Project Environment and Organization
Organizational Process Assets
PMP · Project Environment and Organization · 3 lessons · about 39 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Enterprise environmental factors are the conditions a project must face; organizational process assets (OPAs) are the stock a project can draw on: the organization's own plans, processes, documents, templates and knowledge repositories, together with the lessons learned and historical information left by earlier projects. This chapter takes three steps. First, the definition, sources and the two main categories of content. Second, OPAs set side by side with enterprise environmental factors, with a method for telling them apart. Third, the highest-frequency use in scenario questions: when you meet an unfamiliar situation, or the stem hints at experience from similar projects, common exam practice is to consult OPAs first; what you borrow has to be fitted to this project; knowledge repositories such as lessons learned are updated continuously during the project; and at the end of the project or phase, lessons learned go into the lessons learned knowledge repository. This is the most heavily tested chapter in the topic, and "use and update" is the key part.
After this chapter you should be able to: state the definition, the sources and the two characteristics of OPAs (first, they come from inside the organization and can be updated; second, they are available to be used); sort common assets into "policies, processes and procedures" and "organizational knowledge repositories"; use three questions to tell them apart from enterprise environmental factors; know that, when you take over an unfamiliar situation, when a similar problem appears or when you prepare a plan, the first step is to consult OPAs; and say what belongs in the knowledge repository at closing. ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery).
Lessons in this chapter
- Lesson 1: Organizational Process Assets: Definition, Sources and Categories. Internal, updatable, usable; coming from the organization, a portfolio, a program or other projects; the two main categories of content; tailoring guidelines. Includes two worked examples.
- Lesson 2: Telling Enterprise Environmental Factors and Organizational Process Assets Apart. A comparison table, three test questions, boundary cases (a company-wide system versus a risk breakdown structure, structure versus process, external versus internal standards). Includes two worked examples, one of them multiple-response.
- Lesson 3: Using and Updating Organizational Process Assets. Four signals for checking first, borrowing is not copying, updating at any time and archiving at closing, correcting outdated content. Includes three worked examples.
Chapter map
Organizational process assets (internal to the organization, updatable, available for use)
- Policies, processes and procedures: tailoring guidelines · life cycles and methods · templates · supplier lists · change control procedures · SLAs · closure guidelines
- Organizational knowledge repositories: configuration management · financial data · historical information and lessons learned · issue and defect data · metrics · project files from previous projects
Use: check first when a problem arises → borrow and fit to this project → update the knowledge repositories continuously during the project, and update policies, processes and procedures according to organizational policy → archive into the repository at closing
Telling it apart from EEFs: is it an environmental condition the team cannot directly control, or a practice, record or knowledge the organization has built up for projects to use? If the latter, is it a process-type asset governed by organizational policy, or a knowledge repository that the project continuously updates?
How the exam tests this
Questions in this chapter fall into roughly three kinds. Classification questions ask whether an item is a policy, process or procedure or an organizational knowledge repository, or whether it is an organizational process asset or an enterprise environmental factor, including one multiple-response question. Scenario questions: the project hits a problem, takes on an unfamiliar task or lacks experience with similar work, and the question asks what to do "first"; the answer is often to consult the lessons learned and historical data in the OPAs. Closing questions ask when lessons learned are archived and where. What the three kinds share at bottom is that OPAs can be "updated and used," while enterprise environmental factors are something to "consider, adapt to or be constrained by."
Study suggestions and practice
- First memorize the "four signals" in Lesson 3; they cover most of this chapter's scenario questions.
- For classification questions, use the three test questions rather than relying on remembering lists.
- After the practice questions, pick a few you got wrong and write down "what was the signal word in this question?"; that is more useful than doing many more questions.
- When you read the scenario questions in the later topics with the thought "is there a ready answer in the OPAs?", you will find this pattern everywhere.
Lesson 1
Organizational Process Assets: Definition, Sources and Categories
Lesson overview
If enterprise environmental factors are the conditions a project has to face, then organizational process assets (OPAs) are the stock it can draw on: the company's ready-made processes and templates, and the data and experience earlier projects left behind. This lesson sets out what OPAs are, where they come from and what characterizes them, then divides them into the two main categories, "policies, processes and procedures" and "organizational knowledge repositories," and says where tailoring guidelines sit. The next lesson compares them with enterprise environmental factors, and the one after covers how to use and update them. It corresponds to ECO: Process domain, Task 1 and Business Environment domain, Task 1.
What organizational process assets are
In the words of PMBOK 8: "Organizational process assets, depending on the industry, organization, and working model, may include the plans, processes, documents, templates, and knowledge repositories specific to and used by the performing organization. These assets influence the management of the project." Any artifact, practice or knowledge from any or all of the performing organizations involved in the project, which can be used to execute or govern the project, counts; the organization's lessons learned from previous projects and historical information, as well as lessons from previous work carried out, are included too.
There are four sources: the organization itself, a portfolio, a program, another project, or a combination of these. For instance, the company's standard project management plan template comes from the organization; a risk library or standard shared at the program level comes from the program; the schedule of a similar project done last year comes from another project. Historical schedule records shared by partners in a joint venture count too, because the source can be any performing organization involved in the project.
They have two characteristics. First, they come from inside the organization and can be updated. For organizational knowledge repositories, authorized project team members may revise and add to them as needed at any time in the project, without waiting for closing. Policies, processes and procedures have to be updated in line with the applicable organizational policy; where the organization encourages tailoring, templates, life cycles, checklists and the like can be tailored according to the tailoring guidelines. Second, they are available to be used. Many project management processes take them as an input, such as completed schedules, risk data and earned value data. As common exam practice, use this rough contrast: enterprise environmental factors are mostly conditions to assess and adapt to, and organizational process assets are assets available to be used, which screens out most confusion. But this is not an absolute split: not all enterprise environmental factors are rules that must be obeyed, and the policies, processes and procedures among OPAs must be used as the organization prescribes; PMBOK 8 says they can be updated only by following the appropriate organizational policies, while organizational knowledge repositories can be updated continuously.
Key point
Organizational process assets: the performing organization's plans, processes, documents, templates and knowledge repositories, plus lessons learned and historical information from earlier projects; they come from the organization, a portfolio, a program or other projects; internal resources, updatable, mainly there to be "used."
Two main categories of content
PMBOK 8 divides organizational process assets into two categories: policies, processes and procedures; and organizational knowledge repositories. A rough prompt (common exam practice): ask whether the asset is mainly something that says how the organization requires things to be done (the first category: policies, processes, procedures and templates), or something used to store and retrieve project and organizational information (the second category: organizational knowledge repositories). The specific category depends on how the asset is organized and on the categories PMBOK 8 lists. For example, a configuration management knowledge repository is an organizational knowledge repository, and it may also hold the baselines of standards, policies, procedures and project documents, so you cannot decide only by whether the content "says how things are done."
Policies, processes and procedures
Generally, these assets are not updated as part of the work required to achieve the outcomes of the project and are usually established by the project management office (PMO) or another function outside of the project. They can be updated only by following the appropriate organizational policies. Some organizations encourage project teams to tailor templates, life cycles and checklists for the project, and in these cases the team should tailor those assets according to the needs of the project. They include but are not limited to:
- Guidelines and criteria for tailoring the organization's set of standard processes and procedures to the specific needs of the project, that is, tailoring guidelines;
- Product and project life cycles, methods and procedures, such as project management methods, estimation metrics, process audits, improvement targets and checklists;
- Templates, such as for project management plans, project documents, project registers, report formats, contracts, risk categories, risk register templates, probability and impact matrices and stakeholder register templates;
- Preapproved supplier lists, contract templates and proposal evaluation criteria;
- Change control procedures, traceability matrices, and issue and defect management processes;
- Resource availability control and assignment management policies, and processes for prioritizing, approving and issuing work authorizations;
- Service-level agreements (SLAs) and project closure guidelines or requirements.
Organizational knowledge repositories
These assets change along with project information: financial performance, lessons learned, performance metrics, issues and defects and the like are refreshed continually over the project life cycle. They include but are not limited to: configuration management knowledge repositories (version information of software and hardware components, and baselines of standards, policies, procedures and project documents); financial data repositories (labor hours, incurred costs, budgets, project cost overruns and so on); historical information and lessons learned knowledge repositories (project records and documents, project closure information, results of previous project selection decisions and previous project performance information, and information from risk activities); issue and defect management data repositories; data repositories for metrics; and project files from previous projects such as scope, cost, schedules, performance measurement baselines, project calendars, schedule network diagrams, risk registers, risk reports and stakeholder registers.
Worked example: sorting eight items into the two categories
The PMO of a medical device company holds the following: (1) a standardized change request form; (2) a summary of actual costs from three projects last year; (3) a list of approved testing laboratories; (4) lessons learned records completed at project closure; (5) tailoring guidelines saying which reviews a small project may omit; (6) a legacy defect database; (7) a list of project risk categories; (8) a contract template.
Classification: items 1, 3, 5, 7 and 8 say "how to do it," so they are policies, processes and procedures; items 2, 4 and 6 "record what has happened," so they are organizational knowledge repositories. All eight are organizational process assets, and none is an enterprise environmental factor.
Tailoring guidelines and using "rule-type assets"
The first category of assets is generally not updated by the project, but that does not mean it can only be applied as is. Where the organization encourages tailoring, the project should use the tailoring guidelines to produce a version suited to this project, and record it. For example, the company's life cycle checklist has 40 items, and a small project of 4 people over two months has no need to do them all. The right approach is to tailor a suitable version under the tailoring guidelines, not to change the company standard directly, not to skip the checklist altogether, and not to ask the PMO to suspend it. The tailoring guidelines are themselves an organizational process asset; they tell you how to tailor, which does not mean the project can bypass organizational processes.
To say "the team can only use them and must not touch them," treating OPAs as unchangeable like enterprise environmental factors, is wrong; to say "only the PMO can update them" is just as wrong, since team members can update and add to the knowledge repositories.
Worked examples
Example 1 Core question: can the team update organizational process assets
A software project at PMLyceum has entered execution, and during testing the team has accumulated new defect statistics and a review checklist worth sharing across the organization. One member thinks “organizational process assets are set by the organization, and the project team can only use them and not touch them.” How should the project manager respond?
Show answer and explanation
Correct answer: A
The project is in execution, and the question asks about a statement concerning organizational process assets.
Organizational process assets are artifacts, practices and knowledge accumulated inside the performing organizations involved in the project. They are internal resources of the organization; when authorized, project team members can update their knowledge repositories throughout the project, and defect statistics can go into such a repository. A review checklist normally belongs to policies, processes and procedures; it may be tailored where the organization encourages tailoring, while updates to the organizational standard must follow organizational policy. The answer is A.
Why the other options are wrong
- B. This confuses organizational process assets with enterprise environmental factors. Enterprise environmental factors are conditions the team cannot directly control and must assess and adapt to. Organizational process assets are internal resources: where organizational authorization permits, team members may update knowledge repositories throughout the project, not only at closure, while changes to policies, processes, and procedures must follow organizational procedures.
- C. This overgeneralizes. What the project management office mainly establishes are policies, processes and procedures, and it is those assets that are usually not updated as part of project work. Organizational knowledge repositories are continually updated with project information, and team members may add to them where organizational authorization permits.
- D. Organizational process assets include both the lessons learned and historical information of earlier projects and the information this project produces and keeps updating, such as defect data and performance metrics, so this project's information can also go into the repository.
Key takeaway Organizational process assets are internal resources whose knowledge repositories the team may update throughout the project where organizational authorization permits; it is enterprise environmental factors that the team cannot directly control and must adapt to (mandatory rules among them must be obeyed).
Variation If a member says “lessons learned can be written into the organizational knowledge repository only when the project closes,” that too needs correcting: they can be updated at any time during the project. If a member says “policies, processes and procedures are generally not updated as part of project work,” that is correct, but add that they can be tailored under the tailoring guidelines, and updates go through the organization's procedures.
Something wrong with this question?
Example 2 Core question: telling knowledge repositories from policies and processes
The PMO at PMLyceum is training newly hired project managers and explaining how organizational process assets are classified. The training material lists four items and asks the trainees to pick the one that belongs to the “organizational knowledge repositories” and not to “policies, processes and procedures.” Which one would you choose?
Show answer and explanation
Correct answer: C
You must decide which category of organizational process assets an item belongs to.
The issue and defect management database stores the status, control information and resolution results of issues and defects and is updated continuously with project information, so it is an organizational knowledge repository, while the question asks you to exclude the category of “policies, processes and procedures.” The way to tell is to ask one question: does this item prescribe how the organization requires things to be done, or does it record what has happened? The former goes under policies, processes and procedures, and the latter under organizational knowledge repositories. Choice C is a record, so the answer is C.
Why the other options are wrong
- A. A change control procedure is a process that prescribes how changes are raised, reviewed and approved. It belongs to policies, processes and procedures and is usually not updated as part of project work.
- B. A preapproved supplier list and contract templates belong to policies, processes and procedures, established by the organization as a whole. They are rules to follow, not data accumulated by projects.
- D. Templates and tailoring guidelines and criteria all belong to policies, processes and procedures. They guide how to tailor standard processes to the needs of the project and are not records produced by a project.
Key takeaway Rule-type assets (policies, processes, procedures, templates, tailoring guidelines) are generally not updated with the project; record-type assets (defects, lessons learned, financial data) are continually updated with the project.
Variation If the question were changed to “pick the item that belongs to policies, processes and procedures,” A, B and D would all qualify; remember in particular that tailoring guidelines are organizational process assets, not enterprise environmental factors.
Something wrong with this question?
Common traps
Common trap
- Organizational process assets are internal resources, not "hard conditions" that can only be obeyed: team members can update and add to the organizational knowledge repositories throughout the project; policies, processes and procedures are updated according to the applicable organizational policy; and where the organization encourages tailoring, templates, life cycles, checklists and the like can be tailored under the tailoring guidelines.
- Lessons learned, historical information and issue and defect databases belong to organizational knowledge repositories; change control procedures, preapproved supplier lists, contract templates and tailoring guidelines belong to policies, processes and procedures.
- The source can be the organization, a portfolio, a program or another project, and historical material shared by collaborating performing organizations counts too; do not treat everything "from outside" as an enterprise environmental factor.
- Rule-type assets can be updated only by following the applicable organizational policy; where the organization allows, templates, life cycles, checklists and the like can be tailored under the tailoring guidelines; tailoring does not mean changing the standard on your own, and it does not mean not using it.
- Tailoring guidelines are themselves organizational process assets.
Key takeaways
Key point
- Organizational process assets: the organization's own plans, processes, documents, templates and knowledge repositories, including lessons learned and historical information; they come from the organization, a portfolio, a program or other projects.
- Characteristics: internal resources, can be updated and added to as needed throughout the project (knowledge repositories are updated with project information; policies, processes and procedures can be updated only by following the applicable organizational policy); an input to many processes; the attitude is to "use" them.
- Two categories: policies, processes and procedures (templates, change control procedures, supplier lists, tailoring guidelines and so on); organizational knowledge repositories (lessons learned, financial data, issue and defect data, project files and so on).
- Rule-type assets are established by the PMO or another function and can be updated only by following the applicable organizational policy; where the organization encourages it, templates, life cycles, checklists and the like can be tailored under the tailoring guidelines; record-type assets keep being updated as the project runs.
Lesson 2
Telling Enterprise Environmental Factors and Organizational Process Assets Apart
Lesson overview
This is the most frequently tested classification point in the whole "project environment" topic. A question often gives a specific item and asks which category it belongs to, enterprise environmental factor or organizational process asset, or asks which statement about the two is true. After the first two lessons you know the definition and list of each. This lesson puts the two side by side, gives a method for deciding that does not depend on memorizing lists, and then practices on a set of boundary cases. Where to look first for the answer in many scenario questions also depends on this distinction.
Comparison table
| Comparison | Enterprise environmental factors (EEFs) | Organizational process assets (OPAs) |
|---|---|---|
| Source | Inside or outside the organization | Inside the organization |
| Can the project team change them? | Not directly controllable | Knowledge repositories can be updated and added to; policies, processes and procedures are updated per the applicable organizational policy, and project methods or processes can be tailored under the tailoring guidelines they contain |
| Nature | Conditions and constraints: they impact, constrain or direct the project | Practices and accumulations: processes, templates, knowledge repositories, historical information |
| How they are treated | Consider and adapt (mandatory requirements such as applicable laws and regulations must be obeyed) | Use and borrow (policies and processes are used as the organization prescribes) |
| Typical examples | Organizational culture, structure and governance, employee capability, information technology systems, resource availability; laws, markets, industry standards | Processes, policies, procedures, templates, tailoring guidelines; lessons learned, historical information, issue records |
Three test questions
Given a specific item, ask three questions in order, and most questions will not need you to go back to the lists.
Question 1: does it arise outside the performing organizations involved in the project as an external condition the team cannot directly influence? If so, it is an enterprise environmental factor (historical material shared by the performing organizations involved in the project is still an organizational process asset). Laws and regulations, tariffs, competitors, industry standards and the weather are all here.
Question 2: can the project team directly change it? First exclude plans and project documents produced by the current project (the project management plan, the issue log and so on are not organizational process assets). Whether it can be directly controlled is only a supporting clue: what the team cannot directly control is mostly an enterprise environmental factor. Knowledge repositories built up inside the organization can be updated with the project, templates can be tailored only where the organization authorizes it, and policies and procedures usually cannot be modified by the project team on its own. The organization's structure and software bought company-wide are not the team's call; the lessons learned repository can be added to as the project goes on; and a template can be tailored for the current project only if organizational policy allows.
Question 3: is it an "environmental condition," or an "organizational practice and record available to the project"? What describes the environment, capability, availability or governance environment is a condition; what prescribes how project work is conducted, or records how things were done before and how well they went, is an organizational practice or record.
Question 2 can only serve as a supporting clue; it has to be weighed together with the source and with whether the item is an environmental condition or an organizational practice and record. An internal source may be an enterprise environmental factor (organizational structure) or an organizational process asset (a template), so "internal or external" can only rule out the external; it cannot settle the answer on its own.
Boundary cases
The following pairs have similar names and are the easiest to get wrong.
| Easily confused pair | The enterprise environmental factor side | The organizational process asset side |
|---|---|---|
| Systems versus knowledge | A task management platform or scheduling software the company deploys uniformly (the team must use it; whether to change it is not the team's call) | A risk breakdown structure, a risk register template (used for reference; whether it can be tailored or updated depends on organizational policy and authorization) |
| Structure versus process | Organizational structures such as functional and matrix, governance levels | Change control procedures, project management methods |
| Contract constraints versus lists | Contracting and purchasing constraints, staffing levels (resource availability) | A preapproved supplier list, supplier evaluation records |
| People versus records | The expertise and skills team members have now (employee capability) | Lessons learned and historical information accumulated from earlier projects |
| External versus internal standards | Quality and safety standards issued by a regulator | The company's own quality templates and acceptance guidelines |
One intuitive conclusion: a project management information system (for example, the task management platform the company uses throughout) is an enterprise environmental factor, because it is a system the team can only use; an organization's existing generic risk breakdown structure template is an organizational process asset, because it is knowledge and a tool offered for reference; a risk breakdown structure customized for the current project belongs to the content of the risk management plan.
Worked example: the full reasoning on one classification question
A project manager is planning an offline event platform project and has the five items below to sort into enterprise environmental factors or organizational process assets:
(1) A new rule in this city requires online ticket sales to use real-name registration; (2) last month the company released a new Stakeholder Communication Template; (3) only two people on the technical team can do payment integration; (4) last year's budget execution data for similar projects is stored in the financial data repository; (5) company headquarters requires all projects to use a single common ticketing system.
Reasoning: (1) comes from outside and the team cannot change it, so it is an enterprise environmental factor. (2) is a template issued by the organization, so it is an organizational process asset (whether it can be updated or tailored depends on organizational policy). (3) is employee capability, which the team cannot directly change, so it is an internal enterprise environmental factor. (4) is historical data, a record-type item, so it is an organizational process asset. (5) The team can only use the system and cannot swap it, so it is an internal enterprise environmental factor. The result: (1), (3) and (5) are enterprise environmental factors, and (2) and (4) are organizational process assets.
Worked examples
Example 1 Core question: a new team member reads historical project files; what is being used
A member joins a mobile app development project, having never taken part in any of the company's projects. The project manager suggests that the member first look through the project files of the company's completed projects to learn past practice. Which of the following is being used?
Show answer and explanation
Correct answer: D
A new member joins, and you must decide which kind of influencing factor the files of completed projects belong to.
The project files, lessons learned and historical information of earlier projects are all organizational process assets, knowledge the organization has kept, which the team can consult and borrow from and to which it can add new experience from this project in the organizational knowledge repository. The stem has the new member look through the files of finished projects, so what is used is a “record,” not a “system” or a “facility.” The answer is D.
Why the other options are wrong
- A. Infrastructure means physical conditions such as facilities and equipment and is an internal enterprise environmental factor. It has nothing to do with project files.
- B. The project management information system means tools such as scheduling software and configuration management systems, which are enterprise environmental factors. What is being used here is the content of files, not a tool.
- C. Enterprise environmental factors are conditions the project team cannot directly control, such as regulations, organizational structure and systems deployed company-wide. The files of earlier projects are the organization's own accumulation that the team can consult and add new experience to, so they do not belong here. This is the most common confusion.
Key takeaway The files, lessons learned and historical information of completed projects are organizational process assets; tool systems and facilities are enterprise environmental factors.
Variation If the project manager had the new member “use the company's standard defect management system to enter defects,” the member would be using the project management information system, an enterprise environmental factor; if the member were to “look up earlier projects' defect records in the system,” the member would be looking at repository content, an organizational process asset.
Something wrong with this question?
Example 2 Multiple response: which statements about the two kinds of factors are true
A convenience retail chain's store management system upgrade project has entered planning. Before preparing the project management plan, the project manager sorts out the enterprise environmental factors and organizational process assets that affect the project. Which of the following statements about them are true? (Select 3)
Show answer and explanation
Correct answer: BCF
The project is in planning. You must decide which of six statements about the two kinds of influencing factors are true. The core is “which are enterprise environmental factors, which are organizational process assets, and can they be controlled?”
Enterprise environmental factors are conditions not directly influenced by the project team that impact, constrain or direct the project, and their source can be inside or outside the organization; internal ones include organizational culture, structure and governance, employee capability and so on. Organizational process assets are the organization's own processes, policies, procedures and knowledge repositories, including the lessons learned and historical information of earlier projects. So B (employee capability is an internal enterprise environmental factor), C (lessons learned are organizational process assets) and F (the source can be inside or outside) are correct. The answer is B, C and F.
Why the other options are wrong
- A. Organizational structure falls under “organizational culture, structure and governance,” an internal enterprise environmental factor. A restructuring is a change in an environmental condition, not a change in organizational process assets.
- D. The two kinds are inputs of a different nature, and there is nothing to support that enterprise environmental factors always affect a project more than organizational process assets. The degree of effect depends on the particular project and cannot be generalized.
- E. The characteristic of enterprise environmental factors is that the project team cannot directly control them and has to take them into account during the project, with the legal, policy and other mandatory constraints among them to be obeyed. What the team can draw on, and in part update, are organizational process assets.
Key takeaway Enterprise environmental factors: not directly controllable by the team, to be considered in planning, from inside or outside. Organizational process assets: from the organization itself; knowledge repositories are updated throughout the project, while policies, processes and procedures change only under organizational procedures.
Variation If the stem were changed to “select the statements that are NOT true,” the answer would become A, D and E. If one more option were added, “organizational process assets come from inside the organization and their knowledge repositories can be updated,” it would be true. In multiple-response questions, judge each option separately against the definitions and not by overall impression.
Something wrong with this question?
Common traps
Common trap
- Tool systems, facilities, culture and organizational structure are enterprise environmental factors; files, records, lessons learned and historical information from earlier projects are organizational process assets.
- Employee capability and resource availability are internal enterprise environmental factors; lessons learned that employees wrote down are organizational process assets.
- A statement such as "enterprise environmental factors always influence more than organizational process assets" does not hold; the two have no fixed order of influence.
- Enterprise environmental factors are usually not directly controllable by the project team; they can come from inside or outside; and their impact on the project can be favorable.
- A restructuring of the organization does not fall under organizational process assets; it is an enterprise environmental factor.
- The boundary between the two is occasionally blurred in real life; the exam goes by the PMBOK 8 classification and the three questions above.
Key takeaways
Key point
- EEF: not directly controllable, to be considered and adapted to (applicable mandatory requirements must be obeyed), can be internal or external, impact favorable, unfavorable or neutral. OPA: from inside the organization, available to the project; knowledge repositories can be updated continuously, other assets are updated per organizational policy and tailored where the organization allows.
- Three test questions: does it come from outside the organization? Can the team directly change it? Is it a condition, or a practice and record to borrow from?
- Organizational structure, a system bought company-wide, employee capability and resource availability are EEFs; templates, processes, lessons learned, historical data and the issue and defect information accumulated in the organizational knowledge repositories are OPAs (the current project's issue log and the like are project documents).
- The two cannot be ranked by influence; neither is inherently more influential than the other.
Lesson 3
Using and Updating Organizational Process Assets
Lesson overview
Organizational process assets are not there to be "known," they are there to be "used." There is one very frequent pattern in scenario questions: the project hits a problem, takes on an unfamiliar task, or prepares an estimate or a plan; where do you look first for the answer? Common exam practice: when there are clear clues such as a similar project, a need for historical data or lessons learned, consider consulting the organizational process assets first, especially lessons learned and historical data (the actual order still depends on the situation). This is the most heavily tested lesson in the topic. We cover three things: when to check first, how to borrow, and how to update and archive. It corresponds to several ECO tasks, including identifying risks, estimating, closing and knowledge transfer.
Check first, then use
There are four trigger signals for "check the organizational process assets first," and you should react as soon as you see them.
Signal 1: you take over an unfamiliar situation. A new project manager takes over Phase 2 and a defect appears; the original engineering team has been reassigned and nobody knows how to fix it. The first step is not to extend the schedule, not to update the risk management plan and not to rush to find outside experts, but to consult the defect records and earlier solutions in the organizational process assets. Once you have found them, decide whether other measures are needed.
Signal 2: there is a similar project in the company and relevant records are available. Another business unit did a similar project that went poorly and was stopped, with its lessons learned archived, or the team has just finished a similar project and the same kind of oversight has appeared again with relevant records available. You should review that project's lessons learned to avoid repeating its mistakes, rather than reporting the risk straight away, urging the sponsor to terminate the project, or handing the project to someone else.
Signal 3: you lack experience and need to check a standard. An expert gives a cost ceiling and the project manager has not done a similar project. First consult the organizational process assets to verify whether the figure is realistic, rather than directly telling the team to squeeze to that number. A supplier has delivered below standard several times: adopt the improvement suggestions and recommended practices already recorded in the history.
Signal 4: the start of preparing a plan. When starting a new project, first review the lessons learned from earlier projects and then move on. When preparing the risk management plan, look at lessons learned from past projects before discussing measures. When estimating, borrow the schedule, cost and earned value data of historical projects. When preparing the stakeholder register, use lessons learned from similar projects as guidance.
The word "first" in these four signals matters. For the same "a familiar-looking problem has appeared," adding people, penalizing the supplier, hiring outside consultants and updating the risk management plan are none of them the first choice, and all come after consulting the organizational process assets. One more hint: if the organization already has relevant and reliable experience, use it first; whether outside resources are still needed is judged by the quality of the information and the needs of the project.
Borrowing is not copying
Borrowing has two boundaries. First, fit it to the unique situation of this project. The stakeholder register of a similar project can be used for reference but not carried over wholesale, because the stakeholders are mostly different by now; likewise the solution from the most recent similar project cannot be moved over unchanged. Second, choose historical information that is relevant to this project and of reliable quality: neither copy mechanically nor ignore clearly relevant data without reason, and above all do not look only afterward. Starting from scratch when usable risk data exists is a waste; "digging into the historical records after something goes wrong" misses the time to prevent. The proper approach is to retrieve and apply lessons learned during planning and risk management.
The same goes for people on the team. Suppose a new team member is about to start and the repository holds many entries from earlier work. One colleague says reading only the similar ones is enough; the project manager wants the new member to read everything. Do not set a hard rule on how much to read. Explain how the entries relate to this project and what they are worth, then decide how to use them. Bringing in the functional manager is not the first step. Likewise, when a team member meets a fault similar to one in an earlier project, the project manager should share the lessons learned from the earlier project rather than have the member troubleshoot from scratch.
Updating and archiving
Organizational process assets also have to be "given back." Three rules:
Update at any time. Team members can update and add project information to the organizational knowledge repositories throughout the project (policies, processes and procedures are updated only by following the applicable organizational policy); this is not done only at closing, at the end of a phase or at milestones. Record problems you meet in the defect and issue database, and record newly discovered practices in lessons learned.
Archive at closing. When the project or phase ends, organize the lessons learned and performance data and put them into the organizational knowledge repository, so that they become part of the organizational process assets. If only the deliverables are handed to the customer and nothing is archived, later projects have nothing to refer to. It is also wrong to keep the material only in personal notes, to merely drop it into the project files and provide it at audit time instead of actively organizing it into the organizational knowledge repository, or to think "this is a project document, not an organizational asset." (Project files themselves can be organizational process assets; the mistake is passive storage with no active archiving, so later projects cannot use them.) If the previous project hit problems but left no record, the remedy is: if that project is still closing, add the record and archive it immediately; if it has already ended, record the lesson in a timely way when the current project identifies it, and put it into the lessons learned knowledge repository as the organization prescribes, so the company can find and deal with similar hidden problems earlier.
Correct what is out of date. If an analysis conclusion in the knowledge repository is out of date and the new data accumulated by this project is enough to supplement it, update the repository with the new data; do not wait until closing, and do not change only this project's own documents. When updating an outdated organizational process document (for example, a procurement approval flowchart that is many years old), propose the update to the function responsible for that asset, invite experts and actual users to take part, and update it according to the facts, so that the document reflects the actual current situation. (Policies, processes and procedures can be updated only by following organizational policy, and the specific approval or change procedure follows the organization's rules; the project team does not modify them on its own, and does not just redraw the old version.)
Worked example: one complete cycle of "check, use, update"
A project manager takes over a store point-of-sale upgrade project. In the second week, during integration testing, receipts print as garbled text. The manager does not add testers first, and does not go to an outside vendor, but searches the company's defect database and finds a record from a similar project six months earlier: the root cause was the character set configuration of an old printer model, and repair steps already existed. The team follows these steps, adjusting them for this project's printer model. At project closing, the manager adds the new model's configuration and the on-site handling time to the database, and writes "confirm the printer model list before go-live" into the lessons learned.
Worked examples
Example 1 Core question: a similar project has been stopped; what do you do first
A project manager is assigned to develop warehouse scheduling software for a logistics company. Another business unit of the company did a similar project that was later stopped because its performance was too poor, and its lessons learned were archived in the organizational knowledge repository. The project manager is worried about how this project will turn out and wants to take action in advance to make sure it succeeds. What should the project manager do?
Show answer and explanation
Correct answer: C
In this project the project manager wants to learn from a similar project's failure within the organization, and the question is what measure the project manager should take.
The reasons a similar project failed are recorded in the lessons learned in the organizational knowledge repository, which is an organizational process asset. Reviewing those lessons learned directly shows the problems to avoid and lets them be prevented in this project's planning, which meets the requirement to “take action in advance and make sure of success” and also reflects the pattern that when you meet a similar project you first consult the organizational process assets. The answer is C.
Why the other options are wrong
- A. Assessing risks and adding outside experts first does not use the ready-made internal experience, costs more, and, with the specific causes of the failure not yet understood, is hard to aim correctly.
- B. That a similar project failed does not mean this one will, and urging the sponsor to terminate is a premature, negative step when the information is still insufficient.
- D. Doing no prevention and adding resources only when problems appear is reactive and does not achieve the aim of “taking action in advance.”
Key takeaway When you see a similar project, first review its lessons learned, and then decide whether other measures are needed.
Variation If the company had no similar project and the project manager lacked experience of the kind, first go to experienced experts or the PMO for advice and also consult outside material; if the similar project had been a success, you would likewise first review its lessons learned and then tailor them for this project.
Something wrong with this question?
Example 2 Core question: a defect appears after taking over; what do you do first
A project manager has just been assigned to Phase 2 of an IoT gateway project. A defect appears during implementation, and the original engineering team has been moved to other projects, so nobody knows how to fix it. The customer points out that a similar defect once held up the project's schedule. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
The project is in Phase 2, a defect has occurred and the original team has left. You must decide the project manager's first action.
The defect has already occurred, the original engineering team has been reassigned, and nobody knows how to fix it. Whether the original team left a record of how it dealt with the defect has to be checked first in the organizational process assets (lessons learned, historical information, the defect repository). Consult them first to find out how it was handled before, and only then can you judge whether to extend the schedule, find resources or take other measures. The customer's mention that a similar defect appeared before is a further sign that the historical records probably already hold an answer. The answer is A.
Why the other options are wrong
- B. At this point nothing is known about the defect, so the situation must first be understood and its impact assessed. If the schedule baseline needs to change, a change request must then follow the change management plan, receive authorization, and be reflected in the relevant plans before implementation; the schedule cannot simply be extended first.
- C. The defect has already occurred, so it is an issue, not a risk. Updating the risk management plan does not fix it and is not the first step.
- D. Finding resources with relevant knowledge is something to do when necessary, but it should not come first before the earlier records have been consulted.
Key takeaway When you take over a project and meet a problem nobody knows how to handle, first consult the organizational process assets (lessons learned, defect records) and then decide whether to extend the schedule or find people.
Variation If, after consulting, you find there are no records at all, the next step is to look for resources with the relevant knowledge. And once the defect is fixed, add the handling to the defect repository for later projects to use.
Something wrong with this question?
Example 3 Archiving at closing
A project has entered closing, and the project manager finds that the team has handed over only the deliverables to the customer and has not put this project's lessons learned and performance data into the organizational knowledge repository. What should the project manager do?
Show answer and explanation
Correct answer: B
A project has entered closing, and the team has handed over only the deliverables and has not put the lessons learned and performance data into the organizational knowledge repository. You must decide how organizational process assets should be updated at closing.
At closing, the project's lessons learned, performance data and other information should be organized and put into the organizational knowledge repository, updating the organizational process assets for later projects to use. The problem in the stem is that the team handed over only the deliverables and did not store this information; the project manager should add that step so that the experience becomes an asset of the organization and does not stay in individual hands. The answer is B.
Why the other options are wrong
- A. Personal notes are useful only to the individual. The organization and later projects cannot see them, so they do not build up organizational knowledge.
- C. Material in a temporary folder has not been submitted through the organization's archiving process, so later projects cannot retrieve it, and it should not be provided only when an audit comes.
- D. The valuable lessons learned and performance data in project files are exactly the content that has to go into the organizational knowledge repository, and it cannot be skipped because it “belongs to project documents.”
Key takeaway At closing, put the lessons learned and performance data into the organizational knowledge repository to update the organizational process assets; they can also be added to at any time during the project.
Variation If the question asked “when can organizational process assets be updated?”, the answer is throughout the project, not only at closing; at closing, archiving the lessons learned and performance data must be completed.
Something wrong with this question?
Common traps
Common trap
- When you meet a similar problem, the first step is to consult the organizational process assets (lessons learned, historical records), not to add people, add outside experts, update the risk management plan or extend the schedule.
- Lessons learned are not something to handle "after the project ends": update them at any time during the project, and be sure to archive them into the organizational knowledge repository at closing.
- Borrowing from historical projects has to be fitted to this project's situation and cannot be copied wholesale or applied mechanically; choose relevant, reliable historical information and tailor it to this project.
- When another project has failed, first apply its lessons learned to your own project; when borrowing, use ready-made experience inside the organization first, then consider outside resources.
- For an outdated process document, have experts and actual users update it together; the project team should not modify it on its own, but should propose the update to the department responsible for the asset and follow the approval or change procedure the organization requires; when there is a dispute about how widely a document applies, first explain how the document relates to this project's work.
Key takeaways
Key point
- When you take over an unfamiliar situation, a familiar-looking problem appears, a standard needs checking, or you are preparing a plan, and the stem has clues such as a similar project, historical data or lessons learned and no more urgent action is required, common exam practice is to consult the organizational process assets first; the actual order depends on the situation.
- Lessons learned are used in initiating, planning, risk management and the stakeholder register; historical data is used for estimating; borrowing must be fitted to this project and is not copying.
- Team members can update and add project information to organizational knowledge repositories throughout the project (policies, processes and procedures follow organizational policy); correct outdated content promptly with new data.
- When the project or phase ends, put lessons learned and performance data into the organizational knowledge repository for later projects to use.
This chapter has 19 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.