Free PMP Practice Test 7: 106 Questions with Explanations
106 PMP sample questions, test 7 of 8 with no question repeated from the other tests: 27 People, 49 Process and 30 Business Environment, covering 24 of the 26 tasks of the Exam Content Outline. Timed mode gives 80 seconds a question, 141 minutes in all; or practice untimed. Every question has a full explanation: why the answer is right and what is wrong with each other option. When you submit you get your total score, your accuracy in each of the three domains and a readiness check.
Updated 2026-11-22 · aligned to the current Exam Content Outline and PMBOK Guide 8th Edition
Ready to start?
Your answers are saved in this browser, so you can refresh or come back later. No account needed.
You can read every question below before you start; the answer options unlock when you press Start.
- Question 1
At a project review meeting, team members list the risks that could occur on the project. The sponsor asks to meet with the project manager to assess how important each risk is. Which analysis should the project manager do to prepare for the meeting?
Show answer and explanation
Correct answer: C
At a project review meeting the team lists possible risks, and the sponsor wants to meet with the project manager to assess how important each risk is. The question asks which analysis the project manager should do to prepare.
The key clue is “how important each risk is”. Assessing the probability of occurrence and the degree of impact of each identified risk, and ranking priorities from them, is the job of qualitative risk analysis. Its result is a relative level such as high, medium or low, which is just what is needed to discuss with the sponsor which risks matter more. Among the options, only this one has individual risks as its object and priorities as its output. The answer is C.
Why the other options are wrong
- A. Quantitative risk analysis evaluates the combined effect of risks and uncertainty on overall project objectives and expresses it numerically. It is done only when needed. It does not rank each risk by probability and impact (although sensitivity analysis can show which risks have the greatest potential effect on project outcomes), so it does not meet the need in this question.
- B. Monte Carlo simulation is a specific quantitative technique. It outputs a probability distribution for overall cost or schedule, so its object is the whole project, not the importance of individual risks.
- D. Expert judgment is a supporting technique that can be used in many kinds of analysis; it is not a type of analysis. What the meeting needs is a systematic assessment and ranking, not “finding experts”.
Key takeaway To assess how important each risk is and rank priorities, choose qualitative risk analysis.
Variation If the sponsor asks “what is the probability that the whole project finishes on time?”, quantitative analysis such as Monte Carlo simulation is needed.
Reference Qualitative Risk Analysis · Lesson 1: Perform Risk Analysis: Qualitative vs. Quantitative, Rank First and Dig Deeper Later
- Question 2
A company's project manager is managing development of a shared-workspace booking system. During execution, a team member finds that adding a self-service configuration feature would greatly reduce the operations workload after launch. What should the project manager do?
Show answer and explanation
Correct answer: A
On a shared-workspace booking system project in execution, a team member finds that adding a self-service configuration feature would greatly reduce the operations workload after launch. What should the project manager do?
An idea from a member of the internal team goes through the same first gate of the change process: the project manager first analyzes the feasibility and the impact on scope, schedule, cost and so on, judges whether it is necessary, and then decides whether to submit a change request. No matter who raises the change, the first gate is assessment, not approval or rejection and not writing it into the plan. If, after assessment, it is decided to proceed, the change request is submitted and approval awaited. The answer is A.
Why the other options are wrong
- B. Submitting without assessment leaves no basis for a decision and violates the order of assessing before submitting.
- C. Discussing only whether the feature is needed with the operations lead does not replace a full feasibility and project-impact assessment; the operations lead may participate in that assessment as a relevant stakeholder.
- D. Being beneficial does not mean it can go straight into the plan; the project management plan is updated only after a change is approved.
Key takeaway For a change proposed internally, assess feasibility and impact first and then decide whether to submit it.
Variation A new idea from a team member should be recorded and assessed first and then handled through the project's established process; it cannot be treated as an approved change.
- Question 3
The project management plan of a predictive project has been approved. A stakeholder proposes replacing a self-developed module with a ready-made open-source framework to shorten development time. After looking into it, the team believes the approach is feasible and beneficial, but it must first be validated with a pilot, and users would need to acquire additional skills. What should the project manager do NEXT?
Show answer and explanation
Correct answer: B
The project management plan of a predictive project has been approved, and a stakeholder proposes replacing a self-developed module with a ready-made open-source framework to shorten development time. The team believes it is feasible and beneficial but a pilot must come first, and users need additional skills. What should the project manager do next?
On a predictive project, switching to an open-source framework means adjusting an approved project management plan, and the impact, which touches scope, schedule, cost and skills, can be judged only after assessment. Raising a formal change request lets stakeholders understand the impact and lets someone with approval authority decide whether to adopt it. The team's study is only part of the assessment and cannot replace approval. The answer is B.
Why the other options are wrong
- A. Training is something that may be needed after the change is approved. No decision to adopt has been made yet, so seeking training budget is premature and does not enter the change process.
- C. Asking the product manager for advice can gather information but cannot replace the formal change control process, and the advice carries no authority to approve.
- D. The financial management plan mainly specifies how finances are estimated, budgeted, managed and monitored. Consulting it cannot answer whether to adopt the new framework and cannot replace assessment and approval.
Key takeaway A proposal that would change the plan is raised through a formal change request.
Variation If the pilot shows it is not feasible, the change request is rejected and the original approach is kept; if it is feasible, update the plan after approval and arrange training; on an adaptive project, record it as a backlog item, analyze the impact and have the product owner prioritize it.
Reference Change Control · Lesson 4: Common Change Question Patterns: Find the Step, Decide Whether to Use Change Control, Assess Before Acting
- Question 4
A company's member app redesign project finishes according to its schedule baseline and cost baseline. At the acceptance review, the client representative explains that voice interaction had been needed from the outset, but the requirement was never elicited or recorded. The team is taken by surprise: had they known, many of the page functions already built could have been dropped or merged. What should the project manager have done beforehand?
Show answer and explanation
Correct answer: A
A predictive member app redesign finishes within its schedule and cost baselines, but at acceptance the client says voice interaction is a must, and it would have let the team drop or merge many page functions. The question asks what should have been done beforehand, so look for the source process of the problem.
All baselines were met and the client is still dissatisfied. That means the team did the work right but did not do the right requirements: a key requirement was not discovered and confirmed with the client during Elicit and Analyze Requirements. The project manager should have had the client confirm the requirements item by item at that stage, using prototypes, interviews and similar techniques where needed, so that a game-changing requirement like voice interaction would surface early rather than at acceptance. The answer is A.
Why the other options are wrong
- B. Define Scope uses the requirements documentation as an input and is not the primary process for eliciting and documenting stakeholder needs. Although a workshop might expose a requirements gap, A addresses the source of the problem more directly.
- C. Confirming scope at completion is the acceptance step, which is already too late. Problems found then can only be fixed by rework at the highest cost, and its purpose is not prevention.
- D. Stronger scope monitoring guards against scope creep or deviation from the baseline. Here there was no deviation: the baseline itself lacked the requirement, so monitoring would not help.
Key takeaway When baselines are met but the client is unhappy, the root cause is requirements not confirmed with the client during elicitation.
Variation If the client kept adding features during the project, that would be scope creep, to be handled through change control and by monitoring scope. This question is about an omitted requirement, which early requirements confirmation prevents.
Reference Requirements Elicitation · Lesson 2: Elicit and Analyze Requirements: Objectives, Inputs, Requirements Documentation and the Six Requirement Classes
- Question 5
A smart-campus access control project has entered implementation. The face-recognition terminals are supplied by an outside vendor. A key stakeholder writes to say that the terminals that arrived do not meet the agreed requirements for use. As project manager, what should you do FIRST?
Show answer and explanation
Correct answer: C
An access control project is in implementation, the terminals are outsourced to a vendor, and a key stakeholder reports that the delivered terminals fall short. The question asks what the project manager does “first”.
Signals: “first”, and purchased terminals that fail to meet requirements. When buyer and seller disagree or things are unclear, everything goes by the contract. First read what the contract requires of the terminals and what remedies it provides for nonconforming deliveries, and only then decide between correction, a claim or something else. The answer is C.
Why the other options are wrong
- A. A claim needs a basis in the contract. Until you have read it, you cannot tell whether the vendor is in breach or what you can claim.
- B. Whether the vendor must correct the defect, and whether a change request is needed at all, depends on the procurement agreement and the impact of the correction. Raising a change request before checking the agreement or confirming the terminals are nonconforming is the wrong order. If the remedy involves a formal change to the agreement or the project baselines, a change request is then submitted through change control.
- D. Replacing the vendor is something you might do only after you know what the contract says. The question asks what to do first.
Key takeaway When a procurement dispute arises, look at the contract first, then act.
Variation If the contract does not state the requirement, verify what the two sides agreed using the statement of work and other procurement documents. Only after you confirm the vendor is in breach do you talk about written notice to correct, a claim or replacing the vendor. Common exam practice: checking the contract first is the usual first step in monitoring and controlling procurements; claims, replacing the vendor and change requests all come later.
- Question 6
On an inventory-system overhaul project for a pharmacy chain, the change control board approves two change requests submitted this week at its weekly meeting. After the meeting, what is the project manager's NEXT task?
Show answer and explanation
Correct answer: D
On an inventory-system overhaul project for a pharmacy chain, the change control board approved two change requests at its weekly meeting. What is the project manager's next step after the meeting?
The changes have been assessed, submitted and approved, so what follows approval is putting the result into effect. In the five-step order that is common exam practice, this is the “update” step (PMBOK 8 requires only that a change be documented in writing, assessed for impact, approved, deferred or rejected by designated persons, and, after approval, updated and its results monitored; the five-step order is common exam practice). In concrete terms, the approved content is carried into the affected parts of the project management plan, the baselines and the change log. After approval, the order is to update the plans and documents, notify the stakeholders, and implement; the first thing put in place is the update of the affected parts of the project management plan. In practice, updating and notifying can run in parallel, but before work starts the plan must already be current. A starts work directly with the plan not yet updated, B repeats the assessment, and C changes only one item; none is right. The answer is D.
Why the other options are wrong
- A. Starting work directly means the team may be working from an outdated plan; notifying and implementing come after the plan has been updated.
- B. The assessment was done before the request was submitted for approval and does not need to be repeated after approval.
- C. An approved change may affect several baselines such as cost and scope, and updating only the schedule would leave the plans contradicting one another.
Key takeaway After a change is approved, the order to use on the exam is to update the project management plan first, then notify and implement; in practice updating and notifying can run in parallel.
Variation If one of the two changes had been rejected, the change log would still be updated and the requester notified, but the plan would not be updated for that change.
- Question 7
During planning, the project manager asks a team member who is preparing a requirements management plan for the first time to draft it. An experienced colleague reviews the draft and wants to find content that should not be in it. Which of the following is NOT part of a requirements management plan?
Show answer and explanation
Correct answer: B
In project planning, a team member drafts a requirements management plan for the first time, and a colleague reviewing it wants to pick out content that should not be there. The question asks which item is not part of the requirements management plan, so you must first separate the boundaries of the requirements management plan and the scope management plan.
PMBOK 8 states that the requirements management plan describes how requirements will be analyzed, documented and managed. Its components include how requirements activities will be planned, tracked and reported; configuration management activities (how changes will be initiated, how impacts will be analyzed, how changes will be traced, tracked and reported, and the authorization levels required to approve changes); the requirements prioritization process; and the traceability structure. Options A, C and D are all on that list. The process for preparing the project scope statement is a component of the scope management plan, not of the requirements management plan. The answer is B.
Why the other options are wrong
- A. Configuration management activities, including how changes are initiated and how impacts are analyzed, are explicit components of the requirements management plan. They govern the controlled path of requirement changes, so this is not the answer.
- C. The requirements prioritization process is also listed in the requirements management plan; it is used to decide which requirements to do first when they conflict or resources are tight. It belongs to this plan, so it cannot be chosen.
- D. The requirements management plan can define the requirement attributes and traceability structure to be used in the requirements traceability matrix, helping requirements be recorded and traced consistently. This belongs to the plan.
Key takeaway The requirements management plan governs how requirements are managed; how to prepare the scope statement, create the WBS and maintain the baseline is written in the scope management plan.
Variation If the question asked “which of the following belongs to the scope management plan,” the answers would be the four kinds: preparing the scope statement, creating the WBS, approving and maintaining the scope baseline, and formally accepting deliverables; requirements prioritization would not be one of them.
Reference Project Scope Statement · Lesson 1: Plan Scope Management: The Scope Management Plan and the Requirements Management Plan
- Question 8
An agile team is developing a warehouse management system for a logistics company. Early in the project, the logistics company's operations director wants something more concrete than the product vision but does not need the detail of a release plan or an iteration plan. What should the team provide to meet his need?
Show answer and explanation
Correct answer: D
Early in the project, the operations director wants something more concrete than the product vision but not as detailed as a release plan and an iteration plan. The question asks you to identify the right layer of the planning onion.
The planning onion (a common exam term; PMBOK 8 Figure 5-1 shows the first four layers) runs from the outside in: product vision, product roadmap, release plan, iteration plan, daily plan, with more detail toward the center. The director's two conditions pin the answer between layers: more concrete than the vision means going one layer in, and not as detailed as the release plan means not going as far as the third layer. That lands on the second layer, the product roadmap. The way to solve these questions is to line up the five layers from the outside in and then use “more concrete” and “not so detailed” to bracket the range between two layers. The answer is D.
Why the other options are wrong
- A. A status email reports current progress. It is not a plan for future versions and features, so it cannot show what he wants to see.
- B. The product vision is the highest-level goal, and the director explicitly wants something more concrete, so it is not enough.
- C. The daily plan is the innermost, most detailed layer, and the director explicitly does not need that much detail.
Key takeaway When the vision is too coarse and the release plan too detailed, show stakeholders the product roadmap.
Variation If the director wanted to show shareholders the themes of versions over the next few quarters, that is again the product roadmap; if he wanted to know which stories the next iteration will do, that would be the iteration plan.
- Question 9
On an e-commerce project, two front-end developers disagree about an interface convention, and the dispute is disrupting the team's rhythm. Following the general steps for resolving conflict, what should the two team members do FIRST?
Show answer and explanation
Correct answer: A
On an e-commerce project, two front-end developers disagree about an interface convention and the dispute is disrupting the team's rhythm. Following the general steps for resolving conflict, the question asks what the two should do first.
Conflict is handled at three levels. When differences of opinion become a negative factor, project team members first resolve them themselves. If the conflict escalates, the project manager helps in private. If disruptive conflict continues, formal procedures are used. What the people involved do first belongs to the first level: the two talk with each other and work it out. This puts the responsibility first on the people involved, which respects the members and keeps the project manager from being drawn into every small dispute. The answer is A.
Why the other options are wrong
- B. The sponsor is not the first level for handling disputes between team members. Going over their heads makes a small matter complicated.
- C. The project manager's help is the second level, after escalation, not the first step for the people involved, and setting a solution directly shuts them out.
- D. Ignoring a conflict does not make it go away. A disagreement that already disrupts the team's rhythm has to be handled.
Key takeaway Three levels: members resolve it themselves; the project manager helps privately once it escalates; formal procedures if disruptive conflict continues. The people involved talk first.
Variation If the two talk several times and still deadlock and the dispute escalates, the project manager steps in and helps both sides in private.
- Question 10
Several uncertain factors affect the project's total cost. The project manager wants to find out how much each factor affects cost on its own, so that effort can be put on the few with the greatest effect. Which technique should be used?
Show answer and explanation
Correct answer: C
Several uncertain factors affect the project's total cost. The project manager wants to know how much each factor affects it, so as to concentrate effort on the few with the greatest effect. Which technique should be used?
The decisive words are the size of the effect of “each factor on its own”. Sensitivity analysis determines which individual risks or sources of uncertainty have the most potential effect on the outcome. It correlates variations in project outcomes with variations in elements of the quantitative risk analysis model, and the result is typically a tornado diagram ordered by descending strength of correlation. This answers exactly “which few to watch”. The answer is C.
Why the other options are wrong
- A. Root cause analysis traces the causes behind a problem so as to find and remove the source. It does not compare the size of each factor's effect on cost.
- B. Decision tree analysis compares the expected monetary value of alternatives and is used to choose an option. It does not analyze the effect of each uncertain factor on its own.
- D. Monte Carlo analysis gives a distribution of results under the combined effect of several uncertainties. It simulates them together and does not compare factors one by one, so it is easy to be misled by “both are quantitative analysis”.
Key takeaway To compare the size of each factor's effect one by one, use sensitivity analysis; for the combined effect, use simulation.
Variation If the project manager wanted to know “how likely it is that total cost stays within $5,000,000”, choose Monte Carlo analysis. If the aim were to compare the EMV of two alternatives, choose decision tree analysis.
Reference Quantitative Risk Analysis · Lesson 3: Sensitivity Analysis, Influence Diagrams and Choosing a Quantitative Tool
- Question 11
A hospital appointment system project uses a predictive approach. A team member responsible for interface development has twice failed to finish tasks on time, and as a result a milestone was missed. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
This is a predictive project. A team member responsible for interface development has twice missed task deadlines, causing a missed milestone, and the stem does not give the reason. The question asks what to do FIRST. With no ready-made process step, an analysis action should come first.
The signal is that the cause is unknown. When the cause is unclear, the project manager first talks privately with the person involved to learn why the tasks were not finished on time. Only then can you tell whether the problem lies with skills, with resources or with the task itself, and decide what to do. Analyze and communicate first, then act. The answer is D.
Why the other options are wrong
- A. Demanding an explanation in front of the whole team holds him to account before the cause is known and damages team relationships. Find out in private first.
- B. Reporting to the functional manager and asking for a performance action before finding out the cause escalates first and investigates afterwards, which is the wrong order.
- C. Changing the schedule baseline requires change control, and the project manager has no authority to push it back directly. Also, with the cause of the delay unknown, you cannot tell whether the schedule really needs to change.
Key takeaway When the cause is unknown, find it out first, and do so in private. Do not hold someone to account in public, do not escalate straight away and do not change the baseline directly.
Variation If it were confirmed that his time had been pulled away, the next step would be to assess the impact and coordinate resources. If the question asked what should have been done beforehand, the answer would be to define roles, responsibilities and communication rules during planning.
- Question 12
The first deliverable of the project is complete, and the project manager invites the stakeholders to accept it. One of them says some requirements were not implemented and refuses to accept, but the project manager believes those requirements were never within the project scope. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
At acceptance of the first deliverable, a stakeholder says some requirements were not implemented and refuses to accept, while the project manager believes they were never in scope. The question asks what the project manager should do “first.”
The point of dispute is whether these requirements belong to the scope, so the facts must be established first. The project exclusions in the scope statement explicitly identify what is excluded from the project scope, and the statement is also the baseline for evaluating whether additional work falls within the project's boundaries. Reviewing it together with the stakeholder shows whether the disputed requirements are in scope, and then the follow-up can be decided. The answer is A.
Why the other options are wrong
- B. Accepting the demand and implementing it before checking whether these requirements belong to the scope may mean doing work outside the scope, which is scope creep.
- C. Change control comes after it has been confirmed that these requirements are really outside the scope and the stakeholder still insists on adding them. Starting it now is premature.
- D. The quality management plan explains quality requirements and how to show they are met. It has nothing to do with the dispute over whether something is in scope.
Key takeaway When it is disputed whether scope includes a requirement, look at the scope statement first (especially the exclusions), and only then talk about change.
Variation If the review shows that the requirements really are in scope and approved, the answer becomes building them as defect repair or corrective action through the applicable change process, re-verifying, and then submitting for acceptance; only if they are in the exclusions and the customer insists on having them do you submit a change request.
- Question 13
A data platform upgrade project is in the execution stage, and the team has hit a performance bottleneck that none of several attempted approaches has solved. The project manager wants an outside supplier to propose a solution. Which bid document should be sent to suppliers?
Show answer and explanation
Correct answer: B
The project is in the execution stage. The team has tried several internal approaches and still cannot overcome a performance bottleneck, and it wants outside suppliers to come up with a solution. The question asks which bid document to send.
PMBOK 8 Appendix X4 sorts bid documents into three types. A request for information (RFI) gathers more information from the market before bid documents go to a set of selected vendors. A request for proposal (RFP) is used for projects with a complex scope where the buyer is looking for the vendor to provide a solution. A request for quote (RFQ) is used when price is the main deciding factor and the proposed solution is readily available. The key signal here is “have the supplier propose a solution”: the approach does not yet exist, so the buyer cannot write a ready-made solution for others to price. The answer is B.
Why the other options are wrong
- A. A statement of work (SOW) is procurement documentation describing what is being procured. It goes out with the bid documents and is not itself a bid document inviting responses, nor does it make suppliers come up with a solution.
- C. An RFI collects market information before formal bidding and cannot replace an RFP, which formally solicits solutions from suppliers. The stem says it wants suppliers to submit a solution, so an RFP fits better.
- D. An RFQ presupposes that price is the main deciding factor and a solution is readily available. Here the solution is unknown, so asking suppliers to quote on a “ready-made solution” gives them nothing to quote.
Key takeaway Use an RFP to have suppliers propose solutions, an RFQ when a ready solution only needs price comparison, and an RFI to sound out the market before formal documents.
Variation If the stem changed to “standard servers with fixed specifications, just compare quotes from several firms”, the answer becomes an RFQ; if the project manager did not yet know what approaches exist on the market, issue an RFI first.
Reference Conducting the Procurements · Lesson 1: Conducting the Procurements: Inputs, Seller Proposals and the Bidder Conference
- Question 14
After several Sprint Retrospectives, the team's efficiency has not improved as the Scrum Master expected. What should the Scrum Master do to make the Sprint Retrospectives bring value to the team and the project?
Show answer and explanation
Correct answer: A
An agile project has held several Sprint Retrospectives, but the team's efficiency has not improved as expected. The question asks how the Scrum Master can make Sprint Retrospectives bring value.
The value of a Sprint Retrospective lies in improvements actually being carried out. If efficiency has not improved, most likely the Sprint Retrospective did not produce action items, or nobody followed them up. The Scrum Master is a servant leader and should coach the team and remind everyone to stay focused on the action items agreed in the Sprint Retrospective, so that improvements take hold. The answer is A.
Why the other options are wrong
- B. Merely holding Sprint Retrospectives more often, with the improvements still not carried out, just means more meetings.
- C. There are many reasons that can hinder follow-through. The Scrum Master can help remove obstacles from outside, but problems within the team have to be solved by the team itself and should not be taken over personally.
- D. The Product Owner orders the Product Backlog. Asking that person to order the improvement items jumps to later arrangements before the team has focused on its action items, and does not solve the follow-through problem.
Key takeaway If Sprint Retrospectives have no effect: first coach the team to focus on action items, do not simply hold more meetings, and do not take it all over yourself.
Variation If action items stay unclaimed, name an owner and a check date in the Sprint Retrospective, and start the next Sprint Retrospective by reviewing the previous action items.
Reference Scrum Events · Lesson 5: The Sprint Retrospective
- Question 15
A company's internal expense reimbursement system is being developed using an agile approach. To order several user stories, the organization requires scoring each on two measures separately, “the relative benefit of building the feature” and “the relative penalty of not having the feature,” and then comparing the totals. According to common exam practice, which method should the agile team use?
Show answer and explanation
Correct answer: D
On an adaptive project, the team must order several user stories for an expense reimbursement system. The organization requires two separate scores, the relative benefit of building the feature and the relative penalty of not having it, and then a combined comparison. The question asks which method to use.
The two scoring bases in the stem, one the relative benefit of building the feature and the other the relative penalty of not having it, are exactly what relative weighting does: it evaluates both the positive benefit a feature brings and the negative effect of its absence, and orders the user stories accordingly, usually relying on expert judgment. Note that relative weighting is a common exam practice term. The prioritization methods PMBOK 8 lists are MoSCoW, the 100-point method, cost of delay and Kano analysis. Among the options here, only relative weighting fits “benefit plus penalty of absence, scored on two measures.” The answer is D.
Why the other options are wrong
- A. Virtual currency gives participants a sum of play money to spend voting on the features. It does not ask for an evaluation of benefit and penalty.
- B. MoSCoW classifies requirements into four tiers: must, should, could and will not have. It is not calculated from benefit and penalty.
- C. Kano analysis classifies and ranks requirements by their effect on user satisfaction. It does not calculate benefit and penalty.
Key takeaway To order user stories by benefit and penalty of absence, use relative weighting (common exam practice).
Variation If the stem said “give each participant a sum of virtual money to bid on features,” the answer would be virtual currency. If it said “classify by effect on satisfaction,” it would be Kano analysis.
- Question 16
The project manager encounters a governance problem during execution: a test engineer receives conflicting instructions from several people for the same testing work, and the team cannot identify who is responsible or ultimately accountable for that work. What should the project manager FIRST establish in the project governance structure?
Show answer and explanation
Correct answer: D
The project is already in execution, and a test engineer is being given work by several people with conflicting priorities. The question asks what to establish first in the governance structure, and the core clue is “assigned work from several people and cannot work effectively”.
Because the team cannot identify who is responsible and ultimately accountable for the same work, the roles and responsibilities for that task are unclear. A responsibility assignment matrix (RACI is its common form) ties each activity to people and marks who is responsible, accountable, consulted and informed, with only one person accountable for each task. It clarifies roles, responsibilities and authority and reduces conflicting assignments. Who has authority to assign and adjust tasks should also be settled with the resource management plan or organizational reporting lines. Of the available options it is the tool most directly aimed at chaotic assignment. The answer is D.
Why the other options are wrong
- A. A risk management plan and an issue resolution plan deal with uncertain events and problems that have already arisen. They cannot set who gives out tasks and who is accountable, so they do not help with assignment from several sources.
- B. A resource management plan covers a wide range, and a conflict resolution mechanism is a remedy after the fact. First draw clear ownership of each task, then discuss how to handle conflict, which comes later in order.
- C. The WBS shows what to do and the schedule shows when. Neither answers “who is responsible and who assigns the work”, so members would still be directed by several people.
Key takeaway When the responsible and ultimately accountable people for the same work are unclear, build a responsibility assignment matrix so each task has one accountable person.
Variation If the scenario were “a member is unsure which task to do first”, the problem would be priority, not ownership, and the project manager should rank priorities from scope and schedule instead of reaching first for RACI.
Reference Responsibility Assignment Matrix and RACI · Lesson 2: The Responsibility Assignment Matrix and RACI: One Accountable Person per Activity
- Question 17
Team members tell the project manager that a department manager on the customer side keeps coming directly to ask about project progress, interrupting them from completing the tasks at hand. What should the project manager do?
Show answer and explanation
Correct answer: C
A customer-side department manager frequently comes straight to team members to ask about progress, disturbing their work. The question asks what the project manager should do.
The department manager keeps asking for status, which shows that the current communication arrangements do not meet the manager's information needs. The problem lies in the plan, not in the manager “breaking the rules.” The suitable move is to review the manager's communication needs again, confirm what information is needed, how often and through which channel, then update the communications management plan accordingly and move the route to information from individual members back to the proper channel. Once the need is met, the interruptions stop. The answer is C.
Why the other options are wrong
- A. Pushing more updates without finding out the need may still miss what the manager wants, so the manager will still go to team members and the interruptions remain.
- B. Communication arrangements are within the project manager's own responsibility, and the manager has done nothing improper. There is no need to escalate this to the sponsor. Handle it yourself first and escalate only if you cannot resolve it.
- D. Barring members from giving any progress cuts off a stakeholder's source of information. It is likely to inflame the situation and goes against the principle that stakeholders should get the information they need in good time.
Key takeaway When a stakeholder keeps asking for information on their own initiative, first reconfirm that person's communication needs rather than restricting or escalating.
Variation If it turns out the manager wants real-time data, open read-only access to the project board rather than adding emails.
Reference Plan Communications Management · Lesson 2: Communication Requirements Analysis and the Number of Communication Channels
- Question 18
On an online food-ordering platform project, the agile coach finds that the service architecture the team built has a flaw and may not work when new features are added later. The coach had earlier raised this by asking questions, but the team did not realize the problem. What should the agile coach do next?
Show answer and explanation
Correct answer: B
On an online food-ordering platform project, the agile coach finds that the team's service architecture has a flaw and may fail when features are added later. The coach had raised this earlier by asking questions, but the team did not realize it. The question asks what the coach should do next.
First settle the role: an agile coach is a servant leader who neither makes technical decisions for the team nor watches a problem happen. If asking questions did not work, the coach should state their own view plainly for the team to consider, so the team has full information. What solution to adopt is still decided by the self-organizing team. The answer is B.
Why the other options are wrong
- A. The coach has already asked, and the team still did not see it. Continuing to question only delays matters and makes the team feel interrogated. Failing to speak up when you should is also a failure of duty.
- C. Deciding that the architecture is wrong and requiring the team to switch to another approach is command and control, and it infringes on the team's right to self-organize.
- D. Stopping the reminders and waiting for the team to meet problems later means keeping silent about a known risk and making the team pay a greater price. The coach has not fulfilled the coaching duty.
Key takeaway The coach can voice an opinion, but the decision stays with the team.
Variation If the stem said the team, having taken the coach's view into account, still wanted to try another architecture, the coach should respect the team's decision and check the results in a Sprint Retrospective.
- Question 19
Midway through an agile team's project, governance has fixed the budget and delivery date but allows scope to be negotiated. The project manager finds that the budget is almost used up while the product is far from finished. How should the project manager resolve this?
Show answer and explanation
Correct answer: B
An agile (adaptive) project is under way. The budget is almost used up, and a great deal of work remains.
Under the constraints stated in this question, the budget and deadline are fixed while the undelivered scope can be adjusted. The project manager should help the product owner and relevant stakeholders re-rank the backlog by value (ranking is the product owner's responsibility), spend the limited money on the highest-value work and reduce scope. This stays within budget and avoids the team spreading effort evenly in the last few iterations and finishing a little of everything but nothing completely. The remaining money is spent on the highest-value stories; scope is smaller, but what is delivered is still the most valuable part. The answer is B.
Why the other options are wrong
- A. Additional budget is not the first choice. An adaptive project should first respond by adjusting scope and priorities, not by asking for money first.
- C. Reducing staff to cut cost makes the remaining work harder to finish and does not solve the trade-off about what to do.
- D. The problem is the budget. Shortening the schedule does not fix a lack of money, and ending the project early would leave most of the value unrealized.
Key takeaway When the budget of an agile project is tight, first adjust backlog priorities and reduce scope.
Variation If the stem said “the sponsor is willing to add budget and the value is clear”, additional budget could be approved through the proper process. If the budget is normal but time is short, likewise rank by value and deliver the minimum viable product first.
- Question 20
A city is building a new metro line. The project manager has the support of several district leaders along the route, but some on the city council argue that the project should be halted and the funds redirected to bus service improvements. A team member suggests recording only supporters in the register, to avoid trouble. What should the project manager do?
Show answer and explanation
Correct answer: B
A new metro line has the support of district leaders along the route, but some on the city council argue for halting it. A team member suggests the register record only supporters. The question asks what the project manager should do.
PMBOK 8 says that identifying stakeholders involves selecting the individuals, groups or organizations that have a stake in the project and documenting their interests, involvement, influence and potential impact on project success. The stakeholder register records all identified people, including their assessment and classification, without picking by position. Opponents above all must be recorded, because their influence and requirements determine whether they turn into resistance later, and only by registering and analyzing them can you engage them in a targeted way. The answer is B.
Why the other options are wrong
- A. Recording only those who clearly support and can provide resources leaves out opponents and neutrals. Opponents are exactly where later resistance comes from, so omitting them means giving up on managing them.
- C. Stakeholders are not chosen by the sponsor. Recording only those the sponsor designates leaves out the people the sponsor did not think of or does not want to mention.
- D. Recording only opponents is equally incomplete. Supporters and neutrals also need engagement and communication, and supporters' attitudes can change as events develop.
Key takeaway The register does not pick by stance: supporters, neutrals and opponents are all recorded as long as they may affect or be affected by the project.
Variation If someone merely “perceives themselves to be affected by the project”, they too belong within the scope of identification, and their influence can be assessed later.
Reference Identifying and Analyzing Stakeholders · Lesson 1: The Stakeholders Performance Domain and Identifying Stakeholders
- Question 21
A project manager has just been assigned to Phase 2 of an IoT gateway project. A defect appears during implementation, and the original engineering team has been moved to other projects, so nobody knows how to fix it. The customer points out that a similar defect once held up the project's schedule. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
The project is in Phase 2, a defect has occurred and the original team has left. You must decide the project manager's first action.
The defect has already occurred, the original engineering team has been reassigned, and nobody knows how to fix it. Whether the original team left a record of how it dealt with the defect has to be checked first in the organizational process assets (lessons learned, historical information, the defect repository). Consult them first to find out how it was handled before, and only then can you judge whether to extend the schedule, find resources or take other measures. The customer's mention that a similar defect appeared before is a further sign that the historical records probably already hold an answer. The answer is A.
Why the other options are wrong
- B. At this point nothing is known about the defect, so the situation must first be understood and its impact assessed. If the schedule baseline needs to change, a change request must then follow the change management plan, receive authorization, and be reflected in the relevant plans before implementation; the schedule cannot simply be extended first.
- C. The defect has already occurred, so it is an issue, not a risk. Updating the risk management plan does not fix it and is not the first step.
- D. Finding resources with relevant knowledge is something to do when necessary, but it should not come first before the earlier records have been consulted.
Key takeaway When you take over a project and meet a problem nobody knows how to handle, first consult the organizational process assets (lessons learned, defect records) and then decide whether to extend the schedule or find people.
Variation If, after consulting, you find there are no records at all, the next step is to look for resources with the relevant knowledge. And once the defect is fixed, add the handling to the defect repository for later projects to use.
- Question 22
A fitness-band team has completed two Sprints. The technical environment and operating procedures were set up in the first two Sprints, and the team is now doing Sprint Planning for the third. Besides members' vacations and various training, what else should the team consider when assessing the Sprint's capacity?
Show answer and explanation
Correct answer: D
The team has completed two Sprints, the environment and procedures are already in place, and it is planning the third. The question asks what to consider, besides vacations and training, when assessing Sprint capacity.
Sprint Planning estimates how much can be done in this Sprint, and the velocity actually achieved in past Sprints is one important source of evidence; the team also considers current capacity factors such as vacations and training, the Definition of Done, and the work itself. Velocity comes from real data and is more reliable than wishes. Velocity is commonly measured from story points completed in a Sprint that meet the Definition of Done. It may fluctuate early and may become more stable as the team gathers data, so it can inform the Developers' forecast without guaranteeing future capacity. So the answer is D.
Why the other options are wrong
- A. Agile stresses a sustainable pace and does not count overtime as part of capacity.
- B. Story points are a relative estimate made jointly by the team, and there is no need to determine who will do the work before points can be assigned.
- C. This preparation work was completed in the first two Sprints and is no longer a factor to deduct when assessing capacity now.
Key takeaway To assess Sprint capacity, past velocity is one important source of evidence, considered together with current capacity, the Definition of Done, and other relevant factors.
Variation If the velocities of the first two Sprints were 18 and 22 and one person is on vacation for 3 days in this Sprint, take an average of about 20 points as the reference and adjust it down for the vacation, giving a forecast slightly under 20 points. You can also do a simplified conversion by the proportion of available person-days (only a rough guide, not a prescribed formula). Velocity from just two Sprints can also fluctuate.
- Question 23
When is the project kick-off meeting BEST held?
Show answer and explanation
Correct answer: B
The question asks at what point the project kick-off meeting is best held.
The project kick-off meeting is mainly for communicating the objectives and the plan, building a shared understanding, making roles clear and obtaining commitment (approval of the project management plan is done separately under the governance arrangements, and the kick-off itself is not an approval meeting). In the conventional predictive-project exam scenario used here, the kick-off is typically held after the whole plan is complete and approved under the governance arrangements and before execution work begins, linking planning with execution. Therefore, B is the best of the options given. In actual projects, kick-off timing is tailored to the project's size, phases and life cycle; this common sequence is not a mandatory rule for every project. The answer is B.
Why the other options are wrong
- A. Before the charter is signed, the project is not yet authorized and no project management plan exists to communicate, so there is nothing to kick off.
- C. Sharing progress when there is good news is reporting or review, not the occasion for a kick-off. A kick-off is decided by the stage of the project and not by mood.
- D. The communications management plan is only one component of the project management plan. Its completion should not set the timing, and you wait until the whole plan is complete.
Key takeaway In a conventional predictive-project exam scenario, the project kick-off meeting is typically held after the project management plan is complete and before execution begins.
Variation A multi-phase project may hold a phase kick-off as each phase starts; actual timing should also be tailored to the project's size, life cycle and governance needs.
Reference The Project Management Plan · Lesson 3: The Project Kick-Off Meeting
- Question 24
A city greenway project covers 45 kilometers and has a budget of $9,000,000. It is planned to finish in 18 months. Every kilometer has the same amount of work and the same budget, and the budget is spread evenly over the 18 months. At the end of month 6, cumulative spending is $2,800,000 and 12 kilometers have been paved. The sponsor wants a status report that includes earned value. What earned value should be reported at this point?
Show answer and explanation
Correct answer: B
Work on this project is measured in kilometers. The question asks only for earned value (EV) at the end of month 6; the spending to date and the months elapsed are distractors.
Earned value equals the work actually completed multiplied by the budgeted unit price. Divide the total budget by the total length to get the budgeted price per kilometer, then multiply by the kilometers already paved. That gives the budgeted value of the work completed, regardless of how much was actually spent or how much was planned to be done. The answer is B.
- Budgeted unit price = $9,000,000 ÷ 45 = $200,000 per kilometer
- EV = 12 × $200,000 = $2,400,000
- Check: 12 ÷ 45 = 4/15 complete, and $9,000,000 × 4/15 = $2,400,000
- Compare: AC = $2,800,000 and PV = $9,000,000 × 6 ÷ 18 = $3,000,000. All three values differ; EV looks only at the work completed
Why the other options are wrong
- A. $747,000 ≈ $2,800,000 × 12 ÷ 45. This multiplies actual cost by the percent complete. EV is value measured at the budget, so it cannot be derived from AC.
- C. $2,800,000 is the actual cost (AC). It treats the money spent as the value of the work completed.
- D. $3,000,000 = $9,000,000 × 6 ÷ 18. Calculated from elapsed time, this is the planned value (PV): what should have been done, not what was actually done.
Key takeaway EV is how much work was actually completed, valued at the budgeted unit price; PV is how much was planned; AC is how much was spent.
Variation If 30% of the work were complete, EV = $9,000,000 × 30% = $2,700,000. In this question, schedule variance is SV = EV − PV = $2,400,000 − $3,000,000 = −$600,000, and cost variance is CV = EV − AC = $2,400,000 − $2,800,000 = −$400,000.
- Question 25
Which role is usually responsible for developing and maintaining the business case?
Show answer and explanation
Correct answer: D
Ownership of business documents: which role is usually responsible for developing and maintaining the business case?
The business case and the benefits management plan are business documents developed before the project starts. PMBOK 8 states that the project sponsor is generally accountable for the development and maintenance of the business case, and the project manager is responsible for providing recommendations and oversight so that the success criteria in the business case, the project management plan, the project charter and the benefits management plan align with one another. The division of labor between the two cannot be reversed. The answer is D.
Why the other options are wrong
- A. The project manager's duty is to provide advice and insight and is not usually to develop and maintain the business case (in some organizational settings the project management team may help prepare it, tailored to the organization), and the project manager may not change it alone.
- B. The customer is the recipient of requirements and value and can take part in discussions, but does not develop and maintain the business case. The customer's views can inform the business case, but the sponsor is responsible for developing and maintaining the document.
- C. A business analyst may help write it, but the one responsible for developing and maintaining the business case is the sponsor.
Key takeaway The business case belongs to the sponsor, and the project manager only advises.
Variation If asked who the benefits owner in the benefits management plan is, the answer is the person named in the plan, usually on the business side, and it does not automatically fall to the sponsor or the project manager.
- Question 26
The project manager of a city light show project is estimating resources and needs to collect information on each person and piece of equipment so that the resource plan can be carried out. Which set of information is MOST critical?
Show answer and explanation
Correct answer: B
The project manager of a light show project is estimating resources and needs to collect information on each person and piece of equipment so that the resource plan works in practice. The question asks which set of information is most critical, and the core is what you need to know in order to estimate resources.
Estimating resources answers three questions: when the resource is available and for how long (the resource calendar), whether it has the skills or experience needed, and what it will cost to use. Resource cost affects the choice in terms of both quantity and skill level, and these three kinds of information directly decide whether the plan can be carried out. The answer is B.
Why the other options are wrong
- A. Contract templates and payment terms belong to procurement management and are needed only after it is decided that a resource will be bought externally.
- C. Reporting relationships and performance appraisal belong to team management. Compared with resource calendars, skill requirements and usage costs, they are not the most critical information in estimating resources.
- D. Storage locations and approval procedures are execution-level details that can be arranged after the resources are settled. They are not core information for estimating resources.
Key takeaway Estimating resources comes down to three things: when they are available, whether they have the skills, and what they cost.
Variation If the stem asked “what are the outputs of estimating resources,” the answer would be resource requirements, basis of estimates, the resource breakdown structure and project document updates; if it asked which method to use “for a quick estimate when detailed information is limited,” that is analogous estimating.
- Question 27
The team for an equipment energy-efficiency project has been formed, and members report to both the project manager and a functional manager. The project manager's authority is low, and the role is held part-time by a person from a functional department and is not a designated job role. After one phase is completed, the functional manager makes the final call on which tasks to take on next. Which organizational type does this describe?
Show answer and explanation
Correct answer: B
The team for an equipment energy-efficiency project has been formed. Members report to both the project manager and a functional manager. The project manager has low authority, works part-time and holds no designated role, and after one phase the functional manager decides which tasks follow. The question asks which organizational type this is.
Members who report to two managers at once indicate a matrix, not a functional organization. In PMBOK 8 Table 2-1, the weak matrix project manager has low authority and a part-time role that is done as part of another job and is not a designated job role, which matches the stem. A balanced matrix has authority of low to moderate, and a strong matrix has moderate to high authority with a full-time, designated role. “The functional manager makes the final call on later tasks” is an identifying clue that is common exam practice. It shows that the final decision rests with the functional manager, which also points to a weak matrix. The answer is B.
Why the other options are wrong
- A. In a strong matrix the project manager has moderate to high authority and is full-time in a designated role. In the stem the project manager has low authority and is part-time, and the functional manager decides task selection.
- C. In a functional organization the reporting line runs only through the functional manager. In the stem members report to both the project manager and the functional manager, which already makes it a matrix.
- D. In Table 2-1, a balanced matrix project manager has authority of low to moderate, and by the common exam clue the two managers have comparable power and must negotiate. The stem says the project manager's authority is low and the functional manager has the final say, so it is not balanced.
Key takeaway Weak matrix: low authority, part-time, not a designated role (Table 2-1). “Who makes the final call” is an identifying clue that is common exam practice.
Variation If it said “later tasks are decided by agreement between the two managers, and the project manager's authority is low to moderate”, it leans balanced matrix; if it said “the project manager makes the call and is full-time in a designated role”, it is a strong matrix.
- Question 28
In an agile environment, a practitioner wants the list of risks and issues to be visible to everyone, continuously watched, and prioritized. Which approach is MOST appropriate?
Show answer and explanation
Correct answer: D
In an agile environment, a practitioner wants the risks and issues list to be visible to everyone, continuously watched and prioritized. Which approach is most appropriate?
PMBOK 8 describes an information radiator as a visible, physical display, posted where people can easily see it, that is easy to update and updated frequently. With an information radiator updated at the daily coordination meeting and the iteration planning meeting, risks and issues stay open and continuously noticed, and can be ordered by importance. This fits agile's way of communicating with highly visible, face-to-face means. The answer is D.
Why the other options are wrong
- A. Agile values individuals and interactions over processes and tools, and detailed documentation by itself does not keep information visible to the team.
- B. Team building and regular review meetings do little for the visibility of risks and cannot keep risks and issues continuously open and in priority order.
- C. A log is not conspicuous enough, and monthly updates distributed by the project manager are neither timely nor able to give the continuous visibility and monitoring required.
Key takeaway Keep risks and issues visible with an information radiator plus the daily coordination meeting and iteration planning.
Variation If a risk suddenly escalates, update the information radiator right away and notify the people concerned, without waiting for the next iteration planning meeting; it can be synced further at the next daily coordination meeting.
Reference Release Planning and Prioritization · Lesson 4: Agile Risk Management: Risks in the Backlog
- Question 29
A smart warehousing project enters closure. Checking against the business case and the benefits management plan, the project manager finds that picking efficiency in go-live testing improved by only 10%, below the expected 25%, but the customer has already signed the acceptance form. What should the project manager do?
Show answer and explanation
Correct answer: D
A smart warehousing project enters closure. Against the business case and benefits management plan, picking efficiency improved only 10%, below the expected 25%, yet the customer has signed acceptance. The question asks how to handle the gap.
At Close Project or Phase, the business case is used to test whether the project achieved its expected economic viability, and the benefits management plan is used to measure whether the planned benefits were achieved. A signed acceptance shows that the deliverables meet the acceptance criteria; it does not mean the benefits have been realized. The gap must be recorded honestly, and the way to handle it confirmed with the sponsor and other stakeholders, for example by continuing to track benefits after handoff to operations. The answer is D.
Why the other options are wrong
- A. A signature shows only that the deliverables are acceptable. Reporting unachieved benefits as achieved misleads management and is not honest.
- B. Changing the expected value in the business case afterward rewrites the standard of evaluation and hides the gap. The business case is the basis for measuring whether the project met the target and cannot be changed to look better.
- C. Pausing closure and redeveloping on your own goes beyond the approved scope and needs a change and authorization. How to deal with the gap should first be agreed with the stakeholders.
Key takeaway The business case and benefits management plan are the yardstick for closure. Report gaps honestly and agree with stakeholders how to handle them.
Variation If the stem said efficiency reached 25%, you would confirm the benefit was realized and state it in the final report. If it said “the customer refuses to sign”, acceptance has not passed and handoff cannot proceed.
- Question 30
A company has limited funds and staff. Which of the following activities falls within portfolio management?
Show answer and explanation
Correct answer: D
A company has limited funds and staff. Among four activities you must identify the one that belongs to portfolio management rather than to program or project work.
PMBOK 8 states that portfolio management involves selecting, prioritizing, managing, and optimizing an organization’s programs and projects in line with its strategic goals, obligations, or business objectives, which helps ensure that resources are allocated efficiently and that the portfolio delivers maximum value. Comparing the strategic value of projects at an annual review under limited resources and deciding which to fund or postpone is exactly selecting and prioritizing at the portfolio level. The answer is D.
Why the other options are wrong
- A. Coordinating several projects that constrain one another and go live together aims at benefits not available from managing them individually. That is program management.
- B. Developing and refining a work breakdown structure is specific scope management work inside one project. It belongs at the project level.
- C. Tracking one project’s cost performance and schedule variance each month is project-level monitoring and control. It involves no trade-offs among several projects.
Key takeaway When resources are limited, comparing value and setting priorities is portfolio work. Coordinating dependencies is program work, and doing the specific work is project work.
Variation If the question asked about deciding how one project manager’s staff are scheduled, that would be project-level work and no longer portfolio management.
Reference Projects, Programs and Portfolios · Lesson 2: Projects, Programs and Portfolios: How They Differ
- Question 31
At a project meeting, a member argues that a low-end model is a low grade, so its quality must also be low, and on that basis relaxes inspection of that model. What should the project manager do?
Show answer and explanation
Correct answer: B
At a meeting, a member argues that a low-end model is a low grade, so its quality must also be low, and relaxes inspection of that model on that basis. The question asks what the project manager should do.
Grade is a classification of products with the same use but different tiers of functions and specifications (grade versus quality is a common exam term). Quality is how well the deliverable's inherent characteristics meet the requirements and target objectives. Low grade does not mean low quality: as long as a low-end model meets the requirements of its own grade, its quality is acceptable, so inspection must not be relaxed. The project manager should clarify the difference between the two and require that the low grade meet its requirements as well. The required grade and its specifications should be established from the requirements, while quality management ensures that the product at that grade meets those requirements. If the wrong grade is selected, it should be corrected through requirements and scope management. The answer is B.
Why the other options are wrong
- A. Equating low grade with low quality is a confusion of concepts. Agreeing with it and cutting inspection frequency would leave the low-end model short of the requirements it should meet.
- C. Raising the feature level changes the product's grade. It is a matter of scope and requirements and does not solve the problem of relaxed inspection.
- D. Not clarifying lets the mistaken practice continue, and waiting for problems to appear is remediation after the fact.
Key takeaway Grade is a classification by tier, and quality is the degree to which requirements are met. Low grade does not mean low quality.
Variation The reverse is equally wrong. If someone says “the high-end model has many features, so its quality must be high”: a high-grade product that does not meet its own requirements still has low quality.
- Question 32
On a smart home development project, the project manager finds that a test engineer has repeatedly missed project meetings and learns that he has been busy with maintenance tasks assigned by his functional manager and has not been working on this project. What action should the project manager take?
Show answer and explanation
Correct answer: D
On a smart home project, a test engineer has repeatedly missed project meetings, and it turns out he has been doing maintenance tasks assigned by his functional manager. The question asks what action the project manager should take.
The member's time is being claimed by both the functional manager and the project. The root is a conflict in resource allocation, not the member's own attitude. The project manager should communicate and negotiate with the functional manager to clarify this member's hours and priority on the project, so that he can truly take part. The answer is D.
Why the other options are wrong
- A. Removing the member does not solve the project's need for this role. It may delay the schedule and would cause dissatisfaction in the team.
- B. A performance appraisal is an after-the-fact evaluation that cannot bring the member back to project work now, and responsibility does not lie with the member, so recording it in the appraisal would be unfair.
- C. Asking other members can only corroborate. The stem already explains why he is absent, and what is needed is direct communication with the functional manager, not further inquiry.
Key takeaway When a member is tied up by the functional manager, negotiate hours with the functional manager rather than dealing with the member personally.
Variation If the functional manager will not adjust the hours, communicate with the sponsor to coordinate; if the member truly cannot be spared, evaluate alternative resources or adjust the schedule.
- Question 33
A manufacturer has run several new product introduction projects in a row, and each one stumbled on the same root cause and went far over budget. The project manager wants later projects not to repeat the mistake. What should be done?
Show answer and explanation
Correct answer: D
Several new product introduction projects at a manufacturer all went over budget for the same root cause. The question asks how to keep later projects from repeating the mistake, that is, how the lessons get used by later projects.
For lessons to be used by later projects, they must settle at the organizational level: at the end of the project, the relevant information goes into the lessons learned repository, where it remains as an organizational process asset. Later projects consult the repository during initiating and planning, can identify and avoid this root cause, and the lessons are not lost as people move on. The answer is D.
Why the other options are wrong
- A. Stakeholder analysis concerns the needs, expectations and influence of the parties. It has no direct connection with the root cause of the cost overruns.
- B. Visiting successful project managers one by one is a one-off personal exchange. It does not settle the lessons systematically and does not address this specific root cause.
- C. Expert judgment can help analyze the root cause, but consulting experts alone does not ensure that the lessons are retained in the organization and reused by later projects.
Key takeaway To keep later projects from running into the same problem, settle the lessons in the organizational knowledge repository.
Variation If the question asked how to use lessons promptly within the current project, the answer would be to update the lessons learned register at any time and consult it during planning. If it asked whether the lessons reached the organizational level, the answer would be filing them in the repository and updating the organizational process assets.
- Question 34
A project manager is leading a new-energy battery development project. Team members have identified the sources of various risks and built a risk register. The project manager wants to concentrate effort on the high-priority risks. What should be done next?
Show answer and explanation
Correct answer: C
Risks have been identified and entered in the register, so the project is at the analysis stage of risk management. The project manager wants to focus limited effort on the high-priority risks, and you must decide what to do “next”.
The deciding signal is “concentrate on the high-priority risks”. To know which risks are high priority, you must first rank each one. The qualitative part of Perform Risk Analysis assesses the probability and impact of each individual risk and uses the probability and impact matrix to set priorities, so that the team can focus on the high-priority risks. It is also the natural next step after identification. In practice, qualitative analysis is usually used first to decide the focus, and quantitative analysis then digs deeper, as needed, into the key risks and overall risk. Decision tree analysis is itself one of the quantitative techniques, and none of these is the first thing to do now. The answer is C.
Why the other options are wrong
- A. The sources of risk have been identified and the register is built, so identification is already done. Identification also only finds and records risks; it cannot put them in order.
- B. Quantitative risk analysis primarily examines the combined effect of risks and uncertainty on overall project objectives and expresses the result numerically. It does not rank individual risks by probability and impact (although sensitivity analysis can show which risks have the greatest potential effect on project outcomes), and not every project requires it, so it is not the first step in ranking here.
- D. Decision tree analysis is a quantitative technique that compares alternatives by EMV. It solves a choice among options and cannot give the high-to-low order of the risks.
Key takeaway After identification, priorities must be set: do qualitative risk analysis first, and then decide which risks deserve quantitative analysis.
Variation If the stem says the top three risks are already ranked and you must calculate their combined effect on total project cost, then quantitative risk analysis is next. If it says some risks have not yet been found, the answer returns to identifying risks.
- Question 35
A project spans several departments. The project manager met with each department's members separately, and each prepared the WBS for the part it was responsible for. After the WBS was finalized, it was found that some work appeared twice in the parts of different departments. To avoid this kind of problem, what should the project manager have done?
Show answer and explanation
Correct answer: D
A project spans several departments. The project manager met with each department separately and each prepared its own WBS; after finalization, some work was found duplicated in different departments' parts. The question asks what the project manager should have done.
A WBS has to have all the work with nothing missing and nothing extra. When departments build their parts separately, they cannot see each other's content, and duplicates and gaps show up only after the parts are merged. Had all members been convened beforehand to review the WBS together, everyone could compare each other's work content, and duplicates could be deleted and omissions filled before the WBS was finalized. The answer is D.
Why the other options are wrong
- A. Subject matter experts giving guidance on scheduling address a scheduling problem and cannot eliminate duplicates in the WBS structure.
- B. Improving communication channels is a long-term measure. It does not target the review step of the WBS and cannot ensure duplicates are found before finalization.
- C. A responsibility assignment matrix is a tool for assigning responsibility after the WBS is done. It cannot prevent duplication within the WBS itself.
Key takeaway When departments build their WBS parts separately, use a joint review by everyone to remove duplicates and fill omissions before finalizing.
Variation If the question asks how to prevent omitted work from being discovered only after the WBS is finalized, the answer is still to conduct a joint review before finalization. If the omission is discovered after the scope baseline has been approved, the current response is to assess the impact and use formal change control. If what is wrong is that a member does not know which work package they are responsible for, clarify responsibility with a responsibility assignment matrix.
- Question 36
A home appliance company is planning a new product. During planning, a stakeholder from the finance department never attends project meetings and shows no interest in the product design. What should the project manager do?
Show answer and explanation
Correct answer: D
A home appliance company is planning a new product. During planning, a finance department stakeholder never attends project meetings and has no interest in the product design. You must decide what the project manager should do.
A finance department that never attends meetings and has no interest in the design is not necessarily a problem: appropriate engagement does not mean attending every meeting. The key is to confirm whether the department's needed level of engagement, information needs and the timing of its involvement have already been arranged in the engagement plan and communication strategy, so first review the engagement plan and the communication strategy; if actual engagement is below the needed level, then adjust the strategy. The stem says only that he does not attend and has no interest. It does not say that requirements were missed or that the register is wrong, so changing requirements or the register would not address the issue. The answer is D.
Why the other options are wrong
- A. The project manager can handle this kind of issue and need not escalate first, and escalating would not answer why the department is not taking part.
- B. The problem is non-participation, not the requirements or the register. Reviewing the requirements and updating the register does not touch the cause.
- C. Compelling attendance is only a means, and the department's needed level of engagement has not been confirmed first. Without reviewing the engagement plan and communication strategy, forcing attendance is neither how engagement is done nor likely to produce real participation.
Key takeaway When a stakeholder's engagement is low, first review the engagement plan and communication strategy to confirm the level of engagement he needs.
Variation If the department did attend meetings but its views were ignored, first go back and check whether its needs were collected and included, and then assess whether the engagement plan and the way of communicating need updating.
- Question 37
A bakery chain's store app development project is at its midpoint. The member responsible for testing has moved to another project and a new member takes over. He wants to understand the description of work, the deliverable and the resources required for one of the work packages. Which document should the project manager have him consult?
Show answer and explanation
Correct answer: D
At the midpoint of the project, a new member takes over testing. He wants to know the description of work, what is to be delivered and the resources required for one work package. The question asks which document to consult.
The three items of information in the stem are all details at the level of a single work package. The WBS dictionary provides detailed information for each WBS component, such as the code of account identifier, description of work, resources required and acceptance criteria, which matches exactly. The WBS shows only the hierarchy and the names of the work packages, and the details have to be filled in from the dictionary. The answer is D.
Why the other options are wrong
- A. The scope statement describes the scope, major deliverables and exclusions of the whole project. It does not go down to a single work package and has no resources required.
- B. The project charter gives only high-level objectives and requirements, with no detail at the work package level.
- C. The WBS presents the levels of decomposition and the names of work packages. It does not provide the description of work and resource requirements of each component.
Key takeaway To learn the detailed information of a work package, look at the WBS dictionary; the WBS gives only structure. The WBS dictionary is the companion document of the WBS, and together with the scope statement and the WBS it forms the scope baseline.
Variation To find the major deliverables and exclusions of the whole project, look at the project scope statement; if asked what makes up the scope baseline, answer the scope statement, the WBS and the WBS dictionary.
- Question 38
During acceptance testing of a corporate website project, the sponsor tells the project manager that the deliverable will pass acceptance only if the main page color is changed from green to orange. The project manager checks the planning documents and confirms that the main color is specified as green, but the sponsor insists. What should the project manager do next?
Show answer and explanation
Correct answer: B
During acceptance testing of a corporate website, the sponsor insists on changing the main page color from green to orange before accepting. The planning documents confirm green. The question asks what the project manager does next.
The planning documents specify green, so the sponsor's request to change to orange is a change to an approved specification, acceptance criterion or scope baseline. The right approach is to suggest that the sponsor submit a formal change request, have the impact on cost and schedule assessed, and make the change only after approval. This respects the sponsor's authority while keeping the baseline under control. The sponsor's position gives the right to raise a change, but it does not mean the team can be told to make it directly. Procedurally, a change raised by the sponsor is also put in writing, assessed for impact and implemented only after approval. The project manager's role is to steer the other party into the formal channel, not to confront or give in. The answer is B.
Why the other options are wrong
- A. Telling the sponsor to accept green is a confrontational response. It ignores the sponsor's right to propose a change, which should be handled through the process rather than refused.
- C. Agreeing just to avoid conflict changes an already confirmed deliverable without change control and damages the baseline.
- D. Changing first and filing the paperwork later is acting before approval. If the change is rejected, the work is wasted, and it violates the principle of approval before implementation.
Key takeaway To change an approved specification or scope baseline, go through a formal change request.
Variation If the sponsor agrees to drop the request, accept the deliverable against the original specification. If the change is approved, update the specification and acceptance criteria and then change the color.
Reference Monitor and Control Scope and Scope Creep · Lesson 3: What to Do When You Find Out-of-Scope Work: Control First, Then Change
- Question 39
At a phase gate review meeting on a warehouse automation project, the project manager finds that the duration estimates were far off. The cause is that the team did not bring in experts familiar with the equipment to judge durations, and as a result the schedule fell behind. What should the project manager do to avoid the same situation in future projects?
Show answer and explanation
Correct answer: A
At the phase gate review it turns out that the duration estimates were far off and the schedule is behind because no experts familiar with the equipment were consulted. The delay has already happened and the cause is clear. The question is how to avoid the same situation in future projects.
The key signal is “future projects”: for other projects to see this and avoid it, the cause and the lesson from this case must be kept where it can be looked up. The lessons learned register is the place that records lessons of this kind, and at closing it is filed in the lessons learned repository for later projects to consult. So the lesson that missing expert judgment caused the delay should go into the register. The answer is A.
Why the other options are wrong
- B. The delay has already occurred, so it is an issue, not a risk. The risk register records uncertain events that have not yet happened. Logging it as a risk is conceptually wrong and passes nothing on to later projects.
- C. Root cause analysis could still be used to check whether a deeper underlying cause exists. However, the risk management plan sets out how risks are managed and is not used to store the lesson from a particular case, so this option does not meet the stated goal of helping future projects reuse the lesson.
- D. The issue log is for tracking and resolving current issues. Logging the delay and assigning a follow-up owner does not carry the lesson to future projects and does not meet the stated purpose.
Key takeaway To keep future projects from making the same mistake, record the lesson in the lessons learned register.
Variation If the aim were to correct the current delay on this project quickly, the delay would go in the issue log with an owner assigned (the lesson can also be recorded in the lessons learned register).
Reference Lessons Learned · Lesson 2: The Lessons Learned Register: What to Record, When to Update It, Where It Goes
- Question 40
A project is building safe drinking-water facilities for villagers in a remote mountain area to improve local water hygiene. What should the project manager do to make sure the villagers know the project's latest progress?
Show answer and explanation
Correct answer: D
A project is building safe drinking-water facilities for villagers in a remote mountain area. The question asks how to make sure the villagers know the latest progress.
The villagers are external stakeholders. To keep them informed of the latest progress, communication should be regular, proactive, and delivered in a way they can reach. Regular village meetings release information steadily and also let people ask questions in person and give feedback, which suits a remote population that may not often be online. This also fits PMBOK 8's approach of choosing communication methods to match stakeholders' needs and preferences. The answer is D.
Why the other options are wrong
- A. Waiting for villagers to ask is passive communication. They cannot keep up with progress in time, and it falls short on transparency.
- B. Passing information through the sponsor adds a relay where it may be distorted, may not reach the villagers in time, and makes it hard to collect their feedback.
- C. An annual summary is too infrequent to show the “latest progress”, and the internet and newspapers may not reach these villagers, so it does not suit the audience.
Key takeaway To keep stakeholders up to date, communicate regularly and proactively, in a way they can reach.
Variation If villagers mostly use mobile instant messaging, add group message updates, but keep the meetings for face-to-face feedback.
Reference Managing and Monitoring Communications · Lesson 2: Project Reports, Meetings and Information Sharing: Including Reporting in Agile Settings
- Question 41
On a store-system modernization project for a supermarket chain, a senior stakeholder in the company instructs the project manager to move a key database engineer from this project to support another newly started project. What should the project manager do FIRST?
Show answer and explanation
Correct answer: B
On a store-system modernization project, a senior stakeholder instructs that a key database engineer be moved to another project. The move has not happened yet. The question asks for the first action after receiving an instruction to adjust resources.
Pulling a key resource affects schedule, cost, quality and risk at the same time, and the stem does not say whether the project can still hold its baselines without this person. PMBOK 8 notes that a lack of needed resources can affect schedule, budget, customer satisfaction, quality and risk. So the first step is not to take a position but to assess: which activities would be affected, and whether someone else can fill in. If the assessment shows a baseline must change, a change request then takes it into change control. B has the right order: it neither simply complies nor simply resists. The answer is B.
Why the other options are wrong
- A. Negotiating is not wrong in itself, but without impact data the project manager cannot explain why the engineer must stay and can only bargain by gut feeling. Negotiation belongs after the assessment, with data in hand.
- C. Rallying other stakeholders against the instruction is confrontation. It damages the relationship with the senior stakeholder and, again, skips finding out what the move actually does to the project.
- D. Proposing termination before the size of the impact is known pushes the problem to an extreme. Bringing in someone from elsewhere or resequencing tasks might solve it, and whether to terminate depends on the assessment.
Key takeaway When a key resource is to be pulled away: assess the impact first, then negotiate and implement a solution; submit a change request only if a baseline or another controlled item must change. Do not start with confrontation or with giving up.
Variation If the stem already said that the critical path would slip three weeks after the move, the first action would become negotiating with the senior stakeholder using the assessment results; if the resulting solution requires a change to a baseline or another controlled item, then submit a change request.
Reference Monitor and Control Resourcing · Lesson 3: Team Member Changes: Assessment, Handover and Negotiating with the Functional Manager
- Question 42
PMLyceum’s PMO requires every project’s sustainability review to reflect the “triple bottom line”. Which of the following is the balance the triple bottom line calls for?
Show answer and explanation
Correct answer: D
The PMO requires each project’s sustainability review to reflect the “triple bottom line”. The question asks which option is the balance the triple bottom line calls for. Be careful to separate the triple bottom line from the “triple constraint” often mentioned in project management: the former balances social, environmental and economic outcomes, while the latter describes constraints within the project.
In the Eighth Edition, by integrating sustainability into project management, organizations can align with the triple bottom line, balancing social equity, environmental stewardship and economic prosperity, summed up as people, profit and planet. Of the four options, only D is a balance among those three dimensions. The answer is D.
Why the other options are wrong
- A. Scope, schedule and cost are the traditional triple constraint, which describes limits inside the project. It is not the triple bottom line.
- B. Quality, risk and value are other elements of project management and do not form the three dimensions of sustainability.
- C. Profit, growth and market share are all economic measures. They cover only the economic part of the triple bottom line, with no society or environment.
Key takeaway The triple bottom line is social equity, environmental stewardship and economic prosperity, that is, people, planet and profit. Do not confuse it with scope, schedule and cost.
Variation If asked about the “triple constraint”, the answer is scope, schedule and cost, a different thing from the triple bottom line.
Reference Sustainability · Lesson 1: Meaning of Sustainability, the Triple Bottom Line and Strategies for Negative Impacts
- Question 43
A logistics company is changing the sorting process in its warehouses nationwide from manual to automated and has set up a dedicated working group for the effort, which has been defined as a project. Which of the following BEST reflects a characteristic of a project?
Show answer and explanation
Correct answer: D
A logistics company is changing the sorting process in its warehouses nationwide from manual to automated and has formed a dedicated working group, and the effort has been defined as a project. You must pick the option that best reflects a characteristic of a project.
The purpose of a project is to move an organization from its current state to a future state to achieve a specific objective. Changing warehouse sorting from manual to automated is exactly such a change, which fits the PMBOK 8 description of a project as creating value and driving change. The other three options describe operations or a narrow view of value. Test it another way: if this work were simply repeated every month with no end, it would be operations. Here there is a clear beginning, the goal is to replace the whole process with a new way of working, and the end point is full rollout of the new process. The answer is D.
Why the other options are wrong
- A. Continuously reproducing identical outputs in volume through a fixed process characterizes operations. A project can still include repeated activities or multiple similar outputs while existing in a unique context.
- B. The value of a project is not necessarily monetary profit. Goodwill, brand, compliance, and benefits to society and the environment are also value, so “must be profitable” is too absolute.
- C. Routine work carried out continuously over the long term is operations. A project is a temporary initiative with a defined beginning and end.
Key takeaway The essence of a project is driving change: moving the organization from its current state to a future state. Its value is not limited to profit, and it is not routine repeated work.
Variation If an option read “run the sorting line on a fixed shift schedule”, that would be operations, not a project. “Rebuild the sorting line once and hand it over for use” would be a project.
- Question 44
To evaluate overall project risk, a risk analysis group uses software to iterate its quantitative risk analysis model thousands of times and draws a cumulative probability curve (S-curve) showing the probability that project cost will not exceed each value. Which technique are they using?
Show answer and explanation
Correct answer: B
A risk analysis group is evaluating overall project risk. It uses software to iterate the model thousands of times and draws a cumulative curve of the probability that cost does not exceed each value. You must judge the quantitative technique from the method and the output.
The stem has two markers: software that iterates the model thousands of times, and an output that is a cumulative probability curve, the S-curve. Each iteration draws random values from the distributions of the uncertain factors and calculates one result, and thousands of results accumulate into the “probability that cost does not exceed a given figure”. This is the typical approach of simulation, and the most common simulation technique is Monte Carlo analysis. Decision tree analysis and sensitivity analysis do not use this kind of large-scale random iteration to generate an S-curve; an influence diagram can yield an S-curve only when its model is evaluated using a simulation technique such as Monte Carlo analysis. The answer is B.
Why the other options are wrong
- A. Decision tree analysis multiplies the probability and payoff of each branch to compare the expected monetary values of alternatives. Its output is a number for each alternative; it does not iterate and has no cumulative probability curve.
- C. Sensitivity analysis (common exam practice) varies one factor at a time with the rest held still, and outputs a tornado diagram sorted by size of effect. It answers “which factor matters most”, not the overall probability distribution.
- D. An influence diagram only represents the causal relationships and dependencies among variables, and it does not iterate by itself. To get the distribution of outcomes from the relationships in an influence diagram you still need Monte Carlo, and it cannot produce an S-curve on its own.
Key takeaway Software iterating repeatedly and a cumulative probability curve (S-curve) point to Monte Carlo analysis.
Variation In a question such as “which of the following is a technique available for quantitative risk analysis?”, the probability and impact matrix, SWOT analysis and assumption and constraint analysis are not quantitative techniques; they are tools for qualitative analysis or for identifying risks.
- Question 45
A manufacturer is transforming to agile. A manager who used to do traditional project management has been appointed Scrum Master and leads a team new to agile. The first change the team makes is to introduce the Daily Scrum, but members feel that meeting every day delays development and strongly resist it. After a few days of trial, the Scrum Master finds that the Daily Scrum is indeed giving him a lot of valuable information, but the members' resistance remains. What should the Scrum Master do NOW?
Show answer and explanation
Correct answer: C
An organization is transforming to agile. A former project manager has become Scrum Master and the team is new to agile and resists the Daily Scrum. The Scrum Master has confirmed that the meeting is valuable to him, but the resistance remains. What is the best thing to do?
The root of the resistance is that members have not yet seen the value of the Daily Scrum and think it only delays “real work”. If that view does not change, the meeting will sooner or later become a formality. An open and candid discussion lets the team voice its concerns and experience the benefits of the meeting together, and with a change of mindset they will be willing to take part. So the Scrum Master should hold an open discussion and work with the team to change its view. The answer is C.
Why the other options are wrong
- A. Suspending the meeting gives up the practice in the face of resistance. The Daily Scrum is a tool for the team to plan and manage its own work, raising transparency and fostering collaboration. Through open discussion, members need to understand its value for inspecting progress, adjusting the day's plan and surfacing obstacles, rather than abandoning it right away.
- B. A hard rule goes against self-organization and consensus. It only deepens the resistance and is not the servant-leader approach.
- D. Interviewing members one by one amounts to canceling the meeting. The information stays with the Scrum Master alone, and the synchronization and mutual commitments among team members disappear.
Key takeaway When a team resists an agile practice: change minds with an open discussion, without forcing it and without giving it up.
Variation If after the discussion the team believes there is a real problem with the meeting format (for example, it runs too long), the team itself can adjust the time and format of the meeting, but the purpose stays the same.
Reference Scrum Events · Lesson 3: The Daily Scrum (Daily Coordination Meeting)
- Question 46
In the final check before shipment, the team on a shared electric scooter project finds a major defect in the mounting structure of the battery compartment, a key component. The mounting could work loose while riding and poses a safety risk to users, and the client plans to begin deploying these scooters in two weeks. What should the project manager do?
Show answer and explanation
Correct answer: B
In the final check before shipment, a major defect in the battery compartment mounting structure is a fact, and the client will deploy in two weeks, so there is time pressure. The question asks what the project manager should do most urgently now.
The defect has already occurred, so first isolate the affected scooters immediately to prevent delivery of an unsafe product and investigate whether the cause lies in design, procurement, or assembly. Following PMBOK 8, the proposed defect repair and corrective action should be raised as change requests, assessed for impact under the change management plan, and submitted to the authorized person or change control board. After approval, update the relevant plans and logs, notify affected parties, implement the changes, and verify their effectiveness. Defect repair addresses the existing scooters, while corrective action addresses the process that produced the defect. Client communication should be timely and run in parallel with the investigation and change process, but it cannot replace action. The answer is B.
Why the other options are wrong
- A. The stem does not say that this defect is an identified risk, and there is no contingent response strategy (a common exam term: contingency plan) that can be triggered directly. Paying the cost up front neither controls the safety risk nor determines the right remedy. It skips steps.
- C. Communicating with the client is necessary and should be done promptly. But explaining the cause in person before the cause is known removes neither the safety hazard nor the client's worry. It should run alongside investigation and correction, not replace them.
- D. An apology letter is only an attitude. It contains no corrective action, the defect is still there, and in two weeks the scooters would still be delivered with a safety risk.
Key takeaway On finding a major defect, immediately prevent delivery of nonconforming products and investigate the cause. Submit defect repair and corrective action through change control, implement them after approval, and keep the client informed.
Variation If the defect had already been found by the client in use and affected operations, correct it as soon as possible and explain the situation and the progress of the repair to the client. Communication runs in parallel with correction, but communicating without correcting is still not enough.
- Question 47
A supermarket chain's membership system upgrade project is integrating the project management plan. The project manager finds that the marketing head expects a go-live date one month earlier than the planned date, and the two conflict. What should the project manager do?
Show answer and explanation
Correct answer: B
While integrating the project management plan, the project manager finds the marketing head's expected go-live date is one month earlier than planned, so expectation and plan conflict. What does the project manager do?
An expectation that does not match the plan is exactly what integrating and aligning the plan is meant to handle. The project manager first communicates: find out why the earlier date is needed and how much flexibility there is, then assess feasibility with the team. If it is feasible, adjust the plan. If resources, dependencies or other constraints prevent it, explain this to the other side and manage the expectation, so that both sides finally agree. That respects the need without breaking the plan's feasibility. The answer is B.
Why the other options are wrong
- A. Changing the date to the expectation without assessment ignores the team's estimates and constraints. The plan may become unachievable, and the team carries the risk of an unrealistic date.
- C. Insisting on the original plan and refusing to discuss it is a refusal to communicate. It damages the relationship with marketing, misses a legitimate need they may raise, and goes against the requirement to engage stakeholders.
- D. The project manager has the authority to coordinate first. Passing it straight to the sponsor to decide and staying out is escalating too early and gives up the responsibility to communicate and assess.
Key takeaway When the plan and expectations conflict, communicate and coordinate first, and adjust the plan or manage the expectation. Neither give in blindly nor refuse flatly.
Variation If, after communicating, you find that launching a month earlier needs added budget and changes a baseline, a change request is required, approved by whoever has the authority.
Reference The Project Management Plan · Lesson 1: Integrate and Align Project Plans: Purpose, Inputs and Outputs, and Practice
- Question 48
An e-commerce app project is delivered iteratively. The tech lead tells the project manager that a developer has failed to finish the tasks he took on for two iterations in a row. What should the project manager do next?
Show answer and explanation
Correct answer: D
On an iterative project, the tech lead reports that a developer has not finished the tasks he took on for two iterations in a row. The question asks what the project manager should do next. The signal is that the cause is unknown.
Unfinished tasks can have many causes: estimates that were too large, interruptions, a lack of skills or personal problems. Leading the team involves tracking team member performance, providing feedback and resolving issues, so the project manager should first meet the member, find out the reasons and give feedback, and then decide on adjusting tasks, providing support or training. The correct answer is D.
Why the other options are wrong
- A. Replacing him with a more experienced person before the cause is known is premature. The problem may lie in how tasks were broken down or in outside interference, which replacement does not fix.
- B. Having the tech lead conduct the conversation can add another layer of interpretation. Since the issue was reported to the project manager, speaking directly with the member provides first-hand information about the cause; the tech lead can still support the subsequent improvement actions.
- C. Skills training helps only when skills are lacking. Assuming a skills problem without first understanding the situation may waste time and make the member feel dismissed.
Key takeaway When a member repeatedly fails to deliver on commitments, meet to understand the cause and give feedback first, then decide on remedies.
Variation If the meeting confirms the tasks were estimated too large, adjust the task breakdown and the amount he commits to. If it is a skill gap, arrange training or pairing.
Reference Team Performance · Lesson 4: Poor Performance and Team Problems: Talk First, Find the Cause, Then Choose Measures
- Question 49
The development team of an online education platform says they cannot tell what benefit each functional requirement brings to the two stakeholder groups, schools and parents, and they often argue over which features can be cut first. What should the project manager do to help the team understand this connection?
Show answer and explanation
Correct answer: B
On an online education platform, the team cannot tell what benefit each functional requirement brings to schools and parents, and they often argue over which features to cut first. The question asks what the project manager should do to help the team understand the connection; look for a tool that links requirements to value.
The requirements traceability matrix links each requirement to the business and project objectives, helping to ensure that each requirement adds business value, and it provides a means to track requirements throughout the life cycle (PMBOK 8). If the team can consult a well-built matrix at any time, they can see who each feature is for and why it is being built, they have a basis for trade-offs, and the arguments have a shared set of facts. The answer is B.
Why the other options are wrong
- A. A stakeholder analysis workshop focuses on identifying stakeholders and their influence. It cannot link each specific functional requirement to a business objective, so it still does not answer “why is this feature built?”
- C. Inviting representatives to progress meetings may improve communication, but progress meetings focus on status and are not suited to tracing each feature to its source of value. It also adds a burden for the representatives.
- D. Asking the sponsor to review the backlog weekly concentrates decisions in the sponsor, slows the pace, and leaves the team still not understanding the link between features and stakeholders.
Key takeaway To let the team see where each requirement's value comes from, have them use the requirements traceability matrix.
Variation If the team were arguing about “can a feature be finished on time,” you would look at the schedule and the risks; if they are arguing about “why a feature is being built,” you look at the business objectives and source in the matrix.
Reference Requirements Traceability Matrix · Lesson 1: Requirements Traceability Matrix: Definition, Purposes, Columns and Attributes
- Question 50
A highway maintenance project has set aside part of its contingency reserve for weather risk, based on the official weather forecast. The latest forecast shows that weather over the next several weeks will be worse than predicted at planning time. What should the project manager do?
Show answer and explanation
Correct answer: A
During risk monitoring, the weather risk is already identified and contingency reserve has been set aside based on the old forecast. The latest forecast shows worse weather, and the project manager has to act on it.
The signals are "contingency reserve already set aside" and "forecast got worse": the risk is an identified one, what has changed is its size, and the original reserve may not be enough. The project manager should do a reserve analysis, comparing the remaining contingency reserve with the remaining risk, and if more is needed, go through change control under the organization's rules and submit a change request. The answer is A.
Why the other options are wrong
- B. You cannot take reserve away from other activities just because their risks are smaller. First compare remaining reserve with remaining risk through reserve analysis, and use or adjust it within your authority; when a cost baseline change or additional funding is involved, follow the formal change control procedure.
- C. Management reserve is for unknown-unknowns. The weather risk is an identified one, so first see whether the contingency reserve is enough; additional funds come up only if it is not.
- D. Checking only the total budget does not assess whether the contingency reserve itself is sufficient, and it skips the change control procedure. It is less complete than a reserve analysis.
Key takeaway When an identified risk worsens, do a reserve analysis first; if reserve is short, supplement it through a change.
Variation If the assessment shows the reserve is sufficient, keep monitoring and no change is needed. If the forecast improves, assess whether surplus reserve can be released through a change. For example, with a 20-day schedule reserve of which 8 days are used, 12 days remain. Assuming the remaining risks are all on the critical path and their delays add up, if they are expected to cause 11.5 days of delay in total, 12 > 11.5 is enough but with a thin margin; with an expected delay of 14 days the shortfall is 2 days and a change is needed (in practice this also has to be checked against the schedule network).
- Question 51
A supermarket chain’s store renovation project buys large quantities of shelving and light fixtures every week. Several suppliers want to work with the project, and the project manager is confident of negotiating a good price. The requirements, specifications, quantities and weekly delivery schedule are all settled. To get the best overall value from the future contract, what should the project manager do FIRST, before negotiating with the suppliers?
Show answer and explanation
Correct answer: A
A store renovation project buys shelving and light fixtures in large weekly volumes. The requirements, specifications, quantities and weekly delivery schedule are settled, and negotiation with suppliers has not started. The question asks what to do first before negotiating so that the future contract delivers the most value.
There are two signals: “the requirements are settled” and “FIRST, before negotiating”. The requirements analysis is done, so the next step is to confirm the boundaries within which the contract will be negotiated. The organization’s procurement policies, procedures and guidelines (organizational process assets) and the applicable legal parameters are the boundaries the contract must respect; external laws and regulations also have to be identified and complied with separately. Once these are clear, the bidding, negotiation and contract that follow are compliant, and a good price can be pursued inside that framework. Price lists and past experience are inputs you can use afterward. The answer is A.
Why the other options are wrong
- B. Price is an important negotiating factor, but collecting price lists before you know the contract’s constraints may produce quotes that do not meet the rules; that comes later.
- C. Past purchasing practice is only a reference. Every project’s needs and value differ, so start with this project’s constraints.
- D. A time-phased bill of materials belongs to requirements analysis, and the stem says the requirements, quantities and delivery schedule are already settled, so this step is done.
Key takeaway Once requirements are settled and before negotiation, first establish the policies, procedures, guidelines and legal parameters the contract must follow, and then negotiate the price.
Variation If the requirements, specifications and quantities were not yet clear, you would first analyze the project’s needs thoroughly and determine the resources required, and only then deal with the compliance framework. If the question were how to shorten the time needed to select a seller, the answer would be the pre-approved seller list.
- Question 52
A project manager is in charge of a showroom fit-out project and has signed an installment-payment contract with the customer. During execution the customer notifies the project manager that the next payment will be a month late and agrees to move the completion date back by a month; the schedule change has been approved through the formal change process. The project manager calculates that, at the current rate of spending, even counting management reserve, the funds will not last until the new payment date. What should the project manager do?
Show answer and explanation
Correct answer: B
During execution the customer delays a payment by a month, and the corresponding delay in completion has been approved through the formal change process. But at the current rate of spending, even with management reserve, the funds will not last until the new payment date.
The timing of funds arriving does not match planned expenditure, so you do funding limit reconciliation: adjust the schedule so that the rate of spending matches the pace at which funds arrive. Since the completion date can slip, release some resources and slow the pace to lower the rate of spending and last until the next payment date. The answer is B.
Why the other options are wrong
- A. Suspending and disbanding the team is too passive. The customer has only delayed a payment and has not terminated the contract, and reassembling the team later would be very costly.
- C. Lowering the quality standard would harm the deliverables. The project manager cannot lower quality standards unilaterally to save money; if quality requirements must be adjusted, it needs assessment and approval through the change process.
- D. The stem says that even counting management reserve the funds will not last until the new payment date, so keeping the current pace would still run dry. Management reserve is also not meant to bridge a payment delay.
Key takeaway When funds do not arrive in time, adjust the schedule and slow the rate of spending so that expenditure matches the arrival of funds. Slowing the pace adjusts the schedule and funding arrangements; if it affects an approved baseline, it still goes through change control.
Variation If the customer did not agree to delay completion, assess reducing scope, applying early for interim funding, or negotiating a change with the customer. If funds arrive early, you can speed up.
- Question 53
On a food-ordering mini-app development project for a restaurant chain, every metric on the dashboard is green, but the development lead privately reports that the team has been working overtime to catch up and defects keep growing in testing. What should the project manager do next?
Show answer and explanation
Correct answer: B
The dashboard is all green, but the development lead privately says the team has been working overtime and defects keep growing in testing. What should the project manager do next?
When the data show normal and the feeling on the front line says the opposite, the metrics may not reflect the real situation: the wrong measure may have been chosen, only good short-term performance may be visible, or data collection may be lagging. The project manager should first verify why the metrics and the actual situation do not match and find the cause, and then decide whether to adjust the metrics or deal with the problem. Verify first and then act. The answer is B.
Why the other options are wrong
- A. Trusting only the dashboard and treating the team's feelings as reference misuses the metrics (if green indicators are accepted selectively to preserve an existing judgment, it is confirmation bias) and lets the problem stay hidden behind the metrics.
- C. Adding more metrics to the dashboard does not guarantee they reflect the real situation, and may add more vanity metrics that do not help decisions.
- D. Requiring an end to overtime before the cause is understood is action without a basis. It cannot show the problem is solved, and waiting for the indicators to change color before reassessing is passive.
Key takeaway When metrics do not match actual experience, verify the cause of the discrepancy first; do not trust only the numbers and do not go only by feeling.
Variation If verification finds that data collection is lagging, speed up the data updates; if the metrics were wrongly chosen, replace them with metrics that reflect customer value and quality, and explain the reason for the change to stakeholders.
- Question 54
After a smart speaker project team completes the first batch of prototypes, the quality inspection team tests them and finds that the battery life of the prototypes is below what the quality metrics require. What should the project manager do FIRST?
Show answer and explanation
Correct answer: B
Testing of the first batch of smart speaker prototypes shows battery life below what the quality metrics require, and the cause has not been found. The question asks what the project manager should do FIRST.
Battery life falling short is a problem that has already surfaced, and the first thing is to understand why. Root cause analysis is used to determine the basic underlying reason that causes a variance or defect; once the cause is clear, you can judge whether to adjust the process, do rework or submit a change request. This is also step two of problem solving: first define the problem, then identify the root cause, and only after that generate solutions, choose one, implement it and verify. So first perform root cause analysis. The answer is B.
Why the other options are wrong
- A. A metric is the yardstick for judging results. A result that falls short is not a reason to relax the yardstick, and adjusting a metric also has to go through change control.
- C. Asking the supplier to replace the batteries when the cause is unknown presumes that the battery or the supplier is at fault. A change request can be raised at any time, but you should usually first understand the root cause and then choose among rework, correction or change according to the result.
- D. Notifying everyone and immediately implementing corrective action before the cause is clear is acting before analyzing. If the corrective action involves controlled items or baselines, it also has to be handled through change management, so this is not what to do first either.
Key takeaway When results fall short, find the root cause first, and only then talk about changes and corrective action.
Variation If the stem had said “the root cause has been found to be insufficient battery capacity”, the next step would be to submit a change request, and to correct it after the evaluation and approval of the change.
- Question 55
The implementation team at PMLyceum has always done retail system rollouts, and the project manager can estimate durations from how past projects were delivered. The company has now taken on an industrial IoT project that differs greatly from past projects, although the scope of work is clear and the WBS has been developed to the work package level. What should the project manager do next?
Show answer and explanation
Correct answer: C
The implementation team has always done retail system rollouts and can estimate durations from past projects. It has now taken on an industrial IoT project that differs greatly from them. What should the project manager do next?
Analogous estimating requires that the earlier activities be similar in substance to the current ones. The stem says the difference is large, so that premise fails and projecting from retail projects would carry a big error. Use the WBS: break the work into smaller tasks, estimate the duration of each one and roll them up level by level. That is bottom-up estimating, which usually gives higher accuracy. It has more basis than a single overall number and does not depend on dissimilar historical projects. The answer is C.
Why the other options are wrong
- A. Scaling from retail projects is analogous estimating, but the stem says the difference is large, so its premise does not hold.
- B. Expert judgment is an estimating technique recognized by PMBOK 8, but when the scope and the WBS are in place, giving only one overall figure and adjusting as you go is less well founded than estimating activity durations item by item.
- D. Estimating the schedule is the responsibility of the project manager and team. Even if the PMO supplies a target date, it cannot replace activity duration estimates based on decomposition of the work.
Key takeaway When there are no comparable historical projects, decompose the work and estimate bottom-up.
Variation If the project had just started with very little information and the sponsor wanted only a rough number, use analogous estimating. If you have reliable historical unit rates and the quantity of work, use parametric estimating.
- Question 56
On a software product launch project, delivery of a third-party interface may come two weeks later than planned. The marketing department is worried about the launch date and has asked about it several times. What should the project manager do?
Show answer and explanation
Correct answer: C
On a software product launch, a third-party interface may be delivered two weeks late. The marketing department is worried about the launch date and has asked several times. The question asks what the project manager should do.
Risk information should be shared promptly and transparently with the stakeholders it affects. By explaining the possible impact together with the response actions already planned, the marketing department can adjust its launch arrangements and feel reassured. This agrees with PMBOK 8's emphasis on distributing project information in a timely and appropriate way: nothing hidden and nothing promised in vain. The explanation can include the specific effect a two-week delay would have on the launch date and the decision point, so marketing knows when to expect a firm answer. The answer is C.
Why the other options are wrong
- A. Notifying them only after the delay is confirmed takes away their time to prepare, and after several inquiries, silence damages trust further.
- B. Telling them the risk without the response leaves them unable to judge the impact and increases their worry. The response actions are what reassure them.
- D. Promising an unchanged date while the risk remains is an empty guarantee. If it fails, trust suffers more, and it does not meet the requirement to communicate honestly.
Key takeaway Explain schedule risk promptly and transparently, with its impact and the response. Hide nothing and promise nothing in vain.
Variation If the response actions still cannot guarantee the date, give a likely range and a decision point instead of a single date.
Reference Managing and Monitoring Communications · Lesson 2: Project Reports, Meetings and Information Sharing: Including Reporting in Agile Settings
- Question 57
Alan has been put in charge of an agile project. While setting team rules, he decides to add transparent communication to put the agile philosophy into effect. What does transparency in communication mean?
Show answer and explanation
Correct answer: D
Alan is in charge of an agile project and adds transparent communication to the team rules. The question asks what transparency in communication means.
Transparency is one of the three pillars of Scrum. It means information is shared openly and honestly inside and outside the team, including good news as well as problems and lessons. Once the information gap is removed, the team and stakeholders can make judgments from the same facts and deliver a high-value product together. So candidly sharing successes and lessons from failure with stakeholders is what transparency in communication means. The answer is D.
Why the other options are wrong
- A. Transparency does not mean sending every piece of information to everyone. Who is told what should be agreed in advance in the communication rules, and too much information buries what matters.
- B. Transparency is information sharing. It does not mean members have no privacy, and the two are not the same thing.
- C. Giving information only to key stakeholders leaves other interested parties without the information they should have, which violates transparency. Information should be shared according to communication needs and confidentiality requirements, not only according to how important the other party is.
Key takeaway Transparency means sharing information openly and honestly, both successes and failures.
Variation If asked what inspection means, it is frequently checking artifacts and progress to detect deviations. Transparency makes sure inspection sees the real picture, the two complement each other, and adaptation then corrects the deviations found.
Reference The Agile Manifesto · Lesson 4: The Agile Mindset: Judging Scenario Questions with the Values and Principles
- Question 58
A team maintains a logistics scheduling system. It wants to make all its work visible, limit the amount of work under way at the same time, deliver results continuously, and not overload its members. This approach is based on lean principles. Which of the following methods fits these features BEST?
Show answer and explanation
Correct answer: B
A team maintaining a logistics scheduling system wants to visualize all its work, limit the work under way at the same time, deliver continuously and not overload its members, and this approach is based on lean principles. Which method fits these features best?
PMBOK 8 defines the Kanban method as a visual workflow management method to limit work in process (WIP) based on lean principles and focusing on continuous delivery without overburdening the team. The four features in the stem (visualization, limited WIP, continuous delivery, no overloading of members) correspond to this definition one for one. The answer is B.
Why the other options are wrong
- A. Scrum sets its rhythm with fixed-length Sprints. Limiting work in progress is not its core.
- C. Extreme Programming is an agile method that particularly emphasizes engineering practices. Pair programming supports code quality, but it is not the WIP-limiting workflow method described in the stem.
- D. The waterfall method typically advances in phases; phase-gate reviews do not provide the stem's combination of lean-based workflow visualization, WIP limits, and continuous delivery.
Key takeaway Kanban is built on lean principles: visualize, limit WIP and deliver continuously. Scrum uses fixed-length Sprints.
Variation For “fixed two-week Sprints, with a Sprint Review and a Sprint Retrospective at the end of each Sprint”, the answer is Scrum. For “write the test first and then the code”, the answer is test-driven development in Extreme Programming.
- Question 59
At delivery of a website redesign, the customer's representative refuses to sign off on acceptance, saying the project does not meet requirements, and asks the team to rework several deliverables. The team believes these rework requests go beyond the agreed requirements and refuses to make the changes. What should the project manager do FIRST?
Show answer and explanation
Correct answer: B
At delivery of a website redesign, the customer refuses to sign, saying requirements were not met, and asks for rework. The team says the rework goes beyond the agreed requirements and refuses. The question asks what to do first.
The heart of the dispute is whether the rework requests fall within the agreed scope. The acceptance criteria and related project documents are the objective basis agreed in advance. Checking against them first shows whether a request is a defect fix inside scope or a new request outside scope, so the team neither reworks blindly nor refuses without grounds. In an acceptance dispute, decide the nature of the request first and then act: inside the criteria it is a defect and must be remedied; outside the criteria it is added scope and must go through change control. Before the check, either response is premature. The answer is B.
Why the other options are wrong
- A. Reworking straight to the customer's wishes accepts out-of-scope requests without assessment and invites scope creep.
- C. Asking for funds before it is clear whether the work is in scope is premature and has no basis.
- D. The point in dispute is whether the rework requests are in scope, not why the requirements were not met. Analyzing causes misses the question.
Key takeaway When acceptance is disputed, check scope against the acceptance criteria and agreed documents first, then decide how to respond.
Variation If the check shows the rework requests are within the acceptance criteria, treat them as defects: record the cause and remedy them through the change control process. If they are outside the criteria, treat them as added scope and submit a change request.
Reference Monitor and Control Scope and Scope Creep · Lesson 1: Monitor and Control Scope: Purpose, Inputs and Outputs
- Question 60
A hotel group changes its long-term strategy to move toward an asset-light model. An ongoing project to standardize renovations of its company-operated hotels now produces results that diverge from the new strategic direction. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
A hotel group shifts to an asset-light strategy, and an ongoing project to standardize renovations of company-operated hotels now produces results that diverge from the new direction. What should the project manager do first?
The strategy change affects the project’s value. The project manager’s order of action is to first verify and assess how the change affects the project’s value, then report to the governing body, which decides whether to adjust or terminate. Project objectives are set through the business case and the governing body, and the project manager provides analysis and recommendations. Note that the project manager does not wait passively to be told: the project manager has a responsibility to identify and report value deviations proactively. But at the level of decision, adjusting the objectives or terminating the project falls within the authority of the sponsor or governing body. The answer is A.
Why the other options are wrong
- B. Continuing as planned puts resources into results that may no longer have value. Deviations should be reported promptly, not after the project ends.
- C. Project objectives are set through the business case and the governing body. A project manager revising them on his or her own after talking with the team is exceeding authority.
- D. Whether to terminate a project is decided by the sponsor or governing body. The project manager has no authority to announce termination alone.
Key takeaway When strategy changes affect value: assess first, report to the governing body, and let it decide whether to adjust or terminate.
Variation If the new strategy is consistent with the project’s direction and the project is only slightly behind schedule, that is routine schedule management and does not trigger value-level escalation.
- Question 61
An online education company starts a course platform upgrade project, and the sponsor wants to be able to see where the money is being spent at any time throughout the project. What should the project manager do when doing the financial planning?
Show answer and explanation
Correct answer: B
The project is in financial planning, the sponsor wants to see where the money goes at any time, and arrangements for tracking expenditure are needed.
The key signal is “at any time throughout the project”. It means tracking has to cover the whole project life cycle, and the planning stage must spell out what is recorded (the basis, for example by phase or work package) and how often it is rolled up (the frequency). Only then can the sponsor see where the money has gone at any moment, and variances be caught in time. The answer is B.
Why the other options are wrong
- A. With only a total, you cannot see how funds are used by phase or work package, cannot detect variances in time, and cannot satisfy “see where the money is spent”.
- C. A control threshold is the standard for judging when to take action, and it presupposes continuous tracking. Starting to record only after the limit is exceeded misses the chance to detect problems.
- D. Expenditures must be tracked inside the project throughout. If they are checked only once at closing, variances during the project cannot be controlled, and the project manager cannot be accountable for spending.
Key takeaway Financial planning should arrange expenditure tracking across the full life cycle, with a defined basis and frequency, not just look at totals or reconcile afterward.
Variation If the sponsor only wants “a report once a quarter”, the plan should still state the report content and frequency, but tracking itself must continue.
Reference Estimate Costs · Lesson 1: The Financial Management Plan, Funding Strategies and Estimate Accuracy
- Question 62
A project manager is in charge of developing an electric-vehicle battery pack. A team member points out that a control chip currently in use may fail at high temperatures. After an initial assessment, the project team and sponsor agree that the risk would affect both this project and other products under development that use the chip and is outside this project's scope. What should the project manager do?
Show answer and explanation
Correct answer: D
On an electric-vehicle battery pack project, a member points out that the control chip in use may fail at high temperatures, and other products under development that use the chip would be affected too. The question asks what the project manager should do.
After the initial assessment, the project team and sponsor have agreed that the risk is outside this project's scope, so it meets the condition for escalation. PMBOK 8 lists escalation as a threat response strategy when the project team or sponsor agrees that a risk is outside project scope or that the proposed response would exceed the project manager's authority. This project alone cannot solve the other products' problem, so escalate it to senior management. The answer is D.
Why the other options are wrong
- A. Risk analysis is an important step after identification, but quantitative analysis is not required for every risk; and since this risk's impact goes beyond this project, the key is to report to the management level that matches its impact, where a higher level can coordinate.
- B. Suspending the project and replacing the supplier is an overreaction: the risk has not been analyzed in depth or approved for such a step, and it looks after only this project while the effect on other products remains unaddressed.
- C. Passing the chip to purchasing while this project only logs and monitors it leaves a cross-project risk inside this project. A risk that affects other products should be actively reported upward, whoever manages it.
Key takeaway When a risk's impact goes beyond this project's scope or the response exceeds your authority, use the escalate strategy so that the level able to coordinate handles it.
Variation If the risk affected only this project and the response were within the project manager's authority, analyze and respond within the project, with no need to hand it up.
- Question 63
A project manager leads a geographically dispersed virtual team whose members come from different cultural backgrounds. What should the project manager do to avoid uncertainty for the project caused by cultural differences?
Show answer and explanation
Correct answer: D
A geographically dispersed virtual team has members from different cultural backgrounds, and the project manager wants to avoid uncertainty caused by cultural differences. The question asks for a suitable way to manage cultural differences proactively.
The most effective response to cultural differences is to learn about them proactively. First gather information on members’ cultural backgrounds, then have members discuss their working habits and work ethic so they better understand one another’s cultures and identify what needs to be considered at work. This reduces uncertainty, and it fits the attitude toward diversity in the Build an Empowered Culture principle. The answer is D.
Why the other options are wrong
- A. Requiring members to drop their cultural habits and adopt a “neutral” way of working is hard to do, consumes resources, and disregards respect for diverse cultures.
- B. Starting the project and just recording the uncertainty in the risk register to watch it takes no positive action. Cultural differences can be understood and managed proactively.
- C. Cultural differences can be dealt with, so there is no need to disband the team. And the resources needed for colocation may not be available in time either.
Key takeaway Learn about cultural differences proactively and discuss them openly, rather than avoiding them, only recording them, or breaking up the team.
Variation If the stem said cultural differences had already caused conflict, have the people involved talk directly and agree on working conventions together. If a member asks for a transfer because of discomfort, first talk with the member to understand the reasons, then consider other measures.
- Question 64
PMLyceum’s PMO has just run training on the Eighth Edition of The Standard for Project Management. At the review meeting, a colleague says: “Focus on Value tells us to cut costs, while Integrate Sustainability Within All Project Areas tells us to spend more. The two principles contradict each other, so we can only follow one.” How should project manager Lena respond?
Show answer and explanation
Correct answer: C
The PMO has just finished training on the Eighth Edition. At the review meeting someone argues that one principle calls for cutting cost and another for spending more, so only one can be followed. The project manager has to respond to that claim.
The problem is the premise itself: “they contradict, so choose one” is wrong. The Eighth Edition explains that principles provide foundational guidance for strategy, decision-making and problem-solving, and that they are not prescriptive; they are intended to reinforce the mindset and guide behavior. The principles are complementary and supplement one another, so no principle contradicts another, and when they overlap in practice, that reflects the complex and interconnected nature of project management. Focusing on value means obtaining value for what is invested, and sustainability concerns long-term value. How to balance them in a specific case depends on the context of the organization, the project and the stakeholders; the answer is not to delete one of them. The answer is C.
Why the other options are wrong
- A. This treats the principles as rules to follow one by one, which contradicts “not prescriptive”, and it invents a priority (“Focus on Value takes precedence”) that does not exist among the principles.
- B. The six principles stand side by side. Even two principles in the same dimension have no order of priority and no ranking that lets one be dropped; dropping one breaks the integrity of the mindset.
- D. Overlap is not a defect. It is normal, and the principles do not need revising before they can be used; they are meant to be applied flexibly in each organization’s own context.
Key takeaway Principles are a direction for thinking and behavior, not rules; they complement one another without contradiction, and they may overlap.
Variation If the question asked how many mindset dimensions the six principles fall into and which one sustainability belongs to, the answer is three dimensions, with sustainability and Focus on Value both in the value-driven dimension. If an option says the six principles have an order of priority, rule it out in the same way.
- Question 65
An airport baggage system upgrade project is carrying out executing work. The risk manager checks the PMBOK 8 mapping table for the work assigned to the Risk performance domain in the Executing Focus Area. Which of the following is a process at that intersection?
Show answer and explanation
Correct answer: B
The baggage system upgrade is carrying out executing work, and the risk manager checks the mapping table for the work assigned to the Risk performance domain in the Executing Focus Area. You must identify the process at that intersection.
Consult the mapping table: the Risk performance domain has four processes in the Planning Focus Area, Plan Risk Management, Identify Risks, Perform Risk Analysis, and Plan Risk Responses; in the Executing Focus Area it has only Implement Risk Responses; and in the Monitoring and Controlling Focus Area it has Monitor Risks. For the executing-classified work asked about here, the corresponding process is Implement Risk Responses. The answer is B.
Why the other options are wrong
- A. Identify Risks is placed in the Planning Focus Area in the PMBOK 8 mapping table, although risk identification continues throughout the project and new risks must still be identified and the register updated during execution; this question classifies by the mapping table, and the Executing Focus Area corresponds to Implement Risk Responses.
- C. Monitor Risks belongs to the Monitoring and Controlling Focus Area, which runs in parallel with executing, but it falls in a different column of the mapping table.
- D. Plan Risk Responses is placed in the Planning Focus Area in the mapping table; when new risks are identified during the project, new responses can also be planned iteratively.
Key takeaway The Risk performance domain: in Planning it identifies, analyzes, and plans responses; in Executing it implements responses; in Monitoring and Controlling it monitors risks.
Variation If the question asked about the Governance performance domain’s processes in the Executing Focus Area, the answer would be Manage Project Execution, Manage Quality Assurance, and Manage Project Knowledge. The Scope, Schedule, and Finance performance domains have no processes in the Executing Focus Area.
- Question 66
In a backlog refinement session, the product owner mentions a large requirement, “membership program”, which the team calls an epic. Which of the following statements about an epic is correct?
Show answer and explanation
Correct answer: B
In a backlog refinement session, the product owner mentions a large requirement, “membership program”, which the team calls an epic.
An epic is a large body of related work. It is too big to be completed in one iteration and must be decomposed further into smaller user stories that can be estimated and fit in an iteration, and the team can break stories down into tasks as needed. So the correct statement about an epic is that it can be split further into smaller user stories. The answer is B.
Why the other options are wrong
- A. What can be completed in one iteration is an ordinary user story. An epic is larger and must be split before it can be placed in an iteration, so the two are not equivalent.
- C. An epic is also an item in the product backlog, just at a coarser granularity, and it is refined step by step as iteration planning approaches.
- D. There is no rule that an epic must be split along functional modules. The aim of the split is to deliver value, make estimating easier and fit within an iteration, and it can be done by user scenario or value slice.
Key takeaway An epic is a coarse-grained requirement: split it into user stories first and, if necessary, into tasks.
Variation If the question is how small an item must be before it can enter an iteration, the answer is small enough to be completed within one iteration and estimable by the team; if the team has a definition of ready, it usually includes these requirements.
Reference User Stories · Lesson 1: User Story Format, Personas and Epic Decomposition
- Question 67
A digital transformation project at a publishing house has entered execution, and the project manager is to monitor how the project management plan is being carried out. Which of the following practices is most appropriate?
Show answer and explanation
Correct answer: A
The project is in execution, and the project manager is to monitor how the project management plan is being carried out. Which practice is most appropriate?
Monitoring project performance is ongoing work throughout the life cycle: tracking execution against the plan continuously and taking action promptly when deviations are found keeps variances small and prevents small ones from accumulating into big problems. This practice is proactive and has a rhythm; the other options concentrate checking at some point in time or wait for an outside trigger, and are not timely enough. The answer is A.
Why the other options are wrong
- B. A review against the plan at closing is a summing-up of experience. By then the variances are established facts and it is too late to correct them, so the lessons can only be left to future projects.
- C. Checking only once at the start of each phase means deviations within the phase are not found in time, and a phase may last several months.
- D. Waiting for stakeholders' comments before checking means inspecting only after outside feedback; it lacks proactive, continuous monitoring, and by the time comments arrive the problem is often serious.
Key takeaway Monitoring of plan execution is continuous. Correct deviations promptly when found; do not make it up at some milestone.
Variation If the project monitors at a high-frequency rhythm such as the daily coordination meeting and the iteration review, that is likewise continuous, not after the fact.
Reference Monitor and Control Project Performance · Lesson 1: Monitor and Control Project Performance: Purpose, Inputs and Outputs, and Analysis Methods
- Question 68
An industry association commissions a team to develop a regional brand promotion strategy, and the project manager is appointed to lead it. While preparing to estimate, the project manager finds that little detailed information is on hand, but several neighboring associations have already successfully carried out almost the same strategy. Which estimating method should the project manager use?
Show answer and explanation
Correct answer: B
While preparing to estimate, little detailed information is on hand, but several neighboring associations have successfully carried out almost the same strategy. The question asks which estimating method to use.
The key signals are “little detailed information” and “almost the same strategy has already been carried out successfully”. PMBOK 8 states that analogous estimating uses historical data from a similar activity or project to estimate the current one, and that it is frequently used when there is limited detailed information, with lower cost and less time. There are similar projects here to refer to directly, so analogous estimating is the best fit, adjusted for differences. The answer is B.
Why the other options are wrong
- A. Multipoint estimating combines optimistic, most likely and pessimistic values to address uncertainty. Here, however, closely analogous completed projects make analogous estimating the more direct and efficient choice.
- C. Expert judgment can also support estimating, but the stem explicitly supplies historical data from highly similar projects, which directly indicates analogous estimating; expert opinion can help assess similarity and adjust for known differences.
- D. Parametric estimating needs reliable historical data and a quantified parametric model. The stem has only similar cases and gives no data that could be modeled.
Key takeaway Little information, with a similar project available to refer to: analogous estimating; the more similar, the more reliable.
Variation If a large body of historical data showed that cost is steadily related to some variable, switch to parametric estimating for higher accuracy.
Reference Estimate Costs · Lesson 2: Estimating Methods: Analogous, Parametric, Bottom-Up and Multipoint
- Question 69
Mike is building a seaside guesthouse. A string of typhoons has delayed the project by 3 weeks. The main structure is now topped out, and the waterproofing layer must be done next, and only after it is done can the roof tiles be laid. The order cannot be reversed. Which of the following is this?
Show answer and explanation
Correct answer: D
On a seaside guesthouse project, typhoons have delayed the work by 3 weeks. The main structure is topped out, and the waterproofing layer must be done before the roof tiles are laid, with no way to reverse the order. What kind of situation is this?
The order of waterproofing and tiling is determined by the nature of the work and cannot be reversed, so it is a mandatory dependency (hard logic). PMBOK 8 states that mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work, and they often involve physical limitations. The 3-week delay is a distractor and has nothing to do with the type of dependency. The answer is D.
Why the other options are wrong
- A. A lag is extra waiting time added to a logical relationship. The stem does not say how long to wait after the waterproofing is done before laying tiles.
- B. A discretionary dependency is an order based on good practice or preference that can be changed freely. The order of waterproofing and tiling cannot be changed, so it is not discretionary.
- C. Crashing is a way to compress the schedule. The stem does not ask for a shorter duration and only describes the nature of the order.
Key takeaway An order that is determined by the nature of the work and cannot be reversed is a mandatory dependency.
Variation If “finish the guest rooms before the corridors” is only the crew's usual order, it is a discretionary dependency, which can be adjusted or run in parallel.
Reference Precedence Diagramming Method · Lesson 2: Types of Dependencies, and Leads and Lags
- Question 70
A product development team has worked together steadily for two years and has always delivered good quality. The project manager fully trusts the team, rarely asks about the day-to-day work and lets the team decide how to do it. Which leadership style is this?
Show answer and explanation
Correct answer: B
A product development team has worked together steadily for two years with consistently good quality. The project manager fully trusts the team and rarely asks about the daily work. The question asks which leadership style this is.
These style names are common exam terms; PMBOK 8 asks the project manager to adjust style to team members’ willingness and ability. Laissez-faire fits a team that is mature, capable, willing to take responsibility and works well together: the leader trusts the team, lets it decide how to do the work and steps in only when needed. The signals in the stem (stable cooperation, good quality, rarely asks, the team decides how) all point to laissez-faire. The answer is B.
Why the other options are wrong
- A. Transactional leadership drives behavior through an exchange of rewards and penalties, handed out according to performance. The stem shows no such exchange; what stands out is trust and a hands-off attitude.
- C. Charismatic leadership moves the team through personal appeal and influence, so the team follows the leader himself. The stem describes a project manager who rarely gets involved, not one who inspires through personal charm.
- D. Transformational leadership uses vision, inspiration and personal care to drive innovation and growth, with the leader actively involved. Here the project manager rarely asks, which is the opposite.
Key takeaway Trusting a mature team, intervening little and letting it decide for itself is laissez-faire.
Variation If the team were newly formed and inexperienced, the same hands-off approach would not fit; the project manager should switch to more guidance and support, adjusting style to members’ willingness and ability.
Reference Leadership Styles · Lesson 1: Leadership vs. Management, and Choosing a Leadership Style
- Question 71
An airport baggage sorting project originally planned to install three sorting lines. One has passed acceptance testing and the other two are being installed. The client issues a change order for one more sorting line, but this new line uses a brand-new sorting technology, its main components must all be custom made, and it differs greatly from the existing three lines, so there is no historical data to refer to directly. What method should the project manager use to estimate the delivery time of this additional line accurately?
Show answer and explanation
Correct answer: A
An airport baggage sorting project has a change order for one more sorting line. It differs greatly from the existing three lines, its main components are custom made, and there is no historical data to refer to directly. What method gives an accurate delivery time for the new line?
The stem stresses “accurate”, and the new line differs greatly from the existing three with no historical data to refer to directly. Analogous and parametric estimating both depend on similar historical data or a reliable parametric relationship, which are not available here. Bottom-up estimating breaks the work into smaller tasks, estimates each and aggregates, which can cover the work the custom parts create, reflects the real situation of the new line better, and is usually more accurate. PMBOK 8 also notes that when an activity cannot be estimated with a reasonable degree of confidence, the work is decomposed in more detail and the estimates aggregated. The answer is A.
Why the other options are wrong
- B. Referring to historical data from similar past projects is the logic of analogous estimating. The new line differs greatly and no historical data can be referred to directly, so the work on custom parts is hard to reflect, and it does not meet the need for “accurate”.
- C. Adjusting the estimates of the existing lines is also essentially analogous. The new line differs greatly from them, so the size of the adjustment cannot be judged and custom work is easily missed.
- D. Parametric estimating needs a reliable statistical relationship between historical data and parameters. The stem provides no such model or data.
Key takeaway When accuracy is required and the work is different, choose bottom-up estimating; analogous and parametric estimating are quicker but rougher.
Variation If management wanted “a rough number today”, choose analogous estimating: quick and low cost, but less accurate.
Reference Estimating Techniques for Duration · Lesson 2: Analogous, Parametric and Bottom-Up Estimating
- Question 72
On a smart speaker development project, the project manager has a team member track risks. The member reports that the register holds many risks whose probability and impact are both very low and does not know how to manage them. How should the project manager advise?
Show answer and explanation
Correct answer: B
The register holds many risks whose probability and impact are both very low, and the team member does not know how to manage them. The question asks how the project manager should advise on allocating effort.
“Both probability and impact very low” corresponds to the low-priority area of the matrix. Such risks do not need heavy effort. They go on the watch list in the risk register and are reviewed periodically, and if their probability or impact rises they are reassessed. Effort goes to the high-priority risks. In this way nothing is missed and no resources are wasted. The answer is B.
Why the other options are wrong
- A. Tracking everything to the same degree dilutes effort, so high-priority risks do not get enough attention. It violates the principle of allocating resources by priority.
- C. Low-priority risks must still be recorded. Their priority may rise when conditions change, and without a record you lose the chance to monitor them. Waiting until they occur and treating them as issues is a passive approach.
- D. Making a detailed plan and setting aside dedicated funds for every low-priority risk puts in effort out of proportion to the benefit. It is over-management.
Key takeaway Low-probability, low-impact risks go on the watch list for periodic review. They are neither ignored nor a focus of investment.
Variation When the probability of a watch-list risk rises because of external change, reassess it and, if necessary, take it off the watch list and plan a response. If a risk is high probability and high impact, a response plan is needed.
- Question 73
On a conference exhibition hall fit-out project, the client's representative believes that making the reception desk height-adjustable would raise satisfaction and has submitted a change request, which has been approved. The project is currently ahead of schedule with ample budget, but the structural designer keeps putting off starting the changed design, believing the change is pointless. What should the project manager do?
Show answer and explanation
Correct answer: A
On an exhibition hall project, the client's change request to make the reception desk height-adjustable has been approved. The project is ahead of schedule with ample budget, but the structural designer thinks the change is pointless and delays starting. The question asks what the project manager should do. The core is that the change is approved and the resistance comes from one person.
The change has gone through approval. The problem lies in the designer's attitude. PMBOK 8 says: “Conflict should be addressed early and usually in private, using a direct, collaborative approach.” The project manager should meet the designer, understand and address his concerns and find out why he resists. Then he will carry out the work actively. The correct answer is A.
Why the other options are wrong
- B. The change was approved through the established process. Asking for a re-review just because one member resists does not address his concerns and needlessly disrupts execution of the change.
- C. Ordering execution without considering the designer's views easily leaves him working with a bad attitude, which hurts design quality, and it does not remove the root of the resistance.
- D. The problem lies with one designer. Calling all stakeholders to a meeting is out of proportion and exposes an individual's issue. Communicate directly and privately first.
Key takeaway When a member resists an approved change, communicate privately first and remove the concerns. Do not re-approve or force execution.
Variation If the designer's concerns involve a real technical risk, the project manager should assess it and give feedback, and if necessary reassess the impact through the change control process.
Reference Team Performance · Lesson 4: Poor Performance and Team Problems: Talk First, Find the Cause, Then Choose Measures
- Question 74
During project execution, a member is transferred away and a newly recruited person takes over the role. The organization has configured this project's PMIS as the central access point for project documents and lessons learned, but the newcomer does not know which system to use to find them. What should the project manager tell the newcomer to use?
Show answer and explanation
Correct answer: A
During execution a member is replaced, and the newcomer wants to look up the lessons learned and project documents the project has accumulated but does not know where. What tool should the project manager point them to?
A project management information system is an information system made up of the tools and techniques used to gather, integrate and disseminate the outputs of project management processes. It can include scheduling tools, a configuration management system, a work authorization system and information collection and distribution tools. A project's lessons learned and documents are gathered in it, so the newcomer can look them up in one place. The key in the stem is “lessons learned and various project documents,” which covers the project's information as a whole and so points to the overall system, not to one of its components. The answer is A.
Why the other options are wrong
- B. Scheduling software is only one component, used to build and track the schedule. It does not hold lessons learned and various documents.
- C. A work authorization system authorizes the start of work and ensures work begins in the right order. It has nothing to do with looking up reference material.
- D. A configuration management system controls configuration items and versions. It is likewise only a component and is not the entry point for looking up all project information.
Key takeaway To look up project documents and lessons learned in one place, use the project management information system.
Variation If the situation were “make sure all parties use the latest version and changes are recorded,” the answer is the configuration management system. If it were “a piece of work may start only after prerequisite work is complete,” it is the work authorization system.
- Question 75
A startup runs 5 projects at once, one of which is a one-year customer portal project that is six months in. The company's cash flow dries up, and senior leaders decide to terminate two projects, including this one. What should the project manager do next?
Show answer and explanation
Correct answer: C
The startup runs 5 projects, cash flow dries up, and leaders decide to terminate two, including this customer portal project six months in. The question asks what the project manager does next.
The termination decision has been made by senior management, and its cause is a company-level funding problem. The project manager's task is to carry out the closure that follows termination: handle it as an early termination, store the historical information and lessons learned in the lessons learned repository for use by future projects or phases, and hand off the completed and uncompleted deliverables. The answer is C.
Why the other options are wrong
- A. The decision was made by senior management and its cause is a hard constraint, the collapse of funding. The project manager's job is to carry out closure after termination, not to ask management to find other ways.
- B. Financing is a company-level matter. Management has decided to terminate, so the team should turn to closure and not brainstorm for funds.
- D. Seeking funds from other projects conflicts with management's decision to terminate and is not the project manager's task at this point. The project manager should proceed with closure under that decision.
Key takeaway Once a project is terminated it goes into closure, and the lessons learned go into the repository for future use.
Variation If the stem asked for “the first step after termination”, start closure as the organization's closure requirements direct, and investigate and record the reason for termination during closure. If the sponsor says “the project is not profitable, we are stopping”, follow the closure process in the same way and do not re-justify the project.
- Question 76
Two members of a project team are in conflict: Member A says Member B is always talking about colleagues behind their backs. A will not listen to any advice, and B will not accept feedback. How should the project manager handle this?
Show answer and explanation
Correct answer: A
Member A thinks Member B is always talking about colleagues behind their backs; A will not listen to advice and B will not accept feedback. The question asks how the project manager should handle this.
The disagreement is essentially about standards of behavior: what counts as acceptable collaborative conduct. The team charter, including its ground rules, sets the behavior and communication the team has agreed on. Going back to the ground rules in the team charter, checking whether they cover talking about others and accepting feedback, and reaffirming or adding to them lets the project manager correct behavior against a standard everyone agreed to, instead of each side saying its own thing. Relying on the shared agreement also keeps the project manager from judging by personal preference. The answer is A.
Why the other options are wrong
- B. Moving one person is avoidance. It does not address the missing agreement on collaborative behavior, and the problem may repeat in the new setting.
- C. The communications management plan is built from stakeholders' communication needs. The stem shows no change in those needs, and the behavior problem between the two members should be addressed first.
- D. These behaviors may affect performance, but the stem does not show that disruptive conflict has continued after correction within the team. Reporting to their supervisors now would therefore be premature escalation; the behavior should first be addressed within the team using the rules.
Key takeaway For a dispute over behavior standards, go back to the ground rules in the team charter and use the shared agreement as the basis.
Variation If the charter has no relevant provision yet, add one together with the team and make clear that the new rule applies to all members.
- Question 77
A global team is about to launch a cross-border e-commerce platform overhaul project. Travel is not feasible for team members, so most will take part virtually. What should the project manager do to get team members truly committed to the project?
Show answer and explanation
Correct answer: D
A global team is about to start a cross-border e-commerce platform overhaul. Travel is not feasible, so most members will participate virtually. The question asks how to get members truly committed to the project.
When the team works virtually most of the time, the key is to let members communicate in real time, share information and work together. A virtual collaboration environment brings video conferencing, instant messaging, file sharing and joint editing into one place. It can support daily collaboration throughout the project, information is open and transparent, and members find it easier to commit. The answer is D.
Why the other options are wrong
- A. One-on-one meetings only improve communication between the project manager and one member at a time, and members still lack collaboration with one another.
- B. Asking HR for team-building advice is only one part of planning, and advice by itself does not get members involved right away.
- C. A weekly meeting helps, but it is infrequent and interaction happens only at the meeting, so it cannot support members’ daily real-time communication and collaboration.
Key takeaway A virtual team relies on a collaboration environment (video conferencing, chat, document sharing) to support daily communication, not meetings alone.
Variation If the stem said the team already had a collaboration environment but engagement was low, strengthen one-on-one conversations and informal online activities. If one member cannot use a particular tool, switch to a tool everyone can use.
- Question 78
A project manager takes over a large logistics park information system project with more than 100 team members. Progress is difficult and the expected benefits are hard to realize. The project manager wants every requirement to be tied to the business objectives and project objectives. What should the project manager do?
Show answer and explanation
Correct answer: D
The project is large with many people, progress is difficult and the expected benefits are hard to realize. The question asks for a management tool that lets “every requirement connect to an objective.”
One purpose of the requirements traceability matrix is to link each requirement to the business objectives or project objectives, which helps confirm that each requirement has business value. Using it, you can check item by item whether each requirement has a corresponding objective; requirements with no objective are exposed, and either a justification is added or the requirement is not built. It also tracks requirements throughout the life cycle. The answer is D.
Why the other options are wrong
- A. Reviewing all the requirements every week is costly on a project of more than a hundred people, and a review by itself does not systematically create and maintain item-by-item links between requirements and objectives.
- B. Reviewing the project management plan thoroughly helps in understanding the overall arrangement, but the plan does not record the relationship between each requirement and its objective one by one.
- C. The project charter contains only high-level requirements. Writing every requirement into it is neither appropriate nor a way to build item-by-item links to objectives.
Key takeaway When you see “ensure that every requirement is linked to the business objectives,” choose the requirements traceability matrix.
Variation If the stem were changed to “ensure that every approved requirement in the requirements documentation is delivered by the end of the project,” the answer would still be the requirements traceability matrix; that is another of its purposes.
- Question 79
The design phase of a factory MES implementation project is taking far longer than planned, and the main stakeholders on the customer side worry that the whole project will be late. What should the project manager do?
Show answer and explanation
Correct answer: B
The design phase has used far more time than planned, the customer side worries that the whole project will be delayed, and the question asks what the project manager should do.
When a variance appears, analyze the cause first and then decide what to do. A root cause analysis workshop can establish why the design phase is slow, so corrective action can address the real problem. The common pattern in variance scenario questions is to find the cause first and then act; here only root cause analysis meets the “analyze first” test, and the other three all act before the cause is understood. Any measure taken before the cause is found may spend cost on something that is not the problem. Once the cause is found, use the control threshold to decide whether action is required and the project's governance and authority limits to decide whether to escalate, and go through change control if necessary. The answer is B.
Why the other options are wrong
- A. Crashing without knowing why the work is slow easily causes quality problems or new risks.
- C. Adding float does not solve a delay that has already happened, and the cause has not been identified.
- D. Contingency reserve is for identified risks, and the stem does not say this delay is an identified risk.
Key takeaway After a variance appears, analyze the cause first; do not go straight to crashing, adding reserve or adding resources.
Variation If the analysis finds that the cause is a shortage of resources on the critical path, then consider crashing; if the variance exceeds the control threshold, action is required, and it goes up through governance if it is beyond your authority.
- Question 80
A filling production line at PMLyceum is being monitored. The net content of the most recently sampled bottle falls outside the control limits on the control chart, and all the other points are within the limits. What should the project manager do?
Show answer and explanation
Correct answer: A
A filling line is being monitored, and the net content of the most recently sampled bottle falls outside the control limits on the control chart, with all the other points within the limits. The question asks what the project manager should do.
Control limits mark the range a stable process's natural variation can reach. As long as one point falls outside the limits, that is one of the cases of out of control, indicating that a special cause may exist, so judge the process out of control, look for the cause and take action. The judgment of out of control does not depend on whether the other points are normal. This is one of the ways to judge out of control; another is the “seven-point rule” used in exam practice, in which 7 consecutive points fall on the same side of the mean. The answer is A.
Why the other options are wrong
- B. The other points being within the limits cannot cancel the point outside; one point outside is enough for out of control.
- C. One point outside is already enough to establish out of control, and there is no need to wait for more data. Delay only lets the problem accumulate.
- D. A point outside the limits is beyond the range of natural variation and cannot be easily put down to chance. Chance fluctuation is usually inside the limits.
Key takeaway One point outside the control limits is out of control. Look for the cause first; do not let it pass as chance variation.
Variation If no point is outside but, under the seven-point rule used in exam practice, 7 consecutive points fall on the same side of the mean, it is also judged out of control; 6 consecutive points do not count yet.
- Question 81
A project manager is appointed to roll out a new solution at the same time in branch offices in three countries, with each country's deployment team responsible for its own integration and go-live. The project manager notices that the teams run into similar problems but each solves them alone. What should the project manager do to promote collaboration among the teams?
Show answer and explanation
Correct answer: C
The deployment teams in three countries go live separately and run into similar problems, but each solves them alone. The question asks what to do to promote collaboration among the teams; the core is managing project knowledge.
The key signal is “similar problems, each solved alone.” It shows that experience is not flowing between teams and that work is being duplicated. The most direct remedy is to call the deployment teams together regularly and lay out the problems they have met and the solutions they already have, so that other teams meeting the same problem can borrow them, saving resources and time. Regular, interactive exchange also promotes the transfer of tacit knowledge. The answer is C.
Why the other options are wrong
- A. A more detailed schedule and action plan is a planning-level management measure. It does not let the teams exchange problems and solutions, and each team would still solve the same problems separately.
- B. Replacing managers addresses each team's own management. The root of the lack of communication between teams is that no sharing mechanism exists, and changing people does not fix that.
- D. Having some countries postpone deployment would delay the overall schedule, deprive those teams of hands-on experience and do nothing to improve communication between the teams.
Key takeaway When different teams meet similar problems, regular meetings to exchange problems and solutions are the most direct way to share knowledge.
Variation If the teams are in different time zones and meetings are inconvenient, switch to a shared knowledge base or an online Q&A platform so that problems and solutions accumulate continuously and can be looked up at any time.
Reference Lessons Learned · Lesson 1: Knowledge Types and Knowledge Management: Explicit vs. Tacit Knowledge
- Question 82
Which of the following is NOT content that a risk management plan should contain?
Show answer and explanation
Correct answer: C
To find the item that should not appear in the risk management plan, you must separate what belongs in the risk management plan from what belongs in the risk register.
The risk management plan sets “how to manage risk”. Its content is rules and framework and it does not record specific risks. The trigger conditions and owner of each threat are information about one identified risk and change risk by risk, so they belong in the risk register. The other three are rules: risk categories group risks, roles and responsibilities set who does what, and measurable risk thresholds express the stakeholders' risk appetite. The stem asks for the item that does NOT belong, so the answer is C.
Why the other options are wrong
- A. Risk categories (often grouped with a risk breakdown structure) are one element of the risk management plan, used to categorize individual risks; they are a rule and should appear in the plan.
- B. Roles and responsibilities for the risk management activities are set out in the plan, saying who leads, who supports and who takes part; they belong in the plan and are not the item to exclude.
- D. Measurable risk thresholds set for each project objective quantify stakeholders' risk appetite and go into the plan; they are plan content and not the item to exclude.
Key takeaway The risk management plan says “how to manage”; detailed information such as a specific risk's triggers and owner goes in the risk register, while the risk report may summarize information about individual risks.
Variation For the difference between plan and register, remember one sentence: the plan covers “how to manage” and the register covers “what to manage”.
- Question 83
An online education platform's student management system is scheduled for release next week. Regulation mandates that student personal information be stored encrypted, and without this the system may not go live. During pre-release completeness verification, the project manager finds that the encryption function was never developed. What should the project manager do next?
Show answer and explanation
Correct answer: B
The project is at pre-delivery verification, and the regulatory requirement is a precondition for release. The gap is that the team did not implement the requirement, not that stakeholders do not understand it.
Encrypted storage is a mandatory regulatory requirement, and without it the system cannot be released. Verification has found the gap, so the project manager has the team build the missing function, verify again, and release only after it passes. The key information is that the function was “never developed”: this is a missing function, not a matter of understanding, and not something that can be waived. A simple way to judge: “regulation mandates” and “may not go live” make this a hard condition. Although the gap is found near the release and will cause rework and delay, it must still be built and verified first, which is better than going live in violation and bearing the regulatory and repair consequences. The answer is B.
Why the other options are wrong
- A. Whether stakeholders understand the regulation is not where the gap lies. The gap is that the team did not build the function, and explaining to them does not solve a missing function.
- C. A mandatory regulation does not lapse because management approves. Going live in a noncompliant state only leaves the violation risk and the penalty consequences with the organization.
- D. There is no basis for applying to company legal for an exception permit: mandatory regulations usually have no exceptions that company legal can approve, and legal has no authority to approve a release that violates a regulation.
Key takeaway A mandatory compliance requirement not implemented: do the missing work first, then verify. Do not release it through approval or waiver.
Variation If what was missing were an internal policy requirement and not a regulation, you would still do the missing work first. Only if an exception is truly needed would you apply through the organization's prescribed channel, and the owner of the policy decides.
- Question 84
A software development project is in the Executing focus area. The team hits a technical bottleneck, and morale and performance drop. Drawing on his own professional skills, the project manager works through the problem with the members and together they find a solution. Which type of power did the project manager use?
Show answer and explanation
Correct answer: D
The project is in the Executing focus area. The team hits a technical bottleneck, and the project manager uses his own professional skills to lead the members to a solution. You need to identify the type of power he used.
By common exam practice, a project manager's power can be positional, expert, referent, reward, coercive and so on. Positional power comes from the formal role and organizational authority; reward and coercive power depend on the specific authority the organization grants; expert power and referent power come from the project manager as a person. In the question the project manager works with members to solve a technical problem “drawing on his own professional skills”. Catch that key phrase: it is expert power. The answer is D.
Why the other options are wrong
- A. Positional power comes from the position and formal authority granted by the organization. The question stresses the project manager's personal professional skills, not his position.
- B. Referent power comes from personal charm, character and personality, so that others identify with and follow someone willingly. The question says nothing like that.
- C. Reward power influences others through rewards (such as bonuses, promotion or recognition). The project manager in the question uses no reward.
Key takeaway Solving a problem with your own professional skills is expert power, which comes from the project manager as a person (common exam practice).
Variation If members follow the project manager willingly because they admire him as a person, that is referent power. If the project manager assigns tasks to members by virtue of his position, that is positional power. If he motivates members with a bonus, that is reward power.
- Question 85
A logistics company is installing a batch of shelving in a new warehouse. The drawings, quantities and acceptance criteria are all settled, market prices are stable, the schedule is short and the risk is low. Which contract should the project manager choose?
Show answer and explanation
Correct answer: C
The project is developing its procurement strategy. The scope of work is clear and the risk is low, and the question asks which contract type fits best.
The signals: the drawings, quantities and acceptance criteria are settled, market prices are stable, the schedule is short and the risk is low. All three conditions say the scope is clear and few changes are expected, so the buyer can agree a fixed price in advance and have budget certainty, while the seller builds to the drawings and earns more if it controls cost well. The answer is C.
Why the other options are wrong
- A. A time-and-materials contract suits small projects where an accurate SOW cannot be written, or topping up with experts. It settles on actual hours and materials, so the total price is not usually fixed in advance and may rise with actual input (a cap can be agreed separately). Using it on work with clear scope gives up the price certainty a fixed-price contract provides.
- B. A cost plus fixed fee contract is cost-reimbursable, so the buyer bears actual cost and it suits work whose scope is unclear. Here the scope is clear, and there is no need to make the buyer carry the risk of cost overruns.
- D. A cost plus award fee contract also leaves cost with the buyer, and the award rests on the buyer’s subjective evaluation. It suits work with unclear scope where performance needs incentives, which does not fit a low-risk, clear-scope scenario.
Key takeaway Clear scope, few changes and low risk point to a fixed-price contract.
Variation If the condition were changed to “performance measures cannot yet be stated and will be settled as the work proceeds”, choose a cost-reimbursable contract; if it were changed to “just hire an outside expert for a few weeks of consulting paid by the person-day”, choose time and materials.
- Question 86
At PMLyceum, a data-center expansion project is behind because rack installation was delayed, and many later activities are affected. The equipment delivery manager tells the project manager that there is not enough specialized lifting equipment, and there are not enough tools, for rack installation, so capacity cannot keep up. What should the project manager have done to avoid this situation?
Show answer and explanation
Correct answer: C
A data-center expansion project is behind because rack installation was delayed, and many later activities are affected. The equipment delivery manager says there is not enough specialized lifting equipment, and there are not enough tools, for installation, so capacity cannot keep up. The question asks what the project manager “should have done”, that is, the routine practice that would have prevented this.
Monitor and Control Resourcing deals with physical resources such as equipment, materials and facilities. Throughout the life cycle it keeps comparing planned with actual use of resources, to ensure they are available at the right time and place, and takes corrective action when a gap appears. Regularly reviewing the availability and capacity of installation equipment and tools with the delivery manager would have exposed the gap before it hit the schedule, which is exactly what PMBOK 8 means by identifying and dealing with resource shortages in a timely manner. The answer is C.
Why the other options are wrong
- A. The stem does not say the capacity problem came from not following the resource management plan. Requiring people to “follow the plan” would neither find the capacity gap nor prevent the next one.
- B. Meeting regularly with crews to check activity conflicts has some value, but conflicts are not the root of the shortage of equipment and tools. Finding out whether resources are available and sufficient is more direct than checking schedules.
- D. The scope statement describes scope; it is not the document that sets out skill requirements. Even if it did, it would not detect changes in actual resource availability.
Key takeaway Monitor and Control Resourcing is continuous: regularly review resource availability and capacity so gaps are found before delays occur.
Variation If the stem were changed to “a capacity gap has already appeared; what should you do?”, you would first run a performance review and trend analysis, assess the impact, then negotiate or raise a change request.
- Question 87
A project manager temporarily takes over a project that is already under way. A key stakeholder warns that the SMS gateway provider the project now depends on has a poor reputation. The project manager assigns a team member to watch the provider's service quality full time, but even so this cannot guarantee that the service will not have problems. How should the project manager handle the risk that remains?
Show answer and explanation
Correct answer: C
A project manager temporarily takes over a project under way. A key stakeholder warns that the SMS gateway provider the project depends on has a poor reputation. The project manager assigns a member to watch the provider's service quality full time, but this still cannot guarantee that the service will not have problems. You must decide how to handle the risk that remains.
First characterize the “remaining risk.” (“Residual risk” and “secondary risk” are common exam terms.) Residual risk is the risk that remains after the planned response has been implemented. Assigning someone to monitor does not eliminate the risk: the possibility of service problems is still there; it is the part of the original risk that was not fully eliminated, so it is a residual risk and should be recorded in the risk register, with a contingency reserve set aside for it if needed. A secondary risk is a new risk created by the response itself, and no new risk appears here. The answer is C.
Why the other options are wrong
- A. A secondary risk is a new risk brought about by a response. Here the original provider risk has not been fully eliminated and no new risk has appeared, so it is not a secondary risk.
- B. The issue log records problems that have already happened. The service has not failed yet, so this is still an uncertain event that has not occurred and belongs in the risk register, not the issue log as a potential issue.
- D. Setting aside a contingency reserve for a residual risk is fine, but calling the reserve a workaround is wrong. A workaround (a common exam term) is improvised after a threat occurs when no applicable response was planned; here the risk has not occurred and a response arrangement already exists.
Key takeaway A residual risk is what is left of the original risk after the response; a secondary risk is a new risk the response creates. Record both.
Variation If assigning someone to watch the service quality had left the team short of people and created a new staffing risk, that new risk would be a secondary risk.
- Question 88
A traditional manufacturer is in a period of organizational change. Management expects projects to move toward agile, but most front-line staff have done only projects that proceed according to plan and are unfamiliar with agile. This project has both stable work that proceeds on an established plan and parts whose requirements are still uncertain and need iterative exploration. Management asks you to weigh everything and decide: given the current situation, which life cycle should the project use?
Show answer and explanation
Correct answer: A
A traditional manufacturer is in a period of change; management expects projects to move toward agile, but front-line staff have done only plan-driven projects and are unfamiliar with agile, and the project has both stable work and parts that need iterative exploration. You must decide which life cycle the current project should use.
Many teams cannot switch entirely to agile overnight, especially people who have already succeeded in a predictive environment, so the transition needs to be gradual. A hybrid approach keeps the planning and control the team is familiar with while adding agile practices such as iterations and increments step by step, which responds to management’s expectation without exceeding the team’s ability to adapt. The deciding signal is the project itself: it has both stable work that proceeds on an established plan and parts whose requirements are still uncertain and need iterative exploration, and only a hybrid approach covers both kinds of work. The team not being ready and management expecting a transition are supporting factors only: PMBOK 8 selects the approach by project factors; organizational change and team familiarity are only considerations and cannot alone decide the life cycle. The answer is A.
Why the other options are wrong
- B. The project still has stable work proceeding on an established plan. A purely adaptive approach can handle stable work, but it gives up the advantages of using that part’s high certainty for up-front planning and baseline control. Because this project contains work suited to both predictive and adaptive treatment, hybrid is the better fit. The staff’s lack of readiness also increases the risk of an immediate full switch.
- C. A purely predictive approach has no way to handle the parts whose requirements are still uncertain and need iterative exploration, so it cannot cover all of the project’s work.
- D. “Incremental delivery within a predictive life cycle” describes delivery in batches, but it still manages the work predictively and does not provide iterative discovery and adaptation for the uncertain requirements; therefore it does not cover both kinds of work in the stem.
Key takeaway When a project has both stable work and parts that need iterative exploration and the team cannot switch fully to agile at once, use a hybrid approach.
Variation If the team already had mature agile experience and the project’s requirements were highly uncertain, choose adaptive directly. If the whole project were stable work, a purely predictive approach could be reasonable.
- Question 89
An agricultural machinery company plans to develop an intelligent irrigation control system, and the project manager decides to outsource the development to a more experienced supplier. After the bid documents are issued, several bids come in. The project manager analyzed them on technical merit and quality and still cannot decide who should win the contract. What document should the project manager have prepared in advance to avoid this?
Show answer and explanation
Correct answer: D
The decision to outsource has been made and the bid documents issued, and several bids have come in, but no winner can be selected. The question asks what document should have been prepared in advance.
The signal: several bids received, technical and quality aspects analyzed, and still no winner. What is missing is a common basis for judgment, not information. Source selection criteria are part of a weighting system, are set before the bid documents are issued, and are used to score and rank all proposals and to establish the negotiating sequence; they can cover technical, quality, cost, financial stability and more. Preparing them in advance gives the evaluation a framework. The answer is D.
Why the other options are wrong
- A. The statement of work describes the products, services or results to be procured so that sellers know what is being bought. It does not provide criteria for scoring sellers.
- B. The procurement management plan guides how procurement is carried out. It does not contain the specific criteria for scoring sellers item by item.
- C. A list of pre-qualified sellers narrows who is invited. The sellers on the list still have to be compared using criteria.
Key takeaway If you cannot select a seller, the usual cause is that source selection criteria were not set in advance.
Variation If the stem said the sponsor asked midway through evaluation to add a low-price supplier, the answer would be to call a meeting and evaluate the supplier against the published selection criteria and procurement governance with the sponsor; if it said only one supplier holds the patent, that points to the single source method.
- Question 90
The members of a project team come from several countries, and cooperation has never gone smoothly. The project manager has accompanied the team through the Storming stage of the Tuckman ladder for some time, but the team still has not moved into the Norming stage, and the schedule has started to slip. What should the project manager do to move the team into the Norming stage?
Show answer and explanation
Correct answer: A
A multinational team has not cooperated smoothly. The project manager has been with the team through Storming for some time, but it has not entered Norming and the schedule is slipping. The question asks how to get the team into the Norming stage.
The crux of Storming is that members disagree about ways of working, views and roles, and their relationships are not yet solid. To enter Norming, members need stronger interpersonal relationships and goals they all accept. Social activities build understanding, and jointly setting team goals gives everyone one direction. Used together, they address this crux directly. The answer is A.
Why the other options are wrong
- B. Leading the team out of Storming is the project manager’s responsibility. Asking the sponsor to replace people at the first conflict is evasion and does not explain how cooperation would improve.
- C. Finding the instigator and applying step-by-step discipline deals only with an individual’s behavior, while poor cooperation is already a team-level problem, and punishment makes the atmosphere tenser.
- D. The stem does not say the delay is directly caused by communication problems. Pressuring the team with data and demanding that people “set differences aside” does not change relationships among members.
Key takeaway When stuck in Storming, use team building to strengthen relationships and set shared goals together.
Variation Once the team has entered Norming, shift to a participative style. Once it is in Performing and running smoothly, shift to a delegating style and intervene less.
- Question 91
On a community e-commerce platform project, the project manager compares the performance measurement baseline with actual completion as of the current status date and finds that several work packages planned to be complete by now are not. What should the project manager do?
Show answer and explanation
Correct answer: A
The project manager compares the performance measurement baseline with actual completion as of the status date and finds that several work packages planned to be done are not.
This is a performance variance between actual completion and the baseline. Analyze why work is behind (checking the schedule baseline as well); if the delivered content deviates from the scope baseline, deal with it through Monitor and Control Scope and change control. The purpose of variance analysis is to establish the cause and degree of the variance and, on that basis, decide on corrective or preventive action. So analyze the cause first, then take targeted corrective action. A variance analysis often needs to be paired with root cause analysis: whether estimates were optimistic, resources did not arrive or scope itself grew determines what corrective action will fit. The answer is A.
Why the other options are wrong
- B. Recording the variance in the status report is only reporting. The variance is not dealt with, and monitoring performance requires acting on variances.
- C. Shrinking later scope on one's own damages the baseline and does not look for the cause of the variance. The variance will not “disappear automatically.”
- D. A baseline update must go through change control; the baseline cannot be changed just to make the plan match actual progress.
Key takeaway For a performance variance, analyze the cause first, then take corrective action; the baseline is not bent to fit actuals.
Variation If trend analysis also shows that the next several weeks will still run behind, take preventive action early. If the variance stems from changed requirements, go through a change request.
- Question 92
A company's new project uses an agile approach. The appointed project manager has no prior agile experience and worries that team collaboration will get out of hand, so asks the PMO about team communication. What advice will the PMO MOST likely give?
Show answer and explanation
Correct answer: A
A new project uses agile, the project manager has no agile experience and worries that collaboration will get out of hand, and asks the PMO about team communication. The question asks what advice the PMO most likely gives.
The principle says: the most efficient and effective method of conveying information to and within a development team is face-to-face conversation. So the PMO will most likely advise putting the team in one office and encouraging face-to-face conversation: problems can be discussed and settled on the spot, information is less likely to be distorted, and it helps build cohesion. The other options rely on hierarchical reporting, isolation or written templates, all contrary to agile communication principles. The answer is A.
Why the other options are wrong
- B. Central decisions by management with reporting up through levels is command-and-control management, the opposite of a self-organizing team, and information flows slowly.
- C. Separate offices reduce interaction. Agile treats frequent face-to-face communication as the basis of collaboration, not as “disturbance”.
- D. Agile values individuals and interactions over processes and tools. Recording communication on standard templates in place of conversation slows communication down and makes it formal.
Key takeaway The most effective communication for an agile team is face to face, and co-location is the most direct way to ensure it.
Variation If the team is spread across cities, use video conferencing, which comes closest to face to face, and set shared working hours.
Reference The Agile Manifesto · Lesson 3: The Twelve Principles (Part 2): Teams, Communication, Sustainable Pace and Simplicity
- Question 93
The agile team of a large platform software project is spread across several time zones, and communication among team members is especially important. As an agile coach, how should you help the team communicate successfully?
Show answer and explanation
Correct answer: C
The agile team of a large platform software project is spread across several time zones, and communication among members is particularly important. The question asks how the agile coach should help the team communicate successfully.
An agile team in different time zones should use online collaboration tools to promote transparent, thorough communication. An online board lets all members see the progress of feature development at any time, regardless of time zone and without relying on live meetings, which is typical remote collaboration practice. Agile values transparency, and putting progress where everyone can see it reduces misunderstanding better than daily emails. The answer is C.
Why the other options are wrong
- A. Daily emailed reports are not absolutely unusable, but the information is scattered and one-way, with less transparency and collaboration than a shared online board.
- B. Splitting deliverables by time zone guarantees communication only within each region. The communication problem for the whole team remains.
- D. Building in some overlapping working hours can support synchronous communication, but asking each member to shift their own hours puts the burden on individuals and gives the team no shared view of progress. An online board gives all members continuous access to the same progress information across time zones, so C fits better.
Key takeaway For an agile team across time zones, use collaboration tools such as an online board for transparent communication.
Variation If the question is how to schedule synchronous meetings, choose the core overlap hours when everyone is working and rotate the inconvenience among time zones. If the question is how new members keep up, rely on the board, minutes and asynchronous communication.
- Question 94
The project management office (PMO) plans to use an AI tool to help identify risks on new projects. Compared with purely manual identification, what is the main advantage of AI?
Show answer and explanation
Correct answer: A
The PMO plans to use an AI tool to help identify risks on new projects. Compared with purely manual identification, what is AI's main advantage?
The use case table in PMBOK 8 states that AI algorithms can analyze historical project data and industry benchmarks to identify potential risks in new projects, and that by using predictive analytics AI can assess the likelihood and impact of these risks, enabling project managers to develop comprehensive risk management plans early in the planning phase. That is, AI's advantage is quickly finding patterns in large amounts of historical data, which is hard to do manually. The answer is A.
Why the other options are wrong
- B. AI cannot guarantee that all risks are covered, and its output still needs human review and validation. The standard states clearly that information from AI may be biased, incorrect, or irrelevant.
- C. A human must ultimately be accountable for each decision. AI can only offer suggestions and cannot replace the risk owner in making the final judgment.
- D. AI can use broader training data to suggest new risks, but it cannot guarantee accurate discovery of entirely new risks without relevant historical data or expert judgment. The word “accurately” makes D too absolute.
Key takeaway AI's advantage is finding patterns quickly in large amounts of historical data. Review, judgment and accountability remain with people.
Variation If asked “which adoption strategy does AI in risk management belong to?”, risk identification and assessment is augmentation, and automated risk mitigation actions is automation.
Reference Artificial Intelligence in Project Management · Lesson 2: Typical AI Use Cases in Project Management
- Question 95
In an internal training session, project management team members discuss which competencies it takes to be a good project manager, and the instructor introduces the current PMI Talent Triangle. Which of the following correctly describes its three skill types?
Show answer and explanation
Correct answer: A
You need to decide which three skill types make up the current PMI Talent Triangle. No specific project scenario is involved.
The current PMI Talent Triangle consists of three skill types: ways of working, power skills and business acumen. These three also appear among the project management team competencies in the standard (section 2.5.1), which add social responsibilities and results. B is the combination PMI used earlier, and C and D are not part of the Talent Triangle. The answer is A.
Why the other options are wrong
- B. This is the combination PMI used earlier (technical project management, leadership, strategic and business management). The current Talent Triangle is ways of working, power skills, business acumen.
- C. Business administration, technical expertise and strategic management are not any of the Talent Triangle's skills.
- D. Project management, technical expertise and business marketing are likewise not the Talent Triangle's three skill types, and business marketing is not a named competency in this framework.
Key takeaway The current PMI Talent Triangle is ways of working, power skills and business acumen. Technical project management, leadership, and strategic and business management is the combination PMI used earlier.
Variation If asked how many competencies are in the PMBOK 8 project management team competency framework, the answer is five: social responsibilities, power skills, business acumen, ways of working and results. If asked which one covers negotiation and conflict resolution, the answer is power skills.
- Question 96
A newly founded coffee shop chain has an owner with no project management experience, who plans to carry out several change projects using the company’s own resources and has assigned a project manager. What should the project manager advise the owner to do FIRST?
Show answer and explanation
Correct answer: A
A newly founded coffee chain has an owner with no project management experience who plans to run several change projects with its own resources and has assigned a project manager. You must decide what the project manager should advise first. The core concepts are governance and tailoring.
Project governance provides structure, systems and processes, roles and responsibilities, and decision-making models. It is the framework that guides project management activities and keeps projects aligned with organizational strategy. Because the owner has no experience, the first step at the organizational level is to put in place a governance framework that supports project success, making clear who approves, who decides and how reporting works. On that foundation, specific approaches are tailored to the context of each project. Governance provides the decision, oversight and accountability arrangements. Each project then tailors its governance, approach and processes to its own context, choosing a suitable predictive, adaptive or hybrid approach. The answer is A.
Why the other options are wrong
- B. The approach should be chosen according to the characteristics and needs of each project. Prescribing agile for every project in advance is a one-size-fits-all rule that skips tailoring.
- C. Developing a work breakdown structure is planning work inside a single project. Before the organization has made clear who approves and who decides, it is not the first thing the owner needs to do. At the organizational level, the first thing to build is the governance framework.
- D. Prescribing predictive for every project is also one-size-fits-all. Each project’s context is unique and needs tailoring, so one approach cannot be applied to all projects.
Key takeaway Governance sets the boundaries and decision-making approach for projects. Projects are unique and so must be tailored; the approach cannot be one-size-fits-all.
Variation If the organization already has a governance framework and the project manager must choose an approach for a new project with unclear requirements, the answer would be to tailor to the project’s characteristics, leaning toward an adaptive or hybrid approach.
- Question 97
While the project is under way, the client reorganizes, and a newly appointed operations director holds final decision authority over the project budget and acceptance. After analyzing the director with the team, the project manager records him in the stakeholder register and assesses his current engagement level as “Unaware” and his desired level as “Supportive.” What should the project manager do next?
Show answer and explanation
Correct answer: A
A newly appointed client operations director has final authority over the budget and acceptance. The team has assessed his current engagement level as “Unaware” and his desired level as “Supportive,” and you must decide the right next step.
Identifying, assessing, planning and executing come in order. The team has already identified and assessed him: current level Unaware, desired level Supportive, so the gap is clear. The next step is to bring him into the stakeholder engagement plan and set engagement strategies and actions for closing that gap, for example, first help him understand the project and its potential impacts, then win his support. Updating the engagement plan and developing a targeted strategy is the work of Plan Stakeholder Engagement. The answer is A.
Why the other options are wrong
- B. Showing credentials is an attempt to please him. It develops no strategy around his needs and expectations and does nothing of substance to win his support.
- C. Putting all the effort into one director neglects other stakeholders. Engagement has to cover every important stakeholder, with effort allocated by priority.
- D. Giving in to every request leads to scope creep. It is not an engagement strategy and does not manage his expectations.
Key takeaway For a new key stakeholder, once the desired level is assessed, update the engagement plan and develop a targeted strategy.
Variation If the team had not yet assessed his current level, they would first assess it through conversations and observation, then compare the gap, and only then develop a strategy.
- Question 98
A project manager is responsible for several very large software modules that must be completed by a few senior engineers over the next few weeks. The modules are large and complex, and no single engineer can take on one of them alone. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
Several software modules are large and complex, and no single engineer can take on one alone. The question asks what the project manager should do first.
The root of the problem is that the modules are too big to assign to individuals, not that there are too few people or that an uncertain event has appeared. The Develop Scope Structure process uses decomposition to break large deliverables, level by level, into smaller, more manageable work packages. Work packages with clear boundaries that can be estimated can be assigned to specific engineers, and later estimating and tracking then have something to work on. So the first step is to break the modules down using Develop Scope Structure. The answer is D.
Why the other options are wrong
- A. The stem does not say people are short; the difficulty is that the modules are too big. Even with more people, the large modules still cannot be split among them, and there is no reason to go to change first.
- B. Handing the whole set of modules to whoever frees up first and letting him divide them leaves the scope division and responsibility unclarified, and pushes the decomposition onto an individual.
- C. The modules being too big is an existing fact, not an uncertain event that may or may not occur, so it should not be registered as a risk.
Key takeaway When a deliverable is too large to assign, decompose it into work packages first, then assign it.
Variation If the work packages are already defined but nobody knows the acceptance criteria of each, what must be added is the WBS dictionary; if the number of available engineers is insufficient, then it becomes a question of resources and schedule.
- Question 99
You take over a smart-home device development project that has been running for about six months under a predictive approach. The team is discussing the previously approved scope: even though the change control procedure is strict, requirements keep changing. What should you do?
Show answer and explanation
Correct answer: A
You take over a development project that has run for half a year. The change control procedure is strict, yet requirements still change continuously. What should you do?
Strict change control is a means of dealing with change. If it is already strict and requirements still keep changing, tightening the process alone will not solve the problem, and the current predictive approach may not match the project’s uncertainty: when a project with highly uncertain requirements uses an approach that depends on stable requirements up front, a large volume of change will usually result. You should consider adjusting the development approach, for example moving to an adaptive or hybrid approach, so the project can adapt to continuously changing requirements. The answer is A.
Why the other options are wrong
- B. Change requests must still be evaluated through the Assess and Implement Changes process. Rejecting all of them is neither reasonable nor able to meet the reality of continuously changing requirements.
- C. The stem already says change control is strict. Tightening it further only makes it harder for real requirements to get in and does not solve the fundamental mismatch between the approach and the requirements.
- D. Accepting every change unconditionally would hit scope, cost, and schedule, and it does not conform to proper change management either.
Key takeaway However strict change control is, it cannot stop requirements from changing; what needs adjusting is the development approach, not blocking the changes.
Variation If the requirements were actually stable and only certain stakeholders kept asking for additions, the problem would be stakeholder management and you should hold to change control. Whether to adjust the approach depends on whether requirement change is the norm for the project.
- Question 100
At the kickoff meeting of a project at a design firm, the project manager invites members to set the phase goals together and puts no strict monitoring system such as clock-in or item-by-item reporting in place. She believes members are willing to take responsibility on their own and are capable of solving the problems the team meets. Which theory is her management philosophy consistent with?
Show answer and explanation
Correct answer: D
At a design firm’s project kickoff, the project manager invites members to set phase goals together and has no strict monitoring such as clock-in or item-by-item reporting, because she believes members are willing to take responsibility and can solve problems. The question asks which theory her management philosophy fits.
The question works backward from management practices to the manager’s assumptions about people. Having members take part in setting goals and dropping strict monitoring reflect a belief that people are intrinsically motivated to do good work, willing to take responsibility and ready to discuss and be creative. PMBOK 8 places this assumption under McGregor’s Theory Y, whose corresponding management style has a more personal, coaching feel, encourages creativity and discussion, and is often seen in creative and knowledge worker environments; a design firm is exactly that kind of setting. The answer is D.
Why the other options are wrong
- A. Theory X assumes people work only for income and are not ambitious, and it calls for a hands-on, top-down style. This is the opposite of removing monitoring.
- B. Two-factor theory distinguishes hygiene factors from motivational factors. The style of supervision might count as a hygiene factor, but the theory does not describe a manager’s basic assumption about whether people take responsibility on their own, so it does not fit.
- C. The hierarchy of needs describes the order of five levels of needs and says nothing about a manager’s basic view of employees.
Key takeaway Believing employees take responsibility on their own and delegating freely is Theory Y; assuming employees slack off and need strict oversight is Theory X.
Variation If the stem said the project manager requires a daily report and docks points for lateness because she thinks members will not work unless watched, it would be Theory X. If it stressed jobs for life and concern for employees and their families, it would correspond to Ouchi’s Theory Z.
- Question 101
PMLyceum is setting sustainability goals for a business park renovation project. The sponsor believes: “Sustainability just means protecting the environment, and cutting emissions is enough.” How should the project manager explain the meaning of this principle to the sponsor?
Show answer and explanation
Correct answer: B
A business park renovation project is setting sustainability goals. The sponsor thinks sustainability just means protecting the environment and cutting emissions, and the question asks how the project manager should explain the meaning of the principle.
The sponsor’s view covers only one aspect, the environment, and that is the point the question wants corrected. The Eighth Edition explains that this principle involves meeting present needs without compromising the ability of future generations to meet their own needs. In performing project activities, it means considering people, the planet, society and value, addressing environmental, social and economic impacts, and following the triple bottom line of social equity, environmental stewardship and economic prosperity. So the answer should reflect “present and future generations” and “several aspects balanced”. The answer is B.
Why the other options are wrong
- A. This limits sustainability to environmental protection and says the project “need not consider” society and the economy. It repeats the sponsor’s one-sided view and leaves out the social and economic impacts.
- C. Talking only about long-term operation and profit treats the economic aspect as the whole. It has neither the environment nor society, and it lacks the requirement not to compromise future generations.
- D. Team stability and less rework and delay are management goals for resources, quality and schedule. They are not what the sustainability principle means.
Key takeaway Sustainability means meeting present needs without compromising future generations, balancing people, the planet, society and value. It is not only environmental protection.
Variation If asked “what is the triple bottom line”, the answer is social equity, environmental stewardship and economic prosperity. If an option offers “scope, schedule and cost”, that is the project’s triple constraint, not the triple bottom line.
- Question 102
The agile team of a map app raises a question about a requirement during an iteration: the team left out the new technology needed to implement the requirement when it estimated, and this new challenge could take quite a lot of extra time. The requirement is very important. To keep the work moving smoothly, what should the product owner do?
Show answer and explanation
Correct answer: B
During an iteration, the map app team finds that its estimate left out the new technology needed to implement an important requirement, and this challenge could take considerable extra time. The question asks what the product owner should do.
The new technology was not estimated and may delay progress, which brings uncertainty. A technical exploration or validation item can be created for the challenge and put into the product backlog, where the product owner orders it by value and risk together with the other items, and the Developers adjust the implementation plan accordingly; if the work affects the current iteration goal, both sides should negotiate the scope of the current iteration. The uncertainty is then visible and ordered, and the iteration timebox is not broken. The answer is B.
Why the other options are wrong
- A. Agile does not make overtime a first choice, and it is not sustainable. Extra work should be handled through ordering and planning.
- C. The way to implement something is decided jointly by the self-organizing team. The stem says the requirement needs the new technology, so it cannot arbitrarily fall back on the old one.
- D. Once an iteration has started its timebox stays fixed and is not extended to finish one requirement. Handle it by negotiating scope and reordering; extending the timebox is not how a new risk is dealt with.
Key takeaway For uncertainty caused by new technology, create a technical exploration or validation item in the backlog and order it together with the features.
Variation If it were an impediment that has already occurred in the iteration rather than a potential risk, it would be raised at the daily coordination meeting and the Scrum Master would help remove it; if the uncertainty is high and the value is high, put the item near the top of the backlog.
- Question 103
A company lists several pieces of work: (1) introduce a new ticketing system for the customer service center; (2) keep the customer service hotline running on the existing shift schedule; (3) add a one-click renewal feature to the existing app; (4) carry out a one-time lean improvement of the warehouse process. Which option lists only work that is suitable to run as projects?
Show answer and explanation
Correct answer: D
The company lists four pieces of work: introducing a new ticketing system, running the hotline on the existing shift schedule, adding a one-click renewal feature to the existing app, and carrying out a one-time lean improvement of the warehouse process. You must pick the option in which every item is suitable as a project.
A project is a temporary initiative in a unique context, while operations is ongoing, repetitive day-to-day work. Item 1 (introducing a new system), item 3 (adding a feature) and item 4 (a one-time process improvement) each have a defined start and end and a unique output, so they are projects. Item 2, running the hotline on the existing schedule, is ongoing, repetitive operations and not a project. A quick method for this kind of question: label each item “ongoing” or “has an end point”. Only item 2 is ongoing, so eliminate every option that contains item 2, and only one answer remains. That is the option without item 2. The answer is D.
Why the other options are wrong
- A. This treats item 2 as a project and also leaves out item 3. Adding a feature is an upgrade to an existing product and is also unique and temporary.
- B. This also treats item 2 as a project. Running the hotline continuously is operations and has no end point.
- C. This also treats item 2 as a project, and it leaves out item 1. Introducing a new system is clearly a project.
Key takeaway “Introduce, add, improve” usually signals a project. “Keep running on the existing schedule” signals operations.
Variation If item 2 were changed to “add intelligent call routing to the hotline and launch it within three months”, it would become a project, and the answer would change accordingly.
- Question 104
At the weekly meeting of PMLyceum’s logistics route optimization project, nearly every team reports that “everything is fine”. In follow-up conversations after the meeting, the project manager learns that two tasks are clearly behind schedule, and that members did not want to say so in the meeting because they feared being singled out and criticized. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
At the weekly meeting every team says “everything is fine”, yet after the meeting two tasks turn out to be late, and members feared being singled out. The question asks what the project manager should do first, and it turns on the accountable leader creating a psychologically safe environment.
The signal is “did not want to say so in the meeting, feared being singled out and criticized”: the root of the concealment is a lack of psychological safety, not a lack of checking. An accountable leader leads by example and fosters an environment where people can speak freely and report problems frankly without fear of retaliation, so that problems surface early and are solved together. Change the environment first, and only then will the information be true. The answer is A.
Why the other options are wrong
- B. Daily written statuses with item-by-item checking only add monitoring burden. Members can still polish their reports, and the root problem, that people are afraid to speak, is untouched.
- C. Having the owners fix things privately leaves the team’s habit of reporting only good news unchanged, and the problem is still not seen and solved by the team together.
- D. Naming people and threatening their reviews makes members more afraid of exposing problems and strengthens the motive to conceal. It is the opposite of psychological safety.
Key takeaway The earlier a problem surfaces the better. First make it safe for members to tell the truth, and only then talk about checking and performance reviews.
Variation If the same scenario were changed to “every score in the risk register is low”, the answer is still to build a culture of candid risk reporting. If asked about the purpose of creating psychological safety, the answer is to let members speak and report problems frankly without fear of retaliation.
- Question 105
A test engineer has just joined a logistics software company and finds that company policy requires all requirements to be collected and the system design reviewed before any code work starts. Which kind of delivery approach is this?
Show answer and explanation
Correct answer: D
Company policy requires all requirements to be collected and the system design reviewed before work starts. You must decide which development approach this delivery method belongs to.
A predictive approach may also be referred to as a waterfall, plan-driven, or traditional approach. Scope, schedule, cost, resource needs, quality requirements, and risks are well defined in the early phases of the life cycle and are expected to remain relatively stable, with much of the planning done up front. “All requirements and the design review must be finished before any code starts” is exactly requirements up front and plan-driven. The answer is D.
Why the other options are wrong
- A. An adaptive approach establishes a vision first, and the initial known requirements are elaborated progressively through the backlog and feedback. It would not fix all requirements and design before any code is written.
- B. In this kind of hybrid pattern the early part is adaptive exploration with fast trial and error. The stem describes an early part that needs complete, settled requirements and design.
- C. Incremental delivery within a predictive approach also plans up front, but its hallmark is delivery in batches. The stem says nothing about batch delivery, so there is nothing to base that judgment on.
Key takeaway Completing all requirements and design before work starts is the hallmark of a predictive approach: plan-driven, requirements up front.
Variation If the stem added “the overall scope is clear, but delivery is in three batches,” the answer would become incremental delivery within a predictive approach. If it said instead “only a vision exists and requirements are elaborated round by round,” the answer would be adaptive.
- Question 106
A cross-border e-commerce warehousing project needs approval from a local regulator. The agency is drafting a new regulation that will change the approval process, but it is unclear when it will take effect. The project manager is concerned that it may delay a key milestone or restrict the construction approach. What should the project manager do?
Show answer and explanation
Correct answer: B
The warehousing project needs regulator approval. The agency is drafting a new regulation that will change the approval process, with an unclear effective date, and the project manager worries about the milestone. What should the project manager do?
The key is “being drafted, effective date unclear”: this is an external uncertainty that has not been settled. It is neither an issue that has occurred nor a reason to change scope or spend money right now. The purpose of monitoring risks is to keep tracking and analyzing risks and to evaluate the effectiveness of responses. For a risk with an unclear impact, keep evaluating the risk exposure and adjust as new information arrives, so that the negative effects on the project are minimized. The answer is B.
Why the other options are wrong
- A. Excluding the related activities before the regulation is issued may leave the project unable to deliver the requirements, and it requires a change anyway. Cutting scope when the information is incomplete is premature.
- C. Requesting extra contingency funds before the impact is known could tie up cost unnecessarily. It is more reasonable to set reserves after the regulation becomes clear and the risk is quantified.
- D. Assuming it will pass smoothly is optimistic neglect of the uncertainty, with no monitoring and no prepared response. If the regulation turns out badly for the project, the team will be caught off guard.
Key takeaway When an external uncertainty is still unclear, keep monitoring and evaluating risk exposure; do not rush to change scope or assume the best.
Variation If the new regulation has been published and is certain to delay approvals, the risk becomes an issue: act on the responses and assess whether the schedule baseline needs a change.
Reference Monitor Risks · Lesson 2: Monitor Risks: Purpose, Inputs and Outputs
Practice test or full mock exam: what is the difference?
- Free practice tests: 8 tests, the first with 120 questions and the others about 107 each, drawn from the 1,000 free questions (you may have met some while practicing by chapter), no login. Good for a quick self-check and for finding your weak domain.
- Full mock exams: 180 questions each, separate from the practice bank (none of them appear there), timed in 3 sittings like the real exam. Use them to judge whether you are ready. See the full mock exams.
Free PMP practice test: common questions
Is this PMP practice test really free?
Yes. There is no account and no email wall. All 106 questions and the full explanation of every answer are free, and your progress is saved in your browser.
How were the 106 questions chosen?
They come from the 1,000 free questions: 27 People, 49 Process and 30 Business Environment questions, covering 24 of the 26 tasks of the Exam Content Outline, with single-answer and multiple-answer questions. There are 8 free tests and no question appears in more than one of them. Once a domain runs out of free questions a test is a little shorter, and the count shown is the real one.
How long does the test take?
Timed mode follows the real exam's pace of 80 seconds a question, so 106 questions get 141 minutes. You can also choose untimed practice and take as long as you like.
How are multiple-answer questions scored?
A multiple-answer question counts as correct only when you select every correct option and nothing else. There is no partial credit, and an unanswered question counts as wrong.
Are these real PMP exam questions?
No. PMI does not release exam questions. Every question here is original, written to the Exam Content Outline, to practice the question styles and the reasoning.
What should I do after the test?
Take another of the free tests, keep practicing by chapter in the 2,876-question bank, or take one of the 10 full mock exams of 180 questions. Your score here is a practice signal, not a prediction of the exam result.
To study first, read the study guide; for the whole bank, practice by chapter.