Close Project or Phase is the last process of the Governance Performance Domain and belongs to the Closing Focus Area. It finalizes all activities related to the project, phase, release, iteration or contract, whether it succeeded or not. Closure done well is what makes the value real: information is archived, planned work is completed, organizational resources are released for new projects, and the extent to which value has been achieved is confirmed.

What this chapter covers

This chapter corresponds to ECO: Process domain, Task 10 (Manage project closure). The questions concentrate on sequence and boundary cases: what comes first in closure, whether lessons learned or archiving comes first, what to do when a project is stopped early, and what to do when the customer raises a new requirement after closure is complete. Memorize the three sequence lines and most questions can be solved directly: acceptance comes before handoff, summarizing comes before archiving, and celebrating comes before disbanding. The five lessons start with why we close and what the basis is, go through the normal steps, early termination, and handover and satisfaction, and end with archiving, closing out contracts and new requirements after closure.

Lessons in this chapter

Chapter map

Normal closure sequence
What to do after a project is stopped

The upper figure shows the eight steps of normal closure and the lower figure shows the five steps after a project is stopped. They are the working sequences used to solve exam questions; the specific activities and their order should be tailored to the project context. For both sequences, common exam practice puts releasing people after recording, handoff and knowledge transfer; in practice, release them in batches as needed. Learn the three sequence lines in the upper figure first, then the lower figure. When you see “early termination”, think: close out first, do not simply stop work, do not try to rescue the project, and do not release people first.

Study tips and practice

The chapter has five lessons with two or three worked examples each. In review, focus on four decision tables: the three words verify, accept and hand off; the eight steps and three sequence lines; the five steps after early termination; and the four things in contract closeout. On a question, first decide which step the project is at: if acceptance has not passed, you cannot hand off; before final archiving, make sure lessons learned have been identified, recorded and added to the repository (lessons learned should be updated throughout the project); and a project that has been closed no longer goes through change control. On EXCEPT questions, remember that quality audits and compliance audits run throughout executing and monitoring according to the plan and organizational requirements, and that at closure you collect and audit the project or phase records and verify that all contractual, regulatory, legal, social and environmental obligations have been met.

Lesson 1

Close Project or Phase: Purpose, Inputs and Completion Criteria

Lesson video

Lesson overview

Close Project or Phase is the last process of the Governance Performance Domain and corresponds to the Closing Focus Area. Many people think closure just means “deliver, close the books, break up the team”, but it actually answers a bigger question: did the project succeed, and has the value landed? This lesson covers why we close, what we base closure on, and what “complete” means. It is the foundation for the next four lessons: normal steps, early termination, handover and archiving all revolve around the completion criteria set here. ECO: Process domain, Task 10 (Manage project closure), covering obtaining stakeholder approval of project completion and determining the criteria to successfully close the project or phase.

What closure does

PMBOK 8 describes it this way: “The Close Project or Phase process involves finalizing all activities related to both successful and unsuccessful projects, phases, releases, iterations, or contracts. The primary benefits include archiving project or phase information, completing planned work, and releasing organizational resources for new projects. The process also includes confirming the extent to which value or the capability to deliver value has been achieved.” Note the words “both successful and unsuccessful”: failed projects and terminated projects must be closed too, as the next lesson explains.

In predictive approaches, “the project manager should ensure that all work is completed and that the objectives are met by reviewing the project management plan.” So closure starts by checking against the plan, not by feeling that the work seems done.

Key inputs: the yardstick for “success”

The main inputs to closure include the project charter; the project management plan and the project documents; accepted deliverables (those accepted by the designated individual or team); agreements such as contracts; and business documents, namely the business case and the benefits management plan. In addition, according to PMBOK 8 Figure 2-12, there are procurement documentation and organizational process assets. Why are these documents inputs? Because closure answers “were the agreed results achieved?”, so the standard of judgment must come from documents agreed in advance:

  • The project charter contains the success criteria, approval requirements and exit criteria, and is the yardstick for checking whether the work is complete.
  • The project management plan is the basis for verifying that scope, schedule, cost and quality have been met.
  • Accepted deliverables are results formally recognized by the designated individual or team with authority to approve them, and are the core evidence for closure.
  • The business case and benefits management plan are used to assess whether the project achieved the expected business objectives and how far value and benefits have been realized; the final report must explain the achievement of the objectives against them.

If there are gaps, report them honestly and agree with the stakeholders on how to handle them. Without criteria for “done”, there is no closure.

Verify, accept and hand off

These three words are easy to confuse; separate them by asking who is judging what. Verification is about whether the deliverables are correct; it is done in the Monitor and Control Scope process and yields verified deliverables. Acceptance is when the designated individual or team with authority to approve (the customer, sponsor, product owner and so on; the test is authority, not whether they are inside or outside the organization) formally confirms the deliverables against the acceptance criteria through the Validate Scope process, yielding accepted deliverables (on the exam this is mostly read as “customer sign-off”). Handoff is transferring ownership and responsibility for use of the result to the operations team or the next phase. The order is verify first, then accept, then hand off. At closure, review the acceptance records obtained from each earlier Validate Scope and obtain the project-level, phase-level or final formal acceptance required by the project or contract.

In predictive approaches, to satisfy the completion or exit criteria, PMBOK 8 lists nine administrative closure steps, including: ensure all documents and deliverables are updated and all issues are resolved; ensure that the measurable project value was delivered, and that there is a plan to maintain this value as the project is closed and transitioned to operations; confirm that deliverables have been delivered and formally accepted by the customer; verify that all costs have been charged to the project; and close project accounts. The other four are: reassign or release project personnel; address excess project materials; reallocate or release project facilities, equipment, and other resources; and prepare final project reports as required by organizational policies.

Worked example: checking exit criteria one by one

The charter of a city transit smart-card project sets these exit criteria: all core functions pass user acceptance testing, zero defects (critical and minor), passenger data migration accuracy of at least 99.5%, and the operations manual delivered. At the closure review, the project manager goes down the list. Function acceptance is signed. Critical defects are zero, but two minor defects remain. Migration accuracy is 99.3%. The operations manual is delivered. Two items are not met, so the project manager does not declare the project complete. Instead, the two defects and the migration gap are put into a report and agreed with the sponsor and customer: the defects will be fixed by a deadline, and the migration gap will be closed by running one more validation pass. The project will close once both are done.

Worked examples

Example 1 A stakeholder questions whether the closure criteria are met

Question 1Example

A hotel chain's membership management system project enters its closure review, and several stakeholders raise concerns that some deliverables may not meet the closure criteria agreed in advance. What should the project manager do FIRST?

Show answer and explanation

Correct answer: D

The project enters its closure review and several stakeholders worry that some deliverables may not meet the closure criteria agreed in advance. The question asks what the project manager should do first.

The closure criteria are the basis for ending the project that all parties agreed in advance, and the issue now is that they “may not be met”, so the facts are unclear. The first step is to establish the facts: analyze thoroughly against the closure criteria, item by item, to find out which criteria are truly not met and why, and only then decide whether to remedy, negotiate or change. The other options draw conclusions or take action before the cause is known. The answer is D.

Why the other options are wrong

  • A. Giving assurances with no factual basis neither removes the concern nor avoids hiding a real gap.
  • B. The closure criteria are the yardstick everyone approved in advance. Deleting unmet clauses just to pass the review violates professional principles and loses the stakeholders' trust.
  • C. Correcting course, changing the criteria and extending the schedule all at once, before the cause is clear, tends to waste resources and may not address the problem.

Key takeaway When closure criteria are disputed, analyze the facts first and then act. Do not make empty promises, and do not change the criteria just to pass.

Variation If the analysis confirms that two criteria are indeed not met, agree a remedy and timeline with the sponsor and customer. If it shows all are met, give the analysis to the stakeholders to remove their doubts.

Something wrong with this question?

Report an issue with this question

Example 2 Acceptance was signed, but the benefits fall short of the business case

Question 2Example

A smart warehousing project enters closure. Checking against the business case and the benefits management plan, the project manager finds that picking efficiency in go-live testing improved by only 10%, below the expected 25%, but the customer has already signed the acceptance form. What should the project manager do?

Show answer and explanation

Correct answer: D

A smart warehousing project enters closure. Against the business case and benefits management plan, picking efficiency improved only 10%, below the expected 25%, yet the customer has signed acceptance. The question asks how to handle the gap.

At Close Project or Phase, the business case is used to test whether the project achieved its expected economic viability, and the benefits management plan is used to measure whether the planned benefits were achieved. A signed acceptance shows that the deliverables meet the acceptance criteria; it does not mean the benefits have been realized. The gap must be recorded honestly, and the way to handle it confirmed with the sponsor and other stakeholders, for example by continuing to track benefits after handoff to operations. The answer is D.

Why the other options are wrong

  • A. A signature shows only that the deliverables are acceptable. Reporting unachieved benefits as achieved misleads management and is not honest.
  • B. Changing the expected value in the business case afterward rewrites the standard of evaluation and hides the gap. The business case is the basis for measuring whether the project met the target and cannot be changed to look better.
  • C. Pausing closure and redeveloping on your own goes beyond the approved scope and needs a change and authorization. How to deal with the gap should first be agreed with the stakeholders.

Key takeaway The business case and benefits management plan are the yardstick for closure. Report gaps honestly and agree with stakeholders how to handle them.

Variation If the stem said efficiency reached 25%, you would confirm the benefit was realized and state it in the final report. If it said “the customer refuses to sign”, acceptance has not passed and handoff cannot proceed.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Acceptance must be given formally by the designated people against the agreed criteria. When the closure criteria are disputed, analyze the facts first and then act; do not make empty promises, and do not change the criteria just to pass.
  • Customer sign-off shows only that the deliverables meet the acceptance criteria. It does not mean the benefits in the business case have been realized.
  • If the project conforms to the project management plan and has been accepted, hand off as planned. When a preference outside the scope is raised after formal acceptance, do not rework directly and do not directly start a change. First decide whether it is a defect, an unmet obligation or new scope, and then handle it through the corresponding process.
  • Verification is about whether the deliverables are correct, acceptance is formal confirmation by the person with authority against the acceptance criteria, and handoff is transfer to operations or the next phase. The order cannot be reversed.

Key point

Normal closure requires formal acceptance: a project that completes normally and produces deliverables should obtain formal acceptance from the person with authority as agreed, and keep the acceptance record, before it is closed; delivery is not acceptance. In early termination and similar cases, record the termination approval and the unfinished items against the exit criteria and then close.

Key takeaways

Key point

  • Close Project or Phase: finalize all activities related to the project, phase, release, iteration or contract, whether successful or not.
  • Primary benefits: archive information, complete planned work, release organizational resources, and confirm the extent to which value has been achieved.
  • Main inputs: the charter, management plan and project documents; accepted deliverables; agreements; the business case and benefits management plan; and procurement documentation and organizational process assets.
  • The yardstick comes from the success criteria and exit criteria in the charter, and from the business case and benefits management plan; report gaps honestly and agree on how to handle them.
  • Verify first, then accept, then hand off; a project that completes normally needs formal acceptance from the person with authority (mostly the customer) before it closes.

Lesson 2

Normal Project Closure Steps: Why the Sequence Matters

Lesson video

Lesson overview

Most closure questions are sequence questions and boundary questions: what comes first after acceptance, which comes first, lessons learned or archiving, what to do with a cost surplus, what to do when management assigns a new project, and how an adaptive project closes. This is the most important lesson in the chapter. Memorize the eight steps and the three sequence lines and you can answer most questions directly. ECO: Process domain, Task 10 (Manage project closure), covering completing the activities to close the project or phase (for example final lessons learned, retrospectives, procurement, finance and resources).

Predictive projects: eight steps

PMBOK 8 groups administrative closure in predictive approaches into three kinds of activity: satisfying completion or exit criteria, contractual agreement completion, and additional closure activities. The last includes collecting and auditing project or phase records, assessing project success or failure, managing knowledge sharing and transfer, identifying and documenting lessons learned, archiving, transferring, and measuring stakeholder satisfaction. Laid out in time order, they give an easy-to-remember main line. This eight-step order is common exam practice; tailor the exact order to organizational policy, the contract and the closure plan.

  1. Final acceptance and handoff;
  2. Close the procurement contracts;
  3. Complete financial closure;
  4. Prepare the final report and survey stakeholder satisfaction;
  5. Summarize lessons learned;
  6. Update organizational process assets and archive;
  7. Celebrate;
  8. Disband the team and release resources.
Normal closure sequence

The three sequence lines

Remember the three lines this way: acceptance before handoff; summarizing before archiving; celebrating before disbanding. If acceptance has not passed, you cannot hand off. Common exam practice is to summarize lessons learned before archiving so that the archive is complete; the exact order follows organizational policy. The celebration comes before disbanding because the team is a temporary organization and a successful finish deserves recognition. Common exam practice: knowledge handover is completed before members leave, so release resources last. In real projects, people may be released earlier under organizational policy once the related work is confirmed complete and the handover is arranged.

You can use these three lines to answer questions directly. If the deliverables have been handed off and the final report distributed, and the project completion approval that is required has been obtained, the next step is to summarize lessons learned, not to archive first. Where the governance arrangement requires sponsor approval that has not yet been obtained, first handle it according to the project approval requirements. If lessons learned have been collected and registered and the results handed to operations, the next step is to organize the project files into the archive for future use; it is not to ask the operations department to archive them, and not to rush the team back to their home departments. What ranks first in the general sequence is the customer accepting and receiving the deliverables, not summarizing, updating assets or disbanding the team.

Phase closure and new assignments

When a project is delivered in batches or phases, administrative closure is also needed at the end of each phase. Take a retailer rolling out a point-of-sale system in four batches. The first batch has completed its full scope, cost is within budget and the customer has formally accepted it. The next step is to carry out phase closure for the first batch (against the phase exit criteria). When the second batch is planned and initiated is set by the project life cycle and the governance arrangement, and in this example the governance arrangement requires administrative closure of one phase before planning of the next (in other projects the arrangement may allow overlap). The next step is not another quality audit and not asking the portfolio manager to approve the results. Formal acceptance generally shows that the batch's deliverables have been verified and meet the acceptance criteria, so there should be no repeated verification without a reason; whether a quality audit is still needed is decided by the quality management plan and organizational requirements.

If you are reassigned to a new project during closure, common exam practice is to first make sure your closure responsibilities on the current project are completed or formally handed over, and only then commit to the new project. If someone else in the organization takes over, complete the handover of authority, documents and knowledge. A satisfied customer and management approval are not reasons to shortcut closure, skip handoff and lessons learned, or just archive the files. Even when the sponsor asks you to end the project immediately and move to a new one, complete the closure responsibilities or formally hand them over in the way the organization accepts. Archiving all project files is one required activity, not a substitute for the rest of closure.

Items that are easy to miss

  • Open issues and outstanding risks: open issues should be resolved before closure. For outstanding risks, state clearly who will accept them or formally transition them to operations, and record the responsibility and response arrangement. They must not be shelved, deleted or falsely closed.
  • Cost surplus: do not spend it just to avoid having the budget taken back, and do not quietly transfer it to another project. Handle it under organizational policy, record in writing where it went, complete financial closure and close the project accounts.
  • Audits: a closure audit that the organization requires must be completed as required before the project is closed.
  • Stop expenses that are no longer needed, and complete financial settlement.
  • Historical data: fill in the actual data and archive it, because it is the basis for estimating the next project. Archive the results of evaluations together with their basis so they can be found and traced later.
  • Knowledge transfer: when team members move on to other projects one by one, the project manager must make sure knowledge transfer has happened and is added to organizational process assets, rather than leaving it to departing members.

Closure in adaptive environments

Closure of an adaptive project centers on completing the release or iteration. Confirm that the prioritized backlog items are finished and the acceptance criteria are met, that all deliverables have been reviewed and accepted by stakeholders, and conduct a final review. Also hold knowledge-sharing sessions and retrospectives to reflect on the iteration or release, and discuss outstanding risks that should be accepted or transitioned to subsequent iterations or releases, clients and operations. So agile projects also close: confirm that the increments are fully integrated, complete the handoff and capture the lessons learned. Submitting a summary report and breaking up is not enough, and neither is immediately deleting the branches and test environments.

Worked example: one week of closing a senior-care service platform

On a community senior-care service platform project, the customer representative signs the final acceptance form on Monday and the system is handed to the operations department. On Tuesday the two outsourced contracts are closed and the payables are checked and settled. On Wednesday finance closes the project accounts. The cost surplus is $120,000, which under company policy goes back to the portfolio budget pool, with a record kept. On Thursday the project manager issues the final report and sends the customer a satisfaction questionnaire. On Friday a lessons learned session is held and the entries are then organized into the repository. The following Monday the organizational process assets are updated and the files archived, on Wednesday the team has a celebration lunch, and on Thursday the members return to their new roles. Midway, someone suggests “let people go first to save cost”. The project manager declines, because knowledge handover and archiving are not yet complete.

Worked examples

Example 1 After the first batch is accepted in a phased rollout

Question 1Example

A retailer divides a new point-of-sale system project into four phases, each phase going live at a batch of 5 stores per region. The governance arrangement requires administrative closure of one phase before planning of the next phase begins. The full scope of the first batch (phase 1) was completed on time, cost is within budget, the customer has formally accepted it, and the phase exit criteria are met. What should the project manager do next?

Show answer and explanation

Correct answer: B

The retailer rolls out the point-of-sale system in four batches, one phase per batch, 5 stores per region. The first batch has finished its scope on time, is within budget, and has been formally accepted by the customer. The question asks what the project manager does next.

The first batch has met the scope, cost and acceptance conditions, so the work of this phase is done. The next step is to end the phase, that is, to carry out administrative closure for the first batch: archiving, summarizing lessons learned, confirming acceptance records, and releasing resources no longer needed. After phase acceptance passes, closure of that phase comes first. Under the governance arrangement in this question, planning of the next batch can begin only after this phase's administrative closure is complete, so it is not the first thing to do. The answer is B.

Why the other options are wrong

  • A. The stem does not show that the quality management plan or the organization requires another quality audit now. The first batch has passed formal customer acceptance and the exit criteria are met, so the phase should now be closed.
  • C. Customer acceptance has already recognized the result, which does not need further approval by the portfolio manager, and such approval is not a step at this point.
  • D. The governance arrangement in this question requires administrative closure of one phase before planning of the next, and since the exit criteria are met, first carry out administrative closure of this phase. Planning the next batch is not the first thing to do.

Key takeaway After the phase exit criteria are met and acceptance has passed, close that phase first. Under the governance arrangement, planning of the next phase begins only after closure is complete, so it is not the first step.

Variation If acceptance of the first batch had not passed, you could not close, and would deal with the acceptance problem first. After all batches are done, you carry out the final closure for the whole project.

Something wrong with this question?

Report an issue with this question

Example 2 Assigned to a new project after acceptance is signed

Question 2Example

The final deliverable of a logistics dispatch system project has passed acceptance and the customer representative has signed. The project manager is running a stakeholder satisfaction survey. The customer's ratings are high and management, appreciating the project manager's ability, then assigns the project manager to lead another new project. What should the project manager do now?

Show answer and explanation

Correct answer: C

The final deliverable has been accepted and signed, the satisfaction survey results are very good, and management assigns the project manager to a new project. The question asks what the project manager should do now.

Overall acceptance and the satisfaction survey are only the first half of normal closure. Still to come are financial closure, summarizing lessons, updating organizational process assets, archiving files, releasing resources and, where applicable, closing contracts. The applicable items should be completed while the needed team members are still available. When assigned a new project during closure, first finish this project's closure with the team, then move to the new project. The answer is C.

Why the other options are wrong

  • A. Closure is a process that must be completed. It is not waived because the customer is satisfied or a new assignment arrives, and the handoff, lessons learned and archiving cannot be “simplified” away.
  • B. Turning to new work before closure is done makes it easy to delay or even miss lessons learned, handoff and archiving. Closure of the current project should be ensured first.
  • D. Archiving is only one item of closure. Handoff, summarizing lessons learned, asset updates and releasing resources cannot be skipped either.

Key takeaway A signed acceptance does not mean closure is done. If you are assigned to a new project during closure, finish the current project's closure first.

Variation If the stem said “the sponsor asks to end the project immediately”, the project manager would still complete the closure responsibilities or formally hand them over; archiving all project files is only one required activity. Resources can be released as planned once the required closure work and knowledge handover are complete or properly transferred.

Something wrong with this question?

Report an issue with this question

Example 3 What ranks first in the general closure sequence

Question 3Example

The project has entered formal closure, and all four activities below remain outstanding. In common exam practice, which should usually be completed FIRST?

Show answer and explanation

Correct answer: B

The question asks which of four tasks ranks first in the general closure sequence, so it tests the order of closure steps.

Common exam practice is that formal acceptance and receipt of the deliverables is an important precondition of closure and comes before the other closure activities. Lessons learned and organizational process asset updates can go on throughout the project and are compiled into the repository at closure. Releasing resources comes after the necessary closure and knowledge handover are done. Of the four options, customer acceptance and receipt of the deliverables fits best at the very front. The answer is B.

Why the other options are wrong

  • A. Lessons learned can be registered throughout the project, but the project-wide summary at closure is, by common exam practice, done after the results are accepted, so it is not the first item.
  • C. Releasing resources usually comes after the necessary closure and knowledge handover. If people are released first, there is nobody left to do the later work.
  • D. Updating organizational process assets puts lessons learned and similar information into the organizational knowledge repository, and is usually done as a compilation after acceptance and summarizing.

Key takeaway Formal acceptance and handoff are an important precondition of closure; release resources as planned after the necessary closure and knowledge handover are complete.

Variation If the options were changed to compare “summarize lessons learned” with “update organizational process assets”, the summary usually comes first and the repository entry after. If comparing “celebrate” with “disband the team”, celebrating usually comes first.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • On EXCEPT questions, read the key words carefully. Quality and compliance audits occur at the points required by the plan and organizational policies. Closure also includes collecting and auditing project or phase records as required and verifying that contractual, regulatory, legal, social and environmental obligations have been met. The main work of closure is acceptance, handoff, summarizing, archiving and releasing resources.
  • A signed acceptance and a high satisfaction score do not mean closure is complete. Handoff, lessons learned, asset updates, archiving and releasing resources still follow.
  • Do not disband the team first and do the knowledge handover afterward. Common exam practice is to release resources last.
  • Open issues must be resolved before closure, and outstanding risks must be handled or formally handed over. Neither may be falsely closed.

Key takeaways

Key point

  • Closure sequence (common exam practice): accept and hand off, close contracts, financial closure, final report and satisfaction, lessons learned, update organizational process assets and archive, celebrate, release resources.
  • Three sequence lines: acceptance before handoff; summarizing before archiving; celebrating before disbanding.
  • After a phase is accepted, first carry out closure of that phase. Planning of the next phase follows the life cycle and governance arrangement and may overlap closure. If you are reassigned to a new project during closure, first complete the closure or formally hand over the closure duties.
  • Open issues must be resolved before closure, and outstanding risks must be handled or formally handed over; handle cost surplus under organizational policy and record it in writing.
  • An adaptive project centers on completing the release or iteration, and still needs integration confirmation, handoff and lessons learned.

Lesson 3

Early Termination: What to Do After a Project Is Stopped

Lesson video

Lesson overview

A project does not always reach its planned end. The budget runs out, the company's cash flow breaks down, new regulations create a constraint, the strategy changes, or a competitor releases a similar product first. When a project or phase is closed before its planned schedule and/or budget is exhausted, that is early termination. Many candidates' first reaction is to stop work abruptly and without order, or to try on their own to “find a way to save it”. Both are wrong. You should stop or safely wind down the project work as approved and complete formal closure. This lesson covers the two kinds of cause for early termination and what the project manager should do after being told to stop. The pattern in the answers is clear: a project terminated early must still be closed out. ECO: Process domain, Task 10 (Manage project closure), covering completing the activities to close the project or phase.

Two kinds of cause

PMBOK 8 lists early termination as a common project governance scenario. Early termination for a positive cause: a project or phase is closed before exhausting its planned schedule and/or budget because the desired value impact has been achieved. Early termination for a negative cause: a project or phase is closed before exhausting its planned schedule and/or budget because the desired value impact is no longer achievable. PMBOK 8 also says the Closing Focus Area “may also address the suspension or early closure of the project (e.g., when canceling the project becomes the best way to maximize the return on that project investment—or perhaps more accurately, to minimize what may have become a negative return).”

So termination is not the same as failure. If the expected value has been achieved early, it is a positive termination. If the expected value can no longer be achieved, it is a negative termination, for example because funding has collapsed, regulation constrains the work, the strategy has changed, a competitor reached the market first, or the market has shifted. In either case the overall value proposition is the main factor in the decision. Whether to terminate is decided by the governing body authorized under the organization's governance model, the sponsor, senior management or a self-governed team (the exam usually says governance and senior management). The project manager's responsibility is to take part in the evaluation within delegated authority and to carry out the approved termination and closure, not to argue, rescue the project or keep going.

After termination: close out first

PMBOK 8 states that the Close Project or Phase process also includes “establishing procedures to investigate and document reasons that the project may have been terminated before completion”, and identifying outstanding risks that should be accepted or transitioned to operations. When a project is terminated, the project manager's steps are:

  1. Follow the organization's closure process. If the organization has a standard closure process, consult the closure guidance and follow it rather than inventing your own approach. The termination decision has already been made, so do not reassess whether to terminate.
  2. Investigate and record the reason for termination. Even if the project was well along and all indicators were good, and was canceled only because of a regulatory constraint, start closure under the organization's process and investigate and record the reason for cancellation during closure. Even if a project is canceled right after its charter was approved, start closure under the organization's process; do not keep planning, do not treat it as a new risk and do not submit a change to reduce scope.
  3. Account for completed and uncompleted deliverables. State the completion status in the closure documents and carry out the handoff. Completed parts can keep their value. For uncompleted parts, make clear the status, the owner and the disposition (where something needs to be continued or kept, carry out the corresponding handoff; it may also be archived or discontinued). At the same time, identify the outstanding risks that should be accepted or transitioned to operations, and record and carry out that acceptance or transition.
  4. Summarize lessons learned and put them in the repository. Store the historical information and lessons in the knowledge repository for use by future projects or phases.
  5. Release resources. There is no fixed order, and release does not have to be last. Common exam practice puts releasing people after recording, handoff and knowledge transfer. In practice you can release people in batches as closure needs dictate, but keep the people and resources needed to finish the related closure work. Do not let the team leave the moment you hear about termination.
What to do after a project is stopped

Worked example: a pipe network upgrade stopped by land acquisition

An industrial park sewage pipe network upgrade has three stages: survey, excavation and laying. Excavation is half done when the land the pipeline runs through is acquired by the government for road construction. The owner cancels the project and the change request to terminate it is approved. The project manager does not disband the construction crew right away. Instead, the project manager confirms the reason for cancellation with the owner and writes it into the closure documents; takes stock of the trenches already excavated, the survey data already completed and the laying that has not started, and lists what is to be handed over; reconciles unsettled construction payments with the subcontractors; stores the lesson “the contract had no suspension clause for land acquisition risk” in the organizational knowledge repository; and only then releases the construction crew, with team members returning to their home departments.

Worked examples

Example 1 Stopped by a regulatory constraint: the next step

Question 1Example

A cross-border e-commerce product-selection platform project is in its middle-to-late stage, with scope, quality, schedule and cost all on plan and acceptance due in about a month. The sponsor then discovers a constraint tied to data export regulations that makes the risk too high, and after review management decides to cancel the project. What should the project manager do next?

Show answer and explanation

Correct answer: C

The project is in its middle-to-late stage with scope, quality, schedule and cost all on plan, and acceptance is about a month away. The sponsor discovers a constraint tied to data export regulations, the risk is too high, and management cancels the project. The question asks what the project manager does next, so it tests handling of early termination.

A project terminated before completion must be closed as well. Close Project or Phase includes establishing procedures to investigate and document the reasons the project may have been terminated before completion. So the next step is to start closure under the organization's process and, during closure, investigate and document the reason for cancellation. Then account for the completed and uncompleted deliverables, carry out handoff, summarize lessons learned, and release resources as appropriate. The answer is C.

Why the other options are wrong

  • A. You cannot stop work and move straight to a new project. A canceled project still needs closure, for example preserving interim results and updating organizational process assets.
  • B. Management has already decided to cancel, and the project manager has no authority to finish the project. Continuing to invest wastes resources and goes against the decision.
  • D. By common exam practice, releasing people comes after recording, handoff and knowledge transfer. Releasing people now would leave nobody to complete the records and handoff.

Key takeaway Early termination also requires closure, starting with finding and recording the reason for termination.

Variation If the stem said “the project was canceled right after its charter was approved”, closure still starts under the organization's process. If the project closed early because the expected value had been achieved, that is early termination for a positive cause and it needs closure too.

Something wrong with this question?

Report an issue with this question

Example 2 A project terminated after funding collapses

Question 2Example

A startup runs 5 projects at once, one of which is a one-year customer portal project that is six months in. The company's cash flow dries up, and senior leaders decide to terminate two projects, including this one. What should the project manager do next?

Show answer and explanation

Correct answer: C

The startup runs 5 projects, cash flow dries up, and leaders decide to terminate two, including this customer portal project six months in. The question asks what the project manager does next.

The termination decision has been made by senior management, and its cause is a company-level funding problem. The project manager's task is to carry out the closure that follows termination: handle it as an early termination, store the historical information and lessons learned in the lessons learned repository for use by future projects or phases, and hand off the completed and uncompleted deliverables. The answer is C.

Why the other options are wrong

  • A. The decision was made by senior management and its cause is a hard constraint, the collapse of funding. The project manager's job is to carry out closure after termination, not to ask management to find other ways.
  • B. Financing is a company-level matter. Management has decided to terminate, so the team should turn to closure and not brainstorm for funds.
  • D. Seeking funds from other projects conflicts with management's decision to terminate and is not the project manager's task at this point. The project manager should proceed with closure under that decision.

Key takeaway Once a project is terminated it goes into closure, and the lessons learned go into the repository for future use.

Variation If the stem asked for “the first step after termination”, start closure as the organization's closure requirements direct, and investigate and record the reason for termination during closure. If the sponsor says “the project is not profitable, we are stopping”, follow the closure process in the same way and do not re-justify the project.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When a project is terminated, stop or safely wind down the project work as approved, but do not skip administrative closure. Also do not rush to rescue it: do not look for funding, re-justify the project, or keep finishing what is left. Then complete the records, settlement, handoff, archiving and disposal of resources.
  • When the sponsor says “the project is no longer profitable, we are stopping”, the project manager's job is not to find money or re-justify the project, but to follow the organization's closure process.
  • Do not release resources the moment you hear about termination. Common exam practice is to release people after recording, handoff and summarizing, in batches as needed.
  • The reason for termination must be investigated and recorded, not glossed over.

Key takeaways

Key point

  • There are two kinds of early termination: closed early because the expected value has been achieved, and closed early because the expected value can no longer be achieved. The overall value proposition is the main factor in the decision.
  • An early-terminated project is still closed out: find and record the reason, account for completed and uncompleted deliverables, carry out handoff, and identify outstanding risks to be accepted or transitioned.
  • Lessons learned and historical information go into the knowledge repository, and then resources are released as needed. Common exam practice puts releasing people after recording, handoff and knowledge transfer; in practice, release them in batches as needed.
  • If the organization has a closure process, follow it. The termination decision is made by the governing body authorized under the organization's governance model, the sponsor or a self-governed team; the project manager takes part within delegated authority and carries out the approved termination and closure, without rescuing the project or continuing it.
  • Investigating and documenting the reason for termination belongs to the Close Project or Phase process.

Lesson 4

Closure Tools and Outputs: Final Report, Handover and Satisfaction

Lesson video

Lesson overview

The first two lessons covered the purpose and the steps of closure. This lesson looks at how it lands in practice: which tools tell you how much of the objectives was achieved, what the final report contains, how the results are handed to the operations team, and how satisfaction is collected. It focuses on three scenarios: explaining overall project performance to stakeholders, the key requirements for handing over to operations, and what to do when users cannot use the product after acceptance. It involves transition readiness and knowledge transfer. ECO: Process domain, Task 10 (Manage project closure) and People domain, Task 7 (Help ensure knowledge transfer).

Tools: expert judgment, data analysis and meetings

Closure uses expert judgment, data analysis and meetings. Expert judgment means asking people with the relevant expertise to help judge the closure work. Data analysis is used to assess how far the objectives were achieved against the project management plan; the common techniques are variance analysis, trend analysis, regression analysis and document analysis. Meetings (in practice, closure meetings and lessons learned meetings) should have stakeholders taking part, to make closure comprehensive. PMBOK 8 also stresses that engaging relevant stakeholders is crucial to ensure a comprehensive closure process.

The final report: explaining overall performance

PMBOK 8 calls for preparing final project reports as required by organizational policies. The final report is a summary of project performance. PMBOK 8 says it can include the following: a summary-level description of the project or phase; scope objectives, the criteria used to evaluate the scope, and evidence that the completion criteria were met; quality objectives, the criteria used to evaluate the project and product quality, the verification and actual milestone delivery dates, and reasons for variances; cost objectives, including the acceptable cost range, actual costs, and reasons for any variances; a summary of the validation information for the final product, service, or result; schedule objectives, including whether the results achieved the benefits that the project was undertaken to address (if the benefits are not met at the close of the project, the degree to which they were achieved and an estimate for future benefits realization); a summary of how the final product, service, or result achieved the business needs identified in the business plan (if not, the degree achieved and an estimate of when those needs will be met); and a summary of any risks or issues encountered on the project and how they were addressed. The report should be honest, including what was not achieved and why, and it should complete the review or approval that organizational policy requires; the exact content depends on organizational policy and the project. Record lessons learned in project document updates. Common exam practice also adds a broader financial summary, such as cash flow or return on investment, to the final report. On exam questions, the content must be complete. If a report covers only schedule and scope completion with no financial summary, add a financial summary showing the final cost and how it compares with the budget. Do not simply record the cost in the lessons learned register, and do not delete the schedule section to pad the length.

When a stakeholder wants to judge whether the project was a success, explain overall performance to them with the final report, together with key performance indicators (KPIs, common exam practice). Do not wait three months to evaluate, and do not substitute a status report or the lessons learned register.

Satisfaction: ask the customer directly

Besides scope, schedule and cost, whether stakeholders are satisfied is also an important performance measure of success. PMBOK 8 lists “measure stakeholder satisfaction” among the additional closure activities. You can collect feedback directly from the relevant stakeholders, including the customer, through questionnaires, interviews and the like, and then compile it into a report. Acceptance cannot replace this, because acceptance shows only that the acceptance criteria were met. Nor can you infer satisfaction from the issue log or lessons learned, because well-resolved issues do not mean a satisfied customer. Thank-you emails lack a uniform basis and will not give reliable results.

Handoff: the receiving party can really take it

PMBOK 8 calls for transferring project products, services or results to the next phase or into production/operations, and for identifying outstanding risks that should be accepted or transitioned to operations. Common exam practice: judge a handoff by whether the receiving party can really take it:

  1. First confirm the receiving party is ready, then hand off. If the operations team is not ready, do not force the handoff and do not dump it on them. Inform the sponsor and replan to shorten the delay.
  2. Complete content. Products, documents, accounts, access rights, outstanding risks and the open issue list are all on the checklist, and the receiving party confirms each item.
  3. The receiving party has the knowledge. The operations team truly has the knowledge needed to operate and maintain the result, and responsibilities, resources and processes are clearly handed over. The project team does not stay on standby, and the receiving party is not left to “digest” a pile of documents on its own.
  4. Reduce transition risk. If new members of the operations team are unfamiliar with the project, authorize an early trial run and involve the receiving party. Do not exclude the new members, and do not train only those who know the project.
  5. End users can use it. If you want users to operate independently and proficiently after go-live, use end-user training. User manuals, a support portal and project documentation are supporting measures. For a complex system, or where users have a capability gap, arrange suitable training, and whether it is enough depends on whether users can handle the operation (common exam practice: when the stem asks for proficient, independent operation, end-user training is the first choice).

If users cannot use the product after acceptance, first check the closure documents to see whether the agreed knowledge transfer was completed and confirmed by the customer, then decide on additional training. Do not go back and change the product, escalate to management, or dig through the risk management plan.

Worked example: handing a meter-reading and billing system to the customer service center

A district water utility's meter-reading and billing system goes live, and the customer service center takes over daily operation. During closure the project manager does four things. First, confirm the service center has named three key staff and freed up two weeks of learning time. Second, go through the handoff checklist item by item, including system accounts, access rights, data backups, emergency contacts and the open issue list. Third, schedule two end-user training sessions: one on operation, and one that practices with last month's real meter-reading data, where the key staff must complete one full billing cycle independently. Fourth, run a two-week trial in which the key staff handle bills directly and the project team only answers questions on the side. When the trial ends, the service center signs the handoff confirmation, and only then does the project team withdraw.

Worked examples

Example 1 How to learn about customer satisfaction

Question 1Example

A software company's customer management system project is in closure. A key stakeholder wants to know how the project turned out and asks the project manager for a report that reflects customer satisfaction. What should the project manager do?

Show answer and explanation

Correct answer: A

The customer management system project is in closure, and a key stakeholder asks for a report that reflects customer satisfaction. The question asks what method to use to get the information.

PMBOK 8 lists measuring stakeholder satisfaction among the closure activities. Satisfaction is the customer's subjective impression, and the most direct way is to send customers a satisfaction questionnaire and compile the returned results into a report, with a uniform basis and data coming straight from the customer. The answer is A.

Why the other options are wrong

  • B. The issue log reflects how issues were handled. Well-resolved issues do not mean a satisfied customer, so satisfaction cannot be inferred from it.
  • C. The lessons learned register records the team's lessons for improving later work. It does not contain the customer's judgment of whether the results are satisfactory.
  • D. A thank-you email is not designed to obtain satisfaction. Replies are scattered and lack a uniform basis, so they cannot make a reliable satisfaction report.

Key takeaway To learn customer satisfaction, use direct means such as questionnaires and interviews, not inference from issue records or lessons.

Variation If the stem asked “how to show the project's overall performance”, the answer is the final report with key performance indicators. If it asked “how to confirm the results meet the acceptance criteria”, look at the acceptance document.

Something wrong with this question?

Report an issue with this question

Example 2 Handing off to the operations department: what matters most

Question 2Example

A manufacturer's internal management system project has passed acceptance and is about to be handed over to the company's operations and maintenance department. What is the most important thing the project manager should do during the handoff?

Show answer and explanation

Correct answer: D

A manufacturer's internal management system has passed acceptance and is about to be handed to the operations and maintenance department. The question asks what the project manager should do most in the handoff.

Handoff of the final result is transferring the product, service or result to another team, which operates, maintains and supports it through its life cycle. The project manager must ensure the handoff content is complete and confirm that the operations team truly has the knowledge it needs; only then is the handoff in place. The standard for handoff is that the receiving party can take it. The answer is D.

Why the other options are wrong

  • A. Handing over all the documents at once, without checking whether the receiving party understands them and can use them, does not complete the handoff.
  • B. Disbanding the team on the day of handoff means the knowledge in the team has not been passed on and nobody can answer the receiving party's questions. Later operations problems should not automatically be treated as a new project; first route them through the applicable operations, warranty, or governance mechanism, with a separately authorized project used when warranted.
  • C. A project is temporary work. After it ends the team disbands and operations belongs to the operations team, so the project team should not take on day-to-day operations long term.

Key takeaway The standard for handoff is that the receiving party can really take it: complete content, and an operations team with the knowledge it needs.

Variation If the stem asked “users cannot use the product after acceptance”, first check whether the knowledge transfer was done, and use end-user training. If it said “the operations team is not ready”, tell the sponsor and replan, and do not force the handoff.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • “Hand over more documents” and “extend project team support” are not what matters for transition to operations. What matters is that knowledge passes to the operations team so the receiving party can run things independently.
  • A project is temporary, so the team should not carry long-term operations, and should not be disbanded too early, before handoff, knowledge transfer and other closure activities are complete. Once everything is done, release people as planned.
  • Satisfaction cannot be replaced by acceptance, the issue log or lessons learned. Ask the customer directly.
  • The final report must be honest, including what was not achieved. Do not pick only the good news.

Key takeaways

Key point

  • Tools: expert judgment, data analysis (variance analysis, trend analysis, regression analysis, document analysis) and meetings (in practice, closure meetings and lessons learned meetings).
  • The final report (what PMBOK 8 says it “can include”): summaries of scope, quality, cost, schedule and benefits, business needs, and risks and issues, reported honestly, with the review or approval that organizational policy requires. Lessons learned go into project document updates, and common exam practice adds a broader financial summary.
  • To explain overall performance to stakeholders, use the final report together with key performance indicators.
  • Satisfaction can be collected directly through questionnaires, interviews and the like; it cannot be replaced by acceptance or the issue log.
  • The standard for handoff is that the receiving party can take it: complete content, an operations team that has the knowledge, and responsibilities, resources and processes clearly handed over; any gaps are filled during closure.

Lesson 5

Closure Documents, Organizational Process Asset Updates and Closing Out Contracts

Lesson video

Lesson overview

The last stretch of closure is settling what the project leaves behind: lessons learned go into the organizational knowledge repository, files are archived as required, contracts are formally closed, and the closure documents are complete. After that comes a common scenario: the project is already closed and the customer comes with a new requirement, or objects to work already completed. What do you do? This lesson ties these together. ECO: Process domain, Task 10 (Manage project closure), covering completing the activities to close the project or phase, and Business Environment domain, Task 6 (Continuous improvement), covering updating organizational process assets.

Lessons learned into the repository, and archiving

As common exam practice, once lessons learned are summarized, the next step is to add them to the lessons learned repository (part of the organizational process assets), then archive and release resources. PMBOK 8 says that at the end of a project or phase the relevant information should be put into the lessons learned repository so that it becomes part of the organizational process assets. In closure you also archive project information for future organizational use, and collect suggestions for improving or updating organizational policies and procedures and forward them to the appropriate unit. Getting lessons learned and historical data into the organizational asset library is the core of updating organizational process assets. So at closure, confirming the extent to which value was achieved and updating organizational process assets are the emphasis. Adding the customer's new requirements to the scope baseline, disbanding the team before acceptance, and extending the project period into the operations period are not closure work.

Archiving follows the process the organization specifies; you cannot store things wherever you like. Suppose a new project manager finds that the predecessor never archived anything and the team feels that time spent on anything other than deliverables is wasted. The right approach is to explain to the team the value of archiving and to keep the files under the organization's archiving process. Valuable material is not only the files directly tied to deliverables. Records of how issues were handled, lessons learned and the basis for decisions should be kept too. A forced order can get the files archived, but explaining the value and winning buy-in works better. Which documents must be kept is already specified by the organization's process, so there is no need to ask the sponsor first.

Closing out contracts

When closing out contractual agreements in the Close Project or Phase process, PMBOK 8 calls for verifying these activities: confirm formal acceptance of the external source's work; finalize any open claims, guarantees, and warranties; update records to reflect the final results; ensure all invoices due to external sources are paid; archive relevant information for future use; and resolve any disputes that may arise or refer them to the dispute board. In short, contract closeout is four things: accept, settle, archive and resolve disputes, and it must be done before the project as a whole is closed.

Closure documents: proof that the project is complete and handed off

Closing a project needs formal closure documents, not verbal agreement or default. (“Closure documents” is a common exam term for the final report, the acceptance and handoff records and similar materials. PMBOK 8 lists the outputs of Close Project or Phase as project document updates, the transition of the final product, service, or result, the final report, and organizational process asset updates.) At closure, prepare the final report as organizational policy requires and complete the formal handoff of the final product, service or result. The acceptance records, evidence of completion and handoff records should be archived as the organization requires, and must be complete, because they are the proof that the project is complete and handed off. Suppose the customer objects after a completed project—for example, the business grinds to a halt after go-live. The project manager should respond to the customer and involve an operations representative in assessing the impact and investigating the root cause. Then use the acceptance and handoff records and the contract terms to determine responsibility and the appropriate response. Closure documents establish the acceptance and handoff status, but they do not replace investigation of the failure. If the problem involves a project defect, a warranty or an unmet contractual obligation, handle it as agreed and escalate if necessary.

New requirements after closure

A new requirement that appears after project closure does not go through the change control procedure of the closed project. The suggested route is a new project, or a new contract or supplementary agreement. Analyze and communicate first; do not start work directly. If the final product has been handed off, the team has been disbanded, and the customer wants a new feature added, do not submit a change request to add it to the original project, do not recall the team, and certainly do not wait for the steering committee to decide. Suggest that the customer start a new project for the new feature. If during closure the customer wants to add new scope to the contract, first confirm whether the project has been formally closed and evaluate against the contract terms and the change control rules. If the project has already been closed, the project manager explains this to the customer and suggests signing a new contract or a supplementary agreement. The project manager neither flatly refuses nor starts work immediately.

For changes during closure, make a distinction. Before closure, the deliverables are either finished or their disposition is agreed by the stakeholders. Once the project is closed, a new requirement becomes a separate project or a separate contract.

Worked example: a new request during closure

On a medical device manufacturer's quality traceability system project, all five contract targets have been met and the project has moved into closure. The customer then asks to add a “supplier scoring” module to the contract. The project manager neither agrees at once nor refuses outright, and does three things. First, explain to the customer that the project has been accepted under the contract and is in closure but not yet formally closed, that the new scope must be evaluated against the contract terms and the change control rules, and that because the original contract work has already been accepted, it is not appropriate to add to the original contract. Second, ask the commercial team and the customer to evaluate together the effort and value of this module, and suggest a supplementary agreement that starts it up as a new project. Third, keep going through the closure process: close the outsourced contracts, update lessons learned and archive the files. The requirement records for the new module go into the initiation materials of the new project.

Worked examples

Example 1 After lessons learned are summarized, what is next

Question 1Example

A corporate group launched a project to overhaul its internal expense reimbursement system so it would be easier to use. After a long push, the results are done and accepted, the project manager has held the lessons learned meeting, team performance appraisals are complete, and releasing the team is scheduled as the last closure step. To wrap up the project, what should the project manager do next?

Show answer and explanation

Correct answer: D

The reimbursement system overhaul has been accepted, the lessons learned meeting has been held, team performance appraisals are complete, and resource release is scheduled as the last step. The question asks what comes next in closure.

PMBOK 8 says that at the end of a project or phase the relevant information should be put into the lessons learned repository, that is, organizational process assets are updated. The lessons learned meeting has been held, so the next step is to consolidate the lessons learned and related information into the organizational process assets. The answer is D.

Why the other options are wrong

  • A. Checking whether the deliverables meet requirements is the verification work done before acceptance, and in this question it was completed with acceptance.
  • B. A celebration is not a required administrative closure step and cannot replace entering lessons into the repository and archiving the project files.
  • C. The stem states that team performance appraisals are complete and that releasing the team is scheduled as the last closure step, so it is not yet time to review appraisals and release people; the summarized lessons should first be transferred into organizational process assets.

Key takeaway After lessons learned are summarized, the next step is to put them into the lessons learned repository, that is, to update organizational process assets.

Variation If the stem said “the lessons learned are in the repository and archived”, closure work is largely done and resources are then released as planned. If it said the lessons have not yet been summarized, you cannot archive first.

Something wrong with this question?

Report an issue with this question

Example 2 Taking over a project and finding nothing archived

Question 2Example

A project manager leaves for personal reasons, and the organization appoints a new project manager to take over a project under way. On checking, the new project manager finds that the predecessor never archived the project and almost no files were kept. Team members feel that time spent on anything beyond the deliverables is a waste. How should the new project manager respond?

Show answer and explanation

Correct answer: A

A new project manager takes over a project under way and finds that the predecessor never archived anything, and the team feels that time spent beyond the deliverables is wasted. The question asks how to respond.

The information and knowledge a project produces can serve the organization's day-to-day operations and later projects, and archiving follows the process the organization specifies. Facing the team's lack of agreement, the project manager should first explain the value of archiving to win their buy-in, and then keep the files according to the organization's archiving process, combining reasoning with process. The answer is A.

Why the other options are wrong

  • B. Which files must be kept is already set by the organization's archiving process, and it is the project manager's own responsibility, so there is no need to ask the sponsor first and then decide.
  • C. Valuable material is not only the files directly tied to deliverables. Records of how issues were handled, lessons learned and the basis for decisions must also be kept, and keeping only part loses knowledge.
  • D. A forced order can get files archived after the fact, but the team does not buy in. The lasting effect is weaker than explaining the value and winning agreement, and it does not fit how a team should be led.

Key takeaway Archive through the process the organization specifies, and help the team understand why archiving matters.

Variation If the archive lacks lessons learned, summarize them first and then archive. If the team still resists archiving, keep explaining the value of archiving to later projects and to the organization.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A project that has been closed no longer goes through change control. Squeezing a new requirement into the original project's change control procedure is a common wrong option.
  • Archiving follows the organization's process. It is not only keeping the files related to deliverables, and it is not done by forced order.
  • Lessons learned should be recorded continuously during the project and put into the lessons learned repository at the end of the project or phase. The specific arrangements for archiving, releasing resources and celebrating are set by the project and the organization (common exam practice: summarize first and then archive, and celebrate before releasing resources).
  • The closure documents are not optional. They are the evidence that the project is complete and handed off.

Key takeaways

Key point

  • After lessons learned are summarized, the next step is to update them into organizational process assets (the lessons learned repository), and then archive and release resources.
  • Archive through the organization's specified process, and help the team understand the value of archiving; valuable material is not only the files related to deliverables.
  • Closing out contracts: formal acceptance of external work, open claims, guarantees and warranties finalized, records updated, invoices paid, information archived, and disputes resolved or referred to the dispute board.
  • Closure documents (a common exam term for the final report, acceptance and handoff records and similar; the PMBOK 8 outputs are the final report, project document updates, organizational process asset updates and transition) must be complete and are the proof that the project is complete and handed off.
  • A new requirement after closure does not go through the closed project's change control; it becomes a separate project or a separate contract or supplementary agreement.

This chapter has 52 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.