Free PMP Practice Test 4: 107 Questions with Explanations
107 PMP sample questions, test 4 of 8 with no question repeated from the other tests: 28 People, 49 Process and 30 Business Environment, covering 24 of the 26 tasks of the Exam Content Outline. Timed mode gives 80 seconds a question, 143 minutes in all; or practice untimed. Every question has a full explanation: why the answer is right and what is wrong with each other option. When you submit you get your total score, your accuracy in each of the three domains and a readiness check.
Updated 2026-11-22 · aligned to the current Exam Content Outline and PMBOK Guide 8th Edition
Ready to start?
Your answers are saved in this browser, so you can refresh or come back later. No account needed.
You can read every question below before you start; the answer options unlock when you press Start.
- Question 1
The sponsor of a chain-supermarket inventory system upgrade reports that a key stakeholder complains that the performance variances in the project manager's reports give the impression that the project is out of control. The project manager has always provided status according to the agreed communications management plan, and this stakeholder rarely attends the status reporting meetings. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
The sponsor relays that a key stakeholder complains that the performance variances make the project look out of control. The project manager has always given status according to plan, and this stakeholder rarely attends the status meetings. The question asks what to do first.
Monitor Communications confirms whether information needs are really met, not merely whether information was sent as planned. This stakeholder seldom attends, so the current channel may not suit them, and the plan itself needs checking. The project manager should first assess the stakeholder's communication needs, identify the gaps against the current plan, and adjust the communications management plan if needed, after which the project status can be clarified effectively. The answer is D.
Why the other options are wrong
- A. The stem has not shown that the schedule really is behind or analyzed which activities could run in parallel. Fast-tracking rashly adds rework and risk and does nothing about the mismatch between needs and channel.
- B. The stakeholder may not appear in a resource breakdown structure, and a complaint is no reason to have someone replaced. It is not an active attempt to solve the communication problem.
- C. Proving to the sponsor that communications went out does not address the stakeholder's unmet need. It only defends the project manager.
Key takeaway If someone is dissatisfied even though communication followed the plan, assess their needs and find the gaps first, and adjust the plan if necessary.
Variation If he attends every meeting yet still says he did not receive it, check the content and format of the information. If he is a newly added stakeholder, update the stakeholder register and analyze his needs together, then update the relevant plans.
- Question 2
The product owner of a software team has to put the user stories in the backlog into order. Which factors should be the main ones considered when ordering?
Show answer and explanation
Correct answer: D
The product owner has to put the user stories in the backlog into order. The question asks which factors should be the main ones to consider when ordering.
The purpose of ordering is to deliver first the value that stakeholders care about most. As a common exam practice, ordering looks at three things: value (how much business value it brings), cost (how much it takes to build) and risk (how uncertain it is and whether it needs early attention). The ordering basis in the PMBOK 8 text is value, dependencies, and technical or operational risk, and in practice cost can also be weighed. The answer is D.
Why the other options are wrong
- A. Size can help measure effort and convenience may reflect customer value, but this group leaves out risk and dependencies and is not the main basis for ordering.
- B. Difficulty and duration can help with economic trade-offs, but this group lacks value, dependencies and risk, and team preference should not drive the order. Ordering is aimed at value, not at ease of work or preference.
- C. Schedule and staff availability affect how much can be selected into one iteration, not the main factors for ordering the user stories themselves.
Key takeaway Backlog ordering looks at three things: value, cost and risk.
Variation If the question asked for a method to quickly separate “must have” from “could have”, the answer would be MoSCoW; if it asked to tell basic expectations from delighters, it would be Kano analysis.
- Question 3
A pharmaceutical company starts a project to develop a cold-chain delivery service. The project management plan has been developed, approved and released to stakeholders. What should the project manager do NEXT?
Show answer and explanation
Correct answer: A
On the cold-chain delivery development project, the project management plan has been developed, approved and released. What is the project manager's next step after plan approval?
Once the plan is approved and released, the project moves from planning into execution: leading and performing the work defined in the plan, executing the work packages as planned and producing deliverables, which is exactly Manage Project Execution. Determining deliverable and timing information, estimating durations and resources, and redeveloping a sub-plan without new information or an identified change is also not the next step here. The signal words in the stem are “developed, approved and released,” which place the moment after planning has ended. In practice a predictive project usually holds a kick-off meeting to obtain commitment before concentrated work begins (common exam practice), but that option is not offered here, so choose executing the work packages as planned. The answer is A.
Why the other options are wrong
- B. Determining information about deliverables, activities and timing is done when developing the plan, and it should be completed before approval.
- C. Estimating activity durations and listing the resources required also belong to planning, and they are no longer the next step once the plan is approved.
- D. The stem provides no new information or identified change requiring the communications approach to be revised, so arbitrarily redeveloping that plan is not the next step. If new information emerges later, planning can still be updated iteratively.
Key takeaway After the plan is approved and released, the next step is to execute the work packages as planned.
Variation If the project charter has only just been approved, the next step is to develop the project management plan, not to execute. If the plan is approved and the customer then asks for added requirements, go through change control first.
- Question 4
A key equipment replacement project at a manufacturer is under way. Because of a sudden tightening of financing conditions, the funds originally earmarked for the project do not arrive, and the money left is not enough to complete the project. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
The project is in execution. Tightened financing means the funds originally planned do not arrive, and the remaining money is not enough to finish. What should be done “first” after discovering the shortfall?
The key qualifier is “first”. When funds and expenditures do not match, the precondition for balancing is to find out how big the gap is, which work it affects and what options exist. So the first step is to assess the impact of the funding gap and evaluate the alternatives, and only then decide whether to adjust scope, reschedule or seek funds. The answer is D.
Why the other options are wrong
- A. Reducing scope may be one of the final options, but cutting directly without assessment may cut critical value. It is acting before analyzing.
- B. Suspending to wait for conditions to improve is passive. There is no basis for believing the funds will come back, and it delays the project and adds fixed costs.
- C. Asking the sponsor for money may be a later action, but asking for help when the size of the gap and the other options are unknown means you cannot say how much is needed or why.
Key takeaway When funds do not arrive, assess the impact and the alternatives first, then choose an action.
Variation If the assessment confirms that the gap is only a timing mismatch, adjust the schedule; if the gap is permanent, submit a change request to reduce scope or request new funds, approved by those with authority.
- Question 5
A project manager has four newly identified uncertain events. Threat A: probability 70%, and if it occurs cost increases by $50,000. Threat B: probability 20%, cost increases by $250,000. Opportunity A: probability 50%, can save $90,000. Opportunity B: probability 10%, can save $400,000. Using expected monetary value analysis and ranking by the absolute value of EMV (the size of the expected effect), which has the greatest effect?
Show answer and explanation
Correct answer: C
At the risk analysis stage there are two threats and two opportunities. The question asks which has the greatest effect when ranked by the absolute value of EMV using expected monetary value analysis.
The stem requires “expected monetary value analysis”, so calculate the EMV of each item: probability times impact, with threats negative and opportunities positive. The question explicitly ranks by absolute value (the size of the expected effect), not by probability or amount alone. Ranking threats and opportunities together by absolute value is common exam practice, but in practice threats and opportunities are usually ranked and treated separately. Among the four, Threat B has the greatest expected effect. The answer is C.
- Threat A: −0.7 × 50 = −$35,000
- Threat B: −0.2 × 250 = −$50,000
- Opportunity A: +0.5 × 90 = +$45,000
- Opportunity B: +0.1 × 400 = +$40,000
- Compare absolute values: 50 > 45 > 40 > 35, so the largest is Threat B
Why the other options are wrong
- A. Threat A has the highest probability (70%) but a small amount, so its EMV is only −$35,000, less than Threat B's $50,000.
- B. Opportunity B has the largest single effect ($400,000) but a probability of only 10%, so its EMV is only +$40,000, third in rank.
- D. Opportunity A's EMV is +$45,000, less than Threat B's $50,000.
Key takeaway Calculate EMV before comparing. The highest probability or the largest amount does not necessarily give the largest EMV.
Variation If you look only at threats, it is still Threat B; if only at opportunities, it is Opportunity A (45 is greater than 40). If the question asked for the total contingency reserve for threats, add up only the threats: 35 + 50 = $85,000.
- Question 6
A software project has passed all its quality tests and meets the established quality standards, but the client's representative is still not satisfied. What should the project manager do?
Show answer and explanation
Correct answer: A
The software has passed all quality tests and meets the established standards, but the client's representative is still not satisfied. The question asks what the project manager should do; the key is that there may be a gap between the established standards and the client's expectations.
PMBOK 8 says quality should satisfy customers' and stakeholders' stated or implied needs as a matter of course. Passing the tests shows only that the work meets the “written-down standard”. If the client is still unhappy, it may mean that some implied need was never written into the standard. So first verify the gap between the client's expectations and the quality standards, find out where it lies, and then decide whether to adjust the standards, add metrics or improve the way of working. You can think of the process in two steps: first find the gap against the client's real expectations; and if a requirement, acceptance criterion or baseline really must change, assess the impact and submit a change request, and once it is approved update the quality management plan with measurable quality metrics. Otherwise the next test will “pass” in the same way and the client will be just as unhappy. The answer is A.
Why the other options are wrong
- B. Showing the test report proves only that the work was done to the standard. It does not answer the client's dissatisfaction and does not find the gap.
- C. Reworking everything without knowing which expectation is unmet wastes resources and may not address the client's real concern.
- D. Asking for sign-off before discussing the dissatisfaction avoids the problem. The basis for acceptance is still unclear, and it may damage the client relationship.
Key takeaway Meeting the standard does not mean the client is satisfied. Verify the gap between expectations and the standard first.
Variation If the stem said that a feature the client explicitly asked for, already written into the approved requirements or acceptance criteria, was not built, that would be a failure to meet the acceptance criteria and you would rework it to the standard. If the request was never part of the approved scope, assess it and use change control. This question does not state the specific source of the dissatisfaction, so first verify the gap.
- Question 7
During a logistics platform project, a stakeholder from the operations department demands a new feature outside the planned scope and says that if it is not put into the current iteration, the issue will be escalated to senior management. What should the agile coach do?
Show answer and explanation
Correct answer: C
During a logistics platform project, an operations stakeholder demands a feature outside the planned scope and says that if it is not put into the current iteration, the issue will go to senior management. What should the agile coach do?
A new requirement goes into the product backlog, and the product owner and the Developers reassess its priority by value. This responds to change while keeping the iteration stable. The coach should help bring that assessment about, without being led by the threat and without pushing the problem to the stakeholder or to senior management. The product owner is responsible for ordering the product backlog and listens to the Developers on effort, dependencies and risk, so value, not pressure, decides the order. The answer is C.
Why the other options are wrong
- A. Whether to include the feature, and how much of it, is for the product owner to decide after hearing the team and assessing value. A coach agreeing a partial implementation alone oversteps, and it may not meet the stakeholder's need.
- B. Requiring the stakeholder to get senior approval first pushes the responsibility back, causes delay, and departs from the agile practice of ordering by value and embracing change.
- D. This is not the most direct way. Ordering the backlog is the product owner's responsibility, with input from the team, and there is no need to escalate for a ruling first.
Key takeaway For a new requirement, first reorder priorities with the product owner and the team; do not be led by pressure or escalation.
Variation If the assessment shows the new feature has very high value, it will usually go into a later iteration; if it is truly necessary and does not endanger the iteration goal, the Developers and the product owner may negotiate adjusting the current iteration's scope.
Reference Release Planning and Prioritization · Lesson 3: Prioritization: Value, Cost, Risk and Common Methods
- Question 8
A team is using Scrum to build a community group-buying mini-app, and the current Sprint is on its third day. The operations director proposes a new coupon feature, and the Product Owner thinks it is very valuable. What is the most appropriate action now?
Show answer and explanation
Correct answer: B
The project uses Scrum, the Sprint is on its third day, the operations director proposes a new coupon feature and the Product Owner thinks it is valuable. How should this change be handled?
A new requirement that appears during a Sprint cannot be pushed straight into the Sprint in progress. It first enters the Product Backlog and is reordered with the other items, and a later Sprint Planning decides which Sprint takes it. The timebox of the current Sprint stays as it is. If the Sprint scope needs adjusting, the Developers and the Product Owner negotiate it around the Sprint Goal, and the Product Owner cannot simply push items in. The answer is B.
Why the other options are wrong
- A. Pushing the new item straight into the Sprint Backlog and extending the Sprint both breaks the fixed timebox and bypasses the mechanism by which the Developers and the Product Owner negotiate scope around the Sprint Goal.
- C. Stopping the Sprint for one new idea breaks the team's rhythm. Only the Product Owner can cancel a Sprint, and only when the Sprint Goal becomes obsolete, which is not the case here.
- D. Scrum embraces change, so a valuable new idea should be accepted. It goes into the Product Backlog rather than the current Sprint. “Never consider it” is wrong.
Key takeaway A change goes first into the Product Backlog to be reordered. It is not pushed into the Sprint in progress, and the Sprint is not extended.
Variation Only if the stem said the new requirement would make the current Sprint Goal pointless might the Product Owner decide to cancel the Sprint. If a new requirement is urgent and valuable, it still enters the Product Backlog first, and the Product Owner orders it by value, risk, dependencies and similar factors. If it does not affect the current Sprint Goal, the Developers and the Product Owner can negotiate whether to adjust the current Sprint scope.
- Question 9
On PMLyceum's warehouse management system project, a core developer habitually takes on most of the tasks personally. He is about to be reassigned away from the project, which makes the project fragile. What should the project manager do?
Show answer and explanation
Correct answer: A
A core developer habitually takes on most of the tasks and is about to be reassigned, leaving the project fragile. What should the project manager do?
The root of the problem is that knowledge is concentrated in one person, which is a single point of dependence. The project manager should first assess the existing knowledge transfer mechanisms among team members, find out whether others have mastered his knowledge and skills and what has not yet been passed on, and then draw up remedial measures. Diagnose first and then treat; this follows “assess before acting.” The answer is A.
Why the other options are wrong
- B. Spreading the tasks across the team spreads the workload, but others do not gain the knowledge in his head, so related work will still suffer after he leaves.
- C. Persuading him to stay with rewards and promotion at best delays things. It does not solve the problem that the knowledge has not been passed on, and next time you cannot keep relying on rewards.
- D. The problem is not an unbalanced workload but concentrated knowledge. Having HR balance workloads cannot fill the knowledge gap his departure creates.
Key takeaway When a core member is leaving, first see whether the knowledge has been passed on and then decide on the remedy.
Variation If the stem said “the successor starts next week,” arrange cross-training and mentoring by senior colleagues. If it said “only he understands a certain rule,” first identify the critical knowledge and draw up a transfer plan.
- Question 10
Last month the project manager issued the bid documents for the curtain wall work on an office building and, from the firms that submitted pre-qualification materials, shortlisted several qualified suppliers. None has submitted a proposal yet. To make these firms understand the bid requirements in exactly the same way and prevent evaluation mistakes caused by information asymmetry, what should the project manager do?
Show answer and explanation
Correct answer: A
The project is in the bidding phase of conducting the procurements. The bid documents have been issued and no proposals have arrived yet, and the qualified suppliers must understand the bid content accurately and consistently. The question asks what to do now.
The signals: the bid documents are out, sellers have not submitted proposals, and the goal is “make the firms understand the requirements in exactly the same way”. That is the bidder conference: before proposals are submitted, call all potential sellers together, with the buyer answering questions and clarifying information in one place, each firm hearing the same content and seeing the other firms’ questions and answers, so that information is level. The answer is A.
Why the other options are wrong
- B. Meeting them separately is troublesome, cannot guarantee that each is told exactly the same thing, and prevents anyone from seeing the other sellers’ questions and answers, which is against the principle of fairness.
- C. The sellers have not yet submitted proposals, so there is nothing to review. Reviewing proposals comes later.
- D. Contract negotiation takes place after the seller is selected. No proposals have even been received yet, so negotiation is premature.
Key takeaway To make several sellers understand the bid documents the same way, hold a bidder conference.
Variation If a supplier privately asks the project manager how to write its proposal, the answer should likewise be made public to all bidders; if the question were “too few potential sellers”, the remedy is advertising to widen the list.
- Question 11
A multipoint estimate using PERT (beta distribution) gives an expected duration of 40 days for an activity, with an optimistic time of 25 days and a most likely time of 38 days. What is the pessimistic time in days?
Show answer and explanation
Correct answer: A
The expected duration of a multipoint estimate is 40 days, the optimistic time is 25 days and the most likely time is 38 days. Work back to the pessimistic time. The stem specifies PERT (beta distribution).
In a backward question you treat the formula as an equation: the expected value times 6 equals the optimistic value plus four times the most likely value plus the pessimistic value, and the unknown is the pessimistic value. It solves to 63 days, which is greater than the most likely value of 38, in line with the expectation that the pessimistic value comes after the most likely value, and substituting back into the formula checks out. In a backward question, do not forget to multiply the most likely value by 4 first, and then subtract from the result of the expected value times 6. The answer is A.
- Set up the equation: (25 + 4 × 38 + tP) ÷ 6 = 40.
- Multiply both sides by 6: 25 + 152 + tP = 240.
- tP = 240 − 177 = 63 days.
- Check: (25 + 152 + 63) ÷ 6 = 240 ÷ 6 = 40, consistent with the known expected value.
Why the other options are wrong
- B. 57 days comes from working back with the triangular distribution: 3 × 40 − 25 − 38 = 57. The stem specifies the beta distribution, so the wrong formula was used.
- C. 88 days leaves out the optimistic value: 240 − 4 × 38 = 88, forgetting to subtract the known 25 days.
- D. 177 days forgets to multiply the most likely value by 4: 6 × 40 − 25 − 38 = 177. This number is absurdly larger than the expected value of 40 and should raise a warning.
Key takeaway To work backward, multiply the expected value by 6 and then subtract the known terms, remembering that the most likely value is multiplied by 4.
Variation If the expected value is 40 days, the most likely value is 38 days and the pessimistic value is 63 days, and you must find the optimistic value, then tO = 240 − 152 − 63 = 25 days. If the triangular distribution were specified, tP = 3 × 40 − 25 − 38 = 57 days.
- Question 12
The project team has been formed, tasks have been assigned to each member, and everyone agrees to use a hybrid project approach. What should the project manager do so that the team operates as a well-ordered whole?
Show answer and explanation
Correct answer: D
The team is formed, tasks are assigned and the method is settled as hybrid. The question is what else the project manager should do so that the team operates as a well-ordered whole; the condition is that everything is ready except collaboration rules.
For a team to operate in an orderly way, it needs shared values, norms of conduct and ways of working together. The team charter is the document that establishes the team's values, agreements and operating guidelines, and PMBOK 8 stresses that it works best when the team helps to develop it. So the project manager should develop the team charter together with the team, agreeing norms of conduct and ways of working together. The answer is D.
Why the other options are wrong
- A. The stem mentions no conflict or bad habits. Asking members to change their habits and behavior first has no factual basis and is a one-sided demand, not something agreed jointly.
- B. Issuing regulations with a punitive flavor, unilaterally, without member participation, easily provokes resistance, and it does not fit the approach of developing the charter together with the team.
- C. Discussing strengths and weaknesses one by one helps with dividing the work, but it cannot establish collaboration rules everyone follows, and members may feel they are being judged.
Key takeaway After a team is formed, for orderly collaboration, develop the team charter together with the team.
Variation If the team already has a charter but is not carrying it out, review the charter periodically at team meetings and update it if necessary, rather than creating a new one.
Reference Team Charter · Lesson 2: Ground Rules and Handling Violations: Prevent First, Correct in Order
- Question 13
A new retail system project is halfway through when the usage scenario changes, and the sponsor convenes a review meeting to discuss whether the project is still worth continuing. What should the review be based on most of all?
Show answer and explanation
Correct answer: D
A new retail system project is halfway through when the usage scenario changes. The sponsor convenes a review to discuss whether to continue, and the basis for that decision must be clear.
Whether to continue is a forward-looking decision: compare “how much more must be invested to continue” with “how much value is expected once continued”. The total already invested is sunk cost (a common exam term, meaning cost already incurred that cannot be recovered), which cannot be recovered whether the project continues or not and should not affect the decision. The “percent already complete” in option A is only information about past progress and cannot by itself be the basis for the decision. The project manager should assemble future investment and expected value for the sponsor, who decides. The answer is D.
Why the other options are wrong
- A. Money already invested is a sunk cost, and percent complete reflects only past progress. Neither can replace the comparison of future investment with expected value, and relying on them leads into the trap of “we have put in so much, we cannot give up”.
- B. Attitudes and wishes affect how hard execution is, but they do not show whether the project still has value and are not the core basis for the decision.
- C. Remaining time is only one factor affecting costs and benefits. Looking at time alone cannot tell you whether continuing is worthwhile, and it makes no comparison of value.
Key takeaway A financial analysis of continue-or-terminate should compare future investment with expected value and should not be influenced by sunk cost; a phase gate should also weigh the business documents, strategic alignment, risk and entry and exit criteria.
Variation If the reassessment finds that the expected value of continuing is lower than the further investment, recommend terminating or adjusting, however much has already been spent.
Reference Net Present Value and Value Evaluation · Lesson 3: Cost Types: Direct and Indirect, Fixed and Variable, Sunk Cost, Opportunity Cost and Life Cycle Cost
- Question 14
A project manager leading a team spread across several time zones to develop an online-course platform finds that the deliverables submitted by almost every member fail to meet requirements. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
A team spread across several time zones is developing an online-course platform, and the deliverables submitted by almost every member fail to meet requirements. The question is what the project manager does first, and the basis is the first step of problem solving.
When nonconformance is widespread in the same way, there is probably a common cause, such as a different understanding of the requirements. Problem solving begins by defining the problem and identifying the root cause, and only then turns to countermeasures. So the project manager first reviews the production process with the team to find at which step the problem arises, including whether the requirements were misunderstood. Note that the three wrong options share the same flaw: they all reach a conclusion or issue instructions before the cause is understood. Find the cause before acting; this also reflects the governance approach of analyzing before taking action. The answer is D.
Why the other options are wrong
- A. Issuing a warning before the cause is known does not solve the problem and damages team morale.
- B. Merely telling the sponsor about a delay, with no analysis and no action, shows a lack of initiative.
- C. Demanding rework without investigating the cause means the reworked output is likely to fail again, adding cost and delay.
Key takeaway When a problem is widespread, find the root cause first and talk about countermeasures afterward.
Variation If the stem said only one member's deliverable was nonconforming, first talk with that member to find out whether skills or resources are lacking; a review with the whole team is not needed.
- Question 15
A project manager is preparing the overall status report for a community group-buying platform project but cannot determine how the individual tasks are going. The investigation finds that team members have not promptly recorded completed work and progress, so it is currently impossible to tell whether the performance objectives have been met. What should the project manager do to complete the report?
Show answer and explanation
Correct answer: D
The project manager is preparing the overall status report but cannot determine how individual tasks are going because members have not promptly recorded completed work and progress. What should the project manager do to complete the report?
A status report rests on work performance data: the amount of work completed and the actual progress both come from what members record. If data are missing or late, the compiling, analysis and reporting that follow are meaningless. The obstacle is in the data source, so the remedy should also start at the data source: have members record the completed work and progress as soon as possible, and prepare the report once the data are in. The answer is D.
Why the other options are wrong
- A. The input to earned value analysis is exactly performance data such as the amount of work completed. When data are missing, an inferred result is unreliable and cannot stand in for the data themselves.
- B. Variance analysis compares actual performance with the baseline and also depends on actual data. It is the step after the data are in hand and must wait until the data are complete.
- C. Logging it in the issue log leaves a record, but if the data are not filled in the report still cannot be completed, so the obstacle in front of the project manager is not removed.
Key takeaway A status report relies on timely and accurate data. If data are incomplete, have the source fill them in first; analysis cannot replace them.
Variation If financial postings arrive two weeks later than actual spending, speed up data updates at the point of collection. If members enter hours wrongly, the remedy is to train the users, not to rush to replace the tool.
- Question 16
A logistics company's new warehouse center project is ready to start, but the power company has not yet said when the substation connection will be made. To make the schedule realistic, what should the project manager do?
Show answer and explanation
Correct answer: D
A warehouse center project is ready to start, but the power company has not said when the substation will be connected. How can the schedule be made realistic?
The substation connection is the power company's responsibility and is outside the project team's control. A dependency between a project activity and a non-project activity is an external dependency. Because the other party has not provided a date, the project manager should first contact the power company to clarify the connection date, then build the external dependency and confirmed date into the schedule, plan the later activities accordingly and continue tracking it. The answer is D.
Why the other options are wrong
- A. Crashing is used when a plan exists and the duration must be compressed. The problem here is that the schedule does not reflect the external dependency, and shortening later activities does not solve that.
- B. The critical path method must rest on complete and correct dependencies. With the external dependency missing, the finish date it produces is unreliable.
- C. Schedule network analysis also relies on complete logical relationships. With the external dependency missing, the total float it calculates is meaningless, so it cannot come before identifying the dependency.
Key takeaway A dependency on a party outside the project is an external dependency. If that party is late or has not provided a date, contact it first to clarify the date, then build the dependency into the schedule and track it.
Variation If an activity could start only after equipment arrives, as required by contract, it is also a mandatory dependency. If the team usually does art before development by habit, it is a discretionary internal dependency and can be adjusted.
- Question 17
At the sixth-month status meeting of a production line customization project, the client representative says bluntly that he is very dissatisfied with the project's performance. Right after the meeting, the project manager goes back and checks: the charter and the project management plan are approved, all activities are proceeding strictly as planned, there are no schedule or cost variances, and all quality tests have passed. What should the project manager do FIRST?
Show answer and explanation
Correct answer: C
In a production line customization project, schedule, cost and quality all match the plan, yet at the sixth-month status meeting the client representative says bluntly he is very dissatisfied. You must decide what to do first.
The stem asks what to do “first.” The work matches the plan and quality is up to standard, so the problem may lie in a mismatch between the client's expectations and the plan itself, not in execution variances. The only reliable way to find out what the client is unhappy about is to ask him in person, and then decide whether an adjustment is needed. Ask first, then act. This is also the basic approach to managing stakeholder expectations: rely on direct communication with the person, not on guesswork. The answer is C.
Why the other options are wrong
- A. What the client thinks can only be learned from the client. An internal team discussion is speculation and yields no real information.
- B. The stem already says there is no variance between actual and planned, so variance analysis cannot uncover why the client is dissatisfied.
- D. Revising the plan without knowing why the client is dissatisfied has no basis, would likely change it in the wrong direction and would cause scope creep.
Key takeaway When work follows the plan and quality is up to standard but the client is still unhappy, first meet him to understand his expectations, and only then talk about adjustments.
Variation If variance analysis showed the schedule four weeks behind and the client was unhappy about that, you would first investigate the cause of the variance and set corrective actions, while keeping the client informed.
- Question 18
A project manager is assigned to a store digitization project. Company practice is to set individual performance plans at the start of the year, with feedback reviewed by the functional manager at year end. Team members worry that the work they are doing on the project does not match what is in this year's individual performance plans. What should the project manager do?
Show answer and explanation
Correct answer: B
Company practice is to set individual performance plans at the start of the year and have the functional manager review feedback at year end. Team members worry that their project work does not match their individual performance plans. The question asks what the project manager should do, and the key premise is that the functional manager holds the authority over appraisals.
Members' individual performance plans and year-end evaluations are in the hands of the functional managers. The project manager does not have that authority, but project contributions must come into the functional managers' view. The project manager should proactively meet the functional managers and align expectations for the members and how often results are reported, so that project work can be reflected in the appraisal. That removes the members' worry without overstepping authority. The correct answer is B.
Why the other options are wrong
- A. Compiling feedback only at year end is too late. The members' worry goes unanswered now, and contributions may be overlooked because the information arrives late. It is a passive approach.
- C. A verbal assurance that “the project is the top priority and you will be assessed accordingly” has no means of follow-through. The members' plans still do not line up, so the concern is not really removed.
- D. Requiring the project manager to draw up the members' individual performance plans goes beyond the functional managers' role under company policy. It is likely to upset them and will not work.
Key takeaway When members are appraised by functional managers, the project manager proactively aligns expectations and reporting frequency with them.
Variation If the project is in a strong matrix organization where the project manager has appraisal authority over members, the project manager can take part directly in the assessment but should still talk with the functional managers to keep information consistent.
Reference Team Performance · Lesson 1: Team Performance Assessments: What to Assess, What to Base It On, What to Do Next
- Question 19
A project manager is assigned to manage a drone development project. Two key resources disagree over a requirement, and the way they argue goes against the ground rules the team set together at the start of the project. What should the project manager do?
Show answer and explanation
Correct answer: B
A project manager is assigned to a drone development project. Two key resources disagree on a requirement, and the way they argue goes against the ground rules the team set together at the start of the project. The question asks what the project manager should do.
PMBOK 8 says team ground rules, group norms and solid project management practices can reduce the amount of conflict. Ground rules are defined in the team charter, which works best when the team develops it or at least has an opportunity to contribute to it. With a disagreement over a requirement, the project manager should refer to the ground rules set at the start to govern how the discussion is conducted, and guide both sides to compare views and reach consensus using collaborate/problem-solve, rather than deciding alone or moving people away. (Ground rules set acceptable behavior and help reduce conflict, but they cannot say which view of the requirement is right.) The answer is B.
Why the other options are wrong
- A. Moving both key resources away because of a disagreement is avoidance, deprives the project of key people and leaves the disagreement itself unresolved.
- C. Adopting the advice of the more experienced person turns seniority into the basis for resolution. Experience alone does not make advice appropriate, and the other side's view is ignored.
- D. Deciding on a course of action from the project manager's own experience is unilateral. A collaborative discussion that incorporates both viewpoints is more appropriate and will typically help the parties reach consensus.
Key takeaway When a disagreement arises, use the ground rules set at the start to frame the discussion, then guide both sides to resolve it collaboratively.
Variation If no ground rules were set at the start, the project manager should first develop them with the team and then use them to resolve disagreements.
Reference Conflict Management · Lesson 4: Conflict and Ground Rules: Set the Rules in Advance, Correct Violations Afterward
- Question 20
A software company plans to hire an outside team to take on part of the system design and implementation. Which of the following procurement techniques best ensures that the process of selecting suppliers is fair to all potential suppliers?
Show answer and explanation
Correct answer: A
A software company wants to hire an outside team for part of the system design and implementation, and the question asks which procurement technique best ensures that supplier selection is fair to all potential suppliers.
The PMBOK 8 glossary defines a bidder conference as meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Appendix X4 also says that once the bid documents are distributed the buyer generally has a bidder conference to respond to questions and provide clarifying information. All potential sellers hear the same explanation and none gets special treatment, which secures fairness. The answer is A.
Why the other options are wrong
- B. Advertising widens the list of potential sellers and lets more suppliers know of the opportunity. It does not ensure that each gets the same information and treatment.
- C. A request for proposal (RFP) is the bid document that solicits proposals. It does not govern how information reaches each supplier and is not a meeting technique for securing fairness.
- D. A list of pre-qualified sellers is a list the buyer has screened in advance, which if anything narrows the field, and has no direct bearing on whether all bidders are treated fairly.
Key takeaway To make all potential sellers understand the same thing and favor none of them, use a bidder conference.
Variation If the question asked how to let more sellers know about this procurement, the answer would become advertising; if it asked how to narrow the sellers in advance, a list of pre-qualified sellers.
Reference Conducting the Procurements · Lesson 1: Conducting the Procurements: Inputs, Seller Proposals and the Bidder Conference
- Question 21
A company's smart fitness band has been on the market for three years, and the company now launches a project to develop a new generation of firmware for it. Which statement about the relationship between this project's life cycle and the product life cycle is correct?
Show answer and explanation
Correct answer: A
A smart fitness band has been on the market for three years, and a project is launched to develop new-generation firmware for it. Which statement about the relationship between the project life cycle and the product life cycle is correct?
PMBOK 8: project life cycles are independent of product life cycles, which can be part of the outcomes produced by a project. The product life cycle is a series of phases that represent the evolution of a product, from introduction through growth, maturity, and to retirement. Projects can be launched at any point in the product life cycle to create or enhance a product's components, functions or capabilities, and a product life cycle often spans multiple projects. After the firmware upgrade project ends, the product remains on the market, and the two do not replace each other. The answer is A.
Why the other options are wrong
- B. The end of a project is just one event in the product life cycle. The product will continue to operate for years and does not retire when the project ends.
- C. The relationship is reversed: a product life cycle contains several projects. It is not one phase of a project, and it is not managed by the project manager alone.
- D. Project phases are divided by the logic of the project work and do not have to correspond one to one with a product's introduction, growth, maturity and retirement.
Key takeaway The project life cycle is independent of the product life cycle, and one product life cycle can include several projects.
Variation If the project is to develop the first version of the product, the project's result becomes the starting point of the product life cycle, but the two are still different life cycles.
Reference The Project Life Cycle · Lesson 2: Life Cycle Flexibility, the Product Life Cycle, and Four Easily Confused Concepts
- Question 22
A project has a planned duration of 10 months, a budget at completion of $40,000, actual cost of $14,000, earned value of $12,000 and planned value of $15,000. Assume planned value accumulates evenly over time and that future schedule performance stays at the current SPI level. How many months in total are expected to be needed to complete the project?
Show answer and explanation
Correct answer: D
The question is clear that what is to be forecast is completion time, not cost, so the schedule performance index (SPI) should be used.
For duration, use SPI. Under the linear simplifying assumption set in the stem (planned value accumulates evenly and SPI stays constant), forecast total duration = planned duration ÷ SPI. This is a simplified method that is common exam practice; on a real project you would forecast from the updated schedule model and the remaining durations. An SPI below 1 means behind schedule, so the duration should be longer than planned. The answer is D.
- SPI = EV ÷ PV = 12 ÷ 15 = 0.8
- Performance continues: forecast total duration = planned duration ÷ SPI = 10 ÷ 0.8 = 12.5 months
- Check: 12.5 × 0.8 = 10, equal to the planned duration, so they agree. BAC and AC are distractor figures. The answer is D
Why the other options are wrong
- A. 10 × 0.8 = 8 multiplies in the wrong direction. An SPI below 1 means behind schedule, so the duration must get longer, not shorter.
- B. 10.8 months adds only the lag already incurred, about 0.75 month (3 ÷ 40 × 10), to the planned duration, assuming no further lag, which does not match “performance stays unchanged”.
- C. This uses CPI: 10 ÷ (12 ÷ 14) ≈ 11.7. CPI reflects cost efficiency; use SPI to forecast duration.
Key takeaway Use SPI, not CPI, to forecast completion duration; when performance continues, forecast total duration = planned duration ÷ SPI.
Variation If EV were exactly equal to PV ($15,000), SPI = 1 and the forecast total duration is still 10 months. If EV were only $10,000, SPI = 10 ÷ 15 ≈ 0.67 and the forecast total duration = 10 ÷ 0.67 = 15 months.
- Question 23
A project manager takes over an overseas data-center deployment project. At the first meeting with the team, a subject matter expert worries that sudden late arrival of key servers would stop the project from finishing on time. Which document should the project manager consult FIRST to confirm stakeholders' tolerance for schedule impact?
Show answer and explanation
Correct answer: B
A project manager takes over an overseas data-center deployment project, and at the first meeting a subject matter expert worries about a sudden late arrival of key servers. The question asks which document to consult first to confirm stakeholders' tolerance for schedule impact.
The stem's “tolerance for schedule impact” is everyday wording for how much schedule variation stakeholders accept; in PMBOK 8 that is expressed as the risk appetite and the measurable risk threshold. PMBOK 8 defines risk appetite as “the degree of uncertainty an organization or individual is willing to accept in anticipation of a reward,” and the risk threshold as the measure of acceptable variation around an objective. Both are recorded in the risk management plan, written as measurable thresholds around each project objective. So the risk management plan is consulted first. The answer is B.
Why the other options are wrong
- A. The communications management plan sets how and to whom to communicate; it does not record stakeholders' tolerance for schedule deviation.
- C. The project schedule gives the timing and does not say how large a delay stakeholders can tolerate, so it cannot answer “how serious is the impact”.
- D. The risk register records identified specific risks and their responses; it is a product of risk management and does not record tolerance. Tolerance is taken from the risk management plan.
Key takeaway To know how much deviation stakeholders can tolerate, check the risk management plan.
Variation If the question asked where to record this late-arrival risk the expert is worried about, the answer is the risk register, with its probability and impact assessed using the definitions in the risk management plan.
Reference Risk Management Plan · Lesson 1: Risk, Issues and Risk Appetite
- Question 24
An iteration planning meeting for an order-lookup feature has just ended and the story points have been totaled. The team draws an iteration burndown chart covering the next 4 weeks. A member makes four statements about the chart. Which one is NOT correct?
Show answer and explanation
Correct answer: C
An iteration planning meeting has just ended, and the team draws an iteration burndown chart covering four weeks. Note that the question asks which of the member's four statements is incorrect.
The scope of an iteration burndown chart is one iteration. Its starting point is the amount of work selected at iteration planning, which is also the starting point of the ideal line. After that, the work not yet completed in this iteration is recorded each day, and a trend line forecasts the situation at the end of the iteration. A release usually contains several iterations, and a chart covering one iteration cannot show how much of the whole release remains; for that you need the release-level burndown chart. “Records the amount of work remaining in the current release” is therefore the incorrect statement. The answer is C.
Why the other options are wrong
- A. Correct statement: an iteration burndown chart tracks the work not yet completed in this iteration's backlog.
- B. Correct statement: the starting point of the chart is the work selected at iteration planning, and the ideal line is drawn from it.
- D. Correct statement: the trend line on the chart extends from current progress and shows how much work is expected to remain in the iteration.
Key takeaway An iteration burndown chart covers only one iteration; for how much of the whole release remains, look at the release-level chart.
Variation If option C were changed to “records the work not yet completed in the current iteration”, it would be a correct description; if the question asked how far the whole project is from the release goal, the answer would be a release-level burndown or burnup chart.
- Question 25
The project manager of an online education platform project is discussing responses to a cost overrun risk with the team. Member A suggests transfer because part of the negative impact can be handed to a third party. Member B suggests mitigation because it can bring the impact down to an acceptable level. After comparing the characteristics and requirements of the two options, the project manager chooses transfer. Which analysis technique did she use?
Show answer and explanation
Correct answer: D
The project is in the Plan Risk Responses stage. The cost overrun risk has already been identified. The team proposes two alternative response strategies, transfer and mitigation, and the project manager compares their characteristics and requirements before choosing transfer. You must decide which analysis technique this comparison represents.
“Comparing the characteristics and requirements of two options and choosing one” points directly to alternative analysis. Alternative analysis is a simple comparison of the characteristics and requirements of alternative response options to decide which is most suitable. The stem contains no currency conversion, no reserve calculation and no ranking of risks, only a comparison between two options, so the technique can only be alternative analysis. The answer is D.
Why the other options are wrong
- A. Qualitative risk analysis scores the probability and impact of individual risks and ranks them by priority, and it happens before response planning. Here the risk is already settled and the team is comparing responses, not ranking risks.
- B. Reserve analysis checks whether contingency and management reserves are sufficient. The stem does not discuss a budget buffer or reserve amounts; it only picks one of two strategies.
- C. Cost-benefit analysis converts the benefit of a response into money and compares it with the cost of the response. The stem mentions only the characteristics and requirements of each option, with no cost and benefit figures, so the words “cost overrun” can mislead you into choosing it.
Key takeaway Comparing the characteristics and requirements of several alternative responses and choosing the most suitable one is alternative analysis.
Variation If each option's response cost were compared in money with the loss it is expected to save, the technique would be cost-benefit analysis. If the task were to decide which risks come first, it would be qualitative risk analysis.
Reference Risk Response Strategies · Lesson 1: Plan Risk Responses: Purpose, Response Requirements and Cost-Benefit Analysis
- Question 26
An online education platform project has video stuttering. Through brainstorming, the team has grouped the causes into video encoding, server bandwidth, client cache and third-party plug-ins, and has counted the number of stutters triggered by each cause, which differ. To decide which cause to solve first, which tool should the project manager use?
Show answer and explanation
Correct answer: B
On an online education platform with video stuttering, the team has grouped the causes into four categories (encoding, bandwidth, cache and third-party plug-ins) and counted the stutters each category triggered, which differ. The question asks which tool to use to decide which to solve first.
The causes have already been listed, and what is missing is the order of priority. The Pareto chart (a common exam term) arranges the causes from the highest number of occurrences to the lowest and adds a cumulative share, helping to find the few causes that contribute the most so resources can be concentrated on them first. The stem explicitly gives “the number of occurrences differs by cause” as the basis for ranking, so use a Pareto chart. The answer is B.
Why the other options are wrong
- A. A cause-and-effect diagram breaks a problem down into cause branches. The causes are already listed, and it does not rank them, so it cannot answer “which to solve first”.
- C. A flowchart shows the sequence of steps and is used to locate the step where a problem occurs. It has nothing to do with setting priorities.
- D. A histogram shows the distribution of numerical data. It does not sort by size and has no cumulative share, so it cannot directly set priorities; the chart that ranks by frequency is the Pareto chart (a common exam term).
Key takeaway When the causes are listed with different counts and you need an order: rank with a Pareto chart and go after the vital few.
Variation If the question asks to “list these categories of causes”, use a cause-and-effect diagram; if it asks “whether the number of stutters falls as bandwidth increases”, use a scatter diagram.
Reference Cause-and-Effect and Pareto Diagrams · Lesson 2: Pareto Chart: Sort by Frequency and Go After the Vital Few
- Question 27
Two members of the procurement group disagree about the format of meeting minutes. After assessing it, the project manager concludes the matter is unimportant and will not affect core project deliverables, and just wants both to calm down and continue working together pleasantly. What is the MOST suitable way to handle the conflict?
Show answer and explanation
Correct answer: A
Two procurement group members disagree about the format of meeting minutes. The project manager judges it unimportant and not a threat to core deliverables, and only wants both to calm down and keep working together happily. The question asks for the most suitable way to handle the conflict.
PMBOK 8 says the choice of resolution method depends on factors such as the importance and intensity of the conflict, the time pressure to resolve it, and the importance of maintaining a good relationship. This matter is unimportant and the aim is only to ease the mood and keep the relationship. Smooth/accommodate emphasizes agreement over differences and gives way to maintain harmony, which fits well. The answer is A.
Why the other options are wrong
- B. Force/direct pushes one side's view through power. Using power on a trivial matter would hurt the relationship and is not worth it.
- C. Collaborate/problem-solve takes a lot of time to dig into root causes, which is too much investment for a small matter that does not affect delivery.
- D. Compromise/reconcile needs both sides to give up some conditions after time spent negotiating. That also costs more than necessary, when the project manager only wants to ease the mood.
Key takeaway When the conflict is unimportant and the aim is just to calm things down and preserve the relationship, use smooth/accommodate.
Variation If the format dispute affected the compliance of contract documents, the importance of the conflict would rise and collaborate/problem-solve should be used instead.
- Question 28
A fast-growing smart home company starts a new-generation voice assistant project, aiming to give users a personalized interaction experience. The project management plan has been approved and the project is moving ahead. The project manager wants to confirm whether the team is carrying out the quality management plan. What should be used?
Show answer and explanation
Correct answer: A
A smart home voice assistant project has an approved project management plan and is moving ahead. The project manager wants to confirm whether the team is carrying out the quality management plan. The question asks what to use.
What needs confirming is whether “the quality management plan is being carried out”, and the object is how the process is executed. PMBOK 8 explains that quality audits are used to identify good practices, nonconformities and gaps, and that they are a tool used in Manage Quality Assurance. Quality audits may be scheduled or random, and can also confirm the implementation of approved change requests. So use a quality audit to check whether team activities follow the established policies, processes and procedures. The answer is A.
Why the other options are wrong
- B. Quality metrics describe the attributes to be measured and how they will be verified. They are the yardstick and cannot by themselves check whether the plan is being executed.
- C. Alternative analysis compares the strengths and weaknesses of different options. It has nothing to do with checking whether a plan is being executed.
- D. A cause-and-effect diagram is for tracing the root cause of a problem, and the stem presents no problem whose cause needs tracing.
Key takeaway To confirm whether the quality management plan is being carried out, use a quality audit.
Variation If the audit finds the team did not carry out one of the reviews, the next step is to analyze the cause with the team and quality experts and agree on corrective action.
Reference Quality Planning and Assurance · Lesson 4: Manage Quality Assurance: Audits, Checklists, Problem-Solving and Process Improvement
- Question 29
Which performance domain has the following responsibility: from project start to completion, it continuously integrates and coordinates the management processes and activities, protects and enhances the project's value proposition, and its decisions include the authority to cancel the project when necessary?
Show answer and explanation
Correct answer: C
The stem gives three responsibilities of a performance domain: integrating and coordinating the processes and activities, protecting and enhancing the value proposition, and holding the authority to cancel the project when necessary. Which performance domain is it?
The most distinctive of the three is “the authority to cancel the project when necessary.” PMBOK 8 states that the Governance performance domain encompasses the processes required to make decisions that protect and enhance the value proposition of a project in an integrated and holistic manner, including the authority to cancel a project when necessary, and that it also encompasses the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Focus Areas. The other three domains each manage one specific area and have neither the cross-domain integration role nor the decision authority to cancel a project. The answer is C.
Why the other options are wrong
- A. This takes “how far the work must go” as the highest decision. The Scope performance domain covers what work must be done and whether deliverables meet acceptance criteria. It does not integrate the other domains and has no authority to decide whether the project continues.
- B. This equates money with the life or death of the project. The Finance performance domain handles budget, cost and funding. It is one of the areas being integrated and coordinated, and it does not carry the decision responsibility to protect and enhance the value proposition or to cancel the project.
- D. This mistakes winning stakeholder support for the final decision. The Stakeholders performance domain focuses on identifying and analyzing stakeholders and engaging them so that they pull together, and it has no authority to integrate the whole or to terminate the project.
Key takeaway When you see the cluster “integrate and coordinate, protect and enhance the value proposition, cancel the project when necessary,” it is the Governance performance domain.
Variation If the wording were “determine what work must be done and accept the deliverables,” the answer would be the Scope performance domain. If it were “manage budget and funding,” it would be the Finance performance domain.
Reference Project Governance · Lesson 1: What Governance Is: The Nine Processes and Governance Models
- Question 30
Soon after an ERP upgrade project at a manufacturing company begins, the project manager is replaced. The new project manager finds that the business departments do not support the project, and after talking with them confirms that senior management is not fully supporting it either. What should the new project manager do next?
Show answer and explanation
Correct answer: D
Soon after an ERP upgrade project begins, the project manager is replaced. The new project manager finds that the business departments do not support the project, and senior management is not fully supporting it either. The question asks what to do next.
To win support, first you need to know who has influence and what each person cares about. PMBOK 8 says stakeholder analysis yields a list of stakeholders and their roles, stakes, expectations and attitudes (their levels of support for the project). So the next step is to do stakeholder analysis and find the most influential people, understand their stakes, and then win their help, changing attitudes by addressing the things they care about. The answer is D.
Why the other options are wrong
- A. A status report is one-way reporting. Without knowing each party's attitude and influence, however complete the information, cooperation is not assured, and it does not touch the reasons for the lack of support.
- B. The problem in the stem is that the business departments and senior management “do not support” the project, not that they object to a specific piece of completed work. Having the business departments explain item by item misses the point.
- C. Directly demanding that senior management declare support amounts to using orders to change their position. First learn their stakes through analysis and meet their needs, and only then will attitudes change.
Key takeaway When the project is not supported, analyze first and then engage; do not start with reporting or pressure.
Variation If the analysis shows the business departments are just worried that going live will disrupt business, use a pilot plan and a training plan to remove their concerns.
Reference Identifying and Analyzing Stakeholders · Lesson 2: Stakeholder Analysis: What Information to Collect and the Five Kinds of Stakes
- Question 31
You are the Scrum Master of a team. A senior executive has many questions about the project and its progress, and quite a few team members are spending a great deal of time answering them. What should you do next?
Show answer and explanation
Correct answer: B
On a Scrum project, a senior executive has many questions about the project and its progress, and quite a few team members spend a great deal of time answering them. The question asks for the Scrum Master's next action.
The Scrum Master's duties include both shielding the team from interference and serving the organization, helping stakeholders understand and apply Scrum. The most appropriate step is to explain agile ways of working to the senior executive and ask the executive to take progress questions to the Scrum Master. This takes the inquiries off the team and keeps a good relationship with the executive. The answer is B.
Why the other options are wrong
- A. Forwarding quietly without any explanation leaves the executive wondering why there are no responses, which damages the relationship and does nothing to help the executive understand agile ways of working.
- C. Telling the executive bluntly to look only at the information radiator and ask no more questions is not how a servant leader treats stakeholders. The information radiator should be introduced proactively and in a friendly way.
- D. Requiring that nobody on the team answer anyone without permission blocks communication by control. It goes against an empowering, serving role and would make the executive even less satisfied.
Key takeaway Shielding the team is done not by blocking but by explaining to the executive and taking over the inquiries.
Variation If the executive asks “why were the features traded off this way and when will it be released”, such questions should go to the Product Owner, and the Scrum Master does not order or commit on the Product Owner's behalf.
- Question 32
PMLyceum's industrial controller design project is contractually due for delivery at the end of this month. Senior management wants to speed up delivery to bring in cash sooner and suggests leaving out the product quality verification step, on the grounds that design work does not need quality testing. What should the project manager do?
Show answer and explanation
Correct answer: A
An industrial controller design project is near its contractual delivery date. Senior management wants faster delivery to bring in cash and suggests omitting quality verification, on the grounds that design work does not need quality testing. The question asks what the project manager should do.
PMBOK 8 stresses embedding quality into processes and deliverables. The purpose of quality activities is to ensure deliverables meet acceptance criteria and stakeholder expectations, and early testing also lowers the cost of fixing things later. Cancelling verification does not actually speed up delivery. It lets defects stay hidden until client acceptance, causing rework, returns and breach-of-contract risk. The project manager should explain these consequences to senior management and change the decision with facts, rather than going along with it or working around it. The answer is A.
Why the other options are wrong
- B. Going through the change process sounds compliant, but quality verification is a necessary activity for ensuring delivery quality, and submitting such a change request amounts to endorsing a wrong suggestion.
- C. Schedule compression shortens the duration without changing scope. It is not achieved by cutting quality checks, and skipping the checks outright passes the quality risk on to the client.
- D. Fast tracking turns sequential activities into parallel ones, which itself raises the risk of rework. Contingency reserve is for identified risks and cannot pay for giving up quality checks, and correcting afterward costs more than preventing beforehand.
Key takeaway Do not cancel quality verification to hurry the schedule. Explaining the risk to management is the project manager's first response.
Variation If management agrees to keep the verification but wants a shorter cycle, you can compress by adding test resources or verifying in batches, rather than deleting the verification itself.
Reference Quality Planning and Assurance · Lesson 1: What Quality Means: Embed Quality Into Processes and Deliverables
- Question 33
A project manager is leading a team that is developing an application, and the project is in the executing phase. The project manager sees that the needs of some stakeholders are not being met while other stakeholders are over-involved, which disrupts the project's normal operation. Which process should the project manager carry out?
Show answer and explanation
Correct answer: C
In the executing phase, the project manager sees that some stakeholders' needs are not being met while others are over-involved and disrupt the project. You must determine which process to carry out.
Both phenomena in the stem, unmet needs and unbalanced engagement, are what Manage Stakeholder Engagement deals with. This process involves communicating and working with stakeholders to meet their needs and expectations, address issues and foster appropriate stakeholder engagement, and it runs throughout the project. The requirements have already been collected, identification is already done, and a communications plan is not what needs to be added now; the problem lies in managing people. The answer is C.
Why the other options are wrong
- A. Requirements have already been collected. The current problem is that requirements are unmet and engagement is inappropriate, not that requirements were never gathered.
- B. Identifying stakeholders records who is related to the project along with assessment information. These stakeholders already exist and the problem is inappropriate engagement, which identification cannot solve.
- D. The output of Plan Communications Management is a communications management plan, which focuses on how information is conveyed. The stem does not describe poor communication but an imbalance of requirements and engagement.
Key takeaway Unmet needs and unbalanced engagement are problems for the Manage Stakeholder Engagement process.
Variation If “different parties are simply receiving inconsistent information,” it belongs to managing communications. If “the project does not know which stakeholders it has,” it is Identify Stakeholders.
Reference Stakeholder Engagement · Lesson 3: Managing Stakeholder Engagement: Follow the Plan, and Use Interpersonal Skills for Concerns and Conflict
- Question 34
A logistics sorting-system upgrade project finds a configuration defect during testing, and the team has to do a large amount of rework. The rework is on the critical path and puts the schedule behind. The project manager has already assessed the rework's impact on schedule, cost and resources. What should the project manager do?
Show answer and explanation
Correct answer: D
On a logistics sorting-system upgrade project, a configuration defect is found in testing, and a large amount of rework on the critical path puts the schedule behind. What should the project manager do?
Change requests include updates, defect repairs, preventive actions and corrective actions. The rework to fix the defect (defect repair) and the corrective action taken to recover the schedule are both change requests. They should be assessed for their impact on scope, schedule and cost and, as the change management plan prescribes, submitted for approval to the designated approver (such as the change control board); a baseline is revised only for a change that is approved and affects it. The answer is D.
Why the other options are wrong
- A. A baseline can be revised only according to approved changes. Resetting the schedule baseline directly rewrites the yardstick for measuring delay by the delay itself.
- B. Reporting to the PMO informs it, but a report alone does not fix the schedule variance and does not replace the impact assessment and submission to the designated approver under the change management plan.
- C. Acting first and filing afterward violates assessing before acting. Overtime also changes cost and resource arrangements, so it should be carried out after approval.
Key takeaway Defect repairs and corrective actions are change requests, submitted for approval to the designated approver under the change management plan (such as the change control board); the baseline is never changed directly.
Variation If the catch-up measures needed for the rework fall wholly within what the plan allows and do not affect the baseline, the project manager can decide and record them as the plan provides; if the baseline is affected, a change is still required.
- Question 35
Which of the following statements about the agile principles is correct?
Show answer and explanation
Correct answer: B
The four options vary across two dimensions, early versus late and requirements versus priorities. You must find the one that matches the principle exactly.
The principle is: welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage. So the correct statement has two points: change remains welcome in the later part of the project, what is welcomed is change in requirements, and the purpose is to give the customer a competitive advantage. B satisfies both. D also mentions the later part of the project, but it claims priorities should no longer be adjusted, which is the opposite of welcoming change even late in development, and the principles contain no such statement. The answer is B.
Why the other options are wrong
- A. Limiting the welcome for change to early in the project is the opposite of “even late in development”.
- C. It both limits the welcome to early in the project and makes the subject priority adjustments. It departs from the principle in both places.
- D. This sentence denies adjustment in the later part of the project, contrary to the principle: the principle welcomes change, even late in development, and priorities should also be adjusted as value changes. It is also not the wording of the principle.
Key takeaway The principle welcomes changing requirements, even late in development, and turns change into the customer's competitive advantage.
Variation If the question asks how to handle a new requirement late in the project, the right approach is to write it as a user story, put it in the product backlog, have the Product Owner order it, and deliver it in a later iteration.
Reference The Agile Manifesto · Lesson 2: The Twelve Principles (Part 1): Customer Value and Continuous Delivery
- Question 36
A project team brings in a system based on a large language model that can generate new text and images from prompts, to draft project communication materials. Which of the following categories does this system belong to MOST precisely?
Show answer and explanation
Correct answer: A
A project team brings in a system based on a large language model that generates new text and images from prompts, to draft project communication materials. Which category does the system belong to most precisely?
The PMBOK 8 appendix divides AI systems into four layers. Artificial intelligence is the broader term, machine learning is its subfield, deep learning is a more advanced type of machine learning, and generative AI is a subset of deep learning that applies large language models to create systems capable of generating new data (text, speech, audio, pictures, videos and so on). The stem's features, a large language model and generating new content, belong to exactly this most specific layer. The answer is A.
Why the other options are wrong
- B. Machine learning uses data to train models to predict outputs. Its scope is wider than generative AI's, and it does not point to the feature of generating new data.
- C. Deep learning relies on multilayered neural networks to extract features and make decisions. It too is wider than generative AI and does not point to large language models and generating new content.
- D. Artificial intelligence is the broadest term. The stem's features correspond to a more specific layer, and you should choose the most fitting category.
Key takeaway The four layers from broad to narrow: artificial intelligence, machine learning, deep learning, generative AI. What can generate new content is generative AI.
Variation If the stem said “uses data to train a model to predict outputs, without generating new content”, it would be machine learning.
Reference Artificial Intelligence in Project Management · Lesson 1: What AI Means and How It Is Classified; Three Strategies for Adopting AI
- Question 37
PMLyceum has taken on the development of an online booking platform. The team has completed the main deliverables and demonstrates them to all parties at a review meeting. The customer representative expresses concern about the quality of these deliverables. The project manager wants to use process data to show that the process that produced these deliverables is stable and its performance is predictable. Which tool should be used?
Show answer and explanation
Correct answer: C
The main deliverables of an online booking platform are complete, and the customer is concerned about quality at the review meeting. The project manager wants to use process data to show that the process that produced the deliverables is stable and its performance is predictable.
The stem asks to “show that the process is stable”. A control chart plots process data in time order and displays upper and lower control limits, to determine whether the process is stable and its performance predictable. If the points all fall within the limits with no abnormal pattern, it can show the customer that the process is in control and performance is predictable. Note that control limits reflect the natural variation range of the process and are not the same as specification limits. To show whether the output conforms, you must also compare it with the specification limits or acceptance criteria. The answer is C.
Why the other options are wrong
- A. A Pareto chart sorts by frequency from highest to lowest to find the “vital few”. It cannot show whether a process is stable.
- B. A cause-and-effect diagram sorts out the possible causes of a problem. It is a tool for finding causes, not for proving quality.
- D. A scatter diagram looks at whether two variables are related. It also cannot judge whether a process is stable.
Key takeaway To prove that a process is stable and its performance predictable, use a control chart.
Variation If a point were outside the limits and the customer questioned the quality, the process may be out of control, so find the cause first instead of continuing to use the chart to claim stability.
- Question 38
A software team has an AI tool analyze data from past projects to forecast the duration of a new project and likely bottlenecks. Which type of AI application is this?
Show answer and explanation
Correct answer: D
A software team has AI analyze data from past projects to forecast the duration of a new project and likely bottlenecks. Which type of application is this?
The core clues in the stem are “data from past projects” and “forecast duration and bottlenecks”. Table X3-1 of PMBOK 8 calls the use case of predicting timelines, resource needs and potential bottlenecks by analyzing historical data and project specifics “predictive analytics for planning” in the governance domain, and the strategy is assistance: AI helps with the analysis, and a person reviews and refines the results. In judging, grab the two words “object” (data from past projects) and “action” (forecast) and match them to the name in the table. The answer is D.
Why the other options are wrong
- A. Automated reporting and representation is automatically generating reports on status, performance metrics and compliance. Its output is a summary of existing information and involves no forecasting.
- B. Meeting minutes transcription is turning the content of a meeting into text and picking out key points, decisions and action items. It has nothing to do with forecasting duration from historical data.
- C. Stakeholder sentiment analysis uses natural language processing to analyze communication data such as emails and chats, judging people's feelings and concerns. Its object is not duration and bottlenecks.
Key takeaway Using historical data plus project specifics to forecast duration is called predictive analytics, at the “assistance” level.
Variation If AI continuously monitored progress against the baseline and flagged deviations, that would be real-time monitoring, which is automation. If AI generated ideas for strategic options, that would be brainstorming and idea generation, which is augmentation.
- Question 39
On a voice assistant development project, a stakeholder firmly demands that a feature be added, or else cooperation will end. Earlier market research led the project manager to think the feature was not very necessary, but after assessing the impact, the project manager finds that adding it would have very little effect on the project as a whole and obtains authorization through the applicable change-governance process before adding it as requested. Which conflict resolution technique is this?
Show answer and explanation
Correct answer: C
On a voice assistant project, a stakeholder demands a feature on pain of ending the cooperation. The project manager's market research suggested the feature was of little necessity, but after assessing the impact, the project manager concludes adding it would have little effect, obtains authorization through the applicable change-governance process, and adds it as requested. The question asks which technique this is.
PMBOK 8 describes smooth/accommodate as emphasizing areas of agreement rather than areas of difference and conceding one's position to the needs of others to maintain harmony and relationships. After finding the impact small and obtaining authorization through the applicable change-governance process, the project manager gave way unilaterally in position to preserve the cooperation, which fits. Following change governance does not alter the nature of the conflict-resolution technique. The answer is C.
Why the other options are wrong
- A. Compromise/reconcile has each side giving up something and gaining some satisfaction. Here only the project manager gave way and the other side conceded nothing.
- B. Collaborate/problem-solve requires the parties to sit down, discuss and form consensus. There was no joint discussion here, just one party conceding.
- D. Withdraw/avoid means retreating, postponing the issue or leaving it to others. The project manager gave a definite response and actually did what was asked.
Key takeaway Conceding unilaterally to preserve the relationship is smooth/accommodate.
Variation If the project manager had assessed the feature as having a large impact and still refused and simply announced the conclusion, that would be force/direct.
Reference Conflict Management · Lesson 2: The Five Conflict Resolution Techniques: Names, Meanings and When to Use Each
- Question 40
A project manager for a fitness chain is based in Country C and is sent to Country D to set up the first branch there. The sponsor has already chosen the city and asks that potential trouble with local government authorities be avoided as far as possible. What should the project manager do to meet this requirement?
Show answer and explanation
Correct answer: D
A project manager based in Country C is sent to Country D to set up the chain's first branch there. The sponsor has chosen the city and asks that potential trouble with local government authorities be avoided as far as possible. The question asks for the approach that meets this.
Potential trouble with the government comes mainly from external compliance requirements such as laws and regulations. The project manager is unfamiliar with local regulations and should work with the company's legal department to understand the local rules, build those requirements into the project requirements and make sure the project complies. Identifying compliance requirements at the source is what reduces later problems. The answer is D.
Why the other options are wrong
- A. Where the team comes from has nothing to do with government issues. A team should be formed by professional capability and need and not only from local residents, and team makeup cannot replace research on regulations.
- B. Even if the exact site still has to be chosen, working with the real estate department to approach the government covers only site selection. It cannot replace systematically verifying all the local regulations and compliance obligations that apply.
- C. Opening files on employees is human resources work, does not help reduce potential problems with the government and cannot replace identifying compliance requirements.
Key takeaway To reduce potential problems with a foreign government, first confirm the local regulations with the legal department and include them in the project requirements.
Variation If the question were how to learn local employment rules, you would likewise check with legal or a local professional advisor first and not infer from experience.
Reference Project Compliance · Lesson 2: Identifying Compliance Requirements and Building Them In
- Question 41
A project manager is preparing to negotiate a supply agreement with a key supplier. The situation is complex, neither side can get everything it wants, and compromise may be needed to avoid schedule delays, cost overruns and reputational damage. To obtain an outcome that benefits the project, what should the project manager do?
Show answer and explanation
Correct answer: B
A project manager is preparing to negotiate a supply agreement with a key supplier. The situation is complex, neither side can have everything it wants, and compromise may be needed. The question is about the preparation needed to obtain an outcome that benefits the project.
To compromise in a negotiation, you must know in advance which interests you cannot give up and which you can. So before the negotiation, analyze priorities with stakeholders, rank the objectives by importance, and separate the bottom line, the expectations and the parts you can concede. Then you can make concessions on a reasoned basis and protect the project's core interests, avoiding schedule delay and cost overruns. The answer is B.
Why the other options are wrong
- A. Revealing priorities midway means doing the preparation at the negotiating table. It invites hasty concessions under pressure and exposes your hand.
- C. Setting objectives before negotiating is fine, but fixing them and following them strictly in the negotiation removes the room to concede and to adapt, particularly when the situation is complex.
- D. Adjusting your priorities at any time as the negotiation develops lacks internal consensus, is high risk and is easily exploited by the other side. This should be done before negotiating.
Key takeaway Before negotiating, clarify priorities with stakeholders and rank your objectives, so that you can protect your core interests when you compromise.
Variation If the stem asked “what to do when negotiations reach a deadlock,” the approach is to go back to the parties' interests and look for a win-win solution or concessions in stages; if the negotiation fails, consider the best alternative.
- Question 42
A software company is developing a scheduling system for internal use. Preparation was thorough and a very high quality measurement standard was set. The project is progressing according to the project management plan, the product quality measurements all meet those standards, schedule and cost match the baselines, scope is being developed strictly to the scope baseline, and everything else is also as planned. At this point the project manager is told that the product cannot pass acceptance and the project may be terminated. What is the most likely cause?
Show answer and explanation
Correct answer: C
On an internal scheduling system project, schedule, cost, scope and quality measurements all match the baselines, yet the project manager is told the product cannot pass acceptance and the project may be terminated. The most likely cause has to be judged.
The stem rules out the internal causes one by one: the quality standard was set high, the stem also says the quality measurements met the standard, and schedule, cost and scope show no deviations. The work was done exactly to plan and the result was still rejected, which shows the plan itself left something out. The most common omission is a key stakeholder who was not identified, whose requirements never entered the requirements documentation or scope, so the product naturally does not match. People who were not identified often become the source of later risks, so the answer is C.
Why the other options are wrong
- A. The stem makes clear the quality standard was high and the quality measurements met it, so quality is not the cause.
- B. A sponsor withdrawing support could indeed end a project, but the direct trigger in the stem is that the product cannot be accepted, and nothing points to the sponsor's attitude.
- D. The stem does not show the team meeting an insurmountable technical obstacle; on the contrary it shows the planned scope and the set quality standards were achieved. That cannot explain “completed to plan yet cannot be accepted” the way a missed key stakeholder and their requirements can.
Key takeaway When all the work conforms but the product is not accepted, first suspect that a key stakeholder was not identified and their requirements were not collected.
Variation If the schedule were badly behind and costs overrun, the answer would turn to technical difficulty or resource problems. When the signal changes from “everything matches the baseline” to “deviations appear”, the cause changes with it.
- Question 43
Three months after an online education company’s learning platform goes live, the project manager finds that an interactive Q&A feature, which passed acceptance, is hardly used. What should the project manager do?
Show answer and explanation
Correct answer: D
Three months after the learning platform goes live, an interactive Q&A feature that passed acceptance is hardly used. What should the project manager do?
Deliverables are used to produce outcomes, outcomes create benefits, and benefits create value. A feature that has been delivered but is not used means the chain has broken at the outcome link, and there is a gap between the outcome and the expected value. While the reason is unknown, first investigate why the feature is not used and assess how large the gap is, then decide how to improve. The signal in this type of question is “accepted but not used”: acceptance shows that delivery met requirements, while usage shows whether an outcome was produced, so turn to investigating the outcome rather than going back to check the delivery process. The answer is D.
Why the other options are wrong
- A. Acceptance shows only that the work was done to requirements, not that it has value. Delivering a deliverable is not the same as creating value, and “no further follow-up” ignores value.
- B. Adding more interactive features while the reason is unknown only increases investment. It may not solve the lack of use and may amplify waste.
- C. Pausing other work and reworking everything without knowing the cause may fix the wrong thing. Investigate first, then decide whether rework is needed.
Key takeaway Delivering a deliverable does not mean value has been realized. When something is not used, find the cause first and assess the value gap.
Variation If the investigation finds that the entry point is buried too deep and users cannot find it, a low-cost remedy such as better guidance and training may be more appropriate than rework.
- Question 44
During execution, an experienced test engineer tells the project manager that because of a scheduling conflict in his department's operations, he cannot take part in this project's activities at the times scheduled. What should the project manager do?
Show answer and explanation
Correct answer: D
During execution, an experienced test engineer says that a scheduling conflict in his department's operations means he cannot take part in this project's activities at the scheduled times. The question asks how the project manager should handle this.
PMBOK 8 notes that internal resources are assigned by functional managers or resource managers. The operations schedule is controlled by the engineer's functional manager, and only he has the authority to adjust it. The project manager should negotiate with that manager to see whether the operations schedule can be adjusted or staggered so that the member can take part in project activities. This both keeps this key team member and respects the department's authority. The answer is D.
Why the other options are wrong
- A. The engineer is experienced and valuable to the project, and the only issue is a scheduling conflict. Replacing him without discussion loses a key person and does not resolve the root of the conflict.
- B. Looking up replacements does not resolve the scheduling conflict, so this member still cannot take part, and the PMO does not manage members' operations schedules.
- C. The schedule was set by the functional manager, and the member has no authority to change his department's operations plan. Insisting that he put the project first would leave him caught between two bosses and goes around the functional manager.
Key takeaway When a member's time is taken by departmental work, negotiate an adjustment with his functional manager rather than replacing him or pressing him.
Variation If the negotiation gets nowhere and the operations work really cannot yield, then consider assessing a replacement or adjusting the schedule through change.
Reference Negotiation · Lesson 1: Purpose and Parties of Negotiation: Whom to Ask for Resources, with a Win-Win Goal
- Question 45
A project manager is implementing an inventory management system for a supermarket chain. Through Monitor and Control Scope, the project team has checked and confirmed that the system is correct, producing verified deliverables. What should the project manager do next?
Show answer and explanation
Correct answer: B
Through Monitor and Control Scope, the project team has checked and confirmed that the inventory management system is correct, producing verified deliverables. The question asks what the project manager does next.
The stem states that the project team checked and confirmed the system through Monitor and Control Scope, so verified deliverables have been produced; these are the input to Validate Scope. Before the system goes to the customer for use, the customer or another stakeholder with acceptance authority must formally accept it against the acceptance criteria, and a formal acceptance record is kept as the contract or the organization requires. The step after verification and before closure is Validate Scope. The answer is B.
Why the other options are wrong
- A. The final report belongs to closure and makes sense only after the deliverables have been accepted.
- C. The deliverables have not yet been formally accepted, so the project cannot move straight into closing the project or phase.
- D. Handover to operations also comes after acceptance. Handing over before acceptance bypasses the customer's formal acceptance.
Key takeaway Passing a quality check is only verification; to hand over the deliverable, it still has to be accepted in Validate Scope.
Variation If the customer has already signed off acceptance, the next step is Close Project or Phase and handover. If testing finds defects, submit a change request for defect remedy; after approval and repair, the work is inspected and reverified through Monitor and Control Scope before it goes to Validate Scope.
- Question 46
A home appliance manufacturer's smart panel development project has just started. The members come from the engineering, purchasing and quality departments, and their cooperation is critical to the project's success. How should the project manager develop an effective team charter?
Show answer and explanation
Correct answer: B
A smart panel development project has just started. Members come from engineering, purchasing and quality, and their cooperation is critical to the project's success. The question is how to develop an “effective” team charter, so the key is the method of development.
The team charter works best when the team develops it or at least has an opportunity to contribute to it. The process of discussing values, roles and responsibilities, and working rules itself builds consensus and commitment, and members follow the rules willingly once they accept them. The kickoff meeting is a suitable occasion for a new team to discuss together, with the project manager facilitating. The stem stresses “effective” and “cooperation is critical,” so the answer is B.
Why the other options are wrong
- A. A charter the project manager writes alone and then sends out expresses personal expectations. Members did not take part, so they will not feel it is “their own agreement.” Buy-in is low and compliance is not assured.
- C. Handing the drafting to one senior member still shuts everyone else out and merely swaps one ghostwriter for another. The charter needs the participation of all members, not an announcement of the result to the team.
- D. A template can be the starting point for discussion, but letting members change only the wording cannot replace the team discussing and reaching consensus together, and it does not reflect the cooperation between this project's three departments.
Key takeaway Have all members take part in developing the team charter, so that buy-in and compliance are assured.
Variation If “a new member joins and finds the charter no longer fits,” review and update it together with all members, rather than announcing the old rules one-way.
- Question 47
A software company launches an internal systems development project, and the project manager begins financial planning. What should the project manager do FIRST in this work?
Show answer and explanation
Correct answer: A
The project manager has just begun financial planning and needs to decide the first step of that work.
Financial planning has to answer “how much money does the project need, when, and from where”. Payment methods, settlement cycles, staffing and placing purchase orders are all follow-up actions built on that answer. Discussing them before the funding requirements are clear easily produces arrangements that do not match actual needs. So the first step is to compile and analyze the project's funding requirements. The answer is A.
Why the other options are wrong
- B. Payment methods and settlement cycles depend on the size and rhythm of the funding requirements. Agreeing on them before the requirements are analyzed gets the order backward.
- C. Placing purchase orders is a spending action. At this point it is not even clear how much money is needed or whether the budget has been approved, so this is a hasty move that also bypasses procurement planning.
- D. Whether a full-time accountant is needed depends on the workload of funds management, which can be judged only after the requirements analysis. It is not the first step.
Key takeaway When planning project finances, analyze funding requirements first, then talk about payment methods, staffing and procurement. First work out how much is needed and when, and then arrange payments, people and purchasing.
Variation If the question asks for “the next step after the funding requirements analysis”, it is to plan how expenditures will be tracked and how financial reports will be produced, and to settle funding sources and contingency arrangements.
Reference Estimate Costs · Lesson 1: The Financial Management Plan, Funding Strategies and Estimate Accuracy
- Question 48
During development and testing, the team keeps talking directly with the customer, has the customer take part in testing in person and takes in feedback promptly, so that the final product stays aligned with the customer's expectations and needs. Which tool or technique of Validate Scope is this?
Show answer and explanation
Correct answer: D
In development and testing, the team keeps talking directly with the customer, has the customer take part in testing and listens to feedback. The question asks which tool or technique of Validate Scope this is.
The signals in the stem are “development and testing phases,” “direct interaction,” “feedback” and “keeping the product aligned with customer expectations and needs.” PMBOK 8 describes customer talks and tests as the collaborative processes and activities involving direct interaction and feedback from customers during the development and testing phases of a project, which enhance transparency and build trust. It is listed alongside inspection, process analysis and review meetings as a tool and technique of Validate Scope. The answer is D.
Why the other options are wrong
- A. Process analysis identifies opportunities for process improvement and examines problems, constraints and non-value-added activities. Its object is the process, not interaction with the customer.
- B. Data analysis is for analyzing work performance data, variances and the like. It is a way of working with data, not a collaborative activity of talking directly with the customer and having the customer test.
- C. A review meeting is a meeting held to review deliverables, a single concentrated event. The stem stresses continuing interaction during development and testing, not one review.
Key takeaway Continuing interaction with the customer during development and testing, and collecting feedback, is customer talks and tests.
Variation If the project manager convenes customer representatives to review a completed deliverable together and decide whether to accept it, that corresponds to a review meeting or inspection.
Reference Validate Scope · Lesson 2: Inputs and Tools of Validate Scope: What You Check Against and How
- Question 49
Because of industry regulation, the project manager of an insurance core-system project uses a hybrid approach: up-front planning and the final closing are done predictively, and development in between is done in iterations. At the third iteration review, the sponsor asks on the spot to move several requirements in the product backlog higher up. As a servant leader, what is the MOST appropriate next step for the project manager?
Show answer and explanation
Correct answer: D
An insurance core system is under regulation and uses a hybrid approach: up-front planning and closing are predictive, and development in the middle is iterative. At the third iteration review, the sponsor asks on the spot to move several requirements higher in the backlog. The project manager is a servant leader. What is the most appropriate next step?
During iterative execution, ordering the backlog by priority is the responsibility of the product owner, and in an adaptive environment it is the product owner’s core duty to represent business value. The sponsor’s input should be weighed and ordered by the product owner. The role of a servant leader is to support the role and protect the team, not to decide in place of the product owner or the team, so the project manager should assist the product owner. The answer is D.
Why the other options are wrong
- A. Adjusting backlog priorities within iterations does not go through the change request process; the change control board approves changes that touch baselines, and using it to handle backlog ordering would cost the iteration its flexibility.
- B. The schedule management plan is a guiding document describing how the schedule will be managed. It contains no specific schedule information, so assessing it does not answer who decides priorities.
- C. Agreeing on the spot and scheduling the items directly into the next iteration bypasses the product owner and bypasses the way the team determines iteration content from the ordered backlog.
Key takeaway Backlog ordering within iterations belongs to the product owner; a servant leader assists and does not decide for the product owner.
Variation If a new requirement would change the formally controlled overall scope baseline or another predictive baseline, handle it through the project’s agreed change control process; if it concerns only backlog items in the iterative part that have not yet been committed, the product owner usually orders and approves them dynamically.
Reference Hybrid Approaches · Lesson 2: Transitioning Gradually to a Hybrid Approach, and Managing a Hybrid Environment
- Question 50
An agile team is developing a back-office management system for a customer. The original plan was to use a Java framework the team knows well, but the customer prefers Go and asks for the change. The team is not familiar with Go and productivity has dropped. To raise the team's productivity, what should the Scrum Master do?
Show answer and explanation
Correct answer: D
An agile team planned to use a Java framework it knows well, but the customer prefers Go. The team is not familiar with Go and efficiency has dropped. The question asks what the Scrum Master should do to raise productivity, and the root cause is a skill gap.
The root cause of the drop in efficiency is the team's unfamiliarity with Go, which is a skill gap. PMBOK 8 says that when competency mismatches are identified, proactive responses such as training, hiring, schedule changes or scope changes are initiated, listing them side by side. Training existing members first and only then considering experts or replacements is common exam practice. One of the Scrum Master's responsibilities is to serve and support the team, so arranging additional training is the most direct response. The correct answer is D.
Why the other options are wrong
- A. Asking the customer to identify the risks of switching to Go hands the work to the customer. Risk identification should be done collaboratively by the project team, and customers and other stakeholders can join in. It also does nothing about the efficiency drop itself.
- B. A temporary drop in efficiency does not make the Sprint Goal obsolete, so it is not a reason to cancel the Sprint; moreover, only the Product Owner has authority to cancel a Sprint.
- C. Hiring an expert to replace some members costs more and disturbs the team more, and the stem does not show that training would come too late. It would also hurt morale. When the existing team can be developed, first raise the existing members' skills, then consider an outside expert.
Key takeaway When skills do not match, train the existing team first, and only then consider bringing in outside experts or replacing members (common exam practice).
Variation If the Sprint must deliver quickly and there is no time for training, you could invite an outside expert to pair with and guide the team for a short period while arranging learning for the team, keeping dependence on the expert to a minimum.
Reference Team Performance · Lesson 2: Training, Coaching and Mentoring: Find the Gap First, Then Choose the Remedy
- Question 51
A key regional government digital services project is in the Executing focus area. One time-boxed activity needs the expertise and guidance of a foreign vendor’s expert to complete commissioning, and the team can handle the on-site work. Because of entry restrictions, the expert cannot come, the activity cannot be done without his expertise, and the team is looking for a way to finish on schedule. How should the project manager help the team?
Show answer and explanation
Correct answer: B
A digital government project is in the Executing focus area. A time-boxed commissioning activity needs the expertise and guidance of a foreign vendor’s expert, and the team can do the on-site work. Entry restrictions keep the expert away, and without his expertise the activity cannot be done. The question asks how the project manager should help the team.
What the activity needs is the expert’s knowledge and guidance. The expert cannot come on site and the activity cannot wait, so the most direct approach is to bring the expert into the team through communication technology: set up a video conference and let the expert guide the team online through the commissioning. This obtains the expert’s knowledge without being affected by the entry restrictions and protects both time and quality. The answer is B.
Why the other options are wrong
- A. It is uncertain when the restrictions will be lifted, and the activity is time-boxed, so waiting indefinitely would drag down the overall schedule.
- C. Training the team to expert-level commissioning skills would take a long time and extra money, which is not realistic under a time limit.
- D. A lessons learned repository might help, but searching takes time and may turn up no similar approach. It is less reliable than having the expert guide the team remotely.
Key takeaway When an expert cannot be on site, having the expert take part remotely through video conferencing or similar technology protects both time and quality.
Variation If the stem said the expert could not use video tools, first make sure a tool is available, replacing it if necessary with one everyone can use. If the activity were not time-boxed, waiting for the expert to arrive could also be considered.
- Question 52
A new energy company recruited a group of highly skilled engineers from several cities for its battery management system development project. The members are spread across different cities and have very different work styles and practices; since the start of work, arguments have been constant and progress is slow. To avoid this situation, which document should the project manager have guided the team to develop beforehand?
Show answer and explanation
Correct answer: D
The engineers on a battery management system project come from several cities and have very different work styles and practices. Since the start of work there have been constant arguments and slow progress. The question asks which document the team should have been guided to develop beforehand to avoid this.
The root of the arguments is that members have no shared expectations of “how we work together.” The team charter records the team's values and the agreements and operating guidelines the team settled on. It spells out communication rules, decision-making methods, conflict handling, and meeting and discipline requirements in advance, and sets clear expectations for acceptable behavior; the earlier everyone commits to it, the fewer the misunderstandings. The signals in the stem are “differences in habits” and “beforehand.” The answer is D.
Why the other options are wrong
- A. The project management plan integrates the baselines and subsidiary plans and governs how the project is executed, monitored and closed. It does not set behavioral rules for members.
- B. The risk management plan covers how risks are identified, analyzed and responded to. Even if disagreements among members become a risk, it is not what unifies behavior in advance.
- C. The stakeholder engagement plan deals with strategies for engaging external and internal stakeholders and does not contain the working rules of members inside the project team.
Key takeaway When members' styles differ greatly and conflict is likely, align expectations in advance through the team charter.
Variation If the stem asked “which document formally authorizes the project and gives the project manager authority to apply organizational resources,” the answer would be the project charter; if it asked “what to do when you find nobody follows the communication guidelines,” go back to the team charter and renegotiate with the team.
- Question 53
A project manager leads a team developing an in-vehicle navigation app. The team consistently completes its tasks on time, but delivery quality keeps declining. The project manager suspects a lack of training is the cause. How should the problem be resolved?
Show answer and explanation
Correct answer: D
An in-vehicle navigation team always completes tasks on time, but delivery quality keeps declining, and the project manager suspects a lack of training. The question asks how to resolve the problem.
“Suspecting a lack of training” is only a hypothesis and has to be verified first. First analyze the root cause of the decline in quality, confirm whether a skill gap exists, find out which skills are missing and who lacks them, and derive the training needs. Then train in a targeted way. This follows the order “assess the gap first, then choose the remedy,” which saves training cost and addresses the real problem. If you skip the analysis and train straight away, you may train people on things they do not lack, spending money and hours while the quality problem remains. Only after analysis do you know whether the issue lies in tool use, testing methods or understanding of requirements. The correct answer is D.
Why the other options are wrong
- A. A team-building workshop improves collaboration and morale. It does not touch the suspected root, which is a skills or training shortfall.
- B. Bringing in new members assumes the existing members cannot be improved through training. It does not first tap the team's potential and it adds cost.
- C. A stricter appraisal system only adds pressure. If the quality decline comes from a lack of skills, appraisal does not fix it.
Key takeaway When you suspect a lack of training, analyze the cause of the quality decline and confirm the skill gap first, then train in a targeted way.
Variation If quality is still declining after the training, the next step is root cause analysis of the quality problem (the cause may not be a training shortfall), followed by targeted measures.
- Question 54
A park landscaping renovation project has passed acceptance and the deliverables have been handed over. The company's finance department pays the contractor the amount stated in the contract, but the contractor refuses to accept it, saying it is less than the amount the project manager promised orally earlier. What should the project manager do?
Show answer and explanation
Correct answer: C
A park landscaping renovation has passed acceptance and been handed over. Finance pays the contract amount, but the contractor refuses it, saying it is below what the project manager promised orally before. The question asks what the project manager should do.
Payment is based first on the contract in force. An oral promise that was not approved through the contract change procedure cannot directly replace the contract amount; its effect must be checked against the contract, change records, and the project manager's authority, with legal guidance if necessary. PMBOK 8's claims guidance emphasizes understanding contract terms, preserving activity and communication records, communicating clearly, and working with legal counsel. The project manager should therefore involve the procurement team to handle the contractor's claim under the contract and records, seeking legal support when needed. The answer is C.
Why the other options are wrong
- A. Recording it in the issue log is only logging. It does nothing to move the dispute toward resolution, the payment stays unsettled, and the contract cannot be closed.
- B. The payment amount is set by the contract, which the procurement department manages. Having the sponsor decide would delay handling and bypass the contract management function.
- D. The contract amount is indeed the basis, but simply rejecting the claim escalates the conflict. Dealing with the contractor is contract management and should be led by the procurement team that knows the terms.
Key takeaway In a payment dispute, the contract in force governs, and an oral promise not approved in writing through the change procedure cannot be used as the basis for payment. Have the procurement team handle it under the contract, and the project manager must not make promises on their own.
Variation If the project manager's oral promise has been recorded in writing and approved through the change procedure, the contract amount is adjusted accordingly and payment follows the new contract.
Reference Monitoring and Controlling Procurements · Lesson 3: Claims Administration and Alternative Dispute Resolution
- Question 55
To meet the go-live milestone the sponsor promised, the team of a smart campus project proposes shortening the third-party safety compliance assessment, which is mandated by regulation. What should the project manager do?
Show answer and explanation
Correct answer: D
The project is close to go-live, and schedule pressure conflicts with a mandatory compliance requirement. The question asks how the project manager should handle it.
Compliance is the bottom line, and a third-party assessment that regulation mandates cannot be cut to save time. The project manager keeps the full assessment and communicates with the sponsor to win time by adjusting the schedule, crashing and so on, balancing the two. Of the four options, three subtract from compliance and only one finds a way on the schedule. In addition, crashing and adjusting the schedule may add cost or risk, so analyze them under the governance and change procedures and obtain support or approval from the sponsor or another authorized person when the decision exceeds the project manager's authority; compliance cannot be sacrificed in any case. The answer is D.
Why the other options are wrong
- A. Completing the assessment after go-live means operating in a noncompliant state, against the mandatory requirement of the regulation.
- B. Assessing only the high-risk modules abandons compliance verification for the rest and also does not meet the mandatory requirement.
- C. Leaving the scope of the assessment for the team to trim means the project manager has given up gatekeeping on compliance requirements.
Key takeaway When compliance conflicts with schedule, compliance does not give way. Resolve it by communicating and adjusting the schedule.
Variation If the assessment were an advisory internal check and not a regulatory mandate, you could weigh adjusting its scope with the sponsor. Mandatory requirements are not in that category.
- Question 56
The project manager has an AI tool generate a draft WBS. What should be done next?
Show answer and explanation
Correct answer: C
The project manager has an AI tool generate a draft WBS, and the question asks what to do next. The draft was written by AI, so decide which adoption strategy this falls under and what the person should do.
Drafting a WBS is “assistance”: AI complements the analysis and iteratively builds toward the expected output. PMBOK 8 is explicit that the result of the first iterations should not be considered complete without further analysis and refinement, and that a project professional should review the results to ensure they are accurate and complete. So next you review and correct the draft, check whether it covers the entire scope (the 100% rule), and only then use it as the formal WBS. The answer is C.
Why the other options are wrong
- A. Issuing it directly treats an unreviewed first draft as the final deliverable. The scope may have gaps or overlaps, and this goes against the requirement that assistance needs human review.
- B. Merely saving it without further handling neither uses the value of AI nor completes the WBS.
- D. An AI draft can perfectly well be used once it has been reviewed and refined, so there is no reason to discard it wholesale. PMBOK 8 encourages understanding and using AI, with people as the gatekeepers.
Key takeaway “Assistance” produces a first draft, which must be reviewed and corrected by a person before it is used.
Variation If the same task were changed to “compile a weekly report in a fixed format”, it would be automation: the prompt can be reused, with outputs reviewed in proportion to risk and the established quality criteria. If it were changed to “discuss whether to start the next phase early”, it would be augmentation, with AI as a brainstorming partner.
- Question 57
An e-commerce system project has been totaling the cost of quality data for the four categories (prevention, appraisal, internal failure and external failure) every month, but nobody has been using it. What should the project manager do?
Show answer and explanation
Correct answer: A
An e-commerce system project has been totaling the cost of quality data for the four categories every month, but nobody has been using it. The question asks what the project manager should do.
The value of cost of quality lies in using it: analyze the share of each of the four categories, judge whether prevention, appraisal and failure costs are balanced, and then adjust quality spending accordingly. Data that is only collected and never analyzed neither lowers cost nor improves quality. The analysis covers each category's share, the trend over time and the largest single items, and then adjusts prevention and appraisal spending in light of the idea of the optimal cost of quality. So analyze the cost of quality data and optimize quality spending accordingly. The answer is A.
Why the other options are wrong
- B. Continuing to collect and filing it until closure means storing it without using it, and quality cannot be improved.
- C. Reducing the totaling frequency cuts the information available for decisions and does not address the problem of nobody using it.
- D. Cost of quality is project cost management information. The project manager may delegate analysis work but should ensure the data is used and must not hand all project decision accountability to the quality department.
Key takeaway Cost of quality data must be analyzed and used to optimize prevention and appraisal spending.
Variation If the analysis finds that external failure takes a very high share while prevention is very low, analyze the causes and cost-benefit balance before making targeted changes to prevention or appraisal spending. If prevention and appraisal are already very high and failure costs are very low, compare the marginal benefit to determine whether spending is excessive.
- Question 58
In the culture of most team members, saving face matters and people are reluctant to oppose others openly. Almost no one raises objections at any review meeting, and the project manager worries that real hidden problems are being kept quiet. How can the project manager get members' true views?
Show answer and explanation
Correct answer: C
Most team members come from a culture that values saving face and avoids openly opposing others. Almost no one raises objections at review meetings, and the project manager worries that real problems are being hidden. The question asks how to get their true thinking.
PMBOK 8 notes that differences in communication style can stem from nationality, ethnicity and the like, and that people from different cultural backgrounds prefer different communication processes and protocols. Members who do not object in public are following cultural habit, not lacking views. To get honest views, use a way that removes the pressure of speaking in public: an anonymous channel outside meetings and private one-on-one conversations. Neither requires anyone to damage another person's face in front of others. The answer is C.
Why the other options are wrong
- A. Asking everyone to take a position in public is exactly what they least want to do. A longer meeting only adds pressure and mostly produces polite answers.
- B. Written, signed comments still make people publicly accountable for their opinions, which is heavy pressure for people who value face, and they still will not say what they think.
- D. Recording only what is said openly yields surface information, and the hidden problems stay unseen. Knowing problems may exist and not asking further gives up the project manager's duty.
Key takeaway For a team that does not speak up in public, use anonymous and private one-on-one channels to hear the truth.
Variation If the team culture is direct, open discussion at the meeting is enough and no special anonymous channel is needed.
Reference Managing and Monitoring Communications · Lesson 4: Tailoring Communication and Common Scenarios: Virtual Teams, Time Zones and External Stakeholders
- Question 59
A product team is working out how to improve its existing home water purifier. The marketing director comes to the project manager and wants to make sure everything needed for a successful launch of the new product is in place. What should the project manager focus on FIRST?
Show answer and explanation
Correct answer: B
A product team is improving a home water purifier, and the marketing director wants to be sure that all preparation for a successful launch is in place. What should the project manager focus on?
“Successful launch” is first a question of how success is measured. Without agreed performance metrics, you cannot judge whether preparation is in place or whether the launch succeeds. The project manager should first align with the marketing director and key stakeholders on the performance metrics for assessing success, such as first-release sales, market share and customer satisfaction, and then check the preparation against them. The other options are all about “doing,” while this one is about “setting the standard.” Without a standard, however much you do, you cannot prove success, so align the metrics first. The answer is B.
Why the other options are wrong
- A. A change management plan governs changes during the project and cannot answer how success is measured.
- C. Regular updates reflect only work progress and cannot tell you whether the launch will be a success.
- D. A scope management plan ensures that the work that should be done gets done, but it cannot measure commercial success.
Key takeaway For everyone to share one standard of “success,” align the performance metrics first.
Variation If asked how the metrics should be determined, the answer is to agree them with the sponsor and key stakeholders. If asked which item suits as a success metric, choose one that is specific, measurable, result-oriented and time-bound, not a measure of effort put in.
- Question 60
Your team is developing an inventory system for a supermarket chain. After the first Sprint has completed several features, you want the team to show stakeholders the work products completed to achieve the Sprint Goal. When should they be shown?
Show answer and explanation
Correct answer: B
On a project, the first Sprint has completed several features, and you want the team to show stakeholders the work products completed to achieve the Sprint Goal. When should they be shown?
The Sprint Review is held near the end of the Sprint. The Scrum Team presents its results to key stakeholders, and together they inspect the Sprint outcome and progress toward the Product Goal, consider changes in the environment, and determine useful adaptations; the Product Backlog may be adjusted accordingly. Increments that meet the Definition of Done may be presented, but the review is a working session and should not be limited to a demonstration. So the answer is B.
Why the other options are wrong
- A. A weekly update meeting with the customer is not an event prescribed by the agile framework and is not designed for demonstrating the Sprint's Increment, so it cannot replace the review.
- C. The Sprint Retrospective is for the team to look back at how it works and improve the process. It is aimed at the team internally and is not a meeting for showing results.
- D. The Daily Scrum is a 15-minute progress synchronization that inspects progress toward the Sprint Goal. It is not an occasion for demonstrating results.
Key takeaway The Sprint Review inspects the Sprint outcome and determines future adaptations, including presenting completed Increments.
Variation If the question asked what to do when a customer proposes an urgent new feature at the review, the answer is to record it in the Product Backlog and discuss it at the next Sprint Planning, not to change the current Sprint on the spot.
- Question 61
On the e-commerce team of a retail company, several dominant members always take over the discussions and team performance is falling. Management has stepped in once already. An agile project manager has recently taken over this team. When he first arrives, what is the MOST appropriate thing to do?
Show answer and explanation
Correct answer: C
On a team using an agile approach, several dominant members always dominate discussions and performance is falling, and management has intervened once. A new agile project manager has just arrived, and the question asks for the most appropriate thing to do.
The key signal is “just taken over”: you do not yet know the team, so do not rush to apply a solution or make personnel decisions, but gather facts first. Review the velocity data to understand the trend in the team’s delivery rhythm and capacity (velocity is used for capacity forecasting of the same team and does not by itself equal a performance appraisal), and observe the interactions among members to find the root cause and pattern of the conflict, and then deal with it accordingly. The answer is C.
Why the other options are wrong
- A. Copying the earlier conflict-resolution plan without knowing the team is poorly targeted and may deepen the conflict. After all, management’s first intervention did not solve the problem.
- B. Listening only to the most vocal members lets the dominant voices keep controlling things, ignores the team as a whole, and does nothing to improve the team’s participation.
- D. Moving people out is a later step and should not be the goal on arrival. Understand the situation and the root cause first, instead of presupposing that people have to be replaced.
Key takeaway When taking over a team with problems, first learn the facts and observe the interactions, and then address the cause.
Variation If observation shows the conflict comes mainly from the behavior of certain members, talk to them individually and set a team agreement to constrain the rules of discussion.
Reference Project Charter · Lesson 5: What a Project Manager Does First When Taking Over a Project
- Question 62
The development team on a cross-border e-commerce platform project is in Shanghai, and the subject matter expert is on the east coast of the United States, about 12 hours apart during daylight saving time. What can the project manager do to improve interaction between members at the two locations?
Show answer and explanation
Correct answer: D
The development team in Shanghai and the subject matter expert on the US east coast are about 12 hours apart, which is a virtual team communication problem. The question asks how to improve interaction between the two locations.
Communication planning becomes more important in a virtual team environment. Choosing a suitable virtual communication method and then holding regular team meetings with it gives members at both locations a fixed, predictable channel for interaction. It takes the time difference into account and is both feasible and low in cost. The answer is D.
Why the other options are wrong
- A. With a 12-hour difference, having both sides work at the same time means one side works in the middle of the night, which harms rest and efficiency and is not realistic.
- B. Having the expert attend every scope planning review only involves him in one kind of meeting. It does little to improve day-to-day interaction between the two locations and does not solve the communication difficulty caused by the time difference.
- C. With great distance and a 12-hour difference, frequent face-to-face meetings are expensive and hard to arrange, and they defeat the purpose of having a virtual team.
Key takeaway With a large time difference and distance, first choose a virtual communication method, then schedule regular meetings that use it.
Variation If the stem asked about members missing meetings because of the time difference, the answer would be complete minutes plus asynchronous participation, with meeting times rotated. If the two sites had one hour of overlap, put the important conversations in the overlap.
- Question 63
PMLyceum has set up three regional divisions: North, East and South. Each division has its own sales, finance and procurement departments, and headquarters sets only annual financial targets for the divisions. The East division's project manager must coordinate the division's resources to push a delivery project forward. Which statement about this organizational form is MOST accurate?
Show answer and explanation
Correct answer: A
The company has set up North, East and South regional divisions, each with its own sales, finance and procurement departments, and headquarters sets only annual financial targets. The East division's project manager must coordinate the division's resources for a delivery project. The question asks for the most accurate statement about this organizational form.
A multidivisional organization may be arranged by product, production process, portfolio, program, geographic region, or customer type, with functions replicated across divisions and little centralization; its project manager typically has low authority, a part-time role, and low resource availability. Divisions set up by geographic region, each replicating functions, fit this type, and the project manager's authority is usually low. The answer is A.
Why the other options are wrong
- B. A project-oriented organization arranges teams by project, and the project manager's authority is high to almost total. In the stem the divisions are standing regional units, not teams formed around projects.
- C. A strong matrix needs functional and project lines to cross, with a full-time project manager of moderate to high authority. The stem has no such cross-reporting relationship.
- D. A virtual (network) structure has nodes at points of contact with other people. The divisions are standing regional departments, so this does not fit.
Key takeaway Multidivisional: divided by region, product and so on, functions may be replicated, and the project manager's authority is usually low.
Variation If the same company also set up a cross-division project office in which full-time project managers allocate people centrally, the structure would be closer to a strong matrix.
Reference Organizational Structures · Lesson 2: Other Organizational Forms and Comparing Structures
- Question 64
A software company agrees with a customer to receive a single project payment of $133,100 three years from now. The finance department uses a discount rate of 10% per year. What is the present value of this payment today?
Show answer and explanation
Correct answer: B
This is the most basic discounting calculation in the Finance performance domain: given a future amount, a discount rate and a number of years, find the value today.
Present value converts future money into today's value with PV = FV ÷ (1 + r)ⁿ. You discount for as many years as there are, and you must divide. At a discount rate of 10% per year, $133,100 received three years from now has a present value of exactly $100,000. The answer is B.
- Substitute into PV = FV ÷ (1 + r)ⁿ with FV = 133,100, r = 10% and n = 3
- (1 + 10%)³ = 1.1 × 1.1 × 1.1 = 1.331
- PV = 133,100 ÷ 1.331 = $100,000
- Check: 100,000 × 1.331 = 133,100, matching the payment in three years, so the answer is B
Why the other options are wrong
- A. $93,170 = 133,100 × (1 − 3 × 10%) = 133,100 × 0.7. This subtracts the discount rate as simple interest instead of discounting year by year with compounding.
- C. $121,000 = 133,100 ÷ 1.10 discounts for only one year and leaves out the other two years.
- D. $177,156 = 133,100 × 1.331 turns the division into multiplication, producing a larger amount three years out. The direction is wrong.
Key takeaway Present value = future amount ÷ (1 + discount rate)ⁿ. Discount for as many years as there are, and always divide.
Variation If the discount rate were 8%, present value = 133,100 ÷ 1.08³ ≈ $105,659. If the $133,100 were received two years from now, present value = 133,100 ÷ 1.21 = $110,000.
- Question 65
A shared EV-charger maintenance and upgrade project in a residential complex is in execution, and team members keep reporting potential risks to the project manager. The project manager wants to categorize these risks by source of risk. What should be used?
Show answer and explanation
Correct answer: D
The project is in execution and team members keep reporting potential risks. The project manager wants to categorize the risks by source of risk. The question asks which tool or document to use.
The key clues are “by source of risk” and “categorize”. The risk breakdown structure (RBS) is a hierarchical representation of potential sources of risk. It is generally divided into the categories technical, management, commercial and external and then broken down further, which is just what is needed to sort identified risks by source, and it can also show which source categories hold the concentrated risk. The answer is D.
Why the other options are wrong
- A. The work breakdown structure decomposes the work, dividing it by deliverables and work packages. It can be used to categorize by area of the project affected, but not by source of risk.
- B. The risk report summarizes the latest status of overall project risk and individual risks. It is an output document and provides no categorization framework.
- C. The risk register records the information about identified risks. It does not itself provide a hierarchical structure for categorizing by source; for that you use the RBS.
Key takeaway Categorize by source with the RBS; categorize by area affected with the WBS.
Variation If the stem were changed to “categorize risks by area of the project affected”, the WBS could be used. If it were changed to “summarize the overall risk situation for the sponsor”, the answer is the risk report.
- Question 66
A project manager is assigned to a new sales promotion project. The sponsor hands over an approved project concept document and a draft plan that list the scope, business needs, deliverables and stakeholders, but do not give the project manager any authority to use organizational resources. The sponsor says the project is small and simple and that no project charter needs to be prepared. What should the project manager do?
Show answer and explanation
Correct answer: C
The sponsor hands over an approved concept document and a draft plan (with nothing authorizing the project manager) and says the project is small and needs no charter. The question asks what the project manager should do now.
The key signal is “no charter needs to be prepared”. The Eighth Edition notes that authorization is typically, but not always, done through a project charter. The charter also records the high-level scope and objectives, whereas this document lists scope, business needs, deliverables and stakeholders; it does not authorize the project manager, so it cannot replace a formal authorization such as a charter, and a small project is not exempt from authorization. When the sponsor takes a different view, the project manager’s first step is to explain to the sponsor what the charter is for and why it is needed, so that the decision maker can reconsider once informed. The answer is C.
Why the other options are wrong
- A. Asking peers goes around the real decision maker. Whether to have a charter is something for the project manager and sponsor to clarify between themselves, and peers’ opinions cannot decide it.
- B. The charter is approved and issued by the sponsor. Drafting one and handing it over before the disagreement is cleared up is acting first and talking later, and only puts you in a weaker position.
- D. The document contains the scope, business needs and deliverables, but it still gives no basis for authority. Agreeing outright means giving up the project manager’s formal authority.
Key takeaway When the sponsor says no charter is needed, first clarify what the charter’s authorizing role is. Neither accept it nor work around it.
Variation If the sponsor agrees to a charter but cannot sign it for a long time, first check who the charter lists as “other persons authorizing the charter” and have that person approve. If the question asks who issues the charter, the answer is the sponsor or initiator.
- Question 67
For half a year a project manager has been unable to settle the project scope. The team and the client keep revising the requirements, and the schedule drags on longer and longer. What should the project manager do to finish defining the scope?
Show answer and explanation
Correct answer: B
For half a year the project manager has been unable to settle the project scope. The team and client keep revising the requirements and the schedule keeps stretching. The question asks what to do to complete the scope definition.
The core problem is that the parties have no consensus on the requirements. A facilitated workshop is one of the meeting types listed in PMBOK 8: it brings key stakeholders together, and a facilitator guides the discussion toward agreement on the deliverables and on the project and product boundaries. It speaks directly to “opinions keep changing and nothing can be finalized.” Choose a tool that fits the problem: if consensus is missing, use a meeting-based technique that builds consensus; if information is missing, use techniques that gather information, such as interviews or questionnaires. The answer is B.
Why the other options are wrong
- A. Training improves team skills, but it cannot resolve the present disagreement among the parties that is keeping the scope from being settled.
- C. Reviewing the collected requirements again offers no mechanism for resolving the disagreement, so the cycle of revisions may simply continue.
- D. Finalizing the requirements inside the team and then sending them to the client bypasses client participation and is likely to trigger another round of revisions.
Key takeaway When opinions diverge and consensus is needed, use a facilitated workshop.
Variation If the stakeholders agree but are numerous and geographically scattered, switch to a technique that collects input uniformly, such as a questionnaire.
- Question 68
On two earlier engineering projects, a project manager worked with the same group of members and personally checked and managed every step. The members are now experienced and self-driven, and he wants to try a different approach: letting the team set its own goals and make its own decisions. Which leadership style should he adopt?
Show answer and explanation
Correct answer: C
On two earlier projects, the project manager personally checked and managed every step for the same group of members. Now he wants a different approach in which the team sets its own goals and makes its own decisions. The question is which leadership style this corresponds to, and all the options are style names.
The deciding clue is that “the team sets its own goals and makes its own decisions.” Handing goal-setting and decision authority to the team, with minimal involvement from the leader, is the laissez-faire style, often described as “hands-off.” Laissez-faire, transactional, charismatic and transformational are common exam terms for leadership styles. PMBOK 8 asks the project manager to adjust style to members’ willingness and ability. Laissez-faire is most suitable for a mature, self-driven team able to set goals and decide for itself; a new team generally needs more guidance and support. The stem states that the members are now experienced and self-driven, so that maturity is present and laissez-faire fits. The answer is C.
Why the other options are wrong
- A. Transactional leadership obtains performance through rewards and penalties; the standards and process remain under the leader’s control, and it is an exchange relationship. That is not the same as letting the team make decisions.
- B. Charismatic leadership moves the team through the leader’s personal appeal, enthusiasm and confidence, so the focus is on the leader himself, not on handing over goal-setting and decision authority.
- D. Transformational leadership uses vision and personal care to inspire members to go beyond the status quo and drive change. It emphasizes inspiration, not letting the team take the decisions on its own.
Key takeaway A team that sets its own goals and makes its own decisions corresponds to laissez-faire leadership, which is most suitable for mature, self-driven teams.
Variation If the stem said the members were newly formed and did not know each other and the project manager wanted them to figure things out themselves, laissez-faire would not fit and he should guide and coach first. If it said he rewards people who hit their targets with bonuses, that would be transactional.
- Question 69
On a process renovation project at an auto parts plant, the project manager finds that the vice president of sales has great power and pays close attention to the project, yet states clearly that he opposes it. What should the project manager do?
Show answer and explanation
Correct answer: C
On a process renovation project at an auto parts plant, the vice president of sales has great power and pays close attention to the project but openly opposes it. The question asks for the right way for the project manager to respond.
The vice president has high power and high interest, so he falls in the “manage closely” cell (the four strategy names are a common exam term). His opposition does not change the cell he is in; it shows that he needs even more active management. The project manager should communicate proactively, find out why he objects, try to win his support and tailor the engagement approach within the manager's authority; any proposed change affecting approved scope or baselines must go through change control. Leaving a high-power opponent alone will make him a roadblock on approvals and resources. The answer is C.
Why the other options are wrong
- A. Monitor is for people with low power and low interest. The vice president is high on both, and watching only when necessary would let his opposition keep festering.
- B. Keep satisfied is for people with high power and low interest. The vice president's interest is high and he is opposing, so without proactive communication you cannot find out and resolve his concerns.
- D. Keep informed is for people with low power and high interest. Passive reporting while waiting for him to state his position is far from enough for a high-power opponent.
Key takeaway For a high-power, high-interest opponent, manage actively and closely and win his support.
Variation If the vice president had high power but did not care about the project and merely held a veto at approval, he would fall in keep satisfied: keep up moderate communication so he does not become a roadblock.
- Question 70
At the Sprint Review of a community group-buying mini-app project, after watching the demo, a customer representative asks for an urgent new enhancement because the platform has just changed its promotion rules. What should the project manager do next?
Show answer and explanation
Correct answer: A
At the Sprint Review of a community group-buying mini-app project, after the demo, a customer representative asks for an urgent new enhancement because the platform changed its promotion rules. The question is what the project manager should do next.
The Sprint Review is a collaborative working session for inspecting the results of the Sprint, gathering feedback and discussing next steps. The Product Backlog can be adjusted according to the feedback, but the team cannot be asked to start building a new requirement on the spot. The new requirement is first recorded in the Product Backlog and ordered by the Product Owner, and whether to select it is discussed at the next Sprint Planning. Even if it is urgent, that shows in the ordering, not by jumping the queue or bypassing the list. PMBOK 8 also says the Product Backlog lets the team prioritize continuously. The answer is A.
Why the other options are wrong
- B. The review focuses on the results of this Sprint. Reviewing item by item and demanding immediate development skips assessment and ordering and disrupts the meeting.
- C. The Sprint Backlog holds the work selected at Sprint Planning. A request that arises at the Sprint Review belongs in the Product Backlog first, and writing it straight into the Sprint Backlog bypasses ordering and damages transparency.
- D. The Sprint Retrospective is about improving how the team works, not the place to handle new requirements, and waiting until then would also delay an urgent one.
Key takeaway A new requirement that comes up at the review is first recorded in the Product Backlog and then discussed at the next Sprint Planning.
Variation If the new requirement must be addressed before the current Sprint ends, the Product Owner and Developers should assess its impact; they may renegotiate the current Sprint's scope as long as the Sprint Goal is not endangered. If the change makes the Sprint Goal obsolete, the Product Owner may cancel the Sprint; otherwise, order the requirement near the top of the Product Backlog for consideration at the next Sprint Planning.
Reference Product Backlog and Increment · Lesson 1: The Product Backlog: Nature, Ownership and Change Handling
- Question 71
While planning the next iteration, the agile team on a logistics tracking project finds that several of the user stories it intends to select carry high risk. How should the iteration plan be arranged to manage these risks?
Show answer and explanation
Correct answer: D
While planning the next iteration, the team finds that several user stories it intends to select are high risk. The iteration plan has to include risk management.
Agile treats risk response as work in its own right. When high-risk stories are found, create risk-based iteration tasks and put the response work into the iteration plan together with the feature stories, for the team to complete during the iteration. The risk then enters the team's daily rhythm at the planning stage instead of waiting until something goes wrong. Risk response takes team capacity just like features do, so it must go into the iteration plan and not be left for “when there is time”. The answer is D.
Why the other options are wrong
- A. Dealing only with probability is not comprehensive, since risk management has to consider both probability and impact, and dealing with the rest after the event misses the time to respond.
- B. A story should not be moved out of the iteration and left for the risk to vanish simply because it is risky, since that only delays the problem surfacing. Assess the risk, adjust the order in light of value, dependencies and constraints, and put the needed response work into the plan.
- C. A retrospective reviews what has already happened. Discussing risks only then is far too late.
Key takeaway Pair high-risk stories with risk-based tasks in the iteration plan so they are dealt with early.
Variation If a new risk appears only midway through the iteration, first talk with the team and decide together, assess it promptly and choose a response; response work to be carried out later can be ordered together with other backlog items of an appropriate type.
- Question 72
Unlike predictive projects, which focus on variance against the plan, which group of metrics do agile projects value MORE for measuring performance?
Show answer and explanation
Correct answer: B
The question contrasts the measurement orientation of predictive and agile projects: predictive focuses on variance against the plan, and the question asks which group of metrics agile values more for measuring performance.
Agile measures value delivery and flow: how much value has been delivered, and how long a piece of work takes from start to finish (cycle time). These two directly reflect whether the team can deliver value continuously and quickly, rather than how strictly the plan was executed. Checking variance against the plan is the predictive orientation. A simple way to remember it: predictive asks “did we stay on plan?”, while agile asks “how much value did we deliver and how fast does it flow?”. The answer is B.
Why the other options are wrong
- A. Variance between planned and actual duration is exactly the variance against plan that predictive projects focus on.
- C. The number of documents does not represent value. Agile values working software over comprehensive documentation.
- D. Individual hours utilization measures how busy people are, not what was delivered or how fast it flows.
Key takeaway Agile places more emphasis on value delivered and cycle time rather than treating plan deviation or individual busyness as the primary performance measures.
Variation Given a cumulative flow diagram, read cycle time as the horizontal distance from the start line to the completion line. For example, if item 15 starts on day 3 and finishes on day 5, the cycle time is 5 − 3 = 2 days.
- Question 73
The project manager presents a milestone schedule to management. Someone asks why none of the milestones has a duration. How should the project manager explain it?
Show answer and explanation
Correct answer: A
The project manager presents a milestone schedule and someone asks why no milestone has a duration. The scenario does not depend on the development approach. What matters is the nature of a milestone.
A milestone is a significant point or event in the project. Like an activity it has attributes such as a name and an ID, but it marks only a single point in time and consumes no time, so its duration is zero. It is activities, not milestones, that have duration and consume resources. This is how the project manager should explain it to management: a milestone is by nature a point in time, so its duration is zero. The time is consumed by the activities before and after it, and the milestone marks the point reached when those activities are complete. The answer is A.
Why the other options are wrong
- B. The durations of preceding activities belong to the activities. A milestone does not accumulate duration. Saying it “equals the sum of the activities before it” treats a point as a span of time.
- C. Zero duration is what defines a milestone. All milestones are the same, whether or not they are on the critical path.
- D. Zero duration comes from the definition, not from being “not yet estimated”, and nothing needs to be added after resources are confirmed. Estimating a duration for a milestone is itself a mistake.
Key takeaway A milestone is a point in time with zero duration. It is not an activity.
Variation If asked what else a milestone list must state, the answer is whether each milestone is mandatory (for example, required by contract) or optional (for example, based on historical information). Changing a critical activity to zero duration to “treat it as a milestone” is wrong, because it erases real work.
- Question 74
Several batches of room-control panels for a hotel chain's smart-room project are produced at an overseas factory. The project manager is told that the first batch of panels will arrive late. Installing these panels is on the critical path, and the delay will cause the project to miss a milestone. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
On a hotel chain's smart-room project, the first batch of panels from an overseas factory will arrive late. Installing them is on the critical path, and the delay will make the project miss a milestone. What should the project manager do first?
The delay has been confirmed, so a current condition now exists that will affect the milestone; manage it as an issue rather than as an uncertain risk. Because the issue comes from an external factory, the project manager first confirms the cause, actual impact and feasible alternatives with the factory. With those facts established, the project manager logs the issue and develops an action plan to reduce the impact on the milestone. The answer is A.
Why the other options are wrong
- B. The lessons learned register can be updated during the project, but when an issue has just appeared the priority is to log, assess and address it; revisions to the project management plan must also follow the applicable change process.
- C. Rescheduling that touches the baseline requires assessment and the applicable change-control process. Timely notice to relevant stakeholders may be appropriate, but that does not make unilateral rescheduling the first action.
- D. Assigning blame is a retrospective commercial action. It does nothing to protect the milestone now, so it is not the first thing to do.
Key takeaway A confirmed external delay is an issue: first verify the cause, impact and alternatives with the external factory, then log and address it rather than putting it in the risk register or submitting a change first.
Variation If the stem said “the supplier says the first batch may be late,” it has not happened and is a risk: record it in the risk register and assess it; once the delay is confirmed it becomes an issue.
- Question 75
A quality audit finds that the project's defect logging and escalation practice does not match the procedure the organization prescribes. What should the project manager do?
Show answer and explanation
Correct answer: A
A quality audit finds that the project's defect logging and escalation practice does not match the procedure the organization prescribes. The question asks what the project manager should do.
A quality audit checks whether project activities follow the organization's policies, processes and procedures, and here it has found a gap. The project manager should first analyze why the practices differ (people did not know, found it a nuisance, or the procedure itself does not fit), then correct the practice so it complies with the procedure, and record the finding as a lesson learned. One purpose of an audit is to identify nonconformities and promote process improvement, not to accommodate the status quo. So analyze the cause first, then correct the practice. The answer is A.
Why the other options are wrong
- B. The procedure is set by the organization. When the project's practice differs, the practice should be corrected. Asking to revise the organization's procedure to fit current practice puts the cart before the horse.
- C. Correcting audit findings is the responsibility of the project team and the project manager. Handing them to the client to decide shifts responsibility and does not serve the purpose of the audit.
- D. Additional product testing is aimed at deliverables, while the audit found a process problem. Testing cannot take the place of correcting the procedure.
Key takeaway When an audit finds a mismatch, first analyze the cause, then correct the practice so it complies with the procedure.
Variation If the analysis shows the procedure itself no longer suits the project, you can submit a revision proposal to the PMO as prescribed. But that is a conclusion reached after the analysis, not the first reaction.
- Question 76
On a connected-vehicle platform project, the project manager sets up a mechanism that lets stakeholders raise ideas at any time. What is the main benefit of this mechanism?
Show answer and explanation
Correct answer: B
On a connected-vehicle platform project, the project manager sets up a mechanism that lets stakeholders raise ideas at any time, and the question asks for its main benefit.
PMBOK 8 lists feedback loops among the communication methods chosen to suit stakeholder needs, and stresses that Manage Communications should adjust methods and techniques to the changing needs of stakeholders and the project. A mechanism for raising ideas at any time lets the project manager learn about opinions and concerns early, spot deviations sooner, and correct the project's direction while the cost is still small. That is its core benefit. The answer is B.
Why the other options are wrong
- A. A feedback loop supplements communication; it cannot replace the regular status reports in the communications management plan. Reports inform stakeholders, while feedback listens to them, and their purposes differ.
- C. Stakeholder ideas are only an input. They must be evaluated, and anything affecting a baseline goes through change control and approval by someone with authority. They do not automatically become scope changes.
- D. A feedback mechanism does not reduce the number of communication channels that must be maintained (the number of potential channels is estimated as n(n−1)/2 under common exam practice). Its main benefit is earlier feedback.
Key takeaway A feedback loop gets stakeholder input and allows course correction early. It does not replace reporting or decide changes.
Variation If the question says a stakeholder's input affects the scope baseline, the next step is to evaluate it and submit a change request, not to implement it directly.
Reference Managing and Monitoring Communications · Lesson 1: Manage Communications: Collecting, Creating and Distributing Information According to the Plan
- Question 77
A software outsourcing company takes on the development of a checkout system for a supermarket chain, and the project manager is an employee of the outsourcing company. Who should issue this project manager’s project charter?
Show answer and explanation
Correct answer: C
A software outsourcing company takes on the checkout system development for a supermarket chain, and the project manager is an employee of the outsourcing company. The question asks who issues the project manager’s charter.
The core information here is that “the project manager is an employee of the outsourcing company”. In a cross-corporate project, a contract establishes the agreement between the two organizations, while the charter is used inside each organization to ensure the contractual obligations are fulfilled. The project manager’s authority comes from authorization in his or her own organization, so the charter is issued by the outsourcing company’s sponsor. Keep the two layers apart: the contract makes the two companies answerable to each other, and the charter gives the project manager the authority to mobilize resources inside their own company. Each governs one layer and neither replaces the other. The answer is C.
Why the other options are wrong
- A. The supermarket’s sponsor has a contractual relationship with the outsourcing company and does not authorize the project manager inside the outsourcing company.
- B. The stem says only that this is a functional manager at the outsourcing company, not that the person also acts as the project initiator or sponsor. A functional manager manages departmental resources, and that status alone does not give the power to approve a project or issue a charter.
- D. The supermarket’s functional manager is outside the outsourcing company’s authorization system and has no authority to issue the charter.
Key takeaway The contract governs between organizations; the charter is issued by the sponsor in the project manager’s own organization.
Variation If the project manager were an employee of the supermarket, the charter would be issued by the supermarket’s sponsor. If asked what the project manager does next after the contract is signed, the answer is to complete the charter first with the sponsor in his or her own organization.
- Question 78
A new member joins the project of a city gas-pipeline monitoring platform. After attending a few Daily Scrums, he notices that every Daily Scrum ends within 15 minutes, but the Scrum Master always arrives with a task list prepared in advance, asks the corresponding developers one by one about their progress, and then assigns everyone new tasks for the day on the spot. Is this kind of Daily Scrum appropriate?
Show answer and explanation
Correct answer: A
On a Scrum project, every Daily Scrum ends within 15 minutes, but the Scrum Master arrives with a prepared task list, asks for progress one by one and assigns the day's tasks on the spot. The question asks whether such a meeting is appropriate.
The Daily Scrum is the Developers' own synchronization meeting: members synchronize on progress and on the obstacles they meet. The Scrum Master's role is that of a servant leader, who fosters the team's self-organization and does not monitor status or hand out tasks. Finishing on time shows only that the timebox has not been broken; the content and the method are still wrong, so it is not appropriate. The answer is A.
Why the other options are wrong
- B. Keeping track of everyone's progress and assigning tasks is command-and-control, the opposite of the Scrum Master's servant-leader role.
- C. Keeping the meeting short (typically no more than 15 minutes) is a requirement of the meeting, not the whole of the Scrum Master's responsibility. You cannot call it appropriate just because it is punctual.
- D. PMBOK 8 says the daily coordination meeting is brief and focused, typically no more than 15 minutes, so it should not be stretched at will, and certainly should not become a place to hand out tasks. This option also fails to identify the role problem.
Key takeaway The Daily Scrum is the team's own meeting: the Scrum Master fosters self-organization and does not direct or assign work.
Variation If the stem had members reporting status one by one to the project manager, the problem is the same: the meeting has become a status report, and it must go back to members synchronizing with each other.
- Question 79
Your company is preparing to transform to agile and has appointed you to lead a software project. You suggest placing a large whiteboard in the team office where everyone can see it, with a Kanban board and a burndown chart posted on it to share the status of backlog items. Here, the Kanban board is an example of which of the following?
Show answer and explanation
Correct answer: C
The company is transforming to agile, and you suggest placing a large whiteboard where everyone can see it, with a Kanban board and a burndown chart on it to share the status of backlog items. The question asks what the Kanban board is an example of.
PMBOK 8 defines an information radiator as a visible, physical display that provides information to the rest of the organization, enabling timely knowledge sharing. It is posted where people can see it easily, is typically “low tech and high touch”, and is maintained by hand. A Kanban board and a burndown chart placed in a prominent spot are examples of information radiators. The answer is C.
Why the other options are wrong
- A. A lean canvas is a visual one-page business plan used to discuss a business model. It is not a tool for showing the status of work.
- B. Agile release planning plans the timing and content of increments delivered to the customer. It is a planning activity, not a display that shows status.
- D. Osmotic communication is the way co-located members pick up relevant information by overhearing it. It is a communication phenomenon, while a whiteboard is a deliberately placed display.
Key takeaway A Kanban board or burndown chart posted in a prominent place is an information radiator.
Variation If the charts were an electronic dashboard that required a login to view, it would depart from the “prominent and easy to get at” feature of an information radiator.
Reference Burndown Charts and Information Radiators · Lesson 2: Forecasting Progress with Charts, Making Decisions, and Information Radiators
- Question 80
In a logistics park construction project, the client’s representative inspects the completed roadbed work and formally accepts the deliverables. The project manager wants to place the work “Validate Scope” in the PMBOK 8 mapping table. Where does it belong?
Show answer and explanation
Correct answer: C
In a logistics park construction project, the client’s representative inspects the completed roadbed work and formally accepts the deliverables. You must place Validate Scope in the PMBOK 8 mapping table, judging both the performance domain and the Focus Area.
The client inspecting and formally accepting completed deliverables is Validate Scope. In the PMBOK 8 mapping table, the Scope performance domain has Plan Scope Management, Elicit and Analyze Requirements, Define Scope, and Develop Scope Structure in the Planning Focus Area and Monitor and Control Scope and Validate Scope in the Monitoring and Controlling Focus Area. Acceptance is a check on results, so it belongs to the Monitoring and Controlling Focus Area of the Scope performance domain. The answer is C.
Why the other options are wrong
- A. The Planning Focus Area holds Plan Scope Management, Define Scope, and so on, which are planning work, not the acceptance of results already completed.
- B. In the mapping table the Scope performance domain has no process in the Executing Focus Area; producing the deliverables is executing, but accepting them is not.
- D. The Monitoring and Controlling Focus Area of the Governance performance domain holds Monitor and Control Project Performance and Assess and Implement Changes; Validate Scope belongs to the Scope performance domain and is not there.
Key takeaway Validate Scope and Monitor and Control Scope are both in the Monitoring and Controlling Focus Area of the Scope performance domain; acceptance is monitoring and controlling, not executing.
Variation If the question asked about “Define Scope,” the answer would be the Planning Focus Area of the Scope performance domain.
Reference Focus Areas and Performance Domains · Lesson 2: Mapping Focus Areas to Performance Domains, and How the PMBOK 8 Structure Changed
- Question 81
The quality team on a part production line is drawing a control chart for part dimensions, and the customer contract gives tolerance requirements for the dimensions. When drawing it, what should the upper and lower control limits be based on?
Show answer and explanation
Correct answer: B
The quality team is drawing a control chart for part dimensions. They have both process data and the tolerance requirements from the customer contract. The question asks what the upper and lower control limits should be based on.
Control limits are calculated from the process's own data using standard statistical principles, are usually set 3 sigma above and below the mean, and represent the natural variation range of a stable process. It is the specification limits that are determined by customer requirements. So when you answer, look at “what is it based on”: limits calculated from process data are control limits, and limits given by customer or design requirements are specification limits. Therefore the answer is the process's historical data, calculated statistically: B.
Why the other options are wrong
- A. The contract tolerance is the customer's requirement for the product, and it corresponds to the upper and lower specification limits (USL, LSL), not control limits.
- C. The project manager can set quality objectives, but control limits cannot be set subjectively from objectives. They reflect the actual variation of the process, not the level one hopes to reach.
- D. Acceptance criteria approved by the sponsor are likewise requirements for the result and relate to specification limits. They do not determine control limits.
Key takeaway Control limits are calculated from process data, and specification limits are set by customer or design requirements. They are not the same thing.
Variation If the control limits use the mean-centered ±3σ convention, then with UCL 334.5 and LCL 325.5, σ = (334.5 − 325.5) ÷ 6 = 1.5 and the mean = (334.5 + 325.5) ÷ 2 = 330; the calculation never uses the specification limits.
- Question 82
A project manager is posted overseas to run a sales-skills training project with over a hundred trainees. The first session ran four hours straight, with the instructor reading from slides the whole time. Afterward, trainees said the content was understandable and they were willing to take part, but they did not like the instructor's one-way reading. What should the project manager do?
Show answer and explanation
Correct answer: D
A project manager overseas runs a sales-skills project for over a hundred trainees. In the first session the instructor read slides for four hours straight. Trainees could follow the content and were willing to take part, but did not like the one-way reading. The question asks what to do.
The trainees' feedback is about how the information is delivered. The communication method does not suit the audience. They are not unwilling to take part (the stem says they are willing), and there is no conflict within a team. PMBOK 8 says communication activities should be flexible, adjusting methods and techniques to the changing needs of stakeholders and the project. So update the communications management plan and change the delivery approach, for example by adding interaction, cases and question time. The answer is D.
Why the other options are wrong
- A. The engagement plan addresses how involved stakeholders are. The stem says the trainees are willing to take part and dislike only the one-way reading, so the issue is communication, not engagement level.
- B. Forming is the first stage of the team development ladder, and the trainees' dissatisfaction is not caused by a team that has not yet formed.
- C. Storming refers to conflict among team members over views and working styles. Here trainees object to the instructor's delivery, which is not conflict inside a team.
Key takeaway Dissatisfaction with how information is delivered is a communication problem. The answer is to update the communications management plan, not team development or the engagement plan.
Variation If trainees were unhappy because the content was unrelated to their work, that is a requirements and scope issue, and the project manager should confirm the training content with the client.
Reference Managing and Monitoring Communications · Lesson 3: Monitor Communications: Checking Whether Information Needs Are Met
- Question 83
A distribution-center renovation project at PMLyceum has entered execution. While monitoring resources, the project manager finds that actual spending on rented forklifts and warehouse equipment is already above plan and is expected to keep overrunning. What should the project manager do?
Show answer and explanation
Correct answer: C
A distribution-center renovation project is in execution. While monitoring resources, the project manager finds that actual spending on rented forklifts and warehouse equipment is already above plan and expected to keep overrunning. The question asks what to do.
The data analysis techniques for Monitor and Control Resourcing include alternative analysis and cost-benefit analysis. Facing an overrun on rented equipment, first list the different resource mixes (quantities, rental periods, rent or buy, staggered usage times), compare cost and benefit for each, and choose the mix that meets work needs while controlling cost. If the adjustment touches a baseline, then raise a change request. This is “analyze first, act after”. The answer is C.
Why the other options are wrong
- A. Cutting proportionally without analysis may leave too little resource, delay the schedule and trade delivery for cost.
- B. Additional budget should be considered after analyzing the resource mix and other feasible alternatives. Applying for extra money without that analysis commits prematurely to one solution.
- D. Leaving the overrun until closure amounts to giving up monitoring. Cost variances should be handled during execution; lessons learned are an after-the-fact supplement, not a response.
Key takeaway When resource costs overrun, use alternative analysis and cost-benefit analysis to optimize the resource mix instead of simply cutting or adding money.
Variation If the stem asked “how much more than planned is actual usage?”, that is a performance review; if it asked “will it keep overrunning in the coming weeks?”, that is trend analysis.
- Question 84
While doing qualitative risk analysis, a subscription music app team finds that the requirements of several backlog items are vaguely defined and have no acceptance criteria, so it is impossible to judge whether a deliverable is acceptable. Under the source categories of the risk breakdown structure, which category should this risk belong to?
Show answer and explanation
Correct answer: A
While doing qualitative risk analysis on an adaptive project, the team finds that the requirements of several backlog items are vaguely defined and have no acceptance criteria, so it cannot judge whether a deliverable is acceptable. The question asks which RBS source category it belongs to.
The signal words are “requirements definition” and “acceptance criteria”: the root of the problem is uncertainty in the requirements and product standards themselves, which belongs on the technical side. The PMBOK sample RBS places requirements definition under technical risk, alongside scope definition, estimates, assumptions and constraints, technical processes, technology and technical interfaces (Figure 4-5). So the answer is A.
Why the other options are wrong
- B. Management risk comes from project management, organization, resourcing and communication arrangements. The crux in this question is vague requirements, not a failure in management arrangements.
- C. Commercial risk originates in transactional factors such as procurement, contractual terms and subcontractors. The stem mentions no contract or supplier, so it has nothing to do with vague requirements and missing acceptance criteria.
- D. External risk comes from outside the organization, such as regulation, markets and competition. Backlog items and acceptance criteria are the team's own work, not an external factor.
Key takeaway In PMBOK 8's sample RBS, the Level 1 categories are technical, management, commercial and external; requirements-definition problems fall under technical risk.
Variation “The contract has no clear acceptance terms and the customer rejects the work afterward” leans toward commercial risk; “the resource manager suddenly pulls away the testers” leans toward management risk; “a new regulation is issued” is external risk.
- Question 85
While planning quality, a project manager intends to use benchmarking. What is the main purpose of doing so?
Show answer and explanation
Correct answer: A
The project is in the quality planning stage, and the project manager intends to use benchmarking. The question asks what the main purpose is.
Benchmarking compares the project's actual or planned products, processes and practices with those of comparable organizations (in the same industry or on similar projects). It is used to identify good practices, generate ideas for improvement and provide a reference for measuring performance, and it helps the project set a reasonable quality level. That is just how PMBOK 8 defines it: the comparison of actual or planned products, processes and practices to those of comparable organizations to identify good practices, generate ideas for improvement, and provide a basis for measuring performance. Benchmarking results are also listed among the commercial databases and academic research that can be consulted in planning. The answer is A.
Why the other options are wrong
- B. Verifying whether activities follow organizational policies and procedures is the purpose of a quality audit. PMBOK 8 explains that a quality audit is usually conducted by a team external to the project and identifies good practices and nonconformities.
- C. Balancing prevention and appraisal investment against failure costs is a question that cost of quality analysis addresses. It has nothing to do with comparing with peers.
- D. Tracing the root causes of defects and ranking them is what tools such as the cause-and-effect diagram and the Pareto chart are for. That is analysis done after a problem has already occurred.
Key takeaway Benchmarking uses the good practices of comparable organizations as a reference to set the quality level and measure performance.
Variation If the stem asked “check whether project activities comply with policies and procedures”, the answer would be quality audit. If it asked about “the best investment ratio”, the answer would be cost of quality.
Reference Quality Planning and Assurance · Lesson 2: Quality Management Plan and Quality Metrics
- Question 86
The risk register has three threats. Risk 1 has a 15% probability and a $20,000 loss if it occurs. Risk 2 has a 5% probability and a $120,000 loss if it occurs. Risk 3 has a 10% probability and a $50,000 loss if it occurs. What is the total expected loss of the three risks (in absolute value)?
Show answer and explanation
Correct answer: A
The risk register has three threats, each with a probability of occurrence and a loss amount. The question asks you to calculate the total expected monetary value of the three risks.
For each risk separately, multiply probability by impact to get its EMV, and then add the three EMVs to get the total expected loss. You cannot first add the probabilities or the losses and then multiply, because each risk's probability corresponds to its own loss. All three are threats, so each EMV is an expected loss. The total comes to $14,000. The answer is A.
- Risk 1: 0.15 × 20,000 = $3,000
- Risk 2: 0.05 × 120,000 = $6,000
- Risk 3: 0.10 × 50,000 = $5,000
- Total: 3,000 + 6,000 + 5,000 = $14,000
- Check: the three losses total $190,000 and every probability is at most 15%, so a total EMV of $14,000 is far below $190,000, which is a reasonable order of magnitude
Why the other options are wrong
- B. $6,000 is the EMV of Risk 2 alone, the largest of the three. This question asks for the total expected monetary value, so all three must be added.
- C. 190,000 = 20,000 + 120,000 + 50,000 adds the three losses directly without multiplying by probability. It is the worst-case loss if all three risks occur, not an expected value.
- D. $3,000 is the EMV of Risk 1, calculated alone because it has the highest probability (15%). The other two risks must also be included in the total.
Key takeaway Calculate EMV for each risk first, then add them to get the total. Do not add up losses that have not been multiplied by probability.
Variation If Risk 3 were an opportunity (probability 10%, gain $50,000), its EMV would be a +$5,000 gain, which offsets the threat losses and makes the net expected loss 3,000 + 6,000 − 5,000 = $4,000. Keep the signs of opportunities and threats distinct.
Reference Decision Tree Analysis · Lesson 2: Worked Decision Trees and the EMV of Risks
- Question 87
Midway through a release cycle, the project manager is replaced. The team tells the new project manager that the predecessor kept pushing for fast delivery, which created friction within the team. What approach should the new project manager take to build trust with the team as quickly as possible?
Show answer and explanation
Correct answer: A
The project manager is replaced midway through a release cycle. The team says the predecessor kept pushing for fast delivery, causing friction inside the team. The question asks how the new project manager can build trust quickly.
The friction comes from the predecessor’s way of managing, so the new project manager should first understand the team’s culture and pain points rather than rush to impose his own approach. Assessing the team culture, observing and interacting with members and learning where the friction comes from respects the team’s current state and lets him tackle the actual causes. PMBOK 8 notes that a team whose members trust one another is more willing to perform at a higher level, and it stresses that leaders listen and stay sensitive to members. The answer is A.
Why the other options are wrong
- B. Recording daily actions and providing feedback focuses on tasks. It does not directly address the team’s need for trust and does not help uncover the source of the friction.
- C. Keeping commitments on time and having ample budget is basic management support. It does not remove the existing friction or reveal what the team really thinks.
- D. Having the team state its needs while the project manager creates tasks and reports progress is passive, offers little guidance and does not actively find the source of the friction, so it does little to build trust.
Key takeaway When taking over a team with friction, assess the culture, observe interactions and understand the problems first, then build trust.
Variation If the team will not say where the friction comes from, the new project manager should hold one-on-one conversations with key members first and then schedule a team meeting.
Reference Leadership Styles · Lesson 5: The Tasks of Leading the Team: Empowering, Speaking Up, Diversity and Problem-Solving
- Question 88
A predictive meeting-platform project with established baselines is in execution. At the weekly retrospective, team members notice that the number of test defects has risen two weeks in a row, and someone suggests analyzing the trend directly within the execution process and immediately adjusting the test arrangements in the project management plan, which are under configuration control. What should the project manager do?
Show answer and explanation
Correct answer: C
A predictive meeting-platform project with established baselines is in execution. The weekly retrospective shows defects rising two weeks in a row, and someone suggests analyzing the trend directly in execution and changing the test arrangements in the project management plan that are under configuration control.
In PMBOK 8, Manage Project Execution itself includes analyzing the performance data and information relevant to current work and making necessary adjustments, so analysis in execution is fine. But a defect count that keeps rising is a comparison of overall performance, and continuing comparison, forecasting and reporting are the job of the monitoring and controlling processes. The stem establishes a predictive project with baselines and states that the test arrangements are under configuration control, so adjusting them must be raised as a change request under the change management rules and implemented only after approval through Assess and Implement Changes by the designated approver. So continue executing, record the data honestly, let monitoring and controlling analyze it, and raise a change request if an adjustment is needed. The answer is C.
Why the other options are wrong
- A. Revising the test arrangements in the project management plan directly means changing controlled content without a change request or approval. The error is changing it directly and bypassing change control, not that “execution cannot analyze.”
- B. Rising defects call first for analysis of the cause, not an unconditional pause. Whether to pause is decided after analysis under established authority and governance rules, and a change request is raised only when a change to the controlled plan is involved. The stem also gives no basis for “wait for an independent assessment.”
- D. Work performance data are the basis for monitoring and controlling analysis. Recording only items that passed would distort the data, and monitoring could not find the real variance.
Key takeaway Execution can analyze data on current work, while comparison of overall performance is done in monitoring and controlling, and plan adjustments go through a change request.
Variation If the defect data have been analyzed and the conclusion is to add a regression-test round and extend by two weeks, the next step is to submit a change request. Once the change is approved, return to execution to implement it.
- Question 89
PMLyceum is planning an entirely new, innovative project, and the team believes there is a good deal of uncertainty and risk in the activities. Which of the following estimating techniques can be used to estimate the project schedule more accurately?
Show answer and explanation
Correct answer: D
An entirely new, innovative project has a good deal of uncertainty and risk in its activities, and the schedule must be estimated more accurately. Which estimating technique should be used?
PMBOK 8 states that multipoint estimating is used when there is uncertainty with the individual activity estimates, using three estimates (optimistic, pessimistic and most likely) to account for uncertainty and risk, which can improve the accuracy of single-point estimates. The stem explicitly states that the activities have substantial uncertainty and risk, and multipoint estimating directly incorporates that uncertainty, so it is the best fit for this scenario. It does not require a similar project to refer to. The team just needs to give one judgment each for the best, most likely and worst cases. The answer is D.
Why the other options are wrong
- A. Analogous estimating needs a similar historical project to refer to. An innovative project usually lacks a suitable reference, and the accuracy is lower.
- B. Parametric estimating needs a reliable statistical relationship between historical data and parameters, and an innovative project often has no such data.
- C. Bottom-up estimating rolls up item by item from decomposed components. It addresses the level of detail of the estimate and does not specifically address uncertainty.
Key takeaway For estimates with high uncertainty and risk, use multipoint estimating.
Variation If the project were highly similar to earlier ones and the data were sufficient, parametric or analogous estimating could be used, with no need for three points.
Reference Multipoint (Three-Point) Estimating · Lesson 1: Multipoint Estimating: Three Estimates and Two Formulas
- Question 90
A children's smart-watch development project reaches customer validation. The customer believes location accuracy and fall-alert sensitivity fall short of requirements, refuses to sign the acceptance report and demands rework; the team believes the product already meets the standard. What should the project manager do?
Show answer and explanation
Correct answer: B
A children's smart-watch project is at customer validation. The customer says location accuracy and fall-alert sensitivity are below requirements and will not sign the acceptance report; the team thinks the product meets the standard.
The disagreement is whether the deliverables actually meet the acceptance criteria. So first check, item by item, whether each acceptance criterion is met, and use measurement data to judge whether the product really falls short; only then decide the follow-up action. That is the “inspection” approach in Validate Scope. Inspection should rest on the acceptance criteria agreed in advance and on measured data, not on impressions, and without giving way just because the customer is unhappy, which keeps acceptance objective. The answer is B.
Why the other options are wrong
- A. Reworking to the customer's demand without checking the acceptance criteria may be unnecessary rework and lets scope grow at will.
- C. A change request and extra funding need a basis, which comes only after it is confirmed that the product really does not conform and needs rework. Submitting now is premature.
- D. Root cause analysis is done after it is confirmed that the product really does not meet requirements. At this point it is not even clear whether it meets the standard.
Key takeaway When the customer refuses to sign, first inspect against the acceptance criteria, then decide whether to rework, analyze or change.
Variation If the check confirms that location accuracy really is below the standard, record the reason, rework through change control and reverify. If it meets the standard, show the customer the inspection record and ask for a signature.
- Question 91
A colleague who has just passed the exam for the previous edition is comparing the structure of PMBOK 8 with that of the Seventh Edition and lists several judgments. According to the PMBOK 8 preface, which judgment is correct?
Show answer and explanation
Correct answer: A
A colleague is comparing the structure of PMBOK 8 with that of the Seventh Edition and lists several judgments. The question asks which judgment is correct according to the PMBOK 8 preface.
The preface of PMBOK 8 explains that the principles were refined from the 12 of the Seventh Edition to 6, more actionable and with less overlap; the process groups were repositioned as five Focus Areas; and the knowledge areas were integrated with other concepts into the seven performance domains. Checking item by item, only “condensed from 12 to 6 and made more actionable” is correct. For “which judgment is correct” questions, break each option into the four objects, principles, performance domains, knowledge areas, and process groups, and check them one by one. The answer is A.
Why the other options are wrong
- B. The number of principles changed, from 12 merged into 6; it was not just a matter of reordering.
- C. The process groups were not kept under their original names as a parallel structure; they were repositioned as Focus Areas.
- D. The knowledge areas have been integrated into the performance domains and no longer continue as a separate parallel structure.
Key takeaway 12 principles were refined to 6, the process groups were repositioned as Focus Areas, and the knowledge areas were merged into the performance domains.
Variation If asked how many processes PMBOK 8 has, the answer is 40 non-prescriptive processes. If asked how many performance domains, the answer is 7, whereas the Seventh Edition had 8.
- Question 92
A new-energy battery R&D team learns that a new industry regulation makes a process it currently uses noncompliant, and a new process must be adopted. Time is very tight, and the project manager must identify the resulting risks in the shortest time and draft a response for each. All team members took part in trials of this process and can attend a meeting on the spot, while one-by-one interviews and an outside expert assessment would each take weeks. What should the project manager do?
Show answer and explanation
Correct answer: B
A battery R&D project must switch to a new process because of a new industry regulation. Time is tight, and the project manager must identify risks and draft responses in the shortest time. Team members all took part in the trials and can attend on the spot, while one-by-one interviews and an outside expert assessment would take weeks.
Three factors decide it: “shortest time”, members who “all know the process” and who “can attend on the spot”. Brainstorming gathers the relevant people in one session, produces many risks on the spot and can also generate potential response options, taking the least time while using the team's familiarity with the process. Those options still need to be evaluated through risk analysis and confirmed during Plan Risk Responses. The other approaches either take weeks or merely report without producing risks. The answer is B.
Why the other options are wrong
- A. Interviewing one by one means scheduling each separately, and the stem says it takes weeks, which conflicts with “shortest time”. Interviews suit cases that need an in-depth look at one person's views; here everyone is present and there is no need to talk to them one at a time.
- C. Briefing the sponsor and asking them to review the risk list is reporting and reviewing; it produces no new risks or responses and is not a technique for identifying risks, so it cannot achieve “identify quickly and draft responses”.
- D. A written assessment from an outside expert also takes weeks, which is too long; the team members are themselves the people who know the process best, so there is no need to wait weeks for an outside assessment first.
Key takeaway When time is tight and the people know the situation and can attend, brainstorming gives the fastest output of risks and potential response ideas; formal responses still require subsequent analysis and confirmation.
Variation To find out what a particular group's representative is worried about, or when people are dispersed, cannot attend at once or confidentiality is involved, use interviews instead.
- Question 93
A cross-border logistics dispatch system is being developed in Sprints. The regulator suddenly issues new data-declaration rules. An item far down the Product Backlog, “declaration data format conversion”, had been thought unimportant, but now the system cannot go live in compliance without it. What should the team do?
Show answer and explanation
Correct answer: B
The project is being developed in Sprints. A new external regulation turns an item far down the backlog into “without it we cannot go live in compliance”. The question is what the team should do next.
The team selects work from the Product Backlog, using its order as an important guide, and the content and order of the backlog are the Product Owner's responsibility. The item's importance has changed because of an external change, so the matching action is to change its position in the backlog, not to look for a workaround outside it. The team should contact the Product Owner and ask him to reorder the item so it moves up to where it should be. The answer is B.
Why the other options are wrong
- A. A prominent reminder only gets people to notice the item. The order of the backlog has not changed, the team still takes work by the old priorities, and the item still does not rise.
- C. Compliance is a hard condition for going live, so value cannot be measured by return on investment alone. Calculating ROI is also not the team's job and does not solve the ordering problem.
- D. Refactoring reorganizes internal structure without changing external behavior. What is missing here is a feature that has not been built yet, which refactoring cannot supply, and it would not move the item up the backlog.
Key takeaway When an item's value changes because of an external change, ask the Product Owner to reorder it first.
Variation If the change affects only a story currently being worked on and that story is no longer needed, the team talks it over with the Product Owner and closes it. If the change comes from a new customer requirement, it likewise goes into the backlog first and is then ordered, not pushed straight into the Sprint.
- Question 94
A logistics platform project is in its late stage, and the project manager finds that critical knowledge, such as the routing rules, sits in the minds of only two members, so if they leave the project will be affected. What should the project manager do?
Show answer and explanation
Correct answer: A
In the late stage, critical knowledge such as the routing rules sits in the heads of only two members, and if they leave the project will be affected. What should the project manager do?
Under the task “Help ensure knowledge transfer,” the PMP Exam Content Outline lists three enablers: identify the knowledge that is critical to the project, gather knowledge, and foster an environment for knowledge transfer. These are enablers, not a mandatory sequence. What matters now is to identify first which knowledge, if lost, would put the project in trouble, and then transfer it by plan, ideally while both people are still on the job. So identify the critical knowledge and develop a knowledge transfer plan. The answer is A.
Why the other options are wrong
- B. Waiting for someone to formally resign before handing over leaves a very short handover period, and the knowledge is likely to be lost. Act in advance.
- C. Asking the two to write work summaries lacks a systematic identification of critical knowledge, a defined target of the transfer and a check on how well it was absorbed. Written summaries can preserve codifiable knowledge but cannot necessarily transfer the tacit knowledge that depends on experience and interaction.
- D. Noting it in the status report only reports the problem and does not lower the risk. The project manager should take action, not merely inform.
Key takeaway Identify the critical knowledge first and then transfer it by plan; do not wait until the people have gone.
Variation If the stem said one of them leaves next week, arrange an in-person handover at once and verify that the successor can work independently. If the sponsor wants to replace an expert, make sure sufficient knowledge passes between the outgoing and incoming person.
- Question 95
A project manager is explaining enterprise environmental factors to a new team member. One of the four statements below is wrong. Which one?
Show answer and explanation
Correct answer: B
This question asks you to find the incorrect statement, so note that the question asks which one is NOT correct, and judge each statement against the definition of enterprise environmental factors.
Enterprise environmental factors are conditions not directly influenced by the project team that impact, constrain or direct the project. The key is that the direction of the effect is not fixed: they can enhance or constrain the options, and for the project they can be favorable, unfavorable or neutral. Statements A, C and D can each be supported by the definition. Statement B moves straight from “cannot be controlled” to “can only limit,” which is inconsistent with the definition, so B is the incorrect statement. The answer is B.
Why the other options are wrong
- A. This statement is correct: the effect of enterprise environmental factors can be favorable, unfavorable or neutral, so it is not the incorrect statement the question asks for.
- C. This statement is correct: organizational culture, structure and governance is one of the internal enterprise environmental factors PMBOK 8 lists, so it is not the incorrect statement.
- D. This statement is correct: enterprise environmental factors can come from inside or outside the organization, so it is not the incorrect statement.
Key takeaway The project team cannot directly control enterprise environmental factors, but their effect can be favorable, unfavorable or neutral, and they cannot all be treated as constraints.
Variation If the question were changed to “find the correct statement,” B would need to be rewritten as “the team cannot control them, but their effect may be favorable, unfavorable or neutral.” An option saying “enterprise environmental factors can be directly changed by the project team as needed” would also be wrong, because the team cannot directly control them; the team can update and add to organizational process assets (knowledge repositories).
- Question 96
A 6-person team at PMLyceum is building an order system using an agile approach, and the project also keeps a schedule baseline. The project manager's assessment shows that the team's current velocity just meets the schedule baseline. Halfway through the project, the sponsor tells the project manager that 3 team members are being moved to another, higher-priority project and cannot be replaced. What is the project manager's BEST next action?
Show answer and explanation
Correct answer: A
This is a hybrid project: a 6-person team develops an order system with an agile approach and the project keeps a schedule baseline, and velocity currently just meets the baseline. Halfway through, the sponsor says 3 of the members are moving to a higher-priority project and cannot be replaced.
The key conditions are that the project “keeps a schedule baseline” and that headcount is “cut in half with no replacement”. Team capacity shrinks sharply, velocity is expected to drop significantly, and continuing against the original baseline is unrealistic; nor does using an agile approach let you bypass change control. The project manager should first assess what the remaining resources can deliver, then use a change request to adjust the schedule baseline (the baseline the stem explicitly keeps) and propose options for scope or the release plan, for someone with authority to decide. PMBOK 8 says change requests that affect project baselines are evaluated and implemented through the formal Assess and Implement Changes process; in adaptive environments, scope changes are typically approved dynamically by the product owner, but this question keeps a schedule baseline. Because this is a team-member issue, the project manager should assess the impact through Lead the Team. Because the schedule baseline is affected, the project manager should then submit a change request. The answer is A.
Why the other options are wrong
- B. Running several more iterations to re-measure velocity would delay the decision. Velocity data can serve as an input to the assessment but cannot replace the change request.
- C. Demanding overtime and paying bonuses without analysis squeezes the team. Overtime can hardly make up for a gap of half the people, and it does not deal with the baseline.
- D. Whether the project is terminated is not the project manager's decision, and change requests and alternatives can still be tried. Announcing termination outright is a defeatist response.
Key takeaway Resources are cut and a baseline exists: assess first, then use a change request to adjust the baseline and offer alternatives.
Variation If the stem were changed to a purely agile project with no formally controlled baseline, the product owner would reorder the product backlog, the team would update its forecast and communicate release expectations to stakeholders; if the project keeps a formal baseline, changing it must go through change control.
- Question 97
A central-kitchen expansion project for a restaurant chain has entered execution. The logistics supervisor, as a stakeholder, raises a new risk that had not been identified before: vehicle scheduling by the new cold-chain supplier may affect the timeliness of raw-material delivery. What should the project manager do?
Show answer and explanation
Correct answer: B
A central-kitchen expansion project is in execution. The logistics supervisor, a stakeholder, raises a risk not identified before: vehicle scheduling by the new cold-chain supplier may affect the timeliness of raw-material delivery. The question asks what the project manager should do.
Identifying risks is not done just once; it is an iterative process that runs throughout the project, and as information grows it is normal for new risks to appear during execution. On receiving a new risk, the project manager should first record it in the risk register so it is not lost, and then, following the process in the risk management plan, assess its probability, impact and priority together with the project team and relevant stakeholders. That way nothing goes unrecorded and the assessment has a full perspective. The risk has not yet been analyzed and there is no evidence that it exceeds the project manager's authority, so there is no need to rush to escalate. The answer is B.
Why the other options are wrong
- A. Confirming the register is complete and asking everyone to verify it is rechecking old content and does nothing about the newly found risk, besides implying that risk identification is not iterative.
- C. Analyzing only with the person who raised it gives a single viewpoint and may miss other risks and effects. Risk analysis and assessment should involve the project team and relevant stakeholders.
- D. The risk has not been analyzed, and whether it exceeds authority is unknown. Identifying, analyzing and planning responses are within the project manager's responsibility, and escalation to senior management is needed only when the risk is outside the project scope or beyond the project manager's authority.
Key takeaway Record a new risk in the risk register first, then assess it with the team and relevant stakeholders; do not rush to escalate.
Variation If the stem were changed to “the supplier notified us yesterday that it cannot supply”, the event has happened and is an issue, to be recorded in the issue log and acted on immediately.
- Question 98
Because the market has shrunk, the customer can pay only part of the committed amount each month and cannot pay in full. The customer and sponsor want the project to continue without additional funding and permit adjustment of the undelivered scope; the project is delivered iteratively. How should the project manager handle this?
Show answer and explanation
Correct answer: A
In an iteratively delivered project, the customer's funds do not arrive in full: only a part of the committed amount is paid each month. How do you keep going under the funding limit?
The stem states that the customer and sponsor agree to continue without additional funding and permit adjustment of the undelivered scope. The project manager should work with them to rank the remaining features by business value and deliver the highest-value parts within the funds actually available. Iterative delivery supports incremental delivery of usable results and renewed decisions at the funding boundary. PMBOK 8 stresses that the Finance performance domain is concerned not only with cost but also with delivering maximum value. Because each iteration produces a usable increment, when funds shrink and you rank by value, what has been delivered still has value and is not wasted. The answer is A.
Why the other options are wrong
- B. The customer is only paying part and has not stopped. Suspending at once would damage the customer relationship and throw away value that can still be delivered.
- C. Continuing to spend as planned when funds are short causes overruns and waste, and waiting for full payment before delivering leaves the customer without value for a long time.
- D. Features should be chosen by business value, not by small size or independence. Small, independent features are not necessarily high in value.
Key takeaway When funds are limited, deliver the highest business value first within the available budget.
Variation If funding stops completely, assess the project's value and discuss suspension or closing with the sponsor instead of continuing development.
Reference Cost Baseline and Reserves · Lesson 3: Project Funding Requirements, Funding Limit Reconciliation and Financing
- Question 99
You have been appointed lead of an agile project at a software company. You analyze the team's performance with a value stream map, and the result shows that one team member spent 5 hours waiting for other members to deliver their results. What improvement advice should you give the team?
Show answer and explanation
Correct answer: D
The project lead analyzed team performance with a value stream map, and it shows that one member spent 5 hours waiting for other members to deliver their results. What improvement advice should the team get?
Time spent waiting creates no value. It is exactly the waste a value stream map is meant to find: it consumes time without adding value. The right attitude is to treat it as a process problem and act to reduce or eliminate it, so that the time goes into value-creating work. It is not to conclude that someone is not trying hard enough, and it is not to accept the wait as a matter of course. The answer is D.
Why the other options are wrong
- A. Limiting WIP is a way of controlling the amount of parallel work, and value stream analysis may also lead a team to adjust its WIP limits. But waiting itself is not a way of limiting WIP, and waste cannot be described as an effective practice.
- B. This statement only describes the situation and solves nothing. Waste can be reduced by improving the process.
- C. Delays cannot all be eliminated. The goal is to plan sensibly and reduce the steps that create waiting waste, not to allow none at all.
Key takeaway Waiting time on a value stream map is waste and should be reduced or eliminated.
Variation If instead the processing time of one step is itself too long, examine how that step is performed and its capability. If total waiting is 8 days and total processing is 7 days, focus on investigating and reducing waiting, prioritizing the longest avoidable waits shown on the map.
- Question 100
A team member tests a feature that has been developed and finds that it does not match the expectations of the corresponding user story, which had not previously been written as an executable acceptance test. What should the member do?
Show answer and explanation
Correct answer: B
A member tests a developed feature and finds it does not match the expectations of the user story, which had not been written as an executable acceptance test. The member must first get the expectations clear and only then make the change.
First, the behavior that the user story expects has to be made explicit. Writing it as a user-facing acceptance test and then changing the feature against the test ensures it is changed correctly and prevents similar deviations in future. So write a user-facing acceptance test first and then change the feature. The acceptance test should be confirmed with the product owner so that individual members do not define the expectation unilaterally. The answer is B.
Why the other options are wrong
- A. Checking the original requirements document can help, but it cannot replace clarifying the story's expectations. The more direct approach now is to write the expectation as a user-facing acceptance test and then change the feature accordingly.
- C. The story has not been written as an executable acceptance test. Changing the feature before the expectation is clear is likely to go in the wrong direction and only adds rework.
- D. Switching to test-driven development is a long-term measure and not the next step for this problem. The task now is to get the expectation clear.
Key takeaway If a feature does not match the story's expectations: write a user-facing acceptance test to make the expectation explicit first, then change the feature.
Variation If, once written, the acceptance test still differs from the product owner's understanding, confirm the acceptance criteria with the product owner before changing the code.
Reference User Stories · Lesson 2: Acceptance Criteria and Review for User Stories
- Question 101
A project manager has completed all the deliverables and they have passed the acceptance criteria. Which of the following statements shows that the project's benefits have been realized?
Show answer and explanation
Correct answer: A
All deliverables are complete and have passed acceptance. The question is what shows that the project's benefits have been realized.
A benefit is the value that the project's results provide to the sponsoring organization and the intended beneficiaries. Acceptance shows only that the deliverables meet the criteria. To show that benefits are realized, the deliverables also need to be approved and their value confirmed, that is, verified against the target benefits and metrics in the benefits management plan. Option A meets both conditions, “approved” and “value confirmed.” The answer is A.
Why the other options are wrong
- B. On-time completion and no complaints show that the project was carried out steadily and users have no dissatisfaction for now, but that does not mean value has been measured and confirmed. No complaints may also mean nobody is really using it yet.
- C. Solving only the problems the sponsor raised is too narrow. Benefits are the value to the sponsoring organization and the intended beneficiaries as a whole, not to the problems raised by an individual.
- D. Even if team collaboration improved during the project, nothing shows that this was a target benefit, and there is no corresponding value measurement or confirmation, so it cannot be used to judge that the project's benefits were realized.
Key takeaway To confirm that benefits are realized, look at whether the value is confirmed, not just that delivery is complete, the schedule is normal or nobody complains.
Variation If the deliverables pass acceptance but the metrics show the benefits below expectations, report to the sponsor and look for the causes under the benefits management plan.
Reference Business Case and Benefits Management Plan · Lesson 2: Benefits Management Plan: Writing Benefits Down and Tracking Them to the End
- Question 102
On a project, team members work remotely from three cities, and the agreed plan is to use a cloud collaboration platform and high-speed network lines. To cut operating costs, management insists that the project switch to a very low-bandwidth shared server and older lines. What should the project manager do NEXT?
Show answer and explanation
Correct answer: C
Team members work remotely from three cities, and the original plan was a cloud collaboration platform and high-speed lines. To cut costs, management insists on a low-bandwidth shared server and older lines. What should the project manager do next?
Because this instruction conflicts with the agreed plan, the project manager should neither resist it without analysis nor implement it without assessment; the relevant decision authority must be determined from the project's governance arrangements. The appropriate approach is to first assess the impact of the decision on schedule, quality and the team's work, and then communicate with management using data to seek an adjustment or a reasonable trade-off. The assessment is to give the communication data behind it: how much longer slower lines will make the schedule and how much extra rework they will cause, so that management can weigh cost savings against delivery risk. The answer is C.
Why the other options are wrong
- A. Replacing people does not fix a line problem. It passes the problem on to team members.
- B. Asking for another project manager is giving up responsibility, not solving the problem.
- D. Accepting directly and changing the plan neither assesses the impact nor tells management the risk, and the project bears the consequences.
Key takeaway When a management decision affects the project, assess the impact first, then communicate.
Variation If what management demands is improper, such as diverting project funds, correct it and escalate under governance requirements instead of assessing it and then tacitly accepting.
- Question 103
A project manager has just taken over an agile project to develop a membership app for a retail chain, and the requirements list has been compiled. What should the project manager remind the team to focus on FIRST?
Show answer and explanation
Correct answer: B
The project manager has just taken over an agile project, and the requirements list has been compiled. The question asks what to remind the team to focus on first, so you must identify the highest goal of an agile project.
The first of the twelve principles reads: our highest priority is to satisfy the customer through early and continuous delivery of valuable software. So what an agile team focuses on first is providing value to the customer, and cost, schedule and teamwork are considerations that serve that goal. The fact that the requirements list is already compiled is only a starting point and does not change the ordering. The answer is B.
Why the other options are wrong
- A. Lowering cost deserves attention, but agile does not make minimizing cost its highest goal, and adopting agile does not guarantee lower cost.
- C. Finishing on time deserves attention, but in agile, schedule is derived from priorities and team velocity and is not defended as a rigid baseline. Besides, working software is the measure of progress.
- D. Cooperation within the team is a means to achieve value, not the goal itself. Treating a means as the goal is a common switch.
Key takeaway The first goal of agile is to deliver value to the customer. When asked what to focus on “first”, think customer value first.
Variation If the question asks about the main benefit of agile to explain to stakeholders, the answer likewise lands on delivering high-value increments early and continuously, not lower cost or higher speed.
- Question 104
Of the four statements below about “project phases”, only one is accurate. Choose it.
Show answer and explanation
Correct answer: D
Of four statements about project phases, only one is accurate. Judge by how phases are divided, how phases relate to each other and where phase gates can be placed.
PMBOK 8: projects are often decomposed into multiple phases, and each phase culminates in the completion of one or more deliverables and/or outcomes. Phases may be sequential, transitional or overlapping, and some projects use a combination of these relationships. Only D is complete and accurate. The answer is D.
Why the other options are wrong
- A. Finer is not always better. Dividing too finely adds coordination and gate review burden, so divide phases appropriately by deliverables and management needs.
- B. Phase gates are traditionally placed at the end of a phase, but PMBOK 8 states they can also be placed at the start of a phase (pre-phase gates), to confirm that direction is aligned, resources and planning are in place, and risks are addressed.
- C. Phases do not have to be strictly queued. They can be sequential, transitional or overlapping, as when fast tracking lets adjacent phases run partly in parallel.
Key takeaway Phases can be sequential, transitional or overlapping; a phase gate is usually after a phase ends and can also be placed before a phase begins.
Variation If asked what a phase gate review is for, the answer is to check whether the desired outcomes or exit criteria have been achieved, and to decide whether to proceed to the next phase.
Reference The Project Life Cycle · Lesson 1: Project Phases, Phase Gates, and the Trends of Risk and the Cost of Changes
- Question 105
A data migration project has a threat with a 40% probability of occurring and a loss of $50,000 if it does. The team has drafted three options: avoid (cost $15,000, reduces the probability to 0); mitigate (cost $5,000, reduces the probability to 10%); transfer (insurance premium $12,000, the insurer bears the whole loss if it occurs). The project manager uses cost-benefit analysis and compares the options by “expected loss avoided ÷ response cost.” Which option should she choose?
Show answer and explanation
Correct answer: A
A threat on a data migration project has a 40% probability and a $50,000 loss, with three options: avoid, mitigate and transfer. The options are to be compared by “expected loss avoided ÷ response cost” to find the best value.
First calculate the original expected loss, then calculate for each option how much loss it avoids and what it costs, and take the ratio. The higher the ratio, the more loss each dollar spent avoids, and the better the option. Avoiding cuts the probability to 0, which looks the most thorough, but its cost is high. Mitigating reduces the probability only to 10%, but it costs just $5,000, so its ratio is the highest (3). Note that the option with the biggest effect is not necessarily the best value. The answer is A.
- Original expected loss = 40% × $50,000 = $20,000
- Avoid: avoids $20,000 at a cost of $15,000; 20 ÷ 15 ≈ 1.33
- Mitigate: remaining 10% × $50,000 = $5,000, so it avoids $20,000 − $5,000 = $15,000 at a cost of $5,000; 15 ÷ 5 = 3
- Transfer: avoids $20,000 at a premium of $12,000; 20 ÷ 12 ≈ 1.67
- Compare: 3 > 1.67 > 1.33, so mitigate is highest. Net benefit is also largest for mitigate ($15,000 − $5,000 = $10,000), so the conclusion is consistent
Why the other options are wrong
- B. Avoid reduces the probability to 0, which looks the most thorough, but at a cost of $15,000 the ratio is 20 ÷ 15 ≈ 1.33, the lowest of the three. This is the classic mistake of looking at the effect without calculating the cost.
- C. Transfer avoids the full $20,000, but the $12,000 premium gives 20 ÷ 12 ≈ 1.67, lower than mitigate's 3. It treats “someone else bears all the loss” as best and ignores the premium.
- D. Accepting costs nothing but avoids nothing: the $20,000 expected loss remains, so there is no “loss avoided” at all, and it is not the option with the best cost-benefit.
Key takeaway Cost-benefit analysis looks at loss avoided against response cost. The option with the biggest effect is not necessarily the best value.
Variation Compared by net benefit (loss avoided − cost): mitigate 10, avoid 5, transfer 8 (in thousands of dollars), so mitigate is still largest. If mitigation could only reduce the probability to 30%, it would avoid $5,000, the ratio would be 1, and transfer would then be better.
- Question 106
An ordering system project for a retailer uses Scrum, and the team has worked flat out for five Sprints in a row, with members visibly tired. What is the Scrum Master's BEST course of action?
Show answer and explanation
Correct answer: A
On a project using Scrum, the team has worked flat out for five Sprints in a row and members are visibly tired. The question asks for the Scrum Master's best course of action.
The signals are “flat out in a row” and “visibly tired”, which point to principle 8: agile processes promote sustainable development, and the sponsors, developers and users should be able to maintain a constant pace indefinitely. How much work the team can finish is forecast from past performance, current capacity, work complexity, dependencies and impediments, and continuing to overdraw only hurts quality and output. The Scrum Master should work with the team to adjust the pace to a level it can sustain over the long term. The answer is A.
Why the other options are wrong
- B. The stem does not say resources are short. Adding people at short notice does not fix chronic overdrawing, and new people take time to integrate, which slows things down in the short term.
- C. The Daily Scrum is a 15-minute event whose purpose is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary. Lengthening the event violates its timebox; difficulties needing deeper discussion can be addressed afterward.
- D. Asking the team to hold on for a few more Sprints is continuing to overdraw, which goes against sustainable development. Once fatigue builds up, quality and output both decline.
Key takeaway When a team is worn out, first adjust the pace back to a sustainable one. Do not add people or meetings or keep rushing.
Variation If the stem were changed to “overtime only in the last Sprint, occasionally”, you need not adjust the whole pace at once and can inspect it in the Sprint Retrospective. Once the pace is unsustainable, adjust promptly however many Sprints it has lasted.
- Question 107
While a logistics company is implementing a change to its dispatching process, front-line dispatchers broadly resist the new process and refuse to use it. What should the project manager do?
Show answer and explanation
Correct answer: C
The project is in the rollout stage of an organizational change, and front-line staff broadly resist the new process. How should the project manager respond to this resistance?
Resistance usually comes from unclear goals, lack of buy-in, lack of incentives or fear of personal loss. Change management first finds the cause of the resistance, then helps employees through the transition with communication, training and coaching. “Broad” resistance suggests the cause most likely lies in too little communication and support for the change itself, not in individual attitudes. The order is to understand the cause first and then choose the measure that fits: if the goals are unclear, add communication; if skills are lacking, add training; if people fear losing out, listen to their concerns and support them. The answer is C.
Why the other options are wrong
- A. An indefinite pause will not make employees accept the process on their own. The cause of the resistance is still unaddressed and the change is delayed.
- B. Forcing the process through with discipline deepens resistance. Employees comply in form only and have not really accepted the new process.
- D. A pilot in some crews can be an effective strategy, but the stem shows broad resistance. D neither finds out the cause nor explains how pilot feedback would drive overall adoption, so it is less direct and less complete than C.
Key takeaway When employees resist a new process, first learn the cause, then drive the transition with communication, training and support.
Variation If the resistance comes from a department director or senior executive, switch to proactive communication, learning their concerns and winning their support; if departmental rules are the obstacle, record the obstacle and ask the sponsor to coordinate.
Practice test or full mock exam: what is the difference?
- Free practice tests: 8 tests, the first with 120 questions and the others about 107 each, drawn from the 1,000 free questions (you may have met some while practicing by chapter), no login. Good for a quick self-check and for finding your weak domain.
- Full mock exams: 180 questions each, separate from the practice bank (none of them appear there), timed in 3 sittings like the real exam. Use them to judge whether you are ready. See the full mock exams.
Free PMP practice test: common questions
Is this PMP practice test really free?
Yes. There is no account and no email wall. All 107 questions and the full explanation of every answer are free, and your progress is saved in your browser.
How were the 107 questions chosen?
They come from the 1,000 free questions: 28 People, 49 Process and 30 Business Environment questions, covering 24 of the 26 tasks of the Exam Content Outline, with single-answer and multiple-answer questions. There are 8 free tests and no question appears in more than one of them. Once a domain runs out of free questions a test is a little shorter, and the count shown is the real one.
How long does the test take?
Timed mode follows the real exam's pace of 80 seconds a question, so 107 questions get 143 minutes. You can also choose untimed practice and take as long as you like.
How are multiple-answer questions scored?
A multiple-answer question counts as correct only when you select every correct option and nothing else. There is no partial credit, and an unanswered question counts as wrong.
Are these real PMP exam questions?
No. PMI does not release exam questions. Every question here is original, written to the Exam Content Outline, to practice the question styles and the reasoning.
What should I do after the test?
Take another of the free tests, keep practicing by chapter in the 2,876-question bank, or take one of the 10 full mock exams of 180 questions. Your score here is a practice signal, not a prediction of the exam result.
To study first, read the study guide; for the whole bank, practice by chapter.