The PMP study guide for Project Management Principles: 2 chapters and 6 lessons, about 1 h 3 min of study. Every lesson has worked examples with the explanation folded until you open it. Read the topic guide first ↓
Watch the free Project Management Principles videos in the PMP video course →
Chapters in this topic
Topic guide
What this topic covers
Project management is not just a set of tools and processes. It is first of all a mindset. Section 3 of The Standard for Project Management in the PMBOK Guide, Eighth Edition answers the question "how should I think and act?": six principles provide foundational guidance for strategy, decision-making and problem-solving, and seven performance domains turn those principles into concrete practice. This topic covers the six principles: Adopt a Holistic View, Focus on Value, Embed Quality Into Processes and Deliverables, Be an Accountable Leader, Integrate Sustainability Within All Project Areas, and Build an Empowered Culture. It also covers the ethical lines a project manager must never cross. When you finish, you should be able to: explain the nature of the principles and place the six principles within the three mindset dimensions; judge in a scenario question whether a practice reflects or violates a principle; connect the principles to the performance domains and to the twelve principles of the Seventh Edition; and, in an ethical dilemma, choose the honest, transparent and rule-abiding course of action.
Two chapters, six lessons
The topic has two chapters and six lessons. The "Project Management Principles" chapter has four lessons: the nature of the principles, the holistic view and focus on value; quality and the accountable leader; an empowered culture, plus how the principles relate to the performance domains and to the Seventh Edition; and professional ethics. The "Sustainability" chapter has two lessons: the meaning of sustainability, the triple bottom line and the four impact strategies; and how to integrate sustainability, the challenges involved, and its relationship to the performance domains and to compliance. Sustainability is one of the six principles, but it has a chapter of its own because there is a lot of material and because the exam content outline explicitly lists it as a new trend.
| Chapter | Content | In one sentence |
|---|---|---|
| Project Management Principles | Nature of the principles; holistic view; value; quality; accountable leader; empowered culture; relationship to the performance domains and the Seventh Edition; professional ethics | How to think, and how to behave and work |
| Sustainability | Meaning; triple bottom line; compensate or offset, restore, minimize, avoid; ways to integrate it; challenges; compliance | Do not exhaust what you depend on |
In the exam content outline, the principles do not have a task of their own. They run through the judgment behind many tasks: leading the team, empowering the team and managing conflict belong to the People domain, and quality, value and compliance belong to the Process and Business Environment domains. Most questions on this topic come down to practices such as "create a safe team environment", "report honestly" and "follow the process".
How the chapters fit together
The six principles are easiest to remember through three dimensions. Proactive: Adopt a Holistic View and Embed Quality Into Processes and Deliverables are about how the work is done, thinking in systems and building quality in. Ownership: Be an Accountable Leader and Build an Empowered Culture are about how people are led, with leaders setting the example and teams empowered in a safe environment. Value-driven: Focus on Value and Integrate Sustainability Within All Project Areas are about why the work is done, not only to deliver outputs but to achieve outcomes, and to benefit the community and future generations. The Eighth Edition also says that all principles relate to all performance domains, though some connections are stronger than others. So as you study each performance domain, you can look back and ask: which principle is at work here?
How to study this topic
Remember the nature first, then the classification. The principles are not prescriptive, they complement one another without contradiction, and they may overlap. This point is often tested. You should be able to write out the three dimensions and six principles from memory. Use the principles as a judgment framework. When you see a scenario question, ask: is this practice pursuing the best result for the whole or only for one part? Is it watching outputs or outcomes? Is it creating a sense of safety or relying on punishment? Is it reporting honestly or dressing up the data? For sustainability, focus on the four strategies. Know the meaning, the triple bottom line, and the order compensate or offset < restore < minimize < avoid; in practice, goals go into formal documents and are confirmed by the sponsor. For ethics questions, hold one line. Common exam practice: honesty and appropriate transparency come before efficiency and relationships, while confidentiality duties are honored. When you find a violation, report it to the person with authority to deal with it. If the facts are unclear, you may do the necessary verification first, but do not use that as an excuse to delay or conceal. Once a violation is confirmed, or it is beyond your authority, report it immediately to the person with authority to act.
How this topic relates to others
The principles are the common foundation of every topic. When you study leading the team and stakeholders, you will meet empowerment, psychological safety and leading by example again and again; in scope and quality, outcomes and value and quality built into processes; in risk, the holistic view and honest reporting. So we suggest you study this topic first. When a scenario question leaves you torn between two options that both seem reasonable, go back to the principles: they often help you choose the one closer to the spirit of the principles.
Common ways to lose points
- Treating the principles as rules that must be followed, or believing that two principles can conflict so that one must be given up.
- Believing a project is successful because it delivered on scope, schedule and budget, and ignoring the intended outcomes and value.
- Assuming the project is healthy because local metrics are met, without looking at the dependencies among the parts.
- When the team reports only good news, using punishment or spot checks instead of creating psychological safety.
- Saying there are seven principles, or treating tailoring or optimizing risk responses as principles.
- Understanding sustainability as environmental protection only, or describing the triple bottom line as scope, schedule and cost.
- In ethics questions where the facts are unclear, do the necessary verification first. When reliable facts or clear evidence of a violation already exist, do not choose "quietly fix it" or concealment; inform the people concerned honestly and report to the person with authority to act.