Life Cycles and Development Approaches

Predictive and Adaptive Approaches and the Stacey Matrix

PMP · Life Cycles and Development Approaches · 3 lessons · about 35 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

A development approach is the means used to create and evolve a product, service, or result during the project life cycle, and it defines how the project will be managed and executed. PMBOK 8 groups the commonly used approaches into predictive, adaptive, and hybrid, and treats them as a spectrum: predictive at one end, adaptive at the other, and hybrid intended as a mix of the two. This chapter covers the two ends: what characterizes predictive and adaptive approaches and which projects suit each, how iterations and increments relate, how to judge uncertainty with the Stacey matrix, which factors drive the choice of approach, and which delivery cadences exist. The hybrid approach is covered in the next chapter.

By the end of this chapter you should be able to do the following. Decide from the facts in a question whether a predictive or an adaptive approach fits. Distinguish iterative, incremental, and adaptive, and recognize incremental delivery inside a predictive approach. Place a project in one of the four Stacey zones (simple, complicated, complex, chaotic) using the two axes. List the three groups of factors that influence the choice of development approach. Tell apart the four delivery cadences: single delivery, multiple deliveries, periodic deliveries, and continuous delivery. And recognize that when change control is already strict yet requirements keep changing, the development approach itself should be reconsidered.

Lessons in this chapter

Chapter map

ItemKey pointsIn one sentence
PredictivePlan-driven, requirements up front, change through a process, value usually appears laterChoose it when requirements are stable, iterating is costly, or regulation is strict
AdaptiveVision first, backlog, frequent feedback; may use short iterations and timeboxes, or flow-based schedulingChoose it when requirements and technology are uncertain and early delivery is needed
Iteration / incrementCycles repeated to get it right / batches delivered for early valueAn adaptive approach can be iterative, incremental, or both; also ask whether the scope evolves with feedback
Predictive incrementsOverall scope is already clear, delivered in batchesAsk whether the scope is already clear
Stacey matrixTwo axes, requirements and technology, four zonesThe four zones show high versus low uncertainty (common exam practice): in the simple zone linear methods work; in the complicated zone, depending on the case, use predictive, iterative, incremental, or hybrid; the complex zone suits adaptive approaches; the actual choice must also consider deliverable, project, and organization factors
Selection factorsDeliverable, project, organizationFirst look at how clear the requirements are and how costly change is

Study tips and practice

  • In scenario questions, look first for two signals: are the requirements stable, and does feedback have value. Then look at regulation, the cost of change, and stakeholder involvement. Let the answer follow the conditions in the stem; do not pick “agile” just because the word appears.

Lesson 1

Predictive vs. Adaptive Approaches: Characteristics and When to Use Each

Lesson video

Lesson overview

A development approach answers the question “how will the project be managed and executed?” PMBOK 8 groups the commonly used approaches into three: predictive, adaptive, and hybrid, and notes they are often viewed as a spectrum. This lesson covers the two ends first: what characterizes predictive and adaptive approaches and which projects suit each. This is the most common type of scenario question on the exam: the stem describes a project and asks which approach to use. ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery) and Task 3 (Help ensure value-based delivery). The next lesson separates iteration, increment, and adaptive and uses the Stacey matrix to judge uncertainty; the hybrid approach comes in a later chapter.

Predictive approaches

A predictive approach may also be referred to as a waterfall, plan-driven, or traditional approach. It may be optimal when the project scope can be stabilized early in the project: the scope, schedule, cost, resource needs, quality requirements, and risks can be well defined in the early phases of the project life cycle and are expected to remain relatively stable. This development approach allows the project team to capture reliable certainty early in the project and to perform much of the planning up front. The schedule baseline, together with the cost baseline, is determined according to the scope that should be delivered. Taken together, the baselines for schedule, cost, and scope are referred to as the project’s integrated baseline.

Putting its characteristics together (the following four characteristics are common exam practice; PMBOK 8 stresses that scope can be stabilized early, that certainty can be captured early, and that planning is done up front): it is plan-driven, with relatively detailed requirements collected and much of the planning performed up front; requirements come first, because the plan rests on the assumption that the requirements are already clear; change goes through a process, so when a requirement changes you use the change control procedure to modify the plan instead of absorbing the change at any time; and value usually appears later, since usable results often cannot be shown until late in the project (a predictive approach can also deliver incrementally to realize value earlier). When feedback comes late, directional errors may be exposed late and the cost of correcting them later may be higher, and the response to market change is also slow. These are both its strengths and its price: strong certainty is bought with weak flexibility.

Predictive approaches suit three kinds of situations. First, projects whose requirements are clear and whose scope can be stabilized early. Second, projects or phases in which the cost of iterating far exceeds its value, such as the build phase of many construction projects: once the trench is dug you cannot “try it and fix it.” Third, large projects involving significant investment or regulatory oversight. These generally need robust change control mechanisms and planned reevaluation between successive phases; in a heavily regulated environment there may also be phase gates that let regulators assess whether the project is worth developing further.

Scenario: strengthening a middle school classroom building

The design institute has issued the complete strengthening drawings, the bill of quantities and contract price are fixed, and the completion acceptance criteria are written in the contract; almost nothing will change during construction. The project manager works predictively: first prepare the full schedule and cost budget and set the scope, schedule, and cost baselines; accept each work package against the drawings when it is completed; analyze and correct any deviation; and use the change control procedure when a baseline must be modified. There is no point in “trying things as you go” here, because strengthened beams and columns cannot be torn down and rebuilt again and again.

Adaptive approaches

Adaptive approaches are also referred to as change-driven or agile approaches. They are useful when a project’s requirements and technical solution are subject to a high level of uncertainty and volatility and are likely to change significantly throughout the project. A clear vision is established at the start of the project, and the initial known requirements are progressively elaborated, changed, or replaced in accordance with stakeholder feedback, the environment, or unexpected events. Adaptive approaches can be both iterative and incremental. Agility is a wide mindset that is broader than a development framework, and agile approaches can be considered adaptive.

A few keywords describe how they work. The first is the iteration: some agile methods entail iterations that are generally 1 to 4 weeks in duration, with a demonstration of the accomplishments at the end of each iteration, and the entire project team is heavily involved in planning at various levels. The second is the product backlog: in the iteration, the team members determine the scope they can achieve based on the prioritized requirements in the backlog, estimate the amount of work, and work collaboratively to develop the scope. The third is the timebox: its length is fixed, the budget is usually fixed too, and the team stays relatively stable, while the scope adjusts with feedback. The constraints therefore often show up as an “inverted triangle”: at the end of each timebox the implemented requirements are reviewed and planning for the next timebox begins. The fourth is flow-based scheduling, a project management approach that focuses on optimizing the flow of work through a system. One goal is to maximize the flow of deliverables; a related goal is to minimize time and resource waste. It is often adopted from flow-maximizing approaches such as the Kanban method and the theory of constraints.

Adaptive approaches are especially well suited to three kinds of projects. Design projects, where requirements are not fully defined up front and partial deliveries and changes are expected during the project. New product development projects, where the final features of the product are refined based on market needs, such as the development of a new mobile app or web service. And digital projects, where scope keeps changing, uncertainty is high, and early or incremental delivery is needed; software development is the typical case. Not all software projects must use an adaptive approach; what matters is the level of uncertainty and the need for early delivery.

Scenario: a volunteer recruitment platform

A nonprofit wants a mini-app for recruiting volunteers. The board has new ideas every month, and the volunteer representatives want to start using a minimal version that lets people sign up. The project manager adopts two-week iterations. Before each iteration the team picks the content for that round from the product backlog by priority; at the end it demonstrates the result to the volunteer representatives and reprioritizes the backlog based on their feedback. Incomplete requirements do not stop work from starting; they are filled in round by round through feedback.

How to decide: the two approaches compared

Comparison pointPredictiveAdaptive
Scope and requirementsDefined early, expected to be stableVision first, elaborated progressively
PlanningSubstantial up-front planning, controlled by baselinesRolling planning by iteration, backlog reprioritized
ChangeThrough the change control procedureAbsorbed between iterations
DeliveryMostly late, or in incrementsFrequent, small deliveries
StakeholdersInvolved as the plan and governance require; feedback is usually less frequent than in adaptiveUsually provide feedback more frequently and continuously
Best suited toStable requirements, costly iteration, strict regulationUncertain requirements and technology, early delivery, feedback needed

When reading a question, look for two signals: are the requirements stable, and does feedback have value. If the stem says “requirements have been confirmed in writing and will not change in the short term,” “the contract price and scope are fixed,” or “regulation requires a review at each milestone,” lean predictive; if it says “the customer keeps raising new requirements and wants to see results as soon as possible” or “only a rough direction was given,” lean adaptive. Remember that the answer must follow the conditions in the stem; do not choose agile just because you see it.

Worked examples

Example 1 Scenario: all requirements and design are completed before work starts

Question 1Example

A test engineer has just joined a logistics software company and finds that company policy requires all requirements to be collected and the system design reviewed before any code work starts. Which kind of delivery approach is this?

Show answer and explanation

Correct answer: D

Company policy requires all requirements to be collected and the system design reviewed before work starts. You must decide which development approach this delivery method belongs to.

A predictive approach may also be referred to as a waterfall, plan-driven, or traditional approach. Scope, schedule, cost, resource needs, quality requirements, and risks are well defined in the early phases of the life cycle and are expected to remain relatively stable, with much of the planning done up front. “All requirements and the design review must be finished before any code starts” is exactly requirements up front and plan-driven. The answer is D.

Why the other options are wrong

  • A. An adaptive approach establishes a vision first, and the initial known requirements are elaborated progressively through the backlog and feedback. It would not fix all requirements and design before any code is written.
  • B. In this kind of hybrid pattern the early part is adaptive exploration with fast trial and error. The stem describes an early part that needs complete, settled requirements and design.
  • C. Incremental delivery within a predictive approach also plans up front, but its hallmark is delivery in batches. The stem says nothing about batch delivery, so there is nothing to base that judgment on.

Key takeaway Completing all requirements and design before work starts is the hallmark of a predictive approach: plan-driven, requirements up front.

Variation If the stem added “the overall scope is clear, but delivery is in three batches,” the answer would become incremental delivery within a predictive approach. If it said instead “only a vision exists and requirements are elaborated round by round,” the answer would be adaptive.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: requirements keep emerging and results are needed quickly

Question 2Example

During execution of an omnichannel retail project, the customer’s representative keeps raising new requirements and repeatedly asks to see usable results as soon as possible. The project’s requirements were never fully settled, the project manager anticipated this before work began, and says the team will accommodate the requests as far as possible. Which development approach is the project manager MOST likely to use?

Show answer and explanation

Correct answer: B

The project is in execution; the customer’s representative keeps adding requirements and pressing to see usable results, and the requirements were never settled. You must judge which approach is most likely.

The Standard says that adaptive approaches are useful when a project’s requirements and technical solution are subject to a high level of uncertainty and volatility and are likely to change significantly throughout the project. The stem has two signals: the requirements were never settled and the project manager expected them to change before work began, and the customer keeps raising requirements and repeatedly asks to see results soon. An adaptive approach, through short iterations or flow-based working, keeps collecting feedback, adjusts the backlog, and delivers frequently, so it can both absorb the new requirements and show results early. The answer is B.

Why the other options are wrong

  • A. A predictive approach relies on fairly complete requirements up front. Changes can be handled through controlled change control, but it is inefficient when requirements keep emerging and results are needed quickly.
  • C. A hybrid approach suits projects in which some requirements are stable and others uncertain. The stem does not mention stable components that would need to be managed predictively on their own, and the information given points more directly to an adaptive approach as a whole.
  • D. A predictive approach with incremental delivery does deliver in batches, but the overall scope remains largely fixed, so it can hardly accept new requirements that keep appearing.

Key takeaway Requirements that keep changing, together with a need for frequent delivery, call for an adaptive approach.

Variation If the stem were changed to “the overall requirements are clear and only a basic version is required first,” the answer would become incremental delivery within a predictive approach. If it also said that part of the requirements were already fixed, you would have to consider a hybrid approach.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • An organization that is transforming to agile does not use agile on every project. A project with clear requirements and experience from similar projects should still choose a predictive approach.
  • However strict change control is, it cannot stop requirements from changing frequently. If requirements keep changing, consider adjusting the development approach rather than blocking the changes.
  • Adaptive does not mean “no planning.” It keeps the vision, the backlog, and a cadence; planning is simply elaborated on a rolling basis by iteration.
  • Adaptive approaches usually require more frequent, continuous stakeholder feedback: the more frequent the feedback, the more consistently the relevant people must stay involved.
  • A predictive approach can also deliver in batches; see the next lesson.

Key takeaways

Key point

  • Development approaches form a spectrum: predictive at one end, adaptive at the other, and hybrid mixing the strengths of both.
  • A predictive approach is also called waterfall, plan-driven, or traditional; its characteristics are plan-driven, requirements up front, change through a process, and value that usually appears later.
  • Predictive suits: scope that stabilizes early; iteration that costs more than it is worth; significant investment or strict regulation.
  • An adaptive approach is also called change-driven or agile; it is vision first, with a prioritized backlog, short iterations plus feedback, and often timeboxes and flow-based scheduling.
  • Adaptive suits: design projects, new product development, and digital projects with changing scope that need early or incremental delivery.

Lesson 2

Iteration vs. Increment vs. Adaptive, and the Stacey Matrix

Lesson video

Lesson overview

“Iteration,” “increment,” and “adaptive” appear in almost every exam, and in the answer options they often impersonate one another. This lesson first separates what problem each one solves. It then looks at a special case in PMBOK 8: a predictive project can also deliver in batches. Finally it introduces the Stacey matrix, which measures a project’s uncertainty on two axes, requirements and technology, and helps you position a method for scenario questions. ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery) and Task 3 (Help ensure value-based delivery). The previous lesson covered the characteristics of predictive and adaptive approaches; this lesson tells them apart precisely.

Iteration and increment

PMBOK 8 says adaptive approaches can be both iterative and incremental. “The iterative approach focuses on refining and improving the project through repeated cycles (iterations). The incremental approach delivers the final product in small, usable segments (increments), where the increments each provide value and build on one another until the complete product is delivered.”

Two small stories show the difference. A clothing maker is developing a new jacket, and nobody is sure the pattern fits. They make a sample and try it on, find the shoulder line too wide, revise the pattern and try again, and again, until the fit is right and only then go into production. Each version redoes the same target better; there is no rush to deliver, and what is pursued is getting the solution right. That is iteration. Another company is furnishing a newly opened guesthouse. The requirements have been clear for a long time, but the guesthouse must open before peak season: bedroom furniture arrives first, the living room a week later, then the dining room. Each batch builds on the previous one and guests can use part of the property earlier; what is pursued is early value and speed. That is increment.

If both problems exist at once, the solution is uncertain and must be adjusted as you try, and the customer is impatient and wants usable parts continuously, then the work is both iterative and incremental. This is the typical way of working in adaptive approaches (though not the only one): each iteration ends with a demonstrable, usable result, and the later backlog is adjusted according to feedback.

TypeRequirementsActivitiesDeliveryPursues
PredictiveDefined early, expected to be stableMainly executes the plan made up front, with controlled changeUsually a single delivery; may be incremental when the overall scope and timeline remain largely fixedCompleting as planned, managing cost
IterativeRequirements or solution uncertainRepeated cycles until the solution is rightMay still be delivered all at onceA correct solution
IncrementalKnown or dynamic, either is fineEach increment carries out the activities needed to complete its partDelivered in batches, frequentlyEarly value and speed
AdaptiveRequirements or the technical solution are uncertain and may changeMay cycle repeatedly, deliver in batches, or combine the twoDepends on the adaptive method used; commonly small, usable increments delivered oftenCustomer value and continuous feedback

Incremental delivery within a predictive approach

In certain predictive approaches, it may be optimal to deliver the product partially and incrementally, rather than as a single, final release. An incremental approach is used when the overall scope is well understood and planned up front, but phased delivery offers advantages due to the size, complexity, or specific risk factors of the project environment. The project is divided into different phases or increments, with each increment delivering a part of the overall product. Each increment builds upon the previous one, progressively adding features and functionality or completing parts of the product. The increments may be sequential or overlap. While stakeholder value is realized earlier through partial delivery, the overall scope and timeline remain largely fixed.

Figure 1 Sample predictive life cycle with incremental delivery, and an adaptive life cycle

How do you tell this apart from an adaptive approach? Look at the scope. In predictive incremental delivery the overall scope is already clear and is simply delivered in batches; in an adaptive approach the scope itself is still evolving. If the stem says “the overall requirements are clear, and we want to go live first with a usable version and deliver the rest in batches,” it is predictive incremental delivery; if it says “the requirements are hard to state and can only be added once results are seen,” it is adaptive.

The Stacey matrix

The Stacey matrix judges a project’s uncertainty on two axes: the vertical axis is requirements uncertainty and the horizontal axis is technology uncertainty, each running from low to high. The two axes divide projects into four zones. The Stacey matrix is a common exam term, and the four-zone description below is common exam practice. When it comes to actually choosing a method, rely on the requirements, technology, deliverable, project, and organization factors that PMBOK 8 discusses.

Figure 2 The Stacey matrix
  • Simple: requirements are clear and so is the technology. Linear methods (predictive) work well here.
  • Complicated: there is some uncertainty in requirements or technology, either one axis is high or both are moderate. Look at the specific uncertainty and choose, as the case requires, a predictive, iterative, incremental, or hybrid approach.
  • Complex: neither requirements nor technology is clear. Adaptive approaches are the best fit.
  • Chaotic: requirements and technology are both extremely uncertain; the project is fundamentally risky and is not suited to being driven forward with ordinary project management methods.

Scenario: one factory, two landing points

A distillery wants to add check-weighing software to a bottling line. The quality standard is a national standard, the equipment vendor has supplied the interface manual, and both requirements and technology are clear. This lands in the simple zone, so choose predictive: fix the scope and acceptance criteria up front, then build. The same distillery also wants a new system that predicts next month’s blending recipe from store sales. The business team cannot say what it wants, and no one has verified whether the algorithm can reach usable accuracy. Requirements and technology are both uncertain, which lands in the complex zone, so use an adaptive approach: build a minimum usable version, test it on real data, and iterate on the feedback.

Worked examples

Example 1 Scenario: overall requirements are clear and the team wants to go live with a basic version first

Question 1Example

A newly founded education company is building an online question-bank website. Resources are limited and the work relies mainly on internal staff. Management can accept a longer overall duration, the overall requirements are already clear, and a usable basic version only needs to go live first, with the remaining features allowed to be delivered in batches later. Which approach should the project use?

Show answer and explanation

Correct answer: C

The overall requirements for the online question bank are clear; management wants a usable basic version live first, with the remaining features delivered in batches, and can accept a longer overall duration. You must decide which approach to choose.

PMBOK 8 says that in certain predictive approaches it may be optimal to deliver the product partially and incrementally rather than as a single, final release. This is used when the overall scope is well understood and planned up front, but phased delivery offers advantages. The deciding conditions here are two: the overall requirements are clear, and a basic version goes live first with the rest delivered in batches. Together they describe incremental delivery within a predictive approach. The answer is C.

Why the other options are wrong

  • A. The requirements are clear, but management wants a usable basic version first, and a single delivery cannot satisfy the requirement to go live in batches.
  • B. Adaptive approaches address highly uncertain requirements. Here the overall requirements are already clear, so there is no need to re-prioritize repeatedly through iteration feedback.
  • D. The early part of this hybrid pattern is meant to explore uncertain requirements. Here the requirements are already clear, so there is nothing to explore.

Key takeaway When the scope is clear and you want a usable version out first, choose incremental delivery within a predictive approach.

Variation If the stem became “the features are hard to define and can only be added after seeing the live version,” the answer would be adaptive. If it became “the overall scope is clear and regulation requires a single acceptance,” choose predictive with a single delivery.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: both requirements and technology are uncertain

Question 2Example

A project manager receives a project to develop a sports social app. The product’s features must be determined step by step based on continuous user feedback, and there is no ready-made technical solution to refer to for how these features will be implemented. Which development approach should the project manager recommend?

Show answer and explanation

Correct answer: D

The features of a sports social app must be determined step by step from continuous user feedback, and no ready-made technical solution exists for implementing them. You must decide which approach to recommend.

Judge with the Stacey matrix (common exam practice): requirements uncertainty on the vertical axis is high and technology uncertainty on the horizontal axis is also high, so the project falls in the complex zone, where adaptive approaches fit best. The two signals map to the two axes: “features determined step by step from continuous user feedback” is requirements uncertainty, and “no ready-made technical solution” is technology uncertainty. An adaptive approach should therefore be used, determining the features and how to implement them gradually through iterations and feedback. The answer is D.

Why the other options are wrong

  • A. A predictive approach suits the simple zone, where both requirements and technology are clear. When both are uncertain, locking the plan up front only causes repeated rework.
  • B. The stem gives no condition requiring predictive components, phases, or governance mechanisms to be kept; both requirements and technical solution must become clear through feedback and exploration, so D matches more directly than B.
  • C. Incremental delivery within a predictive approach requires the overall scope to be well understood and planned up front. Here the features are determined gradually through feedback, so the premise is absent.

Key takeaway When both requirements and technology are uncertain (the complex zone of the Stacey matrix), choose an adaptive approach.

Variation If requirements were clear but the technology had some uncertainty, the project might fall in the complicated zone, and you would still choose iteration, increment, hybrid, or another suitable approach according to the degree of technical uncertainty. If both were clear, it is the simple zone and predictive applies.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Iteration solves the problem of an uncertain solution and increment solves the problem of delivering in batches. When both problems exist, the common approach is iteration plus increment, the typical adaptive way of working (an adaptive approach may also be only iterative or only incremental).
  • Predictive incremental delivery requires that the overall scope be well understood and planned up front. If the stem says only “we want to release part of it first” while the scope is still changing, it does not qualify.
  • When the customer is unwilling to wait until the end to see results, first assess the impact of switching to incremental delivery; do not abandon the whole plan outright.
  • Do not switch to predictive in the complex zone just because there is a fixed deadline. Keep using an adaptive approach and protect the deadline through timeboxes and prioritization.
  • The Stacey matrix looks at the requirements and technology axes, not at project value or volume of work. A project with a large volume of work can still land in the simple zone.

Key takeaways

Key point

  • Iteration: repeated cycles, pursuing a correct solution. Increment: delivery in batches, pursuing early value. An adaptive approach can be iterative, incremental, or a combination of both; iteration plus increment is common but not required by the definition.
  • A predictive approach can also deliver incrementally, provided the overall scope is well understood and planned up front and the overall scope and timeline remain largely fixed.
  • The two Stacey axes: requirements uncertainty and technology uncertainty.
  • The four zones: simple (linear methods work), complicated (some uncertainty in requirements or technology; use predictive, iterative, incremental, or hybrid as the case requires), complex (adaptive approaches are the best fit; the preceding is common exam practice), and chaotic (fundamentally risky).
  • To tell predictive increments from adaptive, check whether the overall scope is already clear.

Lesson 3

How to Choose a Development Approach, and Delivery Cadences

Lesson video

Lesson overview

The first two lessons covered what each approach is; this lesson covers how to choose. PMBOK 8 divides the factors that influence the choice into three categories, deliverables, the project, and the organization, and expects the necessary evaluations to be done before the approach is set. Once the approach is chosen, the delivery cadence must also be decided. This is the main battleground for scenario questions: the stem gives a pile of background and asks which approach to use, or what to do “first.” ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery) and Task 3 (Help ensure value-based delivery), and Business Environment domain, Task 7 (Support organizational change).

Who chooses, and what to consider

The choice of the development approach for a project is typically made by the project manager in consultation with the project management team, who, based on the nature of the project, carry out the necessary evaluations for establishing the framework and way of working with the team. The main factors are the requirements, scope, timeline, and goals of the project; the organization’s culture and needs; and the level of stakeholder involvement, risk profile, technological considerations, and overall complexity of the broader project context. “The diversity of factors often implies that several development approaches may be used within the same projects for different deliverables.”

Three categories of selection factors

Deliverable factors. Degree of innovation: when new or complex technological and/or business model innovation is needed, an adaptive approach may be optimal. Requirements certainty: when the requirements are well known and straightforward to define, a predictive approach may be optimal. Degree of scope stability: in general, the less stable the scope is, the more optimal it will be to apply an adaptive approach. Ease of change: if the nature of the deliverable makes it difficult or costly to manage and incorporate changes, a predictive approach may be optimal. Delivery options: whether the deliverables can be delivered in components or progressively elaborated. Risk: adaptive approaches may be helpful to manage risk and uncertainty. Safety requirements: products with rigorous safety requirements often use a predictive approach, as there is a need for significant up-front planning to ensure safety compliance. Feedback: if significant value is likely to be realized from frequent feedback from end users and stakeholders, an adaptive approach may be optimal. Regulations: environments with significant regulatory oversight may use a predictive approach due to the required processes, documentation, and demonstration needs.

Project factors. Stakeholders: projects that use adaptive methods typically call for significant stakeholder involvement throughout the process. Schedule constraints: if there is value to be realized from delivering something early, even if it is not a finished product, an iterative or adaptive approach may be optimal; when a fixed end date must be met, a predictive approach can help focus planning on delivery timelines. Financing uncertainty: projects executed in an environment of financing uncertainty may generate more value using an adaptive or iterative approach. Project size and complexity: more flexible approaches are more suitable for larger, complex projects with evolving requirements. Team experience and skills: adaptive or agile projects may benefit from teams with strong communication, collaboration, and problem-solving skills. Interdependencies: a reliance on other projects, departments, or functions for decisions, components, or resources may be a factor in delivering with an iterative approach.

Organization factors. Organizational structure: organizations with a fixed functional structure and more traditional hierarchical arrangements are more inclined to select a predictive approach due to preferred lines of authority; organizations with a network-oriented structure may be more naturally inclined to embrace adaptive or hybrid approaches. Culture: a predictive approach may be a better fit in an organization with a culture of managing and directing, where the work is planned out and progress is measured against baselines; adaptive approaches may fit better in a culture that more easily embraces uncertainty while emphasizing self-managed teams, flexible thinking, and innovation. Organizational capability: policies, ways of working, reporting structures, and attitudes should be aligned with the delivery method chosen. Project team size and location: adaptive approaches often work better with smaller project teams, and team location is relevant to all approaches, though some adaptive methods call for the colocation of team members.

How to choose in practice

The reading order below is common exam practice; PMBOK 8 Section 4.3 lists the factors that influence the choice. When you meet a scenario question about choosing an approach, you can work through it in this order. Step 1: look at requirements and scope. Are they clear and stable, or vague and changing? Are there components that can be delivered in batches? Step 2: look at the cost of change and at regulation. High cost of change and strict regulation often point toward predictive. Step 3: look at whether stakeholders can be heavily involved and whether the team has strong communication, collaboration and problem-solving skills; an adaptive approach typically calls for both. Step 4: look at whether the organization’s structure and culture support it. If after all four steps both directions still apply, you are usually looking at a hybrid scenario. Note that before the approach is set, you should first analyze project characteristics such as scope complexity and size and then choose the approach, rather than starting from which training the team has received.

Scenario: building a data center and its monitoring platform

A corporation is building a new data center and also needs a facility monitoring platform. The civil and electrical design drawings have been fully issued by the design institute, the cost of change is extremely high, and the codes are strict, so choose predictive. The monitoring platform will be used by operations staff, who are willing to attend a demonstration every two weeks; the feature list is still under discussion, and the team has only seven people with good experience, so choose adaptive. Using different approaches for the two deliverables within the same project is exactly what PMBOK 8 means when it says that the diversity of factors often implies that several development approaches may be used.

The suitability filter

The suitability filter is a useful decision-making tool, not a rigid method or procedure. It helps project teams evaluate their unique circumstances: it assists with analyzing the project’s characteristics and determining the best fit among predictive, adaptive, or hybrid approaches, and it combines its assessment with other data and decision-making activities. By evaluating criteria based on culture, project team dynamics, and project factors, it assists discussion and decision on the initial approach.

Delivery cadence

Based on the selected development approach, projects can have a single delivery, multiple deliveries, periodic deliveries, or continuous deliveries. A single delivery produces all outcomes at the end of the project; for example, a process-reengineering project may not have any deliveries until near the end, when the new process is rolled out. With multiple deliveries, a project may have multiple components or elaborations delivered at different times throughout the project; for example, a new drug may have deliveries such as preclinical submissions, the results of each clinical trial phase, registration and regulatory approval, and then launch, in sequence. Some deliveries are developed separately rather than sequentially, such as the physical barriers to entry, new badges, and new key code pads in a building security update. Periodic deliveries are commonly used in adaptive approaches; they are like multiple deliveries but on a regular and fixed delivery schedule such as monthly or semimonthly. Continuous delivery is the practice of incrementally delivering value to production on an ongoing basis. It focuses on delivering tested and validated product increments, ensuring they are production-ready at all times, and by leveraging automation teams can deploy frequently and efficiently.

Worked examples

Example 1 Scenario: change control is strict, yet requirements keep changing

Question 1Example

You take over a smart-home device development project that has been running for about six months under a predictive approach. The team is discussing the previously approved scope: even though the change control procedure is strict, requirements keep changing. What should you do?

Show answer and explanation

Correct answer: A

You take over a development project that has run for half a year. The change control procedure is strict, yet requirements still change continuously. What should you do?

Strict change control is a means of dealing with change. If it is already strict and requirements still keep changing, tightening the process alone will not solve the problem, and the current predictive approach may not match the project’s uncertainty: when a project with highly uncertain requirements uses an approach that depends on stable requirements up front, a large volume of change will usually result. You should consider adjusting the development approach, for example moving to an adaptive or hybrid approach, so the project can adapt to continuously changing requirements. The answer is A.

Why the other options are wrong

  • B. Change requests must still be evaluated through the Assess and Implement Changes process. Rejecting all of them is neither reasonable nor able to meet the reality of continuously changing requirements.
  • C. The stem already says change control is strict. Tightening it further only makes it harder for real requirements to get in and does not solve the fundamental mismatch between the approach and the requirements.
  • D. Accepting every change unconditionally would hit scope, cost, and schedule, and it does not conform to proper change management either.

Key takeaway However strict change control is, it cannot stop requirements from changing; what needs adjusting is the development approach, not blocking the changes.

Variation If the requirements were actually stable and only certain stakeholders kept asking for additions, the problem would be stakeholder management and you should hold to change control. Whether to adjust the approach depends on whether requirement change is the norm for the project.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: collaboration with business departments decides success or failure

Question 2Example

A project manager in the IT department of a retail chain is assigned a new project. The requirements are not yet fully clear, and the business departments must keep providing feedback and re-prioritizing; their collaboration is critical to success, but he is not sure which approach to use. The organization assigns a senior project manager to help him. What advice should the senior project manager give?

Show answer and explanation

Correct answer: D

Requirements are not yet clear, the business departments must provide continuous feedback, and their collaboration decides success. The project manager is unsure which approach to use. You must decide what advice the senior project manager should give.

Adaptive projects typically call for significant stakeholder involvement throughout the process and emphasize frequent communication, customer involvement, and fast feedback. The stem says the requirements are not fully clear, the business departments must keep giving feedback and adjusting priorities, and their collaboration is critical to success. So the project most needs collaboration and a feedback mechanism, which matches an adaptive approach best, and an adaptive approach should be recommended. “Collaboration matters” alone is not enough to choose an approach; combine it with whether the requirements are clear and whether they change frequently. If requirements were stable and rarely changed, a predictive approach would be preferred. The answer is D.

Why the other options are wrong

  • A. A template is only a standardizing tool. It does not answer “which approach promotes collaboration with the business departments.”
  • B. Inventing a new method from scratch is time-consuming and unnecessary; the established adaptive approaches already meet the need for collaboration.
  • C. Requiring the business departments to submit daily written progress reports is one-way reporting, not collaboration. It only adds to their burden and provokes resistance.

Key takeaway When collaboration and frequent feedback decide success and requirements are unclear, choose an adaptive approach.

Variation If the stem said “the business departments take part only when requirements are confirmed and are almost unreachable afterwards,” the premise of an adaptive approach would not hold, and you should consider a predictive or hybrid approach.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Before the approach is set, analyze the project’s characteristics first (clarity of requirements, complexity, frequency of change, stakeholder involvement, and so on) and then choose the approach. Do not start from which training the team has had or which approach you are used to.
  • To judge complexity, look at uncertainty, interdependencies, stakeholders, and technical difficulty, not at the format or quantity of documents.
  • When factors conflict, do not insist on choosing only one approach. Different deliverables can use different approaches; this is where the hybrid approach comes from.
  • A fixed deadline does not automatically mean predictive. If delivering part of the result early realizes value, an adaptive or iterative approach can still be used, managing the deadline through fixed timeboxes, value-based prioritization, release planning, and scope trade-offs.
  • Delivery cadence is a decision made after the approach is chosen. You must be able to tell single, multiple, periodic, and continuous apart.

Key takeaways

Key point

  • The factors for choosing an approach fall into three categories: deliverables, the project, and the organization. The approach is chosen by the project manager in consultation with the project management team, evaluating first and choosing afterward.
  • Clear and stable requirements, a high cost of change, strict regulation, and rigorous safety requirements lean predictive; innovation, unstable scope, high uncertainty, and the need for frequent feedback lean adaptive.
  • Adaptive approaches typically call for significant stakeholder involvement throughout and often work better with smaller teams.
  • The suitability filter is a tool that helps teams discuss the initial development approach; it is not a rigid method.
  • There are four delivery cadences: single, multiple, periodic, and continuous; periodic delivery is commonly used in adaptive approaches.

This chapter has 36 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.