Free PMP Practice Test 6: 106 Questions with Explanations
106 PMP sample questions, test 6 of 8 with no question repeated from the other tests: 27 People, 49 Process and 30 Business Environment, covering 23 of the 26 tasks of the Exam Content Outline. Timed mode gives 80 seconds a question, 141 minutes in all; or practice untimed. Every question has a full explanation: why the answer is right and what is wrong with each other option. When you submit you get your total score, your accuracy in each of the three domains and a readiness check.
Updated 2026-11-22 · aligned to the current Exam Content Outline and PMBOK Guide 8th Edition
Ready to start?
Your answers are saved in this browser, so you can refresh or come back later. No account needed.
You can read every question below before you start; the answer options unlock when you press Start.
- Question 1
A multinational retail group plans to expand into a country where it has no existing business. After the business case is reviewed and approved, a project manager is appointed to initiate the project. When developing the implementation strategy, what should the project manager consider FIRST?
Show answer and explanation
Correct answer: C
A multinational retail group plans to expand into a country where it has no existing business. After the business case is approved, a project manager is appointed to initiate the project. What should the project manager consider first when developing the implementation strategy?
The project involves a new country where the group has no business, so local external enterprise environmental factors such as the market, laws and regulation are unknown. In initiation, the first thing to do is assess the local environment and regulatory factors and use them to identify high-level risks and assumptions, which are also important content of the project charter. Only after the environment is understood do resources and plans have a basis. The answer is C.
Why the other options are wrong
- A. The project has only just been initiated and the environment and risks are not yet understood. Asking the sponsor to commit that deliverables and timeline stay fixed for the whole project is premature and not the first consideration.
- B. Sourcing resources locally does not necessarily reduce uncertainty, and it is not the first consideration in initiation. The resource strategy should be built on an understanding of the environment.
- D. Monitoring risks is ongoing work that follows risk identification and planning. In initiation the risks have not even been identified, so there is nothing to monitor. The lack of lessons learned is exactly why the assessment must come first.
Key takeaway On a project entering a new region, assess the external environment and regulatory factors during initiation and identify high-level risks and assumptions.
Variation If the group already had a mature business in that country, it could draw on existing lessons learned, and the assessment would focus on changes specific to this project.
Reference External Business Environment · Lesson 1: External Enterprise Environmental Factors and PESTLE
- Question 2
After a membership points system is delivered, it needs long-term operations support. What should the project manager do during closure?
Show answer and explanation
Correct answer: D
A membership points system needs long-term operations support after delivery, and the project is in closure. The question asks what the project manager should do.
Handoff of the result is giving it to another team to operate, maintain and support, so the project manager must confirm the operations handover arrangements with the operations side, including responsibilities, resources and processes, so the operations side can take it. A project has a clear beginning and end, while operations support is continuing work that the operations team must carry. This step is done during closure and not left until after the project ends, or there will be a gap in responsibility when the operations side takes over. The answer is D.
Why the other options are wrong
- A. A project has a clear end point and the team must be released. The project team cannot be left on to stand in for operations, which would also tie them up when they could work on other things.
- B. Handing over only the system and the manual, without clear responsibilities, resources and processes, makes the handoff incomplete. The operations side cannot take it, and nobody is responsible when problems arise.
- C. The final report summarizes project performance. It cannot replace operations handover arrangements, and writing something in it does not mean the other side has people and processes to take it over.
Key takeaway For a result that must keep running, hand over responsibilities, resources and processes clearly instead of leaving the project team on standby.
Variation If the operations side has not yet been formed, agree with the sponsor before closure on the plan for setting up the operations team and on who is temporarily responsible in the transition period.
Reference Project Closure · Lesson 4: Closure Tools and Outputs: Final Report, Handover and Satisfaction
- Question 3
During project execution, the company sets up a new data analytics department, and its manager asks to be included in the project's regular communication and reporting. What should the project manager do?
Show answer and explanation
Correct answer: B
During project execution, the company sets up a new data analytics department, and its manager asks to join the project's regular communication and reporting. The question asks what the project manager should do.
The new department manager is a newly added stakeholder, and the appearance of this person shows that the list and the plans need updating. The correct order is to enter the manager in the stakeholder register while carrying out stakeholder analysis, find out what information the manager needs and how deeply to be involved, and then update the communications management plan accordingly, stating the content, frequency and method of communication. Also check the stakeholder engagement plan and update it if needed. That manages the manager's expectations and also avoids information overload. The answer is B.
Why the other options are wrong
- A. Having the manager take part in all communication without analysis means you cannot tell what information the manager really needs, and it goes against the principle of communicating as needed.
- C. The communications management plan is not a dead document that cannot be changed. When a new stakeholder and new needs appear, it should be updated. Using the plan as an excuse to refuse is wrong.
- D. Communication is the project manager's responsibility. Pushing this manager to the steering committee and the project management office amounts to avoiding the problem.
Key takeaway When a new stakeholder appears, register and analyze them first and then update the communications management plan.
Variation If the newcomer is a senior executive with major impact, register and analyze them first, clarify their desired engagement level, then update the engagement plan and the communications management plan as needed.
- Question 4
At a status review meeting on a consulting project, the project manager and key stakeholders are to discuss whether the risk management process is running effectively, in particular whether the agreed risk responses are being carried out. Which process does this work belong to?
Show answer and explanation
Correct answer: D
At a status review meeting on a consulting project, the topic is whether the risk management process is running effectively, and in particular whether the agreed risk responses are being carried out. What does this work belong to?
The key points are “whether the process is running effectively” and “whether the responses are being carried out”: what is being evaluated is the existing risk management process and the responses, not looking for new risks or ranking them. A risk audit is a tool used in Monitor Risks to consider the effectiveness of the risk management process, which includes checking whether the agreed responses are being carried out, so this work belongs to Monitor Risks. The answer is D.
Why the other options are wrong
- A. Identify Risks finds new individual project risks and sources of overall project risk. This question evaluates existing responses and the management process.
- B. Perform Risk Analysis (including qualitative analysis) assesses the probability and impact of risks and ranks them. It does not evaluate whether the management process is effective.
- C. Plan Risk Responses selects strategies and develops actions for risks, and takes place before responses are carried out. It does not evaluate how well the responses are working.
Key takeaway Evaluating the effectiveness of the risk management process and the responses is a risk audit in Monitor Risks.
Variation If the question asked about the “tool” with options such as brainstorming or the assumption log, the answer would still be a risk audit. If it asked who is responsible for ensuring audits happen at the frequency set in the plan, the answer is the project manager, with the frequency defined in the risk management plan.
- Question 5
A startup making innovative hardware runs an exploratory product project full of uncertainty and many risks, and the team uses an agile approach. What overall strategy should the project manager use to manage these risks?
Show answer and explanation
Correct answer: A
A startup's exploratory hardware product project has high uncertainty and many risks, and the team uses an agile approach, which is an adaptive environment. The question asks for the project manager's overall strategy for managing these risks.
In an adaptive project, requirements and solutions keep evolving and risks change with them, so risk planning done once at the start is not enough. The overall strategy is to assess risks continuously throughout the project and adjust the priorities of the backlog as the work progresses and requirements change, so that newly emerging risks and opportunities are scheduled into the work promptly. This fits the adaptive rhythm of small iterative steps and constant feedback. The answer is A.
Why the other options are wrong
- B. Concentrating risk analysis in the retrospective at the end of the project is too late. Risk management must run through the whole project; by the end, risks have long since happened or disappeared.
- C. Appointing a dedicated agile risk manager to carry it alone goes against the agile emphasis on the whole team sharing responsibility and watching risk, and it does not ensure that risks are assessed continuously and reflected in priorities.
- D. A risk matrix can serve as a tailored tool for tracking and evaluating risk, but it is only a means; it cannot replace continuous risk assessment and the overall strategy of adjusting backlog priorities accordingly.
Key takeaway Managing risk in an adaptive project: assess continuously throughout, and adjust priorities as the work progresses, not plan once.
Variation With a predictive approach, risk planning is usually more systematic early on, and risks are identified, analyzed, responded to and monitored as planned throughout the life cycle.
- Question 6
A team has done everything it can, yet several items on its kanban board are still blocked. A Sprint Retrospective finds that all the blocks come from business processes the company enforces, which cause long waiting times. What should the project manager do next?
Show answer and explanation
Correct answer: D
The team has done everything it can, but several items on the kanban board are still blocked. A Sprint Retrospective found that the blocks all come from business processes the company enforces, causing long waits. The question asks what the project manager does next. The root cause is at the organizational level, not in the team itself.
A servant leader should work within the organization to simplify the processes that affect the team as far as possible. Internal company processes cannot be abolished entirely, so the project manager should work with the process owners to simplify them while giving the team guidance on completing them. That reaches the root of the blocks, and the team is no longer stuck waiting. The answer is D.
Why the other options are wrong
- A. Walking the items through the processes solves only a few items for now, and a team-building event does nothing to remove the blocks. The processes themselves are untouched, so the team will be stuck again next time.
- B. Spending a whole Sprint on training delays value delivery, and the problem lies in the processes themselves, so a more self-sufficient team will not shorten the waits.
- C. Raising story points hides the delay inside the estimates. The waiting time remains, the impediment has not been removed, and measures such as velocity are distorted.
Key takeaway For blocks caused by organizational processes, work with the process owners to simplify them.
Variation If a process were mandated by regulation, its control requirements could not be removed, but you could still streamline how it is handled within compliance, for example by starting earlier, handling steps in parallel and clarifying the documents required.
Reference Scrum Roles · Lesson 5: Removing Impediments and Shielding the Team from Outside Interference
- Question 7
The project manager at a software company has just finished a largely outsourced systems integration project in which the two sides read the contract terms differently, acceptance was repeated, and the whole procurement went badly. The project manager wants to avoid the same mistakes on the next project. What should the project manager do?
Show answer and explanation
Correct answer: B
The project manager wants to capture the problems and experience from this procurement for use on the next project and must decide which approach to use.
A procurement audit is a structured review of the procurement process, including the contract and contracting process. Its purpose is to find problems in procurement management and to sum up what worked and what did not as lessons learned for future projects. The stem says the whole procurement process went badly and the aim is to avoid a repeat on the next project, which is exactly what a procurement audit is for. The answer is B.
Why the other options are wrong
- A. The issue log records specific problems that need tracking and resolution while a project is under way, and this project has ended. A PMO also does not take on a project's procurement problems one by one. This approach cannot systematically find process defects.
- C. An oral review in a meeting is not structured and produces no reusable record. The lessons are not put into the lessons learned register or organizational process assets, so the next project may repeat the mistakes.
- D. Adding clauses on the spot addresses only the individual problems exposed this time. It does not first review the whole procurement process, so it finds no root cause and does not cover other potential problems.
Key takeaway To learn lessons from the whole procurement process, use a procurement audit for a structured review and put the conclusions into lessons learned.
Variation If the question asks how to judge a supplier's performance this month, use a performance review, not a procurement audit. If it asks about accepting a delivery of floor tiles, use an inspection.
- Question 8
An e-commerce team is developing a new promotions module in an agile way. Because of market swings and changes in regulation, people on the customer side hand the developers requirement adjustments every few days. As a team member, what should you do?
Show answer and explanation
Correct answer: D
On an agile project, customer-side people hand developers requirement adjustments every few days because of market and regulatory changes. The question asks how a team member should respond.
On an adaptive project, the product owner manages the backlog and is the coordinator between customer needs and the development team. A team member who meets a change request should talk with the product owner and win support, so that the product owner assesses the value and ranks the item, rather than accepting, rejecting, or implementing the request on their own. Key words are “customer side,” “requirement adjustments” and “team member”: in adaptive projects, team members can clarify requirements directly with the customer, but new requirement adjustments go to the product owner to be added and ranked, and are not accepted, refused or implemented unilaterally. The answer is D.
Why the other options are wrong
- A. Passing through a change control board is a predictive practice. On adaptive projects the product owner approves changes dynamically, without a formal change control procedure.
- B. Adaptive projects embrace change. Changes should be assessed and ranked by the product owner, not dismissed across the board as scope creep.
- C. The project manager is not responsible for choosing backlog items. Passing the request along and waiting is a detour to the wrong person, because that decision belongs to the product owner.
Key takeaway When an agile team meets a customer's requirement change, talk it through with the product owner.
Variation If the person responding is the project manager, first verify the adjustment with the product owner and the development team; the product owner then updates and ranks the product backlog, and when the current iteration is affected, the developers and the product owner negotiate the scope.
- Question 9
On an ERP implementation project, a team member reports that a key team member disclosed another member’s confidential information to management, which may violate professional ethics requirements, but the matter has not been verified. At the team meeting, some members demand that this key member be removed from the team. What should the project manager do NEXT?
Show answer and explanation
Correct answer: D
On an ERP implementation project, someone alleges that a key member disclosed another member’s confidential information to management, and at the team meeting some people demand his removal. The question asks what the project manager should do “next”. For suspected breaches of professional ethics, the principle is to verify first and handle afterwards.
Hold on to the gap between “alleged to have violated” and “facts not yet clarified”. The respect and fairness values in professional ethics call for not disciplining anyone on rumor and not deciding in haste under team pressure; an accountable leader first learns the facts and then decides. So the project manager’s next step is to talk with this key member and clarify what happened, and then decide the follow-up measures on the verified result, avoiding losses to the team through a misunderstanding. The answer is D.
Why the other options are wrong
- A. Convening the team to discuss and decide forms a collective view on how to handle it without verifying the facts. That easily turns into collective blame of an individual, and it also avoids the project manager’s own responsibility.
- B. Asking human resources for a solution pushes onto someone else the fact-finding that the project manager should do first, and it looks like not taking the initiative. Human resources can take part after verification.
- C. Suspending the member before the facts are clear is premature punishment. If it turns out to be a misjudgment, the harm to the individual and to the team is hard to undo.
Key takeaway When the team demands action against someone, the project manager first verifies the facts with the person concerned and then decides how to handle it.
Variation If verification confirms that he did disclose confidential information, report and handle it honestly to the person with authority according to organizational rules and professional ethics. If the member has clearly admitted illegal or seriously improper conduct, the project manager does not need to run a full investigation personally; preserve the facts and report to the appropriate person or department with authority under organizational policy.
- Question 10
A project manager at a logistics company finds that an outside software supplier delivered a feature module on budget, but at acceptance it did not meet the agreed quality standard, and the supplier could only rework it, which delayed the whole project. The after-the-fact review finds that the problem came from a lack of oversight of the supplier's delivery process. What should the project manager do to keep such problems from happening in later procurements?
Show answer and explanation
Correct answer: D
A supplier has already delivered a module that failed quality and delayed the schedule, and the review concludes that the problem was a lack of oversight of the supplier's delivery process. To prevent a recurrence, a preventive method of monitoring and controlling procurements is needed.
An inspection examines the contractor's deliverables or work in progress, and inspecting interim results regularly can reveal quality problems before overall acceptance. A procurement audit is a structured review of the procurement process, including contracts and contracting processes, for completeness, accuracy, and effectiveness so that shortcomings can be identified and improvements made. The two together are the way to “avoid future procurement problems”. The answer is D.
Why the other options are wrong
- A. The contract is already signed. Renegotiating terms and price will not prevent the next quality failure, because the real problem is the lack of oversight of the delivery process.
- B. Revising the quality management plan only adjusts a document and is not itself oversight of the supplier's delivery process. The stem already says the problem was a lack of oversight, so the oversight method is what needs to be added.
- C. A penalty is a remedy after the fact. Holding the supplier accountable for rework that has already happened does nothing to prevent the same problem later, and it may not match the contract's penalty terms.
Key takeaway To prevent procurement quality problems, use inspections to monitor the seller's deliverables and a procurement audit to sum up the shortcomings in the procurement process.
Variation If the question asks for the first step after finding a supplier quality problem, first review the supplier's performance, check the contract to confirm responsibility, and then require correction. A procurement audit looks more like an after-the-fact review of the process.
- Question 11
On a shared finance services platform project at PMLyceum, after a review meeting a vice president tells the project manager privately that she is not confident the final delivered quality will meet the target. The project is already in execution. What is the MOST appropriate thing for the project manager to do?
Show answer and explanation
Correct answer: B
The project is already in execution, and a vice president tells the project manager privately that she is not confident the final delivered quality will meet the target. The question asks for the most appropriate response.
The quality management plan sets out the quality standards the project uses, the quality objectives, roles and responsibilities, the deliverables and processes subject to review, and the quality activities and tools. Inviting the vice president to go through the plan together both confirms whether the quality requirements she cares about are covered and explains how the project will ensure quality by following the plan, which responds directly to her concern. In answering a manager's concern, the point is to let that person see that “there is a plan, there are standards and there is a path to carry them out”, not to rely on verbal assurance. The answer is B.
Why the other options are wrong
- A. The size of the backlog reflects only the amount of work. It cannot be used to infer a quality level, much less prove that quality is on target.
- C. User acceptance testing is only one part of quality activities. Asking her to sign off on that arrangement does not answer her concern about overall quality.
- D. Saying only that the standards were approved long ago does not explain how the project will achieve them. It does not dispel the doubt and looks evasive.
Key takeaway When a senior manager worries about quality, first invite that person to review the quality management plan together.
Variation If the concern comes from the client, you can also show the quality control measurements and quality reports. The plan explains “how we do it”, and the measurements show “what was actually achieved”.
- Question 12
Maya is asked to drive a cold-chain delivery project with two key pieces of work. One is a driver shift-scheduling mini-app, where users cannot say what they want and it will very likely be adjusted again and again. The other is installing temperature sensors in the warehouses, where the construction content and scope are clear from start to finish. Which life cycle should Maya choose for the whole project?
Show answer and explanation
Correct answer: B
A cold-chain delivery project has two pieces of work: the scheduling mini-app has unclear requirements that will change repeatedly, and the sensor installation has a scope that is clear from start to finish. You must decide the life cycle of the whole project.
First look at what approach suits each piece. The mini-app has unclear requirements that will change several times, so it suits an adaptive approach; the sensor installation has a clear scope, so it suits a predictive approach. When both kinds of work exist in one project, use a hybrid life cycle that combines the two approaches, taking the strengths of each and aligning at the handoffs. When judging block by block, ask three things about each: Are the requirements clear? Will they change? Is frequent feedback needed? The answer is B.
Why the other options are wrong
- A. “Incremental delivery within a predictive approach” is only a way of delivering in batches. It does not address the difference between unclear requirements and installation work that must be planned predictively.
- C. A fully predictive approach cannot cope with the repeated changes in the mini-app’s requirements.
- D. “Iterative development within an adaptive approach” suits the part with unclear requirements, but the sensor installation has a clear scope, so iterating throughout is unnecessary and uneconomical.
Key takeaway When a clear part and an uncertain part coexist, choose a hybrid approach and choose the method block by block.
Variation If the requirements of both pieces were unclear, choose adaptive overall; if both were clear, choose predictive. When the two kinds coexist, combining the two approaches, that is, a hybrid approach, is the fit.
- Question 13
A city passenger-flow analytics platform project runs for two years, with part of the work outsourced to suppliers. In month 8, a team member suddenly leaves, and after negotiating with the functional manager the project manager brings in a replacement who has no procurement management experience. The project manager asks the new member to first look through the procurement documents and supplier evaluation records from the company's earlier projects. What is the new member making use of?
Show answer and explanation
Correct answer: B
A two-year passenger-flow analytics project outsources part of the work. In month 8 a team member leaves, and the replacement has no procurement management experience, so the project manager asks the replacement to first review the company's earlier procurement documents and supplier evaluation records. You must decide what the new member is using.
The procurement documents and supplier evaluation records of the company's earlier projects are documents the organization has accumulated and records of previous projects, so they belong to the organizational knowledge repositories among the organizational process assets, which the project team can use and also update and add to during the project. PMBOK 8 states plainly that organizational process assets include the lessons learned and historical information from previous projects and previous work carried out. The answer is B.
Why the other options are wrong
- A. Organizational culture, structure and governance is an internal enterprise environmental factor and describes the climate and structure of the organization, not documents that can be consulted.
- C. The project management information system is a tool, which falls under information technology systems among the enterprise environmental factors. What the new member needs to look at is the content of documents, not a tool.
- D. Enterprise environmental factors are conditions the project team cannot directly control, while the documents of earlier projects are kept by the organization and the team can consult and update them.
Key takeaway Documents and records of earlier projects are organizational process assets; culture, structure and system tools are enterprise environmental factors.
Variation If the new member were reading the company's procurement management policy, it would be the policies, processes and procedures among organizational process assets.
Reference Organizational Process Assets · Lesson 2: Telling Enterprise Environmental Factors and Organizational Process Assets Apart
- Question 14
The velocity of a software team has dropped recently. To regain momentum, the team decides to stop testing in this Sprint. What problem should the project manager watch for as a result?
Show answer and explanation
Correct answer: C
A software team's velocity has dropped, and to regain momentum it decides to stop testing in this Sprint. Giving up quality to go faster has consequences that show up later, and those are what the project manager should watch.
Skipping tests pushes work that should be done now into the future, which amounts to taking on technical debt (a common exam term): defects accumulate and rework costs more later. This is exactly what the project manager needs to watch, and it also runs against the quality requirements in the Definition of Done. The interest on technical debt is paid later: more defects, changes that are harder to make, and lower velocity. So the decision appears to recover velocity but actually borrows from the future. The answer is C.
Why the other options are wrong
- A. Skipping tests does not directly raise the team's burn rate. The effect shows up later as rework.
- B. A higher total cost is a result that technical debt brings when it comes due, not the first consequence this decision directly causes.
- D. In the short term efficiency may even look higher. The problem is the quality that follows, not an immediate drop in efficiency.
Key takeaway Skipping tests to go faster buys technical debt.
Variation If the team wants to raise velocity, it should analyze the root cause at the Sprint Retrospective instead of cutting quality steps. Technical debt already incurred does not disappear by itself and should be recorded in the backlog and paid down in order of priority.
Reference Product Backlog and Increment · Lesson 3: The Increment and Technical Debt
- Question 15
A multi-year ERP rollout project is in execution when a key team member suddenly resigns. The team is one person short, and a replacement will not arrive for several weeks. Several candidate activities can each release a member with the required skills, and pulling a member would cause the same activity delay in each case. The project manager decides to use a resource optimization method to minimize the effect. From which kind of candidate activity should the member be pulled?
Show answer and explanation
Correct answer: A
The project is in execution. A key member has suddenly resigned, and a replacement will not arrive for several weeks. The project manager wants to use resource optimization to minimize the effect. The question asks from which kind of activity to pull a member.
If you pull people from activities that have float, delaying those activities mainly consumes their float. As long as the delay stays within the available total float, the finish date is unaffected, which is exactly what resource smoothing does. The longer the total float, the more delay it can bear and the smaller the effect, so pull from the activity with the longest total float. Taking people from the critical path would deliberately push back the finish date, the opposite of the goal of minimizing the effect. The answer is A.
Why the other options are wrong
- B. Starting early does not mean having float; the activity may be on the critical path. Pulling people from it cannot guarantee that the finish date is unaffected.
- C. The activity furthest behind schedule needs the people more, and taking more would let the slippage grow. It may also be on the critical path.
- D. Critical path activities usually have the least float, so taking resources from them is the most likely to lengthen the critical path and the project duration. You should prefer to reassign people from activities that have more available total float and a matching skill set.
Key takeaway The critical path protects the duration, and non-critical paths supply resources; pulling people from the activity with the longest total float has the least effect.
Variation If the gap is larger than all the float can accommodate, smoothing is not enough, and you can only level resources and accept a longer duration, or look for other resources.
- Question 16
A portfolio manager and senior management are ranking four candidate projects for next year. Project A is aligned with company strategy and has clear target benefits and metrics. Project B is favored by the chief executive. Project C is relatively easy to do and its plan can be drawn up quickly. Project D meets the demands of a key stakeholder. Based on portfolio management's strategic-value criteria, which project should be chosen first?
Show answer and explanation
Correct answer: C
A portfolio manager and senior management are ranking four candidate projects for next year: A is aligned with strategy and has clear target benefits and metrics; B is favored by the chief executive; C is easy to do; D meets a key stakeholder's demands. The choice has to be made on strategic-value criteria.
Portfolio management selects and prioritizes projects according to strategic alignment and the value they are expected to deliver. Project A is aligned with strategy and has clear target benefits and metrics, so it provides the strongest evidence of strategic alignment and measurable expected value. The other three descriptions each provide only one piece of information that is insufficient by itself to determine priority: a leader's preference, ease of doing, or meeting one demand. Unlike Project A, they do not establish strategic alignment and measurable expected value. Prioritization looks at contribution to the organization's business value, so the answer is C.
Why the other options are wrong
- A. Meeting a stakeholder's demand can be one reason for approval, but prioritization looks at strategic alignment and expected benefits, not at whose demands are met.
- B. A leader's favor may influence a decision, but personal preference does not establish strategic alignment or expected value and cannot by itself determine project priority.
- D. Being easy to do and having a plan quickly written shows only low difficulty. It has nothing to do with how large the benefits are or whether the project is aligned with strategy.
Key takeaway When prioritizing projects, look at strategic alignment, target benefits and metrics, not personal preference or ease.
Variation To compare further between two strategically aligned projects, look at cost-benefit; when several financial measures conflict and the candidates are comparable, look at net present value first (common exam practice).
- Question 17
A user story reads “Exporting reports should be as fast as possible.” At the iteration review, the product owner feels it is still not fast enough, while the developers think it meets the bar, and neither side will give way. By the INVEST criteria, which one does this story mainly violate?
Show answer and explanation
Correct answer: B
A user story says “Exporting reports should be as fast as possible.” At the review the product owner and the developers cannot agree whether it meets the bar. The question asks which INVEST criterion the story violates.
“As fast as possible” has no objective standard, so neither side can judge whether it passes, and that is why they cannot agree. The property that lets both sides use the same standard to decide pass or fail is Testable in INVEST, and that is mainly what this story violates. The fix is to write a quantifiable acceptance criterion, such as “an export of 100,000 rows completes within 5 seconds”. The six INVEST criteria are Independent, Negotiable, Valuable, Estimable, Small and Testable. On the exam they usually appear as scenarios, and you have to match the symptom to the criterion. The answer is B.
Why the other options are wrong
- A. Independent means stories should have as few dependencies on each other as possible. The stem says nothing about dependencies on other stories.
- C. Estimable means that the size of the work can be judged. What the two sides dispute is whether it meets the bar, not how much work it is.
- D. The stem does not indicate that the story lacks value; the direct cause of the dispute is that “as fast as possible” cannot be objectively verified.
Key takeaway Vague words such as “as fast as possible” and “very friendly” make a story untestable. Turn them into quantifiable acceptance criteria.
Variation If the scenario is that a story is too big to estimate, the criteria violated are Small and Estimable. If a story can only be done after another story, it violates Independent.
- Question 18
A consumer electronics company’s smart band project has reached system testing when a competitor suddenly releases a similar product with more features at a lower price, so the project’s output no longer has market value. What should the project manager do?
Show answer and explanation
Correct answer: D
A smart band project is in system testing when a competitor releases a better, cheaper product, and the project’s output no longer has market value. What should the project manager do?
A sudden market change has removed the project’s value. The project manager should submit an assessment report explaining how far value is affected and what the alternatives are, and recommend that the governing body consider whether to terminate the project; the governing body makes the decision. PMBOK 8 notes that if misalignment persists or the project is unlikely to deliver the intended value, it may be best to terminate the effort, but that is a governance decision. The answer is D.
Why the other options are wrong
- A. Delivering as planned when the output is known to have no value keeps consuming resources, and waiting to observe the market after launch pushes the risk to a later stage.
- B. Cutting testing and quality activities cannot restore value and would harm quality. It trades quality for savings without solving the loss of value.
- C. Stopping work or terminating is not something the project manager can decide alone. Stopping work inside the team and waiting for a new direction lacks the governing body’s authorization.
Key takeaway When an external change removes the value of the output, submit an assessment and recommend that the governing body consider termination.
Variation If the assessment shows that repositioning would still create value, recommend that the governing body approve an adjusted scope instead of termination.
Reference The System for Value Delivery · Lesson 3: Value-Driven Decisions: What to Do When Value Changes
- Question 19
A drone delivery project is close to delivery when the government suddenly issues a new regulation that may affect the final product, and the project is forced to pause for a time. The sponsor wants the project closed out quickly, the head of R&D wants to wrap up as planned, and the head of testing says the product cannot move forward. The two argue fiercely. Which conflict resolution technique should the project manager use to reach a long-term solution?
Show answer and explanation
Correct answer: A
A drone delivery project nears delivery when a new regulation may affect the product. The sponsor wants a quick close-out, the head of R&D wants to finish as planned, and the head of testing says the product cannot move forward. The R&D and testing heads argue fiercely. The question asks which technique yields a long-term solution.
The deciding clue is the requirement for a long-term solution. The two sides hold different positions, each with grounds. To pursue a durable resolution, the most suitable approach is to face the matter directly, lay out each side's views and concerns, and work toward consensus and commitment through open dialogue. That is collaborate/problem-solve, which can produce a win-win result. Because the sponsor, R&D and testing all hold different positions, it is better to bring them together and jointly assess the regulation's impact against the project's objectives. The answer is A.
Why the other options are wrong
- B. Compromise/reconcile means each side gives a little. It resolves the conflict only temporarily or partially and can even produce a lose-lose result, so it is not a fundamental solution.
- C. Smooth/accommodate emphasizes common ground and does not resolve the conflict itself.
- D. Force/direct pushes one side's view through power and is suited to emergencies, but it often produces a win-lose outcome and damages relationships, making it unsuitable for the durable, mutually accepted resolution requested here.
Key takeaway When the stem calls for a long-term solution, choose collaborate/problem-solve (win-win, with consensus and commitment).
Variation Only if just half a day remained, a decision had to be made at once, and that decision was within the project manager's authority and consistent with the new regulation, would force/direct be an option; otherwise the decision should be made by the responsible governance or compliance owner.
- Question 20
The members of a joint project come from different regions and are working together for the first time. Because the travel budget is limited, it is not possible to bring them together in one place in the short term. The project manager worries that members will not gel and decides to do team building. How should it be arranged?
Show answer and explanation
Correct answer: B
A joint project’s members come from different regions and have not worked together before. The project manager fears they will not gel and decides on team building. The question asks how to arrange it.
PMBOK 8 is explicit: team-building strategies are particularly valuable when team members operate from remote locations without the benefit of face-to-face contact, and informal communication and activities can help in building trust and establishing good working relationships. The members are dispersed and new to one another, and budget prevents bringing them together, so informal online exchanges and activities improve mutual understanding and interaction without gathering everyone in one place, at low cost. The answer is B.
Why the other options are wrong
- A. Face-to-face activities are very valuable for a newly formed virtual team (PMBOK 8 suggests at least one), but the stem says the travel budget is limited and a gathering is not possible in the short term, so this option is not feasible now.
- C. Assessing each member’s performance and arranging training builds capability, which does not match the goal of helping members gel.
- D. Relying mainly on email promotes communication poorly: email is one-dimensional with little interaction and does not help members gel.
Key takeaway A virtual team does team building through informal online activities, and needs it even more than a colocated team does.
Variation If the budget allowed, PMBOK 8 suggests that a newly formed virtual team hold at least one face-to-face meeting to lay a foundation for relationships, supplemented by online activities. With the budget limit removed, A could also be valid.
Reference Virtual Teams · Lesson 3: Collaboration Tools and Remote Work: Equip the Team First, Then Agree How to Use the Tools
- Question 21
A project's stakeholders grow from 8 to 11 people, and the number of communication channels is calculated as n(n-1)/2. By how many channels does the number of communication channels increase?
Show answer and explanation
Correct answer: D
Stakeholders grow from 8 to 11 people, and the number of channels is calculated as n(n-1)/2. You are asked by how many channels the number increases, so the quantity needed is the change, not the new total.
The formula and the headcounts are given, so the key is reading the question: you need “by how many” the channels increase, which means subtracting the number before the change from the number after, not simply giving the new total. Calculate the two totals with the formula, then subtract. This formula is the common exam calculation. The result is 27, which shows that every 3 additional people add channels much faster than headcount. The answer is D.
- With 8 people: 8×(8−1)÷2 = 28 channels.
- With 11 people: 11×(11−1)÷2 = 55 channels.
- Increase in channels = 55 − 28 = 27.
- Check: each of the 3 new people connects to the original 8, 3×8 = 24 channels, plus 3×2÷2 = 3 channels among the 3 new people, 27 in all, which agrees.
Why the other options are wrong
- A. This is the increase in headcount, 11 − 8 = 3, treated as the increase in channels. The number of channels grows with the square of headcount, not linearly.
- B. This is the original number of channels with 8 people, 8×7÷2 = 28. It counts only the total before the change, without calculating the total after or subtracting.
- C. This is the total with 11 people, 11×10÷2 = 55, that is, “increase to” 55. It does not subtract the original 28, answering “increase to” instead of “increase by.”
Key takeaway Calculate the channel counts before and after, then subtract; “increase by” needs the subtraction, “increase to” does not.
Variation If it asked “from 5 to 9 people, by how many do the channels increase,” the answer is 9×8÷2 − 5×4÷2 = 36 − 10 = 26. If it asked “increase to how many,” the answer is 36.
- Question 22
A smart-campus project is proceeding according to the strategic plan, and the key milestones in the plan have been aligned with stakeholders. During execution, several new tasks within the approved scope and important dependencies appear, work stalls as a result, and the team cannot say who should decide and take action. What should the project manager do?
Show answer and explanation
Correct answer: A
The project is in execution and the key milestones are aligned. When new tasks and dependencies appear, work stalls and the team cannot say who decides and acts. The conflict is not about schedule or scope but about unclear ownership.
A RACI matrix uses four roles (responsible, accountable, consulted, informed) to tie each task to people, and it ensures each task has only one accountable person. Using it to settle responsibility for the new tasks makes clear who decides and who acts, and the stall clears. The key signal in the stem is “cannot say who should decide and take action”. The answer is A.
Why the other options are wrong
- B. A Gantt chart shows the timing of activities and milestones and answers “when”, not “who is responsible and who decides”. The milestones were already aligned and are not the issue.
- C. Having the sponsor name an owner for each task means the project manager gives up the lead on resource management and slows the response. A better approach is for the project manager to assign actively with the tool and ask the sponsor to confirm only if needed.
- D. The WBS breaks down scope that has already been defined. It is not for identifying all requirements and cannot by itself guarantee none are missed, and it also does not assign responsibility or decision rights. Nobody deciding on new tasks is not a problem of scope omission.
Key takeaway When it is unclear who does the work and who makes the call, use a RACI matrix to assign responsibility to people, with one accountable person per task.
Variation If the question asked how to confirm every deliverable has been included in scope, the answer would become the WBS. If it asked how to show which department is responsible for which work packages, the answer is the organizational breakdown structure.
- Question 23
A project manager receives a project to develop a sports social app. The product’s features must be determined step by step based on continuous user feedback, and there is no ready-made technical solution to refer to for how these features will be implemented. Which development approach should the project manager recommend?
Show answer and explanation
Correct answer: D
The features of a sports social app must be determined step by step from continuous user feedback, and no ready-made technical solution exists for implementing them. You must decide which approach to recommend.
Judge with the Stacey matrix (common exam practice): requirements uncertainty on the vertical axis is high and technology uncertainty on the horizontal axis is also high, so the project falls in the complex zone, where adaptive approaches fit best. The two signals map to the two axes: “features determined step by step from continuous user feedback” is requirements uncertainty, and “no ready-made technical solution” is technology uncertainty. An adaptive approach should therefore be used, determining the features and how to implement them gradually through iterations and feedback. The answer is D.
Why the other options are wrong
- A. A predictive approach suits the simple zone, where both requirements and technology are clear. When both are uncertain, locking the plan up front only causes repeated rework.
- B. The stem gives no condition requiring predictive components, phases, or governance mechanisms to be kept; both requirements and technical solution must become clear through feedback and exploration, so D matches more directly than B.
- C. Incremental delivery within a predictive approach requires the overall scope to be well understood and planned up front. Here the features are determined gradually through feedback, so the premise is absent.
Key takeaway When both requirements and technology are uncertain (the complex zone of the Stacey matrix), choose an adaptive approach.
Variation If requirements were clear but the technology had some uncertainty, the project might fall in the complicated zone, and you would still choose iteration, increment, hybrid, or another suitable approach according to the degree of technical uncertainty. If both were clear, it is the simple zone and predictive applies.
- Question 24
On PMLyceum’s supply chain system upgrade project, the project manager notices that developers who find a risk are reluctant to report it, fearing they will be held responsible, and the problem is usually exposed passively only after it blows up. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
On the supply chain system upgrade project, developers who find a risk do not want to report it and the problem is exposed only after it erupts. The question asks what to do first, and the basis for the judgment is the trust and psychological safety requirements in Build an Empowered Culture.
The key signal is “fearing they will be held responsible”: the members are not failing to report because of ability, but because of a lack of trust and safety. An empowered culture requires an environment that promotes trust, so the project manager first creates an atmosphere of psychological safety and sets up a reporting channel that does not assign blame to individuals, so that risks are spoken about while they are still small. The answer is A.
Why the other options are wrong
- B. Cutting ratings and naming names is punishment. Members will fear exposing problems even more, and the concealment will only get deeper.
- C. Surprise spot checks are a monitoring measure. They do nothing to remove members’ worries and in fact damage trust.
- D. Handing a cultural problem inside the team to functional managers is passing the buck. For emotional and attitude issues like this, the project manager should first talk with the people and improve the environment personally.
Key takeaway When members hide problems, first solve whether they dare to speak, not punishment, monitoring or handing it off.
Variation If the scenario were “the team does not dare try new methods for fear of failure”, the answer becomes allowing small-scale experiments and lowering the cost of failure. If it were “a new member is interrupted in meetings”, it becomes setting a team agreement and inclusive rules for discussion.
- Question 25
At an executive meeting, someone asks what exactly the project sponsor is responsible for on a project. Which statement is MOST accurate?
Show answer and explanation
Correct answer: B
You need to judge the sponsor's role, independent of any particular project phase, by distinguishing the sponsor's responsibilities from those of the project manager and the team.
PMBOK 8 says the sponsor may provide decision leadership outside the project management team's authority: communicating the organization's vision and expectations to the team, keeping the project aligned with business objectives, facilitating executive-level decisions, helping to secure resources, and addressing or removing obstacles beyond the project management team's authority, so that the intended business benefits are realized. B is consistent with this. A, C and D are the day-to-day work of the project manager or the team, or are excessive interference. The answer is B.
Why the other options are wrong
- A. Assigning and checking tasks every day is the affair of the project manager or a self-managing team, not the sponsor's responsibility.
- C. The daily coordination meeting is a routine activity inside an adaptive team and is run by the team itself. It is not the sponsor's responsibility.
- D. Approving technical details item by item is excessive interference. The sponsor focuses on business value and executive-level decisions, not technical details.
Key takeaway The sponsor drives approval, secures resources, clears executive-level obstacles and safeguards business value, and does not manage day-to-day tasks.
Variation If the question asked who is responsible for assigning tasks every day and following up, the answer is the project manager (or the self-managing team). If it asked who keeps watching whether the benefits are realized after the project ends, the answer is the benefits owner designated in the benefits management plan (the sponsor may also be designated).
- Question 26
A showroom renovation project is in the middle of execution, and the project manager plans to take a week of annual leave while the delivery deadline is tight. He has not yet worked out which decisions will come up during his absence. To make sure the project still progresses on schedule during his absence, what should the project manager do FIRST?
Show answer and explanation
Correct answer: C
A showroom renovation is mid-execution with a tight deadline, and the project manager plans a week of annual leave. The question asks what he should do FIRST so that the project still progresses on schedule while he is away.
For a FIRST question, find the earliest step in the whole sequence. Delegation needs a rationale and boundaries: first analyze what impact the absence will have, which decisions will come up in those days and which could block the work; then set up the team’s decision-making arrangements on that basis, stating what the team may decide on its own, the basis for judging and the situations that must be escalated; only then delegate. This is consistent with the PMBOK 8 line on empowerment, delegation and autonomy: delegation has a scope and a rationale. The answer is C.
Why the other options are wrong
- A. Delegating is not wrong in itself, but without first analyzing the impact and stating the scope and basis for decisions, the delegation lacks grounding and is not the first step.
- B. The leave is already planned, and postponing it is no way to arrange the team’s decision-making; it means the project manager keeps making every decision himself.
- D. Handing all necessary decisions to the sponsor pushes the responsibility for managing the project back up and does not empower the team during the absence.
Key takeaway Before leaving, analyze the impact of the absence and set up team decision-making arrangements, then delegate.
Variation If the question asked what the team should do when it meets a decision beyond its delegated scope, the answer is to state the escalation path and contact person in advance; if it asked about after the project manager returns, review how the delegation worked and update the arrangements.
- Question 27
On a route optimization project at a logistics company, data analyst Maya has lately been saying her work is dispensable and nobody pays attention to her results. What should the project manager do to motivate her effectively?
Show answer and explanation
Correct answer: D
On a route optimization project at a logistics company, data analyst Maya has lately said her work is dispensable and nobody pays attention to her results. The question asks what the project manager should do to motivate her effectively.
The symptom is “no value, nobody notices,” so what is missing is a sense of achievement and recognition, which are higher-level needs. In Herzberg’s two-factor theory they correspond to motivational factors, and in Maslow’s hierarchy to esteem and self-actualization (Maslow's hierarchy is a common exam term). What directly meets such needs is a challenging task plus timely recognition, so that she sees her results and their value. The answer is D.
Why the other options are wrong
- A. The office environment and atmosphere are hygiene factors. Improving them only removes dissatisfaction and does not solve her sense that her work is of no value.
- B. Benefits and insurance are also hygiene factors and meet lower-level needs, unrelated to her needs for achievement and recognition.
- C. An extra bonus after the project ends is only a material reward. She would have to wait until the end, and it would not make her feel her work is valuable or her results seen.
Key takeaway When a member wants achievement and recognition, motivate with challenging tasks and recognition, not with environment, benefits or bonuses.
Variation If the stem said she was irritable because her work area was too noisy, fixing the environment (a hygiene factor) would be right; if she said she wanted to learn modeling, support her learning and growth.
- Question 28
A team is using a short-iteration adaptive approach to develop a mobile payment mini-app. The sponsor asks whether the project, like a predictive project, has a complete project management plan fixed once before work starts. How should the project manager describe the project's plan?
Show answer and explanation
Correct answer: A
On an adaptive mini-app project, the sponsor asks whether, as in a predictive project, there is a complete project management plan fixed once before work starts.
The plan of an adaptive project is lightweight: a product vision, a roadmap and a release plan, with the team planning the details at the start of each iteration and adjusting continually based on feedback. The project manager should say so honestly: the plan is kept lean and refined progressively by iteration. A predictive project usually plans more fully up front and establishes baselines, with later changes controlled. An adaptive project is detailed in the near term and high level further out, and the plan is updated with feedback from each iteration. The answer is A.
Why the other options are wrong
- B. Completing it all at once and strictly not changing it does not fit the continual adjustment of adaptive work, and the statement is too absolute in itself, since a predictive plan can also be updated under change control.
- C. An adaptive project is not without a plan. The plan is just lighter and adjusted more often.
- D. Keeping only the budget would drop key content such as scope and schedule. The plan should be lean as a whole, not reduced to a single item.
Key takeaway An adaptive project's plan is lightweight, refined progressively by iteration and adjusted continually.
Variation In a hybrid project, the predictable parts are managed against baselines and the uncertain parts are refined by iteration, chosen by the nature of each part and not one approach for everything. If asked how scope or requirement changes are managed in an adaptive project, common exam practice is continuous refinement and ordering through the backlog.
- Question 29
A retail-system upgrade project at PMLyceum is in execution. The company announces a merger of two business units, and several key members of the project may be reassigned as a result. What should the project manager do NEXT?
Show answer and explanation
Correct answer: D
A retail-system upgrade is in execution. The company announces a merger of two business units, and several key members “may” be reassigned. The question asks what the project manager should do next, so the order of actions matters.
Start with the word “may”: the members have not left, so the risk has not become a fact. The project manager should first determine what their leaving would do to the project and identify the potential risks, then carry out mitigation measures according to the project management plan, to keep the schedule and other objectives from being hurt. This is the common order for monitoring processes: assess first, then act. The option “assess the impact and carry out mitigation” contains both steps. The answer is D.
Why the other options are wrong
- A. Talking to the members and supporting them in the transition has its place, but it does not address the impact on the project and offers no mitigation. It is not what to do first.
- B. Finding replacements is one mitigation measure and should follow the impact assessment; besides, the members only “may” leave, which is not yet a fact.
- C. The merger is a company-level decision, so the project manager cannot “make sure” it will not affect the project. Analyze the impact proactively first instead of going to the sponsor first.
Key takeaway When key members may leave: assess the impact on the project first, then carry out mitigation measures according to the plan.
Variation If the stem said a key member “has already submitted a resignation”, you would still assess the impact first, but the risk has become fact, so you move into response: handover, replacement and plan adjustment.
- Question 30
A logistics system upgrade project uses a predictive approach. The customer asks for a scope change, and the project manager has recorded it, evaluated its impact and submitted the change request to the change control board (CCB). The CCB reviewed it and rejected the request. The decision is not yet in the change log, and no one has been told. What should the project manager do NEXT?
Show answer and explanation
Correct answer: D
This is a predictive project. The change request has been recorded, evaluated and submitted to the CCB, and the CCB has rejected it. The decision is not yet in the change log and no one has been notified. The question asks what the project manager should do next.
PMBOK 8 requires the status of change requests to be tracked, and the final decision to be managed and communicated to stakeholders. The CCB has already rejected the request, so the decision must be recorded in the change log and communicated to the customer who raised the change and to the team members concerned. Recording and notifying are two actions within the same task, and there is no fixed order for them, nor a fixed five-step change process; follow the change management plan or the stem. D carries out both and does not go back to evaluation or submission. To judge what comes “next”, first locate where the process has got to, then choose the action that follows. The answer is D.
Why the other options are wrong
- A. This notifies only the customer and postpones recording the decision until the customer replies. The decision does not reach the change log in time, which does not meet the requirement to track change status and record decisions.
- B. Evaluation comes before submission and has already been done. Without new information, a rejection by the CCB is no reason to evaluate again and resubmit; that would step back to earlier parts of the process.
- C. The scope baseline can be changed only through formal change control. The CCB has rejected the request, and the project manager cannot get around that decision by accepting the change on their own.
Key takeaway After a change request is rejected, record the decision (in the change log) and notify stakeholders; the order of the two follows the change management plan or the stem.
Variation If the customer had raised the change verbally and nothing was recorded yet, the first step would be to record it. If the CCB had approved it, the next step would be to update the baselines and related plans and notify stakeholders.
- Question 31
The resource management plan has been completed. Team members are spread across four countries, span multiple time zones, and work in different languages. The project manager wants the team to run smoothly and to reduce the harm that misunderstandings arising from this could do to the project. What should the project manager do?
Show answer and explanation
Correct answer: A
The resource management plan is complete. Team members are spread across four countries, several time zones and different working languages, and the project manager wants the team to run smoothly and to limit the damage misunderstandings could do.
Time zones, languages and cultural differences all affect communication. The communications management plan is the document that says how communication is planned, carried out and monitored. Writing the regional differences into it and arranging meeting times, language and channels in one place is how misunderstandings are reduced systematically, and it is exactly what tailoring communication to the project means. The answer is A.
Why the other options are wrong
- B. A management training course has no direct bearing on communication differences and does not reduce misunderstanding.
- C. A cultural awareness workshop can improve understanding, but it does not solve the scheduling problems of time zones and language. It handles only part of the issue.
- D. The political environment is only one aspect of the differences. Discussing it strays from the point and does not address time zones or language.
Key takeaway For teams spread across regions, time zones and languages, revising the communications management plan to arrange things in one place is more complete than any single training.
Variation If the stem said only that members do not understand each other's cultures, a cultural awareness activity would fit better. If the question is how to set meeting times, choose the core overlap hours when everyone is working and provide minutes for those who miss it.
- Question 32
In a weak matrix organization, the project manager of a prototype-production project receives feedback from an outside machining shop: the parameter requirements that the functional manager set for a deliverable conflict with the project manager's requirements, so machining cannot continue. What should the project manager do?
Show answer and explanation
Correct answer: C
On the project, the two managers disagree about the requirements, and the disagreement is already holding up machining. The question asks how the project manager should respond.
The stem makes clear this is a weak matrix; under common exam practice, the functional manager has more power than the project manager there. The two managers' requirements for the same deliverable conflict, and machining has already stopped, so this is a disagreement that must be resolved through communication. The project manager should consult the functional manager first and work out a solution together. That is the standard way to manage stakeholders, and it matches the approach of “when authority is short, rely on communication and negotiation”. The answer is C.
Why the other options are wrong
- A. The disagreement has already stopped machining. It is a problem that has occurred, not an uncertain risk, and it should not be recorded in the risk register.
- B. Under common exam practice, the functional manager has the greater power in a weak matrix, so the project manager cannot force the machining shop to follow only the project manager's parameters. That would deepen the conflict.
- D. The stem already tells you the reporting relationship (weak matrix). Looking it up would not resolve the disagreement and would only delay action.
Key takeaway In a weak matrix, when you disagree with the functional manager, negotiate first and solve it together. Do not go around the manager or force the other party.
Variation If the organization were functional and the information technology department delayed a project task because of other priorities, the approach would be the same: meet the department manager, find out why, and agree on a schedule. If the disagreement involves resource allocation beyond your authority, ask the sponsor to coordinate.
- Question 33
An IT project manager, on a recommendation, learns of a well-regarded new supplier of network security testing services. The project manager intends to have this supplier take part in a new project, but its quote exceeds the project budget. What should the project manager do next?
Show answer and explanation
Correct answer: A
The project manager wants a well-regarded new supplier to take part, but its rates exceed the budget. The question asks what to do next, and the key is who leads the negotiation.
PMBOK 8 says that procurement negotiation should be led by a member of the procurement team who has the authority to sign contracts, with the project manager and other members of the project management team present to assist as needed, and Appendix X4 points out that the personnel authorized to procure may be project team members, management or members of the purchasing department. A rate above budget has to be resolved through negotiation, and the stem does not say the project manager has negotiating or signing authority, so contact the procurement team so that a procurement team member with contract signing authority leads the negotiation (if the project manager has been given that authority, he or she can lead under the organization’s process). The answer is A.
Why the other options are wrong
- B. Submitting the budget gap to the management team first escalates too early without trying negotiation and bypasses the procurement function.
- C. Communicating with stakeholders cannot change the supplier’s rates and does not remove the conflict between the quote and the budget.
- D. Lowering the rates unilaterally and having the supplier sign is not negotiation, the supplier may not accept, and the project manager has not been given that signing authority.
Key takeaway When a supplier’s price exceeds the budget, the project manager works with the procurement team and negotiates through the process, without setting prices or signing alone.
Variation If the project manager holds contract signing authority and has been named lead negotiator, he or she may lead; the points negotiated still have to be written into the contract.
Reference Conducting the Procurements · Lesson 2: Evaluating Proposals: Weighting and Screening, and Procurement Negotiation
- Question 34
A project manager is in charge of developing an autonomous delivery vehicle, and the project is going well. To understand development of the navigation module, team members report percent of work complete, test pass rate, number of change requests, number of defects, actual cost and actual duration. What do these items represent?
Show answer and explanation
Correct answer: C
On the autonomous delivery vehicle project, the team reports a string of values: percent complete, test pass rate, number of change requests, number of defects, actual cost and actual duration. What are they? You decide by telling data, information and reports apart.
Work performance data are the raw observations and measurements taken directly from each activity while the project work is performed. Percent complete, number of defects, actual cost and actual duration are all typical examples. The stem lists only unprocessed values and says nothing about any analysis, correlation or integration. You decide this kind of question by asking only one thing: has it been analyzed, correlated or integrated? If not, it is data. Only after analysis and integration does it become information, and only when summarized into a document for decision-makers is it a report. The answer is C.
Why the other options are wrong
- A. A report is a document that summarizes work performance information for decisions and communication, such as a status report. The stem gives only scattered values, with no document and no conclusion.
- B. The schedule management plan sets out how the schedule is developed, monitored and controlled. It is a planning document, not values measured during the project.
- D. Information is the result of analyzing and integrating data, such as “$3,000 over budget.” The stem has only raw values, not yet analyzed or integrated.
Key takeaway Raw measurements are data; after analysis and integration they become information; summarized in a document they are a report.
Variation In the case of “9 defects, 4 more than the planned limit,” a comparison has been made, so it is work performance information. In the case of “turn the overrun and a recommendation for added budget into a status report for the sponsor,” it is a work performance report.
- Question 35
While reviewing the schedule, the project manager finds that the “mobile refactoring” team is using a new framework for the first time, but the duration estimates for its activities are still based on the efficiency of an experienced team and do not account for the learning curve. What should the project manager do?
Show answer and explanation
Correct answer: A
On review, the “mobile refactoring” team is using a new framework for the first time, but activity durations are still estimated at an experienced team's efficiency with no learning curve. What should be done?
Team proficiency is a factor that influences duration: using a new technology for the first time means lower efficiency and a need to learn and make mistakes. The estimates do not match the team's real level, so the problem should be dealt with at the estimating stage. For the affected activities, include the learning curve in the duration and update the basis of estimates so that the schedule becomes feasible. This addresses the affected activities and not the whole plan. The answer is A.
Why the other options are wrong
- B. Waiting for variances to appear and then crashing is costly and risky, and the problem can be fixed entirely at the estimating stage.
- C. Adding one block of buffer at the end of the plan does not identify which activities are affected and has no basis, so it cannot reflect the true duration of each activity.
- D. Adding resources does not necessarily offset the learning curve. The effect depends on the skills of the added people and on whether the work can be done in parallel, and new people also need training and coordination, so duration may even get longer. More importantly, now that the basis of the estimates is found not to hold, the first step is to correct the estimates and the basis of estimates for the affected activities.
Key takeaway Proficiency affects duration. In estimating, include the learning curve and update the basis of estimates.
Variation If the activity were a 24-hour stress test and the team wanted to add people to shorten it, the duration is set by the nature of the work and adding people will not shorten it. If the resource calendar shows members can give only 3 days a week, you must also re-estimate using their productive time.
- Question 36
A project manager at PMLyceum is responsible for a project whose members are spread across several countries. In past work with remote teams, the project manager found that the quality of work that members submit is often poor, and an investigation showed that the cause was that members understood the work requirements and objectives differently. For the project to deliver on time and with quality, what should the project manager do?
Show answer and explanation
Correct answer: A
The project's members are spread across several countries, and in past work with remote teams the quality of submitted work was poor. The question is what the project manager should do for the project to deliver on time and with quality.
Quality is poor because members do not fully understand the requirements and objectives, and in a remote setting deviations are more likely. Establishing clear objectives with members through team meetings and one-on-one conversations lets each person understand the expectations and their own role, and also builds a sense of responsibility, which raises quality at the source. The answer is A.
Why the other options are wrong
- B. Time records show how much time was spent. They can make management more efficient, but they do not ensure that the work meets requirements.
- C. Taking turns to report progress solves information sharing, but the stem does not say information is opaque, so it does not target the quality problem.
- D. Peer evaluations scheduled for the end of the project are an after-the-fact measure with no effect on quality during execution.
Key takeaway For remote teams to deliver quality, first make the shared objectives and expectations clear through team-wide and one-on-one communication.
Variation If the stem said remote members “understand the objectives but lack tools,” first provide the collaboration tools; if new members join, have them learn and accept the ground rules the team already has.
- Question 37
A membership system development project for a convenience store chain has been running for a while. Several members complain to the project manager that their workloads are too heavy and that resources are unevenly allocated. The project manager cannot add resources for now and also notices that several tasks have no clear owner and are repeatedly passed among members, each saying “that's your job”. What should the project manager do?
Show answer and explanation
Correct answer: D
Members complain of heavy workloads and uneven allocation, the project manager cannot add resources, and some members pass their tasks to others. Taken together, the two signals show that members are not clear about what each of them should do.
Passing tasks around is a typical sign of unclear responsibility, and being unable to add resources closes off the option of adding people. Reviewing the responsibility assignment matrix with the team lets you check task by task whether each has a clear accountable and responsible person and lets members confirm their own responsibilities, which cuts passing at the root. Whether workloads are out of balance should be dealt with after responsibilities are clear, by looking at each person's workload and availability. The answer is D.
Why the other options are wrong
- A. The project manager should first review and clarify the existing responsibility assignments. If changing people or responsibilities exceeds the project manager's authority, the functional manager can then be consulted or the matter escalated. Immediate escalation does not first resolve the current lack of clear responsibility boundaries.
- B. An even split looks fair, but tasks and members' skills differ, so equal is not reasonable. More importantly, responsibilities would remain unclear and passing would continue under any new split.
- C. The resource breakdown structure divides resources by category and type for acquiring and reporting resources. It has nothing to do with how responsibilities are split among members.
Key takeaway When members pass tasks to each other, it signals unclear responsibility. First go back over the responsibility assignment matrix with the team.
Variation If the stem said clearly that idle resources could be reassigned, consider moving idle resources to overloaded members (resource leveling is used only when resource conflicts must be solved by adjusting activity dates). If several people assign work to one member at the same time, the answer is again to use RACI to name a single accountable person.
- Question 38
A project manager starts an early-stage project to explore a new product. The sponsor and the main stakeholders are bound by specific agreements and confidentiality requirements that prevent them from disclosing their sensitive information to one another. Several of them have never worked together and none is familiar with the field. To define the requirements, which data gathering technique should the project manager mainly use?
Show answer and explanation
Correct answer: C
The project manager starts an early-stage project to explore a new product. The sponsor and main stakeholders are bound by confidentiality requirements, several have never worked together and none knows the field. The question asks which data gathering technique to mainly use.
An interview is a direct conversation with a stakeholder. It can be done one-on-one, so sensitive or confidential information can be obtained under conditions of trust and confidentiality, and it does not require the participants to share information with one another. The confidentiality and unfamiliarity in the stem make group discussion methods unsuitable. When choosing a technique, start with the constraints of the situation: where confidentiality applies and participants are strangers to one another, group discussion techniques fit less well than interviews. One-on-one conversation makes it easier to control who learns sensitive information, to build trust step by step and to obtain key stakeholders' requirements directly, so interviews are the first choice in this kind of situation. The answer is C.
Why the other options are wrong
- A. Brainstorming generates ideas as a group and needs members to exchange openly. Where there is confidentiality and the members are strangers, it fits less well than interviews.
- B. Benchmarking compares practices with those of other organizations, mainly to compare practices and inspire improvement. It cannot replace interviewing the sponsor and key stakeholders about their requirements.
- D. A focus group brings pre-qualified stakeholders together to discuss. Members learn what the others say, so under confidentiality requirements and among strangers they are likely to hold back.
Key takeaway Where confidentiality or sensitive information is involved, use interviews.
Variation If the stakeholders know each other, have no confidentiality needs and a consensus is needed quickly, a focus group or a facilitated workshop may be used. If there are many people in scattered locations, use questionnaires.
Reference Requirements Elicitation · Lesson 3: Requirements Elicitation Techniques: From Brainstorming to Prototypes and Facilitation
- Question 39
A project manager is in charge of the interior fit-out of an office building and plans to outsource the curtain wall installation. After the bids came in, the team finished evaluating the proposals and has selected one supplier, but the structure of the contract and its terms have not yet been confirmed with that supplier. What should be done next?
Show answer and explanation
Correct answer: D
The project is in the middle of conducting the procurements. The proposals have been evaluated and a supplier determined, but the contract terms have not yet been confirmed with it. The question asks for the very next work.
The signals: the proposals are evaluated and the supplier is selected, but “the structure of the contract and its terms have not been confirmed”. After the seller is selected and before the contract is signed, what you do is procurement negotiation: clarify the structure of the contract, the parties’ rights and obligations and the other terms so that both sides reach a shared understanding, and the final contract wording reflects everything agreed. The answer is D.
Why the other options are wrong
- A. The statement of work is written after the decision to outsource and before the bid documents are issued. Since the proposals have already been evaluated, a statement of work obviously exists.
- B. The bidder conference is held before proposals are submitted so that all potential sellers understand the same thing. The seller has already been selected, so that step is long past.
- C. Awarding the contract before the terms are confirmed leaves rights and obligations unclear. It means signing first and negotiating afterward, and it leaves the seeds of disputes.
Key takeaway After the seller is selected and before the contract is signed, conduct procurement negotiation first.
Variation If negotiation reaches a deadlock, first communicate face to face to move it forward, and if there is still no result start a fallback; if you find during negotiation that the contract protects the buyer too little, fill the gap before signing.
- Question 40
Every time the team borrows the company's shared test server, it must go through a three-day approval, and three tasks have already been blocked this week. This is an impediment from organizational process. What should the project manager do?
Show answer and explanation
Correct answer: B
Each time the team borrows the shared test server it must go through a three-day approval, and three tasks are blocked this week. The stem already identifies this as an impediment from organizational process. What should the project manager do?
A process impediment sits at the organizational level. The project manager first assesses its impact on the schedule and then coordinates with the process owner, for example for an expedited channel or pre-authorization; if coordination fails or the matter exceeds his or her authority, it is escalated along the escalation path. The order is assess, coordinate, and escalate if necessary. The project manager first does what can be done within his or her own authority and only then considers escalation, in line with “coordinate first, escalate later.” Process owners can often provide an expedited channel or pre-authorization, which is more reliable than bypassing the process. The answer is B.
Why the other options are wrong
- A. Bypassing the approval violates organizational process and creates new compliance and management problems.
- C. Submitting requests in one batch on its own, without coordinating with the process owner, only adapts to the process; tasks already blocked remain unresolved.
- D. Moving the tasks out of this week only avoids the impediment without trying to remove it, and it also costs schedule.
Key takeaway For an organizational process impediment: assess the impact, coordinate first, escalate only if necessary, and never bypass the process.
Variation If the same approval blocks the project every month, then besides coordinating, give the process owner suggestions for improvement, backed by data on how long it takes.
- Question 41
A chain of training centers launches an online course development project. Members come from instructional design, art, technology and other departments, and the project takes up only part of their time; the rest of the time they work as scheduled by their home departments. The project manager wants to know clearly when each member can take part and for how long. What should be done?
Show answer and explanation
Correct answer: C
The members of an online course development project come from several departments, and the project takes only part of their time; the rest follows their home departments' schedules. The question asks how to know “clearly” when each member can take part and for how long, so the point is knowing availability.
A resource calendar records, resource by resource, the working days, shifts and leave, and shows when a team member is available and for how long. Part-time members' available time is scattered and changes, and only if it is recorded in the resource calendar and kept up to date can the project manager know it clearly, which also helps with scheduling and resource assignment. The answer is C.
Why the other options are wrong
- A. Having the sponsor negotiate hours addresses “whether the resource can be given.” It does not produce a record of available time that can be checked at any time.
- B. The team charter sets out values, how to communicate and decide, ground rules and so on. It is not a tool for recording members' available time.
- D. Verbal agreements with functional managers one by one produce no record and can change at any time, so the project manager still does not know who is available when.
Key takeaway To know who can work when, look at the resource calendar; negotiation can only secure resources and cannot replace a record.
Variation If the question asked “what to do when a member is tied up by another department and cannot attend,” negotiate hours with the functional manager; if it asked “what is the basis for scheduling,” the basis is likewise the resource calendar.
- Question 42
A project manager convenes a workshop of senior managers for a new membership program build, going through the project's strengths, weaknesses, opportunities and threats one by one. Which process is she carrying out?
Show answer and explanation
Correct answer: C
For a new membership program build, the project manager convenes senior managers for a workshop and goes through the project's strengths, weaknesses, opportunities and threats one by one. The question asks which process she is carrying out.
Going through strengths, weaknesses, opportunities and threats is SWOT analysis, a data analysis technique used when identifying risks: first find the project's strengths and weaknesses, then the opportunities and threats that follow from them, and thereby find risks. Its purpose is to find risks, not to rank them or choose strategies, so it belongs to Identify Risks, and having senior managers take part helps find strategic-level risks. The answer is C.
Why the other options are wrong
- A. Plan Risk Management defines how risk management activities will be carried out and produces the risk management plan; SWOT analysis is not a typical tool for it.
- B. Perform Risk Analysis includes qualitative analysis, which assesses probability and impact and ranks risks, often with a probability and impact matrix, not SWOT.
- D. Plan Risk Responses chooses response strategies for the risks already analyzed, and SWOT is not used in that step.
Key takeaway SWOT analysis is a tool of the Identify Risks process.
Variation If the workshop assessed probability and impact on risks already listed, it would be Perform Risk Analysis; if it chose avoid or mitigate strategies for those risks, it would be Plan Risk Responses.
Reference Risk Register · Lesson 3: Analysis Techniques, Prompt Lists, the Risk Register and the Risk Report
- Question 43
An agile team is developing a waybill system for a logistics company. Development is going well, but the client representative is lukewarm and has repeatedly missed the iteration review meetings. After talking with the client representative, the project manager learns that he has simply not realized how much early feedback matters to the results. The team reports that it cannot get timely feedback and cannot confirm whether the delivered work meets the needs. What should the project manager do?
Show answer and explanation
Correct answer: B
An agile team is developing a waybill system. Development is going well, but the client representative is lukewarm and keeps missing the iteration reviews, so the team gets no timely feedback and cannot tell whether the delivered work meets the needs. You must decide how the project manager should respond.
The success of an adaptive project depends on continuous client involvement and quick feedback, and the review is the key moment for getting it. The project manager has already learned that the client is absent because he has not realized the value of early feedback, and his absence directly leaves the team without feedback. So the project manager should explain that value (for example, the earlier deviations are found, the cheaper the rework) to win his attendance in person. Outside consultants, indirect collection and pausing the iteration all bypass the client himself and do not address the root problem, which is his unwillingness to take part. The answer is B.
Why the other options are wrong
- A. An outside consultant knows the business but is not the client; his opinion cannot replace the client's confirmation of requirements, and you still would not know whether the client accepts the work.
- C. Email and phone can serve as supplementary or interim feedback channels, but C does not directly address the client's repeated absence from reviews and continuing lack of involvement. Nor does it ensure the client reviews the work with the team and confirms requirements promptly, so it is weaker than B.
- D. What the team lacks is feedback, not requirements. Pausing the iteration and redoing requirements gathering wastes the progress already made and still does not get the client to attend the reviews.
Key takeaway When a client's involvement is low, first help the client see the value of taking part and giving feedback; do not use substitutes to bypass the client.
Variation If the client is willing to take part but cannot give feedback in time, you can agree on a fixed review time or designate a client representative with decision authority. If the client is absent because of a disagreement, it has to be resolved through negotiation.
Reference Stakeholder Engagement · Lesson 3: Managing Stakeholder Engagement: Follow the Plan, and Use Interpersonal Skills for Concerns and Conflict
- Question 44
A project manager responsible for deploying a chain store's checkout system is very dissatisfied with the terminal equipment supplier, whose deliveries are always late and often lack key components. The company has decided to terminate the contract and replace the supplier, but the only candidate for the new supplier is an overseas company. To move this replacement forward, what should the project manager do FIRST?
Show answer and explanation
Correct answer: A
On a project, the company has decided to terminate the contract and replace the supplier. The question asks what the project manager does “first”.
Terminating a contract and replacing a supplier involve contract terms and legal consequences and should be handled by people in the organization who have the appropriate procurement or contract authority, following the process. Here there is a procurement department, so the project manager should first bring it in to help terminate the existing contract and move the follow-on procurement forward. Learning about culture, hiring a translator and finding contacts are preparations to take up once the termination and procurement arrangements are clear, and they are not the first thing to do. The answer is A.
Why the other options are wrong
- B. Cultural differences matter when negotiating with the new supplier, but that is preparation to take up after the termination and the new procurement arrangements are clear. It is not the first thing to do.
- C. A translator is preparation for communicating with the overseas supplier. The existing contract has not yet been dealt with, so this is not the first step.
- D. Finding mutual contacts is a way to approach the new supplier. The existing contract has not been dealt with, so this is not the first step either.
Key takeaway Early termination and replacing a supplier should be handled by people with procurement or contract authority. In this question, the project manager first brings in the procurement department.
Variation If the question asks what to do about work already done after termination, work completed and accepted is paid as agreed, and whether the seller's preparatory work is compensated depends on the reason for termination and the contract terms. If you are unsure whether there is a right to terminate, check the contract's termination clause first.
- Question 45
An energy management software project produces a detailed status assessment report every month, but the project steering committee has never made a decision based on it, and the reports are just filed. What should the project manager do?
Show answer and explanation
Correct answer: A
The project is being executed and monitored, and a detailed status assessment report is produced monthly, but the steering committee has never made a decision based on it, and the reports are just filed. What should the project manager do?
The purpose of work performance reports and status assessments is to prompt decisions, drive action or draw attention. A report that is only filed has not met its purpose, and the problem is not how much it says but that the results have not turned into action. The project manager should distill the assessment results into specific decision recommendations, making clear who needs to decide what and by when, and submit them to the right parties for decision. The answer is A.
Why the other options are wrong
- B. Even if a report supports filing, audits or awareness, it still does not resolve the governance problem in this scenario if it fails to prompt the decisions or actions currently needed. Continuing unchanged only lets the status quo persist.
- C. Shortening the report changes only its form. It does not say who needs to decide what, and the committee may still do nothing.
- D. Canceling regular assessments means problems are found later, and ad hoc reports also need conclusions that can be turned into action, so this is the same thing in a different form.
Key takeaway The value of a status assessment lies in prompting decisions and action; turn the results into decision recommendations.
Variation If the committee does not decide because authority is unclear, first clarify decision authority and the escalation path, and then submit the recommendations to the people who have authority.
Reference Monitor and Control Project Performance · Lesson 2: Work Performance Reports and Status Reports: Making Reports Drive Decisions
- Question 46
During execution of an omnichannel retail project, the customer’s representative keeps raising new requirements and repeatedly asks to see usable results as soon as possible. The project’s requirements were never fully settled, the project manager anticipated this before work began, and says the team will accommodate the requests as far as possible. Which development approach is the project manager MOST likely to use?
Show answer and explanation
Correct answer: B
The project is in execution; the customer’s representative keeps adding requirements and pressing to see usable results, and the requirements were never settled. You must judge which approach is most likely.
The Standard says that adaptive approaches are useful when a project’s requirements and technical solution are subject to a high level of uncertainty and volatility and are likely to change significantly throughout the project. The stem has two signals: the requirements were never settled and the project manager expected them to change before work began, and the customer keeps raising requirements and repeatedly asks to see results soon. An adaptive approach, through short iterations or flow-based working, keeps collecting feedback, adjusts the backlog, and delivers frequently, so it can both absorb the new requirements and show results early. The answer is B.
Why the other options are wrong
- A. A predictive approach relies on fairly complete requirements up front. Changes can be handled through controlled change control, but it is inefficient when requirements keep emerging and results are needed quickly.
- C. A hybrid approach suits projects in which some requirements are stable and others uncertain. The stem does not mention stable components that would need to be managed predictively on their own, and the information given points more directly to an adaptive approach as a whole.
- D. A predictive approach with incremental delivery does deliver in batches, but the overall scope remains largely fixed, so it can hardly accept new requirements that keep appearing.
Key takeaway Requirements that keep changing, together with a need for frequent delivery, call for an adaptive approach.
Variation If the stem were changed to “the overall requirements are clear and only a basic version is required first,” the answer would become incremental delivery within a predictive approach. If it also said that part of the requirements were already fixed, you would have to consider a hybrid approach.
- Question 47
Halfway through a review meeting, an executive at PMLyceum paged through the interim deliverables of the mobile app and, on the spot, pointed out several places that did not match his expectations. He demanded rework item by item, and the iteration schedule slipped as a result. The project manager is stunned: at every earlier status meeting this executive only listened and said nothing. Looking back, what should the project manager have done to avoid this situation in advance and keep the project on track with the project management plan?
Show answer and explanation
Correct answer: C
At a review meeting, an executive suddenly points out many mismatches with his expectations and demands rework item by item, although he only listened and never spoke at earlier status meetings. In hindsight, you must determine how this could have been avoided.
The key signal is “only listened, then objected at the review”: this executive has strong influence but was never really engaged, and his expectations were never aligned up front. The stakeholder engagement plan is exactly the document that plans how each stakeholder will take part, including having them join reviews early, see interim results early and state their expectations. Bringing a silent, key stakeholder in early and aligning expectations in advance means no surprises at the review, and the project can stay on track with the project management plan. The other options deal with something else and do not address the root cause, which is that the executive was never engaged. The answer is C.
Why the other options are wrong
- A. A risk management plan sets out how risk management will be carried out and who is responsible. It does not plan how one executive will take part in reviews and does not get his expectations heard early.
- B. An issue log records problems that have already occurred, so it tracks them after the fact. The executive's dissatisfaction did not surface before the review, so there was nothing to log.
- D. Passing the executive's silence on to the sponsor only shifts the responsibility. The executive himself is still not engaged, and the sponsor cannot judge on his behalf whether silence means agreement.
Key takeaway For a stakeholder with high influence who stays silent, use the engagement plan to arrange his involvement early; do not wait for the review to hear his views.
Variation If the executive had already raised comments requesting a scope change, first clarify the request with him and check it against the approved scope and baselines. If it exceeds the approved scope, assess the impact, then submit a change request under the change management plan for approval by the authorized person or CCB before any rework. If he were a newly appearing executive, add and analyze him in the stakeholder register, then update the engagement plan.
Reference Stakeholder Engagement · Lesson 1: Planning Stakeholder Engagement and the Stakeholder Engagement Plan
- Question 48
The interface documentation the project needs is supplied by an external partner, which is already several days late, so the team cannot proceed with integration development. What should the project manager do?
Show answer and explanation
Correct answer: A
The interface documentation for the project comes from an external partner, which is already several days late, and the team cannot start integration development. What should the project manager do?
The key signals are “external partner” and “already several days late”: the impediment comes from outside and the team cannot solve it on its own, so the project manager has to coordinate actively. The first step is to talk with the partner, find out why it is late, and agree on how to deliver; that moves the problem forward and also protects the relationship. Escalating level by level can follow if communication fails. The answer is A.
Why the other options are wrong
- B. Writing interfaces based on one's own understanding and revising them once the documentation arrives carries a high risk of rework later. It only works around the impediment and does not remove it.
- C. Going over the counterpart's head and writing to his or her superiors at the outset is excessive escalation that can damage the relationship; communicate directly first.
- D. Pushing the whole task back passively accepts the delay without trying to remove the impediment, and it delays the whole plan.
Key takeaway For an impediment caused by an external dependency, communicate and coordinate first, find out the reason and agree on a way forward, and escalate level by level only if necessary.
Variation If the partner says clearly after discussion that it cannot deliver, assess alternatives and adjust the plan through the change control process.
Reference Issue Management · Lesson 4: Removing Impediments: Impediments vs. Issues, Types and Handling
- Question 49
The sponsor is worried that the project has several risks but cannot say which one has the greatest effect on the cost objective. Which tool should the project manager use to address this concern?
Show answer and explanation
Correct answer: D
The sponsor is worried that the project has several risks but cannot say which has the greatest effect on the cost objective. The project manager must choose a suitable tool to address this concern.
“Which one has the greatest effect” is about the relative size of each factor's effect, which is exactly what sensitivity analysis answers. In PMBOK 8 it correlates variations in project outcomes with variations in elements of the quantitative risk analysis model, and the results are usually shown in a tornado diagram. By common exam practice, the analysis lets “one uncertain factor at a time vary across its range” and sees how much total cost changes, then arranges the factors from largest effect to smallest. The bars at the top correspond to the factors that most deserve priority management. What is needed here is “ranking by size”, not “comparing options” or “finding causes”. The answer is D.
Why the other options are wrong
- A. Decision tree analysis compares the expected monetary value of alternative courses of action. The stem has no options to choose among, and it is not comparing the size of the effects of the risks.
- B. A cause-and-effect (fishbone) diagram traces the causes of a problem and helps find root causes. It does not quantify the effect of each risk on the cost objective and cannot rank them by size.
- C. SWOT analysis is used to identify risks by laying out strengths, weaknesses, opportunities and threats. It gives no numeric effect of each risk on cost and cannot answer “which is greatest”.
Key takeaway To know which risk or factor has the greatest effect, use sensitivity analysis, with the result drawn as a tornado diagram.
Variation If the question were changed to “find out how much each factor affects cost on its own”, the answer is still sensitivity analysis. If it asked “which piece of risk work is this?”, the answer is quantitative analysis within Perform Risk Analysis.
- Question 50
An iterative project has 150 user stories, delivered evenly over 6 iterations (the same number of user stories is planned for each iteration). Each user story has a budgeted value of $4,000. Halfway through the planned schedule, cumulative actual spending is $260,000 and 75 user stories have been delivered. Which assessment is correct?
Show answer and explanation
Correct answer: C
The iterative project measures work by the number of user stories delivered. The planned schedule is half over, and both schedule and cost status must be judged.
Convert story counts into budget value first, then use earned value to compare against both baselines: schedule by EV versus PV, cost by EV versus AC. The same number of stories is planned in each iteration, so by the halfway point 75 stories should have been delivered (PV = 150 ÷ 2 × $4,000 = $300,000). 75 stories were delivered, so EV = PV and the schedule is on plan. Spending of $260,000 is below the $300,000 value of the work completed, so costs are under plan. The answer is C.
- PV = 150 ÷ 2 × $4,000 = 75 × $4,000 = $300,000
- EV = 75 × $4,000 = $300,000; AC = $260,000
- SV = EV − PV = 0, so the schedule is on plan; CV = EV − AC = $300,000 − $260,000 = +$40,000, so costs are under plan
- Check: SPI = 1.0 and CPI = $300,000 ÷ $260,000 ≈ 1.15, consistent with the conclusion
Why the other options are wrong
- A. The schedule is indeed on plan, but CV = +$40,000: actual spending is $40,000 less than the value of the work completed, so it is not exactly on budget.
- B. This compares spending of $260,000 with PV of $300,000 and concludes that spending less means doing less. Schedule is judged by EV against PV, and both are $300,000, so the project is not behind.
- D. A positive CV is not an overrun, and an SV of zero is not behind schedule. Both the signs and the comparison values are misused.
Key takeaway Schedule is EV against PV and cost is EV against AC. Never compare AC directly with PV.
Variation If only 60 stories had been delivered with the same $260,000 spent, EV = $240,000, SV = −$60,000 and CV = −$20,000: behind schedule and over budget.
Reference Earned Value Management · Lesson 2: Variance Analysis: Schedule Variance (SV) and Cost Variance (CV)
- Question 51
An online education platform project is in execution. The team holds a review meeting with the customer so that the customer can accept the platform. Before the meeting, the team had verified that indicators such as concurrent-user capacity meet the specified quality standards, and at the meeting the customer's representative checked the platform against the acceptance criteria and formally signed to accept it. Which piece of work did this meeting accomplish?
Show answer and explanation
Correct answer: D
In execution, a review meeting is held so the customer can accept the platform. The team had verified capacity and similar indicators beforehand, and the customer's representative then checked against the acceptance criteria and formally signed. The question asks which work this meeting accomplished.
The meeting's result is that the customer's representative, after checking against the acceptance criteria, formally accepted the platform. That is Validate Scope. PMBOK 8 gives Validate Scope two objectives: checking the processes used to achieve quality standards and formalizing acceptance of the deliverables. Accepted deliverables result only when the deliverables meet the applicable quality standards (or deviations have been approved through governance and change procedures) and someone with acceptance authority formally accepts them. Here the team verified the quality indicators before the meeting, and what happened at the meeting was the customer's acceptance. To decide which work it is, look at who is doing what: the customer accepting corresponds to Validate Scope. The answer is D.
Why the other options are wrong
- A. A quality audit is a structured, independent review of quality processes and activities, performed by independent reviewers. The stem contains no such review, only the customer accepting at the meeting.
- B. Project closure is the work of ending the project or phase after acceptance. The stem says the project is still in execution, and the meeting's content is acceptance of the platform, not closure.
- C. Quality control, the team checking deliverables against quality standards, is what the pre-meeting check of capacity and the like was. The “acceptance” decided at the meeting is made by the customer and is not internal verification by the team.
Key takeaway Look at who acts: the customer formally accepting a deliverable is Validate Scope; the team checking that it passes is verification.
Variation If the customer's representative had found the capacity short and refused to accept, the meeting would still be Validate Scope, only with the result that acceptance was not granted; the reasons would then be recorded and remedied through change control.
Reference Validate Scope · Lesson 1: Purpose and Position of Validate Scope: Verify First, Then Accept
- Question 52
Two teams at a consulting firm schedule the same project with different methods: Team A uses the critical path method and Team B uses the critical chain method. Which of the following is a difference between the two?
Show answer and explanation
Correct answer: B
Two teams schedule the same project with different methods: A uses the critical path method and B uses the critical chain method. The question asks how the two differ.
PMBOK 8 explains that critical chain project management aggregates task-level (or sprint-level) variability into a project buffer and allocates that buffer only when and where needed to protect the due date. It uses nearly identical scheduling logic to the critical path method, and both are based on critical path analysis calling for a resource-loaded and resource-leveled critical path. The only meaningful difference in logic is that critical chain project management also calculates the percentage of the project buffer remaining and compares it with the percentage of the critical chain remaining, producing the “buffer protection index” and giving all participants a real-time signal of schedule performance. Option B describes exactly this difference. The answer is B.
Why the other options are wrong
- A. This does not match PMBOK 8: both methods call for a resource-loaded and resource-leveled critical path, so you cannot say that Team A ignores resources or that Team B does.
- C. Critical chain project management uses nearly the same scheduling logic as the critical path method and still uses the logical relationships between activities; it does not sequence by resource availability alone.
- D. The scheduling logic of the two methods is nearly identical, but critical chain project management monitors progress with a project buffer and the buffer protection index, so the way of monitoring is different, not exactly the same.
Key takeaway The difference between critical chain project management and the critical path method: safety is pooled into a project buffer and progress is monitored with the buffer protection index.
Variation If the question instead asked how the buffer protection index differs from the schedule performance index (SPI), the answer is that the former protects the due date and the latter measures how far the project is from the schedule baseline.
- Question 53
The project has entered formal closure, and all four activities below remain outstanding. In common exam practice, which should usually be completed FIRST?
Show answer and explanation
Correct answer: B
The question asks which of four tasks ranks first in the general closure sequence, so it tests the order of closure steps.
Common exam practice is that formal acceptance and receipt of the deliverables is an important precondition of closure and comes before the other closure activities. Lessons learned and organizational process asset updates can go on throughout the project and are compiled into the repository at closure. Releasing resources comes after the necessary closure and knowledge handover are done. Of the four options, customer acceptance and receipt of the deliverables fits best at the very front. The answer is B.
Why the other options are wrong
- A. Lessons learned can be registered throughout the project, but the project-wide summary at closure is, by common exam practice, done after the results are accepted, so it is not the first item.
- C. Releasing resources usually comes after the necessary closure and knowledge handover. If people are released first, there is nobody left to do the later work.
- D. Updating organizational process assets puts lessons learned and similar information into the organizational knowledge repository, and is usually done as a compilation after acceptance and summarizing.
Key takeaway Formal acceptance and handoff are an important precondition of closure; release resources as planned after the necessary closure and knowledge handover are complete.
Variation If the options were changed to compare “summarize lessons learned” with “update organizational process assets”, the summary usually comes first and the repository entry after. If comparing “celebrate” with “disband the team”, celebrating usually comes first.
- Question 54
On a restaurant chain's new ordering system project, the members come from three departments: R&D, operations and store training. While preparing the pilot, R&D and operations get into an argument: R&D is determined to launch on time and within budget, while operations insists the system must fit the stores' actual ordering workflow. What should the project manager do?
Show answer and explanation
Correct answer: C
On a new ordering system project, members come from R&D, operations and store training. During pilot preparation, R&D wants an on-time, within-budget launch and operations insists the system fit the stores' real ordering workflow. The groups argue. The question asks what the project manager should do.
Both groups' demands have merit: one concerns delivery, the other whether the system can actually be used in the stores. The project manager should push the groups to discuss together, put their real needs on the table and find an approach that is on time, within budget and fits the store workflow. That is collaborate/problem-solve, aimed at a win-win. In the process, the two groups' demands can be listed side by side so that the project manager does not listen only to the louder side. The answer is C.
Why the other options are wrong
- A. Urging each side to give a little is compromise/reconcile, which may leave the core needs of both groups unmet.
- B. Deciding that R&D's position is sound takes sides and ignores operations' needs. The system might not work in the stores.
- D. Having the groups each submit a plan and comparing them encourages competition, which would intensify the conflict and hurt cohesion.
Key takeaway When each side's demands are legitimate, get them to discuss together and find a way that serves both.
Variation If the system had to go live the day after the pilot began, requiring a plan that same day, and the project manager had the authority, force/direct could be used; otherwise the project manager should still push the team toward quick, collaborative decision-making.
- Question 55
The procurement payment plan the project manager prepared states that equipment payments will be made in a single prepayment before the supplier ships. The finance department points out that the organization's financial policy requires equipment payments to be made in installments at acceptance milestones. What should the project manager do?
Show answer and explanation
Correct answer: A
The payment arrangement in the procurement plan conflicts with the organization's financial policy. The question tests how binding organizational policy is on the project and the order of handling when they conflict.
Organizational policy is a compliance requirement that organizational governance places on the project, and one function of organizational governance is to enforce compliance requirements through policies and procedures. The signal is “the financial policy requires equipment payments to be made in installments at acceptance milestones”: this is a rule, not a suggestion. The project manager cannot bend it for project convenience. First make the plan conform to the policy and pay in installments at acceptance milestones; if an exception is truly needed, apply to the finance department through the prescribed channel. The answer is A.
Why the other options are wrong
- B. Shortening delivery time is the project's own consideration and cannot override organizational policy. A deviation from the policy needs the prescribed approval and is not something the project simply keeps.
- C. Violating first and explaining afterward leaves it to the audit to find the violation. Compliance requirements should be met in the planned arrangements and not remedied after the fact.
- D. You cannot assume the policy will be revised in time for this project, and suspending procurement to wait for an uncertain revision only causes delay. Run the project under the current policy first and apply for an exception if one is truly needed.
Key takeaway When the plan conflicts with organizational policy, follow the policy first, and if an exception is truly needed, apply through the prescribed channel.
Variation If the stem changed to “organizational policy conflicts with a contract term”, you would still first work out how binding each is and handle it through the legal and management channels prescribed, not decide on your own as project manager.
- Question 56
An events company is preparing an outdoor light show. During risk identification it finds that a protective coating to be used at the venue fails if applied in rain, and the application window falls in the local rainy season. The event date cannot move and the coating must be completed. The project manager decides to take no action: work will go ahead in the rainy season as usual, and if the coating fails the team will accept the rework. Which response strategy is this an example of?
Show answer and explanation
Correct answer: D
An outdoor light show project has identified a threat that the protective coating will fail in the rainy season. The event date cannot move and the coating must be completed, so the project manager decides to take no action and to redo the work if the coating fails. Which threat response strategy is this?
The deciding phrases are “take no action” and “accept the rework if it fails.” The accept strategy acknowledges that the threat exists and takes no proactive action; it suits threats that cannot be addressed cost-effectively in another way, and the threat is dealt with if it occurs. The strategy is accept because the project manager explicitly decides to take no proactive measures and the project bears the rework if the coating fails; the fixed date and the coating that must be finished only show that avoidance, such as moving the date or cancelling the work, is not available. The answer is D.
Why the other options are wrong
- A. Avoid takes action to eliminate the threat, for example by working outside the rainy season or changing the material. But the date cannot move and the coating must be completed, and the stem says this is not done, so the threat remains.
- B. Transfer gives the responsibility and consequences to a third party, usually through a contract or insurance. The stem contains no external sharing arrangement, so the project still bears the rework.
- C. Mitigate proactively reduces probability or impact, for example by putting up a rain cover. The stem says explicitly “take no action,” so nothing reduces the probability or the impact.
Key takeaway Choosing to take no action, carry on and redo the work if it happens is the accept strategy.
Variation If the project manager set aside a contingency reserve for the rework, it would be active acceptance. If a rain cover were built to lower the chance of failure, it would be mitigate.
Reference Risk Response Strategies · Lesson 2: Strategies for Threats: Escalate, Avoid, Transfer, Mitigate, Accept
- Question 57
On the operations project team of a software outsourcing company, each member has their own daily start time, and at times the overlap in working hours is very short. Interaction within the team has dropped and efficiency has fallen with it. What should the project manager do?
Show answer and explanation
Correct answer: A
On an operations project team, members each have their own start times and the overlap in working hours is sometimes very short, so interaction drops and efficiency falls. The question is what the project manager should do, based on how to handle working hours that do not line up.
The team charter records the ground rules the team has agreed on. Having the team discuss and agree a block of core working hours when everyone is on duty increases the overlap, and because everyone agreed to it, it is easier to follow. It is also consistent with the principle that ground rules should be set with everyone taking part. The answer is A.
Why the other options are wrong
- B. Requiring those who start later to come in earlier means the project manager is unilaterally asking some people to adjust, without consulting everyone. It invites resistance; even if imposed as a ground rule, it would be less effective than one agreed by the team.
- C. Assigning each member an overlap window and enforcing it is still a top-down arrangement. The team does not discuss it or reach consensus, so it is less effective than a schedule the team agrees itself.
- D. Requiring everyone to start at the same moment ignores each member's circumstances. It is also imposed, and a one-size-fits-all rule does not improve the quality of collaboration.
Key takeaway When working hours do not line up, have the team agree core working hours in the team charter rather than having the project manager designate them unilaterally.
Variation If the team spans several time zones with almost no overlap, agree in the charter on rotating meeting times and on how synchronous and asynchronous communication are used. The thinking is the same: the team decides together.
- Question 58
A home appliance company's new product packaging project is in execution. The project manager has the team keep tracking the identified risks in the risk register and assess whether risk management is effective. During tracking, a risk with an active response strategy and allocated contingency reserve occurs, and dealing with it requires extra cost. What should the project manager do?
Show answer and explanation
Correct answer: A
During execution, the team tracks the identified risks in the risk register. One of them occurs, and dealing with it requires extra cost. You must judge what to do.
The core basis for the judgment is that the risk is identified. When an identified risk has an active response strategy and allocated contingency reserve, implement that response when the risk occurs and use the reserve in accordance with the financial management plan, reserve use approach and applicable authority. Under common exam practice, the project manager uses it within their authority and keeps a record. Whether contingency reserve is inside the cost baseline and whether its use needs separate approval depend on the project's budget structure and the organization's governance rules; in the common case it is used under the response plan with no separate change. The answer is A.
Why the other options are wrong
- B. The risk is already identified, so what matters first after it occurs is executing the planned response, not running a quantitative risk analysis on the spot. Not every identified risk needs quantitative analysis.
- C. Management reserve is for unidentified risks (unknown-unknowns). The cost of an identified risk is borne by contingency reserve, and releasing management reserve requires a change.
- D. The stem does not say that the planned response is ineffective or that the risk conditions have changed, so handle it under the existing response plan first. If the response proves ineffective or circumstances change after implementation, reassess and update the response, and activate a fallback plan if necessary.
Key takeaway When a risk with an active response strategy and allocated contingency reserve occurs, use that reserve under the response plan and applicable authority; whether a separate change is needed depends on the budget structure and governance rules.
Variation If this risk were not in the risk register, use management reserve and submit a change request. If contingency reserve is used up while the identified risk may still occur, submit a change request to increase contingency reserve.
- Question 59
Predictive projects usually verify quality through phase-based testing and inspection. A customer service system for an insurance company is being developed by an agile team that follows lean thinking. How should quality be managed on a project like this?
Show answer and explanation
Correct answer: A
Predictive projects usually verify quality through phase-based testing and inspection. An insurance company's customer service system is being developed by an agile team that follows lean thinking. The question asks how quality should be managed on a project like this.
PMBOK 8 points out that on agile or adaptive projects quality assurance can be performed formally or informally depending on context, and that the team is self-organizing and self-managing. Members of an agile team share responsibility for quality, improving continuously within iterations and solving the problems they meet, instead of relying on phase-based external inspection or instructions from above. Lean's emphasis on continuous improvement and eliminating waste is consistent with this. The answer is A.
Why the other options are wrong
- B. More testing is only one quality control measure. It does not show the characteristic of the team being responsible itself and improving continuously.
- C. A coach's job is to guide and help the team build its capability, not to check the team's quality item by item. Guarding quality for the team goes against self-organization.
- D. Having a team leader give the order is a command-and-control approach, and it goes against self-organization and the principle that the whole team shares responsibility for quality.
Key takeaway In agile, quality is the shared responsibility of a self-organizing team, which improves itself and solves its own problems.
Variation Predictive projects usually use more formal, planned-in-advance quality assurance and phase-based testing. In an adaptive environment, the team relies more on iteration reviews, retrospectives and the definition of done to check and adjust in good time.
Reference Quality Planning and Assurance · Lesson 5: Quality Reports, Quality Control Measurements and Quality Practices in Adaptive Environments
- Question 60
A newly appointed project manager takes over a project that replaces an old order management system with a new one. The team has some members who know only the old system and others who have almost no relevant experience. To ensure the project succeeds, what should the project manager do?
Show answer and explanation
Correct answer: D
A new project manager takes over a project that replaces an old order management system with a new one. Some of the team know only the old system and some have almost no relevant experience. The question asks what to do to ensure success.
The new system differs from the old one, so members' past experience may not apply, and it is not yet clear what the team really lacks. The project manager should first assess the team's current effectiveness and find the capability gaps, then arrange training, mentoring and other development measures on that basis. That is the purpose of team performance assessments: to identify the specific training, coaching and assistance needed to improve team performance. The correct answer is D.
Why the other options are wrong
- A. Assigning roles by past job experience assumes that past experience applies to the new system, without checking the gap.
- B. Annual appraisals reflect overall performance in the past. They are neither specific to the new system nor a measure for closing the capability gap.
- C. Letting members pick their own work makes use of personal strengths, but the lack of new-system experience in the team remains, and there is no coordinated arrangement.
Key takeaway When you take over a new team, assess effectiveness and find capability gaps first, then decide on development measures.
Variation If the assessment shows that only a few members have large gaps, arrange pairing and mentoring for them rather than training everyone.
- Question 61
A project manager needs to estimate the development cost of a new mobile app. Based on years of accumulated data, the company has established a statistical relationship between the number of screens and the labor hours needed to develop each screen. Which estimating technique should be used to make use of this information?
Show answer and explanation
Correct answer: A
For the cost estimate of a new mobile app, the company's data accumulated over many years contains a statistical relationship between the number of screens and the labor hours per screen, and the question is which technique to use.
The deciding signals are “data accumulated over many years” and “statistical relationship”. Parametric estimating uses exactly the statistical relationship between historical data and variables to build a model (number of screens × hours per screen × hourly rate) and compute the cost; its accuracy depends on the quality of the model and the data. The answer is A.
Why the other options are wrong
- B. Analogous estimating refers directly to historical data of a similar activity or project. It does not require building a statistical relationship among variables and would not compute from the number of screens.
- C. Bottom-up estimating estimates each work package item by item and aggregates. It rests on the specific work content and not on a statistical relationship.
- D. A rough order of magnitude estimate is a grade of accuracy (the exam reference range is −25% to +75%), not a technique that calculates from historical data.
Key takeaway When you see “statistical relationship, parametric model, unit price × quantity”, choose parametric estimating.
Variation If it said “refer to the total cost of another similar app last year and raise it by 10%”, that is analogous estimating; if it said “estimate the development task of each screen item by item and add them up”, that is bottom-up estimating.
- Question 62
A logistics company approves a warehouse scheduling system project, and the requirements have not yet been detailed. The project manager wants to ensure the project ultimately delivers business value. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
A logistics company approves a warehouse scheduling system project and the requirements are not yet detailed. The project manager wants to make sure the project ultimately delivers business value. What comes first?
PMBOK 8 stresses that value is seen especially from the perspective of key stakeholders, and that project justification and organizational strategy give the team the information needed to make decisions that meet or exceed the intended business value. When requirements are not yet detailed, the first step toward ensuring value delivery is to identify the elements of value together with key stakeholders and learn what matters most to them. With the elements of value in hand, requirements, scope and budget have a sound basis. The answer is D.
Why the other options are wrong
- A. Confirming vendor pricing, delivery time and payment terms is procurement work, and it comes after you know what value is to be delivered and what needs to be procured.
- B. If the elements of value are not yet clear, having the team build the first features from preliminary requirements may produce something of no value and may cause rework.
- C. A detailed budget must rest on scope and value that are already clear. Preparing one while requirements are still undetailed is premature and has no reliable basis.
Key takeaway The first step toward ensuring value delivery is to identify the elements of value together with key stakeholders.
Variation Once the elements of value are identified and the requirements are detailed, the next step is to build those elements into the scope and budget.
Reference The System for Value Delivery · Lesson 1: Value, Business Value and the System for Value Delivery
- Question 63
An internal survey at a consulting firm finds the following: shabby office conditions, pay below that of peers, unfair expense and attendance rules and tense relationships among colleagues. As soon as any of these appear, employees are clearly dissatisfied and their efficiency drops; yet after all of these conditions are improved, their drive does not noticeably increase. Which motivation theory is consistent with this phenomenon?
Show answer and explanation
Correct answer: D
A consulting firm’s survey finds that when office conditions, pay, policies or colleague relationships go wrong, employees are clearly dissatisfied and less efficient, yet drive does not rise after all of them are improved. The question asks which motivation theory this phenomenon matches.
The Herzberg model described in PMBOK 8 splits the factors that shape attitudes at work into two groups: hygiene factors such as company policies, salary and the physical environment, which cause dissatisfaction when insufficient but do not lead to satisfaction even when sufficient, and motivational factors such as achievement, growth and advancement, which lead to satisfaction. “Dissatisfaction when conditions go wrong, no rise in drive after they are fixed” is exactly the signature of hygiene factors, so it corresponds to two-factor theory. The answer is D.
Why the other options are wrong
- A. McClelland’s theory of needs classifies drives as the needs for achievement, power and affiliation. It focuses on types of needs and cannot explain why drive does not rise after conditions are improved.
- B. The hierarchy of needs (Maslow, a common exam term) describes the order in which needs are satisfied by level. It does not divide factors into those that remove dissatisfaction and those that produce satisfaction, so it is not the pattern the stem describes.
- C. Theory X and Theory Y deal with a manager’s assumptions about employee motivation and the corresponding management style. The stem is about which conditions cause dissatisfaction and which motivate, not about management style.
Key takeaway Insufficient hygiene factors cause dissatisfaction, and sufficient ones do not bring satisfaction; to raise motivation, rely on motivational factors such as achievement, growth and advancement.
Variation If employees’ drive rose markedly after they were given more growth opportunities and a promotion path, that shows motivational factors at work, and it would still correspond to two-factor theory.
Reference Motivation Theories · Lesson 1: Maslow’s Hierarchy of Needs and Herzberg’s Hygiene and Motivational Factors
- Question 64
An employee attendance app project has handed the final product to the customer, and the project team has been disbanded. Soon after, the customer contacts the project manager and wants one more new feature added. What should the project manager do?
Show answer and explanation
Correct answer: D
The attendance app project has handed the final product to the customer and the team is disbanded. Soon after, the customer contacts the project manager wanting one more feature. The question asks what the project manager should do.
The key signals are “handed over” and “team disbanded”. A new requirement that comes after closure is complete cannot be folded into the closed original project, and should be evaluated through the current product or organizational governance mechanism and separately authorized. Of the options given, D is the only one that reflects separate authorization and independent management: suggest that the customer start a new project for the new feature, with its own authorization, budget and team. That does not disturb the records of the closed project, and it gives the new feature its own scope, budget and acceptance basis. The answer is D.
Why the other options are wrong
- A. A change request adjusts the baseline of a project still in progress. The project has completely ended and there is no baseline left to change, so a change can no longer be submitted.
- B. The team has been disbanded and its resources released. You cannot pull them back into the original project for a new requirement, or the original project could never end.
- C. The project has ended, and handling new requirements for closed projects is not the steering committee's role. It also gives no workable way forward.
Key takeaway A new requirement after closure is not folded into the original project. It gets separate authorization (such as a new project) and does not go through the original project's change control procedure.
Variation If the project were not yet closed and the customer asked for the same new feature, a change request would be submitted and approved by the change control board.
Reference Project Closure · Lesson 5: Closure Documents, Organizational Process Asset Updates and Closing Out Contracts
- Question 65
The schedule management plan has been approved and the team has chosen its development approach. The project manager must develop the schedule for a new product release and already has the approved scope baseline. Where should she start?
Show answer and explanation
Correct answer: C
The schedule management plan is approved, the development approach has been chosen, and the approved scope baseline is in hand. The project manager must develop the schedule for a new product release. At which step does Develop Schedule begin?
Developing the schedule takes four steps, which proceed in this order (the whole is iterative and you can go back and revise): define activities, determine sequence, estimate effort and duration, and adjust. Each step builds on the previous one. Activities are drawn from the work packages at the lowest level of the WBS in the scope baseline, and without activities there is nothing to sequence or estimate. The scope baseline is approved, so step 1 is to decompose the work packages into activities and build the activity list. Only after that do you sequence. The answer is C.
Why the other options are wrong
- A. Estimating is step 3. At this point the activities are not defined and the sequence is not set, so there is nothing to estimate.
- B. Determining sequence is step 2 and takes the activity list as input. With no activities broken out, there is nothing to sequence, so you cannot start here.
- D. Reviewing and adjusting is step 4. There is not even a draft schedule yet, let alone anything to adjust.
Key takeaway The four steps proceed in order and can be revisited. With a scope baseline in hand, start with defining activities.
Variation If the stem said “the activity list is complete but many precedence relationships are not yet worked out”, the next step is determining sequence. If it said “the network diagram is drawn but has no durations”, the next step is estimating effort and duration.
- Question 66
On a membership system upgrade project for a restaurant chain, the project manager has built the stakeholder register and is considering how to pass project information to the customer effectively. What should the project manager do next?
Show answer and explanation
Correct answer: D
The stakeholder register is built, and the project manager is thinking about how to get information to the customer. The question is what comes next after the register.
Plan Communications Management takes the stakeholder register and the stakeholder engagement plan as inputs and produces the communications management plan. The register identifies, assesses and classifies stakeholders, but it cannot replace an analysis of specific information needs (content, frequency, channel). So the next step is to build on the register and stakeholder analysis by carrying out a communication requirements analysis (supported by a communication styles assessment where needed), find out what each party needs, then set content, frequency and channel and develop the communications management plan. The sequence is analyze first, plan second, execute last. The answer is D.
Why the other options are wrong
- A. One standard weekly meeting does not distinguish between audiences: it is too much for some and not enough for others. Analyze first, then set frequency and format.
- B. A mass update is direct execution. It is not targeted, it risks information overload or missing key content, and there is no plan to follow.
- C. Every project has different stakeholders. Past project materials can be a reference but cannot replace an analysis of this project's stakeholders.
Key takeaway In the scenario described, where the project manager is planning how to communicate, use the stakeholder register to analyze needs and develop the communications management plan before executing communications.
Variation If the communications management plan has already been approved, the next step is to carry out Manage Communications according to it. If someone has not received information, first consult the plan and determine why. Update the plan only if needs or communication arrangements have changed; if delivery merely failed, correct the execution problem under the existing plan.
- Question 67
The project team is going through the deliverables list of a smart warehouse project with the customer. A stakeholder worries that one requirement he raised will not be met. What should the project manager do?
Show answer and explanation
Correct answer: D
The team is going through the deliverables list of a smart warehouse project with the customer, and one stakeholder worries that a requirement he raised will not be met. The question asks what the project manager should do; look for a way to verify the implementation status of this requirement.
The requirements traceability matrix links each requirement to the deliverable that satisfies it, records the current status and status date of each requirement, and includes the test strategy and test scenarios (PMBOK 8). Reviewing the matrix together with the stakeholder lets him see on the spot which deliverable the requirement corresponds to and which test strategy and test scenarios are associated with it; this provides a basis for the answer and eases his concern. Test records should be consulted separately for test-execution progress. The answer is D.
Why the other options are wrong
- A. Going through the approved requirements documentation shows only whether the requirement was recorded. It does not show which deliverable it corresponds to or its progress.
- B. Asking him to add other requirements adds scope before the existing requirement has been verified, may trigger new changes, and does not address his concern.
- C. Negotiating to improve the acceptance criteria changes the standard, but the issue is whether the existing requirement has been implemented. Changing the standard before the situation is clear has no basis.
Key takeaway When someone worries that a requirement will not land, review the requirements traceability matrix together with them.
Variation If the matrix shows that the requirement really has no corresponding deliverable, assess whether it was an omission or was canceled, and submit a change request to add it if necessary; if there is a corresponding deliverable that passed testing, show the evidence.
Reference Requirements Traceability Matrix · Lesson 2: Requirements Management Plan, and Using the Matrix for Change and Acceptance
- Question 68
After a bank introduces an AI tool, some employees worry their jobs will be replaced and are anxious. What should be done in change management?
Show answer and explanation
Correct answer: A
After a bank introduces an AI tool, some employees worry their jobs will be replaced and are anxious. What should be done in change management? This is an organizational and people issue in introducing AI, and the core is communication and capability building.
PMBOK 8 notes that AI is already creating a major shift in most professions, increasing the productivity of the workforce and creating new job opportunities while possibly extinguishing others, and that project professionals should foster a culture in which team members understand AI, use it ethically and take on greater ethical responsibility for AI-related decisions. Making the path of the transition clear to everyone and arranging retraining reduces anxiety and also fits a culture of responsible AI use. The answer is A.
Why the other options are wrong
- B. Not announcing the plan before go-live and letting employees adapt on their own deepens distrust. Change calls for communication in advance.
- C. Requiring use by the deadline and counting it in appraisals without explanation will provoke resistance and does not respond to employees' worries.
- D. Putting the introduction on hold until no one is worried is unrealistic, since not everyone will ever stop worrying. Change management relies on communication, not indefinite postponement.
Key takeaway When AI causes job anxiety, explain the transition plan in advance and arrange retraining for employees.
Variation If the employees' worry came from specific compliance concerns, give clear policies and safeguards that address those concerns.
Reference Artificial Intelligence in Project Management · Lesson 4: Organizational Culture and What the Project Manager Does: Putting AI to Work Safely
- Question 69
The agile team on an enterprise data dashboard project is in its third Sprint. The customer suddenly raises an urgent change: if it is not made, the value delivered to the customer will suffer, and if it is made, the Sprint Goal will be at risk. What should the team do next?
Show answer and explanation
Correct answer: B
In the third Sprint, the customer raises an urgent change: not making it harms the value delivered, and making it puts this Sprint's Sprint Goal at risk. The question is what the team should do next.
During a Sprint, no change may endanger the Sprint Goal, but as more is learned the Developers may negotiate the scope of the Sprint Backlog with the Product Owner. This change has a cost either way, so the team should work with the Product Owner to reassess its value, order and impact; the Developers can then update the Sprint Backlog while protecting the Sprint Goal. The answer is B.
Why the other options are wrong
- A. Putting it in the next Sprint means the change is not made now. The stem states that not making it harms the customer's value, so this does not meet the premise.
- C. Handing it to another team is passing the buck, and it does not assess the value or impact of the change.
- D. Agile stresses a sustainable pace. Taking on both the new requirement and the original work through overtime increases quality risk and is not the preferred way to resolve this conflict.
Key takeaway When an urgent change appears in the middle of a Sprint, the Product Owner and the team reassess priority and impact together.
Variation If the team finds that a new task takes too long and this Sprint cannot finish it, so that features must be cut or a whole story dropped, it likewise talks with the Product Owner, and does not decide by itself or turn to stakeholders or the Scrum Master.
- Question 70
A project manager at an advertising agency cannot get more designers and has to work with the existing staff. She wants to use them more fully and evenly without pushing back the project finish date. Which technique should she use?
Show answer and explanation
Correct answer: A
The advertising agency cannot get more designers and has to use the existing staff. The project manager wants to use them more fully and evenly, and the completion date must not be pushed back. The question asks which technique to use.
PMBOK 8 notes that resource smoothing uses free and total float without affecting the critical path, and the completion date may not be delayed; activities are delayed only within their float. It makes resource use more even and also meets the requirement of “no delay to the completion date”. The precondition is that there is genuinely float available in the network; if the float is used up, smoothing has nothing to work with. Among the listed techniques, resource smoothing best fits the constraints of adding no people and allowing no delay, but the improvement it can achieve depends on the available float. The answer is A.
Why the other options are wrong
- B. Fast tracking is a schedule compression technique. It addresses the schedule, not resource evenness, and running activities in parallel can make resource conflicts worse.
- C. Crashing needs added resources, which contradicts “cannot get more resources”.
- D. Resource leveling adjusts dates and can affect the critical path and lengthen the duration, which violates “the completion date must not be pushed back”.
Key takeaway Limited resources and no delay allowed: resource smoothing, adjusting only within float.
Variation If the completion date were allowed to slip, resource leveling would give more room to optimize.
Reference Resource Leveling and Resource Smoothing · Lesson 2: Resource Smoothing, and How It Differs from Resource Leveling
- Question 71
An agile team is building a mobile payment page, and the members disagree sharply and cannot settle which front-end framework to use. What should the team do?
Show answer and explanation
Correct answer: C
An agile team building a mobile payment page is split on which front-end framework to use and cannot settle it. What should the team do?
A technical approach is a matter of “how to build”, and the development team decides it itself. When there is a disagreement, each side should put its reasons on the table and discuss them fully, and then the team should reach a decision using its previously agreed decision method. This preserves participative decision-making without treating unanimous agreement as the only valid method. The answer is C.
Why the other options are wrong
- A. Directly adopting the framework management recommends lets outside views stand in for the team's decision, without considering this project's characteristics or the members' ideas. Management can offer advice for reference, but the decision belongs to the development team.
- B. Matching other teams is only a convenience and may not suit this project, and it does not resolve the disagreement among members.
- D. Using “the most material” as the sole criterion lets a single factor conclude for the team, without listening to each member's considerations.
Key takeaway A technical disagreement is settled by discussion within the team, reaching a decision the team can accept, not by copying management or others. In discussion, each side presents facts and reasons, and in the end the team decides in the way it has agreed, with the leader not ruling for it.
Variation If the team charter set a decision rule and the vote passed under that rule, the leader should respect the result and may note objections but not overturn it.
- Question 72
A furniture factory's order-management system project has entered execution. The client's representative asks for an inventory-alert feature, which would change the scope baseline, and the change management plan states that changes affecting the baseline are approved by the change control board. The project manager and team assess the change's effects on scope, schedule, cost and risk, and unanimously agree that the requirement is worth implementing. What should the project manager do NEXT?
Show answer and explanation
Correct answer: C
The order-management system project is in execution. The client's representative asks for an inventory-alert feature that would change the scope baseline, and the team agrees it is needed. What should the project manager do next?
In this question the change management plan says baseline changes are approved by the change control board, so the change control process must be followed. A change can be raised orally but should be recorded in writing; after the project manager assesses the impact, the request is submitted to the change control board as the change management plan specifies, and only after approval does it enter the revised baseline and get implemented. The team's view that it is needed is only part of the assessment; the authority to approve lies neither with the team nor with the client. The answer is C.
Why the other options are wrong
- A. The client is the party raising the change and has no authority to approve it. An arrangement made privately between the two sides bypasses change control, and the baseline would not be formally changed.
- B. The stem states that the change management plan assigns approval to the change control board, so the sponsor is not the approver of this change.
- D. That the team thinks it is needed does not mean the change is approved. Implementing without approval quietly alters the baseline.
Key takeaway A baseline change should follow the change control method set for the project; here a change request must be submitted and approved by the change control board designated in the change management plan, and nothing is implemented before approval.
Variation If the project baseline has not yet been established, changes are not under formal control and the impact is analyzed first; if the sponsor is a member of the board, approval is still made through the board.
- Question 73
When comparing projects with operations, which of the following describes operations correctly?
Show answer and explanation
Correct answer: A
The question compares projects with operations and asks for the correct description of operations. Operations is ongoing work, while a project is temporary with a defined beginning and end.
PMBOK 8 states that operations management focuses on the efficient, effective production of products and/or services and manages processes that transform inputs (materials, components, energy and labor) into outputs, and that ongoing operations are outside the scope of a project. A project, by contrast, is temporary with a defined beginning and end. So the description that fits operations is “ongoing, continually producing products or services”. The answer is A.
Why the other options are wrong
- B. “Unique and temporary, with a defined beginning and end” describes a project, not operations.
- C. “Aimed at driving change and finished once complete” describes a project, whose purpose is to move an organization from one state to another.
- D. “An entirely new context and new objectives each time” reflects the unique context of a project. Operations is ongoing, repetitive work.
Key takeaway Operations is ongoing and repetitive. A project is temporary and unique.
Variation If the stem asked about a one-time job of migrating user data to a new system, that would be a project, not operations. If it asked which kind of work creates value by continually converting inputs into outputs, the answer is again operations, because that work does not end when something is delivered.
Reference Projects, Programs and Portfolios · Lesson 3: Operations, Governance and Tailoring
- Question 74
A project manager at a logistics company faces several schedule risks and needs to periodically verify that the risk management process is robust and effective. Which of the following tools should the project manager use?
Show answer and explanation
Correct answer: D
A logistics company project manager faces several schedule risks and needs to periodically check that the risk management process is robust and effective. Which tool should be used?
The key clue is “verify that the risk management process is effective”. PMBOK 8 describes a risk audit as a type of audit that may be used to consider the effectiveness of the risk management process; the project manager is responsible for ensuring that risk audits are performed at the frequency defined in the risk management plan. The other options each have a role, but none of them is aimed at assessing the effectiveness of the process. The answer is D.
Why the other options are wrong
- A. Brainstorming is a technique for gathering ideas and is often used to identify risks. Its output is a list of ideas; it cannot assess how well the risk management process is working.
- B. The stakeholder register records the identification and assessment of stakeholders. It is a stakeholder management document and has nothing to do with the effectiveness of the risk management process.
- C. The assumption log records assumptions and constraints and helps identify risks that arise from assumptions. It is not an audit tool for checking the effectiveness of a process.
Key takeaway To check whether the risk management process is effective, use a risk audit.
Variation If the question asked to “evaluate whether the risk management process is effective”, the answer would still be a risk audit; if it asked to “find out what other risks exist”, you would use identification tools such as brainstorming or checklists.
Reference Monitor Risks · Lesson 3: Risk Monitoring Tools: Technical Performance Analysis, Reserve Analysis and Risk Audits
- Question 75
PMLyceum is upgrading the inventory system for its retail stores, using a predictive approach. The project is critical to the company, but during execution the project manager finds that nobody on the team has the specialized data migration skills required, so one deliverable cannot be produced. What should the project manager have done to avoid this?
Show answer and explanation
Correct answer: B
A predictive project is already in execution, but no one on the team knows data migration, so a deliverable cannot be produced. The question asks what should have been done to avoid this, which means looking back at what planning should have covered.
Planning should first identify the team resources and skills the work requires, using the approach set out in the resource management plan, and then decide on recruiting, training or procurement. A predictive project stresses planning up front, so the list of skills should be complete during planning: gaps then show up before work starts, and there is still time to train or add people. “Should have” and “avoid” in the stem point to an action taken beforehand, and identifying all skills during planning fits best. The answer is B.
Why the other options are wrong
- A. Training must be planned, but what to train depends on which skills are missing. Without the skills list there is nothing to base a training plan on. It is work that follows identifying skills, not the first thing to do.
- C. Identifying skills as work proceeds leaves gaps to appear only in execution, which is exactly the failure in the stem: the skill is missing and the deliverable cannot be produced.
- D. Identifying the required skills is planning work led by the project manager and team. The sponsor focuses on business objectives and authorization and does not know the specific technical skill requirements better than the project team, so passing it to the sponsor shirks the duty.
Key takeaway Skill gaps must be identified during planning by the project manager and the team, not found late during execution.
Variation If the gap had been found during planning, first assess its impact and the relevant constraints. Common exam practice is then to address the gap in the resource management plan and arrange training. On an adaptive project, reassess team skills and gaps before each iteration.
- Question 76
A cross-functional team is working on a complex project whose requirements keep changing. The team needs a management framework built around a product backlog, fixed-length iterations, and iteration review meetings and retrospectives to improve the process. Which approach should it adopt?
Show answer and explanation
Correct answer: D
A cross-functional team is doing a complex project with constantly changing requirements. A framework built around a product backlog, fixed-length iterations, and iteration reviews and retrospectives is needed. Which approach should be adopted?
The signals are “product backlog”, “fixed-length iterations”, “review meetings” and “retrospectives”. These are the core elements of Scrum (the Product Backlog, Sprints, the Sprint Review and the Sprint Retrospective): a cross-functional, self-managing team uses the rhythm of fixed Sprints to inspect and adapt, which suits complex work with changing requirements. The answer is D.
Why the other options are wrong
- A. Kanban focuses on visualizing the workflow and limiting work in progress, with continuous flow. It does not itself prescribe fixed-length iterations or review and retrospective events.
- B. Extreme Programming emphasizes engineering practices such as pair programming and test-driven development. It is not a management framework built around a backlog and iteration events.
- C. Feature-Driven Development is characterized by modeling by feature and building in stages. It is not a framework built around a cross-functional team, fixed iterations, reviews and retrospectives.
Key takeaway A cross-functional team, changing requirements, and a need for fixed iterations with review and retrospective: use Scrum.
Variation If the stem said the need was to visualize the existing workflow and limit work in progress, choose Kanban. If it said the aim was to raise code quality with an emphasis on pair programming and test-driven development, choose Extreme Programming.
- Question 77
PMLyceum has taken on an 8-month store system upgrade project. At the project kickoff meeting, the project manager plans to announce that one data migration task will finish later than originally planned. That task is exactly what one key stakeholder values most about the project, and he is expected to object strongly. What should the project manager do to reduce the chance of a strong rejection at the kickoff meeting?
Show answer and explanation
Correct answer: B
The project kickoff meeting is coming up, and the project manager foresees that a key stakeholder will object strongly to the delay to be announced there. The question is how to lower the chance of rejection in advance.
Stakeholder engagement has to happen before a problem erupts. The signals in the stem are “is expected to object strongly” and “reduce the chance of a strong rejection at the kickoff meeting”: the goal is to defuse the disagreement, not to respond to a conflict. A private conversation before the meeting lets the project manager learn why this work matters to him and hear his views on scope and timing, so the disagreement is worked through beforehand and he is not blindsided at the meeting. The answer is B.
Why the other options are wrong
- A. The assessment matrix is only a tool for comparing current and desired engagement levels. It does not give him a chance to voice his views before the meeting, and it does nothing to ease his unhappiness about the delay.
- C. A written notice is one-way communication, and stating that the meeting will not reopen the discussion collects no feedback. The objection will simply surface later, at the meeting or after it, in a stronger form.
- D. Logging the risk and planning a response can be a supplementary step, but those actions do not engage him directly and do not do enough to reduce the chance of a strong objection at the kickoff meeting. The priority is to reach out, learn what he wants and resolve the disagreement beforehand.
Key takeaway When you foresee that a key stakeholder will object, communicate proactively before the meeting and listen; do not wait to deal with it in the room.
Variation If he has already rejected the delay on the spot at the meeting, the first step is to steady the room and promise a follow-up conversation afterward, then find out what he needs. Prevention and after-the-fact repair lead to different answers.
- Question 78
A project manager is discussing with a team developing a new home appliance which working methods and tools to use to produce the deliverables. What should this discussion ultimately produce?
Show answer and explanation
Correct answer: C
A project manager discusses with a team developing a new home appliance which working methods and tools to use to produce the deliverables. What should the discussion ultimately produce?
PMBOK 8: tailoring is the deliberate adaptation of the project management approach, governance, and processes to make them more suitable for a given environment and fit for the purpose of the work at hand. The outcome of the discussion should be a set of methods and tools that the team accepts and that fits the business needs and project constraints (budget, time, and so on), and that keeps being adjusted as the project proceeds. The answer is C.
Why the other options are wrong
- A. A risk mitigation plan is an output of risk management, not what this discussion is meant to produce, and there is no need to write a detailed plan for each method and tool.
- B. “Once settled, everything will go as expected” is an overly idealistic agreement. The project will meet changes and needs continuous adjustment.
- D. Each project’s environment and purpose differ, so this choice cannot be fixed as a standard way for all similar deliverables in the future, which would defeat the purpose of tailoring.
Key takeaway The result of tailoring is a set of practices that the team accepts and that fit the business needs and constraints, and it keeps being adjusted.
Variation If the organization mandated a standard process, tailoring would have to be done within the limits of organizational policy.
Reference Tailoring · Lesson 1: What Tailoring Means, Why We Do It, and What We Tailor
- Question 79
PMLyceum has four new-product development projects ready to start. They serve the same growth strategy but have no dependencies on one another. Management is comparing the strategic value of each project and deciding the order in which to invest. Which of the following activities is this?
Show answer and explanation
Correct answer: D
Four new-product development projects serve the same growth strategy and have no dependencies. Management compares their strategic value and decides the order of investment. You must identify what type of activity this is.
The key actions in the stem are comparing strategic value and deciding the order of investment. That is selecting and prioritizing among several projects, which is portfolio management. The components of a portfolio need not depend on one another; they are managed together to maximize overall value, achieve strategic objectives, meet mandatory obligations, or generate income streams. The stem says there are no dependencies, and management is only comparing value and ranking, with no action to coordinate interdependencies, so this is not program management. Two cross-checks help. First, the action: comparing value and setting an order is selecting. Second, the object: several projects that have not yet started are portfolio components, not one project already chartered. The answer is D.
Why the other options are wrong
- A. Program management manages a group of related projects and program activities in a coordinated way to obtain benefits not available from managing them individually, and its emphasis is coordination. The stem says only that the projects serve the same strategy and have no dependencies. Management is comparing value and ranking, and nothing is being coordinated across interdependencies.
- B. Operations management concerns the ongoing production of products and services. It has nothing to do with this batch of new-product development projects that have not yet started.
- C. Project initiation is the work of authorizing one project and issuing its charter. The stem discusses trade-offs among several projects, not initiating one.
Key takeaway Comparing value, setting priorities and allocating resources across several projects is portfolio management, not program management.
Variation If the four projects had interdependent interfaces and their schedules needed to be coordinated together, the answer would become program management. Look at the verb: ranking and trade-offs point to a portfolio, coordinating dependencies points to a program.
- Question 80
While reviewing a decision tree drawn by the team, the project manager finds a chance node with three branches whose probabilities are 50%, 30% and 15%. How should the project manager handle this?
Show answer and explanation
Correct answer: A
The team has drawn a decision tree and handed it to the project manager for review, to be used for calculating expected monetary value (EMV). The probabilities of the three branches of one chance node total only 95%. The question asks how to handle this.
The key evidence is “the same chance node” and “total 95%”. A chance node represents one uncertain event, and the branches leaving it must exhaust all possible outcomes, so their probabilities must sum to 100%. A total of 95% means a scenario was left out or a probability was misjudged. The project manager cannot simply fill in a number but should check with the experts who supplied the estimates, bring the total back to 100% and then calculate EMV. The answer is A.
Why the other options are wrong
- B. Treating the missing 5% as “no effect” silently assumes that an undescribed outcome has zero effect, which has no basis. Branch probabilities below 100% mean the model is incomplete, and an EMV calculated on 95% will be distorted and may lead to a wrong decision.
- C. This wrongly assumes that switching to a decision node avoids the check. The type of node is determined by the nature of the event: something we can choose is a decision node, and only an uncontrolled uncertain event is a chance node. Events such as suppliers or weather cannot be changed by changing the symbol, and the branches of a decision node are not probability-weighted anyway.
- D. Taking only the 50% branch with the highest probability turns the expected value into the “most likely outcome”. EMV is by definition the probability-weighted sum over all branches, and dropping the other two branches erases all the information about the distribution of risks and opportunities.
Key takeaway The probabilities of the branches of a chance node must total 100%. If they do not, check with the experts first, then calculate EMV.
Variation If the three branches were 50%, 30% and 30%, totaling 110%, they would likewise need to be checked and corrected first. If there were only two branches, 60% and 40%, totaling 100%, you could directly weight the branch net values to find EMV.
Reference Decision Tree Analysis · Lesson 1: Decision Tree Symbols and Expected Monetary Value (EMV)
- Question 81
The IT department of a retail chain has always developed its store management system in a waterfall way. As business change has sped up in recent years, management brings in an experienced project manager to help the department move from the traditional way to hybrid project management, and requires that this approach be used on a newly launched system upgrade project. During project execution, which of the following is the project manager LEAST likely to do?
Show answer and explanation
Correct answer: D
The organization is moving from a traditional way of working to a hybrid approach, and the new project uses a hybrid approach and is in execution. What the project manager is “least likely” to do is the practice that conflicts with the characteristics of a hybrid approach.
A hybrid approach combines predictive and adaptive approaches: parts with clear requirements are planned predictively, and parts that are still evolving become clear gradually as the project proceeds. So the project does not start by making a detailed plan for all subsequent work; that is closer to a purely predictive practice and conflicts with the characteristics of a hybrid approach, making it the thing the project manager is least likely to do. The answer is D.
Why the other options are wrong
- A. Close collaboration between business staff and developers is an adaptive practice that the adaptive part of a hybrid project will use.
- B. Hybrid projects also have change and influencing factors, and continuously identifying and recording them is a normal management action.
- C. Combining predictive, incremental, agile, and other practices as needed is exactly what characterizes a hybrid approach.
Key takeaway A hybrid approach plans in detail only the parts that are clear; the unclear parts become clear gradually as the project proceeds, so it does not plan everything to the end at the start.
Variation If the question asked for “the practice that best fits a hybrid approach,” the answer would be C, combining several practices. If the stem were a purely predictive project, detailed up-front planning would be more common, but “making a detailed plan for all subsequent work at the start” would still be too absolute.
- Question 82
A project manager emails the project management plan to team members, and a member replies “received” immediately on getting it and then starts executing. During execution the project manager finds someone doing work outside the scope, and an investigation confirms that the member misunderstood the plan. To prevent this kind of deviation, how should communication have been arranged beforehand?
Show answer and explanation
Correct answer: A
During execution, the project manager emails out the project management plan, a member replies “received” and starts executing, but the member misunderstood and did work outside the scope. The question asks how communication should have been arranged beforehand.
The interactive communication model adds “acknowledge” and “feedback” to the basic model's encode, transmit and decode. “Received” is only an acknowledgment of receipt and does not mean agreement or comprehension. Real feedback is the receiver decoding and understanding the message, then encoding their own thoughts and sending them back; communication succeeds when the sender perceives that the feedback matches the original message. Because the member did not send back their understanding, the deviation stayed hidden. So communication should have been arranged so that the member returns their understanding for the project manager to confirm. The answer is A.
Why the other options are wrong
- B. The email already delivered the information, so the channel itself was not the problem, and changing the channel cannot guarantee understanding.
- C. This is only decoding. The understanding is not sent back to the other side to confirm, so it may still be the member's own misunderstanding.
- D. Collecting communication needs and selecting a delivery method addresses how information gets to people. Here the email arrived and the member replied that it was received; the problem is that understanding was not confirmed.
Key takeaway “Received” does not equal “understood.” Having the receiver send back their own understanding is effective feedback.
Variation If the scenario were “the email went into a spam folder and the member never saw it,” the problem would be in transmission, and you would change channels or add a notice. If it were “the member saw it but did not want to listen,” that would be noise and the receiver's responsibility.
- Question 83
A team uses Scrum to develop a membership system for a bookstore chain. Each Sprint is a fixed 2 weeks, and the team has a fixed 5 people. At the end of this Sprint, the two low-priority items at the bottom of the Sprint Backlog are not done. Which line of thinking about the next step is most consistent with Scrum?
Show answer and explanation
Correct answer: D
The team works with a fixed timebox and fixed people, and at the end of the Sprint the two low-priority items at the bottom are not finished. The question asks which next step is most consistent with Scrum.
Scrum keeps the Sprint length fixed and the team stable, and scope flexes with priority. Items are ordered by value so the most important are delivered first, and what remains unfinished is the lowest-priority items at the bottom. So the team does not extend time, add people or work extra hours to finish. The unfinished items return to the Product Backlog, are reordered with the others, and the next Sprint Planning decides whether to select them. The answer is D.
Why the other options are wrong
- A. Lengthening the next Sprint just to fit leftover work abandons the stable rhythm and treats scope as fixed. Select less based on velocity instead.
- B. Borrowing members changes the stable make-up of the team. Newcomers need time to settle in, and it goes against the practice of a stable team.
- C. Working weekends to buy scope breaks a sustainable pace and is not the idea of delivering smaller increments in priority order.
Key takeaway With a fixed timebox and fixed people, scope flexes by priority, and unfinished items return to the Product Backlog.
Variation If the team fails to finish several Sprints in a row, it should select fewer items at Sprint Planning based on its historical velocity, rather than keep adding time or people.
Reference Scrum Framework · Lesson 1: Understanding Scrum Through a Shopping List, and How Scrum Flows
- Question 84
A retail company starts a large digital-transformation project to respond to market change. During execution a new technology appears, and the uncertainty it brings falls outside the risk categories and methods defined in the risk management plan. What should the project manager do?
Show answer and explanation
Correct answer: A
During execution of a large digital-transformation project, a new technology appears, and the uncertainty it brings falls outside the risk categories and methods defined in the risk management plan. The question asks what the project manager should do.
The risk management plan sets out how the project manages risk. If the uncertainty from the new technology falls outside the plan's categories and methods, first review the risk management plan and assess the gap. If risk categories, probability and impact definitions, or other plan content must change, submit the change through the project's change management process, obtain authorization, update the risk management plan, and then use the approved approach to identify and analyze risks. The answer is A.
Why the other options are wrong
- B. Notifying IT to arrange learning: arranging training before any assessment may waste resources, and it is not yet clear whether the new technology is an opportunity or a threat.
- C. Reporting to the steering committee and calling a brainstorm: the project manager should manage risk proactively first, and brainstorming is an identification technique, not the first step at this point.
- D. Reviewing the procurement management plan for affected contracts: that plan covers only procurement, while the effect of the new technology may involve scope, schedule, cost and more, so looking only at procurement cannot give a full assessment.
Key takeaway When the risk management plan cannot cover newly emerging uncertainty, review the plan, carry out Plan Risk Management again and update the plan.
Variation If the new technology brought only a single risk that still falls inside the defined categories, you only need to identify and log it, with no need to re-plan risk management.
Reference Risk Management Plan · Lesson 3: Plan Risk Management and the Risk Management Plan
- Question 85
After a cross-border logistics project enters execution, a major problem arises that exceeds the project manager's authority to handle and will affect a key milestone, so management must be informed immediately. Which approach is MOST appropriate?
Show answer and explanation
Correct answer: C
During execution of a cross-border logistics project, a major problem beyond the project manager's authority arises that will affect a key milestone, and management must be informed. The most appropriate way to handle it must be chosen.
The governance escalation mechanism exists to handle matters beyond the project team's authority. A major problem should be escalated promptly along the path agreed in advance, making three things clear: what the problem is, what impact it has on the project and how it is proposed to respond, so that management can decide quickly. Note that “wait for a clear result before reporting,” “just send an email and wait for a reply” and “align internally first” are all ways of delaying escalation; a major problem calls for timeliness and transparency. The answer is C.
Why the other options are wrong
- A. Waiting for a clear result before reporting misses the time for a decision, and management is left on the back foot by outdated information.
- B. Sending only an email and waiting for a reply lacks proactive communication, and a major problem may be delayed as a result.
- D. Aligning internally first and then having the sponsor relay it adds delay when the major problem requires immediate escalation; the option also does not state the problem's impact or the proposed response.
Key takeaway Escalate a major problem promptly along the escalation path, and explain the problem, its impact and the proposed response.
Variation A minor issue the team can handle internally need not be escalated; if the path has not yet been defined, first ask the sponsor and any existing steering committee or other governance authority to define it.
- Question 86
At the review meeting for a new-energy power station project, the team complains: “We cannot find a unified sustainability standard to judge whether the project is successful.” Someone proposes that the PMO issue one set of uniform metrics that applies to all projects. According to The Standard for Project Management, which statement is MOST appropriate?
Show answer and explanation
Correct answer: B
At the review meeting for a new-energy power station project, the team complains that no unified sustainability standard exists for judging success, and someone proposes that the PMO issue uniform metrics for all projects. The question asks which statement is most appropriate according to The Standard for Project Management.
The Eighth Edition notes that one challenge of including sustainability goals is the lack of universal sustainability criteria: assessing a project’s success is challenging, each project requires a tailored approach, and the team should have access to tools that provide the necessary information. So the appropriate statement is that there is no universal standard and each project needs to tailor an assessment approach that suits it. The answer is B.
Why the other options are wrong
- A. The Standard does not say to wait for the industry to publish a unified standard before assessing. Assessment is something the project has to do within the project.
- C. Sustainability is part of project value and cannot be left out of the evaluation of project success.
- D. Sustainability covers society, the economy and the environment. Looking only at environmental metrics is incomplete, and the other two aspects have to be assessed too.
Key takeaway There is no universal sustainability standard, so each project tailors its own approach to assessment.
Variation If the organization has already published internal sustainability metrics, the project should tailor and use them according to the project’s characteristics.
Reference Sustainability · Lesson 2: Integrating Sustainability Into a Project: Practices, Challenges, Performance Domains and Compliance
- Question 87
A project manager is running a multinational project with more than 120 stakeholders. The project manager's concern is whether stakeholder engagement is appropriate, and at the level needed, for successful delivery. What should the project manager do?
Show answer and explanation
Correct answer: B
A multinational project has more than 120 stakeholders, and the project manager wants to know whether the engagement needed for successful delivery is appropriate and at the right level. You must decide what the project manager should do.
Judging whether engagement is “appropriate and at the right level” is exactly what the stakeholder engagement assessment matrix is for: it sets each stakeholder's current level next to the level the project needs, so the gaps are plain to see and you can tell which people need more communication. With this many people, a matrix is more efficient than talking to each one. The answer is B.
Why the other options are wrong
- A. The stem presents no specific problem, so there is nothing to “work out solutions” for, and one-on-one conversations with more than 120 people are impractical. This does not answer the question.
- C. The issue log records issues that have already occurred and has nothing to do with assessing engagement levels. Going through every entry would waste effort.
- D. Assumption and constraint analysis is used when planning engagement to tailor strategies, whereas this question is about whether the current state is adequate. That calls for a comparison, not an analysis of assumptions.
Key takeaway To find out whether engagement levels are sufficient, use the stakeholder engagement assessment matrix to compare current and desired levels.
Variation If “one key person's engagement level is below what is needed, for unknown reasons,” you would first do a root cause analysis and then develop a strategy to raise the level.
- Question 88
A building design firm wins a project that could greatly raise its profile, thanks to the reputation it has built over many years, and the customer has already signed a contract with the firm. You are assigned as project manager, and the firm’s leaders have high hopes for the project. What should you do FIRST?
Show answer and explanation
Correct answer: B
The contract has been signed, the project manager has just been assigned, and the firm’s leaders have high hopes. The project is in initiating. The question asks what should be done first.
A contract is a form of agreement and one of the inputs to developing the charter. In initiating, the project manager should take part in preparing the charter from the information at hand, including the contract, and hand it to the sponsor for approval, at which point the project is formally authorized. So the first thing is to start writing the charter from the existing information, not to move directly to acquiring resources or determining a detailed scope; those follow later under the charter’s authority and the planning. The answer is B.
Why the other options are wrong
- A. Pulling in a technical expert is acquiring resources, which happens after the charter authorizes the project and resource planning is done. Without the charter’s authorization, the project manager does not even have the authority to do it.
- C. Identifying and initially engaging stakeholders can start in initiating, but “organizing various activities to raise enthusiasm” is vague and is not the top task now. The priority is first to complete and submit the charter.
- D. Eliciting and analyzing requirements and defining the detailed scope come after the charter. The charter contains only a high-level project description, boundaries and key deliverables.
Key takeaway A contract is an input to the charter; once the contract is signed, prepare the charter first.
Variation If the charter has already been approved, the next step is to identify stakeholders and develop the project management plan.
Reference Project Charter · Lesson 2: Inputs to Initiating: Business Documents and Agreements
- Question 89
After the latest retrospective, the team decides to drive change and process improvement continuously and iteratively. Which of the following methods should the project manager adopt?
Show answer and explanation
Correct answer: D
After the latest retrospective, the team decides to drive change and process improvement iteratively and continuously, and the question asks which method to adopt.
PDCA is a cycle for continuous improvement: plan, do, check, act. Each round evaluates the effect and carries the result into the next, so it allows small trial steps and also locks in what works, which suits driving change iteratively. “Continuously and iteratively” in the stem points to a cycle, not a one-time analysis tool. The answer is D.
Why the other options are wrong
- A. Root cause analysis is used to find the deeper cause of a problem. It is an analysis tool, not a cyclical method for driving improvement continuously and iteratively.
- B. Value stream mapping lays out the value-adding and wasteful steps in a process and helps you find points to improve, but it is not itself a cycle that drives improvement.
- C. A Pareto chart finds and ranks the few causes behind most of the problems. It is an analysis tool and does not drive iterative improvement.
Key takeaway To drive improvement continuously and iteratively, use the PDCA cycle; the other options are analysis tools.
Variation If the stem asked to “find the few causes behind most of the defects,” the answer would be the Pareto chart; if it asked about “the deep cause of the same error recurring,” the answer would be root cause analysis.
- Question 90
A team member is rushing to complete a key deliverable when their work computer suddenly breaks down. The IT department replies that, because of a backlog of tickets, it cannot assign anyone to handle it within a week. What should the project manager do?
Show answer and explanation
Correct answer: B
A member rushing to finish a key deliverable has a computer failure, and the IT department, with a ticket backlog, cannot schedule a repair within a week. The question is what the project manager should do; this is a resource impediment.
With a resource impediment, first assess the impact and coordinate: based on the urgency of the task, talk with the IT department and ask it to speed up the repair or discuss alternatives. This is a direct first step that requires no immediate additional expenditure and does not overstep authority. If coordination works, the delay to the key deliverable can be kept to a minimum. The answer is B.
Why the other options are wrong
- A. Going to the sponsor for budget without coordinating first skips a step within the project manager's own authority. A budget request should come only after coordination has failed.
- C. Using contingency reserve to buy new equipment directly creates an immediate additional expense and skips both assessment and coordination, so it should not be the first choice.
- D. Simply telling the member to work it out lacks coordination with the IT department and does not discharge the project manager's responsibility to remove impediments.
Key takeaway For a resource impediment, coordinate with the relevant department first and push for faster handling according to urgency, rather than spending money straight away. First work out whether it can be settled by coordination within one's own authority, and then escalate level by level.
Variation Only if IT clearly says it cannot speed things up and a critical path delay is imminent should the project manager go on to assess renting equipment and request budget within his or her authority.
- Question 91
The project management office is organizing the table of contents of a project management plan by the PMBOK 8 structure. Which of the following is one of the PMBOK 8 performance domains?
Show answer and explanation
Correct answer: D
The PMO organizes the table of contents of a project management plan by the PMBOK 8 structure and must decide which item is one of the PMBOK 8 performance domains. Here you must tell real performance domains from management topics that are customarily listed separately.
PMBOK 8 integrates project management work into seven project management performance domains: Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk. Finance is one of them. PMBOK 8 has no quality performance domain (deliverable quality and verification belong to Scope, and Manage Quality Assurance belongs to Governance), communication is handled under the Stakeholders performance domain, and procurement content is not listed as a performance domain. Of the four options, only Finance is among these seven. The answer is D.
Why the other options are wrong
- A. Quality is the name of an old knowledge area, and PMBOK 8 has no separate quality performance domain: deliverable quality and verification belong to Scope, and Manage Quality Assurance belongs to Governance.
- B. Communications is an old knowledge area; PMBOK 8 handles it under the Stakeholders performance domain, so it is not an independent performance domain.
- C. Procurement is an old knowledge area, and PMBOK 8 does not list it as a performance domain, so it cannot be chosen as one.
Key takeaway The seven performance domains are Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk; quality, communications, and procurement are no longer listed separately.
Variation If the question asked “which of the following is NOT a performance domain,” you would choose old knowledge area names such as quality, communications, or procurement.
Reference Focus Areas and Performance Domains · Lesson 1: The Five Focus Areas and the Seven Performance Domains
- Question 92
Which of the following MOST accurately describes the core purpose of the Manage Project Execution process?
Show answer and explanation
Correct answer: B
The question is the core purpose of the Manage Project Execution process. Among the options, A and D describe monitoring and controlling work, C describes stakeholder work, and only B is Manage Project Execution itself.
Manage Project Execution leads the team to complete the work set out in the project management plan and implements approved changes, in order to meet the project's objectives. Its key benefit is the comprehensive management of project work and deliverables, which enhances the likelihood of project success. Of the four options, only B contains both key points, “complete the work in the plan” and “implement approved changes.” The answer is B.
Why the other options are wrong
- A. Tracking, reviewing and reporting progress against the plan's objectives is what Monitor and Control Project Performance does. Manage Project Execution produces performance data, and the monitoring and controlling processes analyze and compare them.
- C. Managing stakeholder expectations and maintaining engagement is work of the Stakeholder performance domain and is not the core purpose of the Manage Project Execution process.
- D. Watching the schedule and finding variances between actual and baseline is monitoring and controlling work. It is not the purpose of the execution process itself, and it confuses executing with monitoring.
Key takeaway Manage Project Execution does the work in the plan and implements approved changes. Monitoring and comparing belong to monitoring and controlling.
Variation If an option described “approving or rejecting change requests,” that belongs to Assess and Implement Changes. If it described “collecting and organizing performance data,” that is an output of execution, not its purpose.
Reference Manage Project Execution · Lesson 1: Manage Project Execution: Purpose, Inputs and Outputs, Deliverables and Work Performance Data
- Question 93
On a newly formed mobile app development team, an experienced back-end engineer is overwhelmed by several complex integration tasks and shows dissatisfaction with the team. What should the project manager do?
Show answer and explanation
Correct answer: D
On a newly formed app development team, an experienced back-end engineer is overwhelmed by several complex integration tasks and shows dissatisfaction with the team. The question asks what the project manager should do.
When a member feels overwhelmed, first find out exactly where the difficulty lies. Listening carefully both eases the emotion and locates the problem. Then work with him to find the support available, such as adjusting the division of work, adding resources or arranging help from others. That handles both the feelings and the task load. Careful listening makes the member feel respected and valued, so he is more willing to say what the real difficulties are, and any later adjustment has a basis. The correct answer is D.
Why the other options are wrong
- A. Recording possible delays in the risk register only logs a potential risk. It neither eases the emotion nor helps him sort out the tasks.
- B. Saying only that the tasks cannot be avoided and asking him to cope himself offers no concrete help and may deepen the dissatisfaction.
- C. Team building can ease the mood, but this member has a clear, specific problem with his tasks, and team building cannot lighten his burden.
Key takeaway When a member is overwhelmed, listen first, then look together for the support available.
Variation If many members are generally tired, first find the source of the pressure and adjust the pace and workload.
- Question 94
An outdoor installation project for a photovoltaic power station must be worked in the open air, so the weather becomes a constraint on the project. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
An outdoor installation project for a photovoltaic power station must work in the open air, and the weather becomes a constraint. The question asks what the project manager should do first.
The key point is that the stem has identified weather as a constraint. The assumption log records assumptions and constraints throughout the project life cycle; among the choices, entering this constraint there is the most appropriate way to establish a shared, traceable planning premise. Recording does not replace impact assessment: depending on urgency, the project manager should also assess the impact and adjust the approach, and these activities may be carried out together. The project manager can maintain the assumption log directly. The answer is A.
Why the other options are wrong
- B. Recording is within the project manager’s authority and does not require telling the sponsor first. Whether to inform the sponsor depends on the impact assessment.
- C. The stem presents no specific problem that requires subject matter experts. Calling an expert meeting before clarifying what needs analysis is poorly targeted.
- D. The stem does not say that the risk management plan contains a weather provision, and merely reviewing that plan does not replace documenting and assessing the identified constraint.
Key takeaway When you identify an assumption or constraint, record it in the assumption log and assess its impact as appropriate.
Variation If the weather has already caused a stoppage and affects the schedule, that is an issue that has occurred and goes in the issue log. If it is only an adverse event that may occur, it goes in the risk register.
- Question 95
A large manufacturing group requires every project manager in the group to report regularly to the group's project management office (PMO). In training, the instructor asks everyone to compare the PMO types in the traditional classification (a common exam term): which type of PMO exerts the highest degree of control over projects?
Show answer and explanation
Correct answer: A
A large manufacturing group requires every project manager to report regularly to the group PMO. In training, the instructor asks which PMO type exerts the highest degree of control over projects.
This is the traditional PMO classification (a common exam term): by degree of control from low to high, the types are supportive, controlling and directive. A directive PMO manages projects directly and exerts the highest degree of control. PMBOK 8 gives directive, supportive and agile as examples of PMO models and says these models are not mutually exclusive and can be combined to meet organizational needs. For this question, the answer is A.
Why the other options are wrong
- B. A controlling PMO requires projects to comply with established frameworks, methods and governance requirements. Its degree of control is in the middle, and it does not manage projects directly.
- C. Under this traditional classification, a supportive PMO provides consultative support such as templates, best practices and training and has the lowest degree of control; it does not itself mandate use of that support.
- D. "Collaborative" is not a PMO type in the traditional classification (a common exam term). The three common types are supportive, controlling and directive.
Key takeaway PMO control from low to high: supportive, controlling, directive (the traditional classification, a common exam term). A memory aid: supportive gives resources, controlling demands compliance, directive manages directly.
Variation If the question asked which PMO type has the lowest degree of control, the answer would be supportive.
Reference Project Management Office · Lesson 1: PMO Definition, Value and Types
- Question 96
During execution of an energy storage battery pack development project, the team finds that if an identified risk occurs, its impact will be wider than originally assessed. Which item should the project manager update FIRST?
Show answer and explanation
Correct answer: A
During execution, the impact of an identified risk, if it occurs, turns out to be wider than originally assessed. The risk has not occurred. Which item should be updated first?
“If it occurs” means the risk has not become reality; what has changed is an attribute of the risk itself (its impact). Information on an individual risk, such as probability and impact, is recorded in the risk register, which is updated continuously throughout risk management. So the new assessment should be entered in the risk register first. The answer is A.
Why the other options are wrong
- B. The risk management plan is a guiding document that sets out methods and rules. It does not record information on any particular risk, so it does not need updating for this.
- C. The issue log records only problems that have already occurred. This risk's impact has only grown and the risk has not occurred, so it does not belong in the issue log.
- D. A contingent response strategy is developed when risk responses are planned; here only the assessment information has changed, so the risk register is updated first and the response strategy is not the first item to update.
Key takeaway When the probability or impact of an identified risk changes, update the risk register first.
Variation If the existing responses are no longer enough after the impact grows, then assess whether to adjust them, and submit a change request if a baseline is affected. If you want management to understand a change in overall risk status, what is updated is the risk report.
- Question 97
A logistics sorting-line upgrade project has a budget at completion of $48,000 and is planned to finish in 6 months. At the end of month 4, the project has spent $32,000, and both cost and schedule match the plan exactly. The project continues to follow the plan, which calls for completion at the end of month 6. What will the project's earned value (EV) be 3 months later, at the end of month 7?
Show answer and explanation
Correct answer: D
BAC is $48,000 and the plan is 6 months. At the end of month 4 cost and schedule both match the plan. The question asks for EV at the end of month 7.
If cost and schedule match the plan at the end of month 4, then EV = PV = AC = $32,000 and CPI = SPI = 1. On plan, the project finishes at the end of month 6, and at completion EV = BAC = $48,000. Earned value is the budgeted value of the work completed; once all the work is done it stops increasing. So at the end of month 7 it is still $48,000. The answer is D.
- End of month 4: cost and schedule match the plan, so EV = PV = AC = $32,000 and CPI = SPI = 1
- On plan, the project finishes at the end of month 6: EV = BAC = $48,000
- The stem says the project continues to follow the plan, so it finishes at the end of month 6; EV therefore remains $48,000 at the end of month 7
- Check: EV cannot exceed BAC, and $48,000 ≤ $48,000 holds. The answer is D
Why the other options are wrong
- A. $32,000 is EV at the end of month 4. It carries today's value forward as if no work were completed over the next 3 months.
- B. Extrapolating $8,000 per month ($32,000 ÷ 4) over 7 months gives $56,000, but EV is a budgeted value and can never exceed the budget at completion of $48,000.
- C. $16,000 = BAC − AC = $48,000 − $32,000. That is the remaining budget, not earned value.
Key takeaway Once the project actually completes as planned, EV equals BAC and does not rise merely because more time passes.
Variation For EV at the end of month 5, you would need the value of the work planned to be complete by then. If planned value is spread evenly over the 6 months, EV = $48,000 × 5 ÷ 6 = $40,000. If only 90% were complete at the end of month 6, EV = $48,000 × 90% = $43,200.
- Question 98
A project manager leads a team that mixes novices and senior staff and finds that team cohesiveness has become a problem. The senior members believe the newcomers lack the technical skills needed to do the work and expect that they themselves will have to make up for the newcomers' experience gap. What should the project manager do?
Show answer and explanation
Correct answer: C
In a team that mixes novices and senior staff, the senior members believe the newcomers lack the technical skills the work needs and expect to cover the gap themselves, and cohesiveness suffers. The question asks what the project manager should do.
The cohesiveness problem may be tied to a capability gap, but the senior members' view still needs objective confirmation, and the issue is not that rewards are too low. The project manager should map the skills of all members, find the gaps and draw up a plan to close them. That gives an objective picture of the current state and solves the problem systematically. The plan can include mentoring and training and can set aside mentoring time for the senior members. It also lets the senior members see that the gap is being formally planned for and that they no longer have to cover for the newcomers passively, which makes the repair of cohesiveness longer lasting. The correct answer is C.
Why the other options are wrong
- A. Rewarding the senior members might encourage mentoring, but before the skill gaps are mapped and an overall plan exists, setting a bonus first is not the preferred step and could unbalance relationships in the team.
- B. Moving the new members to other projects avoids the responsibility for team development and affects resource planning. The gap would still need to be closed once newcomers arrive.
- D. Leaving members to sort it out themselves goes against the project manager's duty to lead the team and close capability gaps.
Key takeaway When a skill gap is the root of a cohesiveness problem, map the skills first, then draw up a plan to close the gaps.
Variation If the stem had said that only one specific skill is missing, you would arrange training aimed directly at that skill.
- Question 99
On a production line renovation project for automotive parts, company rules tie the team bonus to the project's cost performance index. The project manager notices that over the last two months the team has postponed necessary testing and cut the training budget, and the cost performance index has kept rising as a result. What should the project manager do first?
Show answer and explanation
Correct answer: C
Company rules tie the team bonus to the project's cost performance index. As a result the team postponed necessary testing and cut the training budget, and the index keeps rising. What should the project manager do?
The very act of measuring influences behavior; this is the Hawthorne effect. With the bonus tied only to the cost performance index, the team will do things such as postponing testing and cutting training to make the number look good, which is the misuse of a metric. The project manager should assess whether the incentive mechanism is reasonable and adjust it, so that it stops misleading the team's behavior. The answer is C.
Why the other options are wrong
- A. Switching to the schedule performance index alone is still a single metric. The team will chase the new number, and the problem merely moves from cost to schedule.
- B. Requiring the testing to be made up corrects only the current behavior. The linking mechanism has not changed, and the team will cut necessary work for the metric again later.
- D. The problem is how the metric and incentive combine to shape behavior. Canceling the bonus without assessing first skips the analysis needed to decide whether the incentive should be modified, weakened or canceled. Assess first, then choose the appropriate adjustment.
Key takeaway Once a metric is tied to incentives it changes behavior, so when designing measures first assess whether they will mislead the team.
Variation If the indicators have always been green but the team feels strained, verify why the metrics and reality disagree. If targets are set so high that the team keeps missing them, that corresponds to the demoralization pitfall.
- Question 100
An agile team is adding a coupon feature to a customer's ticket-booking app. A test engineer finds that the feature may break the structure of the existing payment flow. The team initially determines that the risk does not threaten the current iteration goal and does not require immediate escalation. Which response to this newly identified risk is MOST appropriate?
Show answer and explanation
Correct answer: C
An agile team adding a coupon feature learns from a test engineer that it may break the payment flow structure. The team initially determines that the risk does not threaten the current iteration goal and does not require immediate escalation. The question asks for the most appropriate handling.
Adaptive projects emphasize transparency and surfacing risks early, then handling them through routine activities instead of a heavyweight meeting for every risk. Posting the risk on the team board makes it visible at any time, and raising it at the next daily coordination meeting lets the team discuss it quickly without interrupting the iteration. This matches the information radiator approach that PMBOK 8 promotes. The answer is C.
Why the other options are wrong
- A. Calling the whole team to an immediate risk meeting interrupts work in the current iteration. Risk information can be shared through existing routine activities; a new risk does not need its own meeting.
- B. A workshop with the senior management team is set at too high a level. The team can discuss and decide on its own; senior management is needed only when a matter exceeds the team's authority.
- D. Emailing the product owner keeps the information between two people, where it is easily overlooked, and it does not meet the adaptive expectation of making risks visible.
Key takeaway On adaptive projects, make a new risk visible and discuss it early through routine activities such as the daily coordination meeting.
Variation If the risk were serious enough to threaten the whole release, the team could schedule a dedicated discussion after raising it at the daily coordination meeting, and place the work in the backlog by priority.
Reference Monitor Risks · Lesson 4: Risk Review Meetings and the Watch List: Monitoring Risks in Predictive and Adaptive Projects
- Question 101
A warehouse system upgrade project at a logistics company has entered execution, and the project manager wants the team to be able to handle day-to-day technical decisions independently from now on. Which approach best empowers the team?
Show answer and explanation
Correct answer: D
A warehouse system upgrade project is in execution, and the project manager wants the team to handle day-to-day technical decisions independently. The question asks which approach best empowers the team.
Empowerment is not laissez-faire, and it is not control under another name. Effective empowerment has three elements: define the scope of authority, let the team decide autonomously within it, and make the team accountable for the results. When authority and accountability match, the team will actually use its decision rights and will build the ability to handle problems independently through practice. The answer is D.
Why the other options are wrong
- A. Designing detailed approvals for each type of decision with the project manager reviewing each item keeps decisions concentrated with the project manager, leaving the team no room to decide.
- B. Postponing delegation until after an assessment, with the project manager deciding in the meantime, separates training from delegation, and the team gets no practice.
- C. Hearing the team’s views only at closing misses the chance to involve the team in decisions during the project and does not amount to empowerment.
Key takeaway Empowering a team = define the scope of authority + autonomous decisions by the team + accountability for results.
Variation If an option read “delegate most of the authority but hold back important information to control the team,” that is not empowerment, because empowerment requires sharing information; if the team is newly formed, guide it first and delegate afterward.
- Question 102
On a factory production line upgrade project, a technical lead came up with a way to raise commissioning efficiency and was praised by the customer at the following performance review meeting, which left some other members a little resentful. He is not sure when such experience should be shared and asks the project manager. How should the project manager advise him?
Show answer and explanation
Correct answer: C
The technical lead has a commissioning practice worth sharing, and the customer's praise has caused some resentment on the team. He does not know when to share it, so the question concerns when lessons learned are collected.
Lessons learned are collected throughout the project; individuals and teams involved in the work can take part in recording them, and they can be captured with video, pictures, audio and other means. Sharing and recording at any time lets the team benefit promptly and also shows members that the practice serves everyone, which helps ease the resentment. So the project manager should advise him not to wait for a particular milestone. The answer is C.
Why the other options are wrong
- A. Sharing only at administrative closure means the experience is no use to the project while it runs and the details are easily forgotten. Lessons learned should be collected at any time during the project.
- B. A phase gate review can be a point for concentrated reflection, but lessons learned are not limited to particular milestones. Waiting for the gate would miss the chance to improve right now.
- D. Sharing experience has nothing to do with whether all the customer's feedback is in. Waiting for complete feedback would delay the use of the experience and would not ease the resentment within the team.
Key takeaway Lessons learned are not collected only at milestones or at closing; they are shared and recorded at any time during the project.
Variation If asked where lessons learned finally end up, the answer is that at project closing they go into the lessons learned repository for later projects to use.
Reference Lessons Learned · Lesson 2: The Lessons Learned Register: What to Record, When to Update It, Where It Goes
- Question 103
The agile team at a software company has worked on a new app for 8 months, with release originally planned for month 14. In month 8 the customer decides that releasing 2 months earlier than planned would be better for the product, and the company moves several of the organization's strongest engineers onto the team to make sure it can finish early. Which risk response strategy is this?
Show answer and explanation
Correct answer: C
An agile team has worked on a new app for 8 months, with release planned for month 14. The customer thinks releasing 2 months earlier would be better, and the company moves the organization's strongest engineers onto the team to make sure it finishes early. You must decide which risk response strategy this is.
Releasing earlier brings a benefit, so it is an opportunity. The stem has two signals: the engineers moved in are the “strongest,” and the purpose is to “make sure” the early finish happens. Exploit means making sure the opportunity happens, raising its probability to 100%, and a typical way is to assign the organization's most capable resources to the project to shorten the duration. Both signals fit, so this is exploit. The answer is C.
Why the other options are wrong
- A. Enhance increases the probability or the impact of the opportunity, and the means are more general, such as adding some staff or more training. The stem stresses the “strongest resources” and “make sure,” a higher degree, which is exploit.
- B. Accept acknowledges the opportunity but does not pursue it actively. The company has actively assigned resources to seize this opportunity, so it is not acceptance.
- D. Share gives responsibility for the opportunity to a third party so both share the benefit, for example through a joint venture or joint contracting. Here the company's own team still does the work and there is no outside partner.
Key takeaway Exploit means making sure, using the strongest resources or newest technology; enhance means increasing, with more general means.
Variation If the company only added a few ordinary engineers working overtime to improve the chance of an early release, it would be enhance. If it developed the app jointly with an outside company and shared the benefit, it would be share.
Reference Risk Response Strategies · Lesson 3: Strategies for Opportunities and for Overall Project Risk
- Question 104
An internal approval-system project at an enterprise is being developed with agile methods. The Product Owner spends very little time on the project and cannot verify the completed work, yet the team lead still needs to ensure that all requirements are met. What should the team lead do?
Show answer and explanation
Correct answer: B
A project uses agile methods. The Product Owner is involved very little and cannot verify completed work in time, yet the team lead still has to ensure requirements are met. The question asks for the most direct and effective step.
For requirements to be met, the Product Owner must inspect completed work promptly and give feedback, which requires deep involvement. The most direct way is to arrange for the Product Owner to meet directly with the team so that the Product Owner actually takes part, verifies results and clarifies requirements, solving the problem at the level of collaboration. The answer is B.
Why the other options are wrong
- A. Confronting the Product Owner in person is a confrontational approach that strains the relationship. The Daily Scrum is also the team's own meeting, not a place to hold the Product Owner to account.
- C. A memo is just “sending a document”. It does not change the fact that the Product Owner is not involved and does not get the work verified.
- D. Escalating up the chain and asking for a replacement turns a problem that communication can solve into a personnel matter, takes a long time and drags down the team's progress.
Key takeaway When the Product Owner is not involved enough, first arrange direct communication with the team. Do not confront, send memos or replace.
Variation If the Product Owner still stays absent after direct communication, consider explaining to the sponsor how this level of involvement affects product value and asking the organization to adjust the Product Owner's schedule.
Reference Scrum Roles · Lesson 1: The Product Owner: Decides What to Build, What Comes First and Whether to Accept It
- Question 105
The R&D team of a software company is scattered across three time zones, and the quarterly review finds low output. After investigating, the project manager learns that the responsibility assignment matrix names a clear owner for every piece of work, but members understand differently what work each should do: some work has no one claiming it and some is done twice. What is the most appropriate thing for the project manager to do?
Show answer and explanation
Correct answer: B
The R&D team is in three time zones. The responsibility assignment matrix states an owner for every piece of work, but members understand the division of labor differently: some work is unclaimed and some is done twice. The question asks what the project manager should do.
The crux is that information is not being conveyed and understood consistently; the tasks are not wrongly assigned. PMBOK 8 notes that the communications management plan describes how, when and by whom information will be administered and disseminated, and it says to review the plan periodically and tailor it as needed. A distributed team relies more on clear information arrangements, so the project manager should review the communications management plan to see whether the content, methods, frequency and responsibilities fit a team spread across time zones, and adjust it. The answer is B.
Why the other options are wrong
- A. Checking the work list and reassigning treats the symptom as the cause: the responsibility assignment matrix is already clear, and the problem is that information is not reaching the time zones consistently. After reassignment everyone would again have their own understanding.
- C. An online team-building event can improve relationships but does nothing about the information problem of who should do what, and does not change how information is delivered.
- D. Bringing three time zones together in one office is costly and unrealistic. It is not what should be done first now, and it does not analyze why communication has failed.
Key takeaway When a distributed team understands the division of work inconsistently, first go back and review the communications management plan.
Variation If the review shows the plan sets no overlapping working hours across time zones, add fixed synchronization times and a written confirmation mechanism.
Reference Plan Communications Management · Lesson 5: The Communications Management Plan: Contents, Use and Updates
- Question 106
A smart home project uses a hybrid approach: the hardware part proceeds predictively, and the application software part is developed using an adaptive, iterative approach. How should scope management be arranged?
Show answer and explanation
Correct answer: A
A hybrid project: the hardware part proceeds as predictive and the application software part is developed using an adaptive, iterative approach. The question asks how scope management should be arranged.
In a hybrid project the overall expectations are set by the scope baseline, schedule baseline and cost baseline, while the sub-teams below may work through the user stories on the backlog iteration by iteration. So scope is managed part by part. The hardware is predictive and gets a scope baseline (project scope statement, WBS, WBS dictionary), with changes going through formal change control; the software is adaptive and carries its scope in a backlog, with the product owner dynamically ordering and approving by value. The answer is A.
Why the other options are wrong
- B. Freezing the software part as well takes away its flexibility to adjust by iteration and respond to feedback, which goes against the adaptive approach.
- C. The hardware proceeds as predictive and needs a scope baseline and formal change control; a backlog alone cannot manage it.
- D. This swaps the methods: what needs a baseline is the predictive hardware, and what can be adjusted dynamically is the adaptive software.
Key takeaway A hybrid project is managed part by part: the predictive part has a baseline, and the adaptive part uses a backlog.
Variation If the whole project were adaptive, you would usually not freeze an overall scope baseline in advance but set the baseline for each iteration at its start; if requirements change on the hardware part, you still raise a change request and go through change control.
Practice test or full mock exam: what is the difference?
- Free practice tests: 8 tests, the first with 120 questions and the others about 107 each, drawn from the 1,000 free questions (you may have met some while practicing by chapter), no login. Good for a quick self-check and for finding your weak domain.
- Full mock exams: 180 questions each, separate from the practice bank (none of them appear there), timed in 3 sittings like the real exam. Use them to judge whether you are ready. See the full mock exams.
Free PMP practice test: common questions
Is this PMP practice test really free?
Yes. There is no account and no email wall. All 106 questions and the full explanation of every answer are free, and your progress is saved in your browser.
How were the 106 questions chosen?
They come from the 1,000 free questions: 27 People, 49 Process and 30 Business Environment questions, covering 23 of the 26 tasks of the Exam Content Outline, with single-answer and multiple-answer questions. There are 8 free tests and no question appears in more than one of them. Once a domain runs out of free questions a test is a little shorter, and the count shown is the real one.
How long does the test take?
Timed mode follows the real exam's pace of 80 seconds a question, so 106 questions get 141 minutes. You can also choose untimed practice and take as long as you like.
How are multiple-answer questions scored?
A multiple-answer question counts as correct only when you select every correct option and nothing else. There is no partial credit, and an unanswered question counts as wrong.
Are these real PMP exam questions?
No. PMI does not release exam questions. Every question here is original, written to the Exam Content Outline, to practice the question styles and the reasoning.
What should I do after the test?
Take another of the free tests, keep practicing by chapter in the 2,876-question bank, or take one of the 10 full mock exams of 180 questions. Your score here is a practice signal, not a prediction of the exam result.
To study first, read the study guide; for the whole bank, practice by chapter.