PMP · Agile and Hybrid · 3 lessons · about 36 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Scrum has three artifacts: the Product Backlog, the Sprint Backlog and the Increment. The first two answer “what is there to do?” and the third answers “what has been built?” (In PMBOK 8 terms the Sprint Backlog is the iteration backlog; this chapter uses the Scrum Guide names because it is about Scrum's artifacts.) The chapter follows that thread: how requirements get into the Product Backlog, how they are refined into items the team can start on, how the Developers manage their current work with the Sprint Backlog, and finally the usable Increment created during the Sprint and the technical debt that so often drags it down. PMBOK 8 describes the backlog as a framework for managing scope in adaptive environments: a dynamic, prioritized list maintained by the product owner.
By the end of this chapter you should be able to do the following. Explain that the Product Backlog is the single source of work undertaken by the Scrum Team (new requirements and changes are all recorded in it and ordered by the Product Owner), and that the Product Owner owns its content and order while the Developers own the estimates. Tell backlog refinement, the definition of ready and the Sprint Backlog apart. Describe how a change enters through the backlog. Explain that an Increment must meet the Definition of Done, and distinguish an Increment that is potentially releasable from one that has actually been delivered and released. Make technical debt visible and put it in the backlog.
Lessons in this chapter
- Lesson 1: The Product Backlog: nature and change handling. The single source of work undertaken by the Scrum Team (the one place where requirements and changes are recorded and ordered); detailed at the top and coarse at the bottom; the Product Owner owns content and order. A change is first recorded as an item, then assessed and ordered; a low priority usually means it is not selected for an upcoming Sprint for now, but dependencies and constraints still have to be weighed.
- Lesson 2: Refinement, the definition of ready and the Sprint Backlog. Refinement is the ongoing work of detailing, estimating and ordering. The team may agree a definition of ready as a reference threshold for items entering a Sprint (Scrum does not require one). The Sprint Backlog belongs to the Developers, tasks are picked up by team members, and a new request that arrives during the Sprint goes to the Product Backlog first.
- Lesson 3: The Increment and technical debt. The Increment is the items that are done and meet the Definition of Done, added to earlier Increments. Meeting the Definition of Done (potentially releasable) is a technical state; whether and when to actually deliver and release is decided by value, stakeholder needs and organizational governance, with the Product Owner playing a key role in judging value. Technical debt goes into the backlog as explicit items, and its impact is assessed before it is paid down.
Chapter map
| Question to answer | Artifact or activity | Who is responsible | Lesson |
|---|---|---|---|
| Where is everything waiting to be done? | Product Backlog | Product Owner | Lesson 1 |
| How are new requirements and changes handled? | Record, assess and order; normally select at Sprint Planning, with scope renegotiation possible during a Sprint if the Sprint Goal is not endangered | Product Owner and team | Lesson 1 |
| How does an item become ready to start? | Refinement (detailing, estimating, ordering), definition of ready | Product Owner owns ordering and list management, Developers estimate, both collaborate on detailing | Lesson 2 |
| How is this Sprint's work divided and tracked? | Sprint Backlog, task pick-up | Developers | Lesson 2 |
| What did the Sprint produce? | Increment (meeting the Definition of Done) | Scrum Team | Lesson 3 |
| How is the hidden risk left by rushing managed? | Technical debt items, refactoring | Team and Product Owner | Lesson 3 |
Study tips and practice
- Start with the picture “one backlog, one owner”: when a new request arrives or importance changes, normally consider the Product Owner and the Product Backlog first, while also checking the Sprint Goal and any governance, regulatory or contractual constraints.
- Keep refinement and Sprint Planning apart. Refinement is ongoing; Sprint Planning is the event that opens the Sprint.
- In the chapter exercises, first decide whether the question is about the backlog, a task or the Increment, and only then choose an answer. The details of the Definition of Done come in the next chapter.
- “The nature of the Product Backlog” is a frequently tested point, so work through the Lesson 1 examples first and then practice the other lessons.
Lesson 1
The Product Backlog: Nature, Ownership and Change Handling
Lesson overview
Scrum has three artifacts: the Product Backlog, the Sprint Backlog and the Increment. This chapter takes them in turn, and this lesson starts with the Product Backlog. It is the agile project's master list of requirements and appears in the background of almost every agile scenario question. The lesson answers three questions: what it is, who owns it, and how new requests and changes get in. ECO: Process domain, Task 3 (Help ensure value-based delivery) and Business Environment domain, Task 3 (Manage and control changes). The next lesson covers how the backlog is refined into items that can be developed, and the third lesson covers the Increment delivered at the end of the Sprint.
What the Product Backlog is
PMBOK 8 describes the product backlog as follows: “The product backlog is a dynamic, prioritized list of work items and features. The product backlog provides teams in adaptive environments with a framework for managing scope by focusing on value-driven outcomes, enabling continuous prioritization, and maintaining alignment with stakeholder expectations.” It is usually prepared by the product owner and includes requirements, features, epic user stories and user stories, representing the overall scope and vision of the product.
In Scrum it carries a stricter meaning as well: it is the single source of work undertaken by the Scrum Team (the requirements and changes themselves may come from customers, regulators, the market and so on). A new feature, an improvement, a defect fix or a technical rework has to become an item on this list before the team will work on it. The items are called product backlog items (PBIs), and most are written as user stories.
The “single source” rule has a practical purpose. If the team draws work from one list, there is only one set of priorities. If the boss's verbal instructions, a customer's phone call and a tester's ticket each go their own way, the team is pulled in several directions and nobody can say what comes first.
How it is organized: detailed at the top, coarse at the bottom, and who owns it
The backlog is ordered from highest priority to lowest. The items at the top are usually the most specific. They are refined and estimated first, and once they reach the level of readiness the team has agreed, they can be selected into a Sprint. The further down the list, the coarser the item, and it may still be just a feature or even an epic. This is deliberate: requirements far in the future are uncertain anyway, and refining them too early wastes the work when the requirement changes. The backlog gets finer bit by bit as refinement goes on, which is why it is called dynamic.
Keep the division of responsibility clear. The Product Owner is responsible for the backlog's content and order. The Product Owner keeps maintaining it and adjusting the order according to the latest feedback and market changes, and makes sure before Sprint Planning that the order of the top items reflects current value. Others can help write items, but the final responsibility stays with the Product Owner. The Developers are responsible for the estimates, because the people who do the work know best how big it is; the Product Owner can only help them weigh trade-offs. The project manager and the Scrum Master neither own this list nor estimate on the team's behalf.
How to do it: changes come in through the backlog
Adaptive projects usually have no traditional change control board and usually do not use a formal change control procedure, although they must still follow organizational governance, regulatory and contractual requirements. PMBOK 8 puts it this way: “In adaptive approaches, managing project changes typically involves backlog management rather than a formal change request process. Changes are continuously assessed and prioritized throughout the iterative development cycle. When a stakeholder proposes a change, it is recorded as a product backlog item and added to the backlog.” An impact analysis is conducted to evaluate the change's effect and set its priority. “Typically, there is not a formal ‘approval’ process; instead, any proposed change can be added to the backlog. If the proposed change is assigned a lower priority, this essentially means that the change is deferred. Conversely, choosing not to add a change to the backlog, or remove an existing change from the backlog, means that it is rejected.”
In practice that comes down to four steps (common exam practice):
- Record: write the new request as an item and put it in the Product Backlog.
- Assess: the Product Owner and the team look at value, cost and impact together.
- Order: if the value is higher than that of existing items, move it up; if lower, it sinks.
- Select: the Developers normally select it according to capacity at a later Sprint Planning event. If new learning during a Sprint permits a scope adjustment without endangering the Sprint Goal, the Developers may instead renegotiate the scope with the Product Owner and bring it into the current Sprint.
A new request normally goes into the Product Backlog first and does not casually interrupt the current Sprint. If the scope can be adjusted without endangering the Sprint Goal, it can be renegotiated with the Product Owner, and if the Sprint Goal has become obsolete, the Product Owner may cancel the Sprint. The next lesson expands on this when it covers the Sprint Backlog.
Worked scenario: a registration mini-app for a community hospital
The team is in its third Sprint. That day the health authority issues a new regulation: appointment booking must verify the patient's real identity, and without it the app cannot go live.
The Product Owner handles it like this. He writes “identity verification for booking” as an item. After assessing it with the team, he decides it is required for compliance and worth more than “waiting-room reminder notifications”, which had been second in line, so he puts it first in the backlog. The current Sprint carries on as planned, and the item is selected at the next Sprint Planning. No change review meeting was called and no supplementary agreement was signed. The change was absorbed by “going into the backlog and being reordered”.
Worked examples
Example 1 An external regulation changes and an item near the bottom suddenly matters
A cross-border logistics dispatch system is being developed in Sprints. The regulator suddenly issues new data-declaration rules. An item far down the Product Backlog, “declaration data format conversion”, had been thought unimportant, but now the system cannot go live in compliance without it. What should the team do?
Show answer and explanation
Correct answer: B
The project is being developed in Sprints. A new external regulation turns an item far down the backlog into “without it we cannot go live in compliance”. The question is what the team should do next.
The team selects work from the Product Backlog, using its order as an important guide, and the content and order of the backlog are the Product Owner's responsibility. The item's importance has changed because of an external change, so the matching action is to change its position in the backlog, not to look for a workaround outside it. The team should contact the Product Owner and ask him to reorder the item so it moves up to where it should be. The answer is B.
Why the other options are wrong
- A. A prominent reminder only gets people to notice the item. The order of the backlog has not changed, the team still takes work by the old priorities, and the item still does not rise.
- C. Compliance is a hard condition for going live, so value cannot be measured by return on investment alone. Calculating ROI is also not the team's job and does not solve the ordering problem.
- D. Refactoring reorganizes internal structure without changing external behavior. What is missing here is a feature that has not been built yet, which refactoring cannot supply, and it would not move the item up the backlog.
Key takeaway When an item's value changes because of an external change, ask the Product Owner to reorder it first.
Variation If the change affects only a story currently being worked on and that story is no longer needed, the team talks it over with the Product Owner and closes it. If the change comes from a new customer requirement, it likewise goes into the backlog first and is then ordered, not pushed straight into the Sprint.
Something wrong with this question?
Example 2 A customer raises a new requirement after a standard is revised
You are in charge of an agile project that is under way. An industry safety standard has just been revised, the product's existing features can no longer meet end users' requirements, and the customer has raised new requirements on that basis, which will put pressure on the schedule. What should you do next?
Show answer and explanation
Correct answer: C
An agile project is in execution. An industry standard has been revised and the customer has raised new requirements on that basis, which will put pressure on the schedule. The question is what you should do next.
The entry point for new requirements is the Product Backlog, and the gatekeeper is the Product Owner. The customer's new request is first discussed with the Product Owner, who adds it to the backlog and orders it by value. After that, at Sprint Planning, the developers select items with the Product Owner, taking the team's capacity and past performance into account. The question asks for the action that comes “next”, and the first step is to talk it through and get the change into the backlog. The answer is C.
Why the other options are wrong
- A. “Embracing change” does not mean folding a change straight into the plan and adding resources to cope. Schedule and resources are limited. What gets adjusted is the value priority of items, not unlimited additions.
- B. Pushing every change to the next release cycle freezes the requirements and goes against agile responsiveness to change. Whether and when to do the work depends on its value once ordered, and it might be selected as early as the next Sprint.
- D. Whether a supplementary agreement is needed depends on the contract, but the question asks for the next step: the Product Owner first adds the new requirement to the Product Backlog and orders it. The contract cannot be amended without assessment.
Key takeaway A new requirement enters the Product Backlog through the Product Owner and is ordered. At Sprint Planning the developers select items, taking the team's capacity and past performance into account.
Variation If the change comes up at the Sprint Review, discuss its impact with stakeholders during the Review and adjust the Product Backlog accordingly; the Developers later decide at Sprint Planning whether to select it. If an urgent change arises during the Sprint, the Product Owner and Developers reassess its impact and renegotiate scope only if the Sprint Goal is not endangered.
Something wrong with this question?
Common traps
Common trap
- The Product Backlog is not a requirements list fixed at project kickoff. It can change throughout the project, including during Sprints.
- A new request is not simply squeezed into the plan in the name of “embracing change”, and it does not wait for the next release cycle either. It goes into the backlog first and is ordered afterward.
- Reordering is the Product Owner's job. The team, the project manager and the customer cannot go around the Product Owner and change the order directly.
- The Developers do the estimating. The Product Owner cannot do it for them, and it is not the project manager's call.
- Changes in adaptive projects are usually handled by “going into the backlog and being reordered”, not by a traditional formal change request process (PMBOK 8: backlog management handles change, and there is typically no formal approval process). But if organizational governance, regulations or contract terms require it, the corresponding approval or contract change steps must still be followed.
Key takeaways
Key point
- The Product Backlog is a dynamic, ordered list and the single source of work undertaken by the Scrum Team. Any new work you want the team to do should go into it first.
- The closer to the top, the more detailed and estimable the item; the closer to the bottom, the coarser. Content and order belong to the Product Owner, and estimates belong to the Developers.
- A change is recorded as an item and added to the backlog: a lower priority means deferral, and not adding it, or removing an existing item, means rejection.
- When an item's value changes because of changes in the external environment, go to the Product Owner first to reorder.
- The order for a new requirement is: record, assess and order it, then normally have the Developers select it at Sprint Planning; during a Sprint, scope may also be renegotiated with the Product Owner if the Sprint Goal is not endangered.
Lesson 2
Backlog Refinement, Definition of Ready and the Sprint Backlog
Lesson overview
The last lesson covered the Product Backlog itself. This lesson covers two things: how to get the items at the top of the list ready to start, and what artifact the team uses to manage its current work once it has started. The first is backlog refinement and the definition of ready; the second is the Sprint Backlog (the iteration backlog in PMBOK 8 terms). The most common exam questions ask “at which point should this be done?” and “what do we do when a new request arrives during the Sprint?” ECO: Process domain, Task 3 (Help ensure value-based delivery) and Business Environment domain, Task 3 (Manage and control changes).
Refinement: keeping the top items ready to use
PMBOK 8 defines backlog refinement as “the progressive elaboration of the content in the backlog and reprioritization of it to identify the work that can be accomplished in an upcoming iteration.” It “involves constantly reviewing, revising, ranking, and editing the product backlog in order to build features that are needed by the business and the customer.” It is an ongoing activity of adding detail, estimating and ordering. It is not a fixed meeting slot and can be done at any time. It continues during the Sprint, with the Product Owner and the Developers working together to prepare the items that will be needed next. It usually covers three interrelated activities that can be repeated and interleaved (there is no strict order):
- Detailing: break large items at the top into smaller ones, small enough to finish within a Sprint.
- Estimating: the Developers give the size, commonly in story points using planning poker.
- Ordering: the Product Owner decides the sequence by weighing value, risk and cost.
A good backlog is often described with the acronym DEEP (a common exam term): Detailed appropriately, Estimable, Emergent, Prioritized. “Emergent” means the backlog keeps evolving as learning, feedback and the environment change: items are added, removed, split and adjusted.
Ordering weighs value, risk, cost, dependencies and constraints (PMBOK 8 makes explicit that dependencies and constraints can affect the order). All else being equal, as a common exam practice, the higher the value, the higher the risk that needs early validation, and the lower the cost, the earlier an item should be placed. Doing high-risk work first is meant to stop losses early if it turns out not to work. PMBOK 8 notes that commonly used methods include MoSCoW (must have, should have, could have, and will not have), the 100-point method, cost of delay, and Kano analysis. WSJF (cost of delay divided by duration; the larger the value, the sooner the item is done) is a common exam term.
The definition of ready: the threshold for entering a Sprint
The definition of ready (DoR) is a checklist for judging whether an item at the top of the list can enter a Sprint: is the value clearly stated, does the team understand it in enough detail, have dependencies been identified, has it been estimated and is it small enough, does it have acceptance criteria, and does the team know how to demonstrate it? PMBOK 8 also says that a checklist used to ensure that a project or task is ready to start “is also called ‘definition of ready’ or ‘full kit,’ and can be particularly useful in minimizing rework.”
So a user story with a vague description and no acceptance criteria should not be forced into a Sprint. It should be taken to refinement and the Product Owner asked to add the missing detail, and the story is generally estimated after that (the order is agreed by the team). Exam tip: questions like this usually want refinement (the backlog refinement meeting), not the daily coordination meeting, the Sprint Review or the retrospective. Refinement itself is an ongoing activity, so the team may use a refinement meeting to do it, but that meeting is not the only fixed slot for it.
The Sprint Backlog: this Sprint's battle plan
PMBOK 8 describes the iteration backlog as “a subset of the product backlog that contains selected user stories and the required tasks to complete the committed work during the current iteration.” In the Scrum Guide's terms, it is made up of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), and an actionable plan for delivering the Increment (how).
It belongs to the Developers. The team breaks the selected stories into tasks, and members can pick them up as the team agrees. The team keeps the Sprint Backlog updated and, if it wishes, records task estimates and remaining work and updates them often (this is an optional team practice). How tasks are split, who does what and how the work is implemented are decided by the Developers themselves. The Product Owner does not assign tasks but can clarify requirements and negotiate scope with the team. If the team has agreed to record tasks and who picked them up in the Sprint Backlog, which may be represented on a task board, this is where you look; Scrum itself does not require assignees to be recorded.
The Sprint Backlog keeps being updated during the Sprint as more is learned, and the Developers can add necessary tasks they discover. New product requirements usually go into the Product Backlog first. If an urgent change must be dealt with in this Sprint, the Product Owner and the Developers negotiate an adjustment of scope and make sure the Sprint Goal is not endangered before deciding whether to adjust. Cutting or even dropping a story is likewise a conversation between the team and the Product Owner, not a decision either side makes alone. Agile stresses a sustainable pace; overtime is not the way to cram more in.
Worked scenario: an online course platform, day five of the Sprint
The Sprint Backlog contains the story “export transcripts”. The business side announces that another system already covers this feature.
The team talks it over with the Product Owner, confirms it is no longer needed, closes the story and records the reason. The freed-up time goes to an item that was lower in the backlog, “course ratings”. The Sprint Goal has not changed, and the team has not built a feature of no value just to honor what it originally committed to.
Worked examples
Example 1 A story is vague and has no acceptance criteria: where should it be fixed?
An agile management professional notices that a new user story added to the Product Backlog has a vague description and no acceptance criteria. At which point in the Sprint cycle should he ask the Product Owner to add more detail?
Show answer and explanation
Correct answer: D
A new user story in the Product Backlog has a vague description and no acceptance criteria. The question asks at which point in the Sprint cycle the Product Owner should be asked to add detail.
A story lacking detail and acceptance criteria is not yet “ready”. Adding detail, estimating and ordering are the work of backlog refinement, led by the Product Owner with the team taking part, so the request should be raised at the backlog refinement meeting, and the story is estimated once it is filled in. Refinement is ongoing and can take place both before and during a Sprint, so that by Sprint Planning the top items already have detail, estimates and acceptance criteria and the planning meeting is not taken up with clarifying requirements. The answer is D.
Why the other options are wrong
- A. The Sprint Retrospective is for reflecting on how the team works and settling improvements. It does not deal with the details of individual items.
- B. The Daily Scrum is for inspecting progress toward the Sprint Goal and adjusting the plan for the work ahead as needed. It is not the place to add requirement details, and it lasts only 15 minutes.
- C. The Sprint Review inspects the completed Increment and gathers feedback. It is not for polishing items that have not been developed.
Key takeaway When an item is vague or lacks acceptance criteria, have the Product Owner add what is missing during refinement.
Variation If the question is what an item must meet before entering a Sprint, the answer becomes the definition of ready. If it is whether an Increment is done, look at the Definition of Done.
Something wrong with this question?
Example 2 An urgent change appears in the middle of the Sprint
The agile team on an enterprise data dashboard project is in its third Sprint. The customer suddenly raises an urgent change: if it is not made, the value delivered to the customer will suffer, and if it is made, the Sprint Goal will be at risk. What should the team do next?
Show answer and explanation
Correct answer: B
In the third Sprint, the customer raises an urgent change: not making it harms the value delivered, and making it puts this Sprint's Sprint Goal at risk. The question is what the team should do next.
During a Sprint, no change may endanger the Sprint Goal, but as more is learned the Developers may negotiate the scope of the Sprint Backlog with the Product Owner. This change has a cost either way, so the team should work with the Product Owner to reassess its value, order and impact; the Developers can then update the Sprint Backlog while protecting the Sprint Goal. The answer is B.
Why the other options are wrong
- A. Putting it in the next Sprint means the change is not made now. The stem states that not making it harms the customer's value, so this does not meet the premise.
- C. Handing it to another team is passing the buck, and it does not assess the value or impact of the change.
- D. Agile stresses a sustainable pace. Taking on both the new requirement and the original work through overtime increases quality risk and is not the preferred way to resolve this conflict.
Key takeaway When an urgent change appears in the middle of a Sprint, the Product Owner and the team reassess priority and impact together.
Variation If the team finds that a new task takes too long and this Sprint cannot finish it, so that features must be cut or a whole story dropped, it likewise talks with the Product Owner, and does not decide by itself or turn to stakeholders or the Scrum Master.
Something wrong with this question?
Example 3 The new Product Owner wants to see how the work was split into tasks and who picked them up
At Sprint Planning, a team using Scrum broke the selected stories into tasks, members picked them up, and the team recorded them as agreed in a shared artifact that is continuously updated during the Sprint. Near the end of the Sprint, the original Product Owner is reassigned and a new Product Owner takes over. He wants to know which tasks one feature was broken into and who picked them up, and would like to consult this ready-made record. Where should he get this information?
Show answer and explanation
Correct answer: A
In a Scrum project, near the end of the Sprint, the new Product Owner wants to see which tasks a feature was broken into and who picked them up, and wants a ready-made record. The question is where to get it.
PMBOK 8 describes the iteration backlog (the Sprint Backlog in Scrum) as containing selected user stories and the tasks required to complete the work for the current Sprint, and it is updated continuously during the Sprint. The stem also says the team recorded the tasks and who picked them up in a shared artifact that is continuously updated during the Sprint, so that record is the Sprint Backlog, which may be represented on a task board. Scrum itself does not require assignees to be recorded. The new Product Owner can consult it directly. The answer is A.
Why the other options are wrong
- B. The Daily Scrum is an oral sync, not a ready-made record, and the next one may not even touch this feature.
- C. The Product Backlog orders the work needed for the whole product, but it is not the artifact the team agreed to use for recording this Sprint's tasks and who picked them up.
- D. Each member's own records are scattered, in different formats, not necessarily complete, and not an artifact shared by the team, so they are less direct than the Sprint Backlog.
Key takeaway If the team has agreed to record the task breakdown and who picked up each task in the Sprint Backlog, consult that backlog; Scrum itself does not require assignees to be recorded.
Variation If the question is which requirements of the whole product are still undone and in what order, the answer becomes the Product Backlog. If it is what was finished in this Sprint, look at the Increment.
Something wrong with this question?
Common traps
Common trap
- Refinement is not done all at once in the Sprint Planning meeting, and it has no fixed adjustment point. It is an ongoing activity.
- When an item is vague and has no acceptance criteria, ask the Product Owner to add them during refinement. Do not wait for the daily coordination meeting, the Sprint Review or the retrospective to deal with it.
- The Sprint Backlog belongs to the Developers and the tasks are divided by the Developers themselves (members can pick them up as the team agrees). The Product Owner does not assign tasks.
- A new request during the Sprint goes into the Product Backlog first. It is not written straight into the Sprint Backlog.
- An urgent change during the Sprint is not handled by working overtime or by passing it to another team. It is re-evaluated with the Product Owner.
Compare
| Product Backlog | Sprint Backlog | |
|---|---|---|
| Content | All known items for the whole product | The items selected for this Sprint, plus tasks and a plan for delivery |
| Owner | Product Owner (content and order) | Developers |
| Granularity | Detailed at the top, coarse at the bottom | Stories are usually broken into tasks, with remaining work recorded if needed |
| Change | Items can be added, removed and reordered at any time | Updated continuously as work progresses; necessary tasks can be added or removed. New product requirements usually go to the Product Backlog first, and anything that really must be handled in this Sprint is negotiated between the Product Owner and the Developers |
Key takeaways
Key point
- Refinement is an ongoing activity: detailing, estimating and ordering, led by the Product Owner with the team taking part.
- The definition of ready is a checklist for before an item enters a Sprint. If an item has no acceptance criteria, they can be added during refinement, usually before the item enters the Sprint; whether this comes before estimating is agreed by the team.
- Sprint Backlog = the items selected for this Sprint + tasks and a plan for delivery, and it belongs to the Developers.
- The Developers divide tasks themselves, and members can pick them up as the team agrees. A new request during the Sprint usually goes into the Product Backlog first.
- An urgent change is re-evaluated with the Product Owner for priority and impact. It is not absorbed by overtime and not passed to someone else.
Lesson 3
The Increment and Technical Debt
Lesson overview
The first two lessons covered the two lists that say “what to do”. This lesson covers “what was done”: the Increment, and a hidden problem that often drags it down, technical debt. You will see what counts as an Increment, why it must meet the Definition of Done, how delivery differs from release, and how technical debt arises and gets managed. ECO: Business Environment domain, Task 4 (Remove impediments and manage issues) and Task 6 (Continuous improvement).
What an Increment is
An Increment is the usable result formed when the Product Backlog items that meet the Definition of Done in this Sprint are integrated with all earlier Increments. The Scrum Guide describes an Increment as a concrete stepping stone toward the Product Goal, and the PMBOK 8 glossary defines a sprint as “a timeboxed interval within a project during which a usable and potentially releasable increment of a product is created.” The Increment can be inspected at the end of the Sprint, and it must be “Done”, meaning it is usable and meets the team's Definition of Done.
Hold on to three points. First, an Increment is counted by what is actually finished, not by what was planned. The items selected at Sprint Planning are only a plan; at the end of the Sprint only the items that meet the Definition of Done count toward the Increment. Second, every Sprint must produce a usable Increment, whether or not the Product Owner decides to release it. Third, distinguish an Increment that is usable and potentially releasable from one that has actually been delivered and released. Meeting the Definition of Done is a technical state: the feature is built, tested and could go live. Actual delivery and release come afterward, and the Product Owner takes part in deciding the timing on the basis of product value, with the decision rights and authorization path following the organization's governance arrangements.
Here is a worked count. At the start of the Sprint, 5 stories totaling 30 points were selected. At the end, 4 of them meet the Definition of Done, and the remaining story, worth 6 points, lacks only integration testing. The Increment for this Sprint contains only those 4 stories, 24 points. The remaining story does not count toward the Increment and goes back to the Product Backlog. The Product Owner reconsiders its order, and the Developers re-estimate it as needed in light of what they have learned. This “count only what is done” rule is also the basis for calculating velocity later.
Technical debt: why it exists and how to pay it down
Technical debt is a metaphor. Earlier on, a stopgap or lower-quality technical solution was adopted to hit a short-term goal, and that leaves a “debt” that will cost extra repair, maintenance or refactoring effort later. It is often incurred deliberately under schedule pressure, but it can also arise from a lack of understanding. A change in requirements or in the technical environment counts as technical debt only when it exposes a shortcoming in the existing solution and causes extra repair cost. Ordinary leftover work that goes back to the Product Backlog because it did not meet the Definition of Done is not automatically technical debt. The usual way to pay it down is refactoring, which restores the internal structure to a sound state without changing the external behavior.
Common consequences include sudden failures, longer delivery times, more defects, falling team confidence and lower customer satisfaction. One common cause is schedule pressure, so skipping tests or omitting reviews to go faster is itself creating technical debt. The signal is typical: each Sprint, more time goes into fixing defects and changing old code, and less and less new functionality gets built.
The key to managing it is to make it visible. Write the work of paying down technical debt as a non-functional item or a dedicated user story and put it in the Product Backlog; only then can it be assessed and ordered. The sequence is to assess its impact on delivery first, then decide with the Product Owner how to pay it down: right away, in installments, or by setting aside a Sprint for it. Do not pay it down quietly in the background through overtime, and do not automatically rank every piece of technical debt first or stop all new features without assessing the impact.
Worked scenario: a logistics dispatch platform, the status check in Sprint 6
The team measured the share of total hours that went into “fixing defects and changing old code” over the last three Sprints: 15%, 25% and 35%, with less and less new functionality produced. Investigation showed that temporary solutions left from an early rush to prepare for a demo had piled up.
The response: the team first assesses the impact and estimates that the refactoring needs about 40 hours, then agrees with the Product Owner to write “refactor the order module” as two user stories in the Product Backlog and pay it off over two Sprints, reserving about 20 hours in each. The debt now has a place and an order, and stakeholders can see why the investment is being made.
Worked examples
Example 1 Inheriting a project with a lot of technical debt: how do you explain it to stakeholders?
A team takes over a new project. The previous team left behind many problems, so the product carries a large amount of technical debt. Stakeholders know this but do not understand how it will affect delivery, and they still want the team to deliver valuable features as fast as possible. To handle this properly, what should the agile coach do?
Show answer and explanation
Correct answer: A
A team takes over a new project whose product carries a large amount of technical debt. Stakeholders know there is debt but do not understand how it affects delivery, and they still want valuable features quickly. The question is what the agile coach should do.
Technical debt that cannot be seen cannot be managed, but listing names alone does not explain its effect on delivery. First assess the delivery impact of the identified debt, then list the related paydown work in the Product Backlog. Stakeholders can then understand the impact, and the Product Owner can order debt and features together on one list. The answer is A.
Why the other options are wrong
- B. Raising story points across the board hides the problem: it does not explain why refactoring is needed and it distorts velocity data and damages forecasting.
- C. Technical debt is not necessarily all top priority. Its impact should be assessed and then it is ordered. Putting it all first could delay more valuable features.
- D. A separate refactoring plan given to stakeholders keeps the work outside the list. It is not transparent and bypasses the Product Owner's ordering.
Key takeaway Technical debt has to be put into the Product Backlog as explicit items so that it can be seen and ordered.
Variation If the stem instead says that the time spent fixing defects keeps growing during Sprints, the handling is still to assess the impact and then have the Product Owner put the paydown work in the list. It is not paid off in the background through overtime, and not by pausing all new features.
Something wrong with this question?
Example 2 Which statement about an Increment is correct?
A team uses Scrum to deliver value to customers in small, quick steps. Which of the following correctly describes the Increment in Scrum?
Show answer and explanation
Correct answer: D
The question asks for the correct description of the Increment in Scrum.
An Increment is the result that has actually been completed (it can be produced at any time during the Sprint and is inspected as a whole at the end). It must be usable and meet the Definition of Done, and it is the sum of the items completed in this Sprint and all earlier Increments. What the team set out to do at the start and what is finally done are not necessarily the same, so the Increment is based on what is actually done. A useful test is whether it can be given to users: items selected into the Sprint Backlog but not finished cannot count as part of the Increment, and only the part that meets the Definition of Done is added. The answer is D.
Why the other options are wrong
- A. The items selected at Sprint Planning are a plan or forecast and are not necessarily the same as what is actually completed in the end, so they are not the Increment.
- B. The task list is the result of breaking down Sprint Backlog items and is part of the plan. Tasks are a means of implementing the items and are not the result.
- C. The Sprint Goal is a one-sentence statement of what the Sprint aims to achieve. It is not the result the Sprint produces.
Key takeaway Increment = the result actually completed that meets the Definition of Done, added up Sprint by Sprint. Only items that meet the Definition of Done count toward the Increment, and half-finished work does not.
Variation If the question is whether a story that lacks only integration testing at the end of the Sprint counts toward the Increment, the answer is no: work that does not meet the Definition of Done goes back to the Product Backlog for future consideration. Added together, the Increments of several Sprints make up the product that is finally delivered.
Something wrong with this question?
Common traps
Common trap
- An Increment is not “how much was done” but “the part that is done and usable”. Anything that does not meet the Definition of Done does not count toward it.
- The items selected at the start of the Sprint are a plan (a forecast). The Sprint Goal is a one-sentence statement and is also the commitment attached to the Sprint Backlog, and the task list is the result of breaking the work down. None of the three is the Increment.
- An Increment that meets the Definition of Done must be usable and potentially releasable, but that does not mean it has already been delivered or released. The Product Owner works with the relevant stakeholders to decide the actual release timing and authorization on the basis of product value, following organizational governance.
- Technical debt does not disappear because nobody mentions it. Invisible debt cannot be ordered, and so it cannot be paid.
- Handling technical debt does not mean “put everything at top priority”, and it does not mean inflating story points to “reserve” time. First assess the impact, then have the Product Owner order it.
Key takeaways
Key point
- Increment = the items done in this Sprint that meet the Definition of Done + earlier Increments, and it must be usable.
- Every Sprint should produce an inspectable Increment. That it is potentially releasable is a technical matter; the actual release timing and authorization are decided by the Product Owner with the relevant stakeholders on the basis of value and organizational governance.
- Technical debt can come from deliberately adopting stopgap solutions to hit a deadline or from a lack of understanding; a change in requirements or the technical environment counts only when it exposes a shortcoming in the existing solution and creates extra repair cost. It is paid back later with extra effort, commonly through refactoring.
- Skipping tests and reviews to hurry is one common source of technical debt.
- Make technical debt visible: put it in the Product Backlog as items, assess the impact, then order it and pay it down.