- Home
- PMP
- Study Guide
- Exam Strategy
PMP Study Guide
Exam Strategy
The PMP study guide for Exam Strategy: 1 chapter and 3 lessons, about 37 min of study. Every lesson has worked examples with the explanation folded until you open it. Read the topic guide first ↓
Watch the free Exam Strategy videos in the PMP video course →
Chapters in this topic
Topic guide
What this topic covers
Many PMP exam questions are situational: the stem describes a project scenario and asks what the project manager should do, and several options usually sound reasonable. You must pick the one that is most appropriate in that scenario. The earlier topics have already taught the content. This topic adds no new knowledge. It collects the judgment rules that keep recurring across those topics and explains the reasoning behind each one. Most of the rules here are common exam practice; where PMBOK 8 states something explicitly, it is labeled separately. A rule can only narrow the field, and you still have to read the stem carefully. After this topic you should be able to: describe the exam format and the domain weightings; read the three question wordings "NEXT", "FIRST" and "should have been done beforehand", and check the limiting conditions before anything else; analyze and communicate first when the facts are unclear; tell an issue from a risk, and contingency reserve from management reserve; and know what a project manager handles within their own authority, what must go through change control once a baseline is affected, and how predictive and adaptive approaches differ.
Three lessons, one chapter
The topic has a single chapter, "Judgment Rules for Situational Questions", in three lessons. Lesson 1: exam format and reading the question wording. Lesson 2: analyze and communicate before acting, and tell issues from risks. Lesson 3: authority, escalation and change control, plus the difference between predictive and adaptive approaches. The worked examples in each lesson come from two core question types: process questions that ask for the NEXT step, and analysis questions that ask what to do FIRST.
| Lesson | Content | In one sentence |
|---|---|---|
| Lesson 1 | 180 questions, 240 minutes; NEXT, FIRST, should have been done beforehand | First work out which point in time the question is asking about |
| Lesson 2 | Find the cause first; issue log vs. risk register; the two reserves | When the facts are unclear, do not act yet; signal words decide the document |
| Lesson 3 | Authority, escalation, change control, predictive vs. adaptive | Handle it within your authority; baseline changes go through change control |
The exam content outline describes the exam as follows: 180 questions, of which 170 are scored and 10 are pretest questions, in 240 minutes, presented in random order. The domain weightings are People 33%, Process 41% and Business Environment 26%. About 40% of the questions use a predictive approach, and about 60% use adaptive or hybrid approaches. These methods are spread across all three domains, so do not expect any domain to be "all predictive".
How the lessons fit together
Working through a situational question takes roughly four steps, which map onto the three lessons. Step 1: read the wording and the limiting conditions, and decide whether the environment is predictive or adaptive (Lesson 1). Step 2: decide whether the stem describes an issue that has already happened or a risk that might happen, and whether the facts are clear; if they are not, find the cause and communicate first (Lesson 2). Step 3: ask whether the matter is within the project manager's authority and whether it touches a baseline. A change to a baseline in a predictive project goes through change control as set out in the change management plan. In an adaptive project, a change in scope usually goes into the backlog and is reprioritized, while budget, contracts and other controlled items are still handled through the project's governance mechanisms (Lesson 3). Step 4: among the remaining options, pick the one that best fits the rules and comes earliest in the process. This order is not a hard rule, but it lets you quickly eliminate options such as "escalate straight away", "change the baseline directly" and "just agree to it".
How to study
Treat the rules as a tool for eliminating options. Each rule narrows the field; it does not read the question for you. When you start a question, write down the limiting words first: predictive or adaptive, NEXT or FIRST, already happened or might happen. Check the rules against the topics you have studied. If you cannot remember why a rule works, go back to the study guide for the relevant topic. That sticks better than memorizing. Review by auditing your mistakes against the rules. When you miss a question, ask which kind of error it was: misread the wording, missed a limiting condition, confused an issue with a risk, confused authority with change control, or misjudged the environment. If the same kind of error keeps recurring, reread the matching lesson. Leave yourself time. The average of about 1.3 minutes per question is only a reference figure, worked out from the total number of questions and the total time; in practice you will trade time between calculation questions, long case questions and short concept questions.
How this topic relates to the others
This topic summarizes all the earlier ones. Reading the wording applies to every kind of process question; issues and risks tie to the risk and governance topics; reserves tie to finance; authority and change tie to governance and to the scope, schedule and cost baselines; predictive and adaptive tie to life cycles and agile. We recommend coming back to it after you have finished most of the other topics. Its value is that it turns scattered knowledge into one workable order for eliminating options. If a rule feels unfamiliar, the matching topic needs another look.
Common ways to lose points
- Treating 180 as the number of scored questions, or misremembering the number of pretest questions.
- Being asked for the NEXT step but choosing a step that comes earlier or later in the process. This is especially common with the order of steps in the change process. Do not memorize a fixed order for notifying and updating. Based on the change management plan, record the decision, update the affected documents and communicate with the relevant stakeholders; rely on the order given in the stem when it states one.
- Blaming someone, escalating, or changing a baseline before finding out the cause.
- Logging a delay that has already happened only as a future risk, without recording and tracking it in the issue log, or treating something that merely might happen as an issue-log item.
- Using management reserve to absorb added scope, or accepting out-of-scope requests directly in a predictive project.
- Choosing "escalate directly to the sponsor" when the stem does not say the matter exceeds your authority.
- Reading the adaptive idea of "welcoming change" as accepting everything unconditionally, or applying the predictive change process to an agile project.