PMP Cheat Sheet: Foundations and Value Delivery
The key points and common traps of 12 lessons in 3 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
Projects, Programs and Portfolios
Lesson 1: What Is a Project? Definition and Characteristics
- A project is a temporary initiative in a unique context undertaken to create value; the keywords are unique, temporary and value.
- Temporary means the project has a defined beginning and end. It applies to the project itself and does not depend on duration or on how long the deliverables are used.
- A project ends in one of five circumstances: objectives achieved, objectives cannot be met, resources exhausted, changes in strategy or environment, or termination for legal or compliance reasons.
- A unique context is why a project must be tailored, and repeated elements do not change uniqueness.
- The mission of a project is to move the organization from its current state to a future state, and its value is not limited to profit.
- “Temporary” applies to the project, not to the product. A product can last a long time, and the project is still temporary.
- “Temporary” does not mean “short”, and it does not mean “will certainly end on time”. A project can be terminated early because its objectives cannot be met, or it can run for many years.
- Repeated elements in the work do not affect a project’s uniqueness (common exam practice).
- A project’s value is not necessarily profit. Goodwill, brand, compliance and benefits to society and the environment are also value, so “a project must be profitable” is wrong.
- The end of a project is not the same as project success: a project also ends when its objectives cannot be met or its resources run out.
Lesson 2: Projects, Programs and Portfolios: How They Differ
- Portfolio: strategy, priorities, selection. Members need not be related to one another, and it can contain programs, projects and operations.
- Program: relatedness, dependencies, coordination, benefits. Its purpose is to obtain benefits not available from managing the projects individually.
- Project: unique, temporary, delivers value. It can stand alone or belong to a program or portfolio.
- The test: ranking and allocating limited resources is a portfolio; coordinating projects that constrain one another is a program.
- A program is not a big project, and portfolio members need not be related. These two points are the most common sources of lost marks.
- The components of a portfolio are not required to be related to one another, which is the opposite of a program. If the stem says “three projects launched for the same strategic goal are being prioritized”, that is portfolio management, not program management.
- The emphasis of program management is coordination and dependencies. Strategic selection across programs and projects, prioritization and resource allocation belong to portfolio management (PMBOK 8, Table 1-1), although program management can also sequence its components according to dependencies and resource constraints in order to realize program benefits.
- A program is not just “a very large project”. The test is whether the projects are interrelated and need coordinating together.
- A portfolio can contain operations; neither programs nor projects are the same as operations.
- What a project management office does depends on how the organization authorizes it. It may provide support, governance or cross-project coordination. Whether it manages dependencies among projects depends on its authority, and you cannot equate a PMO with a program manager on the basis of its title alone.
Lesson 3: Operations, Governance and Tailoring
- Operations are ongoing and repetitive and produce everyday products and services. Projects are temporary and drive change. Operations maintain ongoing, repetitive value delivery, and projects create unique results and drive change through temporary initiatives.
- Projects and operations intersect when new products are developed or upgraded, when operations are improved, at the end of the product life cycle, and at each closeout phase or iteration.
- Project results that operations must sustain or apply should usually be handed over to operations, and the operations team should be involved early in planning.
- Organizational governance gives direction and control. Project governance is the framework that guides projects and aligns them with strategy, and commonly uses a RACI matrix (responsible, accountable, consulted, informed).
- A project is unique, so it must be tailored. Governance draws the boundaries, and tailoring chooses the way of working.
- Ongoing operations are not projects, but project results that operations must sustain are usually handed over to operations. The two have intersection points, so you cannot say “projects and operations have no connection”.
- Operations are ongoing and repetitive; temporary is a characteristic of projects. Treating “continuous production” as a characteristic of a project is wrong.
- It is usually not advisable to wait until project closeout to involve operations. Engaging the operations team early in planning usually helps long-term success and sustainability.
- Governance draws boundaries for a project and tailoring chooses the way of working. They are not the same thing, and “everything uses agile” or “everything uses predictive” cannot replace tailoring.
- Organizational governance and project governance are two levels: the former covers the whole organization and the latter covers specific projects.
The System for Value Delivery
Lesson 1: Value, Business Value and the System for Value Delivery
- Value is the excess of financial and nonfinancial benefits over investment gained from achieving goals. Different stakeholders understand it differently.
- Business value includes tangible and intangible kinds, from monetary assets and market share to goodwill, compliance and reputation. Value is not the same as profit.
- A project is an investment, and its expected value should meet or exceed thresholds set in advance.
- The system for value delivery includes portfolios, programs, projects, products and operations. It sits inside the internal environment, which in turn sits within the external environment.
- The chain: deliverables → outcomes → benefits → value (outcomes may also create disbenefits). Delivering does not mean creating value.
- The components keep aligned with strategy by continually sharing information and feedback.
- Value is not profit. Tangible value and intangible value are both components of business value.
- Falling short on tangible value does not mean the project has no value, but you also must not lower the financial requirement to make the project “pass”.
- Acceptance of a deliverable only shows that the work was done to requirements, not that value has been realized.
- Outcomes can bring disbenefits, so the design of the system must take negative consequences into account.
- Financial measures (net present value, internal rate of return, return on investment and so on) are only tools for measuring tangible value. The calculations are covered in the finance topic.
Lesson 2: The Two Dimensions of Project Success
- Project success = outcome success (is the intended value realized?) + management success (are constraints such as cost, scope, time and quality adhered to, are resources used effectively, and are stakeholder expectations met; social and environmental sustainability goals are an example of strategic objectives under the outcome dimension).
- Outcome success is decisive for business value, and management success helps ensure efficient execution. Both must be assessed.
- The Sydney Opera House (outcome success, management not a success) and the demolished overpass (management success, outcome failure) are two classic counterexamples.
- Project success is the consensus view of intended beneficiaries, other stakeholders and project participants, so judge it from several perspectives. The test is whether the delivered value was worth the effort and expense, looking at quality, timeliness, budget compliance, sustainability and stakeholder satisfaction.
- To avoid differing understandings of the objectives, involve key stakeholders early in discussing them.
- “Finished on time, on budget and on scope” shows only that these constraints performed well. For the management process to be successful you also look at quality and more, and it certainly does not equal project success. If business value is low after delivery, the project as a whole is still not a success.
- Conversely, a project that overran its budget and schedule but whose outcome value is huge is not good in management but can be called a success in outcomes.
- Project success is decided by consensus among several parties. The project manager’s own good rating does not equal success.
- Value may appear long after the project ends. You cannot judge failure because “no benefit is visible right now”, nor success because “it has already been accepted”.
- Zero changes and zero risk events are not criteria of project success.
Lesson 3: Value-Driven Decisions: What to Do When Value Changes
- Value-driven decisions: focus on outcomes, not just deliverables, and evaluate value at the program and portfolio level and across the whole life cycle.
- The order when value changes: verify the impact → communicate and recommend → the role or team with the appropriate authority, under the governance structure and authority arrangements, decides to continue, adjust or terminate.
- Without authorization, the project manager does not terminate the project on his or her own, and does not change objectives or requirements on his or her own.
- Sunk cost is not a reason to continue; if misalignment with the business case cannot be corrected over time, termination may be the best option.
- Everyday practice: identify the elements of value with stakeholders, prioritize by value, deliver in batches and shorten the feedback cycle.
- Predictive projects check value through gates and regular reviews, and adaptive projects through value-ordered, incremental delivery. Neither skips the justification of the project’s reason, expected value and continuing justification, and either can use a business case or a similar document with the same function.
- When the project manager finds value falling, first verify and assess the impact, then report to the sponsor and recommend a reassessment. Do not decide to terminate the project or change the objectives on your own.
- Even when external conditions change, you should not refuse all changes because they “might cause rework”, and certainly not handle only the small requirements.
- Whether a change in value requires a change must be judged against the business documents, which are covered in the next chapter.
- “A lot has already been invested” is not a reason to continue, and adding people to go faster does not fix outdated requirements.
- Focusing on outcomes rather than deliverables: delivering without checking value is the mistake that recurs throughout this lesson.
Lesson 4: Benefits Tracking and Handover After the Project
- Benefits often appear after the project, so benefits tracking cannot be done only during the project.
- The benefits management plan sets how and when benefits are delivered and the mechanisms to measure them. The benefits owner monitors, records and reports benefits throughout the timeframe.
- At closure: assess the gap, record it, confirm the owner and metrics, and hand the tracking responsibility to the benefits owner designated in the benefits management plan. The project is not postponed indefinitely because benefits have not appeared.
- The benefits owner is designated by the plan. “Usually on the business side” is common exam practice.
- Also handed over are operating training and the knowledge operations needs, and the operations team should be involved early.
- Passing acceptance does not mean benefits have been realized.
- Benefits not realized at closure should not be made to “hit target” by changing the objectives, and closure should not be postponed indefinitely.
- The benefits owner is usually on the business side (common exam practice). Do not assume it is the project team or the change control board by title alone (also common exam practice). The designated benefits owner in the benefits management plan governs.
- The benefits management plan has been developed iteratively since early in the life cycle. The project manager at closure can only recommend and cannot rewrite it alone, which is common exam practice. PMBOK 8 says that the project manager works with the sponsor to ensure that the project charter, project management plan and benefits management plan remain in alignment throughout the life cycle.
- Recording benefits data only in the lessons learned register does not complete the handover.
Business Case and Benefits Management Plan
Lesson 1: Business Case: Is the Project Worth Doing?
- The business case is a documented economic feasibility study, prepared before approval, and the basis for approving the investment and authorizing later project management activities.
- It usually contains an analysis of business need and a cost-benefit analysis (common exam practice); three elements: business need, economic feasibility and technical feasibility.
- The measures of success are written in before the start, and success or failure is judged against them at the end.
- Keep it apart from the project charter, the cost-benefit analysis, the project management plan and the scope baseline.
- Before approval, when an executive proposes a new idea, when someone challenges the project, or when you take over a project in progress, go to the business case first.
- An approved business case shows the project has a basis for approval. The project still has to be formally launched through a project charter or similar authorization before it moves into planning, and approval does not mean the project will succeed.
- The business case answers "is it worth doing?" It does not lay out how work is arranged; that belongs to the project management plan, and the activity list and who is responsible are even less a part of the business case.
- Use the business case to judge whether the investment is worthwhile before approval, and do not confuse it with the benefits management plan, which tracks benefits through to the end.
- The business case usually includes a cost-benefit analysis (common exam practice), but the analysis cannot replace the whole business case.
- When a new idea appears, prepare the business case first, then talk about collecting requirements, assigning resources or a SWOT analysis.
Lesson 2: Benefits Management Plan: Writing Benefits Down and Tracking Them to the End
- The benefits management plan describes how and when benefits will be delivered and establishes the mechanisms to measure them; the business case covers "is it worth doing?", while the benefits management plan covers how and when benefits are realized and how they are measured.
- Seven elements: target benefits, strategic alignment, timeframe for realizing benefits, benefits owner, metrics, assumptions, risks.
- The plan begins early in the life cycle as the target benefits are defined, is maintained iteratively, and stays aligned with the business case, the project charter and the project management plan.
- Metrics must be measurable and state the target or criterion and data source, with a comparison baseline where relative improvement is being measured; the owner must be clear, and external dependencies go into assumptions and risks.
- When someone challenges the value, the descriptions of benefits do not agree, or nobody can say what the benefit is, go back to the benefits management plan first.
- If benefits have begun to be realized, or governance and communication requirements call for it, the status report should include tracking results for benefits metrics as well as schedule and cost.
- The measures of benefits should be agreed with stakeholders and approved at the start; if they are set only at the end, there is no baseline to compare with.
- When a benefit depends on outside conditions, manage it as an assumption and a risk; do not assume it will hold.
- Registers and logs are project documents, not part of the benefits management plan.
- On time and on budget is usually not enough in itself to prove value has been delivered; judge on the business case, the benefits management plan and the agreed quantitative or qualitative success criteria together (if satisfaction is defined as a target benefit, its measurement can also serve as evidence of value).
- The benefits management plan measures the benefits themselves, not the deliverables.
Lesson 3: Business Documents: Nature, Maintenance and Ownership
- The business case and the benefits management plan are business documents, developed before initiation; they are not project documents or components of the project management plan.
- Business documents can be inputs to processes such as Initiate Project or Phase and are used after completion to judge success or failure; they need periodic review.
- The sponsor usually develops and maintains the business case; the project manager mainly provides advice and insight so the success criteria in the four documents match.
- On finding gaps: explain the situation and offer suggestions. On taking over a project in progress: check your understanding with the sponsor and the author first.
- Sensitive matters such as benefit ownership are written before the start into a jointly approved business case, with the benefits owner and metrics recorded in the benefits management plan, and the two stay consistent.
- When you find the business case has gaps or outdated information, verify the inconsistencies first and give the sponsor suggestions; do not change it yourself and do not ignore it.
- When taking over a project already under way, check your understanding of the business case with the sponsor and the author first, clear up misunderstandings, and then move on.
- Benefit ownership must be confirmed by all parties before the start and recorded in a business case both sides accept, and the benefits owner and metrics are written into the benefits management plan; remedying it afterward is too late.
- Business documents are not project documents and are not components of the project management plan.
- Review the business documents periodically during the project; do not wait until acceptance to find that the objectives have drifted from the business need.
Lesson 4: Business Documents in Scenario Questions
- Challenge to the project: listen, then go back to the business case (supported by the objectives and rationale in the project charter where needed) to explain; if stakeholders disagree, review the business case together.
- A new idea from the sponsor, or benefits wanted early: first review the business case and the benefits management plan, analyze value and cost and advise the sponsor; the sponsor maintains the business case as governance arranges, and a change decision follows where needed.
- External change shakes the value: first assess the effect on value, scope and the business case, then inform the sponsor, review the business case again, and once the organization is confirmed to still support it, update the requirements through the change process.
- Doubt about strategic alignment: first clarify with the sponsor, and together recommend adjusting the benefits or the plan.
- Predictive, adaptive and hybrid approaches all depend on the business case and the benefits management plan; check the benefits realized at the points, gates or milestones the plan specifies.
- When business parameters change, the project manager should not decide alone to terminate or continue. Report to the sponsor, review the business case again, and after confirmation update the requirements through the change process.
- When an external change appears, do not refuse it for fear of rework, and do not first draw on the management reserve or change the procurement channel directly.
- When a key stakeholder does not accept the benefit estimates, meet as soon as possible, communicate and agree on corrective action; do not avoid it.
- Deviations in value must be caught early by monitoring throughout, not discovered at closure.
- When someone challenges the approval of the project, what you produce is the business case, not the cost baseline, and not just the cost-benefit analysis alone.
- When benefits and strategy are not aligned, recommend adjusting the benefits or the project plan; do not change the business documents yourself.
Lesson 5: Project Selection and Prioritization: What the Decision Rests On
- The basis for prioritizing is in the business documents: strategic alignment, target benefits and metrics, and cost-benefit.
- Choose projects by contribution to the organization's business value; a leader's preference, ease and a stakeholder's demand are not the core basis.
- When the strategy changes, first work out how the project relates to the new strategy, then recommend adjusting the benefits or the plan; for questions about the project's purpose and strategy, go back to the benefits management plan.
- Agile prioritization considers value, dependencies, technical or operational risks, and stakeholder feedback; cost or effort may inform economic sequencing. Common exam practice: priority rises with value and risk and falls with cost, used as a guide rather than an exact formula.
- Financial measures: ROI, payback period, NPV, IRR, benefit-cost ratio; when selecting projects, look at net present value first (common exam practice; the candidates must be comparable).
- Choose projects by maximizing business value, not by a leader's preference, ease or duration, and not on risk or revenue alone.
- Agile prioritization considers technical or operational risk; high-risk work may be brought forward when early validation reduces later loss, but “the higher the risk, the earlier” is not a fixed rule.
- When strategy and benefits do not match, the project manager recommends alignment; the project manager does not change the business case directly.
- The scope management plan, the project management plan and the communications management plan do not answer "why is the project being done and does it fit the strategy?"; the business documents do.
- When several financial measures contradict one another, look at net present value first (common exam practice; the candidate projects must be comparable).