Business Environment domain · Task 5

Plan and manage risk

"Plan and manage risk" is task 5 of the Business Environment domain in the PMP exam content outline. The Business Environment domain makes up 26% of the exam, and the outline does not publish a question count for each task. The task covers the whole risk cycle: plan, identify, analyze, respond, monitor. Scenario questions often ask "what do you do next": a newly found risk is recorded in the risk register and analyzed, a risk that has occurred moves to issue handling, and you work according to the risk management plan.

What the outline asks for (enablers)

The outline lists 7 enablers for this task. The table maps each one to the chapters of this study guide.

EnablerWhat you need to knowChapter
Identify risks.Risk identification is iterative; data gathering techniques; the standard handling of a newly found risk; threats and opportunitiesRisk Register
Analyze risks.Qualitative analysis (probability and impact, prioritization); quantitative analysis (expected monetary value, simulation); decision treesQualitative Risk Analysis, Quantitative Risk Analysis
Monitor and control risks.Technical performance analysis, reserve analysis, risk audits; risk reviews and the watch listMonitor Risks
Develop a risk management plan.Contents of the risk management plan; risk appetite, thresholds and tolerance; project resilience and tailoringRisk Management Plan
Maintain a risk register (e.g., poor IT security).Contents of the risk register and the risk report; update them as risk status changesRisk Register
Execute a risk management plan (e.g., risk response for security and managing sustainability risks).Risk response strategies (threats and opportunities); implementing risk responses so the actions really happen; sustainability risks (they arise when societal, economic and environmental considerations are not balanced)Risk Response Strategies, Monitor Risks, Sustainability
Communicate the status of a risk impact on the project.The risk report; telling the sponsor and stakeholders the state of risks and response progressRisk Register, Monitor Risks

How to read risk scenario questions

  1. New risk: record it, analyze it, then decide the response. Do not jump straight to a response and do not ignore it. Identify, record, assess probability and impact, then choose a response under the risk management plan.
  2. Once it has happened, it is no longer a risk. A risk that has occurred moves to the issue log and is handled by the agreed response plan, drawing on the matching reserve.
  3. Work according to the risk management plan. Roles, methods, thresholds and report formats come from the plan. Check it before you act.
  4. Identified risks draw on contingency reserve, unidentified surprises on management reserve. Using management reserve goes through change control.
  5. Deal first with the risks that most affect objectives. Qualitative analysis ranks them for attention, and quantitative analysis supports decisions on high-impact risks.
  6. Risk is managed iteratively. Risks change as the project moves, so keep identifying, reassessing and updating the register at reviews, and communicate the status to stakeholders.

Rule 5 is common exam practice. The others follow the study guide and PMBOK 8.

Predictive versus agile and hybrid environments

PredictiveAgile and hybrid
Review rhythmRisk review meetings at the frequency set in the risk management plan, often folded into the regular status meetingRisks assessed at the start of each iteration and reviewed with stakeholders at the end; risks are made visible on an information radiator (for example a risk board); the retrospective and the daily coordination meeting are not the main places for risk review
Where risks liveThe risk register and risk reportIn the backlog, and they can feed iteration planning
ResponsePlanned in advance under the risk management plan, with contingency reserveShort experiments and incremental delivery reduce uncertainty; expose early and adjust early

Task quiz

These free questions come from the chapters linked to this task and cover as many chapters as possible. Pick an answer first, then open the explanation to see why the right option is right and why the others are wrong. For more, practice by chapter in the question bank.

Question 1Free

PMLyceum’s in-vehicle software project is at mid-execution. Looking through the risk register, the project manager finds that every score entered by the risk owners is “low”, and no new risk has been added in three months, yet more and more technical obstacles are surfacing at the phase-gate review. The team seems to be avoiding reporting bad news. What should the project manager do?

Show answer and explanation

Correct answer: C

The in-vehicle software project is at mid-execution. Every score in the risk register is “low” and no new risk has appeared in three months, while more and more technical obstacles appear at the phase-gate review. The team seems to be avoiding bad news. The question asks what the project manager should do.

A register that stays all “low” while real problems grow means the owners are not reporting honestly. The Eighth Edition notes that an accountable leader, with integrity, honesty and fairness as values, shows honesty by passing on bad news early and making sure status reports reflect the real progress of the project. The project manager should build a culture in which risks can be reported candidly and members know that exposing a risk will not bring blame; only then will the risk information be true. The answer is C.

Why the other options are wrong

  • A. Assessing all the risks alone bypasses the owners who know the situation best. The information stays distorted, and it also goes against the practice that risk management needs the team’s participation.
  • B. Fewer reports and risk meetings make risks surface even later, and the team’s tendency to avoid reporting does not change in any way.
  • D. Raising every score uniformly rests on no facts. The data is still distorted, and it does nothing about why members dare not report honestly.

Key takeaway When risk information is distorted, the root cause is culture: create an environment where people dare to report candidly, rather than scoring for them.

Variation If the risk scores are honest but the response is inadequate, improve the risk response plan, not the culture.

Reference Project Management Principles · Lesson 2: Embed Quality Into Processes and Deliverables; Be an Accountable Leader

Something wrong with this question?

Report an issue with this question

Question 2Free

A project manager takes over an overseas data-center deployment project. At the first meeting with the team, a subject matter expert worries that sudden late arrival of key servers would stop the project from finishing on time. Which document should the project manager consult FIRST to confirm stakeholders' tolerance for schedule impact?

Show answer and explanation

Correct answer: B

A project manager takes over an overseas data-center deployment project, and at the first meeting a subject matter expert worries about a sudden late arrival of key servers. The question asks which document to consult first to confirm stakeholders' tolerance for schedule impact.

The stem's “tolerance for schedule impact” is everyday wording for how much schedule variation stakeholders accept; in PMBOK 8 that is expressed as the risk appetite and the measurable risk threshold. PMBOK 8 defines risk appetite as “the degree of uncertainty an organization or individual is willing to accept in anticipation of a reward,” and the risk threshold as the measure of acceptable variation around an objective. Both are recorded in the risk management plan, written as measurable thresholds around each project objective. So the risk management plan is consulted first. The answer is B.

Why the other options are wrong

  • A. The communications management plan sets how and to whom to communicate; it does not record stakeholders' tolerance for schedule deviation.
  • C. The project schedule gives the timing and does not say how large a delay stakeholders can tolerate, so it cannot answer “how serious is the impact”.
  • D. The risk register records identified specific risks and their responses; it is a product of risk management and does not record tolerance. Tolerance is taken from the risk management plan.

Key takeaway To know how much deviation stakeholders can tolerate, check the risk management plan.

Variation If the question asked where to record this late-arrival risk the expert is worried about, the answer is the risk register, with its probability and impact assessed using the definitions in the risk management plan.

Reference Risk Management Plan · Lesson 1: Risk, Issues and Risk Appetite

Something wrong with this question?

Report an issue with this question

Question 3Free

A central-kitchen expansion project for a restaurant chain has entered execution. The logistics supervisor, as a stakeholder, raises a new risk that had not been identified before: vehicle scheduling by the new cold-chain supplier may affect the timeliness of raw-material delivery. What should the project manager do?

Show answer and explanation

Correct answer: B

A central-kitchen expansion project is in execution. The logistics supervisor, a stakeholder, raises a risk not identified before: vehicle scheduling by the new cold-chain supplier may affect the timeliness of raw-material delivery. The question asks what the project manager should do.

Identifying risks is not done just once; it is an iterative process that runs throughout the project, and as information grows it is normal for new risks to appear during execution. On receiving a new risk, the project manager should first record it in the risk register so it is not lost, and then, following the process in the risk management plan, assess its probability, impact and priority together with the project team and relevant stakeholders. That way nothing goes unrecorded and the assessment has a full perspective. The risk has not yet been analyzed and there is no evidence that it exceeds the project manager's authority, so there is no need to rush to escalate. The answer is B.

Why the other options are wrong

  • A. Confirming the register is complete and asking everyone to verify it is rechecking old content and does nothing about the newly found risk, besides implying that risk identification is not iterative.
  • C. Analyzing only with the person who raised it gives a single viewpoint and may miss other risks and effects. Risk analysis and assessment should involve the project team and relevant stakeholders.
  • D. The risk has not been analyzed, and whether it exceeds authority is unknown. Identifying, analyzing and planning responses are within the project manager's responsibility, and escalation to senior management is needed only when the risk is outside the project scope or beyond the project manager's authority.

Key takeaway Record a new risk in the risk register first, then assess it with the team and relevant stakeholders; do not rush to escalate.

Variation If the stem were changed to “the supplier notified us yesterday that it cannot supply”, the event has happened and is an issue, to be recorded in the issue log and acted on immediately.

Something wrong with this question?

Report an issue with this question

Question 4Free

A project manager is leading a new-energy battery development project. Team members have identified the sources of various risks and built a risk register. The project manager wants to concentrate effort on the high-priority risks. What should be done next?

Show answer and explanation

Correct answer: C

Risks have been identified and entered in the register, so the project is at the analysis stage of risk management. The project manager wants to focus limited effort on the high-priority risks, and you must decide what to do “next”.

The deciding signal is “concentrate on the high-priority risks”. To know which risks are high priority, you must first rank each one. The qualitative part of Perform Risk Analysis assesses the probability and impact of each individual risk and uses the probability and impact matrix to set priorities, so that the team can focus on the high-priority risks. It is also the natural next step after identification. In practice, qualitative analysis is usually used first to decide the focus, and quantitative analysis then digs deeper, as needed, into the key risks and overall risk. Decision tree analysis is itself one of the quantitative techniques, and none of these is the first thing to do now. The answer is C.

Why the other options are wrong

  • A. The sources of risk have been identified and the register is built, so identification is already done. Identification also only finds and records risks; it cannot put them in order.
  • B. Quantitative risk analysis primarily examines the combined effect of risks and uncertainty on overall project objectives and expresses the result numerically. It does not rank individual risks by probability and impact (although sensitivity analysis can show which risks have the greatest potential effect on project outcomes), and not every project requires it, so it is not the first step in ranking here.
  • D. Decision tree analysis is a quantitative technique that compares alternatives by EMV. It solves a choice among options and cannot give the high-to-low order of the risks.

Key takeaway After identification, priorities must be set: do qualitative risk analysis first, and then decide which risks deserve quantitative analysis.

Variation If the stem says the top three risks are already ranked and you must calculate their combined effect on total project cost, then quantitative risk analysis is next. If it says some risks have not yet been found, the answer returns to identifying risks.

Something wrong with this question?

Report an issue with this question

Question 5Free

While introducing risk analysis to a new team member, the project manager explains the role of quantitative risk analysis. What is it mainly used to assess?

Show answer and explanation

Correct answer: A

The project manager is introducing risk analysis to a new member and explains the role of quantitative risk analysis. You need to understand how it differs from qualitative analysis.

The object of quantitative analysis is the whole. It numerically analyzes the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives, and its output is a number for objectives such as cost and schedule, for example “there is an 80% chance the work is finished before a given date”. This is the most basic difference from qualitative analysis: qualitative analysis gives the relative level of each risk, while quantitative analysis gives numbers on the overall objectives. The answer is A.

Why the other options are wrong

  • B. Assessing the relative priority of risks is mainly the role of qualitative risk analysis, and the probability and impact matrix is one commonly used tool. The main purpose of quantitative analysis is to quantify the combined effect of risks and uncertainty on overall project objectives.
  • C. Statistics on the distribution across risk categories belong to risk categorization and the risk report. They reflect the makeup of the risks, not their numeric effect on objectives.
  • D. Deciding who follows up is work done when identifying risks and planning responses. It is the assignment of responsibility, not something quantitative analysis assesses.

Key takeaway Quantitative analysis assesses the numeric combined effect of risks and uncertainty on overall objectives; qualitative analysis ranks individual risks by relative priority.

Variation If the question asked “what is the output of qualitative analysis?”, the answer is a priority ranking of the risks. If it asked “must every project do quantitative analysis?”, the answer is no; it is done when needed.

Reference Quantitative Risk Analysis · Lesson 1: Quantitative Risk Analysis and Monte Carlo Simulation

Something wrong with this question?

Report an issue with this question

Question 6Free

A project manager is drawing a decision tree for the choice “whether to buy a component from an outside supplier” and for the uncertain event “whether the supplier delivers on time after purchase”. Which symbols should be used for these two, respectively?

Show answer and explanation

Correct answer: C

When drawing a decision tree for a choice among alternatives, you must pick symbols for “whether to buy a component from outside” and for “whether the supplier delivers on time after purchase”. The question asks which symbol each takes.

To tell the symbols apart, ask one question: “who decides?” Whether to buy is the project's own choice, so it is a decision node (square). Whether the supplier delivers on time is beyond the project's control and is an uncertain event, so it is a chance node (circle). The triangle only marks the end of a branch, the end point of a path. So the order is square, circle. The legend of Figure 5-5 in PMBOK 8 uses the square for a decision node, the circle for a chance node and the triangle for the end of a branch. The answer is C.

Why the other options are wrong

  • A. Circle, square reverses the order. The decision maker's own choice should be a square, and only an uncontrolled uncertain event is a circle.
  • B. The first item is a choice, yet it takes a triangle. A triangle marks the end of a branch; it represents neither a choice nor an uncertain event.
  • D. The second item is an uncertain event and should be a chance node, a circle. A triangle is the end of a path and does not represent the event itself.

Key takeaway Square: we choose (decision). Circle: the environment decides (chance). Triangle: end of branch.

Variation “Whether to run a proof of concept” is a square, and “whether the validation result is good or poor” is a circle. The end of every path is always a triangle, marked with the net path value.

Something wrong with this question?