PMP Cheat Sheet: Life Cycles and Development Approaches

The key points and common traps of 12 lessons in 5 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.

Mind map of Life Cycles and Development Approaches
Tap the map to enlarge

The Project Life Cycle

Lesson 1: Project Phases, Phase Gates, and the Trends of Risk and the Cost of Changes

Key takeaways

  • A project phase is a collection of logically related activities that culminates in the completion of one or more deliverables and/or outcomes; phases may be sequential, transitional or overlapping.
  • Phase attributes include name, number, duration, resource requirements, entrance criteria and exit criteria.
  • A phase gate review checks against the exit criteria and compares the project's performance and progress with the expectations in project and business documents. It can decide to continue to the next phase, continue with modification, end, remain, repeat or park.
  • Gates can be placed after a phase ends or before a phase begins (pre-phase gates).
  • Risk and uncertainty are highest at the start and fall afterward; the cost of changes is low at the start and usually rises (see Figure 2).

Common traps

  • A gate review's conclusions are not limited to "pass" and "stop". Continuing with modification, remaining in the phase, repeating the phase, and parking the project to do something more urgent are all outcomes that PMBOK 8 lists explicitly.
  • The end of a phase is not the end of the project. At a phase end you close out the phase and hand over. For a project that completes normally, overall closure comes after all phases are complete (a project terminated early must also be closed out; closing first and then releasing people is common exam practice).
  • A gate is not always placed after a phase. A pre-phase gate checks that direction, resources, planning and risks are ready.
  • The time of greatest risk and uncertainty is the start of the project or phase, not the end. The cost of changes goes up the later it is, not down.
  • The two curves show trends, not exact quantitative relationships, and they do not mean that changes can never be made late.

Lesson 2: Life Cycle Flexibility, the Product Life Cycle, and Four Easily Confused Concepts

Key takeaways

  • A life cycle needs enough flexibility: you can select the approach or a mix, identify the types of processes and activities, and adjust the name, duration, entrance criteria and exit criteria of phases.
  • When there is no standard life cycle, the project manager and team determine the best one for this project. They do not wait and do not copy.
  • The project life cycle is independent of the product life cycle, and one product life cycle can include several projects.
  • A development approach is a means; the development phase is the stage where deliverables are created and tested; focus areas are five groupings of management actions; and a project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables and/or outcomes.
  • The three commonly used approaches form a spectrum, and hybrid blends the advantages of both ends.

Common traps

  • When you see "life cycle", first tell whether it is the project's or the product's. A project has a start and an end, while a product life cycle can be much longer and may include several projects.
  • A life cycle is not a fixed template. With no standard, choose the one that best fits the project; with a standard, you can still adjust phase attributes within what it allows. This is a form of tailoring.
  • A "development approach" is a means, and a "development phase" is a span of time. The names are similar but the meanings are completely different.
  • A focus area is a classification of management actions, not a phase. Initiating is not "the first period of the project", and closing does not appear only at the end.

Predictive and Adaptive Approaches and the Stacey Matrix

Lesson 1: Predictive vs. Adaptive Approaches: Characteristics and When to Use Each

Key takeaways

  • Development approaches form a spectrum: predictive at one end, adaptive at the other, and hybrid mixing the strengths of both.
  • A predictive approach is also called waterfall, plan-driven, or traditional; its characteristics are plan-driven, requirements up front, change through a process, and value that usually appears later.
  • Predictive suits: scope that stabilizes early; iteration that costs more than it is worth; significant investment or strict regulation.
  • An adaptive approach is also called change-driven or agile; it is vision first, with a prioritized backlog, short iterations plus feedback, and often timeboxes and flow-based scheduling.
  • Adaptive suits: design projects, new product development, and digital projects with changing scope that need early or incremental delivery.

Common traps

  • An organization that is transforming to agile does not use agile on every project. A project with clear requirements and experience from similar projects should still choose a predictive approach.
  • However strict change control is, it cannot stop requirements from changing frequently. If requirements keep changing, consider adjusting the development approach rather than blocking the changes.
  • Adaptive does not mean “no planning.” It keeps the vision, the backlog, and a cadence; planning is simply elaborated on a rolling basis by iteration.
  • Adaptive approaches usually require more frequent, continuous stakeholder feedback: the more frequent the feedback, the more consistently the relevant people must stay involved.
  • A predictive approach can also deliver in batches; see the next lesson.

Lesson 2: Iteration vs. Increment vs. Adaptive, and the Stacey Matrix

Key takeaways

  • Iteration: repeated cycles, pursuing a correct solution. Increment: delivery in batches, pursuing early value. An adaptive approach can be iterative, incremental, or a combination of both; iteration plus increment is common but not required by the definition.
  • A predictive approach can also deliver incrementally, provided the overall scope is well understood and planned up front and the overall scope and timeline remain largely fixed.
  • The two Stacey axes: requirements uncertainty and technology uncertainty.
  • The four zones: simple (linear methods work), complicated (some uncertainty in requirements or technology; use predictive, iterative, incremental, or hybrid as the case requires), complex (adaptive approaches are the best fit; the preceding is common exam practice), and chaotic (fundamentally risky).
  • To tell predictive increments from adaptive, check whether the overall scope is already clear.

Common traps

  • Iteration solves the problem of an uncertain solution and increment solves the problem of delivering in batches. When both problems exist, the common approach is iteration plus increment, the typical adaptive way of working (an adaptive approach may also be only iterative or only incremental).
  • Predictive incremental delivery requires that the overall scope be well understood and planned up front. If the stem says only “we want to release part of it first” while the scope is still changing, it does not qualify.
  • When the customer is unwilling to wait until the end to see results, first assess the impact of switching to incremental delivery; do not abandon the whole plan outright.
  • Do not switch to predictive in the complex zone just because there is a fixed deadline. Keep using an adaptive approach and protect the deadline through timeboxes and prioritization.
  • The Stacey matrix looks at the requirements and technology axes, not at project value or volume of work. A project with a large volume of work can still land in the simple zone.

Lesson 3: How to Choose a Development Approach, and Delivery Cadences

Key takeaways

  • The factors for choosing an approach fall into three categories: deliverables, the project, and the organization. The approach is chosen by the project manager in consultation with the project management team, evaluating first and choosing afterward.
  • Clear and stable requirements, a high cost of change, strict regulation, and rigorous safety requirements lean predictive; innovation, unstable scope, high uncertainty, and the need for frequent feedback lean adaptive.
  • Adaptive approaches typically call for significant stakeholder involvement throughout and often work better with smaller teams.
  • The suitability filter is a tool that helps teams discuss the initial development approach; it is not a rigid method.
  • There are four delivery cadences: single, multiple, periodic, and continuous; periodic delivery is commonly used in adaptive approaches.

Common traps

  • Before the approach is set, analyze the project’s characteristics first (clarity of requirements, complexity, frequency of change, stakeholder involvement, and so on) and then choose the approach. Do not start from which training the team has had or which approach you are used to.
  • To judge complexity, look at uncertainty, interdependencies, stakeholders, and technical difficulty, not at the format or quantity of documents.
  • When factors conflict, do not insist on choosing only one approach. Different deliverables can use different approaches; this is where the hybrid approach comes from.
  • A fixed deadline does not automatically mean predictive. If delivering part of the result early realizes value, an adaptive or iterative approach can still be used, managing the deadline through fixed timeboxes, value-based prioritization, release planning, and scope trade-offs.
  • Delivery cadence is a decision made after the approach is chosen. You must be able to tell single, multiple, periodic, and continuous apart.

Hybrid Approaches

Lesson 1: Hybrid Approaches: Definition, Four Patterns, and When to Use One

Key takeaways

  • A hybrid approach combines some predictive elements with some adaptive elements; most projects can strongly benefit from one.
  • Four patterns: adaptive early then predictive; both throughout the life cycle; predictive-led with a small adaptive component; adaptive-led with a small predictive component.
  • It fits when: there is uncertainty or risk around requirements; deliverables can be modularized or developed by different teams; there is a regulated stage but a wish to shorten the cycle.
  • Choosing block by block (common exam practice): for each block ask whether the requirements are clear, whether they change, and whether frequent feedback is needed.
  • When predictive and adaptive vocabulary coexist in the stem, think hybrid first.

Common traps

  • A hybrid approach is not taking a bit of each at random. Which parts use a predictive approach and which use an adaptive approach must have a clear division of labor and a reason.
  • “Phasing” is not a development approach. A phase is a division of time; a hybrid approach uses different approaches in different phases and different components.
  • “Uncertain requirements with a fixed deadline” can be handled by an adaptive approach by itself and is not on its own a reason to choose a hybrid approach; a hybrid approach fits only when there is also a part that must be planned predictively against a baseline or a stable scope, and a hybrid approach does not guarantee on-time completion either.
  • A hybrid project usually does not make a detailed plan for all of the work at the start; only the parts with clear requirements are planned in detail first (common exam practice).
  • A hybrid project may use single, multiple, periodic, or continuous delivery depending on value and the characteristics of the deliverables; when delivering incrementally, each delivery should serve the stated business objectives and be a result that is valuable to the customer.

Lesson 2: Transitioning Gradually to a Hybrid Approach, and Managing a Hybrid Environment

Key takeaways

  • Gradual transition: try on a low-risk project first and roll out after success; build awareness first, and communicate before implementing (all common exam practice). The PMO can review and approve tailored approaches (PMBOK 8 Section 3.4.2).
  • A hybrid approach is a suitable bridge when management wants agile and the team has no experience yet (common exam reasoning).
  • Interfaces in a hybrid environment (common exam practice): dependencies and commitments, communication and reporting, stakeholder engagement, planning and risk review, contract type, quality and acceptance, artifacts and knowledge transfer, servant leadership.
  • The product owner orders the product backlog; the work plan for the current iteration is adjusted by the team members doing the work (without endangering the iteration goal); the project manager provides support and removes impediments.
  • When every batch going live is taken over by operations, transfer knowledge batch by batch.

Common traps

  • When the team has no adaptive experience and management wants an adaptive approach, a hybrid approach is a gradual compromise; it is neither an immediate full switch to agile nor standing still (common exam reasoning).
  • Do not roll out a new approach across the board, and do not force it. Find a pilot first and persuade with success stories (common exam practice).
  • When two approaches coexist in one project, do not insist on unifying them into one. Let each team keep the approach that suits it and align at the interfaces.
  • The adaptive part commits to the goal of the current iteration, and the work selected for the iteration is a forecast that can be renegotiated without endangering the goal; later deliveries are only a continuously updated forecast and must not be treated by the predictive part as fixed completion dates.
  • When a key skill is temporarily missing, first assess the impact and the options; provided no extra risk is introduced, you may adjust the order of work, and at the same time close the capability gap through training, negotiation, or obtaining internal or external resources.
  • When operations takes over after every batch goes live, hand over batch by batch; knowledge transfer cannot wait until the project ends.

Lesson 3: Organizational Transformation to Agile: Assess, Then Pilot, Then Expand

Key takeaways

  • The main line of transformation: assess first (culture, suitability, maturity, readiness, target state), then train and pilot, then expand gradually.
  • Start the pilot with lightweight activities: the daily coordination meeting, the iteration review meeting, and the retrospective. Proceed within the permitted cultural and regulatory boundaries and gradually adjust the management methods that do not fit.
  • Win the buy-in of senior leaders and the trust of those who resist through visible results delivered quickly, not through added resources or force.
  • Management must shift from directing and checking to serving and empowering, and the way people are evaluated must change in step.
  • The difficulty of transformation is the inertia of culture and governance; when the organization has already decided to transform, first explain the decision and plan with the team how to adopt it.

Common traps

  • Before pushing agile, first assess organizational culture and suitability, then decide whether to adopt it and which practices to adopt. Remedying after failure, or training first and assessing afterward, are both in the wrong order.
  • The inertia of culture and governance is usually one of the core obstacles to an agile transformation, not tools or space; still judge the organization’s main obstacle from the assessment results.
  • Rolling out comprehensively, immediately, and across the board is the most typical wrong option.
  • When members do not buy in or business partners resist, win support with visible value and communication, not with force or empty promises.
  • Outside agile teams or coaches can add implementation capability, but they cannot replace the judgment of cultural fit.

Tailoring

Lesson 1: What Tailoring Means, Why We Do It, and What We Tailor

Key takeaways

  • Tailoring is the deliberate adaptation of the project management approach, governance, and processes to suit the environment and the purpose of the work; it is driven by principles, organizational values, and organizational culture.
  • The aim is just right: too little overlooks key activities, too much is costly and wasteful.
  • Three aspects can be tailored: life cycle and development approach selection, processes, and engagement; practices within performance domains can be tailored too.
  • The five verbs of process tailoring: add, modify, remove, blend, align.
  • Artifacts are chosen by the project manager and the project team according to the project’s characteristics, not copied from templates; organizational policy or the contract may limit the room for tailoring.

Common traps

  • Tailoring is neither arbitrary cutting nor adopting everything wholesale. It is a deliberate selection and adjustment, and you must verify that the adjusted approach is effective.
  • The uniqueness of the project is the fundamental reason tailoring is needed; no single approach suits all projects.
  • Process tailoring has five verbs: add, modify, remove, blend, align; “remove” is only one of them.
  • The 40 processes are a tailorable reference, not a checklist that must all be done; inputs, outputs, tools, and techniques are likewise only examples.
  • When organizational policy or the contract mandates an approach, the room for tailoring is limited and you must not override it on your own.

Lesson 2: The Four Steps of Tailoring, Influencing Factors, Approval, and Diagnostics

Key takeaways

  • Four steps: select the initial development approach → tailor for the organization → tailor for the project → implement ongoing improvement.
  • Tailoring for the project looks at three groups of attributes: product or deliverable, project team, and culture.
  • Tailoring that affects only the project team is usually approved by the project manager; tailoring that affects external groups may need PMO approval.
  • Diagnose through retrospectives, lessons learned meetings, or issues, threats, quality metrics, and stakeholder feedback; Table 3-1 gives common situations and suggestions.
  • Before tailoring, thoroughly analyze the project environment, and verify that the adjusted approach is effective.

Common traps

  • The order of the four steps is: select the initial approach, tailor for the organization, tailor for the project, improve continuously. It is not tailor the processes first and select the approach afterward.
  • PMBOK 8 requires thoroughly analyzing and understanding the project environment before tailoring, and then going through the four steps of selecting the initial approach, tailoring for the organization, tailoring for the project, and implementing ongoing improvement. This applies equally when a new approach is used for the first time: make an appropriate initial tailoring first, and keep testing and adjusting during implementation through retrospectives and similar means.
  • Common exam practice: when using an approach for the first time, change as little as possible, first practice the standard way to get familiar, and then adjust based on real problems; if you make big changes from the start and something goes wrong, you cannot tell whether the cause is the approach itself or your modifications.
  • Whether to introduce a new practice: first analyze the organization’s culture and its readiness for change, then train and implement; do not roll it out directly.
  • Ongoing improvement is the fourth step, not an optional extra after tailoring is complete; waiting until project closing to evaluate is too late.

Focus Areas and Performance Domains

Lesson 1: The Five Focus Areas and the Seven Performance Domains

Key takeaways

  • Five Focus Areas: Initiating, Planning, Executing, Monitoring and Controlling, Closing; they are the process groups recast and are implemented through formal processes, informal practices, or policies.
  • Focus Areas are not project phases and are not strictly sequential; they often overlap within a phase, and Monitoring and Controlling runs in parallel with the others.
  • Seven performance domains: Governance, Scope (including quality), Schedule, Finance, Stakeholders, Resources, Risk; in no particular weight or order, they run concurrently throughout the life cycle.
  • Each performance domain has five subsections: Key Concepts, Processes, Tailoring Considerations, Interactions With Other Domains, Check Results.
  • Inputs, tools and techniques, and outputs are examples only; project management activities do not by themselves provide value, so results are what you check.

Common traps

  • Treating Focus Areas as phases is the most common mistake. Initiating is not “the first stretch of the project,” and Planning is not something that must be finished before Executing.
  • Monitoring and Controlling is not something done only before closing; it runs throughout and in parallel with the other areas.
  • Exam questions often say “the project is in the execution phase,” “the planning phase” or “the closing phase.” That is common exam practice for “the project is being executed, planned or closed,” which maps to the matching Focus Area, not to a life-cycle phase. Answer from the scenario; don’t get stuck on the label.
  • The names of the five areas are the same as the former five process groups, and neither is a sequence of project phases to be completed one after another. PMBOK 8 recasts them as Focus Areas, a classification of actions that covers formal processes, informal practices, and flexible policies and procedures.
  • There are seven performance domains. Quality has no separate performance domain, and it has not been deleted either: deliverable quality and its verification sit in the Scope performance domain, and process quality assurance (the Manage Quality Assurance process) sits in the Governance performance domain; communication sits in the Stakeholders performance domain.

Lesson 2: Mapping Focus Areas to Performance Domains, and How the PMBOK 8 Structure Changed

Key takeaways

  • Each cell of the mapping table holds the processes of a performance domain in a Focus Area, 40 in total: Initiating 2, Planning 19, Executing 8, Monitoring and Controlling 10, Closing 1.
  • The Risk performance domain: in Planning, Plan Risk Management, Identify Risks, Perform Risk Analysis, and Plan Risk Responses; in Executing, Implement Risk Responses; in Monitoring and Controlling, Monitor Risks.
  • Validate Scope and Monitor and Control Scope are both in Monitoring and Controlling; Estimate Costs is in Planning; Identify Stakeholders is in Initiating.
  • PMBOK 8 versus the Seventh Edition: 12 principles refined to 6; performance domains updated to 7; the old knowledge areas integrated into the performance domains; process groups repositioned as Focus Areas; 40 non-prescriptive processes selected.
  • Quality has no separate performance domain: deliverable verification goes to Scope and Manage Quality Assurance goes to Governance; communications merges into Stakeholders; integration corresponds to Governance; procurement goes into an appendix.

Common traps

  • PMBOK 8 is not a return to the Sixth Edition. The evolution runs from the Sixth to the Seventh to the Eighth; the skeleton is still principles plus performance domains, with processes brought back.
  • Twelve principles, eight performance domains, and knowledge areas are the language of the Seventh Edition or earlier; PMBOK 8 has 6 principles, 7 performance domains, 5 Focus Areas, and 40 processes.
  • The 40 processes are a non-prescriptive, tailorable reference; the process groups were not deleted but repositioned as Focus Areas.
  • The processes of one performance domain are spread across different Focus Areas; do not map the two one to one.
  • Estimate Costs is in Planning, not Executing; Validate Scope is in Monitoring and Controlling, not Closing; Identify Stakeholders is in Initiating, not Planning.
  • In the Executing Focus Area the Risk performance domain has only Implement Risk Responses; Plan Risk Responses maps to the Planning Focus Area, not the Executing Focus Area.