Resources and Team
Team Performance
PMP · Resources and Team · 4 lessons · about 47 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Once a team is built, the project manager keeps asking four questions. How is the team doing? How do we close gaps in capability? How do we make sure good work is seen? What do we do when something goes wrong? This chapter follows the core work of the Lead the Team process in PMBOK 8: team performance assessments (an output of the process), training, coaching and mentoring, and recognition and rewards. It adds problem solving, which belongs to ECO: People domain, Task 3 (Lead the project team). Four lessons cover it all.
This is a frequently tested chapter, especially the training and poor-performance topics. The stems vary a great deal, but the logic of the answer is very stable: assess first, then respond to the cause; talk first, then take measures. The usual distractors are punish first, replace first, escalate first, add a bonus first and extend working hours first. Almost all of them are later-stage measures.
Lessons in this chapter
- Lesson 1: Team performance assessments. Four indicators (individual skills, team competencies, staff turnover, cohesiveness); what to base an assessment on; individual performance can be judged against key performance indicators agreed in advance, work performance information and tools such as surveys, interviews and competency tests; after the assessment, take improvement actions and identify the resources needed (and, where appropriate, create an improvement plan).
- Lesson 2: Training, coaching and mentoring. The steps from identifying a skill gap, through choosing an intervention, to evaluating its effect; training goes into the resource management plan; coaching works through questions, while mentoring is a longer-term relationship; choose in-house experts, pairing, mentoring or outside training according to the skill gap and project conditions (common exam practice: when the stem gives no other conditions, in-house experts, pairing and mentoring come first).
- Lesson 3: Recognition and rewards. Give them throughout the project and promptly; match them to the individual's needs; intangible rewards work too; how to handle hidden contributions, overtime-pay disputes and omitted recognition.
- Lesson 4: Poor performance and team problems. Talk first, find the cause, then choose measures; problems at the individual level and the team level; cliques, isolation, groupthink and diffusion of responsibility.
Chapter map
Assess (typical indicators: individual skills, team competencies, turnover, cohesiveness) ──> find gaps ──> training / coaching / mentoring Recognition and rewards (throughout, prompt, matched to needs)
- > A problem appears: talk privately → find the cause → agree a solution → train or adjust → corrective actions → formal measures
Study tips
Study in order. Assessment is the starting point, training and recognition are the tools, and the last lesson applies all of the tools to specific problems. When a question asks for the "first step" or what to do "first," think of communication and assessment. When you see "lacks skills," think of a gap analysis first. When you see "motivation," think of prompt recognition matched to needs. Lesson 4 is tested most often, so save it for last and practice it in one block. Get comfortable with the tools in the first three lessons first, then see how they apply to specific problems. After one round of practice, sort your wrong answers into three groups: "should have talked first but chose punishment," "should have assessed first but chose training," and "should have matched the individual's needs but chose a uniform reward." Your mistakes will usually fall into just these three groups.
Lesson 1
Team Performance Assessments: What to Assess, What to Base It On, What to Do Next
Lesson overview
Once the team is built, the project manager has to answer one question: how is this team really doing? PMBOK 8 puts the answer among the outputs of the Lead the Team process, where it is called team performance assessments. This lesson covers three things: which indicators to use when assessing the team, what to base an individual assessment on and how to give feedback, and what to do after the assessment. The next three lessons cover training, recognition and rewards, and handling poor performance, and this lesson is their starting point.
What team performance assessments are
"As project team development efforts such as training, team building, and colocation are implemented, the project management team makes formal or informal assessments of the project team's effectiveness. Effective team development strategies and activities are expected to increase the team's performance, which increases the likelihood of meeting project objectives." The result of the evaluation is the team performance assessments, an output of the Lead the Team process.
The evaluation of a team's effectiveness may include indicators such as:
- Improvements in skills that allow individuals to perform assignments more effectively,
- Improvements in competencies that help team members perform better as a team,
- Reduced staff turnover rate, and
- Increased team cohesiveness where team members share information and experiences openly and help one another to improve the overall project performance.
A memory aid is "skills, competencies, turnover, cohesiveness." Note that PMBOK 8 introduces these four with "may include," so the list is not closed. Common exam practice: schedule and cost variances reflect project performance and are generally not used as indicators of how effective team building has been; a specific project can add other indicators that fit its context. Common exam practice: when a question uses PMBOK 8's team effectiveness indicators and asks "how can you tell whether team building is working," look for these four first.
When PMBOK 8 describes high-performing teams, it also lists a set of descriptive factors: open communication, shared understanding, shared ownership, trust, collaboration, adaptability, resilience, empowerment, delegation and autonomy, and recognition. You do not need to memorize them as a list. They are angles of observation when you assess a team. For example, cohesiveness rests on members being willing to tell the truth. If you create an atmosphere free of blame, welcome early disclosure of problems, and then delegate within the business scope so the team decides the specific way it works, you are building "open communication" and "empowerment."
An assessment can be formal or informal. Formal examples are a team review at the end of a phase and an annual appraisal. Informal examples are everyday observation, one-to-one conversations, and feedback you hear in an iteration retrospective. PMBOK 8 lists individual and team assessments and retrospectives among the tools and techniques of the Lead the Team process, which tells you that assessment is not a one-time score at the end of the project. It is a check repeated as team development moves forward. With repeated assessments you can see the trend: if the indicators improve, the team development strategy is working; if they stall or worsen, go back and examine the strategy.
What to do with the results
"As a result of conducting an evaluation of the team's overall performance, the project management team can identify the specific training, coaching, mentoring, assistance, or changes required to improve the team's performance. This effort should also include identifying the appropriate or required resources necessary to achieve and implement the improvements identified in the assessment."
After the assessment, act on the findings with training, coaching, mentoring, assistance or other improvements, identify the resources needed and, where appropriate, create a performance improvement plan. Common exam practice: when a question asks for the next step after the assessment, the usual answer is to develop and carry out improvement measures. If the assessment shows that one member is still short of expectations, draw up a performance improvement plan for that person. Do not keep the results secret, give everyone a general reward, simply rotate the person to other work, or wait until the next assessment.
When you take over a new team, especially one whose members have uneven experience, first assess the team's current effectiveness and determine which capabilities need to improve, and only then arrange development measures. Do not assign roles from members' past job experience alone, do not rely only on annual appraisal results, and certainly do not let everyone pick their own work. A new system differs from the old one, so existing experience may not apply, and none of these approaches answers the question "what is the team missing?"
Assessing individuals and giving feedback
An assessment of an individual needs a basis. PMBOK 8 asks the project manager to track team member performance and provide feedback. Work performance information is often used to evaluate individual performance, and "individual and team assessments" can also draw on attitudinal surveys, specific assessments, structured interviews, ability tests and focus groups. Individual performance should be judged against performance criteria that were defined and communicated beforehand, together with work performance information and suitable assessment tools; key performance indicators (KPIs) can be one such basis. Common exam practice: when the stem mentions "indicators agreed with the member at the start of the project," both the rating and the feedback go back to those indicators. Explain the link between each indicator and the member's actual performance, and explain how the indicators were set in the first place. A member who receives only a grade, with no detail, will be disappointed. The remedy is not a uniform goal for the whole team, and not forwarding the project's full set of indicators, but going through the member's own indicators with him or her one by one.
Where company practice has the functional manager give annual feedback, a member's project work may not line up with the individual performance plan. The project manager should proactively meet the functional manager to align expectations for the member and the frequency and format of reporting results. Do not set up a separate system on your own, and do not wait for year end.
Example: a mid-term assessment and improvement
A community hospital's appointment-booking system project has nine members. Three months before go-live, the project manager assessed the team. She compared four indicators against the situation at project start. The number of members who could complete interface integration on their own rose from three to six (individual skills). Testing and development no longer waited on each other's environments (team competencies). Nobody had left this year, whereas the previous project lost two people (turnover). At the weekly team coordination meeting, members raised the tasks they were stuck on much more often (cohesiveness). The assessment also showed that two new members still had a gap in performance testing, so she worked with the functional manager to draw up a training and mentoring plan for the two of them and recorded the resources the plan needed in the resource requirements, aligned when they were needed in the project schedule, and checked their availability against the resource calendars.
Worked examples
Example 1: Performance feedback: go back to the agreed indicators
After the annual appraisal, a test engineer on a logistics system upgrade project asks the project manager for more specific feedback. The project manager regards him as proactive, generally delivering on time with only an occasional delay, and the key performance indicators were agreed with him at the start of the project. The engineer is disappointed that the appraisal result contains no detailed information. What should the project manager do to prevent further disappointment?
Show answer and explanation
Correct answer: B
After the annual appraisal, the test engineer wants more specific feedback. The project manager sees him as proactive and generally on time, with only an occasional delay. He is disappointed that the appraisal result has so little detail. The question asks how to prevent further disappointment.
The root of the disappointment is that he does not know how his performance turned into the appraisal result. Individual performance is assessed against key performance indicators agreed in advance, so the feedback should go back to those indicators, comparing his actual performance with each one, giving specific, constructive feedback and agreeing improvement measures. That way he can see the gap and knows where to improve in future. The correct answer is B.
Why the other options are wrong
- A. A uniform team goal describes the team's overall result. It cannot answer the question “how did I myself actually perform?”
- C. The human resources department would supply indicators for the whole project. They are not specific to him and are not feedback.
- D. A tracking tool lets him see data but does not explain how the appraisal result was reached, so the sense of missing feedback remains.
Key takeaway Individual performance feedback goes back to the key performance indicators agreed in advance, one by one.
Variation If the member's appraisal is the responsibility of the functional manager, the project manager should first align expectations and reporting frequency with the functional manager, then give the member feedback.
Something wrong with this question?
Example 2: Taking over a new team: assess effectiveness first, then set development needs
A newly appointed project manager takes over a project that replaces an old order management system with a new one. The team has some members who know only the old system and others who have almost no relevant experience. To ensure the project succeeds, what should the project manager do?
Show answer and explanation
Correct answer: D
A new project manager takes over a project that replaces an old order management system with a new one. Some of the team know only the old system and some have almost no relevant experience. The question asks what to do to ensure success.
The new system differs from the old one, so members' past experience may not apply, and it is not yet clear what the team really lacks. The project manager should first assess the team's current effectiveness and find the capability gaps, then arrange training, mentoring and other development measures on that basis. That is the purpose of team performance assessments: to identify the specific training, coaching and assistance needed to improve team performance. The correct answer is D.
Why the other options are wrong
- A. Assigning roles by past job experience assumes that past experience applies to the new system, without checking the gap.
- B. Annual appraisals reflect overall performance in the past. They are neither specific to the new system nor a measure for closing the capability gap.
- C. Letting members pick their own work makes use of personal strengths, but the lack of new-system experience in the team remains, and there is no coordinated arrangement.
Key takeaway When you take over a new team, assess effectiveness and find capability gaps first, then decide on development measures.
Variation If the assessment shows that only a few members have large gaps, arrange pairing and mentoring for them rather than training everyone.
Something wrong with this question?
Common traps
Common trap
- Team effectiveness is judged on four indicators: individual skills, team competencies, turnover and cohesiveness. Schedule and cost variances belong to project performance and are generally not used to judge how well team building is working (common exam practice).
- Common exam practice: the step after an assessment is to develop and carry out improvement measures (and, where appropriate, create an improvement plan). It is not to keep the results confidential, give a universal reward or simply rotate people.
- An individual rating should rest on performance criteria that were defined and communicated beforehand (KPIs can be one of them). Common exam practice: when the stem gives indicators agreed in advance, feedback goes back to each indicator and cannot be just a conclusion.
- When a functional manager is responsible for member appraisals, the project manager proactively aligns expectations and reporting.
- An atmosphere where members dare to tell the truth and surface problems is the foundation of cohesiveness. PMBOK 8 says that an environment that fosters open and safe communication helps productive meetings, problem solving, brainstorming, understanding, trust and collaboration; without it, trust and collaboration are hard to build.
Key takeaways
- Team performance assessments are an output of the Lead the Team process and can be formal or informal.
- Assessment indicators: improved individual skills, improved team competencies, reduced turnover and increased cohesiveness.
- The purpose of assessment is to find the training, coaching, mentoring, assistance or improvements needed, and the resources they require, and then carry out the matching improvement actions, creating a performance improvement plan where appropriate.
- When you take over a new team, assess its current effectiveness first, then decide which capabilities to improve.
- Individual assessment rests on performance criteria defined in advance (such as key performance indicators agreed beforehand), with feedback given item by item; align expectations with the functional manager.
- Open communication, freedom from blame and appropriate delegation are the soil in which cohesiveness and trust grow.
Lesson 2
Training, Coaching and Mentoring: Find the Gap First, Then Choose the Remedy
Lesson overview
When a team performance assessment reveals a capability gap, the next step is to close it. The three common ways to close a gap are training, coaching and mentoring. This topic is tested often, and the stem is almost always "the team lacks a certain skill; what should the project manager do?" The line of reasoning is fixed: work out what is missing, choose the remedy that fits, and put it in the plan. This lesson explains how the three remedies differ and the order in which to choose among them. The next lesson covers recognition and rewards. ECO: People domain, Task 3 (Lead the project team).
What training is
"Training includes all activities designed to enhance the competencies of the project team members. Training can be formal or informal. Examples of training methods include classroom, online, computer-based, on-the-job training from another project team member, mentoring, and coaching. If project team members lack the necessary management or technical skills, such skills can be developed as part of the project work."
Training strategies should be planned in the resource management plan, while unplanned training may also be initiated as needs emerge during the project. When you plan resource management, you decide there what training is needed and for whom. "Training costs could be included in the project budget or supported by the performing organization if the added skills may be useful for future projects. Training may be performed by in-house or external trainers."
When a stem says "lacks a certain skill," "knowledge gap," or "is not familiar with the new system or tool," think first of "assess the gap, then train." Training is one of the main ways to close a gap, but it is not the first step. Understanding the gap is the first step.
How training works: from gap to evaluation
PMBOK 8 says only that scheduled training takes place as stated in the resource management plan and that unplanned training takes place as a result of observation, conversation and performance appraisals. It does not prescribe fixed steps. What follows is a checklist of common exam practice; adapt it to the stem by skipping steps that are already done. If the gap is not yet clear, assess first. If the gap is already clear, go straight to choosing and carrying out the right training, coaching or mentoring approach.
First establish the requirements and the current state. Define the skills the project requires; talk with members one by one or run a skills assessment to find each person's gap; and where there is a functional manager, talk to him or her and draw up the plan together. Next, do a training needs analysis to decide what to train and whom to train, rather than buying courses straight away. Then choose the method. When everyone lacks the skill, train as a group. When only a few people lack it, use an in-house expert to mentor them or have them work in pairs. When only one person holds a key skill and later activities need at least three people, you can either bring in an external trainer or encourage members to pair up and share knowledge. Write the training strategy into the resource management plan and reserve time in the schedule. After the training, evaluate the effect. If the problem persists after training, run a root cause analysis to find out why it persists. Do not simply repeat the same training, and do not blame the member directly.
Several high-frequency details follow. Before training, assess members' preferred ways of learning, and take these into account when choosing the method. If training is not effective, analyze the root cause and adjust. When there is no training budget, first assess the value of the training and apply through the organization's funding approval or change governance process. (PMBOK 8: training costs can be included in the project budget or supported by the performing organization. Common exam practice: when the stem gives no other conditions, assess the value and then make the case to the sponsor.) When a member wants to attend an outside course related to the project, coordinate the course with the tasks and balance the schedule against the member's development. When a member volunteers to study a new skill the project needs, support it. Keep following up after training; do not skip further guidance because someone has taken a course. Record the content in full and share it, so that members who did not attend benefit too.
Coaching and mentoring
"Coaching provides guidance and helps people (e.g., a project team member or a stakeholder) to find a solution to a specific problem on their own by asking the right questions. Mentoring is serving as a counselor, guide, or mentor by sharing knowledge, skills, or experience with a person who has to develop their own knowledge or skills. Both coaching and mentoring include one-to-one conversations. However, coaching is more related to achieving specific goals, while mentoring is a more long-term, ongoing relationship-building practice."
To choose, look for the key words. If what is missing is a specific piece of knowledge or skill and many people lack it, choose training. If a member keeps failing to keep commitments and needs to think the problem through personally, choose coaching, using questions to lead the person to a solution. If a newcomer lacks hands-on experience and needs long-term guidance, choose mentoring, that is, an apprenticeship in which a senior member brings a new one along. For a new member who has just joined and cannot keep up with the schedule, ask a senior member to guide them. When someone asks for advice, give guidance and keep following their growth. Common exam practice (when the stem gives no other conditions): if the organization already has an expert, have that expert act as mentor or coach. It is the most direct route, and there is no need to hire externally first. If a senior member thinks mentoring has no value, set aside dedicated mentoring time in the plan so that it becomes formal work.
Example: the new test engineer
On a pharmacy chain's ordering-system project, a new test engineer was responsible for the regression test report, and his first report missed several defects. The project manager did not replace him on the spot, and did not simply order a testing course. She first talked with the engineer and found that he knew functional testing well but did not know the project's defect severity criteria and had never used the team's test management tool. She then did three things. She talked with his functional manager and agreed the training content together. She asked the most senior tester on the team to guide him through the next regression cycle, checking against the criteria at each review. And she added the training and mentoring arrangement to the resource management plan. Two weeks later his reports missed far fewer defects.
Worked examples
Example 1: Cohesiveness is slipping and a skill gap is suspected: sort it out first, then fill the gap
A project manager leads a team that mixes novices and senior staff and finds that team cohesiveness has become a problem. The senior members believe the newcomers lack the technical skills needed to do the work and expect that they themselves will have to make up for the newcomers' experience gap. What should the project manager do?
Show answer and explanation
Correct answer: C
In a team that mixes novices and senior staff, the senior members believe the newcomers lack the technical skills the work needs and expect to cover the gap themselves, and cohesiveness suffers. The question asks what the project manager should do.
The cohesiveness problem may be tied to a capability gap, but the senior members' view still needs objective confirmation, and the issue is not that rewards are too low. The project manager should map the skills of all members, find the gaps and draw up a plan to close them. That gives an objective picture of the current state and solves the problem systematically. The plan can include mentoring and training and can set aside mentoring time for the senior members. It also lets the senior members see that the gap is being formally planned for and that they no longer have to cover for the newcomers passively, which makes the repair of cohesiveness longer lasting. The correct answer is C.
Why the other options are wrong
- A. Rewarding the senior members might encourage mentoring, but before the skill gaps are mapped and an overall plan exists, setting a bonus first is not the preferred step and could unbalance relationships in the team.
- B. Moving the new members to other projects avoids the responsibility for team development and affects resource planning. The gap would still need to be closed once newcomers arrive.
- D. Leaving members to sort it out themselves goes against the project manager's duty to lead the team and close capability gaps.
Key takeaway When a skill gap is the root of a cohesiveness problem, map the skills first, then draw up a plan to close the gaps.
Variation If the stem had said that only one specific skill is missing, you would arrange training aimed directly at that skill.
Something wrong with this question?
Example 2: Quality is declining and training is suspected to be missing: do a skill gap analysis first
A project manager leads a team developing an in-vehicle navigation app. The team consistently completes its tasks on time, but delivery quality keeps declining. The project manager suspects a lack of training is the cause. How should the problem be resolved?
Show answer and explanation
Correct answer: D
An in-vehicle navigation team always completes tasks on time, but delivery quality keeps declining, and the project manager suspects a lack of training. The question asks how to resolve the problem.
“Suspecting a lack of training” is only a hypothesis and has to be verified first. First analyze the root cause of the decline in quality, confirm whether a skill gap exists, find out which skills are missing and who lacks them, and derive the training needs. Then train in a targeted way. This follows the order “assess the gap first, then choose the remedy,” which saves training cost and addresses the real problem. If you skip the analysis and train straight away, you may train people on things they do not lack, spending money and hours while the quality problem remains. Only after analysis do you know whether the issue lies in tool use, testing methods or understanding of requirements. The correct answer is D.
Why the other options are wrong
- A. A team-building workshop improves collaboration and morale. It does not touch the suspected root, which is a skills or training shortfall.
- B. Bringing in new members assumes the existing members cannot be improved through training. It does not first tap the team's potential and it adds cost.
- C. A stricter appraisal system only adds pressure. If the quality decline comes from a lack of skills, appraisal does not fix it.
Key takeaway When you suspect a lack of training, analyze the cause of the quality decline and confirm the skill gap first, then train in a targeted way.
Variation If quality is still declining after the training, the next step is root cause analysis of the quality problem (the cause may not be a training shortfall), followed by targeted measures.
Something wrong with this question?
Common traps
Common trap
- When the gap is unclear, training is not the first step. Assess the current state and find the gap first. When the stem already states the gap, go straight to the training, coaching or mentoring approach that fits.
- If the problem persists after training, run a root cause analysis. Do not add the same training again, and do not punish directly.
- Common exam practice (when the stem gives no other conditions): when the organization already has experts or experienced members, have them mentor or pair first, with no need to hire outside trainers first. PMBOK 8 says only that training can be given by in-house or external trainers.
- Coaching works through questions that let the person work it out, with a focus on specific goals. Mentoring is a long-term relationship that shares experience. Both can include one-to-one conversations (mentoring can also be directed at the whole project team). Keep their distinct purposes straight, while remembering that PMBOK 8 treats coaching and mentoring as possible training methods within the broader category of training.
- Training goes into the resource management plan, with time set aside for mentoring and learning. It is not something to do "when there is time."
- When members volunteer to learn skills the project needs, support them. Do not refuse across the board just because the schedule is tight.
Key takeaways
- Training includes all activities that enhance members' competencies, formal or informal, and the training strategy goes into the resource management plan.
- The order for closing a gap: define requirements, assess the current state, find the gap, set training needs, choose a method, write it into the plan, evaluate the effect.
- If the problem persists after training, run a root cause analysis first.
- Coaching uses questions to help a person solve a specific problem on their own. Mentoring is an experienced person sharing knowledge and experience over the long term.
- A common skill gap across many people usually calls for training. A need to solve a specific problem independently through questions calls for coaching. A need for ongoing sharing of knowledge, skills or experience calls for mentoring (an apprenticeship, or pairing).
- In-house experts come first (common exam practice; choose according to the gap, cost and timing). With no budget, assess the value first and then apply through the funding approval process (common exam practice: make the case to the sponsor).
Lesson 3
Recognition and Rewards: Prompt, Specific, Matched to Needs
Lesson overview
Training closes capability gaps. Recognition and rewards deal with motivation. PMBOK 8 lists them among the tools and techniques of the Lead the Team process: when members' good performance is seen and acknowledged, it is more likely to continue. The stems on this topic vary a lot: how to reward, when to reward, what to do when someone is left out, what to do about an overtime-pay dispute. But only a few rules sit behind them. This lesson sets out the rules and tells you which approaches look considerate but are in fact traps. The next lesson covers handling poor performance.
Basic rules of recognition and rewards
"Part of the team development process involves recognizing and rewarding desirable behavior. The original plan for rewarding people is developed during the Plan Resource Management process. Cultural differences influence how recognition and rewards are best delivered, and understanding these differences helps ensure that the rewards program is meaningful and motivating for everyone. Tailoring recognition to align with cultural preferences increases the effectiveness of reward systems and enhances employee satisfaction."
"People are motivated when they feel they are valued in the organization, and this value is demonstrated by the rewards given to them. Generally, money is viewed as a tangible aspect of any reward system, but intangible rewards could be equally or even more effective. Most project team members are motivated by an opportunity to grow, accomplish, be appreciated, and apply their professional skills to meet new challenges. A good strategy for project managers is to give the team recognition throughout the project life cycle rather than waiting until the project is complete."
Combining PMBOK 8 with common exam practice, four rules come up often in the exam. First, give recognition throughout the project and promptly. After a member achieves a specific result, acknowledge it at the next suitable occasion, even if it is only a specific word of praise in person. Saving it all up and handing it out after project closing is wrong. Second, match it to the individual's needs. A certificate may not work for someone who values money, and for someone who values public recognition, being acknowledged in front of the group may mean more than a bonus. So find out the person's motivation and interests first, then choose the reward. (PMBOK 8 says to understand individual motivators and tailor rewards accordingly.) Third, be fair. When there is a misunderstanding about how rewards are used, hold a meeting, listen to members' views and agree the approach together (common exam practice). Fourth, intangible rewards (growth opportunities, a sense of accomplishment, appreciation, more responsibility and a chance to take part in decisions) often last longer than tangible ones. In its recognition section, PMBOK 8 says that money is a tangible aspect of a reward system and that intangible rewards could be equally or even more effective. Common exam practice: the satisfaction of a pay raise fades quickly, so intangible rewards are often treated as longer lasting.
How to handle common situations
When morale is low and members feel their effort is not appreciated, give them more project responsibility, involve them in the relevant decisions, and acknowledge results promptly. When the team has just finished a major deliverable for a phase and more work lies ahead, common exam practice (when the stem gives no other conditions): recognize the contribution first, then give a reasonable rest, and finally plan the goals for the next phase, which keeps motivation going. When the team has worked overtime for a long stretch, is nearing closure and is tired, first assess and ease the excessive workload and arrange rest, while honoring the reward promised under the performance appraisal and acknowledging the effort already given, rather than just pushing harder. When an agile team has tackled a very hard iteration, recognize the result specifically, in public and in front of the team.
When recognition was missed, as when a key member was left out at the celebration, explain the situation to that member and follow through to put the recognition and reward in place. An apology or a team meal is not enough, and the member's motivation will suffer. When a reward such as overtime pay is disputed, first talk to the person concerned and explore solutions together. Do not refuse outright, and do not approve it automatically without asking why. A member may quietly carry "hidden work," such as helping a colleague troubleshoot a fault or tidying a shared document. It may not appear on the task list, so the project manager must actively notice it, recognize it, and rebalance the workload.
Recognition at closing matters too. After the project is accepted, thank each member individually, write down each person's contributions and copy the functional manager. This acknowledges the contributions and also helps the member's later career. Measuring an individual only by cost performance index (CPI) and schedule performance index (SPI) is not comprehensive enough. To record a member's progress formally, capture the improvement in individual skills in the team performance assessments. You can also acknowledge the member's achievement promptly at a team meeting.
Example: two weeks of night cutovers
On a bank's core-system cutover project, the development group worked night shifts for two straight weeks. The project manager did several things. The morning after the successful cutover, she named each person's specific contribution at the team meeting, for example "Sam spotted the timeout setting in the batch job early." She noticed that one colleague valued learning opportunities most and secured him a seat as an observer at the architecture review. Another member had quietly put together the cutover handbook, so the project manager thanked her separately in the meeting and counted that work in her workload. When some people questioned how the bonus money would be used, she called a meeting, listened to everyone's views and agreed the approach together. After closing, she wrote each person a thank-you letter and copied their functional managers.
Worked examples
Example 1: A senior developer who delivers results over a long period: understand motivation before choosing a reward
On a recommendation system project for an e-commerce platform, a senior developer has worked hard over a long period and produced outstanding results. The project manager is very pleased with his contribution and believes he should be rewarded. What should the project manager do FIRST?
Show answer and explanation
Correct answer: B
On a recommendation system project, a senior developer has worked hard for a long time and delivered outstanding results, and the project manager is pleased and thinks he should be rewarded. The question asks what the project manager should do first.
Rewards are generally more motivating when they fit the individual's motivations and needs. Some people value money, some value growth opportunities and some care most about public recognition. The project manager should first learn this developer's motivations and interests, then choose the form of reward. That shows respect and meets his needs. Even with the same “praise,” naming an introverted person in public may be a burden, while for someone who values public recognition it is the best reward. The correct answer is B.
Why the other options are wrong
- A. For an individual reward, presenting a certificate in public at the regular meeting is a preset form. It has not been checked whether he wants to be honored in public.
- C. Expressing recognition in person is a usable form in itself, but it is a form chosen in advance. The stem asks what to do “first,” so understand the individual's motivation before choosing.
- D. An all-hands email copied to management is likewise a preset form. It does not start from his expectations and has limited motivating effect.
Key takeaway Before rewarding, understand motivation, then choose a form that fits the individual's needs.
Variation If the stem asked when recognition is best given, the answer is promptly and specifically throughout the project, without waiting until the project ends.
Something wrong with this question?
Example 2: Keeping up steady performance for the last two weeks before closing: prompt recognition
A data center migration project is two weeks from acceptance, and the sponsor keeps calling to demand that there be no further delays. The team has performed steadily so far, and the project manager wants everyone to maintain this level of performance through the end. Which approach would BEST motivate the team?
Show answer and explanation
Correct answer: C
A data center migration project is two weeks from acceptance, the sponsor keeps pressing, the team has been steady so far, and the project manager wants it to maintain that level of performance to the end. The question asks which approach best motivates the team.
Motivation comes from prompt recognition and rewarding of desirable performance. The team has been steady throughout, and recognizing their effort with certificates is direct, specific recognition that shows good performance is noticed and makes people more willing to keep it up to the last moment. With only two weeks to acceptance and the team producing steadily, what they need most is to be acknowledged, not more pressure or orders. The certificate is a phase-level public recognition for the whole team. If the reward were for an individual, you would first learn the person's preferences. The correct answer is C.
Why the other options are wrong
- A. A written notice to maintain standards is an instruction. It does not recognize members' work and so has no motivating effect.
- B. Passing on the sponsor's urging unchanged only adds to the team's anxiety, and it is not recognition.
- D. Bringing in temporary helpers can share the workload, but that is a resource measure and not an incentive for performance.
Key takeaway Motivate through prompt recognition of good performance, not through orders and pressure.
Variation If the team is tired from long periods of overtime, then besides recognition you should also honor the rewards you promised and watch the workload.
Something wrong with this question?
Common traps
Common trap
- Recognition runs through the whole project. It is not handed out all at once at the end. "Save it all for a single reward after closing" is wrong.
- Rewards should match individual needs. A ready-made uniform form (a certificate, an email to everyone) does not suit everyone, so understand the motivation first. Note the distinction: for an individual's reward, understand their motivation first; for a team-wide, phase-level, immediate recognition, a public certificate is acceptable (see Example 2).
- Intangible rewards (growth, sense of accomplishment, appreciation, responsibility) work equally well and sometimes better. Common exam practice: monetary rewards are treated as less durable than intangible ones.
- With an overtime-pay dispute, talk first and then look for a solution. Do not refuse outright, and do not approve every request.
- When recognition has been missed, explain the situation to the member in person and add suitable recognition promptly, based on the person's preferences and the original rewards plan. PMBOK 8 notes that even a simple thank-you reinforces positive behavior, but an apology alone, with no remedy for the omission, is usually not enough to repair the damage.
- After a phase-level result, recognize the contribution promptly (PMBOK 8: give recognition throughout the project life cycle rather than waiting until the project is complete). Whether to give a rest and when to plan the next phase should be decided from the team's condition and the project's needs. Common exam practice: when the stem gives no other conditions, the usual order is recognize first, then rest, then plan.
Key takeaways
- Recognition and rewards happen in the Lead the Team process. The original rewards plan is developed during Plan Resource Management and goes into the resource management plan.
- Beyond tangible rewards (money), intangible rewards (growth opportunities, sense of accomplishment, appreciation) can be equally effective and sometimes more so.
- Give recognition throughout the project life cycle, promptly and specifically, and do not wait until the end.
- Understand individual motivation and needs before choosing a reward. Keep rewards fair, and where there is a misunderstanding about their use, let members help agree it.
- Actively identify hidden contributions, recognize them and balance the workload.
- Cultural differences affect how recognition lands, so tailor it to cultural preferences.
Lesson 4
Poor Performance and Team Problems: Talk First, Find the Cause, Then Choose Measures
Lesson overview
This is the most frequently tested topic in the team performance chapter. The stems are all over the place: a member is late, a member is down, a key member hints at leaving, cliques form, someone is isolated, nobody dares disagree, the whole team is worn out. The options are always the same few: some punish at once, some replace at once, some escalate, some add a bonus, and only one finds the cause first. This lesson sets out that main line, then lists the matching remedies by type of problem. The assessment, training and recognition from the first three lessons are the tools used here.
One main line: talk first, find the cause, then choose measures
When a member's performance slips, the reason varies from person to person. It may be a skill gap, an excessive load, a personal matter, a process bottleneck or a problem in team relationships. Punishing, replacing, pressuring or adding a bonus before you understand the cause is usually not the first step. PMBOK 8 stresses adjusting management and leadership styles to team members' willingness and ability, and it does not prescribe a fixed order. Common exam practice follows this order of handling: talk one to one in private to understand the cause, without blaming anyone in public; work out whether the problem is ability, willingness or resources; agree a plan with the person concerned; add training, or adjust tasks or workload, as needed; if performance has still not improved after training, keep talking and set measurable corrective actions. For an ordinary performance problem, formal documentation and replacing staff usually come later, and the timing should depend on how serious the problem is, organizational policy and governance requirements. Serious dereliction of duty, or compliance or safety problems, may call for earlier formal documentation or replacement. Common exam practice: when the stem asks for the "first step" or what to do "first," the answer is almost always to communicate and understand the cause.
This main line fits many "change in behavior" situations: a previously excellent member is late several times in a row, a member who always spoke up suddenly goes quiet, a new member's output is low, a technically strong member has recently been down, or a member's performance keeps sliding. In every case, talk to the person first and find out why things changed. The project manager talks directly. Do not go straight to human resources or escalate. Normally, talk to the person alone as soon as possible. But if the slide has already caused consequences in front of the customer and the impact is still growing, take loss-limiting action, customer communication and any necessary escalation at the same time, according to urgency. (PMBOK 8: leading the team includes resolving and escalating issues. Whether to report upward is decided by organizational governance requirements and urgency.) You cannot wait until after the conversation every time.
Problems at the individual level
A member is overwhelmed and unhappy with the team: listen carefully first, then work with the member to find the support available, such as adjusting the division of work, adding resources or arranging help from others. Do not just tell the member to cope alone, and do not use team building as a substitute for specific help. A key member hints at leaving: talk privately, understand what the person wants and assess whether retention is possible. A member is tired and enthusiasm is fading: talk with the members one by one to find the source of the pressure, then take supportive measures aimed at that cause, and care about the member's condition.
A member fears being seen as incompetent and does not dare to voice difficulties: create a safe atmosphere, encourage raising problems early, and do not blame members for volunteering their difficulties (where misconduct, dereliction of duty or safety is involved, investigate under organizational policy as usual). A member fears being shut out and will not raise concerns in meetings: listen in private, explain how the information will be used and the limits of confidentiality, and protect sensitive information under organizational policy (some matters may have to be investigated or reported). Where suitable, offer an anonymous feedback channel. A member suppresses others and always shoots down other people in meetings: first give that member feedback on the suppressing behavior and guide the person to voice disagreement constructively. If the team already has agreed ground rules, enforce them strictly.
Problems at the team level
The whole team shows declines on several indicators, complaints increase and morale is low: do a root cause analysis first, hold an open communication meeting to find the real pain points, and then clarify the project's situation openly and positively. A team that has been overloaded for a long time and works overtime without results needs to find the step that limits output and improve planning, processes and methods. It should not try to solve the problem by extending working hours.
Cliques and information silos: first find out why the cliques formed, then bring people together around shared goals. Set up open, transparent information-sharing mechanisms and build cross-group communication channels. Do not forbid communication, and do not break members up. A member is isolated: listen to the isolated member's feelings and to the other members' views, find the cause, then use team building to strengthen cohesiveness and actively help the member to integrate.
Groupthink: when everyone keeps echoing the mainstream view and nobody dares to offer another, decision quality drops, so encourage critical thinking and listen to differing opinions. When senior members always dominate meetings, guide the team to build an inclusive way of speaking so that everyone gets a chance. Diffusion of responsibility: when a fault occurs and the group chat calls on everyone, each person assumes someone else will handle it and nobody acts. The remedy is to make responsibility clear and use a responsibility assignment matrix to place each task with a specific person, with exactly one person accountable for each task (the A in RACI). When competition outweighs cooperation in the team, adjust the incentives and strengthen shared goals, team results and collaborative behavior, so that individual competition does not hurt overall performance. (PMBOK 8: members of a high-performing team work together as a team, rather than working in silos or competitively.)
Be careful with two situations that look as if they call for immediate action. In an urgent case, such as when only two days remain before delivery, a junior developer's code keeps showing the same kind of defect and the customer may impose penalties, you can weigh skills, risk and schedule impact, explain the situation to the member, and consider moving the task to a senior person. That is a trade-off for an urgent case, and if a skill gap is confirmed, training should follow afterward. When a superior's decision is already made and the project manager disagrees, help the appointed person adapt to the new role, keep the person who was passed over motivated, and do not express dissatisfaction in public.
Example: falling output in the test group
On a logistics-system upgrade project, the test group's weekly count of completed test cases fell for three weeks running. The project manager did not criticize first, and did not add people straight away. She first talked separately with the group lead and two members, and found two problems. The test environment had to be reset by hand every week, which took half a day from each person, and one member was also being pulled in to support another project. She coordinated with the functional manager to stagger that member's support work, and had the development group turn the environment reset into a script. Two weeks later output recovered. Along the way she also privately encouraged a member who had recently gone quiet to speak up more in the weekly meeting, without naming the person in front of others.
Worked examples
Example 1: A member is overwhelmed and shows discontent: listen first, then find support together
On a newly formed mobile app development team, an experienced back-end engineer is overwhelmed by several complex integration tasks and shows dissatisfaction with the team. What should the project manager do?
Show answer and explanation
Correct answer: D
On a newly formed app development team, an experienced back-end engineer is overwhelmed by several complex integration tasks and shows dissatisfaction with the team. The question asks what the project manager should do.
When a member feels overwhelmed, first find out exactly where the difficulty lies. Listening carefully both eases the emotion and locates the problem. Then work with him to find the support available, such as adjusting the division of work, adding resources or arranging help from others. That handles both the feelings and the task load. Careful listening makes the member feel respected and valued, so he is more willing to say what the real difficulties are, and any later adjustment has a basis. The correct answer is D.
Why the other options are wrong
- A. Recording possible delays in the risk register only logs a potential risk. It neither eases the emotion nor helps him sort out the tasks.
- B. Saying only that the tasks cannot be avoided and asking him to cope himself offers no concrete help and may deepen the dissatisfaction.
- C. Team building can ease the mood, but this member has a clear, specific problem with his tasks, and team building cannot lighten his burden.
Key takeaway When a member is overwhelmed, listen first, then look together for the support available.
Variation If many members are generally tired, first find the source of the pressure and adjust the pace and workload.
Something wrong with this question?
Example 2: An excellent member is suddenly late several times: find out why things changed
A project manager is managing a fairly large project. At the quarterly review meeting, he notices that a UI designer who has performed well in the past has recently missed several deadlines. What should the project manager do?
Show answer and explanation
Correct answer: B
At a quarterly review of a large project, the project manager notices that a UI designer who used to perform well has recently been unable to finish work on time on several occasions. The question asks what the project manager should do.
The stem does not state a cause. It could be task difficulty, a personal reason, a lack of skills or a blocked process. If you act before the cause is known, you are likely to prescribe the wrong remedy. First talk with the designer to find out why his performance has changed, and then agree countermeasures together. That is the first step in handling a performance problem. In the conversation, listen, assume no conclusion and do not point out the problem in public, so as to protect his past good performance and his motivation. The correct answer is B.
Why the other options are wrong
- A. Lowering the demands of his tasks before the cause is known may not address the problem at all and may make him feel demoted.
- C. The stem does not say he lacks skills. Asking for training directly offers a solution before the cause is understood.
- D. Bringing a human resources representative to the conversation is premature escalation and puts pressure on the communication. The project manager should first talk with him personally.
Key takeaway When performance changes suddenly, talk privately to find the cause first, then choose measures.
Variation If the conversation confirms a skill problem, arrange training or mentoring. If it confirms a personal reason, agree an adjustment of his workload with him.
Something wrong with this question?
Common traps
Common trap
- "Document first," "punish first," "add a bonus first," "replace first" and "escalate to HR first" are usually later-stage measures in a performance problem, not the first step.
- Talking privately is not the same as doing nothing. If there is still no improvement after the conversation, agree measurable corrective actions together and use formal procedures only when necessary.
- Cliques cannot be solved by banning communication or breaking them up. Use open, transparent information sharing and shared goals.
- A team that works long overtime without results does not need still longer hours. Find the step that limits output.
- When nobody raises a different opinion, it does not mean there is no disagreement. It may be groupthink, or members may be afraid to speak. Create a safe environment.
- When a superior's decision is already made, the project manager should support the appointee and not express dissatisfaction in public.
Key takeaways
- The main line for poor performance: talk privately, find the cause, agree a solution, train or adjust where necessary. Punishment and replacement usually come later. Serious dereliction of duty, or compliance or safety problems, should be handled early in line with organizational policy and governance requirements.
- When the stem asks for the "first step," choose a one-to-one conversation to understand the cause, and do not blame anyone in public.
- For problems affecting the whole team, do a root cause analysis first, hold an open conversation, and then clarify the situation.
- Cliques and isolation: find the cause, set up open information sharing, and help the member integrate through team building.
- Groupthink and reluctance to speak: create a safe environment and encourage critical thinking. For diffusion of responsibility, use a responsibility assignment matrix.
- A tired team needs better planning and processes, not longer hours.
This chapter has 63 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.