PMP Cheat Sheet: Exam Strategy
The key points and common traps of 3 lessons in 1 chapter, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
Judgment Rules for Situational Questions
Lesson 1: Exam Format and Reading the Question Wording
- The exam has 180 questions (170 scored, 10 pretest) and a 240-minute time limit, with questions in random order.
- Question types are multiple-choice, multiple-response, case or scenario, and graphic-based, plus other formats such as matching, point and click, and pull-down list; the domain weightings are 33%, 41% and 26%.
- Predictive is about 40% and adaptive and hybrid about 60%, spread across the three domains; decide the environment first, then apply the rules.
- Wording: for NEXT, see how far the process has progressed; for FIRST, when there is no ready-made process step and the facts are unclear, find the cause and assess the impact; for should have been done beforehand, trace back.
- A common mnemonic for change handling (common exam practice; the decision must be included): record, evaluate, submit, decide, update, notify. Check the stem's limiting conditions first.
- 180 is the total number of questions and 170 is the number of scored questions; the pretest questions number 10. Do not take the number of scored questions as the total.
- Questions are presented in random order, and predictive and adaptive approaches are spread across all three domains; there is no domain that is "all predictive".
- The Process domain has the highest weighting (41%), not the People domain.
- "NEXT" does not mean "the best step": first find out how far the process has progressed.
- Change handling: evaluation comes before submission. After approval or rejection, record the outcome (update the change log) and notify stakeholders; the order of these two depends on the change management plan or the stem.
- Do not answer "should have been done beforehand" with an after-the-fact remedy or rework.
Lesson 2: Analyze and Communicate Before Acting; Issues vs. Risks
- When the facts are unclear, find the cause and assess the impact first, then act; for disagreements, communicate and negotiate first, and do not refuse outright or escalate directly.
- If scope, schedule, cost and quality are all on target but the project is still halted, a key stakeholder was probably missed.
- What has happened is an issue: update the issue log. What might happen is a risk: update the risk register.
- For an issue whose facts are clear, update the issue log and act at once (if it comes from an external party, contact that party first); for an issue whose cause is unclear, find the cause first.
- A risk that is identified, has an active response planned and has reserve set aside can use contingency reserve according to the plan; unforeseen work can request management reserve under the organization's governance arrangements (common exam practice: when the stem gives no other conditions, use contingency reserve for identified risks, and use management reserve with a change request for unidentified risks).
- "Analyze first" does not mean sitting on your hands: after the analysis you still have to act. A high-priority issue that is still unresolved must not be closed just to make the list look tidy, and scope must not be cut directly.
- "Communicate first" does not mean handing over the decision: when a baseline has to change, you still go through change control after communicating.
- Do not replace people, add budget, cut scope or escalate before you have found out the cause.
- When a new risk appears, do not implement a response straight away, and do not stop work or add budget directly: record it in the risk register first, review the existing strategies, then assess it.
- When a new risk is reported to management directly, bypassing the team, the wrong channel is not a reason to refuse it: if the information is clear, register it first and then assess it; if it is unclear, communicate with the person who raised it first.
- The risk register covers individual project risks; overall project risk is described in the risk report.
- A delay that has already happened is not a risk: do not record it in the risk register, and do not rush to draw on management reserve.
Lesson 3: Authority, Escalation and Change Control
- Handle matters within your authority yourself; escalate only when a matter exceeds your authority or meets an escalation criterion (including a threshold breach that is also beyond your authority); a request beyond scope goes through the change process first; do not change documents and baselines that are not yours to change.
- In predictive projects, anything that touches a baseline goes through change control. Common exam practice is this order (it must include the decision): record, evaluate, submit, decide, update, notify (updating and notifying have no absolute order; follow the change management plan or the stem). The baseline does not move until approval.
- Corrective actions, preventive actions and defect repairs are all change requests.
- Scope changes in predictive projects go through formal change control; new requirements in adaptive projects go into the backlog and are ordered by value.
- In an agile environment, work with audit, finance and the change control board rather than going around them.
- If the stem does not say the matter exceeds your authority, do not choose "escalate directly to the sponsor".
- The adaptive idea of "welcoming change" does not mean accepting everything unconditionally: new requirements need to be assessed and prioritized, and the amount of work stays constant when time and cost are fixed. The project manager should not reject a request unilaterally without assessment and a product-owner decision; after assessment and ordering, the product owner may decide not to add it to the backlog.
- In adaptive work, a new requirement usually goes into the backlog first and is handled by reordering within the existing contract boundaries; there is no need to escalate directly to the project management office. If it goes beyond what the contract provides or changes the commercial terms, a contract change is still required.
- In a predictive project, management reserve cannot be used to absorb added scope; added scope goes through change and the baselines are updated.
- Order of change handling (common exam practice): record, evaluate, submit, decide; after approval, update and notify (the order of updating and notifying depends on the change management plan or the stem). Do not put evaluation after submission.