, and the rest in turn by urgency, impact, dependencies and risk. This is a common exam practice. The order of features belongs to the Product Owner, but the order in which impediments are handled is settled collaboratively, with the Scrum Master helping the team and the relevant stakeholders assess each impediment's impact and tracking until it is resolved. This is different from the Product Owner's accountability for ordering the Product Backlog. The Scrum Master's job is to get impediments removed and help the team record and track how they are handled, not to let them lie and not to reorder features in place of the Product Owner.
If the team thinks the Scrum Master is not removing impediments, the right way to give feedback is to talk with the Scrum Master directly at a Sprint Retrospective or afterward, first agreeing on “what counts as an impediment and what counts as removing it”, and then urge the Scrum Master to act, rather than going over the Scrum Master's head with a complaint at the outset. (If the conversation does not work and the problem persists, escalating along the governance path is still reasonable.)
A decision table
| Source of the impediment | What the Scrum Master does |
|---|---|
| Environment, tools, permissions | The team handles what it can on its own. For what is beyond its authority, coordinate with the people concerned, push for escalation and follow through to the end |
| A functional manager or other departments taking up members' time | Communicate and negotiate with them, with no confrontation and no tattling |
| Executives, supervisors or sales asking about progress | Explain the way of working, take over the inquiries, and pass release questions to the Product Owner |
| A sticking point inside the team, no ideas | Organize the team to brainstorm, guiding and not doing it for them |
| Several impediments at once | Rank collaboratively by urgency, impact, dependencies and risk. Those that may cause a stoppage or serious violation (such as compliance) are usually handled first |
Three days of being chased by executives
A retail product team is concentrating on completing the user stories in the current Sprint, but several stakeholders have recently been phoning and emailing team members directly for progress. The Scrum Master does three things. First, the Scrum Master meets these stakeholders, explains how the team works and invites them to the Sprint Review. Second, the Scrum Master sends them links to the electronic task board and the burndown chart and asks them to look at progress there first. Third, questions that need a product decision go to the Product Owner. Three days later, the number of times team members are interrupted drops from a dozen a day to the occasional one or two.
Worked examples
Example 1: A functional manager takes up members' time: what does the Scrum Master do?
In a cross-functional agile team, a tester cannot complete the tasks the team assigned because the functional manager has suddenly assigned the tester work inside the department. What should the Scrum Master do?
Show answer and explanation
Correct answer: C
In a cross-functional agile team, a tester cannot complete the tasks the team assigned because the functional manager has suddenly assigned department work to the tester. The question asks for the Scrum Master's correct response.
On the surface it is a resource conflict, but in essence the functional manager's interference has become an impediment to the team. Removing impediments is the servant leader's duty, and the resource conflict is resolved by negotiating with the functional manager: the Scrum Master should talk with the functional manager, understand what the manager needs, and negotiate the member's available time in the Sprint. The answer is C.
Why the other options are wrong
- A. Sending the member back to the department weakens the team, does not solve the root cause of the functional manager taking up resources and creates a new gap.
- B. Escalating directly to the sponsor before attempting to negotiate is premature and could damage the relationship with the functional manager. Communicate and negotiate first, and consider escalating only if negotiation fails.
- D. The project charter is not a document that governs the functional manager's day-to-day arrangements, and a firm tone of “demanding compliance” does not help negotiation.
Key takeaway Outside interference is also an impediment. Communicate and negotiate first, with no confrontation and no skipping straight to escalation.
Variation If the stem were changed to “the functional manager calls status meetings several times a week”, you would likewise negotiate an alternative first, for example asking the manager to look at the team's information radiator.
Something wrong with this question?
Example 2: A senior executive chases progress: the next step in shielding the team
You are the Scrum Master of a team. A senior executive has many questions about the project and its progress, and quite a few team members are spending a great deal of time answering them. What should you do next?
Show answer and explanation
Correct answer: B
On a Scrum project, a senior executive has many questions about the project and its progress, and quite a few team members spend a great deal of time answering them. The question asks for the Scrum Master's next action.
The Scrum Master's duties include both shielding the team from interference and serving the organization, helping stakeholders understand and apply Scrum. The most appropriate step is to explain agile ways of working to the senior executive and ask the executive to take progress questions to the Scrum Master. This takes the inquiries off the team and keeps a good relationship with the executive. The answer is B.
Why the other options are wrong
- A. Forwarding quietly without any explanation leaves the executive wondering why there are no responses, which damages the relationship and does nothing to help the executive understand agile ways of working.
- C. Telling the executive bluntly to look only at the information radiator and ask no more questions is not how a servant leader treats stakeholders. The information radiator should be introduced proactively and in a friendly way.
- D. Requiring that nobody on the team answer anyone without permission blocks communication by control. It goes against an empowering, serving role and would make the executive even less satisfied.
Key takeaway Shielding the team is done not by blocking but by explaining to the executive and taking over the inquiries.
Variation If the executive asks “why were the features traded off this way and when will it be released”, such questions should go to the Product Owner, and the Scrum Master does not order or commit on the Product Owner's behalf.
Something wrong with this question?
Common traps
Common trap
- Environmental, tooling and permission impediments, and outside interference, are removed with the Scrum Master's help. But for what the team can figure out within its own capability, let the team figure it out.
- For outside interference, usually communicate and negotiate directly first, with no confrontation and no tattling. If the impediment is beyond authority, negotiation fails or an established escalation criterion is met, escalate along the governance path in time and keep tracking the outcome.
- Shielding the team is not blocking. Explaining to the source of interference and taking over the inquiries is the long-term answer.
- Concerns about releases go to the Product Owner, and the Scrum Master does not order for the Product Owner.
- Impediments cannot be handled by “only giving advice” or “only escalating”. Help resolve them actively and follow through.
Key point
- Cross-team or organizational impediments and outside interference are removed with the Scrum Master's help. For sticking points within the team's own capability, guide the team to find its own way.
- Outside interference: communicate and negotiate, take over the inquiries, and pass on to the Product Owner what should go there.
- Several impediments at once: rank by urgency, impact, dependencies and risk. Those that may cause a stoppage or serious violation are usually handled first.
Key takeaways
- An impediment is anything that stops the team from moving forward, including outside interference. Helping get impediments removed is one of the Scrum Master's key responsibilities.
- What the team can solve internally: organize a brainstorm. What involves outside people and resources: the Scrum Master negotiates personally.
- A functional manager taking up members: negotiate the available time first. Do not send people back, tattle or cite the charter forcefully.
- A supervisor chasing progress: explain the way of working, take over the inquiries, and pass release concerns to the Product Owner.
- With several impediments, rank by urgency, impact, dependencies and risk, and handle first those that may cause a stoppage or serious violation. A servant leader's first reaction is to help resolve actively.
This chapter has 56 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.