PMP Cheat Sheet: Project Environment and Organization

The key points and common traps of 11 lessons in 5 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.

Mind map of Project Environment and Organization
Tap the map to enlarge

Enterprise Environmental Factors

Lesson 1: Enterprise Environmental Factors: Definition and Internal Factors

Key takeaways

  • Enterprise environmental factors: the team cannot directly control them, but they impact, constrain or direct the project; favorable, unfavorable and neutral are all possible.
  • They can be internal or external, act at the organizational, portfolio, program or project level, and are an input to many planning processes.
  • Internal, 7 categories: organizational culture, structure and governance; geographic distribution of facilities and resources; infrastructure; information technology systems; resource availability (contracting, purchasing, staffing); employee capability; financial capability of the organization.
  • An organizational restructuring is an internal enterprise environmental factor; a software system the company uses across the board is one too, as far as the team is concerned.
  • The purpose of identifying environmental factors is to influence the plan, tailoring and the choice of development approach; the attitude toward them is to comply and adapt.

Common traps

  • That an enterprise environmental factor is "not controllable" does not mean it is "necessarily unfavorable": the impact can be favorable, unfavorable or neutral.
  • A change in governance arrangements such as organizational structure, hierarchy and authority relationships is an internal enterprise environmental factor; the organization's project management policies, procedures, templates and lessons learned are what count as organizational process assets.
  • Employee capability and resource availability are internal enterprise environmental factors; lessons learned, historical information, templates, policies and procedures are what count as organizational process assets.
  • In the internal factor "financial capability of the organization," what matters is whether the organization can raise funds and has additional money; exchange rates, interest rates, tariffs and taxes are external "financial considerations." Do not mix them up.
  • The influence of enterprise environmental factors and of organizational process assets cannot be compared directly; there is no fixed conclusion such as "enterprise environmental factors have more influence."

Lesson 2: External Enterprise Environmental Factors and Responding to Change

Key takeaways

  • External, 9 categories in three groups: rules (legal restrictions; government or industry standards; public health and safety regulations); environment (marketplace conditions; financial considerations; physical environmental elements); trends (social and cultural influences and issues; academic research; emerging technologies and innovations).
  • Exchange rates, interest rates, inflation rates, tariffs and taxes are external financial considerations; whether the organization itself can raise funds is an internal factor.
  • Handling external change (common exam practice): when the change is confirmed, first assess the impact on scope, schedule, cost and quality, then agree on a response with stakeholders, go through change control if needed, and update plans and related artifacts as needed; when the change is not yet confirmed, investigate first.
  • Environmental factors influence tailoring and the choice of approach: strict regulation leans predictive, a self-managing culture leans adaptive.

Common traps

  • Regulations, industry standards, tariffs and exchange rates come from outside the organization and are external enterprise environmental factors; the company's own templates, processes and historical records are organizational process assets.
  • The first step on an external change is to assess the impact: not to submit a change request directly, not to suspend the project, and not to negotiate with the regulator.
  • "Assess the impact" must cover scope, schedule, cost and quality, not just check whether there is a risk entry.
  • Enterprise environmental factors must be brought into planning and influence tailoring and the choice of approach; "not controllable" does not mean "no need to deal with it."
  • Once a new rule is confirmed to apply to the project, it is a known compliance requirement and cannot be called an unknown-unknown risk; its specific impact on scope, schedule and cost still has to be assessed.

Organizational Process Assets

Lesson 1: Organizational Process Assets: Definition, Sources and Categories

Key takeaways

  • Organizational process assets: the organization's own plans, processes, documents, templates and knowledge repositories, including lessons learned and historical information; they come from the organization, a portfolio, a program or other projects.
  • Characteristics: internal resources, can be updated and added to as needed throughout the project (knowledge repositories are updated with project information; policies, processes and procedures can be updated only by following the applicable organizational policy); an input to many processes; the attitude is to "use" them.
  • Two categories: policies, processes and procedures (templates, change control procedures, supplier lists, tailoring guidelines and so on); organizational knowledge repositories (lessons learned, financial data, issue and defect data, project files and so on).
  • Rule-type assets are established by the PMO or another function and can be updated only by following the applicable organizational policy; where the organization encourages it, templates, life cycles, checklists and the like can be tailored under the tailoring guidelines; record-type assets keep being updated as the project runs.

Common traps

  • Organizational process assets are internal resources, not "hard conditions" that can only be obeyed: team members can update and add to the organizational knowledge repositories throughout the project; policies, processes and procedures are updated according to the applicable organizational policy; and where the organization encourages tailoring, templates, life cycles, checklists and the like can be tailored under the tailoring guidelines.
  • Lessons learned, historical information and issue and defect databases belong to organizational knowledge repositories; change control procedures, preapproved supplier lists, contract templates and tailoring guidelines belong to policies, processes and procedures.
  • The source can be the organization, a portfolio, a program or another project, and historical material shared by collaborating performing organizations counts too; do not treat everything "from outside" as an enterprise environmental factor.
  • Rule-type assets can be updated only by following the applicable organizational policy; where the organization allows, templates, life cycles, checklists and the like can be tailored under the tailoring guidelines; tailoring does not mean changing the standard on your own, and it does not mean not using it.
  • Tailoring guidelines are themselves organizational process assets.

Lesson 2: Telling Enterprise Environmental Factors and Organizational Process Assets Apart

Key takeaways

  • EEF: not directly controllable, to be considered and adapted to (applicable mandatory requirements must be obeyed), can be internal or external, impact favorable, unfavorable or neutral. OPA: from inside the organization, available to the project; knowledge repositories can be updated continuously, other assets are updated per organizational policy and tailored where the organization allows.
  • Three test questions: does it come from outside the organization? Can the team directly change it? Is it a condition, or a practice and record to borrow from?
  • Organizational structure, a system bought company-wide, employee capability and resource availability are EEFs; templates, processes, lessons learned, historical data and the issue and defect information accumulated in the organizational knowledge repositories are OPAs (the current project's issue log and the like are project documents).
  • The two cannot be ranked by influence; neither is inherently more influential than the other.

Common traps

  • Tool systems, facilities, culture and organizational structure are enterprise environmental factors; files, records, lessons learned and historical information from earlier projects are organizational process assets.
  • Employee capability and resource availability are internal enterprise environmental factors; lessons learned that employees wrote down are organizational process assets.
  • A statement such as "enterprise environmental factors always influence more than organizational process assets" does not hold; the two have no fixed order of influence.
  • Enterprise environmental factors are usually not directly controllable by the project team; they can come from inside or outside; and their impact on the project can be favorable.
  • A restructuring of the organization does not fall under organizational process assets; it is an enterprise environmental factor.
  • The boundary between the two is occasionally blurred in real life; the exam goes by the PMBOK 8 classification and the three questions above.

Lesson 3: Using and Updating Organizational Process Assets

Key takeaways

  • When you take over an unfamiliar situation, a familiar-looking problem appears, a standard needs checking, or you are preparing a plan, and the stem has clues such as a similar project, historical data or lessons learned and no more urgent action is required, common exam practice is to consult the organizational process assets first; the actual order depends on the situation.
  • Lessons learned are used in initiating, planning, risk management and the stakeholder register; historical data is used for estimating; borrowing must be fitted to this project and is not copying.
  • Team members can update and add project information to organizational knowledge repositories throughout the project (policies, processes and procedures follow organizational policy); correct outdated content promptly with new data.
  • When the project or phase ends, put lessons learned and performance data into the organizational knowledge repository for later projects to use.

Common traps

  • When you meet a similar problem, the first step is to consult the organizational process assets (lessons learned, historical records), not to add people, add outside experts, update the risk management plan or extend the schedule.
  • Lessons learned are not something to handle "after the project ends": update them at any time during the project, and be sure to archive them into the organizational knowledge repository at closing.
  • Borrowing from historical projects has to be fitted to this project's situation and cannot be copied wholesale or applied mechanically; choose relevant, reliable historical information and tailor it to this project.
  • When another project has failed, first apply its lessons learned to your own project; when borrowing, use ready-made experience inside the organization first, then consider outside resources.
  • For an outdated process document, have experts and actual users update it together; the project team should not modify it on its own, but should propose the update to the department responsible for the asset and follow the approval or change procedure the organization requires; when there is a dispute about how widely a document applies, first explain how the document relates to this project's work.

Organizational Structures

Lesson 1: Functional, Project-Oriented and Matrix Organizations

Key takeaways

  • Authority runs roughly from least to most: for functional and weak matrix, the project manager's authority is low; balanced matrix, low to moderate; strong matrix, moderate to high; project-oriented, high to almost total (Table 2-1).
  • Functional: project manager authority low, part-time, members listen to the functional manager. Project-oriented: authority high to almost total, full-time, and members report to the project manager. Where the team goes next at closing is only a helper clue, since personnel are reassigned or released at closing in other structures too.
  • Weak matrix: low, part-time. Balanced matrix: low to moderate, part-time. Strong matrix: moderate to high, full-time, designated role (all of this is from Table 2-1). "Who makes the final call" and "both managers negotiate" are identifying clues that are common exam practice.
  • Shared features of matrix structures: dual reporting, competition for resources, and a project manager who often has only an advisory voice in performance appraisal (a common exam generalization that depends on organizational delegation).
  • There is no one-size-fits-all best structure, and organizational structure is an enterprise environmental factor.

Common traps

  • Under the functional structure the project manager is not worthless, just low in authority and part-time, working mainly by coordinating; team members' performance belongs to the functional manager.
  • Project-oriented is not "all-powerful": resource utilization can be low, technology can fall behind, and people need to be reassigned at closing.
  • Among the three matrix types, only the strong matrix has a full-time, designated project manager role; the weak matrix project manager is neither full-time nor in a designated role. Project-oriented is also full-time and designated.
  • A balanced matrix simply has authority comparable to the functional manager's; it is not "the best structure".
  • The shared features of matrix structures are dual reporting and competition for resources. When the project manager needs people and the functional manager disagrees, the weak and balanced matrices usually call for negotiation with the functional manager; a strong matrix project manager may have considerable direct power to allocate people, depending on organizational delegation.
  • Organizational structure is itself an enterprise environmental factor, and the project manager cannot change it unilaterally; the usual approach is to coordinate within the existing structure. If needed, the project manager may suggest improvements and push for evaluation through appropriate governance channels, but should not use "get someone to change the structure" as a substitute for solving the problem within the current structure.

Lesson 2: Other Organizational Forms and Comparing Structures

Key takeaways

  • Other forms: organic or simple, multidivisional, virtual or network, hybrid. They are not heavily tested; classify them using the Table 2-1 features.
  • Virtual: network structure, members connected through points of contact (geographic dispersion and remote work are common but not required; temporary assembly and disbanding at completion are only helper clues). Multidivisional: divided by product, region or customer, possibly with functions replicated in each division, and low project manager authority.
  • Resources most under the project manager's control: project-oriented. Full-time project manager: strong matrix and project-oriented.
  • Three classification questions: Is the project manager full-time? Whom does the team report to? Must people be placed after the project?
  • When authority is insufficient, negotiate, communicate and seek sponsor support. Do not go over someone's head or force people to be reassigned.

Common traps

  • What identifies a virtual (network) structure is the network structure, with members connected through points of contact (geographic dispersion and remote work are common but not required). Temporary assembly and disbanding once the goal is met are only helper clues and cannot decide the type alone. It is not "hybrid", and it is not simple.
  • A multidivisional organization may replicate functions in each division, and the project manager's authority is usually low. Do not mistake it for project-oriented.
  • Classify the structure by the authority the project manager actually has, not by the company's nominal chart. Hybrids are common in practice.
  • A question that asks "which structure should it be changed to" is usually not heading in the right direction. The safer approach is to negotiate, communicate and seek delegation within the existing structure.
  • A stem that mentions arranging where members go after the project is only a helper clue for project-oriented. Combine it with the project manager's authority, whether the role is full-time, and the reporting line.

Project Management Office

Lesson 1: PMO Definition, Value and Types

Key takeaways

  • PMO: an organizational entity that centralizes activities related to the management of portfolios, programs and/or projects (PMBOK 8 glossary). "Standardizes governance processes, shares resources and methods, and serves projects that need not be related" is common exam practice. PMBOK 8 Appendix X2 stresses alignment with strategy and the two sides of value.
  • Value has two sides: actual value delivered and value perceived by stakeholders. A modern PMO is a customer-oriented partner.
  • The project manager manages a single project; the PMO manages the whole.
  • Traditional types, by degree of control from low to high: supportive (consultant), controlling (requires compliance), directive (manages directly and assigns the project manager).
  • PMBOK 8 stresses that there is no universal best model, and successful PMOs often blend characteristics drawn from the directive, supportive and agile models.

Common traps

  • A PMO is an organizational entity, not a person, and it is not the same as an executive or a sponsor.
  • A PMO standardizes governance and enables teams. It does not do the project manager's specific work for the project manager, and it is not just a keeper of documents. With the right authority it can manage projects directly (directive).
  • By traditional classification, control runs from low to high: supportive, controlling, directive. "Controlling" does not mean "manages the project directly". The type that manages projects directly and assigns project managers is directive.
  • A suitable, tailored standard process can reduce trial and error and improve efficiency. A process that is too heavy or does not suit the project's context can slow the project down.
  • PMBOK 8 discourages rigid PMO labels, but when a question asks for a classification using the traditional three types, answer with "support, control, direct".

Lesson 2: How the PMO Supports Project Managers, and Its Relationship to Tailoring, Programs and Portfolios

Key takeaways

  • Four kinds of PMO support: managing (shared resources and best practices), monitoring (audits), coaching and training (policies, templates and training) and coordinating (communication across projects).
  • When there is a similar project and the PMO maintains relevant material, check its historical records and guidelines first.
  • Division of work: standards and the whole belong to the PMO, a single project belongs to the project manager. If there is a conflict with PMO policy, discuss with the PMO first.
  • The PMO develops tailoring guidelines and reviews tailored approaches; its services can cover portfolios, programs and projects.
  • In an agile transformation, move from control to enablement and coaching, and under a hybrid approach provide lightweight oversight. The more mature the organization, the better it can leverage the PMO.

Common traps

  • When project procedures conflict with PMO policy, do not change the policy yourself or organize others to push for a change, and do not act first and report later. Discuss with the PMO first, and consider a change together if needed.
  • When there is a similar project or problem and the PMO maintains relevant material, check its historical records and guidelines first, then decide the next step.
  • When a PMO transforms to support agile, it does not abolish oversight or add approvals. It moves from control to enablement and coaching, and under a hybrid approach it provides lightweight oversight.
  • "Coaching and mentoring" is how you help people learn to handle difficult situations. It is not the same as on-the-job training, contract negotiation or performance appraisal.
  • The policies, templates and historical data a PMO provides are organizational process assets.

The Project Manager Role

Lesson 1: The Project Manager and Project Management Team Roles, and Competencies and Development

Key takeaways

  • The project management team is the team members directly involved in project management activities. It can be one person or several, takes part throughout (and, where needed, before initiation for evaluation and after the project for benefit analysis), and is tailored to the organization.
  • Project management is a function, whatever the title. Product owners, agile coaches and others may share project management responsibilities.
  • The project manager's responsibility and authority are usually based on the project charter.
  • The Talent Triangle: ways of working, power skills, business acumen. The full five add social responsibilities and results.
  • Competency development: a learning culture, mixed seniority, coaching and mentoring, continuous improvement. Leadership style adjusts to the situation.

Common traps

  • Project management is a function, not a title. The absence of anyone called "project manager" in an agile environment does not mean nobody is doing project management.
  • The project manager's responsibility and authority are usually defined in the project charter. If someone questions your qualifications, clarify with the charter. Do not ask to cancel the project, and do not ask to be replaced.
  • The project manager integrates and leads, and does not need to be an expert in every technical field.
  • The older Talent Triangle was technical project management, leadership, and strategic and business management. PMBOK 8 corresponds with ways of working, power skills and business acumen, and its full competency framework adds social responsibilities and results.
  • Mixing team members of different seniority is for mentoring and coaching, not for cutting cost.

Lesson 2: The Project Manager's Power and Authority, and Other Key Roles

Key takeaways

  • Sources of power (common exam practice): positional power is granted by the organization; expert power and referent power come from the individual; there are also reward power and coercive (penalty) power. Different structures give different amounts of positional power.
  • Escalate matters beyond your authority to the sponsor or governing body; send requests unrelated to the project through a formal process.
  • Commonly outside the team: senior management, the project steering committee, functional managers, the customer and users. Commonly inside the team: the project manager, the project management team, the project team and experts. The product owner is listed alongside the sponsor and customer and may provide decision leadership outside the authority of the project management team (whether a role belongs to the team depends on the governance structure and approach).
  • The sponsor communicates the vision and goals, secures resources, removes obstacles beyond the project team's authority, keeps the project aligned with business objectives, and monitors progress and drives the expected benefits (tracking after the project ends is done by the benefits owner designated in the benefits management plan, and the sponsor may hold that role as well).
  • The customer accepts or purchases the result, takes part in clarifying requirements and acceptance (and may provide funding); the user uses the result; the functional manager controls resources; the product owner is listed alongside the sponsor and customer, orders the backlog and is a role distinct from the customer.

Common traps

  • Do not mistake "good at coordinating" for "authorized to decide". For matters beyond what the charter authorizes, ask the sponsor or governing body for approval.
  • The sponsor is usually not the person who manages day-to-day tasks. How day-to-day work is organized depends on the approach used.
  • The customer who pays and the user who uses are often not the same people. The product owner is listed alongside the sponsor and customer as a role that provides decision leadership, and it is a role distinct from the customer (it can be filled by a customer representative).
  • For a request unrelated to the project, do not commit resources on your own. Point the customer to the formal sales and quotation process.
  • When expectations about roles differ, hold a meeting to discuss and agree. Do not decide unilaterally, and do not simply pass it to someone else.
  • An actively involved sponsor significantly increases the likelihood of achieving the desired outcome, while an absent one might adversely impact the project.