Life Cycles and Development Approaches

The Project Life Cycle

PMP · Life Cycles and Development Approaches · 2 lessons · about 24 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The project life cycle is the series of activities and/or phases that a project passes through from its start to its closure, and it provides the foundational framework for managing a project. This basic framework applies regardless of the specific project work involved or the development approach adopted. This chapter covers the skeleton of that timeline: how a project is divided into phases, how phase gates control the passage between them, and how risk, uncertainty and the cost of changes vary along the timeline. It then covers why the life cycle is not a fixed template, how it differs from the product life cycle, and how to tell apart four concepts that are often confused: project phase, development approach, development phase and focus area.

After this chapter you should be able to: name the three time relationships between phases and the attributes of a phase; say what a phase gate review checks against and which decisions it can produce; judge what to do after a phase ends in a predictive-project scenario; sketch (or describe) the trends of the risk and cost-of-change curves; explain what a project manager does when no standard life cycle exists; distinguish the project life cycle from the product life cycle; and tell apart the four easily confused concepts in one pass.

Lessons in this chapter

Chapter concept map

ConceptKey pointsIn one line
Project phaseSequential, transitional or overlapping; has entrance and exit criteriaCulminates in the completion of one or more deliverables and/or outcomes
Phase gateA review leads to one of six decisions; can be placed before a phaseChecks against criteria; more than just pass or stop
Two curvesRisk and uncertainty are usually high early and low later; the cost of changes is usually low early and high laterMove important decisions and responses earlier
FlexibilityChoose the approach, define the processes, adjust the attributesWith no standard, tailor one to the project
Product life cycleIntroduction, growth, maturity, retirementOne product may include many projects
Four conceptsPhase, development approach, development phase, focus areaA span of time, a means, the stage where deliverables are created and tested, a grouping of actions

Study tips and practice

  • First memorize the trends of the two curves, then the six decisions a gate review can make, and finally run through the common concept questions using the distinction among development approach, development phase and focus area. When options have similar names, first ask which kind of question each one answers.

Lesson 1

Project Phases, Phase Gates, and the Trends of Risk and the Cost of Changes

Lesson video

Lesson overview

The life cycle topic starts with the plainest question: how is a project divided over time, and how is each segment verified? This lesson covers two things: project phases and phase gates, and how risk, uncertainty and the cost of changes trend along the timeline. On the exam they show up in two forms: predictive scenario questions that ask "what do you do after a phase ends?", and concept questions that ask "which curve goes up and which goes down?". ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery) and Task 10 (Manage project closure). The next lesson covers why the life cycle is not a fixed template, and how it differs from the product life cycle, development approaches and focus areas.

The project life cycle and project phases

The project life cycle is the series of activities and/or phases that a project passes through from its start to its closure. It provides the foundational framework for managing a project, and this basic framework applies regardless of the specific project work involved or the adopted development approach. Projects are often decomposed into multiple phases. A project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables and/or outcomes.

Phases may be sequential, transitional or overlapping, and one project can use a combination of these. In a renovation project, the plumbing and wiring must be finished before the tile goes down, which is sequential; the procurement department starts requesting quotes when only half of the design drawings are out, which is overlapping. Phases can also be described by a set of measurable attributes: name, number, duration, resource requirements, entrance criteria for moving into the phase, and exit criteria for completing it. The entrance and exit criteria are the basis for the phase gate review that follows.

Figure 1 Project phases and phase gates

Phase gates: what is reviewed and how decisions are made

A phase gate may occur after the end of a phase, before the beginning of the next phase. Phase gates often include a review (sometimes known as stage gate, gate review, iteration review or decision point review) to check that the desired outcomes or exit criteria for the phase have been achieved before proceeding to the next phase. Think of a gate as a door with someone checking a list: projects that meet every criterion proceed, while the others may be modified, repeated, paused, or stopped.

The review uses two kinds of criteria. Exit criteria may be tied to acceptance criteria for deliverables, contractual obligations, meeting specific performance targets, or other tangible measures. Factors such as resource availability, verification of the project's viability, and current alignment with organizational goals may determine the entrance criteria. The project's performance and progress are compared to project and business documents that specify expectations, and a decision (for example, a go/no-go decision) is made as a result of this comparison. PMBOK 8 lists six possible decisions: continue to the next phase; continue to the next phase with modification; end the project or phase; remain in the phase; repeat the phase or elements of it; or park the project temporarily to address another urgent business initiative.

While phase gates are traditionally placed at the end of each phase, they can also be placed at the start of each phase. These starting phase gates (pre-phase gates) help confirm three things: that the project is properly aligned, that sufficient resources and planning are in place, and that potential risks are addressed before progressing further. One more checkpoint means more control and a better chance of success.

Worked example: how a gate review turns into a decision

A medical device company is developing a home blood pressure monitor, and holds a gate review when the prototype design phase ends. The exit criteria say all three key specifications must be met. The review finds that measurement error is about 20% above the maximum permitted level, while the other two specifications pass. The review panel's decision is "continue to the next phase with modification": the design team has two weeks to run additional calibration tests and may proceed to pilot production only after they pass. If the error had been far off and competitors had already launched, the decision might have been "repeat the phase" or even "end the project". So a gate's outcome is not limited to "pass" and "stop".

What the project manager does after a phase ends

In a predictive project, completing the first phase does not mean the project is complete. What you do now is close out the phase: confirm that the deliverables have been verified through Monitor and Control Scope for quality and formally accepted by the authorized stakeholders through Validate Scope, organize the project documents, record lessons learned, and prepare to hand over to the next phase. If the governance arrangement includes a phase gate, then hold the gate review and act on its decision: move on to the next phase (completing the handover of results), move on with modification, remain in the phase, repeat it, park the project, or end the project or phase. A project that completes normally gets its overall closure after all the planned phases are finished. A project terminated early must also be closed out (PMBOK 8's Closing focus area includes early termination; closing first and then releasing people, rather than simply pulling staff off, is common exam practice). Some industries also use gates to bring in outside oversight. For example, projects in heavily regulated fields such as new drugs or medical devices may require phase gates so that a regulator can carefully assess whether the project has shown enough promise to justify further development.

Trends of risk, uncertainty and the cost of changes

Regardless of the project life cycle, risk and uncertainty are usually greatest at the start of the project or phase and decrease over the project's life cycle as decisions are reached and deliverables are accepted. The cost of changes runs the opposite way: low at the start, and usually higher later on (the curves are from PMBOK 8 Figure 4-1).

Figure 2 Risk and uncertainty and the cost of changes over project progress

Think of building a community canteen. Before construction, whether the stove goes on the east wall or the north wall is just a line on the drawing, and erasing it and redrawing it costs almost nothing. But nobody can say how many diners there will be at peak time, so uncertainty is high. Once the equipment is installed and the pipes are buried, the requirements have long since become clear and uncertainty is low, but asking to move the stove to another wall now means tearing out finishes, rerouting pipes and re-inspecting, at many times the cost. So important decisions, assumption checks and risk responses should be moved as early as possible.

Two other characteristics also apply within a phase. In many predictive projects, cost and staffing levels are low at the start, increase as the work is carried out, and drop rapidly as the project or phase ends. And the ability of stakeholders to influence the project’s scope is, in some scenarios, highest at the start and decreases gradually; in other scenarios they should be encouraged to take part actively during execution and give feedback, so that risks and their impacts are detected earlier.

How predictive and adaptive approaches respond to this pattern

  • Predictive: the scope is defined up front and changes get more expensive the later they come, so invest in planning early and use change control to limit late changes.
  • Adaptive: results are reviewed regularly and feedback is gathered continuously, so that risks and their impacts surface earlier and changes are absorbed between iterations instead of piling up until late in the project.

Worked examples

Example 1 Scenario: what to do after the first phase ends

Question 1Example

On a predictive project, the planned delivery work of the first phase is complete and the phase is nearing its end, but the project as a whole has not ended. What should the project manager do?

Show answer and explanation

Correct answer: A

A predictive project proceeds in phases. The planned delivery work of the first phase is complete and the phase is nearing its end, but the project as a whole has not ended. You must decide what the project manager should do now.

A phase is a stretch of work that culminates in the completion of one or more deliverables. When a phase ends, what you do is close out that phase: verify that the deliverables meet the acceptance criteria, organize the project documents, record lessons learned and prepare for the next phase. If the governance arrangement includes a phase gate, then participate in the review and act on its decision. For normal completion as planned, closing the project as a whole waits until all phases are complete; the end of the current phase cannot be treated as the end of the project. The answer is A.

Why the other options are wrong

  • B. A phase boundary is a control point. Ignoring it bypasses the required phase-closing work and, if governance calls for a phase gate, also skips that review, allowing the previous phase's leftover problems to be carried into the next phase.
  • C. For a project completed as planned, overall closure comes after all phases are complete. Only the first phase has ended, and closing all work would cut off the later phases with it.
  • D. The end of a phase is not project termination. The gate review may indeed decide to end the project, but until the review makes a decision the project manager should not halt work and wait on his own.

Key takeaway At the end of a phase, close out the phase; if a phase gate is established, participate in the review and act on its decision. For normal completion as planned, overall project closure follows completion of all phases.

Variation If the gate review finds that only some of the exit criteria were met, the decision could be “continue to the next phase with modification”, “remain in the phase” or “repeat the phase”. It is not limited to pass and stop.

Something wrong with this question?

Report an issue with this question

Example 2 Concept: the trend of the curves

Question 2Example

Which statement correctly describes the project life cycle of most predictive projects?

Show answer and explanation

Correct answer: B

In most predictive project life cycles, risk, uncertainty and the cost of changes follow a pattern over time.

The two curves run in opposite directions. Risk and uncertainty are usually highest at the start of the project or phase and fall gradually as decisions are reached and deliverables are accepted. The cost of changes is small at the start, and the later it gets, the more work has been done and the wider the knock-on effects, so late in the project it usually rises sharply (see PMBOK 8 Figure 4-1). Of the four options, only “the cost of changes gradually rises as the project progresses” fits this pattern. The answer is B.

Why the other options are wrong

  • A. This is backwards. Risk and uncertainty are high early and low later, and do not rise as the project proceeds.
  • C. This is backwards. The later a change is requested, the more completed work has to be undone and the greater the cost.
  • D. Near the end of a project, decisions have been made and results accepted, so uncertainty is at its lowest, not its highest.

Key takeaway Risk and uncertainty are high early and low later; the cost of changes is low early and high later.

Variation If asked at which point a change costs the least, the answer is early in the project. If asked how an adaptive approach responds to this pattern, the answer is regular reviews and frequent feedback so that risks surface earlier and changes are absorbed between iterations.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A gate review's conclusions are not limited to "pass" and "stop". Continuing with modification, remaining in the phase, repeating the phase, and parking the project to do something more urgent are all outcomes that PMBOK 8 lists explicitly.
  • The end of a phase is not the end of the project. At a phase end you close out the phase and hand over. For a project that completes normally, overall closure comes after all phases are complete (a project terminated early must also be closed out; closing first and then releasing people is common exam practice).
  • A gate is not always placed after a phase. A pre-phase gate checks that direction, resources, planning and risks are ready.
  • The time of greatest risk and uncertainty is the start of the project or phase, not the end. The cost of changes goes up the later it is, not down.
  • The two curves show trends, not exact quantitative relationships, and they do not mean that changes can never be made late.

Key takeaways

Key point

  • A project phase is a collection of logically related activities that culminates in the completion of one or more deliverables and/or outcomes; phases may be sequential, transitional or overlapping.
  • Phase attributes include name, number, duration, resource requirements, entrance criteria and exit criteria.
  • A phase gate review checks against the exit criteria and compares the project's performance and progress with the expectations in project and business documents. It can decide to continue to the next phase, continue with modification, end, remain, repeat or park.
  • Gates can be placed after a phase ends or before a phase begins (pre-phase gates).
  • Risk and uncertainty are highest at the start and fall afterward; the cost of changes is low at the start and usually rises (see Figure 2).

Lesson 2

Life Cycle Flexibility, the Product Life Cycle, and Four Easily Confused Concepts

Lesson video

Lesson overview

The previous lesson covered phases, gates and the two trend curves. This lesson answers two other questions: whether the project life cycle is a fixed template and how it relates to the product life cycle, and how to tell apart "project phase", "development approach", "development phase" and "focus area". The second group of concepts is a high-frequency exam trap, and answer options often substitute one for another. ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery). After this lesson, whenever you see an option of the form "X is ...", you will be able to say which kind of question it answers.

Life cycle flexibility

Organizations with multiple projects will often adopt a few standard project life cycles. Project managers and project teams may need to advise their management on the most appropriate life cycle to use, or it may be prescribed for them. If there is no standard life cycle, project managers and project teams should determine the best life cycle for each project. The project life cycle should be flexible enough to meet or exceed the project's target objectives in a way that protects and enhances the project's value proposition as much as possible.

Life cycle flexibility often includes three things: selecting the development approach or mix of approaches; identifying the types of processes and activities that should be performed; and adjusting the various attributes of an activity, phase or process (for example, name, duration, entrance criteria and exit criteria). In other words, a life cycle is something you can tailor to a project, not a template to apply as it is.

Scenario: what to do when there is no standard life cycle

A regional pharmacy chain wants to develop a loyalty-points mobile app. The company has no standard life cycle, and the sponsor's requirements are: validate quickly whether members will use it, and have a rigorous review before the official launch. The project manager and team design it together. First, spend three weeks building a minimal version with only scan-to-earn points and trial it in two stores, with no elaborate entrance criteria for this segment. If the trial meets its targets, move on to full development. When full development ends and before launch, set a formal phase gate that checks the acceptance criteria and whether staff training is ready. The names, durations and entrance and exit criteria of the phases were all adjusted to this project's needs. That is life cycle flexibility: they neither copied the last project nor waited for the company to issue a standard.

The project life cycle and the product life cycle

The project life cycle is independent of the product life cycle. The product life cycle is a series of phases that represent the evolution of a product, from introduction through growth, maturity, and to retirement. According to PMBOK 8 Section 4.1, project life cycles are independent of product life cycles, which can be part of the outcomes produced by a project. At the same time, one product may have several projects over its life cycle, adding or improving components, attributes or capabilities at different points. Projects may also generate outputs, which in turn enable outcomes that progressively realize the organization's strategy.

Figure 1 Several projects within one product life cycle

For example, a smart fitness band has been on the market for three years, and now a project is launched to develop a new generation of firmware for it. That project has its own start and end, and it finishes a few months later when the new firmware is delivered. The band's product life cycle began long ago and will continue after the project ends, with other projects in between, such as a new strap design or a switch of battery supplier. So when you see "life cycle" in a question, first work out whether it is the project's or the product's. The two are independent, and their phases do not have to correspond one to one.

Projects and operations meet at several points in the product life cycle: when developing new products or services, upgrading offerings or expanding outputs; while improving product or service delivery operations or their development process; at the end of the product life cycle; and at each closeout phase or iteration. Ongoing operations are not themselves part of a project.

Four easily confused concepts

Section 4 of PMBOK 8 describes the project life cycle through five factors: project phases, project development approaches, considerations for selecting a development approach, delivery cadence, and Project Management Focus Areas (formerly known as Process Groups). Four terms around them are the easiest to mix up.

A development approach is the means used to create and evolve a product, service or result during the project life cycle, such as predictive, adaptive or hybrid methods; it defines how the project will be managed and executed. The development phase is a specific stage within the project life cycle where both the actual creation and testing of deliverables occur, and it involves the detailed work that produces the project's outputs. Note that the "development approach" is separate from the "development phase of the project". The Project Management Focus Areas group project management actions into five: Initiating, Planning, Executing, Monitoring and Controlling, and Closing. A project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables and/or outcomes.

ConceptThe question it answersExample
Project phaseInto which segments is the project work divided, by related activities and deliverables?Feasibility, design, build, inspection, handover
Development approachWhat means is used to create and evolve the result, and how is the project managed and executed?Predictive, adaptive, hybrid
Development phaseWhich segment is where deliverables are actually created and tested?The build phase
Focus areaWhich category does a management action belong to?Planning focus area, Monitoring and Controlling focus area

The three commonly used development approaches are often seen as a continuous spectrum: predictive at one end, adaptive at the other, and hybrid intended to blend the advantages of both. Different phases of one project can use different approaches. Different industries may use different terms for the approaches; when the wording changes, go back to the definition of "how the project will be managed and executed" to decide.

Focus areas should not be confused with project phases, even though some names may be the same or a phase may consist mainly of the activities of one focus area. When a project is divided into phases, the actions of the focus areas interact within each phase, and the five areas do not advance in strict sequence; they often overlap within a phase. Planning and monitoring, for example, can go on at the same time. The focus areas are covered in detail in the last chapter of this topic.

Worked example

A community appointment mini-program project has five phases (feasibility, design, build, inspection and handover) and uses a hybrid approach overall. A new member asks: "Is the build phase the same as the Executing focus area?" The answer is no. The build phase is a span of time, and also the development phase in which deliverables are actually created and tested. Within it there is also planning (scheduling the next round of tasks), executing (writing code) and monitoring (watching progress and defects). Executing is a category of management action, the build is a phase, and hybrid is the development approach used for the whole project. The three terms belong to three different levels.

Worked examples

Example 1 Scenario: when there is no standard life cycle

Question 1Example

PMLyceum is about to start a store inventory-counting system project. The company has no standard project life cycle, and the sponsor requires only that the project both validate its value quickly and have reviews at key points. What should the project manager do NEXT?

Show answer and explanation

Correct answer: C

The company has no standard life cycle, and the sponsor requires quick validation of value and reviews at key points. You must decide what the project manager should do NEXT.

When there is no standard life cycle, the project manager and project team should determine the best life cycle for the project. A life cycle should be flexible enough: you can select the development approach or a mix of approaches, identify the types of processes and activities to perform, and adjust the phase name, duration, entrance criteria and exit criteria, so as to meet the objectives while protecting the value proposition. The sponsor's two requirements, quick validation and reviews at key points, call for a design that fits the project's characteristics. The answer is C.

Why the other options are wrong

  • A. A life cycle is not a fixed template. Copying the previous project does not address this project's specific need for quick validation and review points.
  • B. The lack of a standard does not mean you wait. Determining a suitable life cycle is the project manager's and team's responsibility in the first place.
  • D. The project life cycle is independent of the product life cycle, so you cannot copy the product life cycle's phases merely to ease the handover to operations.

Key takeaway A life cycle is not a template: with no standard, tailor one to the project; with a standard, you can still adjust attributes within its limits.

Variation If the organization already has a standard life cycle, you can still adjust phase names, durations and entrance and exit criteria within what is allowed. If a policy or contract requires a certain approach, you cannot override it on your own.

Something wrong with this question?

Report an issue with this question

Example 2 Concept: what a "development approach" is

Question 2Example

In training material, the project management office wants to place predictive, adaptive and hybrid under one correct concept name. Which of the following MOST accurately describes a “development approach”?

Show answer and explanation

Correct answer: B

You must place predictive, adaptive and hybrid under one concept name and judge the most accurate description of a “development approach”. Four similar concepts have to be told apart.

A development approach is the means used to create and evolve a product, service or result during the project life cycle, such as predictive, adaptive or hybrid methods, and it defines how the project will be managed and executed. The three names in the stem answer exactly the question “by what means, and how is the project managed and executed?”, which corresponds to B. The answer is B.

Why the other options are wrong

  • A. This is the definition of the development phase, the stage in the life cycle where deliverables are actually created and tested. It is a division of time, not a method.
  • C. These are the Focus Areas, which group project management actions into initiating, planning, executing, monitoring and controlling, and closing. It is a classification of actions.
  • D. This is a phase gate review, which checks applicable criteria and may decide to continue, continue with modification, end, remain, repeat, or park the project. It has nothing to do with a development approach.

Key takeaway A development approach is a means, a development phase is a span of time, Focus Areas are a classification of actions, and a gate is a review point.

Variation If the option were changed to “a grouping of project management actions into five categories”, the answer would become Focus Areas. If it were changed to “the phase where deliverables are actually created and tested”, the answer would become the development phase.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When you see "life cycle", first tell whether it is the project's or the product's. A project has a start and an end, while a product life cycle can be much longer and may include several projects.
  • A life cycle is not a fixed template. With no standard, choose the one that best fits the project; with a standard, you can still adjust phase attributes within what it allows. This is a form of tailoring.
  • A "development approach" is a means, and a "development phase" is a span of time. The names are similar but the meanings are completely different.
  • A focus area is a classification of management actions, not a phase. Initiating is not "the first period of the project", and closing does not appear only at the end.

Key takeaways

Key point

  • A life cycle needs enough flexibility: you can select the approach or a mix, identify the types of processes and activities, and adjust the name, duration, entrance criteria and exit criteria of phases.
  • When there is no standard life cycle, the project manager and team determine the best one for this project. They do not wait and do not copy.
  • The project life cycle is independent of the product life cycle, and one product life cycle can include several projects.
  • A development approach is a means; the development phase is the stage where deliverables are created and tested; focus areas are five groupings of management actions; and a project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables and/or outcomes.
  • The three commonly used approaches form a spectrum, and hybrid blends the advantages of both ends.

This chapter has 10 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.