What this chapter covers
Once the project management plan is approved and released, the project moves into execution. The core process of execution is Manage Project Execution. It produces the work according to the plan, implements approved changes, and hands the data generated during execution to the monitoring and controlling processes for analysis. This chapter first covers the purpose, inputs and outputs of the process, and deliverables and work performance data. It then covers how approved changes return to execution, the four kinds of action in a change request, and tools such as the project management information system and meetings. Finally it covers the division of work between executing and monitoring and controlling, and the difference between quality assurance and quality control.
The chapter is dense with concepts, and the exam tests it in a narrow set of ways: what comes next after the plan is approved; whether a string of raw values is data, information or a report; which kind of change request each of several actions belongs to; which process applies when an audit finds the standard was not followed; and whether you can change the plan directly when execution shows rising defects.
Lessons in this chapter
- Lesson 1: Manage Project Execution: purpose, inputs and outputs, deliverables and work performance data. Executing work packages as planned; five kinds of input; deliverables, work performance data and the issue log as the three key outputs (plus change requests and various updates); how data, information and reports differ and where each is produced.
- Lesson 2: Implementing approved changes, and tools and team coordination during execution. Approval happens in monitoring and controlling and implementation in executing; corrective action, preventive action, defect repair and updates; the project management information system, the daily coordination meeting, and expert judgment.
- Lesson 3: Executing versus monitoring and controlling, and quality assurance versus quality control. Executing does and records, monitoring and controlling compares and reports, change control approves and governs; quality assurance looks at processes and quality control looks at deliverables (in PMBOK 8 quality control is a concept, not a separate process: process quality sits in Manage Quality Assurance and verifying deliverables falls within monitoring and controlling of scope).
Chapter map
Manage Project Execution (execute as planned, implement approved changes)
- Inputs: project management plan · project documents · approved change requests · enterprise environmental factors · organizational process assets
- Outputs: deliverables · work performance data · issue log · change requests · various updates
- Tools: project management information system · meetings (daily coordination meeting) · expert judgment
- Where it goes: data → the monitoring and controlling processes (analyzed into work performance information) → Monitor and Control Project Performance (consolidated into work performance reports) → adjustment needed → change request → Assess and Implement Changes → approved → back to execution
Quality: quality assurance (processes, audits) quality control (a concept, not a separate PMBOK 8 process: deliverables, testing, defects; verification falls within monitoring and controlling)
Practice: start with the core questions in the chapter practice set, then the required ones.
Lesson 1
Manage Project Execution: Purpose, Inputs and Outputs, Deliverables and Work Performance Data
Lesson overview
Once the project management plan is approved and released, the project moves from planning into execution. The core process of execution is Manage Project Execution. This lesson answers three questions. What does the process actually do? What does it take in and what does it produce? Of what it produces, what are deliverables and work performance data, and how do you tell them apart from “information” and “reports”? “What is the next step after the plan is approved?” and “Is this set of numbers data, information or a report?” are both tested here. The next lesson covers how approved changes are implemented and the tools used in execution.
The purpose of the process: get the work done as planned
The Manage Project Execution process involves leading and performing the work defined in the project management plan and implementing approved changes to meet the project's objectives. The primary benefit of this process is the comprehensive management of project work and deliverables, which enhances the likelihood of project success. When leading project teams, the collective team members have more knowledge than any single person. Directing and managing execution provides a way to align the knowledge and skills of all team members toward the project objectives.
The process mainly does four things: it executes the planned project activities to complete deliverables; it allocates resources and manages their efficient use; it implements approved changes; and, based on analysis of work performance data and information, it raises change requests where adjustment is needed, with the project plans updated once those are approved. Hold on to one keyword: it executes the plan, and it does not decide again what to do. Work that is not in the plan cannot be quietly added because it “looks useful.” If the plan needs to change and the proposed change affects a project baseline, the change is approved through the Assess and Implement Changes process under formal change control. Other updates are handled under the change management plan and organizational procedures.
So when a question says “the plan has been approved and released” and asks for the next step, the answer is to start executing the work packages. Estimating durations and listing resources are usually planning activities completed before approval; without new information or an identified change, arbitrarily reworking a sub-plan is not the next step. PMBOK 8 notes that planning is iterative, and rolling wave planning continues to refine activities, durations and resources as the project advances, but when the question is “the plan was just approved, what next,” the exam answer is execution.
Inputs and outputs
There are five kinds of input: the project management plan (any component may be used); project documents, such as the change log, lessons learned register, milestone list, project communications, project schedule, requirements traceability matrix, risk register and risk report; approved change requests; enterprise environmental factors; and organizational process assets.
The outputs are deliverables, work performance data, the issue log and change requests, plus project management plan updates, project document updates (such as the activity list, assumption log, lessons learned register, requirements documentation, risk register and stakeholder register) and organizational process asset updates. Three outputs are tested most: deliverables are the results, work performance data are the raw records, and the issue log records problems that surface during execution. It is first created here, and its use is covered in the chapter on issue management. Change requests are also an output of this process (PMBOK 8 Figure 2-6). If execution reveals that something needs adjusting, you raise a change request. Approval is completed in Assess and Implement Changes, and the execution process does not decide it by itself.
Approved change requests are change requests that were processed by the project manager, the change control board or another designated person under the change management plan, with a status of approved, deferred or rejected. Approved changes are implemented through this process. For deferred or rejected ones, the requester is notified.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project. Projects are undertaken to fulfill objectives by producing deliverables, and deliverables may be tangible or intangible. Two modifiers are what the exam tests. “Unique” means each project's results have their own character. “Verifiable” means you can check whether they meet the requirements, and the later verifying and accepting of deliverables both rest on that. Some deliverables can be seen and touched, such as a building or a batch of equipment. Others have no physical form, such as a training service or a new approval capability.
Deliverables are produced in execution and then go to the controlling processes to be checked. Delivering is not the same as succeeding. PMBOK 8 stresses attention to intended outcomes, and deliverables may not fully realize the project vision.
Three layers: data, information, reports
Execution keeps generating data. You must separate three layers, and the exam likes to show a string of numbers and ask “what is this?”
Work performance data are the raw observations and measurements collected from each activity being performed while carrying out the project work. They usually hold only the lowest level of detail and are passed to other processes to be refined. Examples are work completed, technical performance measures, actual start and finish dates of activities, story points completed, the number of defects, actual costs incurred and actual durations.
Work performance information is the result of analyzing the performance data against the project management plan, project documents and other information. “$8,000 spent to date” means nothing by itself, since you do not know whether that is too much or too little. Only when it is compared with the budgeted value of the work completed (say $5,000) do you know the project is $3,000 over. Comparison turns work performance data into work performance information. Comparing it again with the variance thresholds in the plan then tells you whether preventive or corrective action is needed.
A work performance report is the summarized work performance information presented in written or electronic form, intended to support decisions, prompt action or raise awareness. Common forms are status reports and progress reports, and also status dashboards, heat maps and stoplight charts. When you see the word “report,” think of something meant for decision-makers.
| Layer | What it is | Example | Where it is produced |
|---|---|---|---|
| Work performance data | Raw observations and measurements | $8,000 spent | Manage Project Execution |
| Work performance information | Data analyzed by comparing with the plan | Work completed is worth $5,000, actual spending is $8,000, so $3,000 over | The relevant monitoring and controlling processes |
| Work performance report | Summarized information, a document used for decisions | An overrun status report recommending added budget | Monitor and Control Project Performance |
Example: one string of numbers, three identities
A community senior-care services company is developing a mini-app for booking home-care visits. In week 3 the tester reports: 14 user stories completed, 9 defects, 310 hours logged. Those three numbers are data. The project manager compares them with the plan, which called for 18 stories done by now and no more than 5 defects, and gets “4 stories behind, defects over the limit.” That is information. On Friday the project manager writes the reasons for the lag, the effect on the go-live date and two recommended responses into a one-page status report for the sponsor. That is a report. It is the same thing at different levels of processing, and so it has different names.
Worked examples
Example 1 After the plan is approved, what does the project manager do next?
A pharmaceutical company starts a project to develop a cold-chain delivery service. The project management plan has been developed, approved and released to stakeholders. What should the project manager do NEXT?
Show answer and explanation
Correct answer: A
On the cold-chain delivery development project, the project management plan has been developed, approved and released. What is the project manager's next step after plan approval?
Once the plan is approved and released, the project moves from planning into execution: leading and performing the work defined in the plan, executing the work packages as planned and producing deliverables, which is exactly Manage Project Execution. Determining deliverable and timing information, estimating durations and resources, and redeveloping a sub-plan without new information or an identified change is also not the next step here. The signal words in the stem are “developed, approved and released,” which place the moment after planning has ended. In practice a predictive project usually holds a kick-off meeting to obtain commitment before concentrated work begins (common exam practice), but that option is not offered here, so choose executing the work packages as planned. The answer is A.
Why the other options are wrong
- B. Determining information about deliverables, activities and timing is done when developing the plan, and it should be completed before approval.
- C. Estimating activity durations and listing the resources required also belong to planning, and they are no longer the next step once the plan is approved.
- D. The stem provides no new information or identified change requiring the communications approach to be revised, so arbitrarily redeveloping that plan is not the next step. If new information emerges later, planning can still be updated iteratively.
Key takeaway After the plan is approved and released, the next step is to execute the work packages as planned.
Variation If the project charter has only just been approved, the next step is to develop the project management plan, not to execute. If the plan is approved and the customer then asks for added requirements, go through change control first.
Something wrong with this question?
Example 2 Is a string of raw values data, information or a report?
A project manager is in charge of developing an autonomous delivery vehicle, and the project is going well. To understand development of the navigation module, team members report percent of work complete, test pass rate, number of change requests, number of defects, actual cost and actual duration. What do these items represent?
Show answer and explanation
Correct answer: C
On the autonomous delivery vehicle project, the team reports a string of values: percent complete, test pass rate, number of change requests, number of defects, actual cost and actual duration. What are they? You decide by telling data, information and reports apart.
Work performance data are the raw observations and measurements taken directly from each activity while the project work is performed. Percent complete, number of defects, actual cost and actual duration are all typical examples. The stem lists only unprocessed values and says nothing about any analysis, correlation or integration. You decide this kind of question by asking only one thing: has it been analyzed, correlated or integrated? If not, it is data. Only after analysis and integration does it become information, and only when summarized into a document for decision-makers is it a report. The answer is C.
Why the other options are wrong
- A. A report is a document that summarizes work performance information for decisions and communication, such as a status report. The stem gives only scattered values, with no document and no conclusion.
- B. The schedule management plan sets out how the schedule is developed, monitored and controlled. It is a planning document, not values measured during the project.
- D. Information is the result of analyzing and integrating data, such as “$3,000 over budget.” The stem has only raw values, not yet analyzed or integrated.
Key takeaway Raw measurements are data; after analysis and integration they become information; summarized in a document they are a report.
Variation In the case of “9 defects, 4 more than the planned limit,” a comparison has been made, so it is work performance information. In the case of “turn the overrun and a recommendation for added budget into a status report for the sponsor,” it is a work performance report.
Something wrong with this question?
Common traps
Common trap
- The output of Manage Project Execution is work performance data, not work performance information and not a report. Information and reports are produced in monitoring and controlling.
- If a stem lists raw measurements such as percent complete, defect counts or actual costs, they are data. Do not treat them as a report just because the team “reported” them.
- Data become information through comparative analysis (comparing against project management plan components, project documents or other performance information). Raw measurements that have not been analyzed are still data.
- When the stem gives no new information requiring plan refinement, the next step after approval is to execute the work packages, not to estimate again or arbitrarily add to the plan.
Key takeaways
- Manage Project Execution: leading and performing the work defined in the project management plan and implementing approved changes to meet the project's objectives.
- After the plan is approved and released, the next step is to execute the work packages as planned.
- Inputs: project management plan, project documents, approved change requests, enterprise environmental factors, organizational process assets.
- Outputs: deliverables, work performance data, issue log, change requests, and various updates.
- A deliverable is unique and verifiable. Data are raw measurements, information is the result of comparative analysis, and a report is a summary for decision-makers.
- Data are produced in execution. Information and reports are produced in monitoring and controlling.
Lesson 2
Implementing Approved Changes, and Tools and Team Coordination During Execution
Lesson overview
Changes are not approved in execution, but they are carried out in execution. This lesson covers how approved changes return to execution and how the four kinds of action in a change request differ. It then covers the tools commonly used in execution: the project management information system, meetings (including the daily coordination meeting) and expert judgment, and how the project manager coordinates the team and adjusts plans. “Which kind of action is each of these three?” and “where does a new member look up lessons learned?” are typical questions. The previous lesson covered the process itself; the next covers the division of work between executing and monitoring and controlling, and quality.
How changes return to execution
Keep the division of work firmly in mind: approval of a change is completed in the monitoring and controlling process, and implementation of a change is completed in the executing process. Manage Project Execution reviews the impact of all project changes and implements approved changes, including corrective actions, preventive actions and defect repair. In a predictive project, once baselines are established, changes are approved through the formal process in Assess and Implement Changes. The plan and documents are then updated as needed, stakeholders are notified, and only then does the work return to execution. Adaptive projects usually manage changes through the backlog, evaluating and ordering them continuously, usually without a formal change approval process.
So when a question says “the change has been approved, the project management plan has been updated and stakeholders have been notified” and asks what comes next, the answer is to implement the change. There is no further evaluation, no further submission and no further notification, because the earlier steps are all done. Conversely, if the stem says the change has “just been raised,” you are nowhere near implementation.
The four kinds of action in a change request
A change request may include corrective action, preventive action, defect repair, or updates reflecting modified or added content. The four fit four situations, and the exam often puts them in the same question for you to match.
- Corrective action: addresses a performance variance that has already occurred and brings work performance back onto the plan, for example adding shifts to catch up after the schedule slips.
- Preventive action: addresses a variance that may occur in the future and acts before the problem happens, for example adjusting transport arrangements in advance because the forecast shows a typhoon.
- Defect repair: addresses a deliverable or component that is already nonconforming and restores it to conformity, for example reworking a nonconforming product.
- Update: changes a document, plan or baseline, for example adjusting the scope, schedule and cost baselines after the customer adds features.
A rule of thumb: look at the object and the timing. If the object is a “performance variance” that has already happened, it is corrective. If the object is a “nonconforming item,” it is defect repair. If the object is a “variance that might occur in the future,” it is preventive. If the object is “the document, plan or baseline itself,” it is an update.
Example: three actions on rental-bike charging cabinets
The team at a shared e-bike company finds that in a recent batch of charging cabinets the battery-bay latch was assembled with too little torque and might work loose in service. The cause is traced to a tightening tool whose torque setting was changed by mistake. The project manager resets the tool to the standard value so that later batches come out conforming. That is corrective action. The project manager recalls the cabinets already shipped and re-tightens the latches. That is defect repair. Before every shift the project manager adds a signed torque spot-check so the problem cannot recur. That is preventive action. In a predictive project with established baselines, all three first need approval through formal change control and then return to execution to be carried out. If it is finally decided to adjust the acceptance criteria or the delivery date as well, that item would be an update.
The project management information system
A project management information system (PMIS) is an information system consisting of the tools and techniques used to gather, integrate and disseminate the outputs of project management processes. It can include schedule tools, a configuration management system, a work authorization system, and information collection and distribution tools. It operates within the larger project management system and helps the team manage configuration, schedule, cost, documents and issues automatically. You can think of the schedule tool, configuration management system and work authorization system as parts of it, each looking after one area, while the PMIS can serve as a centralized access point.
So when someone asks “a new member wants to look up the lessons learned and all kinds of documents accumulated on the project in one place; what should they use?”, the answer is the project management information system, not one of its components. A geographically distributed team likewise relies on one document registry and change control system to avoid version confusion.
Meetings and the daily coordination meeting
Meetings are the main means of coordinating execution and include the kick-off meeting, status meetings, issue-resolution meetings, retrospectives and so on. PMBOK 8 specifically names the daily coordination meeting among this process's tools. A daily coordination meeting is a brief, daily collaboration meeting in which the team reviews progress from the previous day, declares intentions for the current day, and highlights any obstacles encountered or anticipated. It should stay short and focused on alignment. Matters that need deeper discussion and resolution are usually continued afterward by the people concerned.
Expert judgment and team coordination
Expert judgment comes from any group or person with specialized education, knowledge, skill, experience or training, and is used to assess inputs, choose options and judge problems. In execution, the project manager and the project team together manage and enable the execution of planned activities, harmonize the technical and functional aspects of the work within the broader project ecosystem, allocate resources, and adjust the project plans based on analysis of work performance data and information. If an adjustment touches a baseline, it must go through a change request and cannot be made directly.
Worked examples
Example 1 Which kind of change request does each of the three actions belong to?
At a furniture factory, a recent batch of desks shipped with drawer-slide mounting holes outside tolerance, creating a risk of loosening. The project manager and team trace the cause to a worn drill bit and submit change requests to replace the bit, recall the shipped desks for rework, and add a rule for regular inspection and replacement of drill bits. After assessment and approval, the team implements all three measures, and the hole positions return to within tolerance. What kinds of action are the project manager's three measures?
Show answer and explanation
Correct answer: C
At a furniture factory, desks' drawer-slide hole positions exceed tolerance. The project manager submitted change requests to replace the worn drill bit, recall the shipped desks for rework, and add a rule for regular bit inspection and replacement; all three were implemented after approval. Match each of the three to a type of change request.
Look at the object and the timing of each measure. Replacing the drill bit makes production conform again and addresses a variance that has already occurred, so it is corrective action. Recalling the shipped nonconforming desks to reprocess them has a nonconforming product as its object, so it is defect repair. Adding the inspection and replacement rule is meant to make sure the variance does not appear again in future, so it is preventive action. Corrective action, defect repair and preventive action match the three measures in order. The answer is C.
Why the other options are wrong
- A. The first is right but the last two are reversed: recalling for rework fixes a nonconforming product, which is defect repair, and the new rule is aimed at the future, which is preventive action.
- B. Replacing the bit makes the process conforming again and addresses a variance that has already occurred, so it is corrective action, not defect repair. Reworking the shipped desks is what is defect repair.
- D. Replacing the bit is not preventive action, because prevention addresses a variance that has not yet occurred. The new rule is not corrective action either, since it does not repair an existing variance.
Key takeaway A variance that has occurred calls for corrective action, a nonconforming product for defect repair, and a possible future variance for preventive action.
Variation If one more measure were added, “relax the acceptance tolerance from 1 mm to 2 mm and revise the contract annex,” it changes documents and a baseline and is an update. In a predictive project with established baselines, actions that touch baselines or other controlled items go through formal change control before implementation.
Something wrong with this question?
Example 2 Where does a new member go to look up lessons learned and documents in one place?
During project execution, a member is transferred away and a newly recruited person takes over the role. The organization has configured this project's PMIS as the central access point for project documents and lessons learned, but the newcomer does not know which system to use to find them. What should the project manager tell the newcomer to use?
Show answer and explanation
Correct answer: A
During execution a member is replaced, and the newcomer wants to look up the lessons learned and project documents the project has accumulated but does not know where. What tool should the project manager point them to?
A project management information system is an information system made up of the tools and techniques used to gather, integrate and disseminate the outputs of project management processes. It can include scheduling tools, a configuration management system, a work authorization system and information collection and distribution tools. A project's lessons learned and documents are gathered in it, so the newcomer can look them up in one place. The key in the stem is “lessons learned and various project documents,” which covers the project's information as a whole and so points to the overall system, not to one of its components. The answer is A.
Why the other options are wrong
- B. Scheduling software is only one component, used to build and track the schedule. It does not hold lessons learned and various documents.
- C. A work authorization system authorizes the start of work and ensures work begins in the right order. It has nothing to do with looking up reference material.
- D. A configuration management system controls configuration items and versions. It is likewise only a component and is not the entry point for looking up all project information.
Key takeaway To look up project documents and lessons learned in one place, use the project management information system.
Variation If the situation were “make sure all parties use the latest version and changes are recorded,” the answer is the configuration management system. If it were “a piece of work may start only after prerequisite work is complete,” it is the work authorization system.
Something wrong with this question?
Common traps
Common trap
- A change is approved in Assess and Implement Changes and implemented in Manage Project Execution. If it is approved, the plan is updated and stakeholders are notified, the next step is to implement. You do not evaluate again or submit again.
- Corrective action fixes a performance variance and defect repair fixes a nonconforming product. Do not mix them up just because both involve “rework.”
- Recalling shipped products to redo them is defect repair. Adding a new rule to prevent a recurrence is preventive action.
- The PMIS is the overall system. The schedule tool, configuration management system and work authorization system are only parts of it.
- When you adjust the plan during execution, anything that touches a baseline needs a change request. You cannot simply edit it.
Key takeaways
- A change is approved in monitoring and controlling (Assess and Implement Changes) and implemented in executing (Manage Project Execution).
- The four kinds of change request: corrective action, preventive action, defect repair, update.
- Corrective action addresses a performance variance that has occurred, defect repair a nonconforming deliverable, preventive action a possible future variance, and an update changes a document, plan or baseline.
- The project management information system can provide integrated access to configuration, schedule, cost and document tools.
- The daily coordination meeting aligns on yesterday's progress, today's plan and obstacles.
- If adjusting the plan touches a baseline, it must go through a change request.
Lesson 3
Executing Versus Monitoring and Controlling, and Quality Assurance Versus Quality Control
Lesson overview
The previous two lessons covered what happens in execution and how changes are implemented. This lesson covers the boundaries: what execution produces, what monitoring and controlling takes over, and who decides to adjust the plan. It then covers the two meanings of quality, where quality assurance looks at processes and quality control looks at deliverables. The traps in this kind of question are almost always about crossing a boundary: putting an analysis activity of monitoring and controlling into execution, or treating a check of deliverables as an audit of processes. This lesson closes the execution chapter in the governance topic, and the material that follows turns to issue management and change control.
Execution produces data; monitoring and controlling analyzes it
Manage Project Execution produces deliverables and work performance data. Execution also analyzes the data and information relevant to current work and makes necessary adjustments on that basis, while the continuing comparison, forecasting and reporting of overall performance are left to monitoring and controlling. Monitor and Control Project Performance involves evaluating performance compared to plan, tracking the utilization of resources, work completed and budget expended, and providing information to stakeholders. When analysis shows that an adjustment is needed and it touches a baseline or an artifact under configuration control, a change request is raised and handled in Assess and Implement Changes. Once approved, the approved change request goes back into Manage Project Execution to be implemented. This is a closed loop: execution produces the data, monitoring and controlling sees the variance, change control decides whether to change, and execution then makes the change.
The three roles can be remembered like this: execution does and records, monitoring and controlling compares and reports, and change control approves and governs. Execution also analyzes the performance data and information relevant to current work and adjusts the plan accordingly. The continuing comparison, forecasting and reporting of overall performance belong to monitoring and controlling, and whether to approve an adjustment that touches a baseline is decided by change control. When a question mentions “continuously comparing variances,” “forecasting” or “deciding whether to adjust the baseline,” it is mostly not the work of the execution process. “Implementing as planned,” “producing deliverables” and “collecting data” are the work of execution.
Example: defect counts keep rising; who acts?
At the weekly retrospective of an online consultation platform project, the tester notices that the defect count has risen two weeks in a row. Someone suggests immediately doubling the testing in the plan, starting tonight. The project manager does this instead. In execution, the daily defect data is recorded as it is, with nothing trimmed or polished. The data goes to monitoring and controlling, where the defect count is compared with the quality metrics and the cause is looked into. If the analysis concludes that more test rounds are needed and the test arrangements are part of a baseline or under configuration control (a predictive project), a change request is raised, the impact is evaluated, and only after approval is the plan changed and the work returned to execution to implement it. Uncontrolled content that can be adjusted within established authority can be adjusted directly in execution. But directly changing a baseline or controlled artifact skips the analysis and the approval.
Two meanings of quality management
PMBOK 8 says there are two ways in which quality should be addressed during execution. The first is during the construction of the project management process, which provides process quality assurance and value delivery throughout the project. The second is during deliverable construction and should be addressed through scope management and control, ensuring that deliverables are produced according to the agreed-upon requirements set in the scope baseline. For adaptive approaches, the scope baseline may be called prioritized requirements or the sprint backlog.
Quality assurance is about using project processes effectively. This effort involves following and meeting standards, and the related concepts are regulations, compliance and audits. Quality control is about creating project deliverables that meet defined specifications and thresholds, and the related concepts are product design, testing and defects. In one sentence: quality assurance asks whether the processes are effective, and quality control asks whether the deliverables are acceptable. Quality control is not a separate process. Verifying that deliverables meet requirements falls within monitoring and controlling of scope.
| Comparison | Quality assurance | Quality control |
|---|---|---|
| What it looks at | Whether processes follow standards and are effective | Whether deliverables meet specifications and thresholds |
| Typical means | Audits, process analysis, following standards | Testing, inspection, defect counts |
| Problems it finds | Inefficient workflows, not following the rules | Nonconforming products, many defects |
| What gets corrected | The process | The deliverable |
How do you decide which one a question wants? Look for clues. A stem that says “the audit found the team did not do peer reviews per the organization's standard” or “you want to judge whether the process is inefficient” describes a process problem, so choose quality assurance. A stem that says “sampling found nonconforming products” or “testing turned up many defects” describes a results problem, which is quality control. One situation can have both sides: with many defects you fix the defects (control) and also look into why they arise (assurance). When the question asks “how do you find the cause of poor performance,” examining the process is closer to assurance.
Key point
- Execution collects data and analyzes information relevant to the current work. Continuing comparison, forecasting and reporting of overall performance belong to monitoring and controlling. Adjusting a controlled baseline needs a change request, and change control decides.
- Quality assurance looks at processes (audits, standards, compliance); quality control looks at deliverables (testing, defects).
- Manage Quality Assurance and Manage Project Execution are both processes of the Governance performance domain; Manage Quality Assurance is performed throughout the project.
Worked examples
Example 1 Rework keeps recurring: check the process or the deliverables?
On a power-tool project in execution, components from the last three batches keep needing rework. An internal audit finds that the team did not carry out peer reviews to the standard the organization requires. The project manager wants to judge whether the review process itself is inefficient and to find the cause of the poor performance. Which process should the project manager use?
Show answer and explanation
Correct answer: A
On a power-tool project in execution, components from three batches keep being reworked, and an internal audit finds the team did not do peer reviews to the standard the organization requires. The project manager wants to judge whether the review process itself is inefficient and find the cause of the poor performance. Which process should be used?
The clues are “audit,” “the standard the organization requires” and “whether the review process itself is inefficient.” All three point to the process, not the product. Manage Quality Assurance is concerned with whether project processes are used effectively, following and meeting standards, and it uses audits and similar means to identify inefficient processes and the causes of poor performance, which matches exactly what the question asks. The answer is A.
Why the other options are wrong
- B. Monitor and Control Scope primarily verifies whether deliverables meet specifications and quality requirements. Although its tools can include root cause analysis, audits and inspections, evaluating whether project processes are effective and identifying causes of poor performance belongs more directly to Manage Quality Assurance.
- C. Monitor and Control Project Performance compares actual performance with the plan, analyzes variances and provides status information. Process audits are not its main means.
- D. Manage Project Execution leads and performs the work in the plan and produces deliverables and data. It is what gets audited, not the means of evaluating process effectiveness.
Key takeaway Manage Quality Assurance looks at whether processes are effective (audits, standards). Monitor and Control Scope measures and verifies whether deliverables meet quality requirements.
Variation If “sampling finds a batch of components outside the dimensional specification and you must judge whether the batch passes,” that is verifying deliverable quality under Monitor and Control Scope. If the problem is “how to improve the review process,” it returns to Manage Quality Assurance.
Something wrong with this question?
Example 2 Defects are rising: can execution change the plan directly?
A predictive meeting-platform project with established baselines is in execution. At the weekly retrospective, team members notice that the number of test defects has risen two weeks in a row, and someone suggests analyzing the trend directly within the execution process and immediately adjusting the test arrangements in the project management plan, which are under configuration control. What should the project manager do?
Show answer and explanation
Correct answer: C
A predictive meeting-platform project with established baselines is in execution. The weekly retrospective shows defects rising two weeks in a row, and someone suggests analyzing the trend directly in execution and changing the test arrangements in the project management plan that are under configuration control.
In PMBOK 8, Manage Project Execution itself includes analyzing the performance data and information relevant to current work and making necessary adjustments, so analysis in execution is fine. But a defect count that keeps rising is a comparison of overall performance, and continuing comparison, forecasting and reporting are the job of the monitoring and controlling processes. The stem establishes a predictive project with baselines and states that the test arrangements are under configuration control, so adjusting them must be raised as a change request under the change management rules and implemented only after approval through Assess and Implement Changes by the designated approver. So continue executing, record the data honestly, let monitoring and controlling analyze it, and raise a change request if an adjustment is needed. The answer is C.
Why the other options are wrong
- A. Revising the test arrangements in the project management plan directly means changing controlled content without a change request or approval. The error is changing it directly and bypassing change control, not that “execution cannot analyze.”
- B. Rising defects call first for analysis of the cause, not an unconditional pause. Whether to pause is decided after analysis under established authority and governance rules, and a change request is raised only when a change to the controlled plan is involved. The stem also gives no basis for “wait for an independent assessment.”
- D. Work performance data are the basis for monitoring and controlling analysis. Recording only items that passed would distort the data, and monitoring could not find the real variance.
Key takeaway Execution can analyze data on current work, while comparison of overall performance is done in monitoring and controlling, and plan adjustments go through a change request.
Variation If the defect data have been analyzed and the conclusion is to add a regression-test round and extend by two weeks, the next step is to submit a change request. Once the change is approved, return to execution to implement it.
Something wrong with this question?
Common traps
Common trap
- In PMBOK 8, the execution process collects data and also analyzes information relevant to current work, assesses the impact of changes and makes necessary adjustments. Monitor and Control Project Performance focuses on continuously tracking, reviewing, comparing, forecasting and reporting overall performance, and changes that touch controlled baselines then go to Assess and Implement Changes. A test-taking tip: when an option asks you to “judge whether the variance is serious and whether a change is needed,” it usually points to monitoring and controlling or to change control.
- In a predictive project, anything under a baseline or under configuration control that must be adjusted requires a change request approved through the formal process, and cannot be rewritten on your own in execution. In an adaptive project, changes are usually recorded in the backlog, assessed for impact and reprioritized, without a formal change request or approval. In execution you can adjust uncontrolled content within established authority and change management rules.
- Many defects do not necessarily mean pausing the project. Look at the data and find the cause first, and raise a change request only when the response touches a baseline or an artifact under configuration control.
- Recording only the “good data” distorts the analysis in monitoring and controlling. Data must be collected honestly.
- When an audit finds the standard was not followed, that is a process problem, so use quality assurance. It does not mean inspecting a few more products.
Key takeaways
- Execution produces deliverables and work performance data and analyzes information relevant to the current work. The continuing comparison, forecasting and reporting of overall performance go to monitoring and controlling.
- Monitoring and controlling compares performance with the plan and finds variances. When the needed adjustment touches a baseline or an artifact under configuration control, a change request is raised. Other adjustments follow established authority and change management rules.
- A plan adjustment that touches a baseline must be approved through Assess and Implement Changes, and execution must not change it on its own.
- Quality assurance: are the processes effective? Its means are audits and following standards.
- Quality control: are the deliverables acceptable? Its means are testing, inspection and defect counts.
- Stem clues: “did they follow the standard” points to assurance, and “the product is nonconforming” points to control.
This chapter has 11 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.