Free PMP Practice Test 5: 107 Questions with Explanations

107 PMP sample questions, test 5 of 8 with no question repeated from the other tests: 28 People, 49 Process and 30 Business Environment, covering 24 of the 26 tasks of the Exam Content Outline. Timed mode gives 80 seconds a question, 143 minutes in all; or practice untimed. Every question has a full explanation: why the answer is right and what is wrong with each other option. When you submit you get your total score, your accuracy in each of the three domains and a readiness check.

Updated 2026-11-22 · aligned to the current Exam Content Outline and PMBOK Guide 8th Edition

Start the test ↓

Ready to start?

Your answers are saved in this browser, so you can refresh or come back later. No account needed.

You can read every question below before you start; the answer options unlock when you press Start.

  1. Question 1

    A project manager has just been appointed to lead a new product project and receives a business case completed by someone else two years ago. She is ready to start the project. What should she do FIRST?

    Show answer and explanation

    Correct answer: B

    The project manager has just been appointed to lead a new product project and holds a business case completed by someone else two years ago. The project is in initiating. The question asks what to do first.

    “Two years ago” and “completed by someone else” are the core information: the business case is an important input to initiating, but its currency is in doubt and it cannot be taken at face value. First review its content and conclusions to see whether they still apply to the current project, and then move on to the charter on that basis. The Eighth Edition classes the business case as a business document, not a project document, typically produced outside the project and before it is initiated. The Eighth Edition says the sponsor is generally accountable for developing and maintaining the project’s business case; common exam practice is that the project manager reviews business documents and makes recommendations rather than revising them personally. The answer is B.

    Why the other options are wrong

    • A. Preparing the charter without a review would carry outdated objectives, assumptions and success criteria into the charter.
    • C. The stem says she has been “appointed to lead” the project. Her appointment is not the urgent matter now, and the review does not have to wait for it.
    • D. Review is right, but “revise” is wrong: the Eighth Edition classes the business case as a business document and not a project document, and by common exam practice the project manager who finds a problem makes a recommendation to the sponsor and does not revise it personally.

    Key takeaway On receiving an old business case, first review whether it still applies; if there are problems, make recommendations and do not edit it yourself.

    Variation If what has to be changed is an outdated entry in the assumption log, that is a project document and the project manager can update it directly. If the review shows the business case is still valid, use it directly to elaborate the charter.

  2. Question 2

    A project has a most likely duration of 9 weeks, an optimistic duration of 7 weeks and a pessimistic duration of 14 weeks. Using multipoint estimating with the beta distribution (PERT), what is the estimated duration in weeks?

    Show answer and explanation

    Correct answer: B

    To estimate a duration, the stem gives an optimistic 7 weeks, most likely 9 weeks and pessimistic 14 weeks and specifies the beta distribution (PERT) formula. What is the estimated duration?

    Under the beta distribution, tE = (tO + 4tM + tP) ÷ 6, which magnifies the weight of the most likely value to 4 to reflect that it is the most likely to occur. Substituting gives 9.5 weeks, which lies between 7 and 14 weeks and slightly above the most likely value of 9 weeks, in line with the pessimistic value being farther out. The answer is B.

    1. tE = (tO + 4tM + tP) ÷ 6
    2. = (7 + 4 × 9 + 14) ÷ 6 = (7 + 36 + 14) ÷ 6
    3. = 57 ÷ 6 = 9.5 weeks
    4. Check: 9.5 lies between 7 and 14 and leans toward the most likely value, which is reasonable

    Why the other options are wrong

    • A. 9 weeks is the most likely value and does not take the optimistic and pessimistic values into account.
    • C. 10 weeks is the triangular distribution result, (7 + 9 + 14) ÷ 3 = 10. The stem specifies the beta distribution, not the triangular distribution.
    • D. 14 weeks is the pessimistic value. The estimated duration is an expected value, not the worst case.

    Key takeaway Beta distribution (PERT) formula: (O + 4M + P) ÷ 6, not a simple average. Use it when the question asks for PERT or beta; triangular is the simple average, (O + M + P) ÷ 3.

    Variation If the stem explicitly specified the triangular distribution, the answer would become (7 + 9 + 14) ÷ 3 = 10 weeks.

    Reference Multipoint (Three-Point) Estimating · Lesson 2: Multipoint Estimating: Worked Examples, Common Mistakes and Using the Results

  3. Question 3

    A retail group is running a membership system project and a warehouse system project at the same time. The membership project's project manager finds that the plan does not account for the dependencies created by sharing a test environment and an interface development team with the warehouse project. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    Two projects run in parallel in one organization. The membership project's plan does not account for the dependencies from sharing a test environment and an interface development team with the warehouse project. What is the action once the omission is found?

    A project plan is not isolated. Dependencies that arise from sharing resources and environments with other projects must be identified, coordinated with the other project and written into this project's plan to be managed continuously. A dependency does not disappear because it is ignored, and only by putting it in the plan can it be controlled. Sharing a test environment and an interface team can create scheduling conflicts. The dependencies should be reflected in the schedule and resource-coordination arrangements, while the resulting uncertain conflict risk should be recorded in the risk register, together with an agreed coordination mechanism and priorities with the other project. The answer is C.

    Why the other options are wrong

    • A. Looking only at your own project and raising it when the other project has trouble lets the dependency risk blow up at the worst moment, by which time it is too late to coordinate.
    • B. Asking the warehouse project to give up the shared test environment passes the problem to someone else, and the project manager has no authority to decide that. The dependency itself is still unmanaged.
    • D. Removing the work related to the shared environment and interface team would change this project's scope, yet that work is necessary for delivery, and the dependency remains.

    Key takeaway Dependencies do not disappear by being ignored. Identify cross-project dependencies, coordinate them and include them in the plan.

    Variation If coordination fails and the other side will not agree to share, escalate to the program or PMO level, where someone with authority coordinates the resources.

    Reference The Project Management Plan · Lesson 4: Plan Integration in Predictive and Adaptive Projects

  4. Question 4

    The company is moving from waterfall management to agile, using Scrum. You are an experienced Scrum Master whose important project has a very high level of customer satisfaction. The company now asks you to coach another team that is struggling to implement Scrum. What should you do?

    Show answer and explanation

    Correct answer: D

    The company is moving from waterfall to agile and has chosen Scrum. You are an experienced Scrum Master whose important project has high customer satisfaction, and you are asked to coach another team that is feeling its way with Scrum. What should you do?

    The parties a Scrum Master serves include the organization, and one of the Scrum Master's duties is leading and coaching the organization in adopting Scrum. Since you have been asked to coach, the most appropriate move is to assess the team's current Scrum maturity together with that team's Scrum Master and Product Owner, and then give targeted guidance. The answer is D.

    Why the other options are wrong

    • A. You were asked to coach, and handing it to the project management office for training or assigning someone else is passing the buck, not giving help directly.
    • B. Asking first whether you will be moved avoids the coaching task and does nothing for the other team's problem.
    • C. The stem does not say that team has failed, so “analyzing the reasons for failure” has no basis, and reporting to the project management office is not coaching-style support either.

    Key takeaway Serving the organization means assessing and coaching together with the other team's roles.

    Variation If the stem said everyone on your team lacked agile knowledge, the first thing to do would be to get everyone trained, not only some of them.

  5. Question 5

    In a cross-functional agile team, a tester cannot complete the tasks the team assigned because the functional manager has suddenly assigned the tester work inside the department. What should the Scrum Master do?

    Show answer and explanation

    Correct answer: C

    In a cross-functional agile team, a tester cannot complete the tasks the team assigned because the functional manager has suddenly assigned department work to the tester. The question asks for the Scrum Master's correct response.

    On the surface it is a resource conflict, but in essence the functional manager's interference has become an impediment to the team. Removing impediments is the servant leader's duty, and the resource conflict is resolved by negotiating with the functional manager: the Scrum Master should talk with the functional manager, understand what the manager needs, and negotiate the member's available time in the Sprint. The answer is C.

    Why the other options are wrong

    • A. Sending the member back to the department weakens the team, does not solve the root cause of the functional manager taking up resources and creates a new gap.
    • B. Escalating directly to the sponsor before attempting to negotiate is premature and could damage the relationship with the functional manager. Communicate and negotiate first, and consider escalating only if negotiation fails.
    • D. The project charter is not a document that governs the functional manager's day-to-day arrangements, and a firm tone of “demanding compliance” does not help negotiation.

    Key takeaway Outside interference is also an impediment. Communicate and negotiate first, with no confrontation and no skipping straight to escalation.

    Variation If the stem were changed to “the functional manager calls status meetings several times a week”, you would likewise negotiate an alternative first, for example asking the manager to look at the team's information radiator.

  6. Question 6

    Two months after a retail company's inventory counting process change goes live, the project manager confirms that many employees understand and support the change, have completed training and can correctly perform the new process, but still use the old process. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    Two months after the change goes live, employees are still using the old process. The new way has not really taken hold and needs to be reinforced.

    A change delivers its results only when the new way is actually used and sustained. The signal is “still using the old process two months after go-live”: the new way has not really taken hold and needs reinforcement. The stem says these employees understand and support the change, have completed training and can correctly perform the new process. Following up on execution, collecting feedback and coaching employees reveals why they still use the old process, corrects their old habits and reinforces the new process. You can work backward through ADKAR's five steps on questions like this (common exam practice): if employees already know why the change is needed and have been taught the new process but still use the old way, what is missing is reinforcement, which calls for continued follow-up. The answer is C.

    Why the other options are wrong

    • A. Closing the project and pushing usage to the departments gives up on reinforcing the result of the change, and the old habits continue.
    • B. Sending another notice is still a one-way demand. It does not find out why employees keep the old process, so it is unlikely to change habits.
    • D. Keeping the old process until employees get familiar with the materials is not a planned parallel cutover with an end date; it sends employees who can already perform the new process back to the old way. The stem does not say employees lack training materials or are unfamiliar with them, so waiting is not targeted and does not correct the old habit that is happening now.

    Key takeaway After a change goes live, keep following up and correct old habits to reinforce the result.

    Variation If the stem changes to “employees do not know why the change is needed”, that corresponds to awareness, and the answer is to communicate the reason for the change; “employees are willing but do not know how” corresponds to knowledge and ability, and the answer is training and coaching.

  7. Question 7

    A consulting firm's project manager reports to the sponsor and executives at mid-project. The cost report gives a point estimate of $480,000 with an estimate range of $460,000 to $500,000. What level of estimate is this?

    Show answer and explanation

    Correct answer: C

    The project is at mid-stage, and the cost report gives an estimate range of $460,000 to $500,000. The question asks which level of estimate this is.

    The estimate grade is judged by the width of the range and the amount of information. A rough order of magnitude estimate is about −25% to +75% and is used early, when little information exists; a definitive estimate is about −5% to +10% and is used once information is sufficient (rough order of magnitude and definitive estimate are common exam grade names and the ranges are common exam reference values, all common exam practice). Here the point estimate is $480,000, and the range is about $20,000 above and below it, roughly ±4%, which falls within the definitive estimate range, and by mid-project information is already fairly complete. The answer is C.

    1. Point estimate = $480,000; lower limit $460,000, upper limit $500,000, each $20,000 away
    2. Deviation ÷ point estimate = 20,000 ÷ 480,000 ≈ 4.2%, a very narrow range
    3. For comparison: a rough order of magnitude estimate would be 480,000 × 0.75 to 480,000 × 1.75 = $360,000 to $840,000, far wider than the range in the question
    4. Check: a definitive estimate of −5% to +10% corresponds to $456,000 to $528,000, and the range in the question lies within it, so choose the definitive estimate

    Why the other options are wrong

    • A. Rolling wave planning is a way of elaborating progressively as the project advances. It is not an estimate grade distinguished by accuracy.
    • B. A rough order of magnitude estimate centered on $480,000 would cover about $360,000 to $840,000, far wider than the range in the report.
    • D. Analogous estimating is a method that refers to similar past projects. It is not an estimate grade.

    Key takeaway A range that is only a few percentage points wide with sufficient information is a definitive estimate; a very wide range with very little information is a rough order of magnitude estimate.

    Variation If the report said “estimate $20,000; the actual may be between $15,000 and $35,000”, the range is −25% to +75% and it is a rough order of magnitude estimate.

  8. Question 8

    At a team meeting, the project manager had members complete a personality assessment and found that more than half of them are introverted. What should the project manager do to collect more input at meetings?

    Show answer and explanation

    Correct answer: D

    The project manager had members take a personality assessment and found more than half are introverted. The question asks what to do to collect more input at meetings. The key is that introverts need time to think.

    Introverted members are usually not comfortable speaking off the cuff and need time to organize their thoughts. Sending the agenda the day before, so they can think before speaking, is a concrete and easy measure aimed at their trait, and it makes them more willing and better able to contribute in the meeting. This is common exam practice, and its thinking fits PMBOK 8’s emphasis on building a collaborative environment through communication and team building. The answer is D.

    Why the other options are wrong

    • A. Requiring detailed personal information at the start of every meeting would make introverted members even more uncomfortable and has no direct link to encouraging them to speak.
    • B. Requiring views to be voiced and explained on the spot only restates expectations and adds pressure. It offers no way to help introverted members speak.
    • C. Adjusting lighting and background noise might relax people a little, but it has little to do with letting introverted members contribute fully and is not aimed at their trait.

    Key takeaway Once you know members’ traits, use measures like sending the agenda ahead to help introverts speak. That works better than pressure or changing the setting.

    Variation For a video meeting, also add a written chat channel for questions and a way to add input after the meeting, giving members with different styles more ways to contribute.

    Reference The Tuckman Ladder · Lesson 2: Team Building: Activities, Trust and Shared Goals

  9. Question 9

    Collaboration problems arise inside a self-organizing team, and team members come to the project manager to report them. As a servant leader, what should the project manager do?

    Show answer and explanation

    Correct answer: C

    Collaboration problems arise inside a self-organizing team and members bring them to the project manager. His role is servant leader, and he should act accordingly.

    PMBOK 8 notes that leaders should be open to feedback and work for the team, supporting its needs and removing barriers when possible, and that these values form the basis for servant leadership. A self-organizing team makes its own decisions and solves its own problems, so the project manager should guide the team to find a way itself and offer support when needed, rather than giving the answer. That is how the team gradually becomes independent. The answer is C.

    Why the other options are wrong

    • A. Having the project manager and the team lead draft the solution leaves most members out, goes against self-organization and makes the solution hard to carry out.
    • B. Passing the problem to management to develop a solution takes away the team’s chance to solve it and adds an unnecessary layer. It is not how a servant leader acts.
    • D. Handing over a ready-made solution is command and control. The team will become dependent, which is the opposite of the servant leader’s goal of helping the team become self-reliant.

    Key takeaway A servant leader guides the team to solve its own problems instead of giving it the answers.

    Variation If the team tries and still cannot resolve it, the servant leader can offer a framework or bring in a third party to help, but the decision still belongs to the team.

    Reference Leadership Styles · Lesson 2: Servant Leadership: Serve the Team First, Then Lead

  10. Question 10

    A manufacturer is drafting the project charter for a new product introduction project. At this point senior management, to meet business needs, decides to convert the current functional organizational structure to a matrix one throughout. Which kind of input affecting the development of the project charter is this change?

    Show answer and explanation

    Correct answer: B

    The project is at initiation and the charter is being drafted. You must decide which kind of input the change in organizational structure belongs to; no specific development approach is involved.

    Organizational structure (functional, matrix and so on) falls under “organizational culture, structure and governance” among the internal enterprise environmental factors. It is an objective condition that the project team cannot directly control and usually has to adapt to, and enterprise environmental factors are an input to be considered when starting a project or phase (developing the project charter). Senior management's move from functional to matrix means the internal environmental conditions of the organization have changed, and the team has no way to control the change directly, so the answer is B.

    Why the other options are wrong

    • A. Organizational process assets include the organization's plans, processes, policies, procedures, templates and knowledge repositories; some may be tailored or updated under the applicable rules. Organizational structure itself is an internal enterprise environmental factor, not an organizational process asset.
    • C. The assumption log records the project's assumptions and constraints and is a document produced along with the project charter. It is not a classification of a change in organizational structure.
    • D. The business case explains why the project is necessary and what benefits are expected, that is, why it is worth doing. A restructuring of the organization is not part of the business case.

    Key takeaway A change in organizational structure is an internal enterprise environmental factor, not an organizational process asset.

    Variation If the company released a new project charter template, it would be an organizational process asset; if the company switched the project management information system everyone must use, that system would be an internal enterprise environmental factor. Classify by the nature of the item: organizational structure and existing information systems are environmental conditions, while policies, processes, templates and knowledge repositories are organizational process assets. Do not rely only on whether the team can change it directly.

  11. Question 11

    A corporate group launched a project to overhaul its internal expense reimbursement system so it would be easier to use. After a long push, the results are done and accepted, the project manager has held the lessons learned meeting, team performance appraisals are complete, and releasing the team is scheduled as the last closure step. To wrap up the project, what should the project manager do next?

    Show answer and explanation

    Correct answer: D

    The reimbursement system overhaul has been accepted, the lessons learned meeting has been held, team performance appraisals are complete, and resource release is scheduled as the last step. The question asks what comes next in closure.

    PMBOK 8 says that at the end of a project or phase the relevant information should be put into the lessons learned repository, that is, organizational process assets are updated. The lessons learned meeting has been held, so the next step is to consolidate the lessons learned and related information into the organizational process assets. The answer is D.

    Why the other options are wrong

    • A. Checking whether the deliverables meet requirements is the verification work done before acceptance, and in this question it was completed with acceptance.
    • B. A celebration is not a required administrative closure step and cannot replace entering lessons into the repository and archiving the project files.
    • C. The stem states that team performance appraisals are complete and that releasing the team is scheduled as the last closure step, so it is not yet time to review appraisals and release people; the summarized lessons should first be transferred into organizational process assets.

    Key takeaway After lessons learned are summarized, the next step is to put them into the lessons learned repository, that is, to update organizational process assets.

    Variation If the stem said “the lessons learned are in the repository and archived”, closure work is largely done and resources are then released as planned. If it said the lessons have not yet been summarized, you cannot archive first.

  12. Question 12

    The project manager of a hospital information platform project is developing a detailed schedule and asks several subject matter experts (SMEs) for initial estimates of activity durations. The experts' numbers differ widely, and the project manager is concerned. How should the project manager help produce the estimates?

    Show answer and explanation

    Correct answer: D

    In planning a hospital information platform project, the project manager asks several subject matter experts for initial estimates of activity durations. The numbers differ widely and the project manager is concerned. How should the project manager help produce the estimates?

    When experts' numbers are far apart, the usual reason is that they are relying on different assumptions and information. Option D follows the wideband Delphi approach: after the experts have estimated individually, have the experts reveal their estimates, discuss the reasons and assumptions behind the highest and lowest values to remove bias and information gaps, and then re-estimate. Repeating this discuss-and-re-estimate cycle for a few rounds brings the estimates together until consensus is reached. The disagreement often comes from an overlooked assumption, so discussion is worth more than averaging. The answer is D.

    Why the other options are wrong

    • A. The project manager should first coordinate the experts to resolve the differences. Reporting them straight to the sponsor avoids the problem, and the sponsor may not know the details of the activities.
    • B. Historical information is a useful reference but cannot replace the experts discussing their differences. After consulting it, each person still carries the original assumptions.
    • C. Adopting only what everyone agrees on hides the disagreement and the overlooked assumptions, and the risk is often exactly where the disagreement is.

    Key takeaway When experts disagree widely, have them reveal their basis, discuss the extreme values, and re-estimate until the numbers converge.

    Variation A project manager who simply averaged two experts' numbers would also not be ideal, because the average does not resolve the difference in assumptions. For an agile team, use planning poker for relative estimates. If the experts must submit anonymously without knowing each other's numbers, that corresponds to the classic (anonymous) Delphi technique.

  13. Question 13

    Which of the following statements about a project schedule network diagram is NOT correct?

    Show answer and explanation

    Correct answer: C

    This question asks which statement about the project schedule network diagram is not correct.

    PMBOK 8 states that activities that have multiple predecessor activities indicate a path convergence and activities that have multiple successor activities indicate a path divergence. Activities with divergence and convergence are at greater risk because they are affected by multiple activities or can affect multiple activities. Statement C says these activities carry “relatively little risk”, which is the opposite, so it is the incorrect statement the question asks for. Every activity in a network diagram (except the first and last) should be connected to predecessors and successors, and it is the number of these connections that makes a convergence or a divergence. The answer is C.

    Why the other options are wrong

    • A. This statement is correct: a project schedule network diagram is a graphical way to show the logical relationships among activities. It is not the incorrect statement.
    • B. This statement is correct: an activity with multiple predecessor activities is at a path convergence. It is not the incorrect statement.
    • D. This statement is correct: an activity with multiple successor activities is at a path divergence. It is not the incorrect statement.

    Key takeaway Activities at path convergences and divergences carry more risk, so assess the need to aggregate schedule reserves where necessary.

    Variation If asked which activities most need an assessment of aggregated schedule reserves, the answer is those where multiple paths converge or diverge.

    Reference Precedence Diagramming Method · Lesson 1: The Precedence Diagramming Method: Network Diagrams and the Four Logical Relationships

  14. Question 14

    PMLyceum is delivering a batch of self-checkout devices to several overseas markets where it has never delivered before. The project manager begins planning and wants to identify the constraints these markets will place on the project. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    The company is delivering self-checkout devices to several overseas markets where it has no delivery experience. The project manager begins planning and wants to identify the constraints those markets will place on the project. The key fact is that the company has no delivery experience in these markets.

    The target markets' legal restrictions, government or industry standards, social and cultural influences and marketplace conditions are all external enterprise environmental factors, and they are what constrains the project in a new region. To identify the constraints, research these enterprise environmental factors. PMBOK 8 states plainly that enterprise environmental factors are conditions not directly influenced by the project team that impact or constrain the project. The answer is A.

    Why the other options are wrong

    • B. Lessons learned from earlier projects can supplement the research, but the company lacks direct delivery experience in these markets, and they cannot replace research into the local external environmental factors.
    • C. Brainstorming with local stakeholders can supplement the local information, but to identify constraints such as law, standards, culture and market comprehensively, first research the target markets' enterprise environmental factors systematically.
    • D. A meeting with the sponsor can bring out what the sponsor knows, but the source of the constraints is the external environment itself. Research the environmental factors first, and treat the meeting as a supplement.

    Key takeaway To identify the constraints of a new region, first research the enterprise environmental factors there; where there is no direct delivery experience, lessons learned are only a supplement.

    Variation If the company already had several projects in that market, you could first look through the lessons learned from those earlier projects.

    Reference Enterprise Environmental Factors · Lesson 2: External Enterprise Environmental Factors and Responding to Change

  15. Question 15

    A project manager is assigned to develop warehouse scheduling software for a logistics company. Another business unit of the company did a similar project that was later stopped because its performance was too poor, and its lessons learned were archived in the organizational knowledge repository. The project manager is worried about how this project will turn out and wants to take action in advance to make sure it succeeds. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    In this project the project manager wants to learn from a similar project's failure within the organization, and the question is what measure the project manager should take.

    The reasons a similar project failed are recorded in the lessons learned in the organizational knowledge repository, which is an organizational process asset. Reviewing those lessons learned directly shows the problems to avoid and lets them be prevented in this project's planning, which meets the requirement to “take action in advance and make sure of success” and also reflects the pattern that when you meet a similar project you first consult the organizational process assets. The answer is C.

    Why the other options are wrong

    • A. Assessing risks and adding outside experts first does not use the ready-made internal experience, costs more, and, with the specific causes of the failure not yet understood, is hard to aim correctly.
    • B. That a similar project failed does not mean this one will, and urging the sponsor to terminate is a premature, negative step when the information is still insufficient.
    • D. Doing no prevention and adding resources only when problems appear is reactive and does not achieve the aim of “taking action in advance.”

    Key takeaway When you see a similar project, first review its lessons learned, and then decide whether other measures are needed.

    Variation If the company had no similar project and the project manager lacked experience of the kind, first go to experienced experts or the PMO for advice and also consult outside material; if the similar project had been a success, you would likewise first review its lessons learned and then tailor them for this project.

  16. Question 16

    A project manager is leading the team on the interface design for an app. At an internal meeting to finalize the interaction prototype, two members disagree and argue until the meeting cannot go on. The project manager decides to postpone the prototype review meeting. Which conflict resolution technique did the project manager use?

    Show answer and explanation

    Correct answer: B

    While finalizing an interaction prototype, two members disagree so heatedly that the meeting cannot continue, and the project manager postpones the prototype review. The question asks which conflict resolution technique this is.

    PMBOK 8 describes withdraw/avoid as retreating from an actual or potential conflict situation, postponing the issue to be better prepared or to be resolved by others. The project manager did not deal with the disagreement itself and postponed the review, so the problem is put aside for now. That matches postponing the issue. The answer is B.

    Why the other options are wrong

    • A. Smooth/accommodate emphasizes areas of agreement and concedes one's position to maintain relationships. Nobody conceded here; the meeting was just postponed.
    • C. Compromise/reconcile seeks a solution that gives each party some degree of satisfaction, temporarily or partially. No middle-ground solution appears in the stem.
    • D. Collaborate/problem-solve means combining multiple viewpoints through open dialogue to reach consensus. Here the members argued, but they did not use open dialogue to solve the problem together; the project manager merely postponed the meeting.

    Key takeaway Postponing or stepping out without dealing with the conflict itself is withdraw/avoid.

    Variation If the project manager had instead asked each of the two to give up a little and take a middle position, that would be compromise/reconcile; if the project manager had had the two study options together, it would be collaborate/problem-solve.

    Reference Conflict Management · Lesson 2: The Five Conflict Resolution Techniques: Names, Meanings and When to Use Each

  17. Question 17

    A project at PMLyceum involves several suppliers and has heavy delivery pressure. At a regular meeting, the sponsor asks how often risks are reviewed. Which document should the project manager consult FIRST?

    Show answer and explanation

    Correct answer: B

    A project involves several suppliers and has heavy delivery pressure. At a regular meeting, the sponsor asks how often risks are reviewed. The question asks which document to consult first.

    The sponsor's question is about the rule, “how often to review”, not about the state of one specific risk. Rule-type content, including the timing and frequency of risk management activities, roles and responsibilities, risk categories and thresholds, is set in the risk management plan, which defines how often the risk processes are performed over the life cycle. So consult the risk management plan first. Information on specific risks is in the register, what has happened is in the issue log, and reports on risk status are in the risk report; none of them defines frequency. The answer is B.

    Why the other options are wrong

    • A. The risk register records specific details of identified individual risks, such as responses, owners and status; it does not set how often risk is reviewed.
    • C. The issue log records issues that have occurred and how they were handled, tracking what has already happened; it has nothing to do with the rule on how often risks are reviewed.
    • D. The risk report summarizes overall project risk and the state of individual risks. It reports results and does not define how often risk reviews take place.

    Key takeaway For how often risks are reviewed and how they are managed, check the risk management plan; for the state of a specific risk, check the risk register.

    Variation For “who is responsible for responding to a certain kind of risk”, check the roles and responsibilities in the plan; for “the owner of one specific risk”, check the risk register.

  18. Question 18

    An agile team's team charter says a decision needs at least 80% of members in favor to go ahead. At the first architecture review meeting, the team chose an approach with 85% in favor, and the project lead strongly objected. What should the project lead do?

    Show answer and explanation

    Correct answer: C

    The team charter says decisions need at least 80% of members in favor. At the architecture review, the approach passed with 85% in favor, and the project lead strongly objected. What does the project lead do?

    The team agreed a decision rule beforehand, and a result that meets the rule should be respected. The project lead can write down the reasons for the disagreement and let the team go ahead with the decision, then use facts to check it in later inspection. That keeps the lead's opinion on record and respects self-organization. Respecting the decision does not mean giving up the opinion: the recorded objection can serve as a basis for inspection at the Sprint Review or Sprint Retrospective. The answer is C.

    Why the other options are wrong

    • A. Privately lobbying members to change their votes manipulates the team's decision and undermines the rule the team agreed together.
    • B. Directly vetoing the team's decision overrides the team's resolution with power and goes against the principle of self-organization.
    • D. Using the sponsor's authority to change the team's decision also bypasses the team's agreement, and the issue is not serious enough to escalate.

    Key takeaway A decision the team makes under its agreed rule should be respected. The leader may record the objection but does not overturn the decision.

    Variation If later inspection showed the decision really carried risk, you should bring the data to the next team meeting and let the team decide again according to its charter.

    Reference Scrum Roles · Lesson 3: The Developers: Self-Organizing, Cross-Functional and Decision-Making by Participation

  19. Question 19

    You are the project manager for a hotel chain on the construction of a new hotel, which is in the execution stage. The civil works and the mechanical and electrical installation have been outsourced to two engineering companies. A newly joined cost engineer wants to know who on the project is responsible for outsourcing matters and what each person’s duties are. Which document should you have the engineer look at?

    Show answer and explanation

    Correct answer: D

    A hotel project is in execution with the civil works and the mechanical and electrical installation outsourced to two engineering companies. A new cost engineer wants to know who is responsible for outsourcing matters and what their duties are, and the question asks which document to consult.

    PMBOK 8 explains that the procurement management plan may include guidance on stakeholder roles and responsibilities related to procurement, including authority and constraints of the project team when the performing organization has a procurement department. To find out who is responsible for outsourcing and what each does, look at the procurement management plan; this plan is a component of the project management plan, and members who join after the project has started should also use it to understand how procurement work is divided. The answer is D.

    Why the other options are wrong

    • A. The communications management plan states who receives information, when and by what means. It does not record the division of procurement duties.
    • B. The stakeholder engagement plan is about how to engage stakeholders and manage their expectations. It does not allocate procurement responsibilities.
    • C. The project charter is a high-level document stating project objectives, the project manager and the manager’s authority. It does not list who is responsible for outsourcing matters.

    Key takeaway To find out who is responsible for outsourcing and how duties are divided, look at the procurement management plan.

    Variation If the question were how progress information is regularly issued to the outsourced contractors, you would look at the communications management plan.

    Reference Make-or-Buy Analysis and Procurement Planning · Lesson 2: Source Selection Analysis, Selection Criteria and the Procurement Management Plan

  20. Question 20

    A smart-band project has just started, and senior managers want the output of the first iteration to be a prototype that the sales team can demonstrate to prospective customers. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    A smart-band project has just started, and senior managers want the first iteration's output to be a prototype that the sales team can demonstrate to prospective customers. The question asks what the project manager should do now.

    The signals are “the project has just started” and “the first iteration must be demonstrable”. To achieve this, you first need to know the fewest features the product needs to hold together and be demonstrable, that is, determine the minimum functionality the demonstration prototype must have, and then plan the first iteration's work around it. This is close to the MVP idea of focusing on the minimum necessary functionality, although the result here is a prototype for demonstration, not a product first released to customers. The answer is B.

    Why the other options are wrong

    • A. Elaborating the WBS to lower levels is detailed up-front planning in the predictive style. It takes a great deal of up-front elaboration time, which is the opposite of producing results in the first iteration.
    • C. Having the sponsor decide the feature list alone bypasses the team and still does not identify the minimum set needed for this demonstrable prototype, so it is less direct than B.
    • D. Dividing the backlog into phases can support release planning, but it cannot replace first determining the minimum functionality, and phasing alone does not guarantee a demonstrable result in the first iteration.

    Key takeaway To produce something demonstrable quickly, first determine the minimum functionality the product needs, that is, the minimum functional scope (an idea close to the MVP).

    Variation If the stem said the MVP had already been determined and asked what to do next, the answer would turn to selecting items within the MVP scope at iteration planning. If it asked who decides the order of items, the answer would be the product owner.

  21. Question 21

    A mobile app team at PMLyceum develops with Scrum. An experienced core developer is moved away and replaced by a less experienced newcomer. A key stakeholder worries that the newcomer will take too long to get up to speed and the project may not deliver on time. What should the project manager do to help ensure successful delivery?

    Show answer and explanation

    Correct answer: B

    A Scrum team develops a mobile app. An experienced core developer is moved away and replaced by a less experienced newcomer, and a key stakeholder worries that the newcomer will ramp up slowly and delivery will be late. The question asks what the project manager should do to ensure successful delivery.

    The replacement is already a fact, so the project manager should first lead an assessment of its impact, such as the newcomer's skill gap and the effect on velocity and the delivery date, and then act on it: arrange knowledge transfer or coaching, let the Developers adjust the division of work themselves and coordinate extra resources if needed. This is the “assess first, then act” order of monitoring processes, and it answers the stakeholder's worry directly. The answer is B.

    Why the other options are wrong

    • A. The replacement has already happened, so first assess the skill gap and its effect on velocity and the delivery date. The possible delay can still be logged as a derived risk, but it should not be escalated to the PMO without assessment.
    • C. The functional manager has limited knowledge of this project's specifics, and the project manager should lead the impact assessment; if resource support is needed after the assessment, negotiate then.
    • D. Reversing the reassignment is often impractical (the original member may already have new tasks), does not solve how the newcomer gets integrated and causes fresh disruption.

    Key takeaway When a member is replaced: assess the impact first, then adjust resources as needed; do not start by escalating or reversing.

    Variation If the assessment shows the newcomer lacks business knowledge, arrange walkthroughs, pairing and knowledge handover; only if the assessment shows the delivery date will certainly be affected do you raise a change request.

  22. Question 22

    A signage replacement project for a coffee-shop chain covers replacing the signs of 10 stores in the city center. When all of them are done, the customer says it will not sign the project closure report unless an 11th store is added, because it fits the customer's new store-opening plan. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    All 10 store signs have been replaced. At acceptance the customer demands an 11th store and otherwise will not sign the project closure report.

    The original scope is complete, so the project manager should ask the customer to formally accept that part against the agreed acceptance criteria; if the customer refuses to sign, record and handle the reason for the refusal (using contract dispute or escalation mechanisms if necessary). The 11th store is outside the scope baseline and is a scope change: record it as a change request, to be assessed and decided by the approver the project designates (the change control board where applicable). It need not wait until acceptance is finished. The two matters are handled separately and not tied to each other. The answer is A.

    Why the other options are wrong

    • B. A scope change first has to go through change control; it is not a matter of going straight to the sponsor for money. Holding off acceptance would also delay accepting the completed work.
    • C. A change must be approved through this project's change control process. The project manager cannot let a department of the customer approve an expansion of scope directly; skipping the process leaves the baseline uncontrolled.
    • D. A request cannot simply be turned into a new project because it came late. A change request is the proper route, decided by the approver the project designates (the change control board where applicable).

    Key takeaway When new requests arise at acceptance, request acceptance of the completed work while sending the new request through change control; handle the two matters separately.

    Variation If the customer asked instead for a fix to a defect where completed work deviates from the acceptance criteria, that is not added scope; record the reason and remedy the defect through change control.

  23. Question 23

    Two team members on a smart fitness band project disagree about quality inspection equipment. Member A says the budget is already tight and that low-spec inspection instruments should be bought as the project management plan says, to save money. Member B disagrees. Low-spec instruments have higher measurement uncertainty and require repeated retests, which would actually push up inspection cost, so B suggests buying the high-spec model to get an accurate measurement the first time. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    Two members disagree about inspection equipment. A wants to buy low-spec instruments as planned to save money, while B says low-spec ones need repeated retests and cost more in the end, and suggests buying high-spec. B's claim has not been verified. The question asks what the project manager should do.

    B's argument is that “paying more to buy the equipment saves the cost of retesting”. That is a claim that can be quantified and compared, but at present there is no data to back it. PMBOK 8 defines cost-benefit analysis as a financial analysis method that compares costs with the benefits they bring and helps determine whether activities are cost-effective. The project manager should evaluate first: set the added purchase cost of the high-spec equipment against the retest cost it saves and the quality it improves, and only then decide whether to adjust the plan through change control. The answer is B.

    Why the other options are wrong

    • A. Following the management plan is not wrong in itself, but B has raised a suggestion that may lower total cost. Rejecting it without evaluating it may miss a chance to optimize the cost of quality.
    • C. B's claim has not been verified. Adopting it directly changes the plan without evaluation, and may also spend more money.
    • D. Quality and budget must be weighed. You cannot claim that quality always comes first without analysis, and doing so would also bypass the change procedure.

    Key takeaway When an unverified suggestion deviates from the plan, do a cost-benefit analysis first, then decide whether to change.

    Variation If the evaluation shows that the expected benefits of the high-spec instrument justify its incremental cost relative to the planned option, the project manager should submit a change request and change the purchase once it is approved. If the cost-benefit analysis does not support the change, keep the original plan and explain the basis to B.

    Reference Cost of Quality · Lesson 2: Optimal Cost of Quality, Cost-Benefit Analysis and Using Cost of Quality

  24. Question 24

    PMLyceum takes on a smart-warehouse system upgrade project, and the team is formed temporarily from members of three departments. The project manager notices that members rarely talk to each other, all feel like “outsiders” and have low motivation. So every month he organizes a team dinner and an outdoor activity to let members get to know each other and build friendships. Which level of Maslow’s hierarchy of needs do these activities mainly satisfy?

    Show answer and explanation

    Correct answer: A

    On a smart-warehouse upgrade project, the team is formed temporarily from three departments. Members rarely talk, feel like “outsiders” and are not motivated. The project manager organizes a monthly team dinner and outdoor activity. The question asks which of Maslow’s five levels these practices mainly satisfy.

    Start with what the members lack: getting to know each other and a sense of belonging, not income, stability or achievement. A dinner and outdoor activities provide chances to interact and build friendships. Maslow’s five levels, from bottom to top, are physiological, safety, social, esteem and self-actualization; friendship, belonging and connection with colleagues are the third level, social needs. The hierarchy of needs is a common exam term. On the exam, spotting the words “getting acquainted, friendship, belonging” maps directly to it. The answer is A.

    Why the other options are wrong

    • B. Safety needs mean stable work, order and a safe environment. The stem has no information about worry over losing a job or physical safety, and dinners and activities provide no such assurance.
    • C. Esteem needs mean achievement, being respected and being appreciated. The purpose of the dinner and activities is to help people get acquainted, and no one’s accomplishment is being recognized.
    • D. Self-actualization needs mean learning, development and using one’s abilities. Social activities have no direct connection with realizing individual potential.

    Key takeaway Friendship, belonging and connection with colleagues correspond to social needs; achievement and recognition are esteem needs.

    Variation If the project manager publicly praised one member’s proposal in a meeting, that would satisfy esteem needs; if he arranged training on a new technology for members, it would address self-actualization needs.

  25. Question 25

    A team building an online learning platform uses the MoSCoW method to order backlog items. What does an item labeled “should have” mean?

    Show answer and explanation

    Correct answer: A

    In an adaptive environment, the team uses the MoSCoW method to order backlog items. The question asks what an item labeled “should have” means.

    MoSCoW sorts requirements into four levels of importance, from highest to lowest: must have, then should have, then could have, and finally will not have this time. Should have means important but not critical: without it the release will not fail, but some value is lost, and when time is tight the item can be deferred. The simplest way to judge each level is to ask “what happens without it?” Without it the release cannot happen: must have. Without it some value is lost: should have. Without it almost nobody minds: could have. The answer is A.

    Why the other options are wrong

    • B. An item explicitly not going to be done in this release is “will not have,” not “should have.”
    • C. Something the team will consider only if it has spare capacity corresponds to “could have,” which ranks below “should have.”
    • D. An item without which the product cannot be released and which must be delivered on time is “must have.”

    Key takeaway “Should have”: important but not critical, and can be deferred.

    Variation If the question asked what to do when a “must have” item cannot be finished: if it is still confirmed to be indispensable for this release, adjust other scope, resources or dates. Only after the business owner reassesses it and confirms it is no longer a release requirement may its priority be changed.

  26. Question 26

    During the executing phase of an education cloud platform project, the project manager finds it hard to reach several key stakeholders and hard to get their feedback on the deliverables. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    During the executing phase of an education cloud platform project, several key stakeholders are hard to reach and it is hard to get their feedback on deliverables. You must decide what the project manager should do.

    The stakeholder engagement plan sets out the strategies for engaging them. Being unreachable and giving no feedback is a signal of insufficient engagement, but the stem does not yet establish the cause. First analyze factors such as availability, concerns and communication methods, and then adjust the engagement strategy accordingly; if a controlled plan must be updated, follow the change management plan for the required approval. The answer is B.

    Why the other options are wrong

    • A. This problem lies within the project manager's responsibility, so there is no need to trouble the sponsor first. Having the sponsor step in is an ineffective escalation made before any adjustment of strategy.
    • C. Sending a feedback form template only lowers the hurdle for filling it out; it does not identify why these stakeholders are hard to reach and provide no feedback.
    • D. Passively waiting for them to make contact takes no step to adjust strategy for the lack of engagement. First analyze the cause and then revise the engagement plan.

    Key takeaway When monitoring finds insufficient engagement, go back to the engagement plan and adjust the strategy.

    Variation If these people are highly engaged but their feedback contradicts one another, turn to conflict management and bring them together to reconcile it.

  27. Question 27

    A company must choose between Project A and Project B based on payback period; the shorter the payback, the better. Project A has a payback period of 30 months. Project B requires an investment of $90,000, brings in net cash inflow of $45,000 in the first year, and from year 2 onward brings in $15,000 each quarter. What would you choose?

    Show answer and explanation

    Correct answer: A

    Choose between Projects A and B on static payback period, where shorter is better. A's is known to be 30 months, so you must first work out B's payback period and then compare.

    Payback period is the time needed for cumulative net cash flow to return to zero. B invests $90,000. In the first year it recovers $45,000, leaving $45,000 still to recover; after that $15,000 comes in each quarter, which takes 3 quarters, or 9 months. In total that is 21 months, 9 months shorter than A's 30 months, so choose B. Note that the time units must be consistent: the first year is 12 months, and the later quarters must be converted into months. The answer is A.

    1. Year-1 inflow is $45,000, so the amount still unrecovered is 90,000 − 45,000 = $45,000
    2. At $15,000 per quarter afterward: 45,000 ÷ 15,000 = 3 quarters = 9 months
    3. B's payback period = 12 + 9 = 21 months
    4. Check: 30 − 21 = 9 months, so B is 9 months shorter than A, and B is chosen

    Why the other options are wrong

    • B. This reverses the comparison: B is 21 months and A is 30 months, so B is shorter and B is the correct choice. Saying “A is 9 months shorter than B” writes the difference in the wrong direction.
    • C. B's payback period is 21 months and A's is 30 months; they are not the same. Since shorter is better, B should be chosen.
    • D. The question gives the investment, the first-year inflow and the quarterly inflow afterward, which is enough to calculate the payback period. No data is missing.

    Key takeaway For a static payback period, accumulate cash flows in segments: deduct the first year, then divide the remainder by the later rate, keeping units consistent.

    Variation If the first-year inflow were only $30,000, the remaining 60,000 ÷ 15,000 = 4 quarters = 12 months, and B's payback would become 24 months, still shorter than A's.

    Reference Net Present Value and Value Evaluation · Lesson 2: IRR, Payback Period, ROI and Benefit-Cost Ratio

  28. Question 28

    In the weekly technical review meeting, one member rarely speaks, but the tasks assigned to him are always completed on time. How should the project manager make use of this member’s strengths?

    Show answer and explanation

    Correct answer: C

    In the weekly technical review, a member rarely speaks, but his assigned tasks are always completed on time. The question asks how the project manager should make use of his strengths.

    Completing his assigned tasks on time shows reliability in meeting commitments; at the same time, he rarely participates in discussions. PMBOK 8 stresses identifying areas where team members perform well and helping individuals grow, and a project manager should also listen to and recognize members. Talking with him, acknowledging his reliability and encouraging him to share ideas in discussions can build his confidence and give the team an opportunity to hear his perspective. The answer is C.

    Why the other options are wrong

    • A. This looks only at his on-time delivery. Loading the critical tasks onto him risks overload, does not fix his absence from discussions and does nothing for his growth.
    • B. Hearing his ideas beforehand and having the project manager relay them still leaves him not speaking and does not build his ability to express himself; relaying can also lose information.
    • D. Having an articulate member speak for him is also speaking on his behalf, which gives him no practice and may make him quieter still.

    Key takeaway When a member is quiet but performs well, first acknowledge his strengths and then encourage him to speak for himself instead of speaking for him.

    Variation If the conversation shows he is quiet for fear of criticism, first build an open and safe communication environment, then encourage him to speak.

    Reference Leadership Styles · Lesson 5: The Tasks of Leading the Team: Empowering, Speaking Up, Diversity and Problem-Solving

  29. Question 29

    The team has identified a set of risks and needs to rank them by probability and impact. Which of the following tools or techniques helps least with this work?

    Show answer and explanation

    Correct answer: D

    The team has identified a set of risks and needs to rank them by probability and impact. You must decide which tool or technique helps least with this work.

    Setting priorities is part of the qualitative side of Perform Risk Analysis, and the techniques available include risk probability and impact assessment, the probability and impact matrix and risk categorization. Brainstorming is primarily used to generate and discuss ideas and is commonly used when identifying risks. It can also support analysis or a discussion of priorities, but it is less direct for this ranking task than probability and impact assessment, the matrix, or risk categorization. Therefore, brainstorming helps least among these options. The answer is D.

    Why the other options are wrong

    • A. The probability and impact matrix maps probability and impact onto a grid and gives the priority of risks directly. It is the main ranking tool and helps most.
    • B. Risk categorization groups risks by source or area affected and helps concentrate on the areas of greatest exposure. It is also a qualitative analysis technique.
    • C. Risk probability and impact assessment evaluates each risk one by one and is the basis for ranking. Without it there would be no scores to rank.

    Key takeaway Brainstorming is primarily for generating risk ideas; the ranking described here relies more directly on assessment, the matrix and categorization.

    Variation If the question asked “which technique is best for generating risks?”, brainstorming, interviews and checklists would be the best choices, and the matrix would be the one that helps least.

    Reference Qualitative Risk Analysis · Lesson 2: Risk Probability and Impact Assessment and the Probability and Impact Matrix

  30. Question 30

    On a system integration project, team members ask the project manager to decide every small matter, and the project manager is in meetings all day, so tasks are delayed while waiting for decisions. What should the project manager do to avoid these delays?

    Show answer and explanation

    Correct answer: B

    On a system integration project, members ask the project manager to decide even small matters, and he is in meetings all day, so tasks are delayed waiting for decisions. The question asks how to avoid the delays.

    The cause of the delays is already clear: decisions are concentrated in the project manager. PMBOK 8 notes that team members who feel empowered to make decisions about the way they work and about specific details in the deliverables, even under limited range, perform better and have a higher degree of satisfaction than those who are micromanaged. Letting the team make some of these decisions on its own without waiting is a direct and effective fix. The answer is B.

    Why the other options are wrong

    • A. A Pareto chart finds the main categories of causes by frequency, but the stem has already identified the cause, so drawing one would not directly remove the waiting.
    • C. Answering once every two weeks lengthens the wait, so the delays continue and the backlog of pending matters grows.
    • D. Decision authority stays with the project manager, and requiring written submissions only adds steps and waiting time; the team is not empowered at all.

    Key takeaway When the decision bottleneck is the project manager, letting the team decide for itself is the direct fix.

    Variation If team members were not yet capable of making such judgments, first clarify the scope of decisions and coach them, then delegate gradually.

    Reference Leadership Styles · Lesson 4: Inputs, Tools and Team Decision-Making for Leading the Team

  31. Question 31

    On an agile project, a coordinator temporarily appointed by a functional manager is organizing the daily coordination meeting for the first iteration. The coordinator notices that team members are anxious about whether the project can be completed and are often interrupted by ad hoc requests from the functional manager. Members report only to the functional manager, who evaluates their workload and performance. The organization has no project manager role, and the coordinator has almost no say in how work is assigned. Which type of organization is this?

    Show answer and explanation

    Correct answer: C

    On an agile project, a coordinator is organizing the daily coordination meeting for the first iteration. The question asks you to identify the organizational structure from the reporting and evaluation relationships.

    The functional manager evaluates members' workload and performance, the functional manager's ad hoc requests interrupt the team, there is no project manager role, and the coordinator has almost no say. These are features of a functional (centralized) organization: the project manager's authority is low, the role is part-time, resource availability is low, and the team mainly listens to the functional manager. The agile project in the stem is only background. Focus on the reporting and evaluation relationships. The answer is C.

    Why the other options are wrong

    • A. In a project-oriented organization, members report to the project manager, whose authority is high to almost total. In the stem, members report only to the functional manager and the organization has no project manager role, so the situation is the opposite.
    • B. In a strong matrix the project manager's authority is moderate to high and the project manager has considerable authority over resources. The stem has no project manager role and a coordinator with almost no say.
    • D. An organic (simple) organization has a flexible structure, few layers and little supervision. In the stem the functional manager repeatedly intervenes and evaluates members, which does not fit.

    Key takeaway When members report only to the functional manager, are managed and evaluated by that manager, and the organization has no project manager role, the organization is functional.

    Variation If “members report to the project manager and must be placed elsewhere after the project”, it is project-oriented; if “the project manager is full-time and can coordinate members directly, but must agree on timing to borrow quality department staff”, it is a strong matrix.

  32. Question 32

    In a probability and impact matrix, what is the most typical feature of an opportunity located in the high-priority area?

    Show answer and explanation

    Correct answer: D

    Threats and opportunities are placed in the same probability and impact matrix. The question asks what characterizes an opportunity located in the high-priority area.

    The matrix sets priority from predefined rules for combining probability and impact, and when numeric scoring is used the product of probability and impact can be calculated. For an opportunity, impact means the positive benefit if it occurs. High probability together with large positive impact is the most typical case of a high-priority opportunity, although the exact zones depend on the matrix the project uses. An opportunity with a high likelihood and a large benefit is both likely to occur and highly rewarding if it does, so it deserves priority attention. The answer is D.

    Why the other options are wrong

    • A. Low probability, large benefit: whether it falls in the high-priority area depends on the matrix definitions in the risk management plan, and it can be high priority when the product reaches the threshold, but that is not the “most typical” feature. The most typical case is large on both dimensions at once.
    • B. High probability but a small benefit gives a product that is not high, so it usually falls in the medium or low priority area. It also does not satisfy “large on both dimensions”.
    • C. What goes on the watch list are risks with both low probability and low impact, the opposite of “high priority”. A low-probability opportunity can reach a high-priority cell only if its impact is extremely large and the product reaches the threshold, which is not the most typical feature.

    Key takeaway In the matrix, both opportunities and threats get their priority from the combination of probability and impact, and high probability with high impact is the most typical high-scoring case.

    Variation If the question asked about a threat in the high-priority area, it would be high probability with a large negative impact, which needs a response arranged first. If it asked for the next step after finishing the register at identification, the answer is to assess probability and impact using the definitions in the plan.

  33. Question 33

    At a project review, the sponsor is concerned that the project is not delivering results as planned, and the project manager assesses the project's status. Which information should the project manager use to judge whether the project is really delivering value?

    Show answer and explanation

    Correct answer: C

    At a project review the sponsor worries the project is not delivering results as planned. The project manager is assessing status and must find information that shows how value is being delivered.

    The benefits management plan explains how and when benefits will be realized and establishes the mechanism for measuring them. To judge whether the project is really delivering value, compare the measured benefit results with the plan's target benefits and timeframe; results that meet the targets at the planned points provide evidence that value is being delivered. If, in assessing status, you answer the sponsor's concern about value with only management measures such as cost and schedule, you have not answered the question; to answer a question about value you have to use measurement on the benefits side. The answer is C.

    Why the other options are wrong

    • A. Satisfaction is a subjective feeling. With no measurement against the target benefits, it cannot prove that value has been delivered.
    • B. Staying within budget and on schedule shows the project management processes are doing well, but the results do not necessarily bring the expected value. That is the difference between management success and outcome success.
    • D. The project charter states the project's purpose, objectives and success criteria, but being consistent with it only shows that execution matches the requirements set at initiation. Whether benefits are realized at the planned points in time has to be checked through the measurement mechanism in the benefits management plan, so it cannot directly measure whether value has been realized.

    Key takeaway To judge whether value is being delivered, check consistency with the measurement mechanism in the benefits management plan, not just cost and schedule.

    Variation If the question asked “what was the basis for judging whether the project was worth investing in at approval?”, the answer would move from the benefits management plan to the business case.

  34. Question 34

    A warehouse-system upgrade project is in execution. While reviewing the issue log, the project manager finds that several high-priority issues remain open. Most of them can be resolved only by specialists from outside the project team. The current resource plan and budget have no provision for such specialist support, and the project manager has no authority to add budget on his or her own. What is the BEST action for the project manager to take?

    Show answer and explanation

    Correct answer: C

    On a warehouse-system upgrade project, the issue log has several open high-priority issues, most of which can be resolved only by specialists outside the team. What should the project manager do best?

    High-priority issues cannot be shelved, and having the team learn the subject in a short time would be too late. The right approach is first to review the issues one by one, confirm that outside specialist capability is needed, and assess the cost, schedule, resource and risk impacts of bringing it in. Because the current resource plan and budget have no provision for this support and the project manager cannot add budget, the assessment is included in a change request; the experts are brought in only after approval. If experts can be assigned within the existing plan and budget, simply coordinate to obtain them. The answer is C.

    Why the other options are wrong

    • A. Closing the issues only makes the log stop showing them; the problems are still there. An issue can be closed only after it is truly resolved.
    • B. Learning the expertise takes time, and it is hard to resolve these high-priority issues one by one in a short time that way.
    • D. Reducing scope avoids the problem, and a scope adjustment also requires approval through change control; the project manager has no authority to cut it directly.

    Key takeaway When a high-priority issue is beyond the team's capability, review it and assess the impacts of outside help before submitting a change request.

    Variation If outside experts can be assigned by a functional department within the existing budget, first coordinate with the functional manager; submit a change request only when the existing authorization is exceeded or controlled content such as the baseline or the contract has to change.

  35. Question 35

    A project is in execution, and the communications management plan already documents each stakeholder's information needs. The functional manager reports not receiving the information needed and asks the project manager for a weekly email status update. The sponsor asks instead for a weekly meeting to report project performance. The project manager judges that if the communication problem is not resolved, the success of the project will be seriously threatened. What should the project manager do?

    Show answer and explanation

    Correct answer: D

    The project is in execution and the communications management plan already documents each stakeholder's information needs. The functional manager wants weekly emails and the sponsor wants a weekly meeting. The two requests differ, and the communication problem could seriously threaten project success.

    Manage Communications means collecting, creating and distributing information according to the communications management plan. When communication goes wrong, go back to the plan first: it records each stakeholder's information needs, frequency and method. The project manager keeps the functional manager and the sponsor informed in a timely way as the plan describes. If the plan does not match the two latest requests, the project manager should first analyze whether the change is necessary and what it affects, then update the plan appropriately under the applicable change control. The answer is D.

    Why the other options are wrong

    • A. Communication is the project manager's own responsibility, and nothing suggests the problem is beyond the project manager's authority. Escalating immediately avoids that responsibility.
    • B. A communication model describes how information is encoded, transmitted, decoded and answered. It explains the transfer process but does not say what each stakeholder needs or how each should receive it.
    • C. Serving one party and ignoring the other has no basis. First check the plan to see what was agreed and whether it needs updating, rather than choosing between stakeholders on the spot.

    Key takeaway When communication goes wrong during execution, look at the communications management plan first, then manage communications according to it.

    Variation If the plan does not contain the functional manager's needs, first discuss those needs and then update the plan. If Monitor Communications finds the plan was not carried out, do the missed communication as planned and find out why.

  36. Question 36

    The self-organizing team on an online education platform has consistently delivered its forecast work, and the project is critical to the company. At a Sprint Retrospective, the project manager finds that most members feel heavy pressure because their forecasts have included more work than they can sustainably complete. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    A self-organizing team has consistently delivered its forecast work. At a Sprint Retrospective the project manager finds that most members feel heavy pressure because their forecasts have been too aggressive. What should the project manager do?

    The source of the pressure is that the forecast amount exceeds what the team can sustain. At Sprint Planning the developers select and forecast the work they can complete according to their own capacity, so the project manager should support the team at the next Sprint Planning so that it forecasts only the amount of work it is confident of delivering, which lets the team keep a sustainable pace and solves the problem at the root. This is consistent with the rules of Sprint Planning: the developers assess their own capacity and select the work they expect to complete in the Sprint, while the Product Owner explains the goal and the ordering, and others cannot set the amount for the team. The answer is B.

    Why the other options are wrong

    • A. Adding people takes time to bring up to speed and does not necessarily raise output at once, and it does not change the root cause of the overly aggressive forecasts.
    • C. Stress-relief activities and team building can help, but they treat the symptom and not the cause: the pressure comes from the forecast amount, so the amount must be controlled at planning time.
    • D. Staggering vacations has nothing to do with the source of the pressure, and vacations should be agreed by the team itself, not something for the project manager to require.

    Key takeaway If the pressure comes from over-aggressive forecasts: forecast only what can be delivered when planning.

    Variation If the stem were changed to “the Product Owner demands 30 points while the team's velocity is about 20”, the team should explain by its velocity that only about 20 points can be completed in this Sprint, with the rest staying in the backlog.

  37. Question 37

    A smart home project uses a predictive approach and is in the Executing focus area. The procurement specialist tells the project manager that the supplier has just notified them that a key sensor component cannot ship by the contract date and will be three weeks late. This component is a prerequisite for the assembly work that follows. What should the project manager do FIRST?

    Show answer and explanation

    Correct answer: D

    This is a predictive project in the Executing focus area. The supplier has notified that a key sensor component cannot ship by the contract date and will be three weeks late; it is a prerequisite for the assembly work. First decide whether this is an issue or a risk, then choose the matching document and action.

    The deciding signal is “has just notified that it cannot ship on time”: the supplier has confirmed a current inability to meet the contract date, so this is an existing issue rather than a future event whose probability still needs assessment. Because the issue comes from an external supplier, the project manager should first contact the supplier to clarify the cause, contract implications, and recovery options, then update the issue log and carry out the agreed response. The answer is D.

    Why the other options are wrong

    • A. The risk register records potential risks that have not yet happened. The supplier has confirmed the late shipment, so this is no longer an uncertain potential risk and belongs in the issue log; assessing probability in the register no longer makes sense.
    • B. Management reserve must be used under the authority and the change procedures the organization prescribes. Also, drawing on reserve and expediting a replacement before the impact has been analyzed gets the order wrong.
    • C. An issue needs immediate action. Waiting until the next status meeting to report it is a delay and means taking no action in the meantime.

    Key takeaway What has already happened is an issue: update the issue log and act at once. What might happen is a risk: update the risk register.

    Variation If the scenario were “the supplier is short of cash and may ship late”, that would be a risk: register it first, then assess it. If the delay had already happened but the cause was not yet clear, you could first update the issue log with the known facts and then continue analyzing the cause and the impact.

  38. Question 38

    According to the Tuckman ladder, in which stage is a team’s work efficiency usually the highest?

    Show answer and explanation

    Correct answer: C

    The question asks in which Tuckman stage work efficiency is usually the highest, which requires a clear picture of the characteristics of the five stages.

    PMBOK 8 notes that in the Performing stage the team functions as a well-organized unit, with members interdependent and working through issues smoothly and effectively, so efficiency is usually highest there. The first three stages, Forming, Storming and Norming, correspond to getting to know roles, working through conflict and building trust; efficiency dips in Storming, recovers in Norming and reaches its peak in Performing. This performance pattern is common exam practice. The answer is C.

    Why the other options are wrong

    • A. In the Storming stage the team begins to address the project work and technical decisions. If members are not collaborative or open to differing ideas and perspectives, the environment can become counterproductive, and the many disagreements and conflicts pull efficiency down.
    • B. In the Forming stage members meet and learn about the project and their formal roles and responsibilities. They tend to be independent and need time to get to know one another, so efficiency is not high.
    • D. In the Norming stage members begin to work together, adjust their habits and gradually build trust. Efficiency is rising, but the team has not yet reached the interdependence and orderly operation of the Performing stage.

    Key takeaway Of the five stages, the Performing stage has the highest efficiency. The characteristics of each stage are the basis for telling them apart.

    Variation A team can also get stuck in a stage or regress to an earlier one, and a team whose members worked together before may skip stages. That is why even a high-performing team can lose efficiency when members change.

    Reference The Tuckman Ladder · Lesson 1: The Tuckman Ladder: Five Stages and How to Lead in Each

  39. Question 39

    You are in charge of an agile project that is under way. An industry safety standard has just been revised, the product's existing features can no longer meet end users' requirements, and the customer has raised new requirements on that basis, which will put pressure on the schedule. What should you do next?

    Show answer and explanation

    Correct answer: C

    An agile project is in execution. An industry standard has been revised and the customer has raised new requirements on that basis, which will put pressure on the schedule. The question is what you should do next.

    The entry point for new requirements is the Product Backlog, and the gatekeeper is the Product Owner. The customer's new request is first discussed with the Product Owner, who adds it to the backlog and orders it by value. After that, at Sprint Planning, the developers select items with the Product Owner, taking the team's capacity and past performance into account. The question asks for the action that comes “next”, and the first step is to talk it through and get the change into the backlog. The answer is C.

    Why the other options are wrong

    • A. “Embracing change” does not mean folding a change straight into the plan and adding resources to cope. Schedule and resources are limited. What gets adjusted is the value priority of items, not unlimited additions.
    • B. Pushing every change to the next release cycle freezes the requirements and goes against agile responsiveness to change. Whether and when to do the work depends on its value once ordered, and it might be selected as early as the next Sprint.
    • D. Whether a supplementary agreement is needed depends on the contract, but the question asks for the next step: the Product Owner first adds the new requirement to the Product Backlog and orders it. The contract cannot be amended without assessment.

    Key takeaway A new requirement enters the Product Backlog through the Product Owner and is ordered. At Sprint Planning the developers select items, taking the team's capacity and past performance into account.

    Variation If the change comes up at the Sprint Review, discuss its impact with stakeholders during the Review and adjust the Product Backlog accordingly; the Developers later decide at Sprint Planning whether to select it. If an urgent change arises during the Sprint, the Product Owner and Developers reassess its impact and renegotiate scope only if the Sprint Goal is not endangered.

  40. Question 40

    During execution, a software project encounters a technical problem that was not identified in advance, and management approves releasing management reserve to solve it. Under common exam practice, management reserve is not inside the cost baseline but is part of the project budget. After the release, which of the following should be modified accordingly?

    Show answer and explanation

    Correct answer: B

    During execution, management has approved releasing management reserve (under the common view, management reserve is outside the cost baseline but part of the project budget) to solve an unidentified technical problem. You need to judge which item must be modified accordingly after the release.

    PMBOK 8 notes that the makeup of the project budget varies by organization, and the stem follows the common view: management reserve was originally outside the cost baseline but is part of the project budget and funding requirements. When it is released, the approved amount is added to the cost baseline, so what should be modified is the cost baseline. Project budget = cost baseline + management reserve, so the money only moves from management reserve into the cost baseline and the total is unchanged. The answer is B.

    Why the other options are wrong

    • A. Total funding requirements = cost baseline + management reserve. The money has only changed position and the total is unchanged, so this is not something that must be modified here. What must change, reflecting the approved change, is the cost baseline.
    • C. Contingency reserve is for identified risks. This problem was never identified, so there is no reason to increase contingency reserve.
    • D. Project budget = cost baseline + management reserve. Releasing the reserve only moves money from the latter into the former, so the total is unchanged.

    Key takeaway When management reserve is released, the amount is added to the cost baseline, and the total budget is unchanged.

    Variation Suppose the cost baseline is $300,000 and management reserve is $15,000. After $6,000 is released, the baseline becomes $306,000, management reserve is $9,000 and the project budget is still $315,000.

  41. Question 41

    A customer complains that the smart speakers delivered recently break down frequently. After a meeting, the quality team submits a chart: vertical bars arranged from the highest defect count to the lowest, with a cumulative percentage curve, from which you can see directly that a few causes produce most of the defects. What kind of chart has the project manager received?

    Show answer and explanation

    Correct answer: D

    A customer complains that the smart speakers delivered recently break down frequently. The quality team submits a chart: vertical bars arranged from the highest defect count to the lowest, with a cumulative percentage curve. The question asks what kind of chart the project manager has received.

    Two features appear together: sorting from highest to lowest frequency, and a cumulative percentage curve, from which you can see at a glance that a few causes produce most of the defects. This is exactly a Pareto chart (a bar chart sorted by frequency with a cumulative percentage line, reflecting 80/20). The “cumulative percentage curve” and “from highest to lowest” in the stem are two features that appear together; if either were missing, it would not necessarily be a Pareto chart. The answer is D.

    Why the other options are wrong

    • A. A cause-and-effect diagram breaks the causes of a problem down into branches. It has no ranking and cannot show which causes produce most of the defects.
    • B. A flowchart shows the series of steps that lead to a defect and is used to locate the step where the problem arises. It does not sort by count.
    • C. A matrix diagram shows the strength of the relationships among factors, causes and objectives at the intersections of rows and columns. It does not sort by count.

    Key takeaway Sorted by frequency, with a few causes producing most of the defects: that is a Pareto chart.

    Variation If the bars were only grouped by value interval, with no ordering and no cumulative curve, it would be an ordinary histogram.

  42. Question 42

    A multinational wind farm construction project has a six-year duration. A year in, the original project manager leaves and the company appoints a more experienced project manager to take over. In year three, the sponsor finds project performance unsatisfactory; the new project manager says that performance will improve step by step as the team gels, but the sponsor is skeptical. Performance data for each past period are on hand. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    On a six-year project, performance is unsatisfactory after the new project manager takes over. The manager says performance will improve as the team gels, and the sponsor doubts it. What should the manager use to test this judgment and respond to the sponsor's concern?

    To test whether the claim that “performance will improve step by step over time” is supported by data, show how performance is changing over time. That is exactly what trend analysis is for: use historical performance data to see whether performance is improving or deteriorating and forecast what may happen if the established trend persists. Plotting the figures from each period as a trend line for the sponsor is the most persuasive. “Step by step” points to a trend of change. The answer is C.

    Why the other options are wrong

    • A. Reporting the current CPI alone shows only current cost efficiency, not a trend of improvement over time. To support “step-by-step improvement,” compare several periods and do a trend analysis.
    • B. Variance analysis concentrates on the current difference from the baseline and the reasons for it. It cannot directly show performance improving step by step over time, so it is not the first choice.
    • D. The estimate at completion (EAC) forecasts total cost at completion, not the completion date, and what the manager must prove is the direction of performance, not total cost.

    Key takeaway To show how performance changes over time and to forecast, use trend analysis; variance analysis looks at the gap from the baseline at this moment.

    Variation If the stem asked “how far behind the plan are we now,” the answer would be variance analysis; if it asked “why are we behind,” root cause analysis; and only if it asked “how much will it cost to finish” does the estimate at completion come in.

  43. Question 43

    A trade-show exhibit construction project has fallen behind schedule because of too many scope changes. This risk was recorded in the risk register during planning, and responses were agreed. Worried about being blamed, the team suggests asking the client for an extension. What should the project manager do FIRST?

    Show answer and explanation

    Correct answer: D

    Too many scope changes have put the schedule behind. This risk was registered during planning. The team wants to request an extension right away, and the question asks what the project manager should do FIRST.

    The deciding clue is that the risk was “recorded in the risk register during planning”. The register holds identified risks and their agreed responses, so when the risk occurs, the right step is to implement the risk response: carry out the response plan and minimize the threat. The delay has already appeared, so the first step is to open the register, see which responses were agreed and who owns them, and act on them to contain the delay. Asking for an extension before using the responses already in hand means giving up early and treating the team's fear of blame as a reason to skip them. The answer is D.

    Why the other options are wrong

    • A. The change log records submitted changes and their current status. The root of the problem is that the scope-change risk has occurred, not that changes went unrecorded. Checking the log will not narrow the delay and is not the first action.
    • B. Asking the team to document the impact of the delay in detail amounts to redoing the impact assessment. This risk was registered and analyzed long ago, and documentation does nothing to reduce the delay; it is after-the-fact work.
    • C. Asking the sponsor for advice hands up something the project manager can handle. With agreed responses in place, carry them out first, and escalate only when they are not enough or exceed the project manager's authority.

    Key takeaway When a registered risk is triggered, the first step is to check the risk register and carry out the responses in it.

    Variation If the stem said the risk register has no such risk, it would be a newly identified risk: first assess the impact and agree on a way forward with stakeholders, then record it in the register.

    Reference Monitor Risks · Lesson 1: Implement Risk Responses: Making the Agreed Actions Happen

  44. Question 44

    A project is in mid-execution, with a budget at completion of $500,000. The budgeted value of the work completed is $150,000 and actual cost is $250,000. For the past several months the team's cost performance index has held steady at about 0.6, with no sign of improvement. The project manager calculates that to finish within the original budget, the to-complete performance index for the remaining work is 1.4. What is the most appropriate action for the project manager?

    Show answer and explanation

    Correct answer: A

    The project is in mid-execution: BAC is $500,000, EV is $150,000, AC is $250,000, CPI has been steady at about 0.6, and the TCPI needed to finish within the original budget is 1.4.

    TCPI is how much work must be completed for every dollar spent from now on. ($500,000 − $150,000) ÷ ($500,000 − $250,000) = 1.4, but actual performance has been only 0.6, and more than doubling it overnight is almost unrealistic. The appropriate action is to assess first whether finishing within the original budget is feasible. If it is not, reforecast EAC and have someone with authority approve it as the new target; if the cost baseline must change, raise a change request. In that case TCPI is calculated as (BAC − EV) ÷ (EAC − AC). The answer is A.

    Why the other options are wrong

    • B. There is no basis for lifting cost performance from 0.6 to 1.4 by overtime. Overtime also pushes costs up, and the efficiency target itself is unrealistic.
    • C. Management reserve is outside the cost baseline and is usually released at the discretion of senior management (in some organizations the project manager or team may decide), following organizational rules. The problem with C is that it uses reserve to mask a known, persistent inefficiency and claims to hold the original budget without first assessing feasibility.
    • D. A TCPI well above 1 is already a clear warning, and cost performance has held at 0.6 for months with no sign of recovering on its own. Continuing to watch is inaction.

    Key takeaway When TCPI is far above 1 and efficiency is not improving, assess the feasibility of the original budget, reforecast and use the approved EAC as the new target, and go through change control if a baseline must change.

    Variation If management approves a new EAC = $650,000, then TCPI = 350 ÷ (650 − 250) = 0.875, below 1. However, it is still above the current CPI of 0.6, so substantial improvement is required; whether the target is realistic still depends on risk, time remaining, technical performance, and the ability to improve.

  45. Question 45

    A team takes over a new project. The previous team left behind many problems, so the product carries a large amount of technical debt. Stakeholders know this but do not understand how it will affect delivery, and they still want the team to deliver valuable features as fast as possible. To handle this properly, what should the agile coach do?

    Show answer and explanation

    Correct answer: A

    A team takes over a new project whose product carries a large amount of technical debt. Stakeholders know there is debt but do not understand how it affects delivery, and they still want valuable features quickly. The question is what the agile coach should do.

    Technical debt that cannot be seen cannot be managed, but listing names alone does not explain its effect on delivery. First assess the delivery impact of the identified debt, then list the related paydown work in the Product Backlog. Stakeholders can then understand the impact, and the Product Owner can order debt and features together on one list. The answer is A.

    Why the other options are wrong

    • B. Raising story points across the board hides the problem: it does not explain why refactoring is needed and it distorts velocity data and damages forecasting.
    • C. Technical debt is not necessarily all top priority. Its impact should be assessed and then it is ordered. Putting it all first could delay more valuable features.
    • D. A separate refactoring plan given to stakeholders keeps the work outside the list. It is not transparent and bypasses the Product Owner's ordering.

    Key takeaway Technical debt has to be put into the Product Backlog as explicit items so that it can be seen and ordered.

    Variation If the stem instead says that the time spent fixing defects keeps growing during Sprints, the handling is still to assess the impact and then have the Product Owner put the paydown work in the list. It is not paid off in the background through overtime, and not by pausing all new features.

  46. Question 46

    An agile team is developing an inventory management system for a supermarket chain. Development is in its middle to late stage, and the operations director wants to know how much development work remains and whether progress is going well. Which tool should the team use to explain this to the director?

    Show answer and explanation

    Correct answer: B

    The project is in its middle to late stage, and the operations director is concerned with “how much work remains and whether progress is going well”. The question asks which tool to use to explain this to the business side.

    “How much remains” and “is progress going well” are about remaining work and progress. A burndown chart plots remaining work as a curve over time and compares it with the ideal line: a line below the ideal line means ahead of plan, above it means behind. The director does not need to read a task list; a glance at the position and direction of the line shows whether work is falling as expected. It is also an information radiator, kept current and understood by everyone. The answer is B.

    Why the other options are wrong

    • A. An iteration plan mainly describes the work to be completed in the iteration and how it will be carried out. Even if the plan can be adjusted, it does not show the change in remaining work over time and the completion trend as intuitively as a burndown chart, and it does not show how much is done and how much remains.
    • C. A product roadmap is long-term, high-level planning that answers what each version will roughly deliver. It does not reflect current development progress.
    • D. A release plan schedules the releases and the iterations they contain. It is also a planning document and does not show the change in remaining work over time.

    Key takeaway For “how much work remains and how is progress”, use a burndown chart; planning documents answer “what we intend to do”.

    Variation If the director also wants to see when scope was added or removed, choose a burnup chart; if the question is how far the whole release is from its goal, use the release-level burndown or burnup chart, not a single iteration's chart.

  47. Question 47

    In a washing machine project at a home appliance manufacturer, a trial batch of complete machines was produced, and quality inspection found that a large number of units from several production lines were leaking. The project manager believes that to solve the leaking problem, the root cause of the leaks must be found first. Which tool should the project manager use?

    Show answer and explanation

    Correct answer: B

    In a washing machine project, a trial batch of complete machines was produced, and quality inspection found a large number of leaking units on several production lines. The project manager believes the root cause must be found first and asks which tool to use.

    The task is “find the root cause”, not “decide which category of defect to handle first”. A cause-and-effect diagram breaks the causes of the problem statement down into discrete branches and helps identify the main or root cause, which is a good fit for first working out “why does it leak?” To draw one, put the problem statement at the fish head, then branch out along people, machines, materials, methods, environment and so on, and keep asking “why” level by level until you reach a root cause you can act on. The answer is B.

    Why the other options are wrong

    • A. A scatter diagram shows the relationship between two variables. The stem does not ask you to analyze whether two variables are related.
    • C. A flowchart shows a sequence of steps and is used to see which step is prone to problems. The stem says only that several production lines are affected; it does not ask which step goes wrong.
    • D. A Pareto chart ranks causes by frequency of occurrence and is used to decide what to handle first. The word “large number” can draw you toward it, but what is needed now is the root cause, not the order of handling.

    Key takeaway To find the root cause of a defect, use a cause-and-effect diagram; only when deciding what to handle first does the Pareto chart come in.

    Variation If the leaks had six categories of causes and only two weeks remained before delivery, and you needed to decide quickly which to fix first, the answer would become the Pareto chart.

  48. Question 48

    A cross-department product redesign project has team members who differ in age, role and family circumstances. The project manager must design a motivation and reward plan for the team. Which approach should be taken?

    Show answer and explanation

    Correct answer: B

    On a cross-department product redesign project, team members differ in age, role and family circumstances. The project manager must design the team’s motivation and reward plan and needs to decide on the approach.

    PMBOK 8 says people perform better when motivated and that people are motivated by different things; understanding what motivates team members helps tailor rewards to the individual, eliciting more effective engagement. With members this different, some want growth opportunities, some want recognition and some want flexible arrangements, so the first step is to find out what each person values and then design measures accordingly, and only then to fit them to the budget and company policy. The answer is B.

    Why the other options are wrong

    • A. The HR department’s standard list is a useful reference, but it was not designed around this project’s members’ needs, so copying it may not match what they want.
    • C. The budget is a constraint to consider after needs are clear. Starting from the budget easily produces rewards that do not fit anyone.
    • D. A public showcase works for some people but not for members who do not want to be on display. It can be one part of the plan, not the only approach.

    Key takeaway Motivate people individually: find out each member’s needs first, then design the measures.

    Variation If the question asked what to do when results are weak after the plan is launched, the answer is still to return to understanding needs and find out where the plan missed, not to raise the bonus.

  49. Question 49

    An industrial IoT platform project has a very tight schedule. Two developers propose learning a new framework that could significantly improve development efficiency, but the product owner worries it will slow progress and objects. What should the agile coach do?

    Show answer and explanation

    Correct answer: D

    On a project with a tight schedule, two developers propose learning a new framework that could significantly raise efficiency. The product owner objects because of the risk to progress. What should the agile coach do?

    Whether the new framework will improve efficiency cannot be confirmed in advance, and discussion alone cannot answer it. The most appropriate step is for the coach to facilitate agreement between the team and product owner on a spike (a common exam term): let the two members try the framework within a clear, short timebox and then decide from the results whether to adopt it. A spike needs a clear question, for example “can the new framework cut build time in half?” The timebox limits the experiment's schedule exposure, although the experiment still consumes capacity. The answer is D.

    Why the other options are wrong

    • A. The value of the new framework is uncertain. Letting the product owner decide alone replaces evidence with authority.
    • B. A technology choice within the project's scope does not first require a functional manager's assessment, and such an assessment cannot settle whether the effect is worth it.
    • C. The real effect of the new framework cannot be judged in advance through theoretical discussion. A small experiment is needed to verify it.

    Key takeaway When technical feasibility or benefit is uncertain, use a time-boxed spike for a quick experiment and replace argument with facts.

    Variation If the stem required only startup preparation such as setting up the environment or configuring infrastructure, iteration zero (a common exam term) could fit; if it required answering a particular unknown, use a time-limited spike with a clear learning goal.

  50. Question 50

    A project manager is drawing a decision tree for the choice “whether to buy a component from an outside supplier” and for the uncertain event “whether the supplier delivers on time after purchase”. Which symbols should be used for these two, respectively?

    Show answer and explanation

    Correct answer: C

    When drawing a decision tree for a choice among alternatives, you must pick symbols for “whether to buy a component from outside” and for “whether the supplier delivers on time after purchase”. The question asks which symbol each takes.

    To tell the symbols apart, ask one question: “who decides?” Whether to buy is the project's own choice, so it is a decision node (square). Whether the supplier delivers on time is beyond the project's control and is an uncertain event, so it is a chance node (circle). The triangle only marks the end of a branch, the end point of a path. So the order is square, circle. The legend of Figure 5-5 in PMBOK 8 uses the square for a decision node, the circle for a chance node and the triangle for the end of a branch. The answer is C.

    Why the other options are wrong

    • A. Circle, square reverses the order. The decision maker's own choice should be a square, and only an uncontrolled uncertain event is a circle.
    • B. The first item is a choice, yet it takes a triangle. A triangle marks the end of a branch; it represents neither a choice nor an uncertain event.
    • D. The second item is an uncertain event and should be a chance node, a circle. A triangle is the end of a path and does not represent the event itself.

    Key takeaway Square: we choose (decision). Circle: the environment decides (chance). Triangle: end of branch.

    Variation “Whether to run a proof of concept” is a square, and “whether the validation result is good or poor” is a circle. The end of every path is always a triangle, marked with the net path value.

  51. Question 51

    A team has completed several iterations but has consistently estimated story sizes poorly: in some iterations stories were overestimated and finished early, and in others they were underestimated and could not be finished. What should the team do to improve planning for the next iteration?

    Show answer and explanation

    Correct answer: A

    The team has completed several iterations but its story estimates keep missing: overestimated in some iterations, so work finishes early, and underestimated in others, so work is not completed. The question asks how to improve planning for the next iteration.

    In planning poker, members reveal cards at the same time, the highest and lowest estimators explain their reasons, and everyone plays again; after several rounds the estimates converge. Differences usually come from different understanding or assumptions about the story, and the discussion exposes and removes them, which makes the estimates more accurate. Revealing cards simultaneously prevents whoever speaks first from swaying the others, and explaining extreme values brings out differences in understanding, so the team's judgment of relative size becomes more consistent and more reliable. The answer is A.

    Why the other options are wrong

    • B. Simply averaging is pulled off by extreme values and skips the discussion, so differences in understanding are never found.
    • C. Story size is estimated by the team that actually does the work. The product owner and Scrum Master are not responsible for estimating.
    • D. Other teams understand the story and use an estimating scale differently. The team that will do the story should estimate it.

    Key takeaway Planning poker converges through several rounds of revealing cards and discussing the extreme values, not by taking an average.

    Variation If the scenario stressed that members submit estimates independently, the facilitator consolidates and feeds them back, and rounds continue until convergence, that would be wideband Delphi. The key points are independent estimating and several rounds of discussion that converge.

  52. Question 52

    A city has newly issued regulations on the safety management of electric bicycle charging facilities, and a community charging station project under construction is bound to be affected. The project manager plans to convene stakeholders to analyze the impact and discuss responses. How should the new regulation be classified?

    Show answer and explanation

    Correct answer: A

    The project is under way and a new regulation has been issued externally. You must decide which kind of factor affecting the project the regulation itself is, not how the project manager should handle it.

    Enterprise environmental factors are conditions not directly influenced by the project team that impact, constrain or direct the project. Regulations issued by a country or locality are typical external enterprise environmental factors (legal restrictions, government or industry standards). The regulation in the stem is made by the government, the project can only comply with it and cannot change it, and it is not a practice the organization has built up. The project manager's later steps of assessing the impact and discussing responses are follow-up actions and do not affect the classification here. The answer is A.

    Why the other options are wrong

    • B. A quality metric specifically describes a project or product attribute and how compliance with it will be verified. The regulation may lead to an adjustment of related metrics, but the regulation itself is an external rule and not a quality metric.
    • C. Organizational process assets are practices and knowledge inside the organization that can be tailored and updated. A regulation comes from outside the organization and does not belong in this category.
    • D. The regulation has been issued, so that it will affect the project is certain. Only the size of the effect remains to be analyzed, which is an already identified situation. An unknown-unknown risk is one that could not be foreseen at all beforehand.

    Key takeaway A newly issued regulation is an external enterprise environmental factor; the project can only comply with it and assess its impact.

    Variation If the regulation were replaced with the company's own newly issued construction checklist for charging stations, it would become an organizational process asset. If the question were changed to “what should the project manager do next?”, the answer would be to assess first with the team its impact on scope, schedule, cost and quality.

  53. Question 53

    The project manager of an HR software go-live project learns that an earlier project that used the same software package lost employee data when it moved to the new system. She decides to make a full backup of the data before migration so it can be restored if something goes wrong. She also buys insurance to pay for manually re-entering data if the import fails. Which two response strategies did she use?

    Show answer and explanation

    Correct answer: B

    The project manager of an HR software go-live project knows that an earlier project using the same package lost employee data during import. Before migration she makes a full data backup and buys insurance to pay for re-entering data. The question asks which two threat response strategies she used.

    Match each action separately. A full backup lets the data be restored if something goes wrong and reduces the impact of data loss, but the loss can still happen; that is mitigate. Buying insurance means paying a premium and handing the cost of re-entering data to the insurer, which gives the consequence to a third party; that is transfer. So the strategies are mitigate and transfer. The answer is B.

    Why the other options are wrong

    • A. Neither action is acceptance. Acceptance means acknowledging the risk without trying to reduce or transfer it and dealing with it only if it occurs (for example by using reserves). A backup reduces impact and insurance transfers cost, so neither is acceptance.
    • C. Share is a strategy for opportunities, used to share the benefit of an opportunity with a third party. It is not one of the threat strategies and cannot be mixed in.
    • D. Avoid eliminates the threat entirely, for example by changing the plan so the risk cannot occur. Neither a backup nor insurance stops data loss from happening, so neither is avoidance.

    Key takeaway Reducing probability or impact is mitigate; paying to hand the consequence to a third party is transfer; share belongs to opportunities.

    Variation Only buying insurance would be transfer, and only making a backup would be mitigate. When a question involves several strategies, count the actions one by one and match each.

  54. Question 54

    PMLyceum is about to start a store inventory-counting system project. The company has no standard project life cycle, and the sponsor requires only that the project both validate its value quickly and have reviews at key points. What should the project manager do NEXT?

    Show answer and explanation

    Correct answer: C

    The company has no standard life cycle, and the sponsor requires quick validation of value and reviews at key points. You must decide what the project manager should do NEXT.

    When there is no standard life cycle, the project manager and project team should determine the best life cycle for the project. A life cycle should be flexible enough: you can select the development approach or a mix of approaches, identify the types of processes and activities to perform, and adjust the phase name, duration, entrance criteria and exit criteria, so as to meet the objectives while protecting the value proposition. The sponsor's two requirements, quick validation and reviews at key points, call for a design that fits the project's characteristics. The answer is C.

    Why the other options are wrong

    • A. A life cycle is not a fixed template. Copying the previous project does not address this project's specific need for quick validation and review points.
    • B. The lack of a standard does not mean you wait. Determining a suitable life cycle is the project manager's and team's responsibility in the first place.
    • D. The project life cycle is independent of the product life cycle, so you cannot copy the product life cycle's phases merely to ease the handover to operations.

    Key takeaway A life cycle is not a template: with no standard, tailor one to the project; with a standard, you can still adjust attributes within its limits.

    Variation If the organization already has a standard life cycle, you can still adjust phase names, durations and entrance and exit criteria within what is allowed. If a policy or contract requires a certain approach, you cannot override it on your own.

  55. Question 55

    At a budget review meeting for a data platform migration project, the project manager says that, with several risks acting together, the confidence of completing the project within the current budget is 70%. The sponsor asks how much additional budget would be needed to raise that confidence to 90%. Which technique should the project manager use to answer?

    Show answer and explanation

    Correct answer: A

    At a budget review for a data platform migration project, the project manager says that with several risks acting together the confidence of finishing within the current budget is 70%. The sponsor asks how much more budget is needed to raise the confidence to 90%. You must decide which technique answers this question.

    “Several risks acting together” and “confidence” are both probability statements at the level of the whole project. Monte Carlo simulation combines the risks and uncertainties and iterates to obtain a cumulative probability distribution of cost, the S-curve, with cost on the horizontal axis and the probability of not exceeding that cost on the vertical axis. A 70% confidence corresponds to one cost point on the curve and 90% to another, and the difference between the two points is the additional budget, usually held as contingency reserve. One probability corresponding to one budget is exactly how an S-curve is read. The answer is A.

    Why the other options are wrong

    • B. Sensitivity analysis finds the factors with the greatest effect on objectives. It gives no correspondence between overall completion confidence and budget, so it cannot answer “how much more”.
    • C. Decision tree analysis compares the expected monetary value of several alternative courses of action. The stem has no alternatives to choose among; instead, it requires reading the costs associated with different confidence levels from a cumulative cost distribution.
    • D. Alternative analysis picks one from several response or implementation options. It does not output a correspondence between “confidence” and “budget”, so it cannot answer how much additional budget.

    Key takeaway “How much confidence, how much extra budget”: read the two costs for the two probabilities from the Monte Carlo S-curve and subtract.

    Variation If the S-curve shows $5,000,000 at 70% and $5,600,000 at 90%, the additional budget is 5,600,000 − 5,000,000 = $600,000. If the question were changed to “the probability of finishing by the end of October”, it is still Monte Carlo, only with the S-curve in terms of schedule.

  56. Question 56

    While a consulting firm is executing a data migration project, heavy rain floods the machine room and destroys the server storing interim deliverables. This type of risk had never been identified in the risk register. Recovering the deliverables requires extra cost. The organization requires management approval to release management reserve. What should the project manager do?

    Show answer and explanation

    Correct answer: D

    During execution, heavy rain floods the machine room. No such risk was in the risk register in advance, and recovering the deliverables needs extra cost. The organization requires management approval to release management reserve.

    A risk not identified in advance is an unknown-unknown and should be handled with management reserve. Management reserve is outside the cost baseline, and PMBOK 8 notes it is usually at the discretion of senior leadership or management (in some organizations it may be the project manager or project management team). In this question the organization requires management approval, so the project manager cannot release it directly. Under common exam practice, submit a change request through the organization's governance procedure, to be approved by the management stated in the stem. Once approved, if the cost baseline must be adjusted, the approved amount is incorporated through formal change control; whether the total project budget changes depends on the organization's budget buildup and reserve-management approach. The answer is D.

    Why the other options are wrong

    • A. Contingency reserve corresponds to identified risks and is released under the risk response plan. This risk was not identified in advance, so it is outside its purpose.
    • B. The organization requires management approval to release management reserve. Releasing it first and informing afterward bypasses approval.
    • C. Quietly folding the cost into later work packages is not transparent, bypasses change control and distorts the cost baseline.

    Key takeaway When an unidentified risk occurs, use management reserve and submit a change request first.

    Variation In an organization where the project manager may release management reserve, release it within that authority and record it. If this kind of risk is later identified, given an active response strategy and allocated contingency reserve, release contingency reserve under that response when it recurs.

  57. Question 57

    During the executing phase of a software delivery project, the project manager finds that approval time for integration testing was not reserved during planning, and a lengthy approval step left a lot of staff idle. The project manager has already merged the approval levels through a change, and the problem has been eliminated. What should the project manager do next to keep a similar situation from recurring?

    Show answer and explanation

    Correct answer: D

    During execution, no approval time was reserved for integration testing in planning, and a lengthy approval step left staff idle. The project manager has merged the approval levels through a change and the problem is gone. The question asks what else to do to prevent recurrence.

    The event has happened and has been resolved; what remains is to make sure it does not repeat. The cause of the planning omission, its impact and the corrective action go into the lessons learned register for later phases and future projects to draw on. The stem stresses “to keep a similar situation from recurring,” so the answer is D.

    Why the other options are wrong

    • A. The risk register records uncertain events that have not yet happened. This variance has already occurred and been corrected, so it does not belong in the risk register.
    • B. The issue log records and monitors information about issues. Because this issue has been resolved, adding it there would at most preserve an issue record for the current project; the lessons learned register more directly supports improvement of future performance.
    • C. Gathering the whole team for a review can help identify lessons, but the option does not say that the result is captured in the register; adding the item to the lessons learned register explicitly creates the reusable record.

    Key takeaway After an issue is resolved, record its cause and the practice in the lessons learned register to avoid a repeat.

    Variation If the stem said “this variance has not yet been resolved,” you would first log it in the issue log and handle it. If it said “approvals are expected to slow the schedule,” that is something that has not happened yet and goes in the risk register.

  58. Question 58

    An agile team has completed 6 iterations with velocities of 14, 22, 30, 32, 31 and 33. The backlog still holds 165 story points, and the product owner wants to know how many more iterations are needed. The team should forecast using the average velocity of the last 3 iterations. How many iterations are needed?

    Show answer and explanation

    Correct answer: B

    A project has completed 6 iterations with velocities of 14, 22, 30, 32, 31 and 33, with 165 story points remaining. Forecast the number of iterations still needed using the average velocity of the last 3 iterations.

    The question specifies the last 3 iterations: 32, 31 and 33. After working out the average velocity, divide the remaining story points by it. A fraction of an iteration still takes up one iteration, so round up. The result is 6 iterations. The earlier 14 and 22 fall outside the last 3 iterations the question specifies, so they are left out. The answer is B.

    1. Take the velocities of the last 3 iterations: 32, 31, 33.
    2. Average velocity = (32 + 31 + 33) ÷ 3 = 96 ÷ 3 = 32.
    3. Iterations needed = 165 ÷ 32 ≈ 5.16, rounded up to 6.
    4. Check: 5 iterations deliver only 5 × 32 = 160, less than 165, so not enough; 6 iterations deliver 6 × 32 = 192, more than 165, so enough. The answer is 6.

    Why the other options are wrong

    • A. Using the highest velocity, 33: 165 ÷ 33 = 5. The highest value does not represent the normal level and is too optimistic.
    • C. Using the average of all 6 iterations, (14 + 22 + 30 + 32 + 31 + 33) ÷ 6 = 27: 165 ÷ 27 ≈ 6.1, rounded up to 7. The low early velocities pull the average down, and this also ignores the “last 3 iterations” the question specifies.
    • D. Using the first iteration's velocity of 14: 165 ÷ 14 ≈ 11.8, rounded up to 12. This uses data outside the last 3 iterations, against what the question specifies.

    Key takeaway Forecast with the average velocity of the number of recent iterations the question specifies, and round the number of iterations up.

    Variation If the question said to use the average of the last 2 iterations, the average would be (31 + 33) ÷ 2 = 32, and the answer would not change; if 200 points remained, 200 ÷ 32 = 6.25, rounded up to 7.

  59. Question 59

    A smart-campus network project is 60% complete when the sponsor verbally asks for an additional deliverable. The project manager has already documented the request in writing and entered it into the change management system. What should the project manager do NEXT?

    Show answer and explanation

    Correct answer: A

    A project is 60% complete and the sponsor verbally asks for an extra deliverable. The project manager has documented it in writing and entered it into the change management system. The question asks what to do NEXT.

    The sponsor's request is a scope change and must go through change control. Even when raised verbally, it should first be documented in writing and entered into the change or configuration management system, which the stem says is done. After that, the project manager's FIRST job is to determine the impact on scope, schedule, cost, resources, risk and so on. With the impact analysis, the person with approval authority (the change control board where applicable) has a basis to approve, reject or defer. The usual order is: document, assess impact, submit to the designated approver, update the relevant baselines, plans and change log once approved, communicate the decision and status, then implement and track the results. Since the stem asks for the first step after documentation, it stops at impact assessment. The answer is A.

    Why the other options are wrong

    • B. A change request should reach the change control board after its impact has been assessed. Submitted unassessed, the board has no basis for a decision.
    • C. Alternatives can be studied as part of the impact assessment, but they cannot replace documenting the verbal request and assessing its impact, so they are not the first thing to do.
    • D. The request has only been raised, not implemented, so it is not scope creep. Rejecting it outright also skips the impact assessment and is not change control.

    Key takeaway Document a verbal change request in writing, assess its impact, and then submit it to the designated approver (the change control board where applicable).

    Variation If the question asked what comes next after the change is approved, the answer would be to update the scope baseline, related plans and change log as approved, communicate the decision and status, then implement the change and track the results.

  60. Question 60

    At the quarterly inspection of the foundation work for a scenic-area viewing platform, a key stakeholder expresses strong dissatisfaction with progress and demands that the project manager rush the work immediately. The project manager knows that the delay was caused by a sudden heavy rainstorm and that the weather is still not suitable for rushing. What is the best thing for the project manager to do?

    Show answer and explanation

    Correct answer: C

    At the quarterly inspection of a viewing platform's foundation work, a key stakeholder is strongly dissatisfied with progress and demands that work be rushed immediately. The project manager knows the delay was due to a sudden heavy rainstorm and the weather is still unsuitable for rushing. You must decide the best course of action.

    When a stakeholder demands that work be rushed, it is quite possible that he does not know the reason for the delay or the conditions on site. The project manager should first talk with him and explain that the rainstorm caused the delay and how the weather limits safe, quality construction, manage his expectations, and then discuss next steps based on the actual situation, such as a catch-up plan once the weather improves. Communicate first, then decide: that is the basic order of engagement and expectation management. Forcing the pace, asking leadership for help or applying for an extension first all fail to address his lack of understanding. The answer is C.

    Why the other options are wrong

    • A. Rushing in unsuitable weather creates safety and quality risks, and making him accept responsibility is not a standard practice; responsibility cannot be transferred.
    • B. The matter is within what the project manager can communicate personally. Asking leadership for help is passive handling and does not first try explaining the facts directly.
    • D. Applying to the sponsor for an extension before he understands the cause of the delay skips the step of communicating with him and does not manage his expectations.

    Key takeaway When a stakeholder's demand comes from not understanding the situation, communicate and explain the facts first, then discuss next steps.

    Variation If he still insists on rushing after the explanation, assess the cost and risk of rushing and decide through a change request. If the delay will exceed the approved baseline, a change request should be submitted.

    Reference Stakeholder Engagement · Lesson 4: Aligning and Managing Stakeholder Expectations: Dissatisfaction, Conflict and Out-of-Scope Requests

  61. Question 61

    After a brainstorming session, the project manager has a list of the project's main stakeholders. What should be done immediately after that?

    Show answer and explanation

    Correct answer: D

    After a brainstorming session, the project manager has a list of the main stakeholders. The question asks what to do immediately next.

    The brainstorming has just produced a preliminary list, and what follows is further analysis: assess each person's power, interest, expectations and attitude, classify them on that basis, and only then set engagement strategies. The signal in the stem is “the list has just been obtained”, with neither analysis nor classification done yet, so the next step is to assess each person's power and interest. The answer is D.

    Why the other options are wrong

    • A. Monitoring is work that follows setting engagement strategies and starting engagement. At this point there is no analysis and nothing to monitor.
    • B. Reporting progress is communication and comes after analyzing and planning communication. It is not yet clear what information each person needs.
    • C. Putting people to work belongs to engagement, which comes after analysis, once strategies have been designed for different people. Putting everyone to work now has no basis and can easily cause resentment.

    Key takeaway After forming a preliminary list, keep analyzing and classifying, and only then set strategies and engage them.

    Variation If the analysis and classification are already done and the question asks what comes next, it is to plan stakeholder engagement: set strategies for each category of stakeholder.

  62. Question 62

    The organization and the selected seller are about to sign an equipment purchase contract. What should the project manager make sure of before it is signed?

    Show answer and explanation

    Correct answer: D

    The project is after the seller has been selected and before the contract is signed, and the question asks what to make sure of before signing.

    The signals: “about to sign” and “what should be ensured”. A contract binds both parties and sets up a buyer-seller relationship under legal protection. An agreement normally includes the statement of work or deliverables, price, payment terms, inspection and acceptance criteria, change handling, termination mechanisms and roles and responsibilities, and before signing you must ensure the terms are clear and unambiguous and each side’s rights and obligations are clear. The answer is D.

    Why the other options are wrong

    • A. Payment should follow the contract’s payment terms and the state of acceptance. Paying in full before signing exposes the buyer to substantial risk.
    • B. What matters in a contract is clear terms and clear rights and responsibilities, not a longer text.
    • C. Setting only the total price omits terms such as deliverables, acceptance criteria and change handling, and invites disputes during performance.

    Key takeaway Before signing, make sure the terms are clear and the rights and obligations are well defined.

    Variation If the question asked who signs the contract, the answer is a person in the organization who holds the appropriate signing authority (often a procurement or contract authorized representative); the project manager signs a legally binding contract on the organization’s behalf only if formally authorized. For high-value, high-risk procurements, whether senior management approval is also needed depends on the organization’s authorization thresholds.

  63. Question 63

    An activity is on the critical path, and whether it finishes on time determines whether the main deliverable can be delivered on time. The project manager wants to take uncertainty and risk into account to improve the accuracy of the duration estimate for this activity. Which of the following tools should be used?

    Show answer and explanation

    Correct answer: B

    An activity is on the critical path and whether it finishes on time determines whether the main deliverable can be delivered on time. The project manager wants to take uncertainty and risk into account to make the estimate more accurate. Which tool should be used?

    The signal in the stem is “take uncertainty and risk into account”. PERT three-point estimating (a common form of multipoint estimating) uses three values, optimistic, most likely and pessimistic, to reflect the uncertainty and risk in the estimate, and then calculates an expected duration, which improves the accuracy of the duration estimate. The activity is on the critical path, and a delay would directly slow the finish, so it is all the more important to reflect risk in the estimate and not give just one single-point number. The answer is B.

    Why the other options are wrong

    • A. A cause-and-effect diagram is used to analyze the root causes of a problem. It is a quality and problem analysis tool, not an estimating tool.
    • C. Analogous estimating is based on historical data from a similar project. By itself it does not explicitly model optimistic, most-likely, and pessimistic scenarios the way multipoint estimating does, so PERT is the better answer for the stated objective.
    • D. Parametric estimating calculates from a statistical relationship. It also does not by itself give estimates for several scenarios and is not designed specifically to reflect uncertainty.

    Key takeaway To build uncertainty and risk into a duration estimate, use PERT three-point (multipoint) estimating.

    Variation If there are reliable historical data and unit labor hours, use parametric estimating. If the project is at an early stage with little information and the answer is needed quickly, use analogous estimating.

  64. Question 64

    A project manager leads an important business transformation project whose goal is to add a mobile module to an existing desktop application. The marketing department judges that the main competitor is also developing a similar product. Which delivery approach should the project manager choose?

    Show answer and explanation

    Correct answer: B

    A business transformation project adds a mobile module to a desktop application, and marketing judges that the main competitor is developing a similar product. Which delivery approach should be chosen?

    Under competitive pressure the key is to get users onto the product quickly and capture the market. PMBOK 8 notes that incremental delivery lets stakeholders use and benefit from parts of the product before the entire project is completed, so value is realized earlier. Releasing the mobile capability as soon as it is finished is how to meet the need for an early launch; delivering everything together or waiting for a major release delays the release and loses the advantage. The answer is B.

    Why the other options are wrong

    • A. Waiting until all development is complete before going live means a late release and no guarantee of a competitive edge. Quality should be assured through the process, not by postponing delivery.
    • C. Extreme programming is a practice used in adaptive approaches, not a delivery approach. The conflict in this question is time to market, not technical risk.
    • D. Folding the module into the next major release delays the release even more, which contradicts “capture the market first.”

    Key takeaway Under competitive pressure to capture the market fast, use incremental delivery and release the completed usable parts first.

    Variation If the mobile module made sense only when its functions were synchronized with the desktop version, it could not be split off and released first; it would have to be delivered together with the desktop side.

    Reference Predictive and Adaptive Approaches and the Stacey Matrix · Lesson 3: How to Choose a Development Approach, and Delivery Cadences

  65. Question 65

    On a precision instrument manufacturing project, several batches of parts were returned by the client, who believes the parts are of poor quality and worries that their own products will be returned too. The project manager is confident quality is under control. How should the project manager communicate with the client so the client is convinced the project produces high-quality products?

    Show answer and explanation

    Correct answer: B

    Several batches of parts were returned by the client, who doubts the parts' quality and worries their own products will be returned too. The project manager is confident quality is under control. The question asks how to convince the client that the project produces high-quality products.

    Quality control measurements are the documented results of quality activities, recorded in the format the quality management plan specifies. They record actual results from inspection, testing and measurement activities and show “what was actually achieved” on the project. Showing them to the client is more complete and more convincing than scattered samples or a standard on its own. Quality control measurements can serve as a basis for communicating the quality status, so when you communicate quality to a client, data and records carry more weight than explanations. The answer is B.

    Why the other options are wrong

    • A. Good samples from earlier batches cannot prove the current product is acceptable, and the client's doubts concern recent batches.
    • C. Tolerances state the specification requirement, and control limits state the statistical variation of the process. Explaining only those limits, without showing actual measurement results, does not prove the product meets requirements.
    • D. A few physical samples pulled from this batch cover too little. They cannot prove the quality of all products and are not a complete measurement record.

    Key takeaway To prove quality to a client, use the quality control measurements, not samples or a standard on its own.

    Variation If the client asks “how will you ensure this in the future?”, show the quality management plan, explain the corrective-action recommendations in the quality reports, and describe how any approved corrective actions will improve the process.

  66. Question 66

    A company's customer service platform project is about to be handed to the operations team. What should the project manager do FIRST before carrying out the handoff?

    Show answer and explanation

    Correct answer: B

    The customer service platform is about to be handed to the operations team. The question asks what the project manager should do first before carrying out the handoff.

    Handoff is giving the result to another team to operate, maintain and support. So before the handoff, first confirm that the operations team is ready for the handoff and the transition, for example whether people, documents and knowledge, and the environment are all in place. If the receiving party is not ready, the handoff will fail or create risk. What to confirm includes whether the receiving staff are in place, whether documents and knowledge have been passed on, and whether the operating environment is available. The answer is B.

    Why the other options are wrong

    • A. Common exam practice puts disbanding the team after the required recording, handoff and knowledge transfer. Releasing people before this handoff would leave it without support, and the operations team would have nobody to ask when problems come up.
    • C. Documents need to be archived for later reference and should not be cleared the moment they are handed over. Nor has readiness of the other side been confirmed, so clearing the library cuts off your own retreat.
    • D. The operating budget is the operations side's work and not the project manager's responsibility before handoff. The project manager should focus on transition readiness.

    Key takeaway Before handoff, first confirm that the receiving party is ready, then hand off.

    Variation If the operations team is not yet ready, postpone the formal handoff and arrange a transition period in which the project team provides support until the other side is ready.

    Reference Project Closure · Lesson 4: Closure Tools and Outputs: Final Report, Handover and Satisfaction

  67. Question 67

    A project manager leads a virtual team spread around the world. What should the project manager do to align members from different cultural backgrounds and overcome the effect of cultural differences?

    Show answer and explanation

    Correct answer: C

    The project manager leads a virtual team around the world and wants members from different cultures to be aligned and to overcome cultural differences. The question asks what measure to take.

    PMBOK 8 notes that in a virtual team environment, additional time may be needed to understand cultural differences and to set clear expectations and facilitate communications. Different cultures may interpret the same message differently. When members form a shared understanding of the team’s goals, they have a common direction and a common yardstick, and disagreements have a shared reference. This is the most central measure for overcoming cultural differences. The answer is C.

    Why the other options are wrong

    • A. Informal communication helps build trust and good working relationships (PMBOK 8), but simply encouraging casual exchange does not ensure that members from different cultures form a shared understanding of goals and expectations, so alignment is not assured and misunderstandings can still arise.
    • B. Fostering stronger personal boundaries and independence would weaken collaboration and hurt cross-cultural communication.
    • D. An atmosphere where members can talk freely at any time is useful, but it is only a condition. It does not directly remove the gaps in understanding caused by cultural differences and is less targeted than a common understanding of goals.

    Key takeaway A cross-cultural team aligns its direction through a shared understanding of goals, which reduces differences in interpretation caused by culture.

    Variation If the differences show up in specific behavior (for example, attitudes toward deadlines), agree clear working norms in the team charter.

    Reference Virtual Teams · Lesson 2: Virtual Team Communication, Time Zones, Trust and Cross-Cultural Management

  68. Question 68

    A corporate training platform project uses a predictive approach. The scope baseline has been approved and development is about halfway done. The customer's representative asks to add a “learning points store” feature that is not in the original scope. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    This is a predictive project in the Executing focus area, and the scope baseline is approved. The customer's representative asks for a “learning points store” feature that was not in the original scope. The question asks what the project manager should do.

    The signals are “the baseline is approved” and “not in the original scope”. Any change that touches a baseline goes through change control: first evaluate the impact of the new feature on scope, schedule, cost and so on, then submit a change request for approval by the approver named in the change management plan (the change control board where applicable). Only after approval can the baselines be updated and the work begin. The answer is B.

    Why the other options are wrong

    • A. Adding the new feature to the WBS and telling the team to start without approval bypasses change control. This is scope creep.
    • C. Once new scope is approved, the scope baseline is updated through change control, and the schedule and cost baselines are updated where needed. Management reserve sits outside the baselines and is for unforeseeable work, and its use also requires authorization. It cannot be used to skip evaluation and approval and absorb the added work while leaving all baselines unchanged.
    • D. Adding budget also requires change approval. Starting work with no evaluation and no approval gets the order wrong.

    Key takeaway Any change that touches a baseline goes through change control: evaluate first, then submit, and it becomes part of the baseline only after approval.

    Variation If the same request arose in an agile project, the product owner would add it to the backlog and order it by value. If the stem said the change had already been approved, the next step would be to update the baselines and plans and notify stakeholders.

  69. Question 69

    On project quality management, which approach best fits the principle Embed Quality Into Processes and Deliverables?

    Show answer and explanation

    Correct answer: B

    The question asks which approach best fits the principle Embed Quality Into Processes and Deliverables.

    “Embedding” means building the target quality requirements into the planning and the process itself. Through training, inspections and testing, and through reviews and audits, the team identifies and prevents errors and defects and reduces rework and waste. Quality comes from planning and prevention, not from a final inspection. Only B shows prevention first. The answer is B.

    Why the other options are wrong

    • A. Concentrating inspection before delivery, with dedicated staff checking item by item, finds mistakes after the fact. The defects already exist, and rework is typically costlier than early prevention and detection, which is the opposite of prevention.
    • C. Quality requirements are set from acceptance criteria and stakeholder needs, and they cannot be relaxed step by step under cost pressure. That goes against the purpose of embedding quality into the process.
    • D. Pushing quality problems to closing for a single rework lets defects accumulate and multiplies rework, which violates the requirement to detect and prevent early.

    Key takeaway Quality is built into the design and the process, not inspected in; prevention works better than inspection after the fact.

    Variation If asked how acceptance criteria are handled in an adaptive project, the answer is that when the project evolves through experimentation, they may need to be updated and refined regularly and checked again for validity at acceptance. If asked from which two aspects quality is viewed, the answer is deliverables and processes.

  70. Question 70

    A team is responsible for a smart customer-service chatbot project. The project management plan describes the next six months of work in great detail, and even a small change in requirements during execution forces a major rewrite, limiting the flexibility of execution. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    The chatbot project's plan writes six months of work in great detail, and even a small requirements change forces a major rewrite, limiting flexibility in execution.

    “Six months all in detail” and “a requirement change forces a major rewrite” are the key information. Rolling wave planning is one form of progressive elaboration: plan near-term work in detail, leave far-term work at a higher level and refine it as work advances, which gives both stability and flexibility. In questions like this, both extremes are wrong: one is so detailed that it is rigid, and the other is so rough that it has no basis. Rolling wave planning takes the middle path, detailed in the near term and leaving room to adjust in the far term. The answer is C.

    Why the other options are wrong

    • A. Adding more detail makes the plan more rigid, and changes cost more to make when they arrive.
    • B. Leaving it unchanged leaves the flexibility problem in place. The plan should be progressively elaborated as information increases, with approved changes incorporated under the applicable change-control requirements.
    • D. Keeping only milestones and not planning any specific work leaves near-term work without a basis for execution and goes to the opposite extreme.

    Key takeaway A plan that is detailed near term and rough far term, refined as work advances, is rolling wave planning.

    Variation If the stem said the plan was too rough for the team to start, you would detail the near-term work. Short iterations also demonstrate progressive elaboration: the current iteration is planned in detail while later work remains at a higher level in the roadmap or backlog.

  71. Question 71

    A store checkout system upgrade project has just been initiated. While planning, the project manager finds that several key members lack the skills needed for the core tasks late in the project. The assessment shows that training started now will close the gap before those tasks begin without breaching the schedule or cost constraints. What should the project manager do?

    Show answer and explanation

    Correct answer: D

    The project has just been initiated and planning is under way. Comparing against the tasks, the project manager finds that several key members lack skills for late-stage core tasks. The assessment has confirmed that training can close the gap in time without breaching the schedule or cost constraints.

    Skill gaps are something the resource management plan deals with: it states how resources are acquired and how people are trained. PMBOK 8 treats training, hiring, schedule changes and scope changes as parallel proactive responses. For a gap found during planning when training is feasible, common exam practice is to arrange adequate training in the resource management plan before replacing people or outsourcing. Among the choices, D best reflects that approach.

    Why the other options are wrong

    • A. A skill gap can be logged and tracked, but merely entering it in the issue log does not close it. In planning, first set out training and any needed resource acquisition in the resource management plan, so logging is not the first step.
    • B. Members lack only some skills, so replacing them during planning is hasty and adds cost. Consider whether training can solve it first, then whether anyone needs replacing.
    • C. The stem has not said that training is infeasible, and no make-or-buy analysis has been done, so outsourcing the core tasks directly is premature. If training cannot close the gap in time, then evaluate external resource options.

    Key takeaway For a skill gap found during planning when training is feasible, common exam practice is to arrange training in the resource management plan before considering replacement or outsourcing.

    Variation If the gap appears during execution and there is not enough time for training, then turn to borrowing staff, outsourcing or hiring. If the question asks what options exist when competence is lacking, the answer is training, hiring new members, schedule changes or scope changes.

  72. Question 72

    A training company's learning platform project is close to delivery. The customer representative arrives on site for acceptance, finds that one requirement he proposed has not been implemented, and is very upset. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    The project is close to delivery. At acceptance the customer representative says a requirement he proposed was not implemented, and he is upset. The question asks what the project manager should do.

    When a customer says a requirement was not implemented, verify the facts first and then decide on action. The requirements traceability matrix links requirements to deliverables and tests, so consulting it confirms whether the requirement was approved and recorded, whether it was assigned to a deliverable, and whether it was implemented and tested. After verifying, if it was indeed approved but missed, assess the impact and process the needed defect repair or corrective action through change control; once it is approved, implement it, reverify the deliverable and re-run acceptance. If it is not within the approved scope, it is a new request and goes through change control. The answer is B.

    Why the other options are wrong

    • A. Agreeing to build it before checking whether the requirement truly belongs to the approved scope can bypass change control and may mean doing work outside the scope.
    • C. The benefits management plan focuses on how benefits will be realized and measured. It does not contain the customer's specific requirements and cannot be used to check whether requirements were implemented.
    • D. The scope management plan only explains how scope is managed. It contains no specific requirements, so asking the customer to compare against it would not reveal the gap.

    Key takeaway When a customer says a requirement was not met, check the requirements traceability matrix first, and only then talk about building it or going through change.

    Variation If the matrix shows that the requirement was never approved, it is a new request. It cannot simply be built; submit a change request, and include it in scope only after assessment and approval.

  73. Question 73

    While observing a team that uses Extreme Programming (XP), a project manager notices that every programmer works in a pair with another person, and the partners change every few days. How should the project manager react?

    Show answer and explanation

    Correct answer: B

    A project manager observing an XP team sees that every programmer works in a pair and the partners change every few days. How should the project manager react?

    Pair programming in XP encourages rotating partners: skills back one another up, communication and feedback flow more smoothly, and knowledge is not concentrated in a few people. The team is self-organizing, so how to pair is the team's own decision, and the project manager should understand it and not interfere. The stem contains no sign of a problem; it merely describes the team's own arrangement, so nothing needs to be “solved” and the manager only needs not to disturb it. The answer is B.

    Why the other options are wrong

    • A. The brief adjustment period that rotation brings is the cost of spreading knowledge, and the team will adjust by itself. Requiring fixed partners weakens skill backup.
    • C. Having the project manager draw up a list of pairs is directing a self-organizing team, which is the opposite of the agile approach.
    • D. A long-fixed “master and apprentice” pairing is not good for everyone learning from one another, and it is also an arrangement imposed from outside.

    Key takeaway The team itself decides the pairing partners and rotates freely; the project manager does not interfere.

    Variation If the stem said “a new member does not know the technology”, the person can be paired with someone who knows it, still arranged by the team. If the team asks the manager to help resolve a pairing conflict, the manager can guide the conversation but does not assign pairs for the team.

  74. Question 74

    The team of a customer relationship management system implementation project has completed the first version of the WBS. A member asks whether project management work such as planning and meetings should also be included in the WBS. How should the project manager answer?

    Show answer and explanation

    Correct answer: A

    The team has completed the first version of the WBS, and someone asks whether project management work such as planning and meetings should be included.

    The WBS reflects the whole scope of work, including both the product scope and the project scope needed to deliver the product; PMBOK 8 says the WBS represents all product and project work, including the project management work. Planning, meetings and similar project management work also consume resources and time and need to be estimated and managed, so they should be included in the WBS, but in the form of suitable project management deliverables or work packages, rather than listing each meeting and other schedule activity as a WBS node. The answer is A.

    Why the other options are wrong

    • B. The WBS contains more than the product scope; it must include the project management work that is part of the project scope, or there is nowhere to collect the cost and schedule of that work.
    • C. If something is in the budget but not in the WBS, the cost has no work package to be collected under, and this also violates the requirement that no scope is left out.
    • D. Whether a cost is indirect is a cost classification question and is a separate matter from whether it belongs in the WBS. Even if its cost is indirect, project management work is still work that has to be done.

    Key takeaway The WBS includes all product work and project work. Project management work belongs in it too, represented as project management deliverables or work packages rather than by listing each meeting or other schedule activity.

    Variation If the work is routine operational work of the organization and unrelated to this project's delivery, it is not part of the project scope and should not be in the WBS.

    Reference Work Breakdown Structure · Lesson 2: Work Packages, Planning Packages and Control Accounts: Where to Stop Decomposing

  75. Question 75

    On an e-commerce mini-program project, the Scrum Team has set the Sprint Goal and the Developers have created the Sprint Backlog for this Sprint, and the highest-priority item is building the order payment flow. Halfway through the Sprint, two developers propose using the remaining time to refactor another module that may cause trouble in future. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    Halfway through a Sprint, for which the Scrum Team had already set the Sprint Goal and the Developers had created the Sprint Backlog, two developers want to spend the remaining time refactoring work outside the Sprint. The question asks what the project manager should do.

    The Sprint Goal was set by the Scrum Team and the Sprint Backlog was created by the Developers, so during the Sprint the Developers should work toward the Sprint Goal and make no change that endangers it. Refactoring has value, but it should go into the Product Backlog as an item, where the Product Owner orders it with the other items and the next Sprint Planning decides whether to select it. The project manager's role here is to remind the team to hold on to the Sprint Goal and to direct the new idea to the right entry point. The answer is A.

    Why the other options are wrong

    • B. Agreeing to the refactoring means giving up the agreed highest-priority work midway. The Sprint Retrospective is held only at the end of the Sprint, by which time the Sprint Goal is already lost, and explaining afterward does not help.
    • C. The team is self-organizing, and trade-offs within the Sprint are settled between the team and the Product Owner. A functional manager is outside the Scrum Team, and escalating would only complicate the team's internal affairs.
    • D. Acknowledging quality awareness is fine, but “as you see fit” tacitly allows the team to drift from the Sprint Goal. Refactoring needs a value judgment and ordering first and cannot jump the queue in the Sprint on someone's personal idea.

    Key takeaway During a Sprint do not drift from the Sprint Goal: a new idea goes into the Product Backlog, and the Product Owner orders it.

    Variation If the payment flow could not be delivered without the refactoring (a direct threat to the Sprint Goal), the team should discuss adjusting scope with the Product Owner. If it is only that something “may cause trouble in future”, leave it for later ordering.

    Reference Scrum Events · Lesson 1: The Sprint: A Fixed-Length Timebox

  76. Question 76

    To keep the software in a working, deliverable state at all times, a team develops with XP. Members want to pick up project information unintentionally from the conversations around them without holding a dedicated meeting, which is osmotic communication. Which of the following XP practices best supports this kind of communication?

    Show answer and explanation

    Correct answer: D

    An XP team wants members to pick up project information unintentionally from the conversations around them, without a dedicated meeting. This is osmotic communication. The question asks which XP practice best supports it.

    The key to osmotic communication is “unintentional” and “conversations around them”: when the team sits in the same shared space, members overhear and absorb one another's discussions without trying to, and information flows naturally. The only practice that provides this environment is the team working together in the same space. Letting information flow naturally depends on the environment, not on one more meeting and not on some coding move. The answer is D.

    Why the other options are wrong

    • A. Refactoring is a technical practice about the structure of the code. It has nothing to do with how members come by information.
    • B. Test-driven development likewise focuses on code and has nothing to do with osmotic communication.
    • C. Pair programming is deliberate, active exchange between two people, while osmotic communication is unconscious and reaches the whole team, not just two people.

    Key takeaway Osmotic communication comes from the team sharing one space, so information flows without anyone trying.

    Variation If the stem asked about “real-time code review and knowledge transfer”, the answer is pair programming. If it asked about “a real user on the team who answers questions full time”, the answer is the on-site customer.

  77. Question 77

    During implementation of an order-sorting module for a logistics platform, an adjustment was made with the approval of the change control board (CCB). During trial operation, a key stakeholder complains that the adjustment makes the operating steps cumbersome. To pass acceptance smoothly, which of the following documents should the project manager present to show that the adjustment was formally approved?

    Show answer and explanation

    Correct answer: A

    An adjustment to the order-sorting module was approved by the change control board. During trial operation, a key stakeholder complains that it makes the operating steps cumbersome. To get through acceptance, the project manager must present a document proving that the adjustment was formally approved. Which document is it?

    The question asks for the “approval record.” The change log is the complete list of all changes submitted during the project and records the current status and disposition of each change request, whether approved, deferred or rejected. Presenting the change log shows when the adjustment was raised and how the board decided, serving as evidence at acceptance. The answer is A.

    Why the other options are wrong

    • B. The issue log records issues that have occurred and need to be followed up. The complaint about cumbersome steps might be recorded there, but it does not record change requests and their approval outcomes, so it cannot prove that the adjustment was approved.
    • C. The assumption log records assumptions and constraints and has nothing to do with whether a change was approved, so it establishes no fact about approval.
    • D. The change management plan is the guiding document that sets out how changes are handled and how the process should run. It does not record the submission and approval status of a specific change, and it is easily confused with the change log.

    Key takeaway To prove whether and how a change was approved, look at the change log.

    Variation If the question were what process changes should follow and who has approval authority, look at the change management plan; if it were an existing issue that needs follow-up, look at the issue log.

    Reference Change Control · Lesson 1: Assess and Implement Changes: Purpose, Responsibilities, Change Requests and the Change Log

  78. Question 78

    At a risk review meeting for a warehouse management system project, the project manager asks each risk owner for a progress report and finds that several of them are not acting on the agreed response strategies. To reduce risk exposure, what should the project manager do?

    Show answer and explanation

    Correct answer: B

    At a risk review meeting the project manager finds that several risk owners are not acting on the agreed strategies. The goal is to reduce risk exposure. How should the project manager move things forward?

    “Not acting on the agreed strategies” shows that the responses have not been executed, but it does not yet establish why. Without knowing why, you cannot fix it: there may be a resource conflict, lack of authority or a technical obstacle, or the strategy itself may not hold up. The project manager should talk with the owners one on one, understand the obstacles and help resolve them. This is how a project manager uses influence to get responses carried out; only when the responses are actually in place does risk exposure really come down. The answer is B.

    Why the other options are wrong

    • A. Giving orders without understanding the obstacles leaves the blockage in place. The same thing will happen at the next meeting, so this treats the symptom, not the cause.
    • C. Going straight to the sponsor and recommending removal skips the conversation and deals with the person instead. It does not get the responses carried out and it damages team relationships.
    • D. Reassigning risks without knowing the cause just passes the same obstacle to someone else, and the owners have not agreed to it. The cause remains unresolved.

    Key takeaway When a risk owner is not carrying out the response, first talk to find the obstacle and help resolve it; only then consider reassigning or escalating.

    Variation If you learn that the strategy itself is not feasible, the answer becomes reassess and replace the strategy, raising a change request if needed. If the owner is outside the team, it is still communication and coordination, not an administrative order.

  79. Question 79

    In a project review meeting, the team member responsible for integration testing tells the project manager that this critical path activity will take three days longer than planned, and that adding resources could shorten its duration. A senior manager says that even if the budget must be increased, a way must be found to deliver the project on the baseline plan. Which method should the project manager use to meet this requirement?

    Show answer and explanation

    Correct answer: A

    Integration testing will take three days longer than planned, and a senior manager requires delivery on the baseline plan even if the budget must be increased. The project manager must choose the schedule compression method that meets this requirement and also fits the condition that the budget can be increased.

    Delivering within the original baseline calls for schedule compression. The two techniques are crashing and fast tracking. The activity is on the critical path and adding resources can shorten its duration, which is the precondition for crashing. The stem also explicitly allows an increase in budget, and crashing trades cost for time, so the available facts directly support crashing. “Even if the budget must be increased, deliver on the baseline” removes the cost constraint while keeping the date fixed, which points to crashing, which trades cost for time, rather than fast tracking, which takes on rework risk. The answer is A.

    Why the other options are wrong

    • B. Fast tracking requires activities that can be overlapped to shorten the critical path. The stem does not establish that condition, so fast tracking is not supported by the available facts.
    • C. The critical chain method manages uncertainty by accounting for resource constraints and setting project buffers, and it does not itself shorten this activity's duration. The stem does not say the project uses the critical chain method; what it does give are the three conditions for crashing (a critical path activity, added resources that work, and an increase in budget allowed).
    • D. Leads and lags are time adjustments applied to the logical relationships between activities: a lead overlaps activities, with an effect similar to fast tracking and its rework risk, and a lag delays the following activity. The stem does not say there are leads or lags to adjust, and with budget available you should prefer shortening the testing activity itself by crashing.

    Key takeaway When the stem confirms that adding resources to a critical path activity shortens it and increased cost is allowed, crashing is a supported choice. When resources cannot or should not be added but the dependencies allow parallel work, then consider fast tracking after assessing rework, quality, risk and cost impact.

    Variation If the senior manager had said “not a cent more can be added”, the answer would become fast tracking, provided the dependencies allow parallel work, and you would assess the rework, quality and cost impact.

  80. Question 80

    During the project, the project manager learns that the company has just introduced a remote work policy, and most team members will now work from home, with working days and working hours unchanged. Which item in the project plans or documents should the project manager adjust to reflect this change?

    Show answer and explanation

    Correct answer: C

    The company introduces a remote work policy, most team members now work from home, and working days and hours are unchanged. The question asks which project plan or document the project manager should adjust.

    Members change from working together to working from home, so their communication methods or channels will usually need adjustment, for example through more online meetings, instant messaging and shared documents. These are recorded in the communications management plan, so update it to reflect the new methods. Resource calendars, responsibilities and emergency contacts are not directly affected. The answer is C.

    Why the other options are wrong

    • A. The stem says working days and hours are unchanged. Members' availability does not change, only where they work, so the resource calendar need not be revised. If remote work also changed availability or created cross-region arrangements, the resource calendar would need updating.
    • B. The responsibility assignment matrix describes who is responsible for what. Working from home changes only location, not roles and responsibilities.
    • D. The stakeholder engagement plan records how to raise stakeholder engagement. Emergency contact details are unrelated to it and are not part of that plan.

    Key takeaway A change in how people work affects how they communicate. Update the communications management plan, not the resource or responsibility arrangements.

    Variation If working from home widens the time zone spread of members, also add fixed overlap hours to the plan.

    Reference Managing and Monitoring Communications · Lesson 4: Tailoring Communication and Common Scenarios: Virtual Teams, Time Zones and External Stakeholders

  81. Question 81

    A film production company planned to shoot a major scene at a seaside location. The weather service forecasts a strong typhoon during the shooting week, and the crew cannot work offshore. The head of production decides to move the scene to an indoor studio. Which risk response strategy did the head of production use?

    Show answer and explanation

    Correct answer: B

    A film company planned to shoot a major scene at a seaside location. A strong typhoon is forecast for the shooting week and the crew cannot work offshore, so the head of production moves the scene to an indoor studio. Which response strategy is this?

    The key is whether the threat still exists after the action. Avoid takes action to eliminate the threat or to protect the project from its impact, typically by changing the plan or strategy. After the scene moves indoors the typhoon no longer affects it at all, so the threat is eliminated and the strategy is avoid. If the crew still shot on location and only reinforced equipment or raced the clock, that would be mitigate, because the threat would remain. The answer is B.

    Why the other options are wrong

    • A. Mitigate keeps the risk and only reduces probability or impact, for example reinforcing equipment and still shooting on location. Here the location was changed outright and the typhoon no longer matters to this scene.
    • C. Accept takes no proactive action and deals with the event if it happens. The head of production actively changed the shooting plan, which is action, not acceptance.
    • D. Transfer gives the consequences to a third party, for example by buying insurance for the shoot. The stem has no third party bearing the impact of the typhoon. The typhoon will still arrive; it just no longer affects this scene.

    Key takeaway Changing the plan so the threat no longer affects the project is avoid; if the threat remains and only its impact is reduced, it is mitigate.

    Variation Buying typhoon insurance on the equipment so the insurer pays for damage is transfer. Preparing wind-protection gear but still shooting on location is mitigate.

  82. Question 82

    An enterprise resource planning system upgrade project has reached integration testing, a critical project phase. A key stakeholder, the head of the quality department, refuses to take part in the review for this phase and does not agree with the testing approach the team is using, and team morale is suffering. What should the project manager do?

    Show answer and explanation

    Correct answer: B

    An ERP upgrade project has entered integration testing, a critical phase. The head of the quality department refuses to take part in the review for this phase and disagrees with the team's testing approach, and team morale is affected. You must decide what the project manager should do.

    A key stakeholder who does not take part and does not agree is a conflict that needs to be dealt with directly and promptly. The project manager should quickly call a meeting of the team and the quality head to discuss their respective reasons face to face, find out why he disagrees, weigh the review standards against the risks, and settle on an approach that both sides accept. That brings him back in and steadies the team; it is the collaborate/problem-solve approach. Recording flaws unilaterally or giving in unilaterally cannot serve both sides at once. The answer is B.

    Why the other options are wrong

    • A. The quality head is not even in the room, and listing flaws only within the team neither gets him involved nor touches the reason for his disagreement, and it may deepen the opposition.
    • C. Unilaterally requiring the team to switch to his approach establishes no cause for the disagreement and assesses no cost, and it hits the team's morale even harder.
    • D. Resolving this kind of disagreement is within the project manager's own authority, and the project manager should communicate directly with both sides first. Asking the sponsor to step in at the outset makes the project manager look incapable of handling it.

    Key takeaway When a stakeholder does not take part or does not agree, the project manager first communicates directly and promptly and brings all parties together to agree on an approach.

    Variation If repeated discussions still fail to settle the approach, only then escalate to the sponsor. If quality standards conflict with contract terms, first verify the applicable requirements and involve the contract owner; handle a change under the governance process only if an approved baseline or contract term must be modified.

    Reference Stakeholder Engagement · Lesson 4: Aligning and Managing Stakeholder Expectations: Dissatisfaction, Conflict and Out-of-Scope Requests

  83. Question 83

    PMLyceum is implementing a membership system for a supermarket chain. The project manager is building the stakeholder register and is not sure of the motives of several customer-side leads. To get this information, what should the project manager do?

    Show answer and explanation

    Correct answer: B

    On a supermarket chain's membership system project, the project manager is building the stakeholder register and is not sure of the motives of several customer-side leads, and needs to decide how to get this information.

    Motives and expectations are information that stakeholder analysis has to collect, and the most reliable source is the person themselves. In a one-on-one conversation with no one else present, a lead is more willing to state real concerns, and the project manager can ask follow-up questions and observe their attitude. Public statements and written statements tend to be official in tone, and inferring from documents is even less reliable. The answer is B.

    Why the other options are wrong

    • A. In a public setting such as a kickoff meeting, leads tend to hold back and will not easily state their real motives, and there is no way to ask follow-up questions one by one.
    • C. An email yields only a statement about the project objectives. It does not reveal personal motives and does not allow follow-up questions.
    • D. The business case states objectives at the project level. Inferring each person's motives from it is subjective guesswork and is unreliable.

    Key takeaway If you are unsure of a stakeholder's motives, talk to the person one on one. A one-on-one conversation helps you understand motives and also supplies a basis for later communication methods and engagement strategies.

    Variation If you need to learn the common needs of eighty users in a short time, one-on-one is impractical, so choose a questionnaire or focus group. One-on-one suits a small number of key people.

  84. Question 84

    A technology company announces a new strategy that shifts its focus from consumer products to enterprise customers. A consumer app project now under development no longer fits the new direction. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    A technology company shifts its strategy from consumer to enterprise customers, and a consumer app project under development no longer fits. What should the project manager do?

    A project’s value depends on its alignment with the organization’s strategy. A change of strategy affects project value, and PMBOK 8 notes that if the project is unlikely to deliver the intended value, it may be best to terminate the effort. The project manager should assess the project’s value and make a recommendation to the governing body, which decides between adjusting the scope and terminating. The answer is C.

    Why the other options are wrong

    • A. Whether to redirect the objective to enterprise customers is for the governing body to decide. The project manager cannot change direction alone, since that changes the project’s overall objectives and justification.
    • B. A project’s value depends on alignment with strategy, so saying the project is unaffected by the strategy change is wrong. Continuing as planned only consumes resources.
    • D. If the effect is not reported, the governing body cannot make a decision, and the team will keep investing resources in a direction that may have no value.

    Key takeaway When a strategy change leaves a project misaligned, assess the value and recommend that the governing body decide between adjusting the scope and terminating.

    Variation If the new strategy keeps a consumer business as a branch, assess whether the project still fits the retained part of the strategy before making a recommendation.

    Reference The System for Value Delivery · Lesson 3: Value-Driven Decisions: What to Do When Value Changes

  85. Question 85

    A software module has completed verification of its deliverables (Monitor and Control Scope), and the project manager is preparing to arrange customer acceptance and is gathering the inputs that Validate Scope needs. Which of the following is a main input to this process?

    Show answer and explanation

    Correct answer: C

    A software module has been verified, and the project manager is preparing customer acceptance and gathering the inputs Validate Scope needs. The question asks which is a main input.

    The main input to Validate Scope is verified deliverables: completed deliverables that have been checked and confirmed for correctness through Monitor and Control Scope. Other inputs include project documents such as requirements documentation, the scope baseline, quality reports and work performance data, and quality control measurements. In the stem, the module has just finished verification, and that verified result is the input to Validate Scope. A way to approach this kind of question is to follow the arrows: the outputs of Monitor and Control Scope are the inputs to Validate Scope, while the outputs of Validate Scope are accepted deliverables, change requests and document updates. The answer is C.

    Why the other options are wrong

    • A. Accepted deliverables are an output of Validate Scope, a result that exists only after acceptance is complete.
    • B. Change requests arise, for example, when deliverables are not accepted. They are an output, not an input.
    • D. The lessons learned register is updated after Validate Scope, so it belongs on the output side.

    Key takeaway Validate Scope takes in verified deliverables; accepted deliverables come out.

    Variation The output of Monitor and Control Scope is verified deliverables. When acceptance fails and a change is needed, a change request is produced as required.

  86. Question 86

    PMLyceum is running a logistics tracking platform project covering six countries, and the countries' regulatory requirements for data protection and cross-border transfer differ. The project manager needs to tailor the project's governance approach. Which of the following approaches is MOST appropriate?

    Show answer and explanation

    Correct answer: D

    The project runs in several countries, and the external environment (each country's regulations) differs a great deal. The question is how governance should be tailored to the environment.

    Project governance should be tailored to the context in which the project operates. A large multinational project must comply with the regulations of several agencies and countries, so governance should integrate across domains to make sure the work is appropriately monitored and controlled to comply with internal and external standards. Compliance requirements with regional variations can be managed in program- or portfolio-level governance. You can use the key words to decide: “six countries” and “different regulations in each country” point to many external constraints and heavy compliance requirements, so choose more integrated governance, not light governance or each country going its own way. The answer is D.

    Why the other options are wrong

    • A. Lightweight self-governance suits innovation projects that need quick feedback. A project with heavy compliance requirements and many external constraints needs heavier governance, and letting teams judge on their own creates compliance risk.
    • B. Regulations are external environmental factors, and the project can only comply with them. Requirements differ by country, so you cannot simply apply the headquarters country's standards.
    • C. Each country going its own way and consolidating afterward loses unified monitoring, and violations are discovered too late. Governance should be integrated continuously during the project.

    Key takeaway The more external constraints there are, the more integrated and targeted governance must be; regional variations can be moved up to program or portfolio level.

    Variation If the stem described a prototype project in a single country with a short cycle and a need for rapid innovation, the answer would lean toward light governance, short feedback and self-governance within boundaries.

  87. Question 87

    During the bid evaluation stage of an equipment procurement project, the project manager finds that a relative of the procurement team lead runs one of the bidding suppliers, and the lead is taking part in the evaluation. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    At the bid evaluation stage, a relative of the procurement team lead runs a bidding supplier, and the lead is still on the evaluation. The question asks what the project manager should do.

    This is a classic conflict of interest: an evaluator is related to a bidder, which may affect the fairness of the evaluation. Handle it under the organization's conflict of interest policy by requiring the person to disclose and recuse, so the evaluation rests on a fair basis, and keep a record so it can be traced. Disclosure and recusal are common practices for handling a conflict of interest, protecting both the fairness of the evaluation and the person concerned. The answer is A.

    Why the other options are wrong

    • B. Staying out and checking after the award misses the fairness stage of the evaluation. The conflict of interest may already have affected the result, and fixing it afterward is costly.
    • C. Having the person handle it at his own discretion with no record cannot guarantee fairness and leaves nothing to trace, so it is hard to defend if challenged.
    • D. Disqualifying the supplier directly has no basis in policy, is unfair to the supplier and would cause new disputes. The problem lies with the evaluator, not the supplier itself.

    Key takeaway When you find a conflict of interest, under organizational policy have the person disclose and recuse, to ensure fairness.

    Variation If the conflicted party is the project manager, the project manager should disclose to the sponsor and recuse from the related decisions, and the sponsor assigns someone else to handle it.

    Reference Project Compliance · Lesson 4: Handling Violations and Compliance Risks

  88. Question 88

    A company takes on a project to develop a smart thermostat app for households in Southeast Asia and the Middle East, intended to reduce users’ everyday electricity costs. Users’ environments differ greatly from country to country, and the development team is spread across several countries. What should the project manager do FIRST when planning how to carry out the project?

    Show answer and explanation

    Correct answer: D

    Early in the project, the smart thermostat app targets households in Southeast Asia and the Middle East, users’ environments differ greatly by country, and the team is spread over several countries. The question asks what the project manager should do first when developing the implementation approach.

    The key signals are “first” and “environments differ greatly”: the approach has to rest on a judgment about its premises. First identify the assumptions and constraints that affect the project’s success. Known climates, electricity prices, time zones and languages are background conditions for planning, while premises that have not been verified and are provisionally treated as true (for example, that users’ habits in each place match expectations) are assumptions; these are recorded in the assumption log and then verified, so that the later scope, resource and coordination arrangements rest on reliable premises. The answer is D.

    Why the other options are wrong

    • A. A work breakdown structure should be created after the relevant factors are understood, or the scope broken down may not suit the environment in each place.
    • B. A bar chart and the allocation of roles and responsibilities are not the first task. You need the premises first to know how resources should be arranged in each region.
    • C. Looking at the organizational chart tells you only how members report. It does not answer what factors affect the project’s success, so it is not the most critical work.

    Key takeaway Before developing the implementation approach, first identify the assumptions and constraints and record them in the assumption log.

    Variation If an assumption later proves false, update the assumption log, assess the impact on scope, schedule and cost, and go through change control if necessary.

    Reference Project Charter · Lesson 4: The Assumption Log, Initiating Tools and the Adaptive Charter

  89. Question 89

    An industrial equipment installation project is working on commissioning activities on the critical path. The risk register already records the risk “delayed arrival of the imported control module”, with agreed responses and an owner. Today the supplier announces that the module will arrive ten days late, and equipment delivery will slip as a result. What should the project manager do FIRST?

    Show answer and explanation

    Correct answer: D

    Commissioning activities on the critical path are affected. The risk is already in the register, with agreed responses and an owner, and today it has been triggered (the supplier announces a ten-day delay). The question is what to do FIRST.

    Three signals matter: the risk is registered, responses are agreed, and the risk has been triggered. So a ready-made response exists, and the first job is to have the owner carry out the actions right away to contain the impact. If a response calls for contingency reserve or a baseline change, handle that as part of the response, and follow up with status records afterward. Updating the register, logging an issue and raising a change request are supporting actions, not the first step. The answer is D.

    Why the other options are wrong

    • A. Even if the delivery date is affected, first carry out the agreed response to determine the residual impact. If that residual impact requires a controlled baseline to change, submit a change request under the change management plan.
    • B. Marking the risk as occurred in the register is a supporting step, not the first action. Carry out the agreed response first, then record it in the issue log and update the register status.
    • C. How contingency reserve is used is set out in the response plan. It is not a first step separate from the response; carry out the plan first, then draw on reserve as needed.

    Key takeaway When a registered risk is triggered, carry out the response plan first; then log the issue, use reserve and raise change requests as needed.

    Variation Remove “agreed responses”: if the risk has not yet occurred, the answer becomes plan the response and then implement it. If it has occurred and there is no prepared response, treat it as an issue, develop a workaround and record it in the issue log. If it is a risk that was never identified, the answer is to bring the team together to find a workaround. The difference is whether the risk was registered beforehand and whether a response was agreed.

  90. Question 90

    An e-commerce company is setting up a customer service center for its promotion season and estimates that it needs 80 call agents: weekdays 9 a.m. to 6 p.m., and weekends 9 a.m. to 1 p.m. Management has not decided whether to hire the people itself or hand the work to an outside company. The project manager must provide a basis for this decision. Which of the following analyses should the project manager use?

    Show answer and explanation

    Correct answer: B

    The project must set up a customer service center with a clear headcount, but it has not been decided whether to do it internally or outsource it. The question asks which analysis gives a basis for that decision.

    The key information is that the headcount and shifts are settled but “hire ourselves or outsource” is not. For a decision about whether to do the work and who should do it, use make-or-buy analysis: it compares in-house hiring with outsourcing on cost, risk, skills and long-term employment obligations. The conclusion comes only after the analysis and is then written into the procurement strategy. None of the other three is a tool for deciding between making and buying. The answer is B.

    Why the other options are wrong

    • A. Earned value analysis measures the performance of work already completed and needs actual performance data. The stem is about deciding whether to hire or outsource, and there is no completed work to measure.
    • C. Reserve analysis compares contingency reserves with the remaining risk to judge whether the reserve is enough. It is not a way of comparing in-house work with outsourcing.
    • D. Trend analysis looks at how performance changes over time to forecast what comes next. It too needs data that already exists and cannot decide between hiring and outsourcing.

    Key takeaway To decide whether to do the work yourself or outsource it, compare the options with make-or-buy analysis, and then record the conclusion in the procurement strategy.

    Variation If the stem said the analysis was finished and the conclusion was to outsource, the next step would be to prepare the statement of work. If it asked how to compare the costs of the two options, you would include indirect costs.

  91. Question 91

    A manufacturing company is moving from predictive methods to agile, and the project manager is sent to lead an inexperienced team on the first pilot. Because of a temporary arrangement, the whole team works remotely. By the second Sprint, the project manager notices that team members lack a sense of commitment, and the team has not yet discussed the reasons together. As a servant leader, what should the project manager do?

    Show answer and explanation

    Correct answer: A

    A manufacturing company is moving from predictive to agile. The project manager leads an inexperienced team on the first pilot, and the team works remotely under a temporary arrangement. In the second Sprint the project manager finds members lack a sense of commitment, and the team has not yet discussed why. As a servant leader, what should the project manager do?

    Two signals: “servant leader” and “lack of commitment”. When an agile team has a problem, first let the team self-organize to solve it: the team finds the causes and proposes the remedies itself, and the servant leader's role is to guide and support. The project manager can guide the team right now to discuss the causes together and propose solutions itself, providing support, coaching and removal of impediments as needed during the discussion but not deciding for the team. That keeps the initiative with the team and also builds commitment. The answer is A.

    Why the other options are wrong

    • B. Forcing every member to attend the Daily Scrum and report status is command and control, contrary to servant leadership. The Daily Scrum is also the team's own meeting to coordinate its work, not a place to report to a manager.
    • C. The lack of commitment may not be caused by remote work, and remote work is already a settled arrangement, so asking for an exception is not necessarily realistic and does not first let the team find the causes.
    • D. Interviewing members one by one, asking them to raise participation and having them report improvements is command and control. It treats a team problem as an individual problem, the cause has not been confirmed and the team has not analyzed it, which fits neither self-organization nor servant leadership.

    Key takeaway When an agile team has a problem, first let the team find its own way, and the leader then provides support.

    Variation If the stem said the team had tried for several Sprints and still could not solve it, and the impediment came from outside the team, the servant leader would step in to coordinate outside resources and help clear it.

  92. Question 92

    To make later review easier, an online course team requires that the live lesson can be switched on only once the screen-recording software has been started. The recording does not have to finish first. Which logical relationship should be used between “start recording” and “start the live broadcast”?

    Show answer and explanation

    Correct answer: C

    An online course team requires that the live lesson can be switched on only once the screen-recording software has been started, and the recording does not have to finish first. Which logical relationship links “start recording” and “start the live broadcast”?

    First see what is constrained: the start of the live broadcast. Then see what it depends on: the start of the recording. Only once the recording has started can the broadcast start. The stem specifically says the recording does not have to finish first, which rules out FS. Depending on a start and constraining a start gives start-to-start (SS). SS fixes only the order of the two starts. It does not require the predecessor to be finished, and it does not mean the two start at the same time. The answer is C.

    Why the other options are wrong

    • A. FS would require the recording to finish before the broadcast starts. The recording runs alongside the broadcast, and the stem says it need not finish first.
    • B. FF constrains when the two finish. The stem is about starting the recording and switching on the broadcast, which are starts, so it does not fit.
    • D. SF depends on the start of the predecessor and constrains the finish of the successor. What the stem constrains is the start of the broadcast, not its finish.

    Key takeaway “It can start only after the other has started” is SS. The predecessor does not have to be finished.

    Variation If it said “the broadcast can end only after the recording has started”, the constrained end would be the finish of the broadcast, which is SF. If it said “the broadcast can start only after the recording ends”, that is FS.

  93. Question 93

    While reviewing the schedule, a project manager finds that the team is behind. The cause is that a core module did not meet the acceptance criteria, and several members each investigated and fixed it independently, doing a great deal of duplicated work. What could the project manager have done in advance to avoid this waste?

    Show answer and explanation

    Correct answer: D

    The team is behind because a core module failed acceptance and several members each investigated and fixed it on their own, duplicating work. The question is what the project manager could have done in advance to avoid this waste.

    The waste comes from the lack of a single record and division of work: nobody knew that others were already working on the same problem. The issue log records and monitors issues that have occurred, including the description, the owner and the resolution date. If members are required to log an issue as soon as they find it and an owner is assigned, one look at the log shows that someone is already handling it, and the duplicated work disappears. The answer is D.

    Why the other options are wrong

    • A. The risk management plan sets out how risk management is carried out, and the response information for specific risks is recorded in the risk register, which deals with uncertain events that have not yet occurred. This defect had already occurred, so it should have been logged as an issue with a named owner. Adding a response plan does not settle who is responsible for handling it.
    • B. Having everyone work out the best fix separately is still everyone working on their own, so the duplication remains; choosing a solution is also a step that comes after logging the issue and assigning the work.
    • C. A change request is for modifying approved content. Not every defect needs one, and it is less direct than simply assigning an owner.

    Key takeaway Log an issue in the issue log and assign an owner as soon as it occurs; this is the most direct way to avoid duplicated handling.

    Variation If issues in the log stay open for a long time, add closure criteria and due dates and resume regular maintenance of the log.

  94. Question 94

    What is the core purpose of the Monitor and Control Scope process?

    Show answer and explanation

    Correct answer: D

    The question asks for the core purpose of the Monitor and Control Scope process.

    Monitor and Control Scope monitors the status of project and product scope, manages changes to the scope baseline, and measures the quality of deliverables so that scope and quality stay aligned with the scope baseline. In practice, every change is assessed first and then approved or rejected, and the baseline is updated only after approval. Keeping changes under control and the baseline valid is the core purpose. Focus on the word “controlled”: options that say “prevent”, “fold in immediately” or “redo for every phase” are extremes that skip the chain of assess, approve, then update. The answer is D.

    Why the other options are wrong

    • A. Monitor and Control Scope does not forbid change. Change is normal; what matters is that it is assessed and approved rather than blocked from being raised.
    • B. Folding in new requests whenever they appear is exactly what scope creep looks like, and the baseline is quietly eroded.
    • C. The baseline is not redone for every phase. Only approved changes cause the baseline to be updated.

    Key takeaway The purpose of Monitor and Control Scope is not to shut change out but to keep change under control and the baseline valid.

    Variation If the question asks for the main outputs of Monitor and Control Scope, choose verified deliverables, change requests and similar items. If it asks who formally accepts the verified deliverables, move to Validate Scope; do not mix up the two processes.

  95. Question 95

    A customer representative complains of not receiving an important deliverable that was agreed in the plan. The responsible team member says the representative was already told by email that delivery would be delayed. What should the project manager do to keep this from happening again?

    Show answer and explanation

    Correct answer: B

    A customer representative complains of not receiving an important deliverable agreed in the plan, while the team member says an email already announced the delay. The question is how to keep this from happening again.

    Email is push communication. It proves that information was sent, not that it was received or understood. The representative claims not to have known, so the communication loop was never closed. To prevent a repeat, confirm that the stakeholder has received and understood the delay, and resend or change the method when confirmation is missing. The answer is B.

    Why the other options are wrong

    • A. Whether members may contact the customer directly is not the issue. Whoever sends the message, the receiver's awareness must be confirmed, and banning direct contact does not solve that.
    • C. Delivering a partial product changes what is delivered. It has nothing to do with the communication problem of announcing the delay, and the customer still does not know which part will be delivered when.
    • D. Whether a member or the project manager sends the notice, receipt and correct understanding still have to be confirmed. Changing the sender does not close the loop and does not prevent the problem at its source.

    Key takeaway Sent is not delivered. For critical information or communication that requires a closed loop, confirm that the other party knows. The communications management plan should specify how receipt will be confirmed when needed, especially for push communication.

    Variation If the member explained the delay in person, still verify through the listener's paraphrase or explicit confirmation that it was received and understood; telling someone face to face does not by itself guarantee this will not happen again. If the email went to a whole customer department, still confirm that the specific person responsible knows.

  96. Question 96

    A company's project manager is leading a ten-month pharmaceutical cold chain transport project, and the sponsor cares most about cost and schedule. For the first half year everything went according to the project management plan, but this week the project manager finds that cost is already over budget. What should the project manager use to report project status to the sponsor?

    Show answer and explanation

    Correct answer: A

    On a pharmaceutical cold chain project, the sponsor cares most about cost and schedule. The first half year went as planned, but this week a cost overrun is found. The question asks what to use to report project status to the sponsor.

    A work performance report presents compiled work performance information in written or electronic form so that readers can decide, act or take note of an issue; status reports and progress reports are its typical forms. The cost overrun is a status the sponsor needs to know about and should be written into a work performance report. The answer is A.

    Why the other options are wrong

    • B. The cost baseline is the approved budget and the yardstick for comparing performance. It is not a document for reporting status.
    • C. The issue log is used to record issues and track their handling. You can log this overrun in it, but it is not the vehicle for presenting overall status to the sponsor.
    • D. An issue resolution meeting is a communication activity for handling a problem, not a report presenting project status.

    Key takeaway The vehicle for reporting project status is the work performance report, and its purpose is to prompt decisions and action.

    Variation If the question asked “after a cost overrun, what do you use to measure the deviation,” the answer is to compare actual cost with the cost baseline; if it asked how to handle the overrun, first analyze the cause and then propose alternatives.

  97. Question 97

    A newly assigned project manager leads an exterior design project for a home appliance maker. The designers are located in different cities. Communication over video and text often causes misunderstandings because people do not express themselves clearly, the team lacks a good collaborative atmosphere, and design quality is suffering. The company has agreed to bring members together in one location for short periods at critical stages. What should the project manager do?

    Show answer and explanation

    Correct answer: C

    A newly assigned project manager leads an exterior design project whose designers are in different cities. Video and text communication keeps causing misunderstandings, the collaborative atmosphere is poor, and quality is affected. The company allows short-term gatherings at critical stages.

    Colocation places the main team members in the same physical location to strengthen the team’s ability to perform, and it can be used only at strategically important times. The root of the problem is dispersed locations combined with poor online communication, and the company allows members to gather at critical stages. Bringing members together temporarily, so that face-to-face conversation clears up misunderstandings and builds a sense of team, is the most direct fix. The answer is C.

    Why the other options are wrong

    • A. Blaming and criticizing individuals does not address the root cause. The communication barrier comes from dispersed locations and the way people communicate online, and criticism will not improve the collaborative atmosphere.
    • B. The problem is within the project manager’s own remit and can be addressed directly with team building and colocation. Passing it to the sponsor is not proactive and may not help.
    • D. The misunderstandings arise from video and text communication in the first place. Using the same channels more often does not fix the root problem and does not build a sense of team.

    Key takeaway When online communication is causing misunderstandings and conditions allow it, use temporary colocation so that face-to-face communication removes the misunderstandings and builds team spirit.

    Variation If the stem said the company would not allow any form of colocation, the answer would change to building a collaboration platform and adding video meetings and one-on-one conversations. If the misunderstandings came from cultural differences, discuss them openly and agree shared working conventions.

  98. Question 98

    A logistics company’s route-planning project is in the Executing focus area, and deliveries have been steady for several months. The project manager notices that team members trust one another, the atmosphere is good, disagreements are quickly worked out by the team itself, and overall performance has stayed high. According to the Tuckman ladder, which stage is the team in?

    Show answer and explanation

    Correct answer: B

    A route-planning project has been running for some time with steady deliveries. Members trust one another, the atmosphere is good, the team resolves disagreements on its own, and performance stays high. The question asks which stage of the Tuckman ladder the team is in.

    PMBOK 8 describes the Performing stage this way: “Teams that reach the performing stage function as a well-organized unit. They are interdependent and work through issues smoothly and effectively.” All three signals in the stem fit: trust is established, disagreements are resolved without outside intervention, and performance stays high. In the Norming stage members are only beginning to build trust and have not yet reached sustained high performance. The answer is B.

    Why the other options are wrong

    • A. In the Norming stage members begin to work together, adjust their habits and gradually build trust, so they are still settling in. The stem stresses months of steady delivery and disagreements resolved by the team itself, which is beyond this stage.
    • C. The typical picture of the Storming stage is disagreement, unwillingness to accept different views and a counterproductive atmosphere. The stem’s good atmosphere and quickly resolved disagreements are the opposite.
    • D. In the Forming stage members have just met and tend to be independent and not as open, so there is little high trust and certainly no sustained high performance.

    Key takeaway Trust plus high performance with disagreements resolved by the team itself points to the Performing stage. The Norming stage is only the beginning of trust.

    Variation If the stem said the team had just started adjusting to one another and trust was gradually building, the answer would be the Norming stage. If it said deliverables were complete and members were leaving, it would be the Adjourning stage.

    Reference The Tuckman Ladder · Lesson 1: The Tuckman Ladder: Five Stages and How to Lead in Each

  99. Question 99

    A group's settlement-system project is in late execution. The CFO discovers that an important requirement was omitted, and if the system is delivered to the current technical specifications it will be unusable; the CFO asks the project manager to start the change immediately. The change is major, but starting immediately could still meet the original deadline. What should the project manager do FIRST?

    Show answer and explanation

    Correct answer: B

    In late execution of a settlement-system project, the CFO finds that an important requirement was omitted and the system would be unusable if delivered to the current specifications, and asks the project manager to start the change at once. The change is major, but starting immediately could still meet the deadline. What should the project manager do first?

    The omitted requirement has to be added before delivery, and it affects scope, schedule and cost at the same time, so it is certainly a change. Whoever raises it and however urgent it is, the request is handled according to the process set out in the change management plan: record, assess and submit for approval. Urgency is not a reason to bypass the process. The answer is B.

    Why the other options are wrong

    • A. As a stakeholder, the CFO can raise a change request. The point is to follow the process, not to question the CFO's authority first.
    • C. Whether the project will be delayed can be known only after assessment; the stem even says it may still meet the original deadline. Drawing a conclusion now is premature, and it does not move the change forward.
    • D. Estimating, planning and carrying out the work at once to avoid losing time implements before approval, violates change control, and may produce work that is not approved.

    Key takeaway An omitted requirement is a typical change; first handle it through the process set out in the change management plan, rather than questioning authority or starting work first.

    Variation If the change is urgent, approval can be speeded up within the emergency process the plan provides, but it must still be recorded and approved; work cannot start before approval.

    Reference Change Control · Lesson 4: Common Change Question Patterns: Find the Step, Decide Whether to Use Change Control, Assess Before Acting

  100. Question 100

    A project manager has just been appointed to take over a project already in progress. The project will draw on a subsidiary of the company to develop a new billing system, and the developers needed come from that subsidiary. The project manager asked the subsidiary's head to confirm that the development team would be available, and the answer was a clear refusal. What should the project manager do FIRST?

    Show answer and explanation

    Correct answer: D

    A newly appointed project manager takes over a project in progress. The project will use the developers of a subsidiary to build a new billing system, and the subsidiary's head clearly refuses to confirm that the team will be available. The question asks what to do first.

    The resource management plan describes how resources are identified, acquired, allocated, managed and released, and it is the basis for handling resource problems. The project manager has just taken over and the availability of resources has become a problem, so first consult the plan's guidance on acquiring resources, roles and responsibilities and related arrangements to see how things were originally arranged, and then decide whether to negotiate, escalate or change under the project's governance. Establishing the facts comes before any action. The answer is D.

    Why the other options are wrong

    • A. Re-sequencing the schedule before the resource arrangements and agreements have been checked is reacting to a result. The cause of the problem has not been confirmed, and notifying stakeholders is premature.
    • B. Buying externally is a later option when internal resources cannot be found. Asking the sponsor to buy outside services without checking the plan adds cost and skips the existing agreements.
    • C. A change request should be raised only after the impact is clear and what has to change is decided. Submitting one without even checking what was agreed is premature.

    Key takeaway When acquiring resources meets an obstacle, consult the resource management plan first and then decide whether to negotiate, escalate or change.

    Variation If the plan says the subsidiary's people are guaranteed by an agreement, the next step is to negotiate with the subsidiary's head on the basis of the agreement and escalate to the sponsor if necessary.

    Reference Estimate Resources and Acquire Resources · Lesson 3: Outputs of Acquire Resources: Assignments, Team Assignments, Resource Calendars and Handling Resource Changes

  101. Question 101

    At the latest project status meeting, a stakeholder who has long been in the stakeholder register says he did not receive the root cause analysis of an issue discussed at the meeting. The project manager confirms that the stakeholder's work requires this analysis and finds that the person is not on the report distribution list. What should the project manager do first?

    Show answer and explanation

    Correct answer: C

    At a status meeting, a stakeholder already in the stakeholder register says he did not receive the root cause analysis of an issue. The project manager confirms that the stakeholder's work requires the analysis and finds he is not on the report distribution list. What should the project manager do “first”?

    The communications management plan specifies how information is delivered, when and by whom, and also who receives it. He is in the register but not on the distribution list, which means the plan did not cover his needs. This is a communication problem, so first update the communications management plan to put him on the distribution list, then send him the material that was missed. The answer is C.

    Why the other options are wrong

    • A. The stem does not involve risk. The problem is the distribution list, and the risk register cannot help.
    • B. Whether a change request is needed is set by the change management plan. Adding someone who needs the material to the distribution list only adjusts communication arrangements and does not touch the scope, schedule or cost baselines, so it is normally updated and recorded as the plan authorizes, without first submitting a change request; only if the communications management plan is under configuration control should it be handled under the change management plan.
    • D. He has long been in the register. What is missing is a communication arrangement, so the register does not need updating.

    Key takeaway If someone who needs the material is missing from the distribution list, first update the communications management plan, then send the material that was missed.

    Variation If he were not in the register at all, you would first register and analyze him, then check and update the stakeholder engagement and communications management plans. If he were on the distribution list and still did not receive the material, you would look into an execution problem.

  102. Question 102

    A logistics-system upgrade project has moved from the critical path method to the critical chain method for its schedule. The project manager finds that every critical-chain activity estimate contains its own safety time, yet the plan has no project buffer to deal with uncertainty. What should the project manager do?

    Show answer and explanation

    Correct answer: D

    The project has moved from the critical path method to the critical chain method for its schedule. Every critical-chain activity estimate contains its own safety time, but the plan has no project buffer.

    The critical chain method calls for activity durations that contain no safety margin; the margin is taken out and pooled into buffers that protect the finish date, with a project buffer at the end of the critical chain. (A feeding buffer, placed where a non-critical chain joins the critical chain, is a common exam term in CCPM.) The buffer replaces task-level safety time; it is not added on top of it. PMBOK 8 stresses that the critical chain buffer is in lieu of task-level or sprint-level buffers, and not in addition to them, which is why the answer is D and not A. The answer is D.

    Why the other options are wrong

    • A. The buffer replaces task-level safety time; it is not an extra layer on top. Doing both counts the safety time twice and stretches the plan.
    • B. With no buffer, there is no protection against resource limits and uncertainty, and any slip hits the finish date directly.
    • C. A small buffer after every activity is still scattered safety time, usable only by each owner. That is the opposite of a pooled buffer.

    Key takeaway Safety margin is taken out of the activities and pooled into a buffer; the buffer replaces task-level safety time rather than adding to it.

    Variation If 4 sequential activities were originally estimated at 7 days each (each including 2 days of safety time), take the safety out and schedule each at 5 days, 20 days in all; then add a 4-day project buffer according to the organization's buffer rule (an example only, not a fixed ratio), for a total of 24 days, tighter than the original 28.

  103. Question 103

    A residential complex under construction has reached the main structure stage, and the owner asks that the electrical and mechanical installation work package be completed earlier. The specialist subcontractor says that staff and materials are not yet in place and that finishing earlier would cost extra. The project manager has already confirmed with the subcontractor the effect of earlier completion on schedule and cost. What should the project manager do NEXT?

    Show answer and explanation

    Correct answer: A

    A residential complex is at the main structure stage. The owner asks to move up completion of the electrical and mechanical installation work package, and the subcontractor says staff and materials are not ready and that finishing early will cost extra. What should the project manager do first?

    Finishing earlier at additional cost changes both schedule and cost, which means it changes the baselines. Any request that affects a baseline must first have its overall impact assessed, then be submitted as a change request under the change management plan and implemented only after approval. Of the four options, only A follows the process; the other three all go around it and handle the matter independently. The answer is A.

    Why the other options are wrong

    • B. Merely making a note in the risk register and a log and watching the budget leaves the owner's request and the extra cost outside the change control process, with no one assessing or approving them. In addition, the owner's request is not an uncertain event and should not be treated as a risk.
    • C. The issue is earlier completion and extra cost, not a scope change, so adjusting scope on one's own has no basis; an adjustment to the scope baseline also needs approval.
    • D. Additional funds can be secured only after the change is approved. Asking senior management for money first and rewriting the budget first skips assessment and approval.

    Key takeaway A request that affects the schedule and cost baselines is handled as a change request, not by simply changing the budget.

    Variation If the owner's request affects no baseline and falls within authority, the project manager can handle it as the plan provides; even if the subcontractor is willing to finish early at no charge, it should be recorded and assessed before being carried out.

    Reference Change Control · Lesson 2: The Five-Step Change Handling Process

  104. Question 104

    A team is using a lean approach to develop an online collaborative document tool. To improve efficiency, it cancels routine meetings that produce nothing, stops writing documents no one reads, and does only the work that is needed now. Which lean principle does this reflect?

    Show answer and explanation

    Correct answer: C

    A team using a lean approach to develop an online collaborative document tool cancels routine meetings that produce nothing and unread documents, and does only the work needed now. The question asks which lean principle this reflects.

    PMBOK 8 defines waste as activities that consume resources and/or time without adding value. Meetings that produce nothing and documents no one reads add no customer value, so they are waste. Removing them and doing only the necessary work is eliminating waste. There are two points of judgment here: the stem says nothing about being “faster” or about “quality”; it only says that activities that add no value are removed. The answer is C.

    Why the other options are wrong

    • A. Deliver as fast as possible stresses shortening the time from request to delivery. The stem does not mention delivery speed.
    • B. See the whole stresses optimizing the whole value stream from a global rather than a local view. The stem is about removing activities that add no value.
    • D. Build quality in stresses putting quality into the development process. It has nothing to do with cancelling meetings and documents.

    Key takeaway Removing activities that add no value is lean's “eliminate waste”.

    Variation If the stem said “work does not move to the next step if it fails review, so defects are stopped inside the process”, that corresponds to build quality in. If it said “shorten the cycle from request to going live”, that corresponds to deliver as fast as possible.

  105. Question 105

    An electric-vehicle charger development project has entered the executing phase, and the customer is especially concerned about the delivery date. A new team member suggested a way to raise the team's efficiency. It was approved and put into practice, and the team's efficiency did go up. Which document should the project manager update afterward?

    Show answer and explanation

    Correct answer: B

    During execution, an efficiency practice proposed by a new member has been approved and implemented, and the team's efficiency has risen. The question asks which document should be updated next.

    Any practice that improves performance on this project or on future projects should be recorded promptly in the lessons learned register. This practice has proved effective in use, and both this team and later projects should be able to draw on it, so it goes in the register. Successful experience is recorded just like failures; the register is not only for failures. The answer is B.

    Why the other options are wrong

    • A. The schedule management plan states how the schedule is to be managed. The stem does not say the rules for managing the schedule change, and it is not the place to record experience.
    • C. The change management plan sets out the change control procedure. The stem does not involve any adjustment to the process; this practice is an approved improvement.
    • D. The stem does not indicate a new risk or any change to an existing risk's probability, impact or response, so it provides no basis for updating the risk register.

    Key takeaway A practice that helps raise performance should be recorded promptly in the lessons learned register; successful experience is recorded too.

    Variation If the practice had not worked and had caused rework, the answer would still be the lessons learned register, because failures are recorded too. If the practice required changing a baseline, change control would have to come first.

  106. Question 106

    A project manager on a logistics system project is developing the schedule, and the schedule baseline has not yet been approved. While reviewing the schedule network diagram, the project manager finds that the dependency between “user training” and “system go-live” was marked wrongly. What should the project manager do?

    Show answer and explanation

    Correct answer: A

    A logistics system project is developing its schedule and the schedule baseline has not been approved. In reviewing the network diagram, the project manager finds the dependency between “user training” and “system go-live” is marked wrongly. What should the project manager do?

    The schedule network diagram is a product of the determine sequence step, and a wrong dependency will affect every date and the critical path derived from it. The baseline has not yet been approved, so the network diagram and the schedule are still drafts. The project manager should correct the network diagram directly and update the schedule accordingly. Change control applies to approved baselines, which is not the case here, and there is no need to ask anyone else for approval. The answer is A.

    Why the other options are wrong

    • B. Change requests and the change control board handle changes to approved baselines. Finding an error in a draft and sending it through the change procedure makes a simple problem complicated.
    • C. Using schedule reserve to absorb an error that could simply be corrected means carrying on with wrong logic, and the critical path and dates will be unreliable.
    • D. Dependencies are part of the project manager's and team's work when they determine sequence. The sponsor does not need to confirm them first, and treating a correction as a decision to escalate is also wrong.

    Key takeaway If an error in the network diagram is found before the baseline is approved, correct it directly and update the schedule. Change control applies after approval.

    Variation If the schedule baseline had already been approved, a wrongly marked dependency would require a change request, and the baseline would be amended only after change control.

  107. Question 107

    The project manager outsources a park landscaping job and gives the supplier construction drawings and a bill of quantities. During construction the supplier says it underestimated the quantities at the start, so its costs have run over, and asks the project manager to make up the difference. The contract has no cost-sharing or price-adjustment clause, and the project manager refuses. Which contract did the two parties most likely sign?

    Show answer and explanation

    Correct answer: B

    The project is in construction with drawings and a quantity list in place, and the supplier asks for a higher price because of its own estimating error. The question asks which contract type this corresponds to.

    The signal: the supplier says it underestimated the quantities and asks for the difference, and the project manager refuses. That means the price does not change because of the seller’s estimating error, and the cost overrun is the seller’s own to bear. This is a firm fixed-price contract. Under a fixed price incentive fee contract the contract must have a sharing ratio, and before the ceiling price the buyer shares by ratio the part above target cost, which does not fit “no cost-sharing clause at all”. Under time and materials and cost plus incentive fee contracts the buyer pays for the added cost, so a refusal would have no contractual basis. The answer is B.

    Why the other options are wrong

    • A. A time-and-materials contract settles on actual hours and materials, so the added work has to be paid for anyway and would not be refused.
    • C. Under a cost plus incentive fee contract the buyer reimburses actual cost and has to pay more when cost rises, so refusing to make up the difference would have no contractual basis.
    • D. A fixed price incentive fee contract has a sharing ratio above target cost, so the buyer shares the part above target cost by ratio and would not refuse it all. Only past the point of total assumption (where the price reaches the ceiling) does the whole overrun fall on the seller.

    Key takeaway Refusing a price increase caused by the seller’s own estimating error corresponds to a firm fixed-price contract.

    Variation If the contract allowed the price to be adjusted for rising material prices, it would be a fixed price with economic price adjustment contract and the seller’s request would have a basis; if the added work came from the buyer changing the scope, the seller could seek compensation through the change procedure.

Practice test or full mock exam: what is the difference?

  • Free practice tests: 8 tests, the first with 120 questions and the others about 107 each, drawn from the 1,000 free questions (you may have met some while practicing by chapter), no login. Good for a quick self-check and for finding your weak domain.
  • Full mock exams: 180 questions each, separate from the practice bank (none of them appear there), timed in 3 sittings like the real exam. Use them to judge whether you are ready. See the full mock exams.

Free PMP practice test: common questions

Is this PMP practice test really free?

Yes. There is no account and no email wall. All 107 questions and the full explanation of every answer are free, and your progress is saved in your browser.

How were the 107 questions chosen?

They come from the 1,000 free questions: 28 People, 49 Process and 30 Business Environment questions, covering 24 of the 26 tasks of the Exam Content Outline, with single-answer and multiple-answer questions. There are 8 free tests and no question appears in more than one of them. Once a domain runs out of free questions a test is a little shorter, and the count shown is the real one.

How long does the test take?

Timed mode follows the real exam's pace of 80 seconds a question, so 107 questions get 143 minutes. You can also choose untimed practice and take as long as you like.

How are multiple-answer questions scored?

A multiple-answer question counts as correct only when you select every correct option and nothing else. There is no partial credit, and an unanswered question counts as wrong.

Are these real PMP exam questions?

No. PMI does not release exam questions. Every question here is original, written to the Exam Content Outline, to practice the question styles and the reasoning.

What should I do after the test?

Take another of the free tests, keep practicing by chapter in the 2,876-question bank, or take one of the 10 full mock exams of 180 questions. Your score here is a practice signal, not a prediction of the exam result.

To study first, read the study guide; for the whole bank, practice by chapter.