Foundations and Value Delivery

Projects, Programs and Portfolios

PMP · Foundations and Value Delivery · 3 lessons · about 34 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

This chapter draws the boundary of what a project is and shows where a project sits in the organization. It answers three questions in turn. What is a project, and which kinds of work count as one? How do a project, a program and a portfolio differ, and which level of management is a given exam question really about? How do you tell projects from day-to-day operations and hand work over between them, and what boundaries do governance and tailoring set for a project? Every later topic is about managing a project well, and this chapter is their shared starting point.

The way this chapter is tested is stable. Most questions ask you to distinguish among closely related concepts. The scenario questions cluster around two issues: whether prioritizing belongs to the portfolio or to the program, and whether ongoing work is a project.

Lessons in this chapter

By the end of this chapter

You should be able to look at a piece of work and decide whether it is a project using three questions: does it have a defined beginning and end, is its context unique, and does it create value? Given a question about a management activity, you should be able to use the “select versus coordinate” test to decide whether it belongs to the portfolio, the program or the project. You should know where operations and projects intersect and why operations teams should be engaged early in project planning, so that project results are handed over smoothly and become part of operations. You should be able to explain how governance and tailoring relate, and not treat “use one method for everything” as a good approach. Study the three lessons in order, then do the chapter practice, and go back to the Common traps section of the relevant lesson for any questions you miss.

Chapter map

Project: unique context + temporary + creates value (moves the organization from its current state to a future state)

  • Above: portfolio (strategy, priorities, selection) / program (relatedness, dependencies, coordination)
  • Alongside: operations (ongoing) — four intersection points: new products or upgrades, operational improvement, end of the life cycle, closeout or iteration
  • Around: organizational governance → project governance (RACI, governance board) → tailoring (projects are unique, so tailor)

The chapter practice is the next step; start with the core questions, then the required ones. The next chapter covers the reason a project exists: value.

Lesson 1

What Is a Project? Definition and Characteristics

Lesson video

Lesson overview

Every later topic is about how to manage a project well. This lesson first draws the boundary of the word “project”: what kind of work counts as one, and what does not. PMBOK 8 defines a project as a temporary initiative in a unique context undertaken to create value, and almost every concept question on the exam turns on three of its keywords: temporary, unique context and creating value. This lesson is the starting point for the ECO task “Help ensure value-based delivery” (ECO: Process domain, Task 3) and is the prerequisite for the next lesson, which separates projects, programs and portfolios.

The definition: three keywords

PMBOK 8 defines a project as “a temporary initiative in a unique context undertaken to create value.” Developing a new drug, designing a new car model, constructing a building and merging two companies are all projects. The definition puts the weight on value. Projects are initiated to create value by producing tangible and/or intangible deliverables such as products, services, or other results, for the organization and its stakeholders.

Progressive elaboration still applies: many details are unclear at the start and are refined as the work proceeds. It is simply not part of the definition. The definition asks, first of all, for whom the project creates what value. So whenever a project starts, go back to the most basic reason for it: if this succeeds, who is better off because of it?

Each keyword carries one kind of judgment. Temporary answers “is there a defined beginning and end?” Unique context answers “is this the same as earlier work or not?” Creating value answers “what is it for?” Only when all three hold is it a project.

Temporary and unique context

Temporary means that the project has a defined beginning and end. Note that it applies to the project itself, not to what the project produces. After the project ends, the deliverables often persist: a recorded course can be watched by learners for ten years, but the work of recording the course still ends on the day recording is finished. “Temporary” does not mean short, either. A construction project that takes many years is still temporary as long as it has a start and an end.

Usually, a project ends when one or more of the following conditions are met:

  • The project’s objectives have been achieved;
  • A governing body, the project sponsor, or the project team has determined that the objectives will not or cannot be met;
  • Resources (funding, human, or physical) are exhausted or no longer available;
  • Due to changes in strategy, priorities, or the external environment, the need for the project no longer exists; or
  • The project is terminated for other reasons such as legal, regulatory, or compliance issues.

This list has an implication that is easy to miss: a project can end early because it “cannot be done” or is “no longer needed”, and ending is not the same as succeeding. When an exam question asks which of the following is NOT sufficient reason for a project to end, look for the statement that matches none of the five conditions above, such as “some team members feel a bit tired”.

Unique context “refers to the specific conditions and environments that distinguish one project from another, even if they have otherwise similar characteristics.” Even if two projects aim for the same value or objectives, each differs due to differences in goals, scope, duration, location, technology, quality, costs, risks, resources and stakeholders. A large housing development is the classic example: the construction vendor may be the same, but each housing unit may involve different lenders and buyers, distinct customization requests and unique grading requirements from one plot to another. The direct consequence of a unique context is that every project needs a management approach tailored to its own needs and challenges.

Repeated elements within a deliverable or an activity do not change the fundamentally unique nature of project work (common exam practice). The same people building two houses from the same materials can still be doing project work, because the location, design, environment and participants differ. Whether to run it as one project or two depends on its objectives, scope and governance boundaries. Do not be misled by “repeated elements”; ask whether the whole context is unique.

Creating value and driving change

From a business perspective, a project’s purpose is to move an organization from one state to another to achieve a specific objective. Before the project begins, the organization is in its current state, and the desired result of the change is the future state. For some projects, the shift may involve a transition state in which several steps are taken in a structured manner. The successful completion of a project results in the organization moving to the future state and achieving value, as defined by key stakeholders (the value does not necessarily appear the moment the project is completed). That value need not be profit. Goodwill, brand, compliance and benefits to society and the environment are all value, so it is wrong to say that a project must be profitable. Value and business value are covered in detail in the first lesson of the next chapter.

How to tell whether something is a project

For a concept question, ask three questions in the following order. It is much faster than going by impression (common exam practice).

  1. Does it have a defined beginning and end? Work that continues forever on a fixed schedule is operations, not a project.
  2. Is its context unique? If the needs, location, technology and stakeholders differ each time, it is unique. Identical repetition in volume is not.
  3. Is it meant to move the organization from where it is to some future state and to create value?

Example: five pieces of work, which are projects?

  • A community canteen serves lunch every day from a fixed menu: operations. It is repetitive and has no end.
  • The canteen decides to build a central kitchen, to be completed and in use within six months: a project. It has an end, the context is unique, and its purpose is to move the canteen from scattered preparation to centralized delivery.
  • A factory that makes custom automation equipment receives a new order, and the customer’s requirements differ every time, so the solution must be redesigned: this order is a project, because the context is unique and there is a delivery date.
  • The same factory produces one model in batches every month from fixed drawings: operations.
  • Three friends take a weekend road trip: generally not managed as a project, but if the trip is treated as a temporary initiative with a clear start and end, a unique context and an intended value, it can also fit the project definition. Whether formal project management methods are needed is a separate matter.

So the boundary between projects and operations is not absolute. It depends on the nature of the specific work, not on the industry or the company name.

Worked examples

Example 1 Temporary applies to the project, not the product

Question 1Example

PMLyceum assigns Priya to lead a project to produce a micro-course called “Key Topics Review”. Production will take about two months, and after completion learners will use the course repeatedly over a long period. Which statement about the temporary nature of this project is correct?

Show answer and explanation

Correct answer: B

A micro-course production project is expected to finish in two months, after which learners will keep using the course for a long time. The question is whether the long-lived deliverable changes the temporary nature of the production project.

Temporary means the project itself has a defined beginning and end. It applies to the project, not to what the project produces. The stem gives two signals: production takes about two months, so the project has an end; and the course stays in use, which describes the life of the deliverable. These are two separate things. A deliverable can outlive the project, and the project is still temporary. Option B keeps them separate, so the answer is B.

Why the other options are wrong

  • A. This confuses how long the deliverable is used with how long the project exists. The course being used for years only shows that the result keeps delivering value after the project ends. The production work ends once the recording is finished, so the project is still temporary.
  • C. Temporary does not mean short. A construction project that takes many years is still temporary as long as it has a beginning and an end. A short duration here is a coincidence, not the test.
  • D. Temporary applies to the project, not to the product. Whether the course is replaced by a newer version later has nothing to do with whether the production project has an end. This reason looks at the wrong object.

Key takeaway Temporary means the project has a defined beginning and end. It does not depend on how long the project lasts or on how long the deliverable stays in use.

Variation If the stem said instead that the project objectives cannot be met and the sponsor decides to terminate it, the project still ends. Determining that the objectives cannot be met is one of the conditions that can end a project, and ending is not the same as succeeding.

Something wrong with this question?

Report an issue with this question

Example 2 Moving the organization from its current state to a future state

Question 2Example

A logistics company is changing the sorting process in its warehouses nationwide from manual to automated and has set up a dedicated working group for the effort, which has been defined as a project. Which of the following BEST reflects a characteristic of a project?

Show answer and explanation

Correct answer: D

A logistics company is changing the sorting process in its warehouses nationwide from manual to automated and has formed a dedicated working group, and the effort has been defined as a project. You must pick the option that best reflects a characteristic of a project.

The purpose of a project is to move an organization from its current state to a future state to achieve a specific objective. Changing warehouse sorting from manual to automated is exactly such a change, which fits the PMBOK 8 description of a project as creating value and driving change. The other three options describe operations or a narrow view of value. Test it another way: if this work were simply repeated every month with no end, it would be operations. Here there is a clear beginning, the goal is to replace the whole process with a new way of working, and the end point is full rollout of the new process. The answer is D.

Why the other options are wrong

  • A. Continuously reproducing identical outputs in volume through a fixed process characterizes operations. A project can still include repeated activities or multiple similar outputs while existing in a unique context.
  • B. The value of a project is not necessarily monetary profit. Goodwill, brand, compliance, and benefits to society and the environment are also value, so “must be profitable” is too absolute.
  • C. Routine work carried out continuously over the long term is operations. A project is a temporary initiative with a defined beginning and end.

Key takeaway The essence of a project is driving change: moving the organization from its current state to a future state. Its value is not limited to profit, and it is not routine repeated work.

Variation If an option read “run the sorting line on a fixed shift schedule”, that would be operations, not a project. “Rebuild the sorting line once and hand it over for use” would be a project.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • “Temporary” applies to the project, not to the product. A product can last a long time, and the project is still temporary.
  • “Temporary” does not mean “short”, and it does not mean “will certainly end on time”. A project can be terminated early because its objectives cannot be met, or it can run for many years.
  • Repeated elements in the work do not affect a project’s uniqueness (common exam practice).
  • A project’s value is not necessarily profit. Goodwill, brand, compliance and benefits to society and the environment are also value, so “a project must be profitable” is wrong.
  • The end of a project is not the same as project success: a project also ends when its objectives cannot be met or its resources run out.

Key takeaways

  1. A project is a temporary initiative in a unique context undertaken to create value; the keywords are unique, temporary and value.
  2. Temporary means the project has a defined beginning and end. It applies to the project itself and does not depend on duration or on how long the deliverables are used.
  3. A project ends in one of five circumstances: objectives achieved, objectives cannot be met, resources exhausted, changes in strategy or environment, or termination for legal or compliance reasons.
  4. A unique context is why a project must be tailored, and repeated elements do not change uniqueness.
  5. The mission of a project is to move the organization from its current state to a future state, and its value is not limited to profit.

Lesson 2

Projects, Programs and Portfolios: How They Differ

Lesson video

Lesson overview

The previous lesson covered what a project is. Most organizations run more than one project, so two higher-level “containers” come in: programs and portfolios. A high-frequency exam question describes a management activity and asks whether it is project, program or portfolio management. This lesson gives you a quick way to decide: is the stem about choosing which projects to do, about coordinating several projects that constrain one another, or about managing a single project well? The next lesson covers how projects relate to day-to-day operations.

The three concepts

A program is “a group of related projects and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.” These interrelated activities may include subsidiary programs. The keywords are relatedness and dependencies. A program is not merely a large project: programs drive significant organizational change by connecting resources and aligning projects strategically to create synergies.

A portfolio is “a collection of programs, projects, and operations managed as a group to maximize overall value delivery and achieve strategic objectives, meet mandatory obligations, or generate income streams.” It may include subportfolios. The components of a portfolio are not necessarily interdependent or related. The keywords are strategy and priorities. Portfolio management involves selecting, prioritizing, managing, and optimizing an organization’s programs and projects in line with its strategic goals, obligations (legal or otherwise), or business objectives, so that resources go to the parts that best serve the strategy.

A project is the thing covered in the previous lesson: a temporary initiative in a unique context undertaken to create value. It can be a stand-alone effort or part of a portfolio or program.

Side-by-side comparison

The table below follows the comparison in the PMBOK 8 standard. Focus on the keywords in each row.

ComparisonPortfoliosProgramsProjects
DefinitionA collection of programs, projects, and operations managed as a group to maximize overall value delivery and achieve strategic objectives, meet mandatory obligations, or generate income streamsA group of related projects and program activities managed in a coordinated manner to obtain benefits not available from managing them individuallyA temporary initiative in a unique context undertaken to create value
ScopeOrganizational scope aligned with strategic objectivesIncludes and integrates the scope of its component projects and subprogramsDefined objectives, progressively elaborated
ChangeAdaptable to continuous monitoring and adjustment to align with strategic priorities and changes in the environmentAdaptable to optimize value delivery at the program levelAdaptable to enable and maximize value delivery
PlanningStrategic planning, priority definition, and resource allocation between programs and projectsHigh-level planning that tracks interdependencies and aligns with program objectivesPredictive, adaptive, or hybrid, depending on project requirements and organizational context
MonitoringMonitors strategic changes and resource allocationMonitors progress of component projects and benefits realizationMonitoring and controlling outputs and value
SuccessMeasured by strategic value delivery, overall change management success, and alignment with organizational vision and missionMeasured by the program’s ability to collectively deliver benefits and value and achieve strategic objectivesMeasured by delivered value that was worth the effort and expense, including quality, timeliness, budget compliance, sustainability, and stakeholder satisfaction

How to decide: selecting or coordinating

Portfolio, programs and projects under organizational strategy (hotel group example)

The figure uses a hotel group as the example. At the group level, deciding which hotels to invest in and whether to keep an operating unit is a question of selection, and it belongs to the portfolio. Renovating a single hotel involves several interdependent projects, such as low-voltage systems, fire safety, fit-out and IT systems, whose schedules and resources must be coordinated together. That is a question of how to manage, and it belongs to the program. Inside the IT systems project, work proceeds by phase, and that is the project’s own management.

You can sum this up in two sentences. A portfolio stresses “choosing the right projects”, and its core is priorities and resource allocation. A program stresses “coordinating related projects in the right way”, and its core is cross-project relatedness, dependencies and overall benefits. A project is managed around its own defined objectives and value delivery. When you read a scenario question, find the verb in the stem first (common exam practice). “Rank, trade off, decide which to do first and which to pause with limited resources” points to a portfolio. “Several projects constrain one another, interfaces conflict, and schedules and resources need unified arrangement” points to a program. A single team doing temporary work with a defined start and end toward a unique objective is a project (ongoing, repetitive work may still be operations).

Examples of judging

  • A group’s board must choose three of five transformation proposals to fund and set the order: portfolio management.
  • A supermarket chain runs a new checkout system, store renovations and staff training at once, all of which must switch over in the same week and whose schedules constrain one another: program management.
  • One team independently builds an internal expense-claim app: project management.
  • A company short of funds and staff has to pause one of three business directions. This is a portfolio-level decision. It is usually driven by analysis from the portfolio manager and approved by the appropriate decision maker under the organization’s governance authority. It is not something an individual project manager or program manager can decide alone.

Everyday life offers an analogy. Renovating, moving and settling in are three things with a sequence of dependencies and one shared goal: living in the new home. If they are only activities within one project, they remain one project. Only when related projects or program activities are coordinated to obtain benefits not available from managing them individually can this be loosely compared to a program. Allocating a family’s whole year of spending and energy, deciding who gets money first and which matter waits, is like a portfolio. An analogy only helps memory; on the exam the PMBOK 8 definitions and keywords still govern.

What a portfolio contains

A portfolio holds more than projects: it holds programs and operations too. This is often overlooked. Operations can be members of a portfolio, because a portfolio manages overall value. Conversely, neither programs nor projects are the same as operations. The members of a portfolio are not required to depend on one another; as long as they all serve strategic objectives, or there is a mandatory obligation (for example compliance) to meet, they can be managed in one portfolio.

Worked examples

Example 1 Ranking several projects: portfolio management

Question 1Example

PMLyceum has four new-product development projects ready to start. They serve the same growth strategy but have no dependencies on one another. Management is comparing the strategic value of each project and deciding the order in which to invest. Which of the following activities is this?

Show answer and explanation

Correct answer: D

Four new-product development projects serve the same growth strategy and have no dependencies. Management compares their strategic value and decides the order of investment. You must identify what type of activity this is.

The key actions in the stem are comparing strategic value and deciding the order of investment. That is selecting and prioritizing among several projects, which is portfolio management. The components of a portfolio need not depend on one another; they are managed together to maximize overall value, achieve strategic objectives, meet mandatory obligations, or generate income streams. The stem says there are no dependencies, and management is only comparing value and ranking, with no action to coordinate interdependencies, so this is not program management. Two cross-checks help. First, the action: comparing value and setting an order is selecting. Second, the object: several projects that have not yet started are portfolio components, not one project already chartered. The answer is D.

Why the other options are wrong

  • A. Program management manages a group of related projects and program activities in a coordinated way to obtain benefits not available from managing them individually, and its emphasis is coordination. The stem says only that the projects serve the same strategy and have no dependencies. Management is comparing value and ranking, and nothing is being coordinated across interdependencies.
  • B. Operations management concerns the ongoing production of products and services. It has nothing to do with this batch of new-product development projects that have not yet started.
  • C. Project initiation is the work of authorizing one project and issuing its charter. The stem discusses trade-offs among several projects, not initiating one.

Key takeaway Comparing value, setting priorities and allocating resources across several projects is portfolio management, not program management.

Variation If the four projects had interdependent interfaces and their schedules needed to be coordinated together, the answer would become program management. Look at the verb: ranking and trade-offs point to a portfolio, coordinating dependencies points to a program.

Something wrong with this question?

Report an issue with this question

Example 2 Projects that constrain one another: the program manager coordinates

Question 2Example

The e-commerce department of a retailer is running three interlocked projects at once: an inventory system, an order system and a logistics integration. Last month the inventory team complained that the order system team was delivering its interface too slowly, which delayed its own work, and a similar conflict arose between the order system team and the logistics integration team. Several project managers have met repeatedly to coordinate, without result. Which role is BEST suited to resolve this kind of problem?

Show answer and explanation

Correct answer: C

The e-commerce department runs inventory, order and logistics integration projects whose interface deliveries constrain one another, and several project managers have met repeatedly without result. You must decide which role is best suited to resolve the problem.

The schedules and interfaces of the three projects affect one another, so they are interrelated and need to be managed together in a coordinated way. That is the scope of program management. A program manager’s job is to coordinate the dependencies among component projects and make each project serve the overall program objectives. You can also test this the other way: if the problem were an interface issue inside a single project, that project manager could coordinate it alone. Once several projects constrain one another and one manager cannot get movement, the next level up, program management, has to bring it together. The root of the conflict is that no one is coordinating the dependencies, so the answer is C.

Why the other options are wrong

  • A. A portfolio manager focuses on strategic alignment, prioritization and resource allocation. A portfolio manager is not responsible for resolving dependency conflicts among specific projects.
  • B. A project management office’s responsibilities depend on organizational authority. The stem does not say that this PMO is authorized to manage the interproject dependencies, while coordinating dependencies among component projects is explicitly the program manager’s role, so the program manager is more suitable.
  • D. A sponsor is usually concerned with, and accountable for, the objectives and resources of a particular project. A sponsor is not a role dedicated to coordinating dependencies across several projects and would find it hard to bring the three together.

Key takeaway When projects affect one another and their dependencies need coordinating, that is program management, so turn to the program manager.

Variation If the three projects did not affect one another and management only had to decide which to do first because the budget is limited, you would turn to the portfolio manager or management. That is portfolio management.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The components of a portfolio are not required to be related to one another, which is the opposite of a program. If the stem says “three projects launched for the same strategic goal are being prioritized”, that is portfolio management, not program management.
  • The emphasis of program management is coordination and dependencies. Strategic selection across programs and projects, prioritization and resource allocation belong to portfolio management (PMBOK 8, Table 1-1), although program management can also sequence its components according to dependencies and resource constraints in order to realize program benefits.
  • A program is not just “a very large project”. The test is whether the projects are interrelated and need coordinating together.
  • A portfolio can contain operations; neither programs nor projects are the same as operations.
  • What a project management office does depends on how the organization authorizes it. It may provide support, governance or cross-project coordination. Whether it manages dependencies among projects depends on its authority, and you cannot equate a PMO with a program manager on the basis of its title alone.

Key takeaways

  1. Portfolio: strategy, priorities, selection. Members need not be related to one another, and it can contain programs, projects and operations.
  2. Program: relatedness, dependencies, coordination, benefits. Its purpose is to obtain benefits not available from managing the projects individually.
  3. Project: unique, temporary, delivers value. It can stand alone or belong to a program or portfolio.
  4. The test: ranking and allocating limited resources is a portfolio; coordinating projects that constrain one another is a program.
  5. A program is not a big project, and portfolio members need not be related. These two points are the most common sources of lost marks.

Lesson 3

Operations, Governance and Tailoring

Lesson video

Lesson overview

A project does not exist in isolation. At one end it connects to day-to-day operations: project results that operations must sustain or apply are usually handed to operations at determined points. At the other end it connects to governance: the organization uses governance to draw the boundaries, and the project chooses its way of working within them. This lesson first covers how operations and projects differ, where they intersect and how work is handed over, and then outlines how organizational governance, project governance and tailoring relate. The details of governance and tailoring come in the later governance topic. Here you only need to tell the concepts apart and know why they are tested under “foundations”.

How operations differ from projects

Operations management focuses on the efficient, effective production of products and/or services. It helps ensure that business operations are conducted efficiently and effectively by using optimal resources to meet customer demands and deliver value. It is concerned with managing processes that transform inputs (materials, components, energy and labor) into outputs (products, goods, services and/or other results). Operations management is distinct from formal project management, and ongoing operations are outside the scope of a project.

In one sentence: operations keep things running and projects drive change. Operations maintain continuous, repetitive value delivery, while projects create unique results and drive change through temporary work. Take a home appliance maker. The washing machines on sale are produced and shipped every day, which is operations, and a day of line stoppage means an immediate loss. The next-generation washing machine is still in development, earns nothing in the short term and needs investment, which is a project, and it determines competitiveness in the next year or two. In this example, the new-product development project is an investment in the company’s future competitiveness.

A few indicator words help. “Continues on an established schedule”, “repetitive” and “day-to-day” lean toward operations. “Introduce”, “add”, “improve once”, “upgrade” and “go live” lean toward projects. Note that of two pieces of work that both seem to “do the same kind of thing”, one may be a project and the other operations. Introducing a new ticketing system for a customer service center is a project; running the customer service hotline on the existing shift schedule is operations.

Intersection points and handover

The two are not unrelated. When business operations need significant change, such as launching a new product or service, that change can be the subject of a project. Projects can intersect with operations at various points during a product life cycle, such as the following:

  1. When developing new products or services, upgrading offerings, or expanding outputs;
  2. While improving product or service delivery operations or their development process;
  3. At the end of the product life cycle; and
  4. At each closeout phase or iteration.

At determined points, deliverables, human resources and knowledge are transferred between the project and operations for implementation of the delivered work. These transfers help ensure the seamless integration of project outcomes into the organization’s operational framework. The transfer may occur through a transfer of project resources or knowledge to operations, or through a transfer of operational resources to the project. Engaging operations teams early in project planning is beneficial and can significantly influence the long-term success and sustainability of a project. At the appropriate delivery or closeout point, the project results that must be sustained or applied are handed over to operations, which sustains and uses them.

Example: handing over a store management app

A retail chain starts a project to develop a store management app. It is planned to take five months, and after delivery the IT operations team will maintain it over the long term. Development, through acceptance, is the project. Day-to-day maintenance and technical support after launch are operations and are not part of the project. The operations team joins the project early in planning to help define operational needs and the handover arrangements. When the project reaches closeout in month five, the team attends training, learns the troubleshooting manual and completes the formal handover, so the project and operations overlap in time. If operations were told only on the day of acceptance that they now own the system, the results might well fail to land.

Organizational governance, project governance and tailoring

Organizational governance provides direction and control through policies, processes, procedures and decisions to meet strategic and operational goals. It is typically overseen by an executive committee or organizational leaders. Project governance is “the adaptable framework that guides project management activities to create value through a unique product, service, or result aligned with organizational, strategic, and operational goals.” It provides structure, systems and processes, roles, responsibilities and decision-making models, such as RACI (responsible, accountable, consulted, informed) matrices or governance boards. A simple way to remember it: organizational governance sets the direction, and project governance turns that direction into specific practice for each project.

Tailoring is “the deliberate adaptation of the project management approach, governance, and processes to make them more suitable for a given environment (environmental factors include industry, culture, regulations, etc.) and fit for the purpose of the work at hand.” Because the context of every project is unique, not every project uses every process, tool and technique in the guide, and one approach cannot be prescribed for all projects. There is no single approach that can be applied to all projects all of the time.

How the three relate: a project is unique, so it must be tailored; governance draws the boundaries for tailoring, setting out what must be followed and what the project can decide for itself. The later topics on governance and tailoring expand on this; for now just build the basic picture.

Example: the first step for a new company

A newly founded retail chain has an owner with no project management experience who plans to run several change projects using the company’s own resources. The most suitable advice from the project manager is to first set up a governance framework that supports project success, that is, make clear who approves, who decides and how reporting works, and only then choose a predictive, adaptive or hybrid approach based on the characteristics of each project. Making all projects use the same method skips the tailoring step.

Governance matters especially at initiation. Sponsors, the project management office or a portfolio steering committee, among others, may do preparatory work or take part in authorization decisions under the organization’s governance arrangements, and a project is formally authorized through a project charter or similar document. When authorizing, the usual checks (common exam practice) are whether the project aligns with the organization’s strategy, whether there is a business case and benefits definition, and whether stakeholders and roles have been identified. Without these, the project lacks a basis for authorization. That is why, when an organization lacks project management experience, “what do you do first?” questions on the exam often point to setting up governance first.

Worked examples

Example 1 Telling which work suits a project

Question 1Example

A company lists several pieces of work: (1) introduce a new ticketing system for the customer service center; (2) keep the customer service hotline running on the existing shift schedule; (3) add a one-click renewal feature to the existing app; (4) carry out a one-time lean improvement of the warehouse process. Which option lists only work that is suitable to run as projects?

Show answer and explanation

Correct answer: D

The company lists four pieces of work: introducing a new ticketing system, running the hotline on the existing shift schedule, adding a one-click renewal feature to the existing app, and carrying out a one-time lean improvement of the warehouse process. You must pick the option in which every item is suitable as a project.

A project is a temporary initiative in a unique context, while operations is ongoing, repetitive day-to-day work. Item 1 (introducing a new system), item 3 (adding a feature) and item 4 (a one-time process improvement) each have a defined start and end and a unique output, so they are projects. Item 2, running the hotline on the existing schedule, is ongoing, repetitive operations and not a project. A quick method for this kind of question: label each item “ongoing” or “has an end point”. Only item 2 is ongoing, so eliminate every option that contains item 2, and only one answer remains. That is the option without item 2. The answer is D.

Why the other options are wrong

  • A. This treats item 2 as a project and also leaves out item 3. Adding a feature is an upgrade to an existing product and is also unique and temporary.
  • B. This also treats item 2 as a project. Running the hotline continuously is operations and has no end point.
  • C. This also treats item 2 as a project, and it leaves out item 1. Introducing a new system is clearly a project.

Key takeaway “Introduce, add, improve” usually signals a project. “Keep running on the existing schedule” signals operations.

Variation If item 2 were changed to “add intelligent call routing to the hotline and launch it within three months”, it would become a project, and the answer would change accordingly.

Something wrong with this question?

Report an issue with this question

Example 2 With little experience, set up the governance framework first

Question 2Example

A newly founded coffee shop chain has an owner with no project management experience, who plans to carry out several change projects using the company’s own resources and has assigned a project manager. What should the project manager advise the owner to do FIRST?

Show answer and explanation

Correct answer: A

A newly founded coffee chain has an owner with no project management experience who plans to run several change projects with its own resources and has assigned a project manager. You must decide what the project manager should advise first. The core concepts are governance and tailoring.

Project governance provides structure, systems and processes, roles and responsibilities, and decision-making models. It is the framework that guides project management activities and keeps projects aligned with organizational strategy. Because the owner has no experience, the first step at the organizational level is to put in place a governance framework that supports project success, making clear who approves, who decides and how reporting works. On that foundation, specific approaches are tailored to the context of each project. Governance provides the decision, oversight and accountability arrangements. Each project then tailors its governance, approach and processes to its own context, choosing a suitable predictive, adaptive or hybrid approach. The answer is A.

Why the other options are wrong

  • B. The approach should be chosen according to the characteristics and needs of each project. Prescribing agile for every project in advance is a one-size-fits-all rule that skips tailoring.
  • C. Developing a work breakdown structure is planning work inside a single project. Before the organization has made clear who approves and who decides, it is not the first thing the owner needs to do. At the organizational level, the first thing to build is the governance framework.
  • D. Prescribing predictive for every project is also one-size-fits-all. Each project’s context is unique and needs tailoring, so one approach cannot be applied to all projects.

Key takeaway Governance sets the boundaries and decision-making approach for projects. Projects are unique and so must be tailored; the approach cannot be one-size-fits-all.

Variation If the organization already has a governance framework and the project manager must choose an approach for a new project with unclear requirements, the answer would be to tailor to the project’s characteristics, leaning toward an adaptive or hybrid approach.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Ongoing operations are not projects, but project results that operations must sustain are usually handed over to operations. The two have intersection points, so you cannot say “projects and operations have no connection”.
  • Operations are ongoing and repetitive; temporary is a characteristic of projects. Treating “continuous production” as a characteristic of a project is wrong.
  • It is usually not advisable to wait until project closeout to involve operations. Engaging the operations team early in planning usually helps long-term success and sustainability.
  • Governance draws boundaries for a project and tailoring chooses the way of working. They are not the same thing, and “everything uses agile” or “everything uses predictive” cannot replace tailoring.
  • Organizational governance and project governance are two levels: the former covers the whole organization and the latter covers specific projects.

Key takeaways

  1. Operations are ongoing and repetitive and produce everyday products and services. Projects are temporary and drive change. Operations maintain ongoing, repetitive value delivery, and projects create unique results and drive change through temporary initiatives.
  2. Projects and operations intersect when new products are developed or upgraded, when operations are improved, at the end of the product life cycle, and at each closeout phase or iteration.
  3. Project results that operations must sustain or apply should usually be handed over to operations, and the operations team should be involved early in planning.
  4. Organizational governance gives direction and control. Project governance is the framework that guides projects and aligns them with strategy, and commonly uses a RACI matrix (responsible, accountable, consulted, informed).
  5. A project is unique, so it must be tailored. Governance draws the boundaries, and tailoring chooses the way of working.

This chapter has 19 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.