What this chapter covers

Scrum has five events: the Sprint itself, plus four meetings inside it. They repeat at a fixed rhythm so the team plans, synchronizes, demonstrates and improves on a regular schedule. Most exam questions on this chapter ask either "which meeting is this activity done in?" or "this meeting has gone off track; what should happen?", so for every event focus on three things: when it happens, who attends, and what it produces. PMBOK 8 defines iteration planning, iteration review, the daily coordination meeting and the retrospective; in this chapter, which is about Scrum, we use the Scrum Guide names (Sprint Planning, Daily Scrum, Sprint Review, Sprint Retrospective) alongside them.

By the end of this chapter you should be able to do the following. Explain that a Sprint is a fixed-length timebox that is never extended and never changed in ways that endanger the Sprint Goal (scope can be renegotiated with the Product Owner where necessary). Name the three topics of Sprint Planning, say who defines the Sprint Goal, and say what the Developers base their selection of items on. Recognize the two common distortions of the Daily Scrum and correct them. Know that the Sprint Review shows only finished Increment and that the Product Backlog may be adjusted afterwards. Know that the Sprint Retrospective changes how the team works, and that its outcomes must become actionable improvements.

Lessons in this chapter

  • Lesson 1: The Sprint: a fixed-length timebox. Fixed length, ends on schedule, goal unchanged; unfinished items go back to the Product Backlog and are refined and re-estimated as needed; only the Product Owner can cancel a Sprint.
  • Lesson 2: Sprint Planning. Three topics: why the Sprint is valuable, what can be done, and how the work will get done (selecting items and breaking them into tasks are useful practices, and "claiming tasks" is not a mandatory step). The Product Owner proposes how the product could increase its value in the Sprint, and the whole Scrum Team collaborates to define the Sprint Goal. The Developers select items based on their capacity and form a forecast, weighing past performance (velocity can be a reference), current capacity and the Definition of Done. It includes a worked example that converts velocity and available person-days into a forecast (common exam practice).
  • Lesson 3: The Daily Scrum (daily coordination meeting). 15 minutes, with a structure chosen by the Developers (the three questions are a common exam practice). It focuses on inspecting progress toward the Sprint Goal, identifying impediments and adjusting the plan; time-consuming discussions continue after the meeting. The Scrum Master does not call on people or hand out work. Two common distortions and how to correct them.
  • Lesson 4: The Sprint Review. Demonstrate the finished Increment and get feedback; the Scrum Team and stakeholders inspect the outcome, discuss feedback and decide on follow-up adjustments. The timebox does not move, and only finished work is shown. After the review the Product Backlog may be adjusted.
  • Lesson 5: The Sprint Retrospective. After the Sprint Review and before the next Sprint Planning; it looks at how the team works. The Scrum Master is an equal participant. Action items should be specific and checkable, and usually have an owner.

Chapter map

The four meetings in a Sprint
EventWhenWhat it looks atOutput
SprintFixed length, one month or lessProducing a finished IncrementAn Increment that can be inspected
Sprint PlanningStart of the SprintWhat to do and how muchSprint Goal, Sprint Backlog
Daily ScrumEvery working day, 15 minutesProgress and impedimentsAn actionable plan for the next working day; the Sprint Backlog or task board is updated as needed
Sprint ReviewEnd of the SprintWhat was achieved, what has changed in the environment, how to adjust nextBased on feedback, the Product Backlog is adjusted if necessary
Sprint RetrospectiveAfter the Sprint ReviewHow the team works and what to change next timeActionable improvements

Study tips and practice

  • Memorize the table above. When a question asks which meeting something belongs in, first ask "when?" and "what is being looked at?".
  • Wording such as "too much pressure" or "overcommitted" points to Sprint Planning; "calling on people by name" or "discussing technical details" points to the Daily Scrum; "demonstrating results" or "customer feedback" points to the Sprint Review; "process problems", "falling velocity" or "keeps recurring" points to the Sprint Retrospective.
  • This is a key chapter in the agile material. Work through the lessons in order, doing the core questions of each lesson first and then the rest.

Lesson 1

The Sprint: A Fixed-Length Timebox

Lesson video

Lesson overview

Scrum has five events: the Sprint itself, plus four meetings inside it. The Sprint is the container for the other four, so this chapter starts with it. Exam questions about the Sprint come down to one concept: the timebox. The length is fixed, the Sprint ends when time is up, and the Sprint Goal does not change. Extending the Sprint, squeezing in work that endangers the goal, and quietly swapping the goal are all wrong. This lesson covers those rules, what to do with work that is not finished, and when a Sprint can be canceled. ECO: Process domain, Task 3 (Help ensure value-based delivery) and Task 8 (Plan and manage schedule). The next four lessons cover Sprint Planning, the Daily Scrum, the Sprint Review and the Sprint Retrospective in turn.

What a Sprint is

The Sprint is the heart of Scrum: a time-limited development cycle that Scrum fixes at one month or less, commonly 1 to 4 weeks, with the aim of producing a "done", usable, potentially releasable Increment. PMBOK 8 also notes that iterations in some agile methods are typically one to four weeks and end with a demonstration of results.

"Fixed" means that once a Sprint starts, its timebox does not change; it is not "somewhere between 1 and 4 weeks, whichever suits us". Teams usually keep a stable cadence. If the length needs to change, change it from the next Sprint onward, never in the Sprint already under way. This fixed length is the timebox: when time is up, the Sprint is not extended whether or not the work is done. Development work wraps up at the planned point, the Sprint Review and Sprint Retrospective take place within the timebox, and the Sprint ends when the Sprint Retrospective ends (the Sprint is the container for the other events). The benefit of a fixed rhythm is that the team settles into a pattern and forecasts become more reliable. Shorter Sprints get the Increment into stakeholders' hands sooner, so feedback arrives earlier and a wrong direction is noticed earlier.

Figure 1 The four meetings in a Sprint

The rules inside a Sprint

During the Sprint, no change is made that would endanger the Sprint Goal. Specifically:

  1. No extension. A customer wants a feature added to the current Sprint and asks whether the Sprint can run a few days longer. The answer is no. The new feature goes into the Product Backlog, where the Product Owner orders it, and is normally left for a later Sprint. If the Sprint Goal is not endangered, the Developers and the Product Owner may also negotiate the scope of the current Sprint. You do not stretch the Sprint to fit in more.
  2. No drifting from the goal. Halfway through the Sprint, a team member wants to use the remaining time for a rework that "might be useful in future". The Scrum Master should remind everyone to stay focused on the Sprint Goal.
  3. Surface problems early. When an impediment could stop the team reaching the Sprint Goal, bring it into the open early and transparently and ask the Scrum Master to help remove it. If scope needs adjusting, the Developers negotiate it with the Product Owner, and the relevant stakeholders are informed in proportion to the impact. Nothing is hidden, and the team does not simply push through with overtime.

Unfinished work and cancellation

Items not finished by the end of the Sprint are not part of the Increment. They return to the Product Backlog for future consideration, and the Product Owner reorders them. The team updates estimates where necessary, based on the remaining work and what has been learned (an unfinished item is partly done, so both the remaining effort and the team's understanding have changed; whether to split the item, re-estimate it on the remaining work, or keep the original estimate follows the team's agreed estimating rules). If unfinished items affect the Sprint Goal or keep recurring, find out why together with the team in the Sprint Retrospective and improve. Do not add extra working hours in the next Sprint, and do not dismiss it as a one-off.

A Sprint can be canceled before it ends, and only the Product Owner has that authority. The condition is that the Sprint Goal has become obsolete: for example, the business direction has changed, or the work in progress would only produce features users no longer need. Continuing valueless work is waste and should stop early; the backlog is then reorganized and a new Sprint planned. Because Sprints are short anyway, cancellations are uncommon.

Worked example: closing out a 2-week Sprint

A logistics team's Sprint starts on Monday and plans 5 stories totaling 28 points. By end of day on Friday of week 2, 4 stories totaling 23 points meet the Definition of Done. The remaining 5-point story still needs integration testing.

The team does not extend the Sprint by even a day. The Sprint Review goes ahead as scheduled and shows only the 4 finished stories. The 5-point story goes back to the backlog, the Product Owner reorders it, and the team updates the estimate based on the remaining work (the work before integration is done, so the updated estimate may be only 2 points). The Sprint's completed work is recorded as 23 points, not 28, and not a "compromise" figure such as 25.5.

Worked examples

Example 1 A customer wants to add a feature mid-Sprint and extend the Sprint

Question 1Example

The team is in the middle of the current Sprint and things are going well. One early morning, a customer representative calls and asks for an urgent meeting. You are a little surprised, because the customer is very happy with the features already developed. At the meeting he says he would like to add one more feature in this Sprint, and asks whether the Sprint can be extended by a few days for it. How should you answer?

Show answer and explanation

Correct answer: D

The team is in the middle of a Sprint and doing well. A customer representative asks to add one more feature in this Sprint and asks whether the Sprint can be extended. How should you answer?

In Scrum, the current Sprint is a fixed-length timebox and the team works toward the Sprint Goal. As more is learned, the Developers may clarify and renegotiate scope with the Product Owner, but the timebox is not extended. The new feature can be recorded in the Product Backlog and considered by priority in later Sprints, but it cannot be accommodated by extending the current Sprint. The customer's good mood is no exception. The answer is D.

Why the other options are wrong

  • A. The Sprint length is fixed, and whether to extend does not depend on the effort of the new feature. Assessing first and deciding afterward also implies that an extension is possible.
  • B. A timebox has no exception for “occasionally extending”. An important customer requirement should also go through backlog ordering and not change the Sprint length.
  • C. The Scrum Master's job is to uphold the rules and protect the team, with no authority to extend the Sprint for a new feature. Even if the Scrum Master agreed, the length would not change.

Key takeaway A Sprint is a fixed-length timebox: a new feature goes into the backlog and is not accommodated by extending the Sprint.

Variation If the team wants to extend by one day before the review to finish the last feature, the answer is the same: the timebox stays and unfinished work returns to the backlog. Only if “the Sprint Goal has lost its meaning” would the Product Owner consider canceling the Sprint.

Something wrong with this question?

Report an issue with this question

Example 2 A more important feature appears mid-Sprint; should the Sprint stop?

Question 2Example

The agile team on a smart-speaker project is in the middle of a Sprint. The Product Owner finds that a stakeholder who had little influence has become a key figure, and the feature he proposes is more important than the one being built in the current Sprint, but adding it now would endanger the established Sprint Goal. How should the team handle it?

Show answer and explanation

Correct answer: C

During a Sprint, a stakeholder becomes a key figure, and the feature he proposes is more important than the one being built. The team uses Scrum. The question asks how to handle it.

No change that endangers the Sprint Goal is made during a Sprint, so the team can focus on the goal and deliver an Increment. The Product Owner immediately records the new feature in the Product Backlog and reorders it, and at the next Sprint Planning the team can select the highest-value work at that time. So the team should complete this Sprint as normal and update the ordering accordingly. The answer is C.

Why the other options are wrong

  • A. Adding a new feature midway would hit the Sprint Goal, which would then be at risk of being missed, and the team could not tell whether it can still finish.
  • B. In Scrum, canceling a Sprint is considered only when the Sprint Goal becomes obsolete. Here only a higher-priority feature has appeared, and the original Sprint Goal still stands.
  • D. Pulling two people off to work on a feature outside the Sprint likewise starts a separate effort inside the Sprint, weakening the ability to meet the Sprint Goal and bypassing the ordering.

Key takeaway A change in priority does not interrupt a Sprint in progress: put it in the Product Backlog and select it at the next Sprint Planning.

Variation If the change makes this Sprint's results completely worthless, the Product Owner assesses whether to cancel the Sprint; merely “more important” is not a reason to cancel.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The Sprint length is "one fixed value", not "flexible between 1 and 4 weeks". A Sprint also cannot be extended for a new feature or out of goodwill toward the customer.
  • If work is not going to be finished, you cannot extend the timebox. Surface and handle impediments promptly; the Developers may negotiate scope with the Product Owner as long as the Sprint Goal is not endangered, and items that have not met the Definition of Done at the end go back to the Product Backlog. Overtime is not a standard remedy, and whether to change staffing depends on the team's circumstances.
  • Only the Product Owner can cancel a Sprint. The team, the Scrum Master and the project manager have no authority to stop one on their own.
  • The reason for canceling is that the Sprint Goal has lost its meaning, not "we are behind schedule" or "someone wants to change direction".
  • After unfinished items return to the backlog, update their estimates on the remaining work where necessary. Do not assume the old estimate still applies, and do not record "half" the points.

Key takeaways

Key point

  • A Sprint is a fixed-length event of one month or less, commonly 1 to 4 weeks, and it ends on time.
  • The Sprint Goal does not change. New ideas go into the Product Backlog and are ordered by the Product Owner, normally for a later Sprint. If the Sprint Goal is not endangered, the Developers may negotiate the scope of the current Sprint with the Product Owner, but the timebox is never extended.
  • Unfinished items are not part of the Increment. They return to the backlog, the Product Owner reorders them, and estimates are updated if necessary.
  • Only the Product Owner can cancel a Sprint, and only when the Sprint Goal has lost its meaning.
  • When something threatens the Sprint Goal, surface it early and transparently, negotiate scope changes with the Product Owner, and inform the relevant stakeholders in proportion to the impact.

Lesson 2

Sprint Planning

Lesson video

Lesson overview

Sprint Planning is the starting point of the Sprint. It decides what the Sprint will deliver, how, and how much. Exam questions about it come in two kinds: "which meeting does this belong in?" and "the team has forecast too much and is under pressure; what now?". The key to the second is who decides how much to select, and on what basis. This lesson covers the three topics of the meeting, the division of roles, the basis for judging capacity, and a complete worked example that converts velocity and available person-days into a forecast. ECO: Process domain, Task 8 (Plan and manage schedule) and People domain, Task 3 (Lead the project team).

What the meeting does

PMBOK 8 defines iteration planning as "a meeting to clarify the details of the backlog items, acceptance criteria, and work effort required to meet an upcoming iteration commitment." The Scrum Guide has Sprint Planning address three topics. Why is this Sprint valuable? (The Product Owner proposes how the product could increase its value, and the whole Scrum Team collaborates to define the Sprint Goal.) What can be done this Sprint? (The Developers select items after discussion with the Product Owner, based on past performance, current capacity and the Definition of Done.) How will the chosen work get done? (The Developers decide this themselves and the result is the Sprint Backlog.) Teaching materials often turn this into three actions. These are practices a team may adopt, not mandatory steps:

  1. Select stories: the Product Owner presents the high-priority content, and the team usually considers the highest-ordered items that are clear enough, selecting them according to its capacity.
  2. Break down tasks: the selected stories are split into concrete tasks, forming the Sprint Backlog.
  3. Claim tasks: team members volunteer for tasks (they need not claim each one in the meeting).

The outputs are the Sprint Goal, the Sprint Backlog, and a shared understanding within the team of what will be delivered. The team also agrees in this meeting how the finished work will be tested. When selecting stories, the main basis is the ordering of the Product Backlog (value and priority) and the Sprint Goal, together with capacity, dependencies and the Definition of Done. It is not by difficulty, not by members' interests, and not to fill the Sprint up to the brim.

Who decides

The Product Owner proposes how the product could increase its value in this Sprint, and the whole Scrum Team collaborates to define the Sprint Goal. The Developers assess their own capacity, discuss with the Product Owner, and select the items and make a forecast (what is committed to is the Sprint Goal, not a fixed number of items). If the team finds that the work exceeds the Sprint's capacity, it tells the Product Owner immediately. The Scrum Master takes part as a member of the Scrum Team, ensures the meeting is positive and productive and stays within the timebox, and facilitates where needed so the meeting stays on the three planning topics. Technical discussion should serve the goal of producing an actionable plan; discussion that goes too deep and is unrelated to this planning can be scheduled separately. The attendees are the Scrum Team: the Product Owner, the Scrum Master and the Developers.

The meeting is timeboxed. For a one-month Sprint it lasts at most 8 hours; for shorter Sprints it is usually shorter, and the team sets a reasonable timebox.

How to judge how much the team can do

To judge capacity, the actual velocity of past Sprints is an important reference. In this lesson's example, velocity is the sum of story points completed and accepted in one Sprint, though in practice other consistent units of work can be used. Velocity swings more in the early Sprints and stabilizes later. Then consider this Sprint's capacity, the Definition of Done, the mix of skills and dependencies, and anything special about this Sprint, such as vacations or training. Overtime does not count as capacity, and the Sprint should not be filled up just to look good.

Worked example: converting velocity and available person-days into a forecast

A team of 5 has a 10-working-day Sprint. The velocity of the last three Sprints was 18, 20 and 22, and the Product Owner would like 30 points this time.

Step 1: baseline velocity. Assume the previous three Sprints also had the same 5-person team, 10 working days and full attendance (50 person-days each). Average velocity = (18 + 20 + 22) ÷ 3 = 20 points.

Step 2: available person-days. Full strength is 5 × 10 = 50 person-days. In this Sprint, one person is on vacation for 3 days and one is in training for 1 day, which is 4 person-days fewer, so 46 person-days are available.

Step 3: scale (a simplified, commonly used forecasting method, not a prescribed formula). Available ratio = 46 ÷ 50 = 0.92, so the forecast ≈ 20 × 0.92 = 18.4, rounded to about 18 points.

Step 4: check. 18 points ÷ 46 person-days ≈ 0.39 points per person-day. The average velocity converts to 20 ÷ 50 = 0.40 points per person-day. The two agree, which only confirms that the linear scaling is arithmetically consistent and does not independently prove the forecast is reliable. The team still has to make its final forecast taking into account its skill mix, dependencies and the real state of the backlog.

Conclusion: the team tells the Product Owner that it forecasts about 18 points for this Sprint and selects only about 18 points of items. The other 12 points stay in the backlog, and the team does not take them on just because "leadership wants 30 points".

If planning reveals a dependency on another team, tell that team about it and confirm that it has put the corresponding work into its own plan. Do not demand that it start immediately, and do not merge the two teams.

Worked examples

Example 1 Team members feel pressure from over-forecasting

Question 1Example

The self-organizing team on an online education platform has consistently delivered its forecast work, and the project is critical to the company. At a Sprint Retrospective, the project manager finds that most members feel heavy pressure because their forecasts have included more work than they can sustainably complete. What should the project manager do?

Show answer and explanation

Correct answer: B

A self-organizing team has consistently delivered its forecast work. At a Sprint Retrospective the project manager finds that most members feel heavy pressure because their forecasts have been too aggressive. What should the project manager do?

The source of the pressure is that the forecast amount exceeds what the team can sustain. At Sprint Planning the developers select and forecast the work they can complete according to their own capacity, so the project manager should support the team at the next Sprint Planning so that it forecasts only the amount of work it is confident of delivering, which lets the team keep a sustainable pace and solves the problem at the root. This is consistent with the rules of Sprint Planning: the developers assess their own capacity and select the work they expect to complete in the Sprint, while the Product Owner explains the goal and the ordering, and others cannot set the amount for the team. The answer is B.

Why the other options are wrong

  • A. Adding people takes time to bring up to speed and does not necessarily raise output at once, and it does not change the root cause of the overly aggressive forecasts.
  • C. Stress-relief activities and team building can help, but they treat the symptom and not the cause: the pressure comes from the forecast amount, so the amount must be controlled at planning time.
  • D. Staggering vacations has nothing to do with the source of the pressure, and vacations should be agreed by the team itself, not something for the project manager to require.

Key takeaway If the pressure comes from over-aggressive forecasts: forecast only what can be delivered when planning.

Variation If the stem were changed to “the Product Owner demands 30 points while the team's velocity is about 20”, the team should explain by its velocity that only about 20 points can be completed in this Sprint, with the rest staying in the backlog.

Something wrong with this question?

Report an issue with this question

Example 2 Judging Sprint capacity: what else to consider besides vacation and training

Question 2Example

A fitness-band team has completed two Sprints. The technical environment and operating procedures were set up in the first two Sprints, and the team is now doing Sprint Planning for the third. Besides members' vacations and various training, what else should the team consider when assessing the Sprint's capacity?

Show answer and explanation

Correct answer: D

The team has completed two Sprints, the environment and procedures are already in place, and it is planning the third. The question asks what to consider, besides vacations and training, when assessing Sprint capacity.

Sprint Planning estimates how much can be done in this Sprint, and the velocity actually achieved in past Sprints is one important source of evidence; the team also considers current capacity factors such as vacations and training, the Definition of Done, and the work itself. Velocity comes from real data and is more reliable than wishes. Velocity is commonly measured from story points completed in a Sprint that meet the Definition of Done. It may fluctuate early and may become more stable as the team gathers data, so it can inform the Developers' forecast without guaranteeing future capacity. So the answer is D.

Why the other options are wrong

  • A. Agile stresses a sustainable pace and does not count overtime as part of capacity.
  • B. Story points are a relative estimate made jointly by the team, and there is no need to determine who will do the work before points can be assigned.
  • C. This preparation work was completed in the first two Sprints and is no longer a factor to deduct when assessing capacity now.

Key takeaway To assess Sprint capacity, past velocity is one important source of evidence, considered together with current capacity, the Definition of Done, and other relevant factors.

Variation If the velocities of the first two Sprints were 18 and 22 and one person is on vacation for 3 days in this Sprint, take an average of about 20 points as the reference and adjust it down for the vacation, giving a forecast slightly under 20 points. You can also do a simplified conversion by the proportion of available person-days (only a rough guide, not a prescribed formula). Velocity from just two Sprints can also fluctuate.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • How much to select is forecast by the Developers based on their own capacity. It is not decided by the Product Owner, the project manager or the Scrum Master.
  • Stories are selected by value and priority, not by difficulty or personal interest, and not to fill the Sprint to the top.
  • If pressure comes from over-forecasting, select only work the team is confident of finishing during planning. Do not arrange stress-relief activities, add people or stagger vacations.
  • Planning is about why the Sprint is valuable, what to do and how to do it. It is not necessary to settle each person's assignments in the meeting, and the team should not get lost in technical detail unrelated to planning. If the meeting drifts, the Scrum Master brings it back.
  • An environment that was already set up in earlier Sprints is not counted again in this Sprint's capacity assessment. Past performance, including the velocity of past Sprints, is an important reference alongside current capacity and the Definition of Done.

Key takeaways

Key point

  • Sprint Planning addresses three topics: why the Sprint is valuable, what can be done, and how the chosen work will get done. As a common exam practice, a team may select stories, break them into tasks, and let members volunteer for tasks. The outputs are the Sprint Goal and the Sprint Backlog.
  • The Product Owner proposes the value direction and is responsible for ordering the backlog. The Scrum Team defines the Sprint Goal together, and the Developers forecast and decide how many items to select.
  • Past performance, including velocity when the team uses it consistently, is one important reference for assessing capacity. Forecast jointly from that evidence, upcoming capacity (vacation, training and similar factors), the Definition of Done, skill mix, dependencies and backlog readiness.
  • For a one-month Sprint, Sprint Planning lasts at most 8 hours; for shorter Sprints it is usually shorter.
  • Pressure caused by over-forecasting is solved at planning time by selecting only work the team is confident of finishing.
  • When you find a cross-team dependency, tell the other team and confirm it has included the work in its plan.

Lesson 3

The Daily Scrum (Daily Coordination Meeting)

Lesson video

Lesson overview

The Daily Scrum is the most frequent meeting in the Sprint, and one of the most heavily tested. The background of the questions is almost always "the meeting has gone off track": the Scrum Master has turned it into a roll call that hands out work, a few people have turned it into a technical discussion, or the team finds it annoying and wants to cancel it. This lesson covers the purpose of the meeting, its rules, the three questions, and how to correct the two common distortions. ECO: People domain, Task 3 (Lead the project team) and Business Environment domain, Task 4 (Remove impediments and manage issues). The previous lesson covered Sprint Planning, and the next covers the Sprint Review.

What it is and why it is held

PMBOK 8 calls it the daily coordination meeting: "a brief, daily collaboration meeting in which the team reviews progress from the previous day, declares intentions for the current day, and highlights any obstacles encountered or anticipated. Daily coordination meetings are a key tool used to enable the project team to self-direct and self-manage project work, particularly in agile approaches to project management. The primary goal is to increase visibility, foster collaboration, and ensure that the team is aligned and moving forward effectively."

The meeting used to be commonly called the daily standup, because standing up keeps it from running long. Standing is only a habit that helps control the length; the Scrum Guide does not require it, and the substance has not changed. Both names can appear on the exam, and PMBOK 8 says daily coordination meeting. Its purpose is to let the team synchronize information and surface impediments early, so when information is unevenly shared or decisions are slow, use the Daily Scrum to synchronize and expose problems.

Rules and the three questions

A common exam practice is for each Developer attending to answer three questions. (The 2020 Scrum Guide no longer prescribes this structure; the Developers may choose the structure and techniques, as long as the meeting focuses on progress toward the Sprint Goal and produces an actionable plan for the next working day. PMBOK 8 also mentions sharing what was accomplished the previous day, the plan for today and any obstacles.)

  • What did I do yesterday to help the team meet the Sprint Goal?
  • What will I do today?
  • Is anything blocking me or the team?

The rules of the meeting:

  1. It lasts 15 minutes or less, at the same time and place every working day (Scrum Guide rule). The team agrees the specific time itself.
  2. The Developers manage the meeting themselves, and the team decides its structure and how it is facilitated (it does not have to go round in turn). The Scrum Master ensures the event takes place and stays within the timebox, but should not turn it into a roll call or a work-assignment meeting.
  3. It focuses on synchronizing, inspecting progress and adjusting the plan for the day. Short, necessary discussion and decisions are fine. Time-consuming technical analysis or problem solving is left for the people concerned to arrange separately after the meeting (common exam practice: when the question says the meeting has "turned into a technical discussion", choose to take it offline after the meeting).
  4. The Daily Scrum is an event for the Developers. The Product Owner or Scrum Master takes part as a Developer only if they are actively working on Sprint Backlog items. Whether others are invited is for the team to decide as needed, and they must not disrupt the meeting (on the exam, stakeholders who sit in usually do not speak).
  5. Update the Sprint Backlog promptly for any adjustments that come out of the meeting. The task board, burndown chart, impediment list or issue log are updated according to whatever management method the team actually uses.

Two distortions and their corrections

It becomes a status-report meeting. The Scrum Master or project manager arrives with a prepared task list, asks each person for progress one by one, and assigns new tasks on the spot. This is command-and-control. Members report up to the leader instead of synchronizing with the team, so their reports are naturally perfunctory. Correction: the Scrum Master should encourage self-organization and let members synchronize with each other.

It becomes a discussion meeting. As soon as someone raises an impediment, everyone starts analyzing solutions right there, the meeting overruns, and the others wait around. Correction: the Scrum Master suggests pausing the discussion, notes the impediment, and lets the next person speak, with the discussion held after the meeting by the people concerned. The same goes for a major risk: say it at the Daily Scrum and hold a separate session afterwards for the details.

What if team members feel the daily meeting wastes development time, arrive late, or chat about unrelated topics? Do not cancel it, and do not have a manager impose rules or penalties on their own. Instead, involve the team in improving the format of the meeting and explain clearly how it helps the team find impediments earlier.

Worked example: a Daily Scrum for a gas-pipeline monitoring team

The team has 6 people. With six people and a 15-minute limit, an equal split would be about 2.5 minutes each, though the meeting does not need equal speaking time. The tester says: "Yesterday I found that meter-reading data synchronization occasionally loses data. Today I'm continuing to track it down, but I'm blocked because the logs are incomplete." A developer immediately says, "I think it's a queue problem", and the two start discussing it. Before long 5 minutes have gone, and 4 people have not yet spoken.

The Scrum Master's response: "Let's note the impediment, and you two can talk separately after the meeting." It is recorded in the issue log and the meeting continues. Everyone finishes within 15 minutes. After the meeting the two stay behind and spend 20 minutes pinpointing the cause. Check: 5 minutes are already used, and the remaining 4 people at about 2 minutes each take 8 minutes, a total of 13 minutes. If the opening and closing together take no more than 2 minutes, the total is still within 15 minutes. If the two had been allowed to carry on, the timebox would have been exceeded.

Worked examples

Example 1 The Scrum Master calls on people from a task list and assigns the day's work

Question 1Example

A new member joins the project of a city gas-pipeline monitoring platform. After attending a few Daily Scrums, he notices that every Daily Scrum ends within 15 minutes, but the Scrum Master always arrives with a task list prepared in advance, asks the corresponding developers one by one about their progress, and then assigns everyone new tasks for the day on the spot. Is this kind of Daily Scrum appropriate?

Show answer and explanation

Correct answer: A

On a Scrum project, every Daily Scrum ends within 15 minutes, but the Scrum Master arrives with a prepared task list, asks for progress one by one and assigns the day's tasks on the spot. The question asks whether such a meeting is appropriate.

The Daily Scrum is the Developers' own synchronization meeting: members synchronize on progress and on the obstacles they meet. The Scrum Master's role is that of a servant leader, who fosters the team's self-organization and does not monitor status or hand out tasks. Finishing on time shows only that the timebox has not been broken; the content and the method are still wrong, so it is not appropriate. The answer is A.

Why the other options are wrong

  • B. Keeping track of everyone's progress and assigning tasks is command-and-control, the opposite of the Scrum Master's servant-leader role.
  • C. Keeping the meeting short (typically no more than 15 minutes) is a requirement of the meeting, not the whole of the Scrum Master's responsibility. You cannot call it appropriate just because it is punctual.
  • D. PMBOK 8 says the daily coordination meeting is brief and focused, typically no more than 15 minutes, so it should not be stretched at will, and certainly should not become a place to hand out tasks. This option also fails to identify the role problem.

Key takeaway The Daily Scrum is the team's own meeting: the Scrum Master fosters self-organization and does not direct or assign work.

Variation If the stem had members reporting status one by one to the project manager, the problem is the same: the meeting has become a status report, and it must go back to members synchronizing with each other.

Something wrong with this question?

Report an issue with this question

Example 2 A member mentions a technical impediment and everyone starts discussing solutions on the spot

Question 2Example

At a Daily Scrum, a developer mentions that he is stuck on a technical impediment, and several other members immediately start discussing how to solve it. What should the Scrum Master do at this point?

Show answer and explanation

Correct answer: D

At a Daily Scrum, a developer says he is stuck on a technical impediment and several others immediately begin discussing solutions. The question asks what the Scrum Master should do.

The daily coordination meeting is brief and focused (PMBOK 8: typically no more than 15 minutes) and is for stating obstacles, not for detailed technical discussion in the meeting. The details of a technical impediment take up a lot of time and leave the other members waiting. The Scrum Master should suggest pausing the discussion, note the impediment, carry on with the meeting, and have the people concerned work it out afterward. The answer is D.

Why the other options are wrong

  • A. Letting everyone discuss until a solution is found breaks the timebox and the rules of the meeting, and crowds out the other members' synchronization.
  • B. Explaining the meaning of the meeting again does not solve the problem of the discussion eating time and does nothing to correct the situation at hand.
  • C. Stopping the whole meeting is too abrupt, since other members have not yet finished synchronizing. First pause the discussion and continue the meeting, and work it out afterward.

Key takeaway The Daily Scrum focuses on progress and impediments, and detailed discussion is taken offline for after the meeting.

Variation If a member mentions at the meeting that a major risk has been identified, the handling is the same: say it at the meeting, take the details to a separate session afterward, and do not discuss it on the spot or leave it to the Sprint Review.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The Daily Scrum is for synchronizing and surfacing impediments. It is not for assigning tasks, not for reporting to a manager, and not for detailed, time-consuming problem analysis (necessary short discussion and quick decisions can be done in the meeting).
  • The Scrum Master makes sure the meeting takes place and may facilitate where needed, but does not call on people or hand out work, and does not turn the meeting into a roll-call report. The Developers manage the meeting themselves and decide its structure and techniques.
  • Staying within 15 minutes does not by itself make a meeting a good one. The form can be compliant while the content is wrong.
  • When the team does not value the meeting, involve the team in improving it. Do not cancel it, force it or punish people. The team agrees the meeting time itself.
  • When a major risk or technical impediment comes up, raise it in the meeting and take the details offline afterward. Do not expand on it on the spot.

Key takeaways

Key point

  • The Daily Scrum: once every working day, 15 minutes or less, same time and place, managed by the Developers themselves.
  • The three questions: what did I do yesterday, what will I do today, is anything blocking us.
  • In the meeting, the focus is on synchronizing and adjusting the plan. Time-consuming discussion and problem solving are arranged separately afterward.
  • The Scrum Master encourages self-management and does not call on people or hand out work. The Product Owner or Scrum Master attends as a Developer when working on Sprint Backlog items.
  • After the meeting, update the Sprint Backlog according to the team's way of working, and update the task board, burndown chart and issue log as needed.
  • When the team does not value the meeting, involve the team in improving it. Do not cancel or force it.

Lesson 4

The Sprint Review

Lesson video

Lesson overview

The Sprint Review takes place near the end of the Sprint. It is used to inspect the Increment produced in the Sprint and to get feedback from stakeholders. It is a frequently tested meeting, and typical question types include: at which meeting should results be shown, how to show items that are not finished, what to do if the Product Owner is absent, and what to do if the customer's evaluation is lukewarm. This lesson works through each of these. ECO: Process domain, Task 3 (Help ensure value-based delivery) and People domain, Task 4 (Engage stakeholders). The previous lesson covered the Daily Scrum, and the next covers the Sprint Retrospective.

What it is

PMBOK 8 describes the Sprint review as "a collaborative review session where the team demonstrates the work that was completed during the sprint to stakeholders and solicits their feedback", and the iteration review as "a meeting held at the end of an iteration to demonstrate the work that was accomplished during the iteration." The team demonstrates the finished Increment and answers questions (answering questions is common exam practice), and the purpose of the demonstration is to get feedback and promote collaboration. The attendees are the Scrum Team and internal and external stakeholders.

The meeting flows roughly in four steps (common exam practice): the Product Owner first summarizes the Sprint Goal and what was completed; the team demonstrates the Increment; the group discusses it with stakeholders; and follow-up is adjusted according to the feedback. The team confirms the Increment against the Definition of Done, and the Product Owner and stakeholders inspect the results in the review and discuss the feedback and follow-up adjustments (the review is not an acceptance, approval or release gate: whether the Increment is “Done” is judged against the Definition of Done, while the Product Owner may confirm whether items meet their acceptance criteria; an Increment may be released before the Sprint Review). For a two-week Sprint the review is usually shorter, and for a one-month Sprint it lasts at most 4 hours (Scrum Guide). The review is also a timeboxed event.

Rules for the review

Center the review on the Done Increment. Work presented as part of the Increment must meet the Definition of Done. Suppose a small amount of testing is still outstanding on the last day of the Sprint. The timebox cannot be extended, and the review cannot be postponed because of it. The team presents the completely finished functionality as the Increment, while unfinished work is not part of the Increment and returns to the Product Backlog. Per the Scrum Guide, a Product Backlog item that does not meet the Definition of Done cannot be released or even presented at the Sprint Review; the team can explain what was not finished and why.

Demonstrate for real. The review is not a progress briefing. Do not just talk without demonstrating, and do not spend a lot of time on technical explanation. If stakeholders cannot see the real Increment, they cannot give useful feedback. If two reviews in a row overrun because of technical explanations, the Scrum Master should coach the Product Owner and the team to focus the demonstration on value. The answer is not to lengthen the timebox, and not to shorten the Sprint.

The Product Owner belongs to the Scrum Team and should attend the review. The Product Owner is accountable for product value and for the ordering of the Product Backlog. A scheduling conflict should be resolved early so that the Product Owner can attend. If the Product Owner is unexpectedly absent, the Scrum Master helps the team hold an effective review within the Sprint timebox. Another stakeholder, or the Product Owner of another project, cannot be substituted to take over the role. (The Scrum Guide has no rule that an absence means rescheduling, and postponing the review would break the fixed rhythm.) If the customer and the Product Owner disagree about acceptance, first clarify on the basis of the Definition of Done, the acceptance criteria and the established decision authority. The Product Owner manages and orders the Product Backlog but cannot in every case replace the customer or the party authorized to accept.

The outcome of the review

The feedback and the adaptations that come out of the review may lead the Product Owner to adjust the Product Backlog and its ordering. (The Scrum Guide says the backlog "may also" be adjusted to meet new opportunities; not every review must produce a revised list.) Feedback may turn into changes in later priorities. If the customer rates the Increment poorly, first analyze why. If the feedback affects product value or requirement priority, the Product Owner then adjusts the Product Backlog and its ordering. If it comes from communication, quality or expectation gaps, take the corresponding measures. The answer is not to keep the original ordering and wait until after release, and not to promise a new feature on the spot or cut the delivery. The content of the current Sprint is not changed at will because of review comments.

Worked example: 30 minutes before the review

It is the last day of a two-week Sprint. The plan was 5 stories totaling 26 points, and one 3-point story still lacks one small test. The team says the test can be done today, but the Sprint Review starts in 30 minutes.

What to do: do not extend the Sprint and do not cancel the review. At the review, show only the 4 stories that are done (23 points). Say honestly that the 3-point story is not finished, and it goes back to the backlog. Check: 26 − 3 = 23, which matches the points shown. After the review, the team takes the feedback into the Sprint Retrospective and finds out why the missing test was only discovered on the last day.

Worked examples

Example 1 You want to show a finished work product to stakeholders; when?

Question 1Example

Your team is developing an inventory system for a supermarket chain. After the first Sprint has completed several features, you want the team to show stakeholders the work products completed to achieve the Sprint Goal. When should they be shown?

Show answer and explanation

Correct answer: B

On a project, the first Sprint has completed several features, and you want the team to show stakeholders the work products completed to achieve the Sprint Goal. When should they be shown?

The Sprint Review is held near the end of the Sprint. The Scrum Team presents its results to key stakeholders, and together they inspect the Sprint outcome and progress toward the Product Goal, consider changes in the environment, and determine useful adaptations; the Product Backlog may be adjusted accordingly. Increments that meet the Definition of Done may be presented, but the review is a working session and should not be limited to a demonstration. So the answer is B.

Why the other options are wrong

  • A. A weekly update meeting with the customer is not an event prescribed by the agile framework and is not designed for demonstrating the Sprint's Increment, so it cannot replace the review.
  • C. The Sprint Retrospective is for the team to look back at how it works and improve the process. It is aimed at the team internally and is not a meeting for showing results.
  • D. The Daily Scrum is a 15-minute progress synchronization that inspects progress toward the Sprint Goal. It is not an occasion for demonstrating results.

Key takeaway The Sprint Review inspects the Sprint outcome and determines future adaptations, including presenting completed Increments.

Variation If the question asked what to do when a customer proposes an urgent new feature at the review, the answer is to record it in the Product Backlog and discuss it at the next Sprint Planning, not to change the current Sprint on the spot.

Something wrong with this question?

Report an issue with this question

Example 2 Last day of the Sprint, review starts in 30 minutes, testing is unfinished

Question 2Example

You are the Scrum Master of a team in a two-week Sprint. Today is the last day, and some small testing tasks remain unfinished. The team says the testing can be finished today, but the Sprint Review is scheduled to start in 30 minutes. What should the team do next?

Show answer and explanation

Correct answer: A

On the last day of a two-week Sprint, some small tests are unfinished. The team says they can be done today, but the Sprint Review starts in 30 minutes. What should the team do next?

A Sprint is a timebox of fixed length that cannot be changed at will once begun, and the review should be held within this Sprint, so the Sprint is not extended and the review is not canceled to wait for unfinished tests. Only work meeting the Definition of Done can be presented as part of the Increment, so the team presents the fully completed features as the Increment and transparently identifies the unfinished testing work; unfinished items return to the Product Backlog to be refined or re-estimated further as needed. This keeps the timebox and also keeps transparency. The answer is A.

Why the other options are wrong

  • B. Once a Sprint has started it cannot be extended. The timebox is a basic constraint of Scrum and cannot be changed for a bit of testing.
  • C. A feature whose testing is unfinished does not meet the Definition of Done and cannot be presented as part of the Increment at the Sprint Review; presenting it as completed work would undermine transparency.
  • D. The Sprint Retrospective comes after the review and is for improving the process. It cannot replace the review and cannot be moved earlier.

Key takeaway The timebox does not move and the review is held as planned: present Done work as the Increment, transparently identify unfinished work, and return unfinished items to the Product Backlog.

Variation If the Product Owner is unexpectedly absent, the review is still held within the timebox, and the team shows work that meets the Definition of Done and collects stakeholder feedback; the review is not a formal acceptance gate; product decisions that need that person can be synchronized afterward. If the customer's rating at the review is lukewarm, analyze why and reorder the later backlog accordingly.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The meeting for showing results is the Sprint Review, not a weekly update meeting, the Sprint Retrospective or the Daily Scrum.
  • Only work meeting the Definition of Done can be presented as part of the Increment. Unfinished work is not presented; the team can explain its status, and it returns to the Product Backlog. The review must not turn into a progress briefing.
  • The timebox does not move: do not extend the Sprint to make the demonstration complete, and do not cancel the review to hold the Sprint Retrospective first.
  • If the Product Owner is absent, do not find someone to take over the role. Resolve the conflict early, and the Scrum Master makes sure the review proceeds effectively within the timebox. If there is disagreement about acceptance, first clarify it on the basis of the Definition of Done and the established authority.
  • Feedback may lead the Product Owner to adjust the Product Backlog and its ordering. It does not change the current Sprint at will.

Key takeaways

Key point

  • The Sprint Review is held at the end of the Sprint to demonstrate the Increment and get stakeholder feedback.
  • Attendees: the Scrum Team plus internal and external stakeholders. Whether the Increment is done is judged against the Definition of Done, and the group inspects the results and discusses follow-up adjustments.
  • Only work meeting the Definition of Done belongs to the Increment and can be presented; unfinished items are not presented and return to the backlog.
  • For a one-month Sprint the review lasts at most 4 hours (Scrum Guide), and usually less for shorter Sprints. The review is a timeboxed event and is not postponed because work is unfinished.
  • Review feedback may lead the Product Owner to adjust the Product Backlog and its ordering.
  • The Sprint Review looks at what was done; the Sprint Retrospective looks at how the team works.

Lesson 5

The Sprint Retrospective

Lesson video

Lesson overview

The Sprint Retrospective is the last meeting in Scrum and a frequently tested one. When the team's velocity is falling, rework is rising, the process is cumbersome or the same problem keeps appearing, the answer very often points to "analyze it with the team in the Sprint Retrospective". This lesson covers its place and purpose, how to run it, why its results must be actionable, and puts the four meetings of this chapter side by side for comparison. ECO: Business Environment domain, Task 6 (Continuous improvement). The previous lesson said that the review looks at what was done; this lesson says that the retrospective looks at how the team works.

Position and purpose

The retrospective comes after the Sprint Review and before the next Sprint Planning, usually on the last day of the Sprint. PMBOK 8 says: "A retrospective is a regularly occurring workshop in which participants explore their work and results in order to improve both the process and product," conducted frequently throughout the project, "at minimum, at the end of each iteration". PMBOK 8 also says that closing work should include holding retrospectives to reflect on the iteration and/or release, identifying lessons learned and opportunities for improvement in future work.

The review looks at "what was done"; the retrospective looks at "how we work". It answers three questions: what went well in this Sprint, what did not, and what should change in the next Sprint. On the exam, these questions usually concern process, collaboration, quality, estimating and the meetings themselves, not the product scope or particular features.

How to run it

The whole Scrum Team attends; people outside the team usually attend only if invited. For a one-month Sprint the retrospective lasts at most 3 hours (set by the Scrum Guide); for shorter Sprints it is usually correspondingly shorter. There are roughly three steps: review what went well and what did not, identify what could be improved, and decide which improvements to put into practice (suitable ones can go into the next Sprint).

For people to speak honestly, you need a safe atmosphere: focus on the issue, not the person, with no blame and no judgment. To help the team recall what happened across the whole Sprint, you can use an event timeline or an emotion curve to build a shared picture. The Scrum Master is an equal participant in the retrospective: like the other members, they identify areas that could be improved and help make the improvement plan, while helping the team understand and make good use of the rules of the meeting, such as the timebox. They are not there to relay requirements from stakeholders, nor to answer stakeholders' questions about the Increment.

Results must be actionable

The results should be actionable: clear, specific improvement measures, with owners assigned to carry them out, and with priority given to implementing the most impactful improvements as soon as possible. Improvements that can be completed in the next Sprint can be added to the next Sprint's plan or Sprint Backlog. If efficiency has not improved after several retrospectives, or the same problem persists across several Sprints, check whether the agreed improvement actions were implemented, analyze with the team why results did not improve, and coach follow-through. Merely increasing meeting frequency usually does not address the root cause.

A final retrospective is also held when the project closes. Even with no further Sprints, its value is to leave useful information for future projects.

What each of the four meetings looks at

MeetingWhenWhat it looks atWho attends
Sprint PlanningStart of the SprintWhat to do and how muchScrum Team
Daily ScrumEvery working dayProgress toward the Sprint Goal, the plan for the day, and impedimentsDevelopers (the Product Owner or Scrum Master attends as a Developer if working on Sprint Backlog items)
Sprint ReviewEnd of the SprintWhat was achieved, what has changed in the environment, how to adjust nextScrum Team plus stakeholders
Sprint RetrospectiveAfter the Sprint ReviewHow the team works and what to change next timeScrum Team

Worked example: the conclusion of a retrospective

An e-commerce team found that code became unstable after merging, in two Sprints in a row. In the retrospective the team looked back over a timeline and found the cause: "there is no uniform automated check before commit".

The improvement action: in the next Sprint one Developer will be responsible for adding automated checks to the commit process, with the finish criterion that the automated checks cover 70% of code modules (or that all merge requests go through the automated check). The team's Definition of Done gets one more line, "automated check passed before commit". At the next retrospective the result is checked: unstable merges fell from 6 in the last Sprint to 1, which shows the improvement worked. The key is that the action is specific, has an owner, and can be verified.

Worked examples

Example 1 The Scrum Master's role in the Sprint Retrospective

Question 1Example

An agile team is developing an online medical-appointment platform. The work of the sixth Sprint is done, and stakeholders rated the features delivered in this Sprint very highly. The team will hold a Sprint Retrospective on Tuesday to inspect itself. As the Scrum Master, what is your role in the meeting?

Show answer and explanation

Correct answer: B

An agile team has completed its sixth Sprint, and stakeholders rated it very highly. The team will hold a Sprint Retrospective on Tuesday, and the question asks what the Scrum Master's role in the meeting is.

The Sprint Retrospective is an internal meeting in which the Scrum Team examines how it works and makes an improvement plan, and everyone attends. The Scrum Master, like the other members, identifies areas for improvement and helps make the improvement plan, while also helping the team understand and use the meeting's rules, such as the timebox and the division of roles. The answer is B.

Why the other options are wrong

  • A. Answering stakeholders' questions about the Increment is something the team does at the Sprint Review, not part of the Sprint Retrospective.
  • C. Discussing what specific work to do next belongs to revising the backlog after the review and to the next Sprint Planning. The Sprint Retrospective is about improving how the team works.
  • D. The Sprint Retrospective is the team inspecting itself. The Scrum Master's duty is to serve the team, not to represent stakeholders and relay requirements.

Key takeaway In the Sprint Retrospective the Scrum Master is an equal participant and also helps the team use the meeting's rules well.

Variation If the question asks for the main purpose of the Sprint Retrospective, the answer is to plan ways to increase quality and effectiveness. If it asks who participates, the whole Scrum Team does, inspecting its own Sprint.

Something wrong with this question?

Report an issue with this question

Example 2 A process problem is continuously hurting code stability

Question 2Example

As Scrum Master you lead a team developing an e-commerce website. The fourth Sprint is about to end, and you notice a problem in the way the team handles code commits that will keep affecting the stability of the code. What is the BEST way to bring the problem up and work with the team to find a solution?

Show answer and explanation

Correct answer: D

The fourth Sprint is about to end, and the Scrum Master notices a problem in how the team handles code commits that will continue to affect code stability. The question asks how to bring it up and solve it together with the team.

This is a problem with the team's own way of working and falls within inspect and adapt. The Sprint Retrospective is the event used to inspect the last Sprint, analyze causes, and plan ways to increase quality and effectiveness. The most impactful improvements are addressed as soon as possible and may be added to the next Sprint Backlog. The answer is D.

Why the other options are wrong

  • A. Assess and Implement Changes is used for project changes that require formal management. Here, the team is inspecting and improving its own way of working, with no indication that a controlled baseline or governance requirement is affected, so analyzing it first in the Sprint Retrospective is more appropriate.
  • B. Showing the team organizational process assets from other projects only offers material. It does not lead the team to analyze and solve the current problem directly.
  • C. The Product Owner is responsible for the backlog and for value. The team's way of working should be discussed and improved by the team itself, so going to the Product Owner is not the most direct and effective route.

Key takeaway A continuing problem in the team's process: analyze it with the team at the Sprint Retrospective and make an improvement plan.

Variation If the problem is “the customer rated the Increment poorly”, look to the Sprint Review and reorder the backlog accordingly. If it is “an impediment blocked a member today”, surface it at the Daily Scrum and discuss it afterward.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The retrospective changes process and collaboration, not product scope. Changes to product scope and ordering come from adjusting the Product Backlog after the Sprint Review.
  • The retrospective comes after the Sprint Review and before the next Sprint Planning. It cannot be moved earlier or replace the review.
  • Stakeholders' requirements are not relayed in the retrospective, and the Scrum Master does not attend on their behalf.
  • Process problems the team can solve internally are usually analyzed first in the retrospective with the team. When a problem goes beyond the team's authority or meets the escalation criteria, escalate it promptly, using organizational process assets as needed. If an improvement affects a controlled baseline or a governance requirement, handle it through the change management process.
  • The result of the retrospective should become action items that have an owner and can be checked. Discussion without follow-through is the same as not having held the meeting.
  • Hold a retrospective in the closing phase even when there are no further Sprints.

Key takeaways

Key point

  • The retrospective comes after the review and before the next planning, usually on the last day of the Sprint. For a one-month Sprint it lasts at most about 3 hours (set by the Scrum Guide).
  • The retrospective looks at how the team works: summarize what went well and what did not, identify improvements, and decide what to implement (suitable ones go into the next Sprint).
  • The whole Scrum Team attends. The Scrum Master is an equal participant and also helps the team use the meeting's rules well.
  • Create a safe atmosphere that focuses on the issue, not the person. A timeline or emotion curve can build a shared picture.
  • The results must be actionable: specific measures with owners assigned, the most impactful improvements implemented first, and suitable ones put into the next Sprint.
  • Falling velocity, rework, process problems and the same problem recurring all point first to the retrospective.

This chapter has 57 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.