Project Charter

PMP · Governance and Business Environment · 5 lessons · about 57 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

A project goes through initiation to get from "having an idea" to being formally ready to start. The Eighth Edition calls this step Initiate Project or Phase, and its main outputs are the project charter and the assumption log (Figure 2-3 of the Eighth Edition shows other outputs as well, indicated by "Etc."). This chapter covers what a charter is, what it contains and who issues it; the inputs that come before the charter, mainly the business case, the benefits management plan and agreements (plus enterprise environmental factors and organizational process assets); the thing the charter most needs everyone to agree on, the common vision; the assumption log, the tools used in initiating and the lightweight charter for adaptive projects; and finally a separate scenario that is often tested: what the first step is when a project manager takes over a project midway.

The chapter has two focal points: the common vision (People domain, Task 1 of the exam content outline) and the content and role of the charter. The common thread in the answers is "authorize first, then plan" and "verify first, then act", never going beyond the sponsor and the process on your own judgment.

Lessons in this chapter

  • Lesson 1: Content and Purpose of the Project Charter. The three things a charter does; five kinds of content; who issues it; what to show when your authority is questioned; what to do when a sponsor says a small project needs no charter.
  • Lesson 2: Inputs to Initiating: Business Documents and Agreements. The business case, benefits management plan, agreements, enterprise environmental factors and organizational process assets; the project manager does not usually edit business documents on their own (the sponsor is generally accountable for developing and maintaining the business case, with the project manager providing recommendations and oversight); on a cross-organization project, a contract establishes the agreement between organizations while each organization uses a charter to establish internal agreements, and the charter is issued by the project initiator or sponsor.
  • Lesson 3: Shared Vision. What a vision is and what it contains; the four enablers of the task: gain consensus, drive consensus, keep the vision current, and analyze the root causes of misunderstandings.
  • Lesson 4: The Assumption Log, Initiating Tools and the Adaptive Charter. Assumptions and constraints; record newly discovered constraints first; facilitation, focus groups and the project canvas; an adaptive charter may be built around some or all of seven guiding questions; a hybrid charter sets boundaries.
  • Lesson 5: What a Project Manager Does First When Taking Over a Project. Charter first, then plan, then handle according to process; the standard approach for more than ten takeover situations.

Chapter map

Initiate Project or Phase

  • Inputs: business case · benefits management plan · agreements · enterprise environmental factors · organizational process assets
  • Tools: expert judgment · brainstorming · focus groups · interviews · conflict management · facilitation · meeting management · meetings · responsibility assignment matrix · project canvas
  • Outputs: project charter (formally approves the project, records the assigned project manager and authority, authorizes use of resources) + assumption log
    • Common vision: developed together and kept current; may be written into the charter (an adaptive project can use a vision statement as a lightweight charter)
    • Adaptive charter: seven questions; hybrid: the charter sets governance boundaries, and teams using adaptive approaches self-organize within the authorized boundaries

Taking over a project: charter first (why) → then plan (how) → then compare with current status → handle according to process

Chapter practice: do the core questions first, then the required questions.

Lesson 1

The Project Charter: Content and Purpose

Lesson video

Lesson overview

Whether a project can start with proper standing, and whether the project manager can legitimately assign people and money, depends on one document: the project charter. It is produced in the Initiate Project or Phase process of the Governance performance domain. This lesson covers what a charter is, what it contains, who issues it, and why it is the strongest card a project manager holds. Questions on this lesson usually take one of two forms: either "what document proves your authority?" or "what do you do when the sponsor says no charter is needed?" The next lesson covers the inputs that come before the charter, such as the business case and agreements.

What a charter is

The Initiate Project or Phase process officially authorizes the start of a project and grants the project manager the authority to allocate organizational resources to project activities by creating a project charter or similar document. It belongs to the Initiating focus area and is usually carried out once, or at certain points during the life cycle of a project, depending on the development approach.

A project charter is a document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. That sentence contains three layers: the project gains legitimate standing in the organization; the project manager gains legitimate standing; and the project manager can use organizational resources. If any one of the three is missing, the project manager will hit a wall when coordinating resources.

The project charter forms a partnership between the performing and requesting organizations. For cross-corporate projects with two or more organizations involved, contracts are used to establish an agreement among the organizations. Project charters are then used inside the organizations to create internal agreements to ensure fulfillment of contractual obligations, which are mostly deliveries made by contractors, with payments made by customers. So a contract governs the relationship between organizations, and a charter governs authorization inside an organization.

Different companies use different names. Some call it a project manager appointment letter, which focuses on confirming the project manager's identity; others call it a project approval document, which focuses on confirming the project itself. The exam generally uses the name "project charter". In real work, make sure both are covered: the project manager's appointment and the project's approval.

What goes in a charter

A charter holds only high-level information, and the detail is left to the components of the project management plan to elaborate. The table below groups the common content by purpose into five categories, and each item is an element of the Eighth Edition's project charter (Table 4-1). Acceptance criteria and project exclusions belong to the project scope statement and are not charter content; the charter gives only a high-level description and the boundaries.

AspectWhat the charter contains
Purpose and objectivesProject purpose; measurable project objectives and related success criteria
Scope and scheduleHigh-level project description, boundaries and key deliverables; summary milestone schedule
FundingPreapproved financial resources
People and approvalKey stakeholder list; assigned project manager, responsibility and authority level; name and authority of the sponsor or other person(s) authorizing the project charter
Approval and exitProject approval requirements (what constitutes success, who decides the project is successful, who approves the project); project exit criteria (the conditions to be met in order to close or cancel the project or phase)

Each of these items is a starting point for later work. The purpose and success criteria guide scope, quality and closing. The high-level project description, boundaries and key deliverables are the starting point of scope planning. The milestones and preapproved funding set the limits of schedule and cost. The key stakeholder list goes to stakeholder management and communications planning. Approval requirements and exit criteria run through governance and phase decisions: a phase gate checks whether the intended outcomes or exit criteria have been met and decides whether to continue, pause or end; and at Close Project or Phase they are used again to check "did we succeed?" and "can we stop?".

Figure 1 Inputs, outputs and downstream uses of the project charter

Using the charter: who issues it and who takes part

The charter is issued by the project initiator or sponsor. The project manager may take part in developing it but cannot issue it. The Eighth Edition also says that the project charter can be developed by the sponsor or the project manager in collaboration with the initiating entity, allowing the project manager to gain a better understanding of the project's purpose, objectives and expected benefits, and facilitating efficient allocation of resources. So the project manager should be identified and assigned as early as possible, ideally during the development of the charter and always before planning begins.

The most direct use of the charter is to establish the project manager's authority. When a functional department will not release people, or other departments are uncooperative, the project manager produces the approved charter and shows who approved the project, who the project manager is, and how funding and resources are arranged. Settling a dispute with a document is far more effective than explaining again and again how important the project is.

Example

PMLyceum took on the renovation of the paint shop at a bicycle factory. The project manager needed to borrow two inspectors from the quality section, and the section chief said, "We were never notified about your project." The project manager did not argue about how urgent the project was. Instead she handed over the issued charter: the sponsor was the vice president of production, the project manager's authority explicitly covered coordinating people from the quality and purchasing sections, the preapproved budget was $90,000, and the success criterion was a first-pass paint yield of 97%. The section chief read it and assigned people that same day.

Worked examples

Example 1 The sponsor says a small project does not need a charter

Question 1Example

A project manager is assigned to a new sales promotion project. The sponsor hands over an approved project concept document and a draft plan that list the scope, business needs, deliverables and stakeholders, but do not give the project manager any authority to use organizational resources. The sponsor says the project is small and simple and that no project charter needs to be prepared. What should the project manager do?

Show answer and explanation

Correct answer: C

The sponsor hands over an approved concept document and a draft plan (with nothing authorizing the project manager) and says the project is small and needs no charter. The question asks what the project manager should do now.

The key signal is “no charter needs to be prepared”. The Eighth Edition notes that authorization is typically, but not always, done through a project charter. The charter also records the high-level scope and objectives, whereas this document lists scope, business needs, deliverables and stakeholders; it does not authorize the project manager, so it cannot replace a formal authorization such as a charter, and a small project is not exempt from authorization. When the sponsor takes a different view, the project manager’s first step is to explain to the sponsor what the charter is for and why it is needed, so that the decision maker can reconsider once informed. The answer is C.

Why the other options are wrong

  • A. Asking peers goes around the real decision maker. Whether to have a charter is something for the project manager and sponsor to clarify between themselves, and peers’ opinions cannot decide it.
  • B. The charter is approved and issued by the sponsor. Drafting one and handing it over before the disagreement is cleared up is acting first and talking later, and only puts you in a weaker position.
  • D. The document contains the scope, business needs and deliverables, but it still gives no basis for authority. Agreeing outright means giving up the project manager’s formal authority.

Key takeaway When the sponsor says no charter is needed, first clarify what the charter’s authorizing role is. Neither accept it nor work around it.

Variation If the sponsor agrees to a charter but cannot sign it for a long time, first check who the charter lists as “other persons authorizing the charter” and have that person approve. If the question asks who issues the charter, the answer is the sponsor or initiator.

Something wrong with this question?

Report an issue with this question

Example 2 What to show when your authority to use resources is questioned

Question 2Example

Development of a household appliance is complete and the product is about to enter the verification phase. The project manager is negotiating to borrow test staff from the quality department, but the head of that department insists the project manager has no authority to assign people from the department. What should the project manager show?

Show answer and explanation

Correct answer: D

After product development, the project is entering verification. The project manager asks the quality department for test staff, and the department head questions whether the project manager has authority to assign them. The question asks what to show.

The key point is “no authority to assign”. The problem is authority, not the number of people needed or how to communicate. The charter is issued by the sponsor, authorizes the project manager to use organizational resources, and states the project manager’s responsibility and authority level. Showing the charter answers the challenge directly. The other documents each have their uses, but none of them is a document that grants authority. This is the biggest difference between the charter and the various plans, and the standard way to approach this type of question. The answer is D.

Why the other options are wrong

  • A. The communications management plan sets out how information is passed along. It cannot show who has the authority to assign people.
  • B. The resource management plan covers how resources are estimated, acquired and managed. It is a method for doing the work once authorized, and it grants no authority itself, so the other side has no obligation to release people because of it.
  • C. Written resource requirements answer “how many people are needed”, but the department head is questioning “whether you have the right to ask”. This document cannot settle an authority question.

Key takeaway When your authority to mobilize resources is questioned, show the charter.

Variation If the department accepts your authority and questions only the headcount and the start date, use the resource requirements and the schedule to negotiate. If the people still do not arrive, escalate to the sponsor according to the escalation path.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A signed contract, a customer's urging, or a sponsor saying "just get started" is not authorization. Without a project charter or a similar formal authorization document, the project manager has no provable formal authority and should first have the sponsor complete the formal authorization.
  • When the sponsor says the project is small and needs no charter, first explain to the sponsor why the charter is necessary. Do not simply accept it, do not work around it yourself, and certainly do not issue a charter without the sponsor's approval. (The project manager may draft it in collaboration with the initiating entity, but the authorization must be issued by the sponsor or initiator.)
  • If you find after the charter is approved that a required budget was left out, do not cut other work on your own to fill the gap, and do not start work and sort it out later. Discuss it with the sponsor and ask for a review.
  • When the sponsor cannot sign, confirm and contact an alternate person with formal approval authority according to the organization's governance arrangements (the charter lists the name and authority of the sponsor or other approving persons). Do not start project work before formal authorization is obtained. Common exam practice is to find the alternate approver rather than stop work.
  • The charter holds only high-level information. Detailed scope, schedule and cost live in the project management plan, and the plan cannot replace the charter.

Key takeaways

  1. The charter does three things: it formally approves the project, records the assigned project manager with responsibility and authority, and authorizes the project manager to use organizational resources.
  2. The charter is issued by the sponsor (or the initiator). The project manager may help develop it and should be assigned as early as possible.
  3. Charter content falls into five categories: purpose and objectives, scope and schedule, funding, people and approval, approval and exit. Preapproved funding, approval requirements and exit criteria are the items most likely to be tested; acceptance criteria and exclusions belong to the project scope statement (Table 4-1).
  4. On a cross-organization project, the contract governs between organizations and the charter is used inside each organization.
  5. When your authority to move resources is questioned, show the charter; a gap in the charter is settled with whoever approved it.

Lesson 2

Inputs to Initiating: Business Documents and Agreements

Lesson video

Lesson overview

A charter is not written out of thin air. Before it is developed, a set of documents is already in hand: the business case that says why the project should be done, the benefits management plan that says how benefits will be realized, the contract between customer and company, and the external environment and the organization's existing assets that no project can avoid. This lesson covers what these four kinds of input are and who maintains them, and two rules that come up again and again in the exam: the project manager does not usually edit business documents on their own, and on a cross-organization project each organization uses a charter to establish its internal agreements, with the charter issued by that organization's project initiator or sponsor. The previous lesson covered the charter itself; the next covers the thing the charter most needs everyone to agree on: the common vision.

Four kinds of input

The Initiate Project or Phase process has four kinds of input: business documents, agreements, enterprise environmental factors and organizational process assets. Business documents means the business case and the benefits management plan.

A business case is a documented economic feasibility study used to establish validity of the benefits to be delivered by a portfolio component, program, or project. The business case helps to define a selected component that is lacking sufficient explanation and that is used as a basis for the authorization of further project management activities. It lists the objectives and reasons for project initiation, and at the end of the project it can be used to measure project success against the project objectives. At its core it is a decision document: it tells you whether the investment is worthwhile.

The benefits management plan is the documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a program or project. It specifies how and when the project's benefits will be delivered and establishes the mechanisms for measuring them. The plan should describe the key elements of the benefits, which may include target benefits, strategic alignment, the timeframe for realizing benefits, the benefits owner, metrics, and assumptions and risks.

Both documents are developed before the project is initiated, and both still need to be reviewed periodically. The sponsor is generally accountable for developing and maintaining the business case; the project manager provides recommendations and oversight, and makes sure the success criteria in the business case, the project management plan, the project charter and the benefits management plan are aligned with one another and with organizational objectives.

Agreements are any document or communication that defines the initial intentions of a project. These agreements can take the form of a contract, service-level agreement (SLA), memorandum of understanding (MOU), letters of agreement, verbal agreement, purchase order, email, etc.

Enterprise environmental factors are conditions, not under the immediate control of the team, that influence, constrain, or direct the project. Organizational process assets are plans, processes, policies, procedures, regulations, and knowledge bases specific to and used by the performing organization. When an organization changes from a functional structure to a matrix structure, that is an internal enterprise environmental factor: a condition outside the project team's immediate control. It is an input and not something the project produces.

How the inputs shape the charter

Rule one: business documents are not project documents, and the project manager cannot update or modify them directly but can only make recommendations (common exam practice; the Eighth Edition says the business case is typically developed and maintained by the sponsor, with the project manager providing recommendations and oversight, and keeping the documents aligned together with the sponsor). When you receive an old business case, the project manager's first step is to review whether its conclusions still apply to the current project. If in doubt, make a recommendation to the sponsor, who is responsible for revising it. This is entirely different from project documents: for documents such as the assumption log and the issue log, the project manager can maintain them directly.

Rule two: the business case is what you use to elaborate the charter, because it provides the objectives, the justification and the way success is measured. Plans and baselines come after the charter, so they cannot be used the other way round to fill in the charter.

Rule three: a contract and a charter are two different layers. When a contractor accepts a customer's project, the contract binds the two organizations. The project manager is an employee of the contracting company, and the charter is issued by the project initiator or sponsor in the project manager's own organization, not by the customer. The contract establishes the agreement between organizations, and charters establish the internal agreements within each organization. After the contract is signed, the project manager's next step is to complete the charter with the sponsor in their own organization, and only then to plan.

Figure 1 The four kinds of input to initiating, and the outputs of the charter

Example

A project manager at a logistics company was assigned to push forward a "cold storage temperature monitoring upgrade" project. The sponsor handed over a business case written eighteen months earlier, in which the estimated unit prices and customer numbers differed considerably from the present. The project manager did not edit the document, and did not write the charter directly from it. Instead, she listed the three assumptions in the case that were out of date and took the list to the sponsor: "Do these still hold? Should the success criteria be adjusted?" Only after the sponsor revised the business case were the charter's objectives and budget finalized.

Worked examples

Example 1 Receiving a business case from two years ago

Question 1Example

A project manager has just been appointed to lead a new product project and receives a business case completed by someone else two years ago. She is ready to start the project. What should she do FIRST?

Show answer and explanation

Correct answer: B

The project manager has just been appointed to lead a new product project and holds a business case completed by someone else two years ago. The project is in initiating. The question asks what to do first.

“Two years ago” and “completed by someone else” are the core information: the business case is an important input to initiating, but its currency is in doubt and it cannot be taken at face value. First review its content and conclusions to see whether they still apply to the current project, and then move on to the charter on that basis. The Eighth Edition classes the business case as a business document, not a project document, typically produced outside the project and before it is initiated. The Eighth Edition says the sponsor is generally accountable for developing and maintaining the project’s business case; common exam practice is that the project manager reviews business documents and makes recommendations rather than revising them personally. The answer is B.

Why the other options are wrong

  • A. Preparing the charter without a review would carry outdated objectives, assumptions and success criteria into the charter.
  • C. The stem says she has been “appointed to lead” the project. Her appointment is not the urgent matter now, and the review does not have to wait for it.
  • D. Review is right, but “revise” is wrong: the Eighth Edition classes the business case as a business document and not a project document, and by common exam practice the project manager who finds a problem makes a recommendation to the sponsor and does not revise it personally.

Key takeaway On receiving an old business case, first review whether it still applies; if there are problems, make recommendations and do not edit it yourself.

Variation If what has to be changed is an outdated entry in the assumption log, that is a project document and the project manager can update it directly. If the review shows the business case is still valid, use it directly to elaborate the charter.

Something wrong with this question?

Report an issue with this question

Example 2 Who issues the charter on an outsourced project

Question 2Example

A software outsourcing company takes on the development of a checkout system for a supermarket chain, and the project manager is an employee of the outsourcing company. Who should issue this project manager’s project charter?

Show answer and explanation

Correct answer: C

A software outsourcing company takes on the checkout system development for a supermarket chain, and the project manager is an employee of the outsourcing company. The question asks who issues the project manager’s charter.

The core information here is that “the project manager is an employee of the outsourcing company”. In a cross-corporate project, a contract establishes the agreement between the two organizations, while the charter is used inside each organization to ensure the contractual obligations are fulfilled. The project manager’s authority comes from authorization in his or her own organization, so the charter is issued by the outsourcing company’s sponsor. Keep the two layers apart: the contract makes the two companies answerable to each other, and the charter gives the project manager the authority to mobilize resources inside their own company. Each governs one layer and neither replaces the other. The answer is C.

Why the other options are wrong

  • A. The supermarket’s sponsor has a contractual relationship with the outsourcing company and does not authorize the project manager inside the outsourcing company.
  • B. The stem says only that this is a functional manager at the outsourcing company, not that the person also acts as the project initiator or sponsor. A functional manager manages departmental resources, and that status alone does not give the power to approve a project or issue a charter.
  • D. The supermarket’s functional manager is outside the outsourcing company’s authorization system and has no authority to issue the charter.

Key takeaway The contract governs between organizations; the charter is issued by the sponsor in the project manager’s own organization.

Variation If the project manager were an employee of the supermarket, the charter would be issued by the supermarket’s sponsor. If asked what the project manager does next after the contract is signed, the answer is to complete the charter first with the sponsor in his or her own organization.

Something wrong with this question?

Report an issue with this question

Common traps

Business documents and project documents

Business documents (business case, benefits management plan): created before initiation. The business case is typically developed and maintained by the sponsor; developing and maintaining the benefits management plan is an iterative activity, and the project manager and sponsor keep the related documents aligned. The project manager provides recommendations and oversight and does not usually edit business documents on their own (common exam practice).

Project documents (assumption log, issue log, risk register and so on): updated continuously as the project advances, and maintained directly by the project team.

Common trap

  • Treating the business case as a planning document you can casually edit is the most common mistake. When the project manager finds a problem, make a recommendation and do not revise it directly.
  • A contract and a charter cannot replace each other: the customer is not the sponsor of a contractor's project manager.
  • Enterprise environmental factors are given conditions that the project team cannot directly control but that influence, constrain or direct the project, and they can come from inside or outside the organization. A reorganization, the market and regulations all count. The organization's existing templates and historical information are organizational process assets.
  • The business case comes before the charter. Do not use plans and baselines to fill in the charter.

Key takeaways

  1. There are four kinds of input to initiating: business documents (business case, benefits management plan), agreements, enterprise environmental factors and organizational process assets.
  2. The business case is an economic feasibility study that says why to do the project and how success will be measured; the benefits management plan says when benefits will be delivered and how they will be measured.
  3. The business case is typically developed and maintained by the sponsor, with the project manager providing recommendations and oversight; the benefits management plan is developed and maintained iteratively, and the project manager and sponsor together make sure it stays consistent with the charter, the project management plan and other documents.
  4. The project manager makes sure the success criteria in the various documents are aligned with one another and with organizational objectives.
  5. Cross-organization projects: the contract establishes the agreement between organizations, and the charter establishes the internal agreement in each organization, issued by the initiator or sponsor of the project manager's own organization.

Lesson 3

Shared Vision

Lesson video

Lesson overview

The first task in the People domain of the exam content outline is "Develop a common vision". It sits in the charter chapter because a vision is best formed during initiating and can be written into the charter (an adaptive project can also use a concise vision statement as a lightweight charter). Questions on this task are scenario-based, and the answers turn on four things: gain consensus, drive consensus, keep the vision current, and analyze the root causes of misunderstandings. This lesson first covers what a vision is and what goes in it, then, by those four things, what to do in different situations. The previous lesson covered business documents; the next covers the assumption log and the adaptive charter.

What a vision is and why it must be shared

The Eighth Edition describes the project vision this way: it summarizes the project's purpose clearly and succinctly, describes a realistic, attractive view of the future project outcomes, and is a powerful motivational tool. A common vision helps keep people pulling in the same direction. When a team is immersed in the details of everyday work, a clear understanding of the end goal can help guide local decisions toward the desired project outcome.

A vision is best formed during initiating. Involving the sponsor, customer and other key stakeholders then makes it easier to reach a shared understanding of the success criteria, and also helps build agreement on the deliverables and raise satisfaction. When the vision is written into the charter, it becomes part of the formal authorizing document and gives later plans and decisions something to be checked against. A vision can also be a separate artifact, or in adaptive projects serve as a lightweight charter.

A vision developed collaboratively between project team members and key stakeholders should answer four questions: What is the project purpose? What defines successful project work? How will the future be better when the project outcomes are delivered? How will the project team know that it is drifting from the vision? Note the first two. A project vision holds the purpose and the definition of project success (when it goes into the charter, the project objectives in the charter should be measurable and list related success criteria). It does not hold the team structure or a day-by-day detailed schedule; those belong to the plan. Separately, the term "vision statement" in the PMBOK Guide glossary refers specifically to a summarized, high-level description of the expectations for a product (target market, users, major benefits, and what differentiates the product from others in the market). It is about the product and complements the project vision described above; the two are not the same document under two names.

A good vision is clear, concise and actionable, and it does four things: it summarizes the project with a powerful phrase or short description; it describes the best achievable outcome; it creates a common, cohesive picture in team members' minds; and it inspires passion for the outcome. In adaptive projects an "elevator pitch" is often used to practice this conciseness: in one minute, say who uses it, what problem it solves and how it differs from other solutions. A vision statement three pages long that nobody remembers has lost its purpose.

The four enablers of the vision task

1. Gain consensus. The vision must be understood and accepted by key stakeholders, who must also be willing to put in effort. When the sponsor and the customer disagree about the project's purpose or main deliverables, the charter cannot move forward. The project manager should call a meeting and use facilitation techniques to help both sides reach consensus on the purpose and the deliverables. The answer is not to ask the sponsor to decide quickly, and not to change the contract terms first.

2. Drive consensus. Consensus is not action. If the vision briefing is over but the team still schedules tasks against the old goals, the vision has not landed. The project manager should check how well the briefing worked and turn the vision into action plans for each department, built into daily arrangements. To get members truly invested, help everyone understand the value of the vision and then design the path to it together; this works better than forcing compliance.

3. Keep it current. The vision must be checked against regularly and not left on a shelf once written. Bring it up proactively at phase-gate reviews and important decisions, and use it to correct course when the work drifts. When there is a major change in strategic direction, the market, regulations or technology, when pilot feedback shows that the value proposition is not accepted by the market, or when another material change may invalidate the project's purpose or intended outcomes, reassess the vision with stakeholders and update it if needed. Performance deviations such as a small cost fluctuation or being ahead of schedule do not trigger a vision update. In adaptive projects, after the vision changes, also align the terms used by all parties so that things do not get more confused with each change.

4. Analyze the root causes of misunderstandings. When a key stakeholder says "what you are building is not what I want", or someone strongly opposes the vision, communicate first and check whether that person's understanding of the vision has drifted. Then judge whether the need has really changed or the two sides understand the same sentence differently. When survey results show customer-side agreement far higher than the internal team's, likewise find the cause first and then build consensus in a targeted way. The root cause is found by talking in depth with the person who disagrees, not by guessing.

Example

On a county hospital's appointment-booking mobile app project, in the third month the head of outpatient services told the project manager: "What I want is shorter lines for older patients, but what you are building is features for young people." The project manager did not change the scope right away. She arranged for the head and the sponsor to go back to the vision statement in the charter and read it sentence by sentence. It said "halve on-site queuing time at peak visiting hours", and the head had understood "queuing" to mean only the geriatric clinic. After checking, it turned out to be a difference in understanding and not a new requirement. The three of them wrote out their shared understanding of "queuing" explicitly, stating which clinics and which patient groups it covers, recorded that shared understanding and told the team, and added no features. If this changes the wording of the charter, first assess the impact through the project's formal change process and then obtain the sponsor's approval through the governance and change mechanisms. If it also affects a project baseline, process it through Assess and Implement Changes and update and implement it only after approval. Conversely, had the check shown that what the head wanted was telephone booking, which was truly not in the charter, that would be a different situation, a new requirement: first assess the impact on requirements and scope, approve it through the project's change mechanism, then update the requirements, scope and the relevant parts of the charter, and tell the team.

Worked examples

Example 1 A key stakeholder says "this is not what I wanted"

Question 1Example

After the project enters the execution stage, a key stakeholder tells the project manager that what the team is delivering is not the product he wants. What should the project manager do FIRST?

Show answer and explanation

Correct answer: A

After the project enters the execution stage, a key stakeholder says the team is delivering a product that is not what he wants. The question asks what the project manager should do first.

“Not what I wanted” has two possible readings: the need has really changed, or the two sides understand the same sentence of the vision differently. Until that is clear, any action lacks a basis. So first talk with him and check whether the two sides’ understanding of the vision and expectations has drifted, find the point of disagreement, and then decide whether to clarify, update the vision or go through change. Verifying first also gives whatever decision follows (clarify, update the vision or go through change) a basis, rather than reacting on one remark from the other side. The answer is A.

Why the other options are wrong

  • B. Changing the charter objectives to accommodate him without verification has no basis, and changing the charter requires the sponsor’s approval. It may make the vision get more muddled with each change.
  • C. Stopping work is costly, and asking the other side to confirm all requirements in writing cannot resolve a difference in understanding.
  • D. Showing progress data can only prove that work is following the plan. It cannot answer whether it is the right thing being built.

Key takeaway When someone says “you built the wrong thing”, first check whether their understanding of the vision has drifted.

Variation If verification shows the need has indeed changed, handle it through the change mechanism of the chosen development approach (a predictive project assesses it through the formal change process; an adaptive project normally adds it to the backlog and assesses the impact). If it is a difference in understanding, use meetings and facilitation to reach agreement again and align the wording that everyone uses.

Something wrong with this question?

Report an issue with this question

Example 2 What kind of change requires going back to check the vision

Question 2Example

A new-energy battery project is already in execution. Which of the following four changes should MOST prompt the project manager to go back and check whether the project vision still holds?

Show answer and explanation

Correct answer: D

The new-energy battery project is in execution. The question asks which of the four changes should most prompt the project manager to go back and check the vision.

A vision has to serve the organization’s strategy, and it describes the project’s purpose and future outcomes. When the company’s strategic direction changes, the project’s link to strategy changes with it, and the project’s purpose and success criteria may change too, so the vision needs to be looked at again. The other three are the project’s internal performance or everyday improvement and do not touch the project’s purpose. The test for whether to revisit the vision is “could the project’s purpose change?”, not “is performance good or bad”: cost, schedule and improvement suggestions are internal performance, to be handled by their own management processes. The answer is D.

Why the other options are wrong

  • A. A slight overrun that has not crossed the threshold is a cost performance matter, handled through cost management.
  • B. A suggested process improvement is everyday continuous improvement and does not change the project’s purpose or success criteria.
  • C. Completing the stage two weeks early is a performance result and does not show whether the vision has become outdated.

Key takeaway When major changes in strategy, market, regulation or technology could invalidate the project’s purpose or intended outcomes, check the vision again.

Variation If it were changed to “pilot feedback shows the core value proposition is not accepted by the market”, the vision again has to be reassessed with stakeholders. If it were only a small cost fluctuation in one month, it does not trigger a check.

Something wrong with this question?

Report an issue with this question

Common traps

Vision and plan

Vision: states the purpose, the success criteria and the future improvement; it is short, everyone can remember it, and it can be updated as strategy changes.

Plan: states tasks, schedule, resources and team structure, and is detailed. A predictive project usually manages change against the approved scope, schedule and cost baselines, while an adaptive project keeps refining and adjusting the plan through the backlog and iteration planning.

Common trap

  • A vision is not a detailed plan. If the vision is unclear, do not replace it with a longer document.
  • A vision is not text you write and shelve. It needs to be checked against repeatedly at key points.
  • When someone challenges it, first check whether their understanding has drifted. Do not immediately change the charter objectives to please them, do not stop work and demand written confirmation of every requirement, and do not argue with schedule data.
  • A small cost overrun, being ahead of schedule, or a member's suggestion to improve a procedure normally does not trigger a vision update when it does not affect the project's purpose. A major change in strategy, market, regulation or technology, pilot feedback that negates the value proposition, or another material change that may invalidate the purpose or intended outcomes should prompt reassessment with stakeholders and an update if needed.
  • When visions conflict, do not first change the contract terms or ask the sponsor to settle it quickly. First use meetings and facilitation to find consensus.

Key takeaways

  1. A vision summarizes the project purpose clearly and succinctly and describes a realistic, attractive picture of the outcome; once written into the charter it has formal standing.
  2. A vision answers four questions: purpose, definition of success, the future improvement, and how to tell if you are drifting. It holds no schedule or team structure.
  3. The four enablers of the task: gain consensus (meeting facilitation), drive consensus (turn it into action), keep it current (check regularly, update when needed), analyze the root causes of misunderstandings (communicate and verify first).
  4. When you get "you built the wrong thing" feedback, first verify understanding of the vision and do not change the charter first.
  5. Bring up the vision at phase gates and important decisions, and check against it regularly.

Lesson 4

The Assumption Log, Initiating Tools and the Adaptive Charter

Lesson video

Lesson overview

Besides the charter, Initiate Project or Phase produces a document that is often overlooked: the assumption log. This lesson first covers what goes into the assumption log, how it is updated, and what the first step is when a new constraint is found. It then covers the tools and techniques used in initiating, with the focus on facilitation and the project canvas. Finally it covers how an adaptive project's charter differs from a predictive one, and how the charter and team authority work together in a hybrid project. Every exam point here is quite specific. The previous lesson covered the vision; the next covers what to do first when you take over a project.

The assumption log

The assumption log is a project document used to record all assumptions and constraints throughout the project. It is created at this step along with the charter. High-level (strategic and operational) constraints are normally identified in the business case before the project is initiated and then flow into the project charter. Lower-level activity and task assumptions are generated throughout the project, such as when defining technical specifications, estimates, schedule activities and risks.

Assumptions and constraints are easy to confuse. An assumption is a premise treated as true before it has been verified, and it is often optimistic: "the supplier will certainly deliver on time" or "the key engineer will be available by then". A constraint is a limitation the project must observe, such as a regulatory requirement, a fixed deadline or a budget ceiling, and it is not up for negotiation. When an assumption proves unreliable, it becomes an important source of risk. Constraints set the boundaries, and planning can only find ways within them.

The assumption log is updated continuously: new assumptions and constraints may be added, and the status of existing ones may be updated or closed out. When an assumption is confirmed, its status is changed to closed. When it is overturned, assess the impact and initiate the appropriate issue, risk, or change handling. The outputs of several processes, such as Manage Project Execution, include updates to it. It is a project document that the project manager can maintain directly, which is different from business documents.

When a project manager finds a new constraint, for example that outdoor work is limited by the weather, the usual step is to record it promptly in the assumption log, and then decide on that basis whether to analyze, communicate, escalate or adjust the plan; the order depends on the scenario (common exam practice: the first step is to record it in the assumption log, and then develop the implementation approach from it). By the same logic, before you develop the implementation approach, identify the assumptions and constraints clearly, so that later estimates and plans are not built on unclear premises.

Tools and techniques used in initiating

The tools and techniques used in Initiate Project or Phase are grouped below by purpose.

ToolKey points
Expert judgmentJudgment provided by any group or person with specialized education, knowledge, skill, experience or training
BrainstormingA group activity led by a facilitator that encourages free contribution, used to identify a list of ideas in a short period of time
Focus groupsBrings together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product, service or result
InterviewsEliciting information from stakeholders by talking to them directly; especially useful for obtaining confidential information
Conflict management, facilitationFacilitation helps ensure effective participation, mutual understanding, that all contributions are considered, and that conclusions or results have full buy-in according to the decision process established for the project
Meetings and meeting managementDistribute an agenda and state the objectives; start and end on time; invite the right participants; stay on topic; manage expectations, issues and conflicts; record action items and owners
Responsibility assignment matrixOne of the tools of Initiate Project or Phase in the Eighth Edition (Figure 2-3); a grid that shows the project resources assigned to each work package and the connections between work packages or activities and team members, used to clarify responsibilities. The charter itself states the project manager's responsibility and authority level and the approval requirements
Project canvasA visual tool on one page that brings together purpose, scope, milestones, stakeholders, resources, risks, lessons learned and more, giving a picture of the whole project

"Which tool to use" depends on what the stem is trying to solve. When the information in the charter is inconsistent and the sponsor refuses to approve for that reason, the tool is facilitation: bring the parties together, discuss the specific differences until consensus is reached, and resubmit. To collect sensitive information, use interviews. To hear the expectations of a group of selected stakeholders, use a focus group. To build up many ideas in a short time, use brainstorming.

The project canvas is like a panorama of the project: it puts the key points on one page, which helps you spot gaps early and lets the team and stakeholders discuss around the same picture. It has roughly three columns. The left column has purpose, scope and requirements, milestones and project phases. The middle column has objectives, scope and deliverables, scope exclusions, stakeholders and users, and the team. The right column has project approval requirements (what constitutes success, who decides if it is successful, who approves the project), assumptions and constraints, resources, risks and lessons learned. Common exam practice is to recognize the project canvas and know what it is used for.

The adaptive charter, and hybrid projects

The charter of a predictive project usually contains the full content covered earlier, and the project is formally established once it is approved. The charter of an adaptive project is more flexible. It can be a concise one-page worksheet or a vision statement, or a moderately detailed document, designed to provide just enough structure while allowing for evolving requirements and priorities. An adaptive project charter typically focuses on answering a subset or all of the following key questions: Why is the project being undertaken? Who will be engaged? What is this project about? Where will it occur? When will it start and end? How will it be carried out? Who is the customer?

In a hybrid project, the charter sets the boundaries, and the team self-organizes inside them. When a sponsor wants to keep the governance role of the charter but also give an agile team room to make decisions, the way to do it is to use the charter to set the goals, scope boundary, budget and approval requirements, and to leave how the work is done inside those boundaries to the team. If you drop the charter without putting an equivalent authorization and governance document in its place, you lose clear authorization and governance boundaries.

Predictive and adaptive charters

Predictive: a complete charter, with objectives, success criteria, milestones, preapproved funding, approval requirements and exit criteria; the project is formally established once it is approved.

Adaptive: a lightweight charter, often a one-page worksheet or a vision statement. It may be built around some or all of the seven guiding questions (why, who, what, where, when, how, and who the customer is), is tailored to the iterative and incremental nature of the work, and leaves room for requirements and priorities to keep evolving. If the charter itself needs to change, approval is still obtained as governance requires.

Example

A mobile preordering app for a bakery chain used a hybrid approach: the store system integration was managed as predictive, and the front-end iterations were done as adaptive. The charter was a page and a half. It set the objective (online orders making up 15% of orders three months after launch), a budget ceiling of $80,000, the go-live deadline, the approvers, and one boundary: changes involving payment and membership data must be reported to the sponsor first. Inside that boundary the front-end team decided for itself every two weeks what to build. The project manager recorded three assumptions in the assumption log, and one of them, "the stores' network is stable", was verified in the first week and closed.

Worked examples

Example 1 A new constraint is found: what is the first step?

Question 1Example

An outdoor installation project for a photovoltaic power station must be worked in the open air, so the weather becomes a constraint on the project. What should the project manager do FIRST?

Show answer and explanation

Correct answer: A

An outdoor installation project for a photovoltaic power station must work in the open air, and the weather becomes a constraint. The question asks what the project manager should do first.

The key point is that the stem has identified weather as a constraint. The assumption log records assumptions and constraints throughout the project life cycle; among the choices, entering this constraint there is the most appropriate way to establish a shared, traceable planning premise. Recording does not replace impact assessment: depending on urgency, the project manager should also assess the impact and adjust the approach, and these activities may be carried out together. The project manager can maintain the assumption log directly. The answer is A.

Why the other options are wrong

  • B. Recording is within the project manager’s authority and does not require telling the sponsor first. Whether to inform the sponsor depends on the impact assessment.
  • C. The stem presents no specific problem that requires subject matter experts. Calling an expert meeting before clarifying what needs analysis is poorly targeted.
  • D. The stem does not say that the risk management plan contains a weather provision, and merely reviewing that plan does not replace documenting and assessing the identified constraint.

Key takeaway When you identify an assumption or constraint, record it in the assumption log and assess its impact as appropriate.

Variation If the weather has already caused a stoppage and affects the schedule, that is an issue that has occurred and goes in the issue log. If it is only an adverse event that may occur, it goes in the risk register.

Something wrong with this question?

Report an issue with this question

Example 2 How the charter and team authority are coordinated in a hybrid project

Question 2Example

On a hybrid project at one company, some teams work in an agile way. The sponsor wants to keep the governance role of the project charter while also giving the agile teams ample room to make decisions. How should the project manager reconcile the charter with the agile teams’ authority?

Show answer and explanation

Correct answer: D

On a hybrid project, some teams use agile. The sponsor wants to keep the charter’s governance role and also give the agile teams ample room to decide. The question asks how to reconcile the two.

The charter’s job is to give formal authorization and set governance requirements, and the agile teams need to decide for themselves within boundaries. The way to join the two is for the charter to set the governance boundaries, such as objectives, scope boundary, budget and approval requirements, with teams self-organizing within those boundaries. This keeps authorization and governance without squeezing the team’s room. In choosing, hold on to two phrases: keep the governance role, and leave room for decisions. Only “boundaries plus self-organization” satisfies both; each of the other options satisfies one and loses the other. The answer is D.

Why the other options are wrong

  • A. Cancelling the charter loses formal authorization and the governance boundaries, and does not meet the sponsor’s wish to keep the governance role.
  • B. A charter that covers only ways of working drops the governance content such as objectives, approvals and exit criteria.
  • C. A charter written as a detailed plan controls everything even inside the boundaries, leaving the team no room to decide, which goes against agile practice.

Key takeaway Hybrid projects: the charter sets the boundaries, and the team self-organizes within them.

Variation A purely adaptive project’s charter can be simplified to a one-page worksheet or a vision statement that answers questions such as why, who and what, and it still keeps its authorizing role.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The assumption log is a project document, not a business document. Entries can be added, updated or closed during the project, and usually do not need the sponsor's approval the way the project charter does, but project governance and configuration management requirements still apply.
  • When you find a constraint, record it first. Do not first call an expert meeting, do not first tell the sponsor, and certainly do not first dig out the risk management plan.
  • Facilitation resolves differences of opinion. It does not make the decision for the sponsor. If the charter is inconsistent, use facilitation to reach consensus and then resubmit.
  • For the project canvas, you only need to recognize it and know how to use it. You do not need to memorize its boxes.

Key takeaways

  1. The assumption log records assumptions and constraints across the whole life cycle and can be added to, updated and closed. When you find a new constraint, record it in the assumption log first.
  2. An assumption is an unverified premise and a constraint is a limit that must be observed; an unreliable assumption is a source of risk.
  3. Choose tools by purpose: facilitation to reach consensus, interviews for sensitive information, focus groups for expectations, the project canvas for the whole picture.
  4. An adaptive charter is lightweight and may address some or all of seven guiding questions.
  5. Hybrid: the charter sets the governance boundaries, and the team self-organizes within them.

Lesson 5

What a Project Manager Does First When Taking Over a Project

Lesson video

Lesson overview

"The project manager takes over a project midway" is a favorite governance scenario: the predecessor has been reassigned, the charter and plan are on file, and the team and schedule have already been running for a while. These questions introduce no new concepts. They test order and judgment: first clarify the purpose, then look at the current state, then handle things through the process, and never try to rescue the project through personal judgment alone. This lesson ties together the charter, the business documents and the project management plan covered earlier into a main line of "three steps for taking over", and then lists the standard approach for common situations. The previous lesson covered the assumption log and the adaptive charter; the next chapter covers governance itself.

Three steps for taking over: purpose first, then current state, then action

When the previous project manager leaves and the new one "enthusiastically" charges ahead with the team, that is the most typical error in the exam. The first step on taking over is not to change the schedule, not to dig through the issue log, and not to assess how much more time is needed. It is to understand the purpose and objectives of the project. The purpose and objectives are in the charter, so review the charter first and confirm the project's objectives and deliverables. The common exam practice: where nothing more urgent is going on (such as an accident or a compliance problem) and you need to build an overall picture, first review the charter to confirm the purpose, objectives and authorization, and then consult the project management plan and the performance information.

The second step is to look at the current state and understand how the work is meant to be done. Review the project management plan to understand the content, the method and the division of work, and then compare it with the latest performance data to see how far actual differs from plan. The division of labor between the two documents is clear: the charter answers "why are we doing this, and what counts as success", and the project management plan answers "how are we going to do it". If the question asks "how do you learn the overall arrangements of the project", the answer is the plan; if it asks about "the project's objectives and deliverables", the answer is the charter. If the options include both "review the charter" and "change the schedule" or "determine whether more time is needed", pick the former.

Only the third step is to act: handle the problems you found through the process. If you find a gap in the controlled plan, baselines or charter, contact the appropriate approver or responsible party. If you find a violation, verify it and then submit it to the responsible party or governance level according to the escalation guidelines. If performance deviates, report it honestly, analyze the variance and judge whether corrective action is needed. If a controlled plan or baseline has to change, go through the change process.

Common situations after taking over

The table below organizes the common takeover situations. When you read a situation, first judge whether the problem is a "charter gap", a "violation", a "performance deviation" or a "team state" issue, and then apply the matching approach.

SituationStandard approachDo not do this
The charter left out budget required to achieve the outcomeGo to the sponsor who approved the charter and ask for a re-approvalCut other deliverables to fill the gap; start work and sort it out later; only log it in the risk register
The predecessor used a procurement practice very different from organizational procedureRecord and verify it, then submit it to the responsible party according to organizational governance, procurement compliance and escalation guidelines; if it is beyond your authority, escalate to the sponsor or the appropriate governance levelAssign blame or fix it unilaterally
Actual performance does not match the planReport the gap to stakeholders promptly and transparentlyHide it; change the baseline on your own first
New circumstances that may affect the baseline (for example, a key material cannot arrive)First assess the impact against the baseline, then decide on actionCrash the schedule by feel or change the plan outright
Requirements keep changing and the team keeps reworkingPredictive: put the change control procedure in order while lifting morale. Adaptive: manage requirements through the backlog and prioritization, and analyze the root causes of reworkReplace people; change the baseline; promise bonuses
The team lacks rhythm and members are lostFirst assess the specific reason. If direction is unclear, go back to the charter and vision to realign. If direction is clear but rhythm is missing, set short-term goals. If skills or information are lacking, use guidance, coaching, training or knowledge sharing. Recognize progress promptlyLet things drift; rush to ask for an extension
Members complain about the predecessor's decisionsBuild ground rules together and align expectationsOverturn the predecessor's decisions one by one
A dominant team member controls discussions and performance has fallenLook at the data and observe the interactions first, then address the causeReassign people straight away
Management plans and documents are lostRe-integrate and align the plans together with the team, and communicate them to key stakeholders according to the communications management planPress on regardless of the plan
A project resumes after being shelved for yearsFirst reconfirm whether the charter and business case are still valid, then identify and meet the new stakeholders to understand their expectationsReuse the old business case and estimates as they are
Only closing remains, and the predecessor left no handoffSort out the unfinished items, develop a transition plan, and complete the closing documentsClose out directly according to the original plan
Figure 1 The three-step order for taking over a project

The same logic stands behind all of these approaches: the project manager's authority comes from the charter and the governance framework, and personal opinion cannot replace process. When requirements keep changing, in a predictive project first analyze why they change and check whether change control is working, and record, assess and approve every change through the established procedure; an adaptive project manages evolving requirements through the backlog, prioritization and iteration feedback, and analyzes the root causes of rework. When the team is lost, first assess the specific reason: if direction is unclear, realign with the charter and vision; if direction is clear but rhythm is missing, use short-term goals; if skills or information are lacking, use guidance, coaching and training; and recognize progress promptly. If you disagree with a decision your predecessor made, assess what needs assessing and put through change control what needs change.

Example

At PMLyceum, a project manager took over a community pharmacy inventory system project that had been running for two months. The previous manager had been reassigned. He did not immediately schedule meetings to change the plan. He read the charter first: the purpose was to bring the stock-out rate below 3%, and the sponsor was the director of operations. He then compared the project management plan with the latest performance report and found that the rework rate had risen sharply over the past two weeks, because several pharmacy managers had made requests verbally that never went through change control. He first confirmed with the sponsor that the objective had not changed. Since the project used a predictive approach and had an established baseline, he paused further implementation of those verbal requests, assessed the impact of work already done and requests not yet implemented, processed them through change control, and required all later requests to be submitted in writing for assessment. He then set the team a small goal every two weeks and recognized it publicly when it was met.

Worked examples

Example 1 After taking over, you find the charter left out budget

Question 1Example

The project charter for a cold-chain warehouse renovation project has already been approved, and the project manager is assigned to take over afterwards. Going through the charter item by item with the team, he finds that the preapproved financial resources leave out several major costs that are essential to achieving the project’s outcome. What should the project manager do NEXT?

Show answer and explanation

Correct answer: A

The charter for the cold-chain warehouse renovation project has been approved, and the project manager is assigned afterwards. Checking against the charter, he finds that the preapproved financial resources omit several major costs essential to achieving the outcome. The question asks what to do next.

Preapproved funding is part of the charter and is approved by the sponsor. A gap in the charter means the charter is what has to change, and the power to change it lies with the approver, so the project manager should talk to the sponsor right away and ask for the budget to be re-approved. The sooner it is handled, the smaller the impact on the project. The charter and its preapproved financial resources are approved by the sponsor or another authorized person, so the correction has to be decided by the approver, and the project manager cannot adjust the funding in the charter alone. The answer is A.

Why the other options are wrong

  • B. Cutting the quality and cost of other deliverables to fill the gap, without the sponsor’s approval, is robbing Peter to pay Paul.
  • C. Starting work with a known gap just leaves the problem for later, and may cause delays or even project failure.
  • D. A budget omission is an established gap, not a “possible” risk, so it does not belong in the risk register. There is also no need to wait for the next steering committee meeting; go straight to the sponsor.

Key takeaway After taking over, when you find a gap in the charter, go directly to the sponsor who approved the charter.

Variation If the gap is in the plan and not in the charter, for example a work item missing from the schedule, first assess the impact; if a controlled item such as the schedule baseline has to change, then use the applicable change process. If what you find is a violation by your predecessor, escalate it as a key issue.

Something wrong with this question?

Report an issue with this question

Example 2 After taking over, the team is lost and lacks rhythm

Question 2Example

A project manager takes over a retail store POS upgrade project that has had nobody leading it for several weeks. The charter has already made the objectives and direction clear, but the team lacks day-to-day leadership and rhythm, and members feel lost about what to do next. What should the new project manager do?

Show answer and explanation

Correct answer: A

The project manager takes over a POS upgrade project that has had nobody leading it for several weeks. The charter has made the objectives and direction clear, but the team lacks rhythm and members feel lost. The question asks what the new project manager should do.

The charter has already stated the direction, so the team’s confusion is not about “not knowing where to go”. It is that nobody leads day to day, and the team lacks a sense of rhythm and accomplishment. The project manager should set short-term goals that are easy to reach so the team quickly sees results, and promptly recognize members who achieve them, rebuilding confidence and rhythm through results and recognition. The signal in this type of question is “the charter has already made the direction clear”: when direction is clear, the answer is not to restate the goals or to explain them again, but to address rhythm and confidence. The answer is A.

Why the other options are wrong

  • B. The direction is already clear in the charter, so having the sponsor explain it again misses the problem. A problem inside the team should be dealt with first by the project manager personally.
  • C. There is no evidence that the team can self-organize, and leaving it alone will only make things more chaotic.
  • D. Being lost is a management problem, not a schedule problem. Reporting up and asking for an extension does not address the cause.

Key takeaway When the team is lost after a takeover, rebuild rhythm and confidence with short-term goals and prompt recognition.

Variation If the cause of the confusion is that the goals themselves are unclear, go back to the charter and the vision to realign with the team. If members resent the predecessor’s decisions, build ground rules together to align expectations.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Do not try to "rescue" the project the moment you take over by changing the schedule or replacing people. First clarify the objectives.
  • A project manager cannot overturn a predecessor's decision directly because they disagree with it. Assess what needs assessing, and put through change control what needs change.
  • On finding a violation, you report it; you do not assign blame yourself. On finding a charter gap, you go to the sponsor; you do not patch it into the plan yourself or push it into the risk register (a budget omission is an established gap, not an uncertain risk).
  • A lost team is a management problem and not a schedule problem. Do not answer it with "ask for an extension".
  • After taking over, still make sure you understand the project's purpose and end point. Do not manage the project as if it were routine operations.

Key takeaways

  1. The first step in taking over is to understand the purpose and objectives: review the charter; then consult the project management plan to learn how the work is to be done; then compare with actual performance.
  2. The charter answers "why are we doing this, and what counts as success"; the project management plan answers "how are we going to do it".
  3. Gap in the charter: go to the sponsor who approved it. Violation: verify and submit to the responsible party or governance level according to the escalation guidelines. Performance mismatch: report promptly and transparently.
  4. When requirements change frequently in a predictive project, first analyze the cause and check whether change control is working, then put the procedure in order; an adaptive project manages evolving requirements through the backlog, prioritization and iteration feedback. When a team is lost, first assess the cause; use short-term goals and recognition when direction is clear but rhythm is missing.
  5. Plan documents lost: the team re-integrates and aligns the plan and shares it. Only closing left: sort out the items first and make a transition plan.

This chapter has 39 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.