Governance and Business Environment
Change Control
PMP · Governance and Business Environment · 4 lessons · about 47 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Once a project is under way, change is almost inevitable: the client changes its mind, regulations shift, or the team finds a better way. Project management does not forbid change; it keeps change under control. On predictive projects, every recorded change request is assessed and then approved, deferred or rejected by the persons designated in the plan or organizational procedures, so that someone is accountable and there is a record. Adaptive projects usually have no formal "approval" process and instead manage change through the backlog and its priorities. PMBOK 8 calls this process Assess and Implement Changes. The chapter first covers the purpose of the process, its five responsibilities, the kinds of change request and the change log. It then covers the five-step flow of record, assess, submit, update and notify. Next it covers the change control board, how to pick the approver, the principle for baseline changes, after-the-fact changes and the change management plan. Finally it sorts change questions into four types of exam question.
Change control is a high-frequency exam topic. When you face a new change request that has not yet been assessed, do not approve it, reject it or act on it directly; clarify any missing content or reason, record it as required, assess its impact, and then submit it to the person with authority to approve. If the stem says how far the change has progressed (assessed, approved, deferred or rejected), continue from that step instead of going back to assess again.
Lessons in this chapter
- Lesson 1: Assess and Implement Changes: Purpose, Responsibilities, Change Requests and the Change Log. The process approves and manages changes (common exam practice: others raise them); five responsibilities; four kinds of action; the change log records every status, rejected requests included.
- Lesson 2: The Five-Step Change Handling Process. The main actions are record, assess, submit, update and notify. Before approval, record and assess the request and submit it to the designated approver; after approval, record the decision, update affected artifacts, notify relevant stakeholders, and then implement the approved change.
- Lesson 3: Change Approval and the Change Control Board. The CCB's responsibilities; approval authority follows the plan or procedures, and the exam default is the CCB; baseline changes are made only on the latest baseline and only for the future (common exam practice); after-the-fact changes; the change management plan.
- Lesson 4: Common Change Question Patterns. Find out how far the change has progressed; decide whether change control is required; assess before acting; adaptive projects rely on the backlog.
Chapter map
Change request (any stakeholder can raise one; even one raised verbally must be recorded in writing)
- Record → assess (scope, schedule, finance, stakeholders, resources, risk, and consider quality) → submit to the designated approver (the CCB where applicable)
- Approved → update (change log; affected plans, baselines and documents as needed) → notify → implement in Manage Project Execution → monitor the results
- Deferred / rejected → record in the change log → notify the requester
Adaptive: change → product backlog → prioritize (avoid changes within an iteration)
To practice this chapter, use the chapter exercises. Start with the core questions, then do the required ones.
Lesson 1
Assess and Implement Changes: Purpose, Responsibilities, Change Requests and the Change Log
Lesson overview
Once a project is under way, change is almost inevitable: the client changes its mind, regulations shift, the team finds a better way. Project management does not forbid change; it keeps change under control. Every change request is recorded and assessed, and a person with authority approves, defers or rejects it, so that someone is accountable and there is a record. PMBOK 8 calls this process Assess and Implement Changes. Change questions are among the most frequently tested scenario questions on the exam. This lesson first covers the purpose of the process and its five responsibilities, and then the kinds of change request and the change log. The next lesson covers the five-step flow of change handling.
Purpose and boundaries of the process
PMBOK 8 defines Assess and Implement Changes as “the process of managing project changes that may impact various aspects of the project and adjusting plans based on stakeholder recommendations throughout the project life cycle.” It runs from the start of a project through its completion, because changes can occur at any stage.
Remember its boundary (common exam practice): treat the process as the stage that approves and manages changes, not the stage that raises them. PMBOK 8 says any stakeholder may propose a change; others raise the request, and the process receives, assesses, and approves or rejects it. Think of it as the project's “gatekeeper”: it does not stop change but does not allow careless change. On predictive projects, once a baseline is established, changes to the baseline and to artifacts under configuration control all have to pass through this gate. Adaptive projects usually treat a change as a product backlog item, which is assessed and prioritized after an impact analysis, without formal change request approval.
Five responsibilities
First, Assess and Implement Changes runs through the whole project, because changes can occur at any stage. The project manager must make sure every change is recorded, assessed and submitted to the person with authority to approve it, and that authority is designated by the project management plan or organizational procedures (PMBOK 8: each documented change request is approved, deferred or rejected by a designated person, such as the project sponsor or project manager). Second, only approved changes may enter a revised baseline. Third, anyone may raise a change request, even verbally, but it must be put into a written record. Fourth, the impact of the change on schedule and cost must be assessed and the results provided to the relevant processes. Fifth, for every documented change request, a designated individual or body must decide to approve, defer or reject it, as specified in the project management plan or organizational procedures and, where necessary, with the change control board acting as that body.
How rigorous the management is depends on the project's scope, its complexity, the contract requirements and the development approach. In predictive approaches, changes are not formally controlled until baselines are established; once a baseline exists, however, all changes should go through a formal process to assess and implement them. The project's configuration management plan should specify which artifacts are subject to configuration control, and changes to those artifacts likewise require a formal change request.
Change requests
A change request is a formal proposal to modify a document, deliverable, or baseline. Change requests may be initiated internally or externally to the project. When issues are found while project work is being performed, change requests are submitted to modify project policies or procedures, project or product scope, project cost or budget, project schedule, or the quality of the project or product results. Change requests may include corrective actions, preventive actions, defect repairs, or updates that reflect modified or additional ideas or content.
A change request can contain four kinds of action. A corrective action addresses a performance variance that has already appeared and brings performance back onto the plan. A preventive action addresses a variance that might appear in the future. A defect repair addresses a deliverable that is already nonconforming. An update modifies a document, plan or baseline. One conclusion the exam likes to test follows: a corrective action is itself a change request. It should be reviewed through the Assess and Implement Changes process, with the decision made by the person with authority designated by the project management plan or organizational procedures and, where applicable, submitted to the change control board or project board. The project manager cannot touch the baseline directly and cannot “act first and file afterward.” A defect found before handover is repaired by the project team under the change control procedure, and the deliverable is handed over after the repair.
The change log
A change log is a comprehensive list of changes submitted during the project, which includes the current status of the submitted changes. Common fields are the change number, category, description, requester, date submitted, status and outcome. The disposition of all change requests is recorded in the change log as a project document update.
A rejected change request must also be recorded in the change log, and the requester and the relevant stakeholders notified. To see a change's current status and recorded disposition, look at the change log; identifying the approver requires the log or a linked approval record to capture that information; the change log is a project document, not the change management plan and not the change request itself. A change request that has been dispositioned has one of three statuses: approved, deferred or rejected. An approved change is implemented through Manage Project Execution; a deferred or rejected change is communicated to the person or group that requested it; and all outcomes are recorded in the change log.
Example: what a change log looks like
On a membership mini-app project for a chain of bakeries, the change log has these three entries. CR-07: add “birthday coupon” issuance; requested by the marketing manager; status “approved”; impact: cost up $18,000, schedule +4 days, baseline updated. CR-08: change membership tiers from three to five; requested by the operations director; status “deferred” because there is not enough historical data to support it at this stage, to be assessed in the next release. CR-09: cancel QR-code payment; requested by the finance manager; status “rejected” because it conflicts with the contract scope, and the requester was notified in writing. All three statuses are on record, so if anyone later asks what decision was recorded or why it was not done, the answer is in the log.
Worked examples
Example 1 The team thinks the requirement is needed and the client agrees: what next
A furniture factory's order-management system project has entered execution. The client's representative asks for an inventory-alert feature, which would change the scope baseline, and the change management plan states that changes affecting the baseline are approved by the change control board. The project manager and team assess the change's effects on scope, schedule, cost and risk, and unanimously agree that the requirement is worth implementing. What should the project manager do NEXT?
Show answer and explanation
Correct answer: C
The order-management system project is in execution. The client's representative asks for an inventory-alert feature that would change the scope baseline, and the team agrees it is needed. What should the project manager do next?
In this question the change management plan says baseline changes are approved by the change control board, so the change control process must be followed. A change can be raised orally but should be recorded in writing; after the project manager assesses the impact, the request is submitted to the change control board as the change management plan specifies, and only after approval does it enter the revised baseline and get implemented. The team's view that it is needed is only part of the assessment; the authority to approve lies neither with the team nor with the client. The answer is C.
Why the other options are wrong
- A. The client is the party raising the change and has no authority to approve it. An arrangement made privately between the two sides bypasses change control, and the baseline would not be formally changed.
- B. The stem states that the change management plan assigns approval to the change control board, so the sponsor is not the approver of this change.
- D. That the team thinks it is needed does not mean the change is approved. Implementing without approval quietly alters the baseline.
Key takeaway A baseline change should follow the change control method set for the project; here a change request must be submitted and approved by the change control board designated in the change management plan, and nothing is implemented before approval.
Variation If the project baseline has not yet been established, changes are not under formal control and the impact is analyzed first; if the sponsor is a member of the board, approval is still made through the board.
Something wrong with this question?
Example 2 Rework is on the critical path: how to handle the corrective action
A logistics sorting-system upgrade project finds a configuration defect during testing, and the team has to do a large amount of rework. The rework is on the critical path and puts the schedule behind. The project manager has already assessed the rework's impact on schedule, cost and resources. What should the project manager do?
Show answer and explanation
Correct answer: D
On a logistics sorting-system upgrade project, a configuration defect is found in testing, and a large amount of rework on the critical path puts the schedule behind. What should the project manager do?
Change requests include updates, defect repairs, preventive actions and corrective actions. The rework to fix the defect (defect repair) and the corrective action taken to recover the schedule are both change requests. They should be assessed for their impact on scope, schedule and cost and, as the change management plan prescribes, submitted for approval to the designated approver (such as the change control board); a baseline is revised only for a change that is approved and affects it. The answer is D.
Why the other options are wrong
- A. A baseline can be revised only according to approved changes. Resetting the schedule baseline directly rewrites the yardstick for measuring delay by the delay itself.
- B. Reporting to the PMO informs it, but a report alone does not fix the schedule variance and does not replace the impact assessment and submission to the designated approver under the change management plan.
- C. Acting first and filing afterward violates assessing before acting. Overtime also changes cost and resource arrangements, so it should be carried out after approval.
Key takeaway Defect repairs and corrective actions are change requests, submitted for approval to the designated approver under the change management plan (such as the change control board); the baseline is never changed directly.
Variation If the catch-up measures needed for the rework fall wholly within what the plan allows and do not affect the baseline, the project manager can decide and record them as the plan provides; if the baseline is affected, a change is still required.
Something wrong with this question?
Common traps
Common trap
- A change that involves a baseline may not be implemented before it is approved; if an unapproved change is found to have been implemented, assess its impact, go through the process after the fact, and strengthen control.
- A decision on a change must be made by someone with authority, and the result must be recorded, updated and communicated; the project manager cannot decide without authorization, though if the project management plan or organizational procedures designate the project manager as approver, he or she may decide within that authority.
- That the team thinks a change is necessary and the client agrees is only part of the assessment; approval authority does not belong to the team, and the client's agreement does not necessarily mean the change is formally approved. Determine the approval authority from the change management plan; for some changes, approval by the client or sponsor is also needed after CCB approval.
- A corrective action is also a change request; it cannot change a baseline directly, and reporting it to the PMO does not count as approval.
- A rejected request is also recorded in the change log, and the requester is notified.
Key takeaways
- Assess and Implement Changes approves and manages changes; as a common exam practice, changes are raised by others, not by this process; it is like a gatekeeper that does not stop change but does not allow careless change.
- The project manager makes sure changes are recorded, assessed and submitted, and the approver is designated by the plan or procedures; only approved changes can enter the baseline.
- Anyone may raise a change, even verbally, but it must be recorded in writing; every change request must be approved, deferred or rejected by a designated individual or body.
- Kinds of change request: corrective action, preventive action, defect repair and update. All are change requests and are reviewed and handled under the change control procedure (adaptive projects usually manage change through the backlog).
- The change log records the status of all submitted change requests, rejected ones included.
- In predictive approaches, changes are not formally controlled before a baseline is established; once a baseline exists, all changes go through a formal process of assessment and implementation.
Lesson 2
The Five-Step Change Handling Process
Lesson overview
The most common type of change question asks “what do you do next?” To answer correctly, you need to recognize the main change-handling actions and the stage reached in the stem: record, assess, submit, update and notify. PMBOK 8 requires that changes be documented in writing, assessed for impact, approved, deferred or rejected by a designated person, and implemented once approved. Common exam practice is that, after approval, you record the decision, update the affected plans and documents as needed, notify the relevant stakeholders, and then implement the change. This lesson takes each step in turn, covering what is done and by whom, then the “three steps before approval, three after” memory aid, the exits from the flow, and what the project manager does before approval. The previous lesson covered change requests and the change log; the next covers approval and the change control board.
First understand what the change is
When a change request comes in, clarify any missing details or reasons with the requester and let the requester know the process; if the request is already clear, proceed to recording and impact assessment as applicable. This step also helps prevent unnecessary changes: many “requests,” once clarified, turn out to be only ideas, or to have alternatives that do not change a baseline. First clarify whether the request really involves modifying a document, deliverable or baseline. If the project uses a predictive approach, a baseline has been established and the change involves configuration-controlled documents, deliverables or baselines, record it in writing and handle it in the five steps below (adaptive approaches usually add the change to the backlog and continuously assess it and adjust its priority). If it is only an inquiry, or it falls within the team's existing authorization and changes no requirement, plan, deliverable or baseline, no change request needs to be started; any other modification, even one that does not touch a baseline, is still recorded and assessed, and the designated person decides it.
What each of the five steps does
Record: Record the change request in writing. The project manager can enter it in the change log, or ask the requester to submit a written change request. A change raised verbally is first put into writing; this is the first step of the process.
Assess: Understand the change fully and assess the impact it brings. The performance domains PMBOK 8 lists for this are scope, schedule, finance (cost), stakeholders, resources and risk, and quality impact should be considered too; communicate the assessed impact to the relevant stakeholders. Assessment gives the requester, affected stakeholders and designated approver a decision-ready view of the change's consequences. If a client wants to switch the exterior paint to stone, the impact is an extra $400,000 and a three-month delay; once the client knows, he may decide not to make the change after all.
Submit: The project manager submits the change request and the assessment results to the approver designated by the project management plan or organizational procedures; where applicable, that can be the change control board or a project board. Submit after assessing. A request without an assessment gives the approver nothing to go on and is easily turned down.
Update: Whether the change is approved or not, the change log must be updated. For an approved change, update the project management plan and related project documents according to its impact, and, if baselines are involved, the baselines too; content that is not affected needs no revision.
Notify: Inform the relevant, affected stakeholders of the outcome of the change.
Three steps before approval, three after
The chain divides into two parts. Before approval: the change is raised and recorded in writing, the project manager and team analyze the impact, and it is submitted for approval. After approval: update the plans and documents, notify the stakeholders, and carry out the change. A memory aid is “record, assess, submit; after approval, update as needed, communicate and implement.” What PMBOK 8 explicitly requires is that a change be documented in writing and assessed for impact, and that it not be implemented before approval; the order of updating and communicating after approval depends on the change control procedure and the specific situation. Exam tip: use this chain to find the “next step,” and do not carry out the change first and then notify, giving stakeholders a “surprise.”
While the decision is pending, the project manager continues to execute the planned tasks while analyzing the impact and risks of accepting or rejecting the change, to minimize negative effects. This does not contradict “no implementation before approval”: the planned work goes on as scheduled, and only the requested part is left untouched.
| Phase | Step | Who | Key point |
|---|---|---|---|
| Before approval | Record | Requester or project manager | Even a verbal request is put into writing |
| Before approval | Assess | Project manager and team | Scope, schedule, finance (cost), stakeholders, resources, risk, and consider the quality impact; communicate the impact |
| Before approval | Submit | Project manager | With the assessment, to the designated approver (the change control board where applicable) |
| Approval | Approve, defer or reject | Change control board or designated person | The project manager does not decide beyond the established authority |
| After approval | Update | Project manager | Log, plans, baselines, project documents |
| After approval | Notify | Project manager, change control board or designated person (per the change control procedure) | The requester and affected stakeholders |
| After approval | Implement | The team, in Manage Project Execution | Then monitor the results |
Exits from the flow
If the change is approved, update the plans and documents, notify, put it into effect in Manage Project Execution, and afterward monitor the results of the change to make sure it produces the intended effect. If the change is rejected, record the outcome in the log and notify the requester; whether the requester may revise and resubmit depends on the project's change control procedure and the approvers' comments. The common treatment on the exam is that it can be resubmitted after revision, and a finally rejected request stays in the change log for the record.
Example: a loyalty-points change
A company is developing a point-of-sale system for a bookstore chain. One week before go-live, the client's representative says in a chat message that she would like a loyalty-points feature. The project manager neither agrees right away nor refuses outright. First he asks what is wanted and why, and then asks the client to put it in a written change request form, which is logged in the change log (record). After assessment, the team gives the impact: 9 person-days of development, a 4-day delay, $24,000 of additional cost, and an effect on the original test schedule. The project manager communicates the assessment to the client, who agrees (assess). He submits the change request with the assessment to the change control board (submit). After the board approves it, the project manager updates the project management plan and the schedule and cost baselines, and updates the change log (update), notifies the team and the test lead (notify), and then the change is carried out in execution.
Worked examples
Example 1 A written change request has arrived: what to do first
Engineer Daniel hands the project manager a written change request. The data interface he is responsible for cannot be built with the current technical approach; he wants to switch to a different approach, which would take more work hours and affect the approved baseline. As the project manager, what is the FIRST thing you do after receiving the request?
Show answer and explanation
Correct answer: C
On a predictive project, Engineer Daniel submits a written change request: the data interface cannot be built with the current technical approach, and he wants a different approach that would take more work hours and affect the approved baseline. What does the project manager do first?
PMBOK 8 requires that a change be documented in writing, that its impact on schedule and cost be assessed, and that designated persons approve, defer or reject it; the five-step order of record, assess, submit, update and notify is common exam practice. The request in the stem is already in writing, and in practice the project manager would also make sure it is entered in the change or configuration management system; none of the options is a logging action, so the best answer now is to assess: find out what the new approach would do to the duration, cost and other objectives, and then submit it for approval. “First” refers to the first action after the request has been recorded. Assessment also does not stop the project manager from having the team continue other planned tasks (PMBOK 8: keep executing planned tasks while waiting for a decision), and the results of the assessment are communicated to the relevant stakeholders before being submitted for approval. The answer is C.
Why the other options are wrong
- A. A change may not be implemented before it is approved, and the new approach would affect the baseline.
- B. Submission for approval comes after assessment. Without knowing the impact, the board has no basis for its review.
- D. Briefing the sponsor alone does not replace the impact assessment and formal approval, and it is not the first step now.
Key takeaway Once a request has been recorded, assess the impact first and then submit it for approval.
Variation If Daniel had raised it verbally, the first step would be to record it in writing; if the assessment has been completed, the next step is to submit it to the approver designated in the change management plan (which may be the change control board, the sponsor or the project manager).
Something wrong with this question?
Example 2 Two changes have just been approved: the next step after the meeting
On an inventory-system overhaul project for a pharmacy chain, the change control board approves two change requests submitted this week at its weekly meeting. After the meeting, what is the project manager's NEXT task?
Show answer and explanation
Correct answer: D
On an inventory-system overhaul project for a pharmacy chain, the change control board approved two change requests at its weekly meeting. What is the project manager's next step after the meeting?
The changes have been assessed, submitted and approved, so what follows approval is putting the result into effect. In the five-step order that is common exam practice, this is the “update” step (PMBOK 8 requires only that a change be documented in writing, assessed for impact, approved, deferred or rejected by designated persons, and, after approval, updated and its results monitored; the five-step order is common exam practice). In concrete terms, the approved content is carried into the affected parts of the project management plan, the baselines and the change log. After approval, the order is to update the plans and documents, notify the stakeholders, and implement; the first thing put in place is the update of the affected parts of the project management plan. In practice, updating and notifying can run in parallel, but before work starts the plan must already be current. A starts work directly with the plan not yet updated, B repeats the assessment, and C changes only one item; none is right. The answer is D.
Why the other options are wrong
- A. Starting work directly means the team may be working from an outdated plan; notifying and implementing come after the plan has been updated.
- B. The assessment was done before the request was submitted for approval and does not need to be repeated after approval.
- C. An approved change may affect several baselines such as cost and scope, and updating only the schedule would leave the plans contradicting one another.
Key takeaway After a change is approved, the order to use on the exam is to update the project management plan first, then notify and implement; in practice updating and notifying can run in parallel.
Variation If one of the two changes had been rejected, the change log would still be updated and the requester notified, but the plan would not be updated for that change.
Something wrong with this question?
Common traps
Common trap
- Use the stem to locate the stage: record and assess before submission, and never implement before approval. After approval, record the decision, update affected plans and documents as needed, notify relevant stakeholders, and then implement the change.
- Submit after assessing. A request with no assessment gives the committee nothing to base a decision on.
- After approval there is no need to assess again; record the decision, update affected plans and documents as needed, notify relevant stakeholders, and then implement the change.
- Revising only the schedule is not enough; an approved change may touch several baselines such as cost and scope.
- Exam tip: when the content of the change is clear and the request has already been recorded as required, and “record” is not among the options, the next step is usually to assess the impact; still judge from the stem whether clarification or additional written information is needed first.
Key takeaways
- First find out from the requester what the change is and why; this also helps prevent unnecessary changes.
- Common exam practice follows this order: record, assess, submit, update and notify.
- Assessment looks at the performance domains of scope, schedule, finance (cost), stakeholders, resources and risk, considers the impact on quality, and communicates the impact to the stakeholders.
- Before approval, record and assess the request and submit it to the designated approver; after the decision, record it, update affected artifacts and notify relevant stakeholders as required, then implement an approved change.
- Update the change log whether the change is approved or not; for an approved change, also update the plans, baselines and project documents.
- While waiting for approval, continue the planned tasks and analyze the impact and risks of accepting or rejecting.
Lesson 3
Change Approval and the Change Control Board
Lesson overview
The change is written up and assessed; who approves it? This is the second major category of change question: who holds approval authority, whether the project manager may decide alone, how to fix things when a change was made without going through the process, and what to do when change is chaotic. This lesson covers the responsibilities of the change control board (CCB), the order for choosing an approver, the principle for baseline changes, how to handle after-the-fact changes, and the change management plan. The formal approval process in this lesson applies mainly to predictive projects that have established a baseline; adaptive projects usually manage change through the backlog, recording, analyzing and reprioritizing, and do not necessarily submit written change requests or send them to a CCB for approval. The previous lesson covered the five-step flow; the next covers how change questions are tested.
The change control board
A change control board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions. It can be made up of senior leaders, the sponsor, functional managers and others. The change management plan establishes the CCB, documents the extent of its authority, and describes how the change control system will be implemented.
The CCB's value is that it is cross-functional. A scope change affects cost, and also schedule and quality, and brings in contracts and resources; when finance, technical, operations and other viewpoints review it together, the decision is more complete and objective. PMBOK 8 allows a person designated in the plan (such as the sponsor or the project manager) to approve, defer or reject changes; but when one person decides alone, with no cross-functional impact assessment, scope easily gets out of control, and that is the judgment the exam applies.
While awaiting the decision, the project manager continues to execute the planned tasks while analyzing the impact and risks of accepting or rejecting the change, to minimize negative effects. Depending on the nature of the change, customer or sponsor approval may be required after CCB approval, unless the customer or sponsor is a CCB member.
Order for choosing the approver
To choose an approver, first look at whether the project management plan or organizational process names a responsible person. The PMBOK 8 rule is that the approver is designated by the project management plan or organizational procedures (for example, the sponsor or project manager), the change control board takes part where applicable, and no fixed order of selection is prescribed. Common exam practice: when the stem does not say who was designated, the default is to submit to the change control board, which is the most common option. If the existing approval arrangement has led to loss of control, first analyze the cause and then adjust the approval authority or the CCB setup according to the governance arrangements and the change management plan (on the exam, the common answer is to add a cross-functional impact assessment before each decision; the designated approver, such as the sponsor, can still decide, and the change control board is just one way to do the assessment). When authority is uncertain, do not decide on your own: go through Assess and Implement Changes and hand the change to the party with the authority to approve it.
| Situation | Who approves |
|---|---|
| The plan or procedures designate a responsible person | The designated person |
| None is designated | The change control board (common exam practice) |
| Approval by a responsible person has gone wrong or scope keeps getting out of control | Add a cross-functional impact assessment before each decision |
| Authority is uncertain | Do not decide alone; check the project management plan or organizational procedures and hand it to the party with authority; when the stem does not name one, common exam practice usually picks the CCB |
| The nature of the change calls for customer or sponsor confirmation | After CCB approval, obtain customer or sponsor approval (unless they are CCB members) |
Principle for baseline changes
A change to a baseline can be made only on the latest version of the baseline, and only for the future; it cannot change past performance (this is common exam practice). That keeps the baseline stable and also does not rewrite historical performance data. An approved change request must also be reflected in the project documents, including the change log.
After-the-fact changes
When a change has been implemented without going through the process, the situation is informally called an “after-the-fact change.” The way to handle it: if unauthorized work is still continuing, pause further work on it while assessing the overall impact; add the written change request and submit it through the change control procedure to the designated approver for a decision (approve, defer or reject); then act on that decision, including reversing or otherwise resolving the unauthorized work if required, and make the rules clear to the team. Do not change the plan first, and do not draw directly on reserves to cover it up. Being near completion is not a reason to skip the change control procedure.
The change management plan
The change management plan is a component of the project management plan that establishes the CCB, documents the extent of its authority, and describes how the change control system will be implemented; it also specifies who approves changes and by what process. When change handling is chaotic, use the change management plan first to set the assessment requirements, the approvers and the process. When the CCB is not suitable, adjust its composition according to organizational governance procedures and authorization, and update the relevant record in the change management plan through a formal change. When changes are numerous or span several projects, recommend setting up a CCB to manage them in one place.
Example: how to handle an after-the-fact change
On a hospital logistics-services platform project, the project manager discovers at a weekly meeting that developers have already built a “water dispenser repair” entry in the test environment, which is not in the project scope; the logistics director had asked for it verbally in private. The project manager does not first reprimand anyone or simply delete it. Instead he first asks the developers to pause further work on it while he assesses the work actually done and its effect on the schedule (about 3 person-days, with no critical path impact), asks the logistics director to add a written change request, submits the assessment and the request to the CCB, which approves it that week, and updates the scope baseline and the change log. Finally he restates at the team meeting: any change in requirements must be raised as a change first, and no one may do the work first and file afterward.
Worked examples
Example 1 The sponsor decides alone, and scope keeps getting out of control
A newly arrived project manager finds that the scope of the project keeps getting out of control. After reading the change management plan, the project manager learns that whether to adopt a change is decided entirely by the sponsor alone, and that these decisions never go through a cross-functional impact assessment. To reduce scope problems, what adjustment should the project manager recommend?
Show answer and explanation
Correct answer: A
Project scope keeps getting out of control. The new project manager reads the change management plan and finds that whether to adopt a change is decided entirely by the sponsor alone, and the decisions never go through a cross-functional impact assessment. What adjustment would reduce the scope problems?
PMBOK 8 allows the sponsor, the project manager or another designated person to approve changes as the plan provides, and the change control board is an arrangement set up where applicable. This question states plainly that decisions never go through a cross-functional impact assessment and that scope is already out of control. Requiring a cross-functional impact assessment before each decision lets impact be judged from finance, technical, operations and other perspectives, so decisions are more complete and objective, while the designated approver, such as the sponsor, can still make the decision. The change management plan itself can specify who approves, so the recommended adjustment should also be reflected in the change management plan. The answer is A.
Why the other options are wrong
- B. The existing arrangement has already led to scope getting out of control, and continuing it does not solve the problem.
- C. Adding the project manager still leaves decisions with a few people and without a cross-functional impact assessment.
- D. Team members are those who carry out changes. Having them vote on changes is not in keeping with procedure, and they lack the decision authority and overall perspective.
Key takeaway When individual approval lacks cross-functional assessment and scope is out of control, recommend requiring a cross-functional impact assessment before each approval decision.
Variation If the change management plan has designated a single owner and it is working well, follow the designation; the body that approves changes is adjusted by updating the change management plan.
Something wrong with this question?
Example 2 The project is 85% complete and two stakeholders disagree
A community senior-care platform project is 85% complete. A key stakeholder asks that a care-level assessment task be included in the project, while another stakeholder objects, arguing that the project is nearly finished and the project management plan should no longer be changed. The project manager has already recorded and assessed the added requirement. What should the project manager do?
Show answer and explanation
Correct answer: C
A community senior-care platform project is 85% complete. One key stakeholder asks to include a level assessment in the project, while another objects, saying the project is nearly over and the plan should not be changed. What should the project manager do?
The project is not yet finished and the added assessment work would likely affect a baseline, so it should be handled through Assess and Implement Changes: record and assess the request, then submit a formal change request to the approver designated in the change management plan (the change control board where applicable), and keep the sponsor informed. Whether to change depends on the process, not on how much of the project is complete or on which side is more forceful. When two stakeholders hold opposing views, the project manager does not take sides but hands the decision to the authorized approver. The answer is C.
Why the other options are wrong
- A. Calling a meeting to “tell” them the change will be made decides the outcome before approval.
- B. Until a change is approved, the plan and budget cannot be updated directly.
- D. Change requests are managed by the project manager and approved by the board or the designated owner; they cannot be left to the person who made the request.
Key takeaway Being near completion is not a reason to skip change control; a baseline change goes to the approver designated in the change management plan (such as the change control board).
Variation If closure has not yet been completed and the client asks only for a revision to a user manual that does not affect a baseline, handle and record it under the existing plan; if closure has already been completed, it is handled through operations, warranty support or new authorized work.
Something wrong with this question?
Common traps
Common trap
- When the project manager has not been given approval authority, he or she cannot approve or reject on his own a change that conflicts with the objectives; first assess the impact, then submit to the approver designated by the plan or procedures (on the exam, usually the CCB).
- When several changes conflict with one another, first assess their effects on each other, then submit them to the CCB for a joint decision, rather than handling them one by one.
- The default approver is the CCB, not the sponsor, senior management or the client, unless the plan names someone else (common exam practice).
- Being near completion, a small change, or everyone agreeing is no reason to skip change control.
- A baseline change is made only on the latest baseline and only for the future (common exam practice).
Key takeaways
- The CCB is a formally chartered group that reviews, evaluates, approves, delays, or rejects changes and records and communicates the decisions.
- Order of approvers: the responsible person designated in the plan or procedures, otherwise the CCB by default (common exam practice); when authority is uncertain, go through change control.
- If individual approval has caused scope to get out of control, recommend adding a cross-functional impact assessment before each decision.
- A baseline change is made only on the latest baseline and only for the future, and does not alter past performance (common exam practice).
- After-the-fact changes: pause any continuing unauthorized work while assessing the overall impact, add the written request and obtain a decision, then act on that decision and make the rules clear; do not change the plan first or draw on reserves to cover it up.
- The change management plan establishes the CCB and sets authority and process; when things are chaotic, use it to set the rules first.
Lesson 4
Common Change Question Patterns: Find the Step, Decide Whether to Use Change Control, Assess Before Acting
Lesson overview
Change control is a high-frequency exam topic. The stems vary endlessly: a customer phones in a requirement, the team proposes switching tools, regulations change, senior management adds requirement after requirement, a supplier is late. But the patterns are few. This lesson groups them into four: find which step the change has reached; decide whether to go through change control; assess before acting; and how adaptive environments handle change. The first three lessons were knowledge; this one is test-taking.
Pattern 1: find which step the change has reached
First decide where the change in the question now stands, then pick the next step in “record, assess, submit, update, notify.” Several phrasings are easy to confuse. Drafting a change request, or asking the client to submit a written change request, corresponds to “record.” Analyzing the change's effect on schedule and cost corresponds to “assess.” “Process the change request” is the name of the overall flow, Assess and Implement Changes.
Some common rules of thumb:
- The request is already recorded: the next step is to assess the impact.
- Assessment is complete: the next step is to submit for approval.
- Change approved: record the decision, update the relevant plans, baselines and project documents as needed, notify the relevant stakeholders, and then implement through Manage Project Execution.
- If “record” is not among the options, clarify the request first when its content or reason is unclear; if it is already clear, assess the impact.
- If the stem says the customer or owner asks to change the schedule and cost and the option is “submit a change request,” that means formalizing the request, which is the starting point of the process.
Pattern 2: whether to go through change control
A modification that involves a baseline goes through change control, and on the exam it almost always does. On a predictive project, every change request is recorded first and then assessed, and is not skipped because the amount is small or time is short. A change that affects a baseline is assessed and implemented through the formal integrated change control process; one that does not affect a baseline is approved, deferred or rejected by the person designated in the project management plan or organizational procedures. A change may be raised verbally but must be recorded in writing. The team's unanimous agreement and the client's feeling that there is no impact cannot replace assessment and approval. Both adding and cutting scope are changes. A change forced by external causes, such as regulation or market shifts, that requires a baseline to change also goes through a change request; do not change the plan directly before approval.
Two exceptions should be recognized. The first: PMBOK 8 says that changes are not formally controlled until baselines are established. There is then no baseline to change, so baseline change approval is not needed; the common exam practice is to record the request on receipt and analyze its impact, neither rejecting it right away nor sending it up for approval right away. The second: for a change that does not affect a baseline, PMBOK 8 says each documented change request is approved, deferred or rejected by a designated person, such as the project sponsor or project manager, as specified in the project management plan or organizational procedures. It can be the project manager, but the change must still be recorded and assessed first; a small amount is no reason to skip assessment. As soon as scope, schedule or cost baselines are affected, submit it to the approver designated in the change management plan (the CCB where applicable).
Pattern 3: assess first, then act
The answer to most change questions is neither “approve” nor “reject” but “assess the impact first.” On receiving a change, do not approve it directly, reject it directly or start work directly. When the client keeps raising changes, assess and communicate the impact first instead of accepting everything on request. When someone suggests deviating from the plan, analyze feasibility and impact first, and if a change is really needed, raise it as a formal change request. A change raised by senior management also goes through the process, and the business case can be used to judge its benefits. When several changes arrive at once, go through Assess and Implement Changes first and do not rush to change documents.
How do you tell whether to “assess” or “submit”? Look at whether there is an assessment result. If the stem says only that “someone proposed it” with no analysis, the answer is most likely assess; only when the stem clearly says “the impact analysis is complete” is it submit. An idea raised internally also has its feasibility and impact analyzed first, and then the decision is made on whether to submit a change request.
| Clue in the stem | Matching action |
|---|---|
| The client phones or verbally raises a new requirement | Record it in writing first, then assess |
| The team or a stakeholder proposes a different approach | Assess feasibility and impact first |
| Small cost impact, client agrees, project nearly done | Still follow the process; assess first |
| The change has been assessed | Submit to the approver designated by the change management plan (the change control board where applicable) |
| The change has been approved | Update the plans, notify, implement |
| No baseline has been established yet | Analyze the impact first; do not reject right away or rush to escalate |
Pattern 4: adaptive environments
On adaptive approaches, changes are typically managed through backlog management rather than a formal change request process, and are continuously assessed and prioritized throughout the iterative development cycle. When a stakeholder proposes a change, it is recorded as a product backlog item and added to the backlog, and an impact analysis is conducted; usually there is no formal change control procedure; choices are expressed through what enters the backlog and how it is ordered. In Scrum, the Product Owner is accountable for the Product Backlog's content and ordering. If the change is assigned a lower priority, it is in effect deferred; choosing not to add it to the backlog, or removing it from the backlog, is rejecting it. A new requirement normally goes into the product backlog first and is ranked. The Scrum Guide's rule is that no change is made during a Sprint that would endanger the Sprint Goal, and as more is learned, the Developers may clarify with the Product Owner and renegotiate the scope of the Sprint. The common judgment on the exam: a new requirement goes into the backlog first; if it would endanger the current iteration's goal, it is usually placed in a later iteration, and the product owner is brought in.
Change on predictive vs. adaptive projects
Predictive: once a baseline exists, a change request that affects the baseline goes through the formal process and is approved by the approver designated in the change management plan or organizational procedures (the CCB where applicable); after approval, baselines and related plans and documents are updated as needed.
Adaptive: a change enters the product backlog and is prioritized; avoid changing the contents of an iteration, and take changes to the product owner.
Example: three sources of change, the same first step
On a digital exhibition-hall project for a city cultural center, three things happen in one week. First, the director says casually in the corridor that she would like to add audio guides to the exhibits. Second, an artist proposes replacing the in-house animation engine with an open-source framework, saving two weeks. Third, a market regulator announces that the electronic labels in the hall must carry an additional marking under a new rule. The project manager does the same thing for all of them. First, record each of the three. Second, assess the impact of each on scope, schedule, cost, quality and risk and communicate with the requesters. After assessment, if it is confirmed that the audio guides and the new marking affect a baseline, submit them to the approver designated in the change management plan (the CCB where applicable); the artist's proposal likewise depends on its actual impact, and if it does not change a baseline it is decided within what the project management plan allows, and recorded. None of the three is “approve first,” “reject first” or “start work first.”
Worked examples
Example 1 A key stakeholder asks to add content, with very little cost impact
A corporate training-courseware development project is in execution, and a key stakeholder asks to add an exercise question bank that would make the courseware more useful. The team's initial estimate is that adding it would have very little effect on cost. What should the project manager do NEXT?
Show answer and explanation
Correct answer: B
A training-courseware development project is in execution. A key stakeholder asks to add an exercise question bank, and the team's initial estimate is that the cost impact is very small. What should the project manager do next?
A small cost impact does not mean the change has no impact. The project manager assesses with the team the full impact of the change on scope, schedule, quality, risk and so on; if a controlled baseline or artifact is affected, the request is then submitted to the approver designated in the change management plan (such as the change control board). Analyze first and then act, and the “next step” is to assess. Stems like this often use phrases such as “very little impact” or “just a small extra” to tempt you into skipping the assessment, so be wary. Only after the assessment is it known whether a baseline is involved, and so whether to submit the request to the designated approver. The answer is B.
Why the other options are wrong
- A. Submission for approval comes after assessment. Reported without a complete assessment, the request leaves the board without a basis for decision.
- C. The project manager cannot implement a change directly without assessment and approval by someone with authority.
- D. Changes are approved by the board or the designated owner; senior management is not the default approver.
Key takeaway When a stakeholder raises a change, assess its full impact first and then decide whether to submit it for approval. A small cost impact does not mean scope, schedule, quality and risk are unaffected, and an initial impression is no reason to skip assessment.
Variation If the stem said “assessment is complete and the scope baseline is involved,” the next step is to submit it, as the change management plan specifies, to the designated approver (such as the change control board).
Something wrong with this question?
Example 2 A team member finds a better feature design
A company's project manager is managing development of a shared-workspace booking system. During execution, a team member finds that adding a self-service configuration feature would greatly reduce the operations workload after launch. What should the project manager do?
Show answer and explanation
Correct answer: A
On a shared-workspace booking system project in execution, a team member finds that adding a self-service configuration feature would greatly reduce the operations workload after launch. What should the project manager do?
An idea from a member of the internal team goes through the same first gate of the change process: the project manager first analyzes the feasibility and the impact on scope, schedule, cost and so on, judges whether it is necessary, and then decides whether to submit a change request. No matter who raises the change, the first gate is assessment, not approval or rejection and not writing it into the plan. If, after assessment, it is decided to proceed, the change request is submitted and approval awaited. The answer is A.
Why the other options are wrong
- B. Submitting without assessment leaves no basis for a decision and violates the order of assessing before submitting.
- C. Discussing only whether the feature is needed with the operations lead does not replace a full feasibility and project-impact assessment; the operations lead may participate in that assessment as a relevant stakeholder.
- D. Being beneficial does not mean it can go straight into the plan; the project management plan is updated only after a change is approved.
Key takeaway For a change proposed internally, assess feasibility and impact first and then decide whether to submit it.
Variation A new idea from a team member should be recorded and assessed first and then handled through the project's established process; it cannot be treated as an approved change.
Something wrong with this question?
Common traps
Common trap
- When you see the big options such as “handle it under the change management plan” or “follow the change control procedure,” they are often the safer choice when you are unsure.
- “The project is nearly done,” “it is just a small change,” “everyone agrees” and “the cost impact is small” are no reasons to skip assessment and change control.
- An approved change request is not the same as an implemented change; implementation happens in Manage Project Execution.
- Do not approve directly, reject directly or start work directly: assess first.
- Adaptive projects usually manage change through the backlog and not through a formal change request process (formal control may still be kept where governance or the contract requires it), with the product owner prioritizing; avoid changes within an iteration.
Key takeaways
- First decide which step the change has reached, then pick the next step among “record, assess, submit, update, notify.”
- A modification that involves a baseline goes through change control whatever its size; even one raised verbally must be put in writing.
- Before a baseline is established, changes are not formally controlled: record and analyze the impact, and neither reject right away nor escalate for approval right away.
- Assess before acting: do not approve, reject or start work directly; an idea raised internally also gets its feasibility and impact analyzed first.
- When several changes arrive at once, assess each and their effects on one another, and then submit them to the designated approver (the CCB where applicable) according to the change management plan and organizational procedures.
- Adaptive projects manage change through the backlog; avoid changing an iteration's content, and take changes to the product owner.
This chapter has 58 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.