Business Case and Benefits Management Plan

PMP · Foundations and Value Delivery · 5 lessons · about 58 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Before a project is launched, the organization has to answer the question "is this worth doing?" Once it is under way, the organization keeps tracking whether the promised benefits are actually showing up. The business case answers the first question; the benefits management plan describes how and when benefits will be realized and measured, while actual measurements verify whether they are being realized. Together they are the business documents: the basis for decisions about the project, and the documents a project manager most often goes back to when checking a scenario question.

This chapter first covers what each of the two documents contains, then their nature, ownership and maintenance. It then uses five signals to summarize how they are used in scenario questions, and finally connects them to project selection and prioritization.

Lessons in this chapter

  • Lesson 1: Business Case. A documented economic feasibility study that outlines costs, benefits, how value will be created and the project success criteria (the analysis dimensions used in common exam practice are business need, economic feasibility and technical feasibility); how it differs from the project charter and from a cost-benefit analysis.
  • Lesson 2: Benefits Management Plan. Its seven elements; developed early and maintained iteratively; using it to answer challenges about value.
  • Lesson 3: Business Documents: Nature, Maintenance and Ownership. They are not project documents; the sponsor is usually responsible for the business case, with the project manager advising, and the benefits management plan is maintained according to the organization's governance arrangements; what to do when gaps are found and when you take over a project already under way.
  • Lesson 4: Business Documents in Scenario Questions. Challenges to the project, new ideas, external changes, strategic alignment and confirming benefits: five signals and the matching actions.
  • Lesson 5: Project Selection and Prioritization. Strategic alignment, target benefits and metrics, cost-benefit; prioritization in agile work; a short net present value example.

What you should be able to do after this chapter

You can state what a business case contains and the three analysis dimensions used in common exam practice, and the seven elements of the benefits management plan. You can distinguish what the business case, the project charter, the cost-benefit analysis and the project management plan each answer. You know that business documents are not project documents, that the sponsor is usually responsible for the business case with the project manager advising and taking part as the organization arranges, and that the project manager and sponsor together keep the benefits management plan aligned with the project charter and the project management plan. When you see one of the five signals (a challenge to the project, a new idea, an external change, a doubt about strategic alignment, confirming benefits), you can say which document to go back to, whom to ask first and what to do next. When prioritizing, you know to look at strategic alignment, target benefits and metrics, and cost-benefit, and you can use net present value for a simple comparison.

Chapter map

Business documents (developed before initiation, reviewed periodically)

  • Business case (sponsor is responsible, project manager advises): is it worth doing? ── business need · economic feasibility · technical feasibility; success criteria
  • Benefits management plan (developed and maintained as the organization's governance arranges; project manager and sponsor together keep it aligned with the charter and project management plan): how and when will benefits be realized and measured? ── target benefits · strategic alignment · timeframe · benefits owner · metrics · assumptions · risks

Scenario signals: challenge to the project / new idea / external change / strategic alignment / confirming benefits → return to the business documents → verify with the sponsor or benefits owner as governance arranges → continue, adjust, escalate or terminate based on the assessment; go through the change process only when approved content must change

Project selection: strategic alignment + target benefits and metrics + cost-benefit (NPV can be one financial comparison measure; the actual ranking also considers resources, risk and other factors)

Lesson 1

Business Case: Is the Project Worth Doing?

Lesson video

Lesson overview

Before a project is launched, the organization has to answer one question: is this worth doing? The document that answers it is the business case. It is the standard answer to exam questions such as "which document should be used before the project is initiated?" and "an executive proposes a new idea; what does the project manager do first?" This lesson covers what a business case is, what it consists of, when to use it, and how it differs from the project charter, a cost-benefit analysis and the project management plan. The next lesson covers its partner document, the benefits management plan.

What a business case is

A business case is a documented economic feasibility study used to establish validity of the benefits to be delivered by a portfolio component, program or project. It lists the objectives and reasons for project initiation, helps to define a selected component that lacks sufficient explanation, and is used as a basis for the authorization of further project management activities. In other words, it is more than "a report": it is the basis on which all the later work can begin.

Put in one sentence, the business case is a decision document. Before committing people and money, look at it. Many companies call it a feasibility study; the name differs, the purpose is the same. It works at three points in time: before initiation, to decide whether to approve the project; during the project, to help decide whether to continue or stop; and at the end, to look back and measure project success against the project objectives.

What it consists of

PMBOK 8 says the business case outlines the costs, benefits, how value will be created, and the project success criteria. Common exam practice summarizes its analysis in three elements:

  • Business need: why do it, that is, what business problem the project solves or what opportunity it seizes.
  • Economic feasibility: whether the investment and the return make sense, often measured by payback period, profit margin and the like.
  • Technical feasibility: whether the available technology and people can support it.

On exam questions, look at all three (common exam practice): a beautiful cost-benefit analysis does not help if the solution cannot be built, because the proposal will not pass review either.

Business case and benefits management plan: from project approval to benefits realization

You can also tie the logic of a business case together with four questions. What is the business need (more complaints, falling market share, a competitor launched a new product)? What is the situation (can it be done technically, does it pay off economically)? What is recommended (build or outsource, buy or develop)? What counts as success (the measures of success must be set before initiation, or at the end there is no yardstick to measure against)?

What it is not

The exam likes to use neighboring documents as distractors. Keep them apart:

DocumentThe question it answersHow it differs from the business case
Business caseIs it worth doing?The basis for the decision before the project is initiated
Project charterWho is authorized to do it, and what are the objectives and the summary?Issued by the project initiator or sponsor and approved by someone with the authority to approve it; formally establishes the project and authorizes the project manager to apply organizational resources to the work
Cost-benefit analysisDo costs or benefits come out larger?The business case usually includes it (common exam practice); it cannot replace the whole business case
Project management planHow exactly will it be done?An output of planning; it does not argue the value of the investment
Scope baselineWhat is in scope and what is not?Approved during planning; it does not exist yet at initiation

When to use the business case

Three situations are the most common. First, evaluating whether to start the project: when the financial forecasts are insufficient and management cannot decide whether to approve, the missing piece is the business case. Second, an executive proposes a new idea, for example after an industry forum, and asks for a new technology to be introduced. Common exam practice is that the project manager should first help the sponsor begin preparing the business case, not first collect requirements, assign resources or run a SWOT analysis. The PMBOK 8 basis is that the sponsor is usually responsible for developing and maintaining the business case, that the project management team may help prepare it in some organizations, to a degree tailored to the organization, and that the idea should in practice first be evaluated through the organization's governance process. Third, someone asks "why are we doing this project?", or the person taking over a project already under way wants to know why it was approved: read the business case first to understand the objectives and success criteria.

The business case is a living document, not something filed away once approved. When a product is aging, the market changes, or active users keep falling, the sponsor can bring stakeholders together to redevelop the business case and decide whether the project is still worth investing in.

Example: a loyalty app for a pharmacy chain

A pharmacy chain wants to build its own member loyalty app. The business case states that repeat purchases in stores are declining, which is the business need. Three competitors have already launched similar features, and a member survey also shows clear demand for online services, so the market wants it. The in-house team has two engineers familiar with mobile app development, so it is technically feasible. The investment is expected to be recovered within three years through higher repeat purchases, so it is economically feasible. The success criterion is also agreed before launch: a target repeat purchase rate among members after one year in operation. With all three conditions met and a yardstick in place, the project has a basis for approval.

A good business case can also be tested in a few ways. First, does it answer "what happens if we do not do this?" If the business need is not pressing, the project lacks a reason to exist. Second, can the numbers stand up to challenge? The assumptions behind the benefit estimates, the cost breakdown and the way the payback period is calculated should all be documented and defensible, and should go through review and approval by the relevant stakeholders under the organization's governance process. Third, can the success criteria be verified? Criteria should be specific enough to measure or verify (state the metric and target value where quantification fits), or at the end of the project there is nothing to judge against. The sponsor brings stakeholders in to draft and review the business case and then submits it to the body with authority to approve it under the governance process, which also gets everyone to agree on benefits and responsibilities before the start.

Worked examples

Example 1 Financial forecasts missing before approval: submit a business case

Question 1Example

A corporate group plans to launch several interrelated projects at the same time, and a mid-level manager suggests combining them into one program managed together. When the board reviews the proposal, it finds that financial forecast data for some of the projects were not provided, so it cannot decide whether to approve them. Which document should be submitted to the board so that it can make the approval decision?

Show answer and explanation

Correct answer: C

A corporate group plans several interrelated projects. In its review the board finds that the financial forecasts for some projects were not provided and it cannot decide whether to approve them. The question is which document should be submitted to the board.

The projects are not yet approved and are at the stage before initiation, and what the board lacks is the evidence needed to decide whether the projects are worth doing. The business case is a documented economic feasibility analysis that tests whether the benefits the project can deliver hold up. It provides the basis for authorizing further project management activities and contains an analysis of business need and a cost-benefit analysis; the project is then formally started through the project charter. What the board lacks is exactly the data on expected benefits and costs, so the business case should be submitted. The answer is C.

Why the other options are wrong

  • A. The scope baseline consists of the scope statement, the WBS and the WBS dictionary. It does not exist yet at initiation, and it contains no financial forecasts.
  • B. The project charter is formally issued after the project is approved and authorizes the project manager to begin work. This question is still at the stage of deciding whether to approve.
  • D. The project management plan explains how the work will be done. It is not the basis for approving a project and certainly not the document that argues the value of the investment.

Key takeaway To answer “is it worth doing?” before approval, rely on the business case (the economic feasibility study).

Variation If the project has already been approved and the project manager must be formally authorized to start work, the document becomes the project charter.

Something wrong with this question?

Report an issue with this question

Example 2 An executive proposes a new idea: first help prepare the business case

Question 2Example

After attending an industry forum, the chairman of a logistics company asks the project manager to introduce blockchain traceability technology into the company's business. The idea has not been approved as a project, and nobody has assessed whether it is worth investing in. What should the project manager do FIRST?

Show answer and explanation

Correct answer: D

After an industry forum, the chairman of a logistics company asks the project manager to bring blockchain traceability into the business. There is only an executive's idea, and nobody has yet argued whether it is worth doing. The question is what the project manager does first.

Introducing a new technology means starting a new project, but at this point it has not even been decided whether to do it. Before a project begins, you first have to say why it is being done and whether it is worth the investment, and that is the business case. The sponsor is responsible for it, and the project manager helps by giving advice; it is the basis for starting the project. Collecting requirements and assigning resources normally wait until the project is approved and the charter issued. A SWOT analysis can support the business case but cannot replace it. The trap in this question is “first”: several options are things that really are done in a project, but only the business case comes at the very front, and it decides whether the later work begins at all. The answer is D.

Why the other options are wrong

  • A. Eliciting and analyzing requirements takes place after the project is approved and the charter issued. It is not the first job at this point.
  • B. Involving stakeholders and assigning resources are also work for after approval. At this point it has not even been decided whether to do the project.
  • C. A SWOT analysis can support the justification, but it is only a tool for identifying internal and external factors. It cannot replace the business case and is not the first step now.

Key takeaway When an executive proposes a new idea, the first thing the project manager does is help prepare the business case.

Variation If the business case has been approved and the charter issued, then asking “what first?” turns the answer toward collecting requirements or identifying stakeholders.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • An approved business case shows the project has a basis for approval. The project still has to be formally launched through a project charter or similar authorization before it moves into planning, and approval does not mean the project will succeed.
  • The business case answers "is it worth doing?" It does not lay out how work is arranged; that belongs to the project management plan, and the activity list and who is responsible are even less a part of the business case.
  • Use the business case to judge whether the investment is worthwhile before approval, and do not confuse it with the benefits management plan, which tracks benefits through to the end.
  • The business case usually includes a cost-benefit analysis (common exam practice), but the analysis cannot replace the whole business case.
  • When a new idea appears, prepare the business case first, then talk about collecting requirements, assigning resources or a SWOT analysis.

Key takeaways

  1. The business case is a documented economic feasibility study, prepared before approval, and the basis for approving the investment and authorizing later project management activities.
  2. It usually contains an analysis of business need and a cost-benefit analysis (common exam practice); three elements: business need, economic feasibility and technical feasibility.
  3. The measures of success are written in before the start, and success or failure is judged against them at the end.
  4. Keep it apart from the project charter, the cost-benefit analysis, the project management plan and the scope baseline.
  5. Before approval, when an executive proposes a new idea, when someone challenges the project, or when you take over a project in progress, go to the business case first.

Lesson 2

Benefits Management Plan: Writing Benefits Down and Tracking Them to the End

Lesson video

Lesson overview

The business case says "this project can bring benefits," but someone has to keep tracking whether the benefits actually appear. The document responsible for that is the benefits management plan. It is a key topic in this chapter, and the questions often look like this: someone says the project has not brought the expected value, so how does the project manager respond; the project is about to close and the benefits have not appeared, so what now; stakeholders describe the benefits differently, so what now? This lesson covers what is written in the plan, when it is developed, and how to use it to answer those questions.

What problem it solves

The benefits management plan is the documented explanation defining the processes for creating, maximizing and sustaining the benefits provided by a program or project. It describes how and when the benefits of the project will be delivered and the mechanisms that should be in place to measure those benefits. A project benefit is an outcome of actions, behaviors, products, services or results that provides value to the sponsoring organization as well as to the project's intended beneficiaries.

The business case and the benefits management plan are two documents that divide the work, and both are business documents. In the PMBOK Guide's words, "both the business case and the benefits management plan are developed prior to the project being initiated," and both are referenced after the project has been completed. Development of the benefits management plan begins early, with the definition of the target benefits, and it is maintained iteratively after that. The business case answers "is it worth doing?" The benefits management plan explains how and when benefits will be realized and how they will be measured, and it is maintained iteratively during the project to answer "did the benefits we promised materialize, and how can we show it?" Common exam practice: for questions about "proving value," "measuring benefits" or "who is responsible for benefits," look at the benefits management plan first, then use the business case and the governance arrangements to decide.

What the plan contains: seven elements

The plan describes the key elements of the benefits and may include the following seven:

  • Target benefits: the expected tangible and intangible value to be gained by the implementation of the project; financial value may be expressed as net present value (NPV).
  • Strategic alignment: the alignment of the project to the business strategies of the organization.
  • Timeframe for realizing benefits: the length of time to realize benefits, for example short term, long term, ongoing or by phase.
  • Benefits owner: the person accountable for monitoring, recording and reporting realized benefits throughout the timeframe established in the plan.
  • Metrics: the direct and indirect measures used to determine the benefits realized.
  • Assumptions: the factors expected to be in place or to be in evidence.
  • Risks: the risks that pertain to the realization of benefits.
Business case and benefits management plan: from project approval to benefits realization

Three of the seven are tested most often. The first is metrics. Write them as measurable indicators: a quantitative metric states the target or threshold and the data source, adding a comparison baseline when the benefit is an improvement from a prior state; a qualitative metric states a verifiable criterion and the source of evidence. For example, "average response time is shortened" cannot be measured if there is no current baseline value and no way to collect the data. The second is the benefits owner. Who is responsible for monitoring, recording and reporting the realization of a given benefit has to be worked out among stakeholders and written into the plan, and if someone raises doubts about who owns a benefit midway, a meeting is needed to clarify it. The third is assumptions and risks. Benefits often depend on outside conditions. If a benefit only appears once a partner completes an interface and that progress is not under the team's control, record it in the assumptions and risks and keep monitoring it; do not assume it will hold.

Example: setting benefits for an online learning product

An online learning product sets these target benefits: 30,000 registered users in the first quarter, a paid conversion rate of 4% in the second quarter, and a 60% renewal rate in the third quarter. The benefits owner is the product director in the business unit, the metrics come from monthly data in the back-end system, an assumption is that the promotion budget arrives on time, and a risk is that a competitor cuts prices in the same period. At the end of each quarter the owner checks actual data against the targets and reports gaps to the sponsor. The key details are filled in: which benefit, by when, who is responsible, how it is measured, what it depends on, and what the risks are.

When to develop it and how to maintain it

The benefits management plan begins early in the project life cycle, as the target benefits are defined, and the data and information documented in the business case and needs assessment are used to develop it. Development and maintenance are iterative. It complements the business case, the project charter and the project management plan. The project manager works with the sponsor to ensure that the project charter, the project management plan and the benefits management plan remain in alignment throughout the life cycle, and the project manager should also provide advice and insight so that the success criteria in documents such as the business case line up with one another.

Well maintained, the plan becomes the yardstick for the whole project. At initiation, agree with key stakeholders on the expected benefits, and agree on how the benefits will be measured and tracked and get the performance parameters approved, so that later evaluation has a basis rather than setting standards only at the end. During execution, use it to monitor business value: in a phased project, at each milestone, evaluate the benefits already produced against the benefits management plan (target benefits, timeframe and metrics) with reference to the business case. If benefits have begun to be realized, or governance and communication requirements call for it, status reports should also include tracking results for the relevant benefits metrics, in addition to schedule and cost. At closure, assess any benefits gap and hand tracking responsibility over to the business side, which an earlier chapter covered.

How to use it to answer challenges

For three kinds of challenge, the answer is the same: go back to the plan. First, someone says the project has not brought the expected value: go through the benefits management plan together, look at the target benefits, timeframe and metrics, and judge whether the challenge holds. Second, departments describe the benefits differently: align the parties and state the metrics in writing. Third, nobody can say what the "benefit" is: work with stakeholders to define measurable metrics and make the value path clear. When a new project manager needs to explain the project's benefits at a kickoff meeting, the same items apply: the expected business value, the metrics that show whether benefits are being realized, and the risks that must be handled to achieve the target benefits.

Worked examples

Example 1 Is the project really delivering value? Check the benefits management plan

Question 1Example

At a project review, the sponsor is concerned that the project is not delivering results as planned, and the project manager assesses the project's status. Which information should the project manager use to judge whether the project is really delivering value?

Show answer and explanation

Correct answer: C

At a project review the sponsor worries the project is not delivering results as planned. The project manager is assessing status and must find information that shows how value is being delivered.

The benefits management plan explains how and when benefits will be realized and establishes the mechanism for measuring them. To judge whether the project is really delivering value, compare the measured benefit results with the plan's target benefits and timeframe; results that meet the targets at the planned points provide evidence that value is being delivered. If, in assessing status, you answer the sponsor's concern about value with only management measures such as cost and schedule, you have not answered the question; to answer a question about value you have to use measurement on the benefits side. The answer is C.

Why the other options are wrong

  • A. Satisfaction is a subjective feeling. With no measurement against the target benefits, it cannot prove that value has been delivered.
  • B. Staying within budget and on schedule shows the project management processes are doing well, but the results do not necessarily bring the expected value. That is the difference between management success and outcome success.
  • D. The project charter states the project's purpose, objectives and success criteria, but being consistent with it only shows that execution matches the requirements set at initiation. Whether benefits are realized at the planned points in time has to be checked through the measurement mechanism in the benefits management plan, so it cannot directly measure whether value has been realized.

Key takeaway To judge whether value is being delivered, check consistency with the measurement mechanism in the benefits management plan, not just cost and schedule.

Variation If the question asked “what was the basis for judging whether the project was worth investing in at approval?”, the answer would move from the benefits management plan to the business case.

Something wrong with this question?

Report an issue with this question

Example 2 Someone says there is no business value: review the benefits management plan together

Question 2Example

At a lessons learned meeting, a stakeholder says the project was not successful because it did not bring the expected business value. How should the project manager respond to this challenge?

Show answer and explanation

Correct answer: B

The project is in closing and the lessons learned stage. A stakeholder says at the meeting that the project was not successful because it did not bring the expected business value, and the question is how the project manager should respond.

The core of the challenge is “was the expected value realized?” The benefits management plan states the target benefits, the timeframe and the metrics. Going through it with the person raising the challenge shows whether the project achieved the expected benefits, whether the challenge holds, and where the gap lies. This is more convincing than each side talking past the other. When handling a challenge, first use the same yardstick, so the two sides do not each use their own standard. If a gap is indeed found, analyze the causes together and record them in lessons learned. The answer is B.

Why the other options are wrong

  • A. Reviewing work tasks one by one looks at what was done. It is not a measure of whether value was realized.
  • C. The budget reflects the input. Checking the budget alone cannot show whether value has appeared.
  • D. The communications management plan specifies how information is passed on. It has no direct bearing on whether benefits were realized.

Key takeaway When someone says the project did not deliver the expected value, check it together against the benefits management plan.

Variation If the challenge were “why did we take on this project in the first place?”, go back to the business case (supported by the objectives and rationale in the project charter where needed) to explain the reasons for approval, not the benefits management plan; the business case answers “whether to do it” and the benefits management plan answers “how it is going.”

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • If benefits have begun to be realized, or governance and communication requirements call for it, the status report should include tracking results for benefits metrics as well as schedule and cost.
  • The measures of benefits should be agreed with stakeholders and approved at the start; if they are set only at the end, there is no baseline to compare with.
  • When a benefit depends on outside conditions, manage it as an assumption and a risk; do not assume it will hold.
  • Registers and logs are project documents, not part of the benefits management plan.
  • On time and on budget is usually not enough in itself to prove value has been delivered; judge on the business case, the benefits management plan and the agreed quantitative or qualitative success criteria together (if satisfaction is defined as a target benefit, its measurement can also serve as evidence of value).
  • The benefits management plan measures the benefits themselves, not the deliverables.

Key takeaways

  1. The benefits management plan describes how and when benefits will be delivered and establishes the mechanisms to measure them; the business case covers "is it worth doing?", while the benefits management plan covers how and when benefits are realized and how they are measured.
  2. Seven elements: target benefits, strategic alignment, timeframe for realizing benefits, benefits owner, metrics, assumptions, risks.
  3. The plan begins early in the life cycle as the target benefits are defined, is maintained iteratively, and stays aligned with the business case, the project charter and the project management plan.
  4. Metrics must be measurable and state the target or criterion and data source, with a comparison baseline where relative improvement is being measured; the owner must be clear, and external dependencies go into assumptions and risks.
  5. When someone challenges the value, the descriptions of benefits do not agree, or nobody can say what the benefit is, go back to the benefits management plan first.

Lesson 3

Business Documents: Nature, Maintenance and Ownership

Lesson video

Lesson overview

The business case and the benefits management plan are together called the business documents. They are neither project documents nor components of the project management plan, and that positioning decides who may change them, when and how. This lesson covers the nature of business documents, their role in the various processes, how the sponsor and the project manager divide the work, and the standard response when a business document has gaps. The question patterns are predictable, and a few rules can help you answer them reliably.

What kind of documents business documents are

The business case and the benefits management plan are both developed before the project is initiated, and both are referenced after the project has been completed. They are therefore considered business documents rather than project documents or components of the project management plan. As appropriate, they may be inputs to some of the processes involved in managing the project, such as Initiate Project or Phase: the business documents are inputs to that process, and the project charter is its output.

Business documents usually originate outside the project and contain the project objectives and information on how the project contributes to the business objectives. Although developed before the project starts, they still need periodic review, because markets, strategies and regulations change and the premises in the documents may no longer hold. In some organizations the business case and the benefits management plan are maintained at the program level.

A table puts the document types side by side and helps you decide "whom to go to, and whether it can be changed":

Type of documentExamplesWho is mainly responsibleCan the project manager change it directly?
Business documentsBusiness case, benefits management planThe sponsor is usually responsible for the business case; the benefits management plan is maintained as the organization's governance arrangesNot on their own; the project manager gives advice and takes part as authorized
Project management plan and its componentsScope management plan, schedule management plan, etc.Project manager and teamYes (through the change process)
Project documentsProject schedule, registers, logs, reportsProject manager and teamUpdated according to responsibilities and document control requirements; documents under configuration control must be changed through the change process

Who is responsible: the sponsor owns the business case, the project manager advises

The project sponsor is usually responsible for developing and maintaining the business case. The project manager's job is to provide advice and insight so that the business case, the project management plan, the project charter and the benefits management plan describe the success criteria in ways that match one another and fit the organization's objectives. In practice, a manager may ask you to write it, but by the body of knowledge the owner is the sponsor; with the sponsor's authorization, the project manager can take part in writing it.

So the sponsor usually develops and maintains the business case, and the project manager provides advice and insight and may take part as the organization arranges. Who may change a business document is decided by organizational governance and authorization, and the project manager should not exceed that authority and change them alone. Common exam practice: when the stem gives no other conditions, "explain the situation to the sponsor and offer suggestions for improvement" beats "fill in the data yourself" and beats "go on without dealing with it".

The role of business documents in the various processes

Business documents are not used just once at approval; they run through the whole project:

  • Initiating: an input to Initiate Project or Phase, stating the project objectives and rationale.
  • Planning: the project management plan must stay consistent with the success criteria in the business case and the benefits management plan.
  • Executing and monitoring: check against the business documents whether the project has drifted from the business objectives; when someone questions the benefits, go back to these two documents as well.
  • Closing: use them to measure whether the project succeeded, and hand benefits tracking over to the business side.
  • Audits and reviews: to verify the cost-benefit analysis made at approval and judge whether the project was reasonable at the time, examine the business case first.

How to handle it: three typical situations

First, the business documents have gaps or are out of date. The business case lacks cost data or does not identify the business need, or the benefits information in the document repository has not been updated. The project manager's first step is to verify the inconsistencies, explain the situation to the sponsor and offer suggestions for improvement. The project manager should neither change the document alone nor ignore the problem and carry on.

Second, taking over a project already under way. First read through the business case, the project charter and so on, then check your understanding with the sponsor and the author of the business case, find and clear up any existing or potential misunderstandings, and only then move on.

Third, preventing conflict in advance. For a question of benefit ownership such as "which department are the cost savings credited to," the sponsor, as the organization's governance arranges, should have the parties confirm before the start who owns the benefits and put the conclusion into the business case. The benefits owner and metrics are also written into the benefits management plan (the two business documents stay consistent), in documents both sides accept, so there is nothing to argue about afterward.

Example: taking over an EV charging station project

A newly assigned project manager has read the business case, the project charter and the statement of work, and has talked with the sponsor about scope and objectives. Before the kickoff meeting, the manager also asks the sponsor and the business analyst who wrote the business case to sit down and compare notes. The sponsor understands "cover the ten operating sites on ten campuses," while the business analyst wrote "cover all twenty-four operating sites" (fourteen of which are outside those campuses), so the coverage and the scale differ greatly. The two align on the spot, the sponsor confirms and updates the business case, and the project manager does not change it alone.

The audit and review scenario deserves one more comment. When internal audit wants to verify the cost-benefit analysis made at approval and judge whether the project was reasonable at the time, it looks first at the business case, not the project management plan or schedule reports. The reason is simple: the business case records the objectives, reasons and estimating basis at that time, while the other documents record "how it is done." This also shows that business documents must be kept carefully and their versions kept clear; even after the project ends they remain the evidence for judging success or failure.

Worked examples

Example 1 How to avoid insufficient value after delivery: regularly confirm that objectives still match business needs

Question 1Example

A mobile app for online food ordering has been completed to standard, and the customer has formally signed the acceptance report. But at handover to the operations department, senior management points out that, as a project, delivery is fine, but given current market conditions the business value of the result is limited. To avoid this outcome in advance, what should the project manager have done?

Show answer and explanation

Correct answer: A

A mobile ordering app was built to standard and the customer signed the acceptance report. At handover to operations, senior management points out that delivery is fine but, given current market conditions, the business value is limited. The question is what the project manager should have done in advance to avoid this.

Business documents are developed before the project starts but need periodic review and maintenance. When market conditions change, the project's objectives may no longer fit the business need. By periodically confirming during the project that the objectives still match the business need, and by advising the sponsor as soon as a deviation is found, the project manager avoids discovering after delivery that the value is insufficient. “In advance” in the stem calls for proactive action during the process: B comes at acceptance, which is too late, and D passively waits until closure to ask the sponsor and lacks proactive, periodic confirmation during the process. The keys are “in advance” and “periodically,” so the answer is A.

Why the other options are wrong

  • B. By acceptance the deliverables are already complete. Inviting a review then can only reveal problems and is too late to change direction.
  • C. The stem already says delivery was compliant. However detailed the processes and plans are, they cannot guarantee that the objectives still match market needs.
  • D. This is passively waiting until closure to ask for help. The project manager should proactively and periodically confirm that objectives and business need are consistent, not ask only after a problem appears.

Key takeaway Business documents need periodic review during the project; when objectives and business need no longer match, find out early and recommend an adjustment.

Variation If a deviation has already been found, the project manager should inform the sponsor immediately and offer recommendations, and the sponsor decides whether to update the business case.

Something wrong with this question?

Report an issue with this question

Example 2 Who is responsible for developing and maintaining the business case

Question 2Example

Which role is usually responsible for developing and maintaining the business case?

Show answer and explanation

Correct answer: D

Ownership of business documents: which role is usually responsible for developing and maintaining the business case?

The business case and the benefits management plan are business documents developed before the project starts. PMBOK 8 states that the project sponsor is generally accountable for the development and maintenance of the business case, and the project manager is responsible for providing recommendations and oversight so that the success criteria in the business case, the project management plan, the project charter and the benefits management plan align with one another. The division of labor between the two cannot be reversed. The answer is D.

Why the other options are wrong

  • A. The project manager's duty is to provide advice and insight and is not usually to develop and maintain the business case (in some organizational settings the project management team may help prepare it, tailored to the organization), and the project manager may not change it alone.
  • B. The customer is the recipient of requirements and value and can take part in discussions, but does not develop and maintain the business case. The customer's views can inform the business case, but the sponsor is responsible for developing and maintaining the document.
  • C. A business analyst may help write it, but the one responsible for developing and maintaining the business case is the sponsor.

Key takeaway The business case belongs to the sponsor, and the project manager only advises.

Variation If asked who the benefits owner in the benefits management plan is, the answer is the person named in the plan, usually on the business side, and it does not automatically fall to the sponsor or the project manager.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When you find the business case has gaps or outdated information, verify the inconsistencies first and give the sponsor suggestions; do not change it yourself and do not ignore it.
  • When taking over a project already under way, check your understanding of the business case with the sponsor and the author first, clear up misunderstandings, and then move on.
  • Benefit ownership must be confirmed by all parties before the start and recorded in a business case both sides accept, and the benefits owner and metrics are written into the benefits management plan; remedying it afterward is too late.
  • Business documents are not project documents and are not components of the project management plan.
  • Review the business documents periodically during the project; do not wait until acceptance to find that the objectives have drifted from the business need.

Key takeaways

  1. The business case and the benefits management plan are business documents, developed before initiation; they are not project documents or components of the project management plan.
  2. Business documents can be inputs to processes such as Initiate Project or Phase and are used after completion to judge success or failure; they need periodic review.
  3. The sponsor usually develops and maintains the business case; the project manager mainly provides advice and insight so the success criteria in the four documents match.
  4. On finding gaps: explain the situation and offer suggestions. On taking over a project in progress: check your understanding with the sponsor and the author first.
  5. Sensitive matters such as benefit ownership are written before the start into a jointly approved business case, with the benefits owner and metrics recorded in the benefits management plan, and the two stay consistent.

Lesson 4

Business Documents in Scenario Questions

Lesson video

Lesson overview

The first three lessons covered what the business case and the benefits management plan contain and who owns them. This is an application lesson: which signals in a stem should send you back to the business documents, and what do you do once you are there? These scenario questions are common, and the stems vary widely: someone challenges the project, a competitor releases a new product, strategy shifts, a key stakeholder does not accept the benefit estimates, the sponsor wants benefits early. But the main thread behind the answer is the same: check the business documents first; where ongoing business justification, strategic alignment or a change of authorization is involved, confirm with the sponsor or the appropriate authorized person as governance arranges, and adjust through the process. This lesson organizes it as five signals and five actions.

Five signals, five actions

Signal 1: someone asks "why are we doing this project?" The person asking may be an executive on the customer side, an influential stakeholder or a team member. First listen to their concern, then go back to the business case (supported by the objectives and rationale in the project charter where needed) and explain why the project is worth doing. When the question asks "which document explains why it is worth doing," choose the business case. When stakeholders disagree about the value, you can bring everyone together to review the business case. Do not avoid the question, and do not defend the project based only on your impressions.

Signal 2: the sponsor proposes a new idea or opportunity. The sponsor wants a new service launched, or the customer wants to benefit earlier. The soundest action for the project manager is first to review the business case and the benefits management plan, analyze the value, cost and impact of the new idea, and give advice to the sponsor. The sponsor maintains the business case as governance arranges, and a change decision follows where needed (common exam practice is "first supplement the business case"). Do not change the approach or add work on your own authority, and above all do not draw on the management reserve to rush the schedule.

Signal 3: external conditions change and shake the product's value. A competitor releases a stronger product, business parameters change, the market shifts sharply. The project manager's first step is neither to reject the change nor to decide alone to stop, but first to assess the effect of the external change on project value, scope and the business case, then inform the sponsor, review the business case together and confirm whether the organization still supports the project. Once it is confirmed to still be supported, handle it through governance and the change process, for example by updating the requirements. Even if schedule and cost are normal, do the analysis before the phase gate so that the gate review can assess business value.

Signal 4: doubt about the alignment of benefits with strategy. The project plan's emphasis has drifted from the latest strategy, or at a charter review stakeholders think the project does not fit company strategy. First go to the sponsor, who knows the strategy best, to clarify; then the sponsor and project manager together recommend adjusting the project benefits or the project plan to align them with organizational strategy. The project manager should not unilaterally change the business documents, and should not go on while skirting the disagreement.

Signal 5: benefits must be confirmed or demonstrated. A new project manager takes over a hybrid project and must confirm the benefits already identified: use the business case. Someone worries that the iterative approach will drift from strategy: have them look at the strategic alignment in the benefits management plan. Keep checking business justification against the business case, and track outcomes and actual benefits according to the metrics, timing and responsibilities in the benefits management plan. Completed deliverables do not mean the benefits have been realized, and benefits that only arise after the project ends are still monitored and reported as the plan says.

Use under different approaches

How the business documents are used under three kinds of approach

  • Predictive: the business case and benefits management plan take initial shape before initiation, are checked against at phase gates, at major changes and when changes are made, and are reviewed periodically; the benefits management plan keeps being updated and maintained.
  • Adaptive: the business case is still needed, to establish economic feasibility; value is delivered in priority order, a little at a time, and each iteration review can check whether the value has materialized.
  • Hybrid: when design and execution are broken into small packages for delivery, first agree with stakeholders on measurable benefits and assign someone to monitor and report them, and only then discuss the form of reporting. Under any approach, look at the benefits management plan for the content, measurement and realization arrangements of the benefits, and check against the business case for the reasons for approval and the expected value.

For a project delivered in phases, check the benefits realized and the leading indicators against what the business case and benefits management plan expect, at the points, phase gates or applicable milestones the benefits management plan specifies (benefits realized after the project is complete continue to be monitored and reported as planned), rather than looking only at cost and schedule. Deviations in value must be caught early by monitoring throughout, not discovered at closure. Intangible benefits such as brand building also need monitoring across the whole project, such as progress in reputation, rather than looking back only at the end.

The order in which to handle things

When several signals stack up, check in this order. First, has a change appeared at the level of value or strategy? If so, check the business documents first. Second, do the business documents still hold? If unsure, confirm with the sponsor. Third, does anything need adjusting? Whether it is the requirements, the benefits or the plan, the project manager analyzes and recommends; approval or prioritization decisions follow the established governance and change management arrangements and are made by the designated authority (the sponsor, the change control board, the project steering committee, the product owner in an adaptive environment, and so on). Fourth, once the adjustment is approved through the established change process, update the project management plan and related documents. This order avoids two typical errors: acting at once (changing the plan, drawing on reserves) or doing nothing.

Example: a tariff change raises procurement cost

A smart warehouse project is reviewing its benefits management plan when the government announces a tariff change on a category of imported equipment, which will raise equipment procurement costs. The project manager's correct action is first to assess the effect of the tariff change on cost and benefits, then to evaluate it with the sponsor and update the benefits management plan as governance arranges, so that target benefits, strategic alignment and so on match reality. Updating the risk register, switching procurement channels, submitting a change and drawing on the management reserve are all possible later actions, but none of them may skip the step of "assess the effect and check the benefits."

Worked examples

Example 1 A change in external business parameters: assess the effect first, then revise the benefits management plan

Question 1Example

A company is carrying out a smart warehouse project, and the project manager and the sponsor are reviewing the benefits management plan to make sure the business objectives and target benefits can be achieved. Just then the government announces a tariff change on a category of imported equipment, which will raise the project's equipment procurement cost, and the project manager first has to confirm the effect of this change on the target benefits. What should the project manager do?

Show answer and explanation

Correct answer: D

On a smart warehouse project, the project manager and the sponsor are reviewing the benefits management plan when the government announces a tariff change on a category of imported equipment, which will raise equipment procurement costs. The project manager first has to confirm the effect of the change on the target benefits. The question is what to do.

An external change may shake the project's expected benefits, so the first step is to assess the effect and then revise the benefits management plan on that basis, so that the target benefits, strategic alignment and the like still match reality. The project manager works with the sponsor to keep the business objectives and benefits aligned, and only after that do downstream adjustments come up. “Reviewing the benefits management plan” in the stem is also a clue: the external change occurs in this context, so you go back and check whether the benefits still hold, rather than going straight to the downstream procurement problem. The answer is D.

Why the other options are wrong

  • A. The tariff change has already been announced, and what comes first is to confirm its effect on the target benefits; merely updating the risk register and drafting a response strategy cannot ensure the target benefits still hold. If the tax rate, effective date or effect is still uncertain, the related uncertainty can still be recorded as a risk.
  • B. Switching channels before the effect has been assessed may cause greater loss. The procurement plan is a downstream document; first see whether the benefits are affected.
  • C. Analyze the effect first, then decide whether a change is needed and whether to draw on the management reserve. Spending the reserve at the outset skips the assessment.

Key takeaway When an external change threatens the benefits, first assess the effect and revise the benefits management plan, and only then deal with downstream adjustments.

Variation If the tariff change were only a rumor and had not been announced, it would be a possible risk, to be recorded in the risk register and assessed, not an immediate reason to revise the benefits management plan.

Something wrong with this question?

Report an issue with this question

Example 2 A customer executive questions the project: present the business case

Question 2Example

A smart home controller development project is about to start. A vice president on the customer side, because a similar project last year returned far less than expected, has publicly said he is not optimistic about this project. Which document should the project manager show him to explain why the project is worth doing?

Show answer and explanation

Correct answer: A

A smart home controller development project is about to start. A customer-side vice president, because a similar project last year returned far less than expected, has said publicly he is not optimistic about the project. The question is which document to show him to explain why the project is worth doing.

The business case is an economic feasibility study that states the objectives and reasons for starting the project and outlines costs, benefits, how value will be created and the project success criteria; it is the document that establishes that the project is worth the investment. To reassure someone who challenges the approval, show it and explain it item by item with the needs, benefit estimates and success criteria in it. You should also make clear how this project differs from last year's similar project, so that the vice president's doubts are really removed. The answer is A.

Why the other options are wrong

  • B. The project charter is a high-level document that authorizes the project and outlines its objectives. It does not systematically argue whether the project is worth investing in.
  • C. A cost-benefit analysis is only one of the financial analysis tools a business case can use. It compares costs and benefits only, and lacks the fuller basis of needs, how value will be created and success criteria.
  • D. The cost baseline usually has not been formed when a project is about to start.

Key takeaway When someone asks “why are we doing this project?”, bring out the business case.

Variation If the challenge were “have the benefits the project is to deliver been realized?”, show the benefits management plan and check against its metrics.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When business parameters change, the project manager should not decide alone to terminate or continue. Report to the sponsor, review the business case again, and after confirmation update the requirements through the change process.
  • When an external change appears, do not refuse it for fear of rework, and do not first draw on the management reserve or change the procurement channel directly.
  • When a key stakeholder does not accept the benefit estimates, meet as soon as possible, communicate and agree on corrective action; do not avoid it.
  • Deviations in value must be caught early by monitoring throughout, not discovered at closure.
  • When someone challenges the approval of the project, what you produce is the business case, not the cost baseline, and not just the cost-benefit analysis alone.
  • When benefits and strategy are not aligned, recommend adjusting the benefits or the project plan; do not change the business documents yourself.

Key takeaways

  1. Challenge to the project: listen, then go back to the business case (supported by the objectives and rationale in the project charter where needed) to explain; if stakeholders disagree, review the business case together.
  2. A new idea from the sponsor, or benefits wanted early: first review the business case and the benefits management plan, analyze value and cost and advise the sponsor; the sponsor maintains the business case as governance arranges, and a change decision follows where needed.
  3. External change shakes the value: first assess the effect on value, scope and the business case, then inform the sponsor, review the business case again, and once the organization is confirmed to still support it, update the requirements through the change process.
  4. Doubt about strategic alignment: first clarify with the sponsor, and together recommend adjusting the benefits or the plan.
  5. Predictive, adaptive and hybrid approaches all depend on the business case and the benefits management plan; check the benefits realized at the points, gates or milestones the plan specifies.

Lesson 5

Project Selection and Prioritization: What the Decision Rests On

Lesson video

Lesson overview

An organization's resources are limited, so when there are many projects they have to be ranked: which to do first, who gets the people, which to put off. Where does the basis for ranking come from? The answer is in the business documents. This lesson connects the business case and the benefits management plan to the portfolio management covered earlier: choose projects by maximizing business value, not by personal preference, and not on risk, revenue or duration alone. At the end it briefly introduces the financial measures often used in a business case and gives a small example, so that you see what "comparing by net present value" means; the full calculation of each measure is in the finance topic.

What to look at when prioritizing

The business documents give three kinds of basis:

  1. Strategic alignment: whether the project is consistent with the organization's strategy and how much it contributes to the strategic objectives.
  2. Target benefits and metrics: the target benefits written in the benefits management plan, and whether they have quantifiable metrics.
  3. Cost-benefit: the cost-benefit analysis in the business case, and whether the investment and the return make sense.

Together the three make up "contribution to the organization's business value." This is in line with portfolio management's "choose the right projects": projects are selected to put limited resources where they best serve the strategic objectives.

Several rules follow. When several projects compete for resources, allocate by contribution to organizational strategy, not by who speaks loudest. For a business case that wants the project to rank well, the most important thing is to show that the project is aligned with the company's objectives and strategy. When the company is not yet profitable and many projects are running late, re-rank them considering organizational strategy, mandatory obligations, risk, funding and expected value; if the current strategy clearly focuses on improving profitability, raise the priority of projects with a larger expected profit contribution and concentrate effort where it is most valuable (value may also be non-financial value such as compliance or social impact).

Reasons that cannot serve as the basis

Questions like to offer distractor reasons that look plausible. Learn to spot them:

Distractor reasonWhy it does not work
The chief executive favors itA leader's preference is not the standard by which the benefits management plan measures a project
It is easy to do and the plan can be drawn up quicklyLow difficulty has nothing to do with how large the benefits are or whether it fits the strategy
It meets a key stakeholder's demandIt can be one reason for approval, but it is not the core basis for ranking
Looking only at low risk, or only at high revenue, or only at short durationA single dimension, not an overall view of business value

What if the strategy changes

After the ranking is set, the strategy may also be adjusted. A project manager is assigned to a legacy order system upgrade whose plan is final and whose requirements have been handed to development, and then the company announces a new strategic direction. What the project manager should do is first work out how this project relates to the organization's overall vision and explain it to the team. When the project plan has drifted from the strategy, or the benefits are not aligned with it, recommend adjusting the project benefits or plan to align with the strategy, and confirm with the sponsor where needed. When a team member asks "why are we doing this project, and does it fit the strategy?", show them the latest benefits management plan, which contains the target benefits and strategic alignment.

Priorities in agile: value, risk, cost

In agile work, ranking weighs value, dependencies, technical or operational risks, and stakeholder feedback; cost or effort may also inform economic sequencing. PMBOK 8 asks that priority be set based on value, dependencies, and technical or operational risks. High-value work is generally favored. Whether high-risk work should be brought forward depends on whether early work will validate assumptions or reduce later loss, together with dependencies and other constraints. Common exam practice is to treat priority as rising with business value and risk and falling with cost, so high-value, high-risk, low-cost items tend to come first; use it as a guide, not an exact formula.

Financial measures in a business case

The financial measures commonly used in a business case are return on investment (ROI), payback period, net present value (NPV), internal rate of return (IRR) and benefit-cost ratio. When several of these appear together and you need to select projects, common exam practice is: when other conditions are equal and the candidate projects are comparable, look at net present value first, because it discounts over time and is the most dependable for investment decisions (actual decisions also consider the discount rate, the evaluation period, funding constraints, strategic alignment and risk). The full calculation of these measures is in the finance topic; here a small example shows why NPV is looked at.

Worked example: two candidate projects compared by net present value

The company must choose one of Project A and Project B, with a cost of capital (discount rate) of 10%.

  • Project A: investment $900,000, net benefit of $400,000 a year for three years.
  • Project B: investment $900,000, no benefit in the first two years, and a one-time return of $1,100,000 in year three.

Step 1. Discount Project A's $400,000 a year for three years at 10%. The present value annuity factor is 2.4869, so present value = $400,000 × 2.4869 = $994,760, and net present value ≈ $994,760 − $900,000 = +$94,760.
Step 2. Discount Project B's $1,100,000 in year three: present value = $1,100,000 ÷ 1.1³ = $1,100,000 ÷ 1.331 ≈ $826,446, and net present value ≈ $826,446 − $900,000 = −$73,554.
Step 3. Project A's net present value is positive and Project B's is negative, so choose Project A.
For comparison: A's payback period is $900,000 ÷ $400,000 = 2.25 years and B's is three years. B's total benefit of $1,100,000 looks not much below A's $1,200,000, but the difference shows once the amounts are discounted.

One last point that is often overlooked: ranking is not done once. During the project the premises in the business case change, and competitors' moves and regulatory changes alter the project's relative value. At the portfolio level the review must be periodic, and if a project keeps failing to stay aligned with the business case and the expected outcomes, terminating it and giving the resources to a more valuable project is a normal portfolio management action. The project manager's responsibility is to give the sponsor and the portfolio manager an honest and timely picture of the project's latest value, so that they have a basis for making trade-offs.

Worked examples

Example 1 Ranking four candidate projects on the basis of the benefits management plan

Question 1Example

A portfolio manager and senior management are ranking four candidate projects for next year. Project A is aligned with company strategy and has clear target benefits and metrics. Project B is favored by the chief executive. Project C is relatively easy to do and its plan can be drawn up quickly. Project D meets the demands of a key stakeholder. Based on portfolio management's strategic-value criteria, which project should be chosen first?

Show answer and explanation

Correct answer: C

A portfolio manager and senior management are ranking four candidate projects for next year: A is aligned with strategy and has clear target benefits and metrics; B is favored by the chief executive; C is easy to do; D meets a key stakeholder's demands. The choice has to be made on strategic-value criteria.

Portfolio management selects and prioritizes projects according to strategic alignment and the value they are expected to deliver. Project A is aligned with strategy and has clear target benefits and metrics, so it provides the strongest evidence of strategic alignment and measurable expected value. The other three descriptions each provide only one piece of information that is insufficient by itself to determine priority: a leader's preference, ease of doing, or meeting one demand. Unlike Project A, they do not establish strategic alignment and measurable expected value. Prioritization looks at contribution to the organization's business value, so the answer is C.

Why the other options are wrong

  • A. Meeting a stakeholder's demand can be one reason for approval, but prioritization looks at strategic alignment and expected benefits, not at whose demands are met.
  • B. A leader's favor may influence a decision, but personal preference does not establish strategic alignment or expected value and cannot by itself determine project priority.
  • D. Being easy to do and having a plan quickly written shows only low difficulty. It has nothing to do with how large the benefits are or whether the project is aligned with strategy.

Key takeaway When prioritizing projects, look at strategic alignment, target benefits and metrics, not personal preference or ease.

Variation To compare further between two strategically aligned projects, look at cost-benefit; when several financial measures conflict and the candidates are comparable, look at net present value first (common exam practice).

Something wrong with this question?

Report an issue with this question

Example 2 A team member asks why the project is being done: share the benefits management plan

Question 2Example

While a project is under way, a key team member asks the project manager which target benefits the project is meant to achieve and whether it is aligned with organizational strategy. Which document should the project manager share with the member?

Show answer and explanation

Correct answer: D

During the project a key team member asks which target benefits the project is meant to achieve and whether it is aligned with organizational strategy. The question is which document to share.

This question rests on the “target benefits” and “strategic alignment” elements of the benefits management plan. It is a high-level business question, so go back to the business documents. The benefits management plan states the target benefits, strategic alignment and so on, and so best answers the team member's questions and shows how their work connects to the organization's objectives. Answering the team member also has another value: helping them see how their work serves the strategy raises their commitment to the project's objectives and makes it easier for the team to take day-to-day decisions consistent with value. The answer is D.

Why the other options are wrong

  • A. The scope management plan explains how scope is defined, validated and controlled. It does not answer the relationship between the project's purpose and strategy.
  • B. The project management plan explains how the project is executed, monitored and closed. For business-level content such as target benefits and strategic alignment, the most direct source is the benefits management plan.
  • C. The communications management plan only specifies how information is passed on. It does not explain the project's purpose or strategy.

Key takeaway To ask whether the project's purpose is aligned with strategy, look to a high-level business document such as the benefits management plan.

Variation If you need to know “why the project was worth investing in at the start,” you can show the business case as well. The two business documents have different emphases: the case explains why it is done, and the benefits management plan explains how and when benefits are realized and how they are measured.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Choose projects by maximizing business value, not by a leader's preference, ease or duration, and not on risk or revenue alone.
  • Agile prioritization considers technical or operational risk; high-risk work may be brought forward when early validation reduces later loss, but “the higher the risk, the earlier” is not a fixed rule.
  • When strategy and benefits do not match, the project manager recommends alignment; the project manager does not change the business case directly.
  • The scope management plan, the project management plan and the communications management plan do not answer "why is the project being done and does it fit the strategy?"; the business documents do.
  • When several financial measures contradict one another, look at net present value first (common exam practice; the candidate projects must be comparable).

Key takeaways

  1. The basis for prioritizing is in the business documents: strategic alignment, target benefits and metrics, and cost-benefit.
  2. Choose projects by contribution to the organization's business value; a leader's preference, ease and a stakeholder's demand are not the core basis.
  3. When the strategy changes, first work out how the project relates to the new strategy, then recommend adjusting the benefits or the plan; for questions about the project's purpose and strategy, go back to the benefits management plan.
  4. Agile prioritization considers value, dependencies, technical or operational risks, and stakeholder feedback; cost or effort may inform economic sequencing. Common exam practice: priority rises with value and risk and falls with cost, used as a guide rather than an exact formula.
  5. Financial measures: ROI, payback period, NPV, IRR, benefit-cost ratio; when selecting projects, look at net present value first (common exam practice; the candidates must be comparable).

This chapter has 53 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.