The Project Management Plan

PMP · Governance and Business Environment · 4 lessons · about 46 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The charter answers “why are we doing this,” and the project management plan answers “how.” PMBOK 8 calls the process that produces it Integrate and Align Project Plans. It corresponds to ECO Process domain, Task 1 (Develop an integrated project management plan and plan delivery). This chapter covers the purpose of the process, its inputs and outputs, the order of tailoring first and integrating second, and iterative development and progressive elaboration. It covers what the plan contains, how it differs from project documents and baselines, how baselines are changed, and configuration management and version control. It covers the project kick-off meeting, which predictive projects usually hold after planning is complete and before execution starts. Finally it covers how plan integration differs between predictive and adaptive projects, rolling wave planning, and dependencies across projects.

The chapter's emphasis falls on integrating the plan (many scenarios) and the kick-off meeting (a stable pattern: the exam asks the same thing in different scenarios).

Lessons in this chapter

  • Lesson 1: Integrate and Align Project Plans: purpose, inputs and outputs, and practice. Integrating, aligning and coordinating all plan components; inputs and outputs; assess needs, complexity and size before choosing an approach; iterative development; what to do when sub-plans contradict each other or expectations conflict; once the plan is done, record it, communicate it and obtain approval where required.
  • Lesson 2: What the plan contains, and how it differs from project documents and baselines. The plan's components and the three baselines; the plan is a living document; how each of four categories (plan components, baselines, project documents, business documents) is changed; baseline changes apply only to the future (common exam practice); configuration management and version control.
  • Lesson 3: The project kick-off meeting. Predictive projects usually hold it after the plan is approved and before work starts, and adaptive projects can hold it once an initial roadmap is enough to support the work; its three tasks; a multi-phase project can hold one at the start of each phase as needed (common exam practice: hold one every phase); what to do when attendees cannot all come; how it differs from the project initiation meeting.
  • Lesson 4: Plan integration in predictive and adaptive projects. More planning up front and an integrated baseline in predictive projects; a lightweight plan, backlog, and evolving baselines in adaptive projects; rolling wave planning; cross-project dependencies.

Chapter map

Integrate and Align Project Plans

  • Inputs: charter · outputs from other processes · enterprise environmental factors · organizational process assets · other applicable inputs
  • Decide tailoring, development approach and life cycle first → integrate each domain's management plans and baselines → verify alignment
  • Output: project management plan (management plans + scope / schedule / cost baselines; a living document)
  • Related, but not outputs of this process: project documents (logs, registers) are updated by the relevant processes and governance authority, and those under configuration control need a formal change; once a predictive baseline exists, changes go through formal change control (adaptive projects adjust dynamically under the agreed governance); business documents get recommendations only
  • Record and communicate, obtain approval where required → kick-off meeting (usually before execution in predictive projects; multi-phase projects can hold one at the start of each phase as needed) → execute
  • Predictive: more planning up front + integrated baseline | Adaptive: lightweight plan + evolving baselines, progressively refined | Rolling wave: near term in detail, far term at a high level

Practice: start with the core questions in the chapter practice set, then the required ones.

Lesson 1

Integrate and Align Project Plans: Purpose, Inputs and Outputs, and Practice

Lesson video

Lesson overview

Once the charter is in place, the next question the project must answer is how the work will actually be done. The answer is the project management plan. It is not a document one person finishes alone. It puts together the plans from the scope, schedule, finance, stakeholder, resource, risk and other performance domains, plus other management plans such as the change management plan, and makes sure they agree with one another. PMBOK 8 calls this process Integrate and Align Project Plans. It corresponds to ECO Process domain, Task 1 (Develop an integrated project management plan and plan delivery). This lesson covers the purpose of the process, its inputs, tools and outputs, the order of tailoring first and integrating second, iteration and progressive elaboration, and the situations you meet most often during integration. The next lesson covers what the plan contains and how it differs from documents and baselines.

The purpose of the process

The Integrate and Align Project Plans process involves integrating, aligning, and coordinating all plan components and consolidating them into a unified project management plan. The primary benefit of this process is the creation of a thorough document outlining the basis for the various aspects of all project activities and how they will be executed. This process is typically conducted once or at specific intervals during the project.

“Integrate” does not mean binding together the plans that each department hands in. It means making trade-offs and coordinating among the elements. Pushing quality to the limit may raise cost; identifying a risk may mean adjusting both schedule and budget. The project manager balances these interactions, and under structured governance the project manager manages the integration even when each sub-plan has its own owner; in self-governance models, that responsibility may be distributed among the team.

Inputs, tools and outputs

The inputs are the project charter, outputs from other processes, enterprise environmental factors and organizational process assets, and other applicable inputs (PMBOK 8 Figure 2-4). The charter is the starting point for planning, and it defines at least the high-level information that the components of the project management plan then elaborate. Outputs from other processes, meaning the sub-plans and baselines of each performance domain, are the main raw material of integration. Any change to a sub-plan or baseline may cause a corresponding update to the project management plan.

The tools and techniques are expert judgment; data gathering (brainstorming, checklists, focus groups, interviews); interpersonal and team skills such as conflict management, facilitation and meeting management; meetings; and the project canvas. A checklist lists items, actions or points to consider and is often used as a reminder, here to check that nothing was missed in integration. The output is the project management plan.

Tailor first, then integrate

At the beginning of the project, this process should establish the overall tailoring considerations and determine the development approach and project life cycle. This information should form part of the project management plan and serve as an input to all performance domains, guiding their planning efforts. Subsequently, all management plans and baselines from the performance domains should be integrated into the project management plan, and their alignments should be verified. Other management plans, such as the change management plan or configuration management plan, should be included if applicable.

So before starting to integrate, the project manager first assesses the project's needs, complexity and size, chooses a suitable development approach and strategy on that basis, and then builds the plan. Writing the plan straight from the charter, setting the cost baseline first, or going off to select vendors often leads to choosing the wrong approach. The concrete work of this ECO task is here too: analyze needs, complexity and size, recommend an approach, and develop and maintain the plan. Procurement negotiation and contract settlement are not part of it.

Iterative development and progressive elaboration

The sub-plans depend on one another, so they cannot all be finished in one pass. Integrate the management plans and baselines iteratively, addressing risk- and change-related impacts as they arise and repeatedly revisiting affected components. For example, suppose an exchange-rate risk is identified. First analyze the risk and plan a response. If the response requires adjusting the approved cost baseline, evaluate, approve and update it under the formal change control procedure. Use or adjustment of reserves follows the financial management plan, the risk management plan and the established authority. Once adjusted, it may touch the schedule in turn, and that is iterative development.

The plan should also be adaptable enough to respond to a dynamic environment, ideally by following progressive elaboration, so that more accurate estimates and detail become available as information grows. The amount of time spent planning is determined by the circumstances. The information gained from planning should be sufficient to move forward in an appropriate manner but not more detailed than necessary.

Figure 1 Integrating and aligning the project plans: from sub-plans to kick-off

Common situations in integration

The integrated plan should be developed by the team together with key stakeholders and be reviewed by them. It should also be documented and communicated to key stakeholders. If the project governance arrangements or organizational procedures require formal approval, submit it to the designated approver. Developing it jointly is what makes it workable and builds consensus. The next step after the plan is finished is to record it, communicate it and obtain any required approval, not to start executing. When neither the charter nor organizational procedures say whether approval is needed, who approves, or in what order, first agree on the responsible person and process with the sponsor and stakeholders and record it; submit the plan only if the agreed process requires formal approval.

First situation: sub-plans contradict each other, for example the go-live date in the schedule conflicts with the date staff become available in the resource management plan. Have the responsible people integrate the sub-plans, check consistency and align them right then, during planning. Do not sidestep the conflict by cutting scope or crashing. When there are unresolved dependencies or gaps, first assess the overall plan, sort out the dependencies, and confirm that the plan still supports the business value. Second: the plan conflicts with a stakeholder's expectations, for example marketing wants to launch a month earlier. Communicate and coordinate first, and adjust the plan or manage the expectation. Do not simply give in, and do not simply refuse. Third: a critical deliverable is missing from the contract. First clarify the high-level business needs with the project sponsor. Then someone with procurement or contract authority assesses the impact with the seller and processes a formal contract change, and afterward the deliverables list, scope and related plans are updated. Fourth: while the project manager was away, the team drew up a schedule on its own. On returning, first check whether it fits the project vision and objectives, then decide whether to adjust it. Do not start over, and do not rush to begin work.

Example

PMLyceum takes on an IT project for a dairy plant's filling line. After the charter is approved, the project manager does not rush to set a timeline. First the project manager assesses needs, complexity and size: many equipment interfaces and a stable customer process, so a predictive approach for the main body and iterations for the reporting module. During integration, the project manager notices that the schedule puts equipment commissioning in July, while the resource plan has the external engineers arriving only in August. The project manager brings the two owners together, moves commissioning to late August, adjusts the travel budget that was to go into the cost baseline to match, and sends the integrated plan to the customer's production director and the sponsor for review.

Worked examples

Example 1 After the charter is approved, what comes before developing the plan?

Question 1Example

A restaurant chain is launching a new store ordering system. The project charter is approved, and the project manager is preparing to develop the integrated project management plan. What should the project manager do FIRST before developing the plan?

Show answer and explanation

Correct answer: C

The store ordering system project has an approved charter, and the project manager is about to develop the integrated project management plan. What comes first before developing the plan?

The development approach, life cycle and tailoring are the premise of integrating the plan and also an input to planning in each performance domain. So first assess the project's needs, complexity and size, and recommend a suitable development approach on that basis, and only then integrate. This step produces the choice of approach, which determines the level of detail and the rhythm of each sub-plan: predictive projects integrate more baselines, and adaptive ones more iteration and release plans. The answer is C.

Why the other options are wrong

  • A. Selecting suppliers requires a sourcing strategy first, and the strategy depends on the approach and scope, so doing it now is premature.
  • B. The cost baseline is developed from cost estimates, schedule information and other relevant inputs, then incorporated into the integrated plan as a baseline. Until the approach and scope are clear, you cannot fix it from an old project's budget.
  • D. Having functional managers submit first drafts from experience, without first understanding this project's characteristics, can leave the sub-plans inconsistent with one another and without team involvement.

Key takeaway Before developing the integrated plan, assess needs, complexity and size and choose the approach.

Variation If the approach is already chosen, first integrate the sub-plans and verify alignment. Once the plan is finished, the next step is to submit it for key stakeholder review under the governance arrangements and communicate it, and, where the organization requires formal approval, obtain the designated approver's approval, not to start executing.

Something wrong with this question?

Report an issue with this question

Example 2 The team drew up the schedule while the manager was on leave

Question 2Example

On a community home-care services platform project, the scope statement has been approved, and the project manager and core team are in place. The project manager has to take two weeks of leave for an urgent family matter, and in that time the team drafts the project schedule on its own. When the project manager returns, the detailed schedule is almost complete. What should the project manager do?

Show answer and explanation

Correct answer: B

The scope statement is approved. While the project manager was away for two weeks, the team drew up a detailed schedule on its own, and it is nearly finished by the time the manager returns. What should the project manager do?

The schedule is part of the project management plan, and the plan must align with the purpose and objectives in the charter, the approved scope and the project vision. The project manager did not take part in building it and its quality is unknown, so the first step is to check whether the schedule fits the vision and objectives and then judge from that whether to adjust it. Verify first, then decide. The basis for the check is the purpose and objectives in the charter, the approved scope and the project vision, not the project manager's personal preference or who built it. The answer is B.

Why the other options are wrong

  • A. Scrapping the plan before checking its quality both wastes the team's work and has no basis.
  • C. The plan has not been checked, and key stakeholders have not agreed to it. By common exam practice the kick-off meeting is usually scheduled after the project management plan is approved and before execution begins. This plan has not yet been checked, so it is not time to start execution.
  • D. Having the team draft the plan while the project manager is on leave is a normal arrangement and not a violation, and there is no need to report it to the PMO first.

Key takeaway When reviewing a plan someone else prepared, first check that it is consistent with the vision and objectives, then decide whether to adjust it.

Variation If the check shows it matches the charter objectives, move on to review and approval. If conflicts show up among the sub-plans, have the responsible people integrate and align them.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • In a predictive approach, before a baseline exists you can revise the draft plan directly (for example an equipment delay). Once a baseline is approved, any change to it, in whatever phase the project is, is assessed and implemented under the formal change control procedure.
  • When integration reveals a contradiction between sub-plans, do not avoid it by cutting scope or crashing. Assess the overall plan first, then integrate and resolve.
  • When the plan is finished, the next step is to record it and communicate it to key stakeholders, and to submit it for approval if formal approval is required. It is not to start executing, and not to hold the kick-off meeting first.
  • The plan is built on the charter and is consistent with organizational strategy. You do not use the plan to flesh out the charter after the fact.
  • Before developing the plan, assess needs, complexity and size. Do not begin with vendors, the cost baseline or functional managers' first drafts.

Key takeaways

  1. Integrate and Align Project Plans integrates, aligns and coordinates all plan components and consolidates them into a unified project management plan. It is typically conducted once or at specific intervals.
  2. Inputs: the charter, outputs from other processes, enterprise environmental factors, organizational process assets and other applicable inputs. Output: the project management plan.
  3. First establish tailoring, the development approach and the life cycle, then integrate the management plans and baselines of each performance domain and verify their alignment.
  4. The plan is developed iteratively and elaborated progressively. The team and key stakeholders develop it together, and it is documented and communicated. Where governance arrangements or organizational procedures require formal approval, the designated approver gives it.
  5. Contradicting sub-plans, conflicting expectations and unclear deliverables are all aligned through communication during planning, not avoided or given in to.

Lesson 2

What the Plan Contains, and How It Differs from Project Documents and Baselines

Lesson video

Lesson overview

The previous lesson covered how to integrate the plan. This lesson covers what the integrated plan is, what it contains, and how it is changed afterward. The exam likes three distinctions here. First, the project management plan versus documents such as the project charter and the business case. Second, plan components versus baselines versus project documents. Third, changing the plan before a baseline exists versus after one is established (this depends on whether a baseline has been established, not on whether the project is still in planning). Once you know what can be changed freely and what must go through change control, most questions in this area can be answered. The next lesson covers the kick-off meeting that predictive projects usually hold after planning is complete and before execution starts; the exact timing can be tailored to the project and life cycle.

What the project management plan is

The project management plan is the document that describes how the project will be executed, monitored and controlled, and closed. It defines the basis for all project decisions and is a living document that can be expected to change over time. It can be high level or detailed, tailored to the project's application context and complexity.

It may go by other names: a project governance plan, project execution plan, project development plan, project implementation plan, or another document that transparently defines, for all team members and stakeholders, the project management framework within which decisions will be made. The exam consistently says “project management plan.”

A project management plan typically consists of the following components: change management plan, communications management plan, financial management plan, iteration plan, procurement management plan, quality management plan, requirements management plan, release plan, resource management plan, risk management plan, schedule management plan, scope management plan, sourcing strategy plan, stakeholder engagement plan, and test plan. The project team or the organization may tailor the content to include only the elements most relevant to the specific project context, objectives and organizational requirements. Besides these management plans, the plan holds the baselines: the scope baseline, schedule baseline and cost baseline. A baseline is the approved version of a work product. In predictive environments it can be changed only through formal change control procedures (in adaptive environments, the product owner typically approves changes to the scope baseline dynamically, with no formal change control procedure). It serves as the basis for comparison to actual results.

The plan does three jobs. First, it is the basis for executing, monitoring and controlling, and closing, so the team and stakeholders know what to do and how. Second, it is used to confirm stakeholder expectations and give them the information they need for decisions and actions. Third, it is the reference for measuring performance, since actual results mean something only when compared with it. So when a question asks “which document describes how the project will be executed, monitored and controlled, and closed,” the answer is the project management plan. The charter only authorizes, the business case says why, and the benefits management plan says how the benefits are realized. None of these is the answer.

Maintaining the plan

Once the plan is approved, it is not frozen. As approved changes are implemented, the plan is maintained and updated to stay valid, and “maintaining” here means updating the plan to follow approved changes. The project management plan typically includes the change management plan (which the team can tailor to the context and include if applicable), which spells out who receives change requests, who approves them and how they are recorded. Once the plan is formed, the relevant documents should be communicated to key stakeholders, and planning artifacts used to confirm their expectations and promote alignment. That prevents later conflicts in advance, such as approved construction being stopped suddenly.

Plan, baselines and project documents

Each of the three kinds of item does one job. Project management plan components describe how the work will be done, such as the scope management plan and the risk management plan. A baseline is the approved version within the plan, used to compare performance. Project documents record the project's current status and data, such as the issue log, change log, risk register, stakeholder register, assumption log and lessons learned register. Project documents are updated often as the project progresses and are generally maintained by the project team, without the formal change approval a baseline needs. Business documents (the business case and the benefits management plan) differ again from project documents. They are usually maintained by the sponsor, the benefits owner or the program level. The project manager mainly provides recommendations and insight and takes part in updates as the organization's governance arrangements provide.

CategoryExamplesHow it is changed
Management plan componentsScope management plan, risk management planUpdated to follow approved changes
BaselinesScope baseline, schedule baseline, cost baselineIn predictive environments only through formal change control; in adaptive environments, the product owner typically approves scope baseline changes dynamically
Project documentsIssue log, risk register, change logThe team updates them through the relevant processes; those under configuration control need a formal change request under the configuration management plan
Business documentsBusiness case, benefits management planThe project manager mainly gives recommendations and insight and takes part in maintaining and aligning them as organizational governance arranges
Figure 1 How the plan, baselines and project documents differ (lower part)

A change to a baseline is made only from the latest version of the baseline and applies only to the future. It cannot rewrite past performance (this is common exam practice). This protects both the baseline and the integrity of historical performance data. In predictive approaches, changes are not formally controlled until baselines are established. Once the project has a baseline, all changes should go through a formal process to assess and implement changes.

Configuration management and version control

The project's configuration management plan should specify which project artifacts are subject to configuration control. Changes to these artifacts require a formal change request. Configuration management is the set of procedures for tracking project parameters and monitoring their changes. Put simply, it manages versions: documents, plans, schedules, software versions and so on can all be placed under configuration control as the configuration management plan provides.

The team has several conflicting schedules, or different versions of the risk register disagree and cause disputes. The solution is configuration management and version control: verify the project artifacts, identify the single controlled latest version and store and publish it in one place. Deleting old files, agreeing verbally, looking up the communications management plan, or asking an expert to judge cannot fix version confusion.

Example

On a sorting-system project for a regional distribution center, at the weekly meeting the buyer and the test lead each bring a copy of the risk register, and they word the “barcode scanner delivery date” differently. The project manager does not judge who is right and first checks the configuration management plan. If it already designates the risk register and schedule as configuration items, the project manager follows it by using one storage location, recording a version number and editor for every change, and releasing only the latest controlled version. If it does not, the project manager first submits a formal change request to update the configuration arrangements and implements version control after approval. The project manager then reminds everyone that a register is a project document that the team usually updates through the relevant process, but in this case it has been placed under configuration management, so changes must keep a version history and follow configuration management requirements (a document designated as a configuration item needs a formal change request to be changed). Once the schedule baseline is established, changing it requires a change request.

Worked examples

Example 1 The main purpose of the project management plan

Question 1Example

Which of the following describes MOST accurately the main role of the project management plan?

Show answer and explanation

Correct answer: D

The question needs you to tell what the project management plan mainly does.

The project management plan integrates the management plans and baselines of each performance domain into one unified document. It specifies how the project will be executed, monitored and controlled, and closed, and it is the basis for all project decisions. So the most accurate statement is that it integrates the sub-plans and baselines and guides execution and monitoring. The stem asks for the “main role,” so among similar functions such as authorization, budget and knowledge capture you pick the one the plan alone has: integrating and guiding. The plan is also the reference for measuring performance, and it is a living document, updated after approval as approved changes occur. The answer is D.

Why the other options are wrong

  • A. Formal authorization is done by the charter. The plan cannot replace the charter.
  • B. Lessons learned are recorded in the lessons learned register. That is not the plan's main role.
  • C. A funding request rests on the business case and the budget. The plan is not a budget request document.

Key takeaway The project management plan integrates the sub-plans and baselines and guides project execution and monitoring.

Variation If asked “which document formally approves the project and authorizes the project manager,” answer the charter. If asked “why is the project worth doing,” answer the business case. If asked “how will the project be executed, monitored and controlled, and closed,” answer the project management plan.

Something wrong with this question?

Report an issue with this question

Example 2 Versions of the risk register disagree

Question 2Example

A project manager takes over a smart parcel-locker deployment project midway. At the first risk review meeting, the project manager finds that the risk register the team members hold differs from the project manager's version. Each member has saved a copy from a different time, and the project has no controlled single storage location. What should the project manager do to avoid this kind of problem?

Show answer and explanation

Correct answer: D

The project manager takes over the smart parcel-locker project midway. At the first risk review meeting, the team's copies of the risk register differ from the manager's version, each person has saved a copy from a different time, and the project has no controlled single storage location. How can this kind of problem be avoided?

The risk register is a project artifact, and the essence of the problem is version management: several versions of the same document are circulating and there is no single storage location. PMBOK 8 says the configuration management plan should specify which project artifacts are subject to configuration control. So the project manager should establish version control for the register under configuration management requirements, store it in one place and release only the single latest version. That removes the inconsistency at its root. Configuration management also requires changes to controlled artifacts to be submitted as formal requests, so it solves both “several versions coexisting” and “who changed what.” The answer is D.

Why the other options are wrong

  • A. Another email is just another notice. It does not control versions and gives no single storage location, so several versions will appear again next time. The communications management plan governs how project information is administered and communicated, but it does not replace configuration management and version control.
  • B. The issue log records only problems that have occurred and been logged. The stem says nothing of this being recorded, and checking it will not prevent inconsistency.
  • C. Expert judgment can help check contents or judge which version is authoritative, but it cannot replace configuration management and version control, and it cannot stop versions from diverging again.

Key takeaway Registers and logs are project artifacts. Establish version control for them under configuration management requirements and unify the version.

Variation If several schedules cite inconsistent dates, the fix is the same, configuration management and version control. If asked how to change a baseline, it can only go through formal change control.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Logs and registers are project documents, not components of the project management plan, and updating them generally does not need approval from the change control board. If they are under configuration control, submit a change request under the configuration management plan. Baselines, plan components and project documents under configuration control go through the formal change process as specified.
  • A baseline change applies only to the future and cannot retroactively change past performance (common exam practice).
  • The approved plan is not final. It is a living document and is updated to follow approved changes.
  • In a predictive approach, before a baseline is established there is no baseline to change, so no baseline change is needed, but changes still have to be recorded and analyzed. Once a baseline is established, related changes are assessed and implemented through the formal process, even if the project is still in the planning phase.
  • The business case and the benefits management plan are business documents. The project manager mainly gives recommendations and insight and takes part in updates as organizational governance arranges.

Key takeaways

  1. The project management plan describes how the project will be executed, monitored and controlled, and closed. It is the basis for all decisions, it is a living document, and its components can be tailored to the context.
  2. The plan consists of the management plans and three baselines. A baseline is an approved version. In predictive environments it changes only through formal change control, while in adaptive projects the product owner can approve scope baseline changes dynamically.
  3. Project documents (logs, registers) record current status and are usually updated by the team through the relevant processes (those under configuration control need a formal change). For business documents, the project manager mainly gives recommendations.
  4. A baseline change is based on the latest version and applies only to the future (common exam practice).
  5. Version confusion calls for configuration management and version control: verify the project artifacts and maintain one controlled latest version.

Lesson 3

The Project Kick-Off Meeting

Lesson video

Lesson overview

Once the plan is complete and approved, the project is about to start work. PMBOK 8 lists project kickoffs only as an example of a meeting and does not require every project to hold one. In predictive projects, or where the organization's governance practice calls for it, a kick-off meeting is usually held before execution begins, and whether to hold one and in what form is tailored to the project context. Questions ask the same thing in different scenarios: when to hold it, why, who attends, and what to do if not everyone can come. The answers are stable. Remember its position (common exam practice: in predictive projects, after the initial plan is formed and approved as the organization requires, and before concentrated execution begins; adaptive projects can hold it once an initial roadmap is enough to support the work) and its three tasks, and you will score. This lesson also separates it from the project initiation meeting held during initiating. The previous lesson covered the plan's contents and baselines; the next covers how plan integration differs in predictive and adaptive projects.

What the kick-off meeting is

In predictive projects, the kick-off meeting is commonly used to bridge planning and execution and is usually held after the project management plan is complete and approved and before execution begins; in adaptive projects, it can be held once an initial roadmap is sufficient to support the work. PMBOK 8 lists project kickoffs as one example of a meeting, alongside decision-making, facilitated workshops, issue resolution, lessons learned and retrospectives, sprint planning, and status updates.

Common exam practice is that it has three tasks: get the key stakeholders to agree on the project management plan; communicate the project objectives to the team and obtain the team's commitment to the project; and explain each stakeholder's role and responsibilities so that the work is assigned. One way to see it: once the plan is approved, leadership first makes the expectations and milestones clear, the team then states its commitment, and top-down requirements meet bottom-up commitment here, so that communication and accountability are settled. A meeting typically has an agenda, a facilitator, background and objectives, opening remarks from leadership, the organization structure and responsibilities, and the scope and delivery approach.

PointContent
Focus areaPlanning (common exam classification)
When it is heldIn predictive projects usually after plan approval and before work starts; a multi-phase project can hold one at the start of each phase as needed
What it doesGets key stakeholders to agree on the plan; makes the project objectives clear and has the team commit; explains each party's role and responsibilities
Adjacent actionsBefore: the plan is complete and approved. After: execution begins
Figure 1 Where the project kick-off meeting sits in the flow (upper part)

When to hold it, who comes, and what if they cannot all come

In predictive projects the timing is usually after the plan is approved and before concentrated execution begins (adaptive projects can hold it once an initial roadmap is enough to support the work). It is not when part of the charter is done, not as soon as the project is approved and funds arrive, and not when the requirements are written. A multi-phase project can hold a phase kick-off at the start of each phase, depending on how the phases differ and what governance requires (common exam practice is to hold one at the start of every phase).

Key stakeholders should attend. The project manager communicates with them proactively and directly to secure the attendance of key stakeholders, encouraging them and winning their support. The project manager does not simply decree “attendance is mandatory” and does not always ask the sponsor to step in. When members are spread across regions, use online or virtual meetings to reduce geographic limits, and do not require everyone to fly to headquarters. When time zones make a single session impossible, hold several sessions by time zone so that all key stakeholders take part. Do not hold it only where most people are, and do not have those who were absent watch the recording later.

If the meeting is already scheduled and a few non-key people are absent at the last minute in a way that does not affect the meeting's objectives, hold it on time and brief the absentees afterward. If a key stakeholder is absent, first try to secure their attendance, and then, depending on their influence, choose among holding separate sessions, arranging a representative, obtaining their input beforehand, or rescheduling. If the plan has already been approved but you find that stakeholders in different countries approved it with uneven understanding, confirm at the kick-off meeting, one by one, that everyone understands the plan the same way. If a substantive misunderstanding turns up that affects the basis of approval, clarify first, then reconfirm or seek approval again as governance requires.

Distinguishing it from the initiation meeting

“Kick-off” and the initiating stage are easy to confuse. Some materials call the meeting at the end of initiating, where the charter is issued, the project manager is appointed and authority is announced, the initiation meeting (an initiating meeting; a common exam term). It is about the charter. The project kick-off meeting is held after the plan is approved and before work starts, and it is about the plan. When a question mentions a “start-up” or “opening” meeting, check the wording: if it says kick-off meeting, treat it as the project kick-off meeting, and if the question gives no other cue, default to kick-off meeting.

Initiation meeting versus project kick-off meeting

Initiation meeting: in the initiating stage; the charter is issued, the project manager is appointed and authority is granted.

Project kick-off meeting: in predictive projects usually after plan approval and before work starts; it secures agreement on the plan, communicates objectives and obtains commitment. A multi-phase project can hold one at the start of each phase as needed.

Example

PMLyceum is building an appointment and follow-up system for a chain of eye clinics. After the sponsor and the clinic director approve the plan, the project manager does not simply tell development to start. Instead the project manager sends invitations to the director, the heads of each branch, the development and test leads and two outsourced designers. In the meeting, the project manager spends twenty minutes explaining the project objectives and milestones, confirms each person's role and responsibilities, and asks each lead to state a commitment to the delivery dates for their part. A branch head says, “Outpatient peak hours make it hard for us to help with testing.” The project manager notes it on the spot and, after the meeting, applies through change control to adjust the testing window, updating the plan only after it is approved. When the meeting ends, no one disagrees about the plan or their responsibilities, and only then does development begin.

Worked examples

Example 1 After planning ends, explaining the objectives and responsibilities to everyone

Question 1Example

A programming-learning platform project for elementary school children has started smoothly. Planning has just ended, the project management plan has been approved by the sponsor, and the project manager informed the sponsor by email a few days ago that planning is complete. Before execution begins, the project objectives still need to be explained to all parties and the role and responsibilities of each stakeholder made clear. What should the project manager do NEXT?

Show answer and explanation

Correct answer: C

The planning of the children's programming platform project has just ended and the plan is approved by the sponsor. Before execution begins, the objectives must be explained to all parties and each stakeholder's role and responsibilities made clear.

“Planning just ended, execution not yet begun” and “explain the objectives and make roles and responsibilities clear” are exactly the timing and tasks of the project kick-off meeting. Call all stakeholders to a kick-off, convey the objectives and set out responsibilities in one session, and let everyone exchange views. The kick-off is also a chance for all parties to reach the same understanding of the plan and their responsibilities, and disagreements that surface in the meeting can be settled on the spot, which costs less than clarifying them one by one afterward. The answer is C.

Why the other options are wrong

  • A. Sending only an electronic document is one-way communication; it cannot confirm shared understanding or jointly clarify roles and responsibilities.
  • B. Conveying things orally one by one is inefficient, and each person may hear different content.
  • D. The sponsor can review or approve the plan, but one-way relaying by the sponsor cannot replace the kick-off meeting's joint clarification of objectives, roles and responsibilities. The project manager should convey the objectives and responsibilities in the meeting.

Key takeaway After the plan is approved and before work starts, use the project kick-off meeting to convey the objectives and make responsibilities clear.

Variation Just after the charter is approved is not the time for the project kick-off meeting. In a multi-phase project, a phase kick-off can be held before each phase starts. If stakeholders are spread across several countries, hold a virtual meeting or separate sessions, and do not cancel the meeting because of it.

Something wrong with this question?

Report an issue with this question

Example 2 Getting key stakeholders to understand the plan and commit

Question 2Example

A healthcare IT project spans several branch hospitals. Planning has just ended, and the project management plan has been approved. Many stakeholders are involved. The project manager wants every key stakeholder to understand the project plan and reach consensus, and also wants the team members to commit to the project. What should the project manager do?

Show answer and explanation

Correct answer: D

The healthcare IT project's planning has just ended and the project management plan has been approved. The project manager wants key stakeholders to understand the plan and reach consensus, and the team members to commit.

“Understand the plan, reach consensus, team commitment” maps to the three tasks of the project kick-off meeting: obtain agreement on the plan, communicate the objectives and obtain the team's commitment, and make roles and responsibilities clear. Explaining the plan face to face and confirming commitment is the most direct way. The strongest distractor is C. A kick-off may review the project's purpose and high-level objectives from the charter, but reviewing only the charter does not meet the stated need to explain the approved plan and confirm commitment, so C is still inferior. The answer is D.

Why the other options are wrong

  • A. Team building can improve team cohesion, but it does not give key stakeholders a shared understanding of the project management plan or confirm the team's specific commitments to that plan.
  • B. Sending the file in a one-way mass email allows no discussion and does not demonstrate the team's commitment.
  • C. The charter may be reviewed at the kick-off, but reviewing only the charter will not help the parties understand the approved project management plan or fully meet the needs stated in the stem.

Key takeaway To have all parties understand the plan and the team commit, hold a project kick-off meeting.

Variation If stakeholders are spread across several time zones, hold sessions by time zone and make sure the key stakeholders all take part. If someone is absent at the last minute, assess the effect on the meeting's objectives and decisions and, if needed, arrange separate communication or adjust the meeting, so that key stakeholders take part fully and understand the plan. The charter and the project management plan serve different purposes. The kick-off may review the charter's purpose and high-level objectives, but it should also build shared understanding of the approved plan and confirm commitment.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The kick-off meeting comes after planning ends and before execution begins. It is not a meeting of the initiating stage, and the meeting can recall the purpose and high-level objectives from the charter, but going over only the charter does not explain the approved plan or confirm commitment.
  • Its purpose is plan agreement, communicating objectives, team commitment, and roles and responsibilities. Team-building activities, mass emails, telling people one by one, or asking the sponsor to relay the message all fall short of those goals.
  • When key stakeholders cannot all attend, do not demand attendance and do not postpone indefinitely. Secure their attendance, hold sessions by time zone, or arrange a representative and obtain their input beforehand. Holding the meeting on time and briefing absentees afterward applies only when the absentees are non-key people.
  • A multi-phase project can hold a phase kick-off at the start of each phase as needed (common exam practice: hold one every phase). It does not hold one only in the first phase to save budget.
  • The kick-off meeting is not a meeting to build the plan from scratch. Even so, disagreements, risks or new information that surface there may still trigger plan elaboration or an update through change mechanisms (the plan is progressively elaborated).

Key takeaways

  1. The project kick-off meeting is classified as planning by common exam practice and is held after the plan is approved and before work starts.
  2. Three tasks: agree on the plan, communicate the objectives and obtain the team's commitment, and make roles and responsibilities clear.
  3. A multi-phase project can hold one at the start of each phase as needed. Geographically dispersed attendees call for a virtual meeting or separate sessions.
  4. If non-key people are absent at the last minute and it does not affect the meeting's objectives, hold the meeting on time and update them afterward. If key stakeholders are absent, reschedule, hold separate sessions, arrange a representative or obtain their input beforehand, depending on their influence. If understanding differs, confirm it one by one in the meeting.
  5. Distinguish it from the initiation meeting of the initiating stage. If a question says “start-up meeting,” check the wording, and with no other cue default to kick-off meeting.

Lesson 4

Plan Integration in Predictive and Adaptive Projects

Lesson video

Lesson overview

The same Integrate and Align Project Plans process produces very different results under different development approaches. Predictive projects usually front-load planning and integrate and align each performance domain's management plans and baselines into the project management plan. Adaptive projects keep the plan lightweight and refine it progressively as work advances. Between the two sits rolling wave planning, another form of progressive elaboration. A project is also not an island, and the plan has to handle dependencies on other projects in the organization. This lesson covers three things: how predictive and adaptive plans differ (the adaptive plan is lightweight and refined progressively), rolling wave planning, and why cross-project dependencies belong in the plan. The previous lesson covered the kick-off meeting. This chapter ends here, and the next chapter covers Manage Project Execution.

Predictive: plan up front, integrate and align, then execute

Predictive approaches usually front-load most of the planning, integrate and align the management plans and baselines produced by each performance domain into the project management plan, and verify that they are consistent. Once the team has enough understanding of and confidence in the course of action, execution can begin, and the plan is still updated and refined over the life cycle. Whether the project management plan needs formal approval depends on organizational and governance requirements. The level of detail in the plan should fit the project's context and complexity and be tailored to the project's needs. More detail is not automatically better, and the time spent planning is whatever yields enough information to move forward. Once baselines are established, all changes are assessed and implemented through the formal process.

Adaptive: a lightweight plan refined as work advances

Adaptive approaches can be both iterative and incremental. Iteration-based teams refine the plan with each iteration; some adaptive approaches instead use flow-based scheduling and refine the plan continuously with the flow of work.

An adaptive project does not have a complete plan fixed once before work starts and detailed down to each task. The plan is usually lightweight: a product vision, a roadmap and a release plan. With iterations, the team plans each iteration's details at its start; with a flow-based approach, the team continually elaborates and pulls ordered work. The iteration plan and release plan among the project management plan's components are exactly this kind of content, and PMBOK 8 lists them as plan components. If the sponsor asks, “Is there a complete plan like the one a predictive project has?”, the project manager should explain: an adaptive project does have a plan, but it is lightweight, detailed in the near term and high level further out, and adjusted continually based on feedback. It is not “no plan,” not “only a budget plan,” and not a plan finished in one pass and strictly frozen.

Changes in an adaptive project usually do not go through the formal change request process of a predictive project either. They are managed through the backlog (tailored to the project context if there are contractual, regulatory or governance requirements). A new requirement goes into the backlog, is ordered by priority after impact analysis, and when and whether it is done is decided in later iteration planning or by pulling work in a flow-based system.

Rolling wave planning

Rolling wave planning is one form of progressive elaboration. Near-term work is planned in detail, and work further out stays at a higher level and is refined as the project advances. Suppose the project management plan describes the next six months of work in great detail, and the plan has to be reworked heavily whenever requirements shift slightly, which restricts execution. The remedy is rolling wave planning: detailed near term, rough far term, which gives both stability and flexibility. The direction in answering is “detailed near, rough far, refined as work progresses.” It is not to tear up the plan, and not to make everything uniformly rough.

Dependencies beyond the plan

Projects have dependencies on one another too. Two projects share a test environment and an interface development team, but one project's plan ignores that. Ignoring the dependency does not make it disappear. The project manager should identify these dependencies, coordinate with the lead of the other project and include them in the plan to manage continuously. Managing only your own scope and schedule and dealing with the other side only when it fails, demanding that the other side stop sharing, or removing the related work from this project's scope, are all ways of avoiding the problem.

Plans in predictive, adaptive and hybrid projects

Predictive: planning up front; each domain's management plans and baselines are integrated and aligned into the project management plan; changes go through a formal process.

Adaptive: a lightweight plan; vision, roadmap, release plan and iteration plan refined layer by layer; changes managed through the backlog.

Hybrid: as the project needs, choose between predictive baselines and adaptive iteration plans, for example hardware managed against baselines and software rolled forward by iteration.

Figure 1 Level of detail in a plan: predictive, rolling wave and adaptive

Example

PMLyceum is building a care-shift scheduling mini-app for a community senior-care provider and uses an adaptive approach. The sponsor asks, “Is there a complete plan, like when you build a house?” The project manager brings a one-page product vision, a roadmap laid out by quarter, the scope list for the first release and the three things the first iteration will do. The project manager explains that the next two months are written down to task level and the period after that only to feature level. After each two-week iteration the next round is adjusted based on feedback, and requirement changes go into the backlog to be reordered. The project manager has also added a separate line in the plan: the project shares an interface with the provider's HR system upgrade project, and once a month the project manager checks schedules with that project's manager.

Worked examples

Example 1 Does an adaptive project have a plan fixed once before work starts?

Question 1Example

A team is using a short-iteration adaptive approach to develop a mobile payment mini-app. The sponsor asks whether the project, like a predictive project, has a complete project management plan fixed once before work starts. How should the project manager describe the project's plan?

Show answer and explanation

Correct answer: A

On an adaptive mini-app project, the sponsor asks whether, as in a predictive project, there is a complete project management plan fixed once before work starts.

The plan of an adaptive project is lightweight: a product vision, a roadmap and a release plan, with the team planning the details at the start of each iteration and adjusting continually based on feedback. The project manager should say so honestly: the plan is kept lean and refined progressively by iteration. A predictive project usually plans more fully up front and establishes baselines, with later changes controlled. An adaptive project is detailed in the near term and high level further out, and the plan is updated with feedback from each iteration. The answer is A.

Why the other options are wrong

  • B. Completing it all at once and strictly not changing it does not fit the continual adjustment of adaptive work, and the statement is too absolute in itself, since a predictive plan can also be updated under change control.
  • C. An adaptive project is not without a plan. The plan is just lighter and adjusted more often.
  • D. Keeping only the budget would drop key content such as scope and schedule. The plan should be lean as a whole, not reduced to a single item.

Key takeaway An adaptive project's plan is lightweight, refined progressively by iteration and adjusted continually.

Variation In a hybrid project, the predictable parts are managed against baselines and the uncertain parts are refined by iteration, chosen by the nature of each part and not one approach for everything. If asked how scope or requirement changes are managed in an adaptive project, common exam practice is continuous refinement and ordering through the backlog.

Something wrong with this question?

Report an issue with this question

Example 2 Six months of work are written in too much detail and a requirement change forces rework

Question 2Example

A team is responsible for a smart customer-service chatbot project. The project management plan describes the next six months of work in great detail, and even a small change in requirements during execution forces a major rewrite, limiting the flexibility of execution. What should the project manager do?

Show answer and explanation

Correct answer: C

The chatbot project's plan writes six months of work in great detail, and even a small requirements change forces a major rewrite, limiting flexibility in execution.

“Six months all in detail” and “a requirement change forces a major rewrite” are the key information. Rolling wave planning is one form of progressive elaboration: plan near-term work in detail, leave far-term work at a higher level and refine it as work advances, which gives both stability and flexibility. In questions like this, both extremes are wrong: one is so detailed that it is rigid, and the other is so rough that it has no basis. Rolling wave planning takes the middle path, detailed in the near term and leaving room to adjust in the far term. The answer is C.

Why the other options are wrong

  • A. Adding more detail makes the plan more rigid, and changes cost more to make when they arrive.
  • B. Leaving it unchanged leaves the flexibility problem in place. The plan should be progressively elaborated as information increases, with approved changes incorporated under the applicable change-control requirements.
  • D. Keeping only milestones and not planning any specific work leaves near-term work without a basis for execution and goes to the opposite extreme.

Key takeaway A plan that is detailed near term and rough far term, refined as work advances, is rolling wave planning.

Variation If the stem said the plan was too rough for the team to start, you would detail the near-term work. Short iterations also demonstrate progressive elaboration: the current iteration is planned in detail while later work remains at a higher level in the roadmap or backlog.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Adaptive does not mean “no plan.” The plan is lightweight and progressively refined. Predictive does not mean “the more detail the better” either. The detail should fit the context and complexity and be tailored to the project's needs.
  • Rolling wave planning is detailed near, rough far, refined as work progresses. It does not make the near term rough.
  • Cross-project dependencies must be identified, coordinated and included in the plan. They do not go away by being ignored.
  • Changes in an adaptive project are managed through the backlog. Do not apply the formal change request process of a predictive project.
  • A hybrid project chooses according to the characteristics of each part of the project. It does not apply one approach to everything.

Key takeaways

  1. Predictive: plan up front; each domain's management plans and baselines are integrated and aligned into the project management plan; changes go through a formal process.
  2. Adaptive: a lightweight plan (such as a vision, roadmap and release plan, plus an iteration plan when iterations are used) refined progressively as work advances; changes go into the backlog.
  3. Rolling wave planning: detail for the near term, a high level for the far term, refined as work advances.
  4. Dependencies between projects cannot be ignored; identify them, coordinate them and include them in the plan.
  5. The level of detail in the plan should fit the project's context and complexity and be tailored to the project's needs.

This chapter has 29 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.