Free PMP Practice Test 2: 108 Questions with Explanations
108 PMP sample questions, test 2 of 8 with no question repeated from the other tests: 28 People, 49 Process and 31 Business Environment, covering 24 of the 26 tasks of the Exam Content Outline. Timed mode gives 80 seconds a question, 144 minutes in all; or practice untimed. Every question has a full explanation: why the answer is right and what is wrong with each other option. When you submit you get your total score, your accuracy in each of the three domains and a readiness check.
Updated 2026-11-22 · aligned to the current Exam Content Outline and PMBOK Guide 8th Edition
Ready to start?
Your answers are saved in this browser, so you can refresh or come back later. No account needed.
You can read every question below before you start; the answer options unlock when you press Start.
- Question 1
A project manager has been assigned to run an equipment procurement project and a system upgrade project at the same time. The daily schedule is packed, but the project manager still wants to find time to collect lessons learned. What should the project manager do?
Show answer and explanation
Correct answer: A
One project manager is running two projects with a very full schedule and still wants to collect lessons learned. What has to be judged is when and how to collect them, not what to collect.
PMBOK 8 is explicit: knowledge management is not just documenting explicit knowledge for sharing, and it is not just obtaining lessons learned at the end of the project. The lessons learned register is created early in the project and then updated throughout; each phase review and each iteration retrospective is a collection point. However busy the project manager is, lessons should be recorded at a regular rhythm from initiation onward, even if each session takes only a short time. So the answer is to record lessons learned at regular intervals from initiation to the end, which is A.
Why the other options are wrong
- B. Summing up only when each project closes means the details from along the way are long forgotten and later phases cannot use the lessons. This is exactly the “only at the end” misunderstanding that PMBOK 8 rejects.
- C. The issue log records only problems that have occurred, while lessons learned also include successful practices and realized risks and opportunities. Compiling old logs is also after-the-fact work, not continuous collection.
- D. Archiving preserves files, but the files do not necessarily contain lessons, and lessons do not come only from files; they come mostly from people's practice and reflection. Archiving cannot replace summing up.
Key takeaway Collect lessons learned continuously from initiation onward; do not leave them for a summary at closing.
Variation If the register is still empty, organize the team to fill it in, unify the format and file it in the lessons learned repository. If the project advances in iterations, lessons can be collected in each iteration's retrospective.
- Question 2
A customer service system outsourcing contract expires next week. At acceptance, a small number of defects are found that have not been fixed. The contract provides that the deliverables must be confirmed by the buyer to be defect-free before the contract can be closed. What should the project manager do?
Show answer and explanation
Correct answer: C
The contract is about to expire but defects remain. The question asks what to do.
Signals: the contract expires next week, defects remain, and the contract says closure requires confirmation that there are no defects. Common exam practice: first check that all deliverables have been delivered and accepted, there are no open claims or invoices, and all final payments have been made; this is not an exhaustive list, and the contract and applicable closure requirements may add conditions. Remaining defects mean the conditions are not met, so require the supplier to fix them under the contract and, once this is confirmed, close formally. The answer is C.
Why the other options are wrong
- A. The contract explicitly requires confirmation of no defects before it can close. Expiry does not mean the closure conditions are met. Closing anyway breaches the agreed closure condition and may be read as accepting the defects, which affects later recovery.
- B. Paying the final amount before the defects are fixed weakens the buyer's payment leverage and, depending on the contract, may be treated as acceptance of defective deliverables.
- D. Fixing defects is already the supplier's obligation under the original contract. Signing a new contract would make the buyer pay extra for it.
Key takeaway Closing a procurement requires the conditions to be met: if defects are not fixed, have the other side fix them under the contract before closing.
Variation If the defect is a hidden one found only during the warranty period after acceptance, handle it with the seller under the contract. The contract is closed only when everything has been accepted, payments are settled and there are no open claims, and the contract administrator notifies the seller in writing.
- Question 3
On an agile project, the project lead notices that one team member has clearly lacked motivation recently, and this is starting to affect the mood of the whole team. How should the project lead improve the situation?
Show answer and explanation
Correct answer: D
On an agile project, a member has clearly lacked motivation lately and this is beginning to affect team morale. The project lead must act to improve the situation.
PMBOK 8 notes that a project team can use emotional intelligence to reduce tension and increase cooperation by identifying, assessing and controlling members’ sentiments, and that teams that succeed in developing team emotional intelligence tend to be more productive with lower turnover. A lack of motivation involves emotion and drive. Of the options, D is the only one that addresses people’s emotions and interactions: the project lead should invest effort in raising the team’s emotional intelligence and improving interactions, not avoid the problem or move the person away. The answer is D.
Why the other options are wrong
- A. The daily coordination meeting and the retrospective are how an agile team keeps transparency and improves continuously. Cutting them back contradicts agile practice and has no direct bearing on motivation.
- B. A long leave only postpones the problem, does not find out why he is demotivated and does not restore the team’s mood.
- C. Moving the member to another team avoids the problem rather than solving it. The cause is unchanged, and other members may take it as punishment, which damages their sense of safety.
Key takeaway Morale problems on agile teams are also improved through emotional intelligence and interaction; moving members away or cutting ceremonies does not help.
Variation If the stem made clear that the member is demotivated because of an excessive workload, the project lead should first adjust the amount of work selected for the iteration with the team.
Reference Leadership Styles · Lesson 3: Emotional Intelligence: The Four Areas and How to Use Them on Projects
- Question 4
A newly appointed project manager is to develop the communications management plan for a time-limited social media promotion project at a software company. This is the first major project since the company moved entirely to remote work. Going through the company's existing materials, the project manager finds a standard operating procedure (SOP) that specifies how all communication is to be carried out. For this project, the SOP is guidance rather than a mandatory requirement. What should the project manager do?
Show answer and explanation
Correct answer: B
During planning, a new project manager has to write a communications management plan and has the company's existing communication SOP at hand, while the company has just gone fully remote. The question asks how to handle the SOP.
An SOP is an organizational process asset and a usable input when planning communications, but it was written for past situations. This question has two signals: the project is a time-limited social media promotion with its own uniqueness, and the company has just gone fully remote, so the SOP's practices may no longer fit. The sensible approach is to assess the SOP's relevance to this project, shape communication arrangements that suit it within the tailoring the organization allows, and take the adapted arrangements to the stakeholders for their input before finalizing the plan. Mandatory provisions in the SOP must be followed, and if the SOP really has to be changed, request the change through the process the organization requires. That uses the existing asset and keeps the plan fitted to this project. The answer is B.
Why the other options are wrong
- A. Following the SOP first and then submitting each change to the change control board postpones the tailoring that belongs in planning into the change process. No baseline exists yet, so there is nothing to change, and any mismatch between the SOP and remote work would cause trouble from the start.
- C. Carrying an unsuitable SOP into execution as the base plan and fixing it later during monitoring is “wrong first, fix later.” Stakeholders would feel the communication problems early, and revision costs more.
- D. Ignoring the SOP entirely wastes an organizational process asset and may miss compliance or security requirements. Assets should be “assessed, then tailored and used,” not either copied wholesale or discarded.
Key takeaway An SOP and similar organizational process assets are inputs: assess their relevance, tailor them within what the organization allows, and consult the stakeholders before using them.
Variation If the SOP were a compliance requirement imposed by a regulator, its mandatory provisions would have to be followed, and only the remainder could be tailored within what is allowed.
Reference Plan Communications Management · Lesson 1: Plan Communications Management: Purpose, Inputs, Techniques and Outputs
- Question 5
A project manager has to decide the contract type while developing the procurement strategy. Which of the following is the main basis for choosing a contract type?
Show answer and explanation
Correct answer: D
The question asks for the main basis for choosing a contract type.
Choose a contract type mainly on three bases: whether the requirements and scope are clear, whether changes are likely, and which of buyer and seller bears the risk. They determine how the price is set and how the cost risk is shared. Among the other options, a seller’s reputation and quote are considerations in selecting a seller, and personal preference, length of the contract and purchase amount are not main bases. The answer is D.
Why the other options are wrong
- A. A seller’s reputation and quote are factors in selecting a seller. They do not decide whether to use a fixed-price, cost-reimbursable or time-and-materials contract, and the height of the quote is something compared when evaluating bids.
- B. Personal preference is not a basis. The contract type has to serve the actual circumstances and risk allocation of the project, not what the project manager happens to be familiar with.
- C. The purchase amount affects approvals and the intensity of management, but the length of the contract is not a basis, and the amount alone does not determine the contract type.
Key takeaway Choose the contract type by how clear the requirements are, how likely changes are and who bears the risk, not by preference. Choosing a contract type is in essence allocating risk between buyer and seller.
Variation If the question asked what is usually chosen when scope is unclear and risk is high, the answer is a cost-reimbursable contract; for a long performance period with fluctuating material prices, choose fixed price with economic price adjustment.
- Question 6
A water utility's pipe-network inspection data platform is under development. The client's contact asks that the platform also capture the manufacturer of each valve, saying the information is easy to look up, while the development team worries that this will push up cost. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
The client's contact asks that each valve's manufacturer also be captured, saying the information is easy to look up, while the development team worries about cost. The two sides disagree and the impact has not been assessed. What should the project manager do first?
On receiving a change request, clarify any missing content or reason with the person who raised it; once the request is clear, analyze its impact on scope, schedule and cost, and only then decide whether to submit it for approval. The contact's “easy to look up” and the team's “it will push up cost” are only opinions, with no data behind them. The answer is A.
Why the other options are wrong
- B. Approving without verifying or assessing skips the assessment and also bypasses the approval prescribed by the change management plan; updating the plan afterward turns the whole order upside down.
- C. The requirement has not yet been verified or its impact assessed, so it should not be submitted now. Later it should be submitted to the approver designated in the change management plan, and depending on the nature of the change, approval from the client or sponsor may also be needed.
- D. Whether it is worth doing depends on assessment; the team's worry about cost is an opinion, not a conclusion. Declining without assessing may mean missing a requirement that is valuable to the client at little cost.
Key takeaway Clarify any missing details in a change request, assess its impact, and then decide whether to submit it.
Variation If the contact confirms the requirement is critical and the impact is negligible, submit the change after assessment; if verification shows the client does not actually need it, there is no need to go on to the later steps.
Reference Change Control · Lesson 2: The Five-Step Change Handling Process
- Question 7
A new project manager takes over a server-room renovation project and finds that the predecessor privately promised the contractor orally to raise the mobilization advance payment from 15% to 25%, but the change was neither recorded in writing nor formally approved. The contractor now submits a payment application filled in at 25% and is waiting for a signature to release the money. How should you respond?
Show answer and explanation
Correct answer: D
After a change of project manager on a server-room renovation, the contractor applies for payment at the 25% advance rate that the predecessor orally agreed to. The new project manager must decide whether to sign.
Signal: the predecessor only “privately promised orally”, and now the new manager is asked to sign off the payment. A procurement change must be recorded in writing and formally approved before it is carried out, and an oral agreement cannot be the basis for payment, so payment stays at the percentage written in the contract. Note that the point is not that a contract can never be changed: to change it, go through change control and approve in writing. The answer is D.
Why the other options are wrong
- A. An oral agreement is not a basis for payment. The predecessor's personal promise cannot replace a written, approved contract change.
- B. Contract terms can be changed, but only through the change control procedure with written approval. The claim that they can “never be changed” is itself wrong.
- C. The point is not whether you personally know the background but that the change was never approved in writing. Even if you knew, the conclusion would be the same.
Key takeaway A procurement change must be recorded in writing and formally approved; an oral agreement cannot be the basis for payment.
Variation If the contractor produces a written change order that has been approved, pay at the changed percentage. If the contract contains no change procedure, the two parties should negotiate a supplementary clause.
- Question 8
There is only a small space on the wall of an agile team's office for showing project status. The team is hesitating between using a software tool the company already holds a perpetual license for, to show progress, and putting sticky notes and index cards describing the current work on the wall. What should the team be advised to do?
Show answer and explanation
Correct answer: D
The wall space for showing project status is small, and the team is hesitating between a software tool the company already has a perpetual license for and sticky notes plus index cards.
The answer depends on the features of an information radiator. PMBOK 8 stresses that it leans toward “low tech and high touch”, is maintained by hand by the team, is posted where people can easily see it, and is easy to update and updated often. Index cards and sticky notes fit this: they move easily, are visible at a glance, and show real-time status, and they can be arranged flexibly even in a small space. A software tool has to be opened in a system before anyone can see it, so it is less timely and less visible than cards on a wall. The answer is D.
Why the other options are wrong
- A. That the license is already bought means there is no cost issue, but it is not a basis for the choice. A software tool must be opened before it can be seen, so it is less immediately visible than handwritten cards.
- B. What other teams do may not suit this team. It should choose the display that works best for itself.
- C. Printed reports updated weekly are not real-time status and lose the benefit of the team updating things as they work.
Key takeaway Information radiators favor low tech and high touch: updated by hand and visible at all times.
Variation If the team were spread across several cities with no shared wall, an electronic board could take its place, but it would still need to keep both features: always up to date and visible to everyone.
- Question 9
The project schedule is ready for approval. The project manager needs to prepare a document for the customer representative that lists only the planned dates of the main deliverables and key external interfaces. Which of the following should be prepared?
Show answer and explanation
Correct answer: D
The schedule is awaiting approval. The project manager must prepare a document for the customer representative listing only the planned dates of the main deliverables and key external interfaces.
The PMBOK 8 glossary defines the milestone schedule as a type of schedule that presents milestones with planned dates, and the Gantt chart as a bar chart of schedule information. Common exam practice divides the schedule by level of detail into milestone, summary and detailed forms; a milestone schedule marks only the planned dates of the main deliverables and key external interfaces, which suits reporting to a customer. For this kind of question, look at the purpose of the document and its reader first: for a customer who needs only the main dates, use milestones; for management tracking progress, use a bar chart; to show the relationships between activities, use a network diagram. The answer is D.
Why the other options are wrong
- A. A Gantt chart uses horizontal bars to show each activity's planned start, finish and duration. It is more detailed than a milestone schedule that lists only the main dates, and it is often used to track activity progress for management.
- B. A detailed schedule network diagram shows the detailed logical relationships between activities. It is not a report that gives a customer the main dates.
- C. A work breakdown structure breaks the project scope down level by level by deliverable. It does not show planned dates.
Key takeaway Milestone schedule for the customer; bar chart for management; network diagram for activity relationships.
Variation If the customer wanted to see a bar for each work package's planned start and finish, use a Gantt chart (a bar chart of schedule information, per the PMBOK 8 glossary).
- Question 10
A company sets the risk threshold for the cost objective at ±8%, and risks beyond this threshold exceed the project manager's decision authority. After assessment, the project manager finds that an identified threat, if it occurs, would cause a 15% cost overrun, which is beyond the threshold. What should the project manager do?
Show answer and explanation
Correct answer: B
The company sets a cost risk threshold of ±8%. An identified threat, if it occurs, would cause a 15% cost overrun, exceeding the threshold. The question asks what the project manager should do.
The risk threshold measures acceptable variation around an objective and reflects the risk appetite of the organization and stakeholders. The threat's impact is 15%, greater than 8%, so it has crossed the threshold and can no longer be passively accepted at the current tolerance; and the stem states that such risks exceed the project manager's decision authority, so someone with authority must decide. Therefore escalate it and submit it to the sponsor and governance level for a decision. The answer is B.
Why the other options are wrong
- A. Choosing a strategy alone and reporting afterward oversteps authority. The risk has crossed the threshold, the decision does not belong to the project manager, and reporting afterward is no safeguard.
- C. Adding contingency reserve only inside the project means the team absorbs the risk itself, bypassing the requirement that a risk over the threshold be decided by those with authority, and the sponsor and governance level do not know.
- D. Logging and monitoring is too passive for a threat that has crossed the threshold. The risk is beyond the project manager's authority, and someone must decide and respond; it cannot just be watched.
Key takeaway When a risk crosses the threshold and exceeds the project manager's authority, escalate it to the sponsor and governance level for a decision.
Variation If the threat would cause only a 5% overrun, within the threshold, the project manager could choose a response strategy within delegated authority, with no need to escalate.
- Question 11
A team is writing several modules. Coding starts on the 6th of this month (a Monday) and needs 3 working days. After development, 2 working days are reserved for unit testing, and integration can start only after testing is finished; integration needs 3 working days. The team does not work on weekends, no other holidays are considered, and everything goes smoothly. Which conclusion holds?
Show answer and explanation
Correct answer: B
The three activities follow one another, and the team does not work on weekends. You must convert working days into calendar dates and identify the logical relationship.
Development takes 3 working days and runs from Monday through Wednesday. Testing takes 2 working days and runs Thursday and Friday. There is no work on the weekend. Integration takes 3 working days and runs the following Monday through Wednesday. So integration finishes on the 15th, and from the 6th to the 15th is 10 calendar days. The sum of the durations is only 3 + 2 + 3 = 8 working days. The answer is B.
- Development: the 6th (Monday), 7th and 8th; it finishes on the 8th
- Testing: the 9th (Thursday) and 10th (Friday); the 11th and 12th are the weekend
- Integration: the 13th (Monday), 14th and 15th (Wednesday); it finishes on the 15th
- From the 6th to the 15th inclusive is 10 calendar days; the sum of the durations is 3 + 2 + 3 = 8 working days
Why the other options are wrong
- A. Tuesday the 14th completes only the second day of integration. It is not done until Wednesday the 15th, so this misses the third day.
- C. 10 is the number of calendar days. The durations add up to 8 working days, so this mixes up elapsed calendar days with duration.
- D. “Integration can start only after testing is finished” is a finish-to-start relationship, not start-to-start.
Key takeaway Durations are counted in working days and must be pushed past weekends. When the next activity can start only after the previous one finishes, the relationship is finish-to-start.
Variation If the team also worked on weekends, development, testing and integration would run back to back and finish on the 13th, 8 calendar days in all, exactly the sum of the durations.
- Question 12
You are the agile team lead at a logistics software company. A new industry policy requires the product vision to be substantially adjusted, and the project goals change with it. How should you communicate these changes to the Developers on the team?
Show answer and explanation
Correct answer: C
During agile development, an external policy change forces a major adjustment to the product vision and project goals. The question asks how to communicate this significant change to the team members.
The agile principles stress that the most effective way of communicating is face to face. When the vision and goals change, the team has to understand what the change means for its work before the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities. Holding a team meeting to explain it in person lets you explain the background, check on the spot that everyone has understood, and answer questions. The answer is C.
Why the other options are wrong
- A. Forwarding the policy text by email is low-bandwidth communication and cannot ensure members understand what it means for the vision and goals.
- B. Having the leader change the plans and then tell the team to follow them is deciding for the team. In agile, the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities, after first understanding the change.
- D. Putting off the decision until the next release goes against the principle of timely adjustment, and the work being continued may no longer fit the new vision.
Key takeaway When the vision and goals change, first make sure the team understands face to face; then the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities.
Variation If members are spread across cities, still prefer a video meeting, which is close to face to face; if the change is only a minor scope adjustment within one iteration, communicating it at iteration planning is enough.
- Question 13
On a hybrid project at one company, some teams work in an agile way. The sponsor wants to keep the governance role of the project charter while also giving the agile teams ample room to make decisions. How should the project manager reconcile the charter with the agile teams’ authority?
Show answer and explanation
Correct answer: D
On a hybrid project, some teams use agile. The sponsor wants to keep the charter’s governance role and also give the agile teams ample room to decide. The question asks how to reconcile the two.
The charter’s job is to give formal authorization and set governance requirements, and the agile teams need to decide for themselves within boundaries. The way to join the two is for the charter to set the governance boundaries, such as objectives, scope boundary, budget and approval requirements, with teams self-organizing within those boundaries. This keeps authorization and governance without squeezing the team’s room. In choosing, hold on to two phrases: keep the governance role, and leave room for decisions. Only “boundaries plus self-organization” satisfies both; each of the other options satisfies one and loses the other. The answer is D.
Why the other options are wrong
- A. Cancelling the charter loses formal authorization and the governance boundaries, and does not meet the sponsor’s wish to keep the governance role.
- B. A charter that covers only ways of working drops the governance content such as objectives, approvals and exit criteria.
- C. A charter written as a detailed plan controls everything even inside the boundaries, leaving the team no room to decide, which goes against agile practice.
Key takeaway Hybrid projects: the charter sets the boundaries, and the team self-organizes within them.
Variation A purely adaptive project’s charter can be simplified to a one-page worksheet or a vision statement that answers questions such as why, who and what, and it still keeps its authorizing role.
- Question 14
A software outsourcing firm is building a membership app for a fitness chain. The team has just completed an iteration, and the product passed its acceptance checks, but it contains a “leaderboard” feature that nobody asked for. The team works in an agile way, and the product owner manages the backlog. The customer noticed the feature during the demo and worries that it brings new security risks. What should the project manager do to prevent this from happening again?
Show answer and explanation
Correct answer: A
A software outsourcing firm builds a membership app for a fitness chain. After an iteration the product passes its acceptance checks but contains an unrequested “leaderboard” feature, and the customer worries about security risks. The team is agile and the product owner manages the backlog. The question asks how to prevent a repeat, which is a preventive measure in an adaptive environment.
Adaptive projects manage scope through the backlog, and the product owner dynamically decides its content and priority in a flexible environment. The root cause of the unrequested feature is that the new content bypassed the product owner and never entered the backlog. To prevent a repeat, any new feature must first be assessed for value by the product owner, placed in the backlog and prioritized, and only then developed. The answer is A.
Why the other options are wrong
- B. Confirming the feature's value with the customer deals only with this one feature. It does not set up a mechanism to prevent a repeat or name who decides.
- C. Managing the scope baseline and eliminating external factors is a predictive mindset; agile teams manage scope through the backlog, and external factors were not the source of this problem.
- D. More frequent reviews can reveal problems sooner, but they cannot stop the team from adding features on its own. There is still no entry point for assessing new content.
Key takeaway To prevent gold plating in an adaptive project, make sure any new content is assessed by the product owner and placed in the backlog before it is developed.
Variation If, once assessed, the extra feature turns out to be valuable, the product owner can schedule it for a later iteration. If not, remove it, and review why the team added it on its own.
Reference Monitor and Control Scope and Scope Creep · Lesson 2: Scope Creep and Gold Plating: Two Ways Work Quietly Exceeds the Baseline
- Question 15
After attending an industry forum, the chairman of a logistics company asks the project manager to introduce blockchain traceability technology into the company's business. The idea has not been approved as a project, and nobody has assessed whether it is worth investing in. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
After an industry forum, the chairman of a logistics company asks the project manager to bring blockchain traceability into the business. There is only an executive's idea, and nobody has yet argued whether it is worth doing. The question is what the project manager does first.
Introducing a new technology means starting a new project, but at this point it has not even been decided whether to do it. Before a project begins, you first have to say why it is being done and whether it is worth the investment, and that is the business case. The sponsor is responsible for it, and the project manager helps by giving advice; it is the basis for starting the project. Collecting requirements and assigning resources normally wait until the project is approved and the charter issued. A SWOT analysis can support the business case but cannot replace it. The trap in this question is “first”: several options are things that really are done in a project, but only the business case comes at the very front, and it decides whether the later work begins at all. The answer is D.
Why the other options are wrong
- A. Eliciting and analyzing requirements takes place after the project is approved and the charter issued. It is not the first job at this point.
- B. Involving stakeholders and assigning resources are also work for after approval. At this point it has not even been decided whether to do the project.
- C. A SWOT analysis can support the justification, but it is only a tool for identifying internal and external factors. It cannot replace the business case and is not the first step now.
Key takeaway When an executive proposes a new idea, the first thing the project manager does is help prepare the business case.
Variation If the business case has been approved and the charter issued, then asking “what first?” turns the answer toward collecting requirements or identifying stakeholders.
- Question 16
A project manager is going to lead a group of remote members who each work independently. What should the project manager do to promote collaboration among the members?
Show answer and explanation
Correct answer: B
A project manager leads remote members who work independently and wants to promote collaboration among them. The key phrases are “work independently” and “among members.”
Collaboration requires interaction among members. PMBOK 8 suggests that virtual teams use audio, video and virtual conferencing capabilities for meetings and set up collaboration sites for working together. Promoting regular video meetings lets members talk directly, discuss in the moment and build a sense of belonging, which makes it an effective way to promote collaboration in a remote team. The answer is B.
Why the other options are wrong
- A. Putting everyone on every project email creates information overload and only has members receive information passively, so it cannot promote interaction.
- C. Calling each member separately every week is one-on-one communication between the project manager and an individual. Members still work on their own.
- D. Requiring daily task logs and progress updates is one-way recording and reporting with no interaction, so it cannot promote collaboration among members.
Key takeaway Remote members build collaboration through interactive communication such as regular video meetings. One-way email and logs will not do.
Variation If members need to edit the same document together, use a shared collaboration platform instead of passing the file back and forth by email.
Reference Virtual Teams · Lesson 3: Collaboration Tools and Remote Work: Equip the Team First, Then Agree How to Use the Tools
- Question 17
A project manager at a software company reviews a newly drafted schedule management plan. It specifies release timeframes and units of measure, but it does not say how schedule performance will be measured or how large a variance must be before action is taken. What should the project manager do?
Show answer and explanation
Correct answer: B
A schedule management plan has just been drafted. It already states release timeframes and units of measure, but it does not say how schedule performance is measured or how large a variance must be before action is taken. How should the gap be fixed?
The schedule management plan establishes the criteria for developing, monitoring and controlling the schedule. Typical contents include release and iteration length, level of accuracy, units of measure, control thresholds and rules of performance measurement. The stem already has two of these, and what is missing is exactly the rules of performance measurement (which rule is used to measure progress) and the control thresholds (how large a variance requires action). Both should be settled before the detailed schedule is built, so that later monitoring has rules to follow. They belong in the schedule management plan. The answer is B.
Why the other options are wrong
- A. Waiting for a delay before discussing how to monitor turns the rules into an after-the-fact fix. The purpose of a schedule management plan is to set the criteria in advance.
- C. The schedule baseline is the approved version of the schedule model and records planned dates for each activity. The allowed range of variance is a control threshold, usually written as a percentage deviation from the baseline parameters, not a number of days attached to each activity in the baseline.
- D. Monitoring rules are one of the things the schedule needs before it is built, so they should be set before the detailed schedule. If they are left until execution, nothing guides the team when a variance appears.
Key takeaway The schedule management plan says how the schedule will be managed, and the rules of performance measurement and control thresholds must be set before the detailed schedule.
Variation If what is missing is the length of each iteration in an adaptive project, add that to the schedule management plan too. If a variance is within the threshold, continue monitoring it; if it reaches or exceeds the threshold, follow the response action specified in the schedule management plan.
- Question 18
A cloud platform upgrade project has a problem: the deployment group and the test environment group are passing responsibility back and forth over “building the pre-release environment”, and no one can say who should deliver it. What should the project manager do next?
Show answer and explanation
Correct answer: D
The deployment group and the test environment group each push responsibility for “building the pre-release environment” onto the other, and no one can say who delivers it. When the project manager coordinates next, the key is to establish who is responsible.
Roles and responsibilities are written in the resource management plan, which sets out each role's responsibility, authority and competence. When people pass responsibility back and forth, return to the plan, check each group's role and responsibilities, draw the boundary accordingly, and have both sides confirm it in writing. If the plan does not say, propose and assess the change through the applicable change process; once authorized, add the responsibility, update the related documents, notify both groups, and implement it. The answer is D.
Why the other options are wrong
- A. The project scope statement describes what is to be delivered and the acceptance criteria. It does not assign which group is responsible.
- B. The WBS dictionary describes the content of work packages. Re-estimating workload does not answer “who is responsible” and does not stop the passing of responsibility.
- C. The integration overview in the project management plan is general content. Specific roles and responsibilities come from its subsidiary resource management plan, which is more direct.
Key takeaway When responsibility is unclear and people pass it back and forth, look at the roles and responsibilities in the resource management plan.
Variation If the review finds the plan itself does not say who owns “building the pre-release environment”, assess and obtain authorization for the change through the applicable change process, then update the responsibility assignment, notify both groups, and implement it.
Reference Responsibility Assignment Matrix and RACI · Lesson 1: Plan Resource Management: Resource Types, Hierarchical Charts and Roles and Responsibilities
- Question 19
During the planning phase of a logistics park construction project (predictive), the project manager has finished developing the schedule, but the key stakeholders have not yet approved it, and the team is pressing for tasks to be assigned. What should the project manager do?
Show answer and explanation
Correct answer: A
In the planning phase of a predictive logistics park construction project, the schedule has been developed but the key stakeholders have not approved it, and the team is pressing for tasks to be assigned. The question asks what the project manager should do.
PMBOK 8 states that the schedule baseline is a schedule model accepted and approved by the appropriate stakeholders, with baseline start dates and baseline finish dates. A plan before approval is only a draft, so the project manager should take the initiative to organize a review with the stakeholders, establish the schedule baseline only after approval, and then use it for monitoring and task assignment. The answer is A.
Why the other options are wrong
- B. Saving the draft as the baseline bypasses approval. A baseline can be established only through approval, and later changes go through change control; you cannot “use first, change later”.
- C. The team can provide input and should confirm that the dates have no conflicts, but the schedule baseline must be accepted and approved by stakeholders, and team agreement cannot replace that.
- D. The change control board approves changes to an existing baseline. Establishing the baseline for the first time is approved by the stakeholders and does not go through the change control procedure.
Key takeaway A plan that is not approved is not a baseline: push for approval first, then create the baseline.
Variation If the date has to be adjusted after the baseline exists, it must go through Assess and Implement Changes and integrated change control and cannot be changed verbally.
Reference Schedule Baseline and Monitoring the Schedule · Lesson 1: The Schedule Baseline and the Three Forms of the Project Schedule
- Question 20
Reviewing a draft equipment purchase contract, the project manager finds that the delivery clause says only “deliver on time” and states no delivery time, location or acceptance criteria. The contract has not yet been signed. What should the project manager do?
Show answer and explanation
Correct answer: A
The contract has not been signed, and its draft delivery clause is vague. The question asks what the project manager should do.
The signal: the contract is “not yet signed” and the delivery clause says only “deliver on time”. An agreement normally covers the deliverables, delivery location, inspection and acceptance criteria, delivery schedule and milestones, and so on. Before signing is when the buyer has the most negotiating power, so write the delivery time, location and acceptance criteria into the contract to avoid disputes later. The answer is A.
Why the other options are wrong
- B. After signing, the seller may not accept new requirements. Filling in later loses negotiating leverage, and the risk of disputes falls on the project.
- C. Deleting the delivery clause strips the buyer of its hold over delivery and makes disputes more likely.
- D. Reputation cannot replace a written agreement. Without a clear clause there is nothing to rely on in a dispute.
Key takeaway The delivery clause in an agreement must state time, location and acceptance criteria, and the gaps are filled before signing.
Variation If the vagueness were found only after signing, first assess the impact, then follow the contract change-control mechanism to negotiate the terms with the seller and obtain an authorized written amendment. If the question asked what to look at first in a dispute, the answer is the complete contract, including any statement of work it expressly references or incorporates; requirements not incorporated into the contract go through the contract’s change, claim or dispute-resolution mechanism. What the two have in common is that terms must be written clearly and gaps filled before signing, since filling them after signing loses negotiating leverage.
- Question 21
A team member on a smart-hardware development project reads a report on an industry news site that the project's main supplier may be in financial difficulty. The news is unconfirmed, and project delivery has not been affected. The member passes it on to the project manager. What should the project manager do?
Show answer and explanation
Correct answer: C
A team member on a smart-hardware project sees an industry news report that the main supplier may be in financial difficulty. The news is unconfirmed, delivery is unaffected, and the member tells the project manager. The question asks what the project manager should do, and the key is telling a risk from an issue.
The report says only that the supplier may be in financial difficulty, which is unconfirmed, and delivery has not been affected. An issue is a current condition or situation; here, whether the supplier really is in difficulty and what effect it would have on delivery are still uncertain events, so this is a risk, not an issue. PMBOK 8 defines a risk as “an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more portfolio, program, or project objectives.” An identified risk may or may not occur. Having identified the risk, the project manager should first add it to the risk register so it enters later analysis and response. The answer is C.
Why the other options are wrong
- A. Finding replacement vendors may be a later response, but the news is unverified and the probability and impact have not been assessed, so replacing the supplier is premature.
- B. Notifying the purchasing department to manage the supplier relationship hands off something that belongs to project risk management. Procurement can help, but the project manager must first bring the risk into management.
- D. The issue log records current conditions that exist now. This report is unconfirmed, and whether the supplier is in difficulty and what it means for delivery remain uncertain events that may happen, so logging it as an issue treats a possibility as fact.
Key takeaway A potential situation that is hearsay, unconfirmed and not yet affecting the project goes in the risk register, not the issue log.
Variation If the supplier had formally notified that it cannot deliver on time, it would be an issue: record it in the issue log and start the response; if the register already holds this risk, carry out its measures directly.
Reference Risk Register · Lesson 1: Identify Risks: Purpose, Characteristics and Handling New Risks
- Question 22
Several experienced senior members tell the project manager that he manages too closely and leaves them no room to do their work. The project manager realizes that his own micromanagement is the cause. What should he do?
Show answer and explanation
Correct answer: B
Several experienced senior members tell the project manager that he manages too closely and leaves them no room to do their work. He realizes that his own micromanagement is the cause. The question asks what he should do.
PMBOK 8 asks the project manager to be sensitive to team members’ willingness and ability to perform their work and to adjust his management and leadership styles as needed; organizations and teams with experience on a specific type of project may be more self-managing and require less leadership. Novices usually need clearer direction, coaching and some oversight, whereas checking every item for experienced members weakens motivation, creativity and trust. The root problem is a mismatch between style and audience, so the project manager should adjust his own style, give more trust and autonomy, and replace item-by-item checking with delegation plus support. The answer is B.
Why the other options are wrong
- A. A team-building activity only eases the atmosphere for a while. It does not change the root cause, over-close management, so it treats the symptom and not the cause.
- C. Asking how to be their mentor still puts him in the position of instructor and does not respond to the complaint of being managed too closely.
- D. Meeting every senior member daily to keep track of their work is essentially denser monitoring, a stronger form of micromanagement, and would only deepen the dissatisfaction.
Key takeaway When members say they are managed too closely, first adjust your own style: let go, keep checkpoints, and do not add more checking.
Variation If the team were newly formed novices who complained that “no one tells us what to do or guides us,” he should switch to directing plus coaching. The direction of the adjustment is always set by the team’s willingness and ability.
- Question 23
A project manager has just taken over a development project for smart home devices. The WBS has been built and the activities assigned to members. He finds that some activities would be done faster if given to other members. If the current assignments are kept, the project is expected to be 3 weeks late. What should the project manager do?
Show answer and explanation
Correct answer: D
A project manager has just taken over a development project for smart home devices. The WBS is built and activities are assigned. He finds that some activities would be done faster by other members, and keeping the present assignments means a 3-week delay.
Some members can complete certain activities faster, which is an opportunity to improve the schedule. The project manager should proactively review the proposed reassignments; if they would affect an approved baseline or controlled plan component, submit a change request and obtain approval before implementing them. An approved plan does not mean it cannot be optimized. The answer is D.
Why the other options are wrong
- A. Leaving the original assignments untouched and crashing other activities fails to use a ready-made opportunity, and it brings extra cost or risk.
- B. Asking for overtime when a better arrangement exists trades the team's rest time for schedule. It is not sustainable and is not the best approach.
- C. “The plan has been approved so keep it as is” is a rigid reading. When you find an opportunity, use it through the change control procedure and do not turn a blind eye.
Key takeaway When task assignments can be improved, proactively review the proposed reassignments; if they affect an approved baseline or controlled plan component, obtain approval before implementing them.
Variation If the stem were changed to “a member on the critical path is overloaded,” consider resource leveling or adding resources; if the reassignment affects the cost baseline, a change request must be submitted before it is carried out.
- Question 24
A warehouse system upgrade project at a logistics park has entered execution. Monitoring runs through the whole project life cycle so that the project management team understands the health of the project and finds the areas needing special attention. What should the project manager do to judge whether the project is on track?
Show answer and explanation
Correct answer: D
The project is in execution and approved baselines exist. Monitoring runs through the life cycle so that the team understands project health. The question asks what to use to judge whether the project is on track.
“Whether it is on track” is at heart a question of the gap between actual and plan. The project baselines (scope, schedule, cost) are the yardsticks of the plan, and only by comparing actual performance with the baselines can you determine the degree of deviation and decide whether corrective or preventive action is needed. This is the most central comparison in monitoring project performance, and it is objective, quantifiable and comprehensive. The answer is D.
Why the other options are wrong
- A. Comparing with the previous period shows only the direction in which performance is changing. Even if the project improves every period, it may still be behind the baseline all along, so this cannot show whether the project is on track.
- B. Verbal reports are subjective information. They are not compared with a baseline, cannot show how large the deviation is, and are not objective enough to be the sole basis for a judgment.
- C. Checking only the scope baseline cannot show whether schedule and cost are off. One dimension being normal does not mean the project as a whole is on track.
Key takeaway To judge whether a project is on track, compare actual performance with the project baselines, not with the previous period or with verbal impressions.
Variation Only if the question is “how much have we improved this month” do you use a comparison with the previous period to show a trend; to judge deviation from the plan, you still compare with the baselines.
Reference Monitor and Control Project Performance · Lesson 1: Monitor and Control Project Performance: Purpose, Inputs and Outputs, and Analysis Methods
- Question 25
On a software project, the project manager finds that a team member who is good at data analysis has long been assigned to organize documents, so his expertise is not being used. What should the project manager do?
Show answer and explanation
Correct answer: A
On a software project, a member who is good at data analysis has long been assigned to organize documents, so his expertise is not being used. The question asks what the project manager should do.
Resources should be used sensibly, with tasks matching skills. PMBOK 8 says a project manager should be sensitive to the willingness and ability of team members to perform their work, and that members who have a chance to use their strengths and to grow are more satisfied and motivated. Assigning a person who is good at data analysis to analysis work raises output and motivation. Once a resource mismatch is found, it should be corrected promptly; if you wait until late in the project to adjust, the loss has already happened. The answer is A.
Why the other options are wrong
- B. Keeping the current division of work means tolerating a resource mismatch. It just avoids adjusting, and both output and motivation suffer.
- C. Reducing his workload lowers output and does not put his expertise to use; it turns the problem into waste.
- D. Training him to be better at organizing documents reinforces the mismatch and does not use the strengths he already has.
Key takeaway Tasks should match skills; when a mismatch is found, reassign.
Variation If nobody else on the team can do the document work, assign a share of his time to analysis and the rest to documents, or add documentation support.
Reference Estimate Resources and Acquire Resources · Lesson 4: Resource Optimization and Release: Balance Workload, Match Skills, Release on Time
- Question 26
The project is in planning, the scope statement is complete, and the team is creating the WBS. Which of the following practices should NOT be used when creating the WBS?
Show answer and explanation
Correct answer: D
In planning, the scope statement is complete and the team is creating the WBS. Note that the question asks which practice should not be used when creating the WBS.
The nodes of a WBS are deliverables and work results; the “work” in its name refers to work products that are the result of activities, not to the activities themselves. Listing every activity needed to complete the deliverables in the WBS confuses the WBS with the activity list; activities are derived later from the work packages when the schedule is developed. So D should not be used. A, B and C are all practices that PMBOK 8 recognizes. The answer is D.
Why the other options are wrong
- A. Components developed by organizations outside the project team can be included as subcomponents, with the seller developing a separate WBS for the contract. This is a common practice.
- B. Using the major deliverables as the second level is one of the common ways to organize the second level.
- C. Deliverables differ in complexity, so they can be decomposed to different depths, according to the degree of control needed for management.
Key takeaway The WBS decomposes deliverables, not activities; activities are listed later, when the schedule is developed.
Variation On the question of whether project management work belongs in the WBS, the answer is yes; on a question about the inputs of Develop Scope Structure, choose the project management plan, project documents (including the project scope statement and requirements documentation), approved changes and so on, and the list is not limited to these.
- Question 27
PMLyceum takes on a predictive ERP implementation project. While reviewing a change request, the project manager finds that it would change the completion date in the schedule baseline. What should the project manager do?
Show answer and explanation
Correct answer: C
On a predictive ERP project, a change request under review would change the completion date in the schedule baseline. The question asks what the project manager should do.
Once approved, the schedule baseline can be changed only through formal change control procedures. The project manager must first assess the effect of the change on the schedule and obtain approval through the Assess and Implement Changes process; after approval, the change is carried into the schedule baseline. The core of this question is the sequence: assess the impact, submit the change, get it approved through the Assess and Implement Changes process, update the baseline. No step can be skipped, and any option that bypasses approval is wrong. The answer is C.
Why the other options are wrong
- A. The baseline can be modified only through formal change control. Changing first and filing afterward violates the procedure.
- B. Leaving the baseline as is and writing the new date only in a report means the change has not gone through assessment, approval and baseline update, so the handling is incomplete. The baseline should stay unchanged until approval and be updated after it.
- D. Crashing is one means of dealing with variances, but the change is already known to alter the date, so it should be assessed and put through the approval procedure; the team cannot be assumed to absorb it.
Key takeaway A change that affects the schedule baseline: assess first, get approval, then update the baseline.
Variation If the project uses Scrum, change control is more flexible, but the impact still has to be assessed and the Product Owner reorders the Product Backlog; other adaptive methods follow their own governance and change mechanisms.
- Question 28
Several stakeholders tell the project manager about compliance gaps and problems and each suggests how to solve them. What should the project manager do?
Show answer and explanation
Correct answer: A
The project is under way, and several stakeholders raise compliance gaps and each offers suggestions. The project manager needs to handle this feedback properly.
Compliance involves professional judgment, and those who know the situation best are the people responsible for compliance. The project manager should discuss the suggestions with them, verify the problems, find the causes and decide the best course of action. In view of “compliance” and “each offering suggestions”: verify first and decide together, rather than picking one suggestion and following it. Note also that since the stakeholders each made suggestions, the project manager cannot adopt one directly nor shelve them all; only after verification can it be decided which suggestion is feasible. The answer is A.
Why the other options are wrong
- B. The lessons learned register is for capturing lessons. Merely recording without acting leaves the problem in place and does not respond to the feedback.
- C. Handing all the problems to the sponsor gives up the project manager's own responsibility, and the sponsor is not the professional owner of compliance matters.
- D. Coaching and mentoring are about capability development. They can neither verify nor solve the compliance gap in front of you.
Key takeaway On receiving compliance feedback, first verify it with those who understand compliance best and decide the action plan together.
Variation If after verification the matter exceeds the decision authority of the project team, then pass it to the governing level through the escalation mechanism instead of deciding within the project.
- Question 29
A logistics park information platform project has been running for two months, and some execution-stage tasks require selecting suppliers first. The team has evaluated several suppliers and picked two as first choices. The sponsor asks for one more supplier with a lower quote to be added to the list, but the project manager knows this supplier does not always meet project requirements. What should the project manager do?
Show answer and explanation
Correct answer: A
A logistics park information platform project has run for two months. The team evaluated several suppliers and selected two first choices. The sponsor wants a lower-priced supplier added, but the project manager knows it does not necessarily meet project requirements. The question asks what the project manager should do.
PMBOK 8 Appendix X4 requires sellers to be selected against predefined criteria and recommends including the evaluation method in the tender documents. Because the team has already completed an evaluation, the project manager should review the established criteria with the sponsor, explain that price is only one criterion, and evaluate the recommended supplier against the same criteria rather than redefining them after seeing the candidates. The answer is A.
Why the other options are wrong
- B. Having the sponsor review the team’s results alone is worse than sitting down together, and a review also needs criteria to rest on.
- C. Choosing the sponsor’s favorite to avoid conflict gives up the selection criteria and leaves the project carrying the performance risk.
- D. Adding a supplier that may not meet the requirements straight to the list has no basis and makes the earlier evaluation pointless.
Key takeaway When people disagree about which supplier to use, return to the predefined evaluation criteria and apply them consistently to every candidate.
Variation If the criteria were already agreed and written down, score the newly added supplier against them in the same way, and leave it off the list if it does not meet the requirements.
Reference Make-or-Buy Analysis and Procurement Planning · Lesson 2: Source Selection Analysis, Selection Criteria and the Procurement Management Plan
- Question 30
PMLyceum is building an online course platform and you are the project manager. After taking stock of internal staff, you find there are not enough testers and plan to hand stress testing whose scope and acceptance criteria are already clear to a qualified outside company. You want the outside company to bear as much of the risk as possible. Which contract should you sign?
Show answer and explanation
Correct answer: A
The project is at the stage of planning the sourcing strategy, with some work to be outsourced. The question asks which contract makes the seller bear the greatest risk.
The signal: you want the outside company to bear as much of the risk as possible. In the fixed-price family the seller bears the cost risk, and under a firm fixed-price contract the price is set at the start and all cost overruns fall on the seller, so its risk is greatest. Among the other options, a fixed price with economic price adjustment contract adjusts the price for external factors, so the seller’s risk is smaller, and the two cost-reimbursable contracts have the buyer reimburse costs, so the risk lies with the buyer. The answer is A.
Why the other options are wrong
- B. A cost plus incentive fee contract is cost-reimbursable, so the buyer reimburses actual cost and the risk lies mainly with the buyer.
- C. Fixed price with economic price adjustment belongs to the fixed-price family, but price changes caused by external factors such as inflation and exchange rates are adjusted in the price, so the seller’s risk is lower than under a firm fixed-price contract.
- D. A cost plus award fee contract is also cost-reimbursable: the buyer bears the cost and pays an additional award fee at its own discretion.
Key takeaway For a clearly defined scope, choose a firm fixed-price contract to make the seller bear the greatest cost-overrun risk.
Variation If the question asked instead what gives the buyer the most certain budget, the answer would also be a firm fixed-price contract; if it asked where the buyer bears the greatest cost risk, the answer would be the cost-reimbursable family.
- Question 31
Because of a market window, the customer submits a change request to move the finish date up by 10 days. After the request is approved, the project manager discusses it with the team and believes that overlapping some critical-path activities will achieve the goal. What should the project manager do?
Show answer and explanation
Correct answer: D
Because of a market window, the customer submits a change request to move the finish date up by 10 days. After the request is approved, the project manager discusses it with the team and believes that overlapping some critical-path activities will achieve the goal. The question is what approach to take.
Making activities that were sequential run partly in parallel is fast tracking. Fast tracking works only for critical-path activities that can overlap and must respect the dependencies: discretionary dependencies can be reviewed, but mandatory dependencies must not be violated. The added rework and quality risk must also be weighed. Releasing a minimum viable product, resource leveling and adding experts are not activity overlap. The answer is D.
Why the other options are wrong
- A. A minimum viable product is an adaptive delivery practice. The team has already settled on overlapping activities, so it is not relevant.
- B. Reviewing the schedule and leveling resources does not speed things up and often lengthens the duration, so it cannot finish 10 days earlier.
- C. Adding subject matter experts is adding resources, which is crashing. The team concluded that activities should be overlapped, and the stem mentions no skill gap.
Key takeaway Overlapping activities is fast tracking: review dependencies on the critical path, and do not violate mandatory dependencies.
Variation If the customer agreed to pay extra, crashing could be considered. If all the dependencies are mandatory, fast tracking is not feasible, and you can only crash or adjust scope.
Reference Crashing vs. Fast Tracking · Lesson 2: Fast Tracking, and a Worked Comparison with Crashing
- Question 32
A company is carrying out a smart warehouse project, and the project manager and the sponsor are reviewing the benefits management plan to make sure the business objectives and target benefits can be achieved. Just then the government announces a tariff change on a category of imported equipment, which will raise the project's equipment procurement cost, and the project manager first has to confirm the effect of this change on the target benefits. What should the project manager do?
Show answer and explanation
Correct answer: D
On a smart warehouse project, the project manager and the sponsor are reviewing the benefits management plan when the government announces a tariff change on a category of imported equipment, which will raise equipment procurement costs. The project manager first has to confirm the effect of the change on the target benefits. The question is what to do.
An external change may shake the project's expected benefits, so the first step is to assess the effect and then revise the benefits management plan on that basis, so that the target benefits, strategic alignment and the like still match reality. The project manager works with the sponsor to keep the business objectives and benefits aligned, and only after that do downstream adjustments come up. “Reviewing the benefits management plan” in the stem is also a clue: the external change occurs in this context, so you go back and check whether the benefits still hold, rather than going straight to the downstream procurement problem. The answer is D.
Why the other options are wrong
- A. The tariff change has already been announced, and what comes first is to confirm its effect on the target benefits; merely updating the risk register and drafting a response strategy cannot ensure the target benefits still hold. If the tax rate, effective date or effect is still uncertain, the related uncertainty can still be recorded as a risk.
- B. Switching channels before the effect has been assessed may cause greater loss. The procurement plan is a downstream document; first see whether the benefits are affected.
- C. Analyze the effect first, then decide whether a change is needed and whether to draw on the management reserve. Spending the reserve at the outset skips the assessment.
Key takeaway When an external change threatens the benefits, first assess the effect and revise the benefits management plan, and only then deal with downstream adjustments.
Variation If the tariff change were only a rumor and had not been announced, it would be a possible risk, to be recorded in the risk register and assessed, not an immediate reason to revise the benefits management plan.
- Question 33
Early in a real estate company's customer management system project, the requirements document keeps failing to get approved. On checking, it turns out that a user department head was not included in the requirements-gathering communication. Which of the following documents may have omissions or be out of date?
Show answer and explanation
Correct answer: C
Early in a real estate company's customer management system project, the requirements document has not been approved. On checking, a user department head was not included in the requirements-gathering communication, and the question asks which document may have omissions or be out of date.
Who the project communicates with and who takes part depend on the stakeholder register, which records the identity, assessment and classification of all identified stakeholders. That the requirements communication left out the user department head suggests the register may not have listed this head, or was not updated in time as the organization changed. So you should check the stakeholder register. The answer is C.
Why the other options are wrong
- A. Business documents (the business case and the benefits management plan) give only an initial list of affected individuals and groups. They are not the documents that maintain the communication audience. When a communication audience misses someone, check whether the register has an omission or is out of date.
- B. The risk register records risks and responses. It is not the document that lists stakeholders and determines who to communicate with.
- D. The project charter lists only key stakeholders. It is not the basis for the full list, and it would not be judged out of date because one user department head was missed.
Key takeaway When communication leaves someone out, first check whether the stakeholder register has an omission or is out of date.
Variation If a stakeholder's communication frequency does not match their needs, check the communications management plan, not the register.
- Question 34
On an agile project, an agile management professional is concerned about the high-risk parts of the project and wants to consider both risk and value when ordering solutions. What should be done?
Show answer and explanation
Correct answer: C
On an agile project, the agile management professional is concerned about parts with high risk and wants to consider both risk and value when ordering. What should be done?
To look at both dimensions, use a value-and-risk quadrant chart: each item falls into one quadrant. As a common exam practice for this simplified matrix, usually implement high-value, high-risk content first: the payoff is large and uncertainty is exposed early, so the team can adjust early if the approach does not work. The other quadrants are commonly considered in the order high-value and low-risk, low-value and low-risk, then low-value and high-risk. This is not a fixed total order, however: actual ordering also considers dependencies, compliance, urgency and risk thresholds, and foundational low-value, high-risk work may still need early attention. The value-and-risk quadrant chart is common exam practice. The answer is C.
Why the other options are wrong
- A. Content with low value should not be done first even when its risk is high; do high-value content first.
- B. An information radiator makes information visible and is not an ordering method. Looking only at risk also ignores value.
- D. A cause-and-effect diagram analyzes the causes of problems and cannot put value and risk together for ordering.
Key takeaway To order by value and risk together, use a quadrant chart and do high-value, high-risk items first.
Variation If an item has low value and high risk, avoid doing it where possible; if the question asked about tracking the overall risk exposure over time, the answer would be a risk burndown chart.
- Question 35
A team uses Extreme Programming (XP) to develop a logistics scheduling system and appoints a member to check periodically whether the team's practices, culture and goals are appropriate. What is the purpose of doing this?
Show answer and explanation
Correct answer: D
A team using Extreme Programming (XP) to develop a logistics scheduling system appoints a member to check periodically whether the team's practices, culture and goals are appropriate. The question asks for the purpose of doing this.
Agile teams believe the process can keep getting better, so they periodically inspect the practices they use, their culture and their goals, and adjust accordingly. This is routine, whole-picture continuous improvement, and its purpose is to improve the way of working and raise the team's effectiveness. The two signals in the stem, “periodically” and “practices, culture and goals”, both point to whole-picture continuous improvement. The answer is D.
Why the other options are wrong
- A. A retrospective is only one form of continuous improvement. The value of periodic inspection is not in preparing material for a particular meeting.
- B. Finding the direct cause of a specific defect is problem analysis. What is inspected here is the overall practices, culture and goals, and it is routine and whole-picture.
- C. The inspection may produce lessons worth recording, but updating organizational process assets is only a by-product, not the purpose of periodic inspection.
Key takeaway An XP team periodically inspects its practices, culture and goals in order to improve the process continuously and raise team effectiveness.
Variation If the case were “a serious defect appeared after a release and the direct cause must be found”, the tool is root cause analysis. If asked what the fixed meeting at the end of an iteration is, it is the retrospective.
- Question 36
Development of a household appliance is complete and the product is about to enter the verification phase. The project manager is negotiating to borrow test staff from the quality department, but the head of that department insists the project manager has no authority to assign people from the department. What should the project manager show?
Show answer and explanation
Correct answer: D
After product development, the project is entering verification. The project manager asks the quality department for test staff, and the department head questions whether the project manager has authority to assign them. The question asks what to show.
The key point is “no authority to assign”. The problem is authority, not the number of people needed or how to communicate. The charter is issued by the sponsor, authorizes the project manager to use organizational resources, and states the project manager’s responsibility and authority level. Showing the charter answers the challenge directly. The other documents each have their uses, but none of them is a document that grants authority. This is the biggest difference between the charter and the various plans, and the standard way to approach this type of question. The answer is D.
Why the other options are wrong
- A. The communications management plan sets out how information is passed along. It cannot show who has the authority to assign people.
- B. The resource management plan covers how resources are estimated, acquired and managed. It is a method for doing the work once authorized, and it grants no authority itself, so the other side has no obligation to release people because of it.
- C. Written resource requirements answer “how many people are needed”, but the department head is questioning “whether you have the right to ask”. This document cannot settle an authority question.
Key takeaway When your authority to mobilize resources is questioned, show the charter.
Variation If the department accepts your authority and questions only the headcount and the start date, use the resource requirements and the schedule to negotiate. If the people still do not arrive, escalate to the sponsor according to the escalation path.
- Question 37
On a convenience store chain's checkout terminal rollout project, a make-or-buy analysis led to the core card reader module being supplied by one vendor, and the risk register records the risk of that vendor's financial deterioration together with a response strategy. During execution, a team member who works with the vendor tells the project manager that the vendor is short of cash and may go bankrupt and be unable to deliver; replacing the vendor would take a month. Before replacing the vendor, what should the project manager do?
Show answer and explanation
Correct answer: B
During execution, the vendor of a core module shows signs that it may go bankrupt. The risk has not yet occurred, and replacing the vendor would take a month. What should the project manager do before replacing the vendor?
“May go bankrupt” is a sign, not a fact, so this is monitoring risks: when new signs appear, reassess the likelihood of the risk occurring and check whether the existing response strategy is still effective, then decide whether to adjust the strategy (for example, activate a backup vendor) and whether to raise a change. “Before replacing” asks about this assessment step, not about direct action. The answer is B.
Why the other options are wrong
- A. Pausing all work when the risk has not occurred causes unnecessary loss and is not how risks are monitored.
- C. Not being bankrupt yet does not mean there is no risk. Ignoring the signs is passive and misses the chance to adjust the strategy.
- D. Adding budget before reassessing the risk is the wrong order. First reassess the risk and check the original response strategy, then decide whether to use reserves or adjust the strategy.
Key takeaway When new risk signs appear, check whether the original strategy is still effective and reassess the likelihood first, then decide on adjustments.
Variation Adjust the strategy only if the assessment shows the probability has risen sharply, and raise a change request if baselines are affected. If the vendor had already declared bankruptcy, the risk has occurred, and you would move to carrying out the plan or a workaround.
- Question 38
The development team of a community group-buying platform had members who held to their own views on the technical approach and would not cooperate. After a period of settling in, the project manager sees that arguments are steadily decreasing and that members are starting to collaborate and trust one another. Which leadership style is MOST suitable for the project manager to use now?
Show answer and explanation
Correct answer: A
The development team used to hold firmly to opposing views on the technical approach. After settling in, arguments are decreasing, and members are beginning to collaborate and trust one another. The question asks which leadership style suits the project manager best.
Fewer arguments, with members starting to collaborate and build trust, is the mark of the Norming stage: it is not the Forming stage of people who have just met, and it is not yet the self-running Performing stage. Trust has only just begun, and processes and boundaries still need to be worked out together, so the project manager should discuss with the team, build ways of working together, and delegate gradually. That is the participative style. Note that the pairing “Forming: directive, Storming: coaching, Norming: participative, Performing: delegating” is common exam practice. The answer is A.
Why the other options are wrong
- B. The directive style goes with the Forming stage, where members do not yet know the project and the leader needs to explain goals, roles and rules. This team has already been settling in for some time, so there is no need to start over.
- C. The coaching style goes with the Storming stage, where the leader guides people to air disagreements while they still exist. Here the arguments are already decreasing, and the focus has moved to building trust.
- D. The delegating style goes with the Performing stage, where the team runs itself and the leader largely steps back. In the Norming stage trust has only just started, so stepping back completely carries more risk.
Key takeaway Under common exam practice, stages and leadership styles pair up one to one: Forming directive, Storming coaching, Norming participative, Performing delegating.
Variation If the stem said the team had worked together for years, understood one another well and quickly solved hard problems on their own, the answer would be delegating. If it said a new team had just been formed and members did not know one another, the answer would be directive.
- Question 39
The project manager checks and finds that 6 approved requirements were never entered in the requirements traceability matrix, so they cannot be traced to deliverables or tests, and the acceptance date is approaching. What should the project manager do?
Show answer and explanation
Correct answer: B
The acceptance date is approaching. A check finds that 6 approved requirements were never entered in the requirements traceability matrix, so they cannot be traced to deliverables or tests. The question asks what the project manager should do.
One purpose of the matrix is to ensure that every approved requirement is delivered by the end of the project. These 6 requirements are approved but not tracked by the matrix, which may mean only that the records are incomplete, or may mean nobody has built or tested them. Enter them immediately, then check the scope baseline, WBS, deliverables, test plan and verification records. Complete trace links where corresponding items exist; where they do not, assess the impact and address the gaps through change control and the quality plan before updating the matrix. The answer is B.
Why the other options are wrong
- A. Waiting until acceptance to enter them means that when omissions are found it is too late to build or test them, which defeats the purpose of tracking throughout the process.
- C. Asking the test team to judge from experience whether they are covered has no basis, cannot prove the requirements were met, and leaves no traceable record.
- D. These 6 are approved requirements and cannot be treated as deferred on one's own. If an adjustment is really needed, it must go through change control.
Key takeaway Approved requirements must all be traceable; if records are missing, enter them, verify the underlying evidence, and then complete valid links or address the gaps through governance.
Variation If the check had found “a requirement has a deliverable but no test case,” the remedy would be to add tests and submit for acceptance after they pass, not to re-enter the requirement.
- Question 40
After assessment, a team finds that the online payment feature the customer values most cannot be finished in one iteration, and it worries that the next iteration will also be affected. What should the team do?
Show answer and explanation
Correct answer: C
On a project, the team assesses that the online payment feature the customer values most will not fit in one iteration. What should the team do?
The story is too big for one iteration, so it should be decomposed further into smaller stories, each completable within one iteration, and delivered step by step over several iterations. That keeps the value the customer cares about most and brings feedback earlier. The split should be vertical by user value, so that each slice is a small but complete and usable piece of functionality. A story should be small enough to be completed and demonstrated within one iteration, which is the goal of the split; if it has not met the Definition of Done by the end of the iteration, it is not counted as complete. The answer is C.
Why the other options are wrong
- A. Cutting features and dropping the rest would lose what the customer values most. Split first, do not cut.
- B. Merely going back to the customer to say it cannot be done solves nothing. The team should first find a way to turn it into small deliverable pieces itself.
- D. Asking the customer to simplify pushes the difficulty onto the customer and also reduces value. Splitting is the right approach.
Key takeaway A big story that cannot be finished: do not cut scope, split it small and deliver incrementally over iterations.
Variation If the question is how to split it, the answer is vertically by user value, for example QR-code payment first and refunds later, and not by technical layer into “create tables”, “write the interface” and “build the screens”.
- Question 41
An old textile mill plans to digitize its production and has set up a new project, asking the project manager to introduce an agile framework in it. Nobody on the team has ever developed in an agile way. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
A traditional textile mill's digitization project is to introduce an agile framework, and nobody on the team has used agile development. The question asks what the project manager does first.
The signal is “nobody has used agile”. If the team does not understand the values and principles of agile, going straight to practices tends to become mere form. So the first step is to bring everyone together and explain the agile principles, so that the team understands why things are done this way, and then specific practices such as the daily coordination meeting and iterations have a foundation. The answer is A.
Why the other options are wrong
- B. The daily coordination meeting is one of the practices for putting agile into effect. Holding it before the principles are understood leaves members unsure of its purpose, and it easily becomes a formal status report.
- C. Exploring the balance between theory and practice presupposes that the team already knows agile theory. For a team starting from zero, it is not the first step.
- D. Gathering the customer's requirements is work for the Product Owner later on, and it has nothing to do with the current obstacle that the team does not know agile.
Key takeaway To introduce agile, first have the team understand the principles, then talk about specific practices.
Variation If the stem were changed to “everyone has agile experience, but their ways of working differ”, the first step shifts to agreeing the team's working agreements (the team charter) and building a shared understanding.
- Question 42
Before the project formally ends, the project manager has reviewed all the relevant documents and paid the printing supplier the final payment as the contract provides. The supplier refuses the payment and instead asks for extra fees. What should the project manager do next?
Show answer and explanation
Correct answer: C
Before the project formally ends, the project manager has reviewed all documents and paid the printing supplier the final payment under the contract. The supplier refuses the payment and asks for extra fees. The question asks what to do next.
The project manager has paid the final payment as the contract provides, and the supplier refuses it and asks for more money. A demand for extra fees like this is a dispute at the contract level. PMBOK 8 Appendix X4 notes that, depending on the organizational structure, those authorized to procure may include project team members, management or members of the organization's purchasing department. The reason for the extra charge is not yet clear, so bring in procurement staff who know the contract and have the relevant contract-management authority, check it together with the project manager, and then decide whether change control is needed. The answer is C.
Why the other options are wrong
- A. The demand for extra fees has already occurred, so it is not a risk that has not yet happened. Registering it in the risk register does not resolve the dispute.
- B. The reason for the extra charge is unclear, so it cannot yet be treated as a change. The procurement team should first verify against the contract. If it turns out to be extra work outside the contract, then go through change control.
- D. This is a contract dispute and procurement staff who know the contract should be brought in. Passing it to the sponsor costs time and bypasses contract management responsibilities.
Key takeaway When final payment has been made under the contract and the other side refuses it and demands more, it is a contract dispute: bring in the procurement team, who know the contract, to verify and handle it against the contract.
Variation If the extra fees the supplier asks for really come from extra work outside the contract, payment is possible only after assessment and approval through change control.
Reference Monitoring and Controlling Procurements · Lesson 4: Closing Out Contracts and Early Termination
- Question 43
At a project management training session, the instructor asks participants to decide which of the following statements about how AI-related technologies nest is correct.
Show answer and explanation
Correct answer: B
The training asks you to judge how artificial intelligence, machine learning, deep learning, generative AI and related technologies nest, that is, which contains which.
PMBOK 8 Appendix X3 divides AI systems into four layers, from broadest to narrowest: artificial intelligence (AI), machine learning (ML), deep learning (DL) and generative AI (GenAI). Each layer is a subset of the layer outside it, and generative pretrained transformers (GPTs) sit in the innermost layer. Generative AI is a subset of deep learning that applies large language models to generate new data. To judge each option, just look at the direction of “which contains which”. The answer is B.
Why the other options are wrong
- A. The direction is reversed: deep learning is a more advanced type of machine learning, so it is a subset of machine learning, not the other way round.
- C. The direction is reversed: machine learning is a subfield of artificial intelligence, and artificial intelligence is the broader term. It is not a subset of machine learning.
- D. Generative AI sits inside deep learning, and therefore also inside machine learning, so it cannot be a broader category than machine learning.
Key takeaway AI ⊃ machine learning ⊃ deep learning ⊃ generative AI ⊃ GPT. Watch the direction of containment and do not call a subset the broader category.
Variation If asked “what is characteristic of generative AI?”, the answer is that it applies large language models to generate new data such as text, speech, pictures and video. If asked where GPT sits, the answer is the innermost layer, a specific implementation of generative AI.
- Question 44
The product owner is anxious: the team may not make it to delivering the minimum viable product (MVP) in the fourth iteration. Which of the following should the project manager use to address this concern?
Show answer and explanation
Correct answer: A
The product owner is concerned that the team may not deliver the minimum viable product (MVP) in the fourth iteration. The project manager needs evidence that can address that concern.
The concern is whether the work will be finished on time, which calls for a tool that forecasts completion. A burndown chart plots the change in remaining work over time; compared with the ideal line and extended with a trend line, it shows whether at the current pace the MVP scope will reach zero before the end of the fourth iteration (this is at release level, and the remaining work is the remaining story points within the MVP scope). The product owner can then adjust scope or date in good time. PMBOK 8 attaches a trend line to the iteration burndown chart to predict the likely variance at iteration completion; applying the same idea to the release-level burndown chart is common exam practice. The answer is A.
Why the other options are wrong
- B. The schedule performance index measures schedule efficiency relative to planned value and is an earned value metric. This question is about forecasting whether the remaining MVP scope will be finished before the fourth iteration, and a burndown trend line is more direct, so B is not the best answer.
- C. The cost performance index measures cost efficiency, while the product owner is worried about on-time delivery, not how much has been spent.
- D. Qualitative risk analysis assesses the probability and impact of risks. It does not track delivery progress and cannot answer whether delivery will be on time.
Key takeaway To judge whether the target scope will be finished on time, look at the burndown trend line (the iteration burndown chart within an iteration, the release burndown chart at release level), not SPI or CPI.
Variation To forecast how many more iterations the whole release needs, use “remaining story points ÷ velocity” and round up; for example, with 42 points remaining and a velocity of 15, 42 ÷ 15 = 2.8, so 3 iterations are needed. CPI is relevant only when the question is whether cost is overrun.
- Question 45
On a bottling-line upgrade project, the equipment supplier tells the project manager that it cannot provide a batch of key sensors. What should the project manager do?
Show answer and explanation
Correct answer: A
On a bottling-line upgrade, the equipment supplier tells the project manager it cannot provide a batch of key sensors. The project manager must first decide whether this is a risk or an issue, and then decide what to do.
The supplier has already said “cannot provide”, which is a fact that has happened, not an uncertain event that may happen. PMBOK 8 distinguishes them: an issue is a current condition that exists or has already occurred, and a risk is a potential future event that has not occurred. So log it in the issue log, bring subject matter experts and relevant stakeholders together to find an alternative, and then decide on that basis whether a change is needed. The answer is A.
Why the other options are wrong
- B. Logging it as a new risk and assessing its probability fails to separate fact from possibility. Failure to supply has already happened, so its probability is 100% and it cannot be assessed again as a new risk. The issue log should be the main document for tracking the current issue, and the status of the original risk (if one was logged) in the risk register can be updated as needed.
- C. Submitting a change request to adjust the performance measurement baseline right away: before any analysis or solution, you do not know whether a change is needed. A change request is submitted only after a solution is settled.
- D. Discussing extra time and budget with the sponsor goes straight to asking for resources without first looking for feasible options. Extra resources may be needed only after an alternative has been settled.
Key takeaway A supplier unable to supply is an issue: log it in the issue log, bring experts together to find options, and do not rush to a change request or a resource request.
Variation If the supplier had only said it “might be unable to supply”, that would be a risk and should be logged and assessed; if the register already holds that risk and a response, carry out the response directly.
Reference Risk Management Plan · Lesson 1: Risk, Issues and Risk Appetite
- Question 46
A project manager assigns a task to a key resource on the project, but the resource does not start work. The resource's functional manager says no formal document has ever been issued showing that the project was approved or that the project manager may assign the manager's staff. What is the MOST likely root cause?
Show answer and explanation
Correct answer: D
The project manager assigns a task to a key resource who does not start work. The resource's functional manager says no formal document has ever shown that the project was approved or that the project manager may assign the manager's staff. The question asks for the most likely root cause.
The key signal is that the functional manager has never received any formal document showing the project was approved or that the project manager may assign the manager's staff. This means the project has no project charter or other formal authorization document, and the project manager has not been granted authority to use organizational resources. The project charter normally authorizes the project manager to use organizational resources and records the project manager’s responsibility and authority level (the Eighth Edition notes that authorization is typically, but not always, through a charter). Without a charter or a similar authorization document, the project manager has not been formally authorized. This is the most likely root cause of the four. The answer is D.
Why the other options are wrong
- A. Bonuses and incentives are rewards and have nothing to do with the charter. With formal authorization in place, team members should carry out the work as assigned, and the lack of an extra bonus is not the root reason for not working.
- B. A time conflict can of course occur, but the stem gives no information on that. It is a specific problem to be coordinated, not the “most likely root cause”.
- C. A poor personal relationship can affect cooperation, but the stem shows no sign of it and it cannot be assumed out of nothing. The authority problem that the charter addresses is more fundamental.
Key takeaway When a project manager cannot direct resources, first check whether there is a charter granting the authority.
Variation If there is a charter but the resource still does not cooperate, check whether the resource is managed by a functional manager or by the project manager, and coordinate with the functional manager.
Reference Project Charter · Lesson 1: The Project Charter: Content and Purpose
- Question 47
The project manager has been commissioned to develop a cross-border e-commerce app. The team is preparing four regional versions, for North America, Europe, Southeast Asia and the Middle East, and the system must automatically set basic configuration settings such as currency, language, tax rate and time zone for each version. Every configuration item of every version must be completely correct, and no item may be missed. To monitor the quality of these configurations, what should the project manager do?
Show answer and explanation
Correct answer: B
A cross-border e-commerce app is to launch four regional versions, for North America, Europe, Southeast Asia and the Middle East, with currency, language, tax rate, time zone and other settings configured automatically for each version. Every item must be completely correct and none may be missed. The question asks what to do to monitor configuration quality.
A checklist is a list of items, actions or points to be considered and is often used as a reminder. With four versions and many configuration items per version, each item must be confirmed with nothing omitted. That is exactly what a checklist is for: list every configuration item, tick them off one by one, and you get a structured verification. The answer is B.
Why the other options are wrong
- A. A questionnaire is a way of collecting information. Here the task is to verify that the configuration is correct, not to collect other people's opinions.
- C. A control chart is used to judge whether a process is stable and whether data is out of control. It cannot confirm item by item that every configuration value is correct.
- D. Statistical sampling checks only part of the items and cannot guarantee that every configuration item is correct, which contradicts the requirement that “no item may be missed”.
Key takeaway When every item must be verified one by one and none may be missed, use a checklist.
Variation In batch production, to judge whether a dimensional parameter is stable, use a control chart; to estimate the overall pass rate of a large batch when 100% inspection is impossible, use sampling.
Reference Cause-and-Effect and Pareto Diagrams · Lesson 4: Telling the Other Common Quality Tools Apart: Checklist, Check Sheet, Histogram, Scatter Diagram, Flowchart, Affinity Diagram
- Question 48
A logistics company's order processing system project is under way. The project manager realizes that after the system goes live, the way warehouse and customer service staff work will change. What should the project manager do?
Show answer and explanation
Correct answer: C
The project manager has seen that the project's result will change how the organization works. What should be done once this is noticed?
A project is meant to move an organization from its current state to a future state, and for some projects the shift can include a transition state. A change in ways of working is part of that change. Change touches scope, schedule, resources and stakeholders, so the project manager should first evaluate the impact of this organizational change on the project and then determine the actions required. The answer is C.
Why the other options are wrong
- A. Compressing the scope avoids the change, weakens the value the project is meant to deliver, and acts before assessing, so it has no basis.
- B. The project drives the change, so the project manager cannot hand it to the operations department. If the project ignores the impact of the change, the result will also be hard for people to accept.
- D. Passively waiting until after go-live means the problems have already surfaced, the cost of correction is higher, and the chance to respond early is gone.
Key takeaway A project drives organizational change. When you find the project will change how people work, evaluate the impact first, then determine the actions.
Variation If the question asks “what do you assess first when supporting organizational change”, the answer is organizational culture and readiness; specific actions such as communication and training come after the assessment.
- Question 49
A factory production line equipment upgrade project has just been approved, and the project manager is preparing the overall budget. The factory's budget rules are that contingency reserve is included in the cost baseline and management reserve is placed outside the baseline. Which of the following accurately describes what the project budget is made of?
Show answer and explanation
Correct answer: D
A predictive project is preparing its overall budget after approval. The factory's rule is that contingency reserve is inside the cost baseline and management reserve is outside it. You must judge what the project budget is made of.
PMBOK 8 notes that how the project budget is built up varies by organization and may or may not include reserves. This question follows the rule given in the stem: inside the cost baseline are the work package cost estimates and contingency reserve, and management reserve is outside the baseline, so project budget = cost baseline + management reserve. Only D distinguishes the baseline from management reserve. The answer is D.
Why the other options are wrong
- A. Aggregating all activity cost estimates and setting aside contingency reserve describes the internal makeup of the cost baseline. It does not add management reserve, so it is not the complete project budget.
- B. Contingency reserve is already in the cost baseline. Writing it this way double counts contingency reserve and omits management reserve, so it does not give the project budget.
- C. Summing the work package estimates and adding contingency reserve is again just the makeup of the cost baseline, with no management reserve, so it is not the complete project budget.
Key takeaway Under the rule “the baseline includes contingency reserve and management reserve sits outside it”: project budget = cost baseline + management reserve.
Variation Under the same rules, if asked what the cost baseline is made of, the answer is the work package estimates plus contingency reserve, without management reserve.
Reference Cost Baseline and Reserves · Lesson 1: Cost Aggregation and the Cost Baseline: What Is in the Budget
- Question 50
On an enterprise ERP project, the lead for the “data migration” activity has not yet been set in the responsibility assignment matrix, and the sponsor and the project manager cannot agree: the project manager prefers member A, while the sponsor thinks member B is more experienced. The resource management plan already states each role's responsibilities and authority, including who decides on resource selection. What should the project manager do to resolve this disagreement over a resource decision?
Show answer and explanation
Correct answer: B
The lead for the “data migration” activity is not yet set in the responsibility assignment matrix, the project manager and the sponsor each have a candidate, and the resource management plan already states each role's responsibilities and authority, including who decides on resource selection. The question asks how to resolve the disagreement over this resource decision.
At heart the disagreement is about how resources are selected and who leads. The resource management plan states roles, responsibilities, authority and other content and is the common basis for the project manager and sponsor, so the project manager should handle the disagreement on that basis and give the decision a footing. The matrix does not yet cover this activity, so consulting it yields no conclusion. The answer is B.
Why the other options are wrong
- A. An organization chart shows only the organization's levels and reporting relationships. It cannot say who chooses the lead for an activity or on what basis.
- C. This activity's lead is exactly what is blank in the matrix, so looking there gives no answer. The matrix records the outcome once the disagreement is settled and is not the basis for settling it.
- D. The functional manager controls staff assignment, whereas the dispute is about who leads within the project. The project manager should first handle it on the basis of the plan rather than hand the disagreement to the functional manager.
Key takeaway When there is disagreement about how resources are chosen and used, rely on the resource management plan, not the functional manager or the organization chart.
Variation If the stem said the matrix already names a lead but members do not accept it, review and confirm the matrix with the team. If a key person is being moved away by the functional manager, move to negotiating with the functional manager.
- Question 51
All deliverables of a smart campus platform project are complete and the project is about to enter closure. While reviewing performance indicators, the project manager finds a cost surplus, and the project manager of another project proposes transferring the surplus to them; the customer has not yet formally accepted the deliverables. What should the project manager do next?
Show answer and explanation
Correct answer: C
All deliverables are complete and the project is about to close. A cost surplus is found, and another project manager proposes taking it. The question asks what the project manager should do next.
PMBOK 8 lists formal customer acceptance as a key predictive closure activity. The stem says the deliverables are complete but the customer has not yet formally accepted them, so C is a clearly outstanding required activity. PMBOK 8 does not prescribe one fixed sequence among acceptance, lessons learned, archiving and financial closure; those activities are coordinated under organizational policy and the project context. Any cost surplus must also be handled by the authorized governance or financial role under applicable policy. The answer is C.
Why the other options are wrong
- A. With or without a surplus, closure follows the process. Rushing to spend money so the budget is not taken back is an improper use of funds and has no value.
- B. Lessons learned can be recorded continuously and compiled at closure. The stem does not show that the customer has formally accepted the deliverables, which is the clearly missing item, so summarizing is not the most pressing action now.
- D. Financial closure is also necessary, but the stem explicitly shows that formal customer acceptance is missing, making C the more direct required activity. This does not establish that financial closure must always occur strictly after acceptance.
Key takeaway After the deliverables are complete, ensure formal acceptance before formally ending the project; handle any surplus under the organization's financial policy.
Variation If the customer raises unmet items at acceptance, first deal with the defects and submit again for acceptance, and only after it passes move to the later closure steps.
Reference Project Closure · Lesson 2: Normal Project Closure Steps: Why the Sequence Matters
- Question 52
A project manager submits a major change proposal. The PMO reviews it, rejects it outright and tells the project manager to improve the proposal as the PMO specifies before reporting back. The PMO manages the project directly, and the project manager was assigned by the PMO and reports to it. Under the traditional classification, which type of PMO is this?
Show answer and explanation
Correct answer: D
A major change is proposed during the project. The PMO rejects it outright and requires revision as it specifies. To decide which type of PMO this is, look at its degree of control over the project.
Common exam practice classifies PMOs by degree of control over projects as supportive, controlling or directive. PMBOK 8 Appendix X2, by contrast, suggests that directive, supportive, agile and other models are not mutually exclusive paths and can be combined as the organization needs. In this question the PMO manages the project directly, the project manager is assigned by it and reports to it, and it not only rejected the change but also required the project manager to revise it as the PMO specified before reporting back. It is directly deciding how the project is done, which best fits the directive type. The answer is D.
Why the other options are wrong
- A. A controlling PMO mainly requires projects to comply with established frameworks, standards and governance processes. It may send back noncompliant requests but usually does not dictate exactly how to revise them. In this question the PMO specifies the direction of the revision, which is more like directive.
- B. A supportive PMO mainly acts as a consultant and a repository of resources, with a very low degree of control. It would not normally manage the project directly, assign the project manager, and dictate the direction of revisions as this PMO does.
- C. In the traditional classification by degree of control (a common exam term), there are only three types: supportive, controlling and directive. Although PMBOK 8 says models can be combined, the behavior in this question (rejecting directly and specifying the revision) clearly shows directive characteristics, so you cannot choose “hybrid” on that basis.
Key takeaway In the commonly used classification, a PMO that directly decides how a project is done is directive; a controlling PMO mainly requires projects to follow its frameworks and standards.
Variation If the PMO requires all projects to use a uniform change request template, but changes are still approved by authorized people or bodies under the governance arrangements and the PMO does not dictate how to revise them, it is controlling. If the PMO only provides templates and gives advice when a project asks, it is supportive.
- Question 53
A project was launched because of a change in the external business situation. During execution, several of the business parameters on which the project was originally approved change. What should the project manager do?
Show answer and explanation
Correct answer: A
A project was launched because the external business situation changed. During execution, several of the business parameters behind its approval change, and the question is how the project manager should handle it.
A change in business parameters may affect the project's feasibility and value. The project manager should inform management and initiate a reassessment of the business case and project requirements so that the project remains aligned with the business objectives. After assessing the effect on value, scope, schedule and cost, any necessary changes to requirements or baselines should be handled through the applicable governance arrangements and the Assess and Implement Changes process. The answer is A.
Why the other options are wrong
- B. Changes are common in projects, and refusing them all is avoiding the problem. A change should be assessed through the formal process and then decided.
- C. Accepting only new requirements and leaving the old ones unchanged may leave the old requirements inconsistent with the new business parameters. It is also avoiding change for fear of rework.
- D. If the work continues on the original scope after the business parameters have changed, the expected value may not be created. Treating “the scope is agreed” as a reason does not hold.
Key takeaway When business parameters change, report them to management and first reassess the business case, project value and requirements; if an adjustment is needed, implement it through the applicable change process.
Variation If the change is so large that the project is no longer worth continuing, or the new parameters make the original requirements meaningless, discuss reassessing the business case with the sponsor, not just updating the requirements.
Reference Business Case and Benefits Management Plan · Lesson 4: Business Documents in Scenario Questions
- Question 54
In comparing how different contracts allocate cost risk between buyer and seller, which of the following puts the greatest cost risk on the buyer?
Show answer and explanation
Correct answer: D
The question asks, in comparing how contracts allocate cost risk between buyer and seller, which contract puts the greatest cost risk on the buyer.
PMBOK 8 Appendix X4 notes that for the client a cost-reimbursable contract allows flexibility but carries the risk of cost escalation, while a fixed-price contract transfers cost risk to the seller. In a cost plus percentage of cost contract (CPPC, a common exam term), the seller’s fee is a percentage of actual cost, so the more it spends, the higher its fee. This fee structure gives the seller no financial incentive to control cost, while overruns fall on the buyer. The buyer’s cost risk is therefore the greatest. The answer is D.
Why the other options are wrong
- A. A fixed price incentive fee contract (FPIF) has a ceiling price. The buyer shares overruns only until the point of total assumption; after that point the seller bears each further overrun. The buyer’s payment is therefore capped, and its cost risk is lower than under CPPC.
- B. Time and materials settles on actual hours and materials and so also carries a risk of rising cost unless the contract sets a ceiling price. But the rates are agreed in advance and the buyer can control it through limits and monitoring, so the risk is usually lower than under CPPC, whose fee rises directly with actual cost.
- C. A firm fixed-price contract has a fixed price with the seller bearing overruns, so the buyer’s cost risk is the lowest, the opposite of what this question asks.
Key takeaway For cost risk, the buyer’s exposure from lowest to highest runs roughly: firm fixed-price, fixed price incentive, time and materials, cost-reimbursable; cost plus percentage of cost is highest.
Variation If the question asked which contract puts the most cost risk on the seller, the answer would be a firm fixed-price contract; if it asked which puts the least cost risk on the buyer, that too would be a firm fixed-price contract.
Reference Contract Types · Lesson 4: Contract Types, Risk and Finance, and New Trends in Contracting
- Question 55
An AI tool suggests that the project manager compress one phase of the plan by two weeks. What should the project manager do?
Show answer and explanation
Correct answer: C
An AI tool has suggested compressing one phase of the plan by two weeks. What should the project manager do?
The signal is “AI tool suggestion”. PMBOK 8 requires that information obtained from AI be checked and validated, and stresses that a human must ultimately be accountable for each decision. Compressing a phase affects schedule, cost, resources and risk, so validate the suggestion against project data, assess the impact, and then have a person decide whether to adopt it. In validating, look at whether the suggestion rests on complete schedule and resource data, and what happens to the critical path, cost and risk after compression. After validation, if an approved baseline must change, submit a formal change request, and the decision is made by the people with authority under the project management plan or by the change control board. The answer is C.
Why the other options are wrong
- A. Changing the plan immediately as suggested hands the decision to the tool and alters the plan without validation, which is very risky.
- B. Merely recording it without further analysis neither uses the value of AI nor fulfills the responsibility to assess.
- D. Ignoring it because it comes from a tool wastes potentially valuable analysis. AI suggestions should be validated, not rejected across the board.
Key takeaway Validate and assess an AI suggestion first, and then have a person decide.
Variation If the AI gives a production scheduling suggestion that conflicts with the critical path, again assess it against the critical path and project data first and then decide. If asked who is responsible, the answer is people.
- Question 56
PMLyceum is launching development of a new underwater cleaning robot, and you are appointed project manager. After research you find that management has not specified what functions the product must have and cannot say which work the development should start with, and the statement of work gives only a rough budget. The development is expected to be long and large with high technical risk, and the buyer will have to bear and monitor actual cost. Which contract should be chosen?
Show answer and explanation
Correct answer: D
Neither the requirements nor the scope is clear, and it is not even clear which work the development should start with. The question asks for the contract type.
Eliminate in two steps. The requirements are unclear and the scope is highly uncertain, and the fixed-price family needs the scope defined before a price can be set, so rule it out. A time-and-materials contract can be used where scope is unclear at the start, but it fits better small, consulting or supporting work priced by trade or unit rate. This is the development of a brand-new product with high scope uncertainty and high risk overall, so a cost-reimbursable contract fits better: the buyer reimburses actual cost, which suits development settled as the work proceeds, and D is the only cost-reimbursable contract among the options. The answer is D.
Why the other options are wrong
- A. A time-and-materials contract usually has no fixed total price or exact quantities at signing, and its value may rise with actual hours and material costs (a limit on amount and duration can also be set). It fits small, consulting or supporting work priced by agreed rates and unit prices. Here there are no agreed hourly or material unit prices, and the stem says the buyer will bear and monitor actual cost, so the cost-reimbursable family fits better than time and materials.
- B. Fixed price incentive fee belongs to the fixed-price family, so the scope must be defined clearly before a target cost and ceiling price can be set, which cannot be done when requirements are unclear.
- C. Fixed price with economic price adjustment suits procurements with a long performance period and prices that move with the market, and it too is fixed-price, requiring a clear scope.
Key takeaway Unclear requirements and highly uncertain development overall point to a cost-reimbursable contract.
Variation If the stem added “architects and other staff have been approved to join, but an SOW cannot be written”, time and materials would fit better; if it also gave a target cost and a sharing ratio, it would point more clearly to a cost plus incentive fee contract.
- Question 57
A cross-border e-commerce product-selection platform project is in its middle-to-late stage, with scope, quality, schedule and cost all on plan and acceptance due in about a month. The sponsor then discovers a constraint tied to data export regulations that makes the risk too high, and after review management decides to cancel the project. What should the project manager do next?
Show answer and explanation
Correct answer: C
The project is in its middle-to-late stage with scope, quality, schedule and cost all on plan, and acceptance is about a month away. The sponsor discovers a constraint tied to data export regulations, the risk is too high, and management cancels the project. The question asks what the project manager does next, so it tests handling of early termination.
A project terminated before completion must be closed as well. Close Project or Phase includes establishing procedures to investigate and document the reasons the project may have been terminated before completion. So the next step is to start closure under the organization's process and, during closure, investigate and document the reason for cancellation. Then account for the completed and uncompleted deliverables, carry out handoff, summarize lessons learned, and release resources as appropriate. The answer is C.
Why the other options are wrong
- A. You cannot stop work and move straight to a new project. A canceled project still needs closure, for example preserving interim results and updating organizational process assets.
- B. Management has already decided to cancel, and the project manager has no authority to finish the project. Continuing to invest wastes resources and goes against the decision.
- D. By common exam practice, releasing people comes after recording, handoff and knowledge transfer. Releasing people now would leave nobody to complete the records and handoff.
Key takeaway Early termination also requires closure, starting with finding and recording the reason for termination.
Variation If the stem said “the project was canceled right after its charter was approved”, closure still starts under the organization's process. If the project closed early because the expected value had been achieved, that is early termination for a positive cause and it needs closure too.
- Question 58
An agile management professional notices that a new user story added to the Product Backlog has a vague description and no acceptance criteria. At which point in the Sprint cycle should he ask the Product Owner to add more detail?
Show answer and explanation
Correct answer: D
A new user story in the Product Backlog has a vague description and no acceptance criteria. The question asks at which point in the Sprint cycle the Product Owner should be asked to add detail.
A story lacking detail and acceptance criteria is not yet “ready”. Adding detail, estimating and ordering are the work of backlog refinement, led by the Product Owner with the team taking part, so the request should be raised at the backlog refinement meeting, and the story is estimated once it is filled in. Refinement is ongoing and can take place both before and during a Sprint, so that by Sprint Planning the top items already have detail, estimates and acceptance criteria and the planning meeting is not taken up with clarifying requirements. The answer is D.
Why the other options are wrong
- A. The Sprint Retrospective is for reflecting on how the team works and settling improvements. It does not deal with the details of individual items.
- B. The Daily Scrum is for inspecting progress toward the Sprint Goal and adjusting the plan for the work ahead as needed. It is not the place to add requirement details, and it lasts only 15 minutes.
- C. The Sprint Review inspects the completed Increment and gathers feedback. It is not for polishing items that have not been developed.
Key takeaway When an item is vague or lacks acceptance criteria, have the Product Owner add what is missing during refinement.
Variation If the question is what an item must meet before entering a Sprint, the answer becomes the definition of ready. If it is whether an Increment is done, look at the Definition of Done.
- Question 59
An agile team is in its fourth iteration when it finds a user story carrying a serious new risk, and it confirms that this risk did not appear in any of the first three iterations. The risk does not affect the current iteration's goal and cannot be handled within the current iteration. What should the team do?
Show answer and explanation
Correct answer: D
In the fourth iteration, the team finds a user story carrying a serious new risk that did not exist in the first three iterations. It does not affect the current iteration goal and cannot be handled within the current iteration. The question asks what the team should do.
Adaptive projects manage risk through a risk-adjusted backlog: risk response work and technical debt are also handled as backlog items. Team members can raise them, they are added to the product backlog, and the product owner prioritizes them to decide what the next iteration will do. A serious new risk follows the same path: add the story that addresses it to the product backlog and prioritize it. The stem states that the risk does not affect the current goal and cannot be handled in this iteration, so the team does not act on it now but turns it into a backlog item. If it did threaten the current iteration goal, it would need immediate assessment and a conversation with the product owner about adjusting the iteration. The answer is D.
Why the other options are wrong
- A. Work in an iteration should come from the agreed backlog. Adding goals mid-iteration undermines the stability of the iteration.
- B. Recording it in the register and waiting for the next retrospective leaves a serious new risk out of the backlog and unprioritized, so it is not handled in time. The retrospective is about process and collaboration, not assessing and ranking individual risks.
- C. Ignoring a serious risk to protect speed lets it get worse, and it goes against the agile practice of finding and responding early.
Key takeaway On adaptive projects, a new risk becomes a backlog item that the product owner prioritizes.
Variation If the new risk will affect the next two iterations, agree on a response with the team at backlog refinement; if the goal is just to make sure everyone knows, put it on the board and raise it at the next daily coordination meeting.
- Question 60
A multinational company hires an agile expert as a project manager, tasked with helping the project team reduce rework and customer dissatisfaction. How should the project manager achieve these goals?
Show answer and explanation
Correct answer: A
A multinational company hires an agile expert as project manager to help the project team reduce rework and customer dissatisfaction. The question asks how to achieve these goals.
Rework and dissatisfaction often arise because the customer sees results too late and requirements are misunderstood. Delivering value in incremental cycles lets the customer see usable results early and comment, and the team adjusts in time, so deviations are corrected while still small and rework and dissatisfaction fall. This is also how value-driven delivery works. The answer is A.
Why the other options are wrong
- B. Narrowing the scope and bringing a new solution avoids the problem, does not involve the customer and gives no chance for feedback.
- C. A schedule and timeline only explain the plan to the customer. They cannot reduce rework or let the customer see anything real.
- D. No amount of detailed delivery preparation guarantees customer satisfaction or avoids rework. Only building something the customer can see and react to helps.
Key takeaway The agile way to reduce rework and dissatisfaction is to deliver in increments and get feedback early. Incremental delivery involves the customer in every small validation step and controls rework better than one big delivery.
Variation If the customer cannot receive deliveries frequently, agree on release-level receipt checkpoints. The team can still inspect the Increment with available stakeholders and adapt the Product Backlog at the Sprint Review, but the Sprint Review is not an acceptance or release gate.
Reference Minimum Viable Product · Lesson 2: Incremental Delivery and Iteration, and the MVP Under Budget or Time Constraints
- Question 61
At the monthly steering committee meeting, the sponsor tells the project manager that a key lead in the procurement department says he has not heard about the recent change to the delivery plan. The project manager has already verified that this person was recorded in the stakeholder register long ago and is classified accurately. To judge the gap between this lead's current level of engagement and the level the project needs, and so decide how much communication effort to put in, which project document should the project manager review FIRST?
Show answer and explanation
Correct answer: C
At the monthly steering committee, the sponsor relays that a key procurement lead says he has not heard about the recent change to the delivery plan. The project manager has verified that he has long been in the register and is classified accurately. To judge the gap between his current and needed engagement and decide how much communication is required, you must decide which project document to review first.
There are two signals: his identity and classification are fine, but he missed an important update. Missing one update does not automatically put him at the Unaware engagement level; it is a signal to reassess engagement and inspect communication execution. The stakeholder engagement assessment matrix compares current and desired engagement levels, showing whether an engagement gap exists and helping direct the communication effort needed. Any failure in channels, frequency or actual distribution should then be checked against the communications management plan and distribution records. Because the question specifically asks how to judge the current-to-desired engagement gap, the answer is C.
Why the other options are wrong
- A. The register records identity, assessment and classification information. The stem already says he is registered correctly, so reviewing it again will not show why he is unaware.
- B. The issue log records problems that have already come up in the project and how they were handled. It does not reflect an individual's awareness of or engagement in the project, so it cannot be used to compare his current and needed engagement.
- D. The requirements traceability matrix links requirements to deliverables to track their fulfillment. It has nothing to do with whether someone knows about progress.
Key takeaway When identification and classification are correct but someone misses an important update, use the assessment matrix to reassess current versus desired engagement; one missed update alone does not mean the person is Unaware.
Variation If you did not know which category to put him in, you would use a mapping tool such as the power/interest grid. If he were not in the register at all, you would update the register first.
Reference Stakeholder Engagement · Lesson 2: The Stakeholder Engagement Assessment Matrix: Five Engagement Levels and the C–D Gap
- Question 62
While creating the WBS, the team confirms that a deliverable has been decomposed to the level of detail needed for control, its cost and duration can be estimated and managed, and one responsible person can be named. What should the project manager do?
Show answer and explanation
Correct answer: C
While creating the WBS, you must decide whether a deliverable should be decomposed further. It has reached the level of detail needed for control, its cost and duration can be estimated and managed, and one responsible person can be named.
The work package is the lowest level of the WBS: work whose cost and duration can be estimated and managed. The stem states that the detail is sufficient for the required control, cost and duration can be estimated and managed, and a responsible person can be named, so it should be kept as a work package and not decomposed further in the WBS; when the schedule is developed later, the work package can still be progressively elaborated into specific activities. Decomposing further only adds burden to rolling up and managing. The answer is C.
Why the other options are wrong
- A. Breaking it into a day-by-day task list is going too far. Excessively fine decomposition wastes management effort and makes rolling up data through the levels harder.
- B. A planning package sits below a control account and above the work-package level, for known work that has not yet been elaborated into work packages. The stem says the detail is sufficient for control and cost and duration can be estimated and managed, so there is no reason to leave it as a planning package awaiting elaboration.
- D. Once merged with the adjacent deliverable, it no longer appears separately in the WBS. This deliverable can already be assigned to one owner and estimated for cost and duration, so merging it would blur responsibility and the basis of the estimate, and there is no need for it.
Key takeaway A component at the lowest level of the WBS whose cost and duration can be estimated and managed is a work package and need not be decomposed further in the WBS; it can still be progressively elaborated into specific activities when the schedule is developed.
Variation If this deliverable will not start for another six months and all that is known now is what has to be done, with no further detail possible, keep it as a planning package and elaborate it on a rolling basis when the information is clear.
- Question 63
A consulting firm completes a project for a customer, who offers two ways to pay: Option A is a single payment of $100,000 one year from now; Option B is a single payment of $110,000 three years from now. The firm uses a discount rate of 10% per year, and all other conditions are the same. How should the options be compared and chosen if the time value of money is considered?
Show answer and explanation
Correct answer: A
The two payments differ in both amount and timing. Considering the time value of money requires knowing how to compare and choose, which is an application of present value.
The key signals are “consider the time value of money” and “discount rate of 10%”. Money at different points in time cannot be compared by size directly; it must first be converted to the same point in time (today) and then compared. That is present value. After discounting, A is about $90,900 and B about $82,600, so A is higher and is the choice. B looks like $10,000 more on paper, but it requires waiting two more years, and the cost of tying up funds for two years exceeds that $10,000 difference. The answer is A.
- A: PV = 100,000 ÷ 1.10 = $90,910
- B: PV = 110,000 ÷ 1.10³ = 110,000 ÷ 1.331 = $82,645
- Check: 90,910 > 82,645, so A has the higher present value and is chosen; B would overtake only if the discount rate fell below about 4.9%
Why the other options are wrong
- B. This compares nominal amounts directly, 110 > 100, and treats “waiting two more years” as negligible. That is the classic mistake of ignoring the time value of money; after discounting B is worth only about $82,600.
- C. This treats payback period as a precondition for comparing. Payback period measures how long it takes to recover an investment and makes no sense for two single receipts. Converting to present value allows a direct comparison without computing payback first.
- D. This assumes that the longer the money is tied up, the higher the return. The later the payment, the more years of discounting and the lower the present value; waiting does not make the money grow by itself.
Key takeaway To compare money at different times, first convert to present value at the same point in time and then compare; do not look only at the nominal amount or the length of time.
Variation If B were changed to $110,000 received in two years, PV = 110,000 ÷ 1.21 ≈ $90,900, almost level with A. The higher the discount rate, the more later money loses.
Reference Net Present Value and Value Evaluation · Lesson 1: Present Value, Discounting and Net Present Value (NPV)
- Question 64
The sponsor of a multinational project pays special attention to communication and asks the project manager to have team members draw the project's communication model and explain it. All of the following statements about communication models are correct EXCEPT which one?
Show answer and explanation
Correct answer: D
The sponsor of a multinational project asks the team to draw and explain the communication model. The question asks which statement about communication models is NOT correct.
In PMBOK 8, the sender is responsible for the transmission of the message, ensuring the information is clear and complete, and confirming the message is correctly interpreted. The receiver is responsible for receiving the information in its entirety, interpreting it correctly, and acknowledging or responding appropriately. Noise and other barriers may exist in the environment of both the sender and the receiver, such as distraction, variations in perception, and lack of knowledge or interest. These are interference to be identified and managed; you cannot say that “taking measures can completely eliminate” them. The absolute claim in D is wrong, so the answer is D.
Why the other options are wrong
- A. This follows the wording of PMBOK 8: the receiver is responsible for receiving the information in its entirety, interpreting it correctly, and acknowledging or responding appropriately. The statement is correct, so it is not the answer.
- B. The sender must make sure the information is clear and complete and use a suitable transmission method, which includes checking the encoding. The statement is correct, so it is not the answer.
- C. The sender must confirm that the information has been correctly understood, and does so through the receiver's feedback. The statement is correct, so it is not the answer.
Key takeaway Noise can be identified and reduced but not completely eliminated; the sender confirms understanding, and the receiver decodes correctly and responds.
Variation If D were changed to “noise in communication can be identified and reduced as far as possible,” it would be a correct statement, and the answer would have to be a different option.
Reference Plan Communications Management · Lesson 4: Communication Models: Encode, Transmit, Decode and Feedback
- Question 65
A Scrum team is developing a consumer product. The product owner wants to analyze how features affect customer satisfaction differently, distinguish features the customer takes for granted, expects and is delighted by, and order the features accordingly. Which method can be used?
Show answer and explanation
Correct answer: C
A Scrum team develops a consumer product, and the product owner wants to separate features the customer takes for granted, features the customer expects and features that delight, and order the features accordingly. Which method can be used?
The three groups in the stem correspond to the basic, performance (expected) and delight attributes of Kano analysis. Kano analysis classifies features along two dimensions, whether the feature is implemented and whether the user is satisfied, and helps the product owner compare how each feature affects satisfaction and then order them. Attributes also shift over time: yesterday's delighter may be a basic expectation today, so reassess regularly when ordering. The answer is C.
Why the other options are wrong
- A. Planning poker is an estimating technique that produces story points. It is not used to analyze customer satisfaction.
- B. SMART is for setting goals that are specific and measurable. It cannot classify or order features.
- D. A cause-and-effect diagram traces the root cause of a problem and has nothing to do with ordering by customer preference.
Key takeaway To tell apart what customers take for granted, what they expect and what delights them, order with Kano analysis.
Variation If the stem asked about “must have, should have, could have and will not have”, the answer would be MoSCoW; if each stakeholder votes with 100 points, it is the 100-point method.
- Question 66
Which statement correctly describes the project life cycle of most predictive projects?
Show answer and explanation
Correct answer: B
In most predictive project life cycles, risk, uncertainty and the cost of changes follow a pattern over time.
The two curves run in opposite directions. Risk and uncertainty are usually highest at the start of the project or phase and fall gradually as decisions are reached and deliverables are accepted. The cost of changes is small at the start, and the later it gets, the more work has been done and the wider the knock-on effects, so late in the project it usually rises sharply (see PMBOK 8 Figure 4-1). Of the four options, only “the cost of changes gradually rises as the project progresses” fits this pattern. The answer is B.
Why the other options are wrong
- A. This is backwards. Risk and uncertainty are high early and low later, and do not rise as the project proceeds.
- C. This is backwards. The later a change is requested, the more completed work has to be undone and the greater the cost.
- D. Near the end of a project, decisions have been made and results accepted, so uncertainty is at its lowest, not its highest.
Key takeaway Risk and uncertainty are high early and low later; the cost of changes is low early and high later.
Variation If asked at which point a change costs the least, the answer is early in the project. If asked how an adaptive approach responds to this pattern, the answer is regular reviews and frequent feedback so that risks surface earlier and changes are absorbed between iterations.
- Question 67
After the annual appraisal, a test engineer on a logistics system upgrade project asks the project manager for more specific feedback. The project manager regards him as proactive, generally delivering on time with only an occasional delay, and the key performance indicators were agreed with him at the start of the project. The engineer is disappointed that the appraisal result contains no detailed information. What should the project manager do to prevent further disappointment?
Show answer and explanation
Correct answer: B
After the annual appraisal, the test engineer wants more specific feedback. The project manager sees him as proactive and generally on time, with only an occasional delay. He is disappointed that the appraisal result has so little detail. The question asks how to prevent further disappointment.
The root of the disappointment is that he does not know how his performance turned into the appraisal result. Individual performance is assessed against key performance indicators agreed in advance, so the feedback should go back to those indicators, comparing his actual performance with each one, giving specific, constructive feedback and agreeing improvement measures. That way he can see the gap and knows where to improve in future. The correct answer is B.
Why the other options are wrong
- A. A uniform team goal describes the team's overall result. It cannot answer the question “how did I myself actually perform?”
- C. The human resources department would supply indicators for the whole project. They are not specific to him and are not feedback.
- D. A tracking tool lets him see data but does not explain how the appraisal result was reached, so the sense of missing feedback remains.
Key takeaway Individual performance feedback goes back to the key performance indicators agreed in advance, one by one.
Variation If the member's appraisal is the responsibility of the functional manager, the project manager should first align expectations and reporting frequency with the functional manager, then give the member feedback.
- Question 68
A healthcare IT project spans several branch hospitals. Planning has just ended, and the project management plan has been approved. Many stakeholders are involved. The project manager wants every key stakeholder to understand the project plan and reach consensus, and also wants the team members to commit to the project. What should the project manager do?
Show answer and explanation
Correct answer: D
The healthcare IT project's planning has just ended and the project management plan has been approved. The project manager wants key stakeholders to understand the plan and reach consensus, and the team members to commit.
“Understand the plan, reach consensus, team commitment” maps to the three tasks of the project kick-off meeting: obtain agreement on the plan, communicate the objectives and obtain the team's commitment, and make roles and responsibilities clear. Explaining the plan face to face and confirming commitment is the most direct way. The strongest distractor is C. A kick-off may review the project's purpose and high-level objectives from the charter, but reviewing only the charter does not meet the stated need to explain the approved plan and confirm commitment, so C is still inferior. The answer is D.
Why the other options are wrong
- A. Team building can improve team cohesion, but it does not give key stakeholders a shared understanding of the project management plan or confirm the team's specific commitments to that plan.
- B. Sending the file in a one-way mass email allows no discussion and does not demonstrate the team's commitment.
- C. The charter may be reviewed at the kick-off, but reviewing only the charter will not help the parties understand the approved project management plan or fully meet the needs stated in the stem.
Key takeaway To have all parties understand the plan and the team commit, hold a project kick-off meeting.
Variation If stakeholders are spread across several time zones, hold sessions by time zone and make sure the key stakeholders all take part. If someone is absent at the last minute, assess the effect on the meeting's objectives and decisions and, if needed, arrange separate communication or adjust the meeting, so that key stakeholders take part fully and understand the plan. The charter and the project management plan serve different purposes. The kick-off may review the charter's purpose and high-level objectives, but it should also build shared understanding of the approved plan and confirm commitment.
- Question 69
A project manager calls a risk identification workshop for a logistics warehouse renovation project. Most stakeholders had confirmed they would attend but are absent at the last minute. How should the project manager complete the risk register?
Show answer and explanation
Correct answer: D
At a risk identification workshop for a warehouse renovation, most stakeholders who had confirmed attendance are absent at the last minute. The question asks how the project manager should complete the risk register.
The purpose of the workshop is to collect stakeholders' views of the risks, and the absence of most of them means many risks may be missed. A sensible approach is to hold the meeting as planned, keep the input of those present, then contact each absentee afterward to fill in their input and complete the register accordingly. How complete the register is depends on how complete the input is. The answer is D.
Why the other options are wrong
- A. Continuing and sending the updated register: sending it only informs people and does not fill in the absentees' input, so the register is still incomplete.
- B. Cancelling the meeting and compiling from project documents and history alone: this discards the input of those present, and documents can only support identification; they cannot replace stakeholders' first-hand views.
- C. Reporting to the sponsor and asking them to urge attendance: absence is a communication and coordination issue the project manager should follow up personally; escalating adds no content and is not a case that must be escalated.
Key takeaway Risk identification relies on stakeholder input; absentees' views must be collected for the register to be complete.
Variation If the absentee is a key technical expert, consider a separate interview, because their views are especially important for technical risks.
Reference Risk Register · Lesson 2: Identify Risks Inputs, Outputs and Data Gathering Techniques
- Question 70
A project team uses a control chart to monitor the number of defects found each day in a module. Which of the following situations indicates that the process is out of control?
Show answer and explanation
Correct answer: C
A team uses a control chart to monitor the number of defects found each day in a module. The question asks which arrangement of points indicates that the process is out of control.
Control limits are calculated statistically, usually set three standard deviations above and below the mean, and represent the natural variation range of a stable process. Besides a point beyond the control limits, the “seven-point rule” used in exam practice holds that 7 consecutive points on the same side of the mean is also a signal that the process is out of control, because in a stable process the points should be randomly distributed around the mean, and a run on one side most likely means the mean has shifted. Note that the seven-point rule is common practice in quality management. The answer is C.
Why the other options are wrong
- A. One point on the mean line means the data happens to be at the center and does not constitute any out-of-control signal.
- B. Six consecutive points on the same side of the mean is one short of the 7-point standard. Under the rule you keep observing, and you cannot judge it out of control.
- D. Four points below the mean that are not consecutive do not form a run of 7 on one side, so on this fact alone you cannot judge the process out of control (you also have to check the chart for other abnormal signals).
Key takeaway Two kinds of out-of-control signals: a point beyond the control limits, and 7 consecutive points on the same side of the mean (the common rule).
Variation If it were changed to “one point beyond the upper control limit”, it would also be judged out of control; with 6 points on one side you keep observing.
Reference Control Charts · Lesson 2: Judging Out-of-Control Signals and Worked Chart-Reading Examples: In Control but Nonconforming, Out of Control but Conforming
- Question 71
An education chain's online course platform project enters closure, and the project manager is about to conduct a full project review. The deliverables have been handed off and the final project report has been distributed to all parties. The project records have not yet been archived, and the archive must include the lessons learned from this project review. What should the project manager do next?
Show answer and explanation
Correct answer: A
The project is in closure, the deliverables are handed off, and the final project report has been distributed to all parties. The question asks what comes next in the closure process.
The key signals are that the deliverables are handed off and the final report is distributed, and that the archive must include the conclusions of this project review. Common exam practice is to summarize lessons learned before archiving so that the archive is complete; the exact order follows organizational policy. Here, summarize and record the lessons while the team is still there and memories are fresh, then archive them with the project records. The answer is A.
Why the other options are wrong
- B. The project is already in closure, so there is no “next phase” to plan. A procurement plan is unrelated to the work now.
- C. The stem states that the archive must contain the lessons learned from this review. If you archive first, the records will be incomplete and you would have to update the archive again later.
- D. The lessons learned and other closure items are not yet done, so it is too early to have the sponsor sign off the whole closure. The signature comes after the closure work is substantially complete.
Key takeaway When the archive must contain lessons learned, summarize the lessons first, then update organizational process assets and archive.
Variation If lessons learned have already been summarized, the next step is to update organizational process assets and archive, and release resources last.
Reference Project Closure · Lesson 2: Normal Project Closure Steps: Why the Sequence Matters
- Question 72
The membership-app team of a retail chain is in the middle of a Sprint. The procurement director goes to the Scrum Master and demands that a feature the director regards as “very important” be added to the current Sprint. What should the Scrum Master do?
Show answer and explanation
Correct answer: D
A Sprint is in progress. The procurement director asks the Scrum Master to add a feature the director considers “very important” to the current Sprint. What does the Scrum Master do?
The content and order of the Product Backlog are the Product Owner's responsibility, and nobody can bypass the Product Owner to make the Developers do something else. The Scrum Master passes the request to the Product Owner, who negotiates with the procurement director. The Product Owner judges whether the requirement enters the Product Backlog and decides its order. If it truly must affect the current Sprint, the Product Owner negotiates the scope adjustment with the Developers, and the Sprint Goal must not be endangered. The Scrum Master does not decide for either side. This protects the Sprint Goal and respects the stakeholder. The answer is D.
Why the other options are wrong
- A. Adding first and talking later means the Scrum Master has already decided for the Product Owner and interrupted the Sprint in progress. Whether to adjust the scope is for the Product Owner and the team to negotiate on the basis of the order.
- B. Pushing it straight to the next Sprint is again the Scrum Master deciding the order for the Product Owner, without judging the value of the requirement, which may in fact matter more.
- C. A stakeholder's rank cannot directly change what goes into a Sprint. Adding it directly breaks the rules and undermines the team's commitment to the Sprint Goal.
Key takeaway Anyone can propose a requirement, but only the Product Owner decides whether it goes in the list and where it ranks.
Variation If the director raised an urgent problem that affects whether the current Sprint Goal can be met, the Product Owner would evaluate it and then talk with the team about whether to adjust.
Reference Scrum Roles · Lesson 1: The Product Owner: Decides What to Build, What Comes First and Whether to Accept It
- Question 73
An operations support team at a company receives service requests every day whose volume and urgency are hard to predict. The team is considering managing the work with Kanban rather than Scrum. What is the advantage of Kanban for this kind of service work?
Show answer and explanation
Correct answer: C
An operations support team receives service requests every day whose volume and urgency are hard to predict, and is considering Kanban instead of Scrum. The question asks for the advantage of Kanban for this kind of service work.
Kanban is based on flow. It has no fixed iterations, work keeps entering and being completed, and new requests can be added to the queue at any time, but they are pulled into active work only when capacity is available under the WIP limits. Service work with unpredictable demand needs exactly this “accept as they come, keep flowing” rhythm, rather than freezing a batch of requests and handling them together. The answer is C.
Why the other options are wrong
- A. Option A describes freezing every request before a fixed iteration, but Scrum does not freeze all incoming requests, and Kanban has no fixed iterations. Kanban lets new requests enter the queue at any time and pulls them into active work as capacity allows.
- B. Developers, Product Owner, and Scrum Master are Scrum's three defined accountabilities. Kanban does not prescribe those Scrum accountabilities, so this is not an advantage of Kanban.
- D. Visualizing the workflow is one of the core features of Kanban. Saying “no need to visualize” is the opposite of the facts.
Key takeaway Kanban has no fixed iterations and work flows continuously, which suits service work whose requests arrive at any time.
Variation If the stem said “a usable increment must be demonstrated to the customer every three weeks, with results confirmed in stages”, Scrum would be the better fit. The two can also be combined: use a kanban board to manage tasks inside a Scrum Sprint.
- Question 74
A chain logistics company has used its warehouse management system for ten years and decides to upgrade it, appointing an experienced project manager to lead the project. During the first round of identifying stakeholders, the project manager finds that the warehouse manager and the dispatch manager believe the current system is good enough and worry that the upgrade will slow their teams' work. What should the project manager do next?
Show answer and explanation
Correct answer: A
A warehouse management system upgrade project is at the stage of identifying stakeholders. The warehouse manager and the dispatch manager think the current system is good enough and worry that the upgrade will slow operations. You must decide the next step.
The two managers' opposition comes from worry about work efficiency. This is a concern to be addressed, not a formal change requirement. One of the activities in Manage Stakeholder Engagement is addressing concerns and managing expectations, which uses communication and interpersonal skills (listening, influencing, negotiation, conflict management). First hear what worries them, then explain how the upgrade will protect operating efficiency, and win their support. The answer is A.
Why the other options are wrong
- B. Escalating before communicating directly with the people involved tends to sharpen the conflict. Stakeholders' concerns should first be handled by the project manager through communication.
- C. Monitoring evaluates how effective existing engagement efforts are. No engagement action has been taken yet, so there is nothing to monitor.
- D. The two managers have expressed worries, not asked for a change to the scope. Going through change control does not answer why they do not support the project.
Key takeaway When stakeholders withhold support out of worry, first use interpersonal skills to address their concerns; do not escalate, run change procedures or only monitor.
Variation If the two managers made it explicit that “we will agree only if an interface function is added,” that is a specific scope request, which should be assessed and submitted as a change request through integrated change control.
- Question 75
After estimating resources for a campus landscaping project at PMLyceum, the project manager finds that the total cost of the planned resources exceeds the approved budget. What should the project manager do?
Show answer and explanation
Correct answer: C
After estimating resources for a landscaping project, the project manager finds that the total cost of the planned resources exceeds the approved budget. The question asks what the project manager should do.
The purpose of Estimate Resources is to identify the type, quantity and characteristics of the resources required and to anticipate potential shortages or surpluses, creating conditions for proactive adjustment. PMBOK 8 defines alternative analysis as a method used to evaluate identified options in order to select the options or approaches to use. When the resource plan exceeds the budget, first use it to compare different resource combinations, for example by adjusting resource types, quantities, sources or timing, to find a feasible option within budget, and then negotiate the option and its impact with stakeholders. The answer is C.
Why the other options are wrong
- A. Management reserve is for unknown risks within scope. A known estimating overrun cannot be covered by drawing on management reserve; that would use the reserve to cover up an estimating problem.
- B. Replacing everything with the lowest-priced resources ignores skills, quality and schedule. It may lead to insufficient capability and rework, and the money saved may not offset the loss.
- D. Asking for additional budget is for after there is no feasible way to optimize the plan. It should not come before optimizing the plan, and asking for money outright shows a lack of analysis.
Key takeaway When resource cost exceeds the budget, do an alternative analysis to optimize first and then negotiate with stakeholders; do not simply ask for money or swap resources at random.
Variation If after the alternative analysis every option still exceeds the budget, the next step is to submit a change request, to be approved by authorized persons or bodies under the project's change control procedure; the sponsor may take part in the decision or provide support.
Reference Estimate Resources and Acquire Resources · Lesson 1: Estimate Resources: Requirements, Basis and the Resource Breakdown Structure
- Question 76
A multi-department project at a multinational group enters a new phase, and several new stakeholders join, with conflicting priorities. To communicate with them effectively, what should the project manager do?
Show answer and explanation
Correct answer: A
A multi-department project at a multinational group enters a new phase and several new stakeholders join with conflicting priorities. The question asks how to communicate with them effectively.
After new stakeholders are added, first identify and classify them, for example with the mapping and representation methods PMBOK 8 describes, such as the power/interest grid, directions of influence or the salience model, so you know who matters and who cares about what, and can then set differentiated communication and engagement strategies for the different types. Classify first and then differentiate: that is the workable path. The answer is A.
Why the other options are wrong
- B. With many people whose priorities differ, a uniform status meeting is too large and unfocused, some people feel it has nothing to do with them, and communication is poor.
- C. Talking to each one separately is costly and unsystematic, tends to create information silos and cannot coordinate their conflicting priorities.
- D. Recognizing diversity is only an attitude with no concrete action, which is not enough to ensure effective communication. Classifying is the workable first step.
Key takeaway When stakeholders are many and complex, classify first and then communicate in a differentiated way.
Variation If only one stakeholder is added, do a separate assessment and update the register; there is no need to reclassify everyone.
Reference Identifying and Analyzing Stakeholders · Lesson 3: Stakeholder Mapping and Classification: the Power/Interest Grid and Other Models
- Question 77
The PMO at PMLyceum is training newly hired project managers and explaining how organizational process assets are classified. The training material lists four items and asks the trainees to pick the one that belongs to the “organizational knowledge repositories” and not to “policies, processes and procedures.” Which one would you choose?
Show answer and explanation
Correct answer: C
You must decide which category of organizational process assets an item belongs to.
The issue and defect management database stores the status, control information and resolution results of issues and defects and is updated continuously with project information, so it is an organizational knowledge repository, while the question asks you to exclude the category of “policies, processes and procedures.” The way to tell is to ask one question: does this item prescribe how the organization requires things to be done, or does it record what has happened? The former goes under policies, processes and procedures, and the latter under organizational knowledge repositories. Choice C is a record, so the answer is C.
Why the other options are wrong
- A. A change control procedure is a process that prescribes how changes are raised, reviewed and approved. It belongs to policies, processes and procedures and is usually not updated as part of project work.
- B. A preapproved supplier list and contract templates belong to policies, processes and procedures, established by the organization as a whole. They are rules to follow, not data accumulated by projects.
- D. Templates and tailoring guidelines and criteria all belong to policies, processes and procedures. They guide how to tailor standard processes to the needs of the project and are not records produced by a project.
Key takeaway Rule-type assets (policies, processes, procedures, templates, tailoring guidelines) are generally not updated with the project; record-type assets (defects, lessons learned, financial data) are continually updated with the project.
Variation If the question were changed to “pick the item that belongs to policies, processes and procedures,” A, B and D would all qualify; remember in particular that tailoring guidelines are organizational process assets, not enterprise environmental factors.
- Question 78
A company decides to outsource development of its customer service system. The statement of work, source selection criteria and bid documents have all been prepared, but the bid documents have not yet been issued, and the procurement management plan calls for national competitive bidding so that proposals are received from sellers. What should the project manager do next?
Show answer and explanation
Correct answer: B
The project is in the procurement stage. The statement of work, source selection criteria and bid documents are ready, no seller proposals have been received, and the question asks for the very next step.
The signals: the SOW, selection criteria and bid documents are all prepared, the procurement management plan requires competitive bidding so as to “receive proposals from sellers”, and no proposals have arrived. For sellers to write proposals they must first have the bid documents, so the very next step is to issue them. The bidder conference is held after the bid documents go out and before proposals are submitted; evaluation has to wait until proposals are in hand; negotiation comes after the seller is selected. The answer is B.
Why the other options are wrong
- A. The bidder conference is held after the bid documents are issued and before proposals are submitted, to clarify requirements. The bid documents have not been issued, so there is nothing to hold a meeting about.
- C. Evaluation takes place after sellers submit proposals, and there are none yet.
- D. Procurement negotiation takes place after the seller is selected and before the contract is signed, which is much later.
Key takeaway Once the bid documents are completed, the next step is to issue them.
Variation If the stem said “the bid documents have been issued and sellers have many questions”, the next step is the bidder conference; if it said “all proposals have been submitted”, only then does evaluation come.
- Question 79
On a smart watch development project, the measurement accuracy of the heart rate sensor is an important acceptance criterion. The project manager wants to compare against the acceptable range for that accuracy and to judge whether the measurement process is stable and its performance predictable. Which of the following tools is the most suitable?
Show answer and explanation
Correct answer: D
On a smart watch development project, heart rate sensor measurement accuracy is an acceptance criterion. The project manager wants to compare against the acceptable range of the accuracy and to judge whether the measurement process is stable and its performance predictable, and asks which tool is the most suitable.
PMBOK 8 explains that the purpose of a control chart is to determine whether a process has stayed stable and whether its future performance can be predicted. The chart can also show the upper and lower specification limits (the maximum and minimum values allowed, set from requirements) together with the control limits (calculated statistically, representing the natural capability of a stable process). The stem asks to compare against the acceptable range (the specification limits come from requirements) and to judge stability and predictability, which is exactly what a control chart is for. Do not confuse specification limits with control limits. None of the other three tools can show limits and judge stability at the same time. The answer is D.
Why the other options are wrong
- A. A scatter diagram represents the relationship between two variables. It does not draw an acceptable range and does not judge whether a process is stable.
- B. A Pareto chart sorts by frequency and finds the few causes that produce most of the problems (Pareto chart is a common exam term). It does not judge stability.
- C. A cause-and-effect diagram traces the root cause of a problem. It is a tool for finding causes once something has gone wrong and cannot set a range or judge stability.
Key takeaway To see whether a process is stable, whether performance is predictable and whether the data are within limits, choose the control chart.
Variation If you wanted to know whether heart rate sensor drift is related to ambient temperature, choose a scatter diagram; to find the few categories of causes with the largest errors, choose a Pareto chart.
Reference Control Charts · Lesson 1: What Control Charts Are For, and Control Limits Versus Specification Limits
- Question 80
Team members fear that AI tools will replace them, so they resist using the newly introduced AI-assisted tool. What should the project manager do?
Show answer and explanation
Correct answer: A
Team members fear that AI tools will replace them, so they resist the newly introduced AI-assisted tool. What should the project manager do?
The root of the resistance is worry about their jobs, not the tool itself. PMBOK 8 asks project professionals to foster a culture in which team members understand AI and use it ethically. Listening to and validating the concerns first, explaining candidly how the tool may affect tasks and roles, and using training to help members master it will address the worry and raise acceptance. In practice you can listen to the worries first, then explain which repetitive work the tool will take over and which higher-value tasks members' work will shift to, give a learning plan, and let members take part in trials and give feedback. The answer is A.
Why the other options are wrong
- B. Forcing use and deducting points will deepen the resistance and does not address members' worries.
- C. Criticizing the resistance and asking people to put the big picture first only drives the worry underground and does not change attitudes.
- D. Ending the introduction does not respond to the problem and gives up the efficiency gains AI brings.
Key takeaway When members fear being replaced, respond with communication, explanation and empowerment through training, not force or criticism.
Variation If the same situation occurred across the whole organization, change management should make the path of the transition clear and arrange retraining. If asked about “the team cannot use the ready-made platform”, the answer is to ask someone familiar to coach.
- Question 81
At the weekly project meeting, a team member reports bad news that will seriously slow the schedule. How should the project manager respond so that the project stays successful?
Show answer and explanation
Correct answer: C
At the weekly meeting, a team member volunteers bad news that will seriously slow the schedule. The question concerns the project manager's attitude toward bad news and first reaction.
The key signal is “so that the project stays successful”: it is a good thing that bad news is surfaced promptly, and the project manager should steer the discussion toward a solution, that is, analyzing the impact and working out how to recover the schedule and get the project back on track, and also record the issue in the issue log. This protects a climate in which the team is willing to report and puts effort into removing the impact. The answer is C.
Why the other options are wrong
- A. Repeatedly stressing how serious it is only adds pressure and does not help recover the schedule; the aim is to solve the problem, not to dramatize it.
- B. Criticizing the person who reports makes everyone afraid to report bad news in future, and problems will be hidden until they are out of control, with consequences worse than this delay.
- D. Thanking and noting it down is right, but moving straight to the next item means there is no follow-up on a serious issue, and the schedule keeps being dragged down.
Key takeaway Faced with bad news, first affirm the person who surfaced the problem, then focus on how to recover, rather than assigning blame or dramatizing.
Variation If it turns out the member had been hiding the problem before, besides discussing recovery, talk with the member about the requirement to report promptly and build an environment of safe communication.
Reference Issue Management · Lesson 2: Problem Solving: The Six Steps and Root Cause Analysis
- Question 82
The members of a preparation group for a home goods trade show now understand their roles and responsibilities, but lately they argue often about the exhibit layout, and meetings frequently end badly. Which stage of the Tuckman ladder is the team in now?
Show answer and explanation
Correct answer: A
The preparation group already understands its roles and responsibilities, but recently it has argued often over the exhibit layout and meetings often end badly. The question asks which Tuckman stage the team is in.
There are two key pieces of information. First, roles and responsibilities are already clear (learning about roles and responsibilities can also happen in the Forming stage, so it cannot decide the question alone). Second, members have begun to deal with the specific plans and approach but are unwilling to accept differing views, with constant arguments and meetings that cannot proceed. This is the typical picture of the Storming stage, in which conflict is at its highest and performance tends to be lower. Preparation work is still going on, and there is no sign of interdependence or of disagreements being resolved by the team itself. The answer is A.
Why the other options are wrong
- B. The Adjourning stage is when work is complete and members leave the project. Preparation is still under way and the team has not been disbanded.
- C. A team in the Performing stage functions as a well-organized unit and works through disagreements smoothly, the opposite of “meetings end badly.”
- D. In the Norming stage arguments have clearly decreased and members begin to act on what they have agreed. Here the arguments are still frequent, so the team has not reached this step.
Key takeaway Clear roles but frequent arguments and meetings that cannot proceed point to Storming. Clearly fewer arguments and acting on agreed ways of working point to Norming.
Variation If the stem said arguments had clearly decreased and members had started reviewing the layout using the process everyone agreed on, the answer would be the Norming stage. If it said members had just met, were polite to one another and no one raised an objection, the answer would be the Forming stage.
- Question 83
Midway through the project, a functional manager replaces a member. The new member is looking for a chart that shows project team members and their reporting relationships graphically. Which should the project manager suggest he look at?
Show answer and explanation
Correct answer: C
Midway through the project, a member is replaced, and the new member is looking for a chart that is specifically a graphical display of team members and their reporting relationships. The locating phrase is “graphically shows reporting relationships”.
PMBOK 8 describes a project organization chart as a graphical display of project team members and their reporting relationships, which can be formal or informal, highly detailed or broadly framed. So a new member who wants to understand the team and reporting lines should look at it. The chart is part of the resource management plan and is updated as the team changes, so a new member joining should also be given the latest version. The answer is C.
Why the other options are wrong
- A. The resource management plan does contain the project organization chart, but it is the whole plan, with roles and responsibilities, training, team development and more, and is not the dedicated chart showing reporting relationships that the stem asks for.
- B. The responsibility assignment matrix shows the relationship between people and work packages or activities, so it shows who does what but not reporting lines.
- D. The resource breakdown structure layers resources by category and type. It does not show specific people and has no reporting relationships.
Key takeaway To see the team's makeup and reporting lines, find the project organization chart, which is part of the resource management plan.
Variation If the new member wants to know who is accountable for an activity, look at the responsibility assignment matrix instead. If he wants to know how the team is developed and trained, look at the matching sections of the resource management plan.
Reference Responsibility Assignment Matrix and RACI · Lesson 3: The Resource Management Plan: What It Contains and How to Use It
- Question 84
An equipment installation project has a budget at completion of $90,000, current earned value of $36,000 and actual cost of $45,000. The project manager expects cost efficiency from now on to stay the same as it is now. What is the estimate to complete (ETC)?
Show answer and explanation
Correct answer: C
BAC is $90,000, EV is $36,000, AC is $45,000, and cost efficiency from now on will be the same as now. What must be calculated is how much more will be spent (ETC), not total cost.
Cost efficiency continues, so this is a typical variance, and the remaining work must be adjusted by the current CPI. First calculate CPI, then divide the remaining budget by CPI to get the money still to be spent. The answer is C.
- CPI = EV ÷ AC = 36 ÷ 45 = 0.8
- EAC = BAC ÷ CPI = 90 ÷ 0.8 = $112,500
- ETC = EAC − AC = 112,500 − 45,000 = $67,500
- Check: calculating directly, (BAC − EV) ÷ CPI = (90 − 36) ÷ 0.8 = $67,500. They agree, so the answer is C
Why the other options are wrong
- A. $45,000 = BAC − AC is the budget at completion minus the money already spent. It is neither the budgeted value of the remaining work (BAC − EV = $54,000) nor adjusted for efficiency.
- B. $54,000 = BAC − EV is the budgeted value of the remaining work. It equals ETC only when efficiency matches the budget, and here CPI is 0.8.
- D. $112,500 is EAC, the total cost at completion. It does not deduct the $45,000 already spent.
Key takeaway ETC = EAC − AC; under a typical variance, ETC = (BAC − EV) ÷ CPI.
Variation If the variance were a one-time event, ETC = BAC − EV = $54,000. If the remaining work were re-estimated at $60,000, ETC is simply $60,000.
- Question 85
A software company's customer management system project is in closure. A key stakeholder wants to know how the project turned out and asks the project manager for a report that reflects customer satisfaction. What should the project manager do?
Show answer and explanation
Correct answer: A
The customer management system project is in closure, and a key stakeholder asks for a report that reflects customer satisfaction. The question asks what method to use to get the information.
PMBOK 8 lists measuring stakeholder satisfaction among the closure activities. Satisfaction is the customer's subjective impression, and the most direct way is to send customers a satisfaction questionnaire and compile the returned results into a report, with a uniform basis and data coming straight from the customer. The answer is A.
Why the other options are wrong
- B. The issue log reflects how issues were handled. Well-resolved issues do not mean a satisfied customer, so satisfaction cannot be inferred from it.
- C. The lessons learned register records the team's lessons for improving later work. It does not contain the customer's judgment of whether the results are satisfactory.
- D. A thank-you email is not designed to obtain satisfaction. Replies are scattered and lack a uniform basis, so they cannot make a reliable satisfaction report.
Key takeaway To learn customer satisfaction, use direct means such as questionnaires and interviews, not inference from issue records or lessons.
Variation If the stem asked “how to show the project's overall performance”, the answer is the final report with key performance indicators. If it asked “how to confirm the results meet the acceptance criteria”, look at the acceptance document.
- Question 86
A retail chain group, seeing its peers move to agile, rolls out a certain agile framework across the whole company without assessing how well its culture fits agile or defining the target state. It invests a large budget, but the rollout fails after a few months. Looking back, what should the project manager have done differently to avoid this outcome?
Show answer and explanation
Correct answer: B
A retail chain group rolls out agile company-wide only because its peers are moving to agile, without assessing cultural fit or defining the target state, and invests a large budget, but the rollout still fails after a few months. You must decide what should have been done differently beforehand.
Agile is not a universal solution for every organization and project. The cause in this scenario is only that “peers are all using it”; no assessment was made before rollout. The first step of a transformation is to assess organizational culture, governance, and existing capability, decide whether agile applies, and define the target state after transformation; once agile is confirmed to apply, training, pilots, and external support have a direction. The answer is B.
Why the other options are wrong
- A. Training comes after assessment confirms that agile applies. Training everyone before it is known whether the culture fits only magnifies the investment.
- C. A review is a remedy after failure and cannot “avoid” this failure, which does not match the question.
- D. An external team can add implementation capability but cannot replace the judgment of cultural fit, and cultural resistance remains.
Key takeaway Transformation means assess first, then act: look at culture and suitability and set the target state.
Variation If the question asked what to do “after the failure,” the answer would be to review and consolidate the lessons; if it asked “after assessment confirms suitability,” the answer would be training plus a pilot.
- Question 87
On an airport information-system upgrade project, the project manager learns that a member who develops the core interface plans to leave the project in a month. The successor cannot acquire the same expertise within a month, so the project may be delayed. What should the project manager do?
Show answer and explanation
Correct answer: D
On an airport information-system upgrade, the member who develops the core interface plans to leave in a month, and the successor cannot acquire the same expertise in that time, so the project may be delayed. The question asks what the project manager should do.
The stem says “may”, which shows the delay has not happened, so this is a newly identified risk. One output of Identify Risks is the risk register (the process also produces the risk report), so first update the risk register, recording the cause (the member's departure), the event (interface development delayed) and the consequence, after which it moves on to analysis and response. The order is record first, then analyze, then respond. The answer is D.
Why the other options are wrong
- A. Earned value analysis assesses performance that has already happened. The member has not left, so current progress may show no deviation, and the analysis cannot solve a risk that has not happened.
- B. Finding ways to speed up the successor's integration is one line of response, but going to the sponsor before the risk has been logged and analyzed is out of order and leaves no record.
- C. Revising the resource management plan may come only after the response is decided, so it is not the first step, and the sponsor's expectations are not relevant.
Key takeaway When you see “may”: log the risk first, then talk about analysis and response.
Variation If the member has already resigned, the successor is not yet in place and interface development has stalled, it is an issue, to be recorded in the issue log and handled according to the response measures.
Reference Risk Register · Lesson 1: Identify Risks: Purpose, Characteristics and Handling New Risks
- Question 88
On a platform project, two subsystem teams are responsible for integration, and a key interface point was not aligned, causing delay. Team A's integration lead is a subject matter expert (SME); Team B's integration lead is not an expert but is more senior and has been on the project longer. The two blame each other. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
Two subsystem teams on a platform project must integrate, but a key interface point was not aligned and caused delay. Team A's integration lead is an SME; Team B's is not an expert but is more senior and has been on the project longer. They blame each other. The question asks what the project manager should do first.
Mutual blame shows that the two have different perceptions of responsibility and cause. PMBOK 8 says conflict arises from people perceiving the same situation differently and that the focus should be on resolving the situation, not casting blame, with a direct, collaborative approach. The project manager should first meet with both leads, find the root cause of the misaligned interface and then agree on a solution together, which both sides are more likely to accept. The answer is D.
Why the other options are wrong
- A. Handing the problem to the SME lead takes the SME's side, and the other side will not accept it. The mutual blame is not removed.
- B. The architect only drew up the integration plan. Referring the problem there does not establish why the interface is misaligned, and it dodges the coordination the project manager should do.
- C. Seniority and long service do not make someone's judgment on the problem more accurate. Giving it to that lead is equally one-sided and deepens the other side's resentment.
Key takeaway When people blame each other, get the parties together to find the root cause; do not assign the solution to one of them.
Variation If the root cause turns out to be an unclear interface document, the next step is for the two sides to clarify and update the document together and then align the interface point.
Reference Conflict Management · Lesson 3: Judging Conflict Scenarios: From Identifying the Source to Choosing the Right Action
- Question 89
The team is in the middle of the current Sprint and things are going well. One early morning, a customer representative calls and asks for an urgent meeting. You are a little surprised, because the customer is very happy with the features already developed. At the meeting he says he would like to add one more feature in this Sprint, and asks whether the Sprint can be extended by a few days for it. How should you answer?
Show answer and explanation
Correct answer: D
The team is in the middle of a Sprint and doing well. A customer representative asks to add one more feature in this Sprint and asks whether the Sprint can be extended. How should you answer?
In Scrum, the current Sprint is a fixed-length timebox and the team works toward the Sprint Goal. As more is learned, the Developers may clarify and renegotiate scope with the Product Owner, but the timebox is not extended. The new feature can be recorded in the Product Backlog and considered by priority in later Sprints, but it cannot be accommodated by extending the current Sprint. The customer's good mood is no exception. The answer is D.
Why the other options are wrong
- A. The Sprint length is fixed, and whether to extend does not depend on the effort of the new feature. Assessing first and deciding afterward also implies that an extension is possible.
- B. A timebox has no exception for “occasionally extending”. An important customer requirement should also go through backlog ordering and not change the Sprint length.
- C. The Scrum Master's job is to uphold the rules and protect the team, with no authority to extend the Sprint for a new feature. Even if the Scrum Master agreed, the length would not change.
Key takeaway A Sprint is a fixed-length timebox: a new feature goes into the backlog and is not accommodated by extending the Sprint.
Variation If the team wants to extend by one day before the review to finish the last feature, the answer is the same: the timebox stays and unfinished work returns to the backlog. Only if “the Sprint Goal has lost its meaning” would the Product Owner consider canceling the Sprint.
- Question 90
The members of a multinational project come from several countries. After identifying communication needs, the project manager finds that each member needs different lessons learned, and so builds a company intranet that lets members search for them on their own. Which communication method has the project manager adopted?
Show answer and explanation
Correct answer: D
On a multinational project, the project manager finds after identifying communication needs that each member needs different lessons learned, and builds a company intranet for members to search on their own. Which communication method is this?
Communication methods are classified by how information flows into push, pull and interactive. Content on the intranet is looked up by recipients themselves rather than sent by a sender to specific people, which is the typical practice of pull communication, suited to large, complex information sets or large audiences. In the question, members are spread across countries and each needs different content, so pushing to each one individually would be inefficient and imprecise; letting members take what they need is the right fit. Lessons learned databases and knowledge repositories are of the same kind. The answer is D.
Why the other options are wrong
- A. Push sends information directly to specific recipients; content on the intranet is looked up by members themselves, not sent.
- B. Interactive communication is a real-time multidirectional exchange, and searching an intranet involves no real-time exchange.
- C. By how information flows, the communication methods are push, pull and interactive; “portal communication” is not one of these three methods. A web portal is usually just a vehicle for pull communication.
Key takeaway An intranet, a knowledge repository or a public web page, anything the recipient accesses on their own, is pull communication.
Variation If the project manager compiled the lessons learned each week and emailed them to every member, that would be push; if an online workshop were held for members to exchange ideas, that would be interactive.
- Question 91
During an iteration, you are the agile team lead and look at the kanban board. The team has not set WIP limits, work items are piled up in some process steps while other steps sit idle, and the team's velocity swings up and down. As an agile practitioner, what should you do?
Show answer and explanation
Correct answer: B
During an iteration, the kanban board shows work items piled up in some steps while other steps sit idle, and the team's velocity swings up and down. The question asks what the team lead should do.
The root of the problem is uneven distribution of work: some steps are jammed and others idle, so flow is blocked. The remedy is to set WIP limits on each process step on the kanban board, fixing the maximum number of work items each step may hold. When a column is full, upstream stops and puts its capacity into helping downstream, so overall flow evens out and velocity steadies. The limits are not there to get less done; they are there to stabilize flow first, and once it is stable the swings in velocity narrow as well. The answer is B.
Why the other options are wrong
- A. The problem is uneven distribution of work, not too many work items. Cutting items outright loses requirements and does not fix the unevenness.
- C. Little's Law can estimate average WIP, throughput or cycle time, but it is only a measurement relationship. It cannot directly remove the pile-up at a step or the imbalance in flow.
- D. Bringing in outside people is a temporary transfusion. It changes no process rules, so the pile-up will return and the pressure may move downstream. Idle team members with the appropriate skills may effectively swarm the bottleneck, but this option brings in people from outside the team without changing the process rules, so the flow imbalance remains.
Key takeaway When work piles up at a step on the kanban board, set a WIP limit for that step so flow evens out.
Variation If the stem said “you want to know how long each piece of work takes on average”, that is when Little's Law applies. For example, with 12 items in progress and throughput of 4 per day, the average is 12 ÷ 4 = 3 days.
- Question 92
You are a project manager at a smart hardware company. Your team is developing a companion app for a new product. Early in the project the team identified risks and planned responses, and for one specific risk set aside part of the schedule as contingency reserve. During execution that risk occurs and delays the related activities by one week. It is not yet clear whether the project completion date will be affected. What should you do next?
Show answer and explanation
Correct answer: C
During execution, a risk identified early, with part of the schedule set aside as contingency reserve, occurs and delays the related activities by one week. It is not yet clear whether the completion date is affected. The question asks for the next step.
The signals are “identified early,” “set aside time as contingency reserve” and “one week delay”: this is a registered risk with a planned response and reserve, but the schedule impact still needs to be analyzed using the activity logic, total float and placement of the reserve. First consult the risk register, check the response and analyze the schedule impact to determine whether the planned response and contingency reserve can absorb the delay. If they can, use the reserve within your authority (common exam practice); if the reserve is already inside the baseline, the baseline does not change. If they cannot absorb the delay and a baseline must change, raise a change request. The answer is C.
Why the other options are wrong
- A. Analyzing the impact is part of the first step, but A bundles it with immediately submitting a change request. Submit a change request only if the analysis shows that the planned response and reserve cannot absorb the delay and a baseline must change.
- B. A workaround is for threats with no planned response or where the existing response is ineffective. This risk has a response and a reserve, so check the register first and handle it as planned.
- D. The risk has occurred, so its probability is 100%. There is no need to assess probability and impact or re-rate it.
Key takeaway When an identified risk occurs, check the register and analyze the impact to determine whether the planned response and contingency reserve can absorb it; use change control if a baseline must change.
Variation With 3 days of reserve and a 7-day activity delay, analyze the effect on the completion date using the activity logic and total float; raise a change request only if the analysis shows that a baseline must change. If the planned response and 10 days of reserve can absorb a 7-day delay, use the reserve within your authority, and if it is already in the baseline, the baseline stays unchanged.
- Question 93
A sports arena project is still in early planning, and its construction plan has not yet been approved; construction is expected to begin once approval is obtained. Merchants around the site worry that noise and dust during construction will hurt their business, and they feel resistant to the project. What should the project manager do?
Show answer and explanation
Correct answer: C
Construction of a sports arena is about to begin. Nearby merchants worry that noise and dust will hurt their business and resist the project. You must decide what the project manager should do.
When an external stakeholder has concerns, communicate early to learn their needs and expectations. Early in a project the cost of adjusting the plan is small; modestly optimizing work hours and dust control measures can often resolve the resistance and also win cooperation for the construction to come. Because the project is still in early planning and the construction plan has not yet been approved, there is still room to assess and optimize the plan before approval. For resistance from external stakeholders, the principle is to communicate early and adjust early, not to wait until the dispute becomes public and then repair it. The answer is C.
Why the other options are wrong
- A. Ignoring the resistance and waiting until it escalates into action costs much more, and it goes against the requirement to manage stakeholder expectations.
- B. The merchants are stakeholders the project has to manage. Passing the coordination to the owner means not taking on the responsibility for managing their engagement.
- D. Recommending cancellation because of concerns is an overreaction and not the project manager's natural first response.
Key takeaway When stakeholders resist, listen early and adjust early; that costs the least.
Variation If the merchants have already blocked the gate to stop construction, first steady the scene and meet with their representatives before resuming negotiation. The later the timing, the fewer the options.
- Question 94
The operating rooms in a hospital must have power around the clock. The facilities department has made arrangements in advance: if the main line loses power, it switches at once to a second utility feed; in addition it keeps a diesel generator set in case both utility feeds are unavailable. Under common exam practice, which of the following is this an example of?
Show answer and explanation
Correct answer: A
The operating rooms in a hospital must have power around the clock. The facilities department has arranged in advance: if the main line loses power it switches at once to a second utility feed, and it keeps a diesel generator in case both feeds are unavailable. You must decide what each of the two layers is.
PMBOK 8 calls strategies designed for use only if certain predefined conditions occur contingent response strategies; “contingency plan” and “fallback plan” are common exam terms for these. Both layers here were prepared in advance for an identified risk (a power loss). Under common exam practice: in the first layer, when the risk occurs the team follows the predefined steps and switches to the second utility feed, which is a contingency plan. The second layer, “in case both feeds are unavailable,” is a backup that comes into use only when the contingency plan fails, which is a fallback plan. This layering is common exam practice. A workaround is an improvised response developed after a threat occurs when no applicable response was planned. Both layers here were prepared in advance, so neither is a workaround and the answer is A.
Why the other options are wrong
- B. The second layer is not a workaround. A workaround is a makeshift fix thought up after the fact, whereas the diesel generator was prepared in advance, so under common exam practice it is a fallback plan.
- C. The first layer is not a workaround. A power loss is an identified risk, and switching to the second feed is a predefined step, so it is a contingency plan.
- D. The second layer is also planned in advance and is not an improvised reaction developed because no applicable response was available, so it does not fit a workaround. “Contingent response strategy” is also the name of the whole category and does not distinguish the two layers.
Key takeaway Responses prepared in advance and used when a trigger condition occurs are contingent response strategies. Under common exam practice, the contingency plan is the first layer, the fallback plan is the backup if it fails, and a workaround is improvised after a threat occurs when no applicable response was planned.
Variation If the cause of the failure had been something nobody anticipated and the team could only improvise, that would be a workaround, not a contingency plan or a fallback plan.
- Question 95
A logistics company's warehouse system upgrade project uses a hybrid approach: hardware deployment proceeds as planned and application development is iterative. When reporting to senior management, how should the project manager present progress on the application development part?
Show answer and explanation
Correct answer: A
On a hybrid project, hardware deployment follows a predictive approach and application development is iterative. How should the project manager present progress on application development when reporting to senior management?
Senior managers care about value and results, not the team's internal units of workload. Application development is the adaptive part, so use the value outcomes already delivered together with trend metrics such as a burndown chart: that shows what has been produced and where it is heading, and it can support senior management's decisions. When reporting the agile part to senior management, prefer value, outcome and trend metrics. The answer is A.
Why the other options are wrong
- B. Story points are the team's internal estimating unit. Cumulative story points and hours consumed show only busyness and say nothing of value or direction, so in a senior management report they may become vanity metrics (PMBOK 8: a vanity metric shows data but does not provide useful information for making decisions). Inside the team, remaining story points or hours can be used for a burndown chart and the story points finished in each iteration for velocity.
- C. The scope of iterative development is adjusted dynamically. Reporting percent complete of activities on a Gantt chart applies a predictive practice and does not show how value is being delivered.
- D. Budget execution is only one side of progress. Senior management needs to know about value and outcomes, and reporting only spending cannot present development progress.
Key takeaway When reporting the agile part to senior management, prefer value, outcome and trend metrics; workload and activity percentages may be vanity metrics if they cannot support decisions.
Variation For the hardware deployment part, traditional schedule and cost metrics can be used; when showing iteration progress inside the team, burndown charts and completed story points are appropriate.
- Question 96
The project manager notices that when the team meets to make decisions, a few people always dominate while everyone else stays silent. What should the project manager do?
Show answer and explanation
Correct answer: D
The project manager notices that in team decision meetings a few people always make the call while everyone else says almost nothing.
PMBOK 8 asks for inclusive decision-making. Team decision-making often follows a diverge/converge pattern: stakeholders first generate a broad set of alternatives, often individually, to avoid senior or charismatic members unduly influencing others, and then the team converges on a preferred solution. Letting everyone state a position also raises buy-in and commitment to the decision. The project manager should give everyone an equal chance to speak, for example by having members write down options independently before pooling them or by going around the table, and should encourage quiet members to express themselves. The answer is D.
Why the other options are wrong
- A. Defaulting to the dominant few reinforces the situation in which a few people decide, and other members participate even less.
- B. Cancelling team decision-making and deciding himself only replaces a few dominant members with the project manager. The team is still bypassed.
- C. Shortening meetings only cuts down the chances to speak, leaving silent members even less opportunity to take part, and does nothing to solve the problem.
Key takeaway When team decisions are dominated by a few voices, create an atmosphere of equal participation instead of shortening meetings or deciding for the team.
Variation If the decision were beyond the team’s authority, the team should investigate alternatives, set out the impact of each and escalate to someone with the proper authority, bringing not only the problem but also solutions.
- Question 97
A project manager is appointed to lead a large and complex supply chain information platform project. Its scope is now stable, and the earlier scope increases were approved and their impacts analyzed. Previously he managed only small internal tool development, and since the project entered the Executing focus area he has run into one problem after another. At a stakeholder meeting, a functional manager mentions that the company recently completed a platform project of similar complexity. The company's PMO keeps historical project records and provides guidelines. What should the project manager do?
Show answer and explanation
Correct answer: A
The project is in the Executing focus area. The project manager lacks experience with complex projects, the company has completed a similar project, and the PMO keeps historical project records and provides guidelines. What should the project manager do?
A PMO supports project managers by managing shared resources, identifying best practices, developing policies and templates, and providing guidance. Because the company has done a similar project, its historical records and guidelines are organizational process assets, and the best first step is to consult the PMO and learn from them. The problems the project manager is facing have very likely occurred before. The answer is A.
Why the other options are wrong
- B. The stem states that the earlier scope increases were approved and their impacts already analyzed, so repeating that analysis is not the most useful next step. The project manager should first draw on the organization's existing experience from a similar project.
- C. Bringing stakeholders together can be a parallel or follow-up measure, but the stem already offers reusable experience from a similar project, so consulting the PMO for records and guidelines is the most direct first step.
- D. Continuing the old small-project approach neither draws on the company's similar project nor deals with the current problems, and it defers lessons learned until the project ends. The PMO already holds historical records and guidelines, so consult them first.
Key takeaway When the company has a similar project, consult the PMO for historical records and guidelines first, then consider other approaches.
Variation If the project manager finds no similar project records at the PMO, the next step is to analyze the impacts and root causes of the current problems or discuss them with stakeholders. If the problem were instead “a procurement project's supplier delivery dates keep slipping”, first communicate with the supplier to understand the cause of the delays; the project manager can then consult the PMO's supplier evaluations and problem-handling records.
- Question 98
A data center migration project is two weeks from acceptance, and the sponsor keeps calling to demand that there be no further delays. The team has performed steadily so far, and the project manager wants everyone to maintain this level of performance through the end. Which approach would BEST motivate the team?
Show answer and explanation
Correct answer: C
A data center migration project is two weeks from acceptance, the sponsor keeps pressing, the team has been steady so far, and the project manager wants it to maintain that level of performance to the end. The question asks which approach best motivates the team.
Motivation comes from prompt recognition and rewarding of desirable performance. The team has been steady throughout, and recognizing their effort with certificates is direct, specific recognition that shows good performance is noticed and makes people more willing to keep it up to the last moment. With only two weeks to acceptance and the team producing steadily, what they need most is to be acknowledged, not more pressure or orders. The certificate is a phase-level public recognition for the whole team. If the reward were for an individual, you would first learn the person's preferences. The correct answer is C.
Why the other options are wrong
- A. A written notice to maintain standards is an instruction. It does not recognize members' work and so has no motivating effect.
- B. Passing on the sponsor's urging unchanged only adds to the team's anxiety, and it is not recognition.
- D. Bringing in temporary helpers can share the workload, but that is a resource measure and not an incentive for performance.
Key takeaway Motivate through prompt recognition of good performance, not through orders and pressure.
Variation If the team is tired from long periods of overtime, then besides recognition you should also honor the rewards you promised and watch the workload.
- Question 99
On a website redesign project, the agile team finds that one testing technique may fail to detect security vulnerabilities during the next several iterations. How should the team respond to this risk?
Show answer and explanation
Correct answer: C
On a website redesign project, the agile team finds that a testing technique may fail to detect security vulnerabilities during the next several iterations. The question asks how the team should respond to this risk.
An adaptive project uses a risk-adjusted backlog to keep risk response work in line with dynamic requirements. The risk affects the next several iterations, so first order it during backlog refinement, then have the team decide at the iteration planning meeting which iteration will handle it. That way the risk work is managed together with all other work. The answer is C.
Why the other options are wrong
- A. Having the agile coach settle it for the team: a self-organizing team should solve its own problems, and the coach facilitates rather than handles the team's risks.
- B. Only logging it in the risk register and returning later: recording alone does not get the risk handled; it has to enter the backlog and iteration plan before anyone works on it.
- D. Stopping the discussion, replacing the technique at once and notifying everyone: without team discussion this is not a joint decision and may affect other work.
Key takeaway In agile, a risk enters the backlog ordering, and the iteration planning meeting decides whether to handle it.
Variation If the weakness has already caused test failures in the current iteration, it is an issue and should be raised and handled at the daily coordination meeting right away.
Reference Risk Management Plan · Lesson 2: Project Resilience, Integrated Risk Management and Tailoring
- Question 100
To reduce the risk of a key part going out of stock, the project team switches its purchasing to a different supplier. It then finds that this supplier's delivery times are very unreliable, which creates a new risk that did not exist before. What should the project manager do?
Show answer and explanation
Correct answer: B
To reduce the risk of a key part being out of stock, the team switches its purchasing to a different supplier, then finds that this supplier's delivery times are very unreliable, which creates a new risk that did not exist before. How should the project manager respond?
A new risk that arises directly from implementing a risk response is called a secondary risk (a common exam term; new risks must also be identified and responses planned for them). It is handled as a new risk: identify it, record it in the risk register and plan a response for it. The unreliable delivery in the stem is brought about by the measure of changing suppliers, which fits the definition of a secondary risk. The answer is B.
Why the other options are wrong
- A. That the original risk is reduced does not mean you can stop paying attention. A secondary risk can affect project objectives just as much, and ignoring it lets the project carry on with a new unmanaged risk.
- C. Immediately reversing the supplier change is premature before comparing the original and new risks and evaluating response alternatives. First identify and record the unreliable delivery as a secondary risk, then plan an appropriate response.
- D. Unreliable delivery is only an uncertainty that may happen and has not yet become an actual issue, so it belongs in the risk register, not the issue log. The issue log records things that have already happened.
Key takeaway When a response creates a new risk, record it as a secondary risk and plan a response; do not just reverse the measure.
Variation If the new supplier had already delivered late, it would now be an issue to log in the issue log with corrective action. A residual risk, by contrast, is the part of the original risk that is still left after the response.
Reference Risk Response Strategies · Lesson 4: Contingent Responses, Fallback Plans, Workarounds, Secondary and Residual Risk
- Question 101
Before the Sprint Review, the Developers find that one of the user stories to be demonstrated, although complete in function, still has automated testing and code review unfinished, so it does not meet the team's agreed Definition of Done. What should the team do?
Show answer and explanation
Correct answer: A
Before a Sprint Review, the Developers find that one of the stories to be demonstrated is complete in function, but its automated testing and code review are unfinished, so it does not meet the Definition of Done. The question is what the team should do.
The Definition of Done is the common standard for judging whether an item is done, and being complete in function is not the same as done. The story does not meet it, so it is not done, and nobody, including the Product Owner, can confer Done status on it. The team should uphold transparency: state openly that the story is not done and keep it out of the Increment presented at the Sprint Review. The story returns to the Product Backlog, and once the remaining work is finished it can be inspected as part of an Increment that meets the Definition of Done. The answer is A.
Why the other options are wrong
- B. Unfinished technical work leaves risk and technical debt. An item that does not meet the Definition of Done cannot count as done, and it cannot be ignored because it is functionally complete.
- C. Presenting the story as done and finishing the work later misrepresents the Increment. An item that does not meet the Definition of Done is not done, and doing this violates transparency and pushes the problem out.
- D. Agile stresses that the team shares responsibility. Blaming an individual does not finish the item and makes people afraid to raise problems later.
Key takeaway An item that does not meet the Definition of Done is not done: say so openly and keep it out of the Increment. Do not hide it and do not blame anyone.
Variation If the shortfall is discovered the day before the review, the team can tell the Product Owner in advance. The review then presents only items that meet the standard, and those that do not go back to the Product Backlog to be re-estimated.
- Question 102
An agile team is refactoring the inventory system of an e-commerce platform, and two modules have very complex logic. One member suggests writing a design note first to help everyone understand. Another member objects, saying the Manifesto is about software over documentation and writing documents is pure waste. What should the agile coach do?
Show answer and explanation
Correct answer: A
The team is refactoring an inventory system during an iteration, two modules have complex logic, and members disagree on whether to write a design note first. The coach's action depends on whether the objector understands the Manifesto correctly.
The Manifesto's value reads “working software over comprehensive documentation”, and it states that the items on the right also have value, only that the items on the left are valued more. “Over” expresses priority when you have to trade off; it does not mean “forbid”. Complex modules are hard to explain verbally, and a sufficient design note lowers the cost of understanding for later people at modest cost. The coach should first correct this misreading and then guide the team to write what is needed in moderation. The answer is A.
Why the other options are wrong
- B. This is the classic misreading of “over” as “instead of”. Follow it and the knowledge of the complex modules stays in a few people's heads.
- C. The disagreement comes from how the Manifesto is understood, and the coach, as a servant leader, can clarify it within the team. Escalating to management delays things and undermines self-organization.
- D. The Product Owner is responsible for value and backlog ordering. A design note is the team's own way of working and the team decides it as needed, without handing it to the Product Owner.
Key takeaway “Over” means priority, not replacement: valuable documentation is still written, to the extent that it is sufficient.
Variation If the document is a deliverable required by the contract, the team should put it in the backlog and estimate the work, rather than arguing over whether to write it.
Reference The Agile Manifesto · Lesson 1: The Definition of Agile and the Four Values
- Question 103
On an exhibition company's set-up project, the only local lighting supplier announces it cannot deliver on time, something the team had completely failed to anticipate. The team switches to buying the same lights from overseas at twice the local supplier's quoted price. Which source of funds should the project manager use to pay this extra cost?
Show answer and explanation
Correct answer: A
On an exhibition set-up project, the only local supplier cannot deliver on time, which the team did not anticipate at all, and buying overseas doubles the cost. Which source of funds should pay the extra cost?
The key signal is “completely failed to anticipate”. It is an unidentified risk (unknown-unknown), there is no matching contingency reserve, and the funds should come from management reserve. PMBOK 8 defines management reserve as money management sets aside outside the baseline for unforeseen work. Under common exam practice, release requires a change request (PMBOK 8 notes that management reserve is typically at the discretion of management, and in some organizations of the project manager), and after approval the amount is added to the cost baseline. A three-question test works here: was the risk identified in advance? Is the money inside the baseline? Who has authority to release it? The answers are no, no and approval needed. The answer is A.
Why the other options are wrong
- B. Contingency reserve covers identified risks that have response strategies. This supplier problem was not identified before, so it cannot be used to pay for it.
- C. Schedule reserve is a time buffer, not a source of funds, and cannot solve the extra purchase cost.
- D. Using the budget of other work packages to pay is robbing Peter to pay Paul inside the baseline. It squeezes out other work and bypasses change control.
Key takeaway For a new threat that nobody anticipated, use management reserve, approved through a change.
Variation If the supplier risk had long been recorded in the risk register, release contingency reserve, which the project manager does under the response plan.
Reference Cost Baseline and Reserves · Lesson 2: Contingency Reserve vs Management Reserve: Where the Money Comes From and Who Approves It
- Question 104
A company is restructuring, and several employees are about to leave because their positions are being eliminated. Project team members are down and do not understand why such a restructuring is happening while the project is going well. What should the project manager do?
Show answer and explanation
Correct answer: A
The company's restructuring has unsettled the team, and the team does not understand the reason for it. How should the project manager respond?
Members' discontent comes from not understanding. Hold a team meeting, explain clearly the reasons for the restructuring and what it means for the company, and let members voice their questions; that eases emotions and keeps collaboration going. This is a direct application of “explain the purpose first, then listen” in change communication. Mind the wording as well: explain honestly what the restructuring means for the company and how it affects employees, avoid demeaning phrases such as “weeded out” that deepen resistance, and leave time in the meeting to hear members' questions. The answer is A.
Why the other options are wrong
- B. Stressing only that the work continues as planned ignores members' emotions and questions, so the problem remains.
- C. Saying only that the chief executive decided and it must be carried out gives no reason and does not listen, and instead deepens resistance.
- D. Escalating to the sponsor and seeking an allowance is neither proactive nor a response to members' confusion about the restructuring.
Key takeaway When a restructuring upsets the team, hold a team meeting and explain the reasons and the meaning.
Variation If rumors such as “more positions will be eliminated” are going around, first hear and verify the specific concern and provide accurate information promptly; if the communications management plan omitted affected employees or has inadequate arrangements, update it and include them in the audience.
- Question 105
A team is developing an online consultation platform, and the system must meet non-functional requirements such as concurrent-user capacity and patient privacy protection. The product owner worries that these requirements will not be carried out and asks the project manager how to guarantee them. What should the project manager do?
Show answer and explanation
Correct answer: C
On an adaptive project, an online consultation platform must meet non-functional requirements such as concurrent-user capacity and patient privacy protection. The product owner worries they will not be carried out and asks how to guarantee them.
The definition of done (DoD) is a checklist of all criteria a deliverable must meet to be considered ready for customer use, and every increment must satisfy it to count as done. If non-functional requirements are written as checkable items in the DoD, they reach every iteration's delivery and gain force and assurance. The DoD suits non-functional requirements because it applies uniformly to every user story, feature or increment and does not depend on any individual's review. The answer is C.
Why the other options are wrong
- A. Leaving it to the operations department splits responsibility and delays feedback, so it cannot ensure every increment meets the requirement.
- B. One expert reviewing acceptance criteria can hardly cover every increment and does not build the requirement into the team's workflow.
- D. Leaving it for the next iteration planning meeting merely discusses it; there is no force behind it and the product owner's worry remains.
Key takeaway Non-functional requirements reach every increment through the definition of done.
Variation If the question asked which checklist sets the preconditions for starting a piece of work, the answer would be the definition of ready; if it asked about a story's specific functional expectations, the answer would be the user story's acceptance criteria.
- Question 106
Irene has just been appointed project manager of a mobile app development project. She plans to use Herzberg’s two-factor theory to manage the team and has learned that the team’s basic conditions have to be in place first. According to the theory, which of the following should be classified as a hygiene factor?
Show answer and explanation
Correct answer: C
Irene has just been appointed project manager of a mobile app project and plans to manage the team with Herzberg’s two-factor theory, knowing that the team’s basic conditions must be in place first. The question asks which option is a hygiene factor, that is, which one is not a motivational factor.
Herzberg divided conditions into two groups. Motivational factors relate to the content of the work, such as achievement, growth and advancement, and lead to satisfaction when sufficient. Hygiene factors relate to the work, such as company policies, salary and the physical environment; if insufficient they cause dissatisfaction, but even if sufficient they do not lead to satisfaction, only remove dissatisfaction. Of the four options, only salary level is a hygiene factor. The answer is C.
Why the other options are wrong
- A. A sense of achievement comes from the work itself and is a motivational factor; only when it is met can motivation truly rise.
- B. Praise from superiors is recognition, which is directly tied to results of the work and is a motivational factor.
- D. Personal career prospects (growth and advancement opportunities) are motivational factors, not conditions that maintain the level of dissatisfaction.
Key takeaway Salary, working conditions and relationships are hygiene factors; achievement, recognition, responsibility and career prospects are motivational factors.
Variation If the question asked which item can most truly raise motivation, the answer would be achievement, recognition or growth opportunities; if it asked whether a raise for everyone would raise motivation, the answer would be that it only removes dissatisfaction and does not produce satisfaction.
- Question 107
An external expert on a project reports being unable to open the project knowledge base pages and asks the team for help. The team replies that the client software needed for access has been upgraded and sends him the new version. Later, at an all-stakeholder meeting, he raises the same problem again. What should the project manager do?
Show answer and explanation
Correct answer: A
An external expert cannot open the knowledge base pages. The team replied that the client had been upgraded and sent the new version, yet at an all-stakeholder meeting he raised the same problem again. The project manager must deal with it, and this is the handling that follows a problem found in Monitor Communications.
When the same problem comes back, the previous communication did not work: the team only replied and sent software and did not find out where he was stuck. Monitor Communications calls for analyzing first and then acting, so the project manager should first talk with him to find the sticking point, and then provide support for that cause (for example, training on the new client if he turns out to be unfamiliar with it). That is what actually solves the problem. The answer is A.
Why the other options are wrong
- B. Continuing with the old version avoids the problem without finding the sticking point or addressing why the communication fell short.
- C. Sending the installer again repeats what was done last time. Without finding the sticking point, the cause stays and the problem will return.
- D. Going around the client avoids the problem, does not fix the root of the failed communication, and adds extra work.
Key takeaway When the same problem returns, the last communication did not work. Find the sticking point instead of repeating the earlier action.
Variation If the expert says “I never receive the email”, check the distribution arrangements and mailbox settings. If he says “I cannot make sense of the report”, adjust the report format to his needs and update the communications management plan.
- Question 108
The project manager of a hotel group is planning a membership system project made up of several work packages. The scope of each work package has been defined, but funds have been approved for the project as a whole. How should the project manager judge whether the approved budget is enough to pay for the project's resource costs?
Show answer and explanation
Correct answer: A
In project planning, the scope of each work package has been defined and the funds are approved for the project as a whole. The question asks how to judge whether the budget is enough.
To judge whether the budget is enough, you first need a reasonably accurate figure for the cost requirement. With the scope defined down to work packages, bottom-up estimating fits: estimate the cost work package by work package, aggregate to the total project cost, and compare it with the approved budget, which makes the answer clear at a glance. The other options either do not reflect true needs, are used for tracking progress later, or adjust scope only after the budget has proved insufficient. The answer is A.
Why the other options are wrong
- B. Work packages differ in scope and workload and so need different resources. An equal split does not reflect the real needs, and verifying that “every package fits within the equal share” is meaningless.
- C. Burndown charts are used to track progress during execution. Here the question is judging in planning whether the budget is enough, and no execution data exists yet.
- D. Allocating funds in order of importance and merging the scope of unfunded packages into funded ones adjusts scope after the budget turns out to be insufficient. It is not how you judge whether it is enough.
Key takeaway To judge whether the budget is enough: estimate each work package bottom-up, aggregate, and compare with the approved budget.
Variation Only if the aggregate exceeds the approved budget do you move to the next step: adjust scope, request additional budget or renegotiate.
Reference Estimate Costs · Lesson 2: Estimating Methods: Analogous, Parametric, Bottom-Up and Multipoint
Practice test or full mock exam: what is the difference?
- Free practice tests: 8 tests, the first with 120 questions and the others about 107 each, drawn from the 1,000 free questions (you may have met some while practicing by chapter), no login. Good for a quick self-check and for finding your weak domain.
- Full mock exams: 180 questions each, separate from the practice bank (none of them appear there), timed in 3 sittings like the real exam. Use them to judge whether you are ready. See the full mock exams.
Free PMP practice test: common questions
Is this PMP practice test really free?
Yes. There is no account and no email wall. All 108 questions and the full explanation of every answer are free, and your progress is saved in your browser.
How were the 108 questions chosen?
They come from the 1,000 free questions: 28 People, 49 Process and 31 Business Environment questions, covering 24 of the 26 tasks of the Exam Content Outline, with single-answer and multiple-answer questions. There are 8 free tests and no question appears in more than one of them. Once a domain runs out of free questions a test is a little shorter, and the count shown is the real one.
How long does the test take?
Timed mode follows the real exam's pace of 80 seconds a question, so 108 questions get 144 minutes. You can also choose untimed practice and take as long as you like.
How are multiple-answer questions scored?
A multiple-answer question counts as correct only when you select every correct option and nothing else. There is no partial credit, and an unanswered question counts as wrong.
Are these real PMP exam questions?
No. PMI does not release exam questions. Every question here is original, written to the Exam Content Outline, to practice the question styles and the reasoning.
What should I do after the test?
Take another of the free tests, keep practicing by chapter in the 2,876-question bank, or take one of the 10 full mock exams of 180 questions. Your score here is a practice signal, not a prediction of the exam result.
To study first, read the study guide; for the whole bank, practice by chapter.