Judgment Rules for Situational Questions

PMP · Exam Strategy · 3 lessons · about 37 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Many PMP exam questions are situational: the stem describes a project scenario and asks what the project manager should do, and several options usually have some merit. You must pick the one that is most appropriate in that scenario. This chapter teaches no new content. It collects the judgment rules already written into the earlier topics and explains the reasoning behind each one, so you can review them all at once before the exam. Most of the rules here are common exam practice; where PMBOK 8 states something explicitly, it is labeled separately. Rules only help you narrow the field, and you still have to read the facts in the stem first.

The chapter has three parts: the exam format and reading the question wording; analyzing and communicating before acting, and telling issues from risks; and authority, escalation and change control.

How to use this chapter

Use this chapter after you have studied the other topics. A good order is to read the key takeaways of the three lessons once, then test yourself with the chapter practice. For each question you miss, return to the matching rule and ask whether you misread the wording, missed a limiting condition, or failed to tell an issue from a risk or authority from change control. To trace a rule back to its source, go back to the study guide for the relevant topic. In the last week before the exam, it is enough to reread each lesson's key takeaways and common traps.

Lessons in this chapter

Chapter knowledge map

Judgment rules for situational questions

  • Judge the environment first: predictive (about 40%) · adaptive / hybrid (about 60%)
  • Read the wording first: NEXT (where the process stands) · FIRST (analysis) · should have been done beforehand (trace back) · limiting conditions
  • Analyze and communicate first, then act
  • Issue (issue log) ≠ risk (risk register); contingency reserve ≠ management reserve
  • Handle within your authority, escalate only beyond it; baseline changes go through change control; adaptive: backlog

Chapter practice: start with the core questions, then do the required ones.

Lesson 1

Exam Format and Reading the Question Wording

Lesson video

Lesson overview

This topic does not teach new content. It collects the judgment rules from the earlier topics and explains the reasoning behind each one. This lesson first looks at the basic format of the exam (number of questions, time, question types, domain weightings) so you can see where situational questions sit. It then covers the first step in reading any question: understanding the wording. Whether a question asks about the "NEXT" step, what to do "FIRST", or what "should have been done beforehand", it is asking what the project manager should do, but the point in time at which the answer sits is completely different in each case. Rules only help you narrow the field, and you still have to read the facts in the stem first.

Exam format

Under the updated PMP Exam Content Outline, the PMP exam has 180 questions: 170 are scored, and 10 are pretest questions. Pretest questions are not scored and are used only to check the validity of future exam questions. All questions are presented in random order rather than sorted by domain, and the time limit is 240 minutes. Question types include multiple-choice questions, multiple-response questions, and the newer case or scenario questions and graphic-based questions, and other formats such as matching, point and click, and pull-down list questions.

Dividing the total time by the total number of questions gives an average of about 1.3 minutes per question (240 ÷ 180). This is only a reference figure, not an allocation from the exam outline. Calculation questions and long case questions need more time and short concept questions need less, so you have to trade time between them as you go.

The three domain weightings are People 33%, Process 41% and Business Environment 26%. Predictive, adaptive/agile and hybrid approaches appear within these three domains rather than in isolation within a single domain or task; about 40% of the questions use a predictive approach, and the remaining 60% or so are spread across adaptive and hybrid approaches. So for any type of question, first decide whether the stem describes a predictive or an adaptive environment, then apply the matching rule.

Key point

  • 180 questions = 170 scored + 10 pretest; 240 minutes; random order.
  • Question types: multiple-choice, multiple-response, case or scenario, graphic-based, plus other formats such as matching, point and click, and pull-down list.
  • Domains: People 33%, Process 41%, Business Environment 26%; predictive about 40%, adaptive and hybrid about 60%.

Reading the question wording

When you read a question, first decide which point in time it is asking about, and only then compare the options. The three common wordings differ as follows.

WordingMeaningHow to judge
NEXTWhat comes immediately after the steps already completedFirst figure out where you are in the process described in the stem, then decide the following action from the applicable process, the dependencies and the project management plan
FIRSTThe action to take before anything else in the current situationWhen there is no ready-made process step, choose an analysis action such as finding the cause or assessing the impact, not direct implementation
Should have been done beforehand; how to avoid itThe problem has already appeared, and the question asks what should have been done in the past to prevent itTrace back to the root cause and choose the action that could have prevented the problem at the time (often in planning and communication, but possibly in risk, quality, resources or governance); do not choose after-the-fact remedies

NEXT: figure out where you are in the process. When the process in the stem has an order, the answer depends on which step has already been completed. PMBOK 8 does not prescribe a fixed "five-step" change process. In a predictive project, once a change has been recorded and its impact analyzed, it is submitted, as set out in the change management plan, to a designated person or the change control board (CCB) for a decision. The decision (approve, defer or reject) is recorded in the change log and communicated to stakeholders.

A mnemonic that is common exam practice is: record, evaluate, submit, decide, update, notify. The mnemonic is often memorized as five steps, "record, evaluate, submit, update, notify", which leaves out the decision; when you use it, put the decision back in. If the stem says only that the change has been evaluated and submitted, the next step is a decision by the person designated in the change management plan. While waiting for the decision, the project manager keeps executing the planned tasks and continues to analyze the impact and risks of accepting or rejecting the change. If the CCB has already reviewed and rejected the change request, what comes next is recording the outcome (at least updating the change log) and notifying the requester; there is no absolute order between updating and notifying.

Building a schedule usually involves identifying activities, analyzing dependencies, estimating durations and optimizing the schedule, and this work may be iterative. "Verify first, then accept" for scope is another sequence of the same kind. Whatever step the stem has reached, judge the NEXT step from there, and do not repeat steps that are already done. The stage a project is in is also a kind of sequence: right after initiation, when the project moves into planning, the first thing to do is develop the plan, not replace people or outsource.

Should have been done beforehand: trace back. In prevention questions, the problem shows up after an earlier preventive action was missed; its root may lie in planning, communication, risk, quality, resources or governance. If stakeholders say at acceptance that their needs were not met, the team should have involved them early and elicited and analyzed the requirements. If meetings keep ending in disagreement, ground rules should have been set. If stakeholders raise important comments late, a stakeholder analysis should have been done and an engagement strategy planned. If the team misunderstands the plan and drifts off course, the sender should have confirmed through feedback that the message was understood. Rework and change control are after-the-fact actions and cannot prevent the problem.

Check the limiting conditions first. A constraint written explicitly in the stem often decides the answer directly. When compressing a schedule, PMBOK 8 defines crashing as "a schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources", so it applies only to critical path activities where adding resources can shorten the duration. Fast tracking performs activities or phases normally done in sequence in parallel for at least a portion of their duration, and it may result in rework and increased risk. Common exam practice: when the stem gives no other conditions, "cost is no object" points to crashing, while "no additional resources" or "cost cannot overrun" points to fast tracking. Cost and resource limits are only one of the conditions to weigh; you also have to check whether the activities meet the applicable preconditions above. For resource optimization, "the finish date cannot change" points to resource smoothing, which adjusts activities within their free and total float, does not change the critical path, and does not delay the completion date. When resource constraints exist, such as resources being unavailable, limited in number or over-allocated, resource leveling can be used. It adjusts activities to fit the resource constraints and may change the critical path or lengthen the schedule, although a longer duration is not a necessary result.

Example: one scenario, three wordings

During a requirements review for a community services app, a stakeholder representative suddenly asks to change a core workflow. Asked for the "NEXT" step, look at the process first. If the change request has only been evaluated and submitted, the next step is to wait for the person with authority (the approver named in the change management plan, or the CCB) to decide. If a decision has already been made (for example, the request was rejected), the turn comes to updating the log and notifying people, not to evaluating again. Asked for the "FIRST" step, if the representative has only mentioned it verbally and nothing has been recorded, the first thing is to record it and find out what the change is and why it is wanted. Asked what "should have been done beforehand", if such last-minute changes keep happening, the representatives should have been fully involved during requirements and rules for raising changes should have been set up. The scenario is the same, but the wording differs and the answer lands somewhere completely different.

Worked examples

Example 1: Exam format, question composition

Question 1Example

A candidate has registered for the updated PMP exam and wants to understand how the exam is made up. Which of the following statements about the total number of questions, scored questions and pretest questions is correct?

Show answer and explanation

Correct answer: B

The question asks how the exam is made up. There is no project scenario; you only need to remember the total number of questions and the number of scored and pretest questions.

The exam content outline states that the exam consists of 180 questions, of which 170 are scored and 10 are pretest questions. Pretest questions do not affect your score and are used only to check the validity of future exam questions. The time limit is 240 minutes, and all questions are presented in random order. The numbers in the options have to fit 180 = 170 + 10, and only B matches exactly. The answer is B.

Why the other options are wrong

  • A. The exam includes 10 pretest questions; it is not the case that all 180 questions are scored.
  • C. There are 10 pretest questions, not 20, so the number of scored questions is 170, not 160. The numbers are misremembered.
  • D. The total is 180 questions, and 170 is the number of scored questions. This option treats the scored count as the total and also gets the number of pretest questions wrong.

Key takeaway 180 questions = 170 scored + 10 pretest, 240 minutes, questions presented in random order.

Variation If the question asked about the domain weightings instead, the answer would be People 33%, Process 41% and Business Environment 26%. If it asked about the share of predictive questions, the answer would be about 40%, with the other 60% or so adaptive and hybrid.

Something wrong with this question?

Report an issue with this question

Example 2: "What comes next": after a change request is rejected

Question 2Example

A logistics system upgrade project uses a predictive approach. The customer asks for a scope change, and the project manager has recorded it, evaluated its impact and submitted the change request to the change control board (CCB). The CCB reviewed it and rejected the request. The decision is not yet in the change log, and no one has been told. What should the project manager do NEXT?

Show answer and explanation

Correct answer: D

This is a predictive project. The change request has been recorded, evaluated and submitted to the CCB, and the CCB has rejected it. The decision is not yet in the change log and no one has been notified. The question asks what the project manager should do next.

PMBOK 8 requires the status of change requests to be tracked, and the final decision to be managed and communicated to stakeholders. The CCB has already rejected the request, so the decision must be recorded in the change log and communicated to the customer who raised the change and to the team members concerned. Recording and notifying are two actions within the same task, and there is no fixed order for them, nor a fixed five-step change process; follow the change management plan or the stem. D carries out both and does not go back to evaluation or submission. To judge what comes “next”, first locate where the process has got to, then choose the action that follows. The answer is D.

Why the other options are wrong

  • A. This notifies only the customer and postpones recording the decision until the customer replies. The decision does not reach the change log in time, which does not meet the requirement to track change status and record decisions.
  • B. Evaluation comes before submission and has already been done. Without new information, a rejection by the CCB is no reason to evaluate again and resubmit; that would step back to earlier parts of the process.
  • C. The scope baseline can be changed only through formal change control. The CCB has rejected the request, and the project manager cannot get around that decision by accepting the change on their own.

Key takeaway After a change request is rejected, record the decision (in the change log) and notify stakeholders; the order of the two follows the change management plan or the stem.

Variation If the customer had raised the change verbally and nothing was recorded yet, the first step would be to record it. If the CCB had approved it, the next step would be to update the baselines and related plans and notify stakeholders.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • 180 is the total number of questions and 170 is the number of scored questions; the pretest questions number 10. Do not take the number of scored questions as the total.
  • Questions are presented in random order, and predictive and adaptive approaches are spread across all three domains; there is no domain that is "all predictive".
  • The Process domain has the highest weighting (41%), not the People domain.
  • "NEXT" does not mean "the best step": first find out how far the process has progressed.
  • Change handling: evaluation comes before submission. After approval or rejection, record the outcome (update the change log) and notify stakeholders; the order of these two depends on the change management plan or the stem.
  • Do not answer "should have been done beforehand" with an after-the-fact remedy or rework.

Key takeaways

  1. The exam has 180 questions (170 scored, 10 pretest) and a 240-minute time limit, with questions in random order.
  2. Question types are multiple-choice, multiple-response, case or scenario, and graphic-based, plus other formats such as matching, point and click, and pull-down list; the domain weightings are 33%, 41% and 26%.
  3. Predictive is about 40% and adaptive and hybrid about 60%, spread across the three domains; decide the environment first, then apply the rules.
  4. Wording: for NEXT, see how far the process has progressed; for FIRST, when there is no ready-made process step and the facts are unclear, find the cause and assess the impact; for should have been done beforehand, trace back.
  5. A common mnemonic for change handling (common exam practice; the decision must be included): record, evaluate, submit, decide, update, notify. Check the stem's limiting conditions first.

Lesson 2

Analyze and Communicate Before Acting; Issues vs. Risks

Lesson video

Lesson overview

The most common wrong option in a situational question is a project manager who acts without understanding the situation: replacing people straight away, adding budget, cutting scope or escalating. The correct approach usually starts with understanding the situation and communicating. This lesson covers two rules: analyze and communicate before acting, and decide whether the stem describes an issue that has already happened or a risk that might happen, because the two call for different documents and different actions. Both rules apply in predictive and adaptive environments alike.

Analyze and communicate first, then act

Find out the cause first, then decide what to do. Typical cases follow. A milestone is missed or a team member does not finish a task on time: find out the reason in private first, and do not demand an explanation in front of the group. A key stakeholder says a deliverable does not meet the quality specification: first find out whether the problem exists and why the stakeholder thinks so. A key stakeholder does not approve a deliverable: first find out why, then brainstorm solutions, rather than asking the sponsor to apply pressure. A team member resigns and the resignation has been approved: first assess the impact, then decide whether to backfill and what resources are needed. The government unexpectedly issues stricter regulations: first assess with the team the impact on scope, schedule, cost and quality, and only then submit a change request; the change request comes after the assessment.

When you disagree with a stakeholder or receive a demand from one, communicate and negotiate first; do not simply refuse and do not simply comply. A customer asks for work outside the contract: first find out from the requester what the change is and why it is wanted, explain the change control procedure and ask for a written change request. A new sponsor needs to understand project status: first update the stakeholder register and analyze the sponsor's communication needs, then update the communications management plan based on that analysis. A new team member is getting mediocre feedback from the team: meet with that member one-on-one first. Three more rules of thumb for stakeholder scenarios are common exam practice. If scope, schedule, cost and quality are all on target and communication is going as planned, yet the project is suddenly halted, a key stakeholder was probably never identified. Identifying stakeholders and engaging them early is usually the right choice. Expectations are managed through negotiation and communication; managing them effectively can improve stakeholder satisfaction.

Example: the test lead who missed two weeks of reviews

On an e-government platform project, the test lead had not attended the defect review meeting for two weeks, and several high-priority defects were left unresolved as a result. The project manager did not single him out in the weekly meeting and did not complain to his functional manager. Instead, the project manager arranged a ten-minute private conversation and learned that he had been pulled in to support another urgent project, and the meeting times of the two projects clashed. Once the cause was clear, the project manager first assessed the impact of the reassignment on defect handling and project objectives, then negotiated the review time and resource arrangements with the relevant stakeholders and updated the resource management plan according to organizational rules. Had the project manager blamed him or escalated at the start, the conflict would not have been solved and the relationship would have been damaged.

Common trap

  • "Analyze first" does not mean sitting on your hands: after the analysis you still have to act. A high-priority issue that is still unresolved must not be closed just to make the list look tidy, and scope must not be cut directly.
  • "Communicate first" does not mean handing over the decision: when a baseline has to change, you still go through change control after communicating.
  • Do not replace people, add budget, cut scope or escalate before you have found out the cause.

Telling issues from risks

PMBOK 8 defines an issue as "a current condition or situation that may have an impact on one or more project objectives. An issue has already occurred and may require immediate action or management attention." A risk is "an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more portfolio, program, or project objectives." The examples in this lesson are mostly about threats. A poorly managed risk can also turn into an issue. When judging, look for the signal words in the stem:

Signal in the stemMatching document or action
"May", "might", not yet occurredUpdate the risk register; analyze and respond through the risk process
A condition that objectively exists, already occurredUpdate the issue log; work on resolving the issue
A new stakeholder appearsUpdate the stakeholder register
A change has been approved or rejectedUpdate the change log

When the stem contains both "has already happened" and "may affect the schedule", the event that has happened is the issue; record and act on it first. A further effect that is still uncertain can be assessed as a risk, but the delay that has already occurred is not. When it is not yet certain that the schedule will slip, the project manager has no authority to update the schedule baseline directly.

"Find the cause first" vs. "update the issue log first"

Both approaches have a basis; the difference is how many facts the stem gives. When the facts are clear, record and address the issue promptly. If the issue comes from an external party—for example, a supplier reports that a key component cannot ship on time—contact that party first to clarify the cause, contract implications, and recovery options, then update the issue log and carry out the agreed response rather than immediately seeking a replacement or waiting until the next status meeting. When the cause and the situation are unclear (for example, a stakeholder is dissatisfied or does not approve), first find the cause. The issue log is only one step in defining the problem; after recording it you still have to identify causes, propose solutions, choose one, carry it out and verify the result.

What resources are used, and what process is followed, once a risk occurs depends on whether it was identified.

Identified riskUnidentified risk
Resource preparedContingency reserve (usually for known risks with active response strategies; whether it sits inside the cost baseline depends on the organization's financial management and governance arrangements)Management reserve (outside the cost baseline)
Who may use itUsed according to the risk response plan and organizational authorization (when the question gives no special governance rules, the project manager is usually assumed able to draw on it within the authority granted)Submit a change request first; use it after approval
ResponseContingency plan, prepared in advance (with a fallback plan if needed, to be activated if the primary response proves ineffective)Workaround, developed after the fact ("workaround" is a common exam term)

PMBOK 8 calls the planned responses "contingent response strategies". "Contingency plan" and "fallback plan" are common exam terms.

If a risk is newly discovered but has not yet occurred, add it to the risk register first, then analyze and assess it through the risk process.

PMBOK 8 notes that in some organizations the management reserve may be at the discretion of the project manager. On the exam, unless the stem says so, treat it as requiring a change request (common exam practice). The basis is the PMBOK 8 Finance performance domain on reserves: management reserves are typically realized at the discretion of senior leadership or management, and in some organizations may be at the discretion of the project manager or project management team.

Worked examples

Example 1: A team member misses deadlines twice; what to do first

Question 1Example

A hospital appointment system project uses a predictive approach. A team member responsible for interface development has twice failed to finish tasks on time, and as a result a milestone was missed. What should the project manager do FIRST?

Show answer and explanation

Correct answer: D

This is a predictive project. A team member responsible for interface development has twice missed task deadlines, causing a missed milestone, and the stem does not give the reason. The question asks what to do FIRST. With no ready-made process step, an analysis action should come first.

The signal is that the cause is unknown. When the cause is unclear, the project manager first talks privately with the person involved to learn why the tasks were not finished on time. Only then can you tell whether the problem lies with skills, with resources or with the task itself, and decide what to do. Analyze and communicate first, then act. The answer is D.

Why the other options are wrong

  • A. Demanding an explanation in front of the whole team holds him to account before the cause is known and damages team relationships. Find out in private first.
  • B. Reporting to the functional manager and asking for a performance action before finding out the cause escalates first and investigates afterwards, which is the wrong order.
  • C. Changing the schedule baseline requires change control, and the project manager has no authority to push it back directly. Also, with the cause of the delay unknown, you cannot tell whether the schedule really needs to change.

Key takeaway When the cause is unknown, find it out first, and do so in private. Do not hold someone to account in public, do not escalate straight away and do not change the baseline directly.

Variation If it were confirmed that his time had been pulled away, the next step would be to assess the impact and coordinate resources. If the question asked what should have been done beforehand, the answer would be to define roles, responsibilities and communication rules during planning.

Something wrong with this question?

Report an issue with this question

Example 2: A supplier says a component will be late: issue or risk

Question 2Example

A smart home project uses a predictive approach and is in the Executing focus area. The procurement specialist tells the project manager that the supplier has just notified them that a key sensor component cannot ship by the contract date and will be three weeks late. This component is a prerequisite for the assembly work that follows. What should the project manager do FIRST?

Show answer and explanation

Correct answer: D

This is a predictive project in the Executing focus area. The supplier has notified that a key sensor component cannot ship by the contract date and will be three weeks late; it is a prerequisite for the assembly work. First decide whether this is an issue or a risk, then choose the matching document and action.

The deciding signal is “has just notified that it cannot ship on time”: the supplier has confirmed a current inability to meet the contract date, so this is an existing issue rather than a future event whose probability still needs assessment. Because the issue comes from an external supplier, the project manager should first contact the supplier to clarify the cause, contract implications, and recovery options, then update the issue log and carry out the agreed response. The answer is D.

Why the other options are wrong

  • A. The risk register records potential risks that have not yet happened. The supplier has confirmed the late shipment, so this is no longer an uncertain potential risk and belongs in the issue log; assessing probability in the register no longer makes sense.
  • B. Management reserve must be used under the authority and the change procedures the organization prescribes. Also, drawing on reserve and expediting a replacement before the impact has been analyzed gets the order wrong.
  • C. An issue needs immediate action. Waiting until the next status meeting to report it is a delay and means taking no action in the meantime.

Key takeaway What has already happened is an issue: update the issue log and act at once. What might happen is a risk: update the risk register.

Variation If the scenario were “the supplier is short of cash and may ship late”, that would be a risk: register it first, then assess it. If the delay had already happened but the cause was not yet clear, you could first update the issue log with the known facts and then continue analyzing the cause and the impact.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When a new risk appears, do not implement a response straight away, and do not stop work or add budget directly: record it in the risk register first, review the existing strategies, then assess it.
  • When a new risk is reported to management directly, bypassing the team, the wrong channel is not a reason to refuse it: if the information is clear, register it first and then assess it; if it is unclear, communicate with the person who raised it first.
  • The risk register covers individual project risks; overall project risk is described in the risk report.
  • A delay that has already happened is not a risk: do not record it in the risk register, and do not rush to draw on management reserve.

Key takeaways

  1. When the facts are unclear, find the cause and assess the impact first, then act; for disagreements, communicate and negotiate first, and do not refuse outright or escalate directly.
  2. If scope, schedule, cost and quality are all on target but the project is still halted, a key stakeholder was probably missed.
  3. What has happened is an issue: update the issue log. What might happen is a risk: update the risk register.
  4. For an issue whose facts are clear, update the issue log and act at once (if it comes from an external party, contact that party first); for an issue whose cause is unclear, find the cause first.
  5. A risk that is identified, has an active response planned and has reserve set aside can use contingency reserve according to the plan; unforeseen work can request management reserve under the organization's governance arrangements (common exam practice: when the stem gives no other conditions, use contingency reserve for identified risks, and use management reserve with a change request for unidentified risks).

Lesson 3

Authority, Escalation and Change Control

Lesson video

Lesson overview

The last lesson covers three judgment rules: which matters the project manager handles within their own authority and which must be escalated; in predictive approaches, once baselines are set, changes that affect a baseline go through formal change control, whereas adaptive approaches usually manage scope changes dynamically through the backlog and the product owner; and predictive and adaptive environments handle change differently. The stem often presents someone making a request or running into difficulty, and the options include tempting choices such as "escalate directly to the sponsor", "just agree to the customer" and "change the baseline directly", while the correct answer is often the step that sits inside the process and within the project manager's authority.

Handle it within your authority; escalate only beyond it

For issues inside the project involving the team, communication, performance, resources, procurement, risk, quality and the like, the project manager first comes up with a solution and handles it personally. By common exam practice, the matters that need the sponsor or senior leadership are usually these: approving the charter around project initiation, developing the business case, deciding whether the project continues, judging success or failure at closing, using management reserve (handled according to authorization and the change process, going to the appropriate approver when it exceeds the project manager's authority), organizational change, and situations where the risk has spread to the whole company. The project manager's first reaction is to solve the problem proactively. Only when a matter exceeds their authority, or meets an escalation criterion (for example, a variance reaches or exceeds the control threshold and is beyond their authority), do they escalate to a higher level. A request that goes beyond the current scope is handled through the change process first and is not simply escalated every time.

  • If the stem does not say the matter exceeds your authority, an option that escalates the problem straight to the sponsor or management is usually not the best answer.
  • When a variance is within the control threshold set out in the plan, the project manager takes corrective action within their own authority. When it reaches or exceeds the threshold, handle it with the actions the plan specifies; if it is also beyond your authority or meets an escalation criterion, escalate through the governance process.
  • "Escalation" in the risk context means handing a risk that lies outside the project scope or the project manager's authority to a higher level to take ownership of and manage, and the project team no longer monitors it.
  • When your authority is not enough, go to the right person. A project manager cannot adjust the compensation of another team. When two teams (each led by a different project manager) jointly deliver a large program, go to the program manager or the project management office that oversees both projects to coordinate. If it is only two teams within the same project, go to whichever role has the authority to coordinate under that project's governance and division of responsibilities.

Conversely, things outside the project manager's authority must not be done on their own. The business case is a business document, not a project document, and is usually developed and maintained by the sponsor or at the program level. The project manager generally provides advice and insight unless organizational governance explicitly authorizes them to develop or update it. If the project charter omits a necessary budget item, follow common exam practice, where whoever approved it is the one who amends it: raise it with the sponsor who approved the charter. Reducing approved scope requires a formal change request, approved by the person designated in the change management plan or organizational procedures (such as the sponsor or the project manager, with the change control board involved where applicable). The project manager cannot bypass the process and cut it directly.

Anything that touches a baseline goes through change control

In a predictive environment, once the scope, schedule and cost baselines are approved, they can be changed only through formal change control. (The adaptive environment is covered below: the scope baseline is usually managed dynamically by the product owner through the backlog, not through formal change control.) A change request can be raised by any stakeholder, and it can be raised verbally, but it must be documented in writing. Each documented change request must be approved, deferred or rejected by the designated person, and handed to the change control board when necessary. The baseline does not move until the change is approved, and only after approval is the change built into a new baseline. PMBOK 8 presents the project change process as an "example flow" of how it might be performed; the degree of formality depends on scope, complexity, contract requirements and development approach, and there is no single prescribed five-step process. Common exam practice can be summarized as: record the request; evaluate the impact (evaluation comes before submission); submit it to the person with authority for approval; after approval, update the relevant baselines, plans and documents, communicate the decision to stakeholders, and implement the approved change in accordance with the updated plan (the order of the update and the communication depends on the change management plan or the stem). The actual process is tailored in the change management plan.

  • Corrective actions, preventive actions and defect repairs are all change requests: when a quality problem causes a lot of rework, go through the change control procedure and do not update the baseline directly.
  • If a supplier changes the design without approval, pause the affected work and assess the impact first, then follow the formal change control procedure in the change management plan; do not continue implementation without approval.
  • If conditions the customer was supposed to provide turn out not to be available, assess the impact and submit a change.
  • Do not carry out out-of-scope requests directly. Once new scope is approved, update the scope baseline and, depending on the impact, the schedule baseline, the cost baseline and other related plans and documents. It cannot be absorbed with management reserve.

Example: a design change on a road project

A city road project has an approved baseline. Partway through construction, the district traffic department asks for a dedicated right-turn lane to be added at an intersection. The project manager did not agree to it and did not tell the crew to start work. First the project manager recorded the request and evaluated the impact on earthwork quantities, schedule, budget and land acquisition, then submitted the change request to the change control board together with the evaluation. Only after the board approved it were the scope, schedule and cost baselines updated and stakeholders notified. Had the crew started work before approval, it would have been unauthorized work, and could have led to rework, additional costs that could not be approved, or a contract dispute.

How predictive and adaptive approaches differ

How change is handled depends on the development approach. First decide which kind of environment the stem describes, then apply the matching rule.

The same kind of scenario under predictive and adaptive approaches

PredictiveAdaptive
Scope changeAfter the scope baseline is set, it is changed only through formal change controlWork items are ordered by value in the product backlog and usually approved dynamically by the product owner, without formal change control
Customer raises a new requirementEvaluate the impact and submit a change requestThe product owner adds it to the backlog and orders it by value; it is pulled into an iteration at iteration planning. When time and cost are fixed and the amount of work is constant, make room by adjusting priorities
Budget under pressureRun variance analysis against the cost baseline; when a control threshold is exceeded, act as the plan specifies, and escalate if beyond your authorityWork with the product owner to order the backlog by business value and deliver a minimum viable product first, rather than cutting everything evenly
Schedule monitoringStatus, reserves, baseline changesWork delivered and accepted, velocity, backlog priorities
Risk reviewAt the frequency set in the risk management plan; may be folded into the status meetingRisks can be assessed at the beginning of each iteration, and risk reviews held with stakeholders at the end of each iteration to bring in their feedback (a PMBOK 8 tailoring example for agile projects; frequency is tailored in the risk management plan)

In an agile environment, a servant leader removes impediments and fosters collaboration. By common exam practice, work with governance functions such as audit and finance, and bodies such as the change control board, and streamline the process rather than going around them. When a key stakeholder keeps interrupting the team, invite that person to look at the information radiator and attend the iteration review, so they can follow progress that way, rather than writing thick status reports.

Worked examples

Example 1: Predictive: a new feature outside the baseline

Question 1Example

A corporate training platform project uses a predictive approach. The scope baseline has been approved and development is about halfway done. The customer's representative asks to add a “learning points store” feature that is not in the original scope. What should the project manager do?

Show answer and explanation

Correct answer: B

This is a predictive project in the Executing focus area, and the scope baseline is approved. The customer's representative asks for a “learning points store” feature that was not in the original scope. The question asks what the project manager should do.

The signals are “the baseline is approved” and “not in the original scope”. Any change that touches a baseline goes through change control: first evaluate the impact of the new feature on scope, schedule, cost and so on, then submit a change request for approval by the approver named in the change management plan (the change control board where applicable). Only after approval can the baselines be updated and the work begin. The answer is B.

Why the other options are wrong

  • A. Adding the new feature to the WBS and telling the team to start without approval bypasses change control. This is scope creep.
  • C. Once new scope is approved, the scope baseline is updated through change control, and the schedule and cost baselines are updated where needed. Management reserve sits outside the baselines and is for unforeseeable work, and its use also requires authorization. It cannot be used to skip evaluation and approval and absorb the added work while leaving all baselines unchanged.
  • D. Adding budget also requires change approval. Starting work with no evaluation and no approval gets the order wrong.

Key takeaway Any change that touches a baseline goes through change control: evaluate first, then submit, and it becomes part of the baseline only after approval.

Variation If the same request arose in an agile project, the product owner would add it to the backlog and order it by value. If the stem said the change had already been approved, the next step would be to update the baselines and plans and notify stakeholders.

Something wrong with this question?

Report an issue with this question

Example 2: Agile: a new feature requested during an iteration

Question 2Example

A government services app project uses an agile approach. Because of a policy change, the customer asks for a new feature in the middle of an iteration. Time and cost are fixed, and the team's workload is already full. What should the project manager do?

Show answer and explanation

Correct answer: C

This is an agile project, in the middle of an iteration. The customer asks for a new feature because of a policy change; time and cost are fixed and the team's workload is already full. The question asks what the project manager should do, and the change must be handled the adaptive way.

In an adaptive environment, changes are typically managed through the product backlog: their impact is assessed and their priority is set, the product owner manages their ordering, and items are pulled into an iteration at iteration planning. When time and cost are fixed and the team's capacity is fully allocated, the new feature is accommodated by adjusting priorities: it goes into the backlog and is compared by value with the other work items, and only if it ranks high enough does it displace lower-priority work. The answer is C.

Why the other options are wrong

  • A. In adaptive work, changes are typically handled through backlog management rather than a formal change request process. Sending the change to the CCB for approval is the predictive approach.
  • B. “Welcoming change” does not mean accepting everything unconditionally. The project manager should not reject the request unilaterally merely because the iteration scope is set; assess and prioritize it with the product owner, who may then decide not to add it to the backlog.
  • D. In adaptive work, scope is typically adjusted through the backlog. The stem also fixes time and cost and gives no basis for amending the contract to add budget and time.

Key takeaway In adaptive work, new requirements go into the backlog and are ordered by value; in predictive work, once baselines are established, changes go through formal change control.

Variation If the same request arose in a predictive project, the answer would become: evaluate the impact and submit a change request. If asked whether it can be added to the current iteration directly, the answer is that neither the customer nor the project manager can simply insert it. It goes into the product backlog first; if it does not endanger the iteration goal, the team can negotiate an adjustment of the current iteration scope with the product owner, otherwise it waits for a later iteration planning.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • If the stem does not say the matter exceeds your authority, do not choose "escalate directly to the sponsor".
  • The adaptive idea of "welcoming change" does not mean accepting everything unconditionally: new requirements need to be assessed and prioritized, and the amount of work stays constant when time and cost are fixed. The project manager should not reject a request unilaterally without assessment and a product-owner decision; after assessment and ordering, the product owner may decide not to add it to the backlog.
  • In adaptive work, a new requirement usually goes into the backlog first and is handled by reordering within the existing contract boundaries; there is no need to escalate directly to the project management office. If it goes beyond what the contract provides or changes the commercial terms, a contract change is still required.
  • In a predictive project, management reserve cannot be used to absorb added scope; added scope goes through change and the baselines are updated.
  • Order of change handling (common exam practice): record, evaluate, submit, decide; after approval, update and notify (the order of updating and notifying depends on the change management plan or the stem). Do not put evaluation after submission.

Key takeaways

  1. Handle matters within your authority yourself; escalate only when a matter exceeds your authority or meets an escalation criterion (including a threshold breach that is also beyond your authority); a request beyond scope goes through the change process first; do not change documents and baselines that are not yours to change.
  2. In predictive projects, anything that touches a baseline goes through change control. Common exam practice is this order (it must include the decision): record, evaluate, submit, decide, update, notify (updating and notifying have no absolute order; follow the change management plan or the stem). The baseline does not move until approval.
  3. Corrective actions, preventive actions and defect repairs are all change requests.
  4. Scope changes in predictive projects go through formal change control; new requirements in adaptive projects go into the backlog and are ordered by value.
  5. In an agile environment, work with audit, finance and the change control board rather than going around them.

This chapter has 10 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.