PMP Cheat Sheet: Project Management Principles
The key points and common traps of 6 lessons in 2 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
Project Management Principles
Lesson 1: Nature of the Principles, Adopt a Holistic View and Focus on Value
- Principles provide foundational guidance for decisions and are not prescriptive; the six principles complement one another without contradiction, and they may overlap.
- The three dimensions of the mindset: proactive (holistic view, quality), ownership (accountable leader, empowered culture), value-driven (focus on value, sustainability).
- Adopt a Holistic View: manage all components and their interdependencies as part of a larger system, and aim for the best result for the whole.
- Focus on Value: move attention from deliverables to intended outcomes, keep checking against the business case, and consider terminating the project if misalignment persists.
- Focusing on value relies on continuous scope management to prevent creep and gold plating; it does not mean adding features.
- A principle is not a rule. It is not a set of clauses to execute one by one, it has no order of priority, and you cannot drop one of them.
- Overlap among principles is normal. It is not a defect in the principles, and nothing needs to be revised first.
- Delivering on scope, schedule and budget does not equal project success: the Eighth Edition looks at the value obtained for what was invested.
- Value is not the same as revenue. Social benefits and the customer's perceived benefits are value too, whether measured quantitatively or described qualitatively.
- A holistic view does not mean every team moves in lockstep. It means seeing the dependencies clearly and letting local goals serve the overall goal.
Lesson 2: Embed Quality Into Processes and Deliverables; Be an Accountable Leader
- Quality is the degree to which characteristics meet or exceed the target objectives; it covers both deliverables and processes, and its foundation is continuous improvement and waste elimination.
- Quality dimensions (the Eighth Edition lists these, "including but not limited to" nine): performance, conformity, reliability, resilience, satisfaction, uniformity, efficiency, sustainability, compliance.
- Quality comes from prevention and shifting left, not from a final inspection. In adaptive projects the acceptance criteria may need regular updating and refining as the project evolves, and their validity is checked at acceptance.
- An accountable leader takes responsibility for objectives, actions and decisions. The five characteristics: integrity, honesty and fairness; self-awareness; respectfulness, humility and availability; flexibility and adaptability; shared leadership.
- Leadership is different from authority and is not exclusive to the project manager; psychological safety lets problems surface early.
- Quality applies not only to deliverables but also to processes; both are protected through prevention.
- Quality is measured against acceptance criteria, the definition of done, fitness for use and efficiency. It is not a matter of subjective feeling, and it must not be loosened at will because of cost pressure.
- Concentrating inspection just before delivery is checking after the fact. Embedding quality means building it into the planning and the process.
- Being accountable does not mean being domineering or pressing people with authority. It means leading by example and owning the outcome.
- When members report only good news, first deal with whether people dare to speak, rather than tightening monitoring, naming individuals or cutting performance ratings.
- Adapting your leadership style flexibly does not mean giving up your core values.
Lesson 3: Build an Empowered Culture; Principles, Performance Domains and the Seventh Edition
- Empowered culture: build trust, clarify roles, responsibilities, team agreements and processes, so that individuals can work together and create synergy.
- Five areas: diversity, process definition, interpersonal skills, knowledge of organizational structures, team agreements; the team creates its agreement at the start of the project.
- When members do not dare to speak or try, first create psychological safety and lower the cost of trying. Do not punish or tighten monitoring.
- Principles are the foundation of the performance domains, and the domains are the mechanism of the principles; all principles relate to all domains, with differing strength.
- Twelve principles were merged and refined into six; tailoring moved out, and optimizing risk responses moved into the Risk performance domain.
- Empowerment is not letting things drift. Authority is delegated within a framework of clear roles, responsibilities, team agreements and processes, and major matters beyond the team's authority go to the person with authority through governance.
- A team agreement is created and maintained by the team at the start of the project. It is not issued unilaterally by the project manager.
- When members do not report or innovate because they fear being blamed, first create psychological safety and lower the cost of trying. Do not use punishment, surprise spot checks or hand the matter to the functional manager.
- When a member has an emotional or attitude problem, the project manager first talks with the person and involves the team; the first move is not to escalate it to the sponsor.
- "All principles relate to all performance domains." Do not choose an absolute statement such as "only the holistic view relates to all domains".
- Tailoring and optimizing risk responses are no longer principles. They went to different places, so do not list them together or fold them into another principle.
Lesson 4: Professional Ethics and Professional Conduct
- The four values of professional ethics are responsibility, respect, fairness and honesty (they match Figure 3-5 of the Eighth Edition and are also a common summary of PMI's Code of Ethics and Professional Conduct; Section 3.6 cites "integrity, honesty, and fairness"). They are the minimum bottom line and the standard for judging scenario questions.
- Report honestly: do not dress up data, schedule or risk, and when you find that real needs are not being met, tell people promptly and negotiate.
- Refuse improper instructions and follow formal procedures; disclose conflicts of interest and step aside; do not leak confidential information.
- When you find illegal conduct or a serious violation, report it promptly and honestly to the person with authority to deal with it. Do not decide the matter yourself and do not pass it on.
- When the facts are unclear, verify first and then decide. Do not discipline on rumor, and do not call people out in public.
- Under pressure, honesty comes first. Do not dress up data or conceal risks because the sponsor asks or because it would be less trouble.
- "The contract terms are met" does not mean you can stay silent. If you know the deliverable cannot meet the customer's real needs, tell them honestly and negotiate.
- When you find illegal conduct, a serious breach of professional ethics, or conduct that meets the organization's escalation conditions, the project manager should promptly and honestly report it to the person with authority to deal with it. Other violations should be corrected and handled promptly according to organizational policy and your authority, and escalated if necessary. Asking the person involved to report it, investigating beyond your authority, or passing the problem to someone else does not count as meeting the duty. Necessary verification within your authority is fine, but once the conditions for reporting are met you must report promptly.
- Verify before you discipline. When the team demands action against a member, first confirm the facts with that person and then decide. Do not suspend the person or announce it publicly first.
- Infringement in outsourced work: stop using the infringing part first and hold the supplier responsible under the contract. It is neither "not my problem" nor "the company pays first and that settles it".
Sustainability
Lesson 1: Meaning of Sustainability, the Triple Bottom Line and Strategies for Negative Impacts
- Sustainability: meet present needs without compromising the ability of future generations to meet their own needs.
- Consider people, the planet, society and value; the triple bottom line is social equity, environmental stewardship and economic prosperity.
- Strategies for external impacts are increasingly impactful, with four levels: compensate or offset, restore, minimize, avoid (Figure 3-7).
- The orientation broadens: compliance-oriented to the life cycle of the process, achievement-oriented to the life cycle of the deliverable, sustainability-oriented to the life cycle of the outcome.
- Where an impact can be avoided at the source, do not wait until it has happened to compensate.
- Sustainability is not only environmental protection. Social equity and economic prosperity stand alongside environmental stewardship, and it also means considering people, the planet, society and value.
- The triple bottom line is social equity, environmental stewardship and economic prosperity. It is not scope, schedule and cost, and not environment, legal and financial.
- Compensation is the lowest level: it makes amends after the harm has happened. Where an impact can be avoided at the source, do not stop at compensation.
- Minimization is not elimination: the impact still occurs but is reduced. Only avoidance means not producing it at all.
- Sustainability must cover all phases of the project life cycle. It is not assessed only at closing.
Lesson 2: Integrating Sustainability Into a Project: Practices, Challenges, Performance Domains and Compliance
- How to put it into practice: write sustainability key performance indicators into formal documents such as the scope statement, charter, business case and contracts, and monitor compliance in planning, execution and closure.
- Three challenges: broader scope and complexity; risk when there is no balance; no universal criteria, so tailoring is needed.
- The sponsor confirms the goals. When they are not in the documents, the project manager still raises them actively in meetings and with stakeholders.
- An enterprise's sustainability strategy and related processes and practices may be enterprise environmental factors, and the requirements that apply to the project are constraints that must be followed. Sustainability relates to all seven performance domains.
- The sponsor, project manager and team carry it out together, across all phases.
- Sustainability goals go into formal documents and are confirmed by the sponsor. If they are not included, keep discussing them in meetings. Do not drop them as "out of scope", and do not change the scope or the budget baseline on your own.
- An enterprise's sustainability strategy and the related processes and practices may be enterprise environmental factors, and the requirements and compliance conditions that apply to the project must be followed. Compliance can be monitored during planning, execution and closure; it is not checked only at closing.
- There are no universal sustainability criteria, so each project requires a tailored assessment approach. Relevant organizational or external approaches may be adapted to the project's context.
- Looking only at cost and ignoring environmental and community impact is a typical source of sustainability risk.
- Integrating sustainability takes the sponsor, project manager and team working together. Do not push it onto a single role.