Governance and Business Environment
Organizational Change
PMP · Governance and Business Environment · 3 lessons · about 34 min
Part of the free PMP video course: every lesson starts with its video →
A common way for a project to create value is to move an organization from one state to another: a new process, a new system, a new way of working. People bear the impact of change, so whether a change succeeds depends on whether they accept it. The three lessons in this chapter map to ECO Business Environment domain, Task 7 (Support organizational change). The answer pattern is consistent: when you meet resistance, first understand the cause, then communicate, train and win support.
What this chapter covers
The ECO gives Task 7 only two requirements: assess organizational culture, and evaluate the impact of organizational change on the project and determine required actions. This chapter first covers how a project moves an organization from its current state to a future state (some projects add a transition state), where resistance comes from and how to deal with it. It then covers three tools: communication, involvement and training. Finally it covers ADKAR, a widely used change model, and how to write change activities into the project plan. Almost all questions are scenario questions. In the options, forcing compliance, avoiding the problem, one-way announcements and escalating straight to someone else are almost never the answer. Keep one distinction in mind: organizational change management (which focuses on people, culture and adoption) is not the same as project change control (which evaluates and handles formal changes to documents, deliverables or baselines).
Lessons in this chapter
- Lesson 1: Projects and Organizational Change: Understanding Resistance. Current state, transition state and future state; the four sources of resistance and the emotional curve; assess culture and readiness first; what to do when you meet resistance.
- Lesson 2: Communication, Involvement and Training in Change. Help people understand the purpose first; when an organizational restructuring causes discontent, hold a meeting to explain it; listen to feedback and involve the people affected; rumors signal insufficient communication.
- Lesson 3: The ADKAR Model and the Organizational Change Plan. Awareness, Desire, Knowledge, Ability and Reinforcement, and the organizational action that matches each; what an organizational change plan contains (it is not a separate project management plan component and is a common exam term), and how it differs from the actual change management plan component, which sets up the CCB and change control; the transition period and scope.
Chapter map
The first figure shows what change is and how an individual comes to accept it. The second shows how to communicate. Study them in that order. When you see a change question, ask two things: does this action address people not understanding or not agreeing, and did the project manager assess before acting?
Study tips and practice
The answer options in change questions often include relying only on forced compliance (disciplinary action, performance appraisal, a deadline to adapt unconditionally), avoiding or delaying without good reason (pausing, shrinking the scope, waiting), one-way notices with no feedback channel (handing out manuals, sending notices, announcing an appointment), and actions that address the problem (find out the cause, explain the purpose, train and coach, listen to feedback, follow up). The first three are usually not the best answer when they bypass assessment, communication and support, but do not eliminate them solely by form: a short pause to assess or a notice used within a broader communication approach may be appropriate. Also remember three pairings: not understanding calls for communication, not knowing how calls for training and coaching, and still using the old way after go-live calls for continued follow-up.
Lesson 1
Projects and Organizational Change: Understanding Resistance
Lesson overview
ECO Business Environment domain, Task 7 is called "Support organizational change" and has only two requirements: assess organizational culture, and evaluate the impact of organizational change on the project and determine required actions. This lesson first explains why projects are tied to organizational change, then covers the most common trouble in change, which is people's resistance: where it comes from, what to assess first and what to do first when you meet it. Most questions are scenario questions. The options include several tempting moves such as forcing compliance, avoiding the problem and escalating straight away, but the answer pattern is very consistent: first understand the cause, then communicate, train and win support.
Why projects drive organizational change
PMBOK 8 lists value creation through organizational change as one way projects create value. In summary: projects, in pursuit of value, drive change in organizations. From a business perspective, a project’s purpose is to move an organization from one state to another to achieve a specific objective. Before the project begins, an organization is in its current state. The desired result of the change driven by the project is described as the future state. For some projects, this shift may involve creating a transition state where several steps are taken in a structured manner to achieve the future state. The successful completion of a project results in the organization moving to the future state and achieving value for the organization, as defined by key stakeholders.
Change management is defined as "a comprehensive, cyclic, and structured approach for transitioning individuals, groups, and organizations from a current state to a future state with intended business benefits." Along with benefits realization and value management, it belongs to the value and impact content of the Governance performance domain. PMBOK 8 also includes strategic thinking and the application of change management techniques among the competencies project professionals need.
One distinction is often confused. Change management deals with how the organization and its people transition to a new state. Change control deals with change requests to documents (including project management plan components and project documents), deliverables or baselines; approval authority is set by the project management plan or organizational procedures, and a change control board is involved where applicable. The names are close but the subjects are completely different.
You find the project will change how people work: what do you do first?
Halfway through an order processing system project, the project manager realizes that after go-live both the warehouse and customer service will work differently. The right move is to evaluate the impact of this organizational change on the project and determine the actions required. The reason is that change touches scope, schedule, resources and stakeholders; without an assessment, the later communication, training and transition arrangements have no basis. Now look at the wrong options. Compressing the scope avoids the very value the project is supposed to deliver. Handing it to the operations department forgets that the project is what drives the change. Waiting for feedback after go-live misses the chance to prepare early, and the cost of correction is higher.
Where resistance comes from
Change takes people out of their comfort zone and also shifts power and the distribution of interests: some roles are weakened and some habits are retired. So change often meets resistance, which can come from front-line staff or from middle and senior managers. There are four common causes:
- Unclear goals: people do not know why they need to change.
- No buy-in: people feel the change is imposed on them by others.
- Lack of incentive: the change brings them no benefit, or even a loss.
- Fear of losing status and interests.
The change-emotion model is a common exam term; it holds that emotions during change usually follow a sequence: at first everyone says they support it, then people begin to question it; next come refusing to change, falling morale and nostalgia for the past; if the effort goes well, people gradually discuss risks, settle the direction, rebuild the mission and complete the change. Many transformations fail by stalling at the stage of nostalgia for the past. Change also needs the support of people who hold power, so you need senior-level support, and you should assess culture, impact and readiness first, and only then arrange communication, training and other transition measures as needed. A typical exam judgment: assess culture and readiness first, and use communication and training to help people understand the purpose of the change; skills training on specific operations comes after people understand and accept the change.
Assess culture and readiness first, then act
The ECO puts "assess organizational culture" first among the Task 7 requirements. Common exam practice: readiness for change rests mainly on two things, management support and a shift in employees' awareness. When assessing, look at whether the organizational culture is open or conservative, how employees have habitually reacted to change, how the change affects work processes and roles, and whether there are enough resources and incentives. Suppose a system go-live will change how stores handle checkout and reconciliation. The first thing the project manager should do is assess the culture and learn how receptive people are. Do not simply send a go-live notice, do not jump straight to scheduling training, and do not have the project team draft new rules on its own and push them out.
When you meet resistance, what do you do?
| Situation | What to do |
|---|---|
| Front-line staff broadly resist the new process | Find the cause, then communicate, train and coach; do not discipline, do not pause indefinitely, and do not use a pilot in willing crews as a substitute for dealing with the cause of the resistance |
| Resistance comes from a department director or senior executive | Communicate proactively, learn their concerns and win their support; do not bypass them, shrink the scope or wait for them to come around |
| Members think the change is unnecessary, and this hurts the discussion | Communicate to learn their concerns and win their agreement; do not just repeat the pitch or switch to email |
| The team drags its feet on cooperating after a requirements adjustment | Learn the specific reasons and help them adapt; do not just restate that the change is approved or refuse the customer's adjustment |
| A department's rules block the change (for example a quality department refuses to accept the work because its rules do not provide for it) | Record the obstacle and ask the sponsor to step in and coordinate approval |
Example: go-live of a pharmaceutical warehouse system
A pharmaceutical distributor is replacing paper documents with a new warehouse system. The project team finds that warehouse associate Gary is leading the resistance. His biggest worry is that the system will replace his hard-earned ability to locate stock from experience and that his job will lose value. The project manager did not criticize him and did not go to the general manager. Instead, the project manager talked with him twice and found three concerns: he did not know how to use it, he feared being evaluated on it, and he feared being replaced. The project manager then arranged one-on-one training, made clear that the new role carries inventory analysis duties, and invited him to help design the pilot plan. A month later Gary was the most proficient user on his crew. Finding the cause first and then treating it is the basic path for handling resistance.
Worked examples
Example 1: Discovering that the project will change how people work
A logistics company's order processing system project is under way. The project manager realizes that after the system goes live, the way warehouse and customer service staff work will change. What should the project manager do?
Show answer and explanation
Correct answer: C
The project manager has seen that the project's result will change how the organization works. What should be done once this is noticed?
A project is meant to move an organization from its current state to a future state, and for some projects the shift can include a transition state. A change in ways of working is part of that change. Change touches scope, schedule, resources and stakeholders, so the project manager should first evaluate the impact of this organizational change on the project and then determine the actions required. The answer is C.
Why the other options are wrong
- A. Compressing the scope avoids the change, weakens the value the project is meant to deliver, and acts before assessing, so it has no basis.
- B. The project drives the change, so the project manager cannot hand it to the operations department. If the project ignores the impact of the change, the result will also be hard for people to accept.
- D. Passively waiting until after go-live means the problems have already surfaced, the cost of correction is higher, and the chance to respond early is gone.
Key takeaway A project drives organizational change. When you find the project will change how people work, evaluate the impact first, then determine the actions.
Variation If the question asks “what do you assess first when supporting organizational change”, the answer is organizational culture and readiness; specific actions such as communication and training come after the assessment.
Something wrong with this question?
Example 2: Front-line staff resist the new process
While a logistics company is implementing a change to its dispatching process, front-line dispatchers broadly resist the new process and refuse to use it. What should the project manager do?
Show answer and explanation
Correct answer: C
The project is in the rollout stage of an organizational change, and front-line staff broadly resist the new process. How should the project manager respond to this resistance?
Resistance usually comes from unclear goals, lack of buy-in, lack of incentives or fear of personal loss. Change management first finds the cause of the resistance, then helps employees through the transition with communication, training and coaching. “Broad” resistance suggests the cause most likely lies in too little communication and support for the change itself, not in individual attitudes. The order is to understand the cause first and then choose the measure that fits: if the goals are unclear, add communication; if skills are lacking, add training; if people fear losing out, listen to their concerns and support them. The answer is C.
Why the other options are wrong
- A. An indefinite pause will not make employees accept the process on their own. The cause of the resistance is still unaddressed and the change is delayed.
- B. Forcing the process through with discipline deepens resistance. Employees comply in form only and have not really accepted the new process.
- D. A pilot in some crews can be an effective strategy, but the stem shows broad resistance. D neither finds out the cause nor explains how pilot feedback would drive overall adoption, so it is less direct and less complete than C.
Key takeaway When employees resist a new process, first learn the cause, then drive the transition with communication, training and support.
Variation If the resistance comes from a department director or senior executive, switch to proactive communication, learning their concerns and winning their support; if departmental rules are the obstacle, record the obstacle and ask the sponsor to coordinate.
Something wrong with this question?
Common traps
Common trap
- Change management is not change control: the former handles the transition of people and the organization, the latter handles change requests to documents, deliverables or baselines.
- "Top-level sponsorship" means the effort will not work without senior support; it does not mean the project manager pushes every problem up to senior leaders. When the team resists, communicate first; ask the sponsor to step in when departmental rules conflict.
- Forcing compliance (discipline, appraisal), avoidance (pausing, shrinking the scope) and passive waiting are not the first choice when you meet resistance.
- Exam scenarios often treat unclear goals, no buy-in and lack of incentive as important reasons a change stalls (common exam practice); be familiar with these three.
Key takeaways
Key point
- A project moves an organization from its current state to a future state; some projects pass through a transition state, reaching the future state in several structured steps. Change management helps individuals, groups and organizations make that transition.
- When you find the project will change how people work: first evaluate the impact of the organizational change on the project, then determine the actions.
- Common causes of resistance: unclear goals, no buy-in, lack of incentive and fear of losing interests; it can come from the front line or from middle and senior management.
- To support change, assess organizational culture and readiness first (management support and a shift in employee awareness).
- When you meet resistance: learn the cause, communicate, train and win support; for rule-based obstacles, ask the sponsor to coordinate; do not force and do not avoid.
Lesson 2
Communication, Involvement and Training in Change
Lesson overview
The previous lesson covered where resistance comes from. This lesson covers the three tools a project manager uses most in change: communication, involving the people affected, and training. The shared premise of change questions is one sentence: whether a change succeeds depends on people. A technical solution may be proven, but if employees do not use it after go-live, the value is zero. The options in this lesson follow a clear pattern. Impersonal, one-way actions such as "hand out a manual", "announce an appointment" and "stress that it is inevitable" are often wrong; what helps people understand the purpose, be heard and learn the new way is right. This maps to ECO Business Environment domain, Task 7 (Support organizational change), specifically evaluating the impact of organizational change on the project and determining required actions.
Principle: put people first and help them understand the purpose
Organizational change affects people directly, so put them first and help them adapt. Specifically, when a transformation meets resistance, first assess the causes of resistance, the organizational culture and the impact of the change. Common exam practice: once you have confirmed that the root cause is that people do not understand the purpose of the change, the first step is to use training and communication so that stakeholders understand the purpose of this change, and only then discuss how to do it. Here the training is a session on why the change is needed, not hands-on skills training, which comes later. A supermarket chain with a conservative culture is digitizing its stores, and the options fall into four types:
- Bringing in an outside expert and naming that person a "change champion" only adds one supporter; it does not solve the problem of everyone else not understanding.
- Having senior leaders announce that the project manager will lead only confirms an identity and does almost nothing to reduce resistance.
- Handing out a digital transformation guide and stressing that the change is "inevitable" is one-way push communication. It makes sure the information is sent, but it cannot make sure employees receive or understand it, and it does not explain why the change is needed.
- Arranging training for stakeholders so that they understand the purpose of the change addresses the cause.
So the test-taking standard is: does this action help people understand the purpose of the change and learn more about the causes of the resistance?
An organizational restructuring causes discontent: hold a meeting, do not avoid it
The company is restructuring, and several employees are about to leave because their positions are being eliminated. The remaining team members are down and do not understand why the project is being disrupted when it is going well. The right move is to hold a team meeting and talk about the restructuring and what it means for the company. Let members voice their questions and explain the reasons clearly. Among the options, "tell them to continue as planned" ignores the emotions, "say the leadership decided and it must be carried out" neither explains nor listens, and "escalate and seek an allowance" is neither proactive nor responsive to their confusion. Watch your wording too: explain the reasons and impacts honestly, acknowledge how eliminated positions affect employees, and avoid demeaning phrases such as saying people are being "cut".
Involve the people affected and listen to feedback
Effective change communication is a complete chain: evaluate the impact of the change on work processes; communicate and train so that employees understand and learn the new way; listen to employee feedback; and avoid relying on compulsion alone (even for requirements that must be carried out, explain why and offer involvement, training and support). Shelving employee feedback "so as not to slow the pace", or setting "a deadline to adapt unconditionally", is wrong. PMBOK 8 explains that value exists only when stakeholders are understood and then guided through the change the project experiences and fosters: keep identifying the people affected, learn their concerns and keep them engaged through the change.
When a new technology succeeds in one place and is rolled out to another, think about people first in the same way. A multinational has proven automation technology at its first sorting center and is introducing it at a new center. The focus is to use an information-sharing session so that the new center's stakeholders learn about the technology and its benefits. Rechecking the rate of return, asking the technology manager about site fit and drafting the new charter from the first center's lessons learned are technical and commercial matters and cannot replace the step of getting people to accept it.
Rumors are a sign of insufficient communication
When rumors appear during a change, for example "the new system will make our work more fragmented and less efficient", they signal a possible communication gap. First hear the employees' specific concerns, verify the claim and the information need it reveals, and provide accurate information promptly. If this shows that the communications management plan omitted these employees or has inadequate arrangements, update it and include them among the audience during system development. Writing a line in the change management plan, merely promising to consider concerns, or generally reviewing a plan cannot replace actual communication.
Example: stores move from manual bookkeeping to an online system
A restaurant chain is replacing manual bookkeeping in its 40 stores with an online system. The finance department worries about losing jobs, and store managers feel it adds to their burden. The project manager works in four steps. First, hold a briefing session explaining that the system aims to cut duplicate entry and let store managers see operating data the next day. Second, pilot in 3 stores, collect managers' feedback and adjust the entry screen. Third, arrange training in new data analysis skills for finance staff and announce the role arrangements. Fourth, when rumors appear, report progress promptly at the weekly meeting. All four steps address people's concerns rather than repeatedly stressing how advanced the system is.
Worked examples
Example 1: Resistance to a transformation: what do you do first?
A project manager is assigned to a store digitization project at a supermarket chain. The group's culture is conservative and broadly resists transformation and innovation; employees say they do not see why the change is needed. What should the project manager do FIRST to support the transformation?
Show answer and explanation
Correct answer: A
A group with a conservative culture is carrying out a digital transformation through a project, and stakeholders resist. The question is what the project manager should do first to support the transformation.
Facing broad resistance, first help stakeholders understand the purpose and necessity of the change, and learn their specific concerns through training and communication; that reduces resistance and wins involvement. The test for the four options is whether the action helps stakeholders build an awareness of the purpose of the change. Only arranging training for stakeholders so that they understand the purpose builds that initial awareness and supports later involvement. Here, the session is a communication and briefing session about the purpose of the change, not hands-on operational skills training. ADKAR is a common exam term: explaining why the change is needed supports Awareness, while hands-on operational training develops Knowledge and Ability. The answer is A.
Why the other options are wrong
- B. Bringing in an expert and appointing that person as champion only adds one supporter and does not solve the problem of everyone else not understanding.
- C. Having senior leaders announce that the project manager will lead the project only confirms an identity and does almost nothing to reduce resistance.
- D. Handing out a guide is one-way push communication. It makes sure the information is sent, but not that employees understand it, and stressing “inevitable” does not explain why the change is necessary.
Key takeaway When stakeholders resist a transformation, first help them understand the purpose of the change.
Variation If the stem says employees already understand the purpose but do not know how to use the new system, that points to knowledge and ability, and the answer becomes training and hands-on coaching.
Something wrong with this question?
Example 2: A restructuring upsets the team
A company is restructuring, and several employees are about to leave because their positions are being eliminated. Project team members are down and do not understand why such a restructuring is happening while the project is going well. What should the project manager do?
Show answer and explanation
Correct answer: A
The company's restructuring has unsettled the team, and the team does not understand the reason for it. How should the project manager respond?
Members' discontent comes from not understanding. Hold a team meeting, explain clearly the reasons for the restructuring and what it means for the company, and let members voice their questions; that eases emotions and keeps collaboration going. This is a direct application of “explain the purpose first, then listen” in change communication. Mind the wording as well: explain honestly what the restructuring means for the company and how it affects employees, avoid demeaning phrases such as “weeded out” that deepen resistance, and leave time in the meeting to hear members' questions. The answer is A.
Why the other options are wrong
- B. Stressing only that the work continues as planned ignores members' emotions and questions, so the problem remains.
- C. Saying only that the chief executive decided and it must be carried out gives no reason and does not listen, and instead deepens resistance.
- D. Escalating to the sponsor and seeking an allowance is neither proactive nor a response to members' confusion about the restructuring.
Key takeaway When a restructuring upsets the team, hold a team meeting and explain the reasons and the meaning.
Variation If rumors such as “more positions will be eliminated” are going around, first hear and verify the specific concern and provide accurate information promptly; if the communications management plan omitted affected employees or has inadequate arrangements, update it and include them in the audience.
Something wrong with this question?
Common traps
Common trap
- Manuals, emails and notices are usually push communication. They can deliver information, but on their own they cannot confirm that the audience has understood and agreed; where needed, add interactive communication and feedback.
- "Announcing who leads" and "hiring an expert as champion" only solve the questions of identity and supporters; they do not help employees understand the purpose.
- In change questions, "mandate", "shelve feedback" and "adapt unconditionally" are almost never the answer.
- Updating the communications management plan (bringing the people affected into the audience) is not the same as updating the change management plan (the rules of change control).
Key takeaways
Key point
- Whether a change succeeds depends on people: put people first and help those affected adapt.
- When a transformation meets resistance: first assess the causes of resistance and the impact of the change; if the root cause is not understanding the purpose, use communication and suitable training to help stakeholders understand.
- When a restructuring causes discontent: hold a team meeting and explain the reasons and what it means for the company; word it as help, not as "cutting" people.
- Effective practice: evaluate the impact on processes, communicate and train, listen to feedback, involve the people affected, and avoid relying on compulsion alone.
- Rumors signal a possible communication gap: first hear and verify the concern and provide accurate information; if the plan omitted affected people or has inadequate arrangements, update the communications management plan.
Lesson 3
The ADKAR Model and the Organizational Change Plan
Lesson overview
The first two lessons covered people's resistance and communication. This lesson closes the chapter with two things: ADKAR, a widely used change model at the individual level, and how to integrate change activities into the project plan. ADKAR is an analytical framework and a common exam term. The ECO's Business Environment Task 7 only asks you to assess organizational culture and the impact of organizational change on the project and determine required actions; it does not name ADKAR. Focus on two skills: seeing which of the five steps a question's problem lies in and knowing which organizational action matches it. The organizational change plan is a common exam term; it can be tailored to the project and is not a separate project management plan component, and you must tell it apart from the change management plan in the project management plan. The lesson is short; what matters is remembering the pairings. This maps to ECO Business Environment domain, Task 7 (Support organizational change): evaluate the impact of organizational change on the project and determine required actions.
ADKAR: five steps for an individual to accept change
ADKAR breaks the process by which a person accepts change into five steps, built up in order:
| Step | Meaning | Organizational action |
|---|---|---|
| Awareness | Realizing why the change is needed | Communicate the reason for the change and its urgency |
| Desire | Being willing to take part and support it | Win support, address personal concerns, offer incentives |
| Knowledge | Knowing how to change | Training; explain the new way clearly |
| Ability | Actually being able to do it | Hands-on practice, coaching, tools and time |
| Reinforcement | Making the new way stick | Follow up after go-live, correct old habits, recognize and reward |
The five elements build up in order logically, though real progress may go back and forth; deal first with the earliest obstacle. Without awareness and desire, no amount of training helps; knowing is not the same as being able to do; and even people who can do it may slide back to the old way two months later.
How to use it: map the symptom to the step
The exam does not ask you to memorize the theory. It gives you a symptom and asks which step is missing:
- Employees ask "why are we changing?": awareness is lacking, so add communication.
- Employees know a change is coming but "do not want to change": desire is lacking, so listen to concerns and provide incentives.
- Employees are willing but "do not know how": knowledge is lacking, so add training.
- Employees are willing and know how, but cannot perform in practice: ability is lacking, so add practice, coaching, tools and time.
- Employees can do it, but two months after go-live still use the old process: reinforcement is lacking, so follow up continuously and correct old habits.
The last one is a common exam scenario. An inventory counting process has been live for two months, and many employees who understand and support the change, have completed training and can correctly perform the new process still use the old way. The project manager keeps following up on how the new process is being carried out and, through feedback and coaching, helps employees correct their old habits. Sending another notice is still a one-way demand and does not find out why employees keep the old way. Keeping the old process with no end date is not a planned parallel cutover; it sends employees who can already use the new process back to the old way. Hastily closing the project and handing the usage to the departments, when there is no clear owner to take over, no value-sustainment plan and no tracking mechanism, means giving up on reinforcing the result. After the formal handover, the operations department or the benefits owner can continue tracking and reinforcing according to the value-sustainment plan.
Write the change into the project plan
When a project causes organizational change, the change activities cannot sit outside the project plan. Integrate them and manage them together with schedule, budget, communication and training. The organizational change plan is a common exam term. It can be tailored to the project. It states the change objectives, the affected stakeholders, and the transition arrangements such as communication and training. It can also state when, by whom and how the effect of the change will be measured. Detailed budgets, procurement items and team management information are usually managed in the financial, procurement and resource management plans, and the change plan can refer to the budget, owners and measures there as needed.
Mind the names. Among the components of the project management plan there is also a change management plan. It "establishes the change control board (CCB), also known as a steering committee; documents the extent of its authority; and describes how the change control system will be implemented." It guides how change requests are evaluated, approved, recorded and implemented, including changes to documents, deliverables or baselines. The organizational change plan discussed above deals with how the organization and its people transition. The two names are easy to confuse. When a stem mentions "change objectives", "affected people" or "communication and training", exam questions usually mean the organizational change plan (not a separate plan component), not the change management plan.
The transition period and scope
Some projects need a transition state, reaching the future state through several structured steps. A transition period may involve running old and new side by side, or other arrangements such as cutting over in batches; either way you must plan temporary processes, data conversion, training and support. The "transition and readiness requirements" category in the requirements documentation of PMBOK 8 Chapter 4 is about exactly this: these requirements describe the temporary capabilities needed while moving from the current state to the future state. So the needs of organizational change feed back into project scope: if the plan lacks them, go-live becomes a "cliff-edge cutover".
Example: transition arrangements for an accounting system cutover
A manufacturing group is merging its branch accounting systems into a headquarters platform, with a 3-month cutover period. The organizational change plan has four parts. Objective: shorten the accounting cycle from 12 days to 5. Affected people: finance staff and approvers at 12 branches. Transition arrangements: run old and new systems in parallel in month 1, have headquarters finance staff on duty to answer questions in month 2, and make the old system read-only in month 3. Measures: each month, compare the share of entries made in the new system and the error rate. These items also appear in the schedule (the parallel period), the budget (the on-duty cost) and the communications management plan, which is why it counts as integrated into the project plan rather than a separate set.
Worked examples
Example 1: Still using the old process after go-live
Two months after a retail company's inventory counting process change goes live, the project manager confirms that many employees understand and support the change, have completed training and can correctly perform the new process, but still use the old process. What should the project manager do?
Show answer and explanation
Correct answer: C
Two months after the change goes live, employees are still using the old process. The new way has not really taken hold and needs to be reinforced.
A change delivers its results only when the new way is actually used and sustained. The signal is “still using the old process two months after go-live”: the new way has not really taken hold and needs reinforcement. The stem says these employees understand and support the change, have completed training and can correctly perform the new process. Following up on execution, collecting feedback and coaching employees reveals why they still use the old process, corrects their old habits and reinforces the new process. You can work backward through ADKAR's five steps on questions like this (common exam practice): if employees already know why the change is needed and have been taught the new process but still use the old way, what is missing is reinforcement, which calls for continued follow-up. The answer is C.
Why the other options are wrong
- A. Closing the project and pushing usage to the departments gives up on reinforcing the result of the change, and the old habits continue.
- B. Sending another notice is still a one-way demand. It does not find out why employees keep the old process, so it is unlikely to change habits.
- D. Keeping the old process until employees get familiar with the materials is not a planned parallel cutover with an end date; it sends employees who can already perform the new process back to the old way. The stem does not say employees lack training materials or are unfamiliar with them, so waiting is not targeted and does not correct the old habit that is happening now.
Key takeaway After a change goes live, keep following up and correct old habits to reinforce the result.
Variation If the stem changes to “employees do not know why the change is needed”, that corresponds to awareness, and the answer is to communicate the reason for the change; “employees are willing but do not know how” corresponds to knowledge and ability, and the answer is training and coaching.
Something wrong with this question?
Example 2: What goes in an organizational change plan
A project manager on an organizational change project is preparing an organizational change plan (a common exam term). What does this plan mainly contain?
Show answer and explanation
Correct answer: D
What goes in the organizational change plan must be told apart from what goes in cost, procurement and resource management.
The organizational change plan (a common exam term) is prepared so that an organizational change transitions smoothly. It mainly contains the change objectives, the affected stakeholders, and transition arrangements such as communication and training, and it can also state when, by whom and how the effect of the change will be measured. Of the four options, only D is about the change itself. In common exam practice, ask whether the option is about the “change transition”: objectives, the people affected, communication and training all concern how people come to accept the new state, while budgets, procurement and resource rosters are contents of plans in other knowledge areas. The answer is D.
Why the other options are wrong
- A. Budget details, disbursement milestones and payment arrangements belong to cost management.
- B. The procurement list, the supplier roster and contract terms belong to procurement management.
- C. The team list, role assignments and performance appraisal criteria belong to resource management.
Key takeaway The organizational change plan states the change objectives, the affected people, and transition arrangements such as communication and training.
Variation If an option mentions “the composition and authority of the change control board”, that describes the change management plan, not the organizational change plan; the two names differ by only a word.
Something wrong with this question?
Common traps
Common trap
- Use ADKAR only to identify which step the problem is in, not to run through all five steps every time; "employees can do it, but some still use the old way after go-live" points to reinforcement; when the cause is unclear, find the earliest obstacle first.
- The organizational change plan (change objectives, affected people, transition arrangements for communication and training) is not the change management plan (the change control board and the change control system).
- Change does not complete itself when the project delivers: keep following up after the result is delivered, or old habits return.
- Training addresses the "knowledge" step, not all of it; not wanting to change and not knowing how to change are two different problems.
Key takeaways
Key point
- ADKAR: Awareness, Desire, Knowledge, Ability and Reinforcement; they build in order logically, though real progress may go back and forth.
- Matching actions: communicate the reason, win support, train, give hands-on coaching, follow up and correct old habits.
- Employees already have the willingness, knowledge and ability but still use the old way after go-live: this is a reinforcement gap, so keep following up with feedback and coaching rather than closing the project and walking away; when the cause is unclear, assess where the obstacle lies first.
- Organizational change plan: change objectives, affected people, and transition arrangements such as communication and training; integrate it into the project plan.
- When old and new run side by side in the transition period, temporary capabilities are needed; transition and readiness requirements affect scope.
This chapter has 15 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.