Project Environment and Organization
The Project Manager Role
PMP · Project Environment and Organization · 2 lessons · about 29 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Whether a project succeeds depends largely on who does what. The project manager does not work alone: above are the sponsor and the governing body, alongside are functional managers and the customer, and below are the project team and end users. Lesson 1 covers the roles of the project manager and the project management team, how far they take part, where their responsibilities come from (the project charter), and PMBOK 8's competency framework and competency development. Lesson 2 covers where the project manager's power comes from and where authority ends, then lays out the other key roles inside and outside the team, with the sponsor as the main focus. This chapter mainly corresponds to People domain Task 3 of the ECO and to the related parts of Business Environment domain Task 1.
After this chapter you should be able to: explain the functions and scope of involvement of the project management team, and know that a title is not a function; name the three skill types of the Talent Triangle and the five competencies in PMBOK 8; tell which kind of power a behavior uses; know to escalate to the sponsor, or use a formal process, when a request is beyond your authority or unrelated to the project; and distinguish the roles of the sponsor, customer, user, functional manager and product owner.
Lessons in this chapter
- Lesson 1: The Project Manager and Project Management Team Roles, and Competencies and Development. The project management team, scope of involvement, a title is not a function; where responsibilities come from; the five competencies; competency development and situational leadership. Includes two worked examples.
- Lesson 2: The Project Manager's Power and Authority, and Other Key Roles. Common sources of power; what to do when something is beyond your authority; roles inside and outside the team; the sponsor's role; end users. Includes three worked examples.
Chapter concept map
Project manager (responsibility and authority set out in the project charter) / project management team
(roles, responsibilities and authority clarified by the resource management plan, responsibility assignment matrix and so on)
- Competencies: ways of working · power skills · business acumen (Talent Triangle) + social responsibilities · results
- Power (common exam classification; common sources, not exhaustive): positional power (granted by the organization) · expert · referent · reward · coercive (penalty) power
- Beyond your authority → escalate to the sponsor or governing body; unrelated to the project → formal process
- Roles (common positions of interaction; where the boundary between inside and outside the team falls varies with governance structure and development approach): Commonly outside the team (senior management · steering committee · functional managers · customer · users) Commonly inside the team (project manager · project management team · project team · experts) Product owner: listed alongside the sponsor and customer; may provide decision leadership outside the authority of the project management team; in Scrum also part of the Scrum Team Sponsor: the bridge between executives and the team, involved throughout
How this is tested
Questions in this chapter fall into four kinds: what to do when your qualifications or authority are questioned (clarify with the project charter); recognizing the competency framework (the Talent Triangle, and how the older version differs from PMBOK 8); identifying the type of power (expert power, positional power and so on); and sorting out roles (the sponsor's responsibilities, customer versus user, where the product owner fits, and how to handle a request unrelated to the project). The answer to most of them follows from three sentences: "The project manager's formal authorization, responsibilities and authority are found in the project charter, and team members' responsibilities are found in the resource management plan and the responsibility assignment matrix." "Anything beyond your authority is escalated along the governance escalation path, which may lead to the sponsor, the governing body or another authorized role." "Day-to-day work belongs to the project manager and the team."
Study tips and practice
- Pair each of the five competencies with a verb: social responsibilities (follow the rules), power skills (lead people), business acumen (understand the business), ways of working (use methods), results (get things done).
- On role questions, first decide "who should do this", then look for which option has someone overstepping.
- This chapter connects closely to the chapters on organizational structure, resources and stakeholders. Look back at it when you study leading the team and managing conflict.
Lesson 1
The Project Manager and Project Management Team Roles, and Competencies and Development
Lesson overview
To get a project done, you first need to know who takes the lead. The project manager does not work alone, and may not even be called "project manager". This lesson first covers what the project manager and the project management team are, how far into the project they take part, and where their responsibilities come from. It then covers PMBOK 8's competency framework for the project management team: the three skill types that correspond to the PMI Talent Triangle, and the full five competencies. Finally it covers team competency development and situational leadership. ECO: People domain, Task 3 (Lead the project team), and related parts of Task 5 (Align stakeholder expectations). The next lesson covers the project manager's power and the other key roles.
The project manager and the project management team
The project manager is assigned by the performing organization to lead the project team to achieve the project objectives. The project management team consists of the members of the project team who are directly involved in project management activities. It may consist solely of a project manager or include more individuals who form a team, and in this lesson the two are treated as synonymous. PMBOK 8 says the project management team is essential for guiding the assigned team to achieve goals and deliver value to the organization and customers while considering flexibility, adaptability and tailoring. Its functions include facilitating and mentoring the project team and managing the processes to deliver intended outcomes.
Scope of involvement: depending on the organization's policies and processes, it is suggested that the project management team be involved from project initiation through closing and, in some cases, in post-project benefit analysis. In some organizations the project management team is involved before initiation in evaluation and feasibility analysis, consulting with executives and business unit leaders, and sometimes it manages or assists in business analysis, business case development and aspects of portfolio management. Because the role and the level of involvement vary from organization to organization, the role should be tailored to fit the organizational structure, like tailoring project processes.
A title is not a function: in many organizations, the title of "project manager" or "project management team" may not explicitly denote someone who is managing a project. A functional manager may oversee project activities, and the title may be "project leader" or "project lead". In adaptive and agile environments, it is common for a function such as product owner or product manager to handle some of the project management tasks, and scrum master, agile coach, team lead or the development team may also share some responsibilities usually performed by project managers. PMBOK 8 stresses that the essence of project management lies in the characteristics of the project itself rather than the title of the individual overseeing it: whatever their official position, anyone fulfilling this function must embrace the core aspects of project management.
Where responsibilities come from: the project manager's responsibility and authority are usually defined in the project charter (an organization may use a similar authorizing document). The approved project charter formally initiates the project, identifies and assigns a project manager, and grants the project manager the authority to support the project. So what should you do when someone questions whether the project manager is qualified because he or she is not an expert in some technology? Produce and explain the project manager's responsibility and authority in the charter. The project manager's job is to integrate and lead. A project manager does not have to be an expert in every technical field, and need not ask to cancel the project or hire an expert to take over.
The competency framework
PMBOK 8 says the skills of the project management team are a mix of different skills such as ways of working, power skills and business acumen. These three types match the three skills of the current PMI Talent Triangle. The older wording was "technical project management, leadership, and strategic and business management". If a question uses the older wording, recognize it, but go by PMBOK 8. The PMBOK 8 project management team competencies list five in full:
| Competency | Meaning | Includes but is not limited to |
|---|---|---|
| Social responsibilities | The project management team makes decisions that are aligned to the common good | Giving back to the profession and to society as a responsibility; adhering to ethical standards by respecting cultural and social norms; striving for self-development and continuous improvement |
| Power skills | All the people skills a project management team should apply to execute the project successfully (e.g., adaptability and emotional intelligence) | Exercising critical thinking, sound judgment and decision-making; implementing team motivation methods; using negotiation and conflict resolution skills |
| Business acumen | The application of strategic thinking and the alignment of the project management team within the organizational context | Setting project selection criteria (cost, feasibility, impact); applying knowledge of the industry; performing strategic thinking, business case development and financial analysis |
| Ways of working | The understanding and application of the standards, methodologies and frameworks a project management team may use to execute projects and add value to the organization | Implementing appropriate project management approaches (predictive, adaptive, hybrid); using brainstorming techniques; applying change management techniques |
| Results | The actual work and execution of ideas and projects to add value | Applying problem-solving techniques (e.g., root cause analysis); acquiring the power and authority to work within organizational policies; dealing with enterprise politics using influence, negotiation, autonomy and power |
Competency development and situational leadership
The project management team plays a pivotal role in competency development. It fosters a learning culture that blends the team's various competencies; it deliberately mixes members of different seniority levels and expertise so that less-experienced members get mentoring and coaching; it identifies individual learning needs and integrates competency development into the project's workflow; and it creates opportunities for members to take on challenges and gives them constructive feedback. This responsibility may also be taken by functional managers, PMOs or members' line managers. The team should also promote a culture of continuous improvement and reflective practice, so that lessons learned are captured and shared.
Situational leadership stresses flexibility based on the project's evolving demands: during critical project phases the leader can be more directive, and when team autonomy is beneficial the leader can use a supportive style. Leaders should be versatile and able to switch between styles.
Worked example: pairing people of different seniority
On a data analytics project, the team includes two newly hired analysts and a data architect with ten years of experience. The project manager pairs the architect with the two newcomers as a review group that jointly reviews each week's model proposal. The newcomers learn to judge risk, and the architect uses the sessions to write down the review criteria. After every weekly meeting the project manager also stays ten minutes to ask the newcomers about the difficulties they met that week and to give specific suggestions for improvement. During the crunch week that is critical to the deadline, the project manager assigns tasks in a more directive way; during the design week that needs creativity, the project manager lets the team discuss freely.
Three things happen at once here. Mixed seniority, coaching and mentoring are competency development. Learning needs are identified through feedback in the weekly meeting and built into the workflow. Being directive at critical phases and hands-off when autonomy is needed is situational leadership.
Worked examples
Example 1 Core question: your qualifications are questioned, so what do you do
A company launches a robot-vacuum development project and appoints a project manager. At a review meeting, a stakeholder questions the project manager's role, arguing that he must be an expert in mechanics, programming and sensing, or he cannot ensure the project's success. What should the project manager do?
Show answer and explanation
Correct answer: B
The project has just started and the project manager has been appointed. A stakeholder questions the technical skills the project manager should have. The question is how the project manager should respond.
The core role of the project management team is to guide the team, manage the processes that deliver the intended outcomes, and coordinate the project. It is not to be an expert in every technical field. The project manager's assignment and the corresponding responsibility and authority are set out in the project charter. Showing and explaining the charter uses a formal document to clarify the role and remove the stakeholder's doubts. The answer is B.
Why the other options are wrong
- A. The project manager's job is to manage the project, and nobody requires expertise in every technical field. Asking the sponsor to cancel the project because of one missing skill is an extreme response.
- C. The stakeholder is questioning the project manager's role, which the charter can clarify. Hiring another expert does not respond to the challenge and creates unnecessary cost.
- D. The stakeholder engagement plan records strategies for fostering stakeholders' engagement in decisions and execution. It does not cover the project manager's role and responsibilities, and the problem is not a lack of stakeholder engagement.
Key takeaway The project manager's responsibility and authority are defined by the project charter. When your qualifications are questioned, use the charter to clarify.
Variation If a stakeholder questions whether the project manager must personally have every strategic competency, explain that the project management team can supply the needed competencies together (including business acumen). If there is a genuine business acumen gap, assess the learning need and fill it through training, coaching or bringing in the relevant expert. If the question is about the limits of the project manager's authority, clarify with the charter, and let the sponsor decide anything beyond it.
Something wrong with this question?
Example 2 Core question: the PMI Talent Triangle
In an internal training session, project management team members discuss which competencies it takes to be a good project manager, and the instructor introduces the current PMI Talent Triangle. Which of the following correctly describes its three skill types?
Show answer and explanation
Correct answer: A
You need to decide which three skill types make up the current PMI Talent Triangle. No specific project scenario is involved.
The current PMI Talent Triangle consists of three skill types: ways of working, power skills and business acumen. These three also appear among the project management team competencies in the standard (section 2.5.1), which add social responsibilities and results. B is the combination PMI used earlier, and C and D are not part of the Talent Triangle. The answer is A.
Why the other options are wrong
- B. This is the combination PMI used earlier (technical project management, leadership, strategic and business management). The current Talent Triangle is ways of working, power skills, business acumen.
- C. Business administration, technical expertise and strategic management are not any of the Talent Triangle's skills.
- D. Project management, technical expertise and business marketing are likewise not the Talent Triangle's three skill types, and business marketing is not a named competency in this framework.
Key takeaway The current PMI Talent Triangle is ways of working, power skills and business acumen. Technical project management, leadership, and strategic and business management is the combination PMI used earlier.
Variation If asked how many competencies are in the PMBOK 8 project management team competency framework, the answer is five: social responsibilities, power skills, business acumen, ways of working and results. If asked which one covers negotiation and conflict resolution, the answer is power skills.
Something wrong with this question?
Common traps
Common trap
- Project management is a function, not a title. The absence of anyone called "project manager" in an agile environment does not mean nobody is doing project management.
- The project manager's responsibility and authority are usually defined in the project charter. If someone questions your qualifications, clarify with the charter. Do not ask to cancel the project, and do not ask to be replaced.
- The project manager integrates and leads, and does not need to be an expert in every technical field.
- The older Talent Triangle was technical project management, leadership, and strategic and business management. PMBOK 8 corresponds with ways of working, power skills and business acumen, and its full competency framework adds social responsibilities and results.
- Mixing team members of different seniority is for mentoring and coaching, not for cutting cost.
Key takeaways
Key point
- The project management team is the team members directly involved in project management activities. It can be one person or several, takes part throughout (and, where needed, before initiation for evaluation and after the project for benefit analysis), and is tailored to the organization.
- Project management is a function, whatever the title. Product owners, agile coaches and others may share project management responsibilities.
- The project manager's responsibility and authority are usually based on the project charter.
- The Talent Triangle: ways of working, power skills, business acumen. The full five add social responsibilities and results.
- Competency development: a learning culture, mixed seniority, coaching and mentoring, continuous improvement. Leadership style adjusts to the situation.
Lesson 2
The Project Manager's Power and Authority, and Other Key Roles
Lesson overview
What does a project manager rely on to get things moving? When something is beyond what the project manager can decide, whom does the project manager go to? Besides the project manager, a project has a sponsor, a customer, functional managers, a product owner, end users and others. What does each of them handle? Most role questions on the exam are scenario judgments: who makes the call, who clears the obstacle, who is the "client". This lesson first covers where power comes from and where authority ends, then sorts the other key roles into "outside the team" and "inside the team", with the sponsor's role as the main focus. ECO: People domain, Task 3 (Lead the project team) and Task 2 (Manage conflicts); Business Environment domain, Task 1 (Define and establish project governance).
Sources of power
The power a project manager uses to influence others typically comes from the following sources (common exam practice):
- Positional (formal) power: comes from the position the organization grants, with the project charter as an important basis.
- Expert power: comes from personal expertise. For example, when a project manager uses his or her own professional knowledge to work with members through a technical bottleneck, this is expert power.
- Referent power: comes from personal charm, standing and being looked up to.
- Reward power: comes from control over rewards, such as recognition, bonuses and assigning attractive tasks.
- Coercive (penalty) power: comes from control over penalties, such as criticism, reducing a performance rating and assigning unpopular tasks. It is a different source from reward power, and on questions you must tell them apart.
Positional power is granted by the organization. Expert power and referent power come from the project manager as a person and do not depend on the position. How much power the project manager has also depends on the organizational structure. In functional and weak matrix organizations the project manager's positional power is small, so he or she relies more on expert power, referent power and negotiation to influence others. In project-oriented and strong matrix organizations positional power is noticeably greater (see the chapter on organizational structure).
What to do when something is beyond your authority
The project manager's authority is set by the charter and by the organization's delegation. Some matters are beyond it, such as allocating resources across departments, decisions that need senior management, and issues that involve changing company policy. These should be escalated to the sponsor or governing body, not decided by overstepping.
Requests unrelated to the project are handled the same way. For example, an operations manager on the customer side calls to ask for help with an urgent outage that is unrelated to this project, believing someone on the project team has the expertise. The project manager should first tell the customer that the request is outside the project's scope and should go through the organization's prescribed business channel (such as the sales manager) as a formal service request and quotation, and should not commit project resources on his or her own. The reason is that it is outside the contract scope, so resources cannot be committed independently. A flat refusal would damage the relationship, so give the right path.
Other key roles on a project
Roles can be divided into two groups by whether they are inside the project team. Here "outside" means outside the project team, not outside the company.
The roles below are organized as "common roles and their main positions of interaction". Whether a role belongs to the project team depends on the governance structure and the approach used, and is not a fixed rule. (PMBOK 8 notes that functions, roles and responsibilities differ from one enterprise and project to another, and in some projects a customer or client representative takes part in the project team's work.)
Roles commonly outside the team (common exam practice): senior management is the company's leadership group, not the leadership of a specific project. The steering committee is an advisory body of senior stakeholders that provides direction and support for the portfolio, program or project team and makes decisions outside the team's authority; its members may include the sponsor and executives. Functional managers control departmental resources, especially people, and the project manager has to borrow people from them. The customer accepts or purchases the project's product, service or result and takes part in clarifying requirements and acceptance (a customer may provide contract funding, but project funding may also come from organizational budgets, grants and other sources). Users (end users) are those who use the deliverable. The customer who pays and the user who uses are often not the same people: the distributor is the customer, and the consumer is the user.
Inside the team: the project manager, the person assigned by the organization to lead the team; the project management team; the project team, the set of individuals who perform the project's work and are directly responsible for achieving project objectives, whose size, composition and skill level depend on the project's type, scale, complexity and the organization's level of maturity; and experts, individuals or groups with specialized knowledge, skills, experience or training in a particular area, from whom expert judgment comes.
The product owner does not fit neatly into either group. PMBOK 8 lists the product owner alongside the project sponsor and the customer, saying that they may provide decision leadership outside of the project management team's authority and power. In an agile environment, the product owner keeps the team focused on valuable features by maintaining and prioritizing the product backlog. The role is different from the customer or "client", though it can be filled by a customer representative or someone from the business. In Scrum, the product owner is also a member of the Scrum Team.
A team can coordinate in a decentralized way (members self-organize, as in an agile team) or a centralized way (led by the project management team or the project manager). Either way, supportive leadership and meaningful continuous engagement with stakeholders are key to success.
The sponsor's role
The sponsor is an individual or group that provides resources and support for the portfolio, program or project, and is accountable for enabling success. Which organization the sponsor belongs to, and whether the sponsor also holds another role, depends on the specific governance arrangement. On the exam the sponsor is often distinguished from the client (customer), and is usually not the person who manages day-to-day tasks. The sponsor holds the relevant decision-making authority, is typically involved in initiating the project, and helps the project manager secure resources. PMBOK 8 groups the sponsor, the customer (internal or external) and the product owner, noting that they may provide decision leadership outside of the project management team's authority and power. They communicate the organization's vision, goals or expectations to the team, keep the project aligned with business objectives, facilitate executive-level decisions, help secure resources, advocate for the project team, address issues or remove obstacles that are beyond the project management team's authority, and continuously monitor project progress so that the project's intended business benefits are realized.
In one sentence: the sponsor is usually actively involved throughout the project life cycle and ensures the deliverables can support long-term benefits. After the project ends, tracking of benefits is handled by the benefits owner designated in the benefits management plan (the sponsor may also be designated as that owner). The sponsor is the bridge between senior management and the project team. PMBOK 8 notes that the presence of the sponsor, customer and product owner, and especially the degree of their involvement, increases the likelihood of achieving the desired project outcome, while their absence might adversely impact the project. In contrast, how day-to-day work is organized depends on the approach used: in a predictive environment the project manager may coordinate tasks, in an agile environment the team self-organizes, and in Scrum the Developers use the Daily Scrum to inspect progress and adapt the plan. The sponsor does not step into day-to-day work management, and does not need to approve every detail of every technical proposal.
With end users, the team should engage in continuous dialogue where possible, capturing and integrating their feedback throughout the life cycle. Prioritizing end-user satisfaction can reduce the risk of delivering a product or service that does not meet the expected utility.
Worked example: you cannot borrow the people, so whom do you go to?
A project manager needs two security test engineers for a member loyalty-points system. The information security department manager says the department is fully booked this quarter. The project manager does not argue with that manager and does not go around the functional manager to approach the engineers directly. Instead, the project manager puts together the impact of the missing people on the launch date and asks the sponsor to coordinate at the management meeting. The sponsor re-sequences this quarter's priorities, and the two engineers join the project for the agreed period. Three months after the project closes, the sponsor (who is also the benefits owner) calls a review to check whether the expected benefits have been realized.
Worked examples
Example 1 Core question: expert power
A software development project is in the Executing focus area. The team hits a technical bottleneck, and morale and performance drop. Drawing on his own professional skills, the project manager works through the problem with the members and together they find a solution. Which type of power did the project manager use?
Show answer and explanation
Correct answer: D
The project is in the Executing focus area. The team hits a technical bottleneck, and the project manager uses his own professional skills to lead the members to a solution. You need to identify the type of power he used.
By common exam practice, a project manager's power can be positional, expert, referent, reward, coercive and so on. Positional power comes from the formal role and organizational authority; reward and coercive power depend on the specific authority the organization grants; expert power and referent power come from the project manager as a person. In the question the project manager works with members to solve a technical problem “drawing on his own professional skills”. Catch that key phrase: it is expert power. The answer is D.
Why the other options are wrong
- A. Positional power comes from the position and formal authority granted by the organization. The question stresses the project manager's personal professional skills, not his position.
- B. Referent power comes from personal charm, character and personality, so that others identify with and follow someone willingly. The question says nothing like that.
- C. Reward power influences others through rewards (such as bonuses, promotion or recognition). The project manager in the question uses no reward.
Key takeaway Solving a problem with your own professional skills is expert power, which comes from the project manager as a person (common exam practice).
Variation If members follow the project manager willingly because they admire him as a person, that is referent power. If the project manager assigns tasks to members by virtue of his position, that is positional power. If he motivates members with a bonus, that is reward power.
Something wrong with this question?
Example 2 Core question: what the sponsor is responsible for
At an executive meeting, someone asks what exactly the project sponsor is responsible for on a project. Which statement is MOST accurate?
Show answer and explanation
Correct answer: B
You need to judge the sponsor's role, independent of any particular project phase, by distinguishing the sponsor's responsibilities from those of the project manager and the team.
PMBOK 8 says the sponsor may provide decision leadership outside the project management team's authority: communicating the organization's vision and expectations to the team, keeping the project aligned with business objectives, facilitating executive-level decisions, helping to secure resources, and addressing or removing obstacles beyond the project management team's authority, so that the intended business benefits are realized. B is consistent with this. A, C and D are the day-to-day work of the project manager or the team, or are excessive interference. The answer is B.
Why the other options are wrong
- A. Assigning and checking tasks every day is the affair of the project manager or a self-managing team, not the sponsor's responsibility.
- C. The daily coordination meeting is a routine activity inside an adaptive team and is run by the team itself. It is not the sponsor's responsibility.
- D. Approving technical details item by item is excessive interference. The sponsor focuses on business value and executive-level decisions, not technical details.
Key takeaway The sponsor drives approval, secures resources, clears executive-level obstacles and safeguards business value, and does not manage day-to-day tasks.
Variation If the question asked who is responsible for assigning tasks every day and following up, the answer is the project manager (or the self-managing team). If it asked who keeps watching whether the benefits are realized after the project ends, the answer is the benefits owner designated in the benefits management plan (the sponsor may also be designated).
Something wrong with this question?
Example 3 An urgent request unrelated to the project
A project manager receives a call from an operations manager on the customer side asking for help with an urgent outage that is affecting the customer's daily operations. The outage is unrelated to the project, and neither the project charter nor the contract authorizes the project team to take on work outside the project scope. The organization requires such requests for services outside the project to be handled by the sales manager through its formal service-request and quotation process. The customer believes one member of the project team has the expertise to propose a solution. What should the project manager do FIRST?
Show answer and explanation
Correct answer: C
While the project is under way, the customer asks for help with an operational outage unrelated to the project, and neither the charter nor the contract authorizes the team to take on work outside the scope. What should the project manager do first?
This work is outside the project scope, and neither the charter nor the contract authorizes it, so the project manager has no authority to commit team resources on his own. The customer's need is reasonable and the team has the skill, so it should be handled through formal channels: tell the customer to contact the sales manager, submit a service request and go through the quotation process, so that the organization decides whether to take it on and how to charge for it. That protects the project's scope and authority and still gives the customer appropriate help. The answer is C.
Why the other options are wrong
- A. The problem is indeed outside the project scope, but refusing outright shows the customer no legitimate way to get it solved, which hurts the relationship. When a formal channel exists, point the customer to it first.
- B. Neither the charter nor the contract authorizes this work. Organizing experts and estimating effort on his own amounts to tacitly accepting out-of-scope work and uses up project resources. First send the customer to the formal process, and let the organization decide whether to take it on.
- D. Assigning the task and promising a time without a formal process goes beyond the project manager's authority and would also disrupt the original project work.
Key takeaway Do not commit resources on your own to requests unrelated to the project. Direct the customer to the formal sales and quotation process.
Variation If the customer's request were related to this project but outside the contract scope, the project manager should go through the change process, assess the impact and submit a change request. If the request is beyond the project manager's authority (for example, allocating resources across departments), escalate to the sponsor.
Something wrong with this question?
Common traps
Common trap
- Do not mistake "good at coordinating" for "authorized to decide". For matters beyond what the charter authorizes, ask the sponsor or governing body for approval.
- The sponsor is usually not the person who manages day-to-day tasks. How day-to-day work is organized depends on the approach used.
- The customer who pays and the user who uses are often not the same people. The product owner is listed alongside the sponsor and customer as a role that provides decision leadership, and it is a role distinct from the customer (it can be filled by a customer representative).
- For a request unrelated to the project, do not commit resources on your own. Point the customer to the formal sales and quotation process.
- When expectations about roles differ, hold a meeting to discuss and agree. Do not decide unilaterally, and do not simply pass it to someone else.
- An actively involved sponsor significantly increases the likelihood of achieving the desired outcome, while an absent one might adversely impact the project.
Key takeaways
Key point
- Sources of power (common exam practice): positional power is granted by the organization; expert power and referent power come from the individual; there are also reward power and coercive (penalty) power. Different structures give different amounts of positional power.
- Escalate matters beyond your authority to the sponsor or governing body; send requests unrelated to the project through a formal process.
- Commonly outside the team: senior management, the project steering committee, functional managers, the customer and users. Commonly inside the team: the project manager, the project management team, the project team and experts. The product owner is listed alongside the sponsor and customer and may provide decision leadership outside the authority of the project management team (whether a role belongs to the team depends on the governance structure and approach).
- The sponsor communicates the vision and goals, secures resources, removes obstacles beyond the project team's authority, keeps the project aligned with business objectives, and monitors progress and drives the expected benefits (tracking after the project ends is done by the benefits owner designated in the benefits management plan, and the sponsor may hold that role as well).
- The customer accepts or purchases the result, takes part in clarifying requirements and acceptance (and may provide funding); the user uses the result; the functional manager controls resources; the product owner is listed alongside the sponsor and customer, orders the backlog and is a role distinct from the customer.
This chapter has 7 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.