Resources and Team

Conflict Management

PMP · Resources and Team · 4 lessons · about 48 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Conflict on a team does not mean the project is badly managed. Resources, schedules and ways of working all create disagreement, and handled well, disagreement can spark creativity and improve decisions. ECO: People domain, Task 2 (Manage conflicts) lists six enablers: identify sources of conflict, analyze the context for the conflict, implement an agreed-on conflict resolution strategy, communicate conflict management principles with the team and external stakeholders, establish an environment that fosters adherence to the ground rules, and manage and correct behavior that violates the ground rules. This chapter covers all six in four lessons.

Conflict questions are mostly scenario questions. The most important thing in this chapter is a solving sequence (common exam practice): identify the source and understand the context first, then talk early and in private, then choose a method by weighing five factors (the importance and intensity of the conflict, the time pressure to resolve it, the relative power of the people involved, the importance of maintaining a good relationship, and whether the motivation is long-term or short-term), and finally follow through until the problem is actually resolved. Exam tip (common exam practice): when the stem gives no other conditions and only asks how to handle a conflict, collaborate/problem-solve is usually the method to consider first, but depending on the situation you may need compromise, smoothing, withdrawing or forcing.

Lessons in this chapter

  • Lesson 1: The nature, sources and principles of conflict. Conflict is unavoidable and can be useful; common sources and the matching fixes; three levels of handling (resolve it themselves, collaborate privately, formal procedures); how conflict escalates.
  • Lesson 2: The five conflict resolution techniques. What withdraw/avoid, smooth/accommodate, compromise/reconcile, force/direct and collaborate/problem-solve mean, their signal words and when each applies; the five factors to weigh when choosing.
  • Lesson 3: Judging conflict scenarios. The solving sequence; what to do in technical disagreements, public blame, misunderstandings, competition for resources, and cross-cultural and personality conflicts.
  • Lesson 4: Conflict and ground rules. Ground rules (defined in the team charter) and team agreements (behavioral parameters and working norms set by the team and upheld through individual and team commitments) are two parallel terms and cannot be swapped; building the environment in advance versus correcting violations afterward; resolving disagreements by returning to the rules.

Chapter map

A conflict appears

  • Identify the source → analyze the context
  • Three levels: members resolve it themselves → project manager collaborates privately → formal procedures (including disciplinary action)
  • Choose a method: collaborate/problem-solve (usually first, depending on the situation) | compromise/reconcile | smooth/accommodate | withdraw/avoid | force/direct (urgent)
  • Prevent and correct: ground rules and team charter (in advance); correcting violations (afterward)
Five conflict resolution techniques
Three levels of handling conflict

Study tips and practice

Start with Lesson 1 to build the habit of identifying first and handling second. Then memorize the five techniques and their signal words in Lesson 2, apply the sequence to scenarios in Lesson 3, and add the rules piece in Lesson 4. When a question asks what to do, for an ordinary conflict that has not yet escalated, first consider finding the cause, talking in private and discussing it together. Escalation, replacing people and punishment come later and are considered only when the conflict persists, exceeds your authority or involves a serious violation. Criticizing people in public should generally be avoided. For questions on the five techniques, rely on signal words: first find what the project manager actually does in the stem, then match it to a technique, rather than going by impressions.

Lesson 1

Conflict on Projects: Nature, Sources and Management Principles

Lesson video

Lesson overview

When people work on a project together, resources, schedules and ways of working all produce disagreement. Conflict is not a sign that the project is badly managed. What the exam cares about is how a project manager views conflict and what to do first when it happens. This lesson covers the first enablers of ECO: People domain, Task 2 (Manage conflicts): identify sources of conflict, analyze the context for the conflict, and communicate conflict management principles with the team and external stakeholders. The next lesson covers the five resolution techniques, and the later ones cover scenarios and ground rules.

Conflict is unavoidable but manageable

Conflict is inevitable in a project environment. Sources of conflict include scarce resources, scheduling priorities, and personal work styles. Team ground rules, group norms, and solid project management practices, such as communication planning and role definition, can reduce the amount of conflict.

Conflict is not necessarily bad. Successful conflict management results in greater productivity and positive working relationships; when managed properly, differences of opinion can lead to increased creativity and better decision-making. Conversely, a team in which everyone agrees and nobody voices a different view is not necessarily healthy; it may mean people have not yet started to work through their differences. So the project manager's job is to manage conflict, neither to eliminate it nor to ignore it. Statements such as “conflict can be prevented in advance,” “all conflict is healthy and needs no intervention,” and “conflict is extremely damaging, so prepare a recovery plan” are all too absolute. The correct view is that conflict is unavoidable on projects and the key is to manage it well.

Identify the source first, then analyze the context

When a conflict arises, the first step is to identify its source and understand the context, and then decide what to do. Ruling immediately, escalating immediately or replacing someone immediately all skip this step. Common sources can be grouped by their fix:

SourceTypical signTypical fix
Scarce resourcesTwo people want the same piece of equipment or the same engineersCheck whether resources match the tasks; adjust the plan or add help
Scheduling prioritiesMore arguments after priorities change frequentlyStabilize priorities and make the ranking rules clear
Personal work stylesOne prefers face-to-face discussion, the other insists on written confirmationLearn each person's habits and agree on how to collaborate
Different understanding of objectivesOne wants the “fastest launch,” another wants “zero defects”Use the project charter to clarify objectives and success criteria
Inconsistent informationMembers hold different information and blame each otherSet up a way to share information
Unclear responsibilitiesEach of two people thinks a task belongs to the otherDefine roles and responsibilities
Uneven workloadSome are overloaded while others have little to doRebalance workload and resources

The first three rows (scarce resources, scheduling priorities, personal work styles) are the sources of conflict listed in PMBOK 8. The last four rows (different understanding of objectives, inconsistent information, unclear responsibilities, uneven workload) are groupings used in common exam practice.

To analyze the context is to find out how the conflict came about: when it began, who is involved, what each side wants, whether there is any history between them, and where it occurred. The same “argument” can call for different handling in different contexts. For example, if a client writes that it does not want to work with a certain team member and gives no reason, first find out the reason rather than replacing the member. If a disagreement between two functional managers is slowing two teams, first find the root cause and then agree on a solution.

Levels of handling conflict

There are three levels of handling, from light to heavy. At the first level, if differences become a negative factor, project team members are initially responsible for resolving them: the people involved talk first and work the matter out. At the second level, if the conflict escalates, the project manager should help facilitate a satisfactory resolution. Conflict should be addressed early and usually in private, using a direct, collaborative approach. At the third level, if disruptive conflict continues, formal procedures may be used, including disciplinary actions. An easy way to remember them: resolve it themselves, collaborate privately, formal procedures.

Three levels of handling conflict

A way of describing escalation that is common exam practice: conflict often escalates step by step. It starts as a discussion about the issue, then emotion enters, then it becomes argument and even personal attack, then people split into opposing camps, and finally they can barely communicate. The project manager should ideally notice it when emotion first appears, step in actively at the argument stage, and not wait until camps have formed. When handling it, focus on the issue and not the person, avoid labels such as “your department is always like this,” and when an argument gets heated, pause and move to a private setting.

Communicate the principles of conflict management to the team and to external stakeholders: conflict is normal; it will be handled early, in private and directly; the people involved talk first, the project manager helps when needed, and formal procedures come last. When these principles are explained in advance, members know what to do when they run into a disagreement.

Example: the fight over the test device

A store-terminal project has only one test device for integration testing. Developer Alex and tester Daniel start arguing in the group chat about who gets it first. The project manager does not rule on it right away. She asks three questions to understand the context: what is the source of the conflict (there is only one device, so scarce resources); what is each person's deadline (integration on Wednesday and regression testing on Thursday); and is there another way (could they borrow a device from another department)? She first asks the two to agree between themselves on a rotation schedule. When they do not settle it, she meets them privately, goes over task priorities with them, and at the same time asks the equipment department for a spare device. She did not call anyone out in the group chat and did not escalate right away, because the matter had not yet gone beyond what the project team could resolve itself.

Worked examples

Example 1 A new project manager who fears conflict: how to view conflict

Question 1Example

A software company's new project manager is leading a team for the first time. At the peak of system integration, developers and testers are deadlocked over defect priorities, and stakeholders are questioning the schedule. She admits she is afraid of conflict and asks an experienced colleague how to think about it. What is the colleague's MOST appropriate answer?

Show answer and explanation

Correct answer: C

A new project manager leading a team for the first time faces developers and testers deadlocked over defect priorities during integration, while stakeholders question the schedule. She admits she is afraid of conflict and asks a colleague how to view it. The question asks for the colleague's most appropriate answer.

Conflict has many sources: scarce resources, scheduling priorities, and differences in work style and personality. Whenever many people work together, conflict is unavoidable, and when it is managed well it can raise productivity and improve decision-making. So the appropriate answer is that conflict is unavoidable on projects and the point is to manage it well, neither eliminating it nor letting it run. The answer is C.

Why the other options are wrong

  • A. Too many factors cause conflict. Planning preventive measures can reduce it but not eliminate it, so “can be prevented” is too absolute.
  • B. Conflict does not necessarily end in disaster, and when handled well it can even surface problems. Preparing a “recovery plan” for it treats conflict as purely bad.
  • D. Moderate disagreement can indeed be useful, but destructive conflict such as personal attacks needs prompt intervention, so “need not get involved” is equally too absolute.

Key takeaway Conflict is unavoidable and beneficial when well managed; do not try to eliminate it and do not ignore it.

Variation If an option read “after conflict escalates, the project manager should provide help,” that statement would be correct: members resolve it first, and the project manager helps once it escalates.

Something wrong with this question?

Report an issue with this question

Example 2 Two developers disagree on an interface convention: what the people involved do first

Question 2Example

On an e-commerce project, two front-end developers disagree about an interface convention, and the dispute is disrupting the team's rhythm. Following the general steps for resolving conflict, what should the two team members do FIRST?

Show answer and explanation

Correct answer: A

On an e-commerce project, two front-end developers disagree about an interface convention and the dispute is disrupting the team's rhythm. Following the general steps for resolving conflict, the question asks what the two should do first.

Conflict is handled at three levels. When differences of opinion become a negative factor, project team members first resolve them themselves. If the conflict escalates, the project manager helps in private. If disruptive conflict continues, formal procedures are used. What the people involved do first belongs to the first level: the two talk with each other and work it out. This puts the responsibility first on the people involved, which respects the members and keeps the project manager from being drawn into every small dispute. The answer is A.

Why the other options are wrong

  • B. The sponsor is not the first level for handling disputes between team members. Going over their heads makes a small matter complicated.
  • C. The project manager's help is the second level, after escalation, not the first step for the people involved, and setting a solution directly shuts them out.
  • D. Ignoring a conflict does not make it go away. A disagreement that already disrupts the team's rhythm has to be handled.

Key takeaway Three levels: members resolve it themselves; the project manager helps privately once it escalates; formal procedures if disruptive conflict continues. The people involved talk first.

Variation If the two talk several times and still deadlock and the dispute escalates, the project manager steps in and helps both sides in private.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Conflict cannot be eliminated entirely and is not always bad; saying it “can be eliminated” or “is all healthy and needs no intervention” is too absolute.
  • When differences become a negative factor, the people involved talk first; the project manager helps only after the conflict escalates; assigning blame and disciplinary action belong to the last stage, formal procedures.
  • It is also wrong to stay completely hands-off and assume an agile team can handle everything itself: when conflict escalates, the project manager still has to help.
  • Criticizing the people involved in public, putting it off, or only suppressing the conflict without following up on the real problem are not good practice.
  • The first response to conflict is to identify the source and analyze the context, not to rule, escalate or replace someone right away.

Key takeaways

  1. Conflict is unavoidable on projects; its sources include scarce resources, scheduling priorities and personal work styles.
  2. Well-managed conflict can raise productivity, spark creativity and improve decisions; the project manager manages conflict, neither eliminating it nor ignoring it.
  3. The first step is to identify the source and analyze the context; different sources have different fixes.
  4. Three levels: members resolve it themselves, the project manager collaborates privately, formal procedures (including disciplinary action).
  5. Early, private, direct and collaborative; focus on the issue, not the person.
  6. Communicate the conflict management principles to the team and external stakeholders in advance.

Lesson 2

The Five Conflict Resolution Techniques: Names, Meanings and When to Use Each

Lesson video

Lesson overview

Once the source of the conflict is clear, the project manager has to choose a way to resolve it. PMBOK 8 gives five general conflict resolution techniques, and each has its place. The exam tests this topic very consistently: the stem describes what the project manager did and asks which technique it is, or describes a situation and asks which technique to use. This lesson first covers the factors that influence the choice, then the meaning, outcome and use of each technique, and finally a judging sequence.

What to consider when choosing a method

The success of project managers in managing their project teams often depends on their ability to resolve conflicts, and different project managers may use different methods. Factors that influence the choice of conflict resolution method include: the importance and intensity of the conflict; the time pressure for resolving it; the relative power of the people involved; the importance of maintaining a good relationship; and the motivation to resolve the conflict on a long-term or short-term basis. None of the five techniques is always right; it depends on these five factors.

The five techniques

Five conflict resolution techniques

The five general techniques are withdraw/avoid, smooth/accommodate, compromise/reconcile, force/direct and collaborate/problem-solve. The order in which they are listed does not rank them by priority, and which to choose depends on the situation. Here is each in turn.

Withdraw/avoid. Retreating from an actual or potential conflict situation; postponing the issue to be better prepared or to be resolved by others. Signals in a stem: “postpones the meeting,” “does not discuss it for now,” “only records it without dealing with it,” “shelves it.” It suits issues that are unimportant, or moments when emotions are running too high and people need to cool down first. It does not directly resolve the conflict: if the issue is only postponed, the problem is still there; if it is passed to others, they carry on dealing with it.

Smooth/accommodate. Emphasizing areas of agreement rather than areas of difference; conceding one's position to the needs of others to maintain harmony and relationships. Signals: “stresses common ground,” “sets differences aside,” “plays down the disagreement,” “steadies the relationship first.” It suits minor conflicts, or situations where the relationship has to be maintained first. The disagreement is only put to one side and remains, and may flare up again later.

Compromise/reconcile. Searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict. This approach occasionally results in a lose-lose situation. Signals: “each gives a little,” “meets in the middle,” “both sides give up part of what they want.” It resolves the problem only temporarily or partially and is not a long-term solution.

Force/direct. Pushing one's viewpoint at the expense of others; offering only win-lose solutions, usually enforced through a power position to resolve an emergency. This approach often results in a win-lose situation. Signals: “decides by authority,” “makes the call on the spot,” “no room for negotiation.” It is used when a decision must be made quickly in an urgent situation, and it normally relies on authority. Because it easily creates a win-lose outcome and damages relationships, it should be used with care.

Collaborate/problem-solve. Incorporating multiple viewpoints and insights from differing perspectives; requires a cooperative attitude and open dialogue that typically leads to consensus and commitment. This approach can result in a win-win situation. Signals: “brings the parties together,” “finds out the real needs,” “works out a solution that serves everyone,” “a long-term resolution.”

How to choose

When the question gives no special conditions, collaborate/problem-solve usually comes first because its open dialogue supports consensus and commitment and is best suited to pursuing a durable resolution; next comes compromise/reconcile, then smooth/accommodate, then withdraw/avoid where necessary, and force/direct in an emergency. This ordering is common exam practice for judging questions. There are four special conditions to remember: when it is urgent and you have the authority to decide, use force/direct; when the conflict is minor and the relationship has to be steadied first, use smooth/accommodate; when the issue is unimportant or emotions are too high and people need to cool down first, use withdraw/avoid; and when you only need a temporary or partial resolution and time is limited, use compromise/reconcile.

The table below puts the five techniques side by side for comparison:

TechniqueWhat you doResultWhen to use
Collaborate/problem-solveOpen dialogue that combines everyone's viewpointsWin-win, consensus and commitmentDefault first choice; a long-term resolution is needed
Compromise/reconcileEach gives a little; meet in the middleTemporary or partial resolution; may be lose-loseTime is limited; a partial resolution is enough
Smooth/accommodateStress agreement; one side gives wayRelationship preserved, disagreement remainsMinor conflict; steady the relationship first
Withdraw/avoidRetreat, postpone or hand it to someone elseThe project manager has not dealt with it directly; the problem may remain or be resolved by othersUnimportant, or people need to cool down first
Force/directPush one side's view through powerWin-lose; harms the relationshipUrgent and you have the authority to decide

The “When to use” column summarizes common exam practice.

Two pairs are the easiest to confuse. Compromise/reconcile versus smooth/accommodate: in the first, both sides step back and each gets part of what it wants; in the second, one side gives way for the sake of the relationship and the disagreement remains. Collaboration versus compromise: collaboration puts each side's real needs on the table and looks for a solution that serves them; compromise has each side give up something and meet in the middle. Also, “only recording it and not dealing with it” is avoidance, not collaboration; “bringing the parties together for open discussion” is collaboration.

Example: the booth lighting plan

Two weeks before a medical-device trade show, two members cannot agree on the booth lighting plan. If there is plenty of time, the project manager brings the two and the lighting supplier together and has each side first explain their constraints (budget, product display effect, installation hours), then evaluates the options against the display goals and settles the plan jointly and records it. That is collaborate/problem-solve. If each drops part of their demands and they settle on a middle plan, that is compromise/reconcile. If the plan is still undecided the day before opening and the project manager picks one by authority, that is force/direct. If the dispute is only over a minor point such as the order of fonts on a display board, stressing what both already accept and playing down the argument over order is smooth/accommodate. If both are angry and the project manager pushes the meeting to the afternoon first, that is withdraw/avoid.

Worked examples

Example 1 A long-term solution is needed: choose collaborate/problem-solve

Question 1Example

A drone delivery project is close to delivery when the government suddenly issues a new regulation that may affect the final product, and the project is forced to pause for a time. The sponsor wants the project closed out quickly, the head of R&D wants to wrap up as planned, and the head of testing says the product cannot move forward. The two argue fiercely. Which conflict resolution technique should the project manager use to reach a long-term solution?

Show answer and explanation

Correct answer: A

A drone delivery project nears delivery when a new regulation may affect the product. The sponsor wants a quick close-out, the head of R&D wants to finish as planned, and the head of testing says the product cannot move forward. The R&D and testing heads argue fiercely. The question asks which technique yields a long-term solution.

The deciding clue is the requirement for a long-term solution. The two sides hold different positions, each with grounds. To pursue a durable resolution, the most suitable approach is to face the matter directly, lay out each side's views and concerns, and work toward consensus and commitment through open dialogue. That is collaborate/problem-solve, which can produce a win-win result. Because the sponsor, R&D and testing all hold different positions, it is better to bring them together and jointly assess the regulation's impact against the project's objectives. The answer is A.

Why the other options are wrong

  • B. Compromise/reconcile means each side gives a little. It resolves the conflict only temporarily or partially and can even produce a lose-lose result, so it is not a fundamental solution.
  • C. Smooth/accommodate emphasizes common ground and does not resolve the conflict itself.
  • D. Force/direct pushes one side's view through power and is suited to emergencies, but it often produces a win-lose outcome and damages relationships, making it unsuitable for the durable, mutually accepted resolution requested here.

Key takeaway When the stem calls for a long-term solution, choose collaborate/problem-solve (win-win, with consensus and commitment).

Variation Only if just half a day remained, a decision had to be made at once, and that decision was within the project manager's authority and consistent with the new regulation, would force/direct be an option; otherwise the decision should be made by the responsible governance or compliance owner.

Something wrong with this question?

Report an issue with this question

Example 2 A minor conflict where the relationship comes first: smooth/accommodate

Question 2Example

Two members of the procurement group disagree about the format of meeting minutes. After assessing it, the project manager concludes the matter is unimportant and will not affect core project deliverables, and just wants both to calm down and continue working together pleasantly. What is the MOST suitable way to handle the conflict?

Show answer and explanation

Correct answer: A

Two procurement group members disagree about the format of meeting minutes. The project manager judges it unimportant and not a threat to core deliverables, and only wants both to calm down and keep working together happily. The question asks for the most suitable way to handle the conflict.

PMBOK 8 says the choice of resolution method depends on factors such as the importance and intensity of the conflict, the time pressure to resolve it, and the importance of maintaining a good relationship. This matter is unimportant and the aim is only to ease the mood and keep the relationship. Smooth/accommodate emphasizes agreement over differences and gives way to maintain harmony, which fits well. The answer is A.

Why the other options are wrong

  • B. Force/direct pushes one side's view through power. Using power on a trivial matter would hurt the relationship and is not worth it.
  • C. Collaborate/problem-solve takes a lot of time to dig into root causes, which is too much investment for a small matter that does not affect delivery.
  • D. Compromise/reconcile needs both sides to give up some conditions after time spent negotiating. That also costs more than necessary, when the project manager only wants to ease the mood.

Key takeaway When the conflict is unimportant and the aim is just to calm things down and preserve the relationship, use smooth/accommodate.

Variation If the format dispute affected the compliance of contract documents, the importance of the conflict would rise and collaborate/problem-solve should be used instead.

Something wrong with this question?

Report an issue with this question

Example 3 The day before opening, a decision is needed now: force/direct

Question 3Example

The day before a trade show opens, two key members are arguing endlessly about the booth lighting layout. The project manager has the authority to decide the layout, and a batch of exhibits is waiting on site to be put on display. If the layout is not settled soon, the show-day presentation will suffer badly. Which approach should the project manager use now?

Show answer and explanation

Correct answer: B

The day before a trade show opens, two key members argue about the booth lighting. The project manager has the authority to decide, exhibits are waiting to be installed, and without a prompt decision the opening-day display will be badly affected. The question asks which approach the project manager should use.

Time pressure is the deciding condition. Collaboration is the most thorough approach but needs time for full discussion, and there is no such time the day before opening. For an emergency the project manager can use their authority to settle it quickly. This is where force/direct applies: it is a win-lose approach, but it avoids a larger loss. After deciding, the project manager should still explain the reasoning and, after the show, review the experience and repair any damage the decision did to relationships. The answer is B.

Why the other options are wrong

  • A. Collaboration needs time for each side to explain, evaluate and build consensus, and the time is not there.
  • C. Compromise/reconcile provides only a temporary or partial resolution and still requires the parties to reach a middle position. Because the stem describes an urgent deadlock and gives the project manager authority to decide immediately, force/direct is more suitable.
  • D. Withdraw/avoid would leave the problem hanging, and it could not be settled before the opening.

Key takeaway When it is urgent, there is no time to negotiate and you have the authority to decide, use force/direct; when it is not urgent, prefer collaboration.

Variation If the situation were “two weeks before the opening,” the project manager should first collaborate, bringing the two together to find out what each needs.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Compromise/reconcile and smooth/accommodate are the easiest to confuse: in the first, both step back and each gets part of what it wants; in the second, one side gives way for the sake of the relationship and the disagreement remains.
  • Shelving, postponing or only recording without dealing with it is withdraw/avoid, not collaboration.
  • If the stem has no urgency signal, do not choose force/direct; it is a win-lose approach and harms relationships.
  • “A long-term resolution,” “win-win” and “consensus and commitment” point to collaborate/problem-solve; “temporary or partial resolution” points to compromise/reconcile.
  • Collaboration needs open dialogue and real needs, not each side submitting a plan to compare, and not making one side give way.

Key takeaways

  1. Factors that influence the choice: importance and intensity, time pressure, relative power of those involved, importance of maintaining the relationship, long-term or short-term motivation.
  2. The five techniques: withdraw/avoid, smooth/accommodate, compromise/reconcile, force/direct, collaborate/problem-solve.
  3. Collaborate/problem-solve can produce a win-win and pursue a durable resolution through consensus and commitment; it is usually the first choice when no special conditions are given.
  4. Compromise/reconcile means each gives a little, for a temporary or partial resolution that may be lose-lose; smooth/accommodate gives way for the relationship while the disagreement remains.
  5. Force/direct is win-lose and is often used when a decision must be made quickly in an urgent situation, so use it with care; withdraw/avoid suits unimportant matters or moments when people need to cool down first.
  6. In questions, catch the signal words first and then match the technique.

Lesson 3

Judging Conflict Scenarios: From Identifying the Source to Choosing the Right Action

Lesson video

Lesson overview

This is the most heavily tested topic in conflict management, and almost all of it is scenario questions: technical disagreements, public blame, emotional outbursts, misunderstandings, competition for resources, and stakeholders who disagree with one another. The wrong options often include escalating first, replacing someone first, punishing first, or pointing out mistakes in public. The right actions follow one consistent logic. This lesson breaks that logic into a sequence and then lists the matching approach for each type of scenario. The source analysis from the first lesson and the five techniques from the second are both used here.

The solving sequence

The sequence below and the approaches for each scenario are common exam practice. PMBOK 8 on conflict management gives principles such as addressing conflict early, talking in private and collaborating directly, plus the five techniques, and the facts in the stem come first. The sequence for scenario questions is basically fixed: first identify the source of the conflict and understand the context; for conflicts involving people, if it can be discussed in private, do not discuss it in public; if it can be handled early, do not let it escalate; anchor on the project objectives and focus on the issue, not the person; when there are no urgency signals, use collaborate/problem-solve: bring the parties together, find the root cause and discuss it jointly; when collaborating, work for a solution that the parties accept, and if they do not accept it, renegotiate rather than forcing it through or declaring the matter closed; a conflict that has merely been suppressed is not resolved, so keep following up on the real problem.

One more point is about the project manager's role: when stepping into a conflict, the project manager should stay neutral and help the parties find their own solution, without taking sides. If the project manager later finds that he or she has unintentionally favored one side, the project manager should correct that and handle the matter fairly again. In an agile environment, the people involved talk first; an agile coach or Scrum Master steps in when necessary to guide the team to work through the disagreement professionally and collaboratively, and a technical disagreement is settled by the team discussing the pros and cons of each option fully and working toward consensus, not by one role making the call.

Approaches by scenario

Technical disagreements and priority disputes. Two people or two groups hold fast to their own solutions and threaten the schedule: bring them together, find the root cause, and discuss it jointly around the project objectives and schedule priorities to find a solution that serves both. For example, if two subsystem teams delay the project because their integration point is not aligned, first meet with the two integration leads, find the root cause and then agree on a solution. When both sides' arguments stay anchored in technical facts, there is no need to suppress them: encourage them to keep arguing from the facts and use the disagreement to improve the solution.

Public blame and escalating emotion. Members argue or blame each other in public: stop it first, move to a private setting and talk in a supportive way; when someone who is emotional demands an immediate ruling, calm that person down and understand the situation first, and then handle it at a suitable time. For an emotionally charged conflict, cool things down first, deal with the emotions, and only then move to facts and solutions; when people blame each other, steer the team to focus on risks and countermeasures, no longer on blaming each other. If a member loses control in front of the client, meet with that member alone after the meeting and restate the expected behavior in front of clients.

Misunderstandings, opaque information and disputes over credit. When people accuse each other of “taking the credit,” first learn each side's view of the division of work and ownership of the results, and clarify the facts; you can also set up a transparent record of progress and contributions so the results are plain to see. When people hold each other up, each waiting for the other, sort out the task dependencies and set up a way to communicate in advance.

Competition for resources and functional managers. Two departments want the same group of engineers: guide both sides to discuss and find an approach that serves both needs. When you disagree with a functional manager over budget or activities: work with that manager to decide together which key activities the budget can cover. When stakeholders disagree about requirements and approval keeps being delayed: first identify the source of the disagreement and find the sticking point, then help them reach consensus, neither passing it to the sponsor nor avoiding it.

Cross-cultural and personality conflicts. A team has members from several countries and cultural differences cause friction: arrange to meet the people concerned, talk through the cultural differences together and coordinate a resolution, and do not try to settle it in front of everyone in a public meeting. If two people on the critical path have a personality clash that is already affecting the project, step in early and in private, get both to work on the problem directly together, and also record the issue, the agreed measures and the owner in the issue log and keep tracking it; if disruptive conflict continues and neither the team nor the project manager can resolve it, then follow the organization's formal procedures, asking the human resources department for help if necessary. When a conflict directly endangers the critical path, step in quickly and, if necessary, reassign people or bring in extra help to protect the critical path.

Example: the interface dispute between the back-end and front-end groups

Two months into a fresh-grocery e-commerce project, the front-end and back-end groups have argued three times over which fields the order interface should include, and are complaining about each other in the group chat. The project manager does not first decide who is right. In order, she does five things: she talks privately with each group lead and learns that the front end wants complete fields while the back end worries about slower responses, so the source is a technical disagreement plus different priorities; she brings the two leads into a meeting room, anchors on the goal that integration testing must be finished by next Wednesday, and asks each side to explain its constraints; comparing response time with the display requirements, they jointly settle on a paginated response; she writes the conclusion into the interface specification and both confirm on the spot that they accept it; and a week later she checks and confirms that integration finished on time and that no similar argument has recurred. Throughout, the project manager did not call anyone out in the group chat and did not escalate to the sponsor.

Worked examples

Example 1 Front end and back end have a technical disagreement and blame each other: bring the team together to understand and resolve it

Question 1Example

The project is in the execution phase. The project manager sees that the front-end group and the back-end group have both a technical disagreement over the interface design and mutual complaints, and relations are tense. What should the project manager do?

Show answer and explanation

Correct answer: C

During execution, the front-end and back-end groups have a technical disagreement about the interface design and also complain about each other, and relations are tense. The question asks what the project manager should do.

The conflict is already affecting collaboration, so the project manager should step in promptly. Calling the team together to understand what happened and then discussing solutions jointly is collaborate/problem-solve, and it follows the order of identifying the source and understanding the background first. A problem arising during execution should be resolved during execution. The meeting has to deal with both the technical disagreement and the emotional complaints: first get both sides to set out the facts, and then discuss solutions. The answer is C.

Why the other options are wrong

  • A. A fixed quarterly meeting would miss the window, because conflict is time-sensitive, and the tension would keep festering until then.
  • B. Lessons learned and retrospectives should run throughout the project, not only at its end. But this conflict is hurting execution now, so it cannot be put off to a later review activity. It needs prompt understanding and resolution.
  • D. Conflict inside the team is within the project manager's authority and should be handled by the project manager first, without bringing in an outside consultant.

Key takeaway When you see conflict, step in promptly, gather the parties and work out the source and solutions together.

Variation If the conflict were a personality clash that neither the team nor the project manager could resolve, only then consider formal channels such as human resources.

Something wrong with this question?

Report an issue with this question

Example 2 R&D wants on-time delivery and operations wants a fit with the stores: find an approach both can work with

Question 2Example

On a restaurant chain's new ordering system project, the members come from three departments: R&D, operations and store training. While preparing the pilot, R&D and operations get into an argument: R&D is determined to launch on time and within budget, while operations insists the system must fit the stores' actual ordering workflow. What should the project manager do?

Show answer and explanation

Correct answer: C

On a new ordering system project, members come from R&D, operations and store training. During pilot preparation, R&D wants an on-time, within-budget launch and operations insists the system fit the stores' real ordering workflow. The groups argue. The question asks what the project manager should do.

Both groups' demands have merit: one concerns delivery, the other whether the system can actually be used in the stores. The project manager should push the groups to discuss together, put their real needs on the table and find an approach that is on time, within budget and fits the store workflow. That is collaborate/problem-solve, aimed at a win-win. In the process, the two groups' demands can be listed side by side so that the project manager does not listen only to the louder side. The answer is C.

Why the other options are wrong

  • A. Urging each side to give a little is compromise/reconcile, which may leave the core needs of both groups unmet.
  • B. Deciding that R&D's position is sound takes sides and ignores operations' needs. The system might not work in the stores.
  • D. Having the groups each submit a plan and comparing them encourages competition, which would intensify the conflict and hurt cohesion.

Key takeaway When each side's demands are legitimate, get them to discuss together and find a way that serves both.

Variation If the system had to go live the day after the pilot began, requiring a plan that same day, and the project manager had the authority, force/direct could be used; otherwise the project manager should still push the team toward quick, collaborative decision-making.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • “Escalate to the sponsor first,” “remove someone outright,” “point out mistakes in public” and “punish first” are usually later-stage measures in scenario questions.
  • With no urgency signal, do not choose force/direct; bring the parties together, find the root cause and discuss it jointly.
  • Suppressing a conflict is not resolving it: follow up on whether the real problem is actually resolved, and where you collaborate, also work for the parties' acceptance of the solution.
  • Do not take sides or jump to conclusions; stay neutral and help the parties come up with a solution.
  • In an agile environment, a technical disagreement is settled by team discussion and consensus, not by one role making the call, and it is not simply left alone either.
  • Handle cultural conflict head-on, but not by settling it in front of everyone at a public meeting; for a personality clash, bring in human resources only if the team cannot resolve it.
  • Waiting for a quarterly meeting or the lessons learned session to deal with a conflict misses the window.

Key takeaways

  1. Sequence for scenario questions (common exam practice): identify the source and understand the context, talk privately, choose a suitable method, choose collaboration when there are no urgent conditions, and follow up until it is truly resolved.
  2. Technical disagreements and priority disputes: anchor on the project objectives, have both sides discuss together and find a solution that serves both.
  3. Public blame and escalating emotion: stop it first, move to private, cool down before turning to the facts.
  4. Misunderstandings and credit disputes: clarify the facts first and set up transparent practices.
  5. Competition for resources and stakeholder disagreement: analyze the context first, find the sticking point, drive consensus and do not push it to the sponsor.
  6. Stay neutral; bring in human resources for a personality clash only if the team cannot resolve it, and treat escalation as a later-stage measure.

Lesson 4

Conflict and Ground Rules: Set the Rules in Advance, Correct Violations Afterward

Lesson video

Lesson overview

The first three lessons dealt with what to do after a conflict appears. This lesson changes direction: how to make conflict less likely and give people something to rely on when it does occur. The answer is ground rules and the team charter. This lesson covers the last two enablers of ECO: People domain, Task 2 (Manage conflicts): establish an environment that fosters adherence to the ground rules, and manage and correct behavior that violates the ground rules. Questions come in two types, agreeing rules in advance and correcting violations afterward, and the two should not be confused. The lesson is short, but it contains several common exam traps.

What ground rules are and why they reduce conflict

Ground rules are expectations regarding acceptable behavior by project team members. Defined in the team charter, ground rules set the expected behavior for project team members and other stakeholders with regard to stakeholder engagement. PMBOK 8 also has a parallel term, team agreements (from The Standard for Project Management): a set of behavioral parameters and working norms that are established by the project team and upheld through individual and team commitments. These agreements should be created at the beginning of a project to determine the essential norms and practices that facilitate ongoing collaborative success. Both are used to agree how members will work together, but they are not the same term: ground rules are defined in the team charter (in the Guide), while team agreements have a definition of their own. Whichever term appears in a question, answer according to that term's definition.

The conflict management section states that team ground rules, group norms, and solid project management practices can reduce the amount of conflict. Ground rules work for three reasons. First, they work best when the team develops them or at least has an opportunity to contribute to them (PMBOK 8: the team charter works best when the team develops it or at least has an opportunity to contribute to it), rather than the project manager simply announcing them, because members are more willing to follow rules they helped shape. Second, because the rules are agreed in advance, when a disagreement arises there is a commonly accepted basis for resolving it, and the project manager does not have to judge by personal preference. Third, when a rule is broken, what is being corrected is “breaking what we all agreed,” not something aimed at one individual.

The team charter items most directly related to conflict are communication guidelines, decision-making criteria and processes, conflict resolution processes and meeting guidelines. Agreeing item by item what rules to follow in meetings, how to communicate day to day and how to settle disagreements, and writing them into the team charter, is building an environment that fosters adherence to the ground rules, and it is prevention in advance.

Agree in advance, correct afterward

Keep two kinds of situations apart.

In advance: develop the rules together at the start of the project; when a new member joins, help that person learn the team's ground rules and settle in quickly; when a dominant member keeps newer members from speaking, guide that person to see things from their side and bring everyone together to set ground rules for equal communication; agreeing on ground rules, keeping communication channels open and resolving small disagreements early are effective ways to keep small disagreements from escalating into conflict (PMBOK 8 puts it as “can reduce the amount of conflict”).

Afterward: only once a rule has been broken does correction come in. If the meeting rules are clearly written and have been repeated many times, and someone still keeps interrupting others, remind that person on the spot to follow the rule against interrupting, and speak with him or her individually after the meeting to correct the repeated violation. When a rule is broken in public (for example, mocking someone in a meeting), stop it on the spot, restate the ground rules and bring the discussion back to the issue itself. If two members argue openly in a meeting and one goes over everyone's head to the sponsor for a ruling, restate the ground rules before the next meeting and confirm that everyone is clear on them, and also talk to each of the two separately to correct their own behavior. When a member repeatedly breaks an agreed process, talk privately, explain the value of the process and invite the member to help improve it, without criticizing in public. When a member believes he has done nothing wrong, ask him to check himself against the team charter and then meet one-on-one. When members shift blame or point fingers because of misunderstandings and information that does not get through, improve the channels and ways of communicating so that information is conveyed accurately.

Resolving disagreements by using the rules: when two key resources cannot agree on a requirement, use the ground rules set at the start of the project to help resolve it; when someone refuses to meet and talk, use the ground rules in the team charter and the project vision to bring the parties back to what they agreed. When team members talk about each other behind their backs and will not accept feedback, revisit the ground rules for collaborative behavior in the team charter, check whether a relevant provision exists, and restate or add to it. For a dispute caused by unclear responsibilities, such as who writes an acceptance document, the root fix is to define roles and responsibilities. When similar conflicts appear one after another, analyze the root cause and summarize what they have in common; if you confirm that a rule or process has a gap, then fix it to prevent recurrence.

Example: a sneer in the weekly meeting

On the order-system team for a pharmacy chain, the ground rules in the team charter say “discussion is about the issue, not the person” and “do not interrupt speakers in meetings.” At a weekly meeting, back-end engineer Mike mocks his tester colleague Joy: “You can't even test this properly.” The room goes quiet. The project manager says on the spot: “Our agreement is that discussion is about the issue, not the person. Please describe it as a specific defect.” Then she brings the discussion back to the defect itself. After the meeting she talks with Mike and Joy separately: with Mike, she points out that his behavior does not fit the team's agreement and asks about the pressure he was under; with Joy, she asks how Joy feels. She did not criticize him in the meeting and did not record it in his appraisal or notify his functional manager. Two weeks later, she adds to the team charter's ground rules: “When your work is questioned by name, first ask the other person to describe the specific problem.”

Worked examples

Example 1 Members talk about each other behind their backs and will not listen: return to the ground rules in the team charter

Question 1Example

Two members of a project team are in conflict: Member A says Member B is always talking about colleagues behind their backs. A will not listen to any advice, and B will not accept feedback. How should the project manager handle this?

Show answer and explanation

Correct answer: A

Member A thinks Member B is always talking about colleagues behind their backs; A will not listen to advice and B will not accept feedback. The question asks how the project manager should handle this.

The disagreement is essentially about standards of behavior: what counts as acceptable collaborative conduct. The team charter, including its ground rules, sets the behavior and communication the team has agreed on. Going back to the ground rules in the team charter, checking whether they cover talking about others and accepting feedback, and reaffirming or adding to them lets the project manager correct behavior against a standard everyone agreed to, instead of each side saying its own thing. Relying on the shared agreement also keeps the project manager from judging by personal preference. The answer is A.

Why the other options are wrong

  • B. Moving one person is avoidance. It does not address the missing agreement on collaborative behavior, and the problem may repeat in the new setting.
  • C. The communications management plan is built from stakeholders' communication needs. The stem shows no change in those needs, and the behavior problem between the two members should be addressed first.
  • D. These behaviors may affect performance, but the stem does not show that disruptive conflict has continued after correction within the team. Reporting to their supervisors now would therefore be premature escalation; the behavior should first be addressed within the team using the rules.

Key takeaway For a dispute over behavior standards, go back to the ground rules in the team charter and use the shared agreement as the basis.

Variation If the charter has no relevant provision yet, add one together with the team and make clear that the new rule applies to all members.

Something wrong with this question?

Report an issue with this question

Example 2 Mocked in public at a meeting: stop it on the spot and restate the rules

Question 2Example

The ground rules in the team charter state: “Discussion is about the issue, not the person.” At a regular meeting, Member A mocks Member B's ability in front of everyone. What should the project manager do?

Show answer and explanation

Correct answer: C

The ground rules in the team charter say “discussion is about the issue, not the person.” At a regular meeting, Member A mocks Member B's ability in front of everyone. The question asks what the project manager should do.

Mocking someone's ability is a personal attack. It breaks the ground rules the team agreed on and happens in public. The project manager should stop it on the spot, restate the rule and bring the discussion back to the issue itself, which protects B and upholds the authority of the rule. After the meeting, the project manager talks privately with A to understand the reason and, as appropriate, with B, to avoid lingering resentment. The answer is C.

Why the other options are wrong

  • A. Letting them finish and asking for statements afterward effectively lets the attack continue. It hurts B and makes the rule meaningless.
  • B. Recording it in the appraisal immediately and notifying the functional manager is too harsh. A violation should first be corrected within the team, and there has been no conversation.
  • D. Pausing the meeting to ask the sponsor to rule on who is right hands off a conflict inside the team that the project manager can handle.

Key takeaway When a ground rule is broken in public, stop it on the spot, restate the rule and bring the discussion back to the matter at hand.

Variation If a member merely kept breaking an agreed process rather than attacking someone in public, talk with him privately and invite him to help improve the process.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Set the rules in advance and correct afterward: agreeing rules in advance is building the environment, and only after a rule has been broken does correcting behavior come in.
  • Ground rules work best when the team develops them or at least has an opportunity to contribute; in exam questions, rules the project manager announces alone are usually not the good answer.
  • When a rule is broken, check against the rule and talk in private first; do not start with public criticism, tattling or escalating to the functional manager.
  • When a rule is broken in public, stop it on the spot and restate it; letting it pass amounts to condoning it.
  • For conflict caused by unclear responsibilities, the root fix is to define roles and responsibilities, not to move people.
  • When the same kind of conflict keeps recurring, go back and repair the rules and processes instead of handling only the individual case.

Key takeaways

  1. Ground rules are expectations regarding acceptable behavior by project team members, defined in the team charter; team agreements are a parallel term, a set of behavioral parameters and working norms established by the team and upheld through individual and team commitments, and the two cannot be swapped.
  2. Team ground rules and norms can reduce conflict; ground rules should be agreed early; the team charter works best when the team develops it or at least contributes to it; team agreements should be created at the beginning of the project.
  3. Establishing an environment that fosters adherence to ground rules (in advance) and correcting behavior that violates them (afterward) are two different things.
  4. For violations: if it happens in public, stop it on the spot and restate the rule; if it keeps happening, talk privately and invite the person to help improve the process.
  5. Disagreements can be resolved against the ground rules agreed in advance and the shared vision; unclear responsibilities call for defined roles and responsibilities.
  6. When similar conflicts keep recurring, repair the rules and processes.

This chapter has 56 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.