Free PMP Practice Test 3: 107 Questions with Explanations
107 PMP sample questions, test 3 of 8 with no question repeated from the other tests: 28 People, 49 Process and 30 Business Environment, covering 24 of the 26 tasks of the Exam Content Outline. Timed mode gives 80 seconds a question, 143 minutes in all; or practice untimed. Every question has a full explanation: why the answer is right and what is wrong with each other option. When you submit you get your total score, your accuracy in each of the three domains and a readiness check.
Updated 2026-11-22 · aligned to the current Exam Content Outline and PMBOK Guide 8th Edition
Ready to start?
Your answers are saved in this browser, so you can refresh or come back later. No account needed.
You can read every question below before you start; the answer options unlock when you press Start.
- Question 1
After a Daily Scrum, a member complains that the team is too large and the meeting does not deliver what it should. Later, at the Sprint Retrospective, the team formally proposes splitting into several smaller teams. What should the agile management professional do?
Show answer and explanation
Correct answer: D
After a Daily Scrum, a member complains that the team is too large and the meeting is not effective. At the Sprint Retrospective, the team formally proposes splitting into several smaller teams. The question asks for the right response of the agile management professional.
An agile team is self-organizing, and nobody tells the team how to organize and manage its own work. The team has put forward a reorganization proposal through the Sprint Retrospective, which shows it has discussed and come up with a plan. The most appropriate step is to support and allow the team to decide for itself whether to reorganize and to carry it out itself. The answer is D.
Why the other options are wrong
- A. The problem is that the team is too large, not that members misunderstand the value of the meeting, so stressing the value does nothing about the size problem.
- B. A self-organizing team can handle this kind of problem itself, so there is no need to escalate it, let alone ask the sponsor to rule. Escalating weakens the team's decision-making authority.
- C. “Directly cutting headcount and having only some members attend” decides for the team, and with only some members attending, the whole team does not benefit. It is also not the “split” the team wanted.
Key takeaway When the team finds and raises a problem itself, let the team decide how to solve it.
Variation If the stem were changed to “the team has grown to 14 people and the Scrum Master finds the meeting room cannot hold them”, the answer would still be to have the team take part in reorganizing into several smaller, cohesive Scrum Teams, usually no more than 10 people each, focused on the same product and sharing the Product Backlog and Product Owner.
- Question 2
Before an iteration begins, an agile team builds a prototype of a feature. After seeing it, the customer gives a large amount of mutually contradictory feedback, and the team discusses it. Some members argue for starting this iteration right away. Others want to review the prototype with management first and only then go back to the customer. What should the team do?
Show answer and explanation
Correct answer: C
On an adaptive project, the team built a prototype before the iteration started and the customer's feedback was heavily contradictory. The team itself disagrees about whether to start the iteration and review with management first. The question asks what the team should do.
“Contradictory feedback” shows that the requirements have not yet been clarified, not that the plan has changed. Adaptive projects resolve this by frequent communication: talk with the customer in depth, find out what is really needed, then set priorities by value and run the iteration on that basis. This reflects value-driven work and customer collaboration. The answer is C.
Why the other options are wrong
- A. Treating the contradictory comments as a risk to analyze qualitatively and quantitatively is the wrong direction. When requirements are unclear, what is needed is communication and clarification.
- B. Submitting a change request and waiting for the customer's confirmation is how requirement changes are controlled against a baseline. Iterative work adjusts requirements through the backlog and communication, and here the requirements were never settled in the first place.
- D. Finishing to the original design first and going back to the customer afterward means continuing to develop with the contradictions unresolved. Later rework will be greater, which goes against early feedback.
Key takeaway With contradictory feedback, communicate and clarify first, then order by value. Do not go through the change process and do not push on to hit the schedule.
Variation If the stem were changed to “during the iteration, the customer raises a new feature that does not conflict with the original requirements”, the answer is to write it into the product backlog for the Product Owner to order.
- Question 3
A retailer divides a new point-of-sale system project into four phases, each phase going live at a batch of 5 stores per region. The governance arrangement requires administrative closure of one phase before planning of the next phase begins. The full scope of the first batch (phase 1) was completed on time, cost is within budget, the customer has formally accepted it, and the phase exit criteria are met. What should the project manager do next?
Show answer and explanation
Correct answer: B
The retailer rolls out the point-of-sale system in four batches, one phase per batch, 5 stores per region. The first batch has finished its scope on time, is within budget, and has been formally accepted by the customer. The question asks what the project manager does next.
The first batch has met the scope, cost and acceptance conditions, so the work of this phase is done. The next step is to end the phase, that is, to carry out administrative closure for the first batch: archiving, summarizing lessons learned, confirming acceptance records, and releasing resources no longer needed. After phase acceptance passes, closure of that phase comes first. Under the governance arrangement in this question, planning of the next batch can begin only after this phase's administrative closure is complete, so it is not the first thing to do. The answer is B.
Why the other options are wrong
- A. The stem does not show that the quality management plan or the organization requires another quality audit now. The first batch has passed formal customer acceptance and the exit criteria are met, so the phase should now be closed.
- C. Customer acceptance has already recognized the result, which does not need further approval by the portfolio manager, and such approval is not a step at this point.
- D. The governance arrangement in this question requires administrative closure of one phase before planning of the next, and since the exit criteria are met, first carry out administrative closure of this phase. Planning the next batch is not the first thing to do.
Key takeaway After the phase exit criteria are met and acceptance has passed, close that phase first. Under the governance arrangement, planning of the next phase begins only after closure is complete, so it is not the first step.
Variation If acceptance of the first batch had not passed, you could not close, and would deal with the acceptance problem first. After all batches are done, you carry out the final closure for the whole project.
- Question 4
A hotel chain's membership management system project enters its closure review, and several stakeholders raise concerns that some deliverables may not meet the closure criteria agreed in advance. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
The project enters its closure review and several stakeholders worry that some deliverables may not meet the closure criteria agreed in advance. The question asks what the project manager should do first.
The closure criteria are the basis for ending the project that all parties agreed in advance, and the issue now is that they “may not be met”, so the facts are unclear. The first step is to establish the facts: analyze thoroughly against the closure criteria, item by item, to find out which criteria are truly not met and why, and only then decide whether to remedy, negotiate or change. The other options draw conclusions or take action before the cause is known. The answer is D.
Why the other options are wrong
- A. Giving assurances with no factual basis neither removes the concern nor avoids hiding a real gap.
- B. The closure criteria are the yardstick everyone approved in advance. Deleting unmet clauses just to pass the review violates professional principles and loses the stakeholders' trust.
- C. Correcting course, changing the criteria and extending the schedule all at once, before the cause is clear, tends to waste resources and may not address the problem.
Key takeaway When closure criteria are disputed, analyze the facts first and then act. Do not make empty promises, and do not change the criteria just to pass.
Variation If the analysis confirms that two criteria are indeed not met, agree a remedy and timeline with the sponsor and customer. If it shows all are met, give the analysis to the stakeholders to remove their doubts.
- Question 5
The solution for a multinational logistics system project is set at headquarters in Country A and goes live in three batches in Country B, Country C and Country D. Only before the go-live in Country B is it discovered that a local law requiring data to be stored within the country has not been met. To avoid this, what should the project manager have done in advance?
Show answer and explanation
Correct answer: C
The solution is set at headquarters in Country A and goes live in three batches in Countries B, C and D. Only before the go-live in Country B is it discovered that a local law requiring in-country data storage is not met. To prevent such a compliance miss, the project manager should have identified each country's regulatory differences at the right time.
The root of the problem is that the solution was defined in one country but is to be delivered in several, and the fact that each country's regulations differ was not identified at the definition stage. The signal is “only before the go-live in Country B”, which shows identification was too late. To prevent it, identify the regulatory differences country by country during planning and include them in the scope and plan as project requirements, and before entering a new country, check the local rules with legal. The answer is C.
Why the other options are wrong
- A. Staffing local resources and suppliers does not change the scope that was defined by the headquarters solution. If the solution did not take local law into account, it will still be in violation once the resources are in place.
- B. This option focuses on risk responses and a review before go-live and does not state that regulatory differences are identified during planning and included in the project requirements. If handled only after the solution is fixed, it may cause rework, and a review right before go-live may be too late, so it is less targeted and less preventive than C.
- D. The project must deliver in these countries, so limiting the countries avoids the problem instead of solving it, and may depart from the project objectives.
Key takeaway On multinational projects, identify the regulatory differences of each country during planning and include them in the project requirements.
Variation If the stem changed to “the requirement of a certain country was discovered only after execution had begun”, the answer becomes: first assess the impact, then add the compliance requirement and do not carry on with the original solution. A predictive project with an established baseline goes through the change process, while an adaptive project updates and reorders its backlog.
- Question 6
A residential community project built by PMLyceum originally planned to pour concrete on site, and night work would cause continuous noise for nearby residents. Following the sustainability principle, the team discusses strategies for dealing with this external impact. Which strategy has the greatest impact and best fits the direction of the principle?
Show answer and explanation
Correct answer: A
The residential community project originally planned to pour concrete on site, and the noise of night work would disturb residents continuously. Following the sustainability principle, the team compares strategies for dealing with the external impact, and the question asks which has the greatest impact.
The Eighth Edition classifies strategies for external impacts as increasingly impactful. Figure 3-7 shows four levels from the bottom up: compensate or offset, restore, minimize, and avoid. Judge which level each option belongs to: switching to factory-precast components and cancelling night pours on site removes this continuous noise at its source (noise from transport and crane installation is a separate matter), so it is avoidance, the highest level. The answer is A.
Why the other options are wrong
- B. Adding sound-insulating panels to the hoarding still produces the noise; less of it gets out. That is minimization.
- C. Paying noise allowances to residents is compensation, making up for disturbance already caused. The noise itself is not reduced, so it is the lowest level.
- D. Shortening the night period and limiting machines also reduces degree and duration, but the noise still exists. That is minimization.
Key takeaway Compensate or offset < restore < minimize < avoid: where an impact can be prevented at the source, do not stop at compensating or reducing it.
Variation If option A were changed to “after construction damages community facilities, repair them and restore their original function”, it would belong to the second level, restore, higher than compensation and lower than minimization. If asked which option fits the “minimize” level, the answer becomes adding sound-insulating panels or shortening the work period.
- Question 7
A government services app project uses an agile approach. Because of a policy change, the customer asks for a new feature in the middle of an iteration. Time and cost are fixed, and the team's workload is already full. What should the project manager do?
Show answer and explanation
Correct answer: C
This is an agile project, in the middle of an iteration. The customer asks for a new feature because of a policy change; time and cost are fixed and the team's workload is already full. The question asks what the project manager should do, and the change must be handled the adaptive way.
In an adaptive environment, changes are typically managed through the product backlog: their impact is assessed and their priority is set, the product owner manages their ordering, and items are pulled into an iteration at iteration planning. When time and cost are fixed and the team's capacity is fully allocated, the new feature is accommodated by adjusting priorities: it goes into the backlog and is compared by value with the other work items, and only if it ranks high enough does it displace lower-priority work. The answer is C.
Why the other options are wrong
- A. In adaptive work, changes are typically handled through backlog management rather than a formal change request process. Sending the change to the CCB for approval is the predictive approach.
- B. “Welcoming change” does not mean accepting everything unconditionally. The project manager should not reject the request unilaterally merely because the iteration scope is set; assess and prioritize it with the product owner, who may then decide not to add it to the backlog.
- D. In adaptive work, scope is typically adjusted through the backlog. The stem also fixes time and cost and gives no basis for amending the contract to add budget and time.
Key takeaway In adaptive work, new requirements go into the backlog and are ordered by value; in predictive work, once baselines are established, changes go through formal change control.
Variation If the same request arose in a predictive project, the answer would become: evaluate the impact and submit a change request. If asked whether it can be added to the current iteration directly, the answer is that neither the customer nor the project manager can simply insert it. It goes into the product backlog first; if it does not endanger the iteration goal, the team can negotiate an adjustment of the current iteration scope with the product owner, otherwise it waits for a later iteration planning.
- Question 8
A mobile app development project is in execution when the project manager meets a risk event that is in no risk response plan and was never identified. What should the project manager do first?
Show answer and explanation
Correct answer: B
During execution, a risk event occurs that is in no response plan and was never identified. The question asks what the project manager should do first.
The signals are "in no response plan" and "never identified." This is an unknown-unknown risk. There is no ready-made response to look up and no contingency reserve set aside for it. The first action is a workaround (a common exam term), which the project manager develops by calling the team together. If funds are needed, then submit a change request to use management reserve. The answer is B.
Why the other options are wrong
- A. Management does need to be informed, but that is not the first action. The project manager should lead the team in working out a response instead of waiting for a decision.
- C. Contingency reserve is set aside for identified risks, so it cannot be used directly for an unidentified one.
- D. Using management reserve requires a change. That comes after the workaround is settled and funds are needed; it is not the first step.
Key takeaway When an unidentified risk occurs, first develop a workaround; if funds are needed, submit a change request to use management reserve.
Variation If the stem said the event was recorded in the register, the answer would be to carry out the response and draw on contingency reserve as needed. If the question asked what to do when the workaround needs funds, the answer is to submit a change request to use management reserve.
- Question 9
PMLyceum is building a new logistics sorting center. The project manager had long ago recorded “negotiations with the campus property manager on the site-entry agreement may be delayed” in the risk register and prepared a response plan. The negotiations are now indeed delayed, slowing the schedule, and installation of the first-phase equipment is about to begin. What should the project manager do?
Show answer and explanation
Correct answer: B
On the logistics sorting center project, the risk of delayed site-entry negotiations was already registered and has a response plan. It has now occurred and slowed the schedule, with first-phase equipment installation about to start. The question asks what the project manager should do.
Once a risk occurs, it becomes an issue. The stem's conditions are: the risk was identified, a response plan exists, and it has now occurred. PMBOK 8 distinguishes a risk from an issue: an issue is a condition that already exists or has occurred and is recorded in the issue log. Because the response was planned long ago, the project manager does not need to discuss options again and simply acts on the actions set in the response plan, using contingency reserve if necessary, to minimize the impact on the installation schedule. The answer is B.
Why the other options are wrong
- A. Looking for contract resources and submitting a change request skips the ready-made response plan. A change request is for measures that would change the baseline; when the response plan can handle it, there is no need to raise one first.
- C. Escalating to the steering committee is for situations beyond the project manager's authority or beyond what the manager can handle. With a response plan in place, act on it first.
- D. Holding a meeting to decide how to mitigate means working out after the event what should already have been decided. The set plan should simply be carried out.
Key takeaway When an identified risk occurs, record it in the issue log and act directly on the risk response plan.
Variation If the negotiation delay had been neither registered nor planned for but had now occurred and slowed progress, it would be an issue arising from an unidentified risk. Record it in the issue log, assess the impact and agree on a response with stakeholders; if necessary, seek release of management reserve under organizational authority, and raise a change request if a baseline must change.
Reference Monitor Risks · Lesson 5: When a Risk Occurs: Reserves, the Issue Log and Workarounds
- Question 10
A large campus energy-upgrade project has been approved for $8.5 million in funding, but the funds cannot be drawn on. Procurement cannot begin, and the cost of delay keeps rising. What should the project manager do?
Show answer and explanation
Correct answer: B
A large campus energy-upgrade project has $8.5 million approved but cannot draw on it, so procurement cannot begin and the cost of delay keeps rising. The question is what the project manager should do. The signal is “approved funds cannot be drawn,” which means the problem lies outside the project.
The obstacle to releasing the funds sits at the organizational level and is beyond the project manager's authority. PMBOK 8 explains that in hierarchical organizations where decision-making authority includes people outside the project team, escalation is useful, because higher-ranking individuals can remove persistent obstacles. The project manager should follow the escalation path and report the problem to the project steering committee, together with the impact of the delay, so that the committee can work with the finance department and senior leaders to resolve it. The answer is B.
Why the other options are wrong
- A. A results demonstration is for showing results and collecting feedback, not for dealing with obstacles to releasing funds. Inviting finance to attend does not fix the approval or disbursement process either.
- C. The requirements are already approved. The problem lies in the funds, not the requirements, so reviewing requirements misses the root cause. The funds still cannot be drawn and procurement still cannot start.
- D. With procurement unable to start, the available resources are unlikely to support later work, and pushing on will only make the delay worse. Waiting for the problem to resolve itself abandons the project manager's responsibility to escalate.
Key takeaway An obstacle beyond the project manager's authority is reported along the escalation path to the governance body with authority to resolve it.
Variation If the funds only needed the project manager to add an application document, add it yourself. If the obstacle came from an external supplier's breach, handle it under the contract terms rather than ask the steering committee for money.
- Question 11
PMLyceum is developing a smart irrigation system for an agricultural cooperative under a time-and-materials contract, and has also signed a fixed-price contract with a subcontractor for the data-collection equipment. Earned value analysis by the team confirms that the project can finish early and that actual spending will come in below the original budget. This will reduce the company’s profit, and the project manager’s profit-based bonus will fall with it. What should the project manager do?
Show answer and explanation
Correct answer: B
The company is developing a smart irrigation system for an agricultural cooperative under a time-and-materials contract and has a fixed-price contract with an equipment subcontractor. Earned value analysis shows the project can finish early and spend less than the original budget, which will reduce company profit and the project manager’s profit-based bonus. The question asks what the project manager should do.
Under a time-and-materials contract, the cost savings mainly benefit the customer, and the customer is entitled to know the true schedule and cost. The Eighth Edition requires an accountable leader to have integrity, honesty and fairness, to make decisions focused on the common good, and to disclose honestly and make sure reports reflect the real progress of the project. The project manager cannot conceal this because of company profit or a personal bonus, and should tell the cooperative honestly that the project can be finished early and costs saved. The answer is B.
Why the other options are wrong
- A. With no request from the customer, the project manager proposing to bring back deleted requirements in order to use up the savings and protect profit is still putting self-interest first.
- C. Having the subcontractor deliberately slow down artificially delays the schedule to maintain profit. It harms the customer’s interest and also distorts the real performance.
- D. Raising acceptance test standards and workload for no need amounts to padding costs to reach the budget, with the customer paying for it. That is equally dishonest.
Key takeaway When personal or company interests conflict with the customer’s, report the real schedule and cost honestly.
Variation If the contract were fixed-price, with savings going to the supplier, you should still report progress honestly, but there is no need to lower the price because of the savings.
Reference Project Management Principles · Lesson 4: Professional Ethics and Professional Conduct
- Question 12
While identifying risks, a project team wants to first find the organization's strengths and weaknesses, then judge to what extent the strengths can offset threats and whether the weaknesses will hinder opportunities from emerging. Which analysis technique should be used?
Show answer and explanation
Correct answer: B
While identifying risks, the team wants to first find the organization's strengths and weaknesses, then judge how far strengths can offset threats and whether weaknesses hinder opportunities.
“Strengths”, “weaknesses”, “offset threats” and “hinder opportunities” in the stem are one method's full routine: list the organization's strengths and weaknesses, then look at the opportunities that strengths bring and the threats that weaknesses cause, and analyze how much strengths can offset threats and whether weaknesses will hinder opportunities. That is SWOT analysis, which can identify both threats and opportunities. The answer is B.
Why the other options are wrong
- A. Root cause analysis starts from a problem statement or a benefit statement and asks about the deeper cause behind it; it does not analyze how strengths and weaknesses offset one another.
- C. Checklist analysis goes through a list built from past similar projects item by item as a reminder; it does not cross-analyze strengths and weaknesses.
- D. Assumption and constraint analysis tests whether the assumptions the project rests on are valid and whether constraints can be relaxed; it has nothing to do with the organization's strengths and weaknesses.
Key takeaway Strengths offsetting threats and weaknesses hindering opportunities is the signature of SWOT analysis.
Variation “Test whether the premises behind the plan are valid” is assumption and constraint analysis; “trace the deeper cause of a problem” is root cause analysis.
- Question 13
The members of a product development team are located on several continents and are building one product together. What is the most typical interpersonal problem associated with this kind of distributed arrangement?
Show answer and explanation
Correct answer: B
A product development team is spread across several continents and builds one product together. The question asks which problem is most typical of such a distributed arrangement, and specifically at the interpersonal level.
PMBOK 8 notes that remote and virtual teams face heightened challenges due to varying work styles, time zones, and the absence of in-person interaction, which can hinder collaboration and relationship building. When members are dispersed, have little day-to-day contact, and also face differences in language, culture and time zone, they tend to cluster into local groups and develop an “us versus them” attitude. This is the most typical interpersonal problem of distributed teams (“us versus them” is a common exam term). The answer is B.
Why the other options are wrong
- A. Remote members can misunderstand the business and domain context, but that comes from information being lost in transmission. It is not specific to distributed arrangements, and colocated teams misunderstand too.
- C. Incompatible technical decisions can be a symptom of poor coordination, but they are not a direct result of geographic dispersion and are not the most representative problem of such teams.
- D. Colocated developers agreeing with the customer has no necessary link to a distributed arrangement. If anything, remote communication often leads to a skewed understanding of the customer.
Key takeaway The typical risk of distributed teams is isolation and an “us versus them” split, which is addressed through communication and trust.
Variation If the question asked about the typical benefit of a colocated team, the answer would be that information flows promptly among members through osmotic communication.
Reference Virtual Teams · Lesson 1: Colocation and Virtual Teams: Meaning, Advantages and Disadvantages
- Question 14
PMLyceum is renovating an exhibition hall. When the project manager develops the schedule, the plan allows 3 days of curing after the floor screed is finished, and only then can display case installation begin, so the screed can cure before the display cases go on it. Which of the following has the project manager applied?
Show answer and explanation
Correct answer: D
While developing the schedule for an exhibition hall renovation, the plan allows 3 days of curing after the floor screed is finished before display case installation can start. Which of the following has been applied?
The key signal is “after it finishes, you must wait another 3 days before starting”. A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity, and here it is written FS+3. The 3 days of curing are a required wait, recorded on the link, and they are not counted in the duration of the display case installation. If a fast-drying material shortened the curing, you would only change the number on the link. So what has been applied is a lag. The answer is D.
Why the other options are wrong
- A. A lead is time by which the successor can start earlier, which is the opposite direction. The stem requires a delay, not an advance.
- B. Free float is the amount of time an activity can be delayed without delaying the early start of its successor. It is calculated slack, not a required wait.
- C. Total float is the amount of time an activity can be delayed without delaying the project finish date. It is also calculated slack, while a lag must be observed.
Key takeaway A lag is time you must wait, and float is time you can delay. Do not mix them up.
Variation If it said display case installation could start when the floor screed had 1 day of work remaining, that would be FS with a 1-day lead (FS−1). If asked in whose duration the curing time is written, the answer is neither the screed's nor the installation's: it is recorded as the lag on the link.
- Question 15
A consulting firm spots a short-term overseas bid opportunity. It temporarily assembles experts from partner organizations in several cities, and they complete the bid by collaborating over the network. The team disbands once the award is announced. Which organizational form does this arrangement represent?
Show answer and explanation
Correct answer: D
For a short-term overseas bid opportunity, a consulting firm temporarily assembles experts from partner organizations in several cities, who complete the bid by collaborating over the network. The team disbands after the award. The question asks which organizational form this is.
In PMBOK 8 Table 2-1, the virtual/network form has a network structure with nodes at points of contact with other people, and members are dispersed and work together over the network. In the stem the experts come from partner organizations in several cities and collaborate over the network throughout, which fits a virtual network structure. “Temporarily assembled and disbanded after the award” is only a helper clue and cannot decide the type alone. The answer is D.
Why the other options are wrong
- A. An organic or simple organization is informal and flexible, with little work specialization, few management layers and light supervision. It stresses flexible collaboration, whereas the stem's defining feature is members connected through networked points of contact (here across several cities).
- B. A multidivisional organization has a center and several semi-autonomous divisions or units. The center sets financial targets and each unit replicates functions. That is different from networked collaboration among dispersed members.
- C. A hybrid combines several structure types. The stem describes no mix of several structure types; the network collaboration is the prominent feature.
Key takeaway Dispersed members who collaborate through networked points of contact indicate a virtual network structure; temporary assembly and disbanding at completion are only helper clues.
Variation If a corporation has three branches in the northeast, north and south, each with its own procurement, finance and project management, and headquarters sets only annual targets, it is multidivisional; if a few people work flexibly together with no fixed hierarchy, it is organic or simple.
- Question 16
A project that matters greatly to the company is in execution. The budget is very tight, and scope, schedule and cost must all be protected at the same time. A team member warns the project manager verbally that costs may overrun significantly, but neither the amount nor the cause is clear yet. What should the project manager do NEXT?
Show answer and explanation
Correct answer: C
The project is in execution with a tight budget. All the project manager has is a verbal warning from a team member; the amount and cause are unknown. The question asks what to do next.
What is missing most right now is facts: where the overrun comes from, how large it is, and whether it will continue. Only after the cause is found can corrective actions be chosen precisely, and only then are there concrete numbers to compare with the cost control threshold and to assess whether reserves are enough. Investigate first, then judge, then act: that is the sensible order for handling variances. The answer is C.
Why the other options are wrong
- A. The overrun is still only something that may happen, which makes it a risk and belongs in the risk register, not the issue log. Merely recording and monitoring also takes no action.
- B. Checking reserves before the cause is understood assumes the overrun is certain and tries to cover it with money. If the cause is not removed, the overrun will grow.
- D. The actual overrun amount is not known, so it cannot be compared with the threshold in any meaningful way. A threshold can be used to judge whether a variance is acceptable, whether preventive or corrective action is needed and whether to escalate, but it does not replace investigating the cause.
Key takeaway When you hear of a possible overrun, find the cause and the amount first, then compare with the threshold and discuss reserves and corrective actions.
Variation If the overrun were confirmed at 12% against a 10% threshold, the next step would be to evaluate corrective actions and submit a change request as needed.
Reference Earned Value Management · Lesson 4: What the Project Manager Does After Finding a Variance
- Question 17
A software project at PMLyceum has entered execution, and during testing the team has accumulated new defect statistics and a review checklist worth sharing across the organization. One member thinks “organizational process assets are set by the organization, and the project team can only use them and not touch them.” How should the project manager respond?
Show answer and explanation
Correct answer: A
The project is in execution, and the question asks about a statement concerning organizational process assets.
Organizational process assets are artifacts, practices and knowledge accumulated inside the performing organizations involved in the project. They are internal resources of the organization; when authorized, project team members can update their knowledge repositories throughout the project, and defect statistics can go into such a repository. A review checklist normally belongs to policies, processes and procedures; it may be tailored where the organization encourages tailoring, while updates to the organizational standard must follow organizational policy. The answer is A.
Why the other options are wrong
- B. This confuses organizational process assets with enterprise environmental factors. Enterprise environmental factors are conditions the team cannot directly control and must assess and adapt to. Organizational process assets are internal resources: where organizational authorization permits, team members may update knowledge repositories throughout the project, not only at closure, while changes to policies, processes, and procedures must follow organizational procedures.
- C. This overgeneralizes. What the project management office mainly establishes are policies, processes and procedures, and it is those assets that are usually not updated as part of project work. Organizational knowledge repositories are continually updated with project information, and team members may add to them where organizational authorization permits.
- D. Organizational process assets include both the lessons learned and historical information of earlier projects and the information this project produces and keeps updating, such as defect data and performance metrics, so this project's information can also go into the repository.
Key takeaway Organizational process assets are internal resources whose knowledge repositories the team may update throughout the project where organizational authorization permits; it is enterprise environmental factors that the team cannot directly control and must adapt to (mandatory rules among them must be obeyed).
Variation If a member says “lessons learned can be written into the organizational knowledge repository only when the project closes,” that too needs correcting: they can be updated at any time during the project. If a member says “policies, processes and procedures are generally not updated as part of project work,” that is correct, but add that they can be tailored under the tailoring guidelines, and updates go through the organization's procedures.
- Question 18
PMLyceum has put together a diverse international team that will collaborate virtually, and the members have never worked together before. The project manager is developing the communications management plan. For the plan to be effective, what should the project manager do first?
Show answer and explanation
Correct answer: B
During planning, the project manager is developing the communications management plan for an international virtual team that has not worked together before. The question asks what must be done first for the plan to be effective.
The communication model points out that the sender's and receiver's emotional state, knowledge, background, personality, culture and biases all affect how a message is expressed and understood and can create noise. For a multinational virtual team with no shared working history, cultural differences are a key consideration when developing the plan. So first work out how cultural differences affect communication effectiveness, then choose methods and tools accordingly; that is what cultural awareness calls for. The answer is B.
Why the other options are wrong
- A. One-way push cannot confirm that the other side has understood, and helps little with an unfamiliar virtual team.
- C. A cloud folder is just a place to store things. It does not touch the root problem of cultural differences, and it is not what should be done first.
- D. A communications manager can help, but the project manager first has to understand cultural differences for the plan to stand on solid ground.
Key takeaway When developing a communication plan for a cross-cultural team, first study the cultural differences, then choose tools and methods.
Variation If the team were in one city with similar cultures, you would first run a communication requirements analysis. If the question said “members always just nod and never ask questions,” the answer would still be to consider cultural awareness and set up a feedback mechanism.
- Question 19
A logistics company's route-scheduling software project is in scope monitoring before acceptance. While verifying deliverables, the project manager finds that the completed “exception order handling” module does not match what the scope statement requires. What should the project manager do?
Show answer and explanation
Correct answer: B
In scope monitoring before acceptance, the project manager finds that the completed “exception order handling” module does not match the scope statement.
A deliverable that fails verification calls for analysis of why it differs and then the appropriate change request. If the team made a mistake, submit a defect-repair or corrective-action request; if the scope itself needs to change, submit a scope change request. Both are reviewed and approved under the change management plan before the deliverable is repaired or the scope is updated. Verification here takes place before acceptance and keeps problems from reaching customer acceptance. The answer is B.
Why the other options are wrong
- A. Recording the difference as “minor” and still submitting for acceptance hides the problem. A deliverable that has not passed verification should not go into Validate Scope.
- C. The scope statement is part of the scope baseline and cannot be changed just to fit a module that has been built; baseline changes go through change control.
- D. Having the team delete features without analyzing the cause may move the deliverable further from the requirements, and it does not use change control.
Key takeaway When a deliverable does not match the scope statement, analyze the cause first, then submit the appropriate defect-repair, corrective-action or scope-change request.
Variation If the analysis finds that the customer's requirements have changed, submit a scope change request, update the baseline once it is approved, and re-verify. If the team simply missed something, submit a defect-repair or corrective-action request, complete the repair after approval, and re-verify.
- Question 20
A team is developing a product with an agile approach. Before launch, all features must reach a pass rate of 97% in customer acceptance testing. Which measure should the team take to achieve this?
Show answer and explanation
Correct answer: A
A team is developing with an agile approach. Before launch, all features must reach a pass rate of 97% in customer acceptance testing. The question asks which measure assures quality.
Test-driven development (TDD) is common agile team practice: write the developer tests first, then write code that makes the tests pass, and keep refactoring. It catches regression problems early and improves built-in quality, so a high pass rate is easier to reach at acceptance. The customer's acceptance requirement itself still has to be verified through clear acceptance criteria and acceptance testing, and TDD alone cannot guarantee 97%. Centralized testing at the end and a fixed block of debugging time both belong to plan-driven thinking. The answer is A.
Why the other options are wrong
- B. Following a test plan prepared in advance and testing together after development reveals defects very late. It is plan-driven, and agile stresses responding to change.
- C. Setting aside a fixed four days for approval and debugging is likewise a traditional, after-the-fact approach, and it cannot keep assuring quality during development.
- D. Agile accepts that the future is uncertain and the test steps cannot all be locked in at the start, so a “highly predictable” process does not fit agile.
Key takeaway To reach a high pass rate at acceptance, verify continuously during development with TDD instead of relying on centralized testing at the end.
Variation If code from several teams often conflicts, the corresponding practice is continuous integration, not TDD.
Reference Extreme Programming · Lesson 2: XP Technical Practices: Test-Driven Development, Refactoring, Pair Programming and Continuous Integration
- Question 21
The project is in the execution phase. The project manager sees that the front-end group and the back-end group have both a technical disagreement over the interface design and mutual complaints, and relations are tense. What should the project manager do?
Show answer and explanation
Correct answer: C
During execution, the front-end and back-end groups have a technical disagreement about the interface design and also complain about each other, and relations are tense. The question asks what the project manager should do.
The conflict is already affecting collaboration, so the project manager should step in promptly. Calling the team together to understand what happened and then discussing solutions jointly is collaborate/problem-solve, and it follows the order of identifying the source and understanding the background first. A problem arising during execution should be resolved during execution. The meeting has to deal with both the technical disagreement and the emotional complaints: first get both sides to set out the facts, and then discuss solutions. The answer is C.
Why the other options are wrong
- A. A fixed quarterly meeting would miss the window, because conflict is time-sensitive, and the tension would keep festering until then.
- B. Lessons learned and retrospectives should run throughout the project, not only at its end. But this conflict is hurting execution now, so it cannot be put off to a later review activity. It needs prompt understanding and resolution.
- D. Conflict inside the team is within the project manager's authority and should be handled by the project manager first, without bringing in an outside consultant.
Key takeaway When you see conflict, step in promptly, gather the parties and work out the source and solutions together.
Variation If the conflict were a personality clash that neither the team nor the project manager could resolve, only then consider formal channels such as human resources.
- Question 22
An industrial water pump project has delivered all the equipment to the client. A few weeks later the client writes that the pumps' flow rate fluctuates widely and is disrupting their production line. The project team has to pay to fix the problem. Which category of cost of quality does this cost belong to?
Show answer and explanation
Correct answer: C
All the industrial water pumps have been delivered, and a few weeks later the client writes that the flow rate fluctuates widely, and the team has to pay to fix it. The question asks which category of cost of quality this cost belongs to.
Cost of quality has four categories: prevention, appraisal, internal failure and external failure. To tell whether a failure cost is internal or external, look at who found the nonconformance: internal failure costs arise when the project finds it, and external failure costs arise when the customer finds it. Here the client discovered the defect in use weeks after delivery and the team has to resolve it, so the loss is an external failure cost (warranty work, liabilities and lost business belong to the same category). External failure is often the most expensive: besides compensation and warranty work you may lose business, which is why prevention spending is usually worthwhile. The answer is C.
Why the other options are wrong
- A. Internal failure costs are the rework and scrap that arise when project staff find defects. Here the client found the defect while using the equipment after delivery.
- B. Prevention costs are investments made to prevent poor quality, such as training and documenting processes. The problem has already occurred, so this is not prevention.
- D. Appraisal costs are what is spent on evaluating, measuring, auditing and testing the product. Only the cost of inspection and testing itself counts as appraisal. This question is about the cost of remedying a defect the client found, which is an external failure cost.
Key takeaway To tell internal from external failure, see who found the nonconformance: the project (internal) or the customer (external).
Variation If the same defect had been found by the quality inspector in the final inspection and reworked, the cost would be an internal failure cost, and the cost of the inspection itself would be an appraisal cost.
- Question 23
The project manager of an online education platform leads a team that is highly diverse in cultural background and gender mix, on a short, high-pressure project. To better understand the team’s state and bring out its best, which of the following skills should the project manager use to manage team performance?
Show answer and explanation
Correct answer: C
The project manager of an online education platform leads a team that is diverse in cultural background and gender, on a short, high-pressure project. The question asks which skill to use to understand the team’s state, lift it and manage team performance.
The key phrases are “high pressure, diverse team, understand and lift the team’s state”; the thing to work with is people’s emotions and interactions. Emotional intelligence lets the project manager identify, assess and control members’ sentiments, anticipate their actions, acknowledge their concerns and follow up on their issues, which reduces tension and increases cooperation. It is a skill that can be used before conflict arises, and PMBOK 8 calls it “a basis of all forms of leadership.” The answer is C.
Why the other options are wrong
- A. Negotiation is used to reach agreement between different positions. The stem names no party or issue on which agreement must be reached.
- B. Conflict resolution primarily addresses a specific disagreement that has already arisen. It may also use emotional intelligence to identify and guide emotions, but this stem describes only pressure and team diversity, not a conflict that needs resolution.
- D. Forcing pushes one viewpoint at the expense of others and offers only win-lose solutions, usually enforced through power to resolve an emergency. In this high-pressure team situation, it would only add to the pressure and is generally not the preferred choice (common exam practice).
Key takeaway When a stem gives only pressure and team diversity, with no specific disagreement, emotional intelligence is the more direct skill; choose negotiation or conflict resolution when the situation actually involves reaching agreement or resolving a dispute.
Variation If the stem said two members were deadlocked over a technical solution, it would fall under conflict resolution; if the goal were to obtain another party’s agreement on resources, it would be negotiation.
- Question 24
You are planning an agile project. The team members are experienced, and you let them choose their own tools. They are discussing how to show clearly what work is currently in progress. Which tool are they MOST likely to choose?
Show answer and explanation
Correct answer: C
The team members are experienced and are choosing their own tools. They are discussing how to show clearly what work is in progress right now. The question asks which tool they are most likely to choose, so focus on “work currently in progress”.
The task board described in PMBOK 8 is a visual representation of the planned work that allows everyone to see the status of the tasks. It can show work that is ready to be started (to do), work in progress, and work that is completed. With it, anyone can see at a glance the status of a particular task or the number of tasks in each stage, and it also helps reveal bottlenecks. The stem asks for a clear display of work in progress, so the answer is C.
Why the other options are wrong
- A. The user story backlog is an ordered list of work to be done, but it does not show which work is currently being handled or its real-time flow status.
- B. The product roadmap describes what the product will deliver and when. It looks ahead and does not show the state of current work in progress.
- D. The work breakdown structure decomposes project scope level by level. It shows the composition of the scope and not the flow state of the work.
Key takeaway To show what is currently in progress, use a task board (kanban board).
Variation If the question asked how to limit the amount of work under way at once, set WIP limits on the columns of the task board. When the number of tasks in a column nears the limit, the team should first help clear the blockage.
Reference Kanban · Lesson 1: Kanban Boards, Pull and WIP Limits
- Question 25
PMLyceum adds a bonus clause tied to service levels in an equipment maintenance contract. What is the main function of an incentive clause like this?
Show answer and explanation
Correct answer: B
PMLyceum adds a bonus clause paid by service level to an equipment maintenance contract, and the question asks what the main function of this kind of incentive clause is.
An incentive clause ties the seller’s extra earnings to the performance the buyer cares about: the seller earns more when it reaches the service level, the goals of buyer and seller move closer together, and the seller is motivated to improve performance. PMBOK 8 Appendix X4 says the goal of structuring contracts should always be to create a win-win scenario that fosters collaboration, and target-cost contracts likewise encourage efficiency while maintaining flexibility. The answer is B.
Why the other options are wrong
- A. An incentive only guides behavior. The buyer still has to monitor the seller through performance reviews and similar means, and a bonus cannot replace day-to-day monitoring and review.
- C. This service-level bonus clause does not by itself transfer all cost-overrun risk to the seller. How cost overruns are shared depends on the underlying contract type and its specific terms, and other incentive arrangements can be designed as risk-sharing mechanisms.
- D. A bonus is extra money paid, and the buyer does not necessarily save; no contract provides a “guarantee that payment is below budget”.
Key takeaway This service-level incentive clause aligns the two sides’ goals and motivates the seller to improve performance. It does not replace monitoring, and the clause alone does not establish that all cost risk has been transferred or that the price will be lower.
Variation If the bonus clause were changed to pay out for early delivery, the function would be the same, tying the seller’s interest to the buyer’s objective, but the way it is measured has to be stated.
Reference Contract Types · Lesson 3: Cost-Reimbursable, Time-and-Materials and Target-Cost Contracts
- Question 26
On a multinational project, online meetings were hard to schedule, so stakeholders switched to a weekly email. Later, at a progress meeting where everyone was present, several key stakeholders were shocked to hear the project's actual status and said they had not received a status report for the past month. What should the project manager do to keep this from happening again?
Show answer and explanation
Correct answer: C
On a multinational project, online meetings were hard to arrange, so stakeholders moved to a weekly email. At a progress meeting with everyone present, several key stakeholders said they had received no status report for a month. The question asks how to prevent a repeat.
The communications management plan sets who is communicated with, when, and how, but email is push communication: even when sent, it is not guaranteed to reach or be understood by its audience. Receiving nothing for a month means the project manager should review the plan and its effectiveness, determine whether the problem lies in the distribution list, channel, acknowledgment mechanism, or execution, and then ensure stakeholders' information needs are met. The answer is C.
Why the other options are wrong
- A. Focusing on a few key people neglects other stakeholders. The need is to prevent a repeat, and narrowing the audience repairs no mechanism.
- B. A shared platform is one possible solution, but changing channels before determining why the emails did not arrive and whether the current arrangement meets stakeholder needs may not address the actual cause.
- D. A requirements traceability matrix links requirements to deliverables and has nothing to do with status reports being missed.
Key takeaway When communication has a gap, go back to the communications management plan and make sure it is carried out.
Variation If the check shows these stakeholders were never listed in the plan, first add their communication needs, then update the plan.
Reference Managing and Monitoring Communications · Lesson 3: Monitor Communications: Checking Whether Information Needs Are Met
- Question 27
Which statement about the critical chain method is correct?
Show answer and explanation
Correct answer: A
The question asks which statement about the critical chain method is correct.
PMBOK 8 defines the critical chain method as a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. Critical chain project management uses nearly identical scheduling logic to the critical path method, and both call for a resource-loaded and resource-leveled critical path; critical chain project management also aggregates task-level variability into a project buffer. Therefore, A correctly describes the nearly identical scheduling logic and pooled-buffer treatment; the critical chain method neither replaces the critical path method nor constitutes crashing. The answer is A.
Why the other options are wrong
- B. The critical chain method still considers activity durations and logical relationships. It extends the critical path method rather than replacing it, so saying it no longer considers logical relationships is wrong.
- C. Using the critical chain method you still consider durations, logical relationships and resource availability. Resource availability is only one consideration, not the only factor.
- D. Adding resources to shorten the critical path is crashing, a schedule compression technique, not the critical chain method. The critical chain method relies on buffers, not on adding resources.
Key takeaway The critical chain method uses scheduling logic nearly identical to the critical path method and uses pooled buffers to address limited resources and uncertainty; it is not crashing.
Variation If asked where the buffer goes in the critical chain method, the answer is the project buffer at the end of the critical chain; if asked how to measure how fast the buffer is being used up, use the buffer protection index.
Reference Critical Chain Method · Lesson 1: The Critical Chain Method and Buffers
- Question 28
A newly arrived project manager finds that the scope of the project keeps getting out of control. After reading the change management plan, the project manager learns that whether to adopt a change is decided entirely by the sponsor alone, and that these decisions never go through a cross-functional impact assessment. To reduce scope problems, what adjustment should the project manager recommend?
Show answer and explanation
Correct answer: A
Project scope keeps getting out of control. The new project manager reads the change management plan and finds that whether to adopt a change is decided entirely by the sponsor alone, and the decisions never go through a cross-functional impact assessment. What adjustment would reduce the scope problems?
PMBOK 8 allows the sponsor, the project manager or another designated person to approve changes as the plan provides, and the change control board is an arrangement set up where applicable. This question states plainly that decisions never go through a cross-functional impact assessment and that scope is already out of control. Requiring a cross-functional impact assessment before each decision lets impact be judged from finance, technical, operations and other perspectives, so decisions are more complete and objective, while the designated approver, such as the sponsor, can still make the decision. The change management plan itself can specify who approves, so the recommended adjustment should also be reflected in the change management plan. The answer is A.
Why the other options are wrong
- B. The existing arrangement has already led to scope getting out of control, and continuing it does not solve the problem.
- C. Adding the project manager still leaves decisions with a few people and without a cross-functional impact assessment.
- D. Team members are those who carry out changes. Having them vote on changes is not in keeping with procedure, and they lack the decision authority and overall perspective.
Key takeaway When individual approval lacks cross-functional assessment and scope is out of control, recommend requiring a cross-functional impact assessment before each approval decision.
Variation If the change management plan has designated a single owner and it is working well, follow the designation; the body that approves changes is adjusted by updating the change management plan.
- Question 29
A mobile app team delivers valuable features to the customer in every Sprint, but the documentation keeps getting missed. The project manager must find a way to keep the documentation in step with the features. What should the project manager do?
Show answer and explanation
Correct answer: C
The team delivers valuable features every Sprint, but documentation keeps being missed, and the question asks how the project manager can keep it in step with the features. The key is to make documentation part of “done”.
Agile does not abolish documentation. It argues for documentation that is just enough. The Definition of Done is a checklist of all the criteria that must be met before an item counts as complete. If documentation work is written into the Definition of Done, documentation is produced together with the features and does not have to be caught up afterward. Once that is in place, an item with missing documentation is not done, so the team will naturally finish the documentation within the Sprint. The answer is C.
Why the other options are wrong
- A. Agile does not prohibit a documentation-only Sprint, but such an arrangement separates documentation from the features and does not keep them in step.
- B. A dedicated resource splits documentation and development into two separate jobs, dilutes the team's shared responsibility for quality, and does not ensure the two stay in step.
- D. Writing everything after the features are delivered means the documentation always lags, and the backlog of owed work keeps growing.
Key takeaway To make sure a kind of work gets done every time, write it into the Definition of Done.
Variation If a certain document is needed only for particular items, put it in those items' acceptance criteria instead of the general Definition of Done. The same approach works for other work that is easily missed, such as testing and code review.
Reference Definition of Done · Lesson 1: The Definition of Done: Meaning, Acceptance Criteria and the Definition of Ready
- Question 30
A corporate group launches a cross-regional ERP rollout project at its headquarters, and each provincial branch sends a few key staff to take part. Because travel is restricted, these key staff can normally only read the minutes issued after headquarters review meetings, and as a result several branches' implementations have drifted from project requirements. To improve this at its root, which communication method should the project manager use?
Show answer and explanation
Correct answer: D
During execution of an ERP rollout project, branch key staff can only read the minutes issued after review meetings because travel is restricted, and implementations have drifted from requirements. The question asks which communication method fixes this at the root.
The root of the problem is that minutes are one-way, after-the-fact information, and there is no way to confirm that the other side has understood. Interactive communication is a real-time, multidirectional exchange of information that allows clarification on the spot and is the most effective method for getting everyone to a shared view. Having the key staff take part in the reviews by video or phone, exchanging and confirming points on the spot, is what resolves the gap in understanding. The answer is D.
Why the other options are wrong
- A. Mass communication is a sender addressing a large, sometimes anonymous audience with minimal connection between them, so it hardly produces common understanding; it is a form of communication classified by scale, not a method at the level of push, pull and interactive.
- B. Meeting minutes are themselves push communication, which only ensures that information is sent, not understood. That is the source of the problem, so continuing with push will not improve it.
- C. Pull means the recipient fetches the content. The branches already have the minutes; what they lack is understanding of and alignment with the content, not a way to fetch it.
Key takeaway Push only sends; when parties need to reach consensus and a common understanding, use interactive communication.
Variation If the provincial key staff need to look up past review materials at any time, the answer becomes pull; if you only need to send one notice to designated people, the answer is push.
- Question 31
On a brand website redesign project in the execution stage, the project manager finds that a front-end developer's task is 5 days behind plan and still not finished, which may affect the page launch milestone. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
On a brand website redesign project in execution, a front-end developer's task is 5 days behind plan and not yet finished, which may affect the page launch milestone. The question asks what the project manager should do first.
The project manager should first find out the cause of the delay, so that a matching solution can be worked out. Discussing with the team and assessing the cause is the first thing to do: whether it is a low estimate, changed requirements, a technical obstacle or a people issue, each cause calls for different measures. Any measure taken before the cause is found may treat the symptom and miss the root. Discussing and assessing first also lets the team member explain the obstacles actually met. The answer is D.
Why the other options are wrong
- A. The problem is still within the project manager's authority, so the project manager should first understand and handle it personally rather than escalating directly to senior management for help.
- B. The functional manager may eventually need to be involved, but only after the problem is understood and handling has been tried. Asking him for a solution now skips the analysis.
- C. Reassigning people is one possible measure, but it should not be the first one when the cause is unknown; it could waste resources and still not solve the problem.
Key takeaway When a task is found delayed: find the cause with the team first, then talk about measures and escalation.
Variation If the delay is caused by changed requirements, go through change control rather than absorbing it by reassigning people or overtime.
Reference Schedule Baseline and Monitoring the Schedule · Lesson 3: Variance Analysis and Schedule Changes
- Question 32
A retail group is forming a cross-departmental membership operations project team. Members are assigned by each department, and the project manager has no direct authority over who is chosen. What should the project manager do?
Show answer and explanation
Correct answer: C
The members of a membership operations project team are assigned by departments, and the project manager has no direct decision on who is chosen. The question asks what the project manager should do; in essence, what to do when the resources are in someone else's hands.
A project manager does not necessarily have the authority to choose people directly. In that case you rely on negotiation and influence: negotiate with the functional managers, explain the project's needs and value, and secure qualified people. When the required resources are controlled by others, acquiring them commonly requires negotiation with parties such as functional managers, other project teams and external organizations. The answer is C.
Why the other options are wrong
- A. Ground rules belong to the team charter and govern how team members behave. They are not a way to obtain members.
- B. Team building targets the members who are already in place and aims to build cohesion and improve performance. It does not solve the problem of “people who are unsuitable or have not arrived.”
- D. Co-location changes how and where people work. It does not solve whether suitable people can be obtained; co-location is a team-building tool and has no effect on who is chosen.
Key takeaway When you have no say over who is chosen, negotiate with the functional managers to secure qualified people. Negotiation is not only about securing people; you also explain needs, timing and the impact on the functional manager's department, aiming for a win-win.
Variation If the functional manager still will not release people after negotiation, the next step is to communicate with the sponsor to coordinate; if nobody internal has this skill, then consider recruiting or procuring external resources.
- Question 33
A market research project is midway through. A team member reports that the SPI on the critical path is 0.88, while the SPI for the project as a whole is 1.08. How should the project manager assess the project's schedule status?
Show answer and explanation
Correct answer: B
The project is midway through. The stem gives both the SPI on the critical path (0.88) and the SPI of the project as a whole (1.08), and asks for the schedule status.
The overall SPI measures the amount of all the work completed and does not distinguish whether the work is on the critical path. What determines the duration is the critical path, whose SPI is 0.88, below 1: the critical path is behind and the duration is at risk. Gains on non-critical paths cannot offset this. The answer is B.
Why the other options are wrong
- A. The critical path SPI is below 1, so the schedule is not on plan, and certainly the duration is not risk-free. An overall SPI above 1 cannot hide this.
- C. “The duration is at risk” is right, but “on schedule” is wrong: the critical path is already behind.
- D. This is misled by the overall SPI of 1.08 and ignores the late critical path. Being ahead overall does not mean the duration is free of risk.
Key takeaway When both the critical path SPI and the overall SPI are given, focus on the critical path: late critical path activities point directly to a completion date risk, so look at the critical path SPI separately and judge the impact together with critical path analysis and schedule forecasts.
Variation If the critical path SPI were 1.05 and the overall SPI 0.90, critical path performance would currently be good, but you would still check the remaining schedule risk, whether float on non-critical activities has been used up, and whether the critical path has changed.
- Question 34
During planning, the project manager finds that the scope management plan covers only how to prepare the scope statement and create the WBS, and says nothing about how to monitor and control scope or how to handle scope changes. What should the project manager do?
Show answer and explanation
Correct answer: B
In the planning phase of a predictive project, the scope management plan covers only how to prepare the scope statement and create the WBS, and lacks monitoring, controlling and change handling for scope. The question asks how to remedy this.
The scope management plan is supposed to set out how scope will be defined, developed, monitored, controlled and validated. If the monitoring and control parts are missing, add the Monitor and Control Scope process and the way changes are handled, and update the scope management plan, so that every later change has rules to follow. A problem with a plan is solved in the plan. The answer is B.
Why the other options are wrong
- A. The scope statement records the scope itself (description, deliverables, acceptance criteria, exclusions). It does not set out how changes are handled.
- C. The change control board approves individual changes, but how scope is monitored and controlled has to be set out in the plan in advance; it cannot rely entirely on ad hoc rulings.
- D. The requirements management plan covers requirements activities, configuration management and the like. The processes for monitoring and controlling project scope belong in the scope management plan.
Key takeaway The scope management plan covers five stages: define, develop, monitor, control and validate. Whichever is missing, add it.
Variation If the stem said that “the requirements management plan lacks a provision on requirements prioritization,” you would likewise add it and update the requirements management plan, not write it into the scope management plan.
- Question 35
Two developers on an enterprise web portal project have thought of a new effect that would change the look and feel of the home page. They believe it may raise customer satisfaction and might even win the company the customer's follow-on contract. Excited, they go to the project manager and ask for approval to add it to the deliverables. How should the project manager respond?
Show answer and explanation
Correct answer: A
Two developers think of a new effect that they believe will raise customer satisfaction and may win a follow-on contract, and they ask the project manager to approve adding it to the deliverables.
The new effect is not in the agreed scope; it is added content outside the scope baseline. To add it, a change request must be submitted, assessed and approved by someone with the authority to approve it. Until then the team should concentrate on the agreed scope, which is a basic requirement of Monitor and Control Scope. However valuable an idea is, it cannot bypass change control. The answer is A.
Why the other options are wrong
- B. The project manager has no authority to approve new content outside change control, and “helping the team reach a satisfaction goal” is no reason to bypass the process. Unassessed additions are gold plating.
- C. Team consensus cannot replace formal change control. Without assessing the impact on schedule, cost and quality, this is still an unapproved change.
- D. Rushing to build it in to improve the odds of a follow-on contract also bypasses the process and is classic gold plating.
Key takeaway However valuable an idea is, it goes through a change request first; until approved, work only on the agreed scope.
Variation If the effect is already written in the scope statement, no change is needed. If the customer asks for it in writing, assess it through the change request process and let whoever is authorized under the project management plan or organizational procedures (such as the change control board, sponsor or project manager) decide.
- Question 36
In conversations before a phase retrospective, the project manager notices that members talk only about what went well and fall silent as soon as mishaps come up, because they fear being held to account afterward. How should the project manager handle this?
Show answer and explanation
Correct answer: C
In conversations before the phase retrospective, members talk only about successes and fall silent about mishaps because they fear being held accountable. The question asks how the project manager should handle this.
The key conditions for knowledge sharing are trust and psychological safety. That members dare not talk about failure shows the team lacks an atmosphere that does not blame individuals and focuses on learning, while the experience of failure is often the most valuable. The project manager should first create an atmosphere where people dare to talk about failure, treating mistakes as learning opportunities, so that members are willing to speak up and continuous improvement has material to work with. The answer is C.
Why the other options are wrong
- A. Calling on people by name to explain their faults in turn deepens their fear of being held accountable and makes people even less willing to be candid.
- B. Recording only successful practices in the register throws away the most valuable lessons and does not solve the problem that people are afraid to speak.
- D. Limiting the topic to the technical level and avoiding failure does not remove the fear of accountability, and what is shared becomes one-sided.
Key takeaway To get failure experience flowing, first build a trusting atmosphere that does not blame individuals and focuses on learning, while keeping the necessary accountability.
Variation If the stem said members are willing to talk but there are no action items after the meeting, improve the retrospective by focusing on specific lessons and turning them into actionable items. If it said staff work in several locations and feedback must be collected quickly from everyone, use a survey.
- Question 37
The business owner of an agile team wants one central place where stakeholders can check project progress themselves. What should the agile practitioner recommend?
Show answer and explanation
Correct answer: C
On an agile project, the business owner wants a central place where stakeholders can check progress for themselves. The question asks what the agile practitioner should recommend.
Agile stresses transparency. An information radiator is a visible display placed where people can easily see it and easy to update, so stakeholders need not wait for reports or call separate meetings. An online collaboration site or board that shows progress in one place lets the business owner and other stakeholders look for themselves at any time. It works like an information radiator in a distributed setting: everyone can see progress in one place at any time. The answer is C.
Why the other options are wrong
- A. Publishing only at the end of the iteration is not timely enough. A detailed document costs more to maintain and is less convenient for self-service than a continuously updated central board.
- B. One-on-one meetings take up time person by person and are not a central place where everyone can check progress themselves.
- D. The daily coordination meeting is a team synchronization, not an information entry point for stakeholders, and it leaves no place to look things up at any time.
Key takeaway For stakeholders to check progress themselves, build a central, open, always-available visual channel: a physical board, or an online collaboration board for distributed teams. Do not rely on one meeting or report at a time.
Variation If the team is co-located, the physical board can go up in the corridor. If the question asks about reporting to management unfamiliar with agile, besides the board also explain metrics such as burndown charts and velocity.
- Question 38
The project charter for a cold-chain warehouse renovation project has already been approved, and the project manager is assigned to take over afterwards. Going through the charter item by item with the team, he finds that the preapproved financial resources leave out several major costs that are essential to achieving the project’s outcome. What should the project manager do NEXT?
Show answer and explanation
Correct answer: A
The charter for the cold-chain warehouse renovation project has been approved, and the project manager is assigned afterwards. Checking against the charter, he finds that the preapproved financial resources omit several major costs essential to achieving the outcome. The question asks what to do next.
Preapproved funding is part of the charter and is approved by the sponsor. A gap in the charter means the charter is what has to change, and the power to change it lies with the approver, so the project manager should talk to the sponsor right away and ask for the budget to be re-approved. The sooner it is handled, the smaller the impact on the project. The charter and its preapproved financial resources are approved by the sponsor or another authorized person, so the correction has to be decided by the approver, and the project manager cannot adjust the funding in the charter alone. The answer is A.
Why the other options are wrong
- B. Cutting the quality and cost of other deliverables to fill the gap, without the sponsor’s approval, is robbing Peter to pay Paul.
- C. Starting work with a known gap just leaves the problem for later, and may cause delays or even project failure.
- D. A budget omission is an established gap, not a “possible” risk, so it does not belong in the risk register. There is also no need to wait for the next steering committee meeting; go straight to the sponsor.
Key takeaway After taking over, when you find a gap in the charter, go directly to the sponsor who approved the charter.
Variation If the gap is in the plan and not in the charter, for example a work item missing from the schedule, first assess the impact; if a controlled item such as the schedule baseline has to change, then use the applicable change process. If what you find is a violation by your predecessor, escalate it as a key issue.
- Question 39
The sponsor asks a young project manager at an education company to prepare a project budget for the first time. The company's practice is to include contingency reserve in the cost baseline and to hold management reserve outside the baseline. The project manager asks you what the project budget is made of. How should you answer?
Show answer and explanation
Correct answer: B
This is the Develop Budget stage of a predictive project. A new project manager is building a budget for the first time, and the company includes contingency reserve in the cost baseline and holds management reserve outside it. You must judge what the project budget is made of.
PMBOK 8 notes that how the project budget is built up depends on the organization's policy and financial management practices, and different scenarios are possible. This question follows the view given in the stem: the cost baseline contains the work package cost estimates and contingency reserve, with management reserve outside the baseline, so project budget = cost baseline + management reserve. The baseline contains contingency reserve and not management reserve, and the budget adds management reserve on top of the baseline. The answer is B.
Why the other options are wrong
- A. This describes what the cost baseline is made of. It does not add management reserve, so it is not the project budget.
- C. Aggregated work package estimates have not yet had contingency reserve added, so they are not the cost baseline, and adding management reserve to them does not give the project budget.
- D. Contingency reserve is already in the cost baseline. Adding it to the baseline again double counts it and also omits management reserve.
Key takeaway Where the baseline contains contingency reserve and management reserve sits outside it: project budget = cost baseline + management reserve.
Variation If an organization manages contingency and management reserves explicitly outside the baseline, look at how the stem defines them. When the stem says nothing, do not assume the equation above.
- Question 40
A high-profile project has run into a problem that could cause a delay, and the project manager needs to notify the stakeholders. The project manager holds a video conference so as to explain the problem clearly and get feedback immediately. Which communication method is this?
Show answer and explanation
Correct answer: C
A problem that could cause a delay has come up, and the project manager holds a video conference to explain it to stakeholders and collect their feedback on the spot. The question asks which communication method this is.
PMBOK 8 classifies communication methods as interactive, push and pull. Interactive communication occurs between two or more parties performing a multidirectional exchange of information in real time, and it employs communications artifacts such as meetings, phone calls, instant messaging and videoconferencing. In this question the video conference both explains the problem and gets immediate feedback, so information flows both ways, which fits interactive communication. The answer is C.
Why the other options are wrong
- A. Push communication sends or distributes information to specific recipients, such as email or reports. It does not ensure understanding and has no immediate feedback; the point of a video conference is real-time exchange.
- B. Pull communication means recipients fetch information themselves from a portal or knowledge repository, and it suits large, complex information sets. Here the project manager called the meeting; nobody fetched anything.
- D. Networks and social computing communication belongs to a different classification (by the form of communication). A video conference is a technology for carrying out interactive communication, not a method category of its own.
Key takeaway Meetings, phone calls and video conferences that give real-time feedback are interactive communication.
Variation If the project manager instead wrote up the problem in an email to the stakeholders, that would be push communication.
Reference Plan Communications Management · Lesson 3: Communication Technology and Communication Methods: Push, Pull and Interactive
- Question 41
A project manager leads a team spread across three time zones that must collaborate on a monthly quality report. The team charter already says that when time zones make a common working window impossible, members must attend weekend meetings. Now a weekend meeting is genuinely needed once in a while, but members say they do not want to work on weekends. What should the project manager do?
Show answer and explanation
Correct answer: A
The team spans three time zones, and the team charter already says members must attend weekend meetings when time zones prevent a shared working window. A weekend meeting is now truly needed, yet members are unwilling to work on weekends. The question is what the project manager should do; the deciding conditions are that it was “already agreed” and “recorded in the team charter.”
The team charter sets clear expectations for acceptable behavior, and PMBOK 8 stresses that all project team members share responsibility for ensuring the rules in the charter are followed, and that the team itself took part in making them. Now that members are unwilling, the project manager should first acknowledge their feelings and then remind everyone of the responsibilities they jointly accepted, using the existing agreement to resolve the problem rather than going around it or postponing delivery. The answer is A.
Why the other options are wrong
- B. If the project manager takes over the report alone, it cannot be done (the report requires collaboration among several people), and members are excused from the responsibility they agreed to, so the team's rules become empty.
- C. Adjusting the reporting schedule to avoid the months that need weekend meetings avoids the conflict. It amounts to unilaterally cancelling the agreement and may cause the report to be late or missed.
- D. Telling stakeholders directly that the report will be late throws the problem outside before it has been handled inside the team. It is too passive and harms the project's commitments.
Key takeaway When members go back on an existing agreement, return to the team charter first, remind them of the responsibilities they jointly accepted, and then negotiate exceptions.
Variation If a member raises a new situation that was not foreseen when the charter was written (for example, family reasons that make weekend attendance impossible), the project manager should discuss it with the team and update the charter rather than demanding mechanical compliance.
Reference Team Charter · Lesson 1: Team Charter and Team Agreements: Purpose, Contents and Who Develops It
- Question 42
A viaduct section of a city rail transit project is under construction, and a residents' rights group along the route questions whether the project is necessary. The customer tells the project manager to ignore the group, on the grounds that they do not support the project. What should the project manager do next?
Show answer and explanation
Correct answer: B
During construction of a rail transit viaduct, a residents' rights group along the route questions the project's necessity, and the customer says to ignore them. The question asks what the project manager should do next.
Groups affected by the project or who perceive themselves to be affected are stakeholders, and opponents are no exception, so “they do not support the project” is not a reason to ignore them. Identifying stakeholders continues throughout the project, so a group that appears during construction is added as soon as it is found. The project manager should add the group to the stakeholder register, analyze their potential impact on the project, and then set an engagement strategy accordingly. The customer funds the project and their view matters, but it cannot replace the project manager's responsibility to identify and manage stakeholders. The answer is B.
Why the other options are wrong
- A. Having the customer tell the group about progress and the completion date is one-way information. The project manager has not yet identified the group as stakeholders or learned why they question the project, and a progress update does not address their concern about whether the project is necessary. Identify and analyze first; that decides who should engage them and how.
- C. The customer funding the project does not mean other stakeholders can be dropped. The project manager is responsible for the smooth delivery of the project and cannot disregard possible resistance because of a customer instruction.
- D. Telling the team to ignore all the group's correspondence gives up on analyzing and managing this group, and the problem is left to grow into a bigger conflict later.
Key takeaway A group that opposes the project is also a stakeholder: first register them and analyze their impact, and do not ignore anyone just because they do not support the project.
Variation If the group said it would complain to the media, then after registering and analyzing them, raise their priority, set a targeted communication strategy and report this risk to the sponsor.
- Question 43
The project schedule network diagram at PMLyceum has two parallel paths. Path 1 contains activity X and activity Y: Y is fixed at 8 days, and X has been estimated with multipoint estimating at optimistic 6 days, most likely 9 days and pessimistic 18 days. Path 2 has only activity Z, fixed at 16 days. The project manager puts X's expected duration (beta distribution) into the network diagram and then runs critical path analysis. What are the critical path and the shortest project duration?
Show answer and explanation
Correct answer: B
A network diagram has two parallel paths, and activity X has a multipoint estimate. Put its expected value (beta distribution) into the diagram, then determine the critical path and the shortest duration.
The expected duration from multipoint estimating is the activity duration that goes into the network diagram, not the most likely value and not the optimistic or pessimistic value. First calculate X's expected value, then the length of each of the two paths. The longer one is the critical path, and its length is the shortest duration. Path 1 at 18 days is longer than path 2 at 16 days, so the critical path is path 1. Entering the wrong number changes the conclusion: with the most likely value path 1 is 17 days, and with the optimistic value path 2 becomes the longest. The answer is B.
- Expected duration of X: tE = (6 + 4 × 9 + 18) ÷ 6 = 60 ÷ 6 = 10 days.
- Path 1: X + Y = 10 + 8 = 18 days; path 2: Z = 16 days.
- Take the longer path: max(18, 16) = 18 days, so path 1 is the critical path.
- Check: X's expected value of 10 lies between 6 and 18, which is reasonable.
Why the other options are wrong
- A. Entering X at the optimistic value of 6 days makes path 1 only 14 days, less than path 2, so path 2 appears critical. That does not use the expected value.
- C. Entering X at the most likely value of 9 days gives path 1 = 9 + 8 = 17 days, which uses the most likely value in place of the expected value.
- D. Entering X at the pessimistic value of 18 days gives path 1 = 18 + 8 = 26 days. That is a worst case, not an expected value.
Key takeaway The expected duration from multipoint estimating is the number that goes into the network diagram.
Variation If Z were changed to 18 days, both paths would be 18 days and there would be two critical paths. If the triangular distribution were used, X would be 11 days and path 1 would become 19 days.
- Question 44
On a consulting project, for several months in a row the client has disputed the monthly invoices issued exactly as the contract specifies, has repeatedly paid after the contractual deadline, and most recently paid only part of the amount. What should the project manager do?
Show answer and explanation
Correct answer: A
On this project the client has disputed invoices issued under the contract for several months in a row, has repeatedly paid late, and most recently paid only part of the amount. This is an issue that has already occurred. How should the project manager handle it?
The key signals are “issued exactly as the contract specifies” and “several months in a row”: the invoices comply, yet the client still disputes them and pays late, which suggests an unresolved disagreement that calls for direct communication. The project manager should hold a meeting with the client, find out the real reason for the objections and agree on a resolution, which is what moves the problem toward a real solution. The answer is A.
Why the other options are wrong
- B. Logging the late payments is necessary, but “log and keep watching” takes no action to resolve the client's failure to pay in full; it is too passive.
- C. Summarizing lessons learned about collections helps later projects, but the present late-payment problem has to be solved first by talking directly with the client; a review cannot replace handling it.
- D. Nothing in the stem suggests a flaw in the procurement strategy. The problem lies in the client's objections and payment behavior, so changing the procurement strategy and payment terms does not address it and cannot change the existing contract.
Key takeaway Late payment that has already occurred is an issue: resolve it by talking directly with the stakeholder, not by merely recording it or summarizing lessons.
Variation If the client still refuses to pay after the discussion, handle it under the contract's dispute resolution clause and escalate to the sponsor or the contract management department.
Reference Issue Management · Lesson 3: Issue Priority and Escalation
- Question 45
On a recommendation system project for an e-commerce platform, a senior developer has worked hard over a long period and produced outstanding results. The project manager is very pleased with his contribution and believes he should be rewarded. What should the project manager do FIRST?
Show answer and explanation
Correct answer: B
On a recommendation system project, a senior developer has worked hard for a long time and delivered outstanding results, and the project manager is pleased and thinks he should be rewarded. The question asks what the project manager should do first.
Rewards are generally more motivating when they fit the individual's motivations and needs. Some people value money, some value growth opportunities and some care most about public recognition. The project manager should first learn this developer's motivations and interests, then choose the form of reward. That shows respect and meets his needs. Even with the same “praise,” naming an introverted person in public may be a burden, while for someone who values public recognition it is the best reward. The correct answer is B.
Why the other options are wrong
- A. For an individual reward, presenting a certificate in public at the regular meeting is a preset form. It has not been checked whether he wants to be honored in public.
- C. Expressing recognition in person is a usable form in itself, but it is a form chosen in advance. The stem asks what to do “first,” so understand the individual's motivation before choosing.
- D. An all-hands email copied to management is likewise a preset form. It does not start from his expectations and has limited motivating effect.
Key takeaway Before rewarding, understand motivation, then choose a form that fits the individual's needs.
Variation If the stem asked when recognition is best given, the answer is promptly and specifically throughout the project, without waiting until the project ends.
- Question 46
PMLyceum is a functional organization developing a warehouse management system. The functional manager of the testing department, who does not understand the project's business value, assigned the department's test engineers to support another project, so verification work on this project cannot start and the delivery date is in danger. What should the project manager do to resolve the problem?
Show answer and explanation
Correct answer: C
In a functional organization, the testing department's functional manager does not understand the project's business value and has assigned test engineers to support another project, so verification on this project cannot start. The question asks what to do to resolve the problem.
In a functional organization, people come under the functional manager, and the project manager secures resources through negotiation and influence, not orders. The manager moved the people because he does not understand the project's business value, so the most targeted approach is to negotiate with him directly, explain the project's value and the consequences of delay, and secure more people. Negotiation is the first choice when acquiring resources. The answer is C.
Why the other options are wrong
- A. The sponsor can help obtain resources and resolve issues beyond the project management team's authority, but the project manager has not first negotiated with the functional manager who controls the assignment of people. Asking the sponsor at once to demand their return would damage the relationship and is not the first choice.
- B. Contacting the test engineers directly and asking them to transfer goes around the functional manager. In a functional organization the project manager has no power to move a department's people, and where the engineers go is decided by the functional manager.
- D. Changing the schedule baseline requires the change control procedure, and the project manager cannot push the date back alone. It also merely accepts that the resources are tied up and does not resolve the resource problem.
Key takeaway When resources are in the functional manager's hands, negotiate with him first and influence him with the project's value, rather than skipping a level or changing the baseline.
Variation If the stem added that “the functional manager still refuses after negotiation,” the next step is to communicate with the sponsor to coordinate; if the organization were a matrix, the thinking is the same and you still go to the functional manager first.
- Question 47
A software company takes on a project to optimize a route-planning algorithm. If the team can quickly master a new framework, the algorithm may reach its target early and win an extra order from the customer. The project manager hires an outside senior expert to give the team a week of focused training. This raises the likelihood of the opportunity but does not guarantee it. Which opportunity response strategy is this?
Show answer and explanation
Correct answer: A
A software company takes on a route-planning algorithm optimization project. If the team masters a new framework quickly, the algorithm may reach its target early and win an extra order, which is an opportunity. The project manager has an outside expert give a week of focused training, which raises the likelihood of the opportunity but does not guarantee it. Which opportunity response strategy is this?
The training targets the cause that decides whether the opportunity occurs: the better the team has mastered the framework, the greater the chance of an early finish and an extra order. The stem says it “raises the likelihood” but “does not guarantee,” so the probability or impact of the opportunity is only increased, not made certain. That is enhance. Measures like this work better the earlier they are taken. The answer is A.
Why the other options are wrong
- B. Exploit takes action to make sure the opportunity is realized, raising the probability to 100%, for example by assigning the best people to it full time. The stem says explicitly that success is not guaranteed, so this is not exploit.
- C. Share gives the opportunity to a third party who is best able to seize it and shares the benefit, as in a joint venture or partnership. The outside expert only provides training and shares no project benefit.
- D. Escalate is for an opportunity beyond the project's scope or the project manager's authority, reporting it to a higher level. Here the project manager acts directly within their own authority and does not escalate.
Key takeaway Exploit makes sure the opportunity happens; enhance only increases its probability or impact.
Variation If the stem said “success guaranteed” and assigned the best expert full time, it would be exploit. The matching threat strategies are avoid and mitigate.
- Question 48
An agile team is developing a voice assistant app. Stakeholders want the product owner to provide a tool that shows completed work clearly and also shows when scope is added or removed. What should the team use?
Show answer and explanation
Correct answer: D
The agile team is building a voice assistant app. Stakeholders want a tool that shows completed work intuitively and also shows when scope is added or removed.
The stem sets two requirements: show what is completed, and show changes in scope. A burnup chart has exactly two lines: a rising cumulative completed line and a total scope line at the top. When scope is added the scope line moves up, and when scope is removed it moves down; when the completed line catches the scope line, the work is done. A burndown chart has a single remaining-work line, so scope changes are mixed in with “work done” and you cannot tell whether the team slowed down or scope grew. When reading this kind of question, first circle the two requirements in the stem and then find the chart that meets both. The answer is D.
Why the other options are wrong
- A. An affinity diagram groups many ideas by similarity and is used to organize ideas. It does not show progress.
- B. A value stream map records and analyzes the flow of information or materials to find waste such as waiting. It does not show scope changes.
- C. A cause-and-effect diagram, also called a fishbone diagram, breaks a problem down layer by layer to find root causes. It has nothing to do with showing progress.
Key takeaway When scope can change and you need to see both completion and scope, use a burnup chart.
Variation If you only need to see how much remains and scope is stable, use a burndown chart; to find waiting time in a process, use a value stream map; to ask for the root cause of a problem, use a cause-and-effect diagram.
- Question 49
A project manager has just taken over a drone inspection system project that is in the planning phase. The team tells her that all the identified risks have been ranked by priority. The sponsor now asks for numbers showing the combined effect of these risks on the cost and schedule objectives. What should the project manager do next?
Show answer and explanation
Correct answer: D
A drone inspection system project is in the planning phase and the identified risks have all been ranked by priority. The sponsor wants numbers showing the combined effect of these risks on the cost and schedule objectives. You must judge the next step in the risk analysis flow.
“Already ranked by priority” shows that qualitative risk analysis is done; the ranking settles “which to manage first”. What the sponsor wants now are “numbers” and the “combined effect”, that is, a quantified conclusion on overall project objectives, which is the task of quantitative risk analysis: a numeric analysis of the combined effect of identified risks. The core evidence is the two words “numbers” and “combined”. The scenario does not ask for new risks to be found or for response measures. So the next step is quantitative risk analysis. The answer is D.
Why the other options are wrong
- A. Concentrating on the top-ranked risks is how the ranking is used. The sponsor wants numbers, not an order of priority, so this option does not answer the question.
- B. Recording additional sources of risk is work in the Identify Risks stage. Although identification can continue, once the risks are ranked, adding sources cannot give the numeric combined effect the sponsor wants, and it is not the action to take now.
- C. Developing a response plan for each risk is Plan Risk Responses and comes after analysis. Quantitative analysis is not a universal prerequisite for response planning, but here the sponsor explicitly asks for the combined effect to be quantified, so that analysis need should be met first and the responses refined from it.
Key takeaway After qualitative ranking, when you must show the overall effect of risks with numbers, the next step is quantitative risk analysis.
Variation If the sponsor asked only “which risk should be handled first?”, the ranking already answers it and no quantitative analysis is needed. If the question were “how confident are we of finishing within the current budget?”, quantitative analysis is still needed, using Monte Carlo simulation.
- Question 50
PMLyceum assigns Priya to lead a project to produce a micro-course called “Key Topics Review”. Production will take about two months, and after completion learners will use the course repeatedly over a long period. Which statement about the temporary nature of this project is correct?
Show answer and explanation
Correct answer: B
A micro-course production project is expected to finish in two months, after which learners will keep using the course for a long time. The question is whether the long-lived deliverable changes the temporary nature of the production project.
Temporary means the project itself has a defined beginning and end. It applies to the project, not to what the project produces. The stem gives two signals: production takes about two months, so the project has an end; and the course stays in use, which describes the life of the deliverable. These are two separate things. A deliverable can outlive the project, and the project is still temporary. Option B keeps them separate, so the answer is B.
Why the other options are wrong
- A. This confuses how long the deliverable is used with how long the project exists. The course being used for years only shows that the result keeps delivering value after the project ends. The production work ends once the recording is finished, so the project is still temporary.
- C. Temporary does not mean short. A construction project that takes many years is still temporary as long as it has a beginning and an end. A short duration here is a coincidence, not the test.
- D. Temporary applies to the project, not to the product. Whether the course is replaced by a newer version later has nothing to do with whether the production project has an end. This reason looks at the wrong object.
Key takeaway Temporary means the project has a defined beginning and end. It does not depend on how long the project lasts or on how long the deliverable stays in use.
Variation If the stem said instead that the project objectives cannot be met and the sponsor decides to terminate it, the project still ends. Determining that the objectives cannot be met is one of the conditions that can end a project, and ending is not the same as succeeding.
- Question 51
On a product-launch project for a brand, the sponsor insists that the scope cover two cities. After the scoping meeting, however, the project charter approved only one city. What should the project manager do?
Show answer and explanation
Correct answer: B
The sponsor insists that scope cover two cities, but the project charter approved only one. The question asks what the project manager should do.
The sponsor is asking for more than the approved scope. That is a scope change, which the project manager cannot decide alone. The project manager should first assess how including the second city affects scope, schedule, cost and more, then submit a change request, and the city can be included only after the change control process approves it. Because the charter approved only one city, any request beyond the approved scope, whether it comes from the sponsor or the customer, is handled by the same change control approach. The answer is B.
Why the other options are wrong
- A. Budget and time cannot be added before assessment. First find out whether to include the city and how large the impact is, then adjust through change control.
- C. A separate project requires its own justification and cannot just be created to satisfy the sponsor, and no one has assessed whether the city belongs in this project.
- D. Simply saying it is “impossible” does not deal with the sponsor's request. Whether to include it should be decided by change control after assessment.
Key takeaway When a request differs from the approved scope, assess the impact and go through a change request.
Variation If the change request is rejected, the project continues with the original scope. If it is approved, update the scope baseline and the related schedule and budget plans.
- Question 52
A team uses Scrum and XP together. Which of the following is a practice that XP has and the Scrum framework does not?
Show answer and explanation
Correct answer: D
A team uses Scrum and XP together. The question asks which of the following is a practice XP has that the Scrum framework does not.
“Slack” is an XP practice (common exam practice): in the weekly cycle, a few extra lower-priority user stories are added, and when other stories take longer than expected, these extra stories are dropped first so that the main commitment is not missed. The Scrum framework does not have this. The other three exist in both methods, so none can be the answer for “unique to XP”. The answer is D.
Why the other options are wrong
- A. Timeboxed iterations are a rhythm that both Scrum and XP use. They are not unique to XP.
- B. Iteration planning exists in both Scrum and XP, to decide at the start of each round what work to complete. It is not unique to XP.
- C. Respect and courage are two of Scrum's five values and are also XP values, so both methods share them.
Key takeaway Unique to XP is “slack”, which is a reserve of extra stories that can be dropped. Timeboxes, iteration planning, respect and courage are in both methods.
Variation For example, a week has 20 ideal hours available, must-do stories are estimated at 16 hours and slack stories at 4 hours. If a must-do story actually takes 3 hours more, the must-do stories originally estimated at 16 hours actually use 19 hours and only 1 hour of capacity remains, so the slack stories estimated at 4 hours are dropped to make sure the must-do stories are finished (story points are relative size and are not used to record actual effort). If asked what the two methods share, choose timeboxes, iteration planning and so on.
- Question 53
You are appointed project manager of a city subway customer-service system upgrade. You have deep experience in this field, and you personally selected the team. You have complete confidence in the team, and the members know it. You have also consistently advocated for opportunities for them to develop their skills and careers during the project. Everyone firmly believes the project will succeed. Which of the following describes your leadership approach?
Show answer and explanation
Correct answer: D
You are the project manager of a subway customer-service system upgrade, with deep experience in the field and a team you chose yourself. You have complete confidence in the team, and you consistently advocate for opportunities for members to develop their skills and careers, and everyone believes the project will succeed. The question asks which leadership approach this is.
PMBOK 8 defines servant leadership as “the practice of leading the team by focusing on understanding and addressing the needs and development of team members in order to enable the highest possible team performance.” In the stem, having “complete confidence” in the team shows trust, and advocating for “opportunities for skills development and career growth” shows attention to members’ development. Together they describe servant leadership. The point that separates it is growth: a laissez-faire leader gives little guidance, support or involvement, whereas this project manager actively advocates for growth opportunities for the members. The answer is D.
Why the other options are wrong
- A. Charismatic leadership moves the team through the leader’s personal appeal, with the focus on the leader himself. The stem emphasizes serving members’ needs and growth, not personal charm.
- B. Transactional leadership trades rewards and penalties for performance. Nothing in the stem describes an exchange of rewards for results; it stresses trust and growth.
- C. A laissez-faire leader rarely gets involved. The project manager in the stem is actively advocating for growth opportunities for members, which is a trait of servant leadership, not laissez-faire.
Key takeaway Trusting the team and actively promoting members’ development is servant leadership; trusting but staying uninvolved is laissez-faire.
Variation If the stem said the project manager pays a bonus at every milestone met and docks it when missed, that would be transactional; if he got people to work overtime through personal inspiration, that would be charismatic.
- Question 54
An exhibition engineering company takes on a venue construction project. The equipment rental company can deliver in June, but the venue will not be handed over until August; installation can start only after handover, and the rental period runs from the delivery date. The project manager finds that the time of acquiring the equipment does not match the time it is needed. What should the project manager do?
Show answer and explanation
Correct answer: B
On a venue construction project, the rental company delivers equipment in June, but the venue is handed over only in August, installation can start only after handover, and rent runs from the delivery date. The equipment would sit idle for two months while rent is paid.
Resources should be acquired when they are needed and released when they are not, to avoid the waste of occupying them early. Installation cannot be moved earlier, so adjust the acquisition time for the equipment to match the delivery date to the installation need, which avoids paying extra rent and does not affect construction. The answer is B.
Why the other options are wrong
- A. Taking delivery early and treating the idle time as buffer means paying two extra months of rent, and this buffer is not something the project needs.
- C. Moving installation as a whole forward to June is impossible: the venue is not handed over until August, and installation can start only after the venue is ready.
- D. The quantity of equipment is determined by installation needs, and reducing it would affect construction. It would also still mean acquiring early and does not solve the timing mismatch.
Key takeaway Acquire resources when they are needed; when acquisition and demand do not match in time, adjust the acquisition time.
Variation If the venue is handed over early while the equipment arrives late, negotiate with the rental company for earlier delivery or look for substitute equipment; if idle equipment cannot be avoided, consider subleasing it or releasing it early.
- Question 55
An agile team is developing a social commerce app, and a newly issued data regulation means that one of its recommendation features cannot launch for now. What should the team do?
Show answer and explanation
Correct answer: B
This is an agile project, and a new external regulation means one feature cannot launch for now. The question is what the team should do.
Agile approaches absorb change through the product backlog. First assess the impact of the regulatory change on the product and the project, then have the product owner adjust priorities, moving the affected feature later and working first on other items that can deliver value. Reordering the backlog is the routine action when an adaptive project responds to an external change. It also shows the strength of adaptive projects in the face of external change: change can be absorbed by reordering the backlog before each iteration, with no need for a heavyweight change procedure. So the answer is to assess the impact and reorder, not to terminate the project and not to keep investing in a feature that cannot launch. The answer is B.
Why the other options are wrong
- A. Only one feature is affected, so terminating the whole project is an overreaction.
- C. Finishing the feature and then hiding its entry point wastes team capacity and does not deal with the constraint the regulation creates.
- D. Rushing out a feature that cannot launch has no value and would crowd out other high-value items.
Key takeaway When a regulation change affects an agile project: assess the impact and reorder the product backlog.
Variation If the same external change affected an approved baseline, the answer would become assessing the impact and submitting a change request.
- Question 56
A project has entered closing, and the project manager finds that the team has handed over only the deliverables to the customer and has not put this project's lessons learned and performance data into the organizational knowledge repository. What should the project manager do?
Show answer and explanation
Correct answer: B
A project has entered closing, and the team has handed over only the deliverables and has not put the lessons learned and performance data into the organizational knowledge repository. You must decide how organizational process assets should be updated at closing.
At closing, the project's lessons learned, performance data and other information should be organized and put into the organizational knowledge repository, updating the organizational process assets for later projects to use. The problem in the stem is that the team handed over only the deliverables and did not store this information; the project manager should add that step so that the experience becomes an asset of the organization and does not stay in individual hands. The answer is B.
Why the other options are wrong
- A. Personal notes are useful only to the individual. The organization and later projects cannot see them, so they do not build up organizational knowledge.
- C. Material in a temporary folder has not been submitted through the organization's archiving process, so later projects cannot retrieve it, and it should not be provided only when an audit comes.
- D. The valuable lessons learned and performance data in project files are exactly the content that has to go into the organizational knowledge repository, and it cannot be skipped because it “belongs to project documents.”
Key takeaway At closing, put the lessons learned and performance data into the organizational knowledge repository to update the organizational process assets; they can also be added to at any time during the project.
Variation If the question asked “when can organizational process assets be updated?”, the answer is throughout the project, not only at closing; at closing, archiving the lessons learned and performance data must be completed.
- Question 57
On a company's mobile payment app development project, a team member thinks the tasks are simple and quality control is unnecessary. The project manager notices that dropping the quality management plan would also lower costs, and cost matters a great deal to the client. What should the project manager do?
Show answer and explanation
Correct answer: D
A team member feels the task is simple and quality control is unnecessary, and dropping the quality management plan would also save money, which matters a great deal to the client. The question asks how the project manager should respond; in essence, whether a quality plan can be abandoned just to cut cost.
Quality matters as much as cost and schedule and cannot be given up to save money. PMBOK 8 requires quality to be embedded in processes and deliverables, and the quality management plan sets out the quality standards, objectives, roles and responsibilities and quality activities as the basis for preventing defects and reducing rework. Dropping the plan looks like a saving but may add the later cost of defects, rework and customer complaints. “The task is simple” is only a personal judgment and cannot replace a plan. So the project manager should develop the quality management plan. The answer is D.
Why the other options are wrong
- A. Starting work with no quality management plan gives up prevention outright. Logging it as a risk and moving the budget saved into management reserve accepts the problem instead of solving it, and management reserve is not meant for this purpose.
- B. Enough team experience is a subjective judgment, and management's verbal confirmation cannot replace a plan. Quality activities are ensured by plans and processes, not by individual experience.
- C. Postponing inspection until an external audit after acceptance finds defects after the fact, when rework costs more. “Cutting the budget accordingly” also has no basis.
Key takeaway Do not unilaterally cancel agreed quality activities just to save cost or hit a date. If a trade-off is truly needed, assess the impact and decide through governance and change control procedures. Have a quality management plan: prevention beats inspection after the fact.
Variation If the end of an iteration is near and the team skips code review to hurry, the answer is the same: restate the definition of done and agree on ways of working that do not sacrifice quality. Do not condone it, and do not lower the definition of done.
- Question 58
On an agile team's risk burndown chart, the horizontal axis is iterations and the vertical axis is the sum of scores of risks not yet closed. The curve falls steadily from iteration 1 to iteration 5. What does the curve show?
Show answer and explanation
Correct answer: C
The risk burndown chart plots iterations on the horizontal axis and the sum of scores of unclosed risks on the vertical axis. The curve falls from iteration 1 to iteration 5, and the question asks what it shows.
Start with what the vertical axis means: the sum of the scores of risks not yet closed. A falling sum means that, under the chart's chosen measure, the remaining exposure from unclosed risks is steadily shrinking; the curve alone does not establish why it fell. A risk burndown chart shows risk reduction, not schedule, cost or the number of issues. Common exam practice is to plot the sum of the scores of unclosed risks on the vertical axis of a risk burndown chart, so a falling curve means remaining risk exposure is shrinking. The answer is C.
Why the other options are wrong
- A. Velocity is reflected by the amount of work completed and is not what a risk burndown chart shows. For velocity, look at an iteration burndown chart or a velocity chart.
- B. Budget consumption comes from cost data. The vertical axis of a risk burndown chart is risk score, not money.
- D. The chart counts risks not yet closed, not issues that have occurred. Risks and issues are different things.
Key takeaway A falling risk burndown chart (PMBOK 8: a burn chart can show reduced risk exposure) means the remaining exposure from identified risks is decreasing.
Variation If the vertical axis were remaining story points, it would be an iteration burndown chart reflecting workload. For “what shows stakeholders risk exposure falling by iteration,” the answer is still the risk burndown chart.
- Question 59
To carry out its expansion strategy, an apparel group is building a new production base, and the facility is close to going into production. The company has an existing governance policy, but a new financial regulation has just been issued. It must be complied with, and complying with it will change the project scope substantially. How should the project manager respond?
Show answer and explanation
Correct answer: C
The project is in its late construction stage, close to operation. A new external financial regulation must be complied with and will change the scope substantially. How should the project manager respond?
Complying with the new regulation is a change for the project, and its effect on scope is large. The signals are “major impact” and “large scope change”: the bigger the impact, the more important it is to understand it first. The project manager should first analyze and assess the effect of the new regulation on scope, schedule, cost and so on, determine the best course of action from that, and submit a change when necessary. Here “analyzing the impact” is not delay: it is the precondition for deciding the scope, cost and time of the corrections. Only after the analysis can a well-founded proposal be put to the sponsor and a change submitted under the project management plan or organizational procedures. The answer is C.
Why the other options are wrong
- A. The stem says the new regulation must be complied with. Following only the current governance policy ignores that requirement.
- B. The new regulation has a major effect on scope. Making corrections without analysis could cause irreversible losses.
- D. The stem does not say the matter exceeds the project manager's authority. Escalating directly is passing the buck; the project manager should complete the analysis first.
Key takeaway When a mandatory new regulation has a major impact, assess the impact first, then decide on the course of action.
Variation If the stem said that the assessment found the approved scope baseline must be modified, the next step would be to submit a change request, to be approved by the designated person or body under the project management plan or organizational procedures (a change control board, if one has been established and authorized).
- Question 60
The day before a trade show opens, two key members are arguing endlessly about the booth lighting layout. The project manager has the authority to decide the layout, and a batch of exhibits is waiting on site to be put on display. If the layout is not settled soon, the show-day presentation will suffer badly. Which approach should the project manager use now?
Show answer and explanation
Correct answer: B
The day before a trade show opens, two key members argue about the booth lighting. The project manager has the authority to decide, exhibits are waiting to be installed, and without a prompt decision the opening-day display will be badly affected. The question asks which approach the project manager should use.
Time pressure is the deciding condition. Collaboration is the most thorough approach but needs time for full discussion, and there is no such time the day before opening. For an emergency the project manager can use their authority to settle it quickly. This is where force/direct applies: it is a win-lose approach, but it avoids a larger loss. After deciding, the project manager should still explain the reasoning and, after the show, review the experience and repair any damage the decision did to relationships. The answer is B.
Why the other options are wrong
- A. Collaboration needs time for each side to explain, evaluate and build consensus, and the time is not there.
- C. Compromise/reconcile provides only a temporary or partial resolution and still requires the parties to reach a middle position. Because the stem describes an urgent deadlock and gives the project manager authority to decide immediately, force/direct is more suitable.
- D. Withdraw/avoid would leave the problem hanging, and it could not be settled before the opening.
Key takeaway When it is urgent, there is no time to negotiate and you have the authority to decide, use force/direct; when it is not urgent, prefer collaboration.
Variation If the situation were “two weeks before the opening,” the project manager should first collaborate, bringing the two together to find out what each needs.
- Question 61
During the bidding stage, a software outsourcing company prepared its project management plan on the assumption that “senior architects will be available during project execution”. After the contract is awarded, the project manager learns from the functional manager that those architects will not be available then, and under the current plan delivery may slip by two weeks. The project has not started yet. What should the project manager do?
Show answer and explanation
Correct answer: A
At bidding, a software outsourcing company prepared its plan on the assumption that senior architects would be available during execution. After winning, it learns they will not be available then, and delivery may slip by two weeks. The project has not started. The question asks what the project manager should do.
The plan rests on the assumption that “the architects will be available then”, and the functional manager has confirmed they will not, so the resource assumption has failed. Resource unavailability is already fact, but the two-week delivery delay that it causes has not happened, and the project has not started, so it remains an uncertain consequence, which makes it a risk. The project manager should assess ways to prevent or mitigate the potential schedule delay and update the risk register with this schedule risk and the potential response options. Of the options, only A both assesses options and records the risk. Changing the plan directly, writing into the risk management plan or drafting another plan all skip the steps of assessing and recording. The answer is A.
Why the other options are wrong
- B. Revising the schedule treats a potential delay as an accomplished fact and skips risk assessment; adjusting the schedule also has to go through the Assess and Implement Changes process first, so it is not the next step.
- C. The risk management plan is a guiding document and does not record specific risks or schedule changes; a contingency plan is activated only when its trigger condition appears, which is not the case yet.
- D. Drafting a separate phased delivery plan sidesteps the problem: it does not assess the risk created by the failed assumption and does not update the risk register, jumping straight to a solution.
Key takeaway When an assumption the plan rests on fails, it may create a threat; assess it and record it in the risk register first, instead of changing the plan directly.
Variation If the project had already started and the architects did not show up, their nonavailability would be an issue to record in the issue log and address immediately; any resulting schedule delay that had not yet occurred would still be assessed and managed as a risk.
- Question 62
A project manager leaves for personal reasons, and the organization appoints a new project manager to take over a project under way. On checking, the new project manager finds that the predecessor never archived the project and almost no files were kept. Team members feel that time spent on anything beyond the deliverables is a waste. How should the new project manager respond?
Show answer and explanation
Correct answer: A
A new project manager takes over a project under way and finds that the predecessor never archived anything, and the team feels that time spent beyond the deliverables is wasted. The question asks how to respond.
The information and knowledge a project produces can serve the organization's day-to-day operations and later projects, and archiving follows the process the organization specifies. Facing the team's lack of agreement, the project manager should first explain the value of archiving to win their buy-in, and then keep the files according to the organization's archiving process, combining reasoning with process. The answer is A.
Why the other options are wrong
- B. Which files must be kept is already set by the organization's archiving process, and it is the project manager's own responsibility, so there is no need to ask the sponsor first and then decide.
- C. Valuable material is not only the files directly tied to deliverables. Records of how issues were handled, lessons learned and the basis for decisions must also be kept, and keeping only part loses knowledge.
- D. A forced order can get files archived after the fact, but the team does not buy in. The lasting effect is weaker than explaining the value and winning agreement, and it does not fit how a team should be led.
Key takeaway Archive through the process the organization specifies, and help the team understand why archiving matters.
Variation If the archive lacks lessons learned, summarize them first and then archive. If the team still resists archiving, keep explaining the value of archiving to later projects and to the organization.
- Question 63
An environmental nonprofit is launching a community recycling project, and the project manager is helping the sponsor prepare the business case. To show the sponsor that the investment is reasonable, a metric is needed that shows how high the average annual net benefit (average annual profit) the project creates is as a proportion of total investment. Which metric should be used?
Show answer and explanation
Correct answer: C
The project manager is helping the sponsor prepare the business case, and the question is which financial metric measures “average annual net benefit as a proportion of total investment”.
Return on investment measures the net return earned relative to the amount invested. The stem explicitly uses an annual-average basis: average annual net benefit (profit) ÷ total investment × 100%, which is exactly the ratio of average annual net benefit to the investment. The larger the value, the more average annual benefit each dollar invested brings back. This metric ignores the time value of money and is simple to use, so it suits explaining to the sponsor in a business case whether the investment is reasonable. The stem asks for a “proportion”, so the answer is C.
Why the other options are wrong
- A. Total cost of ownership measures all costs of an asset over its whole period of use. It speaks only of cost and does not involve a benefit proportion.
- B. Budget at completion (BAC) is the total budget for the project work, used to plan and monitor cost. It does not measure benefits.
- D. Payback period measures how long it takes to recover the investment. It is a length of time, not the proportion of benefit to investment.
Key takeaway ROI measures the net return relative to the amount invested. On the annual-average basis it is average annual net benefit (profit) ÷ total investment, showing how much benefit each unit of investment brings; payback period measures time. ROI ignores the time value of money; when the time value matters, use NPV or IRR instead.
Variation If the stem asked “how long until all of the investment is recovered?”, the answer is payback period; if it asked “is the ratio of benefits to costs greater than 1?”, the answer is benefit-cost ratio.
- Question 64
The scope of a data center room renovation project has been clearly defined. While planning the sourcing strategy, the sponsor asks for the contract type that leaves the buyer with the least cost risk. Which of the following best meets that requirement?
Show answer and explanation
Correct answer: C
The scope of a data center room renovation has been clearly defined. While planning the sourcing strategy, the sponsor asks for the contract type that leaves the buyer with the least cost risk, and the question asks which option fits best.
PMBOK 8 Appendix X4 says a fixed-price contract establishes a predetermined fee against a clearly defined scope of work, transferring cost risk to the seller while offering budget predictability for the buyer, whereas under a cost-reimbursable contract the buyer pays actual costs and there is a risk of cost escalation. Among the subtypes, a firm fixed-price contract fixes the price at signing. As long as the scope does not change the buyer’s payment is fixed and cost overruns fall entirely on the seller, so the buyer’s risk is lowest. The answer is C.
Why the other options are wrong
- A. Cost plus incentive fee (a common exam term): the buyer reimburses actual costs, and both savings and overruns are shared with the seller by the agreed ratio. The buyer still bears most of the cost risk.
- B. Time and materials: it usually has no fixed total price in advance, and payment follows actual hours and materials, so the buyer carries a larger risk of uncertain effort and cost (the contract may also set a maximum value or time limit).
- D. Fixed price incentive fee (a common exam term): it has a ceiling price. The buyer shares overruns by the agreed ratio until the point of total assumption; after that point the seller bears each further overrun. The buyer’s cost risk is therefore still greater than under a firm fixed-price contract.
Key takeaway For a clearly defined scope and a comparison of cost risk, the buyer’s cost risk is lowest under a firm fixed-price contract; it is greater under cost-reimbursable and time-and-materials contracts.
Variation If the question asked for the contract with the least financial risk to the seller, the answer would be a cost-reimbursable contract; to balance cost risk between buyer and seller, an incentive contract with a sharing ratio is a choice.
Reference Contract Types · Lesson 2: Fixed-Price Contracts: FFP, FPIF and FP-EPA
- Question 65
A team uses an AI tool to assist testing. The tool reports several anomalies, but there have been false alarms in the past. How should the team handle this?
Show answer and explanation
Correct answer: A
A team uses an AI tool to assist testing, and the tool reports several anomalies, but it has produced false alarms before. Past false alarms do not mean the alerts can be ignored. What the team must handle is the reliability of AI output: it should neither be trusted entirely nor rejected entirely.
PMBOK 8 stresses the reliability of AI: information obtained from AI should be checked and validated, and it may be biased, incorrect or irrelevant. So the anomalies the AI reports should be verified by a person to confirm whether they are real, and those confirmed as defects are then handled. This neither lets real problems slip through nor wastes resources on false alarms. The answer is A.
Why the other options are wrong
- B. Ignoring all alerts will miss real defects, which is too risky. Past false alarms do not mean they are all false this time.
- C. Treating results that contain anomalies as passed and releasing gives up quality gatekeeping, and the responsibility ultimately falls on people.
- D. Redoing manual tests of all functions is too costly, loses the efficiency AI brings, and is not targeted.
Key takeaway AI output must be validated by a person: verify whether alerts are real, and handle them once confirmed.
Variation If the false alarm rate stays high over a long time, adjust the tool's thresholds or training data and test its accuracy periodically.
Reference Artificial Intelligence in Project Management · Lesson 3: Responsible Use of AI and the Eight Ethical Concerns
- Question 66
PMLyceum is developing a cross-border live-stream e-commerce platform. Management attaches great importance to it and has agreed to engage the architects and algorithm engineers you identified through an outside supplier at hourly rates to join the project team. Because live-streaming formats change quickly, the sponsor cannot give an exact statement of work (SOW). Which contract type might the project use?
Show answer and explanation
Correct answer: D
An accurate SOW cannot be written but the staff are known, and the question asks which contract to choose.
Two signals together: the sponsor cannot give an exact SOW (the scope is hard to determine), but the architects and algorithm engineers named will be bought from an outside supplier at hourly rates (the trades and rates are known, while the amount of work and duration are uncertain). This is exactly where a time-and-materials contract applies: payment for actual hours and materials plus a profit margin, suited to cases where you need to add staff or hire experts. The answer is D.
Why the other options are wrong
- A. Fixed price with economic price adjustment is also fixed-price, so it requires a clear scope, and it is used where the performance period is long and material prices move with the market.
- B. A firm fixed-price contract requires a clear scope. If an SOW cannot be written, no price can be set.
- C. Cost plus fixed fee suits cases where the seller undertakes a whole body of work of uncertain scope and the buyer reimburses costs. Here the purchase is of designated professionals billed by the hour, which time and materials fits better.
Key takeaway When an SOW cannot be written but the staff or trades are known, choose time and materials. Unit prices are agreed in advance; if no cap is agreed, the total floats with actual hours, risk is split between buyer and seller, and the buyer has to monitor hours closely; if a maximum amount is agreed it is bound by that.
Variation If the stem said “it is not even clear which trades are needed and the development direction is not set”, choose a cost-reimbursable contract instead; if the scope were clear and the work were built to drawings, choose a fixed-price contract.
- Question 67
An agile team is delivering a warehouse dispatch platform incrementally over several iterations. Halfway through the third iteration, the company announces that the database version the platform depends on will go out of support next quarter, affecting thousands of terminals. What should the project manager do FIRST?
Show answer and explanation
Correct answer: C
An agile team is delivering a warehouse dispatch platform over several iterations. Halfway through the third iteration, the company announces that the database version the platform depends on will go out of support next quarter, affecting thousands of terminals. What the impact actually is remains unclear. What does the project manager do first?
The end-of-support notice describes only the change. Which terminals and features are affected, and whether delivery is affected, are still unknown. When an external environment change appears, first meet the affected stakeholders to find out the specific impact; only then can follow-up actions be decided, such as adding backlog items, upgrading terminals or adjusting the plan. Understand first, then act. The answer is C.
Why the other options are wrong
- A. Notifying the product owner and asking for more people before the impact is understood is asking for resources before any analysis. The extra people may not be needed.
- B. Upgrading all terminals is one possible response, but it can be scheduled only after the impact and priorities are understood. A blanket upgrade may waste effort and cost.
- D. New stories should be discussed and analyzed first. Story priority is set by the product owner according to value, so the project manager putting them at the top unilaterally is inappropriate, and the impact has not yet been clarified.
Key takeaway When the external technology environment changes, first find out the impact, then act.
Variation If the notice had clearly identified the affected terminals and the deadline, you could assess right away and bring the related stories into the backlog, with the product owner ordering them.
Reference External Business Environment · Lesson 2: Responding to External Environment Changes
- Question 68
At the Daily Scrum, an agile coach learns that a developer's items are behind the Sprint plan. The coach wants to help the developer solve the problem. What should the coach do?
Show answer and explanation
Correct answer: A
In a team using Scrum, the Daily Scrum has revealed that one developer's items are behind the Sprint plan. The question asks what the agile coach should do to help.
An agile team is self-organizing. When a problem appears, first invite the team to offer suggestions and find its own way, with the coach only facilitating. That keeps the initiative with the team and lets everyone share ownership of the result. The one who is behind is supported as part of the team, not singled out or replaced. The answer is A.
Why the other options are wrong
- B. Having the coach decide who takes over the items amounts to assigning work for the team, which goes against self-organization and takes the decision away from the team.
- C. A progress problem within the team should first be solved by the team itself. There is no need to bring in stakeholders, which would escalate an internal matter and take away the team's chance to solve it itself.
- D. The stem does not say the delay comes from exhaustion, so a team-building event has nothing to do with the problem and misses the target.
Key takeaway When a problem appears, let the team find its own way first, with the coach guiding and not deciding for the team. The coach's role is to ask questions and guide so that the team finds the way and owns the result.
Variation If the stem said the cause of the delay was waiting for another department to grant access, that would be an external impediment, and the Scrum Master should step in personally to coordinate.
- Question 69
A project manager is managing a fairly large project. At the quarterly review meeting, he notices that a UI designer who has performed well in the past has recently missed several deadlines. What should the project manager do?
Show answer and explanation
Correct answer: B
At a quarterly review of a large project, the project manager notices that a UI designer who used to perform well has recently been unable to finish work on time on several occasions. The question asks what the project manager should do.
The stem does not state a cause. It could be task difficulty, a personal reason, a lack of skills or a blocked process. If you act before the cause is known, you are likely to prescribe the wrong remedy. First talk with the designer to find out why his performance has changed, and then agree countermeasures together. That is the first step in handling a performance problem. In the conversation, listen, assume no conclusion and do not point out the problem in public, so as to protect his past good performance and his motivation. The correct answer is B.
Why the other options are wrong
- A. Lowering the demands of his tasks before the cause is known may not address the problem at all and may make him feel demoted.
- C. The stem does not say he lacks skills. Asking for training directly offers a solution before the cause is understood.
- D. Bringing a human resources representative to the conversation is premature escalation and puts pressure on the communication. The project manager should first talk with him personally.
Key takeaway When performance changes suddenly, talk privately to find the cause first, then choose measures.
Variation If the conversation confirms a skill problem, arrange training or mentoring. If it confirms a personal reason, agree an adjustment of his workload with him.
- Question 70
On an enterprise ERP agile project, the team works in two-week Sprints, and several representatives from the finance department want to meet with the team every two weeks to learn how the project is progressing. What should the project manager do next?
Show answer and explanation
Correct answer: D
On an agile project, several finance representatives want to meet the team every two weeks to learn about progress. What should the project manager do next?
A Sprint Review is held at the end of a Sprint, where the team shows stakeholders the work completed during the Sprint and asks for their feedback. A meeting every two weeks matches the Sprint Review of each Sprint, so inviting them to watch the team demonstrate the product Increment directly lets them see real progress and give feedback on the spot. The answer is D.
Why the other options are wrong
- A. The Sprint Retrospective is the team's internal meeting to review how it works and set improvements, not a meeting to show progress to outsiders, and outsiders listening in would hinder the team's candor.
- B. A dedicated progress-reporting meeting costs more, only relays progress verbally and is not as good as seeing the Increment itself, and it fails to use the existing review meeting.
- C. An email is a one-way text description. It cannot replace seeing a working Increment with their own eyes, and it does not meet their wish to meet.
Key takeaway Stakeholders who want to see progress: invite them to the Sprint Review to see the Increment.
Variation If someone wants to know about the team's internal improvement items, that belongs to the Sprint Retrospective and outsiders should not be invited. If what they want to see is longer-term direction, look at the product roadmap.
Reference Scrum Events · Lesson 4: The Sprint Review
- Question 71
A company has just formed a new project team whose members come from the engineering, marketing and operations departments and do not know one another. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
A company has formed a new project team whose members come from three departments and do not know one another. The question is what the project manager should do first, and the basis is the opening order for a new team.
Before a new team gets to work, the project manager should first state expectations at team level and work with members to define roles, responsibilities and collaboration rules. This is the foundation of leading the team: once everyone knows what each person does and how to work together, later division of work and technical work have a shared starting point. The signals in the stem are “newly formed,” “strangers” and “first.” The answer is A.
Why the other options are wrong
- B. Sending out a task list before expectations and rules are made clear leaves members unsure of the division of work and how to collaborate, which leads to misunderstandings and overlaps.
- C. A technical solution is of course needed, but having the project manager finish it alone and then announce it gives the team no part in it, and it is not the first thing a new team needs.
- D. Waiting for obvious conflicts before stepping in is passive. The project manager should establish expectations and rules in advance to prevent conflicts, not wait for problems to occur.
Key takeaway A new team first clarifies expectations, roles, responsibilities and collaboration rules, and only then assigns tasks and discusses technical work.
Variation If the stem were changed to “the members have been working together for a while and overlaps and gaps have appeared,” go back to clarifying and confirming roles and responsibilities, using the responsibility assignment matrix if necessary.
- Question 72
A community senior-care platform project is 85% complete. A key stakeholder asks that a care-level assessment task be included in the project, while another stakeholder objects, arguing that the project is nearly finished and the project management plan should no longer be changed. The project manager has already recorded and assessed the added requirement. What should the project manager do?
Show answer and explanation
Correct answer: C
A community senior-care platform project is 85% complete. One key stakeholder asks to include a level assessment in the project, while another objects, saying the project is nearly over and the plan should not be changed. What should the project manager do?
The project is not yet finished and the added assessment work would likely affect a baseline, so it should be handled through Assess and Implement Changes: record and assess the request, then submit a formal change request to the approver designated in the change management plan (the change control board where applicable), and keep the sponsor informed. Whether to change depends on the process, not on how much of the project is complete or on which side is more forceful. When two stakeholders hold opposing views, the project manager does not take sides but hands the decision to the authorized approver. The answer is C.
Why the other options are wrong
- A. Calling a meeting to “tell” them the change will be made decides the outcome before approval.
- B. Until a change is approved, the plan and budget cannot be updated directly.
- D. Change requests are managed by the project manager and approved by the board or the designated owner; they cannot be left to the person who made the request.
Key takeaway Being near completion is not a reason to skip change control; a baseline change goes to the approver designated in the change management plan (such as the change control board).
Variation If closure has not yet been completed and the client asks only for a revision to a user manual that does not affect a baseline, handle and record it under the existing plan; if closure has already been completed, it is handled through operations, warranty support or new authorized work.
- Question 73
A project manager takes over a retail store POS upgrade project that has had nobody leading it for several weeks. The charter has already made the objectives and direction clear, but the team lacks day-to-day leadership and rhythm, and members feel lost about what to do next. What should the new project manager do?
Show answer and explanation
Correct answer: A
The project manager takes over a POS upgrade project that has had nobody leading it for several weeks. The charter has made the objectives and direction clear, but the team lacks rhythm and members feel lost. The question asks what the new project manager should do.
The charter has already stated the direction, so the team’s confusion is not about “not knowing where to go”. It is that nobody leads day to day, and the team lacks a sense of rhythm and accomplishment. The project manager should set short-term goals that are easy to reach so the team quickly sees results, and promptly recognize members who achieve them, rebuilding confidence and rhythm through results and recognition. The signal in this type of question is “the charter has already made the direction clear”: when direction is clear, the answer is not to restate the goals or to explain them again, but to address rhythm and confidence. The answer is A.
Why the other options are wrong
- B. The direction is already clear in the charter, so having the sponsor explain it again misses the problem. A problem inside the team should be dealt with first by the project manager personally.
- C. There is no evidence that the team can self-organize, and leaving it alone will only make things more chaotic.
- D. Being lost is a management problem, not a schedule problem. Reporting up and asking for an extension does not address the cause.
Key takeaway When the team is lost after a takeover, rebuild rhythm and confidence with short-term goals and prompt recognition.
Variation If the cause of the confusion is that the goals themselves are unclear, go back to the charter and the vision to realign with the team. If members resent the predecessor’s decisions, build ground rules together to align expectations.
- Question 74
A smart agriculture project is developing its project management plan. The sponsor believes that the project's success depends on the guidance of an agronomy expert, and the project charter names a senior agronomist to join the project. Which of the following is this approach?
Show answer and explanation
Correct answer: B
A smart agriculture project is developing its project management plan. The sponsor believes success depends on an agronomy expert and has named a senior agronomist in the project charter. The question asks what this approach is, which requires distinguishing concepts related to acquiring resources.
Preassignment refers to project resources determined in advance. Typical situations include specific people committed in a competitive proposal, dependence on the expertise of particular persons, and team members already assigned in Initiating or another process before the initial resource management plan is completed. Here the sponsor directly named the person in the charter, and the project depends on that person's expertise, so it fits the description of preassignment. The answer is B.
Why the other options are wrong
- A. Physical resource assignments are an output of Acquire Resources that records materials, equipment, sites and other physical resources. They are about things, not people, and are not an approach.
- C. Multicriteria decision analysis is a technique for selecting people by weighted scoring against criteria, which requires comparing several candidates. Here the person was named directly, with no comparison.
- D. Project team assignments are also an output of Acquire Resources, recording team members and their roles and responsibilities. They are a result, not a way of naming people.
Key takeaway If the person was determined in advance (committed in a bid, specialized skills, named in the charter), it is preassignment.
Variation If the stem said “there are three candidates and they are scored and ranked on experience, availability and cost,” the answer would be multicriteria decision analysis; if it asked “where the preassigned person is recorded,” the answer is the project team assignments.
- Question 75
A city smart-streetlight upgrade project is being delayed because several key decisions are caught up in conflicting opinions from the company's senior management and external stakeholders. What should the project manager do?
Show answer and explanation
Correct answer: A
A streetlight project is being delayed because several key decisions are caught up in conflicting opinions from senior management and external stakeholders. The question is what the project manager should do. The signal “decision delay plus conflicting opinions” points to a missing decision mechanism.
Decisions that drag on without resolution may indicate that the rules, authority or process for deciding are unclear, so the project manager should first check whether the governance arrangements are adequate, including who holds decision authority, who reconciles conflicting opinions and whether an escalation path exists. If needed, establish or add a decision structure, and then have all parties work through it. Finding the root cause before acting is the right treatment. The answer is A.
Why the other options are wrong
- B. The stakeholder register records who cares about what, and the communications management plan explains how to communicate. Neither says who holds decision authority. Communicating only according to those documents still does not resolve who decides or how the matter should be escalated.
- C. Separating the team from senior management and external parties is unrealistic and damages relationships. It also leaves the team making decisions without authorization. The decision structure is still missing and the problem is only hidden.
- D. Rescheduling only absorbs the delay. It does not fix the root cause, a missing decision authority and coordination mechanism, and if the rescheduling changes the approved schedule baseline, it must also go through change control. If decisions are still not landing, the rescheduled plan will be delayed in the same way.
Key takeaway When decisions are blocked, check governance first: are the rules, authority and decision structure in place?
Variation If governance is complete and one decision-maker simply will not commit, escalate along the escalation path to the steering committee. If opinions conflict but the decision-maker is clear, the project manager coordinates and obtains the decision.
Reference Project Governance · Lesson 3: Escalation Paths, Investment Control and Tailoring the Governance Framework
- Question 76
A newly founded education company is building an online question-bank website. Resources are limited and the work relies mainly on internal staff. Management can accept a longer overall duration, the overall requirements are already clear, and a usable basic version only needs to go live first, with the remaining features allowed to be delivered in batches later. Which approach should the project use?
Show answer and explanation
Correct answer: C
The overall requirements for the online question bank are clear; management wants a usable basic version live first, with the remaining features delivered in batches, and can accept a longer overall duration. You must decide which approach to choose.
PMBOK 8 says that in certain predictive approaches it may be optimal to deliver the product partially and incrementally rather than as a single, final release. This is used when the overall scope is well understood and planned up front, but phased delivery offers advantages. The deciding conditions here are two: the overall requirements are clear, and a basic version goes live first with the rest delivered in batches. Together they describe incremental delivery within a predictive approach. The answer is C.
Why the other options are wrong
- A. The requirements are clear, but management wants a usable basic version first, and a single delivery cannot satisfy the requirement to go live in batches.
- B. Adaptive approaches address highly uncertain requirements. Here the overall requirements are already clear, so there is no need to re-prioritize repeatedly through iteration feedback.
- D. The early part of this hybrid pattern is meant to explore uncertain requirements. Here the requirements are already clear, so there is nothing to explore.
Key takeaway When the scope is clear and you want a usable version out first, choose incremental delivery within a predictive approach.
Variation If the stem became “the features are hard to define and can only be added after seeing the live version,” the answer would be adaptive. If it became “the overall scope is clear and regulation requires a single acceptance,” choose predictive with a single delivery.
- Question 77
Project manager Maya wants to strengthen her team’s sense of ownership. She leads by example and takes responsibility for project decisions, and at the very start of the project she clarifies everyone’s roles and responsibilities and sets up a team agreement. Which dimension of the project management mindset do these practices mainly reflect, and which two principles are involved?
Show answer and explanation
Correct answer: A
The project manager wants to strengthen the team’s sense of ownership: she leads by example, takes responsibility for project decisions, and at the start clarifies each person’s role and responsibilities and sets a team agreement. The question asks which mindset dimension these practices reflect and which two principles are involved.
The Eighth Edition’s mindset has three dimensions, proactive, ownership and value-driven, which correspond to the six principles. The ownership dimension focuses on the accountability of leaders and the development of a high-performance team culture, and it includes Be an Accountable Leader and Build an Empowered Culture. Leading by example and taking responsibility for decisions belong to the former; clarifying roles and responsibilities and setting a team agreement belong to the latter. The answer is A.
Why the other options are wrong
- B. The proactive dimension emphasizes systems thinking and appropriate levels of planning, and it includes Adopt a Holistic View and Embed Quality Into Processes and Deliverables. It does not match the leadership and team-culture practices in the stem.
- C. The value-driven dimension includes Focus on Value and Integrate Sustainability Within All Project Areas. It is about alignment with strategy and contributions to the community and the environment, none of which the stem mentions.
- D. The dimension is right, but Focus on Value belongs to the value-driven dimension, not to ownership. The team agreement in the stem reflects Build an Empowered Culture.
Key takeaway Ownership maps to the accountable leader and empowered culture; proactive maps to the holistic view and quality; value-driven maps to value and sustainability.
Variation If the practice emphasizes systems thinking and building quality requirements into every phase, it maps to the proactive dimension.
Reference Project Management Principles · Lesson 1: Nature of the Principles, Adopt a Holistic View and Focus on Value
- Question 78
A city bus dispatch platform project uses a predictive approach. After the passenger lookup module is delivered, a key stakeholder says they will not approve the deliverable but does not explain the specific reason. What should the project manager do FIRST?
Show answer and explanation
Correct answer: C
A city bus dispatch platform project uses a predictive approach. After the passenger lookup module is delivered, a key stakeholder says they will not approve the deliverable and gives no reason. The question asks what the project manager should do first.
When the cause is unknown, communicate and analyze first, then act. The project manager should talk with the stakeholder to find out why they are not approving it, and work out whether it is a misunderstanding of requirements, a quality defect or a disagreement over acceptance criteria, then look for a solution together with the stakeholder. Only once the cause is clear can the next steps be targeted. The answer is C.
Why the other options are wrong
- A. Asking the sponsor to influence the stakeholder applies pressure from above before the cause is known. It is an escalate-first approach and may sour the relationship.
- B. A change request should rest on a clearly identified problem and an assessment of it. Submitting a request to redo the work when you do not even know the reason is premature.
- D. The CCB handles change requests. There is no clear change yet and no communication has taken place, so going straight to escalation is not appropriate.
Key takeaway When a deliverable is rejected and the reason is unknown, talk to the stakeholder to find the reason first, then decide on next steps.
Variation If the stakeholder says a requirement was missed, the next step is to assess the impact and submit a change request. If it is a defect, handle it through the quality process and rework.
Reference Judgment Rules for Situational Questions · Lesson 2: Analyze and Communicate Before Acting; Issues vs. Risks
- Question 79
A team uses an agile approach to build an internal expense reimbursement system, and the organization requires the project to meet an audit-trail compliance requirement. What is the BEST practice?
Show answer and explanation
Correct answer: C
The agile team builds an internal expense reimbursement system, and the organization requires an audit trail. The question asks for the best practice.
The key to meeting compliance on an agile project is to build the necessary compliance record requirements into the definition of done and the iteration activities: when the work of each iteration is done, the needed records are left, keeping the agile rhythm without missing the evidence the audit requires. What compliance requires is timely and complete records, not a particular process form. That way the evidence an audit needs is produced naturally in the course of the work and is not an extra burden. The answer is C.
Why the other options are wrong
- A. Records written up all at once afterward are unreliable and cannot meet the timeliness an audit trail needs, and over time details are hard to reconstruct.
- B. Compliance does not mean you must switch to a predictive process. You only have to meet the necessary records, and switching to predictive processes would lose agile flexibility.
- D. Keeping only the iteration review minutes cannot show that each piece of work was compliant. The scope of necessary records is too narrow and the audit would lack evidence.
Key takeaway To meet compliance in agile, build the necessary records into the definition of done and the iteration activities.
Variation If the audit requires approval records only for a certain type of change, write that approval requirement into the acceptance criteria or compliance task of the matching item. If it is a quality requirement that applies to all increments, put it in the shared definition of done.
- Question 80
On a home appliance development project, the team is dissatisfied with its current development speed and finds an automated testing technique. After analysis, the project manager confirms that adopting it would cut the testing cycle from 20 days to 10 days and save 25% of testing labor cost. After the change control board approves, the team starts using the technique immediately. Which risk response strategy is this?
Show answer and explanation
Correct answer: B
The team on a home appliance development project is dissatisfied with its development speed and finds an automated testing technique that could cut the testing cycle from 20 days to 10 days and save 25% of testing labor cost. It starts using it immediately after the change control board approves. Which risk response strategy is this?
An automated testing technique that shortens the schedule and lowers cost is an uncertainty that favors the project, that is, an opportunity. Exploit makes sure the opportunity happens, raising its probability to 100%, and typical approaches include adopting a brand-new technology or upgrading an existing one to cut cost and shorten duration. The team confirmed the benefit and put the technique into use immediately after approval, which is action to make sure the benefit is realized, so this is exploit. The answer is B.
Why the other options are wrong
- A. Share gives responsibility for the opportunity to a third party and shares the benefit, for example through a partnership. Here the team uses the technique itself and no third party is involved.
- C. Accept acknowledges the opportunity but does not pursue it actively. The team went through change control and started using the technique immediately, which is actively seizing it, not passively accepting it.
- D. Mitigate is a strategy for threats. The uncertainty here is a favorable opportunity, and applying a threat strategy to an opportunity is the most common confusion.
Key takeaway Adopting new technology to make sure the opportunity is realized is exploit.
Variation If the team only added testing resources to make adoption of the technique more likely without making sure of it, that would be enhance. If the technique were supplied by a third party who took a share of the benefit, it would be share.
Reference Risk Response Strategies · Lesson 3: Strategies for Opportunities and for Overall Project Risk
- Question 81
On a testing project, the project manager finds that two members each believe interface testing is theirs to handle, while another part of the regression testing is claimed by no one, so work is both overlapping and missing. What should the project manager do?
Show answer and explanation
Correct answer: C
On a testing project, two members both believe interface testing is theirs, while part of the regression testing is claimed by no one, so work overlaps and is missed. The question is what the project manager should do, and the clue is “overlap plus gaps.”
Overlap and gaps show that role and responsibility boundaries are unclear. The project manager should call the members together to clarify each person's role and responsibilities and confirm them in writing. This is the basic way to make team expectations clear, and PMBOK 8 also stresses that project managers should ensure team members understand and fulfill their roles and responsibilities. Once this is clarified and confirmed, the regression testing no one claimed also gets an owner. The answer is C.
Why the other options are wrong
- A. Letting the two work it out without involvement resolves only who owns the interface testing; the regression testing nobody claimed is still missed, and the project manager gives up the responsibility to set clear responsibilities.
- B. Giving everything to the most experienced member overloads that person and creates a bottleneck. It also avoids the unclear-boundary problem, and the other members remain unclear about their roles.
- D. Adding a coordinator is just one more relay step. It does not fundamentally clarify responsibility boundaries and adds communication cost and new unclarity.
Key takeaway For overlapping and missing responsibilities, clarify role boundaries and confirm them in writing; do not avoid the issue or add more steps.
Variation If after clarification some work still has no willing owner, assess whether there is a shortage of people or skills and fill it through resource arrangements or training, rather than assigning it by force.
Reference Team Charter · Lesson 3: Shared Vision and Clear Expectations: The Opening Order for a New Team
- Question 82
A trade-show booth construction project currently has planned value of $6,000, earned value of $5,100 and actual cost of $4,500. Which of the following correctly states the schedule variance?
Show answer and explanation
Correct answer: A
PV, EV and AC are all given. The question asks for the schedule variance (SV), not the cost variance.
Schedule variance is the difference between earned value and planned value: SV = EV − PV. The value of the work completed is lower than the value planned to be complete, so the project is behind schedule. AC is a distractor here; it is used only for the cost variance. The answer is A.
- SV = EV − PV = $5,100 − $6,000 = −$900
- SV is below 0, so the project is behind schedule
- For contrast: CV = EV − AC = $5,100 − $4,500 = +$600 is the cost variance and is irrelevant to this question
- Check: SPI = $5,100 ÷ $6,000 = 0.85, below 1, consistent with behind schedule
Why the other options are wrong
- B. $5,100 − $4,500 = +$600 is the cost variance (CV), not the schedule variance that was asked for. It does not answer the question.
- C. The numbers are right but the subtraction is reversed: $6,000 − $5,100 = +$900. In variance formulas EV always comes first, and a negative result means behind schedule.
- D. −$1,500 = $4,500 − $6,000, which is AC minus PV. AC and PV correspond to different amounts of work and cannot be subtracted directly.
Key takeaway SV = EV − PV measures schedule and CV = EV − AC measures cost. EV always comes first.
Variation If the question asked for cost variance, CV = $5,100 − $4,500 = +$600, under budget. If EV were $6,600, SV = +$600, ahead of schedule.
- Question 83
A team uses Scrum to deliver value to customers in small, quick steps. Which of the following correctly describes the Increment in Scrum?
Show answer and explanation
Correct answer: D
The question asks for the correct description of the Increment in Scrum.
An Increment is the result that has actually been completed (it can be produced at any time during the Sprint and is inspected as a whole at the end). It must be usable and meet the Definition of Done, and it is the sum of the items completed in this Sprint and all earlier Increments. What the team set out to do at the start and what is finally done are not necessarily the same, so the Increment is based on what is actually done. A useful test is whether it can be given to users: items selected into the Sprint Backlog but not finished cannot count as part of the Increment, and only the part that meets the Definition of Done is added. The answer is D.
Why the other options are wrong
- A. The items selected at Sprint Planning are a plan or forecast and are not necessarily the same as what is actually completed in the end, so they are not the Increment.
- B. The task list is the result of breaking down Sprint Backlog items and is part of the plan. Tasks are a means of implementing the items and are not the result.
- C. The Sprint Goal is a one-sentence statement of what the Sprint aims to achieve. It is not the result the Sprint produces.
Key takeaway Increment = the result actually completed that meets the Definition of Done, added up Sprint by Sprint. Only items that meet the Definition of Done count toward the Increment, and half-finished work does not.
Variation If the question is whether a story that lacks only integration testing at the end of the Sprint counts toward the Increment, the answer is no: work that does not meet the Definition of Done goes back to the Product Backlog for future consideration. Added together, the Increments of several Sprints make up the product that is finally delivered.
- Question 84
A reservation-system integration project for a hotel chain involves many stakeholders. One key stakeholder asks for a small scope change. The project manager judges that the team needs to put in very little effort for it, but worries that going through full change control will delay the schedule. What should the project manager do?
Show answer and explanation
Correct answer: A
On a hotel-chain reservation-system integration project, a key stakeholder requests a small scope change. The effort is small, but the project manager fears full change control will delay the schedule.
Whenever a change affects the scope baseline, regardless of effort, it must go through formal change control: assess the impact, submit a change request, obtain approval from the designated approver and then update the baseline. A small change can be assessed quickly but cannot skip the process, or small changes accumulate into scope creep. A small change is not the same as no impact. Change control can be tiered by size, for example by authorizing the project manager to approve low-impact changes, but only if the process already provides for that; without such authority, any change that touches a baseline must be assessed and submitted as a change request. The answer is A.
Why the other options are wrong
- B. Asking the key stakeholder for formal approval to avoid change control does not work: approval authority rests with the people or board named in the change control process, and one individual's approval cannot replace it.
- C. Implementing directly to avoid schedule adjustment changes the baseline without approval, and the schedule becomes inaccurate. It is where scope creep starts.
- D. Change requests cannot be blanket-rejected. Changes may be raised during a project as long as they follow the process.
Key takeaway The size of a change is no reason to skip change control. If it touches a baseline, submit a change request.
Variation If the change affects no baseline, for example a choice of implementation details within approved scope, no change request is needed and the team decides internally.
Reference Monitor and Control Scope and Scope Creep · Lesson 3: What to Do When You Find Out-of-Scope Work: Control First, Then Change
- Question 85
A newly appointed business director on the client side comes to the project site to verify the project's results and feels that the project manager has provided too little information. The project manager has already added the director to the stakeholder register. What should the project manager do FIRST?
Show answer and explanation
Correct answer: C
A newly appointed client-side business director comes to the site to verify the project's results and finds the information provided insufficient. You must decide what the project manager should do first.
A new senior stakeholder who finds the information insufficient shows that the existing engagement and communication arrangements do not cover his needs. So the first step is to carry out stakeholder analysis and communication requirements analysis for this new director to learn his information needs and communication preferences, then update the stakeholder engagement plan and the content, format and frequency of information in the communications management plan accordingly. Logging an issue, raising a risk or adding meetings are all actions taken before his needs are understood. The answer is C.
Why the other options are wrong
- A. Logging it in the issue log is fine, but there is no reason yet to escalate to the sponsor right away, since it is not yet clear what information he is actually missing.
- B. Treating insufficient information as a risk uses a tool for uncertain events on a communication problem that has already occurred, and registering it does not supply the missing information.
- D. Before increasing meetings and report frequency you need to know what he needs and what format he prefers. Otherwise the step may miss the mark and even add to his burden.
Key takeaway When a new stakeholder finds the information insufficient, first analyze his information needs, then update the stakeholder engagement plan accordingly.
Variation If the information the director wants is already in the communications management plan and was simply not sent, send it and check the distribution list. If his request goes beyond the scope, it must be negotiated.
Reference Stakeholder Engagement · Lesson 5: Monitoring Stakeholder Engagement: Assess Results, Adjust Strategy and Plan
- Question 86
A project manager knows the following data for the project to date: planned value $15,000, actual cost $17,500, and schedule performance index 1.2. The project manager wants to judge cost performance. Which statement is correct?
Show answer and explanation
Correct answer: C
Only PV, AC and SPI are given to date. You must back out EV first and then judge cost performance.
SPI = EV ÷ PV, so EV = 1.2 × $15,000 = $18,000. CPI = EV ÷ AC = $18,000 ÷ $17,500 ≈ 1.03, above 1; CV = +$500, a small cost saving. So the work completed has not gone over budget. Note that a positive CV is a saving, not an overrun. The answer is C.
- EV = SPI × PV = 1.2 × $15,000 = $18,000
- CPI = EV ÷ AC = $18,000 ÷ $17,500 ≈ 1.03, above 1
- CV = EV − AC = $18,000 − $17,500 = +$500, a cost saving
- Check: SV = $18,000 − $15,000 = +$3,000, so the project is also ahead of schedule
Why the other options are wrong
- A. CV = +$500 is positive, which means a saving, not an overrun. The meaning of the sign is reversed.
- B. A CPI below 1 comes from computing PV ÷ AC = $15,000 ÷ $17,500 ≈ 0.86, which uses the wrong numerator. The CPI numerator must be EV.
- D. A CPI above 1 means the value of work completed exceeds actual spending, which is a saving. The direction of the index is read backwards.
Key takeaway When data is incomplete, first back out EV = SPI × PV. A positive CV and a CPI above 1 both mean a cost saving.
Variation If AC were $19,000, CPI = $18,000 ÷ $19,000 ≈ 0.95 and CV = −$1,000, an overrun.
Reference Earned Value Management · Lesson 3: Performance Indices: SPI and CPI, and Judging Project Status
- Question 87
The project manager of a retail chain is building the budget for a two-year system overhaul. The project manager has created the WBS and, using past projects as a reference, produced a cost estimate for each work package. The organization's financial management policy states that the cost baseline includes contingency reserve but not management reserve. What work must the project manager still complete before determining the cost baseline?
Show answer and explanation
Correct answer: C
This is the Develop Budget stage of a predictive project. The organization specifies that the cost baseline includes contingency reserve but not management reserve, the WBS is built and every work package has a cost estimate. The question is which step is still missing before the cost baseline is determined.
The organization specifies that the cost baseline includes contingency reserve (PMBOK 8 allows the cost baseline to include or exclude contingency reserve depending on the organization), so the cost baseline is built up layer by layer from work package cost estimates plus contingency reserve. PMBOK 8 notes that contingency reserve can be provided at any level from the specific activity to the entire project. The work package estimates are already in place; what is missing is the contingency reserve for identified risks. So you must first set aside contingency reserve at the appropriate level and aggregate it in before you get the cost baseline, and the order cannot be reversed. The answer is C.
Why the other options are wrong
- A. Past projects can serve as a reference, but you cannot apply an old project's total to the current project, and this is not a required step in forming the baseline.
- B. Estimates and baselines are approved by the authorized body under organizational governance rules. They do not have to go to all stakeholders item by item, and this is not work that must come before aggregating the baseline.
- D. The project schedule is an input to Develop Budget, and the cost baseline must be time-phased. However, the stem gives no reason to revise scope or schedule; D combines two unsupported changes and does not replace the missing aggregation of contingency reserve.
Key takeaway Under the view that the cost baseline includes contingency reserve, cost baseline = work package cost estimates + contingency reserve (varies by organization); add the reserve at the appropriate levels before aggregating.
Variation If the stem went on to ask “what is added on top of the baseline to get the project budget?”, the answer is management reserve. If estimates stop at the planning package level, first roll the planning package estimates up to the control account.
- Question 88
In training material, the project management office wants to place predictive, adaptive and hybrid under one correct concept name. Which of the following MOST accurately describes a “development approach”?
Show answer and explanation
Correct answer: B
You must place predictive, adaptive and hybrid under one concept name and judge the most accurate description of a “development approach”. Four similar concepts have to be told apart.
A development approach is the means used to create and evolve a product, service or result during the project life cycle, such as predictive, adaptive or hybrid methods, and it defines how the project will be managed and executed. The three names in the stem answer exactly the question “by what means, and how is the project managed and executed?”, which corresponds to B. The answer is B.
Why the other options are wrong
- A. This is the definition of the development phase, the stage in the life cycle where deliverables are actually created and tested. It is a division of time, not a method.
- C. These are the Focus Areas, which group project management actions into initiating, planning, executing, monitoring and controlling, and closing. It is a classification of actions.
- D. This is a phase gate review, which checks applicable criteria and may decide to continue, continue with modification, end, remain, repeat, or park the project. It has nothing to do with a development approach.
Key takeaway A development approach is a means, a development phase is a span of time, Focus Areas are a classification of actions, and a gate is a review point.
Variation If the option were changed to “a grouping of project management actions into five categories”, the answer would become Focus Areas. If it were changed to “the phase where deliverables are actually created and tested”, the answer would become the development phase.
- Question 89
A company's operating model transformation project is run with a hybrid approach. While reviewing the budget allocation for each phase, the project manager is told by senior leaders that no additional funds will be approved. With no extra funds available, what should the project manager do?
Show answer and explanation
Correct answer: D
In a hybrid transformation project, the total funding is locked and senior leaders have clearly said that no more will be added. What should the project manager do?
The key signal is “no additional funds will be approved”. When the total is fixed, you can borrow the agile value orientation: allocate the limited budget first to the deliverables with the higher business value for the organization, so as to maximize project value. PMBOK 8 stresses that the Finance performance domain aims to deliver maximum value to the organization, and the budget is the primary financial constraint. The ranking criteria should be transparent and accepted by the sponsor and key stakeholders to avoid later disputes. The answer is D.
Why the other options are wrong
- A. External procurement costs money too. It does not address the cap on total funding and only confirms who pays, not how to allocate.
- B. Senior leaders have already said no more money will be added. Dividing funds equally ignores value, dependencies, and the actual funding needs of each phase, so it does not maximize project value.
- C. Doing small items first and leaving large ones until the end ranks by size rather than value, and the most important deliverables may end up without funding.
Key takeaway When funds cannot be increased, allocate the budget first to deliverables with higher business value.
Variation If senior leaders said “some additional funds are possible”, first quantify the gap and submit a change request, rather than directly re-ranking by value.
Reference Cost Baseline and Reserves · Lesson 4: Financial Constraints and Budgeting in Agile Environments
- Question 90
A smart-door-access installation project has a planned duration of 24 months. In month 12 the project manager is reassigned and you take over. The handoff materials show that, to date, the value of the work that should have been completed according to the plan is $420,000, the value of the work actually completed is $390,000, and cumulative spending is $410,000. What is your assessment of the project's current status?
Show answer and explanation
Correct answer: B
The project manager takes over a project in progress. The handoff materials give three figures in words; they must first be mapped to PV, EV and AC before judging status.
“The value of the work that should have been completed according to the plan” is PV = $420,000; “the value of the work actually completed” is EV = $390,000; “cumulative spending” is AC = $410,000. Schedule compares EV with PV and cost compares EV with AC, and the two judgments are independent: the project is behind schedule and over budget, meaning spending exceeds the value of the work completed and the project is behind schedule. The answer is B.
- Translate: PV = $420,000, EV = $390,000, AC = $410,000
- SV = EV − PV = $390,000 − $420,000 = −$30,000, behind schedule
- CV = EV − AC = $390,000 − $410,000 = −$20,000, over budget
- Check: SPI = $390,000 ÷ $420,000 ≈ 0.93 and CPI = $390,000 ÷ $410,000 ≈ 0.95, both below 1. The answer is B
Why the other options are wrong
- A. This compares AC of $410,000 directly with PV of $420,000 and concludes that spending is below plan. Cost must be judged by comparing EV with AC.
- C. This reads the schedule variance sign backwards (PV − EV = +$30,000) and concludes the project is ahead of schedule.
- D. Both variance signs are reversed (PV − EV = +$30,000 and AC − EV = +$20,000), the opposite of the real situation.
Key takeaway Map the words to PV, EV and AC first, then compare EV with PV and with AC.
Variation If cumulative spending were $380,000, CV = $390,000 − $380,000 = +$10,000, under budget, and the status would become “behind schedule, under budget”.
- Question 91
A project manager is writing internal training material on the PMBOK 8 framework. A colleague suggests listing “quality” as a separate performance domain alongside the other performance domains. How should the project manager respond?
Show answer and explanation
Correct answer: B
A colleague suggests making “quality” a separate performance domain alongside the others. You must know how the seven PMBOK 8 performance domains are made up and decide where quality belongs.
PMBOK 8 has seven performance domains: Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk. Quality is not among them. Quality has not been listed on its own: deliverable quality and verification belong to the Scope performance domain, handled through Monitor and Control Scope and Validate Scope to make sure deliverables meet requirements, standards, and specifications; Manage Quality Assurance (process quality assurance) belongs to the Governance performance domain. The colleague’s proposal does not match the PMBOK 8 structure, and the project manager should point out that PMBOK 8 has no quality performance domain and explain where the quality content sits. A memory aid: you will not find a separate “quality” among the seven performance domains; deliverable quality is under Scope and process quality assurance is under Governance. The answer is B.
Why the other options are wrong
- A. Treating quality as an eighth, independent performance domain does not match the seven performance domains of PMBOK 8.
- C. Quality was not folded into the Governance performance domain as a whole: only Manage Quality Assurance belongs to Governance, while deliverable quality and verification still belong to the Scope performance domain (Monitor and Control Scope, Validate Scope).
- D. PMBOK 8 does not merge quality with risk; the Risk performance domain has its own content.
Key takeaway The seven performance domains are Governance, Scope, Schedule, Finance, Stakeholders, Resources, and Risk; there is no quality performance domain, deliverable quality and verification belong to Scope, and Manage Quality Assurance belongs to Governance.
Variation If asked “which performance domain does communication belong to,” the answer is Stakeholders. For “procurement,” it is placed in an appendix as additional content and is not a separate performance domain.
- Question 92
A project's cost curve shows a trend toward breaking through the cost baseline, but the project has not actually gone over yet. To manage the budget well, what should the project manager do FIRST?
Show answer and explanation
Correct answer: A
The project is in execution and monitoring. The cost curve shows a trend toward breaking through the cost baseline, but no actual overrun has occurred yet. The first step in managing the budget must be identified.
A trend is not yet an overrun that has happened, and neither its cause nor its size is known. After a variance or trend appears, the first step is analysis: compare against actual costs to find where the variance comes from, how large it is and whether it will persist. Only then can you decide whether to correct, prevent, or change the baseline. So first convene the team, analyze actual costs and find the cause. The answer is A.
Why the other options are wrong
- B. The overrun is only a trend, and its cause and size have not been established. Announcing an outcome to stakeholders now is neither accurate nor calm; notify them after analysis and a forecast are available.
- C. Adding budget means changing the baseline, which goes through change control. Asking for money before the cause is understood means you do not know how much to ask for, or whether to ask at all.
- D. When a trend appears, the project manager first acts within their authority under the financial management plan. The sponsor is brought in only when the matter exceeds that authority, meets escalation criteria, or needs a governance decision.
Key takeaway When a cost variance or trend appears, analyze the cause first, and only then talk about notification, change requests or asking for help.
Variation If cumulative cost has already exceeded the control threshold, the overrun has become an issue: analyze the variance and its root cause promptly, record and handle it according to the governance arrangements, and take corrective action or submit a change request if needed.
- Question 93
To launch a new product before the year-end promotion season, the operations department requires the project to go live earlier than planned. The project manager hires two additional engineers for a critical task. Which technique is the project manager using?
Show answer and explanation
Correct answer: B
To launch a new product before the year-end promotion season, the operations department requires an earlier go-live, and the project manager hires two additional engineers for a critical task. The question is which technique this is.
The stem gives the goal (an earlier go-live) and the means (hiring additional people for a critical task). Crashing adds resources to get a shorter duration for the least incremental cost; in short, you pay money to buy time. Hiring additional engineers for a critical task fits that definition, and cost will rise. Resource smoothing, fast tracking and resource leveling do not work by adding people. The answer is B.
Why the other options are wrong
- A. Resource smoothing adjusts activities within their float to even out resource demand. It does not change the critical path and cannot bring the delivery forward.
- C. Fast tracking turns sequential activities into parallel ones. The stem has no overlapping of activities; the means is adding people, which is crashing.
- D. Resource leveling adjusts dates according to resource constraints and often lengthens the duration, the opposite of what an earlier go-live requires.
Key takeaway Adding resources to a critical task in order to finish earlier: crashing.
Variation If the scenario were starting development before the design is finished, it would be fast tracking. If you must judge why the duration did not shorten, check whether the added resources were on the critical path.
Reference Crashing vs. Fast Tracking · Lesson 1: Schedule Compression Basics and Crashing
- Question 94
PMLyceum plans to cut over its inventory management system from the old system to the new one over a weekend. Several key stakeholders believe the cutover may take longer than planned. What should the project manager do?
Show answer and explanation
Correct answer: B
The weekend cutover of the inventory system has not happened yet. Key stakeholders think it may overrun the time window, and the question asks what the project manager should do.
“Believe it may take longer than planned” is a clue to a risk. It is not a problem that has already occurred, and no data confirms it. The order in risk management is to assess first and respond afterward: find out the probability that the cutover overruns the window and what consequences that would have, and then choose to add people, extend the window or take other action. Changing the plan or the schedule without an assessment is acting by reflex. The answer is B.
Why the other options are wrong
- A. Adding people is a response. Changing the plan before assessing means you do not know how big the problem is, and you may add cost for nothing.
- C. The risk management plan is a guiding document. The stem does not say the plan itself is flawed, and the answer for a specific risk is not in the plan, so reviewing the plan does not address the concern.
- D. Extending the window directly is also a response made without assessment. The concern has not yet been verified with data, and changing the window may disturb the business downtime arrangements.
Key takeaway When you hear “something may go wrong”, assess its probability and consequences first, then choose a response. Do not change the plan directly.
Variation If the stem said “the cutover has already overrun”, the risk has become an issue and action should be taken immediately. If it said “the probability of overrunning the window has been assessed as very high”, the next step would be Plan Risk Responses.
- Question 95
In the network diagram of a trade-show preparation project, Activity P takes 4 days. Activity Q starts after P finishes and takes 8 days. Activity R also starts after P finishes and takes 5 days. Activity S can start only after both Q and R are finished and takes 3 days. What are the critical path and the shortest total duration of the project?
Show answer and explanation
Correct answer: D
Trade-show preparation project: P takes 4 days; Q follows P and takes 8 days; R follows P and takes 5 days; S follows both Q and R and takes 3 days. All relationships are finish-to-start. The question asks for the critical path and the shortest total duration.
Two paths run from P: P→Q→S and P→R→S. Q and R are parallel, so only the longer path counts toward the total duration. The critical path is the path with the longest sum of durations, so it is P→Q→S, and the shortest total duration is 15 days. The answer is D.
- P→Q→S = 4 + 8 + 3 = 15 days
- P→R→S = 4 + 5 + 3 = 12 days
- The critical path is the longer one: P→Q→S, duration 15 days
- Total float of R = 15 − 12 = 3 days (R is 3 days shorter than Q)
Why the other options are wrong
- A. 12 days is the length of the shorter path P→R→S. This takes the shortest path for the critical path; the critical path is the longest one.
- B. The path is right, but the duration adds all four activities: 4 + 8 + 5 + 3 = 20 days. Q and R run in parallel, so only the longer one counts.
- C. The 15 days is correct, but P→R→S is only 12 days, so the duration and the path do not match.
Key takeaway The critical path is the longest path: list the paths, add up each one, and for parallel activities count only the longer one.
Variation If R's duration were changed to 8 days, both paths would be 15 days. Both would be critical paths, and neither would have float.
Reference Critical Path Method · Lesson 2: Forward Pass and Backward Pass: The Seven-Box Node and a Step-by-Step Example
- Question 96
An agile team is developing an online medical-appointment platform. The work of the sixth Sprint is done, and stakeholders rated the features delivered in this Sprint very highly. The team will hold a Sprint Retrospective on Tuesday to inspect itself. As the Scrum Master, what is your role in the meeting?
Show answer and explanation
Correct answer: B
An agile team has completed its sixth Sprint, and stakeholders rated it very highly. The team will hold a Sprint Retrospective on Tuesday, and the question asks what the Scrum Master's role in the meeting is.
The Sprint Retrospective is an internal meeting in which the Scrum Team examines how it works and makes an improvement plan, and everyone attends. The Scrum Master, like the other members, identifies areas for improvement and helps make the improvement plan, while also helping the team understand and use the meeting's rules, such as the timebox and the division of roles. The answer is B.
Why the other options are wrong
- A. Answering stakeholders' questions about the Increment is something the team does at the Sprint Review, not part of the Sprint Retrospective.
- C. Discussing what specific work to do next belongs to revising the backlog after the review and to the next Sprint Planning. The Sprint Retrospective is about improving how the team works.
- D. The Sprint Retrospective is the team inspecting itself. The Scrum Master's duty is to serve the team, not to represent stakeholders and relay requirements.
Key takeaway In the Sprint Retrospective the Scrum Master is an equal participant and also helps the team use the meeting's rules well.
Variation If the question asks for the main purpose of the Sprint Retrospective, the answer is to plan ways to increase quality and effectiveness. If it asks who participates, the whole Scrum Team does, inspecting its own Sprint.
- Question 97
The project manager of a data platform migration project is developing the project's governance approach. Several of the procedures he plans to use are inconsistent with policies set by the project management office (PMO), but he believes they are necessary for this project given the particularities of the technology. What should the project manager do?
Show answer and explanation
Correct answer: B
On a project, the project manager is developing the governance approach, and the procedures he wants to use are inconsistent with PMO policy, but he believes they are necessary. What should the project manager do?
A PMO can play a vital role in reviewing and approving project governance and tailoring, with the specific approval authority depending on the organization's governance arrangements. The project manager should not deviate from PMO policy on his own. Since he believes the procedures are genuinely necessary for this project, the right approach is to take the proposed procedure adjustments to the PMO, explain the technical particularities, and consider a change together if needed. That protects the project's real needs and respects the organization's governance requirements. The answer is B.
Why the other options are wrong
- A. Organizing stakeholders to push for a policy change and asserting that the proposed procedures are better, before discussing the conflict with the PMO, escalates the disagreement prematurely. The project manager should first explain the project's special needs to the policy owner and jointly assess whether an adjustment is warranted.
- C. Acting first and notifying afterward is telling the PMO after the fact. It skips the PMO's review and approval and violates the PMO's policy requirements.
- D. Dropping his procedures entirely means not expressing his professional judgment. When the project truly has special needs, he should seek an adjustment through discussion.
Key takeaway When project procedures conflict with PMO policy, go to the PMO to discuss. Do not change the policy yourself or act first and report afterward.
Variation If the question asked “The company is transforming to agile. What should the PMO focus on?”, the answer is moving from control to enablement and coaching. If it asked how a PMO oversees projects under a hybrid approach, the answer is lightweight oversight at the iteration rhythm, not copying the multi-level approvals of predictive projects.
- Question 98
A project manager leads a cross-functional team in a requirements workshop and finds that several members think this change is unnecessary, which is hurting the results of the discussion. How should the project manager handle it?
Show answer and explanation
Correct answer: A
A project manager leads a cross-functional team in a requirements workshop, and several members think the change is unnecessary, which hurts the results of the discussion. This is a question of members' buy-in to the change, and it lies within the project manager's authority. The question is how to handle it.
Members doubting whether the change is necessary is a form of resistance to change. The project manager should first communicate with these members, learn their specific concerns and involve them in the discussion, so that the doubts can be resolved in a targeted way and agreement won. Agreement is built in conversation; it is not obtained by announcement or by escalation. The answer is A.
Why the other options are wrong
- B. The members' doubts are within the project manager's own authority, so there is no need to escalate to the sponsor, and a review of the charter would not address their concerns about whether the change is necessary.
- C. The members do not lack knowledge of the objectives; they cannot see how the change relates to them. Merely restating the objectives has limited effect and does not listen to their views.
- D. An explanatory email is one-way. It does not listen to the members' concerns, loses the chance to reach consensus in face-to-face discussion, and may be seen as avoiding dialogue.
Key takeaway When members question a change, first communicate to learn their concerns and win agreement; do not rush to escalate or lecture one way.
Variation If after the conversation the members' concerns prove valid, for example the change proposal itself has a flaw, feed the comments back to whoever proposed it and evaluate whether to adjust the change.
Reference Organizational Change · Lesson 1: Projects and Organizational Change: Understanding Resistance
- Question 99
When carrying out a performance review of an outsourced supplier, what does the project manager mainly base the evaluation of its performance on?
Show answer and explanation
Correct answer: C
On a project, the buyer carries out a performance review of a contracted outsourced supplier. The question asks what the evaluation of its performance is mainly based on.
A performance review measures, compares and analyzes the seller's performance on quality, schedule and cost against the agreement during monitoring and controlling procurements. PMBOK 8 Appendix X4 notes that effective contract management ensures the seller meets its obligations, and the seller's obligations come from the contract. So the basis is the quality, schedule and cost requirements agreed in the contract. Only when the contract is the yardstick does the result carry weight and leave the supplier no room to dispute it. The answer is C.
Why the other options are wrong
- A. A price promised at bidding reflects only price. Evaluating performance requires all the requirements in the contract, not just the bid price.
- B. The industry average can serve as a reference, but the supplier's performance obligations come from the contract, and the level of other firms does not bind it.
- D. Subjective impressions lack data, will not convince the supplier, and do not match the practice of measuring and comparing against the agreement.
Key takeaway Evaluate supplier performance against the quality, schedule and cost requirements in the contract, comparing data, not impressions or industry averages.
Variation If the contract does not state a particular performance requirement, you cannot evaluate against it, and it must first be added through a contract change.
Reference Monitoring and Controlling Procurements · Lesson 2: Performance Reviews, Inspections and Procurement Audits Compared
- Question 100
A project manager needs to win the support of a leader at an external partner organization (a key stakeholder) who does not report to him. Which source of power produces influence that is both effective and lasting?
Show answer and explanation
Correct answer: D
A project manager needs to win the support of a leader at an external partner (a key stakeholder) who does not report to him. The question asks which source of power produces influence that is both effective and lasting.
An outsider is beyond the project manager’s jurisdiction, so neither position nor penalties work. Expert power comes from knowledge and capability and rests on the other person’s respect and trust. It does not depend on position or punishment, it works on people outside one’s reporting line, and it lasts (the classification of power types is common exam practice). For an external key person whose voluntary support is needed, this kind of influence is the most dependable. The answer is D.
Why the other options are wrong
- A. Coercive power forces compliance through penalties, which breeds resistance, cannot produce lasting support and does not apply to outsiders.
- B. Positional power rests on a formal position, and a leader at an external partner is outside the project manager’s jurisdiction, so it has no effect on him.
- C. Connection power as described here, using connections with senior leaders to apply pressure, yields only momentary compliance; the other person feels pressured and the support does not last.
Key takeaway To influence people outside your authority, the influence that comes from professional capability lasts longest.
Variation When influencing one’s own subordinates, positional and reward power can be combined, but in the long run respect still has to be earned through expertise.
Reference Leadership Styles · Lesson 6: Power and Influence: Getting Things Moving Without Authority
- Question 101
A company's server room renovation project is being implemented. The equipment engineer tells the project manager that, because of a technical misjudgment, several required materials were not included in the budget. How should the project manager have avoided this?
Show answer and explanation
Correct answer: B
The server room renovation is under way, and the equipment engineer says that a technical misjudgment left out required materials. The question asks how this should have been avoided, a judgment about prevention beforehand.
The wording “should have” points to a measure taken beforehand. The root of an omission is that the estimating stage did not identify all the materials and costs needed. When developing the estimate, referring to the experience and historical data of similar past projects helps identify materials and costs that were previously required and, among the given options, best reduces omissions at the source. The answer is B.
Why the other options are wrong
- A. The sponsor is responsible for funding approval and high-level support and does not check materials detail, so cannot prevent an omission caused by a technical misjudgment.
- C. Known required materials belong in the cost estimate, and excess reserves cannot substitute for complete estimating. Moreover, “coping with all uncertainty” is both unrealistic and ties up too much funding.
- D. Updating the budget before the next phase is a remedy after the fact and does not meet the requirement of avoiding the problem in advance.
Key takeaway Avoid omissions by consulting historical data and similar projects beforehand, not by patching afterward and not by over-reserving.
Variation If the stem asked “what do you do after finding an omission”, the answer would become assess the impact and go through change control; if it asked “how can you confirm the estimate is complete”, check item by item against the WBS and have experts review it.
- Question 102
PMLyceum’s in-vehicle software project is at mid-execution. Looking through the risk register, the project manager finds that every score entered by the risk owners is “low”, and no new risk has been added in three months, yet more and more technical obstacles are surfacing at the phase-gate review. The team seems to be avoiding reporting bad news. What should the project manager do?
Show answer and explanation
Correct answer: C
The in-vehicle software project is at mid-execution. Every score in the risk register is “low” and no new risk has appeared in three months, while more and more technical obstacles appear at the phase-gate review. The team seems to be avoiding bad news. The question asks what the project manager should do.
A register that stays all “low” while real problems grow means the owners are not reporting honestly. The Eighth Edition notes that an accountable leader, with integrity, honesty and fairness as values, shows honesty by passing on bad news early and making sure status reports reflect the real progress of the project. The project manager should build a culture in which risks can be reported candidly and members know that exposing a risk will not bring blame; only then will the risk information be true. The answer is C.
Why the other options are wrong
- A. Assessing all the risks alone bypasses the owners who know the situation best. The information stays distorted, and it also goes against the practice that risk management needs the team’s participation.
- B. Fewer reports and risk meetings make risks surface even later, and the team’s tendency to avoid reporting does not change in any way.
- D. Raising every score uniformly rests on no facts. The data is still distorted, and it does nothing about why members dare not report honestly.
Key takeaway When risk information is distorted, the root cause is culture: create an environment where people dare to report candidly, rather than scoring for them.
Variation If the risk scores are honest but the response is inadequate, improve the risk response plan, not the culture.
Reference Project Management Principles · Lesson 2: Embed Quality Into Processes and Deliverables; Be an Accountable Leader
- Question 103
A company launches a 30-month software modernization project. After a fiercely competitive procurement, a consulting firm wins the contract. The company sponsor asks the buyer's project manager why the contract with the consulting firm was signed for only 12 months and does not cover the full 30 months. The project manager finds that an unplanned second tender is needed to keep the service going until the project ends. To avoid this, what should the project manager have done?
Show answer and explanation
Correct answer: D
The contract term covers only part of the project, so an unplanned second tender is needed. The question asks what should have been done beforehand to avoid it.
The signal is a buyer-side 30-month project covered by only a 12-month contract, followed by an unplanned re-tender. The procurement management plan did not cover all relevant procurement needs and key procurement activities across the project life cycle, and the contract term and phasing were not confirmed through the applicable governance arrangements. Preparing a phased procurement management plan covering all relevant procurement activities and obtaining the required governance confirmation would expose the gap early. The other options are either after-the-fact fixes or unrelated to the problem. The answer is D.
Why the other options are wrong
- A. The client can take part in key decisions, but having it join every round of negotiation and approve in advance is unnecessary and does not ensure the plan covers all the work.
- B. Negotiating the second contract only after the first is signed is a remedy after the problem arises. It prevents nothing, and it presumes the project continues with this firm.
- C. Agreeing on how often to report is only a communications arrangement. It has nothing to do with the contract term being too short.
Key takeaway The procurement management plan should cover the procurement needs, required contract periods and key procurement activities over the whole project life cycle and be reviewed by the relevant stakeholders under the project's governance arrangements; that is how to avoid an unplanned second tender.
Variation If the stem asked who is responsible for outsourcing and what their duties are, the answer would still be the procurement management plan; if it asked for a detailed description of the item procured, the answer would be the statement of work.
- Question 104
An e-commerce team is building a recommendation system and moves into the feature implementation phase after the framework is set up. The team reviews its burndown chart and finds that setting up the framework took longer than expected; at this rate, delivery of the features will be 5 days late. As an agile management professional, how should you help the team?
Show answer and explanation
Correct answer: B
On an agile project, the framework is set up and the team has moved into feature implementation. The burndown chart shows that the framework took longer than expected, and at this rate feature delivery will be 5 days late. The question asks how to help the team.
The burndown chart has already exposed the variance, and the next step follows the principles of transparency and adaptation: negotiate early and face to face with the product owner and stakeholders. They can choose to push out the delivery date or reduce the scope. The product owner listens to stakeholders and is responsible for the content and ordering of the product backlog, while business constraints such as the delivery date are negotiated with the relevant stakeholders. The team's responsibility is to lay out the facts and the options. A delivery commitment reached this way is reasonable and does not sacrifice the team's sustainable pace. The answer is B.
Why the other options are wrong
- A. Waiting until delivery is near gives stakeholders no time to adjust and only causes greater dissatisfaction. It goes against transparency.
- C. Cutting features is a decision for the product owner and stakeholders. The agile coach is a servant-leader role and has no authority to cut scope on his own initiative.
- D. Continuous overtime is not sustainable, harms quality, and does not change the team's real velocity, so the 5-day variance remains.
Key takeaway If the chart shows the team falling behind, negotiate early with the product owner and stakeholders to delay or reduce scope.
Variation If stakeholders insist the date cannot move, negotiate cutting low-priority scope, still without overtime. If only a single iteration is behind, the developers negotiate with the product owner and, without endangering the iteration goal, move low-priority stories out of the iteration and back into the product backlog, where the product owner reorders them.
- Question 105
A project manager runs a port expansion project. All senior managers attended the phase 1 status meetings. After the project moves into phase 2, one senior manager asks to receive project status information before each status meeting. What should the project manager do?
Show answer and explanation
Correct answer: D
The port expansion project has entered phase 2, and a senior manager asks to get project status information before each status meeting. The question asks what the project manager should do.
“Receive status information before the meeting” is a new communication requirement. The communications management plan contains stakeholders' communication requirements, so when a requirement changes, first talk with the manager to learn what information is wanted, when and in what form, then choose a suitable communication method and update the communications management plan, and then carry it out according to the plan. If this step is skipped, choosing email, mass sending or having members report separately may not match the form and timing the manager really wants, and may also produce inconsistent figures. The answer is D.
Why the other options are wrong
- A. “You can get it at the meeting” ignores the manager's new requirement and is a passive response.
- B. Email is a specific method and should be decided after the need is understood; at this point it is not even clear what content the manager wants.
- C. Having members send information separately also fixes the method before the need is clear and with no plan to rely on, and it would produce inconsistent figures.
Key takeaway When a communication need changes: first understand the need, then choose a communication method and update the communications management plan.
Variation If it changed to “a senior manager asks for the report to become a one-page summary,” the line of thought is the same: confirm the need first, then update the plan. If the request goes beyond the project's scope, evaluate it first and then decide whether to accept it.
- Question 106
A supermarket chain group launches a store inventory management system project, and the project charter has just been approved. In identifying stakeholders, the project manager finds that the group's president both cares a great deal about whether the project succeeds and holds final decision authority. According to the power/interest grid, how should the project manager manage the president?
Show answer and explanation
Correct answer: B
A supermarket chain group launches a store inventory management system project, and the charter has just been approved. The project manager finds the group's president both cares greatly about success and holds final decision authority. The question asks how to manage the president according to the power/interest grid.
Break down the stem first: “cares a great deal about whether the project succeeds” is high interest, and “holds final decision authority” is high power. High power and high interest fall in the “manage closely” cell of the grid (the four strategy names are a common exam term). Invest the most effort, communicate closely and manage the president's expectations. People in this cell can drive the project and can also bring it down, so you cannot skimp on communication. The answer is B.
Why the other options are wrong
- A. Keep satisfied is for people with high power and low interest. The president's interest is high, and merely “keeping satisfied” would leave a highly concerned person without enough involvement.
- C. Keep informed is for people with low power and high interest. The president has the highest power, and merely reporting progress without managing closely would let go of the person who most needs to be won over.
- D. Monitor is for people with low power and low interest. The president is high on both, so just watching their moves would seriously underestimate their influence on success or failure.
Key takeaway High power and high interest mean manage closely; judge the two dimensions first and then place the person.
Variation If the president has high power but does not care about project details, place them in keep satisfied: ensure they do not become a roadblock at the approval stage, and give regular brief reports.
- Question 107
A project manager is responsible for a complex project, and the team is communicating with stakeholders to reach a consensus on the project scope. Several key stakeholders hold different views on whether certain deliverables are in scope, and the project boundary and acceptance conditions remain unclear. To settle the detailed scope description, what should the project manager do?
Show answer and explanation
Correct answer: B
A complex project is defining scope. Several key stakeholders hold different views on whether certain deliverables are in scope, and the boundary and acceptance conditions cannot be settled. The question asks how to settle the detailed scope description.
One tool for Define Scope is facilitation: bring together key stakeholders with different expectations and expertise and, in a workshop, reconcile their differences so that they form a cross-functional consensus on the deliverables and on the boundaries of the project and product. The obstacle in the stem is exactly a disagreement over the boundary with no consensus. The answer is B.
Why the other options are wrong
- A. The scope has not been settled yet. Leaving the dispute to later change management avoids what needs doing now, and a change management plan cannot substitute for consensus on scope.
- C. The project is already in Define Scope. The problem is disagreement over where to draw the boundary, not requirements that were never elicited, so eliciting again does not resolve the disagreement.
- D. If the team settles scope unilaterally and then informs stakeholders, it will not win the consensus of key stakeholders, and the result is easily overturned later, causing disputes.
Key takeaway When stakeholders disagree on the scope boundary, use facilitation to reach consensus; it is a tool of Define Scope.
Variation If the stem were changed to “choose among several technical options by scoring them on cost, risk and duration,” the answer would be multicriteria decision analysis; “turning a high-level product description into specific deliverables” would be product analysis.
Practice test or full mock exam: what is the difference?
- Free practice tests: 8 tests, the first with 120 questions and the others about 107 each, drawn from the 1,000 free questions (you may have met some while practicing by chapter), no login. Good for a quick self-check and for finding your weak domain.
- Full mock exams: 180 questions each, separate from the practice bank (none of them appear there), timed in 3 sittings like the real exam. Use them to judge whether you are ready. See the full mock exams.
Free PMP practice test: common questions
Is this PMP practice test really free?
Yes. There is no account and no email wall. All 107 questions and the full explanation of every answer are free, and your progress is saved in your browser.
How were the 107 questions chosen?
They come from the 1,000 free questions: 28 People, 49 Process and 30 Business Environment questions, covering 24 of the 26 tasks of the Exam Content Outline, with single-answer and multiple-answer questions. There are 8 free tests and no question appears in more than one of them. Once a domain runs out of free questions a test is a little shorter, and the count shown is the real one.
How long does the test take?
Timed mode follows the real exam's pace of 80 seconds a question, so 107 questions get 143 minutes. You can also choose untimed practice and take as long as you like.
How are multiple-answer questions scored?
A multiple-answer question counts as correct only when you select every correct option and nothing else. There is no partial credit, and an unanswered question counts as wrong.
Are these real PMP exam questions?
No. PMI does not release exam questions. Every question here is original, written to the Exam Content Outline, to practice the question styles and the reasoning.
What should I do after the test?
Take another of the free tests, keep practicing by chapter in the 2,876-question bank, or take one of the 10 full mock exams of 180 questions. Your score here is a practice signal, not a prediction of the exam result.
To study first, read the study guide; for the whole bank, practice by chapter.