Free PMP Practice Test 8: 106 Questions with Explanations

106 PMP sample questions, test 8 of 8 with no question repeated from the other tests: 27 People, 49 Process and 30 Business Environment, covering 24 of the 26 tasks of the Exam Content Outline. Timed mode gives 80 seconds a question, 141 minutes in all; or practice untimed. Every question has a full explanation: why the answer is right and what is wrong with each other option. When you submit you get your total score, your accuracy in each of the three domains and a readiness check.

Updated 2026-11-22 · aligned to the current Exam Content Outline and PMBOK Guide 8th Edition

Start the test ↓

Ready to start?

Your answers are saved in this browser, so you can refresh or come back later. No account needed.

You can read every question below before you start; the answer options unlock when you press Start.

  1. Question 1

    A data-platform construction project is under way, and a senior data engineer who is critical to the project is moved by the company to another, higher-priority project. What should the project manager do FIRST?

    Show answer and explanation

    Correct answer: A

    A data-platform construction project is in execution, and a senior data engineer critical to the project is moved by the company to a higher-priority project. The question asks what the project manager should do “first”.

    At this point the project manager does not yet know how much the transfer will affect schedule, cost and scope, so the first step is to analyze the impact and then choose a response accordingly. This is “assess first, then act”. In the analysis, use the resource management plan and the responsibility assignment matrix to find the activities the engineer owns, then check whether the risk register already holds a response. The answer is A.

    Why the other options are wrong

    • B. The project management plan needs updating only after the impact is clear and a response has been chosen; updating before the impact is known has no basis.
    • C. The fact of the transfer can be shared in due course, but how big the impact is remains unclear, and communication is more targeted after you have analyzed the impact and set the direction of the response. It is not the first thing to do.
    • D. A change request is a possible measure after the impact analysis and is submitted only when the analysis shows a baseline or plan really must change. It is not the first step.

    Key takeaway When a resource is pulled away: analyze the impact on the project first, then decide whether to notify, change or update the plan.

    Variation If the stem asked for the step after the analysis, then depending on the size of the impact, choose among negotiating with the functional manager, adjusting the division of work, adding resources or raising a change request.

  2. Question 2

    A multinational group is reviewing its policies on project management approaches. Team members complain that every project they join has a different process, because predictive, adaptive, and hybrid approaches are all in use. A project manager who has just joined the working group is responsible for developing a unified standard for selecting the approach for new projects. What should he do?

    Show answer and explanation

    Correct answer: D

    A multinational group is reviewing its policy on project management approaches. Members complain that every project has a different process, since predictive, adaptive, and hybrid approaches are all in use. A project manager newly in the working group must develop a unified standard for selecting the approach. What should he do?

    To give different projects a consistent selection logic while keeping flexibility, first build the basis for classification: identify project types (size, complexity, and so on), constraints (time, budget, compliance, and so on), and available resources, and tailor the approach systematically on that basis; this is the starting point for standardized tailoring. PMBOK 8 also notes that organizations provide guides and standards for tailoring the organization’s standard processes, and projects then tailor further as needed. The answer is D.

    Why the other options are wrong

    • A. Using “most used” as the standard is one-size-fits-all and ignores differences in project type and constraints.
    • B. With no standard and each team customizing by preference, the current situation of varying processes, the source of the complaints, would simply continue.
    • C. Eliminating differences and keeping a single approach is also one-size-fits-all and would force unsuitable projects to use a mismatched approach.

    Key takeaway A unified standard is not a unified approach: build the starting point for tailoring from project types, constraints, and resources.

    Variation If asked who finally approves the tailoring scheme, it depends on organizational governance and the scope of impact: tailoring that affects only the internal team is usually approved by the project manager; tailoring that affects external groups may need approval by the PMO or another governance body.

    Reference Tailoring · Lesson 2: The Four Steps of Tailoring, Influencing Factors, Approval, and Diagnostics

  3. Question 3

    A membership-system rebuild at a retail chain involves several teams, and the organization's governance level recently decided to move from a predictive to an agile approach. Halfway through, a team member finds that the team lacks the technical capability to support the real-time inventory synchronization requirement, so the project needs rework and the situation must be explained to all stakeholders. To avoid this, what should the agile project leader have done?

    Show answer and explanation

    Correct answer: D

    A membership-system rebuild with several teams has just moved from predictive to agile. Halfway through, the team finds it lacks the technical capability for real-time inventory sync, rework is needed and all stakeholders must be told. The question asks what the agile project leader should have done beforehand.

    The rework traces back to inadequate technical and organizational readiness that surfaced only midway. Before work began, whether the team's technical capability was sufficient was uncertain, and that uncertainty is itself a risk; the earlier it is identified, the lower the cost of dealing with it. A gap that has been confirmed is an issue, and the future effects it may cause, such as rework and delay, are tracked as risks. So the leader should have assessed the team's technical and organizational readiness before the first iteration began, identified risks on that basis, and logged and kept tracking them, closing the gap before requirements were built. “Identify risks early and throughout” is PMBOK 8's thinking, while “assess technical and organizational readiness before the first iteration” is common exam practice. The answer is D.

    Why the other options are wrong

    • A. The rework came from inadequate technical capability, not unclear acceptance criteria. Hiring outside experts to define acceptance criteria misses the point and does not close the capability gap.
    • B. Defining acceptance criteria clearly at the start helps reduce disputes, and acceptance criteria also need timely clarification, but the root of the rework is the team's lack of technical capability; clarifying acceptance criteria alone cannot discover or close the capability gap, so it is not the best answer.
    • C. More communication has no specific identification action. The product owner mainly handles requirements and priorities and can do little to confirm the team's technical capability, so it does not ensure the capability gap is found.

    Key takeaway Whether capability is sufficient before work starts is uncertain, which makes it a risk; a confirmed gap is an issue. Assess technical and organizational readiness and identify risks before starting, instead of finding out halfway.

    Variation On an agile project, run risk identification again at the start of every iteration afterward, so that capability-gap risks surface as early as possible.

  4. Question 4

    At a risk analysis meeting, the sponsor asks three questions in a row: (1) which of several uncertain factors has the greatest effect on total cost; (2) how confident can we be of finishing the project within the current budget; (3) which of two alternatives has the higher expected monetary value. Which group of techniques should the project manager use to answer, in order?

    Show answer and explanation

    Correct answer: B

    At a risk analysis meeting, the sponsor asks three questions at once: which uncertain factor has the greatest effect on total cost, how confident we can be of finishing within the current budget, and which of two alternatives has the higher expected monetary value. You must match a suitable technique to each of the three questions in order.

    Look for the signal in each question. (1) “Greatest effect” compares the size of each factor's effect, so use sensitivity analysis. (2) “How confident we can be of finishing” asks for an overall probability, so use Monte Carlo analysis to obtain an S-curve. (3) “Expected monetary value” and “two alternatives” is a comparison of options, so use decision tree analysis. In order, that is sensitivity analysis, Monte Carlo analysis, decision tree analysis. The four options are only different orderings of these three techniques, and when all three questions are matched correctly the answer is unique. The answer is B.

    Why the other options are wrong

    • A. This swaps (1) and (2). Monte Carlo mainly gives the probability distribution of the overall result, and to compare the size of each factor's effect directly you should use sensitivity analysis (simulation results can also be used for sensitivity ranking after correlation analysis). Sensitivity analysis itself cannot give the confidence of finishing within budget.
    • C. This swaps (2) and (3). A decision tree compares the expected monetary value of options and cannot give the confidence of finishing. Monte Carlo can model outcome distributions for different decisions or courses of action, but the explicit request to compare expected monetary value calls for decision tree analysis. Both are mismatched.
    • D. Only (2) happens to be right. (1) is wrong: a decision tree compares options and cannot find the factor with the greatest effect. (3) is wrong: sensitivity analysis looks only at the size of a single factor's effect and cannot calculate the expected monetary value of alternatives.

    Key takeaway Choose the tool by the question: greatest effect means sensitivity analysis, confidence of finishing means Monte Carlo, and comparing options means a decision tree.

    Variation If the three questions are reworded as “the probability of finishing within budget”, “which option to choose” and “which factor has the greatest effect”, the matching does not change: Monte Carlo, decision tree, sensitivity analysis, matched correctly whatever the order.

  5. Question 5

    An agile team is building an appointment-booking app. Halfway through a Sprint, a core back-end developer must leave for a few weeks because a family member has suddenly fallen seriously ill. What should the project manager do about the work the developer was responsible for?

    Show answer and explanation

    Correct answer: D

    Halfway through a Sprint, a core back-end developer must leave for a few weeks because of a family member's sudden serious illness. The question asks how the project manager should handle the developer's work, and the key is how a self-organizing team handles a member's absence.

    When a member becomes unavailable, first assess with the team the impact on the Sprint Goal, capacity and plan. The team can then negotiate how to share the work, adapt the Sprint Backlog, or, when necessary, renegotiate scope with the Product Owner. The project manager facilitates this response while showing understanding and support for the member concerned. The answer is D.

    Why the other options are wrong

    • A. Going straight to procurement to hire externally is costly, a newcomer needs time to learn the project, and it skips the team's own negotiation.
    • B. Before the team assesses the impact and attempts to form a response, there is no basis for handing the work arrangement directly to senior management; escalation may follow if the assessment shows that the issue exceeds the team's authority or capacity.
    • C. Asking a member who is leaving because of a family member's serious illness to stay and finish shows no human care and is unrealistic.

    Key takeaway When a core member is absent for a while, first assess the impact with the team and then negotiate how to share or adapt the work. Consider escalation or additional staffing only if the team cannot absorb the impact or the response exceeds its authority, while caring for the member concerned.

    Variation If the absence were very long and the team could not absorb it, the Product Owner and the team would adjust the scope of this Sprint together, and adding people would be considered if necessary.

    Reference Scrum Roles · Lesson 4: Problem-Solving in an Agile Environment: Let the Team Try First

  6. Question 6

    Two team members argue about “who gets to use the only test device first.” Which type of source does this conflict mainly come from?

    Show answer and explanation

    Correct answer: D

    Two team members argue over who gets to use the one test device first. The question asks which type of source the conflict mainly comes from.

    PMBOK 8 says sources of conflict include scarce resources, scheduling priorities, and personal work styles. The argument centers on there being only one device, so the right to use it cannot be given to both people at once. At root, there are not enough resources: scarce resources. To identify a source, look at what the two sides are fighting over: a device is a resource, which task goes first is a priority, and how to do things is a work style. The answer is D.

    Why the other options are wrong

    • A. Conflict from scheduling priorities is about which task or goal should come first. The stem is about the right to use a device, not the order of tasks.
    • B. Conflict from differences in work style comes from different ways or paces of working. Nothing in the stem says the two differ in how they work; the device is simply not enough for both.
    • C. Personality differences would mean the two clash because they do not get along. Nothing in the stem indicates a personality clash; the dispute is over access to a scarce device.

    Key takeaway Common sources of conflict: scarce resources, scheduling priorities, personal work styles. Identify what is being fought over and you can classify it.

    Variation If the situation were “two people argue over whose task should be scheduled first so each can finish their own,” it would be scheduling priorities.

    Reference Conflict Management · Lesson 1: Conflict on Projects: Nature, Sources and Management Principles

  7. Question 7

    A project manager on an organizational change project is preparing an organizational change plan (a common exam term). What does this plan mainly contain?

    Show answer and explanation

    Correct answer: D

    What goes in the organizational change plan must be told apart from what goes in cost, procurement and resource management.

    The organizational change plan (a common exam term) is prepared so that an organizational change transitions smoothly. It mainly contains the change objectives, the affected stakeholders, and transition arrangements such as communication and training, and it can also state when, by whom and how the effect of the change will be measured. Of the four options, only D is about the change itself. In common exam practice, ask whether the option is about the “change transition”: objectives, the people affected, communication and training all concern how people come to accept the new state, while budgets, procurement and resource rosters are contents of plans in other knowledge areas. The answer is D.

    Why the other options are wrong

    • A. Budget details, disbursement milestones and payment arrangements belong to cost management.
    • B. The procurement list, the supplier roster and contract terms belong to procurement management.
    • C. The team list, role assignments and performance appraisal criteria belong to resource management.

    Key takeaway The organizational change plan states the change objectives, the affected people, and transition arrangements such as communication and training.

    Variation If an option mentions “the composition and authority of the change control board”, that describes the change management plan, not the organizational change plan; the two names differ by only a word.

  8. Question 8

    On a software outsourcing project, the customer's liaison has been replaced. The new liaison is an important stakeholder and is lukewarm about the project work, while the predecessor was very cooperative. Project manager Alex wants to win this person's understanding and support. To communicate better with the new liaison, what should Alex do first?

    Show answer and explanation

    Correct answer: D

    The customer has a new liaison who is lukewarm and is an important stakeholder. The question asks what Alex should do “first” to communicate better.

    The key word is “first.” The new liaison is lukewarm about the project, so engagement is low, and the person's preferred communication methods, formats and content are not yet known. Before acting, those preferences must be identified, which is exactly what a communication styles assessment does; it is often used with stakeholders who do not support the project and may follow a stakeholder engagement assessment. Here, the liaison's lukewarm attitude already shows the engagement gap; the missing information is the person's communication preferences. With the assessment results, the communications management plan and the stakeholder engagement plan can be revised, or a visit decided on. Any action without a needs-based foundation involves guesswork. The answer is D.

    Why the other options are wrong

    • A. A visit can build rapport, but Alex does not yet know what the liaison wants. Leading a team to visit without that knowledge may backfire. A visit comes after the analysis, not first.
    • B. The communications management plan should be revised from analysis results. Adding arrangements before knowing the person's needs gives content with no basis, and the revised plan may still not fit.
    • C. Revising the engagement plan before finding out what the liaison needs is acting on a guess, and “meeting the requests the liaison has made” also implies simply going along with them.

    Key takeaway For a lukewarm stakeholder who needs to be won over, first run a communication styles assessment to identify preferred methods, formats and content, then revise the communications management plan and engagement plan accordingly.

    Variation If the question stated that the liaison had already made specific reporting requirements, the project manager could revise the communications management plan directly on that basis.

    Reference Plan Communications Management · Lesson 2: Communication Requirements Analysis and the Number of Communication Channels

  9. Question 9

    One deliverable of a training project is a batch of translated and bound learning materials for participants every two weeks. The company's binding workshop is available, but because other projects are more profitable and have higher priority, the workshop cannot guarantee this project's schedule slot. What should the project manager do to mitigate the risk that the materials cannot be bound on time?

    Show answer and explanation

    Correct answer: A

    A training project must bind a batch of learning materials every two weeks. The company workshop is available, but because other projects have higher priority, its schedule is not guaranteed. The project manager wants to mitigate the risk that the materials cannot be bound on time.

    Mitigation works on the cause of the risk with measures that are reasonable in cost, to reduce probability or impact. The cause here is that the workshop schedule is not guaranteed, so the most direct and lowest-cost approach is to negotiate with the workshop manager and agree priority scheduling for this project. It acts directly on the cause, changes no project requirement and costs nothing extra, so it comes first. The answer is A.

    Why the other options are wrong

    • B. Responses are recorded in the risk register, not the resource management plan. And merely writing a measure down does not change the schedule, so the risk is not reduced.
    • C. Buying equipment would solve the problem but at high cost, and the low-cost route of negotiation should be tried first. Spending money on equipment straight away is an over-response and not cost-effective.
    • D. Changing delivery from every two weeks to monthly changes the project requirement to suit the risk and also needs a change request. It might ease the scheduling pressure at the original rhythm, but it alters the delivery requirement and depends on the change being approved. While the scheduling cause can still be handled by negotiation, it is not the first choice.

    Key takeaway Work on the cause of the risk and choose the most direct, lowest-cost measure first, such as negotiating priority. That is a typical mitigate.

    Variation Only if the workshop manager refuses to negotiate would you consider outsourcing under an agreement that transfers responsibility and liability for timely binding (transfer), or buying equipment. If the binding deliverable were cancelled, it would be avoid.

    Reference Risk Response Strategies · Lesson 2: Strategies for Threats: Escalate, Avoid, Transfer, Mitigate, Accept

  10. Question 10

    A membership system upgrade project for a retail chain has mostly completed its deliverables, but yesterday's testing still found some defects. After the project manager reports to the sponsor, the sponsor hires an external team to review the project's activities and processes to determine whether something is wrong in quality management. Which tool or technique is this?

    Show answer and explanation

    Correct answer: D

    The project is close to completion, but testing still found defects. The sponsor hires an external team to review the project's activities and processes to determine whether something is wrong in quality management. The question asks which tool or technique this is.

    “External team” and “reviewing activities and processes” are the key signals. A quality audit is a structured, independent process used to verify that project activities follow the organization's and the project's policies, processes and procedures, and it is usually conducted by a team external to the project. It is a tool of Manage Quality Assurance. Its object is the process, not the deliverable. Similar signal words include “independent”, “not part of the project team” and “check whether established procedures were followed”, all of which point to a quality audit. The answer is D.

    Why the other options are wrong

    • A. Statistical sampling takes part of a population as samples to inspect. The stem describes an independent compliance review of activities and processes by an external team, which is a quality audit.
    • B. Data analysis is a family of techniques for organizing and evaluating data and information. It is not an independent review of whether activities and processes comply.
    • C. Inspection examines whether deliverables meet standards, while what the stem has reviewed is the process, not the deliverables.

    Key takeaway An independent review of activities and processes by an external team to check compliance is a quality audit.

    Variation If the task were to check whether completed software modules meet the acceptance criteria, the answer would be inspection (deliverable verification, in Monitor and Control Scope), not a quality audit.

  11. Question 11

    The IT team of a furniture manufacturer plans to move from traditional project management to agile, and none of its members has used agile methods before. The agile coach has arranged a two-month training program for everyone, and it is now complete. What should the agile coach do next?

    Show answer and explanation

    Correct answer: A

    The IT team of a furniture manufacturer is moving from traditional project management to agile, no member has used agile before, and a two-month training program is done. What should the agile coach do next?

    Training is only the starting point of the transformation. After training, agile practices should be started gradually: pick one project and try lightweight activities such as the daily coordination meeting, the iteration review meeting, and the retrospective, letting the team adapt as it works and expanding step by step. That is the reasonable way to transition gradually. “No agile exposure, training completed” corresponds to the second step of the transformation, the pilot. Lightweight activities are chosen for the pilot so that the team builds a feel for agile at low risk and has the confidence to roll it out after success. The answer is A.

    Why the other options are wrong

    • B. Past performance can provide some information about team capability, but it cannot by itself determine whether agile is suitable; because the training is complete, the best next step here is a small pilot in which the team can practice and learn.
    • C. Carrying on with the original methods after training means the transformation has not really begun.
    • D. Rolling agile out across all projects without giving the team time to adapt can easily bring work to a halt; transformation should proceed step by step.

    Key takeaway After training, first pilot lightweight agile activities, then expand step by step.

    Variation If you were at the stage “before deciding to transform,” the answer would be to assess culture and suitability first. If you were at the stage after the pilot, it would be to show results, win buy-in, and then expand.

  12. Question 12

    A project manager regularly reviews key indicators of a technically complex project with the main stakeholders. At one meeting the sponsor says they use the risk register the project manager maintains as the basis for reporting project status to senior leadership. How should the project manager make sure the register accurately reflects project risk?

    Show answer and explanation

    Correct answer: B

    On a technically complex project, the sponsor says they use the risk register maintained by the project manager as the basis for reporting project status to senior leadership. The question asks how the project manager can make sure the register accurately reflects project risk.

    The risk register keeps being added to as the project moves forward, recording identified risks along with responses and status. To keep it accurate, review and update it regularly throughout the project life cycle: add new risks, and update or close obsolete risks and responses, including those that have occurred. As the basis for reporting, the register must be current. The answer is B.

    Why the other options are wrong

    • A. Completing the updates in one go at closure: the register would be out of date throughout execution and could not serve as a basis for reporting.
    • C. Writing identified risks into the risk management plan and issuing them with it: the risk management plan is a methodological document and does not record specific risks, which are recorded in the risk register.
    • D. Recording only the risks identified at the kickoff meeting: it would miss risks that appear later and could not reflect risks that have changed.

    Key takeaway The risk register must be updated continuously throughout the project to stay accurate.

    Variation The update rhythm should match the risk management plan, for example a monthly review.

    Reference Risk Register · Lesson 3: Analysis Techniques, Prompt Lists, the Risk Register and the Risk Report

  13. Question 13

    The senior modeling engineer on a data analytics project is about to leave, and the new member who will replace him starts next week. What should the project manager do to maintain project performance after the handover?

    Show answer and explanation

    Correct answer: D

    The senior modeling engineer is about to leave and the new member starts next week. The question asks what to do to maintain performance after the handover.

    The key signal is “maintaining performance after the handover”: performance depends on how soon the new member acquires the predecessor's skills and experience, so the focus is knowledge transfer. Arranging cross-training and mentoring by senior colleagues lets the predecessor's knowledge and practices, especially experience that is hard to put in writing, be passed on before and after the change of staff, so the new member can become effective quickly. The answer is D.

    Why the other options are wrong

    • A. Recording the risk is not wrong, but it concerns the risk management process and does not directly address whether the new member can do the job, so it is not the most direct way to maintain performance.
    • B. Incentives cannot replace skills. If the new member lacks sufficient skills and experience, a bonus will not guarantee output and may only add pressure.
    • C. Files help the new member understand the project background, but reading them does not give mastery of skills, cannot pass on the predecessor's tacit experience and keeps the new member from taking on work for a long time.

    Key takeaway When key people change, use cross-training and mentoring to complete knowledge transfer and protect performance.

    Variation If the new member starts after the predecessor has left, document the knowledge and record explanatory videos before the predecessor leaves, so the knowledge stays for the new member to study.

    Reference Lessons Learned · Lesson 3: Knowledge Transfer and Knowledge Risk: What to Do When a Key Person Is Leaving

  14. Question 14

    A project has a budget at completion of $200,000, current earned value of $80,000 and actual cost of $100,000. The project manager reforecasts at the current cost efficiency and calculates a variance at completion of −$50,000. The sponsor asks what the latest forecast means. Which conclusion should the project manager report?

    Show answer and explanation

    Correct answer: A

    BAC is $200,000, EV is $80,000 and AC is $100,000. Forecasting at the current cost efficiency gives a variance at completion VAC = −$50,000. What should be reported to the sponsor?

    VAC = BAC − EAC measures the budget variance at completion. A negative VAC means EAC is above BAC: EAC = 200 + 50 = $250,000, so the project is expected to finish $50,000 over the budget at completion. This is a forecast of the end point, not a variance that has already occurred. The answer is A.

    Why the other options are wrong

    • B. The variance to date is CV = EV − AC = 80 − 100 = −$20,000, only $20,000 overspent. VAC is a forecast for completion.
    • C. The sign is read backward: a positive VAC means an expected saving, and a negative VAC means an expected overrun.
    • D. The estimate to complete is ETC = EAC − AC = 250 − 100 = $150,000, not $50,000. The $50,000 is the expected total overrun.

    Key takeaway VAC = BAC − EAC. A negative value means an overrun is expected at completion, not that one has already occurred.

    Variation If VAC = +$30,000, then EAC = BAC − 30, a saving of $30,000 is expected. If asked about the variance to date, look at CV, not VAC.

  15. Question 15

    A pharmacy chain’s member mini-app project has closed and been handed over to operations. Three months later the sponsor wants to know how the target benefit “an 8% increase in the member repeat-purchase rate” is progressing, and someone must report on it regularly. According to the benefits management plan, who is responsible for monitoring, recording and reporting the realization of this benefit?

    Show answer and explanation

    Correct answer: D

    A member mini-app project has closed and been handed to operations. Three months later the sponsor wants to know how the target benefit “an 8% increase in the member repeat-purchase rate” is progressing, and someone must report regularly. Who is responsible according to the benefits management plan?

    The benefits management plan defines the benefits owner as the person accountable for monitoring, recording and reporting realized benefits throughout the timeframe established in the plan. The question asks who is responsible according to the benefits management plan. Where the plan names the owner, follow the plan. Do not infer who would be most suitable; look at who the plan names. The answer is D.

    Why the other options are wrong

    • A. Being the original project manager does not in itself show responsibility for later benefits tracking, and that person has moved to a new project. The project manager is responsible only if the benefits management plan names him or her as benefits owner, and the stem does not.
    • B. Dealing with members every day does not mean the supervisor has been authorized to report on benefits. The owner must be named explicitly in the benefits management plan, not whoever is closest to the data.
    • C. A change control board reviews and approves or rejects change requests. It has nothing to do with tracking and reporting benefits, and its function ends once the project closes.

    Key takeaway Benefits have a named owner, recorded in the benefits management plan, whose responsibility covers the whole timeframe set for realizing the benefits.

    Variation If the plan does not name an owner, the project manager should confirm with the sponsor and fill in the arrangement before closure and then hand it over, instead of leaving benefits untracked.

  16. Question 16

    A company is in the middle of transitioning to agile methods. The executive leadership team worries that after the transition it will lose control of project scope. What should the project manager responsible for the project do to reduce this risk?

    Show answer and explanation

    Correct answer: C

    The company is moving to agile and the executive leadership team fears losing control of project scope. What should the project manager do to reduce this risk?

    The core is “we want agile, but fear losing control.” Agile stresses empowered teams and scope that is progressively elaborated over iterations, so governance has to adjust with it. Teams decide day-to-day matters within boundaries, and leaders keep the necessary oversight through goals, metrics and outcome reviews, balancing empowerment and oversight. What needs reducing here is the leadership's sense of losing control, so treat that directly: do not deny the change, do not fall back on centralized approval, and do not let leadership let go completely. The answer is C.

    Why the other options are wrong

    • A. A verbal assurance that nothing is affected is unrealistic, since agile does change how scope is managed, and it comes with no specific measure.
    • B. Re-approving all scope at every gate is centralized approval. It strips the team of empowerment and runs against the direction of the transition.
    • D. Requiring leadership approval for every scope change is likewise centralized approval. It slows the team down and contradicts empowerment.

    Key takeaway In an agile transition, governance must balance empowering the team with leadership oversight.

    Variation For a large project with demanding governance requirements, where the worry is too little governance, you can add phase gates and escalation mechanisms. The intensity of governance is always tailored to approach, size and risk.

  17. Question 17

    A team is listing the five Scrum events on a whiteboard. It has written Sprint Planning, the Daily Scrum, the Sprint Review and the Sprint Retrospective and is missing one. Which one is missing?

    Show answer and explanation

    Correct answer: B

    A team lists the five Scrum events on a whiteboard, with Sprint Planning, the Daily Scrum, the Sprint Review and the Sprint Retrospective already written. The question asks which one is missing.

    The five Scrum events are the Sprint itself, Sprint Planning, the Daily Scrum, the Sprint Review and the Sprint Retrospective. The Sprint is the timebox that contains the others, and the other four events all happen inside the Sprint, so what is missing is the Sprint itself. The common mistake is to treat the Sprint as a “container” and forget that it counts as an event, so check item by item. The answer is B.

    Why the other options are wrong

    • A. Backlog refinement is an ongoing activity and is not one of the five events.
    • C. Release planning is a planning activity over a longer period and is not one of the five events.
    • D. In Scrum, changes are managed through the Product Backlog, and there is no dedicated change-request review meeting.

    Key takeaway Five events = the Sprint itself + four meetings. The Sprint is both the timebox and the fifth Scrum event.

    Variation If asked how many events Scrum has, the answer is five. If asked which are meetings, the answer is the four: Sprint Planning, the Daily Scrum, the Sprint Review and the Sprint Retrospective.

    Reference Scrum Framework · Lesson 2: The Scrum Core 3-3-5-5 and the Five Values

  18. Question 18

    A logistics startup has begun developing a freight-dispatch app. After the project charter is approved, the project manager starts acquiring resources and finds that the developers and testers needed are spread across several cities, while the budget includes no relocation or travel costs. What should the project manager do to make sure the project can be completed?

    Show answer and explanation

    Correct answer: C

    The charter for the freight-dispatch app is approved and the project manager is acquiring resources. The developers and testers are spread across several cities, and the budget has no relocation or travel money. The question is how to get the project done under the constraints of “no relocation or travel budget, people in different places.”

    Virtual teams are groups of people with a shared goal who fulfill their roles with little or no time spent meeting face to face. With modern communication technology, the team can store files online, discuss issues in conversation threads and keep a shared calendar. This saves travel and relocation costs and still lets the project use the right talent in other locations. When members are scattered and there is no relocation budget, forming a virtual team and creating an online team environment turns the constraint into a workable solution. The answer is C.

    Why the other options are wrong

    • A. The budget never included relocation money, and asking for more means a change request and change control, which costs time and money. The value of a virtual team is precisely that it avoids relocation and travel.
    • B. A responsibility assignment matrix can clarify roles, but the main difficulty here is geographic dispersion and the resulting communication and collaboration needs; a matrix by itself does not provide a remote collaboration environment.
    • D. Letting members work alone and deliver at milestones provides no shared online environment or communication routine, so collaboration and engagement are not assured. It is less complete than forming a virtual team.

    Key takeaway When members are scattered and there is no relocation or travel budget, use a virtual team with an online team environment instead of paying to bring everyone together.

    Variation If the stem said the budget was ample and the project had reached a critical stage, temporary colocation could be considered. If the question asked for the benefits of a virtual team, the answer would be more skilled resources, reduced costs, and less travel and relocation expense.

  19. Question 19

    A project sponsor decides to add a feature, which will affect cost, schedule and scope, and the change control board has approved the change. Which process should implement this approved change?

    Show answer and explanation

    Correct answer: C

    The sponsor decides to add a feature that affects cost, schedule and scope, and the change control board has approved it. Which process implements the approved change? You must match process names to responsibilities.

    Approved change requests are implemented through the Manage Project Execution process. That process leads the team to complete the work in the plan and puts approved changes into the work, and approved change requests are one of its inputs. Approval is only a decision, and the actual carrying out happens in the execution process. The answer is C.

    Why the other options are wrong

    • A. Manage Quality Assurance is concerned with whether quality processes are performed as expected. It does not implement approved changes. Do not be misled by the association “the change affects quality.”
    • B. Monitor and Control Project Performance tracks and compares performance and reports progress. It does not implement approved changes. It may raise change requests after finding a variance but does not implement them.
    • D. Manage Project Knowledge manages and uses experience and knowledge and has nothing to do with implementing changes. Only the lessons learned generated during implementation relate to it.

    Key takeaway Implementation of an approved change is completed in Manage Project Execution.

    Variation If asked which process assesses change requests and produces approved ones, it is Assess and Implement Changes; a person or body designated in the plan or organizational procedures approves, defers or rejects them. If asked how the effect of a change is tracked after implementation, it is the monitoring and controlling processes.

    Reference Manage Project Execution · Lesson 2: Implementing Approved Changes, and Tools and Team Coordination During Execution

  20. Question 20

    A robot development project has a tight schedule, and the customer wants to see a prototype on site in three weeks. The sponsor asks the project manager to use the data of a similar earlier project to produce a rough budget as quickly as possible so a delivery plan can be agreed with the customer. What method should the project manager use to estimate cost?

    Show answer and explanation

    Correct answer: C

    A robot development project has a tight schedule, and the sponsor asks for a rough budget as quickly as possible, using the data of a similar earlier project. The question asks which estimating method to use.

    The stem gives three signals: refer to the data of a similar earlier project, as quickly as possible, and rough. These are the features of analogous estimating: it projects from historical data of a similar past activity or project, top-down, at low cost and high speed but with lower accuracy, and it suits situations where detailed information is insufficient and a result is needed quickly. The answer is C.

    Why the other options are wrong

    • A. Bottom-up estimating is usually more accurate, but it requires estimating each work package and aggregating level by level, which takes longer and does not fit “as quickly as possible” and “rough”.
    • B. Multipoint estimating uses optimistic, pessimistic and most likely values to handle uncertainty. The stem stresses reference to a similar project and speed and does not mention uncertainty.
    • D. Expert judgment is a source of opinion that runs through all methods. The stem says explicitly to use the data of a similar project, and analogous estimating corresponds to that more directly.

    Key takeaway “Refer to a similar project, fast, rough”: analogous estimating.

    Variation If a historical regression model of cost per square meter against area existed, choose parametric estimating; if accuracy down to each work package were required and more time were acceptable, choose bottom-up estimating.

  21. Question 21

    A newly appointed project manager takes over a mechanical and electrical installation project at a commercial complex. After reading the project plan through, the project manager finds that health and safety measures for workers on site are almost entirely missing, feels uneasy and wants to fix it right away. Why is this situation a hazard?

    Show answer and explanation

    Correct answer: D

    After reading through the plan, the new project manager finds that health and safety measures for site workers are almost entirely missing. The question asks why this is a hazard, and the key is to identify the root cause rather than a possible consequence.

    Health and safety requirements come from the laws and regulations where the project is located. They are an external constraint the project cannot avoid and a mandatory requirement among the enterprise environmental factors. The project manager has an obligation to comply with the regulations where the project is located, so omitting these measures from the plan is a compliance hazard: if something happens, the project bears legal responsibility, not just schedule impact. So the root of the hazard is the duty to comply with the law. The answer is D.

    Why the other options are wrong

    • A. Performance measurement targets are standards for measuring scope, schedule, cost and other performance. They are not directly related to health and safety requirements and do not explain why missing safety measures are a hazard.
    • B. An accident could indeed delay delivery, but that is only one consequence. What is asked for is the root cause: even with no accident, omitting legally required safety measures is itself a violation.
    • C. Organizational process assets include the organization's internal policies, procedures and templates, and applicable internal policies and procedures must be followed too. But the legal floor for workers' health and safety comes from the regulations that apply where the project is located and is an enterprise environmental factor, so D explains the compliance hazard of the omission more directly.

    Key takeaway Health and safety is a regulatory requirement. The project manager has an obligation to comply, and leaving it out is a compliance hazard.

    Variation If there is no written safety regulation where the project is located but the employer has an internal safety policy, follow the organizational process assets. If both exist, comply with both; where they address the same point and one is stricter, common exam practice is to apply the stricter standard.

    Reference Project Compliance · Lesson 1: What Project Compliance Means and Where It Comes From

  22. Question 22

    The project manager asks the risk analyst to run a quantitative analysis of overall cost risk every quarter and to submit the results. What should the analyst submit?

    Show answer and explanation

    Correct answer: B

    The project asks the risk analyst to run a quantitative analysis of overall cost risk every quarter and to submit the results. You must judge what the typical result of this quantitative analysis is.

    The most common way to analyze overall cost risk quantitatively is Monte Carlo simulation: put the cost uncertainties into a model and iterate repeatedly to obtain a probability distribution of cost. This distribution is often drawn as a cumulative probability curve, the S-curve, from which management can read the probability that cost will not exceed a given figure and then set the contingency reserve. So the result is a cumulative probability distribution curve. The other three are outputs about individual risks or groups of risks, not quantitative conclusions about overall cost risk. The answer is B.

    Why the other options are wrong

    • A. The probability and impact matrix is a result of qualitative risk analysis. It grades and ranks individual risks by probability and impact and does not give a probability distribution of overall cost.
    • C. A risk categorization summary groups risks by source or area affected to show where risk is concentrated. It is a qualitative organization of information and contains no numeric probability conclusions.
    • D. The watch list records low-priority risks that are not being actively addressed for now. It is a product of qualitative analysis and has nothing to do with quantitative analysis of overall cost risk.

    Key takeaway The typical result of quantitative analysis (Monte Carlo) is a cumulative probability curve (S-curve), used to read probabilities and reserves.

    Variation If the question asked “what is the output of Monte Carlo?”, the answer is a probability distribution of a range of outcomes, often represented by a histogram or cumulative probability curve, rather than a single-point estimate or priority ranking. If it asked what to use to grade individual risks, it is the probability and impact matrix.

  23. Question 23

    On an engineering project, all the deliverables required by the plan have been completed and the team is eager to declare closure. But when stakeholders question it, the project manager cannot offer a convincing reason to show that “it is now time to close.” Looking back, what should the project manager have done earlier to avoid this predicament?

    Show answer and explanation

    Correct answer: D

    All deliverables are complete and the team is eager to close, but the project manager cannot give a convincing reason that “it is now time to close.” The question asks what should have been done earlier; look for something that should have been done in advance.

    Whether a project can close depends first on whether the deliverables meet the acceptance criteria and have been formally accepted (the closing activities, such as completion or exit criteria, should also be checked). Acceptance criteria are a set of conditions that are met before deliverables are accepted (PMBOK 8), and they are written into the scope statement when scope is defined. If acceptance criteria were set for each deliverable in advance and checked at closing, there is objective evidence that the requirements have been met. Without criteria, the judgment can only rest on impressions and will hardly persuade doubters. The answer is D.

    Why the other options are wrong

    • A. Business value may continue to be realized after the project ends and is often hard to demonstrate item by item at the moment of closing. To judge whether the project can close now, look at conditions such as deliverable acceptance and completion or exit criteria; business value is less clear and checkable than acceptance criteria set in advance.
    • B. Clearing all the customer's complaints before the last phase is unrealistic and is not a basis for closing. Whether a complaint is valid still has to be judged against the acceptance criteria.
    • C. Checking the sponsor's expectations item by item: expectations are often vague and less clear than written acceptance criteria. Closing on the basis of expectations still lacks objective evidence.

    Key takeaway Whether closing can be justified depends on whether acceptance criteria were set during planning.

    Variation If the acceptance criteria were set and all are met, but the customer is still unwilling to sign, go through formal acceptance or dispute handling based on the scope statement and the contract; if the criteria are not yet met, rework first.

    Reference Project Scope Statement · Lesson 3: The Project Scope Statement: Four Components, Acceptance Criteria and Exclusions

  24. Question 24

    A project manager is leading a warehouse system project for a logistics company, with the goal of reducing operating costs. The project was planned for 10 months but has been extended to 14 months because of various problems during execution. At the end of month 8, the expected cost savings have been exceeded, but not all the features planned to be live by that date have gone live. How should the project manager report progress to stakeholders?

    Show answer and explanation

    Correct answer: B

    During execution, a warehouse system project planned for 10 months has been extended to 14. At the end of month 8, cost savings are ahead of target, but some features that should be live by now are not. The question asks how to report progress to stakeholders.

    Status communication should be complete and forward-looking: it lets stakeholders see that cost savings have been exceeded, honestly explains that some features are late, and says how the rest will be completed. Then they understand cost and schedule clearly and can form their own judgment. The answer is B.

    Why the other options are wrong

    • A. Saying only that features were not completed on time leaves out the savings already achieved and any follow-up arrangements. The information is one-sided.
    • C. Waiting until the work is done to report leaves the sponsor uninformed for a long time, violates the requirement for timely communication, and may delay the project further.
    • D. A fixed monthly email of schedule and cost data may not respond to the immediate need to report progress, and it does not clearly cover the savings beyond target, the impact of the delayed features or the follow-up plan. Push email is not wrong in itself, but here it is less complete and less timely than B.

    Key takeaway A status report must explain results, delays and the follow-up plan. It should not report only the gap, and it should not wait until the work is done.

    Variation If costs were also over budget, report that honestly too and attach the response plan. If executives want a brief summary, tailor the report to the audience by highlighting key indicators and exceptions.

  25. Question 25

    A project manager at a consulting firm is technically strong but repeatedly interrupts and belittles team members in review meetings. When a member raises this with him in person, he completely denies ever behaving this way. What is the most likely reason for this behavior?

    Show answer and explanation

    Correct answer: D

    A technically strong project manager at a consulting firm repeatedly interrupts and belittles team members in review meetings. When a member raises this with him face to face, he flatly denies it. The question asks for the most likely reason for this behavior.

    PMBOK 8 defines emotional intelligence as the ability to identify, assess and manage the emotions of oneself, other people and groups, and its model has four areas: self-awareness, self-management, social awareness and social skills. The decisive signal is that the project manager denies the behavior even after being told in person, showing that he is not aware of his behavior or its effect on others. That is weak self-awareness and supports a lack of emotional intelligence. Recurrence alone does not establish weak self-management; that would normally require evidence that he recognizes the behavior as inappropriate but cannot control it. The answer is D.

    Why the other options are wrong

    • A. The stem describes only behavior and does not show whether he has had project management training. Even a lack of training would not explain the denial after being confronted.
    • B. The stem gives no information about his authority, and the size of his authority would not explain why he denies his own behavior when confronted.
    • C. The stem states that he is technically strong, so there is no basis for a role mismatch, and a mismatch would not explain the denial of his own behavior either.

    Key takeaway Denial after inappropriate behavior is pointed out directly indicates weak self-awareness; inability to control behavior despite recognizing it as inappropriate would additionally indicate weak self-management.

    Variation If the stem said the project manager knows his attitude is bad but loses his temper under pressure, the missing skill is mainly self-management; if he had not noticed that members were already discouraged, the missing skill is social awareness.

  26. Question 26

    A corporate training-courseware development project is in execution, and a key stakeholder asks to add an exercise question bank that would make the courseware more useful. The team's initial estimate is that adding it would have very little effect on cost. What should the project manager do NEXT?

    Show answer and explanation

    Correct answer: B

    A training-courseware development project is in execution. A key stakeholder asks to add an exercise question bank, and the team's initial estimate is that the cost impact is very small. What should the project manager do next?

    A small cost impact does not mean the change has no impact. The project manager assesses with the team the full impact of the change on scope, schedule, quality, risk and so on; if a controlled baseline or artifact is affected, the request is then submitted to the approver designated in the change management plan (such as the change control board). Analyze first and then act, and the “next step” is to assess. Stems like this often use phrases such as “very little impact” or “just a small extra” to tempt you into skipping the assessment, so be wary. Only after the assessment is it known whether a baseline is involved, and so whether to submit the request to the designated approver. The answer is B.

    Why the other options are wrong

    • A. Submission for approval comes after assessment. Reported without a complete assessment, the request leaves the board without a basis for decision.
    • C. The project manager cannot implement a change directly without assessment and approval by someone with authority.
    • D. Changes are approved by the board or the designated owner; senior management is not the default approver.

    Key takeaway When a stakeholder raises a change, assess its full impact first and then decide whether to submit it for approval. A small cost impact does not mean scope, schedule, quality and risk are unaffected, and an initial impression is no reason to skip assessment.

    Variation If the stem said “assessment is complete and the scope baseline is involved,” the next step is to submit it, as the change management plan specifies, to the designated approver (such as the change control board).

  27. Question 27

    The sponsor and executive team of a consulting firm are preparing the business case for a new project and have two alternatives. Alternative 1: 40% probability of success, with a profit of $150,000 on success, and a total loss of the $50,000 invested on failure. Alternative 2: 60% probability of success, with a profit of $200,000 on success, and a total loss of the $100,000 invested on failure. Which statement is correct?

    Show answer and explanation

    Correct answer: B

    In the business case stage, both alternatives have two outcomes, success and failure. They are compared by EMV, and the question asks which statement is correct.

    EMV is the sum of each outcome's probability times its net value, and a loss on failure enters the calculation as a negative number. Calculate both branches of each alternative, then check the alternative and the figure in each of the four options. The EMV of Alternative 1 is $30,000 and that of Alternative 2 is $80,000, so Alternative 2 has the higher expected return. The answer is B.

    1. Alternative 1: 0.4 × 150 + 0.6 × (−50) = 60 − 30 = $30,000
    2. Alternative 2: 0.6 × 200 + 0.4 × (−100) = 120 − 40 = $80,000
    3. Probability check: the probabilities of both alternatives total 100%
    4. Comparison: 80 is greater than 30, so Alternative 2 has the higher expected return, matching option B

    Why the other options are wrong

    • A. Mixes up the two EMVs: Alternative 1 is actually $30,000, and it is Alternative 2 that is $80,000.
    • C. 100 = 200 − 100: this subtracts the failure loss directly from the success profit without multiplying by the probabilities, so it is not an expected value.
    • D. 60 = 0.4 × 150: this calculates only the success branch and leaves out the failure branch of −$30,000, so the figure is too high.

    Key takeaway EMV = Σ (probability × net value). Calculate both the success and failure branches, with failure negative.

    Variation If Alternative 2's probability of success fell to 40%, EMV = 0.4 × 200 − 0.6 × 100 = $20,000, below Alternative 1's $30,000, and the conclusion would flip.

  28. Question 28

    A corporate group plans to launch several interrelated projects at the same time, and a mid-level manager suggests combining them into one program managed together. When the board reviews the proposal, it finds that financial forecast data for some of the projects were not provided, so it cannot decide whether to approve them. Which document should be submitted to the board so that it can make the approval decision?

    Show answer and explanation

    Correct answer: C

    A corporate group plans several interrelated projects. In its review the board finds that the financial forecasts for some projects were not provided and it cannot decide whether to approve them. The question is which document should be submitted to the board.

    The projects are not yet approved and are at the stage before initiation, and what the board lacks is the evidence needed to decide whether the projects are worth doing. The business case is a documented economic feasibility analysis that tests whether the benefits the project can deliver hold up. It provides the basis for authorizing further project management activities and contains an analysis of business need and a cost-benefit analysis; the project is then formally started through the project charter. What the board lacks is exactly the data on expected benefits and costs, so the business case should be submitted. The answer is C.

    Why the other options are wrong

    • A. The scope baseline consists of the scope statement, the WBS and the WBS dictionary. It does not exist yet at initiation, and it contains no financial forecasts.
    • B. The project charter is formally issued after the project is approved and authorizes the project manager to begin work. This question is still at the stage of deciding whether to approve.
    • D. The project management plan explains how the work will be done. It is not the basis for approving a project and certainly not the document that argues the value of the investment.

    Key takeaway To answer “is it worth doing?” before approval, rely on the business case (the economic feasibility study).

    Variation If the project has already been approved and the project manager must be formally authorized to start work, the document becomes the project charter.

  29. Question 29

    A restaurant chain is launching a new store ordering system. The project charter is approved, and the project manager is preparing to develop the integrated project management plan. What should the project manager do FIRST before developing the plan?

    Show answer and explanation

    Correct answer: C

    The store ordering system project has an approved charter, and the project manager is about to develop the integrated project management plan. What comes first before developing the plan?

    The development approach, life cycle and tailoring are the premise of integrating the plan and also an input to planning in each performance domain. So first assess the project's needs, complexity and size, and recommend a suitable development approach on that basis, and only then integrate. This step produces the choice of approach, which determines the level of detail and the rhythm of each sub-plan: predictive projects integrate more baselines, and adaptive ones more iteration and release plans. The answer is C.

    Why the other options are wrong

    • A. Selecting suppliers requires a sourcing strategy first, and the strategy depends on the approach and scope, so doing it now is premature.
    • B. The cost baseline is developed from cost estimates, schedule information and other relevant inputs, then incorporated into the integrated plan as a baseline. Until the approach and scope are clear, you cannot fix it from an old project's budget.
    • D. Having functional managers submit first drafts from experience, without first understanding this project's characteristics, can leave the sub-plans inconsistent with one another and without team involvement.

    Key takeaway Before developing the integrated plan, assess needs, complexity and size and choose the approach.

    Variation If the approach is already chosen, first integrate the sub-plans and verify alignment. Once the plan is finished, the next step is to submit it for key stakeholder review under the governance arrangements and communicate it, and, where the organization requires formal approval, obtain the designated approver's approval, not to start executing.

  30. Question 30

    The project manager has an AI tool forecast the estimate at completion (EAC) from earned value data and plans to compare it with the EAC calculated by formula. Compared with a formula calculation, what needs the MOST extra attention when using an AI forecast?

    Show answer and explanation

    Correct answer: B

    In a project, the project manager has AI forecast the estimate at completion (EAC) from earned value data and will compare it with the EAC calculated by formula. The question asks what needs the most extra attention with an AI forecast compared with a formula calculation.

    The key is what an AI forecast requires beyond a formula calculation. A formula calculation also depends on accurate, consistent inputs, but its method is fixed. An AI forecast also depends on training data and model assumptions, and its output may be inaccurate or biased, and PMBOK 8 stresses that information obtained from AI should be checked and validated. So you must examine both the input data and the model assumptions and also validate the forecast output, comparing it with the formula result. The answer is B.

    Why the other options are wrong

    • A. The style and colors of a chart affect only presentation, not whether the forecast is reliable.
    • C. Choosing an EAC formula is a consideration in formula calculation, not an extra point for AI forecasts. The particular risk of an AI forecast lies in its data and model inputs.
    • D. Converting currency units at exchange rates is a routine check in any cost calculation and is not specific to AI.

    Key takeaway An AI forecast is not black-box truth: examine the input data and model assumptions, and check and validate the output.

    Variation If the AI result differs greatly from the formula, the next step is still to check the input data and model assumptions first, not to accept or reject it outright. If asked which strategy level this application belongs to, the answer is assistance (predictive analytics for planning).

  31. Question 31

    The sponsor wants to see the project's work performance report. While compiling members' work performance data, the project manager finds that a test engineer has neither reported progress as the communications management plan requires nor finished work on schedule, and when asked why, the engineer gives no explanation at all. How should the project manager handle this member's problem?

    Show answer and explanation

    Correct answer: A

    The project is in execution and monitoring. The sponsor wants the work performance report, and in compiling the data the project manager finds a test engineer who does not report as the communications management plan requires, does not finish work on schedule and gives no reason. What does the project manager do first?

    When there is a deviation from the plan, assess first and then act. The cause is unknown and the impact unclear, so the first thing is to work out how much the member's delay affects the project schedule, for example whether the work is on the critical path and which other work it will push back. Once the impact is clear, you can decide whether to prompt the member, adjust staffing or escalate. The answer is A.

    Why the other options are wrong

    • B. Requiring strict adherence to the schedule from now on neither assesses the impact already caused nor finds out why the member is not reporting, so the problem may persist.
    • C. Replacing the person is a specific remedy. Replacing someone without assessing the impact may cost more in handover and risk than the delay itself.
    • D. Going to the sponsor at the first sign of trouble is passive. The project manager should assess first and escalate afterward if necessary.

    Key takeaway When a member deviates from the plan, first assess the impact on the schedule, and then decide what measures to take.

    Variation If the assessment shows that the delay is on the critical path and has a large impact, then consider adjusting staffing or crashing. If the cause turns out to be an unclear task description, clarify the requirements first.

  32. Question 32

    In project governance, the project manager sets out to determine the success metrics for a new project. How should these metrics be determined?

    Show answer and explanation

    Correct answer: A

    The question is how success metrics should be determined, who takes part in determining them, and by what method.

    Success metrics express the parties' shared understanding of what counts as success. If only the project manager endorses them, then after delivery the sponsor or key stakeholders may feel the goals were not met. So the metrics should be agreed with the sponsor and key stakeholders, which both aligns expectations and ensures that all parties recognize them when performance is later evaluated. Agreeing them is itself a communication that aligns expectations, and once written into a document, later performance evaluation and go/no-go decisions rest on them. The answer is A.

    Why the other options are wrong

    • B. If the project manager drafts them alone and sends them out without the other side's endorsement, the metrics can easily diverge from the sponsor's expectations and lead to significant disputes later.
    • C. Copying the previous similar project's metrics ignores this project's own goals and value proposition. Similar does not mean identical, and the metrics may measure the wrong thing.
    • D. A team vote reflects only the team's internal opinion, while the judgment of “success” cannot do without the sponsor and key stakeholders, and a majority vote does not mean they agree.

    Key takeaway Success metrics are not set by the project manager or the team alone. They are determined together with the sponsor and key stakeholders.

    Variation If the stem asked what to do once the metrics are set, record them in project documents and compare against them regularly in governance. Changes to the metrics follow the project's applicable governance and change procedures; in a predictive project, a change to a configuration-controlled artifact or baseline goes through formal change control.

    Reference Project Governance · Lesson 2: Governance Scenarios, Value-Based Decisions and Success Metrics

  33. Question 33

    In one iteration, a team is developing an order export feature and it looks as if it cannot be finished on time. The reason is that the developer responsible for the feature is not yet skilled in the technology required, while another member of the team is familiar with it. How should the team resolve this?

    Show answer and explanation

    Correct answer: B

    In an iteration, the team is developing an order export feature and it looks as if it cannot be finished on time. The reason is that the developer responsible is not yet skilled in the technology required, while another member of the team is familiar with it. An appropriate way to resolve this must be chosen.

    The root of the problem is an individual skill gap. The XP approach is pair programming: the developer works at the same station as a member who knows the technology, and the more experienced one teaches while doing, so the work catches up with schedule and the skill stays in the team. The team happens to have someone familiar with the technology, so the resource is at hand. The answer is B.

    Why the other options are wrong

    • A. Re-estimating changes only the numbers. It does not remove the skill gap, and the next similar feature will be late in the same way.
    • C. The stem does not say that the Scrum Master has the required coding expertise, while it explicitly identifies a team member who does. Pairing the two developers addresses the work and transfers knowledge directly, so C is less suitable than B.
    • D. Handing the hard feature to someone else just avoids the problem. The original feature still has no one to do it, and the team learns no new skill.

    Key takeaway When a member's lack of skill slows progress, first have the team solve it internally with pair programming, instead of changing estimates or swapping tasks.

    Variation If no one on the team is familiar with the technology, bring in the skill through training or an outside expert, or first schedule an exploratory technical spike. For a small one-off task, weigh knowledge transfer before deciding.

  34. Question 34

    On an online food-ordering platform project, the same kind of order-status synchronization error recurs every few weeks, and each time the team patches it temporarily. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    On an online food-ordering platform project, the same kind of order-status synchronization error recurs every few weeks, and the team patches it temporarily each time. What should the project manager do?

    When the same kind of issue keeps recurring, the temporary fixes are treating only the symptom and have not removed the cause. Root cause analysis is used to determine the underlying source of a defect, and once all the root causes are eliminated the problem will not recur. So the project manager should conduct a root cause analysis, find the underlying cause and then take action. The signal phrases in this kind of question, “every few weeks” and “temporarily fixed each time,” point to treating the symptom, not the cause. Once the root cause analysis is done, the measures can be targeted. The answer is A.

    Why the other options are wrong

    • B. Keeping the temporary fix and adding more log entries means the issue will keep recurring.
    • C. Adding testers and inspections only finds problems faster. It does not remove the cause and costs more.
    • D. Downgrading it to low priority lets a latent defect keep consuming team effort over a long time. “Fixed quickly every time” does not mean no impact.

    Key takeaway When a problem recurs, do a root cause analysis; do not stop at temporary fixes.

    Variation If the stem said “first occurrence, minor impact,” log it and handle it through the normal process; root cause analysis becomes the preferred answer when the problem recurs or is widespread.

  35. Question 35

    A store checkout system upgrade project has used up its budget, and the project sponsor, who has authority to make the termination decision, formally decides to terminate the project early. What should the project manager do next?

    Show answer and explanation

    Correct answer: C

    The project budget is exhausted, and the project sponsor, who has authority to make the termination decision, formally decides to terminate the project early. It therefore goes through Close Project or Phase. The question asks what the project manager should do once the termination decision has been given.

    An early-terminated project must also be formally closed. PMBOK 8 calls for establishing procedures to investigate and document the reasons the project may have been terminated before completion, so C corresponds most directly to this requirement: document the reason for termination and the status of completed and uncompleted deliverables in the closure documents so that any needed handoff or disposition can be completed. Contract termination, claims handling, summarizing lessons learned, archiving and releasing resources are also matters to coordinate in formal closure. The answer is C.

    Why the other options are wrong

    • A. Terminating outsourced work is a specific closure task that should be handled promptly under the contract's termination clauses, but it is not a direct response to the requirement to investigate and record the reason for early termination.
    • B. The authorized project sponsor has formally made the termination decision. Filing a change to cut scope to fit the budget would conflict with that decision and cannot be used to keep the project going.
    • D. The charter records what was approved at initiation and is not revised to reflect actual cost and time. The circumstances of termination go into the closure documents and the final report.

    Key takeaway An early-terminated project is also closed out: record the reason for termination and account for the completed and uncompleted deliverables.

    Variation If the project sponsor does not terminate the project and instead approves additional funding through the governance process, the cost baseline is adjusted through change control.

    Reference Project Closure · Lesson 3: Early Termination: What to Do After a Project Is Stopped

  36. Question 36

    A project manager at PMLyceum is in charge of a large project. After a make-or-buy analysis, the team decides to buy a batch of standard components. After the request for quote is issued, quotes arrive from several sellers. What should the project manager use to judge whether the quotes are reasonable?

    Show answer and explanation

    Correct answer: B

    The make-or-buy analysis is done, the request for quote has been issued and the sellers’ quotes have been received. The question asks what to use to test whether the quotes are reasonable.

    The signals: the decision to buy is made, the quotes are in, and the core task is “judging whether the quotes are reasonable”. To judge that you need a price benchmark independent of the sellers: an independent estimate (the term in the PMBOK 8 procurement management plan; “independent cost estimate” is a common exam term) prepared by the buyer or by an outside estimator. Compare the quotes against it once they arrive; if the difference is marked, then check whether the statement of work is deficient and whether the seller misunderstood the requirements. The answer is B.

    Why the other options are wrong

    • A. Proposal evaluation can assess responsiveness, price and other established criteria, but it is not itself an independent price benchmark for testing whether quotes are reasonable.
    • C. Expert judgment can be used to prepare an independent cost estimate, but it is not itself the benchmark for comparing quotes, and it is less directly tied to the stem than the independent cost estimate.
    • D. The bidder conference is held before sellers submit proposals, and the quotes have already been received.

    Key takeaway The independent cost estimate is the buyer’s benchmark for testing whether the seller’s quote is reasonable.

    Variation If a quote is far below the independent estimate, first check the statement of work and the seller’s understanding rather than assume it will save money; if the question asks how to make all bidders understand the same thing, the answer is the bidder conference.

  37. Question 37

    A client proposes a small change and wants it done with no delay and no fee. The project manager believes he has enough authority to decide on his own but is not sure. What should the project manager do NEXT?

    Show answer and explanation

    Correct answer: B

    A client proposes a small change and wants it done with no delay and no fee. The project manager thinks he has the authority to decide it alone but is not sure. What should the project manager do next?

    Whatever the size of the change and whether or not the project manager thinks he has the authority, the change control process is followed first: record and assess it, then have it decided by the owner designated in the change management plan or project management plan, or by the change control board. The stem makes clear the project manager is “not sure” about his authority, so he should first find out who the change management plan designates as approver (it may be the project manager, the sponsor or the change control board), then record, assess and submit to that approver, and implement only after approval, which also leaves a complete record. The answer is B.

    Why the other options are wrong

    • A. A change is first assessed and taken through approval; it is not an opportunity to quote a price and earn a profit. The client expects no charge, so quoting first both departs from the process and harms the relationship.
    • C. Using contingency measures on one's own to complete it for free, with no record or approval, bypasses change control and may let costs get out of hand. Client satisfaction does not override the process.
    • D. Putting the change off until closure and folding it into the settlement lets problems pile up, goes against timely assessment, and may lead to a final dispute.

    Key takeaway When authority is uncertain, do not decide it alone: check the change management plan to confirm the approver, then go through Assess and Implement Changes, with the designated owner or the change control board giving approval.

    Variation If the change management plan expressly authorizes the project manager to approve small changes, he can approve and record them himself; where the authorization is unclear, always submit.

    Reference Change Control · Lesson 3: Change Approval and the Change Control Board

  38. Question 38

    A fitness chain is considering expanding to one of three neighboring business districts. The project manager needs to explain to management the benefits of each of three paths: build a new club, lease an existing space, or not expand at all. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    The project is at the options-evaluation stage. You need to decide what method puts the value of the three paths (including not expanding) on the same basis for comparison.

    Each path has its own cash outflows and inflows at different points in time. Only by discounting them to present value and computing net present value can costs and benefits be compared at the same point in time. The NPV of not expanding can be taken as 0, so it can be included too. The path with the largest positive NPV has the most value and directly supports management's decision. The answer is C.

    Why the other options are wrong

    • A. Rent is only part of cost and applies only to the lease path. It includes no benefits and does not cover building or not expanding.
    • B. Payback period says only how long it takes to recover the investment. It does not reflect the size of benefits after payback or the time value of money, and here it also omits the “do not expand” path.
    • D. Kano analysis is a tool for prioritizing requirements and understanding customer satisfaction. It is not a financial method for comparing the value of investment options.

    Key takeaway To compare the overall value of several investment options (including doing nothing), discount costs and benefits to a common basis and compare the net present values.

    Variation If the NPVs of the three paths are +$120,000, +$80,000 and 0 (not expanding), choose the +$120,000 path; if all were negative, choose not to expand.

  39. Question 39

    PMLyceum is developing an AI resume pre-screening system. The project lasts 12 months and uses Scrum with two-week Sprints. The model team finds that in the past 5 years of hiring data, female candidates' pass rate is 18% lower than male candidates', and out-of-town candidates' pass rate is 30% lower than local ones'. Training directly on this would make the model reproduce this discrimination. How should the project manager address the identified data bias before training?

    Show answer and explanation

    Correct answer: A

    The AI resume pre-screening system is in the model development stage and the team uses Scrum Sprints. In the historical hiring data, female candidates' pass rate is 18% lower than male candidates', and out-of-town candidates' is 30% lower than local ones'. Training directly would make the model reproduce discrimination. How should the project manager address the identified data bias before training?

    One source of bias is that the training data itself is biased, so differences in the data are learned by the model and reproduced in its decisions. The mitigation measures in PMBOK 8 include diversifying the data sets on which the AI system is trained. The most direct and effective approach in the development stage is to treat the data before training to weaken the gender and regional bias, and to test periodically afterward. Resampling and weighting are technical means used in practice to handle data bias and are in the same direction as the measure of diversifying the training data sets. The answer is A.

    Why the other options are wrong

    • B. Training on it as is because “the historical data reflects reality” lets discrimination happen knowingly, which goes against responsible use.
    • C. The stem gives no law or policy requiring the team to report first and wait for regulatory guidance. The team should apply feasible bias mitigations while following applicable law and organizational policy on reporting or seeking external guidance.
    • D. Suspending the whole project until all bias is eliminated is too extreme: bias can be handled during development, and the bias in historical data may not be fully removable.

    Key takeaway When training data is biased, treat the data before training and test periodically. Do not let it go, and do not stop everything.

    Variation If the stem asked “what else should be done besides treating the data?”, the answer is to test periodically with a focus on bias and involve different teams in development. If the bias came from the algorithm's design, the algorithm must be adjusted and retested.

  40. Question 40

    In an iteration team, the team lead notices that the back-end developer and the front-end developer cannot agree on which interface fields to keep, and they have ignored each other for several days. What should the team lead do?

    Show answer and explanation

    Correct answer: D

    In an iteration team, a back-end developer and a front-end developer cannot agree on which interface fields to keep and have not spoken for several days. The question asks what the team lead should do.

    The conflict has lasted several days, is hurting collaboration, and the two have not resolved it themselves, so it has escalated. PMBOK 8 says that when conflict escalates the project manager should help facilitate a satisfactory resolution, address it early, and usually take a direct, collaborative approach; in an iteration team the team lead plays the same kind of helping role (common exam practice). Arranging a meeting and helping the two find a solution they both accept neither delays nor escalates. The answer is D.

    Why the other options are wrong

    • A. The retrospective is still many days away. Waiting for it is avoidance, and the conflict will keep hurting collaboration, so it should be faced early.
    • B. A conflict between two members should not, and need not, be taken to the sponsor at the outset. Going over their heads would also weaken the team's own ability to resolve problems.
    • C. Moving one person away avoids the conflict. It neither resolves the disagreement nor does the team any good, since it loses a member.

    Key takeaway For conflict inside the team, face it early, in person and collaboratively; do not delay, escalate or avoid.

    Variation If this were the first time the two disagreed and they had not yet talked, the team lead should first encourage them to talk it out themselves and step in later if necessary.

    Reference Conflict Management · Lesson 3: Judging Conflict Scenarios: From Identifying the Source to Choosing the Right Action

  41. Question 41

    A cross-border e-commerce operations platform is being developed using an adaptive approach. The project manager keeps receiving complaints from stakeholders that the delivered functions are not what the business departments need. The sponsor wants to know whether resources are being used effectively. To avoid, at the source, work that has no value to the business, what should the project manager do?

    Show answer and explanation

    Correct answer: D

    A cross-border e-commerce operations platform is being developed using an adaptive approach. The project manager keeps receiving complaints that the delivered functions are not what the business needs, and the sponsor wants to know if resources are used effectively. The question asks what to do to avoid work that has no business value at the source, so look for a preventive measure.

    On an adaptive project, requirements are collected as user stories, placed in the backlog and continuously ordered by priority. Having the product owner meet regularly with stakeholders and create and adjust the backlog from their actual requirements means the team is always working on what the business needs most, which avoids wasted resources. The answer is D.

    Why the other options are wrong

    • A. Having stakeholders write complaints as change requests is a remedy after the fact. It adds process burden and does not solve the disconnect between the requirements and the business.
    • B. Defining the product scope first and asking people not to deviate is a predictive mindset. In an adaptive environment requirements change, and rigid locking creates larger deviations.
    • C. Reviewing and improving at the retrospective is continuous improvement after the fact. It can improve later iterations, but it is not the direct way to avoid valueless work beforehand.

    Key takeaway On an adaptive project, have the product owner keep talking with stakeholders and order the backlog by their requirements, to avoid work that adds no value.

    Variation On a predictive project, stakeholders would confirm requirements during Elicit and Analyze Requirements and the scope would be validated when scope is confirmed. The adaptive approach is continuous ordering.

    Reference Requirements Elicitation · Lesson 4: Decision Methods and Prioritizing Requirements: Voting, Multicriteria Analysis, MoSCoW and User Stories

  42. Question 42

    The customer and product owner have clarified the data-storage outcomes required from a new system, but the team is still unsure which storage architecture can meet them and cannot estimate reliably or move forward. As an agile practitioner, what should you do next?

    Show answer and explanation

    Correct answer: C

    At the start of the project, the customer and product owner have clarified the required data-storage outcomes, but the team remains unsure which architecture can meet them and cannot estimate reliably or proceed. What should be done next?

    When work is highly uncertain and the team has not done it before, first run a spike (a common exam term): a time-boxed, small-scale exploration that clarifies the risk caused by the technical uncertainty, and then write stories, estimate and schedule based on what is learned. The output of a spike is knowledge, not product. Its result may be “feasible”, “not feasible” or “a different approach is needed”; in any case the team now has a basis for estimating and scheduling. The answer is C.

    Why the other options are wrong

    • A. Writing stories when both the product and the technology are poorly understood only produces vague stories, and the uncertainty is not removed.
    • B. Iteration zero (a common exam term) may include several startup activities and even initial architectural exploration, but this option specifies only environment, infrastructure, and document-library setup and does not investigate the particular technical unknown in the stem.
    • D. Continuing to refine the list without resolving the unknowns has no basis, and merely reporting the situation does not move anything forward.

    Key takeaway When the required outcome is clear but the technical approach remains uncertain, use a spike to reduce the technical uncertainty and then estimate and plan the subsequent work.

    Variation If the stem were changed to “the team cannot tell whether an interface can respond within 1 second”, the answer would still be a spike, with a short timebox appropriate to the question, a conclusion as the output, and any experimental implementation not automatically treated as production code.

  43. Question 43

    A team takes over a complex smart-wearable project. The product uses a new technology, the team is unfamiliar with both the technology and the chosen approach, and the customer is also worried about how well the product will sell once launched. How should the project manager help the team and the customer?

    Show answer and explanation

    Correct answer: D

    A team takes over a complex smart-wearable project. The product uses a new technology, the team is unfamiliar with the technology and the chosen approach, and the customer worries about sales after launch. The project manager must help both the team and the customer.

    PMBOK 8 describes the minimum viable product as defining the scope of the first release to customers by identifying the fewest features that would deliver value. By building the MVP first, the team can use the most basic version to test whether the technology works, and the customer can judge from real market feedback whether the product is worth building. Both concerns are eased step by step, and later work is adjusted with feedback. The answer is D.

    Why the other options are wrong

    • A. Under high uncertainty it is hard to get all the detailed requirements at once, and having them would still not test technical feasibility or market response.
    • B. Risk management is needed, but “manage the various risks” is too general and does not specify an experiment that tests both technical feasibility and market acceptance. Option D gives a concrete way to generate real feedback.
    • C. Market research and segmentation are useful references, but they cannot verify that the new technology works, and they are less convincing than feedback from real users.

    Key takeaway When both technology and market are uncertain, use an MVP to validate assumptions. It is more direct than research or planning alone.

    Variation If the technology were mature and only the market uncertain, the MVP could contain just the minimum feature set and be released to a small group of users, focusing on validating demand.

    Reference Minimum Viable Product · Lesson 1: Minimum Viable Product (MVP): Why You Need One and What It Is

  44. Question 44

    A paper mill is carrying out a flue gas treatment upgrade project and is in the execution stage. The local government unexpectedly issues stricter emission standards than before. To ensure the project complies with the new standards, what should the project manager do INITIALLY?

    Show answer and explanation

    Correct answer: D

    The project is in execution and the government unexpectedly issues a stricter emission standard. You must decide what the project manager should do “initially.”

    The new standard is an external enterprise environmental factor, and the project can only comply with it. The first step on such an external change is to understand its effect on the project: assess with the team what the new standard does to scope, schedule, cost and quality, and then decide on that basis whether a change is needed and how to adjust the plan. The question asks for the “initial” action, and keeping to that limit makes it clear that the assessment must come before the change. The answer is D.

    Why the other options are wrong

    • A. Regardless of whether the regulatory change was previously recorded as a potential risk, merely checking the risk register does not assess its actual effect on the project and therefore is not the best initial action.
    • B. A change request has to say what is to be changed, and that is known only after the effect has been assessed. Submitting a change request comes after the assessment and is not the initial action.
    • C. The project side cannot postpone the effective date of the new standard on its own, and seeking an extension before the effect has been assessed is not the first action either. First confirm the requirements that apply and assess the impact.

    Key takeaway When an external regulation changes, first assess the impact with the team, and then decide on a change; do not go straight to a change request or negotiation.

    Variation If “initially” were changed to “after the impact has been assessed,” the next step would be to draft a change request in accordance with the change management plan and submit it to the authorized person or change control board (B); stakeholder consultation may help refine the response but does not replace formal approval. If the government standard were replaced by a change in the customer's own acceptance requirements, the approach would still be to assess the impact first and then go through change control.

  45. Question 45

    A food-ordering mini-app team finishes its first Sprint and holds the review. Stakeholders say that the work delivered contains clearly more technical features than business features. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    A food-ordering mini-app team finishes its first Sprint and holds the review. Stakeholders say the delivery has clearly more technical features than business features. The question is what the project manager should do.

    Having more technical than business features may indicate that the makeup or ordering of the backlog needs adjustment, but it may also reflect necessary technical dependencies. Before the next Sprint Planning, the project manager should review and refine the Product Backlog with the Product Owner, verify the value and dependencies of the technical work, and adjust ordering based on value, importance, dependencies and constraints. This addresses the stakeholder feedback before planning. The answer is B.

    Why the other options are wrong

    • A. The Daily Scrum is a short meeting for syncing the day's plan and obstacles. It is not the place to discuss the structure of the list.
    • C. Waiting for the planning meeting to have the Product Owner explain the proportions is too late. Planning time should go to the Sprint Goal, the selected work and how to deliver it, so the list should be refined beforehand.
    • D. The Sprint Retrospective is about how the team works and how it improves, not about the content and priority of the backlog.

    Key takeaway If the makeup of the backlog is out of balance, refine it with the Product Owner before planning, not at planning or at the Sprint Retrospective.

    Variation If the technical work really is a prerequisite for the business features, explain the dependency to stakeholders and tie the technical stories to business value when ordering.

    Reference Product Backlog and Increment · Lesson 2: Backlog Refinement, Definition of Ready and the Sprint Backlog

  46. Question 46

    You are organizing a Sprint Review with the customer attending. What is the purpose of this meeting?

    Show answer and explanation

    Correct answer: D

    A customer attends the Sprint Review. The question asks about the purpose of the meeting. The point is that the review is oriented to value, not to estimating or improvement.

    The Sprint Review is held near the end of a Sprint so that the Scrum Team and key stakeholders can inspect the Sprint outcome and progress toward the Product Goal, then determine useful adaptations based on the results, feedback, and changes in the environment. The Product Backlog may be adjusted accordingly, but the review is not a formal acceptance gate. The customer's attendance indicates collaboration about value and what to do next. The answer is D.

    Why the other options are wrong

    • A. Story point estimates are the Developers' responsibility. They are not something the review checks, and the customer does not need to check them.
    • B. Story size is a matter for backlog refinement and estimating. The review is concerned with whether the results have value.
    • C. Improving delivery methods and development approach is the content of the Sprint Retrospective, which is the team's internal reflection.

    Key takeaway At the review, the Scrum Team and key stakeholders inspect the Sprint outcome, discuss value, and determine future adaptations; improving how the team works is left to the Sprint Retrospective.

    Variation If the customer raises a new requirement at the review, the Product Owner records it in the Product Backlog and orders it, rather than adding it to the current Sprint at once.

    Reference Scrum Events · Lesson 4: The Sprint Review

  47. Question 47

    A team spread across several locations has delivered a project successfully. The project manager wants to collect feedback from all members as quickly as possible and run a statistical analysis. Which method should be used?

    Show answer and explanation

    Correct answer: D

    The project has been delivered successfully and the team is dispersed. The question asks which method to choose to collect all members' feedback quickly and run a statistical analysis.

    Three conditions decide the answer: “as quickly as possible” calls for fast distribution and collection, “all members” calls for broad coverage, and “statistical analysis” calls for a uniform format and quantifiable results. A survey can be sent to everyone at once, and standardized questions are easy to tabulate and calculate, which suits dispersed respondents especially well. The other methods either reach only some of the people or give results that are hard to quantify, so they do not meet the statistical analysis requirement. The answer is D.

    Why the other options are wrong

    • A. A video conference yields spoken, unstructured feedback that is hard to tabulate uniformly, and coordinating time across several locations is inefficient.
    • B. A focus group usually involves only some representatives, so it cannot cover all members; its results are mainly qualitative and are hard to turn into statistics quickly.
    • C. Email feedback has no uniform format and varies in length, so it needs a lot of sorting after collection and is not convenient for direct statistical analysis.

    Key takeaway To collect quantifiable feedback quickly from a dispersed team, use a survey questionnaire.

    Variation If you need to understand the reasons behind a disputed issue in depth, interviews or a focus group are usually more suitable; a questionnaire is especially useful for collecting quantifiable opinions quickly but can also include open-ended questions.

    Reference Lessons Learned · Lesson 4: Continuous Improvement: Retrospectives, PDCA, and Embedding Learning in the Organization

  48. Question 48

    For the same batch of work, assuming the usual risk allocation for each contract type and no special provisions such as an additional cost cap, under which type of contract does the buyer bear the greatest cost risk?

    Show answer and explanation

    Correct answer: A

    A comparison, from the buyer’s side, of how the cost risk is borne under different contract types.

    Under the stem’s assumption of usual risk allocation and no special provisions such as an additional cap, compare cost risk from the buyer’s side. Under a cost-reimbursable contract the buyer reimburses the seller’s actual cost, so cost-overrun risk lies mainly with the buyer, who therefore has the greatest risk. Under a firm fixed-price contract the price is fixed and the buyer’s risk is lowest; a fixed price incentive fee contract has a ceiling price; uncapped time and materials sits in the middle and usually exposes the buyer to less risk than cost-reimbursable. The answer is A.

    Why the other options are wrong

    • B. Under a firm fixed-price contract the price is fixed and the seller bears cost overruns, so the buyer’s risk is lowest.
    • C. A fixed price incentive fee contract has a ceiling price, and beyond the point of total assumption (where the price reaches the ceiling) the price stays at the ceiling and the overrun falls entirely on the seller, so the buyer’s payment has an upper limit.
    • D. Under time and materials the buyer pays for actual hours and materials. Under the stem’s assumption that no additional cost cap applies, its risk usually lies between fixed-price and cost-reimbursable contracts, and the buyer bears less risk than under a cost-reimbursable contract.

    Key takeaway Under a cost-reimbursable contract the buyer bears the risk; under a fixed-price contract the seller bears it; time and materials is in the middle.

    Variation If the question asked where the seller bears the greatest cost risk, the answer would be a firm fixed-price contract; if it asked what gives the buyer the most certain budget, that would also be a firm fixed-price contract.

  49. Question 49

    On a supplier contract for an outdoor billboard installation project, the two sides see the result of performing several clauses differently. The project team believes it followed the clauses strictly; the supplier believes the requirements were not met. The two sides have not yet communicated formally, and each holds its ground. To keep the situation from escalating, which method should the project manager use FIRST to resolve the dispute?

    Show answer and explanation

    Correct answer: A

    On a project, the two sides see the result of performing contract clauses differently and have not yet communicated formally. The question asks which method to use first to resolve the dispute.

    The usual first step is direct negotiation by the two parties (PMBOK 8 Appendix X4 defines negotiation as direct discussions between parties to resolve disputes without third-party intervention). If negotiation fails, consider, under the contract's dispute resolution clause, mediation, a dispute review board or other methods that involve a neutral third party, or the more formal arbitration. Litigation is the last option when all other means are exhausted. Negotiation is direct, efficient and confidential, and it preserves the working relationship, so negotiate first. The answer is A.

    Why the other options are wrong

    • B. Arbitration is a more formal procedure, and whether and when it is used depends on the contract's dispute resolution clause. Here the two sides have not formally communicated, so they should not skip direct negotiation and proceed immediately to arbitration.
    • C. Litigation is the last resort and is considered only after all other means have failed. It cannot be the first move.
    • D. Mediation brings in a neutral third party and is usually used under the contract after direct negotiation fails. Here the two sides have not formally communicated, so going to a third party and skipping direct negotiation is premature.

    Key takeaway For a dispute, negotiate directly first; if that fails, consider mediation or other methods with a neutral third party, or arbitration, as the contract provides. Litigation is the last choice.

    Variation If the stem says the two sides have negotiated several times without result, the next step, as the contract provides, can be mediation, a dispute review board or another method with a third party. If the question asks about having an independent expert decide a technical or financial issue, that is expert determination.

  50. Question 50

    At the current pace it will take several more Sprints to complete the currently forecast product scope, because some items fail to meet the product's Definition of Done and are returned to the Product Backlog. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    At the current pace, completing the currently forecast product scope will take several more Sprints because some items do not meet the product's Definition of Done and are returned to the Product Backlog. The question asks what the project manager should do. The key is whether the problem lies in conformance to the established standard or in the standard itself.

    The problem is that the team did not bring items up to the established standard, so at the end of the Sprint they were not done. Strengthening conformance to the Definition of Done so that items meet the standard before the Sprint ends can prevent repeated returns. The stem says the items fail to meet the product's Definition of Done, which means the standard exists but was not met in execution. The answer is B.

    Why the other options are wrong

    • A. Handling the changes in the next release only pushes the problem back, and unfinished work keeps piling up.
    • C. The stem is explicit that the product's Definition of Done was not met. The problem is conformance to the established Definition of Done, not unclear acceptance criteria.
    • D. Lengthening the Sprint breaks the fixed rhythm of agile and treats the symptom, not the cause.

    Key takeaway When items keep being sent back, first enforce the Definition of Done properly. Do not change the timebox.

    Variation If items are sent back because the acceptance criteria are unclear, go back to the acceptance criteria. The difference is at which level the problem lies. Also use the Sprint Retrospective to find which standards are most often missed and analyze why.

    Reference Definition of Done · Lesson 2: The Definition of Done and Quality

  51. Question 51

    A Scrum team makes both of its backlogs and its work progress fully public, so any team member or stakeholder can view them at any time. Which Scrum value does this mainly reflect?

    Show answer and explanation

    Correct answer: C

    A Scrum team makes both backlogs and its progress fully public, available to any team member or stakeholder at any time. The question asks which value this mainly reflects.

    The Scrum values are Commitment, Focus, Openness, Respect and Courage. The key signals are “fully public” and “can be viewed at any time”: being transparent about work and progress corresponds to Openness. Making information public also supports the three pillars of transparency, inspection and adaptation. It is the precondition for the pillar of transparency: what cannot be seen cannot be inspected or adapted. The answer is C.

    Why the other options are wrong

    • A. Commitment means being willing to commit to goals and support each other. It is about responsibility, not about whether information is public.
    • B. Focus means putting your mind and abilities into the work you have committed to. It is about the degree of dedication, whereas the stem is about how open the information is.
    • D. Courage means having the courage to do the right thing and face hard problems. Making a list public is not in itself facing a hard problem, so it should not be filed under Courage.

    Key takeaway Openness = work and progress are transparent to the relevant parties.

    Variation If the stem said that the Developers set aside other matters and went all out on the items selected for the Sprint, the answer would be Focus. If it said the team proactively exposed a serious defect, it would lean toward Courage.

  52. Question 52

    As Scrum Master you lead a team developing an e-commerce website. The fourth Sprint is about to end, and you notice a problem in the way the team handles code commits that will keep affecting the stability of the code. What is the BEST way to bring the problem up and work with the team to find a solution?

    Show answer and explanation

    Correct answer: D

    The fourth Sprint is about to end, and the Scrum Master notices a problem in how the team handles code commits that will continue to affect code stability. The question asks how to bring it up and solve it together with the team.

    This is a problem with the team's own way of working and falls within inspect and adapt. The Sprint Retrospective is the event used to inspect the last Sprint, analyze causes, and plan ways to increase quality and effectiveness. The most impactful improvements are addressed as soon as possible and may be added to the next Sprint Backlog. The answer is D.

    Why the other options are wrong

    • A. Assess and Implement Changes is used for project changes that require formal management. Here, the team is inspecting and improving its own way of working, with no indication that a controlled baseline or governance requirement is affected, so analyzing it first in the Sprint Retrospective is more appropriate.
    • B. Showing the team organizational process assets from other projects only offers material. It does not lead the team to analyze and solve the current problem directly.
    • C. The Product Owner is responsible for the backlog and for value. The team's way of working should be discussed and improved by the team itself, so going to the Product Owner is not the most direct and effective route.

    Key takeaway A continuing problem in the team's process: analyze it with the team at the Sprint Retrospective and make an improvement plan.

    Variation If the problem is “the customer rated the Increment poorly”, look to the Sprint Review and reorder the backlog accordingly. If it is “an impediment blocked a member today”, surface it at the Daily Scrum and discuss it afterward.

  53. Question 53

    A company takes on an outdoor music festival stage construction and operations project. During planning, the project manager identified “heavy rain” as a high risk, recorded it in the risk register and set aside matching funds in the cost baseline. On the eve of the event, heavy rain does arrive and extra drainage and protection costs are needed. Which reserve should this cost come from?

    Show answer and explanation

    Correct answer: D

    In a predictive project, “heavy rain” was recorded in the risk register long ago and matching funds were set aside. On the eve of the event heavy rain does arrive. Which reserve pays the extra cost?

    The key signals are “identified during planning”, “recorded in the risk register” and “set aside matching funds in the cost baseline”. This is an identified known risk, and the matching funds are the contingency reserve inside the cost baseline, which the project manager releases under the risk response plan and the authorization procedure the organization specifies. The reasoning path for this type of question is: first see whether the risk was identified in advance and a response strategy made; if so, it corresponds to contingency reserve inside the baseline; if not, consider management reserve. The answer is D.

    Why the other options are wrong

    • A. Schedule reserve is a time buffer set aside for schedule risks. It is not a source of funds and cannot pay for drainage and protection.
    • B. Management reserve is for unidentified risks (unknown-unknowns). Heavy rain was identified long ago, so management reserve should not be used.
    • C. Additional budget requires a change and is considered only when the reserve is not enough. Contingency reserve has already been set aside here, so no additional budget is needed.

    Key takeaway When an identified risk occurs, the money is spent from contingency reserve; only an unidentified risk uses management reserve.

    Variation If an earthquake occurred, an event nobody had identified, you would go through change control to release management reserve.

    Reference Cost Baseline and Reserves · Lesson 2: Contingency Reserve vs Management Reserve: Where the Money Comes From and Who Approves It

  54. Question 54

    A project team is designing a new interactive feature for an online-education app. Members widely fear that if a new approach fails they will be blamed, so they stick to what they have done before. The project manager wants to encourage innovation. What should the project manager do?

    Show answer and explanation

    Correct answer: D

    A project team designing a new interactive feature for an online-education app fears being blamed if a new approach fails, so it only follows past practice. The question asks what the project manager should do to encourage innovation.

    Members do not dare try because they worry that failure will be held against them. Building an empowered culture requires a sense of safety for the team. The project manager should allow small-scale experiments and soften the consequences of failure, so that members can try boldly in a controlled environment, and treat the results of experiments as learning opportunities. This protects the project and really encourages innovation. The answer is D.

    Why the other options are wrong

    • A. Criticizing the team publicly in the meeting and forcing everyone to submit an idea adds pressure, and the ideas that come in will mostly be token ones, not real innovation.
    • B. Staying with the old solution and leaving innovation for the next project avoids the problem and does not address why members dare not try.
    • C. Replacing the members who worry about failure treats a cultural problem as a staffing problem. It damages the trust of the existing members and still cannot make the whole team willing to try.

    Key takeaway To encourage innovation, first lower the cost of failure: allow small-scale experiments and create a safe atmosphere.

    Variation If an experiment would touch a compliance or safety red line, it must not be tried; verify it in a controlled sandbox or pilot environment instead.

    Reference Project Management Principles · Lesson 3: Build an Empowered Culture; Principles, Performance Domains and the Seventh Edition

  55. Question 55

    A company is evaluating an internal platform project. It requires an investment of $150,000 and has an 8-month delivery period. From month 9 onward it is expected to bring in a net cash inflow of $25,000 per month. Calculated as a static payback period (counted from the start of the project), what is the project's payback period in months?

    Show answer and explanation

    Correct answer: B

    This question involves calculating a static payback period. The key is that the payback period is counted from the start of the project, not from the day income begins.

    The static payback period is the time needed to recover the initial investment from the project's net cash inflows, without discounting. Cash inflows start only in month 9, so the payback period must include the first 8 months of the delivery period, plus the number of months needed after cash inflows begin to recover the $150,000. The answer is B.

    1. Time to recover the investment after income begins = 150,000 ÷ 25,000 = 6 months
    2. Add the 8-month delivery period before income begins
    3. Payback period = 8 + 6 = 14 months
    4. Check: cumulative income at the end of month 14 = 6 × 25,000 = $150,000, equal to the investment, so the answer is B

    Why the other options are wrong

    • A. 6 months counts only the recovery time after income begins and leaves out the first 8 months of delivery.
    • C. 8 months is only the delivery period. At that point the project has just begun to produce income and recovery of the investment has not yet started.
    • D. 15 months double counts a month, for example counting month 9 as a separate month and then adding the 6 months of recovery. In fact months 9 through 14 are themselves exactly those 6 months of income.

    Key takeaway When there are no inflows during construction and payback is measured from project start, static payback period = construction period + investment ÷ net cash inflow per period.

    Variation If the delivery period were cut to 5 months, payback = 5 + 6 = 11 months. If monthly net cash inflow fell to $20,000, payback = 8 + 150,000 ÷ 20,000 = 15.5 months.

  56. Question 56

    At Sprint Planning, a team using Scrum broke the selected stories into tasks, members picked them up, and the team recorded them as agreed in a shared artifact that is continuously updated during the Sprint. Near the end of the Sprint, the original Product Owner is reassigned and a new Product Owner takes over. He wants to know which tasks one feature was broken into and who picked them up, and would like to consult this ready-made record. Where should he get this information?

    Show answer and explanation

    Correct answer: A

    In a Scrum project, near the end of the Sprint, the new Product Owner wants to see which tasks a feature was broken into and who picked them up, and wants a ready-made record. The question is where to get it.

    PMBOK 8 describes the iteration backlog (the Sprint Backlog in Scrum) as containing selected user stories and the tasks required to complete the work for the current Sprint, and it is updated continuously during the Sprint. The stem also says the team recorded the tasks and who picked them up in a shared artifact that is continuously updated during the Sprint, so that record is the Sprint Backlog, which may be represented on a task board. Scrum itself does not require assignees to be recorded. The new Product Owner can consult it directly. The answer is A.

    Why the other options are wrong

    • B. The Daily Scrum is an oral sync, not a ready-made record, and the next one may not even touch this feature.
    • C. The Product Backlog orders the work needed for the whole product, but it is not the artifact the team agreed to use for recording this Sprint's tasks and who picked them up.
    • D. Each member's own records are scattered, in different formats, not necessarily complete, and not an artifact shared by the team, so they are less direct than the Sprint Backlog.

    Key takeaway If the team has agreed to record the task breakdown and who picked up each task in the Sprint Backlog, consult that backlog; Scrum itself does not require assignees to be recorded.

    Variation If the question is which requirements of the whole product are still undone and in what order, the answer becomes the Product Backlog. If it is what was finished in this Sprint, look at the Increment.

  57. Question 57

    A project manager is responsible for a project delivered to a strategic customer. While verifying resource availability in a matrix organization, the project manager finds that a key person has already been moved to another project inside the company and confirms that this will jeopardize the planned project start. What action should the project manager take NEXT?

    Show answer and explanation

    Correct answer: B

    The organization is a matrix, and the project is delivered to a strategic customer. While verifying resource availability, the project manager finds that a key person has already been moved to another project in the company and confirms that this will jeopardize the planned project start. The question asks what the project manager should do next.

    In a matrix organization, the project manager usually needs to negotiate with the functional manager who has the authority to manage or assign the person; the specific authority depends on the type of matrix and the governance arrangements. On finding that a key person has been moved, the project manager should proactively acquire the resource, and the first step is to negotiate with his functional manager to try to get him back, explaining how important this person is to a strategic customer's project. Consider other options only if negotiation fails. The answer is B.

    Why the other options are wrong

    • A. When there is a resource problem, you first have to resolve the resource problem, not directly push back the project start. Pushing back means giving up the initiative and would affect the strategic customer.
    • C. The authority of a project management office depends on the organization's governance arrangements. The stem does not say it has the authority to assign this person, and in a matrix organization the functional manager is usually the first party to negotiate with; asking the PMO to reassign him is not the best choice.
    • D. Merely recording that the person has been moved in the risk register is passive recording. It takes no step to acquire the resource, and the problem remains.

    Key takeaway When a key person in a matrix organization is pulled away, negotiate with the functional manager to get him back first, and put other options later.

    Variation If after negotiation the functional manager cannot release him, communicate with the sponsor to coordinate or evaluate alternative resources; if the person pulled away was an external person, contact the supplier or the procurement department.

  58. Question 58

    The core team of a cross-border e-commerce platform redesign project has 4 people including the project manager. Halfway through execution, 1 member is reassigned to another project, and then 3 new members join. What happens to the number of potential communication channels within the core team?

    Show answer and explanation

    Correct answer: C

    The team has 4 people including the project manager; 1 leaves and 3 join, so people both leave and join. You must judge how the communication channels change, telling “increase to” from “increase by.”

    First calculate the net headcount, then apply n(n-1)/2, and finally subtract the earlier number from the later. Calculate once before and once after the change; the numbers among the options are intermediate results or typical mistakes in this process, so be clear whether the total or the increment is asked for. Only C is correct as worded: the increase is 15 - 6 = 9. The total after the change is 15, but “Increase to 15” is not offered; B writes 15 as an increase. The answer is C.

    1. Before the change: n = 4, channels = 4×3÷2 = 6
    2. Headcount after the change: 4 − 1 + 3 = 6
    3. After the change: n = 6, channels = 6×5÷2 = 15
    4. Change: 15 − 6 = 9, so channels increase by 9 (increase to 15)
    5. Check: going from 4 to 6 people adds 4 channels and then 5, 9 in all

    Why the other options are wrong

    • A. 6 is the number of channels before the change (and also happens to be the headcount after it). This treats a headcount or the original channel count as the result of the change.
    • B. 15 is the total number of channels after the change; it should be described as “increase to 15.” The option says “increase by,” which would also require subtracting the original 6.
    • D. 36 = 6×6, which squares n instead of calculating n(n-1)/2.

    Key takeaway Calculate the headcount after the net change first, then apply n(n-1)/2, and keep “increase to” and “increase by” apart.

    Variation If, after 1 person leaves and 3 join, the question asked “increase to how many,” the answer would be 15. If 2 leave and 1 joins, n = 3 and there are 3 channels, a decrease of 3.

  59. Question 59

    While reviewing quotes, the project manager finds that one seller’s quote is far below the independent cost estimate the buyer prepared in advance. Each of the following could be a cause of this difference EXCEPT which one?

    Show answer and explanation

    Correct answer: A

    While reviewing quotes, the project manager finds one seller’s quote far below the buyer’s independent cost estimate. Each option could cause the difference; note that the question asks which one does not.

    The independent cost estimate is the buyer’s advance estimate of a reasonable price, used as a reference for evaluating quotes. PMBOK 8 says the procurement management plan should determine whether independent estimates will be used and whether they are needed as evaluation criteria. When a quote differs markedly from the estimate, the usual reading is that the statement of work is deficient or unclear, or that the seller misunderstood it or did not fully respond to it. But “whenever it wins, the buyer is certain to save a great deal” cannot be concluded. So A is not a cause, and A is the answer.

    Why the other options are wrong

    • B. If the seller misunderstood the requirements for the deliverable, it prices on the wrong understanding and its quote departs from the estimate. This is a possible cause.
    • C. If the seller did not fully respond to the requirements and left out some of the work, its quote is naturally low. This is a possible cause.
    • D. If the statement of work is deficient or ambiguous, different readings produce different prices. This is a possible cause.

    Key takeaway When a quote differs a lot from the independent estimate, first find the cause; a low price does not necessarily mean savings.

    Variation If a quote is far above the estimate, the cause could likewise be an ambiguous statement of work, a risk premium added by the seller, or a wider understanding of the scope.

    Reference Make-or-Buy Analysis and Procurement Planning · Lesson 3: Bid Documents, the Statement of Work and the Independent Cost Estimate

  60. Question 60

    The team rules that no stage of the workflow may have more than a set number of work items in progress at the same time, so that inefficiencies show up earlier within a cycle. What is this practice called?

    Show answer and explanation

    Correct answer: B

    There is a rule that no stage of the workflow may have more than a set number of work items in progress at once, so that inefficiencies show up earlier within a cycle. What is the name of this practice?

    Work in progress (WIP) is the work items in the process that have been started but not finished. Putting a cap on the number of items in each stage is limiting WIP: once a stage is full, no new work is pulled in, the team is forced to focus on finishing what it has, and inefficiencies are easier to see. The two signals in the stem, “no more than a set number” and “inefficiencies show up earlier”, both point to it. The answer is B.

    Why the other options are wrong

    • A. Swarming is several team members concentrating on the same problem or work item. It is not a cap on quantity.
    • C. Pair programming is two programmers writing code together. It has nothing to do with the number of items in progress.
    • D. Continuous integration is merging work into the whole frequently and retesting it. It also has nothing to do with a limit on work in progress.

    Key takeaway Capping the number of work items in each stage is limiting work in progress.

    Variation If the stem said “a column is near its limit and members work together to help whoever is slowing the flow”, the answer would change to swarming. If it asked how to estimate the average time, use Little's Law: items in the system ÷ throughput (WIP only gives cycle time; include the queue for lead time).

  61. Question 61

    A community elder-care service platform is being built using a predictive approach. Baselines have been established, execution is halfway through, and the customer has formally accepted the deliverable's quality standard. Then a new standard issued by a government agency may have a major impact on the project, and the deliverable must be modified to meet the new quality standard. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    Execution is halfway through, the quality standard has been accepted by the customer, and a new external standard requires the deliverable to be modified. This is a change triggered by an external change.

    A new government standard is an external enterprise environmental factor that must be complied with. The project has baselines and the customer has formally accepted the quality standard, so modifying it requires first assessing the impact on scope, schedule, cost and so on and then submitting a change request, handled through Assess and Implement Changes and implemented once approved by those with the authority (if it also affects the scope, schedule or cost baselines, it is also a baseline change). The project manager cannot change a baseline on their own. The answer is B.

    Why the other options are wrong

    • A. An independent review process is for managing and controlling quality against the new standard. That work comes after the standard update is approved; it is not the first step now.
    • C. Recording it in the lessons learned register and telling senior management can be done, but it does not replace assessing the impact and submitting a change request.
    • D. Training can be a supporting measure, but it does not replace the impact assessment and the change request. If the training itself requires changing controlled plans or affects a baseline, carry it out after the relevant change is approved.

    Key takeaway When a new government standard requires changing accepted, controlled content: assess the impact first, then submit a change request.

    Variation If the project manages work with a product backlog, the same new rule can be handled by reordering backlog items after assessing the impact. If it affects controlled artifacts or an approved baseline, or governance rules require approval, a change request is still needed.

  62. Question 62

    A custom software project is in execution. At the monthly progress review, the project manager finds that an identified risk in the risk register, “the client's test environment may not open on time,” which has a response plan and an assigned risk owner, has become a real issue. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    In a custom software project, an identified risk with a response plan and an assigned owner, “the client's test environment may not open on time,” has become a real issue. The question asks what the project manager should do.

    The stem says the identified risk has a response plan and an owner. Once the risk occurs, the agreed response plan should be carried out. In implementing risk responses, the project manager works with the risk owner and relevant stakeholders to put the plan into effect, and also records the issue in the issue log and tracks it. The emphasis is on executing, not on discussing again. The answer is A.

    Why the other options are wrong

    • B. Scheduling a high-priority meeting to discuss how to handle the issue means renegotiating. The response was decided when responses were planned; the task now is to execute it.
    • C. Brainstorming solutions with the team and client is again a search for solutions. When an identified risk occurs, acting on the agreed response is faster.
    • D. A change request to draw on management reserve is not the right step. Management reserve is for unknown-unknown risks. This is an identified risk, so funding comes from contingency reserve and this step is not needed.

    Key takeaway When an identified risk becomes an issue, work with the owner and stakeholders to execute the risk response plan.

    Variation If the environment still cannot open on time after the response and the baseline must change, only then raise a change request; if the original response plan proves insufficient, add to or revise the response.

    Reference Monitor Risks · Lesson 5: When a Risk Occurs: Reserves, the Issue Log and Workarounds

  63. Question 63

    At a Daily Scrum, a developer mentions that he is stuck on a technical impediment, and several other members immediately start discussing how to solve it. What should the Scrum Master do at this point?

    Show answer and explanation

    Correct answer: D

    At a Daily Scrum, a developer says he is stuck on a technical impediment and several others immediately begin discussing solutions. The question asks what the Scrum Master should do.

    The daily coordination meeting is brief and focused (PMBOK 8: typically no more than 15 minutes) and is for stating obstacles, not for detailed technical discussion in the meeting. The details of a technical impediment take up a lot of time and leave the other members waiting. The Scrum Master should suggest pausing the discussion, note the impediment, carry on with the meeting, and have the people concerned work it out afterward. The answer is D.

    Why the other options are wrong

    • A. Letting everyone discuss until a solution is found breaks the timebox and the rules of the meeting, and crowds out the other members' synchronization.
    • B. Explaining the meaning of the meeting again does not solve the problem of the discussion eating time and does nothing to correct the situation at hand.
    • C. Stopping the whole meeting is too abrupt, since other members have not yet finished synchronizing. First pause the discussion and continue the meeting, and work it out afterward.

    Key takeaway The Daily Scrum focuses on progress and impediments, and detailed discussion is taken offline for after the meeting.

    Variation If a member mentions at the meeting that a major risk has been identified, the handling is the same: say it at the meeting, take the details to a separate session afterward, and do not discuss it on the spot or leave it to the Sprint Review.

  64. Question 64

    A team manages its development process with a kanban board. The Test column has a WIP limit of 3 and already has 3 items in testing, and the Development column has just finished another item. The team wants to improve flow by addressing the bottleneck. What should it do NEXT?

    Show answer and explanation

    Correct answer: B

    A team manages its development process with a kanban board. The Test column has a WIP limit of 3 and already has 3 items in testing, and Development has just finished another item. To improve flow by addressing the bottleneck, what is the right next step?

    Kanban uses WIP limits to control the work under way so that bottlenecks become visible and the team concentrates on dealing with and easing them. A full Test column means the bottleneck is in testing, and nothing more can go in. The team should hold off on putting in new items, concentrate on finishing the work in testing, and pull in the next item once a space opens. The answer is B.

    1. The Test column limit is 3 and 3 items are in testing: 3 − 3 = 0 open slots.
    2. Development has just finished 1 item. It needs an open slot to enter testing, and there is none, so this item can only wait in the Development done area.
    3. Only when testing finishes 1 item does a slot open, and only then can the next item be pulled in. So the team should put its effort into finishing the work in testing.
    4. Check: if the item were forced in, the Test column would hold 4 items, over the limit of 3, which violates the WIP limit.

    Why the other options are wrong

    • A. Raising the limit only hides the bottleneck. More work in progress slows overall flow.
    • C. If developers keep starting new items, work waiting for testing will keep piling up and the bottleneck gets worse.
    • D. Removing the WIP limits throws away the means Kanban gives for exposing and eliminating bottlenecks.

    Key takeaway When the WIP limit is reached, clear the bottleneck first. Do not keep putting work in.

    Variation If the stem said the Test column had only 1 item, there would be 3 − 1 = 2 open slots, and the item Development finished should be pulled in. If the upstream pile-up continues, developers can go and help with testing (swarming).

  65. Question 65

    A city plans to build a new waste-to-energy incineration plant, which once built will reduce dependence on external waste treatment facilities. The project manager has the support of several district leaders, but some resident representatives and some people in the city argue that the project should be halted and replaced with a program of waste sorting and recycling. Which stakeholders should the project manager include in the stakeholder engagement plan?

    Show answer and explanation

    Correct answer: D

    On a waste-to-energy plant project in a city, the district leaders support it, while resident representatives and some others oppose it. The question asks which stakeholders the engagement plan should include.

    A stakeholder is an individual, group or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a portfolio, program, or project. Identification and engagement must cover those inside and outside the organization, including supporters, neutrals and opponents. The stem sets support and opposition side by side, and the key is “do not pick and choose”: the criterion for inclusion is whether they may affect, be affected by, or perceive themselves to be affected by the project, regardless of their attitude and regardless of who designated them. The resident representatives and others who want the project halted are on the list as well. So the plan should cover all the identified stakeholders who may affect, be affected by, or perceive themselves to be affected by the project. The answer is D.

    Why the other options are wrong

    • A. Stakeholders are defined by their relationship to the project, not designated by the sponsor. Choosing people only by the sponsor's wishes leaves out those the sponsor did not think of or does not want to face.
    • B. Supporters only leaves out the neutrals and the opponents. Later resistance often comes from opponents who were not managed, and supporters' support also needs to be maintained.
    • C. Opponents only is equally incomplete. Supporters and neutrals also need to be engaged and communicated with, or their support will drain away over time.

    Key takeaway The engagement plan does not pick and choose: every identified stakeholder who may affect, be affected by, or perceive themselves to be affected by the project must be considered, and opponents in particular must not be left out.

    Variation Including only high-power stakeholders would be just as incomplete: residents and users with low power and high interest also have to be managed, only with a different intensity. Only when the question asks “who to manage closely” do you answer by layering on power and interest.

  66. Question 66

    The president of a corporation complains about project communication: each week he receives five project reports by email, has no time to read each one, and the content has nothing to do with what he cares about, so he cannot tell the project's status. What should the project manager do first?

    Show answer and explanation

    Correct answer: C

    The president receives five project reports by email every week, cannot tell the status and finds the content irrelevant. The question asks what the project manager should do first.

    Focus on “first”: work out whether the problem lies in the plan or in execution. The communications management plan records the information content, frequency and method agreed for the president. By consulting it you can tell whether the plan itself is unreasonable or whether execution has deviated from the plan, and then confirm the needs with the president and adjust on a sound basis. Without this step, any change is a guess. The answer is C.

    Why the other options are wrong

    • A. Having the team agree the content and frequency for the president decides things on the team's own, bypasses the president, and has no plan to rely on, so it may still miss the mark.
    • B. The engagement plan deals with engagement levels and strategies. The president's complaint is about the number and content of reports, so checking the engagement level does not match the problem and is not the first document to look at.
    • D. Switching straight to one executive summary is a “solution” based on a guess. It checks nothing against the plan and does not ask what the president wants, so it may miss again.

    Key takeaway When a stakeholder is dissatisfied with the frequency or content of communication, first go back to the communications management plan and check what was agreed.

    Variation If the check shows the plan said a monthly summary, the problem is that execution deviated, and you should correct the execution rather than change the plan.

    Reference Plan Communications Management · Lesson 5: The Communications Management Plan: Contents, Use and Updates

  67. Question 67

    A food company plans to upgrade its cold storage management system. After assessing its internal capabilities, it finds that no one in-house has the necessary skills and decides to outsource. The project manager is now putting together a document that spells out what functions the system must have, what the performance measures are and when it is due, so that interested suppliers can judge whether they can take the job on. Which of the following is this document?

    Show answer and explanation

    Correct answer: C

    The project has decided to outsource and is in the sourcing planning stage. The question asks which deliverable the project manager is preparing.

    The signals: outsourcing has been decided; the document states functions, performance measures and delivery time; its purpose is to let suppliers judge whether they can take the job on. This is the statement of work: prepared for this procurement from the scope baseline, it describes the product, service or result to be procured in enough detail for a seller to judge whether it can supply it, and it ends up incorporated into the agreement. The answer is C.

    Why the other options are wrong

    • A. Make-or-buy analysis happens before the decision to outsource and decides whether to do the work in-house or outsource it. Here outsourcing has already been decided.
    • B. The procurement management plan guides how procurement is carried out. It is not a detailed description of the item procured.
    • D. Bid documents ask sellers for proposals and are issued after the statement of work is prepared, and they contain it.

    Key takeaway Once outsourcing is decided, spell out what is being bought in a statement of work.

    Variation If the stem said “decide whether to do it ourselves or outsource”, that would be make-or-buy analysis; “a document asking sellers for proposals” would be bid documents; “how procurement is carried out” would be the procurement management plan. The “management plan” option describes how to procure, not what to procure, and this is the most common confusion.

  68. Question 68

    In the planning stage of a software migration project, a response has been drafted for a high-priority threat, but estimates show that implementing it costs more than the loss the risk would cause if it occurred. Looking only at costs and benefits that can be expressed in money, what should the project manager do?

    Show answer and explanation

    Correct answer: D

    A software migration project is planning risk responses. A response has been drafted for a high-priority threat, but estimates show that it costs more to implement than the loss if the risk occurs. The question asks what the project manager should do.

    A risk response must be cost-effective. Looking only at costs and benefits that can be expressed in money (common exam practice), what is spent on a response should be less than the loss it avoids. The original response costs more than it avoids, so it is not worthwhile and should not be carried out. The right approach is to use alternative analysis and cost-benefit analysis to compare other response options and pick the one with the best cost-benefit, that is, a response cost lower than the loss avoided. The threat is high priority, so active options should be compared fully first; the answer is to change the response, not to give up or escalate. If no option is feasible or worthwhile, active or passive acceptance is still possible. The answer is D.

    Why the other options are wrong

    • A. Implementing a response that costs more than the loss it avoids defeats cost-effectiveness, and the management reserve is held for unknown risks, not to pay for an uneconomic response.
    • B. Falling back to passive acceptance for a high-priority threat without comparing options amounts to giving up on an active response. Acceptance is considered only when no cost-effective option can be found after a thorough search.
    • C. The threat is not beyond the project's scope or the project manager's authority, so there is no reason to escalate, and escalating would not solve the problem that the response is uneconomic.

    Key takeaway Response cost should not exceed the loss avoided. If a response is uneconomic, change it, and compare options with cost-benefit analysis.

    Variation Only if every option is infeasible or not worthwhile does acceptance come in: active acceptance means establishing a contingency reserve, while passive acceptance only records the risk and reviews it periodically.

  69. Question 69

    On a Scrum team, who is mainly responsible for guiding the team in using Scrum and clearing the impediments the team meets?

    Show answer and explanation

    Correct answer: C

    The question asks who on a Scrum team is mainly responsible for guiding the team in using Scrum and clearing impediments. Each of the three roles has its own duties, so match them.

    The Scrum Master makes sure Scrum is understood and carried out and is a servant leader on the team, serving the Product Owner, the Developers and the organization by removing impediments and coaching the team to self-organize. “Guiding the team in using Scrum and clearing impediments” in the stem describes exactly this role. Compared with the other two roles, the Product Owner is accountable for value, the Developers are accountable for the Increment, and only the Scrum Master is accountable for Scrum taking hold. The answer is C.

    Why the other options are wrong

    • A. The Product Owner manages the Product Backlog and is accountable for its order and for value. The Product Owner is not the role that guides Scrum practice and clears impediments.
    • B. A functional manager manages people in the home department, is not part of the Scrum team and is not responsible for clearing the team's daily impediments.
    • D. The Developers have no titles inside the team and nobody ranks above anyone else. Seniority does not carry the duties of coaching and clearing impediments.

    Key takeaway The one who clears impediments and guards Scrum is the Scrum Master, who supports the team as a coach and servant leader. The Product Owner is accountable for value, the Developers for the Increment, and the Scrum Master for Scrum taking hold.

    Variation If asked “who decides the order of Product Backlog items”, the answer is the Product Owner. If asked “who turns the items into an Increment”, the answer is the Developers.

    Reference Scrum Roles · Lesson 2: The Scrum Master: Servant Leader

  70. Question 70

    In the planning stage, the project manager finds that company strategy puts great weight on environmental outcomes, but the project’s business case contains no sustainability goals and the sponsor has never confirmed any. The sponsor says the budget is tight and is unwilling to revise the business case. What is the MOST appropriate thing for the project manager to do now?

    Show answer and explanation

    Correct answer: D

    The project is in planning. Company strategy values environmental outcomes, but the business case has no sustainability goals, and the sponsor is unwilling to revise it because the budget is tight. The question asks what is the most appropriate thing for the project manager to do.

    The core basis for the judgment is the two conditions “not in the formal documents” and “the sponsor does not agree for now”. The Eighth Edition says sustainability goals should be included in formal project documents such as the business case and confirmed by the project sponsor, and that if they are not included, the project manager should still encourage discussions about their impact during meetings and among stakeholders. So the project manager neither gives up nor oversteps: keep discussing the impact, and work to have the goals included in the business case. The answer is D.

    Why the other options are wrong

    • A. Treating sustainability as out of scope and not raising it again leaves the related risks unmanaged, which goes against the requirement to keep discussing its impact.
    • B. Changing the scope statement and raising the budget baseline without the sponsor’s confirmation bypasses authorization and the change procedure. It is overstepping authority.
    • C. Waiting until closing to assess is too late. Sustainability runs through planning, execution and closing, and adding it to the lessons learned repository cannot make up for its absence in the early stages.

    Key takeaway Goals go into formal documents and are confirmed by the sponsor; if they are not included, keep discussing them in meetings and among stakeholders.

    Variation If the sponsor agrees, update the business case and obtain confirmation. As the project needs, the related key performance indicators can also go into the scope statement, project charter, contracts or other formal documents, and compliance can be monitored in later phases. If asked about the main challenges of integration, the answer is broader scope and complexity, risk from imbalance, and the lack of universal criteria.

  71. Question 71

    An agile team is developing an order management system for a logistics company, and the company's warehouse administrators will use it daily after delivery. During an iteration, the team wants to deliver the streamlined entry screen defined in the signed specification in the contract appendix. The administrator, on the customer's side, insists on keeping the original multi-level menus. The two sides are deadlocked over the contract terms and development cannot move forward. To resolve the standoff between team and customer, which value in the Manifesto should the team rely on MOST?

    Show answer and explanation

    Correct answer: D

    During iterative development, the team and the end user (a warehouse administrator on the customer's side) disagree about the entry screen. The team wants to deliver to the specification in the contract appendix, and the two sides are deadlocked over the contract terms until development stalls. The question asks which value in the Manifesto should be used to resolve it.

    First find the signal: the deadlocked parties are the team and the user, and the disagreement is about what the screen should look like, not a dispute about documents or process. The team wants to follow the signed specification while the user wants the original menus, so what has to be resolved is the standoff between the contract terms and the user's current needs. A disagreement like this cannot be settled by arguing over clauses. Let the user try it and give feedback, and you can find a solution both accept. This corresponds to “customer collaboration over contract negotiation”: keep collaborating with the customer rather than haggling over terms. The answer is D.

    Why the other options are wrong

    • A. “Working software over comprehensive documentation” addresses a contest between documents and software. Nobody in this question is asking for documents first.
    • B. “Individuals and interactions over processes and tools” addresses processes or tools that get in the way of people communicating. The problem here is not process or tools, and it is not poor communication within the team. It is that the team and the user on the customer's side see the product's form differently, which is resolved by involving the customer, letting them try it and give feedback, and that is customer collaboration.
    • C. The administrator's current preference differs from the signed specification, so the stem does contain a change signal. However, the question expressly asks how to resolve a team-customer standoff centered on contract terms, which maps most directly to “customer collaboration over contract negotiation”. “Responding to change over following a plan” does not address that collaboration-versus-contract conflict as directly.

    Key takeaway When the team and users disagree about the form of the product, rely on customer collaboration: let users try it and give feedback, not argue from the specification or negotiate.

    Variation If the customer raises a new feature midway and the team wants to finish the original plan first, that corresponds to “responding to change over following a plan”. If the team wants to spend a month writing the design documents before coding, that corresponds to “working software over comprehensive documentation”.

  72. Question 72

    On review, the project manager finds that the stakeholder engagement plan does not include several external consultants who recently joined the project, whose information is already recorded in the stakeholder register. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    On review, the project manager finds the stakeholder engagement plan does not include several external consultants who recently joined; their information is already in the register. The question asks what to do.

    The engagement plan should cover the stakeholders in the register who need to be managed. The consultants are already registered and have assessment information, which shows that identification and analysis have been done, and what is missing is that the plan has not kept up. PMBOK 8 says Plan Stakeholder Engagement develops strategies based on the identified stakeholders' needs, expectations, interests and potential impact. So update the engagement plan from the assessments in the register and bring the consultants in. The answer is A.

    Why the other options are wrong

    • B. Waiting passively for the consultants to get in touch makes the project lose the initiative. The purpose of the engagement plan is to plan proactively how to engage stakeholders.
    • C. External consultants have different stakes and expectations from internal team members. Managing them together cannot reflect targeted engagement strategies.
    • D. Putting all the consultants into low priority without analysis acts on assumption, and dealing with them only when problems appear misses the chance to engage them in advance.

    Key takeaway When the register changes, the engagement plan must keep up; do not let a newly added stakeholder drift outside the plan.

    Variation If the consultants had not been registered yet, you would first identify, assess and register them and then update the engagement plan.

    Reference Identifying and Analyzing Stakeholders · Lesson 4: The Stakeholder Register: What to Record and What to Do When a New Person Appears

  73. Question 73

    Which of the following statements about using recognition and rewards in a project is NOT correct?

    Show answer and explanation

    Correct answer: D

    Note that the question asks which statement is NOT correct. The content follows PMBOK 8's requirements on recognition and rewards, and each option must be checked against PMBOK 8.

    PMBOK 8 says that cultural differences influence how recognition and rewards are best delivered and that recognition should be tailored to cultural preferences. Intangible rewards could be equally or even more effective than money. A reward program should be meaningful and motivating for everyone. A good strategy for project managers is to give the team recognition throughout the project life cycle rather than waiting until the project is complete. Option D says that saving it all for the end is best, which is the opposite of PMBOK 8, so it is the incorrect statement. The correct answer is D.

    Why the other options are wrong

    • A. Cultural differences should be considered when choosing the form of reward, as PMBOK 8 states clearly. The statement is correct, so it cannot be chosen.
    • B. A reward that fits the recipient's motivations and needs is generally more motivating. This agrees with PMBOK 8's point that the rewards program should be meaningful and motivating for everyone. The statement is correct.
    • C. Beyond money there are intangible rewards such as growth opportunities, a sense of accomplishment and appreciation, and PMBOK 8 says they could be equally or even more effective. The statement is correct.

    Key takeaway Recognition and rewards run through the whole project and take account of individual needs and cultural background. They are not saved up for closing.

    Variation Other incorrect statements of this type include: rewards can only be money, everyone should get the same reward, and recognition is given only for the best performance. All should be judged wrong.

    Reference Team Performance · Lesson 3: Recognition and Rewards: Prompt, Specific, Matched to Needs

  74. Question 74

    An online education team is building a course platform in an agile way. During development, the project manager notices that the customer side keeps raising new requirements, one round after another. How should these requirements be handled?

    Show answer and explanation

    Correct answer: B

    An agile team is building a course platform, and the customer side keeps raising new requirements. The question asks how to treat them.

    New requirements go into the product backlog, where the product owner ranks them by value and priority, and they are pulled into an iteration at iteration planning. That embraces change, so valuable requests are considered, while keeping control of the current iteration's scope so it is not disrupted at will. Look at the key words, “agile” and “new requirements”: the action is to record them in the backlog and rank them, not to build, refuse or postpone them outright; which items enter an iteration is determined by priority and iteration planning. The answer is B.

    Why the other options are wrong

    • A. Building them immediately in the current iteration bypasses the product owner's ranking and negotiation with the developers, may endanger the iteration goal, and skips any assessment of value.
    • C. Agile embraces change: new requirements that have value should be considered, and turning them all down contradicts that.
    • D. Deferring everything until all iterations are over means the customer's value is not delivered in time, which amounts to not handling the requirements.

    Key takeaway New requirements on an agile project go into the backlog and are handled by priority.

    Variation If a new requirement is a feature required to meet a new regulation, the product owner likewise adds it to the backlog; after analyzing its compliance urgency and impacts and setting its priority, the product owner and developers determine the earliest iteration that can deliver it.

  75. Question 75

    A project manager is responsible for a smart hardware development project and knows that a senior algorithm engineer must take part for the project to succeed. A key stakeholder tells the project manager that Project B, which is under way, happens to have such an engineer. What should the project manager do to try to secure his participation?

    Show answer and explanation

    Correct answer: A

    A smart hardware development project needs a senior algorithm engineer to succeed, and Project B happens to have one. The project is at the resource acquisition stage, and the question asks how to try to secure his participation.

    The engineer is managed by a functional manager, and internal resources are assigned by functional managers or resource managers. The project manager should, on the basis of this project's cost-benefit case and value, discuss with his functional manager a plan for his participation in this project. This uses negotiation and influence to secure the resource, in line with PMBOK 8's requirements for acquiring resources. The answer is A.

    Why the other options are wrong

    • B. Asking the functional manager to recruit someone else is an option to consider only after negotiation fails. It cannot ensure that this particular engineer joins, and it shifts responsibility to the other side.
    • C. Project B also needs this engineer, so unilaterally demanding that its project manager release him is not negotiation, and that project manager has no authority to decide where he belongs, which in the end must be coordinated by the functional manager.
    • D. The sponsor can help obtain resources, but asking the sponsor at the outset to reassign the engineer means escalating before talking to the functional manager who has the authority to assign. The project manager should first try to secure him through negotiation, and ask the sponsor for help only if that cannot be solved.

    Key takeaway To win people from other projects, negotiate with their functional manager on the basis of this project's value.

    Variation If the functional manager insists on not releasing him after negotiation, assess the risks of using an alternative resource and escalate to the sponsor if necessary.

    Reference Negotiation · Lesson 2: Preparing for Negotiation, Techniques, and Applications to Resources and Procurement

  76. Question 76

    A quarterly assessment of a content development project for an online education platform shows that the planned course direction clearly deviates from the needs of the target users, and the assessment recommends adjusting the direction. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    The project is in execution and monitoring. The quarterly assessment shows the planned course direction clearly departs from the needs of the target users, and recommends adjusting it. What should the project manager do?

    The purpose of an assessment is to find problems and adjust accordingly. The assessment has already shown that the direction is off, so the project manager should propose an adjustment of direction based on the results; if the adjustment involves a baseline change, handle it first through the change control procedure and implement it once approved. This respects the assessment's conclusion and also complies with change control. The answer is C.

    Why the other options are wrong

    • A. Waiting for the next quarterly assessment to confirm lets the deviation keep accumulating, wastes resources and makes the assessment pointless.
    • B. Continuing to put resources into completing all the courses in the wrong direction only enlarges the waste. Adjust according to the assessment's conclusion first.
    • D. That the original direction was approved does not mean it cannot be adjusted. Monitoring exists to find deviations and prompt correction, and waiting for the sponsor to raise it is passive.

    Key takeaway When an assessment finds the direction off, adjust based on the results, going through change control where baselines are involved; do not delay or ignore it.

    Variation If the adjustment involves no baseline document at all, the project manager can adjust directly within delegated authority and record it and inform the stakeholders.

    Reference Monitor and Control Project Performance · Lesson 4: When Performance Deviates: Assess First, Then Act

  77. Question 77

    An online education platform project is defining its quality metrics. Which of the following is the BEST quantifiable quality metric?

    Show answer and explanation

    Correct answer: D

    A project needs to define quality metrics for its quality management plan. The question asks which metric can be quantified and measured.

    A quality metric must describe an attribute specifically and state how compliance will be verified. Whether a metric is usable depends mainly on four questions: what is measured, how it is measured, how often (a one-time acceptance metric may not need this), and what value counts as acceptable. “Total downtime per month does not exceed 4 hours” has a clear object, a monthly totaling basis and a target value. It can be measured directly during the project, and it matches the “total downtime per month” kind of metric PMBOK 8 lists. Conversely, any goal worded with “as … as possible”, “the more … the better” or “feel” has no target value and no measurement method, so you cannot tell whether it has been met, and it cannot serve as a basis in an audit. The answer is D.

    Why the other options are wrong

    • A. “Attractive and easy to use” has no number and no measurement method. It is a subjective impression, and you cannot tell whether it has been met.
    • B. “As fast as possible” has no target value, so everyone has a different idea of what level counts as acceptable.
    • C. “Feel good” is a subjective description. Unless a survey score and a target value are given, it cannot be measured.

    Key takeaway A good metric has a number and a counting basis. “The more … the better” and “feel good” do not qualify.

    Variation Rewrite C as “after each course, the learner satisfaction score is at least 4.2 (out of 5)” and it can be quantified. Rewrite B as “the home page loads within 2 seconds, with a weekly sampled pass rate of at least 95%” and it can be too.

  78. Question 78

    Two companies form a joint venture to take on a smart warehousing project, and the project manager, preparing the project management plan, wants to draw on past practice. A partner in the joint venture holds a complete set of historical project schedule records and risk data and agrees to share them. Which statement about this material is correct?

    Show answer and explanation

    Correct answer: B

    Two companies form a joint venture for a smart warehousing project, and while preparing the project management plan the project manager wants to draw on past practice. A partner holds historical project schedule records and risk data and agrees to share them. The question is about the range of sources of organizational process assets.

    PMBOK 8 states that organizational process assets may include any artifact, practice or knowledge from any or all of the performing organizations involved in the project, including the lessons learned and historical information from previous projects, which can be used to execute or govern the project. The historical schedule records and risk data the partner shares are historical information accumulated from earlier projects, so they are likewise organizational process assets and can serve as an input to the plan. The answer is B.

    Why the other options are wrong

    • A. Enterprise environmental factors are conditions the team cannot directly control that constrain or direct the project, such as marketplace conditions and legal restrictions. Historical records that have been shared are assets that can be used, not external conditions.
    • C. The source of organizational process assets is “any or all of the performing organizations involved in the project,” not only the lead party. The partner is a performing organization, and its material counts as well.
    • D. This material is the record of earlier projects and can be used as an input as early as planning, without waiting for closing. Adding to the repository at closing refers to the new information this project produces.

    Key takeaway Organizational process assets come from any or all of the performing organizations involved in the project, and include the historical information and lessons learned from earlier projects.

    Variation If the partner's material carries confidentiality terms, confirm the scope of sharing and the authorization before using it.

    Reference Organizational Process Assets · Lesson 1: Organizational Process Assets: Definition, Sources and Categories

  79. Question 79

    A bank has engaged PMLyceum to carry out an information-security remediation project. Several of the client's stakeholders want the project manager to commit to a firm delivery date. The project has many internal and external dependencies, plus several milestones that must be met within fixed time windows. What should the project manager do FIRST to determine the shortest project duration as the basis for the committed delivery date?

    Show answer and explanation

    Correct answer: C

    The project has many dependencies and milestones fixed to time windows. The question specifically asks for the shortest project duration as an analytical basis for the committed delivery date.

    The shortest project duration is set by the longest path in the network, which is the critical path. Integrate the activities into a network according to their logic, find the critical path, and add its length to the start date. That gives the earliest finish date without regard to resource limits, which is the basis for the delivery date you commit to; the fixed windows, calendars and resource constraints still have to be checked in the schedule analysis. “Many dependencies and fixed milestones” in the stem is the cue to do network analysis. The answer is C.

    Why the other options are wrong

    • A. The work breakdown structure answers “what is the work” by decomposing it into deliverables. It contains no sequence or durations, so it cannot yield a delivery date.
    • B. The schedule baseline is the approved schedule model. It is the result of schedule analysis, not a method for arriving at dates; the analysis comes first and the baseline after.
    • D. Resource availability determines whether activities can be performed on time, but looking at resources alone cannot give the overall duration, nor does it show how dependencies affect the dates.

    Key takeaway To answer “when is the earliest the project can be delivered?”, find the critical path.

    Variation To identify which activities could start a few days later without affecting the delivery date, you look at the total float of each activity, which still starts from the critical path analysis.

  80. Question 80

    A logistics company's warehouse system upgrade project is in the planning stage. The project manager compares the resource requirements list with the people and equipment available to assign and finds an obvious gap between them. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    The warehouse system upgrade project is in planning. The resource requirements list is done, and compared with the people and equipment available to assign there is an obvious gap. The question asks what the project manager should do; the point is the first step after a gap appears.

    After Estimate Resources produces the resource requirements, if available resources fall short, you should first do an alternative analysis, comparing the cost and impact of ways to fill the gap such as internal reassignment, external procurement, leasing and outsourcing, and then plan acquisition accordingly, staying consistent with the resource management plan and other documents. A gap can be addressed with options at the planning stage, so the project manager should first come up with an analysis rather than give up the objective. The answer is A.

    Why the other options are wrong

    • B. Handing the gap straight to the sponsor to decide means no analysis was done first. The project manager should first propose ways to fill the gap and their impacts, then ask for support with evidence, rather than throw the problem over as it is.
    • C. Cutting scope changes the project objectives. It is a choice to consider only after other options prove infeasible and it has been agreed with stakeholders; it is not the first reaction to finding a gap.
    • D. Postponing the start does not fill the gap. It is just waiting, and it affects overall schedule and cost, so it does not count as a solution.

    Key takeaway When there is a gap between requirements and available resources, do an alternative analysis and plan how to acquire them; do not cut scope or just wait.

    Variation If the stem adds that “the cost of the options to fill the gap exceeds the approved budget,” the next step becomes communicating with the sponsor and, if necessary, submitting a change request; if only a certain skill is missing, consider training first.

  81. Question 81

    An e-commerce app project uses an agile approach. The Product Owner does not write acceptance criteria for all user stories at release planning. Instead he plans to write them at Sprint Planning only for the stories to be built in that Sprint, believing this makes the most of agile's continuous improvement. Is this approach appropriate?

    Show answer and explanation

    Correct answer: C

    In an agile project, the Product Owner plans to write acceptance criteria at Sprint Planning only for the stories to be built in that Sprint, instead of writing them for all stories at release planning. The question is whether the timing is appropriate.

    At the user-story level in this question, acceptance criteria are the conditions that the story must meet to be accepted, and it is enough to settle them before development of that story starts. At release planning the stories are still coarse, so writing criteria for all of them is neither realistic nor useful, since later changes would invalidate them. By Sprint Planning the stories are clearer, and writing criteria then for the stories of that Sprint is exactly the agile way of rolling refinement. So the approach is appropriate. The answer is C.

    Why the other options are wrong

    • A. There is no rule that criteria must be written for all stories at release planning, and doing so would produce a lot of documents that later have to be changed.
    • B. If the customer proposes criteria only at the review, development is already over, the team can only guess, and the criteria no longer guide the work.
    • D. By the time of the demonstration, coding may long since be done. Criteria set then cannot guide development and testing, so the timing is too late.

    Key takeaway At the user-story level, acceptance criteria apply to the specific story and need only be settled before development. The Definition of Done is the shared quality standard for the Increment.

    Variation If the question is what to do when an item lacks acceptance criteria before entering a Sprint, the answer is to add them at refinement or Sprint Planning, making them clear before the item is selected. Whether this comes before estimating is for the team to agree. If the question asks where “every page must load within 3 seconds” goes, it is elevated into the Definition of Done.

  82. Question 82

    On a logistics company’s information platform project, members are in three countries and different time zones. The work each member delivers is acceptable, but joint reviews and cross-group cooperation always go badly, and overall performance is below expectations. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    An information platform project has members in three countries and different time zones. Each member’s own deliverables are acceptable, but joint reviews and cross-group cooperation are always rough, and overall performance is below expectations. The question asks what the project manager should do.

    Start with “each member’s own deliverables are acceptable”: there is no evidence of deficient individual ability. The stem explicitly locates the problem in joint reviews and cross-group cooperation—that is, communication and collaboration while working as a team—and gives no indication that tasks were assigned poorly. Team building is conducting activities that enhance the team’s social relationships and build a collaborative and cooperative working environment, and a team across countries and time zones needs to promote communication actively. The answer is B.

    Why the other options are wrong

    • A. The stem does not say any member is unqualified, and individual performance is satisfactory, so swapping members will not fix the cooperation problem and would force the team to settle in again.
    • C. The communications management plan might be worth reviewing, but the stem does not point to reporting frequency or channels as the problem. Time zones only show that communication is harder. Since individual deliverables are all acceptable, the issue is trust and collaboration, and revising a plan does not replace team building.
    • D. Task assignment has not been identified as a problem, and every individual deliverable is acceptable, so reassigning tasks does not address the issue.

    Key takeaway When individuals are competent but the team does not work together well, what is missing is trust and collaboration, and team building is the fitting remedy.

    Variation If one member’s deliverables were always unacceptable, first find out why and then consider training or coaching, not team building.

  83. Question 83

    The team on a data analytics project is mostly senior data engineers. Several of them tell the project manager that the newly arrived junior analyst always asks about data definition questions by typing in the team's instant messaging app, yet such questions can only be explained properly face to face. When the project manager asks the junior analyst, the analyst says that written answers can be reread and do not interrupt anyone's work. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    On this team the senior engineers prefer face-to-face discussion and the junior analyst prefers asking in writing, and each preference has its own reason. The project manager has to resolve the conflict of preferences at its root.

    Communication styles assessment is a technique used in Plan Communications Management to identify stakeholders' preferred communication methods, formats and content. Both sides in the question give reasons: face to face makes the data definitions clear, while writing can be reread and does not interrupt others. Neither side is wrong, so the project manager should not favor one. The project manager should first find out the preferences, then agree with the team on an arrangement everyone accepts and write it into the communications management plan. That resolves the disagreement at its root. The answer is B.

    Why the other options are wrong

    • A. This accommodates only the senior engineers and ignores the junior analyst's reasons (answers can be reread and do not interrupt others), so the disagreement remains as it was.
    • C. A fixed weekly session only standardizes the occasion. It does not establish anyone's preferences and does not settle the day-to-day conflict over face to face versus writing.
    • D. This swings the other way and accommodates only the junior analyst. It is equally one-sided and turns the arrangement into a unilateral order.

    Key takeaway When members' communication preferences differ, use a communication styles assessment to find the preferences, then agree an arrangement together, without favoring either side.

    Variation If the question changed to “a key stakeholder does not support the project and rarely replies to email,” you would first assess the engagement gap and then, as needed, run a communication styles assessment to find the stakeholder's preferred approach. An option saying “require everyone to use the same tool” is still not the answer.

  84. Question 84

    The team on a smart business park project has finished risk identification, and the risk register already lists more than twenty risks. What should the project manager do next?

    Show answer and explanation

    Correct answer: D

    A smart business park project has completed risk identification, and the register already lists more than twenty risks. The question asks what the project manager should do next.

    Right after risk identification, the next step is qualitative analysis: assess each risk using the probability and impact definitions in the risk management plan, so that the matrix can rank priorities and provide a basis for the responses that follow. Once priorities are set, the team has a sounder basis for deciding the response focus and whether quantitative analysis is needed. The assessment must also use consistent definitions so that risk levels are comparable. The answer is D.

    Why the other options are wrong

    • A. Developing measures and estimating funds for every risk without ranking spreads effort evenly and spends resources on low-value risks. Response planning should be built on priorities.
    • B. Monte Carlo simulation evaluates the combined effect on overall duration. It is quantitative analysis, normally done after qualitative ranking and only as needed, and it is not the step right after identification.
    • C. Submitting all the risks to the sponsor to set the order: ranking is analysis work that the project team completes using the risk management plan, and it should not be passed up wholesale to the sponsor.

    Key takeaway After identification, assess probability and impact first, then talk about responses and quantitative analysis.

    Variation If the ranking shows that a few risks have a major effect on overall duration and their combined effect needs to be quantified, then consider quantitative analysis such as Monte Carlo.

    Reference Qualitative Risk Analysis · Lesson 2: Risk Probability and Impact Assessment and the Probability and Impact Matrix

  85. Question 85

    You are the Scrum Master of a team in a two-week Sprint. Today is the last day, and some small testing tasks remain unfinished. The team says the testing can be finished today, but the Sprint Review is scheduled to start in 30 minutes. What should the team do next?

    Show answer and explanation

    Correct answer: A

    On the last day of a two-week Sprint, some small tests are unfinished. The team says they can be done today, but the Sprint Review starts in 30 minutes. What should the team do next?

    A Sprint is a timebox of fixed length that cannot be changed at will once begun, and the review should be held within this Sprint, so the Sprint is not extended and the review is not canceled to wait for unfinished tests. Only work meeting the Definition of Done can be presented as part of the Increment, so the team presents the fully completed features as the Increment and transparently identifies the unfinished testing work; unfinished items return to the Product Backlog to be refined or re-estimated further as needed. This keeps the timebox and also keeps transparency. The answer is A.

    Why the other options are wrong

    • B. Once a Sprint has started it cannot be extended. The timebox is a basic constraint of Scrum and cannot be changed for a bit of testing.
    • C. A feature whose testing is unfinished does not meet the Definition of Done and cannot be presented as part of the Increment at the Sprint Review; presenting it as completed work would undermine transparency.
    • D. The Sprint Retrospective comes after the review and is for improving the process. It cannot replace the review and cannot be moved earlier.

    Key takeaway The timebox does not move and the review is held as planned: present Done work as the Increment, transparently identify unfinished work, and return unfinished items to the Product Backlog.

    Variation If the Product Owner is unexpectedly absent, the review is still held within the timebox, and the team shows work that meets the Definition of Done and collects stakeholder feedback; the review is not a formal acceptance gate; product decisions that need that person can be synchronized afterward. If the customer's rating at the review is lukewarm, analyze why and reorder the later backlog accordingly.

  86. Question 86

    PMLyceum's innovation lab is building a prototype for a voice assistant. Market feedback and the related technology are changing quickly, the sponsor asks only that the team work within budget and brand boundaries, and the project cycle is short. When tailoring project governance, what should the project manager do?

    Show answer and explanation

    Correct answer: A

    The cycle is short, the market and technology change quickly, and the sponsor gives only a budget and brand boundaries. How should governance be tailored to the environment?

    Governance is tailored to the project's context. A project that needs rapid innovation can use a faster feedback cycle and an adaptive approach, with the team governing itself under lighter governance and clear boundaries and managing value delivery and quality. When the external environment changes fast, shorter feedback cycles help the team respond in time. “Short cycle”, “fast change” and “the sponsor gives only boundaries” together point to light governance and an adaptive approach; any option that adds approval layers runs against these signals. The answer is A.

    Why the other options are wrong

    • B. Phase gates and multi-level approvals are heavier governance and suit predictive projects with many internal and external constraints. On a fast-changing innovation project they would slow feedback.
    • C. Adding a multi-department governance board also makes governance heavier, and it is inconsistent with a sponsor who gives only boundaries.
    • D. Governance should be just enough; it is not the absence of governance. Self-governance still has boundaries, and communication with the sponsor must continue.

    Key takeaway Fast-changing environment, innovation needed: light governance, short feedback, boundaries. Many constraints, heavy compliance: stronger, more integrated governance.

    Variation If the same team's project were changed to one that must meet multi-country regulation, the answer would become more integrated, more targeted governance. Whether to use phase gates would still depend on the development approach, regulatory mechanism and other project conditions.

  87. Question 87

    Your agile team did not complete the planned story points in this iteration, and members are discouraged. After discussing it, everyone sees that the later iteration plans will also be hard to complete, which will affect the commitment for the whole release. What should you do now?

    Show answer and explanation

    Correct answer: C

    The team did not complete the planned story points in this iteration, and members are discouraged. After discussion, they see that later iterations will also be hard to complete, which will affect the commitment for the whole release. The question asks what to do now.

    Agile emphasizes face-to-face communication, which has the highest information bandwidth and the fastest feedback. With the release commitment under threat, the product owner and the team need to reassess scope, priorities and the arrangement of later iterations together, so the right step is a face-to-face meeting with the product owner and the team to plan the next steps. This both deals with the impact and involves the team in the decision, which restores confidence. The answer is C.

    Why the other options are wrong

    • A. A phone call involves only the sponsor and the product owner. The team does not take part, and there is no face-to-face exchange, so it is worse than meeting directly.
    • B. A root cause analysis only explains why, and a detailed written report is slow and arrives late. It cannot immediately deal with the threat to the release commitment.
    • D. Email is one-way, and waiting for a reply delays action. It is unsuitable when the plan has to be adjusted quickly.

    Key takeaway When progress is at risk, first meet the product owner and the team face to face to decide the next steps.

    Variation If the problem were conflict between team members that kept work from being finished, the Scrum Master should first help resolve it within the team, and scope adjustment would come afterward.

    Reference Burndown Charts and Information Radiators · Lesson 2: Forecasting Progress with Charts, Making Decisions, and Information Radiators

  88. Question 88

    A software services provider has just appointed a new project manager to run a small but high-profile project. If it succeeds, it will bring the company more work, and an effective closure is the key to success. To close the project smoothly, which document must the project manager obtain?

    Show answer and explanation

    Correct answer: C

    The project is at closure; it is small but high-profile, and effective closure is the key to success. The question asks which document the project manager must obtain to close smoothly.

    Accepted deliverables are an important input to Close Project or Phase. For a successfully completed project, a formal acceptance document from the customer or other authorized acceptor provides evidence that the results were accepted. The project manager must also complete the applicable handoff, lessons capture, archiving, and contract, financial, and resource closeout. The acceptance document does not mean that all these activities can begin only afterward, and it is not a prerequisite for formally closing a project that was terminated early. The answer is C.

    Why the other options are wrong

    • A. An analysis of contingency reserve usage evaluates the relationship between risk and reserves. It cannot show that the customer has accepted the deliverables.
    • B. This month's schedule status report records only execution. It cannot show whether the customer formally accepted the results, so it matters little for closure.
    • D. A procurement audit report on the contractor examines the procurement work itself. It has nothing to do with whether the deliverables were accepted and is not required for closure.

    Key takeaway For a successfully completed project, obtain formal acceptance from the customer or other authorized acceptor and complete the other applicable closure activities.

    Variation If a phase's exit criteria require formal acceptance, obtain the acceptance document for that phase's deliverables before confirming that the phase is complete.

    Reference Project Closure · Lesson 1: Close Project or Phase: Purpose, Inputs and Completion Criteria

  89. Question 89

    The task of developing the internal system of a pharmacy chain is handed to a project manager. The project manager finds that the requirements keep changing and the scope is unclear, and after talking with the team decides to work in an agile way. The company sends an agile coach, but the team members have neither agile experience nor agile training, and the training cost is already in the project budget. What should the agile coach do?

    Show answer and explanation

    Correct answer: B

    The requirements keep changing and the decision is to go agile. The team members have no agile experience and no training, the training cost is in the project budget, and the company sends an agile coach. The question asks what the coach should do.

    An agile coach's work includes training the team and helping members learn agile practices and change how they work. The whole team lacks an agile foundation, so the coach should select and carry out the most cost-effective plan for the whole team, so that everyone learns and changes together and builds shared practices. Training is the first step in changing how the team works, and it also builds the shared understanding for Sprint Planning and Daily Scrums later. The answer is B.

    Why the other options are wrong

    • A. Training only a few core members leaves the rest ignorant of agile, so the team cannot change how it works together.
    • C. The training cost is already in the project budget, so no change request for funding is needed. What the coach has to do now is support a team starting from zero, and carrying out whole-team training directly fits the coach's duty better.
    • D. Contingency reserve is for identified risks. Training cost is not a risk response and should not be paid from the contingency reserve.

    Key takeaway When everyone lacks agile knowledge, the coach's first job is to get everyone trained. Training the team is one of the coach's tasks.

    Variation If the budget were limited, you could arrange basic training for everyone first and then advanced training for key roles, rather than training only some of the members.

    Reference Scrum Roles · Lesson 2: The Scrum Master: Servant Leader

  90. Question 90

    A membership system upgrade project at a restaurant chain has entered execution. The team stops for every matter, even routine trade-offs, to wait for the project manager’s approval one by one, and the schedule is slipping. After observing, the project manager confirms that the members are fully capable of handling these tasks themselves. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    A membership system upgrade at a restaurant chain is in execution. The team waits for the project manager’s approval on every matter, even routine trade-offs, and the schedule slips. The project manager confirms that the members are fully capable of handling these tasks.

    Find the bottleneck first: the waiting comes from all decision authority being concentrated in the project manager alone, and the stem has already ruled out a capability problem. The servant-leadership response is to empower the team: clarify roles and responsibilities, set the range of matters the team can decide for itself and authorize it to act within that range, so that decisions return to the team and the waiting disappears. PMBOK 8 also notes that team members who feel empowered to make decisions about the way they work and about specific details in the deliverables perform better and have a higher degree of satisfaction than those who are micromanaged. The answer is B.

    Why the other options are wrong

    • A. A training budget addresses insufficient ability, and the stem confirms that the members are capable. Training would be slow and does not match the real problem, which is concentrated decision authority.
    • C. This adds another reporting step, and the functional manager cannot set the team’s scope of delegation for the project manager. It pushes off something that is the project manager’s own job.
    • D. Setting up an approval process for requests to the project manager locks the dependency in place: all requests still go to the project manager and the bottleneck remains.

    Key takeaway When a capable team waits for the project manager to decide, the answer is to clarify responsibilities and delegate, not to add training, escalation or process.

    Variation If the stem said the members were new hires unfamiliar with the business, the project manager should guide and train them first and delegate gradually; the scope of delegation must match maturity, and relevant information should be shared.

  91. Question 91

    While reviewing meeting minutes, the project manager finds that last month the team replaced the supplier of the core module with another one, and this major decision did not go through the approval that project governance requires. What should the project manager do?

    Show answer and explanation

    Correct answer: D

    While reviewing meeting minutes, the project manager finds that last month the team replaced the supplier of the core module, and this major decision did not go through the approval that governance requires.

    A major decision must be approved by someone with authority through the prescribed governance process. When the project manager discovers that the team has implemented a major unauthorized decision, the project manager should first pause the related unauthorized work, assess its impacts on scope, schedule, cost, quality, risk and procurement, and then submit it to the authorized decision-maker through governance and change control. If approved, update the relevant plans and documents, notify stakeholders and implement the approved outcome; if rejected, reverse or correct the decision. The answer is D.

    Why the other options are wrong

    • A. Accepting the fait accompli amounts to tacitly accepting that governance was bypassed, and the value and risk of the decision are never assessed.
    • B. Recording it as a lesson learned only helps future improvement. The unauthorized decision in front of you is not dealt with.
    • C. A verbal confirmation does not go through the required approval procedure and lacks a formal assessment.

    Key takeaway When a major decision has bypassed required approval, pause the related unauthorized work, assess the impacts, then submit it through governance and change control and act on the result.

    Variation If the team was already authorized to make this decision, no higher-level approval is needed, but the project manager should still confirm that it stayed within the delegated boundaries and record it. If the team keeps bypassing approval, explain which decisions go to which level. If assessment and approval show that the new supplier is more suitable, the governance outcome is to approve and record the decision, not to reverse it merely for the sake of correction.

  92. Question 92

    At PMLyceum, a smart home gateway project has just completed initiation. The project manager is about to begin planning and first needs to assess the external business environment. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    The project is between initiation and planning, and the project manager needs to understand the external business environment in which the project operates. What exactly should be done to assess the external environment?

    External enterprise environmental factors (marketplace conditions, legal restrictions, government or industry standards, emerging technologies and so on) cannot be controlled directly by the project team, yet they constrain or influence the project. To assess them, you must actively investigate the current state of, and changes in, these external factors so that you can judge their impact on the project. Hold on to the word “external”: only B looks at regulations, technology and markets. You can also rule out the inward-looking options: what needs assessing is the external business environment, so any option that talks only about the organization's own policies, resources and past projects is not assessing the external environment. The answer is B.

    Why the other options are wrong

    • A. Every project sits in a different market, regulatory and technology environment, and these change over time. The conclusions of an old project cannot replace an investigation for this project.
    • C. Policies, processes and internal resource conditions describe the organization's internal situation, while the question asks about the external business environment.
    • D. The sponsor's briefing can be one source of information, but a verbal briefing has not been verified by investigation and cannot be treated as the assessment conclusion.

    Key takeaway To assess the external business environment, actively investigate changes in external factors such as regulations, technology and markets.

    Variation If the stem were changed to “entering a country where there is no existing business”, then while developing the implementation strategy you would first assess the local environment and regulatory factors and identify high-level risks and assumptions.

  93. Question 93

    At a company with a matrix structure, the project manager needs a test engineer who belongs to a functional department to give priority to this project’s acceptance testing this week. The engineer also has other work assigned by the functional manager, and the project manager has no direct authority over him. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    At a matrix-structure company, the project manager needs a test engineer from a functional department to prioritize this project’s acceptance testing this week, but the engineer also has work assigned by the functional manager, and the project manager has no direct authority over him. The question tests what the project manager relies on to move the work forward: influence, not authority.

    PMBOK 8 states: “Because project managers often have little or no direct authority over team members in a matrix environment, their ability to influence stakeholders on a timely basis is critical to project success.” Key influencing skills include being persuasive, clearly articulating points and positions, high levels of active and effective listening, awareness of and consideration for various perspectives, and gathering relevant information to reach agreements while maintaining mutual trust. Option B, listening to the engineer’s work arrangements first and then explaining the project’s needs and working toward agreement, uses all of these skills. The answer is B.

    Why the other options are wrong

    • A. Stressing urgency and demanding unconditional compliance leans hard on authority he does not have. It ignores the engineer’s own arrangements and damages mutual trust.
    • C. Having the sponsor issue a written directive without first talking with the engineer and the functional manager skips the influencing skills the project manager should use first, and damages the relationship with the functional department.
    • D. Logging it in the risk register and waiting for him to be free is passive. It exerts no influence and does not ensure that acceptance testing is done on time.

    Key takeaway In a matrix environment authority is limited, so move others through influencing skills: persuasion, listening, clear articulation and maintaining trust.

    Variation If the question asked which kind of power is shown when a project manager assigns members of his own project team to carry out tasks, the answer would be formal power, based on the project charter. If it asked which power to rely on first, common exam practice favors expert power.

  94. Question 94

    A renovation project has seven activities, and all of the logical relationships are finish-to-start. Activity 1 starts first and takes 3 weeks. After it finishes, Activities 2, 4 and 5 can start at the same time, taking 4, 6 and 8 weeks respectively. Activity 3 follows Activity 2 directly and takes 3 weeks; Activity 6 follows Activity 4 directly and takes 4 weeks; Activity 7 can start only after Activities 3, 5 and 6 are all finished and takes 2 weeks. Activity 3 has now taken 4 weeks longer than planned. What is the length of the critical path now?

    Show answer and explanation

    Correct answer: C

    All logical relationships are finish-to-start. Activity 3 has overrun by 4 weeks, which may shift the critical path, so the three paths must be compared again.

    First list the three paths and add them up to find the critical path before the delay, then include Activity 3's overrun and compare again. After the delay, 1-2-3-7 is longer than the original critical path and becomes the new critical path, with a length of 16 weeks. The answer is C.

    1. Before the delay: 1-2-3-7 = 3 + 4 + 3 + 2 = 12 weeks; 1-4-6-7 = 3 + 6 + 4 + 2 = 15 weeks (critical path); 1-5-7 = 3 + 8 + 2 = 13 weeks
    2. Activity 3 goes from 3 weeks to 7 weeks: 1-2-3-7 = 3 + 4 + 7 + 2 = 16 weeks
    3. Take the maximum again: max(16, 15, 13) = 16 weeks, and the critical path shifts to 1-2-3-7
    4. Check: 16 − 15 = 1 week, so the finish date is 1 week later than originally planned

    Why the other options are wrong

    • A. 15 weeks is the length of 1-4-6-7, the critical path before the delay. It misses that after Activity 3's overrun, 1-2-3-7 has become longer.
    • B. 12 weeks is the length of 1-2-3-7 before the delay. It does not include the overrun.
    • D. 13 weeks is the length of path 1-5-7, which is neither the longest before the delay nor the longest after it.

    Key takeaway After an activity slips, compare all the paths again, because the critical path may shift.

    Variation If Activity 3 had overrun by only 2 weeks, 1-2-3-7 would be 14 weeks, still less than 15 weeks. The critical path would not change, and this path's total float would drop from 3 weeks to 1 week.

  95. Question 95

    A hybrid project at PMLyceum has entered execution, and the project manager and team have started holding a daily coordination meeting. So far the project manager has resolved 75% of the impediments the team reported, but the schedule variance is still growing day by day with no sign of improving. What should the project manager do to keep the schedule from deteriorating further?

    Show answer and explanation

    Correct answer: C

    A hybrid project is in execution, with a daily coordination meeting to surface impediments. 75% of the impediments have been cleared, yet the schedule variance still widens day by day. The question asks how to keep it from deteriorating further.

    That most impediments have been cleared while the schedule variance keeps growing suggests turning your limited effort to the bottlenecks that affect the finish date. A delay on the critical path pushes back the finish date directly, so among the options given, rank the impediments by their effect on the critical path and deal first with those that affect it; you should still monitor the float of non-critical activities and analyze whether there are other sources of variance. The general approach in this kind of question is that, with limited resources and effort, you put them where they directly affect the finish date; impediments on non-critical paths can be handled later as long as the float is enough. The answer is C.

    Why the other options are wrong

    • A. The stem does not say the daily coordination meetings are run badly. Sending the agenda in advance would not make impediment handling more targeted and would not solve the variance.
    • B. Quality problems can cause rework that delays the schedule, but the stem gives no hint of any quality problem. Focusing on the critical path is more direct.
    • D. The stem does not mention any lack of skills. Developing skills takes time to pay off and does not address the direct cause of the deterioration.

    Key takeaway With limited resources, first resolve the impediments that would delay the critical path rather than spreading effort evenly.

    Variation If all the impediments were on non-critical paths with ample float, that would only mean the finish date is not yet affected; if the schedule variance kept growing, you would analyze the root cause further.

  96. Question 96

    The team finds a process problem during an iteration and starts using a kanban board to improve it. You want to measure the results of the improvement and present the data clearly. What should you do?

    Show answer and explanation

    Correct answer: D

    The team finds a process problem in an iteration and starts improving it with a kanban board. It wants to measure the results of the improvement and present the data clearly. What should it use?

    The standard tool Kanban teams use to measure flow is the cumulative flow diagram: time on the horizontal axis, cumulative work items on the vertical axis, and one band per state. It shows the average arrival rate, cycle time and the amount of work in progress together, and changes in these three reflect the effect of process improvement directly, for example a narrowing in-progress band or a shorter cycle time. The answer is D.

    Why the other options are wrong

    • A. A burnup chart shows cumulative completions against total scope. It does not show work in progress along the way, so it is hard to use to measure process improvement.
    • B. A burndown chart shows remaining work decreasing over time. It focuses on what remains, not on arrival rate, cycle time and work in progress in the process.
    • C. A value stream map is good for depicting the end-to-end process, separating work from waiting and spotting waste, but it is not used, as a cumulative flow diagram is, to keep showing changes in arrival rate, cycle time and WIP for each state.

    Key takeaway Kanban teams measure process improvement with a cumulative flow diagram: arrival rate, cycle time and WIP in one chart.

    Variation If the stem asked what a continuously widening band means, the answer is a pile-up in that state. If no effective WIP limit exists, first set or enforce one and stop new intake; if the limit is already effective, keep intake stopped and diagnose why work is stuck. If it asked how to identify waiting waste in the process, use a value stream map.

  97. Question 97

    A project manager has always used predictive approaches and is currently managing several plant production-line upgrade projects at the same time. Senior leaders are strongly encouraging teams to incorporate more agile practices into their current ways of working, and the sponsor also wants these projects to use more agile. Before requiring any project to adopt agile practices, what should the project manager do FIRST?

    Show answer and explanation

    Correct answer: C

    A project manager who has always used predictive approaches manages several production-line upgrade projects, and senior leaders and the sponsor want more agile practices. You must decide what to do first before requiring projects to adopt agile practices.

    Before tailoring, first analyze and understand the project environment thoroughly. Tailoring for the project means evaluating three groups of attributes: the product or deliverable, the project team, and culture. Before requiring projects to adopt agile practices, the first thing is to examine the organization’s culture and the team’s readiness for change, such as buy-in, trust, and empowerment, to judge whether the introduction is feasible and how risky it is, and only then decide how to tailor and whether to train. The answer is C.

    Why the other options are wrong

    • A. Training comes after it has been confirmed that the change will be made; it is not the first thing to do.
    • B. Switching everything at once to agile with strict timeboxes is too aggressive; it does not assess suitability first and creates substantial risk.
    • D. Stopping all projects causes loss and does not answer whether the change is suitable.

    Key takeaway Whether to introduce a new practice: first analyze the organization’s culture and its readiness for change, then train and implement.

    Variation If the stem asked “after the assessment confirms feasibility, what is next,” the answer would be training and a pilot. If it asked how to diagnose whether an adopted practice is effective, the answer is retrospectives and measures.

  98. Question 98

    A new retail project in the execution phase has this situation: quality specifications that apply to every Increment were not included in the existing Definition of Done, and team members have different understandings of what counts as complete. As a result, the delivered features did not meet the specifications required by key stakeholders, SPI fell from 1.00 to 0.74, and CPI dropped from 1.40 to 1.05. What action should the project manager take to reduce the chance of rejection again in the next Sprint?

    Show answer and explanation

    Correct answer: C

    A project in execution delivered features that did not meet the quality specifications required by key stakeholders: specifications that apply to every Increment were not included in the existing Definition of Done, and the team has inconsistent understandings of completion. The question asks how to reduce the chance of rejection in the next Sprint. The key is fixing the identified completion-standard gap.

    The stem explicitly says that quality specifications applying to every Increment were omitted from the Definition of Done and that the team lacks a shared understanding of completion. Strengthening the Definition of Done to include those general specifications restores that shared understanding and ensures that later Increments are checked against the same standard before being considered done. Therefore C is the best answer. The changes in SPI and CPI describe performance impacts; they are not the basis for choosing C.

    Why the other options are wrong

    • A. Submitting a change request and giving the quality problem priority mainly arranges remedial work. It does not directly correct the missing general completion standard and inconsistent understanding identified in the stem, so it is not the best answer.
    • B. The priority and dependencies of backlog items have no direct link to whether the quality specification is met, so this will not fix the rejections.
    • D. A dedicated Sprint to finish leftover specifications postpones the quality problem and handles it in a lump. It cannot prevent rejection in the next Sprint and goes against building quality in.

    Key takeaway If a quality problem comes from a missing or unclear shared standard of completion, strengthen the Definition of Done first. Do not detour into the change process or a dedicated Sprint.

    Variation If the delivered features all meet the quality specification and only the schedule variance has widened, the problem does not lie in the Definition of Done. Look for causes in schedule and capacity instead of strengthening the Definition of Done.

  99. Question 99

    A project manager at PMLyceum has just taken over a newly formed team and is doing agile release planning for an internal expense-reimbursement app. The customer representative knows little about the technical details and can give only very general feature requirements. To make sure the customer is satisfied with the final product, what should the project manager do?

    Show answer and explanation

    Correct answer: C

    A newly formed team is doing agile release planning, and the customer representative knows little about the technology and describes requirements only in general terms. The question asks how to make sure the customer is satisfied with the final product.

    Two signals: the customer cannot state the requirements clearly, and wants to be satisfied in the end. The Manifesto values customer collaboration over contract negotiation, and principle 4 requires business people and developers to work together daily. The most effective way is to have the customer representative take part continuously in every iteration: at the iteration review and in daily exchanges they keep seeing results and giving feedback, the requirements become clearer through that feedback, increasing the likelihood of customer satisfaction. The answer is C.

    Why the other options are wrong

    • A. Having the customer hire a technical consultant to turn requirements into specifications pushes the responsibility back to the customer, slows the start, and does not address the root of the communication gap.
    • B. Scheduling extra features on your own to “make up” for general requirements is guessing. The extra features have no value basis, they add waste, and satisfaction is not assured.
    • D. Spelling out acceptance requirements item by item in the contract is “contract negotiation over customer collaboration”. The customer cannot state requirements clearly in the first place, so the terms could not be written in detail anyway.

    Key takeaway Customer satisfaction comes from continuous involvement and feedback, not from contract terms and not from adding features.

    Variation If the stem were changed to “contact between the team and customer broke off for a while and what was built does not match”, the answer is to restore direct, frequent communication with the customer first, on the same basis, principle 4.

  100. Question 100

    A logistics company's warehouse dispatch system is being developed with Scrum. During the Sprint, the Developers find an inventory rule that affects the warehouse supervisor, a key stakeholder, and they must get the supervisor's opinion soon or the Sprint will be affected. By team agreement, communication between the Developers and stakeholders goes through the Product Owner. The Product Owner normally meets this supervisor once a week, but this week's meeting has been postponed because of a schedule conflict. What should the Developers do?

    Show answer and explanation

    Correct answer: C

    A warehouse dispatch system is being developed with Scrum and is in the middle of a Sprint. The Developers need a key stakeholder's (the warehouse supervisor's) opinion soon. By team agreement, communication goes through the Product Owner, and the Product Owner's regular meeting with the supervisor was postponed this week. What should the Developers do?

    Division of roles is the core of this question. Scrum itself does not forbid the Developers from collaborating directly with stakeholders, but the Product Owner is responsible for understanding stakeholders' needs and conveying them to the team. The stem is explicit that there is an agreement that “communication goes through the Product Owner”, and the postponed regular meeting is only a distraction. It does not mean the agreement can be bypassed. The Developers should go to the Product Owner first, ask the Product Owner to arrange a separate consultation with the supervisor as soon as possible, and bring the result back to the team. The answer is C.

    Why the other options are wrong

    • A. Contacting the supervisor directly violates the communication channel the team agreed and leaves the Product Owner out. The supervisor's view may conflict with the order of the Product Backlog or with other stakeholders' needs, and without knowing it the Product Owner cannot coordinate.
    • B. An email also bypasses the Product Owner, and the back-and-forth of emails is slower, which does not meet the need to get it “soon” and leaves a risk of confused communication channels.
    • D. The Daily Scrum is a 15-minute meeting where the Developers inspect their own progress and coordinate the day's work. It is not an occasion for consulting stakeholders, and inviting an outsider would disrupt its rhythm.

    Key takeaway When the team has agreed that the Product Owner is the single contact for stakeholders, Developers go to the Product Owner first.

    Variation If the stem said a stakeholder called a Developer directly and demanded a feature, it would likewise be passed to the Product Owner. If it said the Sprint Review, stakeholders could give the team feedback directly at the review.

  101. Question 101

    The test engineer is the only person on the team who knows automated testing, and every Sprint's testing tasks land on that one person. The team decides to have the developers learn automated testing too. What is the main purpose?

    Show answer and explanation

    Correct answer: C

    The test engineer is the only person on the team who knows automated testing, and every Sprint's testing rests on that one person. The team decides to have the developers learn it too. The question asks for the main purpose, and the key is the risk of “only one person knows it”.

    The team as a whole covers each link of the delivery chain and members can cover for each other, which is a kind of staffing backup, so work does not get stuck with one person and the bottleneck risk falls. That is the direct benefit of cross-functional development. If only one person holds a skill, that person's leave, departure or overload hits the whole Sprint, so more people should learn it. The answer is C.

    Why the other options are wrong

    • A. Learning a skill does not directly increase how often members communicate, and that is not the purpose of learning automated testing. Even if communication rises through collaboration, that is a by-product and not what decides to build the skill.
    • B. Learning automated testing is skill development and has nothing to do with replacing a progress-tracking tool.
    • D. Building cross-functional ability has nothing to do with getting stakeholders to accept risk.

    Key takeaway The direct benefit of cross-training is fewer bottlenecks. A skill concentrated in one person is a bottleneck, and cross-training spreads it out.

    Variation If the bottleneck were in clarifying requirements, you would have team members learn basic business-analysis skills from each other, on the same principle.

    Reference Scrum Roles · Lesson 3: The Developers: Self-Organizing, Cross-Functional and Decision-Making by Participation

  102. Question 102

    A test engineer at a game company has recently been slacking off. The project manager learns that it is because the work assigned to him is too simple: he longs to complete tasks that are difficult but achievable and to see his results. The project manager moves him to a very challenging performance-testing module, and he quickly regains his drive. Which motivation theory is this an example of?

    Show answer and explanation

    Correct answer: B

    A test engineer at a game company has been slacking off because his work is too simple; he wants tasks that are hard but achievable and wants to see his results. The project manager gives him a very challenging performance-testing module, and his drive returns quickly. The question asks which motivation theory this exemplifies.

    The clues are that “work that is too simple” led to slacking and a “more difficult task” restored drive. McClelland’s theory of needs, as described in PMBOK 8, says that people who are motivated by achievement are motivated by activities and work that is challenging but reasonable. This engineer was re-energized by a challenging task, which satisfied his need for achievement, so it is an example of McClelland’s theory of needs. The answer is B.

    Why the other options are wrong

    • A. Theory X assumes people work only for income and lack ambition, with a corresponding hands-on, top-down management style; the stem instead makes clear that this member actively wants challenging but achievable work, so the Theory X assumption does not fit.
    • C. Expectancy theory stresses the expected relationship among effort, performance and reward. The stem does not mention expectations about outcomes or rewards.
    • D. The hierarchy of needs describes the order of five levels of needs; it is a common exam term. The clue in the stem is the need for challenge and achievement, which corresponds to McClelland’s theory of needs.

    Key takeaway Meeting the need for achievement with challenging but achievable tasks corresponds to McClelland’s need for achievement.

    Variation If the stem said he was promoted to lead a team of three, it would correspond to the need for power; if he were invited to more team gatherings, it would be the need for affiliation.

  103. Question 103

    In testing, an early prototype of a smart earbuds project shows an unacceptably high defect rate, and the quality management plan explicitly says that a quality problem requires causal analysis. The team includes members who know the product and are good at analysis, and the analysis needs to start soon. What should the project manager do as the first step in handling this problem?

    Show answer and explanation

    Correct answer: A

    In testing, an early prototype of a smart earbuds project shows an unacceptably high defect rate, and the quality management plan explicitly says that a quality problem requires causal analysis. The team has members who know the product and are good at analysis, and the analysis needs to start soon. The question asks for the first step in handling the problem.

    Causal analysis does not start with a report or with outsourcing. It starts by having team members who know the product and are good at analysis take part in identifying the causes. They use brainstorming and a cause-and-effect diagram to organize the possible causes of the defects and then verify them with suitable data; when categorized frequency data is available, a Pareto chart can be used to decide which causes to focus on first. By common exam practice, the team members who know the product list the possible causes first, and A is the most suitable of the four options. With the right people, the causes listed are close to reality; with too mixed a group, the discussion tends to wander. The answer is A.

    Why the other options are wrong

    • B. Having an outside expert do it alone leaves out the team, who know the product details best. Without their participation the causes are often incomplete, and it is harder to carry out the correction.
    • C. The change control board is not the forum for starting causal analysis; if the analysis later produces a change request that requires its review, submit it through the applicable change process. Relevant stakeholders may be informed earlier according to the issue's severity and the communications management plan, but reporting does not replace starting the analysis.
    • D. Inviting every senior leader and customer representative to lead the analysis is unnecessarily broad and would slow its start, while the team already has members who know the product and are good at analysis. People with relevant knowledge and analytical ability should start identifying causes, with other stakeholders involved as needed when they can provide useful information, so D is not the first step.

    Key takeaway For causal analysis, start with team members who know the product and understand analysis brainstorming, then draw the diagram and verify.

    Variation After the group lists the possible causes, the next step is to verify them with data; when categorized frequency data is available, rank with a Pareto chart, then concentrate the correction and verify that it worked.

  104. Question 104

    A customer service system project uses a predictive approach. In scope performance checks, the requirements stability metric has been low for several consecutive periods, and frequent changes to requirements make it hard for scope to settle. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    On a predictive customer service system project, the requirements stability metric has been low for several periods in a row, with frequent requirement changes.

    Low requirements stability suggests there may be a problem in how requirements are collected or confirmed. PMBOK 8 lists scope creep and similar measures among the scope performance checks, and an abnormal metric means finding the cause. The project manager should use root cause analysis to find the source of the frequent changes, such as requirements never confirmed, stakeholders not involved or poor communication, and then improve requirements management so that scope becomes more stable. Requirements stability is one of the metrics used in the scope performance domain to see whether scope is under control, and a metric that stays low across several periods signals a systemic problem, not a one-off. The order is to investigate first and improve second, rather than suppress the symptom with restrictions or reserves. The answer is C.

    Why the other options are wrong

    • A. Asking the customer to freeze requirements and accept no change is too absolute, ignores that change is legitimate and would damage the relationship.
    • B. Writing every change into the baseline abandons change control, and a baseline that is changed constantly no longer serves as a reference.
    • D. Holding extra management reserve to deal with change tolerates the problem passively without removing the source of frequent change, and reserve is not meant to absorb new scope.

    Key takeaway When requirements are unstable, find the source with root cause analysis and then improve requirements management.

    Variation If the metric is low because the external environment is genuinely volatile (such as frequent new regulations), consider switching to an iterative approach. If the cause is insufficient internal confirmation, strengthen elicitation and confirmation.

    Reference Monitor and Control Scope and Scope Creep · Lesson 4: Variance Analysis, Trend Analysis and Inspections: Tools for Monitoring Scope

  105. Question 105

    A project manager is in charge of building a cold-storage warehouse center. Because the construction involves many uncertainties, the sponsor and the project manager agreed that a cost variance within 5% is acceptable. After 3 months of execution, the team's data show an actual cost (AC) of $250,000 and an earned value (EV) of $225,000. What should the project manager do FIRST?

    Show answer and explanation

    Correct answer: D

    The sponsor agreed that a cost variance within 5% is acceptable. AC is $250,000 and EV is $225,000. First judge whether the variance crosses the threshold, then decide what to do first.

    CPI = $225,000 ÷ $250,000 = 0.9 and CV = −$25,000, about −11.1% of EV, beyond the agreed 5%. The overrun has already happened, so it is an issue, not a risk. When an issue occurs, first record it in the issue log (so it is tracked) and carry out cause analysis; then develop measures and, if needed, submit a change request. The answer is D.

    1. CPI = EV ÷ AC = $225,000 ÷ $250,000 = 0.9
    2. CV = EV − AC = $225,000 − $250,000 = −$25,000
    3. Variance percentage = CV ÷ EV = −$25,000 ÷ $225,000 ≈ −11.1%; the absolute value exceeds 5%, so the threshold is crossed
    4. Check: if AC were $235,000, CV = −$10,000 and −$10,000 ÷ $225,000 ≈ −4.4%, within the threshold. Here it is crossed, so record it in the issue log first. The answer is D

    Why the other options are wrong

    • A. The first action now is to log the issue and analyze its cause so it can be tracked and handled promptly. Lessons learned can be captured while analysis and handling go on, and with the cause not yet known there is not yet a complete lesson to record. So A is not the first action.
    • B. A change request comes after the issue has been recorded, its cause analyzed and a solution determined. It is a later step.
    • C. A risk is an uncertain event that has not yet occurred. The overrun has already happened, so it is handled as an issue and recorded in the issue log, not the risk register.

    Key takeaway Calculate first whether the variance crosses the agreed threshold. An overrun that has crossed it is an issue, and it is recorded in the issue log first.

    Variation If AC were $235,000, CV = −$10,000, about −4.4%, which is within 5%, so the project manager would normally continue monitoring and correct within their authority if the plan or analysis indicated that action was needed. If the agreed threshold were 12%, the project would also be within the threshold.

  106. Question 106

    At the iteration planning meeting, a team selects 4 user stories estimated at 8, 5, 3 and 2 story points. At the end of the iteration, the first three stories meet the Definition of Done, while the fourth does not because integration testing is unfinished. What velocity should be recorded for this iteration?

    Show answer and explanation

    Correct answer: B

    The iteration has ended. The team selected 4 stories (8, 5, 3 and 2 points). The first three met the Definition of Done; the fourth lacks only integration testing. The task is to calculate the iteration's velocity.

    In a Scrum context, completion is judged by the Definition of Done, which should include the relevant acceptance criteria and testing. The first three stories total 16 points and the fourth does not meet the Definition of Done, so it is excluded. The answer is B.

    1. Count only stories that meet the Definition of Done: 8, 5 and 3.
    2. Velocity = 8 + 5 + 3 = 16.
    3. The fourth story (2 points) lacks only integration testing and is not complete, so it is not counted and is not pro-rated for partial completion.
    4. Check: total selected 8 + 5 + 3 + 2 = 18, minus the 2 incomplete points, gives 16, which matches the velocity.

    Why the other options are wrong

    • A. 4 is the number of stories selected. Velocity is counted in story points, not story count, and only 3 stories were completed, not 4.
    • C. This gives partial credit for the unfinished story. Velocity does not recognize “almost done”: a story that does not meet the definition of done earns nothing.
    • D. 18 is the total points planned into the iteration. That is a forecast amount, not the amount completed.

    Key takeaway Velocity counts only story points that meet the Definition of Done; a story that is almost done earns nothing.

    Variation If the fourth story had also met the Definition of Done, velocity would be 8 + 5 + 3 + 2 = 18; if the third story had also not met the Definition of Done, velocity would be 8 + 5 = 13.

Practice test or full mock exam: what is the difference?

  • Free practice tests: 8 tests, the first with 120 questions and the others about 107 each, drawn from the 1,000 free questions (you may have met some while practicing by chapter), no login. Good for a quick self-check and for finding your weak domain.
  • Full mock exams: 180 questions each, separate from the practice bank (none of them appear there), timed in 3 sittings like the real exam. Use them to judge whether you are ready. See the full mock exams.

Free PMP practice test: common questions

Is this PMP practice test really free?

Yes. There is no account and no email wall. All 106 questions and the full explanation of every answer are free, and your progress is saved in your browser.

How were the 106 questions chosen?

They come from the 1,000 free questions: 27 People, 49 Process and 30 Business Environment questions, covering 24 of the 26 tasks of the Exam Content Outline, with single-answer and multiple-answer questions. There are 8 free tests and no question appears in more than one of them. Once a domain runs out of free questions a test is a little shorter, and the count shown is the real one.

How long does the test take?

Timed mode follows the real exam's pace of 80 seconds a question, so 106 questions get 141 minutes. You can also choose untimed practice and take as long as you like.

How are multiple-answer questions scored?

A multiple-answer question counts as correct only when you select every correct option and nothing else. There is no partial credit, and an unanswered question counts as wrong.

Are these real PMP exam questions?

No. PMI does not release exam questions. Every question here is original, written to the Exam Content Outline, to practice the question styles and the reasoning.

What should I do after the test?

Take another of the free tests, keep practicing by chapter in the 2,876-question bank, or take one of the 10 full mock exams of 180 questions. Your score here is a practice signal, not a prediction of the exam result.

To study first, read the study guide; for the whole bank, practice by chapter.