Project Environment and Organization
Enterprise Environmental Factors
PMP · Project Environment and Organization · 2 lessons · about 25 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
A project does not run in a vacuum. The organization's culture, structure and people, and the outside world's laws, markets and technology, all affect how the project is done and how far it can go. PMBOK 8 calls these conditions enterprise environmental factors (EEFs): conditions not directly influenced by the project team that impact, constrain or direct the project. This chapter first sets out the definition and the 7 internal categories, then the 9 external categories, and then what the project manager does when the external environment changes (common exam practice). It is also the reference point for the next chapter, on organizational process assets: only once you recognize this kind of "condition you can only adapt to" can you tell which things are "assets" you can draw on.
After this chapter you should be able to: state the definition of an EEF and its three characteristics; list the 7 internal and 9 external categories and sort specific examples into them; decide which category an organizational restructuring, a company-wide deployed system, a tariff and a new regulation each fall into; and, when external regulations or standards change, answer in line with common exam practice: once the change is clear, first assess the impact, then agree on a response, submit a change if needed, update and track.
Lessons in this chapter
- Lesson 1: Enterprise Environmental Factors: Definition and Internal Factors. Not directly controllable, effect not fixed in direction, source not restricted; the 7 internal categories (culture, structure and governance; geographic distribution; infrastructure; information technology systems; resource availability, including contracting and staffing; employee capability; financial capability); how to read environmental factors into the plan. Includes two worked examples.
- Lesson 2: External Enterprise Environmental Factors and Responding to Change. The 9 external categories, remembered as rules, environment and trends; the boundary between financial considerations and internal financial capability; the order for handling external change; how environmental factors push the choice of approach. Includes two worked examples.
Chapter map
Enterprise environmental factors (not directly controllable by the team; the impact can be favorable, unfavorable or neutral)
- Internal, 7 categories: culture, structure and governance · geographic distribution · infrastructure · information technology systems · resource availability (contracting, staffing) · employee capability · financial capability
- External, 9 categories
- Rules: legal restrictions · government or industry standards · public health and safety regulations
- Environment: marketplace conditions · financial considerations · physical environmental elements
- Trends: social and cultural influences · academic research · emerging technologies and innovations
- When external conditions change (common exam practice): investigate/assess the impact → agree on a response → change if needed → update plans and related artifacts as needed and track
How the exam tests this
Questions in this chapter are of two kinds. One is classification: given a specific condition (an organizational restructuring, a company-wide software system, a new regulation, a tariff), is it an EEF, and is it internal or external? These often come with organizational process assets as the distractor. The other is the scenario question: during execution, an external regulation, standard or customer rule changes, and the question asks what the project manager does "initially" or "first." In common exam practice: when the change is already clear, the answer is usually to assess the impact first; when the change is not yet confirmed, investigate first (Task 8 of the exam content outline runs in order: investigate changes, assess the impact and prioritize, keep reviewing). The ECO reference is Business Environment domain, Task 8 (Evaluate external business environment changes).
Study suggestions and practice
- Turn the 7 internal and 9 external categories each into a single sentence, and give one example from your own industry for each; this works better than memorizing the list.
- For classification questions, first ask "can the team change it directly?" and then "does it come from outside the organization?" These two steps remove most distractors.
- For external change questions (common exam practice): when the change is clear, assess the impact first; if the stem only says there are signs and nothing is confirmed, investigate first.
- This chapter and the next come as a pair; after finishing the next chapter, come back and redo this chapter's practice.
Lesson 1
Enterprise Environmental Factors: Definition and Internal Factors
Lesson overview
Take the same "launch a new system" project. Put it in an old, rule-bound company with tight resources, or in a flat, flexible internet company with a full set of tools, and how it is done and how hard it is can be completely different. The difference is not in the project itself but in the environment around it. PMBOK 8 calls the influences that come from the environment enterprise environmental factors (EEFs). This lesson first sets out the definition and its three characteristics, then goes through the 7 internal categories one by one; the next lesson covers external factors and how to respond when they change. The lesson corresponds to ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery), which includes assessing the project context and recommending a development approach, and also touches Business Environment domain, Task 1 (Define and establish project governance). It is also the precondition for telling organizational process assets apart.
What an enterprise environmental factor is
Enterprise environmental factors refer to conditions not directly influenced by the project team that impact, constrain, or direct the project. They may come from inside the organization or from outside it. By level, they can act at the organizational, portfolio, program or project level. PMBOK 8 also notes that these factors can either enhance or constrain project management options, can influence tailoring needs, and can affect project outcomes positively or negatively.
Three characteristics are enough. First, not directly controllable: the project team cannot control them directly, so you usually need to identify their influence and comply or adapt, and where necessary keep assessing them and, within your authority, encourage stakeholders to adjust. Second, effect not fixed in direction: for project characteristics, stakeholders or project teams, the impact may be favorable, unfavorable or neutral. Third, source not restricted: they come from both inside and outside, and most planning processes list them as an input. So when planning, identify and consider the relevant environmental factors and adjust the plan accordingly.
The easiest place to go astray is to assume "not controllable" means "a constraint." Take a defect tracking tool that the company buys centrally: the project cannot swap it, which looks like a constraint, but it also saves the trouble of selecting, buying and training on a tool, which helps most projects. The same factor acts differently on different projects, so judge by the specific project.
Key point
Enterprise environmental factors: the project team cannot directly control them, but they impact, constrain or direct the project; favorable, unfavorable or neutral; both internal and external; they act at the organizational, portfolio, program or project level; and they are an input to many processes (especially planning processes). The attitude toward them is "comply and adapt."
Internal enterprise environmental factors
Internal factors come from the performing organization itself, ranging from culture and structure to facilities, systems, people and funding. PMBOK 8 lists 7 categories.
| Internal factor | Typical content |
|---|---|
| Organizational culture, structure and governance | Vision, mission, values, beliefs, cultural norms, leadership styles, hierarchy and authority relationships, organizational styles, ethics and codes of conduct |
| Geographic distribution of facilities and resources | Physical locations, corporate offices, research and development centers, customer service hubs, and virtual or hybrid teams |
| Infrastructure | Existing facilities, equipment, organizational telecommunications channels, information technology hardware, availability and capacity |
| Information technology systems | Task management tools, cost management tools, scheduling software tools, configuration management systems, web interfaces to other online automated systems, work authorization systems and the like (these are examples of the category) |
| Resource availability | Contracting and purchasing constraints, staffing levels or team capacity, collaboration agreements |
| Employee capability | Existing human resources expertise, skills, competencies and specialized knowledge |
| Financial capability of the organization | External funding options and additional financial resources that may be required for projects |
To remember the 7 categories, run through them in the order "organization, space, hardware, software, headcount, people, money" (the same order as in PMBOK 8): culture, structure and governance is what the organization looks like; geographic distribution is where the people and facilities are; infrastructure is the hardware; information technology systems are the software-type systems; resource availability is which resources can be mobilized and what constraints apply from contracts, purchasing, staffing and collaboration agreements; employee capability is what people know how to do; and financial capability is where the money comes from.
Three kinds of content are often overlooked and deserve a few more words. The first is structure. Organization types such as functional, matrix and projectized are themselves internal EEFs. If senior management turns a functional organization into a matrix one, the internal environment has changed; the project team cannot directly control this kind of change and usually has to comply or adapt, though within its authority it can also encourage an adjustment through stakeholders. See the chapter on organizational structure. The second is governance. The organization's approval levels, decision authority, ethics and codes of conduct determine whom the project turns to for decisions and what may not be done. The third is employee capability and resource availability. Who on the team knows what, and how many person-days are available each month, are the real boundaries of the project plan, and however attractive the plan is, it cannot go beyond them.
How to read environmental factors into the plan
Identifying environmental factors is not about handing in a list. It is to answer three questions: will this condition limit how I work, will it change how I tailor, and will it affect whether I choose a predictive, adaptive or hybrid approach? When choosing a development approach, PMBOK 8 spells out several correspondences. Organizations with a fixed functional structure and more traditional hierarchical arrangements are more inclined to select a predictive approach due to preferred lines of authority. Organizations with a network-oriented structure may be more naturally inclined to embrace more adaptive or hybrid approaches. A predictive approach may be a better fit in an organization with a culture of managing and directing, where the work is planned out and progress is measured against baselines, and adaptive approaches may fit better in a culture that more easily embraces uncertainty while emphasizing self-managed teams. Organizational policies, ways of working, reporting structures and attitudes should all be aligned to employ delivery methods successfully. Environments with significant regulatory oversight may likewise use a predictive approach, because of the required processes, documentation and demonstration needs.
Worked example: an inventory of internal factors
A logistics company is building a new waybill management system. During planning, the project manager takes stock against the 7 internal categories:
- Culture, structure and governance: a strong matrix organization; any change over $500,000 in budget must be approved by the responsible vice president.
- Geographic distribution: the development team is in one city, and the warehouse users are spread across three states.
- Employee capability: nobody in the company has done mobile development.
- Infrastructure and information technology systems: the company's standard task management platform and code repository must be used.
- Resource availability: testers can commit at most 40 person-days a month.
- Financial capability: this year there is only one fixed budget, and additional funding has to be requested next year.
Conclusions: the mobile capability gap is filled by training or procurement, the approval path is written into the change management plan, and the test schedule is worked back from a capacity of 40 person-days. Each item finds a place in the plan.
Worked examples
Example 1 Core question: reasoning backward from the definition
A project manager is explaining enterprise environmental factors to a new team member. One of the four statements below is wrong. Which one?
Show answer and explanation
Correct answer: B
This question asks you to find the incorrect statement, so note that the question asks which one is NOT correct, and judge each statement against the definition of enterprise environmental factors.
Enterprise environmental factors are conditions not directly influenced by the project team that impact, constrain or direct the project. The key is that the direction of the effect is not fixed: they can enhance or constrain the options, and for the project they can be favorable, unfavorable or neutral. Statements A, C and D can each be supported by the definition. Statement B moves straight from “cannot be controlled” to “can only limit,” which is inconsistent with the definition, so B is the incorrect statement. The answer is B.
Why the other options are wrong
- A. This statement is correct: the effect of enterprise environmental factors can be favorable, unfavorable or neutral, so it is not the incorrect statement the question asks for.
- C. This statement is correct: organizational culture, structure and governance is one of the internal enterprise environmental factors PMBOK 8 lists, so it is not the incorrect statement.
- D. This statement is correct: enterprise environmental factors can come from inside or outside the organization, so it is not the incorrect statement.
Key takeaway The project team cannot directly control enterprise environmental factors, but their effect can be favorable, unfavorable or neutral, and they cannot all be treated as constraints.
Variation If the question were changed to “find the correct statement,” B would need to be rewritten as “the team cannot control them, but their effect may be favorable, unfavorable or neutral.” An option saying “enterprise environmental factors can be directly changed by the project team as needed” would also be wrong, because the team cannot directly control them; the team can update and add to organizational process assets (knowledge repositories).
Something wrong with this question?
Example 2 Core question: which kind of input is an organizational restructuring
A manufacturer is drafting the project charter for a new product introduction project. At this point senior management, to meet business needs, decides to convert the current functional organizational structure to a matrix one throughout. Which kind of input affecting the development of the project charter is this change?
Show answer and explanation
Correct answer: B
The project is at initiation and the charter is being drafted. You must decide which kind of input the change in organizational structure belongs to; no specific development approach is involved.
Organizational structure (functional, matrix and so on) falls under “organizational culture, structure and governance” among the internal enterprise environmental factors. It is an objective condition that the project team cannot directly control and usually has to adapt to, and enterprise environmental factors are an input to be considered when starting a project or phase (developing the project charter). Senior management's move from functional to matrix means the internal environmental conditions of the organization have changed, and the team has no way to control the change directly, so the answer is B.
Why the other options are wrong
- A. Organizational process assets include the organization's plans, processes, policies, procedures, templates and knowledge repositories; some may be tailored or updated under the applicable rules. Organizational structure itself is an internal enterprise environmental factor, not an organizational process asset.
- C. The assumption log records the project's assumptions and constraints and is a document produced along with the project charter. It is not a classification of a change in organizational structure.
- D. The business case explains why the project is necessary and what benefits are expected, that is, why it is worth doing. A restructuring of the organization is not part of the business case.
Key takeaway A change in organizational structure is an internal enterprise environmental factor, not an organizational process asset.
Variation If the company released a new project charter template, it would be an organizational process asset; if the company switched the project management information system everyone must use, that system would be an internal enterprise environmental factor. Classify by the nature of the item: organizational structure and existing information systems are environmental conditions, while policies, processes, templates and knowledge repositories are organizational process assets. Do not rely only on whether the team can change it directly.
Something wrong with this question?
Common traps
Common trap
- That an enterprise environmental factor is "not controllable" does not mean it is "necessarily unfavorable": the impact can be favorable, unfavorable or neutral.
- A change in governance arrangements such as organizational structure, hierarchy and authority relationships is an internal enterprise environmental factor; the organization's project management policies, procedures, templates and lessons learned are what count as organizational process assets.
- Employee capability and resource availability are internal enterprise environmental factors; lessons learned, historical information, templates, policies and procedures are what count as organizational process assets.
- In the internal factor "financial capability of the organization," what matters is whether the organization can raise funds and has additional money; exchange rates, interest rates, tariffs and taxes are external "financial considerations." Do not mix them up.
- The influence of enterprise environmental factors and of organizational process assets cannot be compared directly; there is no fixed conclusion such as "enterprise environmental factors have more influence."
Key takeaways
Key point
- Enterprise environmental factors: the team cannot directly control them, but they impact, constrain or direct the project; favorable, unfavorable and neutral are all possible.
- They can be internal or external, act at the organizational, portfolio, program or project level, and are an input to many planning processes.
- Internal, 7 categories: organizational culture, structure and governance; geographic distribution of facilities and resources; infrastructure; information technology systems; resource availability (contracting, purchasing, staffing); employee capability; financial capability of the organization.
- An organizational restructuring is an internal enterprise environmental factor; a software system the company uses across the board is one too, as far as the team is concerned.
- The purpose of identifying environmental factors is to influence the plan, tailoring and the choice of development approach; the attitude toward them is to comply and adapt.
Lesson 2
External Enterprise Environmental Factors and Responding to Change
Lesson overview
The project team cannot directly control either internal or external factors. But internal factors can sometimes still be moved by communication and coordination, while external factors are mostly "facts on the ground": how the law is written, where interest rates go, what a competitor did, are usually beyond both the project team and the whole organization. Worse, they can change suddenly while the project is running. This lesson first covers the 9 external factors PMBOK 8 lists, then the high-frequency scenario: when the external environment changes, what does the project manager do first? It corresponds to ECO: Business Environment domain, Task 8 (Evaluate external business environment changes).
External enterprise environmental factors
External factors come from outside the organization. PMBOK 8 lists 9 categories; the table below arranges them in the three groups discussed next, with typical content for each.
| External factor | Typical content |
|---|---|
| Legal restrictions | Country or local laws and regulations related to security, data protection, business conduct, employment and procurement |
| Government or industry standards | Regulatory agency regulations and standards related to products, production, environment, safety, quality and workmanship |
| Public health and safety regulations | Government-imposed health protocols, travel restrictions, quarantine measures, social distancing guidelines and public safety mandates |
| Marketplace conditions | Competitors, customer behavior, market share, brand recognition and trademarks |
| Financial considerations | Currency exchange rates, interest rates, inflation rates, tariffs, taxes and geographic location |
| Physical environmental elements | Working conditions, weather, and constraints such as geopolitical issues |
| Social and cultural influences and issues | Political climate, codes of conduct, ethics and perceptions |
| Academic research | Industry studies, publications, benchmarking results, empirical data that can inform decision-making, and emerging trends within the management field |
| Emerging technologies and innovations | Advancements in artificial intelligence, automation, blockchain and the Internet of Things (IoT) |
The 9 categories can be remembered in three groups. Rules: legal restrictions, government or industry standards, and public health and safety regulations. Laws and applicable regulatory requirements are hard constraints that must be obeyed, while whether a government or industry standard is mandatory also depends on regulation, contract and project governance requirements. Environment: marketplace conditions, financial considerations and physical environmental elements, which are the market and the weather outside. Trends: social and cultural influences, academic research and emerging technologies and innovations, which are forces that slowly change how work is done. In scenario questions, a new ordinance, a new standard, a tariff adjustment, exchange rate swings and public health controls each match one of these.
Two boundaries are easy to get wrong when classifying external factors. One is "financial considerations" versus the internal "financial capability of the organization": exchange rates, interest rates, tariffs and taxes are external, while whether the organization itself has money and can raise funds is internal. The other is "government or industry standards" versus the organization's own standards: emission standards and safety standards issued by a regulator are external, while the quality templates and acceptance guidelines the company drew up internally come from the organization itself and are organizational process assets. Put simply, regulations, standards, market conditions and the like that originate outside the organization and impact, constrain or direct the project are external enterprise environmental factors; templates, processes and historical records the company created and accumulated internally are organizational process assets. Whether an external standard must be followed also depends on regulation, contract and governance requirements.
Worked example: classifying a new rule
A restaurant chain is running a "smart kitchen temperature control" project. Once the pilot begins, the state issues a new rule requiring cold chain equipment to connect to a regulatory platform. The reasoning steps (common exam practice): the rule is made by the government and the company has no power to change it, so it is external; it is a regulation, so it falls under "legal restrictions" and "government or industry standards"; it has nothing to do with company templates, so it is not an organizational process asset. What to do next is assess the new rule's impact on scope (an interface must be added), schedule, cost and quality, not argue about which category it belongs to.
What the project manager does when the external environment changes
What the exam content outline asks of this kind of task is to investigate changes in the external business environment, assess and prioritize the impact of those changes on project scope or the backlog, and then keep tracking the external environment. In scenario questions, the order of handling is quite stable under common exam practice:
- Assess the impact first. Work with the project team to see what the change does to scope, schedule, cost and quality.
- Then agree on a response with stakeholders. Where necessary, verify the requirements together with those responsible for compliance, legal and so on, and confirm the reasons and the action plan.
- Then use formal channels. If a baseline must change, submit a change request and handle it through the Assess and Implement Changes process.
- Finally update and keep tracking. The disposition of the change request (whether approved, deferred or rejected) must be recorded in the change log. Once a change is approved, update the affected project management plan components or baselines, then implement the approved change through the project's work, and update the issue log and other artifacts as needed; if future uncertainty triggered by the change is identified, update the risk register as well; and keep watching the environment.
So in "initially" and "first" questions, there are four common wrong options: suspending the project without analysis; drafting a change request straight away (a change must say what is being changed, and that is known only after the assessment); negotiating a delay with the regulator (mandatory rules are not ours to negotiate); and merely flipping through the risk register or researching the background to the policy (neither begins to assess the impact on this project). On compliance there is one more detail: when a stakeholder points out a compliance gap, it is not enough to log it in the lessons learned register; verify the cause and decide the action together with the people responsible for compliance.
A change on the customer's side also counts as the external environment. For example, a long-term customer changes its bidding and evaluation rules. The project manager's first step is to analyze the impact of the new rules, then act within the organization's governance and authorization boundaries: where management has to decide, submit the analysis and a recommendation, and where necessary also seek clarification of the rules from the customer's procurement department through formal channels, rather than negotiating a response directly without analysis and authorization, or preparing documents based only on past experience with the customer.
Finally, environmental factors are also "updated" by project processes. For example, the outputs of the Acquire Resources process include enterprise environmental factors updates (such as a change in resource availability within the organization). This is a reminder that enterprise environmental factors are not a fixed backdrop; the plan has to be updated as they change.
How enterprise environmental factors push toward different development approaches
- Strict regulation, with prescribed processes and documented evidence required: leans toward predictive.
- Fixed functional structure and clear hierarchy: leans toward predictive; network-oriented structure and many self-managed teams: more naturally embraces adaptive or hybrid.
- A culture of managing and directing, planning first and measuring against baselines: suits predictive; a culture that tolerates uncertainty and stresses self-direction and innovation: suits adaptive.
Worked examples
Example 1 Core question: which kind of factor a new ordinance is
A city has newly issued regulations on the safety management of electric bicycle charging facilities, and a community charging station project under construction is bound to be affected. The project manager plans to convene stakeholders to analyze the impact and discuss responses. How should the new regulation be classified?
Show answer and explanation
Correct answer: A
The project is under way and a new regulation has been issued externally. You must decide which kind of factor affecting the project the regulation itself is, not how the project manager should handle it.
Enterprise environmental factors are conditions not directly influenced by the project team that impact, constrain or direct the project. Regulations issued by a country or locality are typical external enterprise environmental factors (legal restrictions, government or industry standards). The regulation in the stem is made by the government, the project can only comply with it and cannot change it, and it is not a practice the organization has built up. The project manager's later steps of assessing the impact and discussing responses are follow-up actions and do not affect the classification here. The answer is A.
Why the other options are wrong
- B. A quality metric specifically describes a project or product attribute and how compliance with it will be verified. The regulation may lead to an adjustment of related metrics, but the regulation itself is an external rule and not a quality metric.
- C. Organizational process assets are practices and knowledge inside the organization that can be tailored and updated. A regulation comes from outside the organization and does not belong in this category.
- D. The regulation has been issued, so that it will affect the project is certain. Only the size of the effect remains to be analyzed, which is an already identified situation. An unknown-unknown risk is one that could not be foreseen at all beforehand.
Key takeaway A newly issued regulation is an external enterprise environmental factor; the project can only comply with it and assess its impact.
Variation If the regulation were replaced with the company's own newly issued construction checklist for charging stations, it would become an organizational process asset. If the question were changed to “what should the project manager do next?”, the answer would be to assess first with the team its impact on scope, schedule, cost and quality.
Something wrong with this question?
Example 2 Core question: what to do "initially" after an external standard changes
A paper mill is carrying out a flue gas treatment upgrade project and is in the execution stage. The local government unexpectedly issues stricter emission standards than before. To ensure the project complies with the new standards, what should the project manager do INITIALLY?
Show answer and explanation
Correct answer: D
The project is in execution and the government unexpectedly issues a stricter emission standard. You must decide what the project manager should do “initially.”
The new standard is an external enterprise environmental factor, and the project can only comply with it. The first step on such an external change is to understand its effect on the project: assess with the team what the new standard does to scope, schedule, cost and quality, and then decide on that basis whether a change is needed and how to adjust the plan. The question asks for the “initial” action, and keeping to that limit makes it clear that the assessment must come before the change. The answer is D.
Why the other options are wrong
- A. Regardless of whether the regulatory change was previously recorded as a potential risk, merely checking the risk register does not assess its actual effect on the project and therefore is not the best initial action.
- B. A change request has to say what is to be changed, and that is known only after the effect has been assessed. Submitting a change request comes after the assessment and is not the initial action.
- C. The project side cannot postpone the effective date of the new standard on its own, and seeking an extension before the effect has been assessed is not the first action either. First confirm the requirements that apply and assess the impact.
Key takeaway When an external regulation changes, first assess the impact with the team, and then decide on a change; do not go straight to a change request or negotiation.
Variation If “initially” were changed to “after the impact has been assessed,” the next step would be to draft a change request in accordance with the change management plan and submit it to the authorized person or change control board (B); stakeholder consultation may help refine the response but does not replace formal approval. If the government standard were replaced by a change in the customer's own acceptance requirements, the approach would still be to assess the impact first and then go through change control.
Something wrong with this question?
Common traps
Common trap
- Regulations, industry standards, tariffs and exchange rates come from outside the organization and are external enterprise environmental factors; the company's own templates, processes and historical records are organizational process assets.
- The first step on an external change is to assess the impact: not to submit a change request directly, not to suspend the project, and not to negotiate with the regulator.
- "Assess the impact" must cover scope, schedule, cost and quality, not just check whether there is a risk entry.
- Enterprise environmental factors must be brought into planning and influence tailoring and the choice of approach; "not controllable" does not mean "no need to deal with it."
- Once a new rule is confirmed to apply to the project, it is a known compliance requirement and cannot be called an unknown-unknown risk; its specific impact on scope, schedule and cost still has to be assessed.
Key takeaways
Key point
- External, 9 categories in three groups: rules (legal restrictions; government or industry standards; public health and safety regulations); environment (marketplace conditions; financial considerations; physical environmental elements); trends (social and cultural influences and issues; academic research; emerging technologies and innovations).
- Exchange rates, interest rates, inflation rates, tariffs and taxes are external financial considerations; whether the organization itself can raise funds is an internal factor.
- Handling external change (common exam practice): when the change is confirmed, first assess the impact on scope, schedule, cost and quality, then agree on a response with stakeholders, go through change control if needed, and update plans and related artifacts as needed; when the change is not yet confirmed, investigate first.
- Environmental factors influence tailoring and the choice of approach: strict regulation leans predictive, a self-managing culture leans adaptive.
This chapter has 12 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.