PMP Cheat Sheet: Exam Strategy

The key points and common traps of 3 lessons in 1 chapter, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.

Mind map of Exam Strategy
Tap the map to enlarge

Judgment Rules for Situational Questions

Lesson 1: Exam Format and Reading the Question Wording

Key takeaways

  1. The exam has 180 questions (170 scored, 10 pretest) and a 240-minute time limit, with questions in random order.
  2. Question types are multiple-choice, multiple-response, case or scenario, and graphic-based, plus other formats such as matching, point and click, and pull-down list; the domain weightings are 33%, 41% and 26%.
  3. Predictive is about 40% and adaptive and hybrid about 60%, spread across the three domains; decide the environment first, then apply the rules.
  4. Wording: for NEXT, see how far the process has progressed; for FIRST, when there is no ready-made process step and the facts are unclear, find the cause and assess the impact; for should have been done beforehand, trace back.
  5. A common mnemonic for change handling (common exam practice; the decision must be included): record, evaluate, submit, decide, update, notify. Check the stem's limiting conditions first.

Common traps

  • 180 is the total number of questions and 170 is the number of scored questions; the pretest questions number 10. Do not take the number of scored questions as the total.
  • Questions are presented in random order, and predictive and adaptive approaches are spread across all three domains; there is no domain that is "all predictive".
  • The Process domain has the highest weighting (41%), not the People domain.
  • "NEXT" does not mean "the best step": first find out how far the process has progressed.
  • Change handling: evaluation comes before submission. After approval or rejection, record the outcome (update the change log) and notify stakeholders; the order of these two depends on the change management plan or the stem.
  • Do not answer "should have been done beforehand" with an after-the-fact remedy or rework.

Lesson 2: Analyze and Communicate Before Acting; Issues vs. Risks

Key takeaways

  1. When the facts are unclear, find the cause and assess the impact first, then act; for disagreements, communicate and negotiate first, and do not refuse outright or escalate directly.
  2. If scope, schedule, cost and quality are all on target but the project is still halted, a key stakeholder was probably missed.
  3. What has happened is an issue: update the issue log. What might happen is a risk: update the risk register.
  4. For an issue whose facts are clear, update the issue log and act at once (if it comes from an external party, contact that party first); for an issue whose cause is unclear, find the cause first.
  5. A risk that is identified, has an active response planned and has reserve set aside can use contingency reserve according to the plan; unforeseen work can request management reserve under the organization's governance arrangements (common exam practice: when the stem gives no other conditions, use contingency reserve for identified risks, and use management reserve with a change request for unidentified risks).

Common traps

  • "Analyze first" does not mean sitting on your hands: after the analysis you still have to act. A high-priority issue that is still unresolved must not be closed just to make the list look tidy, and scope must not be cut directly.
  • "Communicate first" does not mean handing over the decision: when a baseline has to change, you still go through change control after communicating.
  • Do not replace people, add budget, cut scope or escalate before you have found out the cause.
  • When a new risk appears, do not implement a response straight away, and do not stop work or add budget directly: record it in the risk register first, review the existing strategies, then assess it.
  • When a new risk is reported to management directly, bypassing the team, the wrong channel is not a reason to refuse it: if the information is clear, register it first and then assess it; if it is unclear, communicate with the person who raised it first.
  • The risk register covers individual project risks; overall project risk is described in the risk report.
  • A delay that has already happened is not a risk: do not record it in the risk register, and do not rush to draw on management reserve.

Lesson 3: Authority, Escalation and Change Control

Key takeaways

  1. Handle matters within your authority yourself; escalate only when a matter exceeds your authority or meets an escalation criterion (including a threshold breach that is also beyond your authority); a request beyond scope goes through the change process first; do not change documents and baselines that are not yours to change.
  2. In predictive projects, anything that touches a baseline goes through change control. Common exam practice is this order (it must include the decision): record, evaluate, submit, decide, update, notify (updating and notifying have no absolute order; follow the change management plan or the stem). The baseline does not move until approval.
  3. Corrective actions, preventive actions and defect repairs are all change requests.
  4. Scope changes in predictive projects go through formal change control; new requirements in adaptive projects go into the backlog and are ordered by value.
  5. In an agile environment, work with audit, finance and the change control board rather than going around them.

Common traps

  • If the stem does not say the matter exceeds your authority, do not choose "escalate directly to the sponsor".
  • The adaptive idea of "welcoming change" does not mean accepting everything unconditionally: new requirements need to be assessed and prioritized, and the amount of work stays constant when time and cost are fixed. The project manager should not reject a request unilaterally without assessment and a product-owner decision; after assessment and ordering, the product owner may decide not to add it to the backlog.
  • In adaptive work, a new requirement usually goes into the backlog first and is handled by reordering within the existing contract boundaries; there is no need to escalate directly to the project management office. If it goes beyond what the contract provides or changes the commercial terms, a contract change is still required.
  • In a predictive project, management reserve cannot be used to absorb added scope; added scope goes through change and the baselines are updated.
  • Order of change handling (common exam practice): record, evaluate, submit, decide; after approval, update and notify (the order of updating and notifying depends on the change management plan or the stem). Do not put evaluation after submission.