Organizational Structures

PMP · Project Environment and Organization · 2 lessons · about 26 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The same project can be easy in one organization and very hard in another. How many people the project manager can call on, how much money the project manager can spend, and whom team members actually listen to are all shaped by the organizational structure. PMBOK 8 treats organizational structure as an internal enterprise environmental factor and compares the effect of different structures on projects in Table 2-1. Lesson 1 covers the three main structures: functional, project-oriented and matrix (weak, balanced, strong). Roughly speaking they are arranged from the least project manager authority to the most (functional and weak matrix are both rated low). Lesson 2 adds the organic or simple, multidivisional, virtual or network and hybrid forms, gives a side-by-side comparison and three questions for classifying a structure, and ends with what to do when your authority is not enough.

After this chapter you should be able to: state the project manager's authority, role (full-time or part-time) and resource availability under each structure; classify a structure from a scenario description; answer questions such as "In which structure does the project manager have the most control over resources?" and "What do team members worry about most at closing?"; and, when departments disagree, know to negotiate first and seek support next, rather than going over someone's head or proposing a reorganization.

Lessons in this chapter

Chapter concept map

Project manager's authority:  Low ─────────────────────────────────────────────────▶ High  
Functional  → Weak matrix → Balanced matrix → Strong matrix → Project-oriented  
Part-time     Part-time     Part-time         Full-time       Full-time  
Resources:  
Low           Low           Low to moderate   Moderate to high  High to almost total  
Other forms: Organic or simple · Multidivisional · Virtual/network · Hybrid  
Three questions: Full-time? Who do members report to? Must people be placed after the project ends?  

How this is tested

Questions in this chapter mostly ask you to read a description and identify the type. The stem gives clues such as the reporting line, who evaluates performance, who makes the final call, and where people go after the project, and you decide whether the structure is functional, weak matrix, project-oriented and so on. There are also recall questions ("In which structure are resources most under the project manager's control?" "In which structures is the project manager usually full-time?") and scenario questions about what to do when a cross-department disagreement arises in a weak matrix or functional organization. The entries in PMBOK 8 Table 2-1 are the basis for these questions.

Study tips and practice

  • Draw a five-column table (authority, role, resource availability, who the team reports to, special notes) and reproduce it from memory twice.
  • When you work a question, circle the clue words: full-time and part-time (features in Table 2-1). Words such as "performance evaluation", "where people go after the project", "who makes the final call" and "negotiate" are helper clues that are common exam practice.
  • Remember that there is no best structure. Be cautious about any option that says the structure should be changed to another type.
  • Review this chapter together with the lesson "The Project Manager's Power and Authority, and Other Key Roles": structure affects how much positional power the project manager has, and when positional power is small the project manager can lean more on expert power, referent power and negotiation.

Lesson 1

Functional, Project-Oriented and Matrix Organizations

Lesson video

Lesson overview

The same project manager can have very different power in different companies. In one company, even borrowing a single person means asking another department head for permission; in another, the whole team reports to the project manager. The difference comes from the organizational structure. Organizational structure is itself an enterprise environmental factor that the project team cannot directly control. The project manager must understand it and adapt to it, and may propose improvements through appropriate governance channels when needed. This lesson covers the three most important structures: functional, project-oriented and matrix (weak, balanced and strong). The lesson takes the functional and project-oriented structures first, then the matrix types in between; the next lesson adds the other forms and a full comparison. Most structure questions on the exam are "read the description, name the type", so for each type you need to remember a few features that identify it at a glance.

Why organizational structure matters

Organizational structure determines three things: how much authority the project manager has to mobilize resources, whom team members listen to, and how information flows between departments. PMBOK 8 notes that determining the appropriate structure involves considerations such as resource allocation efficiency, decision-making speed, communication pathways, and the distribution of authority and responsibility, and that the optimal structure depends on variables such as the organization's size, industry, geographical spread, strategic objectives and project complexity. "There is not a one-size-fits-all structure for any given organization." So you cannot declare one structure the best without context. The exam usually gives you conditions in the stem and asks you to identify the structure, or to say what will happen under it.

Figure 1 Organizational structure and project manager authority (a taller bar means more authority)

Functional (centralized)

A functional organization is divided by the kind of work done, such as engineering, manufacturing and finance. PMBOK 8 Table 2-1 describes it this way: the project manager's authority is low; the role is part-time and may or may not be a designated job role such as coordinator; resource availability is low. Team members' day-to-day work, performance reviews and promotion all belong to the functional manager, and common exam practice portrays project coordination as running mainly through the functional manager, so the project manager often acts more like a liaison.

The advantages are clear specialization, clear supervisors and clear career paths, which suit stable products with little cross-department work. The costs are that the project is cut into pieces, cross-department matters must be coordinated level by level, departments easily pass the buck, and innovation suffers. Typical identifying features: members "listen only to the functional manager", the project manager "has no say", and workload and performance are evaluated by the functional manager.

Project-oriented

A project-oriented organization is divided by project. The project manager's authority is high to almost total, and the role is full-time and a designated job role. Resource availability is high to almost total. Team members usually report directly to the project manager, and the team is more likely to be set up around the project, although it can still be affected by the organization's total resources and by project priorities. Because resources and authority are concentrated on the project, decision-making and coordination are usually faster, but the actual result still depends on the situation.

Remember the costs too. Resource utilization may be low, since key people mostly serve the current project. Without a standing functional team that keeps building expertise, technical skills can fall behind. When the project ends, people may have nowhere to go, and their old positions may already be filled, so during closing, team members often worry about what comes next. Exam tip (common exam practice): a stem that mentions arranging where the team goes after the project ends can be a hint toward project-oriented, but you must combine it with the project manager's authority, whether the role is a full-time designated one, the team's reporting line and resource availability. (Reassigning or releasing project staff at closing is a normal closing activity, and matrix organizations face it too.)

Matrix: weak, balanced and strong

A matrix organization lays a project line over the functional line, so team members belong to a functional department and also serve the project. This produces "dual reporting". There are three kinds, ordered by project manager authority from least to most:

  • Weak matrix: work group arranged by job function. The project manager's authority is low; the role is part-time, done as part of another job and not a designated job role such as coordinator; resource availability is low. It is close to the functional structure, and members mainly listen to the functional manager. Identifying clues that are common exam practice: the project manager needs the functional manager's approval to use people, and the functional manager often has the final word on which tasks to take on.
  • Balanced matrix: the project manager's authority is low to moderate; the role is part-time, embedded in the functions as a skill; resource availability is low to moderate. Common exam practice: the project manager and functional manager have roughly equal power, and using people requires agreement between them.
  • Strong matrix: the project manager's role is a function of its own, with moderate-to-high authority; the role is full-time and a designated job role; resource availability is moderate to high. The project manager has strong power to allocate people and can coordinate members directly, but resources still belong to the functional departments.

Project managers in a matrix typically face three difficulties. First, resources belong to functional managers, so using people takes negotiation. Second, the project manager often has only advisory power and no power over employees' performance evaluations (this depends on the organization's delegation; it is a common exam generalization), and members tend to respond first to whoever controls their performance review, so in a weak matrix members usually respond first to the functional manager (in balanced and strong matrices it depends on the two managers' authority and on organizational delegation). Third, one person may work on several projects, so priorities conflict. The remedies differ by problem. For resource and priority conflicts, negotiate first with the functional managers, resource managers and other project teams, and agree on allocation rules. If members listen only to the functional manager, seek input into their performance appraisals or some share in them. If the matter is beyond the project manager's authority, seek support from the sponsor or governing body.

Worked example: how to classify a scenario

An industrial equipment company has a project management department, and project manager Daniel works full-time in that role. On a new production line integration project he can directly assign the engineers sent by various departments, but to borrow an inspector from the quality department he must first agree on timing with the quality manager. After the project, the engineers return to their own departments.

Classification: full-time, designated role, moderate-to-high authority point to a strong matrix. Having to agree on timing for the inspector shows that resources still belong to the functional department, so it is not project-oriented. The engineers returning to their departments after the project further shows that people still belong to the functional departments, which supports the strong matrix (where people go afterward cannot, by itself, rule out project-oriented). Conclusion: strong matrix.

Worked examples

Example 1 Core question: the functional manager evaluates members, so what type is it

Question 1Example

On an agile project, a coordinator temporarily appointed by a functional manager is organizing the daily coordination meeting for the first iteration. The coordinator notices that team members are anxious about whether the project can be completed and are often interrupted by ad hoc requests from the functional manager. Members report only to the functional manager, who evaluates their workload and performance. The organization has no project manager role, and the coordinator has almost no say in how work is assigned. Which type of organization is this?

Show answer and explanation

Correct answer: C

On an agile project, a coordinator is organizing the daily coordination meeting for the first iteration. The question asks you to identify the organizational structure from the reporting and evaluation relationships.

The functional manager evaluates members' workload and performance, the functional manager's ad hoc requests interrupt the team, there is no project manager role, and the coordinator has almost no say. These are features of a functional (centralized) organization: the project manager's authority is low, the role is part-time, resource availability is low, and the team mainly listens to the functional manager. The agile project in the stem is only background. Focus on the reporting and evaluation relationships. The answer is C.

Why the other options are wrong

  • A. In a project-oriented organization, members report to the project manager, whose authority is high to almost total. In the stem, members report only to the functional manager and the organization has no project manager role, so the situation is the opposite.
  • B. In a strong matrix the project manager's authority is moderate to high and the project manager has considerable authority over resources. The stem has no project manager role and a coordinator with almost no say.
  • D. An organic (simple) organization has a flexible structure, few layers and little supervision. In the stem the functional manager repeatedly intervenes and evaluates members, which does not fit.

Key takeaway When members report only to the functional manager, are managed and evaluated by that manager, and the organization has no project manager role, the organization is functional.

Variation If “members report to the project manager and must be placed elsewhere after the project”, it is project-oriented; if “the project manager is full-time and can coordinate members directly, but must agree on timing to borrow quality department staff”, it is a strong matrix.

Something wrong with this question?

Report an issue with this question

Example 2 Core question: the functional manager makes the final call on later tasks

Question 2Example

The team for an equipment energy-efficiency project has been formed, and members report to both the project manager and a functional manager. The project manager's authority is low, and the role is held part-time by a person from a functional department and is not a designated job role. After one phase is completed, the functional manager makes the final call on which tasks to take on next. Which organizational type does this describe?

Show answer and explanation

Correct answer: B

The team for an equipment energy-efficiency project has been formed. Members report to both the project manager and a functional manager. The project manager has low authority, works part-time and holds no designated role, and after one phase the functional manager decides which tasks follow. The question asks which organizational type this is.

Members who report to two managers at once indicate a matrix, not a functional organization. In PMBOK 8 Table 2-1, the weak matrix project manager has low authority and a part-time role that is done as part of another job and is not a designated job role, which matches the stem. A balanced matrix has authority of low to moderate, and a strong matrix has moderate to high authority with a full-time, designated role. “The functional manager makes the final call on later tasks” is an identifying clue that is common exam practice. It shows that the final decision rests with the functional manager, which also points to a weak matrix. The answer is B.

Why the other options are wrong

  • A. In a strong matrix the project manager has moderate to high authority and is full-time in a designated role. In the stem the project manager has low authority and is part-time, and the functional manager decides task selection.
  • C. In a functional organization the reporting line runs only through the functional manager. In the stem members report to both the project manager and the functional manager, which already makes it a matrix.
  • D. In Table 2-1, a balanced matrix project manager has authority of low to moderate, and by the common exam clue the two managers have comparable power and must negotiate. The stem says the project manager's authority is low and the functional manager has the final say, so it is not balanced.

Key takeaway Weak matrix: low authority, part-time, not a designated role (Table 2-1). “Who makes the final call” is an identifying clue that is common exam practice.

Variation If it said “later tasks are decided by agreement between the two managers, and the project manager's authority is low to moderate”, it leans balanced matrix; if it said “the project manager makes the call and is full-time in a designated role”, it is a strong matrix.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Under the functional structure the project manager is not worthless, just low in authority and part-time, working mainly by coordinating; team members' performance belongs to the functional manager.
  • Project-oriented is not "all-powerful": resource utilization can be low, technology can fall behind, and people need to be reassigned at closing.
  • Among the three matrix types, only the strong matrix has a full-time, designated project manager role; the weak matrix project manager is neither full-time nor in a designated role. Project-oriented is also full-time and designated.
  • A balanced matrix simply has authority comparable to the functional manager's; it is not "the best structure".
  • The shared features of matrix structures are dual reporting and competition for resources. When the project manager needs people and the functional manager disagrees, the weak and balanced matrices usually call for negotiation with the functional manager; a strong matrix project manager may have considerable direct power to allocate people, depending on organizational delegation.
  • Organizational structure is itself an enterprise environmental factor, and the project manager cannot change it unilaterally; the usual approach is to coordinate within the existing structure. If needed, the project manager may suggest improvements and push for evaluation through appropriate governance channels, but should not use "get someone to change the structure" as a substitute for solving the problem within the current structure.

Key takeaways

Key point

  • Authority runs roughly from least to most: for functional and weak matrix, the project manager's authority is low; balanced matrix, low to moderate; strong matrix, moderate to high; project-oriented, high to almost total (Table 2-1).
  • Functional: project manager authority low, part-time, members listen to the functional manager. Project-oriented: authority high to almost total, full-time, and members report to the project manager. Where the team goes next at closing is only a helper clue, since personnel are reassigned or released at closing in other structures too.
  • Weak matrix: low, part-time. Balanced matrix: low to moderate, part-time. Strong matrix: moderate to high, full-time, designated role (all of this is from Table 2-1). "Who makes the final call" and "both managers negotiate" are identifying clues that are common exam practice.
  • Shared features of matrix structures: dual reporting, competition for resources, and a project manager who often has only an advisory voice in performance appraisal (a common exam generalization that depends on organizational delegation).
  • There is no one-size-fits-all best structure, and organizational structure is an enterprise environmental factor.

Lesson 2

Other Organizational Forms and Comparing Structures

Lesson video

Lesson overview

The previous lesson covered the three main structures. PMBOK 8 Table 2-1 also lists several less common forms: organic or simple, multidivisional, virtual or network, and hybrid. They are not heavily tested, but they sometimes appear as "identify the organizational form" scenario questions. This lesson first explains the features and recognition clues of these forms, then puts all the structures in one table, gives three questions for classifying a structure, and finally covers what a project manager generally does when a disagreement arises across departments under different structures. ECO: Business Environment domain, Task 1 (Define and establish project governance) and Task 4 (Remove impediments and manage issues).

Other organizational forms

TypeWork group arrangementProject manager's authorityProject manager's roleResource availability
Organic or simpleFlexible; people working side by sideLowPart-time role; may or may not be a designated job role such as coordinatorLow
MultidivisionalOne of the following: product; production processes; portfolio; program; geographic region; customer type. May replicate functions for each division with little centralizationLowPart-time role; may or may not be a designated job role such as coordinatorLow
Virtual/networkNetwork structure with nodes at points of contact with other peopleLow to moderateFull-time or part-time roleLow to moderate
HybridMix of other typesMixedMixedMixed

Organic or simple: people are arranged flexibly and rely on close cooperation. There are usually few layers, as in a small team or a start-up. The project manager role is often held by someone as a side duty. Recognition clue: a few people work side by side and divide the work by agreement.

Multidivisional: the organization is divided by product, region, customer type and so on into semi-autonomous divisions, and each division may have its own sales, finance, procurement and other functions, with little centralization. Recognition clue: one headquarters plus several divisions, each of them nearly self-sufficient. The project manager mainly relies on the resources of his or her own division; when resources from other divisions are involved, coordination usually goes through the appropriate management channels, and authority remains low.

Virtual or network: the core is a network structure in which people are connected at points of contact. Members are often in different locations and cooperate over the network, but geographic dispersion is not a requirement. Recognition clue: members work together through networked points of contact and collaborate remotely. Temporary assembly and disbanding once the goal is reached may occur, but those clues do not determine the type on their own. This form is also called a network structure; the project manager may be full-time or part-time, with authority low to moderate.

Hybrid: a combination of two or more organizational structure types. In reality, many companies are functional overall but set up a temporary strong matrix or project-oriented team for a major project. So do not look only at the company's nominal structure; look at what authority the project manager actually has on this project.

Comparing the structures

Putting the five main structures into one table is the safest way to memorize them. The first four columns come from PMBOK 8 Table 2-1; the "Team reports to" column is not in Table 2-1 and is a clue that is common exam practice.

Structure typeProject manager's authorityProject manager's roleResource availabilityTeam reports to
FunctionalLowPart-timeLowFunctional manager
Weak matrixLowPart-timeLowMainly the functional manager
Balanced matrixLow to moderatePart-timeLow to moderateBoth about equally
Strong matrixModerate to highFull-timeModerate to highBoth, leaning toward the project manager
Project-orientedHigh to almost totalFull-timeHigh to almost totalProject manager

For a scenario question, use three questions to classify the structure:

  1. Is the project manager full-time? A full-time project manager with high authority points to a strong matrix or project-oriented.
  2. Whom do team members report to? Only to the project manager: project-oriented. To two bosses at once: matrix. Only to the functional manager: possibly functional, possibly a weak matrix, so combine the Table 2-1 features such as the project manager's authority, whether the role is a designated one, and resource availability.
  3. Does the stem mention placing people after the project ends? Common exam practice: if the stem clearly stresses that members have no fixed functional home and must be reassigned after the project, that can serve as a helper clue for project-oriented, but the mere mention of placing people cannot settle the answer.

"In which structure does the project manager have the most control over resources?" The answer is project-oriented. "In which structures is the project manager usually full-time?" Possibly strong matrix or project-oriented. Both are full-time, designated roles, so you also have to look at authority (moderate to high for a strong matrix, high to almost total for project-oriented) and resource availability. "Full-time, designated role" alone cannot separate the two. When both appear as options you must find conditions such as authority, resource availability and reporting lines. If the stem gives none of these, information is insufficient, so go back and look for other clues in the stem instead of favoring one by impression. Budget control and communication paths follow the same pattern: the closer to functional, the more you must coordinate level by level through the functional manager; the closer to project-oriented, the more the project manager can decide directly.

What to do when the structure is not enough

Organizational structure is an enterprise environmental factor that the project team cannot control directly, so the project manager should usually first coordinate within the existing governance and authority. When authority is not enough, the general approach is "negotiate, communicate, seek support". It is not to go over someone's head, not to force people to be reassigned, and certainly not to start by recommending a change to the organizational structure (where needed, a change can be proposed or supported through formal channels).

  • Disagreement with the functional manager in a weak matrix (for example, different parameter requirements for a deliverable): negotiate with the functional manager first, and find a solution together. Do not demand that an outside party follow only your requirements, do not simply log it in the risk register, and do not first spend time working out the reporting relationships.
  • A task delayed by a functional department in a functional organization (for example, the information technology department has other priorities): meet the department manager, find out why the task is delayed and agree on a schedule. Do not unilaterally change the schedule to accommodate the delay, and do not outsource the whole job on your own. If the agreed resolution requires a change to a controlled schedule, assess the impact and follow the applicable change process before updating it.
  • Members listen only to the functional manager: seek input into performance appraisals, and if needed ask the sponsor to step in.

Worked example: virtual or multidivisional?

Two companies, two scenarios. Company A: a design studio hears about a landscape tender in a city, invites freelance designers from five cities to work on the proposal online, and the team disbands after the contract is won and the project ends. Company B: a corporation has three regional branches in the northeast, north and south, each with its own procurement, finance and project management. Headquarters only sets annual targets, and a north-region project manager who wants to use south-region staff has to go through headquarters.

Company A: temporary assembly, networked collaboration, disbanding once the goal is met: virtual (network). Company B: divided by region, functions replicated in each unit, low centralization: multidivisional, and the project manager's authority is low.

Worked examples

Example 1 Core question: a temporarily assembled expert team

Question 1Example

A consulting firm spots a short-term overseas bid opportunity. It temporarily assembles experts from partner organizations in several cities, and they complete the bid by collaborating over the network. The team disbands once the award is announced. Which organizational form does this arrangement represent?

Show answer and explanation

Correct answer: D

For a short-term overseas bid opportunity, a consulting firm temporarily assembles experts from partner organizations in several cities, who complete the bid by collaborating over the network. The team disbands after the award. The question asks which organizational form this is.

In PMBOK 8 Table 2-1, the virtual/network form has a network structure with nodes at points of contact with other people, and members are dispersed and work together over the network. In the stem the experts come from partner organizations in several cities and collaborate over the network throughout, which fits a virtual network structure. “Temporarily assembled and disbanded after the award” is only a helper clue and cannot decide the type alone. The answer is D.

Why the other options are wrong

  • A. An organic or simple organization is informal and flexible, with little work specialization, few management layers and light supervision. It stresses flexible collaboration, whereas the stem's defining feature is members connected through networked points of contact (here across several cities).
  • B. A multidivisional organization has a center and several semi-autonomous divisions or units. The center sets financial targets and each unit replicates functions. That is different from networked collaboration among dispersed members.
  • C. A hybrid combines several structure types. The stem describes no mix of several structure types; the network collaboration is the prominent feature.

Key takeaway Dispersed members who collaborate through networked points of contact indicate a virtual network structure; temporary assembly and disbanding at completion are only helper clues.

Variation If a corporation has three branches in the northeast, north and south, each with its own procurement, finance and project management, and headquarters sets only annual targets, it is multidivisional; if a few people work flexibly together with no fixed hierarchy, it is organic or simple.

Something wrong with this question?

Report an issue with this question

Example 2 Core question: conflicting requirements in a weak matrix

Question 2Example

In a weak matrix organization, the project manager of a prototype-production project receives feedback from an outside machining shop: the parameter requirements that the functional manager set for a deliverable conflict with the project manager's requirements, so machining cannot continue. What should the project manager do?

Show answer and explanation

Correct answer: C

On the project, the two managers disagree about the requirements, and the disagreement is already holding up machining. The question asks how the project manager should respond.

The stem makes clear this is a weak matrix; under common exam practice, the functional manager has more power than the project manager there. The two managers' requirements for the same deliverable conflict, and machining has already stopped, so this is a disagreement that must be resolved through communication. The project manager should consult the functional manager first and work out a solution together. That is the standard way to manage stakeholders, and it matches the approach of “when authority is short, rely on communication and negotiation”. The answer is C.

Why the other options are wrong

  • A. The disagreement has already stopped machining. It is a problem that has occurred, not an uncertain risk, and it should not be recorded in the risk register.
  • B. Under common exam practice, the functional manager has the greater power in a weak matrix, so the project manager cannot force the machining shop to follow only the project manager's parameters. That would deepen the conflict.
  • D. The stem already tells you the reporting relationship (weak matrix). Looking it up would not resolve the disagreement and would only delay action.

Key takeaway In a weak matrix, when you disagree with the functional manager, negotiate first and solve it together. Do not go around the manager or force the other party.

Variation If the organization were functional and the information technology department delayed a project task because of other priorities, the approach would be the same: meet the department manager, find out why, and agree on a schedule. If the disagreement involves resource allocation beyond your authority, ask the sponsor to coordinate.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • What identifies a virtual (network) structure is the network structure, with members connected through points of contact (geographic dispersion and remote work are common but not required). Temporary assembly and disbanding once the goal is met are only helper clues and cannot decide the type alone. It is not "hybrid", and it is not simple.
  • A multidivisional organization may replicate functions in each division, and the project manager's authority is usually low. Do not mistake it for project-oriented.
  • Classify the structure by the authority the project manager actually has, not by the company's nominal chart. Hybrids are common in practice.
  • A question that asks "which structure should it be changed to" is usually not heading in the right direction. The safer approach is to negotiate, communicate and seek delegation within the existing structure.
  • A stem that mentions arranging where members go after the project is only a helper clue for project-oriented. Combine it with the project manager's authority, whether the role is full-time, and the reporting line.

Key takeaways

Key point

  • Other forms: organic or simple, multidivisional, virtual or network, hybrid. They are not heavily tested; classify them using the Table 2-1 features.
  • Virtual: network structure, members connected through points of contact (geographic dispersion and remote work are common but not required; temporary assembly and disbanding at completion are only helper clues). Multidivisional: divided by product, region or customer, possibly with functions replicated in each division, and low project manager authority.
  • Resources most under the project manager's control: project-oriented. Full-time project manager: strong matrix and project-oriented.
  • Three classification questions: Is the project manager full-time? Whom does the team report to? Must people be placed after the project?
  • When authority is insufficient, negotiate, communicate and seek sponsor support. Do not go over someone's head or force people to be reassigned.

This chapter has 13 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.