Governance and Business Environment
Issue Management
PMP · Governance and Business Environment · 4 lessons · about 46 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Things go wrong on every project: a vendor slips, a core module fails acceptance, or another department's approval holds the team up. The project manager's job is not to keep problems from happening but to make sure they are seen, recorded, analyzed and resolved, and to know where to escalate when they cannot be resolved. This is the content of ECO: Business Environment domain, Task 4 (Remove impediments and manage issues). The chapter first covers the issue log and the difference between an issue, a risk and a change request. It then covers the steps of problem solving (the six steps PMBOK 8 lists, which "generally" apply and need not all be completed in every situation; the exam expects you to answer in this order) and root cause analysis. Next it covers how to prioritize several issues at once and when to escalate. Finally it covers the difference between an impediment and an issue, and how to handle each kind of impediment.
The answer patterns in this chapter are very consistent. An issue that has already occurred is recorded in the issue log, its impact and urgency are assessed to set a priority, and urgent ones are acted on immediately. Define the problem and find the root cause before choosing a solution. When something goes beyond your authority, escalate promptly along the agreed path, bringing the issue, its impact and your proposed response. For an impediment, assess first and coordinate first; do not bypass the process and do not spend money first.
Lessons in this chapter
- Lesson 1: Issue Log: Issues, Risks and Change Requests Compared. What the log contains, how it is created and maintained; an issue has already occurred, a risk has not, and a change request is needed when a document, deliverable or baseline must be formally modified, with its status tracked in the change log; when a risk occurs it becomes an issue.
- Lesson 2: Problem Solving: The Six Steps and Root Cause Analysis. Define the problem, identify the root cause, generate possible solutions, choose the best solution, implement it, and verify its effectiveness (the exam expects you to answer in this order); look for the root cause first when a problem is widespread or keeps recurring; decide together with the team.
- Lesson 3: Issue Priority and Escalation. Rank issues by their impact on project objectives and by urgency (for the critical path, focus on the effect on the completion date); escalate along the path agreed in advance when an issue is beyond your authority; when an issue is beyond the team's capability or authority, coordinate resources or escalate along the governance path, and if the solution involves a formal change, then submit a change request (common exam practice: use a change request to bring in outside help).
- Lesson 4: Removing Impediments: Impediments vs. Issues, Types and Handling. An impediment is an obstacle that prevents the team from achieving its objectives and can come from inside or outside the team; four types (process, resource, external dependency, inside the team); assess, then coordinate, then escalate; look for the root cause when an impediment recurs.
Chapter map
An issue occurs
- Record: issue log (description, owner, due date, status) risks → risk register baseline must change → submit a change request (track its status in the change log), then update the baseline after approval
- Resolve: define the problem → root cause → solutions → choose → implement → verify
- Prioritize: by impact on schedule (critical path), cost and satisfaction
- Beyond your authority: escalate along the escalation path (issue + impact + proposed response)
- Impediments (from inside or outside the team): assess impact → communicate and coordinate → escalate if needed
To prevent recurrence: lessons learned register
To practice this chapter, use the chapter exercises. Start with the core questions, then do the required ones.
Lesson 1
Issue Log: Issues, Risks and Change Requests Compared
Lesson overview
Things go wrong on every project: a vendor slips, a core module fails acceptance, or another department's approval holds the team up. No project manager can guarantee that problems will never occur. The job is to spot potential problems early, take preventive action, and make sure the problems that do occur are seen, recorded, analyzed and resolved. The first step depends on the issue log. This lesson covers what goes into an issue log, where it is created and how it is maintained, and then the three concepts most often confused, the issue, the risk and the change request, and where each belongs. The next three lessons cover the steps of problem solving, priority and escalation, and removing impediments.
What the issue log is
An issue log is a project document where information about issues is recorded and monitored. Every project has issues, and the value of the log is that every issue has an owner, a due date and a status, so that none is forgotten for lack of follow-up and no two people end up handling the same thing separately.
PMBOK 8 defines the issue log as a project document for recording and monitoring issues. The fields below are common practice. A log usually contains the issue description, the owner and the resolution date, and often also the date the issue arose, the cause, short-term and long-term solutions and the current status. Before an issue is closed, the closing criterion should be written down: what counts as resolved, and who confirms it. Without a closing criterion, people will hold different views on whether an issue is resolved, and issues will hang open in the log for a long time.
| Field | What to write | Why |
|---|---|---|
| Issue description | What happened and what it affects | So others can understand it |
| Owner | Who is responsible for resolving it | Avoids duplicated handling or no handling |
| Resolution date | The latest date it should be resolved | So it can be followed up and escalated |
| Status and closing criterion | In progress, resolved; what counts as resolved and who confirms it | So it can be closed rather than left hanging |
Where it is created and how it is maintained
The issue log is first created in the Manage Project Execution process, as an output of that process. After that it is updated continuously as part of monitoring: a new issue is added when it appears, and a resolved issue is closed after its status is updated. A log that no one has updated for two months is a common management defect; the project manager should restore the rhythm of maintenance, record new issues promptly and close resolved ones promptly.
As soon as an issue occurs, record it promptly, assess its impact and priority according to its urgency, and begin at once, within your authority, to reduce its impact; do not start by talking about a delay. If the measures involve a controlled artifact or a baseline, submit a change request and handle it through the process. Items that need follow-through, such as corrective items raised at a review meeting, follow the same management logic: prioritize them, assign an owner and a due date, and then keep tracking them. Before a corrective action is implemented, likewise first record the issue in the log and analyze the effect of the action.
The issue log is not the only "register"; several project documents divide the work. The issue log covers problems that have already occurred. The risk register covers uncertain events that have not yet occurred. The change log covers submitted change requests. The stakeholder register covers people. The lessons learned register covers the knowledge gained, for reuse in current and future work.
Issues, risks and change requests
An issue is a current condition or situation that may have an impact on one or more project objectives; it has already occurred and may require immediate action or management attention. A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on objectives and has not yet happened. A change request is a formal proposal to modify any document, deliverable or baseline.
Use the timeline to tell them apart. If it has not happened, it is a risk. If it has happened, it is an issue. A change request arises only when a document, deliverable or baseline must be formally modified, or when a corrective action, preventive action or defect repair has to be handled through the change process (on a predictive project, once a baseline has been established, all changes should be assessed and implemented through a formal process). When a risk occurs, treat it as an issue: record it in the issue log to track it, and update the status of that risk in the risk register (common exam practice; the ECO expects you to recognize when a risk will turn into an issue). To keep the same issue from happening again, analyze and remove the root cause, implement a preventive action if necessary, and record the lesson in the lessons learned register for reuse in current and future work. Logging the issue one more time does not prevent it from recurring.
The way an issue is dealt with is not always a change. Logging an issue, analyzing it and handling it without modifying any controlled item do not necessarily generate a change request. A change request is raised only when the solution requires formally modifying a controlled document, deliverable or baseline, for example adjusting scope, schedule or cost, and then Assess and Implement Changes handles it. If the solution the team proposes for a logged issue requires adjusting the approved delivery scope, the change control procedure must be followed.
An issue that was never logged still has to be dealt with. Suppose that in month five of a predictive project an issue appears that had never been listed in the risk register. The project manager first records it in the issue log and assesses its impact, then agrees a solution with the team and stakeholders. The project manager does not ignore it because it was never registered, and does not first ask why it was not identified.
Example: one event, three records
On a smart medicine-cabinet project, the cooling-module supplier phones on Monday: “We may not be able to gather enough compressors before the 15th of next month.” That is a risk; it has not happened, so it goes in the risk register. On Wednesday the supplier confirms that this batch of compressors really is out of stock and delivery will slip three weeks. That is an issue, recorded in the issue log, with the procurement manager as owner and a due date of Friday for an alternative plan. The team finds a compatible model, but it requires changing a structural drawing, which touches the approved design baseline, so a change request is submitted and recorded in the change log. Afterward, the project manager writes “dual-source critical components” into the lessons learned register.
Worked examples
Example 1 Several people investigate the same defect: how to prevent it in advance
While reviewing the schedule, a project manager finds that the team is behind. The cause is that a core module did not meet the acceptance criteria, and several members each investigated and fixed it independently, doing a great deal of duplicated work. What could the project manager have done in advance to avoid this waste?
Show answer and explanation
Correct answer: D
The team is behind because a core module failed acceptance and several members each investigated and fixed it on their own, duplicating work. The question is what the project manager could have done in advance to avoid this waste.
The waste comes from the lack of a single record and division of work: nobody knew that others were already working on the same problem. The issue log records and monitors issues that have occurred, including the description, the owner and the resolution date. If members are required to log an issue as soon as they find it and an owner is assigned, one look at the log shows that someone is already handling it, and the duplicated work disappears. The answer is D.
Why the other options are wrong
- A. The risk management plan sets out how risk management is carried out, and the response information for specific risks is recorded in the risk register, which deals with uncertain events that have not yet occurred. This defect had already occurred, so it should have been logged as an issue with a named owner. Adding a response plan does not settle who is responsible for handling it.
- B. Having everyone work out the best fix separately is still everyone working on their own, so the duplication remains; choosing a solution is also a step that comes after logging the issue and assigning the work.
- C. A change request is for modifying approved content. Not every defect needs one, and it is less direct than simply assigning an owner.
Key takeaway Log an issue in the issue log and assign an owner as soon as it occurs; this is the most direct way to avoid duplicated handling.
Variation If issues in the log stay open for a long time, add closure criteria and due dates and resume regular maintenance of the log.
Something wrong with this question?
Example 2 A panel on the critical path is confirmed late: what to do first
Several batches of room-control panels for a hotel chain's smart-room project are produced at an overseas factory. The project manager is told that the first batch of panels will arrive late. Installing these panels is on the critical path, and the delay will cause the project to miss a milestone. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
On a hotel chain's smart-room project, the first batch of panels from an overseas factory will arrive late. Installing them is on the critical path, and the delay will make the project miss a milestone. What should the project manager do first?
The delay has been confirmed, so a current condition now exists that will affect the milestone; manage it as an issue rather than as an uncertain risk. Because the issue comes from an external factory, the project manager first confirms the cause, actual impact and feasible alternatives with the factory. With those facts established, the project manager logs the issue and develops an action plan to reduce the impact on the milestone. The answer is A.
Why the other options are wrong
- B. The lessons learned register can be updated during the project, but when an issue has just appeared the priority is to log, assess and address it; revisions to the project management plan must also follow the applicable change process.
- C. Rescheduling that touches the baseline requires assessment and the applicable change-control process. Timely notice to relevant stakeholders may be appropriate, but that does not make unilateral rescheduling the first action.
- D. Assigning blame is a retrospective commercial action. It does nothing to protect the milestone now, so it is not the first thing to do.
Key takeaway A confirmed external delay is an issue: first verify the cause, impact and alternatives with the external factory, then log and address it rather than putting it in the risk register or submitting a change first.
Variation If the stem said “the supplier says the first batch may be late,” it has not happened and is a risk: record it in the risk register and assess it; once the delay is confirmed it becomes an issue.
Something wrong with this question?
Common traps
Common trap
- A delay, defect or late payment that has already occurred is an issue and goes in the issue log; it is neither a risk nor a change request.
- When an issue occurs, record it promptly, assess the impact and reduce it within your authority right away; do not rush to ask for a delay or a change.
- The risk management plan sets out how risk management is carried out, and the risk register records identified risks that have not yet occurred, together with their response information. A defect that has already occurred is an issue: record it in the issue log with an owner and a due date, and do not settle for writing a response plan afterward.
- Handling an issue is not the same as making a change: a change request is raised only when the solution must formally modify a controlled document, deliverable or baseline.
- To keep the same issue from happening again, analyze and remove the root cause, implement a preventive action if necessary, and record the lesson in the lessons learned register; do not just log the issue one more time.
Key takeaways
- The issue log is for recording and monitoring issues; the description, owner, resolution date, and status with closing criterion are common practice.
- The issue log is first created in Manage Project Execution and then updated continuously through monitoring; resolved issues are closed.
- Already occurred means issue; not yet occurred means risk. A change request arises only when a controlled item (a document, deliverable or baseline) must be formally modified, or when a corrective action, preventive action or defect repair has to be handled through the change process.
- After a risk occurs, update its status in the risk register and record the situation that has occurred in the issue log as an issue.
- When an issue occurs, record it promptly and act at once; submit a change request only if the solution needs a formal modification to a controlled item or baseline.
- To prevent recurrence: remove the root cause, implement a preventive action if necessary, and record the lesson in the lessons learned register.
Lesson 2
Problem Solving: The Six Steps and Root Cause Analysis
Lesson overview
Once an issue is logged, how is it resolved? This is the core topic in issue management. The scenarios in the stems vary widely: a member reports bad news, deliverables are widely nonconforming, the same mistake keeps recurring, a third party is late, requirements are vague. Behind them is the same logic: first understand the problem, then find the root cause, then compare solutions, and only then choose, carry out and verify. This lesson covers the six steps, root cause analysis, how the project manager works through a problem with the team, and the standard responses to common situations. The previous lesson covered the issue log; the next covers priority and escalation.
The six steps
“Problem-solving entails finding solutions for issues or challenges. Problem-solving can include gathering additional information; critical thinking; and creative, quantitative, and/or logical approaches. Effective and systematic problem-solving is a fundamental element in quality assurance and quality improvement. Using a structured problem-solving method can help eliminate the problem and develop a long-lasting solution. Problem-solving methods generally include the following actions: Define the problem, Identify the root cause, Generate possible solutions, Choose the best solution, Implement the solution, and Verify solution effectiveness.”
The order is a favorite exam target: questions often turn the steps into options and ask which to do first. The method is to read from the stem which step the situation has reached and pick the next one. PMBOK 8 says problem-solving methods “generally include” these actions, which does not mean every situation requires every step in sequence. The common exam practice is this: when a new problem arises, first define it, which includes verifying the facts and assessing its scope and impact; then find the root cause; then list solutions; then choose, implement and verify. In an emergency you may first take the necessary containment measures and then go on to analyze the root cause and develop a lasting solution. When options include “cost-benefit analysis” or “choose a solution,” first ask whether the earlier impact assessment and cause analysis have been done. If not, it is not yet that step's turn.
| Step | What to do | Common mistake |
|---|---|---|
| Define the problem | State what happened, how large it is and what it affects | Acting on a mere “something went wrong” |
| Identify the root cause | Dig down to the underlying source, not just the surface | Treating only the symptom |
| Generate possible solutions | List several options together with the team | Thinking of only one option |
| Choose the best solution | Compare by impact, cost and risk | Deciding on personal preference |
| Implement the solution | Carry it out as planned, going through change control if needed | Bypassing the process |
| Verify effectiveness | Confirm that the problem is really solved | Closing it as soon as the work is done |
Root cause analysis
Root cause analysis is an analytical method used to determine the basic underlying reason that causes a variance, defect, or risk. A root cause may underlie more than one variance, defect, or risk. When all root causes for a problem are removed, the problem does not recur.
This gives two rules of application. First, for a widespread problem, look for the root cause first. If nearly every member's deliverable is nonconforming, the cause is probably shared, such as differing understandings of the requirements or acceptance criteria that were never made clear. Punishing one person or demanding rework across the board does not get at the source. Second, if the same problem keeps recurring, the earlier measures only treated the symptom, so root cause analysis has to be done again rather than continuing with temporary repairs. When an existing measure has proved ineffective, first analyze the root cause and log the issue, then develop a new measure.
Solving it with the team
For a problem the team can solve internally, the project manager first assesses the impact, compares solutions and decides together with the team. The project manager neither decides alone nor passes everything upward. For problems that involve several parties, work with the relevant stakeholders to agree on a solution. If the solution is not accepted, keep communicating and adjust it together, and proceed under the established decision rules; where necessary, the person with authority decides or the matter is escalated. Agreement from everyone is not required in every situation.
When facing bad news, first thank the member for surfacing the problem, and then focus on how to recover rather than on assigning blame. Only a psychologically safe team will surface problems early, and problems surfaced early are usually smaller and cheaper.
Responses to common situations (common exam practice):
- Delay caused by resource overload: log it first and agree a solution with the team; do not directly swap people or cut scope.
- Delay by an external party: clarify the cause and constraints with the external party and assess the impact with the team; develop alternatives, agree a way forward with the relevant parties, and carry it out.
- Variance caused by unclear requirements: first analyze with the team where the work departs from what was needed, then decide on rework and correction.
- A problem not yet confirmed: verify the facts first, then decide whether to adjust the arrangements.
- Performance problems: first verify and define the problem and assess its impact, then perform root cause analysis; bring in an expert if skills are lacking.
Example: acceptance keeps failing, so where is the problem?
On an appointment-booking mini-app for a community hospital, over three consecutive iterations the pass rate on feature acceptance falls from 90% to about 56%. The project manager does not immediately demand overtime and rework. First the problem is defined: of the 36 features in the last three iterations, 16 failed, concentrated in two kinds, “cancel appointment” and “reschedule appointment.” Then, reviewing with developer and tester representatives, they find that the user stories have no acceptance criteria, and developers and testers each work from their own understanding. There are three possible solutions: add acceptance criteria to every story and confirm them one by one at the iteration planning meeting; add a mid-iteration review; or replace some members. The team chooses the first, which is cheapest and corresponds directly to the cause. After two iterations the pass rate is back to 88%, and only then is the issue closed.
Worked examples
Example 1 Almost every member's deliverable is nonconforming: what to do first
A project manager leading a team spread across several time zones to develop an online-course platform finds that the deliverables submitted by almost every member fail to meet requirements. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
A team spread across several time zones is developing an online-course platform, and the deliverables submitted by almost every member fail to meet requirements. The question is what the project manager does first, and the basis is the first step of problem solving.
When nonconformance is widespread in the same way, there is probably a common cause, such as a different understanding of the requirements. Problem solving begins by defining the problem and identifying the root cause, and only then turns to countermeasures. So the project manager first reviews the production process with the team to find at which step the problem arises, including whether the requirements were misunderstood. Note that the three wrong options share the same flaw: they all reach a conclusion or issue instructions before the cause is understood. Find the cause before acting; this also reflects the governance approach of analyzing before taking action. The answer is D.
Why the other options are wrong
- A. Issuing a warning before the cause is known does not solve the problem and damages team morale.
- B. Merely telling the sponsor about a delay, with no analysis and no action, shows a lack of initiative.
- C. Demanding rework without investigating the cause means the reworked output is likely to fail again, adding cost and delay.
Key takeaway When a problem is widespread, find the root cause first and talk about countermeasures afterward.
Variation If the stem said only one member's deliverable was nonconforming, first talk with that member to find out whether skills or resources are lacking; a review with the whole team is not needed.
Something wrong with this question?
Example 2 The same kind of error appears every few weeks and only gets a temporary fix
On an online food-ordering platform project, the same kind of order-status synchronization error recurs every few weeks, and each time the team patches it temporarily. What should the project manager do?
Show answer and explanation
Correct answer: A
On an online food-ordering platform project, the same kind of order-status synchronization error recurs every few weeks, and the team patches it temporarily each time. What should the project manager do?
When the same kind of issue keeps recurring, the temporary fixes are treating only the symptom and have not removed the cause. Root cause analysis is used to determine the underlying source of a defect, and once all the root causes are eliminated the problem will not recur. So the project manager should conduct a root cause analysis, find the underlying cause and then take action. The signal phrases in this kind of question, “every few weeks” and “temporarily fixed each time,” point to treating the symptom, not the cause. Once the root cause analysis is done, the measures can be targeted. The answer is A.
Why the other options are wrong
- B. Keeping the temporary fix and adding more log entries means the issue will keep recurring.
- C. Adding testers and inspections only finds problems faster. It does not remove the cause and costs more.
- D. Downgrading it to low priority lets a latent defect keep consuming team effort over a long time. “Fixed quickly every time” does not mean no impact.
Key takeaway When a problem recurs, do a root cause analysis; do not stop at temporary fixes.
Variation If the stem said “first occurrence, minor impact,” log it and handle it through the normal process; root cause analysis becomes the preferred answer when the problem recurs or is widespread.
Something wrong with this question?
Common traps
Common trap
- If the problem has not been defined and the cause not found, do not jump to choosing a solution or doing a cost-benefit analysis, much less demand rework or warn the team first.
- For a widespread or recurring problem, the answer is often root cause analysis, not assigning blame or adding inspection staff.
- Decide on solutions together with the team, and do not escalate everything; when several parties are involved, consult the relevant stakeholders.
- On hearing bad news, thank the member first and discuss recovery afterward, not blame first.
- Finishing the solution does not close the issue; verify that it works.
Key takeaways
- The six steps: define the problem, identify the root cause, generate possible solutions, choose the best solution, implement the solution, and verify solution effectiveness.
- When a problem arises, assess the impact first, then find the cause, and choose a solution last.
- When all root causes of a problem are removed, the problem does not recur; one root cause may underlie several problems.
- For widespread or recurring problems, do root cause analysis first.
- Assess and decide with the team; for problems involving several parties, work with the relevant stakeholders; on bad news, thank first and then recover.
- After implementation, verify; close the issue only once it is confirmed effective.
Lesson 3
Issue Priority and Escalation
Lesson overview
An issue log usually holds more than one issue, while the project manager's time, the team's capacity and the budget are all limited. Which to handle first, what to do when you cannot handle one, and when to hand it to a higher level are the subject of this lesson: prioritizing issues, and the escalation mechanism that governance provides. The answers to this kind of question are very consistent. Rank by impact first. When an issue is beyond your authority, escalate promptly along the agreed path, bringing the issue, its impact and your proposed response. When a high-priority issue is beyond the team's capability, bring in outside help; do not close the issue or avoid it. The previous lesson covered how to resolve issues; the next covers how to remove impediments.
Prioritize first
When several issues exist at once, you cannot give equal effort to all of them. Rank them by their impact on schedule, cost, scope, quality and satisfaction, and deal first with the one with the greatest impact and urgency. Issues that affect the critical path usually come first, because the critical path is usually the path with the least float and a delay in its activities is more likely to affect the project completion date (whether delivery actually slips also depends on total float, constraints and schedule adjustments). For issues that affect customer satisfaction or may break the budget, the order depends on the size of the impact and the time window.
Two questions give a quick ranking: if this issue is not resolved, how much damage will it do to the objectives? When will that damage arrive? Issues with large damage arriving soon go first; issues with small damage and some buffer go later, but are still logged, with an owner and a due date. Prioritizing does not mean handling only the biggest issue and ignoring the rest; it means setting a clear order and reviewing it regularly, because priorities change as the project advances.
| Issue | Impact | Urgency | Rank |
|---|---|---|---|
| Equipment delay on the critical path | A milestone may be missed | Within this week | 1 |
| 4% budget overrun | Must be explained to the sponsor | Within this month | 2 |
| Customer dislikes the interface color | Affects satisfaction, does not affect delivery | Before the next iteration | 3 |
When to escalate
The escalation mechanism that governance provides is for matters beyond the project team's authority. Note that PMBOK 8 lists escalation as one of two governance components that predictive environments “may call for” as additions (alongside investment control): “Escalation is often useful in hierarchical organizations where decision-making authority includes individuals outside of project team members, or in organizations in which higher-ranking individuals have greater ability to remove persistent obstacles or resolve conflicts to enhance a project's probability of success.” Among the information governance should report, it also mentions the “escalation criteria” for risks. When an issue exceeds the project manager's authority and needs a decision, resources or coordination from a higher level, escalate it along the escalation path agreed in advance under governance. An issue serious enough to go beyond the project level should be escalated promptly along the established path (common exam practice: do not wait until the issue has become unmanageable).
Three points to watch when escalating. First, look at the project's established escalation process and act according to it. To whom to escalate and who decides are set by the project's governance arrangements or organizational procedures (it could be the sponsor, a steering committee, the change control board or another authorized person); the project manager cannot overstep authority. Second, the criteria for escalation, that is, which situations call for it, should be defined, recorded and communicated in advance (common exam practice: agreed between the project manager and the sponsor), and not left to personal feeling. If the team does not agree on “what counts as an issue to escalate,” the criteria should be established; the answer is not to let each member make that judgment independently. Third (common exam practice), when escalating, make clear what the issue is, what impact it has on the project and what response you already have, instead of just throwing over a bare “something went wrong.”
When the escalation path is unclear and an issue has dragged on with no one making a decision, that is a gap in the governance arrangements or their documentation. What the project manager should do is first find out what escalation path already exists and, if it is missing, the common exam practice is to ask the sponsor and, if the project has one, the steering committee or other governance authority to define it, rather than going to some leader of the project manager's own choosing for a decision.
Issues beyond the team's capability
When a high-priority issue exceeds the team's capability or authority, PMBOK 8 has the sponsor and other senior roles help secure resources and deal with matters beyond the project team's authority; in practice the project manager coordinates with them or escalates along the governance path. Common exam practice: the project manager first reviews the issue. In a predictive environment, when adding specialists or budget would change controlled content such as existing authorizations, the budget or a baseline, first submit a change request and, once it is approved, bring in outside help through the resource acquisition or procurement arrangements (on adaptive projects such changes are usually handled through backlog management); if it is within existing authority, simply coordinate. Do not close the issue directly and do not shrink the scope to avoid it (an approved scope adjustment is itself a legitimate solution, but it cannot be used as a way to dodge an issue). A late payment that has already occurred is an issue and should be resolved by communicating directly with the stakeholders, not merely recorded or turned into a lesson learned.
Example: a complete escalation
A farmers' market digitization project is midway through when the third-party payment interface for the core settlement module needs recertification because of a regulatory change, which will take at least six weeks. The project manager has no authority to add budget and cannot adjust the contract. First the project manager ranks the issue by impact: it is on the critical path, so it ranks first. Then the project manager drafts the escalation: the issue is a six-week delay in certification; the impact is that go-live slips by a month and a half and the market's opening event suffers; there are two possible responses, one is expedited certification, which needs an extra $80,000 of budget, and the other is going live first with offline settlement and adding online payment later. The project manager submits it to the sponsor and the steering committee along the agreed path, asks for a decision before Friday's meeting and informs the stakeholders at the same time.
Worked examples
Example 1 A major issue beyond your authority: how to escalate
After a cross-border logistics project enters execution, a major problem arises that exceeds the project manager's authority to handle and will affect a key milestone, so management must be informed immediately. Which approach is MOST appropriate?
Show answer and explanation
Correct answer: C
During execution of a cross-border logistics project, a major problem beyond the project manager's authority arises that will affect a key milestone, and management must be informed. The most appropriate way to handle it must be chosen.
The governance escalation mechanism exists to handle matters beyond the project team's authority. A major problem should be escalated promptly along the path agreed in advance, making three things clear: what the problem is, what impact it has on the project and how it is proposed to respond, so that management can decide quickly. Note that “wait for a clear result before reporting,” “just send an email and wait for a reply” and “align internally first” are all ways of delaying escalation; a major problem calls for timeliness and transparency. The answer is C.
Why the other options are wrong
- A. Waiting for a clear result before reporting misses the time for a decision, and management is left on the back foot by outdated information.
- B. Sending only an email and waiting for a reply lacks proactive communication, and a major problem may be delayed as a result.
- D. Aligning internally first and then having the sponsor relay it adds delay when the major problem requires immediate escalation; the option also does not state the problem's impact or the proposed response.
Key takeaway Escalate a major problem promptly along the escalation path, and explain the problem, its impact and the proposed response.
Variation A minor issue the team can handle internally need not be escalated; if the path has not yet been defined, first ask the sponsor and any existing steering committee or other governance authority to define it.
Something wrong with this question?
Example 2 A high-priority issue beyond the team's capability: what to do
A warehouse-system upgrade project is in execution. While reviewing the issue log, the project manager finds that several high-priority issues remain open. Most of them can be resolved only by specialists from outside the project team. The current resource plan and budget have no provision for such specialist support, and the project manager has no authority to add budget on his or her own. What is the BEST action for the project manager to take?
Show answer and explanation
Correct answer: C
On a warehouse-system upgrade project, the issue log has several open high-priority issues, most of which can be resolved only by specialists outside the team. What should the project manager do best?
High-priority issues cannot be shelved, and having the team learn the subject in a short time would be too late. The right approach is first to review the issues one by one, confirm that outside specialist capability is needed, and assess the cost, schedule, resource and risk impacts of bringing it in. Because the current resource plan and budget have no provision for this support and the project manager cannot add budget, the assessment is included in a change request; the experts are brought in only after approval. If experts can be assigned within the existing plan and budget, simply coordinate to obtain them. The answer is C.
Why the other options are wrong
- A. Closing the issues only makes the log stop showing them; the problems are still there. An issue can be closed only after it is truly resolved.
- B. Learning the expertise takes time, and it is hard to resolve these high-priority issues one by one in a short time that way.
- D. Reducing scope avoids the problem, and a scope adjustment also requires approval through change control; the project manager has no authority to cut it directly.
Key takeaway When a high-priority issue is beyond the team's capability, review it and assess the impacts of outside help before submitting a change request.
Variation If outside experts can be assigned by a functional department within the existing budget, first coordinate with the functional manager; submit a change request only when the existing authorization is exceeded or controlled content such as the baseline or the contract has to change.
Something wrong with this question?
Common traps
Common trap
- For a major issue beyond your authority, do not first try to settle it internally and report afterward, and do not just send an email and wait for a reply; escalate along the path promptly and state the issue, the impact and the response.
- The escalation path is made clear under the project's governance arrangements (common exam practice: when it is missing, ask the sponsor and, if there is one, the steering committee to define it), and the escalation criteria are agreed and recorded in advance (common exam practice: agreed between the project manager and the sponsor), not left to personal feeling.
- When a high-priority issue is beyond the team's capability, do not close the issue, do not shrink the scope to avoid it, and do not have the team cram a short course. Review the issue and coordinate along the governance path; common exam practice (predictive): when controlled content is affected, first submit a change request and bring in outside help once it is approved.
- Rank by impact on objectives and by urgency. Issues on the critical path usually come first (a delay is more likely to affect the completion date).
- A late payment that has already occurred is an issue: resolve it by communicating directly with the stakeholders, not merely recording it or summing up lessons.
Key takeaways
- When several issues coexist, rank them by their impact on schedule (especially the critical path), cost, scope, quality and satisfaction.
- An issue beyond the project manager's authority that needs a higher-level decision or resources is escalated along the path agreed in advance.
- The escalation path and who decides are made clear under the project's governance arrangements (common exam practice: the sponsor and, if there is one, the steering committee make them clear); the escalation criteria are agreed, recorded and communicated in advance (common exam practice: agreed between the project manager and the sponsor). PMBOK 8 lists escalation only as a component that predictive environments may add.
- When escalating, bring the issue, the impact and the response, and do it promptly; do not wait until there is a result before speaking up.
- When a high-priority issue is beyond the team's capability, review the issue and coordinate along the governance path; common exam practice (predictive): when adding specialists or budget would change controlled content, first submit a change request and bring in outside experts or budget after approval.
- An issue may be closed only when it has truly been resolved.
Lesson 4
Removing Impediments: Impediments vs. Issues, Types and Handling
Lesson overview
The ECO puts “remove impediments” and “manage issues” in the same task because the two are related but not identical. Every time the team wants to borrow a server it waits three days for approval, IT cannot schedule a repair for a broken work computer, another business unit will not release a person: these are all impediments. This lesson covers what an impediment is and how it differs from an issue, how to handle each type, what is within your authority and what is not, and what to do when an impediment keeps recurring. The answers to questions on this lesson are highly consistent: assess first, coordinate first, do not bypass the process, do not spend money first, and do not run to senior management at the outset. The previous lesson covered the priority and escalation of issues.
What an impediment is
An impediment, also called a blocker, is an obstacle that prevents the team from achieving its objectives. An issue is a current condition that has occurred or is still occurring and may affect project objectives; an impediment is an obstacle that prevents the team from achieving its objectives, and it can come from inside or outside the team. The two sometimes overlap, and source alone does not decide it; choose to coordinate, intervene or escalate according to the impact and your authority. Common exam practice for telling them apart: what the team finds internally and can resolve itself is mostly a work-level issue handled by the team; what comes from outside the team and cannot be resolved by it is mostly treated as an impediment. Common external impediments include lengthy approval processes, other departments with different resource priorities, unrelated stakeholders who keep interrupting, and inadequate environment and tools. One of the project manager's duties is to keep impediments, especially external ones, away from the team so it can concentrate on delivery.
Issue vs. impediment
Issue: a current situation that may affect project objectives. Most are resolved inside the team or within the scope of the project, and they are recorded in the issue log.
Impediment: an obstacle that prevents the team from achieving its objectives. It can come from outside or inside the team (on the exam it mostly means external factors the team cannot resolve itself). The project manager steps in to coordinate and remove it, and escalates if it is beyond his or her authority.
Types of impediment and how to handle them
The first step differs by type, but with most impediments you assess the impact first. When a team member breaks the team's agreements, communicate promptly, understand why, and work together to restore the team's agreements; when safety, compliance or clearly destructive behavior is involved, stop it immediately.
| Type | Example | Preferred approach | Common mistakes |
|---|---|---|---|
| Organizational process impediment | A shared device takes three days to approve; go-live needs sign-off from several committees | Assess the impact and coordinate with the process owner, escalating if necessary; if the process keeps blocking people, suggest improving it | Bypassing the process; going straight to complain to senior management |
| Resource impediment | IT will not repair a computer because of a ticket backlog; not enough test devices | Assess the impact, coordinate with the relevant department and push for resources according to urgency | Buying new equipment without coordinating first; drawing on reserves without assessment and authorization; leaving it to members to figure out |
| External dependency impediment | A partner delivers interface documentation late | Communicate first, find out why and agree a way forward together | Waiting idly; changing the plan unilaterally |
| Impediment inside the team | A member does not follow the agreed ways of working | Communicate promptly, find out why and work together to restore the team's agreements; stop it immediately if it involves safety, compliance or destructive behavior | Turning a blind eye |
Note the order of handling: first assess the impact, how large it is, how many days it has cost and which tasks it affects; then communicate and coordinate; escalate only if coordination fails or the matter exceeds your authority. When handling an impediment, do not spend money at the outset and do not go to senior management at the outset.
Within and beyond your authority
For an impediment within the project manager's own authority, the project manager should take the initiative to decide on and carry out an intervention strategy, and not wait, accommodate or put it off; an impediment that has remained unresolved for two weeks and lies entirely within the project manager's authority has even less excuse for delay. For an impediment beyond your authority, ask the sponsor and other senior people for support along the escalation path.
When several impediments exist and resources are limited, rank them by impact and then remove them one by one. Impediments that hurt team morale, such as a test environment that keeps failing or a team that keeps redoing work, must be removed promptly; that is the real way to restore confidence, and meetings that only offer encouragement do not help. Raising the team's productivity comes from removing impediments, improving processes and securing resources, not from overtime and extra tasks. Logging an impediment is not the same as resolving it, and not every impediment should be escalated: assess the impact, set priorities and keep tracking.
When an impediment recurs
When the same kind of impediment keeps coming back, for example every release requires a dozen forms and sign-off by several committees and the process belongs to another department, find the root cause and give the process owner suggestions for improvement, using facts: the work hours wasted and the number of delays. Do not treat each occurrence as an isolated event, do not bypass the process, and do not just push through with overtime.
Example: three days waiting for the test environment
On a membership-system project for a chain of clinics, every use of the company's shared integration environment goes through three levels of approval and takes three days on average, and three tasks are already stalled this week. The project manager first assesses the impact: this week the three tasks have waited a total of 9 task-days, and a milestone next week is at risk. Then he meets the environment administrator and learns that the approvals exist to prevent conflicts, so they agree that project-related integration windows will be booked in one batch and the project will be authorized for the commonly used environments. Two weeks later the wait has dropped to half a day. The project manager also compiles the time data on this process for the environment owner and recommends a new “project booking channel.” At no point did he bypass the approval or escalate to senior management.
Worked examples
Example 1 Approval for the shared test server holds up tasks
Every time the team borrows the company's shared test server, it must go through a three-day approval, and three tasks have already been blocked this week. This is an impediment from organizational process. What should the project manager do?
Show answer and explanation
Correct answer: B
Each time the team borrows the shared test server it must go through a three-day approval, and three tasks are blocked this week. The stem already identifies this as an impediment from organizational process. What should the project manager do?
A process impediment sits at the organizational level. The project manager first assesses its impact on the schedule and then coordinates with the process owner, for example for an expedited channel or pre-authorization; if coordination fails or the matter exceeds his or her authority, it is escalated along the escalation path. The order is assess, coordinate, and escalate if necessary. The project manager first does what can be done within his or her own authority and only then considers escalation, in line with “coordinate first, escalate later.” Process owners can often provide an expedited channel or pre-authorization, which is more reliable than bypassing the process. The answer is B.
Why the other options are wrong
- A. Bypassing the approval violates organizational process and creates new compliance and management problems.
- C. Submitting requests in one batch on its own, without coordinating with the process owner, only adapts to the process; tasks already blocked remain unresolved.
- D. Moving the tasks out of this week only avoids the impediment without trying to remove it, and it also costs schedule.
Key takeaway For an organizational process impediment: assess the impact, coordinate first, escalate only if necessary, and never bypass the process.
Variation If the same approval blocks the project every month, then besides coordinating, give the process owner suggestions for improvement, backed by data on how long it takes.
Something wrong with this question?
Example 2 IT cannot fit the repair in, and a key member's computer is broken
A team member is rushing to complete a key deliverable when their work computer suddenly breaks down. The IT department replies that, because of a backlog of tickets, it cannot assign anyone to handle it within a week. What should the project manager do?
Show answer and explanation
Correct answer: B
A member rushing to finish a key deliverable has a computer failure, and the IT department, with a ticket backlog, cannot schedule a repair within a week. The question is what the project manager should do; this is a resource impediment.
With a resource impediment, first assess the impact and coordinate: based on the urgency of the task, talk with the IT department and ask it to speed up the repair or discuss alternatives. This is a direct first step that requires no immediate additional expenditure and does not overstep authority. If coordination works, the delay to the key deliverable can be kept to a minimum. The answer is B.
Why the other options are wrong
- A. Going to the sponsor for budget without coordinating first skips a step within the project manager's own authority. A budget request should come only after coordination has failed.
- C. Using contingency reserve to buy new equipment directly creates an immediate additional expense and skips both assessment and coordination, so it should not be the first choice.
- D. Simply telling the member to work it out lacks coordination with the IT department and does not discharge the project manager's responsibility to remove impediments.
Key takeaway For a resource impediment, coordinate with the relevant department first and push for faster handling according to urgency, rather than spending money straight away. First work out whether it can be settled by coordination within one's own authority, and then escalate level by level.
Variation Only if IT clearly says it cannot speed things up and a critical path delay is imminent should the project manager go on to assess renting equipment and request budget within his or her authority.
Something wrong with this question?
Common traps
Common trap
- With an organizational process impediment, do not bypass the process on your own and do not rush to complain to senior management; assess the impact first and coordinate with the process owner.
- With a resource impediment, assess and coordinate first; do not spend money first, draw on reserves without assessment and authorization, swap people or leave it to members to work out.
- When an impediment recurs, find the root cause and give the process owner suggestions for improvement; do not treat each occurrence as an isolated event.
- Act proactively on impediments within your own authority and do not wait; escalate along the path only when it is beyond your authority.
- Logging an impediment is not removing it; with several impediments, rank them first and handle them one by one.
Key takeaways
- An impediment is an obstacle that prevents the team from achieving its objectives and can come from inside or outside the team; common exam practice is that what comes from outside the team and that the team cannot resolve is mostly treated as an impediment, while a work-level issue the team can solve itself is handled by the team.
- The project manager keeps impediments, especially external ones, away from the team so it can concentrate on delivery.
- Order of handling: assess the impact, communicate and coordinate, and escalate only if coordination fails or the matter exceeds your authority.
- Do not bypass an organizational process impediment; with a resource impediment, coordinate first and do not spend money first.
- Intervene proactively on impediments within your authority; with several impediments, rank them first.
- When an impediment recurs, find the root cause and suggest process improvements.
This chapter has 42 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.