Life Cycles and Development Approaches

Focus Areas and Performance Domains

PMP · Life Cycles and Development Approaches · 2 lessons · about 25 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The knowledge structure of PMBOK 8 has two lines. Horizontally there are the five Project Management Focus Areas (Initiating, Planning, Executing, Monitoring and Controlling, and Closing), which say what kind of action a project management activity is. Vertically there are the seven project management performance domains (Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk), which say which aspects of the project must be managed well. The two lines intersect to give 40 processes. This chapter first explains the five kinds of action and the seven aspects separately, then how to read the mapping table, and finally summarizes how the structure of PMBOK 8 differs from the Seventh Edition: the principles were refined from 12 to 6, the process groups were repositioned as Focus Areas, and the old knowledge areas were integrated into the performance domains.

By the end of this chapter you should be able to do the following. State the purpose of each of the five Focus Areas and be clear that they are not project phases. List the seven performance domains and know that quality no longer has its own performance domain (deliverable verification belongs to Scope, Manage Quality Assurance belongs to Governance) and that communication is merged into Stakeholders. Decide which Focus Area a piece of work belongs to. Name the processes of the Risk and other performance domains in each Focus Area. State the column distribution of Initiating 2, Planning 19, Executing 8, Monitoring and Controlling 10, and Closing 1. And distinguish PMBOK 8 wording from that of the Seventh Edition.

Lessons in this chapter

Chapter map

ItemKey pointsIn one sentence
Five Focus AreasInitiating, Planning, Executing, Monitoring and Controlling, ClosingA classification of actions, not phases
Seven performance domainsGovernance, Scope (including quality), Schedule, Finance, Stakeholders, Resources, RiskSeven aspects that run concurrently
Mapping tableInitiating 2, Planning 19, Executing 8, Monitoring and Controlling 10, Closing 140 non-prescriptive processes in all
Structural changes12 principles → 6; process groups → Focus Areas; knowledge areas → performance domainsThe skeleton is still principles plus performance domains

Study tips and practice

  • Memorize the mapping table by performance domain, and for each process remember its “type of action” (planning, carrying out, monitoring). Then go back to the five Focus Areas and ask yourself which kind the action belongs to. Use this together with the other topics: whenever you learn a process, also say which performance domain and which Focus Area it belongs to.

Lesson 1

The Five Focus Areas and the Seven Performance Domains

Lesson video

Lesson overview

The knowledge structure of PMBOK 8 has two lines. One is the five Project Management Focus Areas: Initiating, Planning, Executing, Monitoring and Controlling, and Closing, which say what kind of action a project management activity is. The other is the seven project management performance domains: Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk, which say which aspects of the project must be managed well. The two lines intersect to give 40 processes. This lesson first explains the five kinds of action and the seven aspects separately; the next lesson covers how they correspond and how the PMBOK 8 structure differs from that of the Seventh Edition. Questions usually ask “which Focus Area does this piece of work belong to” and “which one is a performance domain.” The content of this lesson gives an overall framework for understanding the tasks of the ECO Process domain; the Planning Focus Area and cross-domain integration connect most directly to Task 1 (Develop an integrated project management plan and plan delivery).

The five Focus Areas

The Standard states that the fundamental actions that take place over the course of any project, regardless of whether the project follows a predictive, adaptive, or hybrid approach, are grouped into five Project Management Focus Areas: Initiating, Planning, Executing, Monitoring and Controlling, and Closing. These Focus Areas are implemented using formal processes, informal practices, or other policies, procedures, or techniques. The areas can involve iterative, continuous, and/or overlapping actions that are performed when planned or needed during the project and/or in each phase of the project.

Their predecessors were the five process groups. Historically, these five areas were seen as logical groupings of formal project management processes; today’s projects often reach the same goals through multiple approaches and are managed through informal practices and flexible policies as well as formal processes, so the old process groups were recast as Focus Areas. The point of the rename is that you should not associate these five words only with predictive projects.

  • Initiating. The processes, practices, or actions performed to define a new project or new phase of an existing project. This often includes formal authorization to start the project or phase. Its purpose is to align the stakeholders’ expectations and the project’s purpose; among the initiating actions, the initial scope is defined and initial financial resources are committed, stakeholders who will interact with and influence the overall outcome are identified, and project management roles are assigned. This information is often captured in artifacts such as a project charter or stakeholder register.
  • Planning. The processes, practices, or actions that establish the intended scope of the effort, define and refine the objectives, and develop the course of action required to attain those objectives. They may involve artifacts such as a product backlog or a project management plan. Planning can follow a progressive, iterative, or rolling wave approach: highly predictive approaches tend to front-load their planning, whereas highly iterative approaches tend to perform some brief, high-level planning up front, sometimes called “roadmapping,” followed by frequent planning and replanning throughout the project life cycle.
  • Executing. The processes, practices, or actions performed to complete the work in a manner consistent with the currently agreed-upon course of action. They include coordinating resources, managing stakeholder engagement, and performing the activities of the project, as well as other project tasks. This Focus Area is also where the choice of development approach (adaptive, predictive, or hybrid) is often most evident.
  • Monitoring and Controlling. The actions required to track, measure, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes. Monitoring can include comparing project performance data, producing performance measures, and reporting and disseminating performance information; controlling can include analyzing variances, assessing trends, evaluating possible alternatives, and recommending appropriate course corrections. It is performed in parallel with the other Focus Areas and is not a separate, stand-alone area.
  • Closing. The actions performed to formally complete or close a project, phase, or contract, or in some cases to terminate a project before completion. This includes verifying the achievement of project outputs, outcomes, and benefits and transitioning to operations in a manner that helps meet or exceed the project’s target business objectives, and it may also address the suspension or early closure of the project.

These five areas are independent of the application area, the industry, and the development approach. Remember especially that Focus Areas are not project phases. If the project is divided into phases, the actions in the Focus Areas interact within each phase; the five Focus Areas are not strictly sequential, and they often overlap within a single phase. For example, planning and monitoring can happen simultaneously. In adaptive approaches, the five areas interact in a flexibly overlapping way within short iterations and need to be revisited and refined regularly.

The seven performance domains

Performance domains run concurrently throughout the project life cycle, regardless of how value is delivered (frequently, periodically, or at the end of the project). Performance domains represent the mechanics of project management, including the knowledge, processes, and methods that are essential for effective project delivery. They are broad areas of focus in which to demonstrate the mindset and behavior guided by the project management principles. PMBOK 8 presents seven performance domains (in no particular weight or order): Governance, Scope (including quality), Schedule, Finance, Stakeholders, Resources, and Risk. Together they form an integrated system that runs concurrently throughout the life cycle.

Each can be summed up in a sentence. Governance keeps the project aligned with organizational strategy and objectives and gives decisions a clear basis. Scope defines clearly what is to be done and to what extent, with quality requirements included. Schedule manages time. Finance manages money, looking beyond cost to benefits and value. Stakeholders identifies and engages them and also includes communication. Resources builds the team and manages physical resources. Risk deals with uncertainty.

Each performance domain is presented with five primary subsections: Key Concepts, Processes, Tailoring Considerations, Interactions With Other Domains, and Check Results. The processes are the study focus, and each lists a sampling of inputs, tools and techniques, and outputs, but these lists are illustrative and not comprehensive. “Check Results” stresses an outcome orientation: project management activities do not provide value by themselves, and the purpose of a schedule is, for example, to give stakeholders a shared understanding of the overall timeline for delivering value.

Keep Focus Areas and performance domains distinct from principles as well. The project management principles guide mindset and behavior, while the performance domains represent the mechanics of project management that put that mindset into practice. PMBOK 8 has six principles. While all the principles relate to all performance domains, some are connected more strongly than others: for instance, the Adopt a Holistic View principle is supported by all performance domains, and the principles on integrating sustainability into all project areas and building an empowered culture apply to all domains.

Scenario: a retrospective of a stadium renovation project

The project manager uses the five Focus Areas to sort the work done. Authorization before the start and identifying the venue operator and the neighbors are Initiating; drawing up the construction plan is Planning; bringing the crews on site and building as planned is Executing; comparing actual progress with the plan every week and dealing with deviations is Monitoring and Controlling, and it happens at the same time as construction; handing over after acceptance and verifying benefits is Closing. Then the seven performance domains: who approves changes is Governance, how far the venue must be completed is Scope, the construction period is Schedule, the budget and benefits are Finance, neighbors’ complaints and communication with the operator are Stakeholders, the crews and equipment are Resources, and the uncertainty of building during typhoon season is Risk. The same event can be viewed along two lines: “what type of action is it” and “which aspect does it manage.”

Worked examples

Example 1 Concept question: which item belongs to the Executing Focus Area

Question 1Example

At a retrospective, a project manager reviews the work done against the PMBOK 8 mapping table. Which of the following belongs to the Executing Focus Area?

Show answer and explanation

Correct answer: B

The project manager reviews the work against the PMBOK 8 mapping table and must decide which item belongs to the Executing Focus Area.

According to the PMBOK 8 mapping table, Manage Communications belongs to the Stakeholders performance domain and falls in the Executing Focus Area. Of the other three, Estimate Costs is in the Planning Focus Area, Validate Scope is in the Monitoring and Controlling Focus Area, and Identify Stakeholders is in the Initiating Focus Area. To judge which Focus Area something belongs to, look at the action itself: is it initiating, planning, executing, or checking? It helps to memorize the mapping table by performance domain: the Stakeholders performance domain has processes in four Focus Areas, Initiating, Planning, Executing, and Monitoring and Controlling. The answer is B.

Why the other options are wrong

  • A. Estimate Costs belongs to the Planning Focus Area of the Finance performance domain; it is the estimating work done when planning finances.
  • C. Validate Scope belongs to the Monitoring and Controlling Focus Area of the Scope performance domain; it is the formal acceptance of completed deliverables.
  • D. Identify Stakeholders belongs to the Initiating Focus Area of the Stakeholders performance domain; the process is performed periodically throughout the project as needed.

Key takeaway Manage Communications and Manage Stakeholder Engagement are in Executing, Identify Stakeholders is in Initiating, estimating is in Planning, and Validate Scope is in Monitoring and Controlling.

Variation If the question asked which Focus Area Monitor Communications belongs to, the answer would be Monitoring and Controlling; for Plan Communications Management, the answer would be Planning.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: should quality be a separate performance domain

Question 2Example

A project manager is writing internal training material on the PMBOK 8 framework. A colleague suggests listing “quality” as a separate performance domain alongside the other performance domains. How should the project manager respond?

Show answer and explanation

Correct answer: B

A colleague suggests making “quality” a separate performance domain alongside the others. You must know how the seven PMBOK 8 performance domains are made up and decide where quality belongs.

PMBOK 8 has seven performance domains: Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk. Quality is not among them. Quality has not been listed on its own: deliverable quality and verification belong to the Scope performance domain, handled through Monitor and Control Scope and Validate Scope to make sure deliverables meet requirements, standards, and specifications; Manage Quality Assurance (process quality assurance) belongs to the Governance performance domain. The colleague’s proposal does not match the PMBOK 8 structure, and the project manager should point out that PMBOK 8 has no quality performance domain and explain where the quality content sits. A memory aid: you will not find a separate “quality” among the seven performance domains; deliverable quality is under Scope and process quality assurance is under Governance. The answer is B.

Why the other options are wrong

  • A. Treating quality as an eighth, independent performance domain does not match the seven performance domains of PMBOK 8.
  • C. Quality was not folded into the Governance performance domain as a whole: only Manage Quality Assurance belongs to Governance, while deliverable quality and verification still belong to the Scope performance domain (Monitor and Control Scope, Validate Scope).
  • D. PMBOK 8 does not merge quality with risk; the Risk performance domain has its own content.

Key takeaway The seven performance domains are Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk; there is no quality performance domain, deliverable quality and verification belong to Scope, and Manage Quality Assurance belongs to Governance.

Variation If asked “which performance domain does communication belong to,” the answer is Stakeholders. For “procurement,” it is placed in an appendix as additional content and is not a separate performance domain.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Treating Focus Areas as phases is the most common mistake. Initiating is not “the first stretch of the project,” and Planning is not something that must be finished before Executing.
  • Monitoring and Controlling is not something done only before closing; it runs throughout and in parallel with the other areas.
  • Exam questions often say “the project is in the execution phase,” “the planning phase” or “the closing phase.” That is common exam practice for “the project is being executed, planned or closed,” which maps to the matching Focus Area, not to a life-cycle phase. Answer from the scenario; don’t get stuck on the label.
  • The names of the five areas are the same as the former five process groups, and neither is a sequence of project phases to be completed one after another. PMBOK 8 recasts them as Focus Areas, a classification of actions that covers formal processes, informal practices, and flexible policies and procedures.
  • There are seven performance domains. Quality has no separate performance domain, and it has not been deleted either: deliverable quality and its verification sit in the Scope performance domain, and process quality assurance (the Manage Quality Assurance process) sits in the Governance performance domain; communication sits in the Stakeholders performance domain.

Key takeaways

Key point

  • Five Focus Areas: Initiating, Planning, Executing, Monitoring and Controlling, Closing; they are the process groups recast and are implemented through formal processes, informal practices, or policies.
  • Focus Areas are not project phases and are not strictly sequential; they often overlap within a phase, and Monitoring and Controlling runs in parallel with the others.
  • Seven performance domains: Governance, Scope (including quality), Schedule, Finance, Stakeholders, Resources, Risk; in no particular weight or order, they run concurrently throughout the life cycle.
  • Each performance domain has five subsections: Key Concepts, Processes, Tailoring Considerations, Interactions With Other Domains, Check Results.
  • Inputs, tools and techniques, and outputs are examples only; project management activities do not by themselves provide value, so results are what you check.

Lesson 2

Mapping Focus Areas to Performance Domains, and How the PMBOK 8 Structure Changed

Lesson video

Lesson overview

The seven performance domains are seven aspects running vertically, and the five Focus Areas are five kinds of action running horizontally. Where they intersect they form a table, and what sits in the cells are the 40 processes of PMBOK 8. This table is the table of contents for every later topic: when you study any process, you should know which performance domain it belongs to and which Focus Area it falls in. This lesson first explains how to read the table, then covers what changed in the structure of PMBOK 8 compared with the two previous editions, so you can recognize old and new wording on the exam. This lesson provides the structural foundation for understanding the tasks of the ECO Process domain.

The mapping table

The table below is the PMBOK 8 guide table “Mapping Project Management Focus Areas to Performance Domains”: the seven performance domains (rows) intersect with the five Focus Areas (columns), and each cell lists that domain’s processes in that Focus Area.

Figure 1 Number of processes by performance domain and Focus Area
Performance domain \ Focus AreaInitiatingPlanningExecutingMonitoring and ControllingClosing
GovernanceInitiate Project or PhaseIntegrate and Align Project Plans; Plan Sourcing StrategyManage Project Execution; Manage Quality Assurance; Manage Project KnowledgeMonitor and Control Project Performance; Assess and Implement ChangesClose Project or Phase
ScopePlan Scope Management; Elicit and Analyze Requirements; Define Scope; Develop Scope StructureMonitor and Control Scope; Validate Scope
SchedulePlan Schedule Management; Develop ScheduleMonitor and Control Schedule
FinancePlan Financial Management; Estimate Costs; Develop BudgetMonitor and Control Finances
StakeholdersIdentify StakeholdersPlan Stakeholder Engagement; Plan Communications ManagementManage Stakeholder Engagement; Manage CommunicationsMonitor Stakeholder Engagement; Monitor Communications
ResourcesPlan Resource Management; Estimate ResourcesAcquire Resources; Lead the TeamMonitor and Control Resourcing
RiskPlan Risk Management; Identify Risks; Perform Risk Analysis; Plan Risk ResponsesImplement Risk ResponsesMonitor Risks

How to read this table

Count by column: Initiating 2, Planning 19, Executing 8, Monitoring and Controlling 10, Closing 1, for a total of 40. Planning has the most, and Closing has only one, Close Project or Phase. A few patterns help you remember it.

First, the processes of one performance domain are spread across different Focus Areas, and the processes of one Focus Area belong to different performance domains, so do not map performance domains and Focus Areas one to one. Second, in the Planning Focus Area almost every performance domain has a “Plan … Management” process or a corresponding planning process; in the Monitoring and Controlling Focus Area almost every performance domain has a “Monitor and Control …” or “Monitor …” process, with Scope having one extra, Validate Scope, Governance having one extra, Assess and Implement Changes, and Stakeholders having two, Monitor Stakeholder Engagement and Monitor Communications. Third, only Governance has a process in the Closing Focus Area, and only Governance has three processes in the Executing Focus Area. Fourth, the Scope, Schedule, and Finance performance domains have no process named for themselves in the Executing Focus Area; execution of the related plans generally proceeds through processes such as Manage Project Execution and is tracked and regulated by the corresponding monitoring and controlling processes. Fifth, Governance covers all five Focus Areas and Stakeholders covers the first four.

The Risk performance domain is a good example: the Planning Focus Area has four processes, Plan Risk Management, Identify Risks, Perform Risk Analysis, and Plan Risk Responses; the Executing Focus Area has Implement Risk Responses; and the Monitoring and Controlling Focus Area has Monitor Risks. Pay particular attention to the positions that are easy to misplace: Estimate Costs is in Planning, Identify Stakeholders is in Initiating, Manage Communications and Manage Stakeholder Engagement are in Executing, and Validate Scope and Monitor and Control Scope are both in Monitoring and Controlling.

The inputs, tools and techniques, and outputs listed for each process are examples only; the 40 processes are also non-prescriptive, and when tailoring a project you can use them as a reference as needed.

Scenario: a few events in a logistics park build

The client’s representative inspects the completed roadbed work and formally accepts this batch of deliverables: this is Validate Scope, in the Monitoring and Controlling Focus Area of the Scope performance domain. After the crews arrive on site, the project manager coaches the new crew leaders on the job: this is Lead the Team, in the Executing Focus Area of the Resources performance domain. The project manager prepares the park construction budget: this is Develop Budget, in the Planning Focus Area of the Finance performance domain. The project team carries out the pre-agreed drainage plan for an identified heavy-rain risk: this is Implement Risk Responses, in the Executing Focus Area of the Risk performance domain; and checking every week whether the plan is still effective and whether new risks have appeared is Monitor Risks, in the Monitoring and Controlling Focus Area. In questions, focus on the action itself: is it planning, carrying out, or checking?

How the PMBOK 8 structure changed

The preface of PMBOK 8 sums up the changes in four categories: key term and concept updates, principle refinement, reintroduction of Process Groups as Focus Areas, and project management performance domain updates.

ItemChange
PrinciplesThe 12 principles of the Seventh Edition are refined into 6 that are more actionable, further consolidated to reduce overlap, repetition, and confusion
Performance domainsUpdated to 7, incorporating and integrating concepts from earlier editions
Knowledge areasNo longer a separate structure; integrated with other concepts into the seven performance domains
Process groupsRepositioned as the five Focus Areas
Processes40 selected non-prescriptive processes, embedded in the performance domains, with tailoring considerations and examples
Inputs and outputs, tools and techniquesReturned to the guide, as examples only

You can understand the evolution this way. The Fifth and Sixth Editions were process-oriented and were organized around five process groups and ten knowledge areas. The Seventh Edition turned to a principles-based standard, with 12 principles and eight performance domains, shifting the focus from processes to outcomes, but the familiar processes, inputs, and outputs suddenly disappeared. The Eighth Edition seeks a balance between the two: it keeps the skeleton of principles plus performance domains, refines the principles, and brings processes, inputs and outputs, and tools and techniques back, embedded in the performance domains.

The old knowledge areas map to the new performance domains roughly as follows. Integration goes into Governance (the Governance performance domain includes elements of project integration management related to strategic alignment, decision-making and change, and project success criteria). Cost becomes Finance. Quality no longer has its own area, and quality activities are dispersed: deliverable quality and verification are in the Scope performance domain (Monitor and Control Scope, Validate Scope), and process quality assurance is in the Governance performance domain (the Manage Quality Assurance process). Communications merges with Stakeholders. Resources, Schedule, and Risk keep their names. Procurement is no longer a separate performance domain and is placed in an appendix as additional content.

Common trap

  • PMBOK 8 is not a return to the Sixth Edition. The evolution runs from the Sixth to the Seventh to the Eighth; the skeleton is still principles plus performance domains, with processes brought back.
  • Twelve principles, eight performance domains, and knowledge areas are the language of the Seventh Edition or earlier; PMBOK 8 has 6 principles, 7 performance domains, 5 Focus Areas, and 40 processes.
  • The 40 processes are a non-prescriptive, tailorable reference; the process groups were not deleted but repositioned as Focus Areas.

Worked examples

Example 1 Concept question: what does the Risk performance domain do in the Executing Focus Area

Question 1Example

An airport baggage system upgrade project is carrying out executing work. The risk manager checks the PMBOK 8 mapping table for the work assigned to the Risk performance domain in the Executing Focus Area. Which of the following is a process at that intersection?

Show answer and explanation

Correct answer: B

The baggage system upgrade is carrying out executing work, and the risk manager checks the mapping table for the work assigned to the Risk performance domain in the Executing Focus Area. You must identify the process at that intersection.

Consult the mapping table: the Risk performance domain has four processes in the Planning Focus Area, Plan Risk Management, Identify Risks, Perform Risk Analysis, and Plan Risk Responses; in the Executing Focus Area it has only Implement Risk Responses; and in the Monitoring and Controlling Focus Area it has Monitor Risks. For the executing-classified work asked about here, the corresponding process is Implement Risk Responses. The answer is B.

Why the other options are wrong

  • A. Identify Risks is placed in the Planning Focus Area in the PMBOK 8 mapping table, although risk identification continues throughout the project and new risks must still be identified and the register updated during execution; this question classifies by the mapping table, and the Executing Focus Area corresponds to Implement Risk Responses.
  • C. Monitor Risks belongs to the Monitoring and Controlling Focus Area, which runs in parallel with executing, but it falls in a different column of the mapping table.
  • D. Plan Risk Responses is placed in the Planning Focus Area in the mapping table; when new risks are identified during the project, new responses can also be planned iteratively.

Key takeaway The Risk performance domain: in Planning it identifies, analyzes, and plans responses; in Executing it implements responses; in Monitoring and Controlling it monitors risks.

Variation If the question asked about the Governance performance domain’s processes in the Executing Focus Area, the answer would be Manage Project Execution, Manage Quality Assurance, and Manage Project Knowledge. The Scope, Schedule, and Finance performance domains have no processes in the Executing Focus Area.

Something wrong with this question?

Report an issue with this question

Example 2 Concept question: structural differences between PMBOK 8 and the Seventh Edition

Question 2Example

A colleague who has just passed the exam for the previous edition is comparing the structure of PMBOK 8 with that of the Seventh Edition and lists several judgments. According to the PMBOK 8 preface, which judgment is correct?

Show answer and explanation

Correct answer: A

A colleague is comparing the structure of PMBOK 8 with that of the Seventh Edition and lists several judgments. The question asks which judgment is correct according to the PMBOK 8 preface.

The preface of PMBOK 8 explains that the principles were refined from the 12 of the Seventh Edition to 6, more actionable and with less overlap; the process groups were repositioned as five Focus Areas; and the knowledge areas were integrated with other concepts into the seven performance domains. Checking item by item, only “condensed from 12 to 6 and made more actionable” is correct. For “which judgment is correct” questions, break each option into the four objects, principles, performance domains, knowledge areas, and process groups, and check them one by one. The answer is A.

Why the other options are wrong

  • B. The number of principles changed, from 12 merged into 6; it was not just a matter of reordering.
  • C. The process groups were not kept under their original names as a parallel structure; they were repositioned as Focus Areas.
  • D. The knowledge areas have been integrated into the performance domains and no longer continue as a separate parallel structure.

Key takeaway 12 principles were refined to 6, the process groups were repositioned as Focus Areas, and the knowledge areas were merged into the performance domains.

Variation If asked how many processes PMBOK 8 has, the answer is 40 non-prescriptive processes. If asked how many performance domains, the answer is 7, whereas the Seventh Edition had 8.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The processes of one performance domain are spread across different Focus Areas; do not map the two one to one.
  • Estimate Costs is in Planning, not Executing; Validate Scope is in Monitoring and Controlling, not Closing; Identify Stakeholders is in Initiating, not Planning.
  • In the Executing Focus Area the Risk performance domain has only Implement Risk Responses; Plan Risk Responses maps to the Planning Focus Area, not the Executing Focus Area.

Key takeaways

Key point

  • Each cell of the mapping table holds the processes of a performance domain in a Focus Area, 40 in total: Initiating 2, Planning 19, Executing 8, Monitoring and Controlling 10, Closing 1.
  • The Risk performance domain: in Planning, Plan Risk Management, Identify Risks, Perform Risk Analysis, and Plan Risk Responses; in Executing, Implement Risk Responses; in Monitoring and Controlling, Monitor Risks.
  • Validate Scope and Monitor and Control Scope are both in Monitoring and Controlling; Estimate Costs is in Planning; Identify Stakeholders is in Initiating.
  • PMBOK 8 versus the Seventh Edition: 12 principles refined to 6; performance domains updated to 7; the old knowledge areas integrated into the performance domains; process groups repositioned as Focus Areas; 40 non-prescriptive processes selected.
  • Quality has no separate performance domain: deliverable verification goes to Scope and Manage Quality Assurance goes to Governance; communications merges into Stakeholders; integration corresponds to Governance; procurement goes into an appendix.

This chapter has 8 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.