Process domain · Task 1

Develop an integrated project management plan and plan delivery

"Develop an integrated project management plan and plan delivery" is task 1 of the Process domain in the PMP exam content outline. The Process domain makes up 41% of the exam, and the outline does not publish a question count for each task. This task tests planning judgment at the start of a project and as it runs: how complex the project is, whether to use a predictive, adaptive/agile or hybrid approach, how the subsidiary plans combine into one whole, and how to keep the plan valid afterwards.

What the outline asks for (enablers)

The outline lists 9 enablers for this task. The table maps each one to the chapters of this study guide.

EnablerWhat you need to knowChapter
Assess project needs, complexity, and magnitude.Judging complexity from objectives, uncertainty, number of stakeholders, and the technical and organizational settingAgile vs. Predictive, Tailoring
Recommend a project management development approach (i.e., predictive, adaptive/agile, or hybrid management).How requirement stability, rate of change and delivery cadence point to an approachAgile vs. Predictive, Hybrid Approach
Determine critical information requirements (e.g., sustainability).What information the project needs to make decisions; how sustainability requirements enter the planSustainability
Recommend a project execution strategy.Choosing the life cycle, phasing and delivery methodProject Life Cycle
Create an integrated project management plan.Which subsidiary plans and baselines make up the project management plan, and how they stay consistentProject Management Plan
Estimate work effort and resource requirements.Common estimating techniques, using historical data, estimate uncertaintyEstimating Techniques
Assess consolidated project plans for dependencies, gaps, and continued business value.Finding conflicts and gaps between subsidiary plans, and confirming the project still supports business valueProject Management Plan
Maintain the integrated project management plan.Updating the plan as changes are approved, through change controlProject Management Plan
Collect and analyze data to make informed project decisions.Using performance data and analysis to support decisions, including what AI tools can and cannot doAI in Project Management

How to read planning scenario questions

  1. Assess first, then choose the approach. When asked which approach to use, look at whether requirements are stable, how often they change and whether the customer can stay involved. Do not default to the method you know best.
  2. Approaches can be tailored and combined. One project can have parts that suit predictive methods and parts that suit agile ones. The organization's standard method is a starting point, not a fixed frame.
  3. The plan is a whole, not a pile of documents. When subsidiary plans conflict (for example, the schedule assumes people the resource plan does not provide), reconcile them and update them together rather than fixing each in isolation.
  4. Keep the plan valid, and change it through change control. In a predictive project, changing the plan or a baseline means: assess the impact, raise a change request under the change management plan, have the person with authority or the change control board decide, update the plan and logs, inform stakeholders, then implement.
  5. Estimates need a basis and a stated uncertainty. Use historical data where it exists, cross-check with more than one technique where it does not, and do not shrink an estimate to match an expectation.
  6. Decide on data, not impressions. Before deciding to adjust a plan, collect and analyze the data, then recommend.

Rules 1, 2, 5 and 6 are common exam practice. Rules 3 and 4 match the plan integration and change control material in the study guide.

Predictive versus agile and hybrid environments

PredictiveAgile and hybrid
Scope of planningA full integrated plan up front, maintained through change controlA high-level plan up front, with detail planned progressively in iterations
EstimatingBased on the work breakdown structure, bottom-up or analogousOften relative estimating, adjusted on the team's observed velocity
Plan maintenanceBaseline changes need a change requestThe backlog is reprioritized continuously and scope evolves with feedback
Choosing the approachBetter when requirements are stable and change is costlyBetter when requirements are uncertain and frequent feedback is needed; use hybrid when both are true

Task quiz

These free questions come from the chapters linked to this task and cover as many chapters as possible. Pick an answer first, then open the explanation to see why the right option is right and why the others are wrong. For more, practice by chapter in the question bank.

Question 1Free

The project manager of an EV charging station project has just been assigned. The manager has already read the business case, the project charter and the statement of work (SOW), and has also talked with the sponsor about scope and objectives. Before scheduling the kickoff meeting, the manager still asks the sponsor and the business analyst who wrote the business case to meet once more. What is the manager's purpose?

Show answer and explanation

Correct answer: D

The project manager of an EV charging station project has just arrived and has read the business case, the project charter and the SOW, and has also talked with the sponsor. Before the kickoff meeting the manager still asks the sponsor and the business analyst who wrote the business case to meet again. The question is the purpose.

The manager has already read the documents. Meeting again with the owner and the author is not meant to change the documents but to check that everyone understands the business case the same way, to identify and clear up existing and potential misunderstandings and keep the project from drifting after the start. The project manager's duty is to provide advice and insight and to make sure the success criteria in the business case, the charter, the project management plan and the benefits management plan align with one another. The answer is D.

Why the other options are wrong

  • A. The sponsor is responsible for developing and maintaining the business case, and the project manager only advises and cannot revise it directly. New objectives are also later changes and should not be added casually at this point.
  • B. Testing whether a solution is feasible is part of the justification work done when the business case is prepared. The new project manager, just arrived, is checking everyone's understanding of the existing business case, not arguing it again (reassessing the business case when conditions change is a later matter led by the sponsor).
  • C. The obstacles and constraints the team will meet are identified during planning with resources and risks in view, and have no direct connection to “understanding the business case.”

Key takeaway After taking over a project, first check your understanding of the business case with the sponsor and the author, and clear up misunderstandings.

Variation If the meeting shows that the business case really has omissions, the project manager should recommend a revision to the sponsor, who decides whether to revise it.

Reference Business Case and Benefits Management Plan · Lesson 3: Business Documents: Nature, Maintenance and Ownership

Something wrong with this question?

Report an issue with this question

Question 2Free

A project manager is explaining enterprise environmental factors to a new team member. One of the four statements below is wrong. Which one?

Show answer and explanation

Correct answer: B

This question asks you to find the incorrect statement, so note that the question asks which one is NOT correct, and judge each statement against the definition of enterprise environmental factors.

Enterprise environmental factors are conditions not directly influenced by the project team that impact, constrain or direct the project. The key is that the direction of the effect is not fixed: they can enhance or constrain the options, and for the project they can be favorable, unfavorable or neutral. Statements A, C and D can each be supported by the definition. Statement B moves straight from “cannot be controlled” to “can only limit,” which is inconsistent with the definition, so B is the incorrect statement. The answer is B.

Why the other options are wrong

  • A. This statement is correct: the effect of enterprise environmental factors can be favorable, unfavorable or neutral, so it is not the incorrect statement the question asks for.
  • C. This statement is correct: organizational culture, structure and governance is one of the internal enterprise environmental factors PMBOK 8 lists, so it is not the incorrect statement.
  • D. This statement is correct: enterprise environmental factors can come from inside or outside the organization, so it is not the incorrect statement.

Key takeaway The project team cannot directly control enterprise environmental factors, but their effect can be favorable, unfavorable or neutral, and they cannot all be treated as constraints.

Variation If the question were changed to “find the correct statement,” B would need to be rewritten as “the team cannot control them, but their effect may be favorable, unfavorable or neutral.” An option saying “enterprise environmental factors can be directly changed by the project team as needed” would also be wrong, because the team cannot directly control them; the team can update and add to organizational process assets (knowledge repositories).

Something wrong with this question?

Report an issue with this question

Question 3Free

Two companies form a joint venture to take on a smart warehousing project, and the project manager, preparing the project management plan, wants to draw on past practice. A partner in the joint venture holds a complete set of historical project schedule records and risk data and agrees to share them. Which statement about this material is correct?

Show answer and explanation

Correct answer: B

Two companies form a joint venture for a smart warehousing project, and while preparing the project management plan the project manager wants to draw on past practice. A partner holds historical project schedule records and risk data and agrees to share them. The question is about the range of sources of organizational process assets.

PMBOK 8 states that organizational process assets may include any artifact, practice or knowledge from any or all of the performing organizations involved in the project, including the lessons learned and historical information from previous projects, which can be used to execute or govern the project. The historical schedule records and risk data the partner shares are historical information accumulated from earlier projects, so they are likewise organizational process assets and can serve as an input to the plan. The answer is B.

Why the other options are wrong

  • A. Enterprise environmental factors are conditions the team cannot directly control that constrain or direct the project, such as marketplace conditions and legal restrictions. Historical records that have been shared are assets that can be used, not external conditions.
  • C. The source of organizational process assets is “any or all of the performing organizations involved in the project,” not only the lead party. The partner is a performing organization, and its material counts as well.
  • D. This material is the record of earlier projects and can be used as an input as early as planning, without waiting for closing. Adding to the repository at closing refers to the new information this project produces.

Key takeaway Organizational process assets come from any or all of the performing organizations involved in the project, and include the historical information and lessons learned from earlier projects.

Variation If the partner's material carries confidentiality terms, confirm the scope of sharing and the authorization before using it.

Reference Organizational Process Assets · Lesson 1: Organizational Process Assets: Definition, Sources and Categories

Something wrong with this question?

Report an issue with this question

Question 4Free

A project manager is appointed to lead a large and complex supply chain information platform project. Its scope is now stable, and the earlier scope increases were approved and their impacts analyzed. Previously he managed only small internal tool development, and since the project entered the Executing focus area he has run into one problem after another. At a stakeholder meeting, a functional manager mentions that the company recently completed a platform project of similar complexity. The company's PMO keeps historical project records and provides guidelines. What should the project manager do?

Show answer and explanation

Correct answer: A

The project is in the Executing focus area. The project manager lacks experience with complex projects, the company has completed a similar project, and the PMO keeps historical project records and provides guidelines. What should the project manager do?

A PMO supports project managers by managing shared resources, identifying best practices, developing policies and templates, and providing guidance. Because the company has done a similar project, its historical records and guidelines are organizational process assets, and the best first step is to consult the PMO and learn from them. The problems the project manager is facing have very likely occurred before. The answer is A.

Why the other options are wrong

  • B. The stem states that the earlier scope increases were approved and their impacts already analyzed, so repeating that analysis is not the most useful next step. The project manager should first draw on the organization's existing experience from a similar project.
  • C. Bringing stakeholders together can be a parallel or follow-up measure, but the stem already offers reusable experience from a similar project, so consulting the PMO for records and guidelines is the most direct first step.
  • D. Continuing the old small-project approach neither draws on the company's similar project nor deals with the current problems, and it defers lessons learned until the project ends. The PMO already holds historical records and guidelines, so consult them first.

Key takeaway When the company has a similar project, consult the PMO for historical records and guidelines first, then consider other approaches.

Variation If the project manager finds no similar project records at the PMO, the next step is to analyze the impacts and root causes of the current problems or discuss them with stakeholders. If the problem were instead “a procurement project's supplier delivery dates keep slipping”, first communicate with the supplier to understand the cause of the delays; the project manager can then consult the PMO's supplier evaluations and problem-handling records.

Something wrong with this question?

Report an issue with this question

Question 5Free

Of the four statements below about “project phases”, only one is accurate. Choose it.

Show answer and explanation

Correct answer: D

Of four statements about project phases, only one is accurate. Judge by how phases are divided, how phases relate to each other and where phase gates can be placed.

PMBOK 8: projects are often decomposed into multiple phases, and each phase culminates in the completion of one or more deliverables and/or outcomes. Phases may be sequential, transitional or overlapping, and some projects use a combination of these relationships. Only D is complete and accurate. The answer is D.

Why the other options are wrong

  • A. Finer is not always better. Dividing too finely adds coordination and gate review burden, so divide phases appropriately by deliverables and management needs.
  • B. Phase gates are traditionally placed at the end of a phase, but PMBOK 8 states they can also be placed at the start of a phase (pre-phase gates), to confirm that direction is aligned, resources and planning are in place, and risks are addressed.
  • C. Phases do not have to be strictly queued. They can be sequential, transitional or overlapping, as when fast tracking lets adjacent phases run partly in parallel.

Key takeaway Phases can be sequential, transitional or overlapping; a phase gate is usually after a phase ends and can also be placed before a phase begins.

Variation If asked what a phase gate review is for, the answer is to check whether the desired outcomes or exit criteria have been achieved, and to decide whether to proceed to the next phase.

Reference The Project Life Cycle · Lesson 1: Project Phases, Phase Gates, and the Trends of Risk and the Cost of Changes

Something wrong with this question?

Report an issue with this question

Question 6Free

A test engineer has just joined a logistics software company and finds that company policy requires all requirements to be collected and the system design reviewed before any code work starts. Which kind of delivery approach is this?

Show answer and explanation

Correct answer: D

Company policy requires all requirements to be collected and the system design reviewed before work starts. You must decide which development approach this delivery method belongs to.

A predictive approach may also be referred to as a waterfall, plan-driven, or traditional approach. Scope, schedule, cost, resource needs, quality requirements, and risks are well defined in the early phases of the life cycle and are expected to remain relatively stable, with much of the planning done up front. “All requirements and the design review must be finished before any code starts” is exactly requirements up front and plan-driven. The answer is D.

Why the other options are wrong

  • A. An adaptive approach establishes a vision first, and the initial known requirements are elaborated progressively through the backlog and feedback. It would not fix all requirements and design before any code is written.
  • B. In this kind of hybrid pattern the early part is adaptive exploration with fast trial and error. The stem describes an early part that needs complete, settled requirements and design.
  • C. Incremental delivery within a predictive approach also plans up front, but its hallmark is delivery in batches. The stem says nothing about batch delivery, so there is nothing to base that judgment on.

Key takeaway Completing all requirements and design before work starts is the hallmark of a predictive approach: plan-driven, requirements up front.

Variation If the stem added “the overall scope is clear, but delivery is in three batches,” the answer would become incremental delivery within a predictive approach. If it said instead “only a vision exists and requirements are elaborated round by round,” the answer would be adaptive.