Process domain · Task 5

Plan and manage procurement

"Plan and manage procurement" is task 5 of the Process domain in the PMP exam content outline. The Process domain makes up 41% of the exam, and the outline does not publish a question count for each task. It has 10 enablers, one of the longest lists in the domain. The task tests the project manager's judgment in buying: make or buy, which contract type, how to negotiate, how to keep watch on vendor performance, and what to do first when a contract goes wrong.

What the outline asks for (enablers)

The outline lists 10 enablers for this task. The table maps each one to the chapters of this study guide.

EnablerWhat you need to knowChapter
Plan procurement.Make-or-buy analysis, the procurement management plan, procurement documents, source selection criteriaMake-or-Buy Analysis
Execute a procurement management plan.Issuing procurement documents, bidder conferences, selecting vendors and signing agreementsBidder Conference
Select preferred contract types.Features of fixed-price, cost-reimbursable and time-and-material contracts; how risk is shared between buyer and sellerContract Types
Evaluate vendor performance.Performance reviews, inspections and audits, measuring performance against contract termsControl Procurements
Verify objectives of the procurement agreement are met.Procurement audits, accepting deliverables, contract closureControl Procurements
Participate in agreement negotiations.Preparing for and conducting negotiation, win-win thinkingNegotiation
Determine a negotiation strategy.Setting goals, limits and tradeable items before negotiatingNegotiation
Manage suppliers and contracts.Contract changes, claims, dispute handling, supplier relationshipsControl Procurements
Plan and manage the procurement strategy.Matching the procurement strategy to project objectives, risk and contract typeContract Types, Make-or-Buy Analysis
Develop a delivery solution.Combining internal capability and outside vendors into a deliverable solutionMake-or-Buy Analysis

How to read procurement scenario questions

  1. Check the contract before acting. When a vendor has a problem, check the contract terms and the rights and duties in the agreement first, then decide how to handle it.
  2. When an outside party is late, talk to them first. Learn the cause and the impact, then handle it under the contract and change control. Do not go straight to penalties or termination.
  3. Pick the contract type by where the risk should sit. When scope is clear, a fixed-price contract puts more risk on the seller. When scope is unclear or likely to change, a cost-reimbursable or time-and-material contract fits better, and the buyer carries more of the risk.
  4. Contract changes follow a formal process. A verbal promise does not replace a written change. Every contract change goes through change control and is recorded in writing.
  5. Prepare before negotiating. Know your goals, limits and what you can concede, understand the other side's position and interests, and aim for a result both can accept.
  6. Accept against the contract and acceptance criteria. After the vendor delivers, inspect against the agreement and formally accept, then close the contract. Closure includes filing records and lessons learned.

Rules 1, 5 and 6 are common exam practice. The other rules match the study guide.

Predictive versus agile and hybrid environments

PredictiveAgile and hybrid
Contract basisFixed-price contracts are common when scope is clearWhen scope will change, time-and-material or flexible contracts are common, with delivery by iteration
Delivery rhythmAcceptance at milestones and deliverables set in the contractThe vendor takes part in iterations, and results can be seen and commented on at the iteration review
Handling changeContract changes go through formal change controlAdjusted in the backlog, with room for change built into the contract
Performance evaluationAgainst the contract's schedule, cost and quality termsBased on increments delivered, while still bound by the contract

Task quiz

These free questions come from the chapters linked to this task and cover as many chapters as possible. Pick an answer first, then open the explanation to see why the right option is right and why the others are wrong. For more, practice by chapter in the question bank.

Question 1Free

A project manager is preparing to negotiate a supply agreement with a key supplier. The situation is complex, neither side can get everything it wants, and compromise may be needed to avoid schedule delays, cost overruns and reputational damage. To obtain an outcome that benefits the project, what should the project manager do?

Show answer and explanation

Correct answer: B

A project manager is preparing to negotiate a supply agreement with a key supplier. The situation is complex, neither side can have everything it wants, and compromise may be needed. The question is about the preparation needed to obtain an outcome that benefits the project.

To compromise in a negotiation, you must know in advance which interests you cannot give up and which you can. So before the negotiation, analyze priorities with stakeholders, rank the objectives by importance, and separate the bottom line, the expectations and the parts you can concede. Then you can make concessions on a reasoned basis and protect the project's core interests, avoiding schedule delay and cost overruns. The answer is B.

Why the other options are wrong

  • A. Revealing priorities midway means doing the preparation at the negotiating table. It invites hasty concessions under pressure and exposes your hand.
  • C. Setting objectives before negotiating is fine, but fixing them and following them strictly in the negotiation removes the room to concede and to adapt, particularly when the situation is complex.
  • D. Adjusting your priorities at any time as the negotiation develops lacks internal consensus, is high risk and is easily exploited by the other side. This should be done before negotiating.

Key takeaway Before negotiating, clarify priorities with stakeholders and rank your objectives, so that you can protect your core interests when you compromise.

Variation If the stem asked “what to do when negotiations reach a deadlock,” the approach is to go back to the parties' interests and look for a win-win solution or concessions in stages; if the negotiation fails, consider the best alternative.

Something wrong with this question?

Report an issue with this question

Question 2Free

A supermarket chain’s store renovation project buys large quantities of shelving and light fixtures every week. Several suppliers want to work with the project, and the project manager is confident of negotiating a good price. The requirements, specifications, quantities and weekly delivery schedule are all settled. To get the best overall value from the future contract, what should the project manager do FIRST, before negotiating with the suppliers?

Show answer and explanation

Correct answer: A

A store renovation project buys shelving and light fixtures in large weekly volumes. The requirements, specifications, quantities and weekly delivery schedule are settled, and negotiation with suppliers has not started. The question asks what to do first before negotiating so that the future contract delivers the most value.

There are two signals: “the requirements are settled” and “FIRST, before negotiating”. The requirements analysis is done, so the next step is to confirm the boundaries within which the contract will be negotiated. The organization’s procurement policies, procedures and guidelines (organizational process assets) and the applicable legal parameters are the boundaries the contract must respect; external laws and regulations also have to be identified and complied with separately. Once these are clear, the bidding, negotiation and contract that follow are compliant, and a good price can be pursued inside that framework. Price lists and past experience are inputs you can use afterward. The answer is A.

Why the other options are wrong

  • B. Price is an important negotiating factor, but collecting price lists before you know the contract’s constraints may produce quotes that do not meet the rules; that comes later.
  • C. Past purchasing practice is only a reference. Every project’s needs and value differ, so start with this project’s constraints.
  • D. A time-phased bill of materials belongs to requirements analysis, and the stem says the requirements, quantities and delivery schedule are already settled, so this step is done.

Key takeaway Once requirements are settled and before negotiation, first establish the policies, procedures, guidelines and legal parameters the contract must follow, and then negotiate the price.

Variation If the requirements, specifications and quantities were not yet clear, you would first analyze the project’s needs thoroughly and determine the resources required, and only then deal with the compliance framework. If the question were how to shorten the time needed to select a seller, the answer would be the pre-approved seller list.

Something wrong with this question?

Report an issue with this question

Question 3Free

An e-commerce company is setting up a customer service center for its promotion season and estimates that it needs 80 call agents: weekdays 9 a.m. to 6 p.m., and weekends 9 a.m. to 1 p.m. Management has not decided whether to hire the people itself or hand the work to an outside company. The project manager must provide a basis for this decision. Which of the following analyses should the project manager use?

Show answer and explanation

Correct answer: B

The project must set up a customer service center with a clear headcount, but it has not been decided whether to do it internally or outsource it. The question asks which analysis gives a basis for that decision.

The key information is that the headcount and shifts are settled but “hire ourselves or outsource” is not. For a decision about whether to do the work and who should do it, use make-or-buy analysis: it compares in-house hiring with outsourcing on cost, risk, skills and long-term employment obligations. The conclusion comes only after the analysis and is then written into the procurement strategy. None of the other three is a tool for deciding between making and buying. The answer is B.

Why the other options are wrong

  • A. Earned value analysis measures the performance of work already completed and needs actual performance data. The stem is about deciding whether to hire or outsource, and there is no completed work to measure.
  • C. Reserve analysis compares contingency reserves with the remaining risk to judge whether the reserve is enough. It is not a way of comparing in-house work with outsourcing.
  • D. Trend analysis looks at how performance changes over time to forecast what comes next. It too needs data that already exists and cannot decide between hiring and outsourcing.

Key takeaway To decide whether to do the work yourself or outsource it, compare the options with make-or-buy analysis, and then record the conclusion in the procurement strategy.

Variation If the stem said the analysis was finished and the conclusion was to outsource, the next step would be to prepare the statement of work. If it asked how to compare the costs of the two options, you would include indirect costs.

Something wrong with this question?

Report an issue with this question

Question 4Free

A logistics company is installing a batch of shelving in a new warehouse. The drawings, quantities and acceptance criteria are all settled, market prices are stable, the schedule is short and the risk is low. Which contract should the project manager choose?

Show answer and explanation

Correct answer: C

The project is developing its procurement strategy. The scope of work is clear and the risk is low, and the question asks which contract type fits best.

The signals: the drawings, quantities and acceptance criteria are settled, market prices are stable, the schedule is short and the risk is low. All three conditions say the scope is clear and few changes are expected, so the buyer can agree a fixed price in advance and have budget certainty, while the seller builds to the drawings and earns more if it controls cost well. The answer is C.

Why the other options are wrong

  • A. A time-and-materials contract suits small projects where an accurate SOW cannot be written, or topping up with experts. It settles on actual hours and materials, so the total price is not usually fixed in advance and may rise with actual input (a cap can be agreed separately). Using it on work with clear scope gives up the price certainty a fixed-price contract provides.
  • B. A cost plus fixed fee contract is cost-reimbursable, so the buyer bears actual cost and it suits work whose scope is unclear. Here the scope is clear, and there is no need to make the buyer carry the risk of cost overruns.
  • D. A cost plus award fee contract also leaves cost with the buyer, and the award rests on the buyer’s subjective evaluation. It suits work with unclear scope where performance needs incentives, which does not fit a low-risk, clear-scope scenario.

Key takeaway Clear scope, few changes and low risk point to a fixed-price contract.

Variation If the condition were changed to “performance measures cannot yet be stated and will be settled as the work proceeds”, choose a cost-reimbursable contract; if it were changed to “just hire an outside expert for a few weeks of consulting paid by the person-day”, choose time and materials.

Something wrong with this question?

Report an issue with this question

Question 5Free

A data platform upgrade project is in the execution stage, and the team has hit a performance bottleneck that none of several attempted approaches has solved. The project manager wants an outside supplier to propose a solution. Which bid document should be sent to suppliers?

Show answer and explanation

Correct answer: B

The project is in the execution stage. The team has tried several internal approaches and still cannot overcome a performance bottleneck, and it wants outside suppliers to come up with a solution. The question asks which bid document to send.

PMBOK 8 Appendix X4 sorts bid documents into three types. A request for information (RFI) gathers more information from the market before bid documents go to a set of selected vendors. A request for proposal (RFP) is used for projects with a complex scope where the buyer is looking for the vendor to provide a solution. A request for quote (RFQ) is used when price is the main deciding factor and the proposed solution is readily available. The key signal here is “have the supplier propose a solution”: the approach does not yet exist, so the buyer cannot write a ready-made solution for others to price. The answer is B.

Why the other options are wrong

  • A. A statement of work (SOW) is procurement documentation describing what is being procured. It goes out with the bid documents and is not itself a bid document inviting responses, nor does it make suppliers come up with a solution.
  • C. An RFI collects market information before formal bidding and cannot replace an RFP, which formally solicits solutions from suppliers. The stem says it wants suppliers to submit a solution, so an RFP fits better.
  • D. An RFQ presupposes that price is the main deciding factor and a solution is readily available. Here the solution is unknown, so asking suppliers to quote on a “ready-made solution” gives them nothing to quote.

Key takeaway Use an RFP to have suppliers propose solutions, an RFQ when a ready solution only needs price comparison, and an RFI to sound out the market before formal documents.

Variation If the stem changed to “standard servers with fixed specifications, just compare quotes from several firms”, the answer becomes an RFQ; if the project manager did not yet know what approaches exist on the market, issue an RFI first.

Reference Conducting the Procurements · Lesson 1: Conducting the Procurements: Inputs, Seller Proposals and the Bidder Conference

Something wrong with this question?

Report an issue with this question

Question 6Free

A smart-campus access control project has entered implementation. The face-recognition terminals are supplied by an outside vendor. A key stakeholder writes to say that the terminals that arrived do not meet the agreed requirements for use. As project manager, what should you do FIRST?

Show answer and explanation

Correct answer: C

An access control project is in implementation, the terminals are outsourced to a vendor, and a key stakeholder reports that the delivered terminals fall short. The question asks what the project manager does “first”.

Signals: “first”, and purchased terminals that fail to meet requirements. When buyer and seller disagree or things are unclear, everything goes by the contract. First read what the contract requires of the terminals and what remedies it provides for nonconforming deliveries, and only then decide between correction, a claim or something else. The answer is C.

Why the other options are wrong

  • A. A claim needs a basis in the contract. Until you have read it, you cannot tell whether the vendor is in breach or what you can claim.
  • B. Whether the vendor must correct the defect, and whether a change request is needed at all, depends on the procurement agreement and the impact of the correction. Raising a change request before checking the agreement or confirming the terminals are nonconforming is the wrong order. If the remedy involves a formal change to the agreement or the project baselines, a change request is then submitted through change control.
  • D. Replacing the vendor is something you might do only after you know what the contract says. The question asks what to do first.

Key takeaway When a procurement dispute arises, look at the contract first, then act.

Variation If the contract does not state the requirement, verify what the two sides agreed using the statement of work and other procurement documents. Only after you confirm the vendor is in breach do you talk about written notice to correct, a claim or replacing the vendor. Common exam practice: checking the contract first is the usual first step in monitoring and controlling procurements; claims, replacing the vendor and change requests all come later.