Life Cycles and Development Approaches

Tailoring

PMP · Life Cycles and Development Approaches · 2 lessons · about 25 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Tailoring is the deliberate adaptation of the project management approach, governance, and processes to make them more suitable for a given environment and fit for the purpose of the work at hand. PMBOK 8 treats project management as a system that can be adjusted for each project, and tailoring is driven by the guiding project management principles, organizational values, and organizational culture. This chapter covers what tailoring is and why to do it; the three aspects that can be tailored (life cycle and development approach selection, processes, and engagement); the four steps of the tailoring process; the three groups of attributes to evaluate when tailoring for a project; who approves tailoring; and how to use retrospectives and measures to diagnose whether further tailoring is needed.

By the end of this chapter you should be able to do the following. Explain that tailoring is neither arbitrary cutting nor adopting everything wholesale. List the five verbs of process tailoring. State the four steps of tailoring and their order. Ask questions from three angles, the product or deliverable, the project team, and culture, when tailoring for a project. Distinguish who approves internal tailoring and who approves tailoring that affects external groups. Use the common situations in Table 3-1 to give tailoring suggestions. And, in scenario questions about “introducing a new practice,” know that the first thing to do is analyze organizational culture and readiness.

Lessons in this chapter

Chapter map

ItemKey pointsIn one sentence
TailoringDeliberately adapting approach, governance, and processesThe goal is just right, not arbitrary picking and choosing
Three aspectsLife cycle and development approach selection, processes, engagementPractices within performance domains can be tailored too
Five verbs for processesAdd, modify, remove, blend, alignRemoving is only one of them
Four stepsInitial approach → for the organization → for the project → ongoing improvementOngoing improvement is not optional
Three groups of attributesProduct or deliverable, project team, cultureAnalyze first, then tailor
ApprovalTailoring that affects only the internal team is usually approved by the project manager; tailoring that affects external groups may need PMO approvalOrganizational policy sets the boundary

Study tips and practice

  • Remember “analyze the environment first, then act.” In questions about introducing or changing a practice, the “first” step is usually to analyze organizational culture and team and project characteristics (when no option offers that analysis, pick the best remaining one). Using a new approach for the first time is covered by the same PMBOK 8 requirement to thoroughly analyze the project environment before tailoring, so make an appropriate initial tailoring first. “First practice the standard way to get familiar, then adjust on evidence from retrospectives” is common exam practice.

Lesson 1

What Tailoring Means, Why We Do It, and What We Tailor

Lesson video

Lesson overview

PMBOK 8 treats project management as a system that can be adjusted for each project, not a set of rules that must be followed in full. This adjustment project by project is called tailoring. This lesson covers what tailoring is, why to do it, and what can be tailored; the next lesson covers how tailoring is done step by step, which factors influence it, and who approves it. Scenario questions typically ask: the project manager wants to introduce a certain practice, or receives a full set of templates; what should be done next? The answer is usually to evaluate the project environment, objectives, and constraints first, then “select and adjust according to the characteristics of the project,” neither adopting everything wholesale nor abandoning everything; whether collaboration, verification, or approval is also needed depends on the situation in the stem and the governance arrangements. ECO: Process domain, Task 1 (Develop an integrated project management plan and plan delivery), which includes assessing complexity and size and recommending a development approach.

What tailoring is

Tailoring is the deliberate adaptation of the project management approach, governance, and processes to make them more suitable for a given environment (environmental factors include industry, culture, regulations, and so on) and fit for the purpose of the work at hand. The guide’s overview puts it this way: tailoring aligns the project management approach, governance, and processes with the project’s environment and objectives; when tailoring, you consider the development approach, processes, project life cycle, deliverables, and the approach to stakeholder and team involvement. The tailoring process is driven by the guiding project management principles, organizational values, and organizational culture; it is not arbitrary picking and choosing. For example, organizations with a low risk appetite often implement structured processes and oversight mechanisms to minimize uncertainty, whereas organizations with higher risk tolerance may prioritize agility and decision-making autonomy, adjusting process rigor to project needs rather than applying a fixed number of procedures.

Why tailor

There is no single approach that can be applied to all projects all of the time. The structure used to deliver projects can be extensive or minimal, rigorous or lightweight, comprehensive or streamlined. Tailoring is performed to better suit the organization, operating environment, and project needs, and many variables factor into it: the criticality of the project, scale, duration, complexity, industry standards, organizational culture, the number of stakeholders involved, and the level of organizational project management maturity. For example, the rigor, checks and balances, and reporting requirements for a critical nuclear reactor project are much greater than those for building a new office building, and the communication and coordination needs for a 10-member project team are far less extensive than for a team of 200 people.

The goal is to get the balance just right: too few processes can lead to ineffective project management because key activities that support effective management are overlooked, while employing more processes than required is costly and wasteful. An example of the former is cutting data verification out of a new-drug clinical trial to save time, with the result that a whole batch of data may not be accepted by the regulator. An example of the latter is running three-vendor price comparisons, a bid evaluation meeting, and contract review to buy a few boxes of printer paper, so that the process costs far more labor than the purchase is worth. Sound tailoring can deliver direct and indirect value to organizations: more commitment from the project team members who helped to tailor the approach, a stronger customer-oriented focus, and more efficient use of project resources.

The project operates in a complex environment and must balance competing demands: delivering as quickly as possible, minimizing project costs, optimizing the value delivered, creating high-quality deliverables, ensuring compliance with regulatory standards and sustainability considerations, satisfying diverse stakeholder expectations, and adapting to change. Some situations limit the degree to which project teams can tailor, for example when organizational policies mandate the use of a specific approach or when a contract specifies a mandated approach. In such cases you may not override the constraint on your own; you tailor within what is allowed.

What to tailor

The guide lists three project aspects that can be tailored: life cycle and development approach selection, processes, and engagement. In addition, based on the uniqueness of the project, the work associated with each performance domain can also be tailored, that is, the practices within the performance domains.

Life cycle and development approach selection. Deciding on a life cycle and its phases is itself an example of tailoring, and additional tailoring can be done while selecting the development and delivery approach. For instance, building a new data center could involve a predictive approach for the physical building construction and finishing and an adaptive approach for understanding and establishing the computing capabilities required. Viewed from the project level, this combination represents a hybrid approach, but the construction team and the computing team may each experience only a predictive or an adaptive development approach.

Processes. Process tailoring involves determining which elements should be added, to address unique conditions or increase rigor; modified, to better fit project or team needs, including adjusting inputs, outputs, and tools and techniques; removed, to reduce unnecessary cost or effort; blended, to combine elements for added value; or aligned, to ensure consistency in definition and application. Remember all five verbs.

Engagement. Tailoring engagement for the people involved in the project covers three things. People: assessing the skills and capabilities of the project leadership and team and ensuring they adapt to evolving project needs. Empowerment: choosing which responsibilities and forms of local decision-making should be deferred to the project team; where the environment and team member capabilities support it, empower more, and otherwise more supervision and direction may be required. Integration: creating one project team from a diverse collection of contributors (contracted entities, channel partners, and other external entities, in addition to staff from inside the sponsoring organization).

Also, artifacts. The inputs, outputs, tools, and techniques the guide lists are common options only, are not exhaustive, and are not required on any given project. Which artifacts to use and how detailed to make them is chosen and tailored by those who know the project best, the project manager and the project team, according to the project’s characteristics, organizational requirements, and stakeholders’ information needs, rather than applying templates mechanically; organizational policy, the contract, or governance arrangements may specify required artifacts and who approves them. When the artifact burden is too heavy and eats into the time for doing project tasks, review and adjust it.

Scenario: an internal reporting tool for a five-person team

A start-up is building an internal reporting tool with a team of five. The project manager tailors the communication-related practices. When planning communications, no separate formal communications management plan is prepared; when managing communications, a ten-minute daily coordination meeting and a shared board are used instead. This is “modify.” Risk management is kept, but the risk register is compressed to a one-page table, which is also “modify.” No external procurement is done and Plan Sourcing Strategy is not needed because only existing resources are used; that is “remove.” The separate weekly report and the iteration review notes are merged into one document, which is “blend.” All four adjustments are tailoring, and each has a reason: each one can answer the question “what value does this add to this project?”

Worked examples

Example 1 Scenario: wanting to use agile practices in a traditional project

Question 1Example

A project manager is assigned to a logistics center relocation and equipment installation project. He has just finished an agile course and wants to use agile practices on this project. What should the project manager do?

Show answer and explanation

Correct answer: A

The project manager of a logistics center relocation and equipment installation project has just finished an agile course and wants to use agile practices on it. You must decide what to do.

Tailoring is the deliberate adaptation of the project management approach to suit the project: it is neither adopting everything wholesale nor abandoning everything, but selecting suitable practices according to the project’s characteristics. Since the project manager wants to use agile practices, he should pick the parts that can be implemented in a relocation and installation project, such as the daily coordination meeting and a visual task board, and apply them. The answer is A.

Why the other options are wrong

  • B. The project manager has already studied agile, so what must be judged now is how to use it, not whether it can be used. Asking an outside consultant to assess is a way of sidestepping the question.
  • C. A project manager who has studied agile can apply practices such as servant leadership himself, without adding a role first.
  • D. You should first analyze which practices apply and only then look at resource changes, rather than adding budget at the outset.

Key takeaway Tailoring means selecting the practices that suit this project, neither copying the whole set nor rejecting it all. Look at the project’s characteristics when selecting: relocation and installation work is mainly physical, so suitable practices should help coordinate and make progress visible.

Variation If a contract mandated a particular management approach, the room for tailoring would be limited, and you would choose practices within what is allowed and not override it on your own.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: who decides which artifacts to use

Question 2Example

A project manager is responsible for a project whose nature is completely different from the organization’s earlier projects and is tailoring the project artifacts for it. Who should decide which artifacts to use?

Show answer and explanation

Correct answer: A

The project’s nature is completely different from the organization’s earlier projects, and the artifacts are being tailored. You must decide who decides which artifacts are used.

Artifacts should be tailored by those who know the project best. The project is unusual, so the organization’s standard artifacts may not apply; the project manager and project team, based on this project’s characteristics, select suitable ones from those available and adjust them where needed, so that they really fit the project. The guide also stresses that inputs, outputs, tools, and techniques are only common options and are not required on any given project. The subject of tailoring is the project manager and the project team; other roles can give input or approve when external groups are affected, but they do not decide the artifacts for them. The answer is A.

Why the other options are wrong

  • B. The sponsor does not necessarily know project management practices and knows the project less well than the project manager and team, so should not directly specify the artifacts.
  • C. The project is unique, so the organization’s full set of standard artifacts cannot be copied directly and must be screened against the project.
  • D. Stakeholders can give input, but choosing artifacts is a professional judgment of the project management team and should not be decided by a stakeholder meeting.

Key takeaway How artifacts are tailored is decided by the project manager and the project team according to the project’s characteristics.

Variation If the tailoring would affect external groups, PMO approval may be required. Tailoring that affects only the internal team is usually approved by the project manager, and organizational policy and governance arrangements must still be followed.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Tailoring is neither arbitrary cutting nor adopting everything wholesale. It is a deliberate selection and adjustment, and you must verify that the adjusted approach is effective.
  • The uniqueness of the project is the fundamental reason tailoring is needed; no single approach suits all projects.
  • Process tailoring has five verbs: add, modify, remove, blend, align; “remove” is only one of them.
  • The 40 processes are a tailorable reference, not a checklist that must all be done; inputs, outputs, tools, and techniques are likewise only examples.
  • When organizational policy or the contract mandates an approach, the room for tailoring is limited and you must not override it on your own.

Key takeaways

Key point

  • Tailoring is the deliberate adaptation of the project management approach, governance, and processes to suit the environment and the purpose of the work; it is driven by principles, organizational values, and organizational culture.
  • The aim is just right: too little overlooks key activities, too much is costly and wasteful.
  • Three aspects can be tailored: life cycle and development approach selection, processes, and engagement; practices within performance domains can be tailored too.
  • The five verbs of process tailoring: add, modify, remove, blend, align.
  • Artifacts are chosen by the project manager and the project team according to the project’s characteristics, not copied from templates; organizational policy or the contract may limit the room for tailoring.

Lesson 2

The Four Steps of Tailoring, Influencing Factors, Approval, and Diagnostics

Lesson video

Lesson overview

The previous lesson covered what tailoring is and what can be tailored. This lesson covers how to do it: tailoring has four steps; there are several groups of questions to ask when tailoring at the project level; internal tailoring and tailoring that affects external groups can have different approval requirements; and after tailoring you need to find problems and adjust again. Most questions in this lesson ask “what is the FIRST thing to do” or “what should be done next”; hold on to the order of the steps and the principle of “analyze first, act afterward” and you can answer them. ECO: Business Environment domain, Task 6 (Continuous improvement) and Task 7 (Support organizational change).

The four steps of tailoring

Before tailoring, the project environment should be thoroughly analyzed and understood, because the environment hugely influences how projects are executed and their resulting outcomes. The tailoring process has four steps: select the initial development approach, tailor for the organization, tailor for the project, and implement ongoing improvement.

Figure 1 The four steps of tailoring and the three things to tailor

Step 1: select the initial development approach. Project teams apply their knowledge of the product, delivery cadence, and awareness of the available options to select the most appropriate development approach for the situation, such as predictive, adaptive, or hybrid. The suitability filter is a decision-making tool that helps the team’s discussion; it is not a rigid method.

Step 2: tailor for the organization. Project teams own and improve their processes, but organizations can provide methodologies and development approaches as starting points for projects requiring oversight. These guides can help support repeatable processes, consistent capability measurement, and continuous improvement. Organizations that have established process governance should ensure tailoring is aligned to policy. Tailoring for the organization involves adding, removing, and reconfiguring elements of the approach to make it more suitable for the individual organization. It should also consider the context of the program and/or portfolio within which the project operates, aligning tailoring decisions across related projects. When projects involve several organizations, use a multiorganization approach and, through integration planning, harmonize the tailored practices of each participating organization.

Step 3: tailor for the project. The key attributes that influence tailoring for the project are the product or deliverable, the project team, and culture. The project team should ask questions about each attribute; the answers can help identify the need to tailor the processes, development approach, life cycle, and tools and techniques.

Step 4: implement ongoing improvement. Tailoring is not a single, one-time exercise. During progressive elaboration, issues with how the project team is working, how the product or deliverable is evolving, and other learnings can indicate where further tailoring could bring improvements. Review points, phase gates, and retrospectives all provide opportunities to inspect and adapt the process, development approach, and delivery frequency, as necessary. Keeping the project team engaged with improving its process fosters pride of ownership and demonstrates trust in its skills and suggestions. The way an organization tailors itself can also be tailored, but most organizations still carry out some or all of the four steps.

Tailoring for the project: three groups of questions

Product or deliverable. Standards compliance: how much process rigor and quality assurance are appropriate? Type of product or deliverable: is it well known and easy to recognize, like a building, or something intangible like software or the design of a new drug? Industry market: is the market highly regulated, fast moving, or slow to evolve? Technology: is it stable and well established or rapidly evolving and at risk of obsolescence? Timeframe: weeks or months, or several years? Stability of requirements: how likely are changes to core requirements? Security: are elements of the product business confidential or classified? Incremental and iterative delivery: can the team develop and get stakeholder feedback incrementally and iteratively, refining the product through repeated cycles, or is it hard to evaluate until it is near completion?

Project team. Team size; team geography (colocated or remote); organizational distribution; team experience; access to the customer (is frequent and timely feedback practical?); team diversity.

Culture. Buy-in: is there acceptance, support, and enthusiasm for the proposed development approach? Trust: are there high levels of trust that the project team is capable of, and committed to, delivering the project outcomes? Empowerment: is the team trusted, supported, and encouraged to own and develop its working environment, agreements, and decisions? Organizational culture: do the organizational values and culture align with the project approach, including distinctions between empowering versus specifying and checking, and trusting local decision-making versus requesting external decision-making? Through the evaluation of these attributes, tailoring decisions around engagement, processes, and tools can be made for the project.

Who approves

A project management office (PMO), in organizations that have one, can play a vital role in reviewing and approving tailored development approaches so that they stay aligned with organizational policy. Tailoring that impacts only the project team requires less oversight than tailoring that impacts external groups, so project manager approval is usually enough when only the team is affected. Tailoring that affects external groups may require the approval of the PMO, which may also assist project teams as they tailor their approaches by providing ideas and solutions from other projects.

Diagnostics: when to tailor again

Periodic reviews, such as retrospectives or lessons learned, help assess the effectiveness of current approaches and identify areas for improvement through tailoring. Teams that do not use retrospectives can rely on issues, threats, quality metrics, and stakeholder feedback to determine if further tailoring is needed. Table 3-1 of the guide lists common situations and tailoring suggestions:

SituationTailoring suggestion
The deliverables are poor qualityAnalyze the root causes of poor quality and implement targeted feedback and quality assurance measures where needed; focus on process improvements rather than just increasing verification steps
Team members are unsure of how to proceed or undertake their workAssess the specific needs of the team to identify the most appropriate support mechanisms, including guidance, mentorship, training, and knowledge-sharing practices
Team members are not cooperative and are working in silosConduct team-building activities and hold individual meetings to understand the cause; take actions to strengthen bonds and promote coordination among team members
There are long delays waiting for approvalsStreamline the approval process by appointing people who are authorized to make decisions up to certain value thresholds, shortening the time needed for approvals
There is too much work in progress and/or wasteUse techniques like value stream mapping and kanban boards to visualize work, identify issues, and find solutions
Stakeholders are not engaged or they share negative feedbackAssess whether stakeholders receive timely and relevant information, tailoring communication methods to balance simplicity with the need for deeper engagement
There is a lack of transparency and understanding about project progressCheck to ensure that appropriate data is collected, analyzed, shared, and discussed during team and stakeholder meetings; validate agreement on the measures with the team and stakeholders
Issues and/or risks for which the team is unprepared continue to surface, requiring the team to react rather than make progress on their workExplore root causes to identify whether there are related gaps in project processes or activities

Scenario: the daily coordination meeting turns into a reporting meeting

A month after a company introduces the daily coordination meeting, members say that “the meetings keep getting longer and everyone is just reading out their own progress.” At the retrospective the project manager reviews this with the team and finds that the meeting has become a place to report to the project manager. The team decides to limit the meeting to fifteen minutes, synchronize quickly around current progress, today’s plan, and impediments, stop reporting person by person to the project manager, and schedule topics that need deeper discussion for after the meeting, with the effect to be checked at the retrospective two weeks later. This is diagnosing with a retrospective and then tailoring further, which is Step 4, “implement ongoing improvement.”

Worked examples

Example 1 Scenario: adopting adaptive for the first time; should the approach be reworked first?

Question 1Example

An auto parts manufacturer has more than twenty years of experience with traditional projects. Because of market changes, it will use an adaptive approach for the first time on an upcoming software project. The sponsor asks you whether the approach should first be reworked to fit the company’s situation. Under common exam practice, what should you say?

Show answer and explanation

Correct answer: A

The company has twenty years of traditional project experience and will use an adaptive approach for the first time on a software project. The sponsor asks whether the approach should first be reworked to the company’s situation. Judge this in light of the continuous improvement requirement of tailoring.

Tailoring is not a one-time exercise. For a company adopting an adaptive approach for the first time, first let the team practice the standard way and become familiar with it, then use retrospectives and review points to find the real problems and adjust on evidence. The fourth step of tailoring in PMBOK 8 is “implement ongoing improvement,” using retrospectives and similar means to inspect and adapt the process, development approach, and delivery frequency. “Use it first the standard way with few changes” is common exam practice (you still analyze the environment first and make an appropriate initial tailoring). The tempting options in this type of question are “rework first, then use” and “change it at will”; both skip the order of practice first, then inspect. The answer is A.

Why the other options are wrong

  • B. Reworking too much at once on first use, when the team is not yet familiar with the approach, makes it hard to tell whether a problem comes from the approach itself or from the rework.
  • C. Changing it at will by preference leaves the team with no stable baseline and no way to tell which practices work.
  • D. Tailoring is continuous and should use retrospectives and review points to keep checking. Waiting until closing to evaluate is too late.

Key takeaway In common exam practice, when adopting a new approach for the first time, first practice the standard way to get familiar, then keep adjusting on real problems (PMBOK 8 requires an appropriate initial tailoring first).

Variation If the team already had mature experience with the approach, it could be adjusted to the project’s characteristics already in Step 3, tailor for the project. On first use, large changes are not advisable.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: before being asked to introduce agile practices

Question 2Example

A project manager has always used predictive approaches and is currently managing several plant production-line upgrade projects at the same time. Senior leaders are strongly encouraging teams to incorporate more agile practices into their current ways of working, and the sponsor also wants these projects to use more agile. Before requiring any project to adopt agile practices, what should the project manager do FIRST?

Show answer and explanation

Correct answer: C

A project manager who has always used predictive approaches manages several production-line upgrade projects, and senior leaders and the sponsor want more agile practices. You must decide what to do first before requiring projects to adopt agile practices.

Before tailoring, first analyze and understand the project environment thoroughly. Tailoring for the project means evaluating three groups of attributes: the product or deliverable, the project team, and culture. Before requiring projects to adopt agile practices, the first thing is to examine the organization’s culture and the team’s readiness for change, such as buy-in, trust, and empowerment, to judge whether the introduction is feasible and how risky it is, and only then decide how to tailor and whether to train. The answer is C.

Why the other options are wrong

  • A. Training comes after it has been confirmed that the change will be made; it is not the first thing to do.
  • B. Switching everything at once to agile with strict timeboxes is too aggressive; it does not assess suitability first and creates substantial risk.
  • D. Stopping all projects causes loss and does not answer whether the change is suitable.

Key takeaway Whether to introduce a new practice: first analyze the organization’s culture and its readiness for change, then train and implement.

Variation If the stem asked “after the assessment confirms feasibility, what is next,” the answer would be training and a pilot. If it asked how to diagnose whether an adopted practice is effective, the answer is retrospectives and measures.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The order of the four steps is: select the initial approach, tailor for the organization, tailor for the project, improve continuously. It is not tailor the processes first and select the approach afterward.
  • PMBOK 8 requires thoroughly analyzing and understanding the project environment before tailoring, and then going through the four steps of selecting the initial approach, tailoring for the organization, tailoring for the project, and implementing ongoing improvement. This applies equally when a new approach is used for the first time: make an appropriate initial tailoring first, and keep testing and adjusting during implementation through retrospectives and similar means.
  • Common exam practice: when using an approach for the first time, change as little as possible, first practice the standard way to get familiar, and then adjust based on real problems; if you make big changes from the start and something goes wrong, you cannot tell whether the cause is the approach itself or your modifications.
  • Whether to introduce a new practice: first analyze the organization’s culture and its readiness for change, then train and implement; do not roll it out directly.
  • Ongoing improvement is the fourth step, not an optional extra after tailoring is complete; waiting until project closing to evaluate is too late.

Key takeaways

Key point

  • Four steps: select the initial development approach → tailor for the organization → tailor for the project → implement ongoing improvement.
  • Tailoring for the project looks at three groups of attributes: product or deliverable, project team, and culture.
  • Tailoring that affects only the project team is usually approved by the project manager; tailoring that affects external groups may need PMO approval.
  • Diagnose through retrospectives, lessons learned meetings, or issues, threats, quality metrics, and stakeholder feedback; Table 3-1 gives common situations and suggestions.
  • Before tailoring, thoroughly analyze the project environment, and verify that the adjusted approach is effective.

This chapter has 11 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.