Project Environment and Organization

Project Management Office

PMP · Project Environment and Organization · 2 lessons · about 26 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

When a company has many projects, each project manager tends to use a different process and nobody coordinates how resources are allocated, so many organizations set up a project management office (PMO). PMBOK 8 Appendix X2 describes the PMO as having moved from a "process-focused entity" to a "customer-oriented partner" that delivers value. Lesson 1 covers what a PMO is, its two kinds of value, the PMO models that PMBOK 8 names (directive, supportive and agile, which are not mutually exclusive), and the traditional three-way classification of supportive, controlling and directive which is still common exam practice. Lesson 2 covers how a PMO supports project managers, how it divides work with them, and its relationship to tailoring, programs, portfolios, agile transformation and maturity. The policies, templates and historical data that a PMO provides are themselves organizational process assets, so this chapter connects directly to the chapter on organizational process assets.

After this chapter you should be able to: define a PMO and distinguish it from a project manager; name the PMBOK 8 PMO models and identify the traditional types by degree of control; name four common ways a PMO supports project managers (a summary that is common exam practice; actual services are tailored to what the organization needs); and know the standard answers to questions such as "a project's procedures conflict with PMO policy", "the company has done a similar project" and "the PMO is transforming to support agile".

Lessons in this chapter

Chapter concept map

PMO (organizational entity: centralizes activities related to the management of portfolios, programs and/or projects; services are tailored to organizational needs; common examples: standardizing governance, sharing resources, methodologies, tools and techniques)

  • PMBOK 8 models: directive PMO · supportive PMO · agile PMO (not mutually exclusive; successful PMOs often blend them)
  • Traditional classification by control (low → high): supportive → controlling → directive
  • Support for project managers: manage (shared resources and best practices) · monitor (audits) · coach and train (policies, templates, training) · coordinate (communication across projects)
  • With project managers: duties vary with organizational needs and the PMO model; usually the PMO provides standards and support while the project manager is responsible for the single, authorized project; in a conflict, verify policy and authority first, then discuss
  • With tailoring, programs and portfolios: develops tailoring guidelines and reviews tailored approaches; in agile transformation, from control to enablement

How this is tested

There are not many topics in this chapter, but the answer patterns are strong. Type-identification questions describe PMO behavior (providing templates, requiring a uniform method, rejecting a proposal and prescribing how to fix it) and ask which type it is. Responsibility questions ask about the PMO's typical duties or ways of supporting projects, and often test whether the PMO does a project manager's work for the project manager (under a directive model a PMO may manage projects directly, but it still does not do the project manager's detailed work for the project manager). Scenario questions ask what to do when a project has similar past experience, when it conflicts with PMO policy, or when the organization transforms to agile. PMBOK 8 discourages rigid classification, but when a question explicitly asks for the traditional control-based classification, answer with supportive, controlling and directive.

Study tips and practice

  • Remember supportive, controlling and directive with three words: "advise, require, direct".
  • "Similar project and the PMO maintains relevant records? Go to the PMO first" and "Conflict with PMO policy? Discuss with the PMO first" each correspond to one type of question.
  • For multiple-response questions, check each option against the keywords "organizational entity, standardization, sharing, enablement". Under a directive model a PMO may manage projects directly, but it still does not do the project manager's detailed work for the project manager.
  • When you study the chapter on tailoring, look back at Lesson 2 of this chapter. The division of responsibility is the same in both places.

Lesson 1

PMO Definition, Value and Types

Lesson video

Lesson overview

When a company has many projects, problems follow: each project manager has a separate way of working, nobody coordinates how resources are allocated, and executives who want to know how projects are going have to ask each manager one by one. Many organizations solve this by setting up a project management office (PMO). This lesson covers what a PMO is and is not, the value it can bring, the PMO models that PMBOK 8 names, and the traditional three-way classification of supportive, controlling and directive, which is common exam practice. The next lesson covers how the PMO supports project managers and how it relates to tailoring, programs and portfolios. ECO: Business Environment domain, Task 1 (Define and establish project governance).

What a PMO is

The PMBOK 8 glossary defines the project management office (PMO) this way: "Organizational entities, typically established as departments or teams, primarily tasked with centralizing activities related to the management of portfolios, programs, and/or projects. The nature of these activities can vary according to the unique needs of each organization." In everyday terms, as common exam practice puts it, it mainly does two things: it standardizes the governance processes related to projects, and it facilitates the sharing of resources, methodologies, tools and techniques across projects. The projects it serves need not be related to each other. PMBOK 8 Appendix X2 stresses that the PMO centralizes related activities, tailors them to the organization's needs, aligns its services with strategic goals, and delivers value that is both actual and perceived by stakeholders.

Two further points. First, a PMO is an organizational entity, not a person. An executive or a project's sponsor is not the PMO. It is typically set up as a department or team (it may also be a temporary or virtual arrangement) and may be called a project management department, project department or center of excellence. Whether something is a PMO depends on its actual functions and authority, not on its name. Second, a PMO does not do the project manager's specific work for the project manager. Appendix X2 says the PMO's role "extends beyond merely executing projects". Under a directive model and with the right authority, a PMO may manage projects directly, so whether it does so depends on the PMO model and its authority; even then, it is not taking over the project manager's detailed work. Usually the project manager is responsible for the results of the project, while the PMO provides standards, tools, training and oversight, and it is not just a department that "manages documents".

The value of a PMO

PMBOK 8 notes that the concept of the PMO has evolved over the last few decades, from a process-focused entity that standardizes methodologies and tools for project management into a customer-oriented partner focused on delivering value perceived by customers and stakeholders within the organization, a shift from process-centric to customer-centric. A modern PMO aligns its services with strategic goals. Its work includes establishing enterprise-wide good practices, fostering cross-team knowledge sharing, strengthening risk management capabilities, and developing project management competencies across the organization.

Its core value proposition is to enable strategic execution, enhance delivery performance, and strengthen organizational capabilities across portfolios, programs and projects. This value is twofold. One side is the actual value delivered, such as cost efficiencies, risk reduction, improved decision-making and accelerated delivery. The other side is the value perceived by stakeholders, which depends on how well the PMO's services resonate with organizational needs and priorities; intangible benefits such as improved collaboration, enhanced transparency and stakeholder confidence also contribute significantly to perceived value. The perception of value is often shaped by the organization's project management maturity, and more mature organizations tend to recognize and leverage PMO contributions more fully.

How do you tell a PMO from a project manager? A simple contrast: the PMO looks at the whole, optimizing resources across projects and managing overall risk, methodology and the governance framework. The project manager looks at this one project, focuses on specific objectives, and controls this project's resources, schedule and risks. One is like the headquarters that plans for the whole, the other like the front-line leader who takes the team forward. They work together, and neither replaces the other.

Worked example: what the PMO did

A home-appliance company with more than a dozen product lines used to let each project manager set the review rhythm, and the same problems kept recurring across projects. After the company set up a PMO, it did three things: it unified the gates and passing criteria from project approval through design reviews to market launch; it built a shared project resource pool and balanced the test equipment among projects each quarter; and every quarter it compiled the problems from all projects into training courses. The first is standardizing governance processes, the second is sharing resources, and the third is sharing methods and building competence. All three address the whole, and none of them is doing a specific project manager's work for that project manager.

Types of PMO

PMBOK 8 Appendix X2 treats the choice of PMO type, model and structure as a nuanced decision. It names models such as the directive PMO, the supportive PMO and the agile PMO, and says they "should not be viewed as mutually exclusive paths. Instead, these models should be seen as a palette of options that can be combined to meet specific organizational needs." It also states that "There are no empirically proven, universally ideal, or consistently more effective PMO models." Successful PMOs often exhibit a blend of characteristics drawn from multiple types.

Traditional sources also classify PMOs into three types by the degree of control a PMO exerts over projects (common exam practice). The mnemonic is "support, control, direct", and the degree of control runs from low to high. "Controlling PMO" is a common exam term; PMBOK 8 names the directive, supportive and agile models instead.

Figure 1 Three traditional PMO types and their degree of control
  • Supportive: acts as a consultant, providing templates, best practices, training, and information and lessons learned from other projects. Control over projects is very low. If a project team faces repeated customer change requests, a supportive PMO can advise it to consult the change management plan and submit the changes to the designated authority; the team must still follow the established governance arrangements.
  • Controlling: besides providing support, it requires projects to comply, for example by requiring a specific framework or methodology, uniform templates and tools, or conformance to governance rules. Control is moderate.
  • Directive: manages and controls projects directly. Project managers are assigned by the PMO and report to it. Control is very high.

To tell controlling from directive, hold on to one point: a controlling PMO requires projects to follow the rules, while a directive PMO manages and controls projects directly. A helper heuristic that is common exam practice is "a controlling PMO requires you to comply; a directive PMO makes the decisions for you." Suppose a PMO reviews a major change proposal, rejects it outright and requires the project manager to revise it as the PMO specifies. That shows the PMO or its governing body has the corresponding approval authority. But a governance committee or change control board may also approve or reject changes under the governance arrangements, so rejecting a change alone cannot establish the type. You must also see whether the PMO manages the project directly and whether the project manager is assigned by it and reports to it. If it manages the project directly, the traditional classification calls it directive. If it only requires uniform templates and processes, and the project manager is still managed through the functional or line management system and does not report to the PMO, it is controlling.

PMBOK 8 also warns that no model is empirically proven to be universally ideal or consistently more effective, and the directive, supportive and agile models should be treated as a combinable palette. Successful PMOs often do not stick to rigid classifications; they blend characteristics drawn from several types. In practice, PMOs are context-specific. A PMO that gives orders, supplies templates and champions best practices may be a hybrid. If a question asks you to classify by the traditional three types, the key is still whether the PMO directly manages and controls projects: if it does, answer directive. Do not simply classify by the highest control feature it has. The traditional "support, control, direct" classification still appears on the exam, so first memorize the three types, then understand the more flexible PMBOK 8 view.

Worked examples

Example 1 Multiple-response: typical PMO responsibilities

Question 1ExampleSelect 2

Which TWO of the following are typical responsibilities of a project management office (PMO)? (Multiple response: choose 2.)

Show answer and explanation

Correct answer: AC

You must pick the two typical responsibilities of a PMO.

The role of a PMO is to unify the governance practices of individual projects and to facilitate the sharing of resources, methodologies, tools and techniques across projects. Establishing organization-wide project governance standards and processes (A) is therefore among its responsibilities. Enabling project teams through templates, training, coaching and lessons learned, and accumulating organizational process assets (C), is also part of the value it provides. Options B and D either overstep or describe the responsibilities too narrowly. The answers are A and C.

Why the other options are wrong

  • B. Doing a project manager's specific work would turn the PMO into the executor of the project. A PMO provides standards, support and oversight, and the project's tasks remain the responsibility of the project manager and the team. Some PMOs may manage projects directly, but that does not mean doing the project manager's specific work tasks for the project manager. A PMO's duties and authority should be tailored to the organization's needs and governance arrangements.
  • D. Collecting and storing documents is only a small part of a PMO's work. Saying it is “only” responsible for this rules out its governance, sharing and enablement functions, and it is not a typical responsibility.

Key takeaway A PMO standardizes governance, facilitates sharing and enables teams. It does not do the project manager's work and is not just a keeper of documents. For multiple-response questions, judge each option separately.

Variation If B were changed to “providing project management templates, training and coaching”, it would be correct. If the question asked how a PMO differs from a project manager, the answer is that the PMO looks at the organization as a whole and standardizes governance, while the project manager is responsible for the results of a single project.

Something wrong with this question?

Report an issue with this question

Example 2 Core question: a PMO that rejects a change proposal outright

Question 2Example

A project manager submits a major change proposal. The PMO reviews it, rejects it outright and tells the project manager to improve the proposal as the PMO specifies before reporting back. The PMO manages the project directly, and the project manager was assigned by the PMO and reports to it. Under the traditional classification, which type of PMO is this?

Show answer and explanation

Correct answer: D

A major change is proposed during the project. The PMO rejects it outright and requires revision as it specifies. To decide which type of PMO this is, look at its degree of control over the project.

Common exam practice classifies PMOs by degree of control over projects as supportive, controlling or directive. PMBOK 8 Appendix X2, by contrast, suggests that directive, supportive, agile and other models are not mutually exclusive paths and can be combined as the organization needs. In this question the PMO manages the project directly, the project manager is assigned by it and reports to it, and it not only rejected the change but also required the project manager to revise it as the PMO specified before reporting back. It is directly deciding how the project is done, which best fits the directive type. The answer is D.

Why the other options are wrong

  • A. A controlling PMO mainly requires projects to comply with established frameworks, standards and governance processes. It may send back noncompliant requests but usually does not dictate exactly how to revise them. In this question the PMO specifies the direction of the revision, which is more like directive.
  • B. A supportive PMO mainly acts as a consultant and a repository of resources, with a very low degree of control. It would not normally manage the project directly, assign the project manager, and dictate the direction of revisions as this PMO does.
  • C. In the traditional classification by degree of control (a common exam term), there are only three types: supportive, controlling and directive. Although PMBOK 8 says models can be combined, the behavior in this question (rejecting directly and specifying the revision) clearly shows directive characteristics, so you cannot choose “hybrid” on that basis.

Key takeaway In the commonly used classification, a PMO that directly decides how a project is done is directive; a controlling PMO mainly requires projects to follow its frameworks and standards.

Variation If the PMO requires all projects to use a uniform change request template, but changes are still approved by authorized people or bodies under the governance arrangements and the PMO does not dictate how to revise them, it is controlling. If the PMO only provides templates and gives advice when a project asks, it is supportive.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A PMO is an organizational entity, not a person, and it is not the same as an executive or a sponsor.
  • A PMO standardizes governance and enables teams. It does not do the project manager's specific work for the project manager, and it is not just a keeper of documents. With the right authority it can manage projects directly (directive).
  • By traditional classification, control runs from low to high: supportive, controlling, directive. "Controlling" does not mean "manages the project directly". The type that manages projects directly and assigns project managers is directive.
  • A suitable, tailored standard process can reduce trial and error and improve efficiency. A process that is too heavy or does not suit the project's context can slow the project down.
  • PMBOK 8 discourages rigid PMO labels, but when a question asks for a classification using the traditional three types, answer with "support, control, direct".

Key takeaways

Key point

  • PMO: an organizational entity that centralizes activities related to the management of portfolios, programs and/or projects (PMBOK 8 glossary). "Standardizes governance processes, shares resources and methods, and serves projects that need not be related" is common exam practice. PMBOK 8 Appendix X2 stresses alignment with strategy and the two sides of value.
  • Value has two sides: actual value delivered and value perceived by stakeholders. A modern PMO is a customer-oriented partner.
  • The project manager manages a single project; the PMO manages the whole.
  • Traditional types, by degree of control from low to high: supportive (consultant), controlling (requires compliance), directive (manages directly and assigns the project manager).
  • PMBOK 8 stresses that there is no universal best model, and successful PMOs often blend characteristics drawn from the directive, supportive and agile models.

Lesson 2

How the PMO Supports Project Managers, and Its Relationship to Tailoring, Programs and Portfolios

Lesson video

Lesson overview

Now that you know what a PMO is, the next questions are these. As a project manager, when should you go to it, and what can you get from it? How do the PMO and the project manager divide the work, and whose view prevails when policy and project practice conflict? After the company transforms to agile, how should the PMO change? This lesson first covers four ways a PMO supports project managers, then its relationship to tailoring, the project manager, programs and portfolios, and agile, and ends with a note on maturity. In scenario questions the PMO is often one of the answers to "the company has a similar project, so where do you look first?" ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery), and Business Environment domain, Tasks 1 and 7 (Define and establish project governance; Support organizational change).

Four kinds of PMO support

A PMO's support for project managers can be summarized in four areas. This summary is common exam practice, and the services a PMO provides are tailored to the organization's needs:

  1. Managing: shared resources and best practices. The PMO manages shared resources and distills each project's best practices into standards. When a project hits a problem like one seen before, it can check the PMO first for historical records and guidelines.
  2. Monitoring: audits. Through project audits, the PMO monitors how well projects comply with standards, so the organization knows where there are deviations and what needs correcting.
  3. Coaching and training: policies, templates and training. The PMO develops and maintains policies, procedures and templates, and also provides coaching and training that help project managers and teams handle difficult situations. Note that helping stakeholders learn to handle a difficult situation is done through "coaching and mentoring", not on-the-job training, contract negotiation or team performance appraisal.
  4. Coordinating: communication across projects. The PMO coordinates communication among projects so that information flows and resource allocation has a basis.

The policies, templates and historical data that a PMO provides are themselves part of organizational process assets, so this lesson connects directly to the chapter on organizational process assets. PMBOK 8 also stresses that a modern PMO should establish enterprise-wide good practices, foster cross-team knowledge sharing, strengthen risk management capabilities, and develop project management competencies across the organization.

Worked example: go to the PMO first, or call a meeting first?

A project manager has just taken over a cross-region procurement project similar to one from last year, and internal coordination problems across regions keep recurring. Step one is to contact the PMO, pull up last year's cross-region coordination and problem-handling records, and ask about the company's recommended escalation process. Step two is to organize the team to adjust the approach to this project's conditions, based on what the records show. The project manager did not start by calling everyone together to discuss it from scratch, and did not rely only on personal contacts to learn what last year's project manager had done. The reason is that the PMO holds standardized historical records and guidelines, from a reliable source with broad coverage.

Dividing work between the PMO and the project manager

The project manager is responsible for the results of the project; the PMO provides standards, tools, training and oversight. Their duties are at different levels. Whether there is a reporting or management relationship between them depends on the organizational structure, governance arrangements and the PMO's authority (a directive PMO may manage projects directly and assign project managers). The work can usually be divided as follows:

ComparisonPMOProject manager
Scope of focusThe organization as a whole; may extend to portfolios and programsA single project
Main workStandardizing governance, sharing resources and methods, audit and oversight, trainingFocusing on objectives, controlling resources, schedule and risk, and delivering results with the tailored approach
What it providesPolicies, templates, tailoring guidelines, historical dataThe plan, execution and results of a specific project

When the two conflict, the handling that is common exam practice is fairly fixed. Suppose the procedures the project intends to use are inconsistent with PMO policy, and the project manager believes they are genuinely necessary for this project because of its technical particularities. The project manager should first verify organizational policy, tailoring authority and the escalation path, and discuss the proposed procedure adjustments with the PMO. Then the person authorized by the governance framework decides whether to approve the deviation or the policy change (escalating to the sponsor or governance board where needed). Do not organize stakeholders to push for a change to the policy on your own, do not act first and report afterward, and do not give up the project's real needs and copy the policy wholesale.

The PMO and tailoring

An organization's standard methodology can be tailored for a project under the PMO's guidance. The PMO usually develops tailoring guidelines and reviews tailored approaches, so that the project's practices both fit its own context and stay within the organization's governance requirements. Tailoring guidelines belong to the "policies, processes and procedures" in organizational process assets, and the details of tailoring are covered in the chapter on tailoring. For now remember the division: the PMO provides rules and standards, and the project manager tailors a version for this project according to its characteristics. PMBOK 8 says a PMO can play a vital role in reviewing and approving tailored development approaches that are well aligned with organizational policy. Tailoring that affects only the internal team can usually be approved by the project manager, while tailoring that goes beyond the project manager's authority or affects external groups is submitted to the PMO or another designated body for review and approval under the governance mechanism.

The PMO, programs, portfolios and agile

A PMO's services can cover three levels (portfolio, program or single project) and are tailored to the organization's unique needs and strategic direction. At the portfolio level it helps set priorities and balance resources. At the program level it coordinates dependencies and benefits among related projects. At the project level it provides standards and support. PMBOK 8 stresses that a modern PMO should align its services with strategic goals and should not focus only on execution.

When an organization adopts an agile or hybrid approach, the PMO should tailor its services to organizational governance, compliance requirements and the degree of team autonomy. It can offer lightweight templates and coaching to help teams use agile methods well, and keep the necessary oversight (PMBOK 8 stresses that there is no universal best PMO model). Common exam practice leans toward a shift from an approval orientation to a service orientation. If a project does deliver iteratively, the PMO can adapt to the iteration rhythm with lightweight oversight, for example by looking at iteration results and the backlog. It neither leaves the team alone nor copies the multi-level approvals and item-by-item reviews of predictive projects.

Maturity

Maturity models are essential tools for organizations aiming to enhance their project management capabilities. They provide a structured framework to assess the PMO's current maturity level, identify areas for improvement and develop a roadmap for growth, and they let the organization set realistic goals by benchmarking against industry standards. More mature organizations generally recognize and leverage the PMO's contributions more fully. PMBOK 8 also notes that a customer-centric maturity model emphasizes aligning PMO services with the organization's strategic goals, and that the PMO's culture and mandate should reflect and support the organization's culture, values and strategic priorities.

Worked examples

Example 1 Core question: taking over a similar project, whom to ask first

Question 1Example

A project manager is appointed to lead a large and complex supply chain information platform project. Its scope is now stable, and the earlier scope increases were approved and their impacts analyzed. Previously he managed only small internal tool development, and since the project entered the Executing focus area he has run into one problem after another. At a stakeholder meeting, a functional manager mentions that the company recently completed a platform project of similar complexity. The company's PMO keeps historical project records and provides guidelines. What should the project manager do?

Show answer and explanation

Correct answer: A

The project is in the Executing focus area. The project manager lacks experience with complex projects, the company has completed a similar project, and the PMO keeps historical project records and provides guidelines. What should the project manager do?

A PMO supports project managers by managing shared resources, identifying best practices, developing policies and templates, and providing guidance. Because the company has done a similar project, its historical records and guidelines are organizational process assets, and the best first step is to consult the PMO and learn from them. The problems the project manager is facing have very likely occurred before. The answer is A.

Why the other options are wrong

  • B. The stem states that the earlier scope increases were approved and their impacts already analyzed, so repeating that analysis is not the most useful next step. The project manager should first draw on the organization's existing experience from a similar project.
  • C. Bringing stakeholders together can be a parallel or follow-up measure, but the stem already offers reusable experience from a similar project, so consulting the PMO for records and guidelines is the most direct first step.
  • D. Continuing the old small-project approach neither draws on the company's similar project nor deals with the current problems, and it defers lessons learned until the project ends. The PMO already holds historical records and guidelines, so consult them first.

Key takeaway When the company has a similar project, consult the PMO for historical records and guidelines first, then consider other approaches.

Variation If the project manager finds no similar project records at the PMO, the next step is to analyze the impacts and root causes of the current problems or discuss them with stakeholders. If the problem were instead “a procurement project's supplier delivery dates keep slipping”, first communicate with the supplier to understand the cause of the delays; the project manager can then consult the PMO's supplier evaluations and problem-handling records.

Something wrong with this question?

Report an issue with this question

Example 2 Core question: project procedures conflict with PMO policy

Question 2Example

The project manager of a data platform migration project is developing the project's governance approach. Several of the procedures he plans to use are inconsistent with policies set by the project management office (PMO), but he believes they are necessary for this project given the particularities of the technology. What should the project manager do?

Show answer and explanation

Correct answer: B

On a project, the project manager is developing the governance approach, and the procedures he wants to use are inconsistent with PMO policy, but he believes they are necessary. What should the project manager do?

A PMO can play a vital role in reviewing and approving project governance and tailoring, with the specific approval authority depending on the organization's governance arrangements. The project manager should not deviate from PMO policy on his own. Since he believes the procedures are genuinely necessary for this project, the right approach is to take the proposed procedure adjustments to the PMO, explain the technical particularities, and consider a change together if needed. That protects the project's real needs and respects the organization's governance requirements. The answer is B.

Why the other options are wrong

  • A. Organizing stakeholders to push for a policy change and asserting that the proposed procedures are better, before discussing the conflict with the PMO, escalates the disagreement prematurely. The project manager should first explain the project's special needs to the policy owner and jointly assess whether an adjustment is warranted.
  • C. Acting first and notifying afterward is telling the PMO after the fact. It skips the PMO's review and approval and violates the PMO's policy requirements.
  • D. Dropping his procedures entirely means not expressing his professional judgment. When the project truly has special needs, he should seek an adjustment through discussion.

Key takeaway When project procedures conflict with PMO policy, go to the PMO to discuss. Do not change the policy yourself or act first and report afterward.

Variation If the question asked “The company is transforming to agile. What should the PMO focus on?”, the answer is moving from control to enablement and coaching. If it asked how a PMO oversees projects under a hybrid approach, the answer is lightweight oversight at the iteration rhythm, not copying the multi-level approvals of predictive projects.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When project procedures conflict with PMO policy, do not change the policy yourself or organize others to push for a change, and do not act first and report later. Discuss with the PMO first, and consider a change together if needed.
  • When there is a similar project or problem and the PMO maintains relevant material, check its historical records and guidelines first, then decide the next step.
  • When a PMO transforms to support agile, it does not abolish oversight or add approvals. It moves from control to enablement and coaching, and under a hybrid approach it provides lightweight oversight.
  • "Coaching and mentoring" is how you help people learn to handle difficult situations. It is not the same as on-the-job training, contract negotiation or performance appraisal.
  • The policies, templates and historical data a PMO provides are organizational process assets.

Key takeaways

Key point

  • Four kinds of PMO support: managing (shared resources and best practices), monitoring (audits), coaching and training (policies, templates and training) and coordinating (communication across projects).
  • When there is a similar project and the PMO maintains relevant material, check its historical records and guidelines first.
  • Division of work: standards and the whole belong to the PMO, a single project belongs to the project manager. If there is a conflict with PMO policy, discuss with the PMO first.
  • The PMO develops tailoring guidelines and reviews tailored approaches; its services can cover portfolios, programs and projects.
  • In an agile transformation, move from control to enablement and coaching, and under a hybrid approach provide lightweight oversight. The more mature the organization, the better it can leverage the PMO.

This chapter has 9 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.