Plan and manage schedule

"Plan and manage schedule" is task 8 of the Process domain in the PMP exam content outline. The Process domain makes up 41% of the exam, and the outline does not publish a question count for each task. This task tests calculation (critical path, float, three-point estimates) and judgment: the schedule must fit the development approach, estimates need a basis, and when the schedule slips you analyze first and then choose between crashing, fast tracking or a change request.

What the outline asks for (enablers)

The outline lists 8 enablers for this task. The table maps each one to the chapters of this study guide.

EnablerWhat you need to knowChapter
Prepare a schedule based on the selected development approachPredictive uses rolling wave planning and the critical path; adaptive uses release planning and iteration planningRolling Wave Planning and Developing the Schedule, Release Planning and Prioritization
Coordinate with other projects and operations.Shared-resource conflicts, external dependencies, resource leveling and smoothingResource Leveling and Resource Smoothing
Estimate project tasks (milestones, dependencies, story points).Effort versus duration; dependency types; story points, planning poker and velocityEstimating Techniques for Duration, Precedence Diagramming Method, Story Points, Planning Poker and Velocity
Utilize benchmarks and historical data.Analogous and parametric estimating rely on historical data; documenting the basis of estimatesEstimating Techniques for Duration
Create a project schedule.Critical path method, total float and free float, critical chain method, multipoint estimatingCritical Path Method, Critical Chain Method, Multipoint (Three-Point) Estimating
Baseline a project schedule.A schedule becomes a baseline only after approval; the forms a schedule can takeSchedule Baseline and Monitoring the Schedule
Execute a schedule management plan.Working to the update frequency, reporting method and control thresholds in the planSchedule Baseline and Monitoring the Schedule
Analyze schedule variation.Variance analysis, why variance on the critical path matters most, choosing between crashing and fast tracking, schedule changesSchedule Baseline and Monitoring the Schedule, Crashing vs. Fast Tracking

How to read schedule scenario questions

  1. Check the critical path first. When an activity is late, ask whether it is on the critical path and how much float is left before deciding whether to act.
  2. Analyze first, then crash or fast track. When the schedule slips, find the cause and assess the impact. Crashing adds cost and fast tracking adds risk; assess both before using them, and normally apply them to the critical path.
  3. Estimates need a basis. When asked to shorten the duration, trade off using the basis of estimates, historical data and scope rather than just agreeing. The people doing the work take part in estimating.
  4. The baseline changes only through change control. A schedule baseline change needs an impact assessment, a change request under the change management plan, and approval by the authorized person or change control board before the baseline is updated.
  5. For resource conflicts, consider the effect of leveling. Resource leveling can change the critical path and extend the duration; resource smoothing does not change the critical path.
  6. For a late external dependency, talk to the other party first. When another project or a supplier causes the delay, learn the cause and negotiate, then assess the effect on your own schedule.
  7. In adaptive work, look at velocity and remaining work. Forecast completion from the team's velocity and the backlog, not from critical path logic.

Predictive versus agile and hybrid environments

PredictiveAgile and hybrid
PlanningWork breakdown structure, activity list, network diagram; detailed near term, rough later (rolling wave planning)Release planning plus iteration planning, driven by a prioritized backlog
EstimatingAnalogous, parametric, bottom-up, three-point; measured in hours or daysRelative estimating with story points and planning poker; forecast with velocity
Schedule monitoringCompare with the schedule baseline; variance and critical path analysisBurndown and burnup charts; the forecast is updated after each iteration review

Task quiz

These free questions come from the chapters linked to this task and cover as many chapters as possible. Pick an answer first, then open the explanation to see why the right option is right and why the others are wrong. For more, practice by chapter in the question bank.

Question 1Free

A project manager at a software company reviews a newly drafted schedule management plan. It specifies release timeframes and units of measure, but it does not say how schedule performance will be measured or how large a variance must be before action is taken. What should the project manager do?

Show answer and explanation

Correct answer: B

A schedule management plan has just been drafted. It already states release timeframes and units of measure, but it does not say how schedule performance is measured or how large a variance must be before action is taken. How should the gap be fixed?

The schedule management plan establishes the criteria for developing, monitoring and controlling the schedule. Typical contents include release and iteration length, level of accuracy, units of measure, control thresholds and rules of performance measurement. The stem already has two of these, and what is missing is exactly the rules of performance measurement (which rule is used to measure progress) and the control thresholds (how large a variance requires action). Both should be settled before the detailed schedule is built, so that later monitoring has rules to follow. They belong in the schedule management plan. The answer is B.

Why the other options are wrong

  • A. Waiting for a delay before discussing how to monitor turns the rules into an after-the-fact fix. The purpose of a schedule management plan is to set the criteria in advance.
  • C. The schedule baseline is the approved version of the schedule model and records planned dates for each activity. The allowed range of variance is a control threshold, usually written as a percentage deviation from the baseline parameters, not a number of days attached to each activity in the baseline.
  • D. Monitoring rules are one of the things the schedule needs before it is built, so they should be set before the detailed schedule. If they are left until execution, nothing guides the team when a variance appears.

Key takeaway The schedule management plan says how the schedule will be managed, and the rules of performance measurement and control thresholds must be set before the detailed schedule.

Variation If what is missing is the length of each iteration in an adaptive project, add that to the schedule management plan too. If a variance is within the threshold, continue monitoring it; if it reaches or exceeds the threshold, follow the response action specified in the schedule management plan.

Something wrong with this question?

Report an issue with this question

Question 2Free

A project manager on a logistics system project is developing the schedule, and the schedule baseline has not yet been approved. While reviewing the schedule network diagram, the project manager finds that the dependency between “user training” and “system go-live” was marked wrongly. What should the project manager do?

Show answer and explanation

Correct answer: A

A logistics system project is developing its schedule and the schedule baseline has not been approved. In reviewing the network diagram, the project manager finds the dependency between “user training” and “system go-live” is marked wrongly. What should the project manager do?

The schedule network diagram is a product of the determine sequence step, and a wrong dependency will affect every date and the critical path derived from it. The baseline has not yet been approved, so the network diagram and the schedule are still drafts. The project manager should correct the network diagram directly and update the schedule accordingly. Change control applies to approved baselines, which is not the case here, and there is no need to ask anyone else for approval. The answer is A.

Why the other options are wrong

  • B. Change requests and the change control board handle changes to approved baselines. Finding an error in a draft and sending it through the change procedure makes a simple problem complicated.
  • C. Using schedule reserve to absorb an error that could simply be corrected means carrying on with wrong logic, and the critical path and dates will be unreliable.
  • D. Dependencies are part of the project manager's and team's work when they determine sequence. The sponsor does not need to confirm them first, and treating a correction as a decision to escalate is also wrong.

Key takeaway If an error in the network diagram is found before the baseline is approved, correct it directly and update the schedule. Change control applies after approval.

Variation If the schedule baseline had already been approved, a wrongly marked dependency would require a change request, and the baseline would be amended only after change control.

Something wrong with this question?

Report an issue with this question

Question 3Free

A logistics management system project at PMLyceum is in planning, and the project manager is developing the schedule. The designated project team is still busy on another project, so the company temporarily assigns a few colleagues to help with planning and estimating activity durations. These colleagues will be replaced by the designated team before the project starts. What should the project manager do before finalizing the schedule?

Show answer and explanation

Correct answer: B

A project is in planning, and the duration estimates in the schedule were made by temporarily assigned colleagues who will be replaced by the designated team before the project starts. What should the project manager do before the schedule is finalized?

The inputs for duration estimates should come from the person or group most familiar with the activity. These colleagues are not the people who will do the work, so the estimates may not match the real capability and ways of working. Before finalizing, the project manager should therefore review the estimates together with the designated project team, align expectations, find the differences and adjust where necessary, so that the team buys into the schedule. The answer is B.

Why the other options are wrong

  • A. Historical data are useful as a check, but every project is unique. Relying on historical data alone, without review by those who will do the work, leaves the estimates without commitment or specificity.
  • C. The risk register records risks, not duration estimates. Estimates belong to developing the schedule and do not go in the risk register.
  • D. The sponsor is usually not familiar with specific activities and cannot judge whether an estimate is reasonable. Estimates should be reviewed by the team members most familiar with the activities, while the overall schedule baseline is accepted and approved by the appropriate stakeholders under the project's governance arrangements.

Key takeaway Duration estimates should be provided or reviewed by the team that will perform the activities, and estimates made by temporary staff must be confirmed again before they are finalized.

Variation If the designated team were already in place, they should be asked to take part in estimating from the start, without a later review of temporary staff's numbers.

Reference Estimating Techniques for Duration · Lesson 1: Estimating Effort and Duration: Effort, Duration and Influencing Factors

Something wrong with this question?

Report an issue with this question

Question 4Free

An activity is on the critical path, and whether it finishes on time determines whether the main deliverable can be delivered on time. The project manager wants to take uncertainty and risk into account to improve the accuracy of the duration estimate for this activity. Which of the following tools should be used?

Show answer and explanation

Correct answer: B

An activity is on the critical path and whether it finishes on time determines whether the main deliverable can be delivered on time. The project manager wants to take uncertainty and risk into account to make the estimate more accurate. Which tool should be used?

The signal in the stem is “take uncertainty and risk into account”. PERT three-point estimating (a common form of multipoint estimating) uses three values, optimistic, most likely and pessimistic, to reflect the uncertainty and risk in the estimate, and then calculates an expected duration, which improves the accuracy of the duration estimate. The activity is on the critical path, and a delay would directly slow the finish, so it is all the more important to reflect risk in the estimate and not give just one single-point number. The answer is B.

Why the other options are wrong

  • A. A cause-and-effect diagram is used to analyze the root causes of a problem. It is a quality and problem analysis tool, not an estimating tool.
  • C. Analogous estimating is based on historical data from a similar project. By itself it does not explicitly model optimistic, most-likely, and pessimistic scenarios the way multipoint estimating does, so PERT is the better answer for the stated objective.
  • D. Parametric estimating calculates from a statistical relationship. It also does not by itself give estimates for several scenarios and is not designed specifically to reflect uncertainty.

Key takeaway To build uncertainty and risk into a duration estimate, use PERT three-point (multipoint) estimating.

Variation If there are reliable historical data and unit labor hours, use parametric estimating. If the project is at an early stage with little information and the answer is needed quickly, use analogous estimating.

Something wrong with this question?

Report an issue with this question

Question 5Free

A bank has engaged PMLyceum to carry out an information-security remediation project. Several of the client's stakeholders want the project manager to commit to a firm delivery date. The project has many internal and external dependencies, plus several milestones that must be met within fixed time windows. What should the project manager do FIRST to determine the shortest project duration as the basis for the committed delivery date?

Show answer and explanation

Correct answer: C

The project has many dependencies and milestones fixed to time windows. The question specifically asks for the shortest project duration as an analytical basis for the committed delivery date.

The shortest project duration is set by the longest path in the network, which is the critical path. Integrate the activities into a network according to their logic, find the critical path, and add its length to the start date. That gives the earliest finish date without regard to resource limits, which is the basis for the delivery date you commit to; the fixed windows, calendars and resource constraints still have to be checked in the schedule analysis. “Many dependencies and fixed milestones” in the stem is the cue to do network analysis. The answer is C.

Why the other options are wrong

  • A. The work breakdown structure answers “what is the work” by decomposing it into deliverables. It contains no sequence or durations, so it cannot yield a delivery date.
  • B. The schedule baseline is the approved schedule model. It is the result of schedule analysis, not a method for arriving at dates; the analysis comes first and the baseline after.
  • D. Resource availability determines whether activities can be performed on time, but looking at resources alone cannot give the overall duration, nor does it show how dependencies affect the dates.

Key takeaway To answer “when is the earliest the project can be delivered?”, find the critical path.

Variation To identify which activities could start a few days later without affecting the delivery date, you look at the total float of each activity, which still starts from the critical path analysis.

Something wrong with this question?

Report an issue with this question

Question 6Free

The project manager at a manufacturer is responsible for two projects at once. One of them, a key project, needs a shorter duration, but there are not enough people, and the company has made clear it will add no more staff to either project. The activities in the schedule must be done in sequence, and none can run in parallel. What should the project manager do?

Show answer and explanation

Correct answer: D

The project manager runs two projects at once. The key project needs a shorter duration, but people are short, the company will not add staff, and the activities must be done in sequence with no room for parallel work.

Rule out the routes that do not work first: no more staff can be added, and with no activities that can run in parallel, fast tracking cannot be used. The resources are shared by the two projects, so analyze the two projects together to find the most effective way to allocate the shared resources, and adjust accordingly. This is the resource optimization approach of assessing before acting. The answer is D.

Why the other options are wrong

  • A. Starting training without analyzing the problem jumps straight to a solution. Training also does not guarantee that skills meet project requirements, let alone shorten the duration.
  • B. The stem states that the company will add no more staff, so asking for more people is a dead end. First optimize the shared resources across the two projects.
  • C. Fast tracking requires activities that can run in parallel, and the stem says there are none, so the technique cannot be used.

Key takeaway When resources are short and fast tracking is not possible, first analyze and coordinate the shared resources; do not go straight to adding people, training or applying compression techniques.

Variation Only if activities could run in parallel would fast tracking be an option, and only if the company were willing to add staff, approve overtime or pay extra would crashing be an option; when resources are in conflict rather than short, use resource leveling.