Business Environment domain · Task 3

Manage and control changes

"Manage and control changes" is task 3 of the Business Environment domain in the PMP exam content outline. The Business Environment domain makes up 26% of the exam, and the outline does not publish a question count for each task. Change questions are among the most frequent scenario questions on the exam. They test whether you know the process: which step of change handling the project is at, whether change control is needed, who has the authority to decide, and what must happen after approval.

What the outline asks for (enablers)

The outline lists 4 enablers for this task. The table maps each one to the chapters of this study guide.

EnablerWhat you need to knowChapter
Execute the change control process.Kinds of change request; assess the impact first, then submit a change request under the change management plan for a person with authority or the change control board to decide; principles for baseline changes; stop unapproved work and assess it before going through change controlChange Control, Scope Creep
Communicate the status of proposed changes.What the change log is for; tell the requester and the affected stakeholders promptly whether a change was approved, rejected or deferredChange Control
Implement approved changes to the project.The steps after approval: record the decision, update affected plans, baselines and documents as needed, notify stakeholders, then implement and monitor the results; implement only what was approvedChange Control, Monitor Project Performance
Update project documentation to reflect changes.After a change, update the baselines, logs and related plans and registers so the documents stay consistentChange Control

How to read change scenario questions

  1. Assess first, then act. When a change request arrives or a requirement shifts, the first step is to assess the impact on scope, schedule, cost, stakeholders, resources and risk, and consider quality too, not to agree or refuse straight away.
  2. Predictive: assess the impact, submit a change request, let the authorized person decide. Submit the change request under the change management plan. The change control board or the person with approval authority decides. After approval, update the plan and logs, inform stakeholders, then implement.
  3. If you find unapproved work, stop and assess first. If a change has already been made without approval, stop, assess the impact, and then go through change control. It is not approved by default after the fact.
  4. Do not implement before approval, do not skip steps after it. Implement only approved changes. After approval, record the decision, update the baselines, logs and related documents as needed and inform stakeholders, then implement and monitor the results.
  5. Do not approve what is beyond your authority. When a change exceeds the project manager's authority, submit it to the person who holds it. The project manager assesses, recommends and drives the process.
  6. Adaptive: a change is a backlog item. A change is usually a backlog item that is reprioritized after impact analysis, with no formal change request approval. An iteration review is not an acceptance gate, and completion is judged against the definition of done.

Rule 5 is common exam practice. The others follow the study guide and PMBOK 8.

Predictive versus agile and hybrid environments

PredictiveAgile and hybrid
Form of a changeA formal change request against a baseline or a configuration-controlled artifactA backlog item, assessed and ordered
Who approvesThe change control board or the person with authorityThe product owner sets priority, the team estimates the effort
How completion is judgedUpdate the baseline and documents once the change is approved; monitor the results after implementationAgainst the definition of done; an iteration review is not an acceptance gate

Task quiz

These free questions come from the chapters linked to this task and cover as many chapters as possible. Pick an answer first, then open the explanation to see why the right option is right and why the others are wrong. For more, practice by chapter in the question bank.

Question 1Free

At a furniture factory, a recent batch of desks shipped with drawer-slide mounting holes outside tolerance, creating a risk of loosening. The project manager and team trace the cause to a worn drill bit and submit change requests to replace the bit, recall the shipped desks for rework, and add a rule for regular inspection and replacement of drill bits. After assessment and approval, the team implements all three measures, and the hole positions return to within tolerance. What kinds of action are the project manager's three measures?

Show answer and explanation

Correct answer: C

At a furniture factory, desks' drawer-slide hole positions exceed tolerance. The project manager submitted change requests to replace the worn drill bit, recall the shipped desks for rework, and add a rule for regular bit inspection and replacement; all three were implemented after approval. Match each of the three to a type of change request.

Look at the object and the timing of each measure. Replacing the drill bit makes production conform again and addresses a variance that has already occurred, so it is corrective action. Recalling the shipped nonconforming desks to reprocess them has a nonconforming product as its object, so it is defect repair. Adding the inspection and replacement rule is meant to make sure the variance does not appear again in future, so it is preventive action. Corrective action, defect repair and preventive action match the three measures in order. The answer is C.

Why the other options are wrong

  • A. The first is right but the last two are reversed: recalling for rework fixes a nonconforming product, which is defect repair, and the new rule is aimed at the future, which is preventive action.
  • B. Replacing the bit makes the process conforming again and addresses a variance that has already occurred, so it is corrective action, not defect repair. Reworking the shipped desks is what is defect repair.
  • D. Replacing the bit is not preventive action, because prevention addresses a variance that has not yet occurred. The new rule is not corrective action either, since it does not repair an existing variance.

Key takeaway A variance that has occurred calls for corrective action, a nonconforming product for defect repair, and a possible future variance for preventive action.

Variation If one more measure were added, “relax the acceptance tolerance from 1 mm to 2 mm and revise the contract annex,” it changes documents and a baseline and is an update. In a predictive project with established baselines, actions that touch baselines or other controlled items go through formal change control before implementation.

Something wrong with this question?

Report an issue with this question

Question 2Free

A furniture factory's order-management system project has entered execution. The client's representative asks for an inventory-alert feature, which would change the scope baseline, and the change management plan states that changes affecting the baseline are approved by the change control board. The project manager and team assess the change's effects on scope, schedule, cost and risk, and unanimously agree that the requirement is worth implementing. What should the project manager do NEXT?

Show answer and explanation

Correct answer: C

The order-management system project is in execution. The client's representative asks for an inventory-alert feature that would change the scope baseline, and the team agrees it is needed. What should the project manager do next?

In this question the change management plan says baseline changes are approved by the change control board, so the change control process must be followed. A change can be raised orally but should be recorded in writing; after the project manager assesses the impact, the request is submitted to the change control board as the change management plan specifies, and only after approval does it enter the revised baseline and get implemented. The team's view that it is needed is only part of the assessment; the authority to approve lies neither with the team nor with the client. The answer is C.

Why the other options are wrong

  • A. The client is the party raising the change and has no authority to approve it. An arrangement made privately between the two sides bypasses change control, and the baseline would not be formally changed.
  • B. The stem states that the change management plan assigns approval to the change control board, so the sponsor is not the approver of this change.
  • D. That the team thinks it is needed does not mean the change is approved. Implementing without approval quietly alters the baseline.

Key takeaway A baseline change should follow the change control method set for the project; here a change request must be submitted and approved by the change control board designated in the change management plan, and nothing is implemented before approval.

Variation If the project baseline has not yet been established, changes are not under formal control and the impact is analyzed first; if the sponsor is a member of the board, approval is still made through the board.

Something wrong with this question?

Report an issue with this question

Question 3Free

A community elder-care service platform is being built using a predictive approach. Baselines have been established, execution is halfway through, and the customer has formally accepted the deliverable's quality standard. Then a new standard issued by a government agency may have a major impact on the project, and the deliverable must be modified to meet the new quality standard. What should the project manager do?

Show answer and explanation

Correct answer: B

Execution is halfway through, the quality standard has been accepted by the customer, and a new external standard requires the deliverable to be modified. This is a change triggered by an external change.

A new government standard is an external enterprise environmental factor that must be complied with. The project has baselines and the customer has formally accepted the quality standard, so modifying it requires first assessing the impact on scope, schedule, cost and so on and then submitting a change request, handled through Assess and Implement Changes and implemented once approved by those with the authority (if it also affects the scope, schedule or cost baselines, it is also a baseline change). The project manager cannot change a baseline on their own. The answer is B.

Why the other options are wrong

  • A. An independent review process is for managing and controlling quality against the new standard. That work comes after the standard update is approved; it is not the first step now.
  • C. Recording it in the lessons learned register and telling senior management can be done, but it does not replace assessing the impact and submitting a change request.
  • D. Training can be a supporting measure, but it does not replace the impact assessment and the change request. If the training itself requires changing controlled plans or affects a baseline, carry it out after the relevant change is approved.

Key takeaway When a new government standard requires changing accepted, controlled content: assess the impact first, then submit a change request.

Variation If the project manages work with a product backlog, the same new rule can be handled by reordering backlog items after assessing the impact. If it affects controlled artifacts or an approved baseline, or governance rules require approval, a change request is still needed.

Something wrong with this question?

Report an issue with this question

Question 4Free

A software outsourcing firm is building a membership app for a fitness chain. The team has just completed an iteration, and the product passed its acceptance checks, but it contains a “leaderboard” feature that nobody asked for. The team works in an agile way, and the product owner manages the backlog. The customer noticed the feature during the demo and worries that it brings new security risks. What should the project manager do to prevent this from happening again?

Show answer and explanation

Correct answer: A

A software outsourcing firm builds a membership app for a fitness chain. After an iteration the product passes its acceptance checks but contains an unrequested “leaderboard” feature, and the customer worries about security risks. The team is agile and the product owner manages the backlog. The question asks how to prevent a repeat, which is a preventive measure in an adaptive environment.

Adaptive projects manage scope through the backlog, and the product owner dynamically decides its content and priority in a flexible environment. The root cause of the unrequested feature is that the new content bypassed the product owner and never entered the backlog. To prevent a repeat, any new feature must first be assessed for value by the product owner, placed in the backlog and prioritized, and only then developed. The answer is A.

Why the other options are wrong

  • B. Confirming the feature's value with the customer deals only with this one feature. It does not set up a mechanism to prevent a repeat or name who decides.
  • C. Managing the scope baseline and eliminating external factors is a predictive mindset; agile teams manage scope through the backlog, and external factors were not the source of this problem.
  • D. More frequent reviews can reveal problems sooner, but they cannot stop the team from adding features on its own. There is still no entry point for assessing new content.

Key takeaway To prevent gold plating in an adaptive project, make sure any new content is assessed by the product owner and placed in the backlog before it is developed.

Variation If, once assessed, the extra feature turns out to be valuable, the product owner can schedule it for a later iteration. If not, remove it, and review why the team added it on its own.

Reference Monitor and Control Scope and Scope Creep · Lesson 2: Scope Creep and Gold Plating: Two Ways Work Quietly Exceeds the Baseline

Something wrong with this question?

Report an issue with this question

Question 5Free

A signage replacement project for a coffee-shop chain covers replacing the signs of 10 stores in the city center. When all of them are done, the customer says it will not sign the project closure report unless an 11th store is added, because it fits the customer's new store-opening plan. What should the project manager do?

Show answer and explanation

Correct answer: A

All 10 store signs have been replaced. At acceptance the customer demands an 11th store and otherwise will not sign the project closure report.

The original scope is complete, so the project manager should ask the customer to formally accept that part against the agreed acceptance criteria; if the customer refuses to sign, record and handle the reason for the refusal (using contract dispute or escalation mechanisms if necessary). The 11th store is outside the scope baseline and is a scope change: record it as a change request, to be assessed and decided by the approver the project designates (the change control board where applicable). It need not wait until acceptance is finished. The two matters are handled separately and not tied to each other. The answer is A.

Why the other options are wrong

  • B. A scope change first has to go through change control; it is not a matter of going straight to the sponsor for money. Holding off acceptance would also delay accepting the completed work.
  • C. A change must be approved through this project's change control process. The project manager cannot let a department of the customer approve an expansion of scope directly; skipping the process leaves the baseline uncontrolled.
  • D. A request cannot simply be turned into a new project because it came late. A change request is the proper route, decided by the approver the project designates (the change control board where applicable).

Key takeaway When new requests arise at acceptance, request acceptance of the completed work while sending the new request through change control; handle the two matters separately.

Variation If the customer asked instead for a fix to a defect where completed work deviates from the acceptance criteria, that is not added scope; record the reason and remedy the defect through change control.

Something wrong with this question?

Report an issue with this question

Question 6Free

PMLyceum takes on a predictive ERP implementation project. While reviewing a change request, the project manager finds that it would change the completion date in the schedule baseline. What should the project manager do?

Show answer and explanation

Correct answer: C

On a predictive ERP project, a change request under review would change the completion date in the schedule baseline. The question asks what the project manager should do.

Once approved, the schedule baseline can be changed only through formal change control procedures. The project manager must first assess the effect of the change on the schedule and obtain approval through the Assess and Implement Changes process; after approval, the change is carried into the schedule baseline. The core of this question is the sequence: assess the impact, submit the change, get it approved through the Assess and Implement Changes process, update the baseline. No step can be skipped, and any option that bypasses approval is wrong. The answer is C.

Why the other options are wrong

  • A. The baseline can be modified only through formal change control. Changing first and filing afterward violates the procedure.
  • B. Leaving the baseline as is and writing the new date only in a report means the change has not gone through assessment, approval and baseline update, so the handling is incomplete. The baseline should stay unchanged until approval and be updated after it.
  • D. Crashing is one means of dealing with variances, but the change is already known to alter the date, so it should be assessed and put through the approval procedure; the team cannot be assumed to absorb it.

Key takeaway A change that affects the schedule baseline: assess first, get approval, then update the baseline.

Variation If the project uses Scrum, change control is more flexible, but the impact still has to be assessed and the Product Owner reorders the Product Backlog; other adaptive methods follow their own governance and change mechanisms.